bruce peterson handout 6 per page.pdf

Upload: abimana

Post on 07-Aug-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    1/36

    The Rehabilitation AlternativeHuey P. Long Bridge Case Study

    Bruce E. Peterson, P.E.Project Manager

    Modjeski and Masters, Inc.

    March 22, 2010

    Introduction• Replacement vs. Rehabilitation

    • Project Background

    • 4 Construction Contracts – Main Bridge – Substructure – Main Bridge – Superstructure

    Truss Widening – Railroad Modifications – Approaches and Main Bridge

    Deck Widening

    BREAK

    • Project Status – Project Timeline – Construction Photographs

    EXISTING

    PROPOSED WIDENING

    Replacement vs. RehabilitationBridge construction represents a large capital investment.

    Through time, all bridges receive “routine maintenance”.However, eventually they must be replaced or rehabilitated.

    Beyond the obvious difference in cost, there are othersignificant differences between these two approaches.

    How is the decision made?

    What influences the choice between these two alternatives?

    Replacement vs. RehabilitationLouisiana Dept. of Transportation and Development

    (LADOTD)

    Methodology for Selecting and Programming Bri dges forReplacement and Rehabilitation

    Priority for the selection of bridges for replacement orrehabilitation with Federal bridge replacement funds basedon three (3) parameters:

    1. Structural adequacy

    2. Functional adequacy and serviceability

    3. Essential for public use

    Replacement vs. RehabilitationThe three parameters are based on the following information:

    1. Structural deficiency

    2. Posted bridges (weight limits below statutory limits)

    3. Traffic count (ADT)

    4. Class of highway

    5. Available detour routes

    6. Bridge geometry (particularly bridges < 20 ft. wide)

    7. Bridge inspection reports

    8. Local district recommendations for replacement(submitted annually)

    Replacement vs. RehabilitationFederal Highway Administration (FHWA) formula for prioritizing

    bridges

    Overall rating called a “sufficiency rating”

    Sufficiency rating assigns a numeric value ranging from 0 to

    100 to a given bridge with the following percentage pointsapplied to each parameter

    ITEM WEIGHT

    Structural Adequacy 55 %

    Functional Adequacy andServiceability 30 %

    Essential For Public Use 15 %

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    2/36

    Replacement vs. RehabilitationRequirement f or replacement:

    • Sufficiency Rating < 50

    • Classification as structurally deficient or functionallyobsolete

    Requirement for rehabilitation:

    • Sufficiency Rating < 80

    Replacement vs. Rehabilitation As previously noted there are three elements to the Sufficiency

    Rating

    1. Structural Adequacy2. Functional Adequacy and Serviceability

    3. Essential for Public Use

    Let’s examine each in detail.

    Replacement vs. RehabilitationStructural Adequacy

    Most important factor in evaluation process as a bridge failurecould be catastrophic

    Determined from:

    • List of posted bridges (bridges with load restrictions)

    • Bridge inspection reports

    • Local district recommendations

    Replacement vs. RehabilitationFunctional Adequacy and Serviceability

    Bridge geometry a key element

    • Clear roadway width most important factor

    • Narrow bridges, if structurally adequate, can be widenedrather than replaced

    Determined from:

    • Bridge inspection reports

    • Local district recommendations

    Replacement vs. RehabilitationFunctional Adequacy and Serviceability (con’d)

    Serviceability is related to factors such as

    • Stream scour

    • Maintenance for movable bridges

    • Deck deterioration

    Other important factors include frequency and severity ofmarine, railroad, and automotive traffic accidents

    Replacement vs. RehabilitationEssential For Public Use

    Determined by the:

    • Traffic count (ADT)

    • Class of highway

    • Available detour routes

    Structural and functional adequacy of the bridge is evaluatedwith the traffic count in order to minimize exposure tounsafe conditions

    Example: two bridges with the same degree ofinadequacy, the one with the higher traffic volumewould receive the higher priority

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    3/36

    Replacement vs. RehabilitationEssential For Public Use (con’d)

    Bridges located on a truck or school bus route or crosses a

    major river or stream receive extra attentionNon-redundant routes (no available detours) receive a higher

    priority than bridges on redundant routes

    Replacement vs. RehabilitationHow Select?

    Numerous rational methods available

    Recommended procedure for State of Louisiana1. Compile 3 lists

    • Bridges with lowest sufficiency rating

    • Bridges with the highest priority based on local districtrecommendations

    • Bridges that are most severely posted for loadrestrictions

    2. Generally, if a bridge makes all three lists, it will have a highpriority for replacement

    Replacement vs. RehabilitationSTRUCTURAL

    ADEQUACY

    FUNCTIONAL

    ADEQUACY AND

    SERVICEABILITY

    ESSENTIALLITY

    TO THE PUBLIC

    Sufficiency Rating

    Sufficiency Rating

    Sufficiency Rating

    Posted Bridges List

    Bridge Geometry,

    Acci dents , etc.

    Highway Class and

    Traffic Count (ADT)

    Bridge Inspection Report

    District Recommendations

    Bridge Inspection Report

    District Recommendations

    Avail able Detou r Rout es

    District Recommendations

    FINAL ORDER

    OF PRIORITY

    Traffic Type

    Source: LADOTD Bridge Design Manual

    Replacement vs. RehabilitationOther Considerations - ReplacementPros :

    1. New structure would meet all currentstandards

    • Loads

    • Geomet ry

    • Highway standards

    2. New Construction

    • Do not have to connect newcomponents with existing ones.

    • Reduced potential for“surprises” during construction

    3. Estimating construction costpotentially more accurate

    Cons :

    1. Potential for greater environmentalimpacts

    2. Potential for greater costs

    3. Potential need for more right-of-way

    4. Can require time for public to agree ona location and other impacts related toa new structure

    5. Can take more time from start ofplanning to final completion anddelivery to public

    6. Removal of an historic structure

    Replacement vs. RehabilitationOther Considerations - RehabilitationPros :

    1. Have the potential to reuse existingelements, thus saving time andmoney

    2. Potentially less environmentalimpacts

    3. Potentially less right-of-wayrequirements

    4. Can fix some “legacy issues” that donot meet current standards or areless than desirable

    Cons :

    1. Increased potential for problems andunknown discoveries with the existingstructure

    2. Greater demands on determination ofexisting conditions, details, geometry,etc. in order to produce accurate plans

    3. Ability to meet all current standardsmay be difficult

    4. Accurate estimation of constructioncosts can be difficult

    5. Modification of an historic structure

    Replacement vs. RehabilitationOther Considerations (con’d)

    Environmental

    • Historic structure?

    • Impacts?

    Remaining life of structure

    • Structural condition (corrosion) and capacity

    • Remaining fatigue life

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    4/36

    Replacement vs. RehabilitationOther Considerations (con’d )

    Owner’s Concerns and Issues

    1. Time required to perform the work2. Funding

    • Available local funding?

    • Federal funds available?

    3. Public• Wants the work completed “yesterday”

    • Does not want to be inconvenienced during the work

    • Low cost (no increased direct costs; e.g.. taxes, tolls, etc.)

    • While doing this work, why not fix these other problems and/oraddress other needs.... ”it’s only a little more $$” (scope creep)

    Replacement vs. RehabilitationWhere does the Huey P. Long Bridge fit within this

    criteria?

    Structurally Adequacy? - GOOD• Excellent condition; adequate strength

    • Reduced fatigue life of stringers and floorbeam brackets

    Functionally Adequacy and Serviceability? - POOR• 18 feet wide roadways

    • Barriers not current standards

    Essential For Public Use? - ESSENTIAL• Few Mississippi River crossings in metro region; essential for

    highway traffic

    • Only rail crossing of Miss. River south of Baton Rouge

    Location

    FrenchQuarter

    Huey P. Long Bridge

    New Orleans Metro Area

    Before the Bridge

    Before the Bridge Construction of The Existing Bridge

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    5/36

    Construction of The Existing Bridge Construction of The Existing Bridge

    Construction of The Existing Bridge Construction of The Existing Bridge

    Construction of The Existing Bridge Background – Huey P. Long Bridge

    • Completed in December 1935, the bridge isone of the longest railroad bridges in the world.

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    6/36

    Background – Huey P. Long Bridge

    • Combinedrailroad – highwaybridge

    – 2 tracks

    – 4 lanes – 9 ft.width

    Background – Huey P. Long Bridge

    • Very heavilybuilt• Carries largest

    modern RRload withoutdistress

    • Many years ofservice liferemaining

    Project Background

    • By widening the existingstructure rather thanconstructing a new rivercrossing: – Reduce environmental

    impact, property takings. – Reduce project cost. – Reuse existing right-of-

    way and traffic corridors.

    • Final report published April 1988.

    Project Background

    EXISTING PROPOSED WIDENING

    Project Background

    1982Study of new bridge in corridor; 5 alternates considered.High cost and large amount of ROW; project dropped.

    1986LADOTD authorized M&M to perform conceptual widening study.3 widening alternates considered.

    1990 Geotechnical investigation of soil capacity under caissons.

    1992-1996

    Preliminary Design Main Bridge; Fatigue Evaluation.Line and Grade Study Approaches.

    1999-2000

    Environmental Processing Agency Consensus

    2000-2007

    Completion of final design plans; main bridge widening, railroadmodifications, and approaches,

    2006-Present

    Construction main bridge substructure widening, railroadmodifications, and main bridge superstructure widening.

    START PROJECT

    END PROJECT

    WEST BANK APPR.

    WEST BANK RR MOD

    EAST BANK RR MOD

    EAST BANK APPR.

    MAIN BRIDGE PIER, TRUSS, ANDDECK WIDENING

    Huey P. Long Widening Project

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    7/36

    START PROJECT

    END PROJECT

    WEST BANK APPR.

    WEST BANK RR MOD

    EAST BANK RR MOD

    EAST BANK APPR.

    MAIN BRIDGE PIER, TRUSS, ANDDECK WIDENING

    Main Bridge Pier Widening Main Bridge Pier Widening

    Pier A Piers I & II Pier III Pier IV

    EXISTING

    PROPOSED WIDENING

    Widened Pier

    Caisson

    SteelFrame

    LowerEncase

    UpperEncase

    Widened Pier - Details

    • The steel frame significantly reduces the loads onthe pier by eliminating concrete and permits thecenter bearing to be jacked, relieving load from theexterior bearings.

    • This is beneficial by reducing load on the end facesof the existing concrete distribution block on top ofthe existing caisson.

    • The upper portion ofthe pier widening iscomposed of a steelframe.

    Widened Pier - Details

    • Inspection access will be provided for the steel metalworkin the upper portion of the pier widening.

    • The steel frame willalso permit moreaccurate setting andadjustment of the finalbearing elevations after

    the lower encasementis poured.

    Widened Pier - Details

    Constructability of Pier Frame• Must be constructed around existing pier • No construction access from above due to

    existing superstructure• Staged construction• Key splice locations.

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    8/36

    Widened Pier - DetailsThe lower portion of the

    encasement serves

    several functions• The nose areas arecolumns to support thewidening truss supportbearings.

    • The remainder confines the existing pier concreteand granite masonry blocks which currently hasminimal reinforcing.

    Widened Pier - Details

    Widened Pier - Details Strength of the Existing Concrete• One of the major questions for widening the

    substructure was the strength of the existingconcrete.

    • Existing concrete was specified for 2000 psi.• Based on construction records, actual strength

    much higher • Using methods to estimate moderate amount of

    additional concrete strengthening with aging,4000 psi could be used with confidence for thestrength of the existing concrete.

    Strength of the Existing Concrete

    PIER AND CAISSON CONCRETE STRENGTHS

    LOCATION 1930 2000 - 1 2000 - 2 USED

    Piers 3,800 4,500 8,800 4,000

    Caisson 3,300 3,870 7,565 3,800

    2000-1 = ACI Committee 209, “Prediction of Creep, Shrinkage, andTemperature Effects in Concrete Structures” (ACI 209R-92)

    2000-2 = Properties of Concrete” by A. M. Neville

    Existing Pier ConditionsUnderwater Acoustic Inspection performed April 2006 by C.

    H. Fenstermaker & Associates.

    Piers I, II, III, & IV examined and found to be in goodcondition.

    The equipment provided detailed information of the existingconditions.

    Examination though the use of a diver would be more costly,must be performed in extreme low to no visibility, and isdangerous.

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    9/36

    Existing Pier Conditions

    Pier I – North Face

    Existing Pier Conditions

    Pier II – West Nose

    START PROJECT

    END PROJECT

    WEST BANK APPR.

    WEST BANK RR MOD

    EAST BANK RR MOD

    EAST BANK APPR.

    MAIN BRIDGE PIER, TRUSS, AND

    DECK WIDENING

    Main Bridge Truss Widening Main Bridge Truss Widening

    Cantilever Truss Span

    SimpleThrough

    Truss Span EXISTING

    PROPOSED WIDENING

    Cross Sections – Existing Bridge

    • 2 new trusses added, parallelto existing trusses.

    • Roadways widened from 18ft. to 43 ft.

    • Currently: 2 – 9 ft. lanesNo offset

    • Proposed: 3 – 11 ft.lanes

    8 ft. shoulder 2 ft. offset

    Widened Main Bridge Features

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    10/36

    Nomenclature• Normal terminology

    for truss bridges

    would be U.S. & D.S.trusses.• Widened HPL Bridge

    is a multiple trussplane structure – U.S. Widening Truss – U.S. Existing Truss – D.S. Existing Truss – D.S. Widening Truss

    2D versus 3D Analysis and DesignTraditional Truss Analysi s (2D)• Vertical loads, e.g. D & L, supported by main (vertical)

    trusses• Transverse loads, e.g. W, supported by top and bottom

    lateral trusses, sway frames, and portals

    3 Dimensional Analysis Used• Widened bridge is multiple truss plane

    system• 3D analysis reflects the reality of the

    structure and its behavior • Load sharing will occur and it is beneficial• Members not normally supporting live load

    will have live loads• Need to know the amount of live load in

    non-traditional live load supportingmembers.

    2D versus 3D Analysis and Design 2D versus 3D Analysis and Design

    3D SAP Computer Model

    Floorbeam and Hangers• Superposition needed to

    solve final forces in theexisting and widenedhangers

    • Moment and sequence ofconstruction affect forces

    Construction and Erection

    • Method and Sequenceof Constructionprovided in ContractPlans

    • Contractor proposedoption also available incontract plans

    • Contractor proposedhis own method

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    11/36

    Maintenance of Traffic Through Construction

    • Marine Traffic Maintained – same vertical and horizontal

    clearances

    • Rail Traffic Maintained

    • Vehicular Traffic Maintained – by use of staged construction

    Main BridgeMaintenance of Traffic

    WORK PERFORMED INTRUSS WIDENING

    CONTRACT

    Main BridgeMaintenance of Traffic - Stage 1

    WORK PERFORMED INTRUSS WIDENINGCONTRACT

    Main BridgeMaintenance of Traffic - Stage 2

    PREVIOUS STAGE

    WORK PERFORMED INTRUSS WIDENINGCONTRACT

    Main BridgeMaintenance of Traffic - Stage 3

    PREVIOUS STAGE

    WORK PERFORMED INTRUSS WIDENING

    CONTRACT

    Main BridgeMaintenance of Traffic - Stage 4

    PREVIOUS STAGE

    WORK PERFORMED IN APPROACH AND DECKWIDENING CONTRACT

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    12/36

    Main BridgeMaintenance of Traffic - Stage 4 - 5

    SWITCH TRAFFIC

    Main BridgeMaintenance of Traffic - Stage 5

    PREVIOUS STAGE

    WORK PERFORMED IN APPROACH AND DECKWIDENING CONTRACT

    Main BridgeMaintenance of Traffic - Stage 6

    PREVIOUS STAGE

    WORK PERFORMED IN APPROACH AND DECKWIDENING CONTRACT

    Main BridgeMaintenance of Traffic - Stage 7

    PREVIOUS STAGE

    WORK PERFORMED IN APPROACH AND DECKWIDENING CONTRACT

    • Top laterals, bottomlaterals, swayframes, and portalframes must hinge

    to permit movement• Erect rigid part overroadways open totraffic; hingeremaining part.

    Deflection Issues

    START PROJECT

    END PROJECT

    WEST BANK APPR.

    WEST BANK RR MOD

    EAST BANK RR MOD

    EAST BANK APPR.

    MAIN BRIDGE PIER, TRUSS, ANDDECK WIDENING

    Railroad Modifications - Westbank

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    13/36

    Railroad Modifications - Westbank

    Project Site

    LA 18 Hwy. 90

    Railroad

    EXISTING

    Huey P. Long Widening ProjectWestbank Railroad Modifications

    Existing Site Conditions

    To Huey P. Long Bridge

    L A 1 8

    U S H W Y 9 0

    Huey P. Long Widening ProjectWestbank Railroad Modifications

    Final Site Conditions

    To Huey P. Long Bridge

    L A 1 8

    U S H W Y 9 0 F u

    t u r e R o

    a d w a y

    Replacement Support

    Huey P. Long Widening ProjectWestbank Railroad Modifications

    Huey P. Long Widening ProjectWestbank Railroad Modifications

    Huey P. Long Widening ProjectWestbank Railroad Modifications

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    14/36

    WestbankSequence of Construction

    1. Construct foundations for newcross girders

    2. Install falsework to lift existinggirder spans

    3. Begin 24 hour rail traffic closure

    4. Lift existing girder spans off steeltower

    5. Remove upper portion steel tower

    6 . Erect cross girders

    7. Lower existing girder spans ontonew cross girders

    8. Restore rai l t raff ic

    9. Remove remaining portion of steeltower

    2 4 H O U R R A I L C L O S U R E

    START PROJECT

    END PROJECT

    WESTBANK APPR.

    WESTBANK RR MOD

    EASTBANK RR MOD

    EASTBANK APPR.

    MAIN BRIDGE PIER, TRUSS, ANDDECK WIDENING

    Railroad Modifications - Eastbank

    Railroad Modifications - Eastbank

    Project SiteJefferson Hwy

    Clearview Pkwy.

    EXISTING

    Huey P. Long Widening ProjectEastbank Railroad Modifications

    Existing Site Conditions

    QWEST Line

    V a c a n

    t G a s

    S t a t i o

    n

    C l e a r v i e w

    P k w y.

    J e f f e r s o n

    H w y

    .

    To Hu e y P . Lo ng Br id g e

    Power Poles & Power Line

    Existing Superstructureand Towers to beReplaced

    Huey P. Long Widening ProjectEastbank Railroad Modifications

    Final Site Conditions

    QWEST Line

    V a c a n

    t G a s

    S t a t i o

    n

    C l e a r v i e w

    P k w y.

    J e f f e r s o n

    H w y

    .

    To Hu e y P . Lo n g Br id g e

    F u t u r e

    R o a d w

    a y

    F u t u r e

    E l e v a t e

    d

    R o a d w a

    y

    New Bents

    Huey P. Long Widening ProjectEastbank Railroad Modifications

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    15/36

    EastbankSequence of Construction

    1. Construct new concrete straddlebents

    2. Prepare steel tower and otherfalsework

    3. Begin 24 hour rail traffic closure

    4. Remove girders under one of thetracks

    5. Erect new girders for one track

    6. Re-establ ish t rack

    7. Restore rai l t raff ic

    8. Repeat girder replacement forother track (Steps 3 – 7 above)

    9. Remove s teel tower

    2 4 H O U R R A I L

    C L O S U R E

    START PROJECT

    END PROJECT

    WEST BANK APPR.

    WEST BANK RR MOD

    EAST BANK RR MOD

    EAST BANK APPR.

    MAIN BRIDGE PIER, TRUSS, ANDDECK WIDENING

    Approaches & Deck Widening

    Approaches & Deck Widening

    WEST BANK APPROACH

    Start Project Bridge City Ave.Interchange

    Conflict w/Existing Rdwy

    Approaches & Deck Widening

    Cantilever Truss Span

    SimpleThrough

    Truss Span EXISTING

    PROPOSED WIDENING

    Approaches & Deck Widening

    EAST BANK APPROACH

    End Project

    Jefferson HwyInterchange

    Conflict w/Existing Rdwy

    NOPBRR Spur

    Approaches & Deck Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    16/36

    Approaches & Deck Widening

    EB APPR.

    EB APPR.

    Created using Google SketchUp

    Approaches & Deck Widening

    CAP

    TRUMPET

    COLUMN

    TRUMPET PC

    FOUNDATION

    W.P.

    Approaches & Deck Widening

    184 - TOTAL SUBSTRUCTURE UNITS

    123 - 4’ X 6’ COLUMN BENTS

    4’x 6’8’ x 12’ 6’ x 12’8’ x 14’

    Approaches & Deck Widening

    Column Type 1: 4’ x 6’

    Column Type 3: 8’ x 12’

    Column Type 2: 6’ x 12’

    Column Type 4: 8’ x 14’

    Approaches & Deck Widening

    Trumpet for 4’x 6’ columns

    4’x 6’

    Trumpets for 6’

    & 8’ x 12’columns

    Trumpet for 8’ x14’ Columns

    8’ x 14’

    8’ x 12’

    6’ x 12’

    Approaches & Deck Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    17/36

    TypicalBent

    FullHeight

    Trumpet

    Sub-Trumpet

    Size 1

    Sub-Trumpet

    Size 2

    Adj ust Fo oti ng Dept h As Neces sary

    Approaches & Deck Widening

    WORK PERFORMED IN APPROACH CONTRACT

    Main Bridge Deck Widening

    East Bank Approach - East Bank Bound

    West Bank Approach - West Bank Bound

    Approaches & Deck Widening

    West Bank Approach

    East Bank Bound

    Approaches & Deck Widening

    WB APPR.Location of West Bank

    Steel Girder Spans

    East Bank Approach

    West Bank Bound

    Approaches & Deck Widening

    EB APPR.

    Location of East BankSteel Girder Spans

    Approaches & Deck Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    18/36

    Approaches & Deck Widening

    SWITCH TRAFFIC

    Project Timeline

    • Work Completed – Railroad Modifications – Main Bridge Pier Widening

    • Work Under Construction – Main Bridge Truss Widening – West Bank Approach, Main Bridge Deck Widening,

    East Bank Approach

    Project Schedule

    Main Bridge Substructure

    Railroad Modifications

    SuperstructureFabrication & Erection

    Appro aches & Mai n Bridg eRe-d ecking

    2012 20132004 2005 2006 2007 2008 2009 2010 2011

    Project Status – Completed

    Main B ridge Pier Widening• Letting Date:

    – December 14, 2005

    • Notice To Proceed Date: – April 10, 2006

    • Construction Bid: – $ 98,826,907

    • Contractor: – Massman Construction Co.

    Main Bridge Pier Widening

    Pier A Piers I & II Pier III Pier IV

    EXISTING

    PROPOSED WIDENING

    Main Bridge Pier Widening Main Bridge Pier Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    19/36

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening

    DistributionBlock

    Main Bridge Pier Widening

    Main Bridge Pier Widening Main Bridge Pier Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    20/36

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening Main Bridge Pier Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    21/36

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening

    New Orleans

    G&G Steel

    Main Bridge Pier Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    22/36

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening Main Bridge Pier Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    23/36

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening Main Bridge Pier Widening

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    24/36

    Main Bridge Pier Widening Main Bridge Pier Widening

    Main Bridge Pier Widening Project Status - Completed

    Railroad Modific ations• Letting Date:

    – May 10, 2006

    • Notice To Proceed Date: – August 28, 2006

    • Construction Bid: – $ 13,782,713

    • Contractor: – Boh Bros. Construction Co.

    Railroad Modifications - Westbank

    Project Site

    LA 18 Hwy. 90

    Railroad

    EXISTING

    Railroad Modifications - Westbank

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    25/36

    Railroad Modifications - Westbank Railroad Modifications - Westbank

    Railroad Modifications - Westbank

    New Orleans

    G&G Steel

    Railroad Modifications - Westbank

    Railroad Modifications - Westbank Railroad Modifications - Westbank

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    26/36

    Railroad Modifications - Westbank Railroad Modifications - Westbank

    Railroad Modifications - Westbank Railroad Modifications - Westbank

    Railroad Modifications - Eastbank

    Project SiteJefferson Hwy

    Clearview Pkwy.

    EXISTING

    Railroad Modifications - Eastbank

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    27/36

    Railroad Modifications - Eastbank Huey P. Long Widening ProjectEastbank Railroad Modifications

    Railroad Modifications - Eastbank Railroad Modifications - Eastbank

    Railroad Modifications - Eastbank Railroad Modifications - Eastbank

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    28/36

    Railroad Modifications - Eastbank Railroad Modifications - Eastbank

    Railroad Modifications - Eastbank Railroad Modifications - Eastbank

    Railroad Modifications - Eastbank Project Status – Under Construction

    Main Bri dge Truss Widening• Letting Date:

    – March 28, 2007

    • Notice to Proceed Date: – November 5, 2007• Construction Bid:

    – $ 452,605,568

    • Contractor: – Massman Construction Co., Traylor Brothers

    Inc., and IHI, Inc.

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    29/36

    Main Bridge Truss Widening

    Cantilever Truss Span

    SimpleThrough

    Truss Span EXISTING

    PROPOSED WIDENING

    Main Bridge Truss Widening

    New Orleans

    Industrial SteelConstruction

    Gary, IN

    Main Bridge Truss WideningTruss Monitoring

    STATIC MONITORINGSYSTEM – 433 Members (777

    Vibrating Wire StrainGages)

    – 5 Piers (10 VibratingWire Tilt Meters)

    – WindSpeed/Direction

    DYNAMIC (LIVE LOAD)MONITORINGSYSTEM – 31 Members (50

    Electrical ResistanceStrain Gages)

    Main Bridge Truss WideningWork Platform

    Main Bridge Truss WideningWork Platform

    Main Bridge Truss WideningFloorbeam Modifications

    Template Fit Up Check

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    30/36

    Main Bridge Truss WideningFloorbeam Modifications

    Installation of Wedge Fill

    Main Bridge Truss WideningFloorbeam Modifications

    Installation of Wedge Fill

    Main Bridge Truss WideningWork on Existing Structure – Bottom Chord

    Main Bridge Truss WideningWork on Existing Structure – Top Chord

    Main Bridge Truss WideningWidening Truss Bottom Laterals

    Main Bridge Truss WideningRemove Existing Sidewalk – Install Temporary Steel Barrier

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    31/36

    Main Bridge Truss WideningMain Bridge Erection - Methods

    A = “ Stick Buil d” B = “ Span by Sp an”

    A B A B B

    Main Bridge Truss WideningMain Bridge Erection

    Main Bridge Truss WideningMain Bridge Erection

    Main Bridge Truss WideningMain Bridge Erection

    Main Bridge Truss WideningMain Bridge Erection

    Main Bridge Truss WideningMain Bridge Erection

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    32/36

    Main Bridge Truss WideningMain Bridge Erection

    Main Bridge Truss WideningMain Bridge Erection

    Main Bridge Truss WideningMain Bridge Erection

    Main Bridge Truss WideningMain Bridge Erection

    December 2009

    Main Bridge Truss WideningMain Bridge Erection

    December 2009

    Main Bridge Truss WideningContractor’s Erection Scheme – “Span by Span” Erection

    • East Anchor Arm• Suspended Span• Through Truss

    Span

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    33/36

    Project Status – Under Construction

    West B ank Appro ach, Main B ridge DeckWidening, East B ank Approach

    • Letting Date: – March 19, 2008

    • Notice to Proceed Date: – May 5, 2008

    • Construction Bid: – $ 433,950,000

    • Contractor: – Kiewit Massman Traylor Constructors

    START PROJECT

    END PROJECT

    WEST BANK APPR.

    WEST BANK RR MOD

    EAST BANK RR MOD

    EAST BANK APPR.

    MAIN BRIDGE PIER, TRUSS, ANDDECK WIDENING

    Approaches & Deck Widening

    Approaches & Deck Widening

    Box Culverts

    Approaches & Deck Widening

    At Grade Roadways – West Bank

    Approaches & Deck Widening

    Foundations - Westbank

    Approaches & Deck Widening

    Foundations - Westbank

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    34/36

    Approaches & Deck Widening

    Substructure - Westbank

    Approaches & Deck Widening

    Substructure -Westbank

    Approaches & Deck Widening

    Superstructure- Westbank

    Approaches & Deck Widening

    Superstructure- Westbank

    Approaches & Deck Widening

    Superstructure- Westbank

    Approaches & Deck WideningSuperstructure - Westbank

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    35/36

    Approaches & Deck WideningSuperstructure - Westbank

    Approaches & Deck WideningSuperstructure - Westbank

    Approaches & Deck WideningSuperstructure - Westbank

    Approaches & Deck Widening

    Created using

    Google SketchUp

    Substructure – Pier IVA

    Approaches & Deck Widening

    Substructure – Pier IVA

    The Rehabilitation AlternativeHuey P. Long Bridge Case Study

  • 8/20/2019 Bruce Peterson handout 6 per page.pdf

    36/36

    Q & A1. Priority for the selection of bridges for replacement or rehabilitation with Federal

    bridge replacement funds based on three parameters. Name them.

    ?

    2. Of the three parameters above, which is given the highest weight?

    ?3. What Sufficiency Rating is required for replacement? ?

    4. Bridge geometry is a key element of Functional Adequacy and Serviceability.What is the most important f actor within bridge geometry?

    ?

    5. For the case study project, name one key design challenge?

    ?

    6. For the case study project, how was approach bent formwork simplified?

    ?