bservices report final (2)

90
1 | Page 1.0 Introduction Located at Jalan SS13/3A, Subang Jaya, this four-storeys multipurpose building known as Lifepoint, Subang Jaya Assembly of God was constructed from the old Faber Castell office and factory that is now changed into a church that is also commonly used as a community center to hold various events and activities. SH Teh Architect had redesigned the building alongside the existing structures on the 21 th of November 2009 and renovated once more on the 10 th of October 2011. Architect: Ar. Teh Soh Huang Total floor area: 4559.2m 2 Address: 14 Jalan SS13/3A 47500 Subang Jaya Selangor Darul Ehsan Malaysia. 1.1 Abstract The following research report will be a compilation of the working building services in the Lifepoint Building such as the Air conditioning and ventilation system, Electrical supply system, Mechanical transportation and Fire protection system. This report will further delve into the process that these systems undergo in accordance to the Uniform Building By-Laws and other related regulations as well as our own analysis on the advantages and disadvantages of the services. SITE

Upload: elaine-bong

Post on 15-Nov-2015

219 views

Category:

Documents


0 download

DESCRIPTION

report

TRANSCRIPT

  • 1 | P a g e

    1.0 Introduction

    Located at Jalan SS13/3A, Subang Jaya, this four-storeys multipurpose building known as

    Lifepoint, Subang Jaya Assembly of God was constructed from the old Faber Castell office

    and factory that is now changed into a church that is also commonly used as a community

    center to hold various events and activities. SH Teh Architect had redesigned the building

    alongside the existing structures on the 21th of November 2009 and renovated once more on

    the 10th of October 2011.

    Architect: Ar. Teh Soh Huang

    Total floor area: 4559.2m2

    Address:

    14 Jalan SS13/3A

    47500 Subang Jaya

    Selangor Darul Ehsan

    Malaysia.

    1.1 Abstract

    The following research report will be a compilation of the working building services in the

    Lifepoint Building such as the Air conditioning and ventilation system, Electrical supply

    system, Mechanical transportation and Fire protection system. This report will further delve

    into the process that these systems undergo in accordance to the Uniform Building By-Laws

    and other related regulations as well as our own analysis on the advantages and disadvantages

    of the services.

    SITE

  • 2 | P a g e

    MECHANICAL VENTILATION AND AIR-CONDITIONING SYSTEM

    2.0 Introduction

    Life Point Church operates mostly on split unit air conditioning system because of its small

    divided spaces. But the main hall is too big for split unit air conditioning system to provide

    conditioned and quality air. So the centralised air conditioning system is used to provide

    adequate fresh cool air to the main hall. The air handling unit is located just behind the main

    hall which is on top of the robbing room and there are not one but two rooms (one for each

    sides). This is to reduce the ductwork required to transfer the cool air from the AHU and to

    reduce heat lost from the cool air thus increasing the efficiency of the air conditioning system

    and as a strategic if one breaks down. The condenser units are placed outside the robbing

    room for the same reason.

    Figure 2.0.1: Location plan of AHU Figure 2.0.2: Entrance of AHU

    Room

    Figure 2.0.3: Location of Condenser Units Figure 2.0.4: Condenser units outside robbing room

  • 3 | P a g e

    2.1 Literature Review

    A HVAC (Heating, Ventilating and Air Conditioning) system is to provide the people

    working inside buildings with conditioned air so that they will have a comfortable and safe

    work environment. Conditioned air means that air is clean and odour-free, and the

    temperature, humidity, and movement of the air are within certain comfort ranges. (BNP

    Media, 2000) To ensure that the air quality in a building is maintained, The American Society

    of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) has set standards that

    more than 80% or more of a commercial building occupants accepts the indoor air quality

    provided.

    2.1.1 Mechanical Ventilation

    To avoid symptoms of sick building syndrome, mould growths, asthma and dust mite

    allergies, provision of air circulation must be integrated with building design. Air infiltration

    can be achieved by natural or mechanical ventilation means. Natural ventilation by these

    means is difficult to regulate in defined quantities, therefore low-energy-use mechanical

    ventilation systems, particularly those with a heat recovery facility, are becoming quite

    common in new-build homes. But when there is enough air ventilation provided from the

    openings of the building, mechanical exhaust might be needed to extract stale air from

    internal spaces.

    Requirements for an acceptable amount of fresh air supply in buildings will vary

    depending on the nature of occupation and activity. Air change per hour or ventilation rate is

    preferred criterion for system design. This is calculated by dividing the quantity of air by the

    room volume and multiplying by the occupancy. (Hall & Greeno, 2007)

    Typical mechanical ventilation systems used by buildings are supply ventilation system,

    exhaust ventilation system and balance ventilation system. (Energy star, n.d.)

    Figure 2.1.1.1: Exhaust Ventilation (Central Air, Inc., 2014)

  • 4 | P a g e

    Case Study

    2.1.2 Air-Conditioning

    Air-conditioning is a process that simultaneously conditions air; distributes it combined with

    the outdoor air to the conditioned space; and at the same time controls and maintains the

    required spaces temperature, humidity, air movement, air cleanliness, sound level, and

    pressure differential within predetermined limits for the health and comfort of the occupants,

    for product processing, or both. (Wang & Lavan, 1999)

    Air conditioning is achieved by developing the principles of moving air in ducted

    ventilation systems to include a number of physical and scientific processes which enhance

    the air quality. The objective is to provide and maintain internal air conditions at a

    predetermined state, regardless of the time of year, the season and the external atmospheric

    environment. For buildings with human occupancy, the design specification is likely to

    include an internal air temperature of 19-23C and relative humidity between 40 and 60%.

    (Hall & Greeno, 2007)

    Types of air conditioning system, individual system, space system, packaged system, air

    system, water system, central plan refrigerant and heating system, and control system. (Wang

    & Lavan, 1999)

    In assembly buildings with seating, people generally remain in one place throughout a

    performance, so they cannot move away from drafts. Therefore, good air distribution is

    essential. Because of the configuration of these spaces, supply jet nozzles with long throws of

    15 to 45m may need to be installed on sidewalls. For ceiling distribution, downward throw is

    not critical if returns are low. This approach has been successful in applications that are not

    noise-sensitive, but designer needs to select air distribution nozzles carefully. (ASHRAE,

    2011)

    Figure 2.1.2.1: Standard of Air Change Rate (Mitsubishi Electric, 2011)

  • 5 | P a g e

    2.2 Mechanical Ventilation

    Indoor

    Outdoor

    Figure 2.2.1: Air flow of Spot Ventilation System

    Figure 2.2.2: Ground Floor Plan, rooms where Mechanical Ventilation is applied

    The spot ventilation system practiced in this building is the extract system where they use

    natural inlet and mechanical extract. The internal space is constantly ventilated whilst indoor

    air is drawn out causing space to be slightly depressurized. This type of mechanical

    ventilation is used in the toilets and the pantry of the case study building. This is mostly

    practised in hot humid climates where there is a risk of drawing hot outdoor air into

    remaining holes and cracks in the construction assembly where it could reach cool interior

    surfaces, condense, and cause moisture problems, stated by Energy star (n.d.)

    Natural inlet (Openings)

    Mechanical outlet

    (Propeller Fan)

    Stale air

    Fresh Air

  • 6 | P a g e

    2.2.1 Natural inlet Windows

    Figure 2.2.1.1: Windows in the Toilet Figure 2.2.1.2: Window in Pantry

    As stated in UBBL 39(1) that every room designed shall be provided with natural lighting

    and natural ventilation by means of one or more windows having a total area of not less than

    10% of the clear floor area of such room and shall have openings capable of allowing a free

    uninterrupted passage of air or not less than 10% of such floor area. The large window

    opening for the rooms stated in Figure 2.2.2. are slightly exceeding the required area

    accordance to the function and usage of the rooms and the area of the respective rooms.

    Where the pantry has an area of 17.1 but there is a 2.25 of window opening provided

    which is 13.1% of the total floor area meeting the requirement of UBBL.

    In UBBL 39(4), every water-closet, latrine, urinal or bathroom shall be provided with

    natural lighting and natural ventilation by means of one or more openings having a total area

    of not less than 0.2 square metres per water-closet, urinal latrine or bathroom and such

    openings shall be capable of allowing a free uninterrupted passage of air. Whereas the total

    area of the female toilet is 22.2 and the windows have a total area of 1.8 which is again,

    more than what is required as there are just five water-closets in the female toilet. Having

    windows that exceeds the requirements isnt all a bad thing as horizontal railings are installed

    for security and safety purposes. By having large surface area of window openings allows

    prevailing wind to pass through it introducing fresh air into the internal spaces of the building

    while maintain the indoor air quality.

  • 7 | P a g e

    2.2.2 Mechanical extract Propeller fan

    According to the Third Schedule (2), the inlets should be at high level with extraction points

    at low level. Re circulation arrangements should not be provided. The incoming air should be

    filtered and air-conditioned (the theatre temperature being capable of adjustment with

    mechanical requirements within the range 20 C to 24.4C. Control over humidity of air in

    the rooms should be provided to ensure that it will be within the range of 55% to 65%. And in

    the Third Schedule (5), Air inlet points shall be not lower than two-thirds of the height of the

    room and exhaust air openings shall be within 1 metre of the finished floor level of the

    enclosure.

    This method of natural inlet and mechanical outlet is used only in various part of the

    building. Locations like, toilets, pantry. As mentioned, internal space requires stale air to be

    transferred out to ensure that indoor air quality is maintained and to have a comfortable

    internal environment.

    2.3 Air-Conditioning System

    Air-conditioning system is a system for controlling the temperature and humidity of air in a

    building. (Space Air conditioning plc, 2014) Besides controlling the temperature of the room

    in the building, air-conditioning provides ventilation to the space bringing oxygen for the

    occupants to breathe in while filtering off dust, pollen and other micro particles from the

    recycled air that will bring harm them.

    There are two types of air-conditioning systems in our building which are the split unit

    air-conditioning system and the centralised air-conditioning system.

    Figure 2.2.2.1: Propeller in Kitchen Figure 2.2.2.2: Surface Mounted Fan

  • 8 | P a g e

    2.3.1 Centralised Air Conditioning System

    Figure 2.3.1.1: Location of Central Air Conditioning System

    Figure 2.3.1.2: Central Air Conditioning System (Pisupati, 2014)

    This centralized air-conditioning system could be seen in the main hall, where the air

    handling unit (AHU) is located behind the stage. In this case, there are two AHU room in the

    building to provide conditioned air to the main hall which is the biggest room in the whole

    building. There are few basic mechanical components which work together to create a

    comfortable internal environment for the users. (How Central Air Conditioner Works, n.d.)

  • 9 | P a g e

    One of the components is the compressor (refer 2.3.2.3) which controls the pressure

    difference in the whole central air conditioning system. The high pressured gas from

    compressor will then moves to the condenser (refer to 2.3.2.4) to release the heat outdoor

    with the aid of condenser fan in the unit. The refrigerant is condensed here turning it to liquid

    form. The evaporator (refer to 2.3.2.7) and blower (refer to 2.3.2.11) work as one to cool

    down the main hall. The refrigerant flows through the evaporator whereas the blower is

    responsible to suck the return air into the AHU then blow it out through the evaporator while

    the refrigerant removes the heat from the air. There is a meter device, which controls the

    amount of refrigerant passing through, called expansion valve (refer 2.3.2.6). In events of

    fire, fire damper (refer to 2.3.2.15) in the ducting system will act. (Knapp. 2014)

  • 10 | P a g e

    2.3.2 Components of Air Conditioner

    2.3.2.1 Refrigerant Cycle

    Figure 2.3.2.1.1: Refrigerant cycle in air-conditioner (Warrior Press, 2014)

    For air conditioner to operate, the refrigerant must be used repeatedly. The refrigerant

    undergoes the same cycle of compression, condensation, expansion and evaporation in a

    closed circuit. (Hoffman, 2006)

    High pressure liquid Low pressure liquid

    Condenser

    Expansion

    Valve

    Evaporator

    Compressor

    High pressure gas Low pressure gas

    Figure 2.3.2.1.2: Basic Refrigerant Cycle

  • 11 | P a g e

    Firstly, the refrigerant goes into the compressor (refer 2.3.2.3) as a low pressure gas and

    comes out as a high pressure gas. The gas will then move to the condenser (refer 2.3.2.4) and

    the gas will start to condense into liquid while removing its heat outside. As the high pressure

    liquid flows into the expansion valve (refer 2.3.2.6), the flow of liquid is restricted and the

    pressure is lowered as it leaves the expansion valve. After that, the low pressure liquid moves

    into the evaporator (refer to 2.3.2.7) and ended up in the compressor where the cycle is

    repeated.

    2.3.2.2 Air Cycle

    The air cycle between the interior spaces and the AHU room works together as one. Air cycle

    is a process where the conditioned air is distributed back to the room. The heat inside the

    spaces is removed when the air is absorbed by the evaporator (refer to 2.3.2.7). Then the hot

    refrigerant will flow back towards the condenser (refer to 2.3.2.4) and release the heat back

    to the external environment.

    Figure 2.3.2.2.1: Schematic diagram of Air Cycle

  • 12 | P a g e

    2.3.2.3 Compressor

    Figure 2.3.2.3.1: First Floor Plan with Compressor indicated

    Total compressors used for site are ten, five on the right and another five on the left. This

    is done in case there is an emergency breakdown, thus the other five compressors can still be

    operated. This component is located in the condenser unit which is the Packaged Unit Air

    Conditioning System, located outdoor for ventilation. Type of compressor used would be the

    reciprocating compressor, where gas is extracted into cylinder in piston stroke, discharge

    valve opens when compressed, as the low pressured vaporized refrigerant flows through the

    compressor, it will be compressed to high pressure causing it to be very hot. One of the

    advantages of using reciprocating compressor would be that high pressure could be achieved

    with low mass flow and is cheap.

    Figure 2.3.2.3.2: Condenser Unit with Compressor Inside

  • 13 | P a g e

    2.3.2.4 Condenser

    The condenser and compressor are placed together in the same system, as they used the

    centralised air conditioning system, while them both plays different role, the condenser is in

    charge of removing heat from the high pressure liquefy refrigerant thus condensing the liquid

    to vapour form.

    2.3.2.5 Air Handling Unit Rooms (AHU)

    Diagram 2.3.2.5.1: First Floor Plan with AHU Room indicated.

    The AHU Rooms are located at the back of the main hall and the compressors being behind

    the room allows easy access and maintenance. It is important to locate the AHU room in an

    appropriate location as it affects structural costs, architectural design. Inside there is the

    control panel (refer 2.3.2.8), evaporator (refer 2.3.2.7), expansion valve (refer 2.3.1.6),

    blower (2.3.2.11) and the entire system needed to run the air-conditioning system. There are

    Figure 2.3.2.4.1: Condenser Unit

  • 14 | P a g e

    a total of two AHU rooms in the entire building. Both used to facilitate just for the main hall.

    The AHU room is usually restricted as it is where the machinery is located. It is important for

    the ventilation engineers to design the AHU room accordance to required air conditioning

    system to it. According to ASHRAE (2011), making sure that the room meets the projects

    budget and provides compliance with the prescribed regulatory requirements such as building

    life safety, energy and ventilation code is important.

    2.3.2.6 Expansion Valve

    Situated in the air handler where it is near the evaporator. When the high pressure liquid

    flows through the expansion valve, it will then lowered the pressure of the liquid and

    restricted the volume of the flow of the liquid and its pressure as it passes to the condenser.

    2.3.2.7 Evaporator

    Positioned in the AHU Room this is behind the main hall. It is a system filled with coils

    where it will convert low pressure liquid refrigerant into low pressure vapour refrigerant

    when the refrigerant absorbs heat. This is known as the evaporation process. Low pressure

    liquid that was partially collected from the expansion valve and main hall will be passes on to

    condenser unit to be pressurized by the compressor.

  • 15 | P a g e

    2.3.2.8 Control Panel

    Electricity for the air conditioning system is separated from the power and lighting system.

    This is due to the fact that if the electric circuit for the lighting trips, they would be able to

    control their air conditioning system. This could be taken into account as an emergent

    solution. The air conditioning system has their very own panel board in the consumer switch

    room. And each air conditioning unit has their own circuit breaker, each labelled accordingly

    in order not to cause confusion for personnel who have little knowledge on the air

    conditioning system. Control panels allow occupant to adjust room temperature accordingly

    to fit their comfort.

    Figure 2.3.2.8.1: HVAC System Control Panel in Consumer Switch Room (left) Control Panel

    of Compressor to indicated designated temperature (right)

  • 16 | P a g e

    2.3.2.9 Air Filter

    Air filter placed on the exterior of machineries and equipment are used to protect the

    machinery and equipment. It is generally used to filter out dust and unwanted substance

    before being suck into the system. Filters needs to be changed occasionally, as used filter

    would affect the quality of airflow in space.

    2.3.2.10 Ventilation

    Louver placed on the on the wall of room in order to provide ventilation to AHU room. The

    ventilation is also used to allow air flow inside room, thus to be recycle. And accordance to

    ASHRAE (2011), by providing ventilation means into the breathing zone of facility

    occupants.

    Figure 2.3.2.10.1: Ventilation louver inside AHU

    Room

    Figure 2.3.2.9.1: Air filters on machinery Figure 2.3.2.9.2: Tissue being used as

    demonstration

  • 17 | P a g e

    2.3.2.11 Blower

    This blower fan is located near the evaporator to blow warm return air passed the evaporator

    coil to remove heat from the return air and discharge the cool supply back to the internal

    spaces through the cone diffuser.

    2.3.2.12 Supply Air Diffuser

    Air supply for large spaces should be designed in order to provide thermal comfort for user.

    According to ASHRAE (2011), air is generally distributed from height of 4.3m and greater.

    By designing the diffuser at a tall height, air could be flow out and produce a constant

    temperature for space. The evaporator behind the cone diffuser, a system of coils that, when

    filled with cold refrigerant, it cools the air around it. It will then convert low pressure liquid

    refrigerant into low pressure vapour refrigerant. Hence cool air is produced.

    2.3.2.13 Return Air Griller

    Figure 2.3.2.13.1: Mechanical

    extraction in main hall under stage

    Figure 2.3.2.12.1: A line of cone Diffuser Figure 2.3.2.12.2: Close-up of Cone Diffuser

  • 18 | P a g e

    The Third Schedule (5) pointed out that, air inlet points shall be not lower than two-thirds of

    the height of the room and exhaust air openings shall be within 1 metre of the finished floor

    level of the enclosure. Whereas the louvers acting as openings, allows the mechanical

    extraction in the AHU Room, absorbs the water vapour and stale air, where the ducts would

    bring the unclean air and odour to compressor as to recycle the air. This mechanical extract

    is also to help maintain cleanliness of the carpet, just so the carpet would not absorb the water

    vapour causing it to be moist.

    2.3.2.14 Duct System

    Ducting is used to transfer cool air to space. It is also used to convey exhaust air from hood to

    the outside along with any grease, smoke, VOCs and odours that are not extracted from the

    airstream along the way. These ducts act as an airstream from the internal to the external, vice

    versa. The ducts must be grease tight; it must be clear of combusts, or combustible material

    must be protected so that it cannot be ignited by fire in ducts; and ducts must be sized to

    convey the volume of airflow necessary to remove the effluence as stated in ASHRAE, 2010.

    In order to control the volume of air flow to space, dampers (refer to 2.3.4.1), are used. It is

    the ventilation engineers job to figure the specified type of ducting that would suit the

    airway based on the velocity of air. As ASHRAE (2010) stated that if the air way is oversized

    and velocity is low, it will cost more than necessary. Appropriate air velocity should be under

    6m/s.

    Figure 2.3.2.14.1: Ducting System in AHU Room

  • 19 | P a g e

    2.3.2.15 Dampers

    Dampers are found inside ducting system of ventilation. Its serve to control the volume of air

    exhausted out from HVAC system. Also serving the purpose of fire protection if fire breaks

    out and smoke kindled, dampers can be used to block out smoke from flowing to another

    space. As static fire dampers applied in HVAC system are built in to shut down in the events

    of a fire upon detection. (Knapp, 2014)

    2.3.2.16 Pipe System

    There are two main lines in the Pipe System; liquid line and suction line.

    The liquid line is located between the condenser unit and the evaporator. In the

    condenser unit, the condenser fan will introduce air into the unit and heat from the internal

    spaces absorbed by the refrigerant will be released to the external surrounding. The smaller

    diameter of the tube carries liquid refrigerant from the condenser unit where the line will get

    very hot when the refrigerant is pressurised as it passes through the tube. In the Life Point

    Church, the liquid line is not insulated as the heat transfer between the refrigerant and the

    surrounding is minimal because of the climate in Malaysia.

    The suction line is a larger diameter tube that carries refrigerant vapour between the

    evaporator and the condenser unit. This line is very cold when it is in operation because the

    vaporized refrigerant expands as it cools down. When the refrigerant pass through the

    evaporator, the return air will be sucked into the unit and cool air will be blown out by the

    blower in the evaporator causing the rooms temperature to be cool. This line has to be

    insulated using the rubber insulation pipe to prevent heat gain from the external surrounding.

    Suction /

    Vapour Line

    Liquid Line

    Figure 2.3.3.6: Refrigerant line

  • 20 | P a g e

    2.3.3 Split Unit Conditioning System

    The split unit air-conditioning system integrated by Life Point Church is the ductless split

    unit where there is no fresh air introduced into the spaces. The existing indoor air is recycled

    and recirculated unless there are openings to provide ventilation. Different types of indoor

    units identified in the building which is the wall mounted and the ceiling mounted/cassette

    type.

    Figure 2.3.3.3: Wall mounted type Figure 2.3.3.2: Wall mounted type

    Figure 2.3.3.4: Ceiling mounted type

    Figure 2.3.3.1: Location of Split Unit Air Conditioner

  • 21 | P a g e

    The wall air conditioners are frequently used in singles room where prayers or meetings

    are held. Each unit would have their own outdoor unit, making a total of 75 units. Piping

    system (refer to 2.3.2.16) could be seen traveling on walls or panel from space to space as

    shown in Figure 2.3.3.5, connecting from their individual outdoor unit to their own

    personalize indoor unit. They could be control individually using a simple remote control,

    allowing user to easily control the temperature to their liking.

    The prayer rooms are ventilated using this system. Individual condenser is place at

    designated location, mostly in rooms designed for minimum amount of people. This system

    isnt used as often, especially when the centralized air conditioning system is being used.

    Figure 2.3.3.5: Piping System

    Figure 2.3.3.6: Split Unit Air-Conditioning

    System (heatingpartscenter, 2012)

    Figure 2.3.3.7: Refrigerant line of split unit air

    conditioner (Snyder, 2014)

  • 22 | P a g e

    The split unit air conditioner consists of two units which are the condenser unit,

    which is placed outdoor, and the evaporator, which is the indoor unit. The condenser unit

    consists of compressor and condenser where they work together as a whole. The outdoor and

    indoor units are both connected by copper tubing that are insulated by black rubber insulation

    pipe. The copper tubing is the refrigerant line which runs between the evaporator coil in the

    air handler (indoor) and the condenser unit that contains the compressor and condenser coil

    (outdoor). The insulation on the suction or vapour lines (refer to Piping System 2.3.2.16)

    connecting to the outdoor condensing unit is very important in maintaining the efficiency of

    the system and reducing energy consumption. (Snyder, 2014)

    Figure 2.3.3.8: Indoor Unit (Evaporator) Figure 2.3.3.9: Outdoor Unit (Condenser Unit)

    2.3.4 Analysis

    The centralised air conditioning system in the main hall are switch on at all times, this is

    to cut cost on the electricity. As by having the compressors on at all times, the energy to turn

    it back off and on would cost more than having the compressors running straight for three

    hours. The condenser units for the split unit air conditioners are also located at places that are

    easier to reach for maintenance.

  • 23 | P a g e

    ELECTRICAL SUPPLY SYSTEM

    3.0 Introduction

    Life Point Church is a four-storeys height community building which consisted of different

    functional spaces, such as halls, cafeteria, classrooms and sports area, to serve the users.

    Electricity plays an important role in supporting the function of the spaces. The electrical

    system used in the building is three-phase four wire system, which are the system applied in

    Malaysia. Since it is a community building which can carries large amount of users, the

    power of 415v instead of 240v is required to be supplied to the equiprment throughout the

    building.

    The total area of Life Point Church is 2130m square, which the indoor connected

    substation is needed. A transformer comes along with the substation is located just right next

    to it in a TNB transformer room, followed by the building consumer switch room.

    Buku Panduan Piawan Elektrik:

    An indoor main distribution substation with 33/11kV power is required in order to supply a

    building with total area of 2116m square.

    Figure 3.0: The image shows the location of main switch room and M&E room at the ground floor.

    As shown in Figure 2.0 there is a Mechanical and Electrical room (M&E) in the

    ground floor which located right next to the Main Hall. This room consists of different

    distribution boards which controls electricity supply towards different spaces in our site. In

    the first and second floor, there is no M&E room but only a distribution boxes which are

    located seperately in each floor since it does not have to support heavy electrical equipment

    such as the air-conditioning system in the main hall located at ground floor.

  • 24 | P a g e

    3.1 Literature Review

    The electric power industry shapes and contributes to the welfare, progress, and technological

    advances of humanity. (El-Hawary and El-Hawary, n.d.) As time goes, the power plants and

    generating station were built bigger in size so that they could perform better and produce

    higher voltage of electric power that could be transmitted over a great distance towards

    different industries to the consumers.

    Figure 3.1.1: The transport of electricity and brief introduction on the flow. (Australian Government

    Department of Industry, n.d.)

    In Malaysia, the electrical system used is three-phase four wire system. Three-phase four

    wire distribution systems have been used to supply single-phase low-voltage loads. The

    advantages of this system is that it is grounded and it has a neutral phase compared to three-

    phase three wire system.

    The structure of the electrical power system included a generation system which

    consist of generators and transformers. In Peninsula Malaysia, we have Tenaga Nasional

    Berhad (TNB) which operates different types of power generators, such as hydroelectric,

    coal-fired plants, oil-fired plants and also plenty biomass and hybrid power station that

    supply electrical power. TNB uses mostly coal-fired plants but due to the consideration of

    environment, excessive conservation of fossil fuels are not recommended to be used. Hence,

  • 25 | P a g e

    other approaches such as hydroelectric power plant is slowly developing in Malaysia

    electrical power generation system.

    Electricity is processed by step-up transformers before it is connected to the national

    grid. (Hall & Greeno, 2005) A step-up transformer reduces loses in line in order to ensure the

    transmission of power could carry on longer and to a long distance. Once the power reached

    its consumer unit, a step-down transformer is now needed to reduce the voltage to a required

    value depends on the needs of the consumer unit. That is why a substation is needed to

    transform power with high efficiency from one level of voltage to another before entering a

    building. Next, the electricity will goes through distribution system which utilise the

    overhead and underground conductor. The distribution system can be classified into two,

    which is the primary distributional line which serves small industries and the secondary

    distribution network that utilises commercial and residential consumers. The planning of an

    electrical power system should be continue in a consumer unit in order to protect the power

    system. This operational planning included instrument transformer, circuit breakers,

    disconnect switches, fuses and lighting arresters. All the compartments are working in

    cooperation with each another and are placed on panel boards in the consumer switch room.

    Figure 3.1.2: A TNB Substation in larger scale that supply power for industrial building which located right

    next to our site.

  • 26 | P a g e

    Case Study

    3.2 TNB Substation

    Diagram 3.2: Schematic diagram of the system component of the electrical power supply system flow from

    the input to the output source.

    According to the TNB Electricity Supply Application Handbook, Tenaga Nasional Berhad

    (TNB), is charged with the two main responsibilities. The first is to generate, transmit and

    distribute and sell energy to consumer throughout Peninsula Malaysia. And following by to

    plan install, operate and maintain electricity installation for the generation, transmission and

    distribution of electricity. The parties such as consultant engineers are involved in making

    decision to change the substation number, size, location and the consumer switch room.

    From substation supply

    Consumer Switch Room

    Panel Board Switch Gear

    Mechanical and Electrical Room

    Distribution Board

    Consumer Unit

    3 Phase Miniature Circuit

    Breaker (MCB)

    Ring Circuit

    Figure 3.2.1 The location of TNB room

    which is located at the ground floor of the

    building.

    Figure 3.2.2 The exterior look of TNB

    transformer room and TNB switch room which are

    placed next to each other.

  • 27 | P a g e

    The TNB transformer room transfer voltage from high to low. It is located between

    the generation station and the consumer switch room to ensure that the electricity can flows

    through in different voltage levels. The total area of TNB switch room in Live Point Church

    is 6600mm x 6000mm x 4000mm. It reached the requirement as stated in Malaysian Grid

    Code.

    Malaysian Grid Code: The TNB switch room was required to reach a minimum size of

    6000mm x 5000mm x 4000mm where the size could be modified through discussion by both

    TNB and consultant engineer.

    In the TNB transformer room, a 1000kVA transformer is used. 15-1000kVA

    transformer is categorised under a three phase transformer. (Jefferson Electric, 2014) This

    type of transformer is used for all general three phase loads, either indoor or outdoor, which

    included lighting, industrial and commercial applications. Advantage of using the three phase

    transformer is that it is smaller, lighter and cheaper than three individual single phase

    transformer connected together. (Storr, 2013)

    Figure 3.2.3: The symbol indicating voltage of

    the transformer used.

    Figure 3.2.4: Meter and fire alarm at the

    exterior of the TNB substation for safety purpose.

  • 28 | P a g e

    3.3 Consumer Switch Room

    A consumer switch room contains of different compartments of operating power system, such

    as panel board, distribution board, switch panels and physical TNB check-up meter. It

    maintains the reactive power balance and acts as a control center to distribute electrical power

    throughout the building. Electric supply from the TNB substation is transferred to this room

    where it serves as the main electrical distribution room for the Live Point Church. Hence, it is

    placed next to the TNB substation to ensure that the power is transferred within a short

    distance to prevent excessive loss of electrical power. Fire protection equipment such as fire

    extinguishers, fire sprinkler and fire alarm are placed inside room to ensure safety. Besides,

    the door and windows in the room are well protected as well, so that the fire will not spread

    to other places.

    Figure 3.3.1: The location of consumer switch room which located right next to the substation, and the side

    entrance.

    Figure 3.3.2, 3.3.3, 3.3.4: Emergency light, Fire extinguishers, smoke detector and fire sprinkler are used.

    The detail of fire protection system in the consumer switch room will be further explain in Topic 3: Fire

    Protection System. These equipment are necessary in ensure the building safety.

  • 29 | P a g e

    3.4 Panel Board

    The main compartment which is located in the Consumer Switch Room is the panel board. It

    has an assembly of switches and circuit protection devices from which power is distributed.

    This distribution of the large incoming electricity supply from the TNB substation into

    appropriate electricity voltage is required in order to serve their individual purposes.

    The type of panel board used in this building is the metal enclosed panel board. Metal

    enclosed panel board in which components arranged in separate compartments with metal

    enclosures is intended to be earthed (Stokes, 2003). The boards are to be totally enclosed with

    sheets of steel fabricated for safety purposes. The components of the board included the main

    switch devices, circuit breaker and busbar chambers.

    Figure 3.4.1: Panel boards inside the Consumer Switch Room.

    Figure 3.4.2: A separated panel board that only supply electrical power to the air-conditioning system.

    Mr. Eddie, the person in-charged in M&E said that, the air-conditioning system is the

    largest and the most important system in Life Point Church. The breakdown of this system

    will influence much to the function of the building and its users. Hence it has to be separated

    by having an individual switch board that only takes control on itself to ensure that the falls

    in other systems will not interrupt the operating of it.

  • 30 | P a g e

    3.5 Switch Gear

    As mentioned, switch is one of the important part in a compartment of a panel board. A

    mechanical switching device is capable in making, carrying and breaking currents under

    normal circuit conditions. (Stokes, 2003) As observed, each switch gear in a panel board

    contains of a main circuit breaker, an earth leakage circuit breaker, and a meter. Busbar

    chamber is another main component that is hidden in the panel board.

    Diagram 3.5: Diagram shows the components in a switch gear.

    Switch Gear

    Switches Circuit Breaker Earth Leakage Circuit Breaker

    (ELCB)

    Busbar Chamber

    Metering apparatus

    Figure 3.5.1: The component in

    compartment in the panel board, which

    included switches, circuit breaker, and meter.

    Figure 3.5.2: A kilowatt hour meter is used

    for the reading of energy consumed.

    Panel

    Board

    Meter

    Circuit

    Breaker

    ELCB

    MCB

  • 31 | P a g e

    3.5.1 Switch

    Switch has a function which is more or the same as a circuit breaker. But switch is relatively

    cheaper than circuit breaker in a distributional system. The only difference between a switch

    and a circuit breaker is that switch does not interrupt fault current flow. (Stokes, 2003) The

    function of circuit breaker on interrupting current will be further explain.

    Figure 3.5.1.1: The switch to control capacity bank.

    3.5.2 High Performance Circuit Breaker

    Circuit breaker is an important feature that ensure the safety in the operation of an electrical

    grid. It is a device that could interrupts and makes, short-circuit current as well as operating

    on load current. (Stokes, 2003) It has to be turned on all time because there are two main

    tasks, first, is its responsibility in the daily switching of lines during normal operating on load

    current, and secondly for the disconnection of the power supply in case of power overload or

    short circuit while the power is off. (Pinnekamp, 2007) The type of circuit breaker used is a

    low-voltage high performance circuit breaker.

    Figure 3.5.2.1: High performance circuit breaker used found in the switch board

  • 32 | P a g e

    3.5.3 Earth Leakage Circuit Breaker (ELCB)

    Earth leakage circuit breaker (ELCB) is also an important part in the panel board. An ELCB

    is a device used in cutting off the power once it detects the happening of leakage from the

    installation to the earth. (Parmer, 2011) The type of ELCB used is a current operated. This

    component is also known as Residual-current devices (RCD). It trips the contact of the circuit

    conductors once the imbalance in current is detected.

    Figure 3.5.3.1, 3.5.3.2: The images show two different types of Residual-current Devices used in site.

    3.5.4 Busbar Chamber

    Busbar is a grounded copper bar in a panel board to which all the neutral and groundling

    wires are connected to different equipment such as distribution board, substation and the

    switch gear. Copper is chosen is because it could conduct electricity better than other metals

    especially brass and aluminium. Besides, it is relatively cheaper as well.

    Figure 3.5.4: Cables that are connected to the busbar chamber which is placed inside the board. It connects

    the busbar to the other electrical apparatus through different wires.

  • 33 | P a g e

    3.6 Mechanical and Electrical Room (M&E)

    M&E stands for the Mechanical and Electrical. The M&E room locates different distribution

    boards in it.

    3.6.1 Distribution Board (DB)

    The Distribution Board, refers to an equipment which connects, controls and protects a

    number of branch circuits fed from one main circuit of a wiring installation in a building or

    premises for easy and safe handling of incoming power supply. (The Development

    Commissioner, 2003) It might consists switches, bus bars, fuse link and some other protective

    equipments.

    3.7 Consumer Unit

    Figure 3.6.1.2: Members consisted in one

    Distribution Board.

    Figure 3.6: Outlook of the M&E room

    with different DB that controls different

    areas and systems which is located at ground

    floor.

    Figure 3.6.1: In the first and second floor, there is no

    room to store the DB. But they put the DB in a cabinet

    which is located in classroom.

    Figure 3.6.1.1: Example of Distribution

    Board. It is called DB in short.

  • 34 | P a g e

    3.7 Consumer Unit

    A consumer unit is very similar to the distribution boards where both acts as a control to

    different system. But consumer unit is smaller than DB and it is not directly connected to the

    main panel boards in the Consumer switch room. It is called fuse box in short. This unit

    contains a two-pole switch isolator for neutral supply cables and the phase. It also has three

    bars for the line, neutral and cpc (circuit protective conductor) to earth terminals. The line bar

    is provided with miniature circuit breakers (MCB) each to protect individual circuits from

    overload. (Hall & Greeno, 2007)

    3.7.1 Miniature Circuit Breaker (MCB)

    The low voltage miniature circuit breaker has the same function other circuit breakers. It is a

    fuse that switches off electricity when abnormal circuit condition is detected. But it is

    preferably use compare to a fuse because of its quick restoration and automatic system.

    Figure 3.7: Consumer unit found in the third floor which controls the lighting system in the sport

    complex.

    Figure 3.7.1: MCB found in the fuse box

  • 35 | P a g e

    3.8 Ring Breaker

    A ring breaker circuit would be taken around the site with supplies taken into each building.

    Using underground electrical cables which are loop-in into the buildings accordingly from the

    substations. This provides a higher stability of supply and lower number of cables compared

    to radial system. It is not connected to the either the distribution board or the consumer unit.

    3.9 Analysis

    In conclusion, due to safety purposes, the TNB rooms are well locked and have been taken

    care in good condition. It proves that the management of the building has been threating the

    TNB switch room as an important space since the high voltage of electrical power could

    endanger the users.

    Besides, there is a TNB check-up meter recording the data of power used in the

    consumer switch room. The checking up of the system is not only providing information to

    the TNB, it also ensure the safety of the building by protecting the system.

    In the other hand, the planning of the distribution board in the first and second floor

    are lack of consideration. This is because of the cabinet is placed in a public open area, the

    learning room for children. The engineers should have consider the safety of users before

    they plan the location to place the distribution boards.

    Lastly, as shown in Figure 3.8.1 and Figure 3.8.2, some of the plug points are not in

    good condition and the cable cover has also been destroyed leaving the cable exposed. The

    management should have more check-up and repair the broken parts to ensure the users

    safety.

    Figure 3.8.1 Circuit plug point found on site.

    Figure 3.8.2: The cable that connected the ring

    breaker circuit to the substation

  • 36 | P a g e

    MECHANICAL TRANSPORTATION SYSTEM

    4.0 Introduction

    Figure 4.0: Location of Elevator at Ground Floor Plan

    The church is using machine room less elevator system. This elevator system is newly built

    along with the new main lobby. There is only one passenger lift in this four storey building.

    The model of lift used is Schindler 3300AP. It installed next to main lobby entrance and main

    hall. It has to be designed according to local laws for safety purpose and user friendly. For

    example, the handrail of the car is installed according to the height of wheel chair. The total

    weight that it can withstand is approximately 1160kg according to the notice pasted in the

    elevator. It is able to transport 17 person at a time.

  • 37 | P a g e

    4.1 Literature Review

    Mechanical transportation system include elevator, escalator and moving walkway. In this

    report, the mechanical transportation system that we cover is vertical mechanical

    transportation system. Elevator is vertical transportation equipment that efficiently moves

    people and goods between floors of a building (Web.mit.edu, 2014).

    An ideal elevator installation provide minimum waiting period for the car at each

    landing level, comfortable acceleration, rapid loading and unloading of doors, quiet operation

    of door, secure, safe and quick (Pickard, 2002).

    The number of elevator installed is due to several factors, which are the population of

    users occupy the building, type of building occupancy, number of floor and height, starting

    and finishing times of the population, position of building in relation to public transport

    services (Pickard, 2002).

    The type of elevator can been classified to four system, which are hydraulic elevator,

    traction elevator, climbing elevator and pneumatic elevator. In the case study, the elevator we

    study is traction elevator. Type of elevator is chosen according to building height, building

    type, hoist mechanism, elevation users and type of users. (Safety rules for the construction

    and installation of lifts - Part 1: Electric lifts (First revision), 2012)

    There are three types of traction elevators, which are geared traction elevator, gearless

    traction elevator and machine-room-less elevator. The type of traction elevator can be

    identified by location of machine room and type of traction machine used. Machine-room-

    less elevator does not required machine room. The traction motor is directly attach to top side

    of lift shaft. MRL elevators saves building space as it does not required machine room. The

    building electricity can saves up to 70% as the motor works with Variable Voltage Variable

    Frequency (VVVF) drive. Hence, the expenses of MRL elevator is lower than other traction

    elevator. (Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First

    revision), 2012)

  • 38 | P a g e

    Case Study

    4.2.1 Operation Chart of Machine-Room-Less Traction Elevator

    ACVF

    Lift Frame

    Traction Machine

    Car Guide Counterweight Guide Counterweight

    Guide

    Gu

    Overspeed Governor

    Buffer

    Wire Rope

    Platform

    Door Operator Door Safety

    Devices

    Landing

    Landing Door

    Landing

    Fixtures

    Lift Shaft

    Lift Car

    Lift Pit

    Car

    Main Control Panel Second Floor Lift Frame

  • 39 | P a g e

    4.2.2 Control Panel

    Figure 4.2.2.1: Key Hole to open Main Control Panel

    Figure 4.2.2.2: Interior of Main Control Panel

    Figure 4.2.2.3: Elevator Section

    The main control panel is installed at lift frame of second floor for service purpose and

    safety purpose. It receive the voltage supplied from main electricity supply (TNB) and turn

    down the voltage to predetermined voltage level to controls the entire elevator system and

    ACVF machine that located in machine room. It receives signal from users through car

    operating panels. It also initiates raise or lower directional command and starting or stopping

    lift car.

  • 40 | P a g e

    4.2.3 ACVF

    Figure 4.2.3.1: ACVF in lift shaft

    Figure 4.2.3.2: Elevator Section

    The ACVF functions to receive signal from main control panel and control the components in

    lift shaft. It has been installed beside the traction motor. If there is emergency, the main

    control panel will cut down the electricity provide to ACVF, then the entire elevator system

    will be stopped.

  • 41 | P a g e

    4.2.4 Traction Machine

    Figure 4.2.4.1: Gearless Traction Motor in Machine

    Room

    Figure 4.2.4.2: Cooling Fan installed at Gearless

    Traction Motor

    Figure 4.2.4.3: Elevator Section

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. The ratio between the pitch diameter of sheaves, pulleys or drums and the nominal

    diameter of the suspension ropes shall be at least 40, regardless of the number of

    strands.

    Gearless traction machine is used in the studied elevator system. It includes machine, traction

    sheave, brake and encoder. The gearless motor used enable a direct power transfer to avoid

    loss of power. A cooling fan is installed on to the motor to avoid overheat. The traction

    sheave is connected directly to the shaft of the traction motor, the motor rotation is

    transmitted directly to the traction sheave without any intermediate gearing. The drive used

    gearless machine for smooth ride quality. As the gearless machine allow smooth ride quality,

    it does not required oil lubrication. A frequency converter is equipped with stand-by power

    mode for emergency purpose.

  • 42 | P a g e

    4.2.5 Overspeed Governor

    Figure 4.2.5.1: Plan view of Lift Shaft

    Figure 4.2.5.2: Overspeed

    Governor on top of lift shaft

    Figure 4.2.5.3: Safety Contact of

    Overspeed Governor

    Figure 4.2.5.4: Speed limit of

    Overspeed Governor

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. Tripping of the overspeed governor for the car safety gear shall occur at a speed at

    least

    Equal to 115 % of the rated speed.

    ii. The tripping speed of an overspeed governor for a counterweight or balancing weight

    safety gear shall be higher than that for the car safety gear according to (i), not,

    however exceeding it by more than 10 %.

    iii. The direction of rotation, corresponding to the operation of the safety gear, shall be

    marked on the overspeed governor.

    iv. The minimum breaking load of the rope shall be related by a safety factor of at least 8

    to the tensile force produced in the rope of the overspeed governor when tripped

    taking into

    Governor Pulley

    Safety Contact Governor Rope Tension Spring

  • 43 | P a g e

    account a friction factor max equal to 0.2 for traction type overspeed governor.

    v. On the overspeed governor a data plate shall be fixed indicating :

    a) The name of the manufacturer of the overspeed governor;

    b) The type examination sign and its references;

    c) The actual tripping speed for which it has been adjusted.

    There are two overspeed governor installed for this elevator system. One is installed on top of

    lift shaft and another one is installed at lift pit. It functions to stop and hold the governor rope

    with a predetermined force when car exceeding 40% of the rated speed. The predetermined

    speed of the car is approximately 1 m/s, if the car speed is detected over this predetermined

    speed, the tension spring will first response, then trigger the safety contact and locking plate.

    A cable is usually attached to the safeties on the underside of the car, which is governor rope.

    The governor rope runs down through a pulley at the bottom of the shaft and back up to the

    machine room and around the governor sheave.

  • 44 | P a g e

    4.2.6 Guide Rails

    Figure 4.2.6.1: Counterweight Guide

    Figure 4.2.6.2: Car Guide with Oil Lubricant Attached on it

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. The guide rails, their joints and attachments shall be sufficient to withstand the loads

    and

    forces imposed on them in order to ensure a safe operation of the lift.

    ii. For T-profile guide rails the maximum calculated permissible deflections are :

    a) 5 mm in both directions for car, counterweight or balancing weight guide rails on

    which safety gears are operating ;

    b) 10 mm in both directions for guide rails of counterweight or balancing weight

    without safety gears.

    iii. Guide rails for counterweights or balancing weights without safety gear may be made

    of

    formed metal sheet. They shall be protected against corrosion.

    Guide rails including car guides and counterweight guides. The machined channel and 'T'

    section secured to car and wall respectively. It guides the car and counterweights to ensure

    that they will travel in a uniform vertical direction. In order to ensure smooth ride, the cotton

    that soaked with oil attached to the surface of guide rails, hence it is able to lubricate the

    guide rails during travelling. The oil level has to be checked frequently to ensure it does not

    goes below the red line to improve travel quality.

    Counterweight

    Guide

    Cotton

    Car Guide

    Oil

  • 45 | P a g e

    4.2.7 Counterweight

    Figure 4.2.7.1: Counterweight Guide

    Figure 4.2.7.2 Elevator Section

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. If the counterweight or the balancing weight incorporates filler weights, necessary

    measures shall be taken to prevent their displacement. To this effect the following

    shall be used:

    a) Either a frame in which the fillers are secured, or

    b) If the fillers are made of metal, and if the rated speed of the lifts does not exceed 1

    m/s, a minimum of two tie-rods on which the fillers are secured.

    It provides traction and acts as a balance to the weight of car about 40% to 50% of the car

    rated load. It also reduces the size of lift motor and provide safety measure when the

    counterweight on its buffer, hence removing traction from car.

    Counterweight

  • 46 | P a g e

    4.2.8 Buffers

    Figure 4.2.8.1 Oil Buffer at Lift Pit

    Figure 4.2.8.2: Elevator Section

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. Lifts shall be provided with buffers at the bottom limit of travel of the car and

    counterweight

    Oil buffer is used in this elevator system. It functions to accumulate and dissipate the kinetic

    energy of the car or counterweight. Oil buffer is commonly used for traction elevators. It is

    combination of oil and springs to reduce speed of descending car or counterweight. It is

    located in elevator pit. It requires routine cleaning and painting to ensure it is in well

    performance specification.

  • 47 | P a g e

    4.2.9 Schindlers Traction Media

    Figure 4.2.9.1: Traction Pulley in Traction Machine

    Figure 4.2.9.2: Elevator Section

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. The ends of each chain shall be fixed to the car, counterweight or balancing weight, or

    suspension points of the dead parts of reeved chains by suitable terminations. The

    junction between the chain and the chain termination shall be able to resist at least 80 %

    of the minimum breaking load of the chain.

    ii. An automatic device shall be provided for equalizing the tension of suspension ropes

    or chains, at least at one of their ends.

    iii. Rope traction shall be such that the following three conditions are fulfilled :

    a) The car shall be maintained at floor level without slip when loaded to 125 %.

    b) it shall be ensured that any emergency braking causes the car, whether empty or

    with rated load, to decelerate with a value not exceeding the setting of the buffer,

    including reduced stroke buffer ;

    Instead of using wire rope, the traction media has been used due to the improved elasticity

    and smaller space requirement. The traction pulley for steel ropes is replaced by an only

    85mm traction shaft. It has 8 traction media to connect to the car for safety purpose. It

    requires smaller motor, which benefit the machine-room-less elevator system. It is connect to

    the car and allow vertical travelling of car.

    Traction Pulley Traction Media

  • 48 | P a g e

    4.3 Safety System

    4.3.1 Hoistway Door Interlock

    Figure 4.3.1.1: Eye of the car level

    Figure 4.3.1.2: Hoistway Door Interlock

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. It shall not be possible in normal operation to open a landing door (or any of the

    panels in the case of a multi-panel door) unless the car has stopped, or is on the point

    of stopping, in the unlocking zone of that door.

    ii. The unlocking zone shall not extend more than 0.20 m above and below the landing

    level.

    iii. Each landing door shall be provided with a locking device satisfying the conditions of

    7.7.1.This device shall be protected against deliberate misuse.

    iv. The effective locking of the landing door in the closed position shall precede the

    movement of the car. However, preliminary operations for the movement of the car

    may take place. The locking must be proved by an electric safety device in conformity

    with 14.1.2.

    v. The car shall not be able to start until the locking elements are engaged by at least 7

    mm.

    vi. The locking elements and their fixings shall be resistant to shock, and be made or

    reinforced with metal.

    It is used to prevent car door to open at false landing level. The eye has been preset to

    certain height and level to allow the car door to be opened. If the door open in false level, the

    eye detected the information, it triggered the interlock function, prevent the door to be opened.

  • 49 | P a g e

    If the doors are forced open, the interlock circuit will be broken, causing the elevator to stop

    instantaneously.

    4.3.2 Progressive Safety Gear

    Figure 4.3.3.1: Eye of the car level

    Figure 4.3.3.2: Hoistway Door Interlock

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. The car shall be provided with a safety gear capable of operating in the downward

    direction and capable of stopping a car carrying the rated load, at the tripping speed of

    the overspeed governor, even if the suspension devices break, by gripping the guide

    rails, and of holding the car there.

    ii. A safety gear operating in upward direction may be used in accordance with 9.10.

    iii. NOTE: The safety gear operating devices shall preferably be located at the lower part

    of the car.

    Safety gear is a mechanical device to stop the elevator car and counterweight by gripping the

    guide rails when the car is travelling over pre-determined speed. Progressive safety gear

    retardation is affected by breaking action on guide rails to limit the forces on elevator car and

    counterweight. A pair of safety gears is installed in bottom part of car sling and operated

    instantaneously by linkage mechanism that actuated by overspeed governor.

    Safety Gear

  • 50 | P a g e

    4.4 Analysis

    Figure 4.4.1: Exhaust fan at the corner of Lift

    Shaft

    Figure 4.4.2: Position of Exhaust Fan at Lift Shaft

    Safety rules for the construction and installation of lifts - Part 1: Electric lifts (First revision)

    i. The well shall be suitably ventilated. It shall not be used to provide ventilation of

    rooms other than those belonging to the lift.

    ii. The machine rooms shall be suitably ventilated. Should the well be ventilated through

    the machine room, this has to be taken into account. Stale air from other parts of the

    building shall not be extracted directly into the machine room. It shall be such that the

    motors, and equipment, as well as electric cables, etc., are protected as far as it is

    reasonably practicable from dust, harmful fumes and humidity.

    NOTE: In the absence of relevant regulations or standards, it is recommended that ventilation

    openings at the top of the well, with a minimum area of 1 % of the horizontal section of the

    well, are provided.

    UBBL

    i. Where openings to lift shafts are not connected to protected lobbies, such lift shafts

    shall be provided with vents of not less than 0.09 square metre per lift located at the

    top of the shafts. Where the vent does not discharge directly to the open air the lift

    shafts shall be vented to the exterior through a duct of the required FRP as for the lift

    shafts.

    ii. Every opening in a lift shaft or lift entrance shall open into a protected lobby unless

    other suitable means of protection to the opening to the satisfaction of the local

  • 51 | P a g e

    authority is provided. These requirements shall not apply to open type industrial and

    other special buildings as may be approved.

    The traction machine is attached by using permanent magnet at the top of lift shaft. Exhaust

    fan is installed to reduce room temperature in lift shaft as these components release heat

    during operation. An exhaust fan is installed on top of car too to allow ventilation in lift car.

    Figure 4.4.3: Checklist for maintenance by DOSH

    Figure 4.4.4: Checklist for maintenance by DOSH

    Maintenance of elevator has been done every month according to the checklist in Figure 4.4.3

    and Figure 4.4.4 to ensure the elevator system satisfies the requirement for safe ride. The oil

    level should not be lower than the red line. The maintenance should be aware and fill in the

    oil tank.

    Figure 4.4.5: Oil Level of Oil Tank

  • 52 | P a g e

    FIRE PROTECTION SYSTEM

    5.0 Introduction

    LifePoint Church is equipped with hose reel system, fire alarm system, heat and smoke

    detectors, portable fire extinguishers and other passive fire systems. The walls are protected

    with Fire Rated Walls to ensure the building is able to withstand the fire for a certain of time

    to allow occupants to escape. For a four-storeys building, water sprinkler system is not

    present. Due to its height below 18.3m, the building does not required any dry riser system.

    Every fire exit and escape staircase is equipped with a Keluar sign to guide the

    building occupants to the exit path. Besides, a simplified floor plan as seen in Diagram 4.0

    with indications on the emergency exit is located next to the lift on every level of the building.

    Emergency lights are also installed at each areas of the building to ensure illumination for the

    building occupants to the nearest exits in thick smokes or sudden blackout.

    Figure 5.0: Ground floor plan with legend

  • 53 | P a g e

    5.1 Literature Review

    Fire, is an oxidation process that releases energy in the form of heat and light and gases. This

    process known as combustion requires fuel, high temperature and oxygen to occur. The

    results caused by combustion such as flame, heat, toxic gases and insufficiency of oxygen can

    pose extreme hazards to the occupants and buildings therefore fire protection is needed

    (Grondzik, Stein, Reynolds & Kwok, 2010). There are three types of fire protection, active

    system, passive system and education of building owners and occupants about fire safety and

    fire systems.

    For successful control, suppression, or extinguishment of fires, the active system

    relies on containing and acting on the fire while it is still manageable to be effective. Hence

    active system needs to work together with passive system that slows down the spread of fire

    (Roach, 2014).

    Requirements for the fire systems vary according to the building types, floor area,

    height of building, types of occupancy and function of building (Uniform Building By-Laws,

    2006).

    Active Fire Protection

    An action is required for active fire protection systems to work, either it to be by manual,

    electrical or mechanical (Roach, 2014). Active system detects fire through detector that will

    send signals to devices such as alarm bell to alert the building occupants. This system then

    controls fire by activating fire shutter doors to limit the spread of fire and smoke to other area

    of the building. It suppresses or extinguish fire through carbon dioxide system, sprinklers,

    hose reel system, riser system and the use of fire hydrant.

    Passive Fire Protection

    Passive system does not require external power or any activation and can be grouped into

    three categories according to its purposes:

    i) Limiting the growth rate of fire

    ii) Compartmentation of fire

    iii) Providing emergency escape from fire areas

    Passive system slows down fire with fire-resistant walls, floors, doors or spray-on

    fireproofing mixture on critical members such as beams and columns. This protects the

  • 54 | P a g e

    building from collapsing due to the weakening of building parts in high temperature

    condition and provides building occupants with more time to evacuate.

    The division of building into one or more fire compartments is intended to prevent the

    spread of fire to nearby compartments and acts as the maximum extension area of the fire

    (Botma, 2013). Fire compartment needs to be enclosed by fire barriers to prevent the fire

    from spreading into other rooms when the fire is from the fire compartment or to act as a

    protected area for the occupants when the fire occurs from outside the fire compartment area

    (Buildings Department, 2012).

    Passive system provides escape for occupants from fire areas through fire staircase,

    corridors and emergency light (Roach, 2014) and by setting regulations such as dead end

    limit to allow occupants to reach the nearest fire exits in time.

  • 55 | P a g e

    Case Study

    5.2 Active Fire Protection

    5.2.1 Hose Reel System

    Figure 5.2.1: Schematic drawing from hose reel system

    5.2.1.1 Water Storage Tank

    UBBL:

    247. (1) Water storage capacity and water flow rate

    for fire fighting systems and installations shall be

    provided in accordance with the scale as set out in

    the Tenth Schedule to these By-laws.

    [Tenth Schedule]

    Minimum storage required for the first hose reel-

    2275 litre

    For each additional hose reel- 1137.5 litre up to a

    maximum of 9100 litre

    (2) Main water storage tanks within the building,

    other than for hose reel systems, shall be located at

    ground, first or second basement levels, with fire

    brigade pumping inlet connections accessible for

    fire appliances.

    Figure 5.2.1.1.1 Hose reel storage tank

    Pressure switch

    Pump control panel

    Storage tank Gate valve

    Hose reel

    Standby diesel hose reel pump

    Pressure gauge

    Electric duty pump

    Water

    main

    Check valves

    Drainage

    Gate valve

  • 56 | P a g e

    Figure 5.2.1.1.2: Location of water storage tank on Ground Floor Plan

    Figure 5.2.1.1.3: Storage tank level indicator

    This storage tank is to supply water only for the hose reel system. It is located on the ground

    floor of the building to allow it to be accessible for fire brigade, which conforms to the UBBL

    247(2). This hose reel storage tank is made of pressed steel and it is 12 x8 x 4 (3.66m x

    2.44m x 1.22m) with a capacity of 9085 litres, approximately the maximum capacity stated in

    UBBL 247(1).

    The figure on the level indicator cannot be less than 7 for the building and it will be checked

    once every three days to ensure the water level and the pressure in the tank is adequate to

    supply for the hose reel system during fire emergency.

  • 57 | P a g e

    5.2.1.2 Pumps

    The existing water tank pumps can be operated automatically or manually. The electric duty

    pump is the main pump for the water storage to pump water to all hose reels when fire

    emergency happens. If the main pump stops operating during fire, the standby diesel pump

    will pump the water up.

    When the hose reel is in use, water flows out of the hose causing the increase in air space and

    decrease in the air pressure in the pipe. This causes the pressure in the check valves to drop

    Figure 5.2.1.2.1: Electric duty pump(right) and standby diesel hose reel pump(left)

    1. Electric duty pump

    2. Standby diesel pump

    3. Flexible coupling

    4. Check valve

    5. Gate valve

    6. Pressure gauge

    7. Pressure switch

    1 2

    4

    3

    5

    6 7

    Figure 5.2.1.2.2: Parts of water storage pumps

  • 58 | P a g e

    below the adjusted pressure field setting of the pressure switch. This triggers the automatic

    operation of the pump to supply water for the hose (Petromas Infiniti Sdn. Bhd., 2012). On

    the other hand, the pump will shut off when the pressure is higher than the pre-set range.

    Figure 5.2.1.2.5: Hose reel duty pump and stand by pump control panels

    Figure 5.2.1.2.3: Pressure gauge and pressure switches

    Figure 5.2.1.2.4: The control panel is to operate the pumps by manual and to check the failure of either

    pump.

  • 59 | P a g e

    5.2.1.3 Valves

    5.2.1.4 Hose Reel

    UBBL:

    248. (1) Wet riser, dry riser, sprinkler and

    other fire installation pipes and fittings shall

    be painted red.

    248. (2) All cabinets and areas of recessed in

    walls for location of fire installations and

    extinguishers shall be clearly identified to

    the satisfaction of the Fire Authority or

    otherwise clearly identified.

    Diagram 5.2.1.4.3: Hose reel diagram

    Figure 5.2.1.4.1: Hose reel

    Check valve:

    Also known as non-return valve, only allows water to flow in

    one direction.

    Gate valve:

    To allow or restrict flow of water through the pipe by turning it

    manually.

    Figure 5.2.1.4.2: Hose reel instruction and specification

    Swing

    Adjustable

    nozzle

    Hose

    Hose reel drum

    Valve

    Figure 5.2.1.3: Check valves and gate valves

  • 60 | P a g e

    Hose reel acts as a first aid firefighting equipment for building users and should be located

    within 30m hose coverage of the hose reel and in noticeable places beside exit doors or

    staircases or along escape routes. It should also be located at places least likely to be

    endangered by fire such as staircase landing (Hall & Greeno, 2013). For every 800m2 of floor

    area there should be a hose reel installed. The building has a hose reel for every main areas

    on the ground floor as seen in Diagram instead for every 800m2 due to the division of spaces.

    This allows users from each space to have their own hose reel.

    The hose reels used are manufactured according to Australian Standard AS1221 and are

    approved by QAS Australia. The rubber hose is 30 meters in length and has a test pressure of

    1.5MPa (15 bar).

    945.7m2

    246.6m2

    288.0m2

    239.2m2

    65.7m2

    36m 24m

    27m

    Hose reel (in building)

    Hose reel (outside building)

    Exit door

    Figure5.2.1.4.4: Location of hose reels in Ground Floor Plan

  • 61 | P a g e

    The hose reels used are all swing type automatic hose reels which have built-in internal

    valves. The internal valve functions by opening after two revolutions of the hose reel and will

    close automatically when the hose is wound back to the reel (Semarak Industri Sdn. Bhd.,

    2013). Swing type hose reel allows the hose to be pulled in different directions.

    Figure 5.2.1.4.5: Hose reel cabinets

    Even though the cabinets have see-through glass panels but there is no identification such as

    painted red or signage on the cabinets as required by UBBL 248. (2)

    5.2.2 Fire Alarm System

    Smoke and heat triggers the detectors

    signal sent to alarm system

    Building occupants are

    alerted

    electrical signals sent to other active systems to control and

    extinguish the fire

    Signal sent to

    Fire Alarm

    Control Panel

    at Guard

    House

    Location of

    fire or

    smoke is

    identified

    Fire is

    extinguished

    manually

    Manual

    breakglass

    unit or key

    switch box

  • 62 | P a g e

    5.2.2.1 Smoke and Heat Detectors

    Figure 5.2.2.1.3: 7 Location of smoke detectors and heat detectors in Ground Floor Plan

    Figure 5.2.2.1.2: Heat detectors

    Smoke detector

    Lift

    Heat detector

    6m

    UBBL:

    153. (1) All lift lobbies shall be provided with smoke detector.

    Pantry and toilet area

    Figure 5.2.2.1.1: Smoke detectors

    Connection to fire alarm

    panel (at Guard house)

  • 63 | P a g e

    The spacing for the heat detectors is approximately 6m each for LifePoint Church as to

    ensure quick detection of fire outbreak. From Figure 5.2.2.1.3, one smoke detector is located

    at the lift lobby, conforming to the UBBL 153. (1). Another smoke detector is also installed

    at the water storage tank area, to detect possible smoke coming from the pumps.

    For the building, no smoke or heat detectors are installed at the pantry and toilet areas. As

    seen in Figure 5.2.2.1.3, all detectors are connected to the Fire Alarm Panel at the Guard

    House.

    Smoke detector

    There are commonly two types of smoke detectors available in the market, which is the

    photoelectric and ionization. Photoelectric detector requires more smoke than ionization

    detector to be activated (Smoke detectors, 2006).

    The light beam is projected to the supervisory photocell in a straight line. When smoke enters

    the detector, the light beam is deflected to the alarm photocell and this creates a current to

    activate the alarm system.

    Figure 5.2.2.1.4: Photoelectric detector (Grondzik, Stein, Reynolds & Kwok, 2010)

  • 64 | P a g e

    Opposite charged ions are attracted by the positive and negative charged plate electrodes

    which causes the flow of ions. The movements of ions between the plates then produce small

    electric current. When smoke particles enter the chamber, the ion flow slows down and the

    current is disrupted. This causes the alarm to sound.

    Heat Detector

    This heat detector has a combination of rate-of-rise and fixed temperature units. The rate-of-

    rise unit operates when the rate of surrounding temperature rises exceeding a preset amount

    usually around 8oC/minute. This rate of change of temperature causes the bellows to expand

    and touches the rate-of-rise contact and sound the alarm.

    For the fixed temperature unit, the bimetal element will expand when a certain temperature is

    achieved usually at 57 oC or 85 oC. The fixed temperature contact attached on the bimetal

    element will then touches the other fixed-temperature contact and electric current will flow

    and activate the alarm system (Grondzik, Stein, Reynolds & Kwok, 2010).

    Figure 5.2.2.1.5: Ionization smoke detector (Hall & Greeno, 2013)

    Figure 5.2.2.1.6: A combination of rate-of-rise and fixed temperature detector (Grondzik, Stein, Reynolds & Kwok, 2010)

  • 65 | P a g e

    5.2.2.2 Manual Breakglass Unit and Key Switch Box

    The fire alarm system alerts the building occupants when there is a fire outbreak so that

    immediate safety measure and firefighting action can be taken. This system can be operated

    either automatically through the detectors or manually by breaking the glass of the breakglass

    unit to activate the fire alarm.

    Figure 5.2.2.2.3, Figure 5.2.2.2.4: Manual key switch boxes located outside of TNB switch room and

    transformer room

    Individual manual key switch boxes are installed outside of each switch room and

    transformer room. This enables quick activation of fire alarm and release of carbon dioxide

    gas when the room is on fire by turning the key of the key switch box. Key switch boxes are

    used here instead of manual breakglass unit is to prevent anyone to intentionally activate the

    Figure 5.2.2.2.2: Breakglass unit

    Figure 5.2.2.2.1: Alarm bell and breakglass unit

  • 66 | P a g e

    carbon dioxide system without emergency as only permissioned individuals and the Fire

    Authority have the key.

    The breakglass units and fire alarms are located along fire escape routes or next to the

    emergency exits. This enables building occupants to be able to activate the fire alarm system

    when fire occurs.

    Diagram 5.2.2.2: Fire Alarm System on Ground Floor Plan

    Smoke detector

    Fire Alarm Panel at Guard

    House Heat detector

    Connection to Fire Alarm

    Panel

    Fire alarm system junction

    box

    Fire Alarm

  • 67 | P a g e

    5.2.2.3 Fire Alarm Control Panel

    The Fire Alarm Control Panel is located at the Guard House because it is detached from the

    main building so the fire could not spread to it and there will be guards monitoring the fire

    alarm panel 24 hours daily so any fire emergency can be detected immediately.

    The Fire Alarm System Junction Box is located at the cafeteria, next to the Consumer Switch

    Room. This is because the Consumer switch room, TNB switch room and TNB transformer

    room have a separated alarm system circuit which is connected to the junction box.

    5.2.3 Portable fire extinguisher

    UBBL:

    227. Portable extinguisher shall be provided in

    accordance with the relevant codes of practice and shall

    be sited in prominent positions on exit routes to be

    visible from all directions and similar extinguishers in a

    building shall be of the same method of operation.

    Figure 5.2.3.1: Portable fire extinguisher

    Figure 5.2.2.3.1: Fire Alarm Control Panel at

    the Guard House

    Figure 5.2.2.3.2: Fire Alarm System Junction Box

  • 68 | P a g e

    Figure 5.2.3.2: Parts of ABC dry powder fire extinguisher

    Diagram 5.2.3: Location of portable fire extinguishers in Ground Floor Plan

    Main hall

    New Main

    Hall

    Dry chemical powder

    Nozzle

    Discharge lever

    Locking ring pin

    Siphon tube

    Carrying handle

  • 69 | P a g e

    Portable fire extinguisher is a compressed cylindrical device used for small fire and as first

    aid fire control. Different color codes represent the different fire sources appropriate for the

    extinguisher (Greeno, 2005). The portable fire extinguishers used are red with blue band,

    indicating it as 9kg ABC dry powder extinguishers which its applications are stated below:

    Source: Hall, F., & Greeno, R. (2013). Portable fire extinguishers.

    As seen in Diagram 5.2.3, the portable fire extinguishers are placed next to the emergency

    exits or along the escape paths which complies to the UBBL 227. No portable fire

    extinguisher is found in the office area.

    For easy reach, portable fire extinguisher should always be hung on wall brackets. Besides it

    should not be placed under excessive heat or cold, as the temperature limit stated on the

    portable fire extinguisher is -20oC to 60 oC.

    The fire extinguisher is placed on the ground and next to the window, under the risk of being

    exposed to high temperature or accidentally knocked down by building occupants.

    Class A organic solids (wood, paper, cloth etc)

    Class B flammable liquids (petrol, oil, paint etc)

    Class C

    flammable gases (methane, propane, acetylene etc)

    Electrical hazards

    Figure 5.2.3.3, Figure 5.2.3.4: Placement of portable fire extinguishers

  • 70 | P a g e

    5.2.4 Hydrant system

    5.2.4.1 Pillar hydrant

    Fire hydrant system functions as water source for fire protection. The pillar hydrants are

    located at the opposite end of LifePoint Church site boundary. The nearest pillar hydrant to

    the water storage tank is approximately 45metres away which exceeds the length of the

    30metres hose.

    Building area

    Fire hydrant Hydrant cabinet

    (with nozzles, hose

    and accessories)

    Water main

    UBBL:

    Part VIII 225. (2)Every building shall be

    served by at least one fire hydrant located not

    more than 91.5 meters from the nearest point

    of fire brigade access.

    UBBL 1984 By Laws-225(2&3):

    Not more than 6 meter from the building

    Not more than 30 meter away from the entrance to the building

    When the hydrant is installed within the

    owners boundary, each should be provided with 30meters of 65mm diameter rubber lined

    hose, instantaneous couplings and nozzles.

    Figure 5.2.4.1: Pillar hydrants

  • 71 | P a g e

    5.2.4.2 Hydrant cabinet

    The hydrant cabinet is placed next to the pillar hydrant and has a key attached to it. In case of

    fire emergency, the key is used to unlock the cabinet and to retrieve the fire hose with nozzle

    and accessories. The hose is to be attached to the pillar hydrant next to it.

    Main entrance

    50.421m

    47.415m

    Figure 5.2.4.2: Hydrant cabinet near the guard house

    Diagram 5.2.4.1: Locations of fire hydrants on Ground Floor Plan

    Guard House

  • 72 | P a g e

    5.3 Passive Fire Protection

    5.3.1 Fire Suppression System

    Diagram 5.3.1.1: Schematic diagram on suppression system.

    Diagram 5..3.1.3: The location of the fire suppression system.

    4 1

    5

    2

    3

    LEGEND 1. Flashing Lights 2. Fire Alarm 3. Manual Fire Alarm with

    Break Glass

    4. Nozzle

    5. CO2 Cylinder

    Fire Detector Fire Alarm

    Flashing Light

    CO2 Cylinder

    Diagram 5.3.1.2: Annotation on members in the system.

  • 73 | P a g e

    The fire suppression system is required within any electrical room although an exclusion is

    allowed for rooms with generators or transformers. The CO2 is an electrically nonconductive

    gas that is 50% more dense than air hence it will cover the fire reducing oxygen and prevents

    combustion.

    Figure 5.3.1.1: The flashing lights in green state.

    The fire suppression system is required within any electrical room although an

    exclusion is allowed for rooms with generators or transformers hence the reason it is only

    present in the switch room in the church. When fire is detected in the switch room, the

    flashing light above the door will turn red before the activation of the gas system. This is to

    prevent the users from entering as the CO2 gas released is an asphyxiate, especially in a small

    room and can build up to a point where respiration becomes difficult.

    Figure 5.3.1.2: CO2 cylinder attached to steel piping.

  • 74 | P a g e

    UBBL:

    The use of CO2 gas by requirements of National Fire Protection Association or

    Jabatan Bomba in the following rooms; transformer room, high voltage switch room,

    power grid room & electric T.E.N. room.

    Figure 5.3.1.3: CO gas

    cylinder.

    Figure 5.3.1.4: Nozzle where extinguisher

    agent is discharged.

  • 75 | P a g e

    5.3.2 Fire Escape System

    5.3.2.1 Fire Rated Doors

    LEGEND 1. Illuminated Exit Sign 2. Stopper 3. Push Bar 4. Latches & Bolts 5. Fire Vision Panel 6. Door Handle 7. Fire Notice

    1

    2

    4 3

    5

    6

    7

    Figure 5.3.2.1.1: 900 x 2100 1

    hour fire rated door.

    Figure 5.3.2.1.2: 1800 x 2100 2 hour fire rated door.

  • 76 | P a g e

    Figure 5.3.2.1.3: Fire rate door approval label.

    Fire rated doors are compartmentalised throughout the building to delay the spread of fire and

    smoke from one area another area. These fire doors come with an aluminium door closer

    mounted on top of the door to ensure the doors close after being opened as closing a door

    remains a low priority when escaping a fire. Certain fire rated doors have a 100mm x 600mm

    vision panel that allows people to see the other side of the door before entering. As people

    tend to panic during a fire, most fire rated doors that has the most circulation come equipped

    with a push bar allowing people to be able to open the door with ease.

    UBBL:

    133. Fire Resisting means the construction so designated, including doors, has a minimum

    standard of fire-resistance of not less