Practical Sustainability
Kirsten Henson
builtfortraining.co.uk
Welcome and Introductions
builtfortraining.co.uk
builtfortraining.co.uk builtfortraining.co.uk
What we said we’d cover:•Legislative drivers and business opportunities
•Formulation and delivery of a comprehensive sustainability strategy
•Design, specification and procurement to maximise innovation
•Assessing the broader value of sustainable solutions
And what we said you would know after today:•Have a sound understanding of the key principles of sustainability
•Understand the key steps in defining, evaluating and delivering sustainable solutions
•Appreciate when, who and how to engage for maximum impact
•Be inspired by the challenge and opportunity that sustainable development offers!
builtfortraining.co.uk
The Day Ahead9:45 What is Sustainability and Why Care?
10:30 Group Discussion: Too Late to Try or Massive Opportunity?
10:45 Setting Out on the Sustainable Path
11:15 Group Exercise: Problem Definition
BREAK (20mins)
12:00 Olympic Examples: Process for Delivering Sustainability
12:40 Group Exercise – KPIs
LUNCH (30mins)
13:30 Olympic Examples: Design, Procurement and Specification
14:30 Group Discussion: Methods of Engagement and Communication
BREAK (15mins)
15:00 Selling Sustainable Solutions (including worked example)
15:40 Closing Remarks and Session Review
builtfortraining.co.uk
Health & Safety Attendance register
Fire Exits Rest Breaks
Smoking AreaMobile phones switched off
Personal Property
builtfortraining.co.uk
What is Sustainability? The Definition
The ‘Brundtland’ Definition:“sustainable development is development that meets the needs of the present without compromising the
ability of future generations to meet their own needs” WCED (1987:43) Our Common Future, Oxford University Press, Oxford
“The Brundtland Commission’s conception of sustainable development brought together
equity between generations
and
equity within generations.
Bringing these two ideas together was a political masterstroke.”Dresner, S. (2002:2) The Principles of Sustainability, Earthscan, London
builtfortraining.co.uk
What is Sustainability? The Principals
Four common principles have been identified as underlying the generic concept:
• futurity (concern for future generations)
• equity (concern for today’s poor and disadvantaged)
• public participation (concern that individuals should have an opportunity to participate in decisions that effect them)
• environment (concern for the protection of the integrity of eco-systems)
Mitchell, G., May, A. and McDonald, A. (1995:107) Picabue: A Methodical Framework for the Development of Indicators for Sustainable Development International Journal of Sustainable Development and World Ecology, 2 pp.104-123
builtfortraining.co.uk
The Ecological Footprint tool has been used to demonstrate that if current developed-world levels of consumption and production were replicated world-
wide we would need three planets’ worth of resources DEFRA (2005:43) Securing the Future: The UK Government Sustainable Development Strategy, HMSO, London
What is Sustainability? The Principals
builtfortraining.co.uk
What is Sustainability? The ModelsThe Triple Bottom Line
• commonly conceptualised using a Venn diagram
• suggests a balance needs to be found between the three elements
• can lead to the tackling of issues in a compartmentalised manner
• Venn diagram has been modified so the three areas are nested
after Parkin et al. (2003:19)
after Giddings et al. (2002:192)
Environment
Economy Society
EnvironmentEconomySociety
= Triple bottom line
builtfortraining.co.uk
Why Care?Global Warming and Climate Change
Source: National Oceanic and Atmospheric Administration
builtfortraining.co.uk
builtfortraining.co.uk
Why Care?The Energy Gap
The problem with nuclear?
builtfortraining.co.uk
The problem with oil?
builtfortraining.co.uk
• Geochemically scarce metals like copper, zinc, lead will be depleted in a matter of decades
• Iron, aluminium and steel are more plentiful but…
• EPA places poor indoor air quality fourth on the list of high cancer risks
• UK landfill space will run out in 8 years time
Assuming rates of consumption remain unchanged:
Why Care?Material scarcity and human health impacts
builtfortraining.co.uk
• Water scarcity in England and Wales, abstraction licenses will become increasingly difficult to come by
• Global picture for water scarcity consider (per tonne of product):• 60,000l for pulp/paper• 283,900l for steel (of which
75,700l freshwater)
Why Care?Water scarcity
builtfortraining.co.uk
Why Care?Declining Habitats
builtfortraining.co.uk
Why Care?The ‘Big Society’
Millions of people are chronically hungry in Sub-Saharan Africa and Southern Asia where half the children under age
five are malnourishedUN (2005) The Millennium Development Goals Report, UN, New York
Develop, support and champion new ways of enabling people to give and engage. Make it easier and more rewarding for
people to give their time, expertise and money to good cause.
builtfortraining.co.uk
Why Care?It makes business sense
• Landfill tax to reach £72/tonne in April 2013• Emissions Trading Scheme, Carbon Reduction Credits (CRC)• UK Green Investment Bank• ‘Green’ investment dollars have increased 10 fold over the past
10years. Third pillar alongside IT and life sciences• Linking CSR to business competitiveness
“The world cannot succeed without business as a committed solution provider to sustainable societies and ecosystems”
WBCSD President Bjorn Stigson
builtfortraining.co.uk
The population problem?
builtfortraining.co.uk
Securing the Future – the UK Government Sustainable Development Strategy
1.Sustainable consumption and Production• Sustainable procurement policies• Strengthening measures to improve environmental performance of
products2.“Confronting the greatest threat” – climate change and energy
• 60% reduction in CO2 emissions by 2050• Zero Carbon Homes by 2016 – really?
3.Protecting our natural resources and enhancing the environment• Enhancing the role of the Environment Agency, integration with
DEFRA4.Creating Sustainable Communities and a Fairer World
• Sustainability at the heart of land use planning
Government Policy
builtfortraining.co.uk
Government PolicyPolicy is all over the place!
Driven by EU legislation on Climate Change, Waste, Water, Energy and Biodiversity
3 key departments
•DECC – Department for Energy and Climate Change http://www.decc.gov.uk/
•DEFRA – Department for Environment, Food, and Rural Affairs http://ww2.defra.gov.uk/
•DCLG - Department for Communities and Local Governmenthttp://www.communities.gov.uk/planningandbuilding/planningsystem/planningpolicy/planningpolicystatements/
builtfortraining.co.uk
Group Discussion
It’s too late to try
I’m too small to make a
difference
I’m too busy to bother with this
We need to take this one step at a time
If we can get this right, there’s a
massive opportunity out there
builtfortraining.co.uk
Setting out on the Sustainable PathReframing the problem
What needs are being addressed?
What are the benefits, and who stands to gain?
What are the costs, and who stands to lose?
To what spatial and temporal extent should we consider the impacts and benefits?
builtfortraining.co.uk
Setting out on the Sustainable PathScenario Planning
carboncreativity
green growth
resourceful regions
sunshine state
Government Office for ScienceSustainable Energy Management and the Built Environment
builtfortraining.co.uk
Setting out on the Sustainable PathBarriers to Change
• Lack of data to inform decision making
• Global nature of issues
• Fear of failure
• Single purpose design focus
• Market failure
• Personal behaviour and expectation
builtfortraining.co.uk
Setting out on the Sustainable PathOvercoming Barriers
• Broadening the problem definition and evaluation criteria
• Visionary leadership
• Regulatory requirements
• Transparent and upfront engagement with stakeholders
• Education and training
• Data collection and publication
• Promotion of ‘soft-failure’
• Ownership and responsibility
builtfortraining.co.uk
Setting out on the Sustainable PathRole of Government and Legislation
• Removal of perverse incentives of regulations
• Direct support for R&D and incentives for innovation
• Creation and dissemination of knowledge through experimentation and demonstration projects
• Creation of markets through government purchasing
• Training of owners, workers, and educating of consumers
builtfortraining.co.uk
Setting out on the Sustainable PathWhy does it not work better?
• By externalising the internalities in a system, the consequences can be exported to others
• By setting narrow boundaries to a system the true impacts of a proposed project are masked, or ignored
• By failing to incorporate the time dependent consequences of a proposed project, the long term impacts are omitted
• By limiting the responsibility of the individuals in a process the defence of “it wasn’t my job to consider that” can be invoked
builtfortraining.co.uk
Group ExerciseThe drawing of tight boundaries around systems or
projects gives a false impression of impacts and compromises sustainability
Select a project: Three Gorges Dam in China, Hydropower from the Severn Estuary, burning of waste tyres as a fuel in cement works, or….
Consider: System / Project boundaries How can needs be defined? How do we allow for future generations? How much should we leave for them? Who should be involved in decision making? How should natural environment be protected? How do we decide how to share resources now? Should people accept a reduced standard of living?
builtfortraining.co.uk
builtfortraining.co.uk
Olympic Example
• Vision and target setting
• Structure, responsibilities, communication
• Reporting and Measurement
builtfortraining.co.uk
The Vision
To be the ‘Greenest Games Ever’‘One Planet’ Olympics
builtfortraining.co.uk
The Sustainable Development StrategyPublished in January 2007. Available on-line at http://www.london2012.com/documents/oda-publications/oda-sustainable-development-strategy-full-version.pdf
Identifies a few site-wide measurable targets including:Energy:
Olympic Village to be 25% more energy efficient than 2006 Building Regs20% of all energy demands for the immediate post-Games Legacy to be derived from on-site renewables
Water:All permanent Venues to reduce water consumption by 40% over current industry standards.
Waste:90%, by weight, of demolition materials to be diverted from landfill
Materials:20%, by value, of construction materials to be of a reused or recycled source
Transport and Mobility:50% of materials, by weight, to be transported to and from the Olympic Park by rail or water during construction
Identifies numerous non-SMART targets:Water:
– Promote rainwater harvesting/greywater recycling where feasibleWaste:
– Operate within the ODA’s waste hierarchy of eliminate, reduce, re-use, recycle, energy recovery, dispose
Ecology and Biodiversity:– Enhancing the ecological value of the Park through integration of habitat
creation and landscape designLand, Water, Air and Noise:
– Waterways planned to be improved for transport, amenity and biodiversity
Supporting Communities:– Protect and enhance ‘sense of place’ and ‘sense of ownership’
Health and Well-Being:– ODA will provide welfare facilities for a diverse workforce
The Sustainable Development Strategy
builtfortraining.co.uk
• ODA/CLM Sustainability and Environment Team:– Carbon– Water– Waste– Materials– Biodiversity and Ecology– Land, Water, Air and Noise
• Other ODA/CLM teams:– Supporting Communities– Transport and Mobility– Access– Employment and Business– Health and Well-Being– Inclusion
Roles and Responsibilities
builtfortraining.co.uk
Stadiu
m
Velop
ark
SBHAqu
atics
Public
Rea
lm
Baske
tball
Monitoring and Supporting Project TeamsProject Champions (SPOCs)
Tech
nica
l Cha
mpi
ons
Energy
Water
Waste
Materials
Biodiversity
Communication and Engagement
Design Briefs•Detailed sustainability objectives
Implementation Guides to Project Teams (IGPTs)•Targets and assessment tools•Reporting requirements against RIBA design stages•Advice and guidance but not ‘The Answer’
Workshops•Theme workshops with Design teams•Environment and Sustainability workshop prior to contractor start on site•On going progress meetings and Leadership groups
builtfortraining.co.uk
Supply Chain Workshops• Interpretation of high level objectives into work
package specifics• Drive understanding and ownership
Procurement• Balanced scorecard approach • Sustainable option (where identified) stated as the
preferred option, or invite innovations to be presented• Buying power and partnership
Contracts•All contracts contain Olympic Park generic and Project specific sustainability requirements
Communication and Engagement
builtfortraining.co.uk
Balanced Scorecard Approach
builtfortraining.co.uk
Development of KPIs and Reporting• Contractors ‘self-assure’ using an on-line system• Review by Single Point of Contact before going to the Project Board.• Executive Management Team challenge Project Team on red and amber
scores• Above all ACCOUNTABILITY
builtfortraining.co.uk
Group ExerciseIn small groups determine a sustainability ‘vision’ for your businessConsider:•What does your client want?•What are your competitors doing?•What skills do you have?•How can the be utilised to deliver extra value?•What might the team structure look like?
Develop 2 or 3 clear targets to help measure progress towards your visionConsider:•Are the targets SMART?•How will you monitor progress towards non-SMART targets?•Do they address the most significant (and possibly challenging) opportunities and threats?
builtfortraining.co.uk
builtfortraining.co.uk
Olympic Successes
builtfortraining.co.uk
• Materials
• Waste
• Energy
• Water
• Biodiversity
• Transport
Areas of Innovation
builtfortraining.co.uk
Demolition Materials Management System
1. Reclamation surveys: Identification of reclamation opportunities
2. Pre-demolition Audits: Quantification of all materials; reclaimed, recycled and disposed (hazardous waste)
3. Project Managers Instruction: Instruction to contractors to reclaim or recycle materials
4. Demolition Activities: Justification report required if PMI cannot be carried out.
5. Recording: Material stockpiles from demolition entered into SMARTWaste
Soil washing 800,000m3. Useful sands and gravel generated (and not so useful contaminated waste!)
Earthworks and RemediationOver 3,000,000m3 of soil ‘cut’, of which 2,400,000m3 have been placed
Bio-remediation of soils 38,000m3Chemical stabilisation 50,000m3Complex sorting 80,000m3
builtfortraining.com
•
Recycled Materials Stockpiles of concrete, mixed masonry, asphalt, blended materials and general fill…
Construction Platforms and piling mats20,000m3
Haul roads and temporary roads50,000m3
Gabion fill30,000m3
Recycled Materials
• Capping under permanent roads• Structural fill• Earth retaining walls
Reclaimed Materials are now being installed on site!
builtfortraining.com
Reclamation for Use Off-Site
Sold for £148,000
290 tonnes of Carbon saved
Embodied Impact of Materials / Recycled Content
Concrete – ready mix 347,500m3 poured to date, 375,000m3 expected
Park-wide, 22% secondary aggregates used in ready mix concrete38% reduction in embodied energy (56,000 tonnes CO2 saved to date
– equivalent to almost 4.5 years of Park operation, or 9 years….)
Concrete – pre castChallenging the supply chain sometimes yields great results…
Reuse of steel3000 tonnes – enough to build that massive roof!
builtfortraining.co.uk
builtfortraining.co.uk
Embodied Impact / Recycled ContentFoam-mixReplacement sub base for temporary roads5000m3 additional site won material used25 tonnes CO2 saved40% increased recycled content of road construction
Precast manholes in South Park roads45% reduction in carbon footprintApproaching zero waste construction
Plastic kerbsInstalled on temporary roads360,000 plastic bottles29 tonnes CO2 saved
builtfortraining.co.uk
Healthy Materials
• Zero asbestos, lead, CFCs, etc
• Reduce VOCs, Formaldehydes…
• Key risk areas include:– Paints, stains and varnishes– Adhesives– Caulking compounds– Carpeting– Particle board– Ceiling tiles– Floor and wall coverings
•Water based form release agents, curing agents, etc
Responsible Sourcing
• ISO 14001• Timber Supply Panel
FSC / PEFC
• BCSA Responsible Sourcing of Steel• BES6001: Responsible Sourcing Certification Scheme
Timber Deliveries - Delivery Booking Module
3
14 16
27
45 46
65 69 69
47
31
14
51 49
76
96 99
2316 19 19
61 2 0 0 0 0 0 0 0 0
70
26 3035
4651 47
67 69 69
47
31
14
51 49
76
103 99
0
20
40
60
80
100
120
Jan
'09
Feb '0
9
Mar
'09
Apr '0
9
May
'09
Jun
'09
Jul '0
9
Aug '0
9
Sep '0
9
Oct
'09
Nov '0
9
Dec '0
9
Jan
'10
Feb '1
0
Mar
'10
Apr '1
0
May
'10
2009 / 2010
No
. Del
iver
ies
Panel
Non-panel
Total
builtfortraining.co.uk
Waste (or Material?) Management
• The most sustainable material is one that is never used!
• A material in a structure with no engineering purpose is ‘waste’
builtfortraining.co.uk
• All buildings have an ‘end of life’ but some materials maintain performance
• The sustainable option is not always the obvious one
Construction Waste Management
• Designing out Waste, Design for deconstruction, Reducing Waste through supply chain engagement
• Consolidated on site reduces vehicle movements
• Contractors financially incentivised to segregate waste (>85% segregation)
• Achieved 97% diversion from landfill for demolition waste and over 80% for earthworks
• Just over 90% of construction waste has been diverted from landfill to date
builtfortraining.com
• Mean - Venues designed to be 15% more energy efficient than Part L
• Lean - Combined Cooling and Heating Plant (CCHP) on site• Green - Biomass gasification, medium scale wind turbine, PV
lighting
Energy: 50% carbon reductions
Water: 40% reduction in water consumption
builtfortraining.co.uk
• Low flow fixtures and fittings (including waterless urinals in all Venues)
• Grey water recycling in Aquatics
• Rainwater harvesting in Velodrome and Handball
• Non-potable network for long-term irrigation, media centre toilet flushing (and CCHP cooling tower?)
Biodiversity: 45ha of habitat, 0.4ha living roofs/walls, 675 bird/bat boxes integrated in structures and buildings
•Bird boxes integrated into structures and buildings •Completed brown roof and green wall•Complex habitat such as wetlands and wet woodlands to be developed and integrated with drainage systems
builtfortraining.co.uk
Transport: 50% of bulk materials to be delivered to site by rail
• Rail deliveries to date:– 95% of raw materials for concrete – Over 90% of loose aggregates – Majority of kerb stones– Precast concrete units– Tiles and plasterboard
Barge deliveries to date:– Rebar cages– M&E pipe work– Waste removal
8,000 tonnes CO2
50,000 road movements
builtfortraining.co.uk
Repeating Successes• Vision• Targets• Accountability and Ownership• Reporting & review
But what about implementation?• Team structure• Communication• Technical support and written guidance• Procurement processes and contracts• Demonstration projects• Replicate process for driving innovation rather than directly translating
innovations
builtfortraining.co.uk
Group DiscussionWhat are the key points in communicating sustainability?
•Instil a positive attitude, inspire rather than dictate•Know when to let an opportunity go…and know when to keep pushing•Get in early and keep pushing•Find the ‘hook’•Communicate in simple, understandable terms that are relevant to specific job functions•Use samples and demonstrations to make your point•Frame the innovation in terms of the organisations key drivers•If at first you don’t succeed…consider the bigger picture, and try again!
builtfortraining.co.uk
builtfortraining.co.uk
Evaluating Sustainable SolutionsCost Benefit Analysis
• Enumerates all possible consequences• Estimates the probability of consequences occurring• Estimates the benefit of loss to society should each occur (expressed in monetary terms
Benefits: • Clarifies choice among alternatives• Potential to foster an open and fair decision-making process• Total impact can be summarised using a common matrix
Limitations • Subject to the same limitations of conventional economic theory• Valuation of health related benefits and eco system services is not understood in detail
(not bought and sold on the open market therefore no clearly defined economic value)• Discount rates – future benefits retain little value in present terms• Overlooks equity and ethics bottom line myopia – lack of appreciation of complexities• Vested interest in the ‘right; outcome can lead to constructed CBAs
builtfortraining.co.uk
Direct Resources:• Building materials• Food• Medicine• Clothing
Evaluating Sustainable SolutionsEcosystem Services
Functional Services• Maintenance of atmospheric gases• Generation and preservation of soils• Disposal of wastes• Control of pests• Cycling of nutrients• Maintenance of the water cycle.
builtfortraining.co.uk
• Disaggregated decision making process
• Keeps each factor in its natural non-aggregated units
Benefits:
• Framework does not specify a final decision – it is a decision making tool
• Avoids assumptions about how to translate environmental, H&S impacts to monetary value
Evaluating Sustainable SolutionsTrade Off Analysis
builtfortraining.co.uk
An Example: Olympic Park Concrete
builtfortraining.co.uk
A Worked Example
Remember these?
builtfortraining.co.uk
A Worked ExampleWhat might be the consideration of plastic vs concrete kerb stones?
How can we address these consideration?
• Visual• Health & Safety – concrete dust, manual handling, plant &
equipment• Recycled content• Transportation• Local manufacture• Wastage rates/damage• Laying technique/skills required• Cost of material• Cost of labour• Programme implications
builtfortraining.co.uk
A Worked Example
Estimated Actual
Concrete Durakeb Concrete Durakerb
Purchase price £2.00 £8.00 £2.19 £8.00
Installation volume/day 100 480 150 200
Installer labour £2.40 £0.50 £4.75 £4.25
Lifter/JCB £1.96 0 Inc
Kerb race installation and haunching
£12.50 £12.50 £12.50 £12.50
Damage rate 15% 2% 15% 2%
Damage costs £2.83 £0.42 £2.83 £0.42
INSTALLED COSTPer linear metre
£21.69 £21.42 £22.36 £25.25
No of days for installation
35days 7days 12days 9days
builtfortraining.co.uk