Building Construction Technology I Practical Session no. 2 02.03.2012 Who appoints who? - The Investor, (himself) - The Designer, (The Investor) - The main site Engineer, (The Contractor) - Project Manager / Manager of works, (The Investor) - The Contractor, (The Investor) - The main Contractor, (The Investor) - The construction site workers, (The Contractor) - The Inspection, (The Ministry) - The Supervisor, (The Investor) Who is responsible for? - To make the buildings comply with relevant regulations, ( The Project Manager ) - Informing investors, building inspection and other of any deficiencies or irregularities before and during construction, ( The Supervision Eng. ) - For the completeness and harmonization of works for mutual coherence of implementation the contractors, ( The main site Eng. )

Upload: hamdija-velagic

Post on 20-Dec-2014

501 views

Category:

Business


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Building Construction 2. rules and definition in construction

Building Construction Technology IPractical Session no. 202.03.2012

Who appoints who?

- The Investor, (himself)- The Designer, (The Investor)- The main site Engineer, (The Contractor)- Project Manager / Manager of works, (The Investor)- The Contractor, (The Investor)- The main Contractor, (The Investor)- The construction site workers, (The Contractor)- The Inspection, (The Ministry)- The Supervisor, (The Investor)

Who is responsible for?

- To make the buildings comply with relevant regulations, ( The Project Manager )- Informing investors, building inspection and other of any deficiencies or irregularities

before and during construction, ( The Supervision Eng. )- For the completeness and harmonization of works for mutual coherence of

implementation the contractors, ( The main site Eng. )- Coordinating the implementation of regulations governing safety and health of workers

during construction works, ( The main site Eng. )- Fencing / enclosing the construction site, ( The Contractor )- Issuing building permits ( The Ministry )- Issuing a solution/permit for removing buildings, ( The inspection )- Administrative supervision over the implementation of the Law on Spatial Planning and

the regulations issued under that act, ( The Ministry )- the legality of the actions of authorities and persons with public authorities relating to

the Spatial Planning and building, ( The Ministry )- Running the Construction dairy, ( Site engineer assistant )- Ensuring the needed machinery, ( the Contractor )- Maintaining the building during its lifetime, (The Investor)- Maintaining the building after its lifetime, (The customer )

Page 2: Building Construction 2. rules and definition in construction

Define the:

- Construction: (object created by constructing works, connected to ground, performed from building products with common installations and equipment, or integrated complex with facility or equipment as well as technical - technological units or solo installations connected to the ground. )

- Construction Works: (Performing constructional and other works (preparation, land, and structural, installation, finishing and mounting of construction products, plant or equipment) with which new buildings are built, existing buildings are reconstructed, removed or maintained. )

- Constructing: (the process of designing, constructing, usage and removal of the construction (building), everything that is related to the constructing of the new buildings can be applied in an appropiate way to reconstructing, maintance and removal of the old buildings. )

- Construction site: (is a place,land or buildings (including other areas that are temporarily occupied ) needed to execute the construction works or the application of appropriate building technology and security, on which to build, reconstruct, remove or perform maintenance work building).

- Maintenance of buildings: (Performing constructional and other works to preserve the essential requirements of a building during its lifetime, with which does not change the compliance with the conditions at the location of the building in accordance with

which it is built.)

Put these actions in order:

- Working permit (7)- Conceptual project (2)- Execution project (6)- Urban permit (3)- Use permit (9)- Appointing the main construction site engineer (8)- Appointing the designer (1)- Appointing the contractor (5)- Main project (4)

Construction site shall be marked with: (name 4 things or more)

- Name of investors, the designer, contractors and persons carrying out construction supervision

- Name and type of buildings that is being built - The name of the authority issuing the document upon which to build

Page 3: Building Construction 2. rules and definition in construction

- Classification code, register number, date of issue and validity of the act upon which to build

- An indication that it is a cultural property that is the national monument

Contractor on construction site must have: (name 8 things or more)

- The decision on registration in court register, or crafts license. - Approval for performing the construction and performance of and the contract on the

association contractors under special legislation. - Act on appointment of chief site engineer, site engineer and works manager. - Act on appointment of supervisor or principal supervisor. - A decision on building conditions, confirmation of the main project, or construction

permit from the conceptual or main project. - Performing projects with the opinion of chief designer of the project and certified by the

reviser that Requested it in a report on the control of the main projects requested , for the previously constructed part of the building , construction and other works that are in progress with all amendments.

- Reviser's report on completed inspection of the execution project if required.Construction Diary.

- Evidence of compliance for construction products installed. - Evidence of compliance by a special law for the installed equipment. - Identifications of Compliance for certain parts of certain construction essential. - Special requirements according to law and quality evidence that is requested by the law,

special regulation or project to collect during the execution of construction work and other commitments and implementation of control procedures for the previously constructed part of the building and construction and other works in progress.

- Survey project of the buildings. - Other documents, licenses and permits for which special regulations stipulates that the