building response to excavation
TRANSCRIPT
-
7/28/2019 Building Response to Excavation
1/80
1/22/2009
1
Examples of building response toxamples of building response toexcavation and tunnelingxcavation and tunnelingBarcelona
December 16, 2008
Edward J . CordingEdward J . Cording
University of Illinois at UrbanaUniversity of Illinois at Urbana--ChampaignChampaign
, . , . , . , ..
In the cases illustrated, the structures themselves served as indicators of the type andcauses of distortions and damage that were imposed on them. The ability to observeand read the building response is aided by an understanding of the chain ofrelationships that extends from the excavation or tunnel and adjacent ground loss orground movement, to the distribution of ground movement and volume change throughthe soil mass, to the interaction of the ground with the building, and then to the buildingdistortion and damage.
To properly assess the building behavior both distortion and damage -- it is necessaryto understand not only the ground movement patterns but also the buildings structuralcharacteristics and finishes: how the building was built, maintained, and repaired.
Often the effects of excavation and tunneling are superposed on pre-existing distortionsand deterioration. In many cases, pre-existing conditions are separate from andunrelated to the excavation- or tunnel-induced damage.
u w u vattribute pre-existing conditions in their building to the effects of the adjacent excavationand tunneling.
Pre-construction photographs and video are important in resolving such issues as wellas early set up of monitoring to obtain a history of building movements due totemperature and seasonal changes. In addition, a logical evaluation and description ofthe limits and magnitude of ground movements and building distortions due toexcavation or tunnelin and earl reco nition and acce tance of res onsibilit for
-
7/28/2019 Building Response to Excavation
2/80
1/22/2009
2
1. Structures often serve as indicators of the causes of imposed distortionsand damage
2. Understand the chain of relationships and behavior extending from tunnel orexcavation to buildingGround movement sources and ground loss
roun movemen pa erns an vo ume c angeBuilding structural characteristics and finishes - - - how it was built,
maintained and repaired.
3. Effects of excavation and tunneling may be superposed on pre-existingbuilding distortions and deterioration
4. Effects of excavation and tunnelin ma be se arate from and unrelated to
pre-existing building distortions and damage
It is most common and natural for residents and owners of buildings toobserve and attribute pre-existing conditions in their building to theeffects of the adjacent excavation or tunneling.
Benefits of:
. re-constructon assessments an nspecton, p otograp s an v eo-- Assess condition of buildings, sensitivity to damage, whether due to
tunneling and excavation or other effects.
-- Assess structural characteristics and building finisheslateral and distortional stiffnesses, weak zones.2. A logical evaluation and description of the limits and magnitude of
ground movements and building distortions due to excavation ortunnelin : zone of influence sizeof buildin with res ect to settlementtrough, change in ground slope.
3. Early building monitoring to determine temperature &seasonal effects.4. Community relations efforts by contractor, engineer and owner
throughout design and construction.5. Early recognition and acceptance of responsibility for excavation or
tunneling induced-damage
-
7/28/2019 Building Response to Excavation
3/80
1/22/2009
3
Increasing ground loss can result in disproportionateincreases in round movement and buildin dama e
Small ground losses may be absorbed by volume increases insoil.
Building damage increases disproportionately with strains
Objective: control ground losses at the tunnel
Increasingly, with pressurized face tunneling, ground movements
are being controlled at the source, around the tunnel shield tolevels that result in negligible damage at the ground surface
Objective: reduce risk of large ground losses or collapse
Examples of building response toExamples of building response to
excavation and tunnelingexcavation and tunneling
Review of ground movements and buildingReview of ground movements and building
Characteristics of bearing wall structuresCharacteristics of bearing wall structures
Bearing walls parallel to tunnel or excavationsBearing walls parallel to tunnel or excavations Separation of upper wallSeparation of upper wall
Side sway of framesSide sway of frames
-
7/28/2019 Building Response to Excavation
4/80
1/22/2009
4
2. REVIEW2. REVIEW
Sources of ground movementSources of ground movement
RiskRisk of large, uncontrolledof large, uncontrolled ground loss in faceground loss in face
Shield, EPB:Shield, EPB:
ControlControl of conditioner and pressure in faceof conditioner and pressure in face
NATM:NATM:
Instability at faceInstability at face
Lining failure during or after excavation sequencesLining failure during or after excavation sequences
Regular ground lossRegular ground loss
Shield: AnnularShield: Annular spacesspaces Overcut at front of shieldOvercut at front of shield
Grout annulus between tail of shield and liningGrout annulus between tail of shield and lining
NATM: Lining deflection and ground displacement during excavationNATM: Lining deflection and ground displacement during excavation
Volume decreaseVolume decrease inin soilsoil DewateringDewatering
Stress increases around tunnelStress increases around tunnel
-
7/28/2019 Building Response to Excavation
5/80
1/22/2009
5
Distortion/damageDistortion/damage
Width of settlement trough
Angular distortion andLateral strain
LINKLINKb
Volumechange
Volume ofSettlementtrough
Slope ofsettlement trough
Settlement & Lateral displacement
slope beneathstructure
EstimateEstimate of regularof regulartunnel groundtunnel ground lossloss
Source ofground loss
Soft Clay: Short term: VS ~ VLAfter consolidation: VS > VL
Estimating Volume loss
(2) Surface Volume, VS = VL - VVs
Large depth/diameter,very dense: VS
-
7/28/2019 Building Response to Excavation
6/80
1/22/2009
6
(3) Estimating Surface Settlement
w = r + Z tan b
max = Vs/w= Trou h Sha e: Gaussian Distribution
max
w = 2.5 ii
Vs
/w
/max = exp ( (x/i)2)Schmidt, Peck, 1969
b oZ Typical values of Angle b:
Sand: 26o Clay: 40o
(+ ~ 5o)
Cording & Hansmire, 1975
(4) Estimating Lateral Movement
(a) Lateral displacement (b) Lateral strain
w = 2.5 i
Li
V
VS mMaximum lateral displacement,
L@ Inflection point, i :
L = 1/3 m (tan b/ 0.5)
FIGURE 3.7 12
L
r
L = m/ w) tan b~ 1/ 2 to 1 x average
settlement slope
-
7/28/2019 Building Response to Excavation
7/80
1/22/2009
7
L L
ANGULAR DISTORTION, LATERAL STRAIN, L(Shear Strain)
ope
L = L / L90
1. Building moves with ground &extends beyond settlement zone:
w
m
Angular Distortion ~
FIGURE 3.6 14
r
Average S ope:
~ m /w
-
7/28/2019 Building Response to Excavation
8/80
1/22/2009
8
2. Building moves with ground & is narrow enough to tilt,distortion concentrated in unit 1.
w
Lb
m
Angular Distortion = Slope Tilt
Angular Distortion = Change in
FIGURE 3.6 15
r Angular Distortion conservativelyestimated as:
< (m /w) (Lb/w)groun s ope e ween wo un s
3. Building moves with ground & is narrow enough to tilt,frame is subject to side sway, which increases tilt
w
Lb
m
AngularDistortion = Slope Tilt
FIGURE 3.6 16
r
~ prevous case
Distortion in both sections ofbuilding
-
7/28/2019 Building Response to Excavation
9/80
1/22/2009
9
4. Building stiff laterally
Grade beams and structural frames reducelateral strain to less than ground strain
Ground strain is concentrated at edges ofbuilding, construction joints between units,or weaker zones in building.
Angular distortion,
-
7/28/2019 Building Response to Excavation
10/80
1/22/2009
10
Strain Determined from state of strain at a point
Average state of strain in structural unit ofbuilding
Lower level
Upper level
by settlement trough
Grade beam/slab stiffnessGrade beam/slab stiffness lateral strainlateral strain
1.0
h / hg
0.5
0
0 2 4 6 8
0.2
0.8
Boscardin and Cording, 1989
Eg A / Es Hexc S
-
7/28/2019 Building Response to Excavation
11/80
1/22/2009
11
4. Effect of soil/building shear stiffness and cracking on angular distortion inmasonry walls.
M. Son, 2004
Examples of building response toExamples of building response to
excavation and tunnelingexcavation and tunneling
Review of ground movements and buildingReview of ground movements and building
Characteristics of bearing wall structuresCharacteristics of bearing wall structures
Bearing walls parallel to tunnel or excavationBearing walls parallel to tunnel or excavation Separation of upper wallSeparation of upper wall
Side sway of framesSide sway of frames
-
7/28/2019 Building Response to Excavation
12/80
1/22/2009
12
Early 1800 faade: alternating headers and stretchers
LATE 1800s, U.S.
-
7/28/2019 Building Response to Excavation
13/80
1/22/2009
13
Savannah: Late 1800s
Interior of bearing wall
-
7/28/2019 Building Response to Excavation
14/80
1/22/2009
14
Joist set in seats on
bearing wall, not tied
Wood lintel sags:
cracks in brick
Lateral displacement of joists:
12 to 20 mm
1800s Timber joists in seats on masonry bearing walls
-
7/28/2019 Building Response to Excavation
15/80
1/22/2009
15
1870: Philadelphia
Masonry bearing walls,
Floors: cast iron I beams
with jacked brick arches
oo suppor : cas rontruss set on bearing wall
-
7/28/2019 Building Response to Excavation
16/80
1/22/2009
16
San Francisco: along proposed tunnelEarly 1900s, industrial, Retrofitted for earthquakes
Openingsenlarged,posted
Retrofitted: diagonal brace behind window
-
7/28/2019 Building Response to Excavation
17/80
1/22/2009
17
RETROFITTED:
BEARING WALLS
Reducedlateral strain
Early 1900s: concrete floors reduce lateral strains
-
7/28/2019 Building Response to Excavation
18/80
1/22/2009
18
Interior of bearingwall building:
Interior of masonry bearing wall buildingI beams tied to brick bearing wall
-
7/28/2019 Building Response to Excavation
19/80
1/22/2009
19
Examples of building response toExamples of building response to
excavation and tunnelingexcavation and tunneling
Review of ground movements and buildingReview of ground movements and building
Characteristics of bearing wall structuresCharacteristics of bearing wall structures
Bearing walls parallel to tunnel or excavationBearing walls parallel to tunnel or excavation
Separation of upper wallSeparation of upper wall
Side sway of framesSide sway of frames
Brick bearing walls parallel to tunnel orBrick bearing walls parallel to tunnel or
excavationexcavation
-
7/28/2019 Building Response to Excavation
20/80
1/22/2009
20
BEARINGWALLSPARALLELTOTUNNELOREXCAVATION
CASE1:
Two
buildings:
G
1tunnels:
Washington
Metro.,
6m
dia
Brickbearingwallwithtimberjoists Terracesandandgravelandstiffclay.
CASE2: Apartment,Evanston 4.6mdia.tunnel,SoftChicagoclay
CASE3: Gymnasium Brickbearingwallwithconcretefloors Trenchinstiffclaynexttoandbelowbaseofbuildingfoundation
concentratedsettlement
Case4: Apartmenthouse: Brickbearingwallwithtimberjoists
Concentrateddisplacement
on
bearing
wall.
Lossofbearingoftimberjoistsonseatsinbearingwall
Case5: Brickbearingwallwithtimberjoists Lateraldisplacements20to30mawayfrom12mhighexcavationwall. Crackinginstreet,basementandlowerfloor: Smalllateraldisplacementoftimberjoistsonseatsinbearingwall.
Case 1: Two buildings, G 1 Tunnels
-
7/28/2019 Building Response to Excavation
21/80
1/22/2009
21
Brick bearing wall, timber joistsTunnel ~ parallel to bearing wall
Common wall & faade wall
38 mm
Washington Metro: G Tunnel:Digger shield in dense sand and stiff clay
-
7/28/2019 Building Response to Excavation
22/80
1/22/2009
22
Tilt and Angular Distortion
Bending: separationadjacent to wall
( x10-3)
= Slope Tilt= 4 -1.9 = 2.1
Tilt = 1.9
Measured = 2
GS = 4 - 0.8 = 3.2 /L = 0.8
-
7/28/2019 Building Response to Excavation
23/80
1/22/2009
23
Numericaldistinct
element
analysis
BuildingII
Joistsdidnotdisplaceatwallwithsmall(10psf)livefloorload+weightoffloor.
Reductionoffloorloadtoweightofflooronlyproducedopeningoffloorjoistsatwall,aswas
observedinthefield
Washington DC Metro, G Tunnel
( x 10-3 ) Building 1 Building 2
Ground Slope: 4 0.8G. S. 4 - 0.8 = 3.2 * NA: . .
Slope Tilt: 4 - 1.9 = 2.1 0.8-0.3 = 0.5from extensometers: 1.8 to 2.0 ** 0*Separation between walls of building 1 & 2 reduces below GS
** Sticking door, minor shear cracks
Lateral strain base: < 0.1 *** 0.3
Lateral strain top: < 0.1 0.8 ***
**** 5 mm gap due toseparation of joists atleft bearing wall
*** Building 1 is in zoneof small lateral strain
-
7/28/2019 Building Response to Excavation
24/80
1/22/2009
24
Case 2: Evanston: Soft Chicago Clay
Tunnel parallel to bearing wall, concrete floors.
Diagonal Cracks Vertical Crack
Effect of tunnelingTunnel
Cracks and out-of plane brick displacement above lintels-- unrelated to tunneling
Diagonal Cracks Vertical Crack
Effect of tunneling
Tunnel
-
7/28/2019 Building Response to Excavation
25/80
1/22/2009
25
Cracks and out-of- plane displacements above lintels,
unrelated to tunnelingbut no pre-construction video in this area of building
FIGURE 4.10
South Wing, pre-existing cracks on construction video,unrelated to tunneling
FIGURE 4.7
-
7/28/2019 Building Response to Excavation
26/80
1/22/2009
26
Figure 5-1
Soft Chicago Clay, Evanston
12-ft-diameter Lovat Shield with Flood Doors (Not EPB)
Figure 6-10
12-ft-diameter articulated shield, LovatMcNally Tunneling: Negotiated 160-ft radius turn
-
7/28/2019 Building Response to Excavation
27/80
1/22/2009
27
Pneumatic Piez.Pneumatic Piez.
MultiMulti--pointpoint
WestbayWestbay
PiezometerPiezometer Deep Settlement Pts .Deep Settlement Pts .
Figure 6-5
Inclinometer/Inclinometer/
SondexSondexInclinometers/Inclinometers/
SondexSondex
Tunnel Centerline
Chicago Clay: Test Section 4, near CTA elevated structureA joint effort: McNally Tunneling and University of Illinois
Distance (ft)
-100 -80 -60 -40 -20 0 20
0w =19.2 m
T S 3: SETTLEMENT DUE TO PASSAGE OF SHIELD
Articulated shield, wheel excavator : 3.6 m dia
Depth(ft)
20
40
60
0.80 in.
0.52 in.
Sand
Soft to medium gray silty clay
Very soft to soft clay
Medium to stiff silty clay
Stiff clayey silt
30 mm VS =0.57 cu m/m
b=38o Z = 22m
Figure 1-6
80
100
72 ft
0.82 in.
Stiff to very stiff gray silty clay
Hard gray silty clay
VL =0.44 cu m/m
.
79 mm
r
-
7/28/2019 Building Response to Excavation
28/80
1/22/2009
28
Distance (ft)
-100 -80 -60 -40 -20 0 20
0w =23 m
T S 3: LONG TERM SETTLEMENT AFTER PASSAGEOF SHIELD
Depth(ft)
20
40
60
0.80 in.
0.52 in.
Sand
Soft to medium gray silty clay
Very soft to soft clay
Medium to stiff silty clay
Stiff clayey silt
34 mm34 mm
445 days Zone of volume change,V, due to consolidationcaused by:
1. Increase in meanstress during
.
80
100
0.82 in.
Stiff to very stiff gray silty clay
Hard gray sil ty clay
passage of shield,and dissipation ofexcess pore pressure
2. Reduction of porepressures due todrainage into tunnel
20 mm
P3 -1 P 4Passage ofshield
Consolidation
MEMBRANE, TS 4
NO MEMBRANE, TS 3
due to stress
increase
Consolidation due
to drainage intotunnel
Figure 6-17
Days after passage of sh ield
Pore Pressure changes with time, Evanston
-
7/28/2019 Building Response to Excavation
29/80
1/22/2009
29
2.5 m
10 m 11m 10 m
StreetStreet
79 mm
30mm
17 m
40 o
18 mCourtyard North WingSouth Wing Central Wing
CHICAGO CLAY
NORTH WING
EY
COURTYARD
ALLEY
N
STREET
CENTRAL WING
SOUTH WING
AL
INTERIOR COURTYARDLATERA
L
EXTENS
ION
3 mm
2mm
Basement floor
;TILT
Tunnel
AB ANGULAR
DISTORTIO
-
7/28/2019 Building Response to Excavation
30/80
1/22/2009
30
South Wing Central Wing
Concrete floors reduce lateral strains in upper levels
MeasuredVertical buildingdisplace: 30 mm
12 mm crackextension
Lateral grounddisplace: 29 mm(calculated) 5 mm separation
between Wings
Angular distortion, South Wing: < 30 mm/11.3 m =2.7 x10-3
Calculated lateral strain, South Wing:
-
7/28/2019 Building Response to Excavation
31/80
1/22/2009
31
Reducedlateral strain
Concrete floors reduce lateral strainsLateral cracks limited to basement/ground floor level
Diagonal Cracks Vertical Crack
Effect of tunneling
Tunnel
FIGURE 5.18
-
7/28/2019 Building Response to Excavation
32/80
1/22/2009
32
Vertical Crack
E wall
At joint between Southand Central Wings.
Open: 5 mm at base
Reducing to hairlineadjacent to 1st floorwindow.
-3) 3
4
SEVERE TO VERY SEVERE
*The results of two fieldcases andone numerical test
are outof range
( ) - Damage level based on
maximumcrack width
(Burlandetal., 1977)
[ ] - Damage level basedon
fieldobservation
Constant Principal
Extension Strain
Damage Criterionbased on state of strain at a point
LateralS
train,L
(x10
1
2
Col 36 vs Col 37Col 39 vs Col 40
Col 48 vs Col 49SLIGHTDAMAGE
MODERATETO
SEVERE DAMAGE
(BoscardingandCording, 1989)
(N) - Negligible
(VSL) - Veryslight
(SL) - Slight
(M) - Moderate
(SE) - Severe
(VSE) - Verysevere
[N] - Negligible
[VS] - Veryslight
[SL] - Slight
[M] - Moderate
[SE] - Severe
[VSE] - Verysevere
Numerical tests
Field cases
MODERATE DAMAGE
Concrete floors:
Reduced lateral strain
Reduced angular distortion due
Angular Distortion, (x10-3)
0 1 2 3 4 5 6 70
NEGL.
Figure 25 Damage level estimation and observed damage level
FIGURE 4-1
Angular Distortion, ( x 10 - 3 )
1/1000 1/500 1/200 1/100Modified after Boscardin & Cording, 1989
to side sway?
-
7/28/2019 Building Response to Excavation
33/80
1/22/2009
33
NORTH WING
EY
COURTYARD
ALLEY
N
STREET
CENTRAL WING
SOUTH WING
AL
INTERIOR COURTYARDLATERAL
EXTENSION
3 mm2mm
Basement floor
;
TILT&
TNAT
Tunnel
AB ANGULAR
DISTORTIO
South Wing
Inner
Courtyard
1.
SECTION B
Street
79 mm 38mm
17m
40o
18 m
Angular distortion reduced by tilt and sidesway No evidence of lateral cracks in basement Hairline crack above door Estimate of angular distortion if structure moves with
ground curvature:
-
7/28/2019 Building Response to Excavation
34/80
1/22/2009
34
Concentrated vertical and lateral displacements at bearing wallConcentrated vertical and lateral displacements at bearing wallfooting.footing.
Brick bearing wall parallel to shallow excavationBrick bearing wall parallel to shallow excavation
CASE 3
Vertical displacements of bearing wall at ground level: 22 to 31 mmVertical displacements of bearing wall at ground level: 22 to 31 mm
Bearing wall drags down cross walls and end wallBearing wall drags down cross walls and end wall
Shear strains are concentrated within 3 m of bearing of bearing wall.Shear strains are concentrated within 3 m of bearing of bearing wall.
Lateral extension restrained at floor levelsLateral extension restrained at floor levels
Outward displacement at foundation level produces rotation ofOutward displacement at foundation level produces rotation ofbearing wall about main floor level producing horizontal tensionbearing wall about main floor level producing horizontal tension
crack on inside of wall above upper second floor level. level:crack on inside of wall above upper second floor level. level: 57 mm/ 6m =10 x 1057 mm/ 6m =10 x 10--33
CASE 3: Gymnasium: brick bearing wall structure with concretefloor. Trench excavated adjacent to and below footing base elev.
68
22 to 31 mm settlement of S. bearing wall drags down E side
wall, producing distortion and damage at intersection
-
7/28/2019 Building Response to Excavation
35/80
1/22/2009
35
Horizontal tensioncrack on inside
Ground movementsconcentrated within~ 3 m of wall
sur ace o wa
Shear crackson cross walls
ConcreteBrick bearing wall
STIFF CLAY
Crosswall
Damage at crosswalls adjacent toS. Bearing wall:
Angular distor tion:
31 mm/6m ? = 5 x 10-3
31 mm /3m = 10 x 10-3
Severe Damage
70
South bearing
wall
31 mm
-
7/28/2019 Building Response to Excavation
36/80
1/22/2009
36
Concentrated vertical and lateral displacements at bearing wallConcentrated vertical and lateral displacements at bearing wall
CASE 4
.. Brick bearing wall parallel to shallow excavationBrick bearing wall parallel to shallow excavation Timber joistsTimber joists Lateral & vertical displacements of wall at ground level: 40 to 75Lateral & vertical displacements of wall at ground level: 40 to 75
mm, shear cracks adjacent to distorting portion of wall.mm, shear cracks adjacent to distorting portion of wall. Displacement of timber joists in seats on bearing wall:Displacement of timber joists in seats on bearing wall:
57 mm.57 mm. Requires evacuation of building,Requires evacuation of building, Tem orar osts to su ort floor oistsTem orar osts to su ortfloor oists
Lateral strains in building at ground level:Lateral strains in building at ground level: 57 mm/ 6m =10 x 1057 mm/ 6m =10 x 10--33
33rdrd Floor: SomeFloor: Some sideswaysideswaycausing pulling of joists on opposite sidecausing pulling of joists on opposite sideof building. Continuous joists across intermediate wall reduces joistof building. Continuous joists across intermediate wall reduces joistbearing as settlement takes place.bearing as settlement takes place.
Adjacent
basement
excavation not
backfilled
before pulling
sheet piles
CASE 4Apartment
72
40 to 75 mm
-
7/28/2019 Building Response to Excavation
37/80
1/22/2009
37
Crawl Space Basement
PLAN Bearing wall
PROFILE
SECTION
AAdjacentexcavation
Basement
Base adjacent excavation
Crawl space
Crawl Space Basement
PLAN
57 mm separation
of joists from
Bearing wall
AAdjacentexcavation
PROFILE
SECTION
Sidesway &
separation
AAdjacentexcavation
57 mm
separation
BasementCrawl space
Base adjacent excavation
-
7/28/2019 Building Response to Excavation
38/80
1/22/2009
38
Crawl Space Basement
PLAN 57 mm reductionof joist bearing
x v
PROFILE
SECTION
Sidesway &reduction ofjoist bearing
reduction ofjoist bearing
BasementCrawl space
Base of adjacent excavation
57 mm reduction in joist bearing57mm
L > 57mm/ 6 m = 10 x 10-3
Severe to Very SevereJ oists supported withtemporary posts
-
7/28/2019 Building Response to Excavation
39/80
1/22/2009
39
Brick bearing walls and wood joistsBrick bearing walls and wood joists
Parallel bearing walls: Opening of joists in seatsParallel bearing walls: Opening of joists in seats
Apartment buildingApartment building
2 in. lateral displacement at seats2 in. lateral displacement at seats
2 in. settlement2 in. settlement
Lateral displacement away from excavationLateral displacement away from excavation
..
= 20 mm /6 m = 3.3 x 10= 20 mm /6 m = 3.3 x 10 --33
Cracks in side walls: total width of cracks: XXXXCracks in side walls: total width of cracks: XXXX
CASE 5: Brick bearing wall parallel to excavation, timber joists
Lateral cracks in street, 20 to 30 m from 12 m deepexcavation: fine sand over soft clay
30 mm/ (30-20 m) = 3 x 10 -3
, ,in basement & main floor:
Basement moves with ground
Decrease in joist bearing on main floorNo significant extension in upper floors
-
7/28/2019 Building Response to Excavation
40/80
1/22/2009
40
Sidewalk crack
-
7/28/2019 Building Response to Excavation
41/80
1/22/2009
41
Lateral displacement of joists:12 to 20 mm
Superficial cracking of plaster/stuccoon brick bearing wall
Lateral strain: 12 to 20 mm/ 6 m = 2 to 3 x 10-3 (Slight )
Lateral StrainsLateral Strains
N side building: 6 to 12 mmN side building: 6 to 12 mm
J oist displacement out of seats:J oist displacement out of seats: 12 to 20 mm12 to 20 mm
Separation of W. concrete block infill cross wall:Separation of W. concrete block infill cross wall: 12 to 20 mm12 to 20 mm
Floor cracks, Center:Floor cracks, Center: 13 mm13 mm E Wall: Cracks at floor level:E Wall: Cracks at floor level: 10 mm10 mm
E Wall: Cracks at ceiling level (~E Wall: Cracks at ceiling level (~g.sg.s.).) 18 mm18 mm
..
Lateral strain: 18mm/6m = 3 x 10Lateral strain: 18mm/6m = 3 x 10--33
-
7/28/2019 Building Response to Excavation
42/80
1/22/2009
42
Predominantly lateral displacements at distance of 1.2 to 2 HPredominantly lateral displacements at distance of 1.2 to 2 Hbehind excavation wallbehind excavation wall
Brick bearing wall parallel to excavationBrick bearing wall parallel to excavation
Timber joistsTimber joists
Lateral strains in building at ground level:Lateral strains in building at ground level: 18 mm/ 6m =3 x 1018 mm/ 6m =3 x 10--33
Approximately equal to lateral strain in groundApproximately equal to lateral strain in ground
Displacement of timber joists in seats on bearing wall:Displacement of timber joists in seats on bearing wall:..
Summation of cracks in floor and wall: sameSummation of cracks in floor and wall: same
33rdrd floor: reduced lateral strains: hairline cracks.floor: reduced lateral strains: hairline cracks.
Damage level: slightDamage level: slight
Examples of building response toExamples of building response to
excavation and tunnelingexcavation and tunneling
Review of ground movements and buildingReview of ground movements and building
Characteristics of bearing wall structuresCharacteristics of bearing wall structures
Bearing walls parallel to tunnel or excavationBearing walls parallel to tunnel or excavation Separation of upper wallSeparation of upper wall
Side sway of framesSide sway of frames
-
7/28/2019 Building Response to Excavation
43/80
1/22/2009
43
5. Separation in upper floors5. Separation in upper floors 77thth St: Perpendicular bearing wallsSt: Perpendicular bearing walls
Shear cracks at faadeShear cracks at faade
Analysis by SonAnalysis by Son
G tunnel: twin buildin s arallel bearin wallsG tunnel: twin buildin s arallel bearin walls Shear first buildingShear first building
Bending at edge of second building: no load in floor joists.Bending at edge of second building: no load in floor joists.
Analysis by Son:Analysis by Son: LoadedLoaded
UnloadedUnloaded
Club 1? Parallel bearing walls.Club 1? Parallel bearing walls.
2 story open.2 story open.
Masonic Temple, Philadelphia: parallel bearing wall. IMasonic Temple, Philadelphia: parallel bearing wall. Ibeams with jacked brick arch. Shear cracks andbeams with jacked brick arch. Shear cracks andseparation at bearing wall.separation at bearing wall.
Separation of upper wallsSeparation of upper walls
-
7/28/2019 Building Response to Excavation
44/80
1/22/2009
44
Distortion patterns in masonryDistortion patterns in masonry walls nextwalls next
to excavationto excavation
87FIGURE 4-4
3. Roof structure and floorjoists perpendicular toexcavation restrain lateraldisplacement & separation in
upper floors.
1. Cracks develop dueto angular distortionand lateral strain
2. Cracks extendupward
Distortion patterns in masonry wallsDistortion patterns in masonry wallsDeep beamDeep beam
88FIGURE 4-3
Extension of shear cracks,or weak connection offaade wall to side walls:
Allows rotation of wall andopening of cracks at top
-
7/28/2019 Building Response to Excavation
45/80
1/22/2009
45
Beam: Large L/H Deep beam: LowBeam: Large L/H Deep beam: Low
L/HL/HTypical conditionTypical condition
ShearL
H H
L
89FIGURE 4-3
If continuous crack or weakconnection of faade to sidewalls: Rotation andseparation of faade wall
Bending
Concentration
Shear crackintersectingfaade causes28 mm
Bearing wall perpendicular to tunnelBearing wall perpendicular to tunnel
As shear cracks
of shearcracks near
edge ofbearing walldevelopsbecause of
separa on ofaade wall
90FIGURE 4-7
they reducethe bendingstiffness at theedge of thebearing wall.
downdrag offaade wall
Tunnelbelowstreet
-
7/28/2019 Building Response to Excavation
46/80
1/22/2009
46
Crack:28 mm
50 mm
Displacement unit: mm
(Horizontal disp, Vertical disp)
Horizontal disp.: Positive sign leftward disp.
Vertical disp.: Positive sign downward disp.
Opening between bearing wall and faade wall: 10 times magnified
(35.48, 27.69)(32.03, 27.43) (9.14, 5.84) (9.14, 1.52) (9.14, -2.29)
Bearing wallFacade
Crack width = 27 mm
Distinct Element Analysis:Each brick modeled as separate block
Crack width= 27 mm
(8.64, 27.50)(4.91, 26.81) (0.76, 6.25)
(22.33, 27.43)
(0.76, 1.29) (1.02, -1.87)
(17.72, 26.37)
wall
LATERAL (
(mm.)
Settlement: 27 mm.Lateral displacement
NUMERICAL ANALYSIS: DOWNDRAG OF FAADE WALL
VERTICAL (Displacement
(M. Son, 2003)
Settlement
-
7/28/2019 Building Response to Excavation
47/80
1/22/2009
47
Damage increases at increasing rate withDamage increases at increasing rate withncrease n se emenncrease n se emen
Bearing Wall Parallel toExcavation
-between joist levels
J oist deterioration at seats
Side wall: water damage,deteriorated mortar
Adjacent Braced Cut:. 18 mm settlement
-
7/28/2019 Building Response to Excavation
48/80
1/22/2009
48
Mortar deteriorated due to water from downspouts
75mm
TIESPLACED
Examples of building response toExamples of building response to
excavation and tunnelingexcavation and tunneling
Review of ground movements and buildingReview of ground movements and building
Characteristics of bearing wall structuresCharacteristics of bearing wall structures
Bearing walls parallel to tunnel or excavationBearing walls parallel to tunnel or excavation Separation of upper wallSeparation of upper wall
Side sway of framesSide sway of frames
-
7/28/2019 Building Response to Excavation
49/80
1/22/2009
49
Abaqus FEMwithHypoplasticSoil,ConcreteFrame
Excavation
Depth:
25
mDisplacementmagnificationfactor:100
Soil modeled as
FIGURE 6-11 97B. Ghahreman, 2004
Side sway and tilt causeBay 1 distortions to be similar to Bay 3
Abaqus FEM,Hypoplastic Soilw/concreteframe
Excavationdepth: 25m Magnificationfactor:100
Angulardistortionsimilar foreach story
6-12 98
floor
First floor columns are distorted
by lateral ground strainsB. Ghahreman, 2004
-
7/28/2019 Building Response to Excavation
50/80
1/22/2009
50
Beambendingmomentrelatedtoangulardistortion
1 = + 0.002 10-32 = + 0.089 10-33 = - 0.087 10-34 = 0.000
Angular distortion, : 0.248 10-3
Slope: 1.647 10-3- Tilt: 1.399 10-3
4
3.02
3.02
2.64 cm
2nd story Bay 1
omen , xe en s: = M = 6(EI/L)( )
M
FIGURE 6-13 99
12 3.
2.56
3.95
2.562.64
7.7 m
M
-
7/28/2019 Building Response to Excavation
51/80
1/22/2009
51
Side sway of hotel with concrete floorsSide sway of hotel with concrete floors
Excavation Hotel with concrete floors Historic Brick Bearing WallStructure
-
7/28/2019 Building Response to Excavation
52/80
1/22/2009
52
Stiff clays and medium dense sands
BuildingExcavation
Hotel basement: 1 levelHistoricHouse: 1
level
~ 3 mm
-
7/28/2019 Building Response to Excavation
53/80
1/22/2009
53
HOTEL
-
7/28/2019 Building Response to Excavation
54/80
1/22/2009
54
Early 1800 faade:Alternating headers andstretchers
No apparent cracks
-
7/28/2019 Building Response to Excavation
55/80
1/22/2009
55
-
7/28/2019 Building Response to Excavation
56/80
1/22/2009
56
ARINGWALL
ALL
SMALLSIDESWAY:
~ 3 mm
(Exaggerated)
SETTLEMENT:
Settlement ofintermediate
EDIATETIMBERB
BRICKBE
ARING12 story
Hotel:
Concretefloors
bearing wallover time
INTERM
~ 50 mm
-
7/28/2019 Building Response to Excavation
57/80
1/22/2009
57
ALL
SMALLSIDESWAY
:
~ 3 mm
(Exaggerated) ARINGWA
LL
SETTLEMENT:
Shrinkage ofintermediate
BRICKBEARING12 story
Hotel:Concretefloors
EDIATETIMBERB
bearing wall
INTERM
~ 50 mm.
CONCLUSIONS
1. Structures often serve as indicators of the causes of imposed distortionsand damage
2. Understand the chain of relationships and behavior extending from tunnel orexcavation to building
Ground movement patterns and volume changeBuilding structural characteristics and finishes - - - how it was built,
maintained and repaired.
3. Damage due to excavation and tunneling may be superposed on pre-existing building distortions and deterioration
4. Damage due to excavation and tunneling may be separate from andunrelated to pre-existing building distortions and damage
-
7/28/2019 Building Response to Excavation
58/80
1/22/2009
58
CONCLUSIONS
It is most common and natural for residents and owners of buildings to
observe and attribute pre-existing conditions in their building to theeffects of the adjacent excavation or tunneling.Benefits of:
1. Pre-construction assessments and inspection, photographs and video-- ssess con ton o u ngs, sens tv ty to amage, w et er ue to
tunneling and excavation or other effects.-- Assess structural characteristics and building finishes
lateral and distortional stiffnesses, weak zones.2. A logical evaluation and description of the limits and magnitude of
ground movements and building distortions due to excavation ortunneling:
a. zone of influence
b. settlement slope,c. size of building with respect to settlement trough,d. change in ground slope.
3. Early building monitoring to determine temperature & seasonal effects.4. Community relations efforts by contractor, engineer and owner
throughout design and construction.5. Early recognition and acceptance of responsibility for excavation or
Control and reduceControl and reduce
RiskRisk of large, uncontrolledof large, uncontrolled ground loss in faceground loss in face
Shield, EPB:Shield, EPB:
ControlControl of conditioner and pressure in faceof conditioner and pressure in face
NATM:NATM:
Instability at faceInstability at face
Lining failure during or after excavation sequencesLining failure during or after excavation sequences
Regular ground lossRegular ground loss
Shield: AnnularShield: Annular spacesspaces Overcut at front of shieldOvercut at front of shield
Grout annulus between tail of shield and liningGrout annulus between tail of shield and lining
NATM: Lining deflection and ground displacement during excavationNATM: Lining deflection and ground displacement during excavation
Volume decreaseVolume decrease inin soilsoil DewateringDewatering
Stress increases around tunnelStress increases around tunnel
-
7/28/2019 Building Response to Excavation
59/80
1/22/2009
59
Allowable lAllowable limit forimit for
distortion/damagedistortion/damage
Observations/ControlObservations/Control
ADDITIONAL MEASURESADDITIONAL MEASURES
If Ground loss causes moreIf Ground loss causes moredistortion than allowabledistortion than allowable
Modify groundModify ground
Compensate groundCompensate ground
Protect structureProtect structureNear tunnel
In soil mass
At surface
At structuresLINK
Estimate tunnelEstimate tunnel
ground lossground loss
on ro unne ngon ro unne ngprocessprocess
Increasing ground loss can result in disproportionateincreases in round movement and buildin dama e
Small ground losses may be absorbed by volume increases insoil.
Building damage increases disproportionately with strains
Objective: control ground losses at the tunnel
Increasingly, with pressurized face tunneling, ground movementsare being controlled at the source, around the tunnel shield tolevels that result in negligible damage at the ground surface
Objective: reduce risk of large ground losses or collapse
-
7/28/2019 Building Response to Excavation
60/80
1/22/2009
60
METHOD OF CALCULATING BUILDING DISTORTION
BAY 1 BAY 2 BAY 3
CD
UDEC analysis of full scale brick bearing wall
BAY 1
A B
6100 mm
6100m
38 77 16 54
L
H
8 92 4 83
61000 67 10 3
. ..
AVERAGE SLOPE :
TILT :
ANGULAR DISTORTION :
LATERAL STRAIN (T) :
LATERAL STRAIN (F) :
61003 64 10 3
. ..
14 73 4 83
6100162 10 3
. ..
( . . ) .3 64 162 10 2 02 103 3
30 90 14 73
61002 65 10 3
. ..
FIGURE 4.6
-
7/28/2019 Building Response to Excavation
61/80
1/22/2009
61
Physical Model Studies, Test 5E
Schnabel Large Soil Model Test Lab at U. I. U. C.
D. Laefer, 2001
1.2 m high
Weightadded atfront tosimulatedowndrag
fromfaade
.
Model Test 5E: Excavation to 1220 mm
-
7/28/2019 Building Response to Excavation
62/80
1/22/2009
62
BAY 1 BAY 2 BAY 3 BAY 1 BAY 2 BAY 3
1.06 1.09 1.02 0.96
2.59 2.65 2.59 2.594.32 2.06 0.65 -0.21
VERTICAL(
LATERAL(
Distance (mm.)
Displacement(mm.)
BAY 1
*
BAY 2
SLOPE 1.93*
BAY 3
SLOPE 1.80*SLOPE 4.59
Distance (mm.)
VERTICAL
SOILBUILDING
4.39 2.07 0.62 -0.19
BAY 1
*
BAY 2
SLOPE 2.38*
BAY 3
SLOPE 1.33*SLOPE 3.80
VERTICAL
BUILDINGSOIL
LATERAL
BUILDING SOIL
(
(
123
.
-0.37
lat(F) 0.16
lat(T) 0.49
.
-0.15
lat(F) 0.03
lat(T) 0.05
.
2.29
lat(F) 1.95
lat(T) 2.25
a. Brick-Bearing Wall (Inelastic Analysis)
* Multiply by 10-3
b. Frame Wall (Elastic Analysis)
* Multiply by 10-3
TIL 2.57
-0.19
lat(F) 0.11
lat(T) 0.10
TIL 2.67
-1.34
lat(F) 0.10
lat(T) 0.00
TILT 2.56
1.24
lat(F) -0.05
lat(T) -0.10
Numerical analyses of 2-story brick-bearing wall (Pit 5E) and elastic frame, 1/10th model scale
1.08 mm
L 1830 mm
/L 6.00E-04
1.08 mm
L 1830 mm
/L 6.00E-04
4/L 2/L
FIGURE 5-5
EXTRAS
-
7/28/2019 Building Response to Excavation
63/80
1/22/2009
63
52.5S of backof Soldier pile
Separation: ~1/8? open to N,behind E column (adjacent toChroma W Wall), at crown molding.
South WallExcavation
Congress St
West
Wall
ChromaGallery
Ray EllisGallery
separation betweensidewalk and wall
54.5: 1/8crack
86.5: 1/ 4crack, curb, & crack in W. side pave.
95.5: 1/ 4@ c. j. in sidewalk
cr
75: 3/8separation at c. j. on brick sidewalk,
64: 5/16crack cuts straight across bricks, towardgallery entrance (crack gauge)
Fig 2. South side Ellis Square
97.5: 1/ 8 crack, curb,97.5: separation of construction joint betweenconcrete pavement slab extends across street
BarnardSt
57 mm reduction in joist bearing57mm
L >57mm/ 6 m =10 x 10-3
Severe to Very SevereJ oists supported withtemporary posts
-
7/28/2019 Building Response to Excavation
64/80
1/22/2009
64
Masonic
Temple,
Philadelphia
-
7/28/2019 Building Response to Excavation
65/80
1/22/2009
65
-
7/28/2019 Building Response to Excavation
66/80
1/22/2009
66
-
7/28/2019 Building Response to Excavation
67/80
1/22/2009
67
N
BarnardSt.
Congress St.
blockwall
Old drainpatches
1/8-3/8 top
Joists: - out of seat
Joistorientation
1/8
CG371mm
Floor crack: 3/8 lat, 3/8 vert.
Concrete
-
separation1/8
1/16 -3/8 top
1/16 -3/16 topJoists: 12 19 mm out of seat
1/8CG551mm
CG42 3mmCG38 2mm
Fig 3. Chroma Gallery, NE BasementFig 3. Chroma Gallery, NE Basement
3/8 lat, 3/8 vert. 1 /4 -1/8 top
1/16
Photos IMGP 2447-2471
Photos IMGP 2472-2476
(Main floor, Chroma Gallery: Photos IMGP 2508-2518)
-
7/28/2019 Building Response to Excavation
68/80
1/22/2009
68
N
BarnardSt.
Congress St.
blockwall
Old drainpatches
3 10 mmtop
J oists:12-20 mmout of seat
NS J oistorientation
3 mm
CG371mm
Floor crack:
Concrete
12-20 mmseparation
3 mm
2-10 mm top
2-5 mm top
J oists: 12-20 mmout of seat
1/8CG551mm
CG42 3mmCG38 2mm
,10 mm vertical.
Fig 3. Chroma Gallery, NE BasementFig 3. Chroma Gallery, NE Basement
10 mm lat,10 mm vert
6 3 mmtop
2 mm
Photos IMGP 2447-2471
Photos IMGP 2472-2476
(Main floor, Chroma Gallery: Photos IMGP 2508-2518)
-
7/28/2019 Building Response to Excavation
69/80
1/22/2009
69
Bearing walls parallel to excavationBearing walls parallel to excavation Contact at party walls a plane of weaknessContact at party walls a plane of weakness
DetermineDetermine G.S. between baysG.S. between bays
Opening at top:Opening at top: G.S x HG.S x H
Strain at top:Strain at top: G.S x H/ 2 LG.S x H/ 2 Lbb = 4 (Defl Ratio) x H/2Lb == 4 (Defl Ratio) x H/2Lb =H/2RH/2R
Distribute:Distribute:
To one side of the wallTo one side of the wall
To both sides of the wallTo both sides of the wall
etween two wa s t tetween two wa s t t Party walls assumed continuousParty walls assumed continuous DetermineDetermine
G.S. between baysG.S. between baysFor bearing walls moving with ground:For bearing walls moving with ground:
G.S.G.S.
-3) 3
4
SEVERE TO VERY SEVERE
*The results of two fieldcases andone numerical test
are outof range
( ) - Damage level based on
maximumcrack width
(Burlandetal., 1977)
[ ] - Damage level basedon
fieldobservation
Constant Principal
Extension Strain
LateralS
train,L
(x10
1
2
Col 36 vs Col 37Col 39 vs Col 40
Col 48 vs Col 49SLIGHTDAMAGE
MODERATETO
SEVERE DAMAGE
(BoscardingandCording, 1989)
(N) - Negligible
(VSL) - Veryslight
(SL) - Slight
(M) - Moderate
(SE) - Severe
(VSE) - Verysevere
[N] - Negligible
[VS] - Veryslight
[SL] - Slight
[M] - Moderate
[SE] - Severe
[VSE] - Verysevere
Numerical tests
Field cases
MODERATE DAMAGE
Angular Distortion, (x10-3)
0 1 2 3 4 5 6 70
NEGL.
Figure 25 Damage level estimation and observed damage level
FIGURE 4-1
Angular Distortion, ( x 10 - 3 )
1/1000 1/500 1/200 1/100
after Boscardin & Cording, 1989
-
7/28/2019 Building Response to Excavation
70/80
1/22/2009
70
Physical Model Studies, Test 5E
Schnabel Large Soil Model Test Lab at U. I. U. C.
D. Laefer, 2001
1.2 m high
Weightadded atfront tosimulatedowndrag
fromfaade
.
Model Test 5E: Excavation to 1220 mm
-
7/28/2019 Building Response to Excavation
71/80
1/22/2009
71
-
7/28/2019 Building Response to Excavation
72/80
1/22/2009
72
South Wing Central Wing
Concrete floors reduce lateral strains in upper levels
37 32
Vert.
1.2
0.5
Lat. 0.9(calc)
0.2 separation
Angular distortion across South Wing = 0.1/37 = 1/370Angular distortion across South Wing = 0.1/37 = 1/370 Lateral strain across South Wing =Lateral strain across South Wing = 0.08/37 = 1/4700.08/37 = 1/470 Lateral strain largely confined to basement levelLateral strain largely confined to basement level
extens on
of cracksbetween Wings
-
7/28/2019 Building Response to Excavation
73/80
1/22/2009
73
Crosswall
Angular distortion:
31 mm6m? =5x 10-3
31 mm /3m ? =10 x 10-3
Severe Damage
145
South bearing wall
31 mm
Max. Lat.
SECTION A
34 37 32
2.5 1.4
56w =
i
.
34
40 o
Z=60 Average Slope = 1/300
Maximum lateral displacement (calculated):
L = 1/3 M (tan b/ 0.5) = 1.4
-
7/28/2019 Building Response to Excavation
74/80
1/22/2009
74
Evaluate strains and displacements across bay:
37 bay 32
StreetStreet Vert.1.2
34
Lat. 0.9(calc)
Angular distortion across 37 bay = 0.1/ 37 = 1/370Angular distortion across 37 bay = 0.1/ 37 = 1/370 Lateral strain across 37 bay =Lateral strain across 37 bay = 0.08/ 37 = 1/4670.08/ 37 = 1/467
-
7/28/2019 Building Response to Excavation
75/80
1/22/2009
75
-
7/28/2019 Building Response to Excavation
76/80
1/22/2009
76
-
7/28/2019 Building Response to Excavation
77/80
1/22/2009
77
-
7/28/2019 Building Response to Excavation
78/80
1/22/2009
78
-
7/28/2019 Building Response to Excavation
79/80
-
7/28/2019 Building Response to Excavation
80/80
1/22/2009