by chiti mataka - developing markets chiti uk... · by chiti mataka senior manager ... 330/132 kv...
TRANSCRIPT
BY
CHITI MATAKA SENIOR MANAGER - BUDGETS, ZESCO LTD
INVESTING IN ENERGY: THE ZESCO EXPERIENCE
2
TABLE OF CONTENTS
1.Introduction
2.Current Status
3.Investment Portfolio
3.1 Generation Projects
3.2 Transmission Projects
3.3 Distribution Projects
4.Conclusion
INTRODUCTION
ELECTRICITY IS A KEY DRIVER OF ECONOMIC GROWTH AND IS A MAJOR INPUT IN ALL MAJOR
ECONOMIC SECTORS - AGRICULTURE, MINING, MANUFACTURING,TOURISM, ETC.
ZESCO’S ELECTRICITY GENERATING CAPACITY STANDS AT 1.6 GW (99% HYDRO)
NET EXPORTS - ROUGHLY 5 % OF TOTAL GENERATION (MOSTLY TO NAMIBIA, BOTSWANA AND THE
DEMOCRATIC REPUBLIC OF THE CONGO -D.R.C.)
CURRENT PEAK DEMAND FOR ELECTRICITY CANNOT BE MET BY AVAILABLE GENERATION DUE TO
THE LOW WATER INFLOWS INTO, AND THE LOW WATER LEVELS IN, THE TWO MAIN RESERVOIR
DAMS OF KARIBA AND ITEZHI-TEZHI, ARISNG FROM THE POOR RAINFALL PATTERNS IN THE
2014/2015 RAIN SEASON.
UP UNTIL THE RECENT ECONOMIC DOWNTURN OF 2015 EMANATING FROM THE FALL IN BASE
COMMODITY PRICES (INCLUDING COPPER), THAT WAS RELATED TO THE REDUCTION IN DEMAND
IN THE MAIN EXPORT MARKET OF CHINA, ZAMBIA HAD EXPERIENCED SUSTAINABLE ECONOMIC
GROWTH OVER THE LAST DECADE. THE DEMAND THAT PRINCIPALLY WAS DRIVEN BY CHINA HAD
ACTED AS A CATALYST TO LARGE STEP DEMAND GROWTH FOR KEY ECONOMIC SECTORS SUCH
AS MINING. THIS IN TURN HAD A POSITIVE IMPACT ON OTHER SECTORS SUCH AS CONSTRUCTION.
3
FACTFILE
ELECTRICITY DEMAND Maximum Demand is now estimated at more than 1, 650 MW.
Access to electricity is estimated at 22% in the urban areas and at 3% the rural
areas.
4
0
500
1000
1500
2000
2500
3000
MW
Years
Demand Forecast for Zambia
Demand
18/06/13ZESCO
6
FACTFILE
GENERATING STATIONS
7
MAJOR POWER STATIONS GENERATION
CAPACITY BEFORE
PRP (MW)
GENERATION
CAPACITY AFTER
PRP (MW)
KAFUE GORGE 900 MW 990 MW
KARIBA NORTH BANK 600MW 720MW
VICTORIA FALLS 108 MW 108 MW
SMALL HYDROS CAPACITY BEFORE
UPRATING (MW)
CAPACITY AFTER
UPRATING (MW)
LUNZUA 0.75 MW 15.3 MW
LUSIWASI 12 MW 86 MW + 15MW
CHISHIMBA 6 MW 14.8MW
MUSONDA 5 MW 10MW
FACTFILE
8
TRANSMISSION ASSETS
VOLTAGE DISTANCE (KM)
330 KV 2,241
220 KV 571
132 KV 202
88KV 794
66KV 1,037
HIGH VOLTAGE SUBSTATIONS 27
NATIONAL CONTROL CENTER 01
REGIONAL CONTROL CENTERS 03
DISTRIBUTION ASSETS
66KV 2,180
33KV 2,100
11KV 1,037
SUBSTATIONS 5,000
LOAD FORECAST
Year 2008 2010 2015 2020 2025
FORECAST
MAXIMUM
DEMAND (MW)
1,579 1,592 2,389 2,595 3,029
FORECAST
SHORTFALL
(MW)
547 753 1,179
INVESTMENTSTHE ZAMBIA POWER REHABILITATION PROJECT (PRP)
The overall objective was to support that of Government of enhancing
the ability of Zambia’s Electricity Supply Industry (ESI) to:
Provide electricity at least cost, and in an efficient and sustainable
manner;
Stimulate more and inclusive growth in the Zambian economy.
The rehabilitation works involved two major components; namely:
Generation infrastructure; and
Transmission and distribution infrastructure..
The PRP was funded by bilateral and multilateral agencies led by the
World BANK; Government and ZESCO also participated.
The project cost more than USD320mn.
10
INVESTMENTS
ZAMBIA POWER REHABILITATION PROJECT (PRP)
The scope included the rehabilitation and uprating of the three
major hydropower stations, i.e. Kafue Gorge Power Station
(KGPS); Kariba North Bank Power Station (KNBPS); and
Victoria Falls Power Station (VFPS).
Other works included the reinforcement and rehabilitation of
some transmission and distribution infrastructure
The major achievement of the PRP has been the uprating of
KGPS from 900 to 990 MW; the reinstatement of VFPS to its
full generating capacity of 108 MW; as well as the up-rating of
KNBPS from 600 to 720 M. The total generation capacity
yielded from the PRP at these brownfield sites is 210 MW.
11
INVESTMENTS
The estimates of expenditure on the PRP are as below:
Victoria Falls Power Station – USD53.7mn
Kafue Gorge Power Station - USD 85.5mn
Kariba North Bank Power Station
– USD81.4mn
Therefore, the total cost – USD 220.6mn
The estimated cost for a 210MW greenfield power
station would be at least USD560mn.
12
INVESTMENTS
New Generation Projects
Kariba North Bank Extension - 360MW
• Owner: ZESCO Limited/KNBEC
• COST: USD 420M
• Estimated Duration: 4 YEARS
• Operation: January 2014
• STATUS: Installation of hydro-mechanical
equipment completed
13
INVESTMENTS
New Generation Projects
Itezhi-Tezhi Hydro-Power Project (120 MW)
• Owner: PPP (ZESCO/TATA)
• Cost: USD 250M
• Estimated duration: 3.5 years
• Operation: 2015/2016
• Status: 94% of construction works
completed. Financial Close achieved and First
Drawdown made in April 2015.
14
INVESTMENTS
New Generation Projects
Kafue Gorge Lower Hydropower Project (750 MW)
• Owner: ZESCO
• Cost: USD 2bn
• Estimated duration: 51 months from October 2015 when
contract was signed.
• Operation: 2019
• Status: Engineering, Procurement and Construction
(EPC) Contractor selected, contract awarded and
signed.
• Government of the Republic of Zambia (GRZ) has allocated
US$186M as ZESCO’s equity contribution to the project.
15
INVESTMENTS
16
New Generation Projects – SMALL HYDROS
MUJILA FALLS 1.4MW-US$25M
75% OF PREPARATORY WORKS DONE. PROJECT COMPLETION
EXPECTED 2017.
LUSIWASI LOWER -86MW-US$164M
EPC CONTRACT AWARDED TO CNEEC
LUNZUA-15MW-US$52M
THE PROJECT WAS COMMISSIONED IN JUNE 2014.
LUSIWASI UPPER -15MW-US$47M
THE PROJECT AWAITS SITE INVESTIGATIONS, AWARD OF CONTRACT,
PROJECT FINANCING
REHABILITATION AND UPRATING OF CHISHIMBA FALLS: 6 -14.8MW – US$46M
PREPARATION BID DOCUMENTS IN PROGRESS, AWARD OF CONTRACT,
PROJECT FINANCING
REHABILITATION AND UPRATING OF MUSONDA FALLS: 5-10MW – US$32M
CONTRACT AWARDED, ADVANCE PAYMENT MADE TO EPC CONTRACTOR,
PROJECT FINANCING. WORKS TO CONCLUDE IN 2016
SHIWANG’ANDU 1 MW – USD4.15 MILLION
PLANT COMMISSIONED IN 2012. HOUSING SCHEME COMPLETED IN 2014
INVESTMENTS
17
NEW GENERATION PROJECTS – POTENTIAL SITES
MPATA GORGE – 540 MW
DEVIL’S GORGE – 500 MW
BATOKA GORGE – 2, 400 MW (1, 200MW EACH BETWEEN
ZAMBIA AND ZIMBABWE)
MUMBOTUTA FALLS - 300 MW
MAMBILIMA FALLS SITE I – 202 MW
MAMBILIMA FALLS SITE II – 124 MW
KABWELUME FALLS - 62 MW
KUNDABWIKA FALLS – 101 MW
MUTINONDO - 40 MW
LUCHENENE – 30 MW
MKUSHI – 65 MW
INVESTMENTS
TRANSMISSION PROJECTS
PENSULO KASAMA AND PENSULO CHIPATA 330 KV
PROJECT
The objective is to improve power quality in Eastern, Muchinga,
Northern and Luapula provinces and to increase transmission
capacity to these areas
Scope: about 382 km of 330 kV lines (Pensulo - Kasama) and
285 km of 330 kV lines (Pensulo - Chipata) with associated
substations
Cost: USD335 million
Status: Both transmission lines have been completed and ahead
of schedule .
Funding: Industrial and Commercial Bank of China
Construction Period: 30 months from August 2012 18
INVESTMENTS
CONNECTION OF NORTH WESTERN PROVINCE TO the
NATIONAL GRID
The objective is to support increased access to electricity and
improved quality of service by displacing expensive diesel
generators
Scope: Construction of 850 km of 132 km transmission lines,
330/132 kV substation and 132/33 kV substations in
Mwinilunga, Kabompo, Mufumbwe, Zambezi, Lukulu and
Chavuma
Cost: appx. USD184 million
Funding: Secured from Nordea Bank (Sweden)
Status: Contract awarded to EL TEL, site mobilisation has
been done. Design works in progress.
Construction period 24 months. Commissioning September
201619
INVESTMENTS
TRANSMISSION PROJECTS
KARIBA NORTH BANK EXTENSION POWER EVACUATION
PROJECT
The objective is to increase transmission capacity from KNBPS
to the grid for the evacuation of power from KNBE project
Scope: 123 km of 330 kV lines and substation works
Cost: USD62 million
Status: The project was completed in December 2014.
Funding: EXIM Bank of China
20
INVESTMENTS
KAFUE TOWN - MUZUMA - VICTORIA FALLS TRANSMISSION
LINE UPGRADE
The objective is to increase transmission capacity
southwards for export to, and from, SAPP and to provide
an evacuation path for new generation projects
Scope: Upgrade 348 km of 220 kV line to 330 kV
Cost: USD100 million
Status: Transformer manufacture is in progress and
contractor has mobilised to site and began site
clearance.
Funding: World Bank and European Investment Bank
Construction Period: 18 months21
INVESTMENTS
ITT - MUMBWA - LUSAKA WEST TRANSMISSION LINE
PROJECT
The objective is to provide power evacuation for the ITT
power station
Scope: 142 km of 220 kV line and 134 km of 330 kV line
and associated substation at Mumbwa
Cost: USD133 million
Funding: EIB, AfDB and AFD
Status: Construction works have been accelerated in
order to ensure that the transmission line is ready and
tests are carried out ahead of the commissioning of the
ITT plant. The line is expected to be ready this month -
November 2015. 22
INVESTMENTS
SUPPLY TO KALUMBILA MINE
The objective is to supply power to the proposed First
Quantum Minerals (FQM) Kalumbila mine
Scope: 500km of 330 kV double circuit line and 66 km of
330 kV single circuit line, and associated substation at
Kalumbila
Cost: USD300 million
Funding from Kalumbila Minerals Limited/ZESCO
Status: The project was 98% complete as at 30th
September 2015. Commissioning is pending system
studies verification.
23
INVESTMENTSCONNECTION OF LUANGWA DISTRICT TO THE GRID
The objective is to support increased access to electricity and
improved quality of service by displacing expensive diesel
generators. There is also export potential to border areas of
Mozambique and Zimbabwe.
Scope: 187km of 132kV transmission, 2x10MVA 132/33kV
Substations at Rufunsa and Luangwa, 60km of 33kV lines in
Mpanshya, service connection to GRZ institutions and 100km of
33kV lines in Luangwa
Cost; USD63million
Funding: Export Import (EXIM) Bank of India
Status: Construction works are in progress.
Construction period: Commissioning is expected in June 2016
24
INVESTMENTS
TRANSMISSION PROJECTS
LUSAKA 132KV RING REINFORCEMENT PROJECT –
PHASE I
The objective is to increase the transmission capacity of
the Leopards Hill – Coventry 132kV transmission line
Scope: Reconductoring 28km of 132kV transmission
lines, Installation of 2x45MVA 132/11kV transformers at
Coventry substation
Cost: USD6.3million
Funding: ZESCO Limited
Status: All works are completed and commissioned.
25
INVESTMENTS
LUSAKA 132KV RING REINFORCEMENT PROJECT –
PHASE II
The objective is to increase the transmission capacity of
the Lusaka Transmission and Distribution Network
Scope: Upgrade of capacity of 132kV transmission lines,
increase capacity of existing substations, create new
substations at 132/33kV, 33/11kV levels, construction
new 33kV and 11kV lines
Cost: USD210million
Funding: World Bank, European Investment Bank and
ZESCO Limited
Status: Negotiations for financing by WB, EIB in process.
Construction period: Completion expected by 201826
INVESTMENTS`ZIZABONA (Zimbabwe, Zambia, Botswana, Namibia)
The objective is to increase regional trade in power by
increasing transmission capacity amongst this group of countries
that also fall within the ambit of the Southern Africa Power Pool,
SAPP.
The project is being promoted by Zimbabwe, Zambia, Botswana
and Namibia and will cost USD230mn
Funding: Discussions ongoing with potential financiers –
Development BSA, AFDB, KfW
Status: technical and market studies completed, project
governance documents prepared
IUMOU, IGMOU signed; Joint Development Agreement to be
signed by Botswana Power Company (BPC). This will lead to the
signing of the Shareholders Agree
Construction period: Commissioning is expected by January
2018 27
INVESTMENTSDISTRIBUTION PROJECTS
ZESCO is carrying out various projects to reinforce and
rehabilitate the distribution infrastructure.
The Distribution, Expansion and Reinforcement Project
(DERP) - USD 106 million - the project is 99% complete.
Increased Access to Electricity Services (IAES) – It is
sponsored by the World Bank, the Japan International Co-
operation Agency (JICA) and other financiers. Thirteen (13)
out of the fifteen (15) project lots had been completed by
30th September 2015.
Euro Bond funded distribution projects (USD69M) – The
projects are progressing, although some fell behind
schedule on account of.delays related to procurement
procedures.28
PLANNED CAPITAL INVESTMENT 2015
+ Results from the current load forecast reveal future
demand/supply imbalances with forecast demand
surpassing forecast supply.
This imbalance will drive long term generation,
transmission and distribution investment plans.
ZESCO planned to expand its capital base in the 2015
Financial Year (FY) Budget by a total of ZMK5, 287bn
as per approved budget, and the equivalent of circa
USD5bn over the full cycle of its 2013-2018 business
plan.
This does not include ZESCO’s participation in the
2,400MW Batoka Hydro-Electric Power Scheme to be
jointly developed with Zimbabwe, whose total cost could
be upwards of USD7.2bn (@USD3mn/MW).
PLANNED CAPITAL INVESTMENT (BREAKDOWN)
STRATEGIC
BUSINESS UNIT
2015
CAPITAL EXPENDITURE (ZMK)
GENERATION 981, 041, 551
TRANSMISSION 2, 578, 742, 003
DISTRIBUTION 1, 500, 819, 593
CORPORATE 220, 040, 160
TOTAL 5, 280, 643, 307
CONCLUSION
ZESCO has been able to show that, either of its own
accord, or in partnership with other equity partners, it is
able to execute projects, although belatedly in some
instances. The delays have been mainly attributable to
delays in attaining Financial Close.
Financial Close, in the past, has been affected by the
nervousness of Lenders/Financiers to lend when the
repayment capacity of ZESCO was questioned.
The decision by GRZ to allow tariffs to migrate to cost
reflective levels will encourage wider participation at all
points of the business value chain of the ESI.
In addition, the bankability of projects is expected to
improve, obviating the need for GRZ support through
government guarantees.31
32
THANK YOU