brussels airport, a roadmap to a-cdm implementation · …make sure the dialogue stays open-minded...
TRANSCRIPT
Brussels Airport, a roadmap to A-CDM implementation
• BRU A-CDM: where did we start from?
• BRU A-CDM: how did we proceed?
• BRU A-CDM: how did we communicate?
• BRU A-CDM: implemented! What about “customer care”?
• BRU A-CDM: the way ahead
• BRU A-CDM: what we have experienced
• Brussels Central Database (CDB): a head start for data sharing through existing syst-to-syst links
Where did we start from?
STAFF
PAGES
CENTRAL
DATABASE
BRU
TOWER
[User
Interfaces]
DGS
Where did we start from?
As a result of CDB ops, a basic understanding of stakeholder opsby each airport partner
• Joint meetings: internal & external usergroups
• Bilateral meetings: set-up of data input procedures
A basis for enhanced collaboration towards A-CDM implementation
How did we proceed?
INBOUND
-2hrs ATFM Slotallocation
-3hrs Flight Plan Submission
Data coherency
check
ATOTALDT
Taxi InLocal Radar Data
Take Off fromOutstation
1 2 3 4 65
FinalApproach
OUTBOUND
Taxi Out
ATOT
ASAT
AOBT
14
15 16
7/8
TURN ROUND
Boarding
AIBTAGHT
TOBT
Minimum TurnRound Times will be
in the CDM platformand can be updated
TSAT
ARDT
ASRT
9 10
11
12/13
• Installing dedicated “task forces” to analyse and map the inbound/turn around/outbound process
• Matching the 16 milestones to the process map
• Each process delivering a “best known” time to the next
How did we proceed?
AO
IFPS CFMU
BSC
GH
ACIS
ATC
E-DPI
GH
ACIS
TOBT = EOBT
1
2
ATC submits E-DPI to CFMU (at SOBT-2H) based upon SOBTand ACIS submits TOBT based upon IOBT = EOBT (at SOBT-2H)
Mapping scenarios to grasp the TOBT & DPI concept
How did we proceed?
ACIS development:
• CDB (Central Database): defining the CDM information elements
• TMA (Terminal Management Application): set-up of CDM data tab
◊ Airport◊ GH staff
• Staff Pages application: web based, easy-to-use, a/c operator based login
◊ Airport community◊ Remote OCC’s, …
• Simultaneous developments in GH and ANSP systems
How did we proceed?
What we kept in mind:
Strict adherence to Eurocontrol functional requirements (terminology, acronyms…)
• A guideline to cover all aspects of the project• A lead through difficult discussions• A back up for CDM procedure adherence• Currently the only “book” to go by for alignment between all A-CDM implementation initiatives (enabler buy-in from AO and a way to CDM-success)
How did we proceed?
TMA view
How did we proceed?
Staff Pages View
How did we proceed?
The CDM alert mechanism:
• Developed out of existing CDB functionality (on line data quality checks)
• Notification by email
• Started off as manual procedure, developing a fully automated mechanism
How did we proceed?
strict project set-up���� setting realistic, “best fit” target dates
���� progress follow-up through well-plotted meeting sequence!
� Steering group meetings: every 2 months
� Advisory group meetings: every 3 weeks
� ARR, turn around, DEP and TOBT “taskforces”: independent meeting schedule, progress reporting on AG meetings
! Backward project planning by bottom-up feedback
How did we proceed?
Opting for a sequenced start-up:
� June 15th 2010: start-up in local mode
• both GH, selected set of AO’s involved• testing ACIS and alert mechanism performance
� June 29th 2010: kick-off
• DPI transmission by Belgocontrol• All airlines involved• Support, adjust, communicate…
� August 17th 2010: procedure adherence
• focus on TOBT/EOBT alignment
How did we proceed?
Last but not least… General Aviation ops
How did we communicate?
Phased project introduction letters via email and letter
How did we communicate?
� The Brussels info brochure
How did we communicate?
� Info sessions for the community, up to 6 in the month of July
� Staff briefings by GH and Belgocontrol
� The BRU info cards
Implemented! What about “customer care”?
� Monthly info sessions, still ongoing, incorporating use cases and
actual operational scenarios
� Dedicated sessions for “tough customers”
� Close monitoring of, and feedback on ACIS performance & alert messaging. Set-up series of “CDM core meeting”
The way ahead
� How are we doing? Performance monitoring
� How do we stay tuned? Procedure adherence… Discipline!
� What if… Fallback procedures
� Ops in adverse weather conditions. “CDM 2.0” kick-off with:
� de-icing process communication by GH� airport operational status by BRU� APOC-approach (establish reduced airport capa, communicate, coordinate corresponding scenarios)
� Sharing experiences to keep our different A-CDM set-ups aligned in the interest of the AO’s
What we have experienced…
… data sharing… BUT also creating mutual process insights!
… “believers” at all stakeholders, at every organisation level
… seamless interaction of your local CDM-representatives between the project and their own organisational disciplines (IT, operations, commercial, legal…)
… good CFMU contacts
… make sure the dialogue stays open-minded at all times, whatever difficulties ahead
… speeding up implementation to a “critical mass” of A-CDM airports will speed up the network benefits for us all