bw security upgrade gate presentation v3

13
BW Security Upgrade Nov 28th, 2011 Gate 1 Presentation

Upload: gopi7869

Post on 15-Oct-2014

89 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: BW Security Upgrade Gate Presentation v3

BW SecurityUpgrade

Nov 28th, 2011

Gate 1 Presentation

Page 2: BW Security Upgrade Gate Presentation v3

2

Confidential Do Not DistributePrinted Date: 04/07/23

Agenda

Executive SummaryProject TimelineProject OrganizationProject Goals and ObjectivesProject Scope ManagementProject RisksAssumptions and DependenciesWork BreakdownCommunication PlanQuestions

Page 3: BW Security Upgrade Gate Presentation v3

3

Confidential Do Not DistributePrinted Date: 04/07/23

Executive Summary

Our current SAP BW system is in version BW 7.0 and the technical upgrade was done in 2010. Security project was not part of the SAP technical upgrade project, so currently all the SAP systems (BWD, BWQ and BWP) are using old security concepts. SAP has stopped supporting the old security model and requires a mandatory upgrade to BI 7.0 Analysis Authorizations. This is also a pre-requisite for future upgrade like SAP BW upgrade to 7.3

Upgrading to SAP BI 7.0 Analysis Authorizations will be a strong step forward toward building the technical framework for future capabilities.

SAP has introduced new features with the BI 7.0 Analysis Authorizations including improvements to the previous issues and gaps.

The new features contain major improvements for security analysts/administrators.

This upgrade is a purely security technical upgrade. Nevertheless, current security is not structured and therefore the upgrade needs input from the business.

Page 4: BW Security Upgrade Gate Presentation v3

4

Confidential Do Not DistributePrinted Date: 04/07/23

BW Security Upgrade :- Proposed Implementation Timeline

Phase Duration Start Date Completion Date

Preparation & Planning 6 Weeks 4th Jan 2012 15th Feb 2012

Business Blueprint 5 Weeks 16th Feb 2012 21st March 2012

Realization 3 Weeks 22nd March 2012 10th April 2012

Testing 8 Weeks 11th April 2012 4th June 2012

Implementation/Go-Live 1 Week 5th June 2012 10th June 2012

JunMayApr

FY2012

Blueprint

Realization

MarFebJan

Go-Live / Support

Final Prep

Go Live 10th June 2012

AugJul

Prep & Planning

Testing

Page 5: BW Security Upgrade Gate Presentation v3

5

Confidential Do Not DistributePrinted Date: 04/07/23

BW Security Upgrade Organization Chart

Project Management

Project Advisory TeamProject Steering Committee

OCM Lead• Srini Muddala

Finance Lead• Amy Dammann

Program Support

Project Change Control Team

Architecture Review Board

• Mark Sims, Dave Judson, Mark Adams, John Rockwood

• Dave Judson• Mark Sims

• Srini Muddala• Mark Adams

Tom Van Atta, Preston Marshall, John Rockwood, , Dave Judson, Tariq Mahmood, Satish Jain, Alan Darcy, Mark Sims, Tom Czajkowski

Project Managers

• Business Project Manager: Mark Adams

• GBIS Project Manager: Venu Mareddy

• Consulting Project Manager: Jeevan Pulapa

Project Sponsor's)/Chairman: Mark SimsMembers: Tom Czajkowski, Dave Judson, Tom Van

Atta, John Rockwood

• Technical Manager – Srini Muddala• Technical Lead – Venu Mareddy• Security Consultant – Jeevan Pulapa• BW Consultant - TBD• Sr Analyst, Security – Jim Warrington• ACS Project Manager – Russ Leadbetter• ACS Security Consultant – Wally Bettes

Technical• Mark Adams – POS/Shipments• Christine Ellenberger - WCO• Brian Hughes – Supply Chain• Ryan Moore – Finance• Melinda Rogers – HR / TPS

Business / Functional

• Mark Adams• Christine Ellenberger• Brian Hughes• Ryan Moore• Melinda Rogers

Organizational Change Management

Page 6: BW Security Upgrade Gate Presentation v3

6

Confidential Do Not DistributePrinted Date: 04/07/23

Project Goals and Objectives

Upgrade the current SAP Business Warehouse security from BW 3.5 to BI 7.0. Achieve compliance for SAP BW security solution with SAP support levels. Simplify the current security model and remove/delete the obsolete roles, users and

authorization objects. Upgrade to a release of BW that will be supported well into the future. It will provide the BW

System with a foundation to continue Business Development without the obstacle of an obsolete system.

Position the BW solution at Scotts to be upgraded from the current 7.0.1 to 7.3. Redefine approval process which mandates business ownership

Manager Approval

Role Owner Approval

Security Approval Access Granted

Page 7: BW Security Upgrade Gate Presentation v3

7

Confidential Do Not DistributePrinted Date: 04/07/23

Project Scope Management

Functional & Business Scope

The scope of this project will be to upgrade the current security from BW 3.5 to BI 7.0

Scope Inclusions

BW Security Upgrade: Security upgrade from BW 3.5 to BI 7.0 Analysis Authorizations

Analysis of current security model – Review current security model. Delete obsolete/unused users, roles and authorizations.

Access points: Portal, Business Objects (BOE) and any other BW access points are taken into account.

Scope Exclusions

SAP BW Front End tool upgrade and BW 7.3 upgrade

Project Success Criteria

Since this is a technical upgrade, it will be critical that the business retains uninterrupted access of regular and ongoing business functions outside of BW, during and after the upgrade

Grant appropriate access to all the users and ensure system and data security

New Process which involves approvals from business process owners Fewer number of authorization profiles for easy ongoing maintenance

Page 8: BW Security Upgrade Gate Presentation v3

8

Confidential Do Not DistributePrinted Date: 04/07/23

Project Scope Management

Facilities in Scope

All Scotts locations using SAP BW (onsite and remote)

Applications in Scope

SAP BW 3.5, 7.0 and the Testing of systems like BOE and Garden.

Migration Activities in Scope

Migrating the existing roles, users and authorization objects will be in scope for the Upgrade. The Base Upgrade is Strictly Technical.

All the custom authorization objects will be replaced by the analysis authorizations

All the roles will adhere to current naming standards at Scotts Usage of SPM on BWP will be taken into account; the security

model will comply with SPM needs

Page 9: BW Security Upgrade Gate Presentation v3

9

Confidential Do Not DistributePrinted Date: 04/07/23

Project Risk

Resources:

As in any project, resource availability can have negative impact on the progress of the project. Therefore, it is critical that we have business and GBIS commitment.

User acceptance testing will require business representatives to dedicate time to testing scenarios in the upgraded environment.

Hardware Availability:

ACS in the Relationship with The Scott’s Company will be able to provide the hardware in a timely manner to meet the schedules.

Execution:

Business Expectations must be managed to minimize changes to the current BW security during the Upgrade project.

Page 10: BW Security Upgrade Gate Presentation v3

10

Confidential Do Not DistributePrinted Date: 04/07/23

Assumptions and Dependencies

AssumptionsNo new functionality will be introduced; therefore, user processes and transactions should not be impacted.

This is purely a security upgrade from 3.5 to 7.0. No BW upgrade will take place.

Business Users will be available to thoroughly test the applications after the BWQ and BWP conversions.

Business Objects testing will be performed by the current Scotts staff that supports the tool today.

GUI upgrade is not part of the project scope and not a requirement identified at this time.

Dependencies

All SAP interfaces must be successfully tested (where applicable) prior to going live.

Page 11: BW Security Upgrade Gate Presentation v3

11

Confidential Do Not DistributePrinted Date: 04/07/23

Work Breakdown

What goes into upgrading BW 3.5 to BW 7.01 SP6

A BW Sandbox is created.

Each SAP BW Environment (Sandbox, BWD, BWQ, BWP) will be upgraded.

Testing will take place in each environment to confirm a successful upgrade.

•Unit Testing

•Integration Testing

•User Acceptance Testing

Page 12: BW Security Upgrade Gate Presentation v3

12

Confidential Do Not DistributePrinted Date: 04/07/23

Communication Plan

Project Management: Project TeamDaily status meetings for planning, progress, and issue resolutionWeekly status reports postedWeekly meetings with GBIS & ACS Security teams Additional meetings as required

Testing: Project Team and Business RepresentativesDaily status meetings for progress and issue resolution

User Community:Daily communication beginning one week prior to cutover through the first week of transition. All the users in the BWQ system will be notified about the freeze during the simultaneous unit testing by BI Team and UAT by Super Users.All users will be asked to test their access in BWQ after the freeze is lifted. This will be the access they would get in production after going live.All the users will be notified about the go-live date. Contact information will also be provided in case the user should run into any issue.Help desk will be notified about the go-live date as well.

Page 13: BW Security Upgrade Gate Presentation v3

13

Confidential Do Not DistributePrinted Date: 04/07/23

Milestones

Upgrade of Sandbox, BWD, BWQ, and BWP

Unit Testing

Integration Testing

User Acceptance Testing

Go-Live within 96 hours

Phase Duration Start Date Completion Date

Preparation & Planning 6 Weeks 4th Jan 2012 15th Feb 2012

Business Blueprint 5 Weeks 16th Feb 2012 21st March 2012

Realization 3 Weeks 22nd March 2012 10th April 2012

Testing 8 Weeks 11th April 2012 4th June 2012

Implementation/Go-Live 1 Week 5th June 2012 10th June 2012