Amount Item No Quantity Rate Bela Bela LDSD Offices SECTION 1 BILL NO. 1 PRELIMINARIES The JBCC Series 2000 Principal Building Agreement (July 2007 edition 5.0 - reprint 1) prepared by the Joint Building Contracts Committee shall be the applicable building agreement, amended as hereinafter described BUILDING AGREEMENT AND PRELIMINARIES The JBCC Principal Building Agreement Contract Data EC and the JBCC Principal Building Agreement Contract Data CE form an integral part of this agreement The ASAQS Preliminaries (November 2007 edition) published by the Association of South African Quantity Surveyors for use with the said JBCC Principal Building Agreement shall be deemed to be incorporated in these bills of quantities Contractors are referred to the abovementioned documents for the intent and meaning of each clause thereof These clauses are hereinafter referred to by clause number and heading only. Where standard clauses or alternatives are not entirely applicable to this agreement such modifications, corrections or supplements as will apply are given under each relevant clause heading and such modifications, corrections or supplements shall take precedence notwithstanding anything contrary contained in the abovementioned documents Where any item is not relevant to this specific agreement such item is marked N/A (signifying "not applicable") 133 Preliminaries Bill No. 1 Section 1 Carried to Collection R

Upload: others

Post on 11-Feb-2021

26 views

Category:

Documents


5 download

TRANSCRIPT

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 1

    BILL NO. 1

    PRELIMINARIES

    The JBCC Series 2000 Principal Building Agreement (July 2007 edition 5.0 - reprint 1) prepared by the Joint Building Contracts Committee shall be the applicable building agreement, amended as hereinafter described

    BUILDING AGREEMENT AND PRELIMINARIES

    The JBCC Principal Building Agreement Contract Data EC and the JBCC Principal Building Agreement Contract Data CE form an integral part of this agreement

    The ASAQS Preliminaries (November 2007 edition) published by the Association of South African Quantity Surveyors for use with the said JBCC Principal Building Agreement shall be deemed to be incorporated in these bills of quantities

    Contractors are referred to the abovementioned documents for the intent and meaning of each clause thereof

    These clauses are hereinafter referred to by clause number and heading only. Where standard clauses or alternatives are not entirely applicable to this agreement such modifications, corrections or supplements as will apply are given under each relevant clause heading and such modifications, corrections or supplements shall take precedence notwithstanding anything contrary contained in the abovementioned documents

    Where any item is not relevant to this specific agreement such item is marked N/A (signifying "not applicable")

    133

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    The Model Preambles for Trades (2008 edition) as published by the Association of South African Quantity Surveyors shall be deemed to be incorporated in these bills of quantities and no claims arising from brevity of description of items fully described in the said Model Preambles will be entertained

    PREAMBLES FOR TRADES

    Supplementary preambles are incorporated in these bills of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

    The contractor's prices for all items throughout these bills of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

    Should the contractor select Option A in terms of subclause 3.2.1 in the Contract Data - Contractor to Employer (CE) for the purpose of adjustment of these preliminaries, the amount entered into the amount column in these preliminaries is to be divided into one or more of the three categories provided namely Fixed (F), Value Related (V) and Time Related (T)

    PRICING OF PRELIMINARIES

    SECTION A: PRINCIPAL BUILDING AGREEMENT

    Item

    Clause 1.0 - Definitions and interpretation

    The measuring system used for the preparation of the bills of quantities is the Standard System of Measuring Building Work (sixth edition, revised 1999) published by the Association of South African Quantity Surveyors [1.1]

    F:............................. V:............................ T:............................

    1

    Definitions (A1)

    134

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 2.0 - Offer acceptance and performance obligations

    F:............................. V:............................ T:............................

    2

    Objective and preparation (A2 - A14)

    Item

    Clause 3.0 - Documents

    Refer to Annexure A for a list of the contract drawings

    Provision is made in the summary page of these bills of quantities for the inclusion of Value Added Tax (VAT) [3.5]

    The principal agent shall decide which portion of the priced document may be used as a specification of materials and goods or methods, if any [3.9]

    F:............................. V:............................ T:............................

    3

    Item

    Clause 4.0 - Design responsibility

    F:............................. V:............................ T:............................

    4

    Item

    Clause 5.0 - Employer's agents

    F:............................. V:............................ T:............................

    5

    Item

    Clause 6.0 - Contractor's site representative

    F:............................. V:............................ T:............................

    6

    135

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 7.0 - Compliance with laws and regulations

    Without limiting the generality of the provisions of clause 7.0, the contractor's attention is drawn to the provisionsof the Construction Regulations, 2003 issued in terms of the Occupational Health and Safety Act, 1993. It is specifically stated that the employer shall prepare a documented health and safety specification for the works and that the employer shall ensure that the contractor has made provision for the cost of health and safety measures during the execution of the works. The contractor shall price opposite this item for compliance with the act and the regulations and the reasonable provisions of the aforementioned health and safety specification [7.1]

    F:............................. V:............................ T:............................

    7

    Item

    Clause 8.0 - Works risk

    F:............................. V:............................ T:............................

    8

    Item

    Clause 9.0 - Indemnities

    F:............................. V:............................ T:............................

    9

    Item

    Clause 10.0 - General insurances

    F:............................. V:............................ T:............................

    10

    Item

    Clause 11.0 - Special insurances

    F:............................. V:............................ T:............................

    11

    Item

    Clause 12.0 - Effecting insurances

    F:............................. V:............................ T:............................

    12

    Item

    Clause 13.0 - Assignment

    F:............................. V:............................ T:............................

    13

    136

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 14.0 - Security

    F:............................. V:............................ T:............................

    14

    Item

    Clause 15.0 - Preparation for and execution of the works

    F:............................. V:............................ T:............................

    15

    Execution (A15 - A23)

    Item

    Clause 16.0 - Site and access

    Certain areas will be occupied during the construction period and the contractor must execute the works with as little noise and disturbance as possible to the occupants. [16.6]

    F:............................. V:............................ T:............................

    16

    Item

    Clause 17.0 - Contract instructions

    F:............................. V:............................ T:............................

    17

    Item

    Clause 18.0 -Setting out of the works

    The contractor shall notify the principal agent if any encroachment of adjoining foundations, buildings, structures, pavements, boundaries, etc. exist in order that the necessary arrangements may be made for the rectification of any such encroachments [18.1]

    F:............................. V:............................ T:............................

    18

    Item

    Clause 19.0 - Temporary works and plant

    Clause 19.1.1 - Enclosure of the works

    F:............................. V:............................ T:............................

    19

    Item

    Clause 19.1.2 - Office accommodation - provide suitable office accomodation for site meetings with tables and chairs for ten people

    F:............................. V:............................ T:............................

    20

    137

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 20.0 - Nominated subcontractors

    Refer to the provisions on general attendance hereinafter

    F:............................. V:............................ T:............................

    21

    Item

    Clause 21.0 - Selected subcontractors

    General attendance of n/s subcontractors for pricing by the contractor shall be in accordance with the n/s agreement. Notwithstanding this provision, general attendance shall be deemed to include for the contractor to provide free of charge to any n/s subcontractor such scaffolding as may reasonably be required by such n/s subcontractor for the execution of the relevant subcontract work

    F:............................. V:............................ T:............................

    22

    Item

    Clause 22.0 - Employer's direct contractors

    F:............................. V:............................ T:............................

    23

    Item

    Clause 23.0 - Contractor's domestic subcontractors

    F:............................. V:............................ T:............................

    24

    Item

    Clause 24.0 - Practical completion

    F:............................. V:............................ T:............................

    25

    Completion (A24 - A30)

    Item

    Clause 25.0 - Works completion

    F:............................. V:............................ T:............................

    26

    Item

    Clause 26.0 - Final completion

    F:............................. V:............................ T:............................

    27

    138

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 27.0 - Latent defects liability period

    F:............................. V:............................ T:............................

    28

    Item

    Clause 28.0 - Sectional completion

    F:............................. V:............................ T:............................

    29

    Item

    Clause 29.0 - Revision of date for practical completion

    The removal and replacement of materials and/or workmanship which do not conform to the specification or the contract drawings shall not constitute grounds for the extension of the construction period nor for the adjustment of the contract value (Clause 29.3)

    F:............................. V:............................ T:............................

    30

    Item

    Clause 30.0 - Penalty for late or non-completion: 0.05% of the Contract Amount inclusive of Value Added Tax per Calendar day

    F:............................. V:............................ T:............................

    31

    Item

    Clause 31.0 - Interim payment

    Materials and goods stored off site shall not be included in the amount authorised for payment [31.6.5]

    F:............................. V:............................ T:............................

    32

    Payment (A31 - A35)

    139

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    N/A

    Clause 32.0 - Adjustment to the contract value - NOT APPLICABLE

    All fluctuations in costs, with the exception of fluctuations in the rate of Value Added Tax, shall be for the account of the contractor [32.13]

    Where prices are submitted by the contractor or n/s subcontractor during the progress of the works in respect of contract instructions or in regard to a claim under the terms of the agreement and notwithstanding the fact that such prices may be used in an interim payment certificate there is to be no presumption of acceptance. Should the principal agent wish to accept any such prices prior to the issue of the certificate of final completion, it shall be in writing

    The contractor shall not receive any mark-up for overheads and profit on any omission of tenant installation work or tenant installation work by others. Claims for loss of profit shall not be entertained [32.2]

    F:............................. V:............................ T:............................

    33

    Item

    Clause 33.0 - Recovery of expense and loss

    F:............................. V:............................ T:............................

    34

    Item

    Clause 34.0 - Final account and final payment

    F:............................. V:............................ T:............................

    35

    Item

    Clause 35.0 - Payment to other parties

    F:............................. V:............................ T:............................

    36

    Item

    Clause 36.0 - Termination by employer - contractor's default

    F:............................. V:............................ T:............................

    37

    Termination (A36 - A39)

    140

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 37.0 - Termination by employer - loss and damage

    F:............................. V:............................ T:............................

    38

    Item

    Clause 38.0 - Termination by contractor - employer's default

    F:............................. V:............................ T:............................

    39

    Item

    Clause 39.0 - Termination - cessation of the works

    F:............................. V:............................ T:............................

    40

    Item

    Clause 40.0 - Settlement of disputes

    F:............................. V:............................ T:............................

    41

    Dispute (A40)

    Item

    Clause 41.0 - Post tender provisions

    The contractor is to complete and submit with his tender the JBCC Principal Building Agreement Contract Data CE

    F:............................. V:............................ T:............................

    42

    Contract variables (A41 - A42)

    Item

    Clause 42.0 - Contractual agreement

    The required information of the parties and the amount of the contract sum shall be inserted in the agreement for signature of the agreement by the parties

    F:............................. V:............................ T:............................

    43

    SECTION B: PRELIMINARIES

    141

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 1.0 - Definitions and interpretation

    F:............................. V:............................ T:............................

    44

    Definitions and interpretation (B1)

    Item

    Clause 2.1 - Checking of documents

    F:............................. V:............................ T:............................

    45

    Documents (B2)

    Item

    Clause 2.2 - Provisional bills of quantities

    F:............................. V:............................ T:............................

    46

    Item

    Clause 2.3 - Availability of construction documentation

    The budgetary allowances and selected subcontract amounts allocated for subsequent trades included in this agreement will be separately procured, based on multiple procurement of selected subcontractors during the construction period

    F:............................. V:............................ T:............................

    47

    Item

    Clause 3.1 - Previous work - dimensional accuracy

    F:............................. V:............................ T:............................

    48

    Previous work and adjoining properties (B3)

    Item

    Clause 3.2 - Previous work - defects

    F:............................. V:............................ T:............................

    49

    Item

    Clause 3.3 - Inspection of adjoining properties

    F:............................. V:............................ T:............................

    50

    142

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 4.1 - Samples of materials

    F:............................. V:............................ T:...........................

    51

    Samples, shop drawings and manufacturer's instructions (B4)

    Item

    Clause 4.2 - Workmanship samples

    F:............................. V:............................ T:............................

    52

    Item

    Clause 4.3 - Shop drawings

    F:............................. V:............................ T:............................

    53

    Item

    Clause 4.4 - Compliance with manufacturer's instructions

    F:............................. V:............................ T:............................

    54

    Item

    Clause 5.1 - Deposits and fees

    F:............................. V:............................ T:............................

    55

    Deposits and fees (B5)

    Item

    Clause 6.1 - Water

    F:............................. V:............................ T:............................

    56

    Temporary services (B6)

    Item

    Clause 6.2 - Electricity

    F:............................. V:............................ T:............................

    57

    Item

    Clause 6.3 - Telecommunication facilities

    F:............................. V:............................ T:............................

    58

    Item

    Clause 6.4 - Ablution facilities

    F:............................. V:............................ T:............................

    59

    143

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 7.1 - Responsibility for prime cost amounts

    F:............................. V:............................ T:............................

    60

    Prime cost amounts (B7)

    Item

    Clause 8.1 - Special attendance

    F:............................. V:............................ T:............................

    61

    Special attendance on n/s subcontractors (B8)

    Item

    Clause 9.1 - Protection of the works

    F:............................. V:............................ T:............................

    62

    General (B9)

    Item

    Clause 9.2 - Protection/isolation of existing/ occupied works

    Certain areas of the sitewill be occupied during the construction period (see item 4 page 14)

    F:............................. V:............................ T:............................

    63

    Item

    Clause 9.3 - Security of the works

    F:............................. V:............................ T:............................

    64

    Item

    Clause 9.4 - Notice before covering work

    F:............................. V:............................ T:............................

    65

    Item

    Clause 9.5 - Disturbance

    F:............................. V:............................ T:............................

    66

    Item

    Clause 9.6 - Environmental disturbance

    F:............................. V:............................ T:............................

    67

    144

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Clause 9.7 - Works cleaning and clearing

    F:............................. V:............................ T:............................

    68

    Item

    Clause 9.8 - Vermin

    F:............................. V:............................ T:............................

    69

    Item

    Caluse 9.9 - Overhand work

    F:............................. V:............................ T:............................

    70

    Information necessary for elections and completion of those clauses contained in the schedule which are necessary for tender purposes is given hereunder. Where no information is given it shall mean that no specific requirements are expected or that the clause is not relevant to this specific contract

    Schedule of variables (B10)

    10.1 - Provisional bills of quantities [2.2] The quantities are provisional No

    10.2 - Availability of construction documentation [2.3] Construction documentation is complete Yes

    10.3 - Previous work - dimensional accuracy [3.1]

    10.4 - Previous work - defects [3.2]

    10.5 - Inspection of adjoining properties [3.3]

    10.6 - Water [7.2]

    Option A (by contractor) YesOption B (by employer - free of charge) NoOption C (by employer - metered) No

    145

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    10.7 - Electricity [7.3]

    Option A (by contractor) YesOption B (by employer - free of charge) NoOption C (by employer - metered) No

    10.8 - Telecommunications [7.4]

    Telephone YesFacsimile YesE-mail Yes

    10.9 - Ablution facilities [7.5]

    Option A (by contractor) YesOption B (by employer) No

    10.10 - Protection of the works [9.1]

    10.11 - Protection/isolation of existing/sectionally occupied works [9.2]

    Protection/isolation is requiredNo

    10.12 - Disturbance [9.5]

    10.13 - Environmental disturbance [9.6]

    Any special items to meet the particular circumstances of a specific project are embodied in this section. Where required for an aspect of the works to be executed according to a design by a consulting engineer, a recital of the headings to the individual clauses of the JBCC Engineering General Conditions are included

    SECTION C: SPECIFIC PRELIMINARIES

    146

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Black economic empowerment and training

    F:............................. V:............................ T:............................

    71

    Item

    Proprietary branded products

    F:............................. V:............................ T:............................

    72

    The contractor shall take delivery of, handle, store, use, apply and/or fix all proprietary branded products in strict accordance with the manufacturers' instructions after consultation with the manufacturer's authorised representative

    Item

    Contract instructions

    F:............................. V:............................ T:............................

    73

    Contract instructions issued on site are to be recorded in triplicate in a contract instruction book which is to be supplied and maintained on site by the contractor

    Item

    Labour record

    F:............................. V:............................ T:............................

    74

    At the end of each week the contractor shall provide the principal agent with a written record, in schedule form, reflecting the number and descriptions of tradesmen and labourers employed by him and all subcontractors on the works each day of that week

    Item

    Plant record

    F:............................. V:............................ T:............................

    75

    At the end of each week the contractor shall provide the principal agent with a written record, in schedule form, reflecting the number, type and capacity of all plant, excluding hand tools used on the works each day of that week

    147

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Guarantees

    F:............................. V:............................ T:............................

    76

    Where guarantees are called for, the contractor shall obtain a written guarantee, addressed to the employer, from the firm supplying the materials and/or doing the work and shall deliver same to the principal agent on the certified completion of the contract. The guarantee shall state that workmanship, materials and installation are guaranteed for a specified period from the date of certified completion of the contract, and that any defects that may arise during the specified period shall be made good at the expense of the firm supplying the materials and/or doing the work, upon written notice from the principal agent to do so. This guarantee will not be enforced if the work is damaged by defects in the construction of the building in which case the responsibility for replacement shall rest entirely with the contractor. The principal agent shall be the sole judge of the cause responsible for defects in the work and his decision shall be final and binding in terms of clause 40.2 of the agreement

    Item

    Overtime

    F:............................. V:............................ T:............................

    77

    Should overtime be required to be worked for any reason whatsoever, the costs of such overtime are to be borne by the contractor unless the principal agent has specifically authorised, in writing, prior to execution thereof, that costs for such overtime are to be borne by the employer

    Item

    Co-operation of contractor for cost management

    F:............................. V:............................ T:............................

    78

    148

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    It is specifically agreed that the contractor accepts the obligation of assisting the professional consultants in implementing proper cost management. The contractor will be advised by the principal agent of all cost management procedures which will be implemented to ensure that the final building cost does not exceed the budget. The quantity surveyor undertakes to make available to the contractor all budgetary allowances and cost assessments/reports to enable the proper procedures to be implemented and the contractor will attend all cost plan review and cost management meetings. The contractor undertakes to extend these procedures in regard to all subcontractors

    Item

    Occupational Health and Safety Specification

    F:............................. V:............................ T:............................

    79

    The contractor shall comply with all the requirements set out in the Construction Regulations 2003 issued under the Occupational Health and Safety Act, 1993 (Act No 85 of 1993).

    It is required of the contractor to thoroughtly study the Health and Safety Specification that must be read together with and is deemed to be incorporated under this Section of the bills of quantities / lump sum document.

    The contractor must take note that compliance with the Occupational Health and Safety Act, Construction Regulations and Health and Safety Specification is compulsory. In the event of parial or total non-compliance, the principal agent, notwithstanding the provisions of clause A31.0 of Section A or any other clause to the contrary, reserves the right to delay issuingany progress payment certificate until the contractor provides satifactory proof of compliance. The contractor shall not be entitled to any compensation of whatsoever nature, including extension of time or interest, due to such delay of payment.

    Provisions for pricing of the Occupational Health and Safety Act, Construction Regulations and Health and Safety Specification is made under this clause and it is explicitly pointed out that all requirements of the aforementioned are deemed to be priced hereunder and no additional claims in this regard shall be entertained.

    149

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Allow for the compulsory equipment and clothing, ie hats, safety shoes, safety clothing, safety glasses, safety masks, harnesses, etc

    F:............................. V:............................ T:............................

    80

    Item

    Allow for all compulsory health and safety posters, boards, etc

    F:............................. V:............................ T:............................

    81

    Item

    Allow for all compulsory health and safety workshops, meetings, lectures, demonstrations, etc

    F:............................. V:............................ T:............................

    82

    Item

    Allow for all compulsary health and safety pamphlets, cards, paperwork, etc to each worker, consultant, public individual, etc coming onto the site

    F:............................. V:............................ T:............................

    83

    Item

    Allow for compulsory health and safety files that must be completed daily and must be handed to the employer on completion of the contract

    F:............................. V:............................ T:............................

    84

    Item

    Scope of Application as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    85

    150

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Notification of Construction Work as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    86

    Item

    Employer's responsiblities as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    87

    Item

    Principal Contractor's responsibility as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    88

    Item

    Supervision of construction work as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    89

    Item

    Risk assessment as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    90

    Item

    Fall protection as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    91

    151

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Structures Formwork and Support as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    92

    Item

    Excavation as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    93

    Item

    Demolotion work as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    94

    Item

    Tunnelling as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    95

    Item

    Scaffolding as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    96

    Item

    Suspended platforms as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    97

    152

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Botswains chairs as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    98

    Item

    Materials hoists as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    99

    Item

    Batch plant as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    100

    Item

    Explosive powered tools as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    101

    Item

    Cranes as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    102

    Item

    Construction vehicles and mobile plant as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    103

    153

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Electrical installations and machinery on construction sites as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    104

    Item

    Use and temporary storage of flammable liquids on construction sites as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    105

    Item

    Water environments as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    106

    Item

    Housekeeping on construction sites as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    107

    Item

    Stacking and storage on construction sites as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    108

    Item

    Fire precautions as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    109

    154

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Construction welfare as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    110

    Item

    Approved inspection Authorities as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    111

    Item

    Offences and penalties as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    112

    Item

    Repeal of regulations as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    113

    Item

    Short title as per Act No 85 of 1993

    F:............................. V:............................ T:............................

    114

    Item

    Obligatory Sub-contracting and Training

    F:............................. V:............................ T:............................

    115

    155

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    The Contractor shall sub-contract 40% of the work to Domestic Sub-contractors as listed in the Schedule of Sub-Contractors in the Returnable Schedules

    The Principal Agent and the Contractor shall at all times make sure that the work complies with the relevant specifications, standards and norms as contained in this tender.

    The Principal Agent and the Contractor shall provide for the necessary skills transfer and assistance to complete the sub-contracted section of the works.

    The Principal Agent and the Contractor shall provide the necessary documentation to the Domestic Sub-Contractor for upgrading of the rating by CIDB.

    BEE Sub-Contractors must be 100% black owned and have offices in Mpumalanga Province

    Item

    Expanded Public Works Programme

    F:............................. V:............................ T:............................

    116

    The Contractor shall study the guidelines for the implimentation of labour-intensive infrastructure projects under the Expanded Public Works Programme (EPWP) attached to this document. The Contractor shall take note of the requirements and inform all selected and or other sub-contractors, as no claim afterwards will be entertained

    Item

    C11.1 Local and targeted labour

    F:............................. V:............................ T:............................

    117

    Item

    Allow for regular submission of proof of employment of local skilled and unskilled labour to Employer's representative

    F:............................. V:............................ T:............................

    118

    156

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Training allowance paid to targeted labour in respect of formal training.

    F:............................. V:............................ T:............................

    119

    Item

    Extra over for the administration of payment of training allowances to targeted labour

    F:............................. V:............................ T:............................

    120

    Item

    Transport and accommodation of workers for training where it is not possible to undertake the training in close proximity to the site

    F:............................. V:............................ T:............................

    121

    Item

    C12: Contract drawings

    F:............................. V:............................ T:............................

    122

    The drawings issued with the tender documents do not comprise the complete set but serve as a guide only for tendering purposes and for indicating the scope of the work to enable the tenderer to acquaint himself with the nature and extent of the works and the manner in which they are to be executed

    Should any part of the drawings not be clearly understood by the tenderer he shall, before submitting his tender, obtain clarification in writing from the principal agent

    Item

    C13: General preambles

    F:............................. V:............................ T:............................

    123

    157

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    C14: Trade names

    F:............................. V:............................ T:............................

    124

    Wherever a trade name form any product has been described in the bills of quantities / lump sum document, the tenderer's attention is drawn to the fact that any other product of equal quality may be used subject to the written approval of the principal agent being obtained prior to the closing date for submission of tenders

    If prior written approval for an alternative product is not obtained, the product described shall be deemed to have been tendered for

    Item

    C15: Community Liaison Officer

    F:............................. V:............................ T:............................

    125

    Item

    Allow for a Community Liaison Officer (CLO) to be appointed

    F:............................. V:............................ T:............................

    126

    Item

    Allow for net extra cost involved in the emloyment of a Community Liaison Officer (CLO) in respect of the site office.

    F:............................. V:............................ T:............................

    127

    Item

    Allow for net extra cost involved in the employment of a Community Liaison Officer (CLO) in respect of the toilets.

    F:............................. V:............................ T:............................

    128

    158

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • Bela Bela LDSD Offices

    Item

    Allow for net extra cost involved in the employment of a Community Liaison Officer (CLO) in respect of the sheds.

    F:............................. V:............................ T:............................

    129

    Item

    C16: SANS 1921-6: HIV/AIDS Awareness read in conjunction with the Associated Specification Data

    F:............................. V:............................ T:............................

    130

    Item

    General requirements (Clause 4.1)

    F:............................. V:............................ T:............................

    131

    Item

    HIV/AIDS awareness programme (Clause 4.2)

    F:............................. V:............................ T:............................

    132

    Item

    Reporting (Clause 4.3)

    F:............................. V:............................ T:............................

    133

    Category : Fixed R........................................

    Category : Value R........................................

    Category : Time R........................................

    SUMMARY OF CATEGORIES

    159

    PreliminariesBill No. 1Section 1

    Carried to Collection R

  • 154

    153

    152

    151

    150

    149

    148

    147

    146

    145

    144

    143

    142

    141

    140

    139

    138

    137

    136

    135

    134

    133Total Brought Forward from Page No.

    Preliminaries

    Section 1

    Bill No. 1

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    160

    PreliminariesBill No. 1Section 1

    Carried Forward R

  • Preliminaries

    Section 1

    Bill No. 1

    AmountPageNo

    COLLECTION

    Brought Forward R

    Bela Bela LDSD Offices

    159

    158

    157

    156

    155Total Brought Forward from Page No.

    161

    PreliminariesBill No. 1Section 1

    Carried to Final Summary R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BUILDINGS

    BILL NO. 1

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 104 for CPAP formula purposes

    FOUNDATIONS (PROVISIONAL)

    SUPPLEMENTARY PREAMBLES

    The nature of the ground is assumed to be loose sandy material, therefore "earth", but possibly interspersed with "hard rock" or "soft rock"

    Nature of ground

    Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site

    Carting away of excavated material

    EARTHWORKS

    SITE CLEARANCE ETC

    2,748m2

    Digging up and removing rubbish, debris, vegetation, hedges, shrubs and trees not exceeding 200mm girth, bush, etc

    1

    Site clearance

    2,748m2Stripping average 150mm thick layer of top soil and stockpiling on site

    2

    EXCAVATION, FILLING, ETC

    655m3Reduced level3

    Excavation in earth not exceeding 2m deep

    162

    Foundations (Provisional)Bill No. 1Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    487m3Trenches4

    37m3Holes5

    28m3Soft rock6

    Extra over trench and hole excavations in earth for excavation in

    15m3Hard rock7

    989m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor

    8

    Extra over all excavations for carting away

    1,539m2Sides of trench and hole excavations not exceeding 1,5m deep

    9

    Risk of collapse of excavations

    ItemKeeping excavations free of all water other than subterranean water

    10

    Keeping excavations free of water

    402m3Under floors, steps, pavings, etc11

    Earth filling obtained from the excavations and/or prescribed stock piles on site compacted to 93% Mod AASHTO density

    306m3Backfilling to trenches, holes, etc12

    640m3Under floors, steps, pavings, etc13

    Earth filling of G6 material supplied by the contractor compacted in 150mm layers to 95% Mod AASHTO density

    68m3Under floors, steps, pavings, etc14

    Earth filling of G6 material supplied by the contractor, stabilized with 3% cement (CEM II B-L 32.5N) to achieve a C4 classification compacted in 150mm layers to 95% Mod AASHTO density

    1,247m2Under floors etc15

    Coarse river sand filling supplied by the contractor

    163

    Foundations (Provisional)Bill No. 1Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    SOIL POISONING

    1,453m2

    Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming

    16

    Soil insectiside

    1,885m2To bottoms and sides of trenches17

    CONCRETE

    (CPAP FORMULA WORK GROUP NO. 110)

    UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

    22m3Surface blinding under footings and bases18

    15MPa/19mm concrete

    REINFORCED CONCRETE

    REINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

    7m3Strip footings19

    25MPa/19mm concrete

    12m3Bases20

    1m3Columns21

    40MPa/19mm concrete

    101m3Beams22

    36NoMaking and testing 150 x 150 x 150mm concrete strength test cube (Provisional)

    23

    TEST BLOCKS

    ROUGH FORMWORK (DEGREE OF ACCURACY II)

    164

    Foundations (Provisional)Bill No. 1Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    208mEdges, risers, ends and reveals not exceeding 300mm high or wide (Provisional)

    24

    Rough formwork to sides

    34m2Column bases25

    Rough formwork to soffits

    24m2Vertical sides of columns26

    REINFORCEMENT

    (CPAP FORMULA WORK GROUP NO. 114)

    1.61t8mm Diameter bars 27

    Mild steel reinforcement to structural concrete work

    5.29t10mm Diameter bars 28

    High tensile steel reinforcement to structural concrete work

    12.95t12mm Diameter bars29

    12.88t16mm Diameter bars 30

    MOVEMENT JOINTS, ETC

    224m12mm Joints not exceeding 300mm high31

    Expansion joints with softboard between vertical concrete surfaces

    BRICKWORK

    (CPAP FORMULA WORK GROUP NO. 116)

    109m2One brick walls32

    Brickwork of NFX bricks (14 MPa nominal compressive strength) in class I mortar

    545m150mm Wide reinforcement built in horizontally33

    Brickwork reinforcement

    FACE BRICKWORK

    165

    Foundations (Provisional)Bill No. 1Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    100m2Extra over brickwork for face brickwork34

    External face bricks (Prime Cost Amount R 3 500.00/1000) pointed with flush horizontal and vertical joints

    166

    Foundations (Provisional)Bill No. 1Section 2

    Carried to Collection R

  • Foundations (Provisional)

    Section 2

    Bill No. 1

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    166

    165

    164

    163

    162Total Brought Forward from Page No.

    167

    Foundations (Provisional)Bill No. 1Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 2

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 110 for CPAP formula purposes

    CONCRETE, FORMWORK AND REINFORCEMENT

    SUPPLEMENTARY PREAMBLES

    The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SABS 1200 G shall include the cost of providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests to the Principal Agent. The testing shall be undertaken by an independent firm or institution nominated by the contractor to the approval of the Principal Agent. (Test cubes are measured separately)

    Cost of tests

    Description of formwork shall be deemed to include use and waste only (except where described as "left in" or "permanent"), for fitting together in the required forms, wedging, plumbing and fixing to true angles and surfaces as necessary to ensure easy release during stripping and for reconditioning as necessary before re-use

    Formwork

    The vertical strutting shall be carried down to such construction as is sufficiently strong to afford the required support without damage and shall remain in position until the newly constructed work is able to support itself.

    Formworks to soffits of solid etc shall be deemed to be slabs not exceeding 250mm thick unless otherwise described

    168

    Concrete, Formwork and ReinforcementBill No. 2Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    Formwork to sides of bases, pile caps, ground beams, etc will only be measured where it is prescribed by the engineer for design reasons. Formwork necessitated by irregularity or collapse of excavated faces will not be measured and the cost thereof shall be deemed to be included in the allowance for taking the risk of collapse of the sides of the excavations, provision for which is made in "Earthworks"

    UNREINFORCED CONCRETE

    2m3Steps, urinal steps, cupboard platforms, etc1

    25MPa/19mm concrete

    REINFORCED CONCRETE

    1m3Vanity slabs, cupboard slabs, cover slabs, etc2

    25MPa/19mm concrete

    185m3Surface beds on waterproofing3

    30MPa/19mm concrete

    41m3Ramps, Aprons, etc4

    15m3Roof slab5

    20m3Roof beams and inverted beams6

    2m3Walls7

    7m3Isolated beams8

    3m3Concrete benches/planter9

    6m3Columns10

    40MPa/19mm concrete

    20NoMaking and testing 150 x 150 x 150mm concrete strength test cube (Provisional)

    11

    TEST BLOCKS

    CONCRETE SUNDRIES

    169

    Concrete, Formwork and ReinforcementBill No. 2Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    19m2Vanity slabs, cupboard slabs, cover slabs, etc12

    Finishing top surfaces of concrete smooth with a steel trowel including rounding edges to form a bullnose finish

    410m2Ramps, slabs, etc to falls13

    Finishing top surfaces of concrete smooth with a wood float

    SMOOTH FORMWORK (DEGREE OF ACCURACY II)

    (CPAP FORMULA WORK GROUP NO. 111)

    19m2Vanity slabs, cupboard slabs, cover slabs, etc. propped up not exceeding 1500mm high

    14

    Smooth formwork to

    12mEdges, risers, ends and reveals not exceeding 300mm high

    15

    Smooth formwork to sides

    ROUGH FORMWORK (DEGREE OF ACCURACY II)

    219mEdges, risers, ends and reveals not exceeding 300mm high or wide (Provisional)

    16

    Rough formwork to sides

    90m2Slabs propped up exceeding 3,5m and not exceeding 5,0m high

    17

    Rough formwork to soffits

    20m2Vertical sides of walls18

    66m2Sides and soffit of isolated beams19

    217m2Vertical sides and soffit of beams20

    16m2Sides of concrete benches/planter21

    34m2Vertical sides of circular columns22

    Smooth formwork to

    170

    Concrete, Formwork and ReinforcementBill No. 2Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    MOVEMENT JOINTS ETC

    563mNot exceeding 300mm wide23

    Slip joint formed of two layers 375micron embossed damp proof courses between horizontal concrete and brick surfaces including cement mortar bed

    1,052m10mm Joints not exceeding 300mm high24

    Expansion joints with closed cell expanded polystirene joint filler between vertical concrete surfaces

    629m10mm Joints not exceeding 300mm high25

    Expansion joints with closed cell expanded polystirene joint filler between vertical concrete and/or brick surfaces

    892m3 x 30mm Saw cut joints in two operations in top of concrete

    26

    Saw cut joints

    REINFORCEMENT (PROVISIONAL)

    (CPAP FORMULA WORK GROUP NO. 114)

    1.10t8mm Diameter bars 27

    Mild steel reinforcement to structural concrete work

    1.48t20mm Diameter bars 28

    High tensile steel reinforcement to structural concrete work

    1.84t16mm Diameter bars 29

    2.21t12mm Diameter bars30

    0.74t10mm Diameter bars 31

    1,235m2Type 395 fabric reinforcement in concrete surface beds, slabs, etc

    32

    Fabric reinforcement

    222m2Type 193 fabric reinforcement in concrete surface beds, slabs, etc

    33

    171

    Concrete, Formwork and ReinforcementBill No. 2Section 2

    Carried to Collection R

  • Concrete, Formwork and Reinforcement

    Section 2

    Bill No. 2

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    171

    170

    169

    168Total Brought Forward from Page No.

    172

    Concrete, Formwork and ReinforcementBill No. 2Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 3

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 116 for CPAP formula purposes

    MASONRY

    SUPPLEMENTARY PREAMBLES

    BRICKWORK

    Where sizes in descriptions are given in brick units, "one brick" shall represent the length and "half brick" the width of a brick

    Sizes in descriptions

    Bricks shall be ordered timeously to obtain uniformity in size and colour

    Face bricks

    Descriptions of recessed pointing to fair face brickwork and face brickwork shall be deemed to include square recessed, hollow recessed, weathered pointing, etc.

    Pointing

    SUPERSTRUCTURE

    501m2Half brick walls1

    Brickwork of NFP bricks in class II mortar

    72m2One brick walls in beamfilling2

    725m2One brick walls3

    532m2280mm cavity wall4

    196m2345mm brick walls5

    BRICKWORK SUNDRIES

    173

    MasonryBill No. 3Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    2,315m75mm Wide reinforcement built in horizontally6

    Brickwork reinforcement

    5,722m150mm Wide reinforcement built in horizontally7

    1,197m225mm Wide reinforcement built in horizontally8

    64m110 x 75mm Lintels in lengths not exceeding 3m9

    Prestressed fabricated lintels

    113m110 x 75mm Lintels in lengths exceeding 4.5m and not exceeding 6,0m

    10

    236m230 x 75mm Lintels in lengths not exceeding 3m11

    20m330 x 75mm Lintels in lengths exceeding 4.5m and not exceeding 6,0m

    12

    233No30 x 1,6mm Roof tie 1,5m long with one end fixed to timber and other end built into brickwork

    13

    Galvanised hoop iron cramps, ties, etc

    FACE BRICKWORK

    1,273m2Extra over brickwork for face brickwork14

    External face bricks (Prime Cost Amount R 5 000.00/1000) pointed with flush horizontal and vertical joints

    WINDOW SILLS

    330m180mm Wide sill set sloping and slightly projecting15

    Brick-on-edge header course copings, sills, etc with wood float plaster pointed with flush joints on all exposed faces

    174

    MasonryBill No. 3Section 2

    Carried to Collection R

  • Masonry

    Section 2

    Bill No. 3

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    174

    173Total Brought Forward from Page No.

    175

    MasonryBill No. 3Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 4

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 120 for CPAP formula purposes

    WATERPROOFING

    DAMP-PROOFING OF WALLS AND FLOORS

    32m2In walls1

    One layer of 375 micron "Consol Plastics Brikgrip DPC" embossed damp proof course

    1,247m2Under surface beds2

    One layer of 250 micron "Consol Plastics Gunplas USB Green" waterproof sheeting sealed at laps with "Gunplas Pressure Sensitive Tape"

    JOINT SEALANTS, ETC

    1,000m5 x 40mm In saw cut joints in floors3

    "Denbraven LM15" polysulphide sealing compound including backing cord, bond breaker, primer, etc

    176

    WaterproofingBill No. 4Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 5

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 124 for CPAP formula purposes

    ROOF COVERINGS ETC

    Where roof coverings are fixed on top of rigid board insulation to purlins, etc. descriptions of roof coverings are to include therefor.

    PROFILED METAL SHEETING AND ACCESSORIES

    1,174m2Roof covering with pitch not exceeding 25 degrees1

    0,6mm "Kliplok" roof sheeting or equally approved, on timber purlins in strict accordance to manufacturer's specification on timber roof structure and structural engineer's detail

    318mFlashing to edges of sheeting and sides of parapet2

    375m2Roof covering with pitch not exceeding 25 degrees3

    0,6mm "Kliplok" roof sheeting or equally approved, on steel purlins in strict accordance to manufacturer's specification on timber roof structure and structural engineer's detail

    62mFlashing to edges of sheeting and sides of parapet4

    ROOF AND WALL INSULATION

    "Sisalation FR430" fire retardant aluminium foil insulation

    1,550m2

    Insulation laid taut over rafters (at approximately 1 200mm centres) and fixed concurrent with battens, purlins, etc

    5

    "Sisalation 410" housing grade glass fibre reinforced aluminium foil bonded insulation

    177

    Roof Coverings, etcBill No. 5Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 6

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No.126 for CPAP formula purposes

    CARPENTRY AND JOINERY

    SUPPLEMENTARY PREAMBLES

    Particle board shall comply with the following specifications:

    a) SABS 1300 Particle board: exterior and flooring type

    b) SABS 1301 Particle board: interior type

    Particle board:

    Descriptions of frames shall be deemed to include frames, transoms, mullions, rails, etc

    Joinery:

    Descriptions of hardwood joinery shall be deemed to include pelleting of bolt holes

    Items described as "nailed" shall be deemed to be fixed with hardened steel nails or shot pins to brickwork or concrete

    Fixing

    Laminate finish shall be glued under pressure. Edge strips shall be butt jointed at junctions with adjacent similar finish

    Decorative laminate finish:

    ROOFS, ETC

    178

    Carpentry and JoineryBill No. 6Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    The following is applicable in respect of roof trusses:

    Trusses are at maximum 1,04m centres

    Roof covering is galvanised IBR roof sheeting on 50 x 75mm purlins at 1,2m maximum centres.

    Ceilings are generally 6,4mm gypsum plasterboard on 38 x 38mm brandering.

    All timber to be sawn softwood in accordance with V4 or M4 as defined in SABS 563 or SABS 1245.

    Metal connector plates shall have a minimum yield strength of 228 MPa and a minimum ultimate tensile strength of 330 Mpa with hot-dip galvanised finish.

    All joints to be close fitted butt joints.

    Trusses shall be designed by a registered supplier of prefabricated trusses who shall issue an Engineers Certificate upon completion of the installation. The dimensions in the descriptions of the trusses are nominal and actual measurements are to be obtained onsite before design or fabricaton commences.

    Plate nailed timber roof truss construction

    167m38 x 114mm Wall plates1

    Sawn softwood

    2No

    Design, manufacture and deliver on site, plate nailed roof truss construction to Office building, size 36 780 x 11 110mm overall on plan consisting of thirty six double pitched trusses, each truss 11 110 x 2 050mm high overall with 800 and 1000mm eaves overhang projecting both sides respectively, including all necessary purlins, runners, bracing and cross bracing (wall plates elsewhere)

    2

    1No

    Design, manufacture and deliver on site, plate nailed roof truss construction to guard house, size 4 690 x 2 830mm overall on plan consisting of six mono pitched trusses, each truss 2 830 x 1 450mm high overall with 600mm eaves overhang projecting both sides respectively, including all necessary purlins, runners, bracing and cross bracing (wall plates elsewhere)

    3

    179

    Carpentry and JoineryBill No. 6Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    24m2

    Take delivery, temporary store, hoist in position and erect plate nailed timber roof trusses, purlins, gangboarding, temporary and permanent bracing, etc (measured on slope of roof)

    4

    6m2Two coats creosote on sawn timbers5

    Sundries

    EAVES , VERGES , ETC

    20m12 x 225mm Fascias and barge boards including galvanised steel H-profile jointing strips

    6

    "Everite Flexit" pressed nutec-cement

    SKIRTINGS

    16m19 x 76mm Skirting including 19mm quadrant bead nailed

    7

    Wrought meranti

    DOORS ETC

    26No40 mm door size, 813 x 2400mm high8

    Interior grade flush semi solid core timber single door with 3mm thick commercial ply on both sides with consolidated edges fitted and complying with SABS 545

    1No40 mm door size, 1500 x 2400mm high9

    2No40 mm door size, 900 x 2400mm high10

    5No40mm door size, 813 x 2400 mm high with aluminium door grill as per drawing 703 rev A

    11

    6No

    40 mm door size, 813 x 2400mm high including kick plate as per drawing number 703 rev A

    12

    4No

    40 mm door size, 900 x 2400mm high including kick plate and vertical grab rail as per drawing number 703 rev A

    13

    180

    Carpentry and JoineryBill No. 6Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    3No

    Lotus Amoretti Michaelangelo collection 40mm thick horizontal 813 meranti door with horizontal slats, size 813 x 2032mm high

    14

    PANEL DOORS

    1NoAcoustic panel door size, 8675 x 3230 mm high15

    Acoustic panel door to supplier specification

    181

    Carpentry and JoineryBill No. 6Section 2

    Carried to Collection R

  • Carpentry and Joinery

    Section 2

    Bill No. 6

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    181

    180

    179

    178Total Brought Forward from Page No.

    182

    Carpentry and JoineryBill No. 6Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 7

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 129 for CPAP formula purposes

    CEILINGS, PARTITIONS AND ACCESS FLOORING

    SUPPLEMENTARY PREAMBLES

    Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins or shot pinned to brickwork or concrete

    Descriptions:

    Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres, and where described as "bolted" the bolts have been given elsewhere

    CEILINGS ETC

    962m275mm Insulation closely fitted and laid on top of brandering between roof timbers etc

    1

    "Aerolite" insulation

    CEILINGS

    54m2

    9.5mm Rhino Plasterboard tapered edged ceiling boards secured to a DONN Suspended hidden T-Steel Grid suspended from concrete slab with 25 x 25 metal angle hangers all as per manufacturers requirements. Boards installed with printed side up and all joints to be taped with Rhino tape and scimmed with Rhinolite or cretestone plaster all in accordance with manufacturers instruction to ensure a smooth unblemished ceiling surface edged with a prepainted shadowline cornice.

    2

    Ceiling Type A

    183

    Ceilings, Partitions and Access FlooringBill No. 7Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    43m2

    GYPREX FISSURED 600 x 600 x 12.5mm thick LAYIN Ceiling tiles on a DONN EXPOSED GRID (T38) with cappings of prepainted Aluminium Grid Suspended from concrete or trusses with metal hangers all as per manufacturers requirements. Ceiling edged with a prepainted shadowline cornice

    3

    Ceiling Type B

    184m2

    OWA SANDILE 600 x 600 x 15mm thick LAYIN Ceiling tiles on a DONN EXPOSED GRID (T38) Main tees and T25 cross tees with cappings of prepainted Aluminium Grid Suspended from concrete or trusses with metal hangers all as per manufacturers requirements. Ceiling edged with a prepainted shadowline cornice

    4

    Ceiling Type C

    771m2

    OWA SANDILE 1200 x 600 x 15mm thick LAYIN Ceiling tiles on a DONN EXPOSED GRID (T38) Main tees and T25 cross tees with cappings of prepainted Aluminium Grid Suspended from concrete or trusses with metal hangers all as per manufacturers requirements. Ceiling edged with a prepainted shadowline cornice

    5

    Ceiling Type D

    13m2

    16mm thick particle board/chipboard ceiling with plum tree finish laid in 800 x 1600mm Grid system as per detail

    6

    Ceiling Type G

    4No

    Extra over ceiling for 650 x 650mm trap door of 38 x 50mm wrought softwood rebated framing with one 38 x 50mm sawn softwood cross brander covered with ceiling board and fitted flush in opening

    7

    54m75mm Coved cornices 8

    "Rhino" gypsum plasterboard cornices

    184

    Ceilings, Partitions and Access FlooringBill No. 7Section 2

    Carried to Collection R

  • Ceilings, Partitions and Access Flooring

    Section 2

    Bill No. 7

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    184

    183Total Brought Forward from Page No.

    185

    Ceilings, Partitions and Access FlooringBill No. 7Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 8

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 132 for CPAP formula purposes

    IRONMONGERY

    SUPPLEMENTARY PREAMBLES

    Where applicable finishes to ironmongery are indicated by suffixes in accordance with the following list: BS Satin bronze lacquered CH Chromium plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodised silver AB Anodised bronze AG Anodised gold ABL Anodised black PB Polished brass PL Polished and lacquered PT Epoxy coated SD SandedNP Nickle plated

    Finishes to ironmongery

    50No200mm Brass barrel bolt with keep fixed to metal1

    HINGES, BOLTS, ETC.

    50No"8052-150" Nickle plated flush bolt with keep fixed to metal

    2

    "Union"

    14No"CZ80941SC" WC indicator bolt with keep fixed to metal3

    LOCKS

    186

    IronmongeryBill No. 8Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    37No"CZ682-24/2247-78" or other similar and approved four lever lockset with striking plate fixed to metal or timber

    4

    "Union"

    13No

    "952/2L" or other equal and approved two lever lockset with chrome plated finish with striking plate fixed to metal

    5

    "Mazac Tarpon"

    36No

    66mm five pin Euro-profile knob cylinder master keyed. Code DKC106601 MK. Satin Nickel finish

    6

    "Dorma"

    15.0PairsDCE-105 S.S Stainless steel narrow stile cylinder escutcheon

    7

    HANDLES

    50No32 x 515mm Stainless steel "D" straight back-to-back pull handles

    8

    "Dorma"

    PUSH PLATES AND KICKING PLATES

    DOOR CLOSERS

    31No"TS83DC BC/BC/EN2-6" door closer with bracket fixed to metal

    9

    "Dorma"

    11No60 x 3mm Thick perspex plate with two 40mm high engraved and painted numerals

    10

    LETTERS, NAMEPLATES, ETC

    3No"DSS-145 FHR" 150 x 150mm stailess steel plate with fire hose reel symbol

    11

    "Dormakaba"

    2No

    "DSS-130 M" 150 x 150mm stailess steel plate with male symbol

    12

    187

    IronmongeryBill No. 8Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    2No"DSS-131 F" 150 x 150mm stailess steel plate with female symbol

    13

    2No"DSS-133 P" 150 x 150mm Stainless steel plate with paraplegic symbol

    14

    1No

    "DSS-136 el" 150 x 150mm Stainless steel plate with ELECTRICAL symbol

    15

    2No"IFSBO" Illuminated fire escape signage16

    1No"DSS-130M"150 x 150mm Baby change sign17

    14No

    Stainless steel toilet roll holders, size 304 x 156 x 140.7mm deep for 2 rolls maximum 108mm diameter with spindle system and cylinder lock with standard key, plugged and screwed to the wall with stainless steel screws..

    18

    "BATHROOM FITTINGS"

    14No

    Stainless steel sanitary towel disposal bins, size 304 x 205 x 134mm deep with capacity of 6 litres, plugged andscrewed to the wall with stainless steel screws

    19

    51No

    Stainless steel recessed waste disposal bins, size 396 x 270 x 520mm high with capacity of 45 litres and cylinder lock with standard key, plugged and screwed to the wall with stainless steel screws or equal approved

    20

    14No

    Stainless steel paper towel dispenser, size 300 x 270 x 340mm high with capacity of 300-400 towels and cylinder lock with standard key, plugged and screwed to the wall with stainless steel screws or equal approved

    21

    9No

    Stainless steel soap dispensers, size 304 x 100 x 134mm deep with a replaceable and refillable 1 litre container and cylinder lock with standard key, plugged and screwed to the wall with stainless steel screws or equal approved

    22

    6No

    Stainless steel Automatic hands free hand dryer, size 284 x 202 x 248mm deep with 2 vandal proof lock screws and key wrench, plugged and screwed to the wall with stainless steel screws, 200 W Motor connected to 230/240 volt power supply, with 5 year warranty

    23

    188

    IronmongeryBill No. 8Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    2No

    32mm stainless steel rear grab rail, in satin finish complete with SS fixing screws and plastic wall plugs. Installed as per manufacturer's instructions to latest standards

    24

    "Chairman Industries"

    2No

    32mm stainless steel 300x300x300 right hand side grab rail, in satin finish complete with SS fixing screws and plastic wall plugs. Installed to latest SABS standards

    25

    SUNDRIES

    51NoNickel plated floor mounted door stop. Code DDS-NP-018

    26

    'Dormakaba'

    10NoHat and coat hook with rubber buffer. Code DHC-SS-031B

    27

    15NoStainless steel dust proof strike. Code DPS-SS-03228

    10NoStainless steel adjustable roller bolt. Code DBC-SS-02229

    8No'DDH-SS-020' Stainless steel wall buffer30

    8NoBBBO Barrel/Necked bolt with keep fixed to metal31

    3.0PairsFBDM Flush bolts32

    52No"BFBDM" Built-in flush bolts33

    3No"37651 AS" WC helping hand indicator bolt for the paraplegic with keep fixed to metal

    34

    "Dormakaba"

    189

    IronmongeryBill No. 8Section 2

    Carried to Collection R

  • Ironmongery

    Section 2

    Bill No. 8

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    189

    188

    187

    186Total Brought Forward from Page No.

    190

    IronmongeryBill No. 8Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 9

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 136 for CPAP formula purposes

    METALWORK

    SUPPLEMENTARY PREAMBLES

    Descriptions of bolts shall be deemed to include nuts and washers

    Descriptions

    Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

    Metalwork described as"holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

    PRESSED STEEL DOOR FRAMES

    17NoFrame for door 813 x 2 032mm high1

    1,2mm Double rebated frames suitable for half brick walls

    23NoFrame for door 813 x 2 400mm high2

    1,2mm Double rebated frames suitable for one brick walls

    6NoFrame for door 900 x 2 400mm high3

    1NoFrame for double door 1 500 x 2 400mm high4

    ALUMINIUM WINDOWS, DOORS, ETC

    191

    MetalworkBill No. 9Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    3NoPurpose made door size 1500 x 2400mm high as per D01 in drawing number 703-rev A

    5

    Bronze anodised swing doors with subframes, and ironmongery complete with double clear safety "GSA SMARTGLASS CLEARVUE GLASS, glazed in accordance with NBF N Schedule 1 and SABS 0137, sealing, etc and fixing to brickwork or concrete

    3NoPurpose made door size 1500 x 2400mm high as per D02 in drawing number 703-rev A

    6

    3No

    Purpose made door size 1200 x 2400mm high as per D08 in drawing number 703-rev A

    7

    16NoPurpose made aluminium window, 600 x 900mm high8

    Bronze anodised standard fixed windows with openable end panels manufactured according to the requirements of AAAMSA complete with subframes, ironmongery, 8.76mm laminated obscured safety glass in all panels below 900mm height from first floor level and 6.38mm thick obscured glass in other panels, sealing, etc and fixing to brickwork or concrete

    1NoPurpose made aluminium window, 900 x 1200 mm high9

    49NoPurpose made aluminium window, 900 x 1200 mm high10

    Bronze anodised standard fixed windows with openable end panels manufactured according to the requirements of AAAMSA complete with subframes, ironmongery, 8.76mm laminated safety glass in all panels below 900mm height from first floor level and6.38mm thick glass in other panels, sealing, etc and fixing to brickwork or concrete

    1NoPurpose made aluminium window, 2885 x 2700mm high

    11

    Bronze anodised standard fixed windows with openable end panels manufactured according to the requirements of AAAMSA complete with subframes, ironmongery, Low- E glass with ATC30 CH SR HPR (Charcoal) window film with 33% visible light transmission,36% Total solar energy-rejection,22% IR energy rejection,29% Selection IR rejection,>99% Utravio-let protection,63% Glare rejection, 6% visible light reflection, sealing, etc and fixing to brickwork or concrete

    192

    MetalworkBill No. 9Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    1NoPurpose made aluminium window, 7785 x 3060mm high

    12

    1NoPurpose made aluminium window, 6110 x 3060mm high

    13

    2NoPurpose made aluminium window, 4300 x 2710mm high

    14

    1No

    Purpose made aluminium window, 1590 x 2350mm high

    15

    1No

    Purpose made aluminium window, 2760 x 2700mm high

    16

    1No

    Purpose made aluminium window, 2780 x 1560mm high

    17

    2No

    Purpose made aluminium window, 1200 x 1560mm high

    18

    1No

    Purpose made aluminium window, 2185 x 2400mm high

    19

    1No

    Purpose made aluminium window, 5000 x 2400mm high

    20

    1No

    Purpose made aluminium window, 8000 x 2700mm high

    21

    1No

    Purpose made aluminium window, 10933 x 2720mm high

    22

    193

    MetalworkBill No. 9Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    7No

    Purpose made aluminium window, 2700 x 2400mm high

    23

    Bronze anodised standard fixed windows with openable end panels manufactured according to the requirements of AAAMSA complete with Double Safety Glass complying with SANS 1263 part 1, 2 or 3 with manufacturer's name permanently marked on each sheet visible after glazing in accordance with NBR N schedule 1 and SABS 0137 including all necessary ironmongery (All in accordance with Architect's design)

    1No

    Purpose made aluminium window, 3000 x 2400mm high

    24

    1NoPurpose made aluminium window, 3505 x 2700mm high

    25

    1No

    Purpose made aluminium window, 1595 x 2400 mm high

    26

    1No

    Purpose made aluminium window, 2000 x 2230mm high

    27

    1NoPurpose made window size, 8048 x 750 mm high28

    Purpose made fully glazed aluminium window with openable end panel manufactured to minimum requirements of AAAMSA complete, with one way view laminated glass complying with SANS 1263 part 1, 2 or 3 with manufacturer's name permanently marked on each sheet visible after glazing in accordance with NBR N schedule 1 and SABS 0137

    1NoPurpose made window size, 5935 x 961mm high29

    1NoPurpose made window size, 8475 x 1645mm high30

    1NoPurpose made window size, 7785 x 1424 mm high31

    3NoPurpose made window size, 4300 x 1275 mm high32

    194

    MetalworkBill No. 9Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    STRONG ROOM

    2NoStrong room door size, 870 x 1970mm high33

    SABS Category 2 strongroom door and frame complete with chrome finished furniture, overal frame size of 1030 x 2010mm

    1No75 x 1mm powder coated steel slats, perforated with 2mm holes complete with frame and locking system

    34

    SLATTED STEEL DOOR

    BALUSTRADES, ETC

    50m

    Horizontal balustrades 1000mm high of 75mm diameter continuous top and bottom rails and 50mm diameter galvanised stanchions at average 500mm centres, bolted to concrete including bolts.

    35

    "Galvanised" welded and bolted patent balustrades to stairs, balconies, etc including bends and ends

    ALUMINIUM LOUVRE GRILLS

    1NoLouvre grill size, 2100 x 2125mm high36

    Purpose made steel frame louvre constructed out of 50 x 50 x2.5mm SHS mild steel tubing frame work. "TROX AGS or equal approved natural anodised aluminium louvre grill as per engineer's specification fixed to inside of mild steel frame

    195

    MetalworkBill No. 9Section 2

    Carried to Collection R

  • Metalwork

    Section 2

    Bill No. 9

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    195

    194

    193

    192

    191Total Brought Forward from Page No.

    196

    MetalworkBill No. 9Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    BILL NO. 10

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 134 for CPAP formula purposes

    STRUCTURAL STEEL (PROVISIONAL)

    Descriptions of bolts shall be deemed to include nuts and washers

    Descriptions

    Descriptions of L-shaped and U-shaped anchor bolts shall be deemed to include bending, threading, nuts and washers and embedding in concrete

    Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

    Descriptions of L-shaped and U-shaped anchor bolts shall be deemed to include bending, threading, nuts and washers and embedding in concrete. Where anchor bolts are described as embedded in sides or soffits of concrete it shall be deemed to include holes through formwork.

    Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

    STEEL COLUMNS AND BEAMS

    0.10t120 x 120 x 4mm SHS columns1

    Welded beams in single lengths with flat section bearer and connection plates bolted to concrete columns

    0.60t152 x 4.0mm circular hollow columns2

    0.30t200 x 150 x 4.0mm rectangular hollow section columns3

    0.75tIPE 180 Beam4

    0.40t60 x 60 x 6mm knee bracing5

    197

    Structural steelworkBill No. 10Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    0.95t70 x 70 x 6mm horizontal angle section bracing6

    0.03t114mm diameter x 3mm thick CHS bracing connected to rafter

    7

    0.05tRound sag rods with threaded ends8

    70No425 x 140 x 6mm thick plate at intersection of bracing including holes and 4No M16 Grade 8.8 bolts

    9

    70No

    450 x 250 x 6mm thick plate welded to steel rafter including holes and bolts sizes 4No M20 Grade 8.8 bolts and 4NO M16 Grade 8.8 bolts

    10

    50No394 x 150 x 6mm thick plate welded to 114 diameter bracing including holes and 2No M20 Grade 8.8 bolts

    11

    200NoM16 bolts grade 8.812

    Bolts to columns, beams, etc

    120NoM20 bolts grade 8.813

    50No

    M16 bolts using 16mm Hilti HST stud anchors 200mm long with domed nut and washer including mortice in concrete

    14

    STEEL TRUSSES ETC

    2.37tTruss member, 100 x 100 x 8mm angle section top chord

    15

    Design, supply, fabricate and erect "MITEK" or equalapproved engineered light weight "ULTRA-SPAN" steel trusses, designed by professional and erected by licensed and approved fabricator and erector

    2.12tTruss member, 90 x 90 x 8mm angle section bottom chord

    16

    1.27tTruss member, 60 x 60 x 6mm angle section diagonal17

    0.86tTruss member, 70 x 70 x 6mm angle section vertical18

    8.70tTruss member, IPE 180 Eaves beam19

    0.46t100 x 100 x 3.0mm square hollow section20

    Steel members to roof canopy

    198

    Structural steelworkBill No. 10Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    0.05t30 x 30 x 3mm angle section21

    0.22tIPE-AA 200 support beam22

    0.86tTruss member, 70 x 70 x 6mm angle section vertical23

    8.70tTruss member, IPE 180 Eaves beam24

    0.45t50 x 50 x 3mm angle section along roof25

    0.10tM20 high tensile stainless steel rods26

    HOT DIPPED GALVANISED PURLINS, GRITS, BRACING, ETC

    0.30t75 x 50 x 20 x 2.0mm lipped channel purlin27

    Purlins, etc, welded and bolted on including cutting, holing, bolting, etc

    1.20t150 x 75 x 20 x 2.5mm lipped channel purlin28

    18.00t150 x 50 x 20 x 3.0mm lipped channel purlin29

    199

    Structural steelworkBill No. 10Section 2

    Carried to Collection R

  • Structural steelwork

    Section 2

    Bill No. 10

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    199

    198

    197Total Brought Forward from Page No.

    200

    Structural steelworkBill No. 10Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 11

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 142 for CPAP formula purposes.

    PLASTERING

    SCREEDS

    1,237m235mm Thick on floors and landings1

    1:4 Cement plaster screeds wood floated on concrete

    INTERNAL PLASTER

    3,602m2On walls2

    Cement plaster on brickwork

    104m2On narrow widths3

    114m2Soffit of Slab 4

    44m2Concrete walls5

    320m2Sides and soffit of beams 6

    76m2Sides of circular columns7

    EXTERNAL PLASTER

    1,345m2On walls8

    Cement plaster on brickwork and marmoran finish according to manufacturer's instruction

    38m2On narrow widths9

    201

    PlasteringBill No. 11Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    147m3 x 32mm Flat section brass dividing strips between different floor finishes

    10

    CORNER PROTECTORS, DIVIDING STRIPS, ETC

    202

    PlasteringBill No. 11Section 2

    Carried to Collection R

  • Plastering

    Section 2

    Bill No. 11

    AmountPageNo

    COLLECTION

    Bela Bela LDSD Offices

    202

    201Total Brought Forward from Page No.

    203

    PlasteringBill No. 11Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 12

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 144 for CPAP formula purposes.

    TILING

    SUPPLEMENTARY PREAMBLES

    Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding

    Descriptions

    WALL TILING

    266m2On walls1

    200 x 200 x 6mm "Cercisa Tinte Unite" White glazed ceramic tiles fixed with adhesive to plaster (plaster elsewhere)

    FLOOR TILING

    1,238m2On floors and landings2

    300 x 300mm x 8mm Porcelain tiles (PC Amount R130.00/m2) fixed with adhesive to bedding (bedding elsewhere) and flush pointed with tinted waterproof jointing compound

    1,135mSkirting 150mm high3

    204

    TilingBill No. 12Section 2

    Carried Forward to Summary of Section No. 2 R

  • AmountItemNo

    Quantity Rate

    Bela Bela LDSD Offices

    SECTION 2

    BILL NO. 13

    NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 146 for CPAP formula purposes.

    PLUMBING AND DRAINAGE (PROVISIONAL)

    SUPPLEMENTARY PREAMBLES

    Soil, waste and vent pipes and fittings shall be solvent weld jointed

    uPVC pipes and fittings:

    Pipes for water supply shall be of the class stated

    uPVC pressure pipes and fittings:

    Pipes of 40mm diameter and smaller shall be plain ended with solvent welded uPVC loose sockets and fittings

    Pipes of 50mm diameter and greater shall have sockets and spigots with push in type integral rubber ring joints. Bends shall be uPVC and all other fittings shall be cast iron, all with similar push-in type joints

    Pipes shall be hard drawn and half-hard pipes of the class stated. Class 0 (thin walled hard drawn) pipes shall not be bent. Class 1 (thin walled half-hard), class 2 (half-hard) and class 3 (heavy walled half-hard) pipes shall only be bent with benders with inner and outer formers. Fittings to copper waste, vent and anti-syphon pipes, capillary solder fittings and compression fittings shall be "Cobra Watertech" type. Capillary solder fittingsshall comply with ISO 2016. Only compression fittings shall be used in walls or in ground

    Copper pipes:

    205

    Plumbing and Drainage (Provisional)Bill No. 13Section 2

    Carried to Collection R

  • Bela Bela LDSD Offices

    Unless specifically otherwise stated, descriptions of pipes shall be deemed to include fixing to walls etc, casting in, building in or suspending not exceeding 1m below suspension level

    Fixing of pipes

    Where fittings have reducing ends or branches they are described as "reducing". In the case of pipes with diameters not exceeding 60mm only the largest end or branch size is given. Should the contractor wish to use other fittings and bushes or reducers he may do so on the understanding that no claim in this regard will be entertained. In the case of pipes with diameters exceeding 60mm all sizes are given and no claim for extra bushes, reducers, etc will be entertained

    Reduc