BW SecurityUpgrade
Nov 28th, 2011
Gate 1 Presentation
2
Confidential Do Not DistributePrinted Date: 04/07/23
Agenda
Executive SummaryProject TimelineProject OrganizationProject Goals and ObjectivesProject Scope ManagementProject RisksAssumptions and DependenciesWork BreakdownCommunication PlanQuestions
3
Confidential Do Not DistributePrinted Date: 04/07/23
Executive Summary
Our current SAP BW system is in version BW 7.0 and the technical upgrade was done in 2010. Security project was not part of the SAP technical upgrade project, so currently all the SAP systems (BWD, BWQ and BWP) are using old security concepts. SAP has stopped supporting the old security model and requires a mandatory upgrade to BI 7.0 Analysis Authorizations. This is also a pre-requisite for future upgrade like SAP BW upgrade to 7.3
Upgrading to SAP BI 7.0 Analysis Authorizations will be a strong step forward toward building the technical framework for future capabilities.
SAP has introduced new features with the BI 7.0 Analysis Authorizations including improvements to the previous issues and gaps.
The new features contain major improvements for security analysts/administrators.
This upgrade is a purely security technical upgrade. Nevertheless, current security is not structured and therefore the upgrade needs input from the business.
4
Confidential Do Not DistributePrinted Date: 04/07/23
BW Security Upgrade :- Proposed Implementation Timeline
Phase Duration Start Date Completion Date
Preparation & Planning 6 Weeks 4th Jan 2012 15th Feb 2012
Business Blueprint 5 Weeks 16th Feb 2012 21st March 2012
Realization 3 Weeks 22nd March 2012 10th April 2012
Testing 8 Weeks 11th April 2012 4th June 2012
Implementation/Go-Live 1 Week 5th June 2012 10th June 2012
JunMayApr
FY2012
Blueprint
Realization
MarFebJan
Go-Live / Support
Final Prep
Go Live 10th June 2012
AugJul
Prep & Planning
Testing
5
Confidential Do Not DistributePrinted Date: 04/07/23
BW Security Upgrade Organization Chart
Project Management
Project Advisory TeamProject Steering Committee
OCM Lead• Srini Muddala
Finance Lead• Amy Dammann
Program Support
Project Change Control Team
Architecture Review Board
• Mark Sims, Dave Judson, Mark Adams, John Rockwood
• Dave Judson• Mark Sims
• Srini Muddala• Mark Adams
Tom Van Atta, Preston Marshall, John Rockwood, , Dave Judson, Tariq Mahmood, Satish Jain, Alan Darcy, Mark Sims, Tom Czajkowski
Project Managers
• Business Project Manager: Mark Adams
• GBIS Project Manager: Venu Mareddy
• Consulting Project Manager: Jeevan Pulapa
Project Sponsor's)/Chairman: Mark SimsMembers: Tom Czajkowski, Dave Judson, Tom Van
Atta, John Rockwood
• Technical Manager – Srini Muddala• Technical Lead – Venu Mareddy• Security Consultant – Jeevan Pulapa• BW Consultant - TBD• Sr Analyst, Security – Jim Warrington• ACS Project Manager – Russ Leadbetter• ACS Security Consultant – Wally Bettes
Technical• Mark Adams – POS/Shipments• Christine Ellenberger - WCO• Brian Hughes – Supply Chain• Ryan Moore – Finance• Melinda Rogers – HR / TPS
Business / Functional
• Mark Adams• Christine Ellenberger• Brian Hughes• Ryan Moore• Melinda Rogers
Organizational Change Management
6
Confidential Do Not DistributePrinted Date: 04/07/23
Project Goals and Objectives
Upgrade the current SAP Business Warehouse security from BW 3.5 to BI 7.0. Achieve compliance for SAP BW security solution with SAP support levels. Simplify the current security model and remove/delete the obsolete roles, users and
authorization objects. Upgrade to a release of BW that will be supported well into the future. It will provide the BW
System with a foundation to continue Business Development without the obstacle of an obsolete system.
Position the BW solution at Scotts to be upgraded from the current 7.0.1 to 7.3. Redefine approval process which mandates business ownership
Manager Approval
Role Owner Approval
Security Approval Access Granted
7
Confidential Do Not DistributePrinted Date: 04/07/23
Project Scope Management
Functional & Business Scope
The scope of this project will be to upgrade the current security from BW 3.5 to BI 7.0
Scope Inclusions
BW Security Upgrade: Security upgrade from BW 3.5 to BI 7.0 Analysis Authorizations
Analysis of current security model – Review current security model. Delete obsolete/unused users, roles and authorizations.
Access points: Portal, Business Objects (BOE) and any other BW access points are taken into account.
Scope Exclusions
SAP BW Front End tool upgrade and BW 7.3 upgrade
Project Success Criteria
Since this is a technical upgrade, it will be critical that the business retains uninterrupted access of regular and ongoing business functions outside of BW, during and after the upgrade
Grant appropriate access to all the users and ensure system and data security
New Process which involves approvals from business process owners Fewer number of authorization profiles for easy ongoing maintenance
8
Confidential Do Not DistributePrinted Date: 04/07/23
Project Scope Management
Facilities in Scope
All Scotts locations using SAP BW (onsite and remote)
Applications in Scope
SAP BW 3.5, 7.0 and the Testing of systems like BOE and Garden.
Migration Activities in Scope
Migrating the existing roles, users and authorization objects will be in scope for the Upgrade. The Base Upgrade is Strictly Technical.
All the custom authorization objects will be replaced by the analysis authorizations
All the roles will adhere to current naming standards at Scotts Usage of SPM on BWP will be taken into account; the security
model will comply with SPM needs
9
Confidential Do Not DistributePrinted Date: 04/07/23
Project Risk
Resources:
As in any project, resource availability can have negative impact on the progress of the project. Therefore, it is critical that we have business and GBIS commitment.
User acceptance testing will require business representatives to dedicate time to testing scenarios in the upgraded environment.
Hardware Availability:
ACS in the Relationship with The Scott’s Company will be able to provide the hardware in a timely manner to meet the schedules.
Execution:
Business Expectations must be managed to minimize changes to the current BW security during the Upgrade project.
10
Confidential Do Not DistributePrinted Date: 04/07/23
Assumptions and Dependencies
AssumptionsNo new functionality will be introduced; therefore, user processes and transactions should not be impacted.
This is purely a security upgrade from 3.5 to 7.0. No BW upgrade will take place.
Business Users will be available to thoroughly test the applications after the BWQ and BWP conversions.
Business Objects testing will be performed by the current Scotts staff that supports the tool today.
GUI upgrade is not part of the project scope and not a requirement identified at this time.
Dependencies
All SAP interfaces must be successfully tested (where applicable) prior to going live.
11
Confidential Do Not DistributePrinted Date: 04/07/23
Work Breakdown
What goes into upgrading BW 3.5 to BW 7.01 SP6
A BW Sandbox is created.
Each SAP BW Environment (Sandbox, BWD, BWQ, BWP) will be upgraded.
Testing will take place in each environment to confirm a successful upgrade.
•Unit Testing
•Integration Testing
•User Acceptance Testing
12
Confidential Do Not DistributePrinted Date: 04/07/23
Communication Plan
Project Management: Project TeamDaily status meetings for planning, progress, and issue resolutionWeekly status reports postedWeekly meetings with GBIS & ACS Security teams Additional meetings as required
Testing: Project Team and Business RepresentativesDaily status meetings for progress and issue resolution
User Community:Daily communication beginning one week prior to cutover through the first week of transition. All the users in the BWQ system will be notified about the freeze during the simultaneous unit testing by BI Team and UAT by Super Users.All users will be asked to test their access in BWQ after the freeze is lifted. This will be the access they would get in production after going live.All the users will be notified about the go-live date. Contact information will also be provided in case the user should run into any issue.Help desk will be notified about the go-live date as well.
13
Confidential Do Not DistributePrinted Date: 04/07/23
Milestones
Upgrade of Sandbox, BWD, BWQ, and BWP
Unit Testing
Integration Testing
User Acceptance Testing
Go-Live within 96 hours
Phase Duration Start Date Completion Date
Preparation & Planning 6 Weeks 4th Jan 2012 15th Feb 2012
Business Blueprint 5 Weeks 16th Feb 2012 21st March 2012
Realization 3 Weeks 22nd March 2012 10th April 2012
Testing 8 Weeks 11th April 2012 4th June 2012
Implementation/Go-Live 1 Week 5th June 2012 10th June 2012