building data

Upload: pandugadu87

Post on 05-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Building DATA

    1/23

    Sl. No. Description Unit Quantity Rate Rs.

    RBR-FNDN1

    b

    1 Earthwork in excavation for structures as per drawing and

    technical specifications Clause 305.1 including setting out,

    construction of shoring and bracing, removal of stumps and

    other deleterious material and disposal upto a lead of 50 m,

    Mechanical Means

    Upto 3 m depth

    Unit = cum

    Taking output = 240 cum

    a)Labour

    Mate da -

    Mazdoor Unskilled da 8.32 258.00

    b) Machinery

    H draulic Excavator 1 cum bucket ca acit hour 6.00 2009.50

    c&d) Overheads & Contractors Profit

    Cost for 240 cum = a+b+c+d

    Rate per cum = (a+b+c+d)/240

    BLD-CSTN-

    2-5

    2 Plain Cement concrete (1:4:8) using 40 mm metal with

    concrete mixture. All work upto plinth level.Unit = 1cum

    A. MATERIALS:

    Cement k 162.00 5300.00

    Coarse a re ate 40 mm cum 0.90 1094.70

    Fine a re ate Sand cum 0.45 630.62

    Seigniorage charges for C.A cum 0.90 0.00

    Seigniorage charges for F.A cum 0.45 0.00

    Water (including for curing) kl 1.20 77.00

    B. MACHINERY

    Concrete Mixer 10 / 7 cft 0.2 / 0.8 cum ca acit hour 1.00 248.40

    C. LABOUR:

    Mason 1st class day 0.10 342.00

    Mazdoor (unskilled) day 1.39 258.00

    Overheads & Contractors Profit @ 14%

    Grand Total

    3 RCC M- 20 nominal mix (Cement:fine aggregate: coarse aggregate)

    corresponding to Table 9 of IS 456 using 20mm size graded machine

    crushed hard granite metal (coarse aggregate) from approved quarry

    including cost and conveyance of all materials like cement, fine

    aggregate (sand) coarse aggregate, water etc., to site and including

    Seigniorage charges, sales & other taxes on all materials including all

    operational, incidental and labour charges such as mixing, laying

    concrete, curing, centering, shuttering etc.,complete but excludingA FOOTINGS UNIT 1.00

    A. MATERIALS:

    Cement for mix kg 400.00 5300.00

    Coarse aggregate 20mm cum 0.90 1273.70

    Fine aggregate cum 0.45 630.62

    Water including kl 1.20 77.00

    Add Seignorage charges on CA @

    Water including

    Total

    B. MACHINERY

    COMPOUND WALL DATA

    SATTENAPALLE MUNICIPALITY

    DATA 2011-2012

    Note: 1. Cost of dewatering upto 5% ofa+b may be added, where required, upto 10 per cent of labo

    Assessment for dewatering shall be made as per site conditions.

    (included in material rate)

    (included in material rate)

  • 8/2/2019 Building DATA

    2/23

    Sl. No. Description Unit Quantity Rate Rs.

    Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80

    Fuel/Energy charges Hour 0.133 61.90

    Needle Vibrator 60mm dia (petrol) Hour 1.00 6.20

    Fuel/Energy charges Hour 0.667 18.60

    Centering charges cum 1.00 59.00

    Total

    C. LABOUR

    Labour charges for centering cum 1.00 330.00Crew for concrete mixer Hour 1.00 141.70

    Crew for needle vibrator Hour 1.00 102.00

    Mason Class-1 Day 0.133 285.00

    Mason Class-2 Day 0.267 260.00

    Mazdoor (unskilled) Day 3.60 215.00

    Total

    Add 20% over basic rate on labour component for Municipal area

    ABSTRACT

    A. Cost of Material including seigniorage charges

    B. Hire charges for Machinery

    C. Cost of Labour

    D. Contractors Profit &over heads on (A+B+C)

    Total cost for 1.00 cum

    COLUMNS UNIT 1.00

    A. MATERIALS:

    Cement for mix kg 400.00 5300.00

    Coarse aggregate 20mm cum 0.90 1273.70

    Fine aggregate cum 0.45 630.62

    Water including kl 1.20 77.00

    Add Seignorage charges on CA @

    Water including

    Total

    B. MACHINERY

    Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80

    Fuel/Energy charges Hour 0.133 61.90

    Needle Vibrator 60mm dia (petrol) Hour 1.00 6.20

    Fuel/Energy charges Hour 0.667 18.60

    Centering charges cum 1.00 89.00

    Total

    C. LABOUR

    Labour charges for centering cum 1.00 747.00

    Crew for concrete mixer Hour 1.00 141.70

    Crew for needle vibrator Hour 1.00 102.00

    Mason Class-1 Day 0.133 285.00

    Mason Class-2 Day 0.267 260.00

    Mazdoor (unskilled) Day 3.60 215.00

    Total

    Add 20% over basic rate on labour component for Municipal area

    ABSTRACT

    A. Cost of Material including seigniorage charges

    B. Hire charges for Machinery

    C. Cost of Labour

    D. Contractors Profit &over heads on (A+B+C)

    (included in material rate)

    B

    (included in material rate)

  • 8/2/2019 Building DATA

    3/23

    Sl. No. Description Unit Quantity Rate Rs.

    Total cost for 1.00 cum

    C PLINTH BEAM UNIT 1.00

    A. MATERIALS:

    Cement for mix kg 400.00 5300.00

    Coarse aggregate 20mm cum 0.90 1273.70

    Fine aggregate cum 0.45 630.62

    Water including kl 1.20 77.00

    Add Seignorage charges on CA @

    Water including

    Total

    B. MACHINERY

    Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80

    Fuel/Energy charges Hour 0.133 61.90

    Needle Vibrator 60mm dia (petrol) Hour 1.00 6.20

    Fuel/Energy charges Hour 0.667 18.60

    Centering charges cum 1.00 993.00

    Total

    C. LABOUR

    Labour charges for centering cum 1.00 795.00

    Crew for concrete mixer Hour 1.00 141.70

    Crew for needle vibrator Hour 1.00 102.00

    Mason Class-1 Day 0.133 285.00

    Mason Class-2 Day 0.267 260.00

    Mazdoor (unskilled) Day 3.60 215.00

    Total

    Add 20% over basic rate on labour component for Municipal area

    ABSTRACT

    A. Cost of Material including seigniorage charges

    B. Hire charges for Machinery

    C. Cost of Labour

    D. Contractors Profit &over heads on (A+B+C)

    Total cost for 1.00 cum

    D BEAMS UNIT 1.00

    A. MATERIALS:

    Cement for mix kg 400.00 5300.00

    Coarse aggregate 20mm cum 0.90 1273.70

    Fine aggregate cum 0.45 630.62

    Water including kl 1.20 77.00

    Add Seignorage charges on CA @

    Water including

    Total

    B. MACHINERY

    Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80

    Fuel/Energy charges Hour 0.133 61.90

    Needle Vibrator 60mm dia (petrol) Hour 1.00 44.80

    Fuel/Energy charges Hour 0.667 18.60

    Centering charges cum 1.00 1276.00

    Total

    C. LABOUR

    Labour charges for centering cum 1.00 795.00

    Crew for concrete mixer Hour 1.00 141.70

    Crew for needle vibrator Hour 1.00 102.00

    (included in material rate)

    (included in material rate)

    (included in material rate)

    (included in material rate)

  • 8/2/2019 Building DATA

    4/23

    Sl. No. Description Unit Quantity Rate Rs.

    Mason Class-1 Day 0.133 285.00

    Mason Class-2 Day 0.267 260.00

    Mazdoor (unskilled) Day 3.60 215.00

    Total

    Add 20% over basic rate on labour component for Municipal area

    ABSTRACT

    A. Cost of Material including seigniorage chargesB. Hire charges for Machinery

    C. Cost of Labour

    D. Contractors Profit &over heads on (A+B+C)

    Total cost for 1.00 cum

    E ROOF SLAB UNIT 1.00

    A. MATERIALS:

    Cement for mix kg 400.00 5300.00

    Coarse aggregate 20mm cum 0.90 1273.70

    Fine aggregate cum 0.45 630.62

    Water including kl 1.20 1273.70

    Add Seignorage charges on CA @

    Water including

    Total

    B. MACHINERY

    Concrete mixer 10/7cft (0.2/0.8cum) capacity Hour 1.00 44.80

    Fuel/Energy charges Hour 0.133 61.90

    Needle Vibrator 60mm dia (petrol) Hour 1.00 44.80

    Fuel/Energy charges Hour 0.667 18.60

    Centering charges cum 1.00 143.00

    Total

    C. LABOUR

    Labour charges for centering cum 1.00 89.00

    Crew for concrete mixer Hour 1.00 141.70

    Crew for needle vibrator Hour 1.00 102.00

    Mason Class-1 Day 0.133 285.00

    Mason Class-2 Day 0.267 260.00

    Mazdoor (unskilled) Day 3.60 215.00

    Total

    Add 20% over basic rate on labour component for Municipal area

    ABSTRACT

    A. Cost of Material including seigniorage charges

    B. Hire charges for Machinery

    C. Cost of Labour

    D. Contractors Profit &over heads on (A+B+C)

    Total cost for 1.00 cum

    BLD-CSTN

    2-18

    4 Supplying, fitting and placing HYSD bar reinforcement in

    foundation complete as per drawings and technical

    specifications for Bars below 36 mm dia including over laps

    and wasta e where the are not weldedUnit = t

    (a) Material

    HYSD bars including 5 per cent for overlaps and wastage t 1.05 44000.00

    Bindin wire k 6.00 55.00

    1000 &

    1200

    (included in material rate)

    (included in material rate)

  • 8/2/2019 Building DATA

    5/23

    Sl. No. Description Unit Quantity Rate Rs.

    (b) Labour for cutting, bending, shifting to site, tying and

    placing in positionBlacksmith / Bar bender day 2.00 360.00

    Mazdoor (Unskilled) day 6.40 258.00

    (c) Overheads on (a+b)

    (d) Contractors profit on (a+b+c)Rate per t = a+b+c+d

    Rate per kg = a+b+c+d /1000

    Cement Mortar (1 : 3)

    Unit : 1cum

    A. MATERIALS:

    Cement k . 480.00 5300.00

    Sand includin 5% wasta e cum 1.05 630.62

    Sei niora e char es for sand cum 1.05

    B. MACHINERY

    - Nil - -

    C. LABOUR:

    Man mazdoor for mixin mortar da 0.20 258.00

    Grand Total

    BLD-CSTN PLASTERING

    BLD-CSTN6-1

    5 Plastering with CM (1:3), 12 mm thick to ceiling includingcost & conveyance of all materials and labour charges curing

    etc., complete

    Unit = 10 sqm

    A. MATERIALS:

    Cement Mortar (1:3) cum 0.15 3257.75

    Sei niora e char es for F.A cum 0.15 0.00

    B. LABOUR:

    Mason 1st class day 0.60 342.00

    Mazdoor (unskilled) day 0.96 258.00

    Overheads & Contractors Profit @ 14%

    Grand Total

    BLD-CSTN6-1

    6 Plastering with CM (1:3), 20 mm thick to ceiling includingcost & conveyance of all materials and labour charges curing

    etc., completeUnit = 10 sqm

    A. MATERIALS:

    Cement Mortar 1:3 cum 0.21 3257.75

    Sei niora e char es for F.A cum 0.21

    B. LABOUR:

    Mason 1st

    class day 0.91 342.00

    Mazdoor unskilled da 1.60 258.00

    Overheads & Contractors Profit @ 14%

    Grand Total

    7 Refilling the foundation with excavated soils other than sand

    complying with standard specification for finished item of

    work - 1cuma)Labour

    Mazdoor Unskilled da 0.31 258.00

    c&d) Overheads & Contractors Profit

    Rate per cum

    8 Brick Masonry in CM (1:6) with 2nd class Bricks traditional

    size 23 x 11 x 7 cms including cost of all materials and labour

    Note: When Motor mix is changed proportionate quantity of cement has to be submitted

  • 8/2/2019 Building DATA

    6/23

    Sl. No. Description Unit Quantity Rate Rs.

    Unit = 1 cum

    A. MATERIALS:

    Cement kg 48.00 5300.00

    Bricks traditional size 23x11x7 cms 2nd class nos 512.00 3100.00

    Fine a re ate Sand cum 0.20 630.62

    Sei niora e char es for sand cum 0.20

    B. LABOUR:

    Mason 1st class day 0.24 342.00

    Mason 2nd class day 0.56 312.00Mazdoor unskilled da 1.89 258.00

    c) Overheads & Contractors Profit @ 14%

    Rate per cum (a+b+c)

    9 White washing two coats with whiting of approved quality to

    give an even shade after thoroughly brushing the surface to

    remove all dirt and remains of loose powdered materials

    including cost of all materials, labour charges and incidental

    such as scaffolding, lift charges etc., complete for finished

    item of work, but excluding conveyance charges of materials

    A. MATERIAL

    Whiting/White Cement kg 2.00 25.00

    Gum, conjee water, or prickly pear juice including necessary fire wood LsB. LABOUR

    Painter 1st class day 0.21 360.00

    Mazdoor (unskilled) day 0.32 258.00

    Sundries includin brushes ladders etc. 1% 158.16

    c) Overheads & Contractors Profit @ 14%

    Rate per 10 sqm

    Rate per 1 sqm

    10 Colour washing two coats over plastered wall surface as per

    Standard specification. - 10 sqmA. MATERIAL

    Rate for "White Washin " two coats s m 10.00 24.30

    Add: For Colours, etc., (50 % of above rate)

    c) Overheads & Contractors Profit @ 14%

    Rate per 10 sqm

    Rate per 1 sqm

    11 Flooring with 15 mm thick Polished black Kadapa slabs

    (0.457x0.457M) , set over base coat of C.M (1:8) 12 mm thick

    over CC bed already laid or RCC roof slab, including pointing

    with cement mortar 1:3 duly filling joints nearly, including

    cost of all materials like flooring stone, cement, sand, and

    water etc., complete, including seigniorage charges, labour

    charges for dressing of flooring stones etc., complete for

    finished item of work, but excluding the cost of conveyance of

    A. MATERIALS:

    Polished black Kadapa slabs minimum of 15 mm thick

    0.457x0.457M BMT-B.06 sqm 10.50 107.60

    Cement for CM (1:8) proportion for base coat kg. 21.60 5300.00

    Cement for CM 1:3 proportion for pointing kg. 9.60 5300.00

    Sand for CM (1:8) proportion cum 0.12 630.62

    Sand for CM (1:3) proportion cum 0.02 630.62

    B. LABOUR

    Mason Class-1 Day 0.96 285.00

    Mason Class-2 Day 2.24 260.00

    Mazdoor (unskilled) Day 3.30 215.00

  • 8/2/2019 Building DATA

    7/23

    Sl. No. Description Unit Quantity Rate Rs.

    Add Water Charges @ 1% 1565.50

    Add 20% on Labour 1565.50

    Total (a+b)

    c) Overheads & Contractors Profit @ 14%

    Cost of 10 sqm

    Cost of 1 sqm

    12 Flooring with Polished Bethamcherla coloured stone

    minimum 25 mm thick (0.254 M x 0.254 M), set over base

    coat of cement mortar (1:8) 12 mm thick over CC bed already

    laid or RCC roof slab, including neat cement slurry of honey

    like consistency spread @ 3.3.kgs per sqm & jointed neatly

    with cement paste mixed with pigment of matching shade to

    full depth, including cost of all materials like cement, sand

    water and tiles etc., complete, including seigniorage charges,

    etc., complete for finished item of work, but excluding the

    cost of conveyance of all materials - 10 Sq.M

    A. MATERIALS:Polished Bethamcherla coloured stone minimum 25 mm thick (0.254M

    x0.254M sqm 10.10 215.20

    Cement for CM (1:8) proportion for base coat kg. 21.60 5300.00

    Cement for jointing & pointing kg. 6.00 25.00Pointing with CM (1:3) cum 1.00 3257.75

    Deduct CM 1:3 cum 0.04 3257.75

    Sand for CM (1:8) proportion cum 0.12 630.62

    Seigniorage charges of sand cum 0.02

    B. LABOUR

    Mason Class-1 Day 0.96 285.00

    Mason Class-2 Day 2.24 260.00

    Mazdoor (unskilled) Day 3.30 215.00

    Add Water Charges @ 1% 1565.50

    Add 20% on Labour 1565.50

    Total (a+b)

    c) Overheads & Contractors Profit @ 14%

    Cost of 10 sqm

    Cost of 1 sqm

    13 Skirting to internal walls with 25mm thick polished

    Bethamcherla colored stone of first quality 125 mm height

    with top edge flat nosed and joints corresponding to the floor

    lines, set over base coat of CM (1:5) 12 mm thick with cement

    slurry of honey like consistency spread at the rate of 3.30 kgs

    per sqm and jointed with white cement paste mixed with

    pigment of matching shade to full depth, including cost of all

    materials like tiles, cement, sand and water etc., complete

    including seigniorage charges, etc., complete for finished

    item of work, but excluding the cost of conveyance of all

    A. MATERIALS:Polished Bethamcherla coloured stone minimum 25 mm thick (0.254M

    x0.254M) sqm 10.10 215.20

    Sand for cm 1:5 base coat cum 0.12 630.62

    Cement for cm 1:5 base coat kgs 34.56 5300.00

    Cement for slurr kgs 33.00 5300.00

    White cement for jointing & pointing kgs 2.00 25.00

    Seigniorage charges of sand cum 0.12

    B. LABOUR

    Mason Class-1 Day 0.96 285.00

    Mason Class-2 Day 2.24 260.00

  • 8/2/2019 Building DATA

    8/23

    Sl. No. Description Unit Quantity Rate Rs.

    Mazdoor (unskilled) Day 3.30 215.00

    Add Water Charges @ 1% 1565.50

    Add 20% on Labour 1565.50

    Total (a+b)

    c) Overheads & Contractors Profit @ 14%

    Cost of 10 sqm

    Cost of 1 sqm

    BLD-CSTN

    6-10

    14 Plastering with CM 2 coats, 12 mm thick, base coat in CM

    (1:5), 8mm thick and top coat in CM (1:3), 4mm thick with

    sponze finishing.

    Unit = 10 sqm

    A. MATERIALS:

    Base Coat in CM 1:5 8 mm thickCement kg 31.70 5300.00

    Fine aggregate (Sand) cum 0.11 630.62

    Top Coat in CM(1:3), 4 mm thick

    Cement k 19.20 5300.00

    Fine a re ate Sand cum 0.04 630.62

    Sei niora e char es for F.A cum 0.15

    B. LABOUR:

    Mason 1

    st

    classday 0.63 342.00

    Mason 2nd

    class day 1.47 312.00

    Mazdoor unskilled da 3.90 258.00

    C) Overheads & Contractors Profit @ 14%

    Cost of 10 sqm

    Cost of 1 sqm

    15 SINTEX OR equivalent SLIDING 2 TRACK WINDOWS Supply

    and fixing of two track or three track sliding window the

    outer frame shall be 58 X 45mm with a wall thickness of

    1.2mm 0.3mm. The sliding shutter frame is made of PVC

    section 57 X 32mm with overall dimensions of 1.5mm

    0.3mm provided with 5mm glazing. Roller bearings and

    arrestor type handle cum lock shall be provided, complete, for

    A. MATERIALS:

    Basic Rate BMT-P.07 sqm 1.00 2680.00

    B) Overheads & Contractors Profit @ 14%

    Cost of 1 sqm

    LD-CSTN-7

    16 Flooring with ceramic tiles, set over base coat of cement

    mortar (1:8), 12 mm thick over CC bed already laid or RCC

    roof slab, including neat cement slurry of honey like

    consistency spread @ 3.3.kgs per sqm & jointed neatly with

    white cement paste to full depth mixed with pigment of

    matching shade, including cost of all materials like cement,

    sand water and tiles etc., complete, including seigniorage

    charges, etc., complete for finished item of work, but

    Unit = 10 sqm

    A. MATERIALS:

    Ceramic tiles sqm 10.10 374.00

    Cement for CM 1:8 for base coat k . 21.60 5.30

    Cement for slurr k . 33.00 5.30

    White cement k . 2.00 30.00

    Sand for CM 1:8 cum 0.12 630.62

    Seigniorage charges of sand cum 0.12

    B. LABOUR

    Mason 1st

    class day 0.96 342.00

    Mason 2nd

    class day 2.24 312.00

    Mazdoor (unskiled) day 3.30 258.00

    Note : When Mortar mix is changed proportionate quantity of cement has to be substituted

  • 8/2/2019 Building DATA

    9/23

    Sl. No. Description Unit Quantity Rate Rs.

    Add water charges 1% 1.00% 1878.60

    Grand Total

    C) Overheads & Contractors Profit @ 14%

    Rate for 10 sqm

    Rate for 1 sqm

    17 Dadooing to walls with first quality glazed coloured tiles

    approved colour of any size set over base coat of CM (1:3) 12

    mm thick with cement slurry of honey like consistency spread

    at the rate of 3.30 kgs per sqm and jointed with white cement

    paste mixed with pigment of matching shade to full depth,

    including cost of all materials like tiles, cement, sand and

    water etc., complete including seigniorage charges, etc.,

    complete for finished item of work, but excluding the cost of

    Unit = 10 sqm

    A. MATERIALS:

    Ceramic tiles 7.30 mm thick(p13-item No.38) sqm 10.00 374.00

    Sand for cm 1:3 base coat cum 0.12 630.62

    Cement for cm 1:3 base coat kgs 57.60 5.30

    Cement for slurry kgs 33.00 5.30

    White cement for ointin & ointin .no.29 i.372 k s 6.00 30.00

    Sei niora e char es of sand

    B. LABOUR

    Mason 1st class day 0.77 342.00Mazdoor (unskiled) day 0.80 312.00

    Mazdoor unskiled da 3.30 258.00

    Add water charges 1% 1.00% 1364.34

    Grand TotalC) Overheads & Contractors Profit @ 14%

    Rate for 10 sqm

    Rate for 1 sqm

    18 Supplying and Fixing European Water Closet of 1st quality

    conforming to IS:2556-Part-2-1973 of Hindustan / Neycer or

    Parr ware make white lazed with 'S' traBasic Rate (BMW-D.14) Each 1.00 1250.00

    B) Overheads & Contractors Profit @ 14%

    Cost of 1 No

    Assistant Engineer, Dy. Executive Engineer, Commission

    Sattenapalle Municipality. Sattenapalle Municipality. Sattenapalle Muni

  • 8/2/2019 Building DATA

    10/23

    Amount

    2146.56

    12057.00

    14203.56

    1988.50

    16192.06

    67.47

    858.60

    985.23

    283.78

    0.00

    0.00

    92.40

    248.40

    34.20

    358.62

    2861.23

    400.57

    3261.80

    cum

    2120.00

    1146.33

    283.78

    92.40

    0.00

    0.00

    3642.51

    ur cost.

  • 8/2/2019 Building DATA

    11/23

    Amount

    44.80

    8.23

    6.20

    12.41

    59.00

    130.64

    330.00141.70

    102.00

    37.91

    69.42

    774.00

    1455.03

    291.01

    1746.03

    3642.51

    130.64

    1746.03

    5519.18

    772.68

    6291.86

    cum

    2120.00

    1146.33

    283.78

    92.40

    0.00

    0.00

    3642.51

    44.80

    8.23

    6.20

    12.41

    89.00

    160.64

    747.00

    141.70

    102.00

    37.91

    69.42

    774.00

    1872.03

    374.41

    2246.43

    3642.51

    160.64

    2246.43

    6049.58

    846.94

  • 8/2/2019 Building DATA

    12/23

    Amount

    6896.52

    cum

    2120.00

    1146.33

    283.78

    92.400.00

    0.00

    3642.51

    44.80

    8.23

    6.20

    12.41

    993.00

    1064.64

    795.00

    141.70

    102.00

    37.91

    69.42

    774.00

    1920.03

    384.01

    2304.03

    3642.51

    1064.64

    2304.03

    7011.18

    981.56

    7992.74

    cum

    2120.00

    1146.33

    283.78

    92.40

    0.00

    0.00

    3642.51

    44.80

    8.23

    44.80

    12.41

    1276.00

    1386.24

    795.00

    141.70

    102.00

  • 8/2/2019 Building DATA

    13/23

    Amount

    37.91

    69.42

    774.00

    1920.03

    384.01

    2304.03

    3642.511386.24

    2304.03

    7332.78

    1026.59

    8359.37

    cum

    2120.00

    1146.33

    283.78

    1528.44

    0.00

    0.00

    5078.55

    44.80

    8.23

    44.80

    12.41

    143.00

    253.24

    89.00

    141.70

    102.00

    37.91

    69.42

    774.00

    1214.03

    242.81

    1456.83

    5078.55

    253.24

    1456.83

    6788.62

    950.41

    7739.02

    46200.00

    330.00

  • 8/2/2019 Building DATA

    14/23

    Amount

    720.00

    1651.20

    48901.20

    6846.17

    55747.368

    55.74

    2544.00

    662.15

    0.00

    51.60

    3257.75

    488.66

    0.00

    205.20

    247.68

    941.54

    131.82

    1073.36

    107.33

    684.13

    311.22

    412.80

    1408.15

    197.14

    1605.29

    160.52

    79.9811.20

    91.18

  • 8/2/2019 Building DATA

    15/23

    Amount

    254.40

    1587.20

    126.12

    82.08

    174.72487.62

    2712.14

    379.70

    3091.84

    50.00

    5.00

    75.60

    82.56

    1.58

    213.16

    29.84

    243.00

    24.30

    243.00

    121.50

    364.50

    51.03

    415.53

    41.55

    1129.80

    114.48

    50.88

    75.67

    12.61

    1383.44

    273.60

    582.40

    709.50

  • 8/2/2019 Building DATA

    16/23

    Amount

    15.66

    313.10

    1894.26

    3277.70

    458.88

    3736.57

    373.66

    2173.52

    114.48

    150.00325.78

    130.31

    75.67

    0.00

    2969.76

    273.60

    582.40

    709.50

    15.66

    313.10

    1894.26

    4864.02

    680.96

    5544.98

    554.50

    2173.52

    75.67

    183.17

    174.90

    50.00

    0.00

    2657.26

    273.60

    582.40

  • 8/2/2019 Building DATA

    17/23

    Amount

    709.50

    15.66

    313.10

    1894.26

    4551.52

    637.21

    5188.73

    518.87

    168.01

    69.37

    101.76

    25.22

    215.46

    458.64

    1006.20

    2044.66

    286.25

    2330.92

    233.09

    2680.00

    375.20

    3055.20

    3777.40

    114.48

    174.90

    60.00

    75.67

    328.32

    698.88

    851.40

  • 8/2/2019 Building DATA

    18/23

    Amount

    18.79

    6099.84

    853.98

    6953.82

    695.38

    3740.00

    75.67

    305.28

    174.90

    180.00

    263.34249.60

    851.40

    13.64

    5853.84819.54

    6673.38

    667.34

    1250.00

    175.00

    1425.00

    r,

    ipality.

  • 8/2/2019 Building DATA

    19/23

    Sl. No. Description Source of supply Unit Lead(KM) Initial RateConveyanc

    e charges

    deduct 14%

    on

    conveyance

    Mpl. Area

    allowancesA

    1 2 3 4 5 6 7 8 91 Cost of Gravel Rajupalem 1Cum 15.00 80.00 158.50 -19.46 2

    Gravel - 15 km

    Upto 5 KM - 57.40

    5 to 15 KM - 86.00

    10x8.60

    143.4

    2 Sand for Mortor (including

    seigniorage charges)

    Amaravati1Cum 36.00 325.00 348.40 -42.78 6

    Sand - 36 km

    Upto 5 KM - 63.50

    5 to 30 KM - 237.50

    25x9.50

    30 to 36 KM - 47.40

    6x7.90

    315.6

    3 Sand for filling (including

    seigniorage charges)

    Amaravati1Cum 36.00 250.00 348.40 -42.78 5

    4 Coarse aggregate 9.5 - 4.75mm

    (including seigniorage charges)Perecherla 1Cum 23.00 520.00 234.50 -28.80 7

    5 Quarry dust (Chips 2.36mm

    &below)Perecherla 1Cum 23.00 255.00 234.50 -28.80 4

    Metal - 23 km

    Upto 5 KM - 63.50

    5 to 23 KM 18x9.50 -

    171.00

    234.50

    LEAD STATEMENT 2011-12

    SATTENAPALLE MUNICIPALITY

  • 8/2/2019 Building DATA

    20/23

    Sl. No. Description Source of supply Unit Lead(KM) Initial RateConveyanc

    e charges

    deduct 14%

    on

    conveyance

    Mpl. Area

    allowancesA

    1 2 3 4 5 6 7 8 9

    6 HBG Stone (Chips 2.36mm

    &below)Perecherla 1Cum 23.00 415.00 234.5 -28.80 6

    7 Aggregates of 40mm nominal size

    (including seigniorage charges) Perecherla 1Cum 23.00 745.00 234.50 -28.80 9

    8 Aggregates of 20mm nominal

    size(including seigniorage charges) Perecherla 1Cum 23.00 1175.00 234.50 -28.80 1

    9 Aggregates of 10mm nominal size

    (including seigniorage charges) Perecherla 1Cum 23.00 820.00 234.50 -28.80 1

    10 Aggregates of 6mm nominal size

    (including seigniorage charges) Perecherla 1Cum 23.00 655.00 234.50 -28.80 8

    11 Aggregates of 12.5mm nominal

    size(including seigniorage charges) Perecherla 1Cum 23.00 980.00 234.50 -28.80 1

    12 Niedle Vibrator 40mm (Petrol)Hour 6.00

    Rs.12.40

    for Fuel

    Rs. 102.00 for

    crew charges12 Niedle Vibrator 60mm (Petrol)

    Hour 6.20Rs.18.60

    for Fuel

    Rs. 102.00 for

    crew charges

    0.7 Cum 20MM 1380.70 966.49 0.50 Cum 40MM 950.70 4

    0.10 Cum 10MM 1025.70 102.57 0.30 Cum 20MM 1380.70 4

    0.10 Cum 6MM 860.70 86.07 0.2 Cum 10MM 1025.70 2

    0.10 Cum 12.5MM 1185.70 118.57

    1273.70 1

    Cum

    20MM 40 MM

  • 8/2/2019 Building DATA

    21/23

    Sl. No. Description Source of supply Unit Lead(KM) Initial RateConveyanc

    e charges

    deduct 14%

    on

    conveyance

    Mpl. Area

    allowancesA

    1 2 3 4 5 6 7 8 9

    13 Niedle Vibrator 60mm (Petrol)Hour 6.20

    Rs. 18.60

    for Fuel

    Rs. 102.00 for

    crew charges

    14 Water Tanker(6000) Hour 345.00 3

    15 Tipper 5 CumHour 351.30

    Rs.233.90

    for Fuel

    Rs. 111.20 for

    crew charges6

    16 Angle Dozer 90 HpHour 1256.70

    Rs.476.10

    for Fuel

    Rs.148.20 for

    crew charges1

    17 Concrete mixer 300/200 dieselHour 44.80

    Rs.61.90

    for Fuel

    Rs. 141.70 for

    crew charges2

    18 Concrete mixer 600/400 dieselHour 77.00

    Rs.123.80

    for Fuel

    Rs. 141.70 for

    crew charges 3

    19 Baching Plant 0.50 Cum(6 Cum/hr)Hour 91.00

    Rs.60.40

    for Fuel

    Rs.213.40 for

    crew charges 3

    20 Disel generating set 30 KVAHour 48.70

    Rs.495.00

    for Fuel

    Rs.85.00 for

    crew charges

    6

    21 Disel generating set 50 KVAHour 92.80

    Rs.742.50

    for Fuel

    Rs.85.00 for

    crew charges8

    22 Vibratory pad foot roller 8tHour 912.50

    Rs.804.40

    for Fuel

    Rs. 170.00 for

    crew charges1

    23 Cement local M.T 5300.00 5

    24 Steel local M.T 44000.00 44

    24 M.S. Flats local M.T 42000.00 42

    25 Bricks Second Class Local 1000 Nos 3100.00 3

    26 Binding wire local Kg 55.00

  • 8/2/2019 Building DATA

    22/23

    Sl. No. Description Source of supply Unit Lead(KM) Initial RateConveyanc

    e charges

    deduct 14%

    on

    conveyance

    Mpl. Area

    allowancesAmo

    1 2 3 4 5 6 7 8 9 1

    27 Water local KL 77.00 77

    28 Motor Grader Hour 2600.00 260

    29 Hydraulic Excavator Hour 2009.50 200

    30 Front end Loader Hour 1320.00 132

    31 Curing Compound ltr 95.00 95

    36 Mason 1st class Each 285.00 57.00 342

    37 Mason 2nd Class Each 260.00 52.00 312

    38 Mazdoor (Unskilled) Each 215.00 43.00 258

    39 Mate 260.00 52.00 312

    40 Surveyor 350.00 70.00 420

    41 Literate mazdoor 237.00 47.40 284

    42 Diesel ltr 38.50 38

    43 Petrol ltr 53.00 53

    Assistant Engineer, Commissioner,

    Sattenapalle Municipality. Sattenapalle Municipality.

    Dy. Executive Engineer

    Sattenapalle Municipality

  • 8/2/2019 Building DATA

    23/23

    63.5

    237.5

    47.4

    348.4