Brighton i360Newsletter - Issue 1 - July 2nd 2014
Welcome to the first project newsletter for the Brighton i360. Thank you to those who attended our meeting on 12th June, it was good to meet so many of our neighbours. For those who could not attend please read on to find out more about us and what to expect during the construction period.
As you may have read in the newspapers or if you have visited the West Pier site recently, the Brighton i360 project is underway. Enabling works to remove the root end of the West Pier have been completed by Dorton. Those parts of the dismantled root end that can be re-used will come back as part of the landscape works. The sea island will remain.
Construction Team
The construction team includes main contractor Hollandia, who built the London Eye steel structure, with subcontractors Poma, who built the London Eye capsules, and local marine and civil contractor Mackley. Mackley is a Sussex based construction firm providing a comprehensive range of services and has a wealth of experience in coastal construction projects. Mackley has extensive experience of
working on Brighton Beach. Enabling works for the construction site have started and you will start to see materials and machines arriving in the next few days.
We will be aiming to create as much interest in the project as possible during the construction phase to create footfall to this area of the beach for the benefit of all the seafront traders. We will be generating interest online via social media. We will also be running community events, hard hat tours of site and will create viewing windows into the site along with many other exciting initiatives.
We will be co-hosting a community event with the Council on Tuesday 29th July 2pm-4pm to celebrate the official opening of the newly renovated arches by the Mayor and to commemorate the ‘first spade’ in the ground for our construction. Do come along to join us.
Talk to Us
Jacqui Bandy is the liaison for Mackley and you can contact her by emailing:[email protected] or by phone on 07917 048912 if you have any questions or concerns.
Jacqui will be on site regularly and will be introducing herself to local businesses and residents over the coming weeks.
As construction continues we will keep you posted on what’s happening and when. If you would like regular updates please email [email protected] and request to be added to the mailing list. We will also be holding regular meetings for local residents and traders; please let us know if you have a suitable room to host the meetings, as we will be aiming to hold the meetings at different local venues.
You can keep up to date with progress by following us on social media using the details below.
Twitter: @thebrightoni360Facebook: www.facebook.com/pages/Brighton-i360Pinterest: www.pinterest.com/Brightoni360Blog: http://brightoni360.wordpress.comWebsite: www.brightoni360.co.uk
Access Road Diagram
Access Road Cross Section
© Marks Barfield Limited 2012
First Steps
The construction team’s first task is to construct the access road that will carry the construction traffic over the course of the build along with the pedestrian walkway. Work for this will start on Monday 7th July and is expected to be completed by the end of July. The road is constructed on the beach by laying down sand and giant timber boards. To protect the public the access road is bordered by a barrier topped with white metal mesh fencing. In light of your feedback, we have aimed to minimise the visual impact of the barrier by selecting a white coloured barrier.
There will be three crossing points for pedestrians to access the promenade from the beach. This includes the following locations:
• The steps between the Bandstand and The Playground (the steps will remain open)
• Entrance between the Playground & Al Fresco restaurant (the steps by Al Fresco will remain open)
• Access to the newly renovated arches
The speed limit on the access road will be 5mph and the crossings will be clearly signed but it is important to cross carefully as you would with any road crossing. Deliveries to businesses will still be between 6am and 11am and delivery vehicles will be able to use the contractors access road to exit the promenade from the eastern end of the site through to the Peace Statue at the western end. Deliveries to businesses on the west of the site will continue to use the existing road.
© Brighton i360 Limited 2014
View from the King’s Road side
Q2 2014
West Pier Removal
Q3 - Q4 2014
Foundations and Sewer Diversion
May / June 2015
Beach Landings
June - Sep 2015
Tower ErectionQ3 2015 - Q2 2016
Pod Installation
Q2 2015 - Q2 2016
Building & Fit OutQ3 2016
i360 Opens
30th June
Mackley Start On Site
1st week July
Site Preparatory Works
2nd Week July
Access Road3rd Week July
Hoardings & Site Accommodation
29th July 2pm-4pm
Opening of Renovated
Arches+
First Spade in the Ground
Event
Construction Timetable
Next Few Weeks