c o m p a n y p r e s e n t a t i o n energotehika juŽna baČka

25
C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

Upload: macey-matheny

Post on 30-Mar-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

C O M P A N Y P R E S E N T A T I O N

ENERGOTEHIKA JUŽNA BAČKA

Page 2: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

C O

N T

E N

T S

1. About the company2. History3. Company services4. Products5. Financial indicators6. Organization scheme7. Energy8. Trade9. Engineering10. Corporate values11. Technical capacity12. Certificates and licenses13. Clients and partners14. Contact

Page 3: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

IN DEVELOPMENT, PRODUCTION, INSTALLATION AND MAINTENANCE OF VARIOUS POWER PLANTS, SUBSTATIONS AND ELECTRICAL EQUIPMENT UP TO 400kV VOLTAGE LEVEL

Over 400 km of erected gas pipelines, heat pipelines and gas distribution networks

Over 8500 erected substations in voltage levels from 0.4kV up to 400kV connected with 12700 km of OHLs

1. ABOUT THE COMPANY

MORE THAN HALF A CENTURY OF EXISTENCE AND EXPERIENCE

Page 4: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

1958

50 years

Today more than 400 employees

TURNOVER in 2012 was 50 mil EUR

Founded as a part of Elektrovojvodina

State owned as a part of Electric Power Industry of Serbia

2. A SHORT HISTORY

Fully privatized

Page 5: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

Performs works in country and abroad in the fields of:

ENERGY

OIL & GAS

RENEWABLE ENERGY SOURCES

TURNKEY PROJECTS

Page 6: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

DESIGN AND PROJECT REALIZATION

3. COMPANY SERVICES

• Overhead transmission lines and substations in all voltage levels ranging from 0.4 kV up to 400 kV

• Thermal power plants, thermal power plants – heating plants, heating plants, heating substations,

• Public and decorative lighting

• Gas pipelines, heat pipelines, oil pipelines and gas substations

• Automation and instrumentation

Page 7: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

4. PRODUCTION RANGE

• LV and MV typicly tested switchgears for substations ranging from 0.4 kV up to 35 kV

• Steel enclosures and various steel structures, towers for overhead power lines and other metal products

• Cable distribution cabinets

• Metering cabinets for power distributing system

• Distribution cabinets and boards for industry automation

• Heat exchangers

Page 8: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

BUSINESS REVENUE

5. FINANCIAL INDICATORS

[ year ]

[ million € ]

Page 9: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

6. ORGANIZATION SCHEMEASSEMBLY

CONTROLLING

ELECTRICAL POWER

PRODUCTION

TRADEBUSINESS

PROCESS SUPPORTLABORATORY AND QUALITY CONTROL

DIRECTOR

THERMALPOWER REPRESENTATIVE

OFFICES

REPRESENTATIVEOFFICE

IN BELGRADE

REPRESENTATIVEOFFICE

IN GERMANY

REPRESENTATIVEOFFICE

IN JAGODINAVEHICLES

INDUSTRYMEDIUM

AND HIGH VOLTAGE LOW VOLTAGE

Page 10: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

7. ENERGY

• Erection and reconstruction of substations in all voltage levels

More than 8500 erected substations of all voltage levels connected with 12700 km of OHLs

• Erection and reconstruction of OHLs in voltage levels up to 400kV

• Equipment testing and maintenance of existing cable lines, substations and OHLs using HV test equipment (stabile and mobile) and IC thermography methods

• Installation of OPGW and ADSS

• Works on public and decorative lighting

• Transport services

Page 11: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

ENERGY / PRODUCTION

Low voltage and medium voltage cubicles are produced for more than 8500 substations

• Production of power equipment for 10/0.4 kV and 20/0.4 kV substations

• Automation of TS and power plants

• Engineering, development and inspection of technical documentation and designs

• Production and installation of equipment for electric motor drives and various cabinets for industry automation

Page 12: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

REFERENCES \ POWER PLANTS, SUBSTATIONS AND OHL

9

• Reconstructionion of SS 400/220/110 kV ''Novi Sad” 3''

• Reconstruction of SS 110/35/20 kV ''Novi Sad” 1''

• Erection of SS 110/20 kV ''Rimski šančevi''

• Erection of SS 110/20 kV Čelarevo

• Erection of SS 110/20 kV Kačarevo

• Erection of OHL 2x110 kV Čelarevo

• Erection of OHL 2x110 kV Kačarevo

• Installation of OPGW on the 220 kV power line ''Obrenovac A'' - ''Beograd 3''

• Installation of ADSS cable on the railway Zlatica - Bar

• Reconstruction of cable configuration in SS ''Novi Sad 5''

• Set of substations for industry: ”Fiat automobili Srbija”-Kragujevac, ”Hemofarm“, ”Merkator”,”Tuš”,”Rodić MB”, ”Merkur” etc.

• Decorative lighting of the Assembly building of APV and Executive Council building of APV in Novi Sad

• Decorative lighting on the Varadin bridge in Novi Sad

• Public and decorative lighting at the Petrovaradin Fortress in Novi Sad

• Public lighting along Somborski Boulevard in Novi Sad

• Public lighting along Evropa Boulevard in Novi Sad

• Spotlighting on “Karađorđe” stadium in Novi Sad

• Decorative lighting of the Matica Srpska building in Novi Sad

Page 13: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

- Mounting of distribution cabinets (DC) and control panels

• ''Elektrovojvodina'' - ltd Novi Sad

- Delivery of medium and low voltage cubicles of different configurations as requested by clients- Maintenance of pylons in the Novi Sad area

• ''Siemens'' Ltd Belgrade

- Electrical works as a part of commissioning of modernization of Oil Refinery Pančevo• NIS with P.O. Novi Sad

- SS SOS in Kikinda, SS-1 in Velebit, supply cables of 20 kV

• E-Control Ltd Novi Sad

• ''Fiat automobili Srbija'' Kragujevac

- Production of cable distribution cabinet and signaling installations - Erection of infrastructure for 20 kV switchgear installation

- Delivery of equipment and erection of TSG, TSM and TSS 20/0.4 kV substations- Electrical works on a boiler house

- Metering instruments and equipment

- SS heating plant ''Sever'' in Novi Sad

REFERENCES \ POWER PLANTS, SUBSTATIONS AND OHL

Page 14: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

PROJECT - FIAT AUTOMOBILI SRBIJA -KRAGUJEVAC

Value of works 25.000.000 EUR

• Construction of cable distribution cabinet and signaling installations, erection of infrastructure for 20 kV switchgear installation

• Equipment delivery and instalation for 20/0,4 kV Substations

• Electrical works in boiler house

The works under the Tender:

• T24 – refurbishment of anexes Building 1,2,3,4,5 and extension of Building 3,4,5 - cca 11.000 m2

• T26a – refubrishement, reconstruction and adoptation of Building 16 cca 6.000 m2

• T28a – refubrishement of loading docks and doors installation (REI – pedestrian and vehicle doors)• T40 – refubrishement of mezanin of Building 5 cca 4.500 m2

Page 15: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

PROJECT - TRITON HOUSE, REMS MUR, YIT - FRANKFURT, GERMANY

Value of works TRITON HOUSE project : 5.000.000 EUR

• Design, delivery and installation materials and equipment

• Building a complete electrical system on the surface of 50.0000 m2 Triton House

• Design, assembling, delivery and installation of all cabinets

• Installation of 300 km of cables

Page 16: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

ENERGY / OIL & GAS

• Installation of pipelines

• Production of metal structures for power equipment and plants (electrical and thermal)

• Design and development of gas metering stations and heat exchangers

• Erection and reconstruction of boiler houses in industry

• More than 120 km of medium pressure gas pipelines

More than 400 km of erected gas pipelines, heat pipelines and gas distribution networks

We have erected:

• More than 170 km of polyethylene gas distribution network

• 180 heating substations

• 60 km of heating pipelines

Page 17: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

DEVELOPMENT AND USAGE OF ALTERNATIVE ENERGY SOURCES

RENEWABLE ENERGY SOURCES

Design, equipment delivery, execution of works - Wind generators - Solar panels - Biogas plants

WE PROVIDE TURNKEY SOLUTIONS FOR ALL PROJECTS

• Geothermal heating and cooling for the building of ET-Južna Bačka: - In the heating period: 4 to 5 times lower costs - In the cooling period: 7 to 9 times lower costs

MAINTENANCE OF GEOTHERMAL ENERGY SYSTEMS

• Construction of thebiomass boiler plant in Sremska Mitrovica in the capacity of 18 MW (€ 2,500,000 investment)

• Construction of the plant for for water heating of water park swimming pools by usage of geo-thermal energy

Page 18: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

REFERENCES \ OIL & GAS

• '‘Heating Plant Novi Sad'' – Erection of the main steam pipeline from the main distribution station to the heating plant ''Sever''

- Erection of heat pipeline in the Almas block

• ''Heating plant Valjevo'' – 2x20 MW plant with a heat pipeline junction

• ''Aleksandar Gradnja''- Erection of heating substations for the building located at the corner of Boulevard Oslobodjenja and Novosadskog sajma St in Novi Sad

• ''A.D.Budućnost”- Steam boiler house for a styrofoam factory

• ''Srbijagas'' - Gasification of Kula municipality - Gasification of Apatin municipality

- Two way gas pipeline Elemir - Banatski Dvor

- Banatski Dvor Gas warehouse

• ''Energotehnika Južna Bačka'' Ltd – Seating and cooling of offices by the means of geothermal energy

• ''Fiat automobili Srbija'' - Kragujevac – Heating plant 3x58 MW

• '‘Heating plant Zrenjanin'‘ with the power of 2x35 MW

• Reconstructions and overhauls in thermal power stations – heating plants in Novi Sad and Zrenjanin, as well as in the power plant in Sremska Mitrovica

Page 19: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

8. TRADE

• Low voltage, medium voltage and high voltage equipment

PRODUCT RANGE IN TRADE

• Lighting and installation material

• Ferrous and nonferrous metallurgy

• Various screws

• Paints and varnishes

• PPE equipment

Page 20: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

9. ENGINEERING

DESIGN AND CONSTRUCTION - WE PROVIDE TURNKEY SOLUTIONS FOR ALL PROJECTS

PERFORMING WORKS IN

the reconstructionadaptation and rehabilitation

projects in the industry

Page 21: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

10. CORPORATIVE VALUES

Employees with university degrees

• More than 400 employees

• More than 50 engineers

• More than 200 skilled workers

Tradition

Constant development

Business efficiency

Social responsibility

Quality management (certificates and licenses)

Competitive advantage of technical resources

Page 22: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

11. TECHNICAL CAPACITY

VEHICLES

OTHER SPECIALIZED EQUIPMENTLIGHT TRUCK VEHICLES

VARIOUS INSTRUMENTS

• Freight vehicles with hydraulic cranes

• Equipment for measuring the light level in public, decorative and industrial lighting

• Devices for installation of conductors and optical fiber wires (OPGW) in OHL

• Freight vehicles without cranes

• Crane PH / 80 tons

• Volvo truck trailer with a special platform for power transformers

• Road pickup truck and alike

• Self propelled telescopic booms for public lighting with the reach of 16-20 m

• Passenger vehicles

• Thermal vision camera

• HV test equipment and various instruments used by our accredited laboratory analysis (in-house and mobile)

• Plants for plastification of metal structures

• Presses and aggregates

• Equipment for production of steel towers and consoles

Page 23: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

12. CERTIFICATES AND LICENSES

SRPS ISO / IEC 17025:2006For electrical testing (total of 20 types)and soil compaction test,applied since 2008

PROFESSIONAL CERTIFICATES AND LICENSES

Design and performance of most complex operations in energy industry

ISO 9001:1994Development and maintenanceof power generating facilitiesapplied since 2007 asISO 9001:2000

ISO 9001:2008Quality management systemapplied since 2010

ISO 14001:2004Environmental management system during the processof erection and maintenance of power generating facilitiesapplied since 2007

ISO / OHSAS 18001:2007Occupational health & safetymanagement systemapplied since 2010

ABB certificate for 110kV cables, joints and terminations (bushing and GIS type)

Specialist knowledge and vast experience in erection of power generating facilities and plants

Page 24: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

13.CLIENTS AND PARTNERS

CLIENTS PARTNERS

Page 25: C O M P A N Y P R E S E N T A T I O N ENERGOTEHIKA JUŽNA BAČKA

ENERGOTEHNIKA-JUŽNA BAČKA d.o.o.

1 Put novosadskog partizanskog odreda21000 Novi Sad, Serbia

CONTACT

14. CONTACT

web: w w w . e n t j u b a . r s

e-mail: [email protected].

Tel: + 381 21 48 77 222Fax: + 381 21 44 21 67