building on best practices in project management: … building on best practices in project...

58
1 Building on Best Practices in Project Management: PMBOK Standards NCAMPO 2013 Conference Winston-Salem, NC May 15 - 17, 2013 Majed Al-Ghandour, Ph.D., PE, CPM Program Development Branch NCDOT

Upload: lephuc

Post on 10-Mar-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

1

Building on Best Practices in Project Management: PMBOK Standards

NCAMPO 2013 Conference Winston-Salem, NC May 15 - 17, 2013

Majed Al-Ghandour, Ph.D., PE, CPM Program Development Branch

NCDOT

2 2

Outline • Introduction about STIP & PMU

• PMBOK

• Project Management Best Practices

• EVM (Earned Value Management)

• Reporting as a Performance Measures

• Conclusions & Recommendations

3 3

Introduction – NCDOT STIP • The Project Management Unit (PMU)- (NCDOT) is

responsible for authorization of funds for various State Transportation Improvement program (STIP) projects:

• Preliminary Engineering (PE).

• Right-of-Way acquisition (ROW).

• Utility relocation, Construction (CON).

• Mitigation, and Landscape development. • Draft STIP (2013 – 2023 ) includes over 2,293 projects (~ $16 billions).

4

TABLE 1 Summary of the Draft STIP FY 2013-2023

As May 2013

5

KEY TO HIGHWAY FUNDING SOURCES

6

APD - Appalachian Development BOND - Revenue Bond BRGI - Bridge Inspection C - City CMAQ - Congestion Mitigation DOD - Department of Defense DP - Discretionary or Demonstration FA - Bridge Replacement On-Federal-Aid System FLPF - Federal Lands Program (Forest Highways) FLPI - Federal Lands Program (Indian Reservation Roads) FLPP - Federal Lands Program (Park Roads) FLPR - Federal Lands Program (Refuge Roads) HES - High Hazard Safety HFA - Highway Fund Appropriation

KEY TO HIGHWAY FUNDING SOURCES

7

HP - Federal-Aid High Priority HRRR - High Risk Rural Roads IM - Interstate Maintenance IM(E) - Interstate Maintenance Exempt IMPM - Interstate Preventative Maintenance L - Local Matching Share MOB - Mobility Funds NFA - Bridge Replacement Off-Federal-Aid System NFAM - Municipal Bridge Replacement Program NHS - National Highway System NHS(E) - National Highway System Exempt NRT - National Recreation Trails

KEY TO HIGHWAY FUNDING SOURCES …continued

8

O - Others PLF - Personal Automobile License Plate Funds RR - Rail-Highway Safety S - State S(E) - State Exempt SF - State Ferries SG - Safety Grant S(M) - State Match S(5) - State (Highway) Trust Funds SRTS - Safe Routes to School STHSR - Stimulus High Speed Rail

KEY TO HIGHWAY FUNDING SOURCES …continued

9

STP - Surface Transportation Program STPDA - Surface Transportation Program - Direct Attributable STPEB - Surface Transportation Program, Enhancements (Bike) STPEL - Surface Transportation Program, Enhancements (Local) STPEP - Surface Transportation Program, Enhancements (Pedestrian) STPER - Surface Transportation Program, Enhancements (Roadside) T - Highway Trust Funds T2001 - State Rail Funds TIFIA - Transportation Infrastructure Finance and Innovation Loan

KEY TO HIGHWAY FUNDING SOURCES …continued

10

• Project management is “the application of knowledge, skills, tools and techniques to project activities to meet project requirements” (PMBOK® Guide, Fourth Edition, 2008, p. 6)

• Project managers strive to meet the triple constraint by balancing project scope, time, and cost goals

What is Project Management?

11

The Triple Constraint of Project Management

Successful project management means meeting all three goals (scope, time, and cost) – and satisfying the project’s sponsor!

13

Project Management Framework

14

15 15

Why PMBOK? • Project Management Body of Knowledge (PMBOK) is a Guide for

applying the standards enables PMU to track the STIP life cycle through Process: • Initiating, • Planning, • Executing, • Monitoring, • Controlling and • Closing Process.

• The PMU utilizes state of the art of the project management concepts

that monitor and control the successful delivery of STIP Projects.

• PMU applies PMBOK process on STIP Projects to provide project performance measurement such as an Earned Value Management (EVM).

16 16

Best Practice 1: Manage the Project Scope and monitor the schedule and budget

Best Practice 2: Use EVM (Earned Value Management)

Best Practice 3: Ensure the project is closed with compliance “Closing and acceptance”

Project Management Best Practices

17 17

• Look at the amount of money your project has actually consumed and determine whether your actual spending is more than originally estimated based on the work that has been completed. • If so, be proactive. Either work with the team to determine how the remaining work will be completed to hit your original budget or else raise a risk that you may exceed your allocated budget.

Monitor the Budget Best Practice 1

18

STIP Budget & Schedule View

Budget View

19

Schedule View

20

21

Project Status Report

22

Project Status Report …continued

Project Count by R/W Year

23

Project Status Report …continued

Project Count by LET Year

24

25

95.44% 89.99%

Dashboard KPI

26

Provide a Monthly Report Details What is Authorized?

27

28

Let List Construction Cost

29

https://apps.dot.state.nc.us/traffictravel/progloc/ProgLocSearch.aspx

30

SAP/PS

31

Schedule

32

33

34

Earned Value Management is a project performance measurement technique that integrates scope, time, and cost data (combines schedule and cost performances). • EVM analyzes project performance to answer these questions:

1. What did we get for the money we spent? 2. Is the project on schedule? (ahead/behind schedule) 3. Is the project on budget? (under/over budget) 4. What do we currently expect the TOTAL project to cost (a forecast)? 5. How much more will the project cost?

What is EVM? Best Practice 2

35

Basic Measurements that are required to measure Earned Value Management: PV: Planned Value Cost: Budget: The approved total cost estimate planned to be spent on the project of the work scheduled (STIP Latest Estimate), as of today AC: Actual Cost: Expenditures (total direct and indirect costs), as of today EV: Earned Value: As of today, the value of the work actually accomplished

What is EVM? …continued

36

RP: Rate of Performance: The ratio of actual work completed to the percentage of work planned (RP=actual completed/planned) BAC: Budget at Completion: The original total budget for the project BAC: Budget * Engineering Contingency factor CV: Cost Variance: CV=EV-AC Negative means the performing the work cost more than planned (over budget) Positive means the performing the work cost less than Planned (under budget)

What is EVM? …continued

37

CPI: Cost Performance Index: CPI=EV/AC >1 is good getting $x of value out of every $1 spent (Project is under budget) Efficiency in utilizing the resources <1 is bad getting $x of value out of every $1 spent (Project is over budget) =1 the planned and actual costs are equal (Project is exactly as budget)

What is EVM? …continued

38

Forecast the Future Performance Trends: EAC: Estimated At Completion: A forecast of total costs that will be accrued by project completion based on past cost performance trends. EAC=AC+BAC-EV/CPI ETC: Estimated To Completion: From today on, how much MORE do we expect it to cost to finish the project (a forecast) ETC=EAC –AC Variance at Completion (VAC). The difference between the new Estimate at Completion and the original Budget at Completion. VAC= EAC – BAC

What is EVM? …continued

39

• Schedule: SV: Schedule Variance: SV=EV-PV

Negative means it took longer than planned to perform the work (behind schedule) Positive means it took less time than planned to perform the work (ahead schedule)

SPI: Schedule Performance Index: SPI=EV/PV >1 the project is ahead of schedule <1 is bad the project is behind schedule =1 the project is on schedule

What is EVM? …continued

40

How do you start? • Create a detailed project schedule with budget

allocated for each tasks

• Baseline the project schedule

• On Status reporting date, Enter: • a) % Complete and • b) Actual Cost (AC)

• Generate Earned value Chart

41

Earned Value Chart

42

43

44

45

Earned Value Chart for Project after Five Months

46

47

• Negative numbers for cost and schedule variance indicate problems in those areas

• CPI and SPI less than 100% indicate problems

• Problems mean the project is costing more than planned (over budget) or taking longer than planned (behind schedule)

Rules of Thumb for Earned Value Numbers

WBS Closure

48

Best Practice 3

49

Flow Charts

50

51

52

53

54

Year 2013: $5,729,739 From 2006 to 4/2013: $150,942,056

55 55

Conclusions & Recommendations (1 of 3)

• Mapping the STIP Process to the PMBOK Knowledge Areas.

• Using PMBOK (Project Management Body of

Knowledge ) standards to track the STIP life cycle through process:

• Initiating, • Planning, • Executing, • Monitoring, • Controlling and • Closing Process.

56 56

Conclusions & Recommendations (2 of 3) • Using Business Intelligent Reporting for EVM analysis.

• Project is under budget Efficiency in utilizing the

resources.

• Project is ahead of schedule project team is very efficient in utilizing the time allocated to the project.

• Closing projects are very crucial.

57 57

Conclusions & Recommendations (3 of 3)

• Finally, we also recommend to use EVM answers these

questions: 1. What did we get for the money we spent? 2. Is the project on schedule? (ahead/behind schedule) 3. Is the project on budget? (under/over budget) 4. What do we currently expect the TOTAL project to

cost (a forecast)? 5. How much more will the project cost?

58 58

Contact Information & Questions

Majed N. Al-Ghandour, Ph.D., P.E., CPM, M.ASCE Assistant Branch Manager, Engineering Manager Program Development Branch - NCDOT 1534 Mail Service Center Raleigh, NC 27699-1534 Tel.: 919-707-4621 Fax: 919-733-3585 Emails: [email protected]

THANK YOU