building response to excavation

Upload: kam-lau

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Building Response to Excavation

    1/80

    1/22/2009

    1

    Examples of building response toxamples of building response toexcavation and tunnelingxcavation and tunnelingBarcelona

    December 16, 2008

    Edward J . CordingEdward J . Cording

    University of Illinois at UrbanaUniversity of Illinois at Urbana--ChampaignChampaign

    , . , . , . , ..

    In the cases illustrated, the structures themselves served as indicators of the type andcauses of distortions and damage that were imposed on them. The ability to observeand read the building response is aided by an understanding of the chain ofrelationships that extends from the excavation or tunnel and adjacent ground loss orground movement, to the distribution of ground movement and volume change throughthe soil mass, to the interaction of the ground with the building, and then to the buildingdistortion and damage.

    To properly assess the building behavior both distortion and damage -- it is necessaryto understand not only the ground movement patterns but also the buildings structuralcharacteristics and finishes: how the building was built, maintained, and repaired.

    Often the effects of excavation and tunneling are superposed on pre-existing distortionsand deterioration. In many cases, pre-existing conditions are separate from andunrelated to the excavation- or tunnel-induced damage.

    u w u vattribute pre-existing conditions in their building to the effects of the adjacent excavationand tunneling.

    Pre-construction photographs and video are important in resolving such issues as wellas early set up of monitoring to obtain a history of building movements due totemperature and seasonal changes. In addition, a logical evaluation and description ofthe limits and magnitude of ground movements and building distortions due toexcavation or tunnelin and earl reco nition and acce tance of res onsibilit for

  • 7/28/2019 Building Response to Excavation

    2/80

    1/22/2009

    2

    1. Structures often serve as indicators of the causes of imposed distortionsand damage

    2. Understand the chain of relationships and behavior extending from tunnel orexcavation to buildingGround movement sources and ground loss

    roun movemen pa erns an vo ume c angeBuilding structural characteristics and finishes - - - how it was built,

    maintained and repaired.

    3. Effects of excavation and tunneling may be superposed on pre-existingbuilding distortions and deterioration

    4. Effects of excavation and tunnelin ma be se arate from and unrelated to

    pre-existing building distortions and damage

    It is most common and natural for residents and owners of buildings toobserve and attribute pre-existing conditions in their building to theeffects of the adjacent excavation or tunneling.

    Benefits of:

    . re-constructon assessments an nspecton, p otograp s an v eo-- Assess condition of buildings, sensitivity to damage, whether due to

    tunneling and excavation or other effects.

    -- Assess structural characteristics and building finisheslateral and distortional stiffnesses, weak zones.2. A logical evaluation and description of the limits and magnitude of

    ground movements and building distortions due to excavation ortunnelin : zone of influence sizeof buildin with res ect to settlementtrough, change in ground slope.

    3. Early building monitoring to determine temperature &seasonal effects.4. Community relations efforts by contractor, engineer and owner

    throughout design and construction.5. Early recognition and acceptance of responsibility for excavation or

    tunneling induced-damage

  • 7/28/2019 Building Response to Excavation

    3/80

    1/22/2009

    3

    Increasing ground loss can result in disproportionateincreases in round movement and buildin dama e

    Small ground losses may be absorbed by volume increases insoil.

    Building damage increases disproportionately with strains

    Objective: control ground losses at the tunnel

    Increasingly, with pressurized face tunneling, ground movements

    are being controlled at the source, around the tunnel shield tolevels that result in negligible damage at the ground surface

    Objective: reduce risk of large ground losses or collapse

    Examples of building response toExamples of building response to

    excavation and tunnelingexcavation and tunneling

    Review of ground movements and buildingReview of ground movements and building

    Characteristics of bearing wall structuresCharacteristics of bearing wall structures

    Bearing walls parallel to tunnel or excavationsBearing walls parallel to tunnel or excavations Separation of upper wallSeparation of upper wall

    Side sway of framesSide sway of frames

  • 7/28/2019 Building Response to Excavation

    4/80

    1/22/2009

    4

    2. REVIEW2. REVIEW

    Sources of ground movementSources of ground movement

    RiskRisk of large, uncontrolledof large, uncontrolled ground loss in faceground loss in face

    Shield, EPB:Shield, EPB:

    ControlControl of conditioner and pressure in faceof conditioner and pressure in face

    NATM:NATM:

    Instability at faceInstability at face

    Lining failure during or after excavation sequencesLining failure during or after excavation sequences

    Regular ground lossRegular ground loss

    Shield: AnnularShield: Annular spacesspaces Overcut at front of shieldOvercut at front of shield

    Grout annulus between tail of shield and liningGrout annulus between tail of shield and lining

    NATM: Lining deflection and ground displacement during excavationNATM: Lining deflection and ground displacement during excavation

    Volume decreaseVolume decrease inin soilsoil DewateringDewatering

    Stress increases around tunnelStress increases around tunnel

  • 7/28/2019 Building Response to Excavation

    5/80

    1/22/2009

    5

    Distortion/damageDistortion/damage

    Width of settlement trough

    Angular distortion andLateral strain

    LINKLINKb

    Volumechange

    Volume ofSettlementtrough

    Slope ofsettlement trough

    Settlement & Lateral displacement

    slope beneathstructure

    EstimateEstimate of regularof regulartunnel groundtunnel ground lossloss

    Source ofground loss

    Soft Clay: Short term: VS ~ VLAfter consolidation: VS > VL

    Estimating Volume loss

    (2) Surface Volume, VS = VL - VVs

    Large depth/diameter,very dense: VS

  • 7/28/2019 Building Response to Excavation

    6/80

    1/22/2009

    6

    (3) Estimating Surface Settlement

    w = r + Z tan b

    max = Vs/w= Trou h Sha e: Gaussian Distribution

    max

    w = 2.5 ii

    Vs

    /w

    /max = exp ( (x/i)2)Schmidt, Peck, 1969

    b oZ Typical values of Angle b:

    Sand: 26o Clay: 40o

    (+ ~ 5o)

    Cording & Hansmire, 1975

    (4) Estimating Lateral Movement

    (a) Lateral displacement (b) Lateral strain

    w = 2.5 i

    Li

    V

    VS mMaximum lateral displacement,

    L@ Inflection point, i :

    L = 1/3 m (tan b/ 0.5)

    FIGURE 3.7 12

    L

    r

    L = m/ w) tan b~ 1/ 2 to 1 x average

    settlement slope

  • 7/28/2019 Building Response to Excavation

    7/80

    1/22/2009

    7

    L L

    ANGULAR DISTORTION, LATERAL STRAIN, L(Shear Strain)

    ope

    L = L / L90

    1. Building moves with ground &extends beyond settlement zone:

    w

    m

    Angular Distortion ~

    FIGURE 3.6 14

    r

    Average S ope:

    ~ m /w

  • 7/28/2019 Building Response to Excavation

    8/80

    1/22/2009

    8

    2. Building moves with ground & is narrow enough to tilt,distortion concentrated in unit 1.

    w

    Lb

    m

    Angular Distortion = Slope Tilt

    Angular Distortion = Change in

    FIGURE 3.6 15

    r Angular Distortion conservativelyestimated as:

    < (m /w) (Lb/w)groun s ope e ween wo un s

    3. Building moves with ground & is narrow enough to tilt,frame is subject to side sway, which increases tilt

    w

    Lb

    m

    AngularDistortion = Slope Tilt

    FIGURE 3.6 16

    r

    ~ prevous case

    Distortion in both sections ofbuilding

  • 7/28/2019 Building Response to Excavation

    9/80

    1/22/2009

    9

    4. Building stiff laterally

    Grade beams and structural frames reducelateral strain to less than ground strain

    Ground strain is concentrated at edges ofbuilding, construction joints between units,or weaker zones in building.

    Angular distortion,

  • 7/28/2019 Building Response to Excavation

    10/80

    1/22/2009

    10

    Strain Determined from state of strain at a point

    Average state of strain in structural unit ofbuilding

    Lower level

    Upper level

    by settlement trough

    Grade beam/slab stiffnessGrade beam/slab stiffness lateral strainlateral strain

    1.0

    h / hg

    0.5

    0

    0 2 4 6 8

    0.2

    0.8

    Boscardin and Cording, 1989

    Eg A / Es Hexc S

  • 7/28/2019 Building Response to Excavation

    11/80

    1/22/2009

    11

    4. Effect of soil/building shear stiffness and cracking on angular distortion inmasonry walls.

    M. Son, 2004

    Examples of building response toExamples of building response to

    excavation and tunnelingexcavation and tunneling

    Review of ground movements and buildingReview of ground movements and building

    Characteristics of bearing wall structuresCharacteristics of bearing wall structures

    Bearing walls parallel to tunnel or excavationBearing walls parallel to tunnel or excavation Separation of upper wallSeparation of upper wall

    Side sway of framesSide sway of frames

  • 7/28/2019 Building Response to Excavation

    12/80

    1/22/2009

    12

    Early 1800 faade: alternating headers and stretchers

    LATE 1800s, U.S.

  • 7/28/2019 Building Response to Excavation

    13/80

    1/22/2009

    13

    Savannah: Late 1800s

    Interior of bearing wall

  • 7/28/2019 Building Response to Excavation

    14/80

    1/22/2009

    14

    Joist set in seats on

    bearing wall, not tied

    Wood lintel sags:

    cracks in brick

    Lateral displacement of joists:

    12 to 20 mm

    1800s Timber joists in seats on masonry bearing walls

  • 7/28/2019 Building Response to Excavation

    15/80

    1/22/2009

    15

    1870: Philadelphia

    Masonry bearing walls,

    Floors: cast iron I beams

    with jacked brick arches

    oo suppor : cas rontruss set on bearing wall

  • 7/28/2019 Building Response to Excavation

    16/80

    1/22/2009

    16

    San Francisco: along proposed tunnelEarly 1900s, industrial, Retrofitted for earthquakes

    Openingsenlarged,posted

    Retrofitted: diagonal brace behind window

  • 7/28/2019 Building Response to Excavation

    17/80

    1/22/2009

    17

    RETROFITTED:

    BEARING WALLS

    Reducedlateral strain

    Early 1900s: concrete floors reduce lateral strains

  • 7/28/2019 Building Response to Excavation

    18/80

    1/22/2009

    18

    Interior of bearingwall building:

    Interior of masonry bearing wall buildingI beams tied to brick bearing wall

  • 7/28/2019 Building Response to Excavation

    19/80

    1/22/2009

    19

    Examples of building response toExamples of building response to

    excavation and tunnelingexcavation and tunneling

    Review of ground movements and buildingReview of ground movements and building

    Characteristics of bearing wall structuresCharacteristics of bearing wall structures

    Bearing walls parallel to tunnel or excavationBearing walls parallel to tunnel or excavation

    Separation of upper wallSeparation of upper wall

    Side sway of framesSide sway of frames

    Brick bearing walls parallel to tunnel orBrick bearing walls parallel to tunnel or

    excavationexcavation

  • 7/28/2019 Building Response to Excavation

    20/80

    1/22/2009

    20

    BEARINGWALLSPARALLELTOTUNNELOREXCAVATION

    CASE1:

    Two

    buildings:

    G

    1tunnels:

    Washington

    Metro.,

    6m

    dia

    Brickbearingwallwithtimberjoists Terracesandandgravelandstiffclay.

    CASE2: Apartment,Evanston 4.6mdia.tunnel,SoftChicagoclay

    CASE3: Gymnasium Brickbearingwallwithconcretefloors Trenchinstiffclaynexttoandbelowbaseofbuildingfoundation

    concentratedsettlement

    Case4: Apartmenthouse: Brickbearingwallwithtimberjoists

    Concentrateddisplacement

    on

    bearing

    wall.

    Lossofbearingoftimberjoistsonseatsinbearingwall

    Case5: Brickbearingwallwithtimberjoists Lateraldisplacements20to30mawayfrom12mhighexcavationwall. Crackinginstreet,basementandlowerfloor: Smalllateraldisplacementoftimberjoistsonseatsinbearingwall.

    Case 1: Two buildings, G 1 Tunnels

  • 7/28/2019 Building Response to Excavation

    21/80

    1/22/2009

    21

    Brick bearing wall, timber joistsTunnel ~ parallel to bearing wall

    Common wall & faade wall

    38 mm

    Washington Metro: G Tunnel:Digger shield in dense sand and stiff clay

  • 7/28/2019 Building Response to Excavation

    22/80

    1/22/2009

    22

    Tilt and Angular Distortion

    Bending: separationadjacent to wall

    ( x10-3)

    = Slope Tilt= 4 -1.9 = 2.1

    Tilt = 1.9

    Measured = 2

    GS = 4 - 0.8 = 3.2 /L = 0.8

  • 7/28/2019 Building Response to Excavation

    23/80

    1/22/2009

    23

    Numericaldistinct

    element

    analysis

    BuildingII

    Joistsdidnotdisplaceatwallwithsmall(10psf)livefloorload+weightoffloor.

    Reductionoffloorloadtoweightofflooronlyproducedopeningoffloorjoistsatwall,aswas

    observedinthefield

    Washington DC Metro, G Tunnel

    ( x 10-3 ) Building 1 Building 2

    Ground Slope: 4 0.8G. S. 4 - 0.8 = 3.2 * NA: . .

    Slope Tilt: 4 - 1.9 = 2.1 0.8-0.3 = 0.5from extensometers: 1.8 to 2.0 ** 0*Separation between walls of building 1 & 2 reduces below GS

    ** Sticking door, minor shear cracks

    Lateral strain base: < 0.1 *** 0.3

    Lateral strain top: < 0.1 0.8 ***

    **** 5 mm gap due toseparation of joists atleft bearing wall

    *** Building 1 is in zoneof small lateral strain

  • 7/28/2019 Building Response to Excavation

    24/80

    1/22/2009

    24

    Case 2: Evanston: Soft Chicago Clay

    Tunnel parallel to bearing wall, concrete floors.

    Diagonal Cracks Vertical Crack

    Effect of tunnelingTunnel

    Cracks and out-of plane brick displacement above lintels-- unrelated to tunneling

    Diagonal Cracks Vertical Crack

    Effect of tunneling

    Tunnel

  • 7/28/2019 Building Response to Excavation

    25/80

    1/22/2009

    25

    Cracks and out-of- plane displacements above lintels,

    unrelated to tunnelingbut no pre-construction video in this area of building

    FIGURE 4.10

    South Wing, pre-existing cracks on construction video,unrelated to tunneling

    FIGURE 4.7

  • 7/28/2019 Building Response to Excavation

    26/80

    1/22/2009

    26

    Figure 5-1

    Soft Chicago Clay, Evanston

    12-ft-diameter Lovat Shield with Flood Doors (Not EPB)

    Figure 6-10

    12-ft-diameter articulated shield, LovatMcNally Tunneling: Negotiated 160-ft radius turn

  • 7/28/2019 Building Response to Excavation

    27/80

    1/22/2009

    27

    Pneumatic Piez.Pneumatic Piez.

    MultiMulti--pointpoint

    WestbayWestbay

    PiezometerPiezometer Deep Settlement Pts .Deep Settlement Pts .

    Figure 6-5

    Inclinometer/Inclinometer/

    SondexSondexInclinometers/Inclinometers/

    SondexSondex

    Tunnel Centerline

    Chicago Clay: Test Section 4, near CTA elevated structureA joint effort: McNally Tunneling and University of Illinois

    Distance (ft)

    -100 -80 -60 -40 -20 0 20

    0w =19.2 m

    T S 3: SETTLEMENT DUE TO PASSAGE OF SHIELD

    Articulated shield, wheel excavator : 3.6 m dia

    Depth(ft)

    20

    40

    60

    0.80 in.

    0.52 in.

    Sand

    Soft to medium gray silty clay

    Very soft to soft clay

    Medium to stiff silty clay

    Stiff clayey silt

    30 mm VS =0.57 cu m/m

    b=38o Z = 22m

    Figure 1-6

    80

    100

    72 ft

    0.82 in.

    Stiff to very stiff gray silty clay

    Hard gray silty clay

    VL =0.44 cu m/m

    .

    79 mm

    r

  • 7/28/2019 Building Response to Excavation

    28/80

    1/22/2009

    28

    Distance (ft)

    -100 -80 -60 -40 -20 0 20

    0w =23 m

    T S 3: LONG TERM SETTLEMENT AFTER PASSAGEOF SHIELD

    Depth(ft)

    20

    40

    60

    0.80 in.

    0.52 in.

    Sand

    Soft to medium gray silty clay

    Very soft to soft clay

    Medium to stiff silty clay

    Stiff clayey silt

    34 mm34 mm

    445 days Zone of volume change,V, due to consolidationcaused by:

    1. Increase in meanstress during

    .

    80

    100

    0.82 in.

    Stiff to very stiff gray silty clay

    Hard gray sil ty clay

    passage of shield,and dissipation ofexcess pore pressure

    2. Reduction of porepressures due todrainage into tunnel

    20 mm

    P3 -1 P 4Passage ofshield

    Consolidation

    MEMBRANE, TS 4

    NO MEMBRANE, TS 3

    due to stress

    increase

    Consolidation due

    to drainage intotunnel

    Figure 6-17

    Days after passage of sh ield

    Pore Pressure changes with time, Evanston

  • 7/28/2019 Building Response to Excavation

    29/80

    1/22/2009

    29

    2.5 m

    10 m 11m 10 m

    StreetStreet

    79 mm

    30mm

    17 m

    40 o

    18 mCourtyard North WingSouth Wing Central Wing

    CHICAGO CLAY

    NORTH WING

    EY

    COURTYARD

    ALLEY

    N

    STREET

    CENTRAL WING

    SOUTH WING

    AL

    INTERIOR COURTYARDLATERA

    L

    EXTENS

    ION

    3 mm

    2mm

    Basement floor

    ;TILT

    Tunnel

    AB ANGULAR

    DISTORTIO

  • 7/28/2019 Building Response to Excavation

    30/80

    1/22/2009

    30

    South Wing Central Wing

    Concrete floors reduce lateral strains in upper levels

    MeasuredVertical buildingdisplace: 30 mm

    12 mm crackextension

    Lateral grounddisplace: 29 mm(calculated) 5 mm separation

    between Wings

    Angular distortion, South Wing: < 30 mm/11.3 m =2.7 x10-3

    Calculated lateral strain, South Wing:

  • 7/28/2019 Building Response to Excavation

    31/80

    1/22/2009

    31

    Reducedlateral strain

    Concrete floors reduce lateral strainsLateral cracks limited to basement/ground floor level

    Diagonal Cracks Vertical Crack

    Effect of tunneling

    Tunnel

    FIGURE 5.18

  • 7/28/2019 Building Response to Excavation

    32/80

    1/22/2009

    32

    Vertical Crack

    E wall

    At joint between Southand Central Wings.

    Open: 5 mm at base

    Reducing to hairlineadjacent to 1st floorwindow.

    -3) 3

    4

    SEVERE TO VERY SEVERE

    *The results of two fieldcases andone numerical test

    are outof range

    ( ) - Damage level based on

    maximumcrack width

    (Burlandetal., 1977)

    [ ] - Damage level basedon

    fieldobservation

    Constant Principal

    Extension Strain

    Damage Criterionbased on state of strain at a point

    LateralS

    train,L

    (x10

    1

    2

    Col 36 vs Col 37Col 39 vs Col 40

    Col 48 vs Col 49SLIGHTDAMAGE

    MODERATETO

    SEVERE DAMAGE

    (BoscardingandCording, 1989)

    (N) - Negligible

    (VSL) - Veryslight

    (SL) - Slight

    (M) - Moderate

    (SE) - Severe

    (VSE) - Verysevere

    [N] - Negligible

    [VS] - Veryslight

    [SL] - Slight

    [M] - Moderate

    [SE] - Severe

    [VSE] - Verysevere

    Numerical tests

    Field cases

    MODERATE DAMAGE

    Concrete floors:

    Reduced lateral strain

    Reduced angular distortion due

    Angular Distortion, (x10-3)

    0 1 2 3 4 5 6 70

    NEGL.

    Figure 25 Damage level estimation and observed damage level

    FIGURE 4-1

    Angular Distortion, ( x 10 - 3 )

    1/1000 1/500 1/200 1/100Modified after Boscardin & Cording, 1989

    to side sway?

  • 7/28/2019 Building Response to Excavation

    33/80

    1/22/2009

    33

    NORTH WING

    EY

    COURTYARD

    ALLEY

    N

    STREET

    CENTRAL WING

    SOUTH WING

    AL

    INTERIOR COURTYARDLATERAL

    EXTENSION

    3 mm2mm

    Basement floor

    ;

    TILT&

    TNAT

    Tunnel

    AB ANGULAR

    DISTORTIO

    South Wing

    Inner

    Courtyard

    1.

    SECTION B

    Street

    79 mm 38mm

    17m

    40o

    18 m

    Angular distortion reduced by tilt and sidesway No evidence of lateral cracks in basement Hairline crack above door Estimate of angular distortion if structure moves with

    ground curvature:

  • 7/28/2019 Building Response to Excavation

    34/80

    1/22/2009

    34

    Concentrated vertical and lateral displacements at bearing wallConcentrated vertical and lateral displacements at bearing wallfooting.footing.

    Brick bearing wall parallel to shallow excavationBrick bearing wall parallel to shallow excavation

    CASE 3

    Vertical displacements of bearing wall at ground level: 22 to 31 mmVertical displacements of bearing wall at ground level: 22 to 31 mm

    Bearing wall drags down cross walls and end wallBearing wall drags down cross walls and end wall

    Shear strains are concentrated within 3 m of bearing of bearing wall.Shear strains are concentrated within 3 m of bearing of bearing wall.

    Lateral extension restrained at floor levelsLateral extension restrained at floor levels

    Outward displacement at foundation level produces rotation ofOutward displacement at foundation level produces rotation ofbearing wall about main floor level producing horizontal tensionbearing wall about main floor level producing horizontal tension

    crack on inside of wall above upper second floor level. level:crack on inside of wall above upper second floor level. level: 57 mm/ 6m =10 x 1057 mm/ 6m =10 x 10--33

    CASE 3: Gymnasium: brick bearing wall structure with concretefloor. Trench excavated adjacent to and below footing base elev.

    68

    22 to 31 mm settlement of S. bearing wall drags down E side

    wall, producing distortion and damage at intersection

  • 7/28/2019 Building Response to Excavation

    35/80

    1/22/2009

    35

    Horizontal tensioncrack on inside

    Ground movementsconcentrated within~ 3 m of wall

    sur ace o wa

    Shear crackson cross walls

    ConcreteBrick bearing wall

    STIFF CLAY

    Crosswall

    Damage at crosswalls adjacent toS. Bearing wall:

    Angular distor tion:

    31 mm/6m ? = 5 x 10-3

    31 mm /3m = 10 x 10-3

    Severe Damage

    70

    South bearing

    wall

    31 mm

  • 7/28/2019 Building Response to Excavation

    36/80

    1/22/2009

    36

    Concentrated vertical and lateral displacements at bearing wallConcentrated vertical and lateral displacements at bearing wall

    CASE 4

    .. Brick bearing wall parallel to shallow excavationBrick bearing wall parallel to shallow excavation Timber joistsTimber joists Lateral & vertical displacements of wall at ground level: 40 to 75Lateral & vertical displacements of wall at ground level: 40 to 75

    mm, shear cracks adjacent to distorting portion of wall.mm, shear cracks adjacent to distorting portion of wall. Displacement of timber joists in seats on bearing wall:Displacement of timber joists in seats on bearing wall:

    57 mm.57 mm. Requires evacuation of building,Requires evacuation of building, Tem orar osts to su ort floor oistsTem orar osts to su ortfloor oists

    Lateral strains in building at ground level:Lateral strains in building at ground level: 57 mm/ 6m =10 x 1057 mm/ 6m =10 x 10--33

    33rdrd Floor: SomeFloor: Some sideswaysideswaycausing pulling of joists on opposite sidecausing pulling of joists on opposite sideof building. Continuous joists across intermediate wall reduces joistof building. Continuous joists across intermediate wall reduces joistbearing as settlement takes place.bearing as settlement takes place.

    Adjacent

    basement

    excavation not

    backfilled

    before pulling

    sheet piles

    CASE 4Apartment

    72

    40 to 75 mm

  • 7/28/2019 Building Response to Excavation

    37/80

    1/22/2009

    37

    Crawl Space Basement

    PLAN Bearing wall

    PROFILE

    SECTION

    AAdjacentexcavation

    Basement

    Base adjacent excavation

    Crawl space

    Crawl Space Basement

    PLAN

    57 mm separation

    of joists from

    Bearing wall

    AAdjacentexcavation

    PROFILE

    SECTION

    Sidesway &

    separation

    AAdjacentexcavation

    57 mm

    separation

    BasementCrawl space

    Base adjacent excavation

  • 7/28/2019 Building Response to Excavation

    38/80

    1/22/2009

    38

    Crawl Space Basement

    PLAN 57 mm reductionof joist bearing

    x v

    PROFILE

    SECTION

    Sidesway &reduction ofjoist bearing

    reduction ofjoist bearing

    BasementCrawl space

    Base of adjacent excavation

    57 mm reduction in joist bearing57mm

    L > 57mm/ 6 m = 10 x 10-3

    Severe to Very SevereJ oists supported withtemporary posts

  • 7/28/2019 Building Response to Excavation

    39/80

    1/22/2009

    39

    Brick bearing walls and wood joistsBrick bearing walls and wood joists

    Parallel bearing walls: Opening of joists in seatsParallel bearing walls: Opening of joists in seats

    Apartment buildingApartment building

    2 in. lateral displacement at seats2 in. lateral displacement at seats

    2 in. settlement2 in. settlement

    Lateral displacement away from excavationLateral displacement away from excavation

    ..

    = 20 mm /6 m = 3.3 x 10= 20 mm /6 m = 3.3 x 10 --33

    Cracks in side walls: total width of cracks: XXXXCracks in side walls: total width of cracks: XXXX

    CASE 5: Brick bearing wall parallel to excavation, timber joists

    Lateral cracks in street, 20 to 30 m from 12 m deepexcavation: fine sand over soft clay

    30 mm/ (30-20 m) = 3 x 10 -3

    , ,in basement & main floor:

    Basement moves with ground

    Decrease in joist bearing on main floorNo significant extension in upper floors

  • 7/28/2019 Building Response to Excavation

    40/80

    1/22/2009

    40

    Sidewalk crack

  • 7/28/2019 Building Response to Excavation

    41/80

    1/22/2009

    41

    Lateral displacement of joists:12 to 20 mm

    Superficial cracking of plaster/stuccoon brick bearing wall

    Lateral strain: 12 to 20 mm/ 6 m = 2 to 3 x 10-3 (Slight )

    Lateral StrainsLateral Strains

    N side building: 6 to 12 mmN side building: 6 to 12 mm

    J oist displacement out of seats:J oist displacement out of seats: 12 to 20 mm12 to 20 mm

    Separation of W. concrete block infill cross wall:Separation of W. concrete block infill cross wall: 12 to 20 mm12 to 20 mm

    Floor cracks, Center:Floor cracks, Center: 13 mm13 mm E Wall: Cracks at floor level:E Wall: Cracks at floor level: 10 mm10 mm

    E Wall: Cracks at ceiling level (~E Wall: Cracks at ceiling level (~g.sg.s.).) 18 mm18 mm

    ..

    Lateral strain: 18mm/6m = 3 x 10Lateral strain: 18mm/6m = 3 x 10--33

  • 7/28/2019 Building Response to Excavation

    42/80

    1/22/2009

    42

    Predominantly lateral displacements at distance of 1.2 to 2 HPredominantly lateral displacements at distance of 1.2 to 2 Hbehind excavation wallbehind excavation wall

    Brick bearing wall parallel to excavationBrick bearing wall parallel to excavation

    Timber joistsTimber joists

    Lateral strains in building at ground level:Lateral strains in building at ground level: 18 mm/ 6m =3 x 1018 mm/ 6m =3 x 10--33

    Approximately equal to lateral strain in groundApproximately equal to lateral strain in ground

    Displacement of timber joists in seats on bearing wall:Displacement of timber joists in seats on bearing wall:..

    Summation of cracks in floor and wall: sameSummation of cracks in floor and wall: same

    33rdrd floor: reduced lateral strains: hairline cracks.floor: reduced lateral strains: hairline cracks.

    Damage level: slightDamage level: slight

    Examples of building response toExamples of building response to

    excavation and tunnelingexcavation and tunneling

    Review of ground movements and buildingReview of ground movements and building

    Characteristics of bearing wall structuresCharacteristics of bearing wall structures

    Bearing walls parallel to tunnel or excavationBearing walls parallel to tunnel or excavation Separation of upper wallSeparation of upper wall

    Side sway of framesSide sway of frames

  • 7/28/2019 Building Response to Excavation

    43/80

    1/22/2009

    43

    5. Separation in upper floors5. Separation in upper floors 77thth St: Perpendicular bearing wallsSt: Perpendicular bearing walls

    Shear cracks at faadeShear cracks at faade

    Analysis by SonAnalysis by Son

    G tunnel: twin buildin s arallel bearin wallsG tunnel: twin buildin s arallel bearin walls Shear first buildingShear first building

    Bending at edge of second building: no load in floor joists.Bending at edge of second building: no load in floor joists.

    Analysis by Son:Analysis by Son: LoadedLoaded

    UnloadedUnloaded

    Club 1? Parallel bearing walls.Club 1? Parallel bearing walls.

    2 story open.2 story open.

    Masonic Temple, Philadelphia: parallel bearing wall. IMasonic Temple, Philadelphia: parallel bearing wall. Ibeams with jacked brick arch. Shear cracks andbeams with jacked brick arch. Shear cracks andseparation at bearing wall.separation at bearing wall.

    Separation of upper wallsSeparation of upper walls

  • 7/28/2019 Building Response to Excavation

    44/80

    1/22/2009

    44

    Distortion patterns in masonryDistortion patterns in masonry walls nextwalls next

    to excavationto excavation

    87FIGURE 4-4

    3. Roof structure and floorjoists perpendicular toexcavation restrain lateraldisplacement & separation in

    upper floors.

    1. Cracks develop dueto angular distortionand lateral strain

    2. Cracks extendupward

    Distortion patterns in masonry wallsDistortion patterns in masonry wallsDeep beamDeep beam

    88FIGURE 4-3

    Extension of shear cracks,or weak connection offaade wall to side walls:

    Allows rotation of wall andopening of cracks at top

  • 7/28/2019 Building Response to Excavation

    45/80

    1/22/2009

    45

    Beam: Large L/H Deep beam: LowBeam: Large L/H Deep beam: Low

    L/HL/HTypical conditionTypical condition

    ShearL

    H H

    L

    89FIGURE 4-3

    If continuous crack or weakconnection of faade to sidewalls: Rotation andseparation of faade wall

    Bending

    Concentration

    Shear crackintersectingfaade causes28 mm

    Bearing wall perpendicular to tunnelBearing wall perpendicular to tunnel

    As shear cracks

    of shearcracks near

    edge ofbearing walldevelopsbecause of

    separa on ofaade wall

    90FIGURE 4-7

    they reducethe bendingstiffness at theedge of thebearing wall.

    downdrag offaade wall

    Tunnelbelowstreet

  • 7/28/2019 Building Response to Excavation

    46/80

    1/22/2009

    46

    Crack:28 mm

    50 mm

    Displacement unit: mm

    (Horizontal disp, Vertical disp)

    Horizontal disp.: Positive sign leftward disp.

    Vertical disp.: Positive sign downward disp.

    Opening between bearing wall and faade wall: 10 times magnified

    (35.48, 27.69)(32.03, 27.43) (9.14, 5.84) (9.14, 1.52) (9.14, -2.29)

    Bearing wallFacade

    Crack width = 27 mm

    Distinct Element Analysis:Each brick modeled as separate block

    Crack width= 27 mm

    (8.64, 27.50)(4.91, 26.81) (0.76, 6.25)

    (22.33, 27.43)

    (0.76, 1.29) (1.02, -1.87)

    (17.72, 26.37)

    wall

    LATERAL (

    (mm.)

    Settlement: 27 mm.Lateral displacement

    NUMERICAL ANALYSIS: DOWNDRAG OF FAADE WALL

    VERTICAL (Displacement

    (M. Son, 2003)

    Settlement

  • 7/28/2019 Building Response to Excavation

    47/80

    1/22/2009

    47

    Damage increases at increasing rate withDamage increases at increasing rate withncrease n se emenncrease n se emen

    Bearing Wall Parallel toExcavation

    -between joist levels

    J oist deterioration at seats

    Side wall: water damage,deteriorated mortar

    Adjacent Braced Cut:. 18 mm settlement

  • 7/28/2019 Building Response to Excavation

    48/80

    1/22/2009

    48

    Mortar deteriorated due to water from downspouts

    75mm

    TIESPLACED

    Examples of building response toExamples of building response to

    excavation and tunnelingexcavation and tunneling

    Review of ground movements and buildingReview of ground movements and building

    Characteristics of bearing wall structuresCharacteristics of bearing wall structures

    Bearing walls parallel to tunnel or excavationBearing walls parallel to tunnel or excavation Separation of upper wallSeparation of upper wall

    Side sway of framesSide sway of frames

  • 7/28/2019 Building Response to Excavation

    49/80

    1/22/2009

    49

    Abaqus FEMwithHypoplasticSoil,ConcreteFrame

    Excavation

    Depth:

    25

    mDisplacementmagnificationfactor:100

    Soil modeled as

    FIGURE 6-11 97B. Ghahreman, 2004

    Side sway and tilt causeBay 1 distortions to be similar to Bay 3

    Abaqus FEM,Hypoplastic Soilw/concreteframe

    Excavationdepth: 25m Magnificationfactor:100

    Angulardistortionsimilar foreach story

    6-12 98

    floor

    First floor columns are distorted

    by lateral ground strainsB. Ghahreman, 2004

  • 7/28/2019 Building Response to Excavation

    50/80

    1/22/2009

    50

    Beambendingmomentrelatedtoangulardistortion

    1 = + 0.002 10-32 = + 0.089 10-33 = - 0.087 10-34 = 0.000

    Angular distortion, : 0.248 10-3

    Slope: 1.647 10-3- Tilt: 1.399 10-3

    4

    3.02

    3.02

    2.64 cm

    2nd story Bay 1

    omen , xe en s: = M = 6(EI/L)( )

    M

    FIGURE 6-13 99

    12 3.

    2.56

    3.95

    2.562.64

    7.7 m

    M

  • 7/28/2019 Building Response to Excavation

    51/80

    1/22/2009

    51

    Side sway of hotel with concrete floorsSide sway of hotel with concrete floors

    Excavation Hotel with concrete floors Historic Brick Bearing WallStructure

  • 7/28/2019 Building Response to Excavation

    52/80

    1/22/2009

    52

    Stiff clays and medium dense sands

    BuildingExcavation

    Hotel basement: 1 levelHistoricHouse: 1

    level

    ~ 3 mm

  • 7/28/2019 Building Response to Excavation

    53/80

    1/22/2009

    53

    HOTEL

  • 7/28/2019 Building Response to Excavation

    54/80

    1/22/2009

    54

    Early 1800 faade:Alternating headers andstretchers

    No apparent cracks

  • 7/28/2019 Building Response to Excavation

    55/80

    1/22/2009

    55

  • 7/28/2019 Building Response to Excavation

    56/80

    1/22/2009

    56

    ARINGWALL

    ALL

    SMALLSIDESWAY:

    ~ 3 mm

    (Exaggerated)

    SETTLEMENT:

    Settlement ofintermediate

    EDIATETIMBERB

    BRICKBE

    ARING12 story

    Hotel:

    Concretefloors

    bearing wallover time

    INTERM

    ~ 50 mm

  • 7/28/2019 Building Response to Excavation

    57/80

    1/22/2009

    57

    ALL

    SMALLSIDESWAY

    :

    ~ 3 mm

    (Exaggerated) ARINGWA

    LL

    SETTLEMENT:

    Shrinkage ofintermediate

    BRICKBEARING12 story

    Hotel:Concretefloors

    EDIATETIMBERB

    bearing wall

    INTERM

    ~ 50 mm.

    CONCLUSIONS

    1. Structures often serve as indicators of the causes of imposed distortionsand damage

    2. Understand the chain of relationships and behavior extending from tunnel orexcavation to building

    Ground movement patterns and volume changeBuilding structural characteristics and finishes - - - how it was built,

    maintained and repaired.

    3. Damage due to excavation and tunneling may be superposed on pre-existing building distortions and deterioration

    4. Damage due to excavation and tunneling may be separate from andunrelated to pre-existing building distortions and damage

  • 7/28/2019 Building Response to Excavation

    58/80

    1/22/2009

    58

    CONCLUSIONS

    It is most common and natural for residents and owners of buildings to

    observe and attribute pre-existing conditions in their building to theeffects of the adjacent excavation or tunneling.Benefits of:

    1. Pre-construction assessments and inspection, photographs and video-- ssess con ton o u ngs, sens tv ty to amage, w et er ue to

    tunneling and excavation or other effects.-- Assess structural characteristics and building finishes

    lateral and distortional stiffnesses, weak zones.2. A logical evaluation and description of the limits and magnitude of

    ground movements and building distortions due to excavation ortunneling:

    a. zone of influence

    b. settlement slope,c. size of building with respect to settlement trough,d. change in ground slope.

    3. Early building monitoring to determine temperature & seasonal effects.4. Community relations efforts by contractor, engineer and owner

    throughout design and construction.5. Early recognition and acceptance of responsibility for excavation or

    Control and reduceControl and reduce

    RiskRisk of large, uncontrolledof large, uncontrolled ground loss in faceground loss in face

    Shield, EPB:Shield, EPB:

    ControlControl of conditioner and pressure in faceof conditioner and pressure in face

    NATM:NATM:

    Instability at faceInstability at face

    Lining failure during or after excavation sequencesLining failure during or after excavation sequences

    Regular ground lossRegular ground loss

    Shield: AnnularShield: Annular spacesspaces Overcut at front of shieldOvercut at front of shield

    Grout annulus between tail of shield and liningGrout annulus between tail of shield and lining

    NATM: Lining deflection and ground displacement during excavationNATM: Lining deflection and ground displacement during excavation

    Volume decreaseVolume decrease inin soilsoil DewateringDewatering

    Stress increases around tunnelStress increases around tunnel

  • 7/28/2019 Building Response to Excavation

    59/80

    1/22/2009

    59

    Allowable lAllowable limit forimit for

    distortion/damagedistortion/damage

    Observations/ControlObservations/Control

    ADDITIONAL MEASURESADDITIONAL MEASURES

    If Ground loss causes moreIf Ground loss causes moredistortion than allowabledistortion than allowable

    Modify groundModify ground

    Compensate groundCompensate ground

    Protect structureProtect structureNear tunnel

    In soil mass

    At surface

    At structuresLINK

    Estimate tunnelEstimate tunnel

    ground lossground loss

    on ro unne ngon ro unne ngprocessprocess

    Increasing ground loss can result in disproportionateincreases in round movement and buildin dama e

    Small ground losses may be absorbed by volume increases insoil.

    Building damage increases disproportionately with strains

    Objective: control ground losses at the tunnel

    Increasingly, with pressurized face tunneling, ground movementsare being controlled at the source, around the tunnel shield tolevels that result in negligible damage at the ground surface

    Objective: reduce risk of large ground losses or collapse

  • 7/28/2019 Building Response to Excavation

    60/80

    1/22/2009

    60

    METHOD OF CALCULATING BUILDING DISTORTION

    BAY 1 BAY 2 BAY 3

    CD

    UDEC analysis of full scale brick bearing wall

    BAY 1

    A B

    6100 mm

    6100m

    38 77 16 54

    L

    H

    8 92 4 83

    61000 67 10 3

    . ..

    AVERAGE SLOPE :

    TILT :

    ANGULAR DISTORTION :

    LATERAL STRAIN (T) :

    LATERAL STRAIN (F) :

    61003 64 10 3

    . ..

    14 73 4 83

    6100162 10 3

    . ..

    ( . . ) .3 64 162 10 2 02 103 3

    30 90 14 73

    61002 65 10 3

    . ..

    FIGURE 4.6

  • 7/28/2019 Building Response to Excavation

    61/80

    1/22/2009

    61

    Physical Model Studies, Test 5E

    Schnabel Large Soil Model Test Lab at U. I. U. C.

    D. Laefer, 2001

    1.2 m high

    Weightadded atfront tosimulatedowndrag

    fromfaade

    .

    Model Test 5E: Excavation to 1220 mm

  • 7/28/2019 Building Response to Excavation

    62/80

    1/22/2009

    62

    BAY 1 BAY 2 BAY 3 BAY 1 BAY 2 BAY 3

    1.06 1.09 1.02 0.96

    2.59 2.65 2.59 2.594.32 2.06 0.65 -0.21

    VERTICAL(

    LATERAL(

    Distance (mm.)

    Displacement(mm.)

    BAY 1

    *

    BAY 2

    SLOPE 1.93*

    BAY 3

    SLOPE 1.80*SLOPE 4.59

    Distance (mm.)

    VERTICAL

    SOILBUILDING

    4.39 2.07 0.62 -0.19

    BAY 1

    *

    BAY 2

    SLOPE 2.38*

    BAY 3

    SLOPE 1.33*SLOPE 3.80

    VERTICAL

    BUILDINGSOIL

    LATERAL

    BUILDING SOIL

    (

    (

    123

    .

    -0.37

    lat(F) 0.16

    lat(T) 0.49

    .

    -0.15

    lat(F) 0.03

    lat(T) 0.05

    .

    2.29

    lat(F) 1.95

    lat(T) 2.25

    a. Brick-Bearing Wall (Inelastic Analysis)

    * Multiply by 10-3

    b. Frame Wall (Elastic Analysis)

    * Multiply by 10-3

    TIL 2.57

    -0.19

    lat(F) 0.11

    lat(T) 0.10

    TIL 2.67

    -1.34

    lat(F) 0.10

    lat(T) 0.00

    TILT 2.56

    1.24

    lat(F) -0.05

    lat(T) -0.10

    Numerical analyses of 2-story brick-bearing wall (Pit 5E) and elastic frame, 1/10th model scale

    1.08 mm

    L 1830 mm

    /L 6.00E-04

    1.08 mm

    L 1830 mm

    /L 6.00E-04

    4/L 2/L

    FIGURE 5-5

    EXTRAS

  • 7/28/2019 Building Response to Excavation

    63/80

    1/22/2009

    63

    52.5S of backof Soldier pile

    Separation: ~1/8? open to N,behind E column (adjacent toChroma W Wall), at crown molding.

    South WallExcavation

    Congress St

    West

    Wall

    ChromaGallery

    Ray EllisGallery

    separation betweensidewalk and wall

    54.5: 1/8crack

    86.5: 1/ 4crack, curb, & crack in W. side pave.

    95.5: 1/ 4@ c. j. in sidewalk

    cr

    75: 3/8separation at c. j. on brick sidewalk,

    64: 5/16crack cuts straight across bricks, towardgallery entrance (crack gauge)

    Fig 2. South side Ellis Square

    97.5: 1/ 8 crack, curb,97.5: separation of construction joint betweenconcrete pavement slab extends across street

    BarnardSt

    57 mm reduction in joist bearing57mm

    L >57mm/ 6 m =10 x 10-3

    Severe to Very SevereJ oists supported withtemporary posts

  • 7/28/2019 Building Response to Excavation

    64/80

    1/22/2009

    64

    Masonic

    Temple,

    Philadelphia

  • 7/28/2019 Building Response to Excavation

    65/80

    1/22/2009

    65

  • 7/28/2019 Building Response to Excavation

    66/80

    1/22/2009

    66

  • 7/28/2019 Building Response to Excavation

    67/80

    1/22/2009

    67

    N

    BarnardSt.

    Congress St.

    blockwall

    Old drainpatches

    1/8-3/8 top

    Joists: - out of seat

    Joistorientation

    1/8

    CG371mm

    Floor crack: 3/8 lat, 3/8 vert.

    Concrete

    -

    separation1/8

    1/16 -3/8 top

    1/16 -3/16 topJoists: 12 19 mm out of seat

    1/8CG551mm

    CG42 3mmCG38 2mm

    Fig 3. Chroma Gallery, NE BasementFig 3. Chroma Gallery, NE Basement

    3/8 lat, 3/8 vert. 1 /4 -1/8 top

    1/16

    Photos IMGP 2447-2471

    Photos IMGP 2472-2476

    (Main floor, Chroma Gallery: Photos IMGP 2508-2518)

  • 7/28/2019 Building Response to Excavation

    68/80

    1/22/2009

    68

    N

    BarnardSt.

    Congress St.

    blockwall

    Old drainpatches

    3 10 mmtop

    J oists:12-20 mmout of seat

    NS J oistorientation

    3 mm

    CG371mm

    Floor crack:

    Concrete

    12-20 mmseparation

    3 mm

    2-10 mm top

    2-5 mm top

    J oists: 12-20 mmout of seat

    1/8CG551mm

    CG42 3mmCG38 2mm

    ,10 mm vertical.

    Fig 3. Chroma Gallery, NE BasementFig 3. Chroma Gallery, NE Basement

    10 mm lat,10 mm vert

    6 3 mmtop

    2 mm

    Photos IMGP 2447-2471

    Photos IMGP 2472-2476

    (Main floor, Chroma Gallery: Photos IMGP 2508-2518)

  • 7/28/2019 Building Response to Excavation

    69/80

    1/22/2009

    69

    Bearing walls parallel to excavationBearing walls parallel to excavation Contact at party walls a plane of weaknessContact at party walls a plane of weakness

    DetermineDetermine G.S. between baysG.S. between bays

    Opening at top:Opening at top: G.S x HG.S x H

    Strain at top:Strain at top: G.S x H/ 2 LG.S x H/ 2 Lbb = 4 (Defl Ratio) x H/2Lb == 4 (Defl Ratio) x H/2Lb =H/2RH/2R

    Distribute:Distribute:

    To one side of the wallTo one side of the wall

    To both sides of the wallTo both sides of the wall

    etween two wa s t tetween two wa s t t Party walls assumed continuousParty walls assumed continuous DetermineDetermine

    G.S. between baysG.S. between baysFor bearing walls moving with ground:For bearing walls moving with ground:

    G.S.G.S.

    -3) 3

    4

    SEVERE TO VERY SEVERE

    *The results of two fieldcases andone numerical test

    are outof range

    ( ) - Damage level based on

    maximumcrack width

    (Burlandetal., 1977)

    [ ] - Damage level basedon

    fieldobservation

    Constant Principal

    Extension Strain

    LateralS

    train,L

    (x10

    1

    2

    Col 36 vs Col 37Col 39 vs Col 40

    Col 48 vs Col 49SLIGHTDAMAGE

    MODERATETO

    SEVERE DAMAGE

    (BoscardingandCording, 1989)

    (N) - Negligible

    (VSL) - Veryslight

    (SL) - Slight

    (M) - Moderate

    (SE) - Severe

    (VSE) - Verysevere

    [N] - Negligible

    [VS] - Veryslight

    [SL] - Slight

    [M] - Moderate

    [SE] - Severe

    [VSE] - Verysevere

    Numerical tests

    Field cases

    MODERATE DAMAGE

    Angular Distortion, (x10-3)

    0 1 2 3 4 5 6 70

    NEGL.

    Figure 25 Damage level estimation and observed damage level

    FIGURE 4-1

    Angular Distortion, ( x 10 - 3 )

    1/1000 1/500 1/200 1/100

    after Boscardin & Cording, 1989

  • 7/28/2019 Building Response to Excavation

    70/80

    1/22/2009

    70

    Physical Model Studies, Test 5E

    Schnabel Large Soil Model Test Lab at U. I. U. C.

    D. Laefer, 2001

    1.2 m high

    Weightadded atfront tosimulatedowndrag

    fromfaade

    .

    Model Test 5E: Excavation to 1220 mm

  • 7/28/2019 Building Response to Excavation

    71/80

    1/22/2009

    71

  • 7/28/2019 Building Response to Excavation

    72/80

    1/22/2009

    72

    South Wing Central Wing

    Concrete floors reduce lateral strains in upper levels

    37 32

    Vert.

    1.2

    0.5

    Lat. 0.9(calc)

    0.2 separation

    Angular distortion across South Wing = 0.1/37 = 1/370Angular distortion across South Wing = 0.1/37 = 1/370 Lateral strain across South Wing =Lateral strain across South Wing = 0.08/37 = 1/4700.08/37 = 1/470 Lateral strain largely confined to basement levelLateral strain largely confined to basement level

    extens on

    of cracksbetween Wings

  • 7/28/2019 Building Response to Excavation

    73/80

    1/22/2009

    73

    Crosswall

    Angular distortion:

    31 mm6m? =5x 10-3

    31 mm /3m ? =10 x 10-3

    Severe Damage

    145

    South bearing wall

    31 mm

    Max. Lat.

    SECTION A

    34 37 32

    2.5 1.4

    56w =

    i

    .

    34

    40 o

    Z=60 Average Slope = 1/300

    Maximum lateral displacement (calculated):

    L = 1/3 M (tan b/ 0.5) = 1.4

  • 7/28/2019 Building Response to Excavation

    74/80

    1/22/2009

    74

    Evaluate strains and displacements across bay:

    37 bay 32

    StreetStreet Vert.1.2

    34

    Lat. 0.9(calc)

    Angular distortion across 37 bay = 0.1/ 37 = 1/370Angular distortion across 37 bay = 0.1/ 37 = 1/370 Lateral strain across 37 bay =Lateral strain across 37 bay = 0.08/ 37 = 1/4670.08/ 37 = 1/467

  • 7/28/2019 Building Response to Excavation

    75/80

    1/22/2009

    75

  • 7/28/2019 Building Response to Excavation

    76/80

    1/22/2009

    76

  • 7/28/2019 Building Response to Excavation

    77/80

    1/22/2009

    77

  • 7/28/2019 Building Response to Excavation

    78/80

    1/22/2009

    78

  • 7/28/2019 Building Response to Excavation

    79/80

  • 7/28/2019 Building Response to Excavation

    80/80

    1/22/2009