briefing on the comprehensive investment programme for water infrastructure development
DESCRIPTION
Portfolio Committee: Water & Environmental Affairs. Briefing on the comprehensive investment programme for water infrastructure development. 27 – 28 March 2013. DOCUMENT 6. Contents. Part 1: Overview of water resources (i.e. augmentation) infrastructure investment programme - PowerPoint PPT PresentationTRANSCRIPT
Briefing on the comprehensive investment programme for
water infrastructure development
27 – 28 March 2013
Portfolio Committee: Water & Environmental Affairs
DOCUMENT 6
Contents
• Part 1: Overview of water resources (i.e. augmentation) infrastructure investment programme
• Part 2: Overview of water services (i.e. regional bulk) infrastructure
2
PART 1: WATER RESOURCES (I.E. AUGMENTATION) INFRASTRUCTURE INVESTMENT PROGRAMME
3
Typical phases for the development of water infrastructure
4
A percentage is allocated to each phase and the total of all phases is 100%
• Needs identification• Identification and selection of possible interventions
• Preliminary investigation of options • Identify best options for detail study
• Detailed investigation and assessment of best option(s) sizing and configuration (technical, environmental & cost)• Recommend the project
• Environmental approval • Reserve determination • Public involvement• Initial funding and institutional arrangements• Some optimisation • Decision to implement
• Formalise institutional arrangements • Secure funding• Procurement procedures• Engineering design and construction documentation
• Procurement• Resettlement & compensation • Construction • Impounding
• Testing to verify if performance is according to design objectives or specifications • Handover to Operations & Maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
Medium term investment on water resources infrastructure
Project name Total project budget
Rand thousand
2013/14 2014/15 2015/16
ORWRDP (Ph 2A) - De Hoop Dam
3,074,000 171,000 - -
ORWRDP BDS - Bulk distribution (Sub Phases 2B and 2C)
3,472,043 543,800 735,000 974,000
GLeWAP Phase ( Raising of Tzaneen dam)
125,000 10,000
65,000
50,000
GLeWAP Phase (Nwamitwa Dam )
1,700,000 17,100 228,000 384,900
Dam Safety Rehabilitation Programme
2,800,000 228,000 250,800 360,000
Water Resources Project Raising of Clanwilliam Dam
1,830,000 316,143 436,459 515,142
Mokolo and Crocodile River (West) Water Augmentation Project (Phase 1)
2,138,000 100,092 117,829 106,929
Mokolo and Crocodile River (West) Water Augmentation Project (Phase 2)
13,950,000
114,000 228,000 617,623
5
Medium term investment on water resources infrastructure
Project name Total project budget
Rand thousand
2013/14 2014/15 2015/16
Development Raising of Hazelmere Dam
360,000 210,000 105,000 5,000
GLeWAP Distribution (Mopani DM)
605,000 56,000 - -
ERP system upgrade from version 4.7 to ECC6
185,075 100,000 - -
NWRI Support/Project management
236,067 250,231 265,245
Financial management/Project support
185,147 217,130 227,987
TOTAL30,239,1
182,210,05
72,570,90
93,423,18
7
6
Phases for the De Hoop dam
7
A percentage is allocated to each phase and the total of all phases is 100%
• Formalise institutional arrangements • Secure funding• Procurement procedures• Engineering design and construction documentation
• Relocation and resettlement negotiations of families underway• Completion of dam construction scheduled for 2013/14 • Impoundment
• Commissioning• Testing to verify if performance is according to design objectives or specifications • Handover to Operations & Maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
Targ
et in
20
13/1
4 AP
P
Phases for Olifants River Water Resources Development (BDS)
8
A percentage is allocated to each phase and the total of all phases is 100%
• Needs identification• Identification and selection of possible interventions
• Preliminary investigation of options • Identify best options for detail study
• Detailed investigation and assessment of best option(s) sizing and configuration (technical, environmental & cost)• Recommend the project
Upgrade of existing pipeline from Steelpoort to Mooihoek•Environmental approval •Reserve determination •Public involvement•Initial funding and institutional arrangements•Some optimisation •Decision to implement
• Funding has been allocated for the project• Tender design completed and advertised for closing on 11 Apr 2013• Estimated date for award of tender is mid June 2013
Sub-phase 2C (Pipe from De Hoop Dam to Steelpoort) •Construction•Procurement •Resettlement and compensation
Sub-phase 2B(Flag Boshielo to Sekuruwe) •Construction•Procurement •Resettlement and compensation
• Testing to verify if performance is according to design objectives or specifications • Handover to Operations & Maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
2013/14 APP target
Phases for the Vaal River Eastern Sub-systems Augmentation
9
A percentage is allocated to each phase and the total of all phases is 100%
• Testing to verify if performance is according to design objectives or specifications • Handover to Operations & Maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
Phases for the Mokolo River Augmentation (phase 1)
10
A percentage is allocated to each phase and the total of all phases is 100%
• Formalise institutional arrangements • Secure funding• Procurement procedures• Engineering design and construction documentation
• Construction at 92% • Impounding
• Testing to verify if performance is according to design objectives or specifications • Handover to Operations & Maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
2013/14 APP target
Phases for the Komati Water Supply Augmentation
11
A percentage is allocated to each phase and the total of all phases is 100%
• Formalise institutional arrangements • Secured funding for the project• The as-built drawings of the dam to be finalised once construction is complete
• Procurement• Construction• Resettlement and compensation
• Commissioning• Testing to verify if performance is according to design objectives or specifications • Handover to Operations & Maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
Phases for the Hazelmere dam raising
12
A percentage is allocated to each phase and the total of all phases is 100%
• Funding secured for the project• Tender design completed and advertised for closing on 11 Apr 2013 – awarding by mid Jun 2013
• Construction of civil works to raise dam spillway by 7 metres in progress during 2013/14• Storage of additional water scheduled for September 2014
• Commissioning of project scheduled for November 2014 • Testing to verify if performance is according to design objectives or specifications • Handover to Operations & Maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
Phases for the Clanwilliam dam raising
13
A percentage is allocated to each phase and the total of all phases is 100%
• Funding allocated for the project• Tender design completed by 31 Mar 2013• Price Bill of quantities by Jun 2013• Complete N7 realignment design (SANRAL) by Apr 2013
• Land acquisition to start by Jun 2013• Advertise tender for N7 realignment by May 2013 and award by Sept 2013 • Site establishment to commence by Oct 2013• Estimated project completion 31 Mar 2014
• Commissioning of project scheduled for Jan 2018• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
Phases for the Mooi-Mgeni Transfer Scheme (phase 2)
14
A percentage is allocated to each phase and the total of all phases is 100%
• Construction of Spring-grove dam• Procurement• Resettlement and compensation • Impounding
• Construction of the conveyance system• Procurement• Resettlement compensation
• Dam operator on site• Testing to verify if performance is according to design objectives or specifications • Handover to operations & maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
• Formalise institutional arrangements • Secure funding• Procurement procedures• Engineering design and construction documentation
Phases for the N’wamitwa dam
15
A percentage is allocated to each phase and the total of all phases is 100%
• Procurement• Resettlement & compensation • Construction • Impounding
• Dam operator on site• Testing to verify if performance is according to design objectives or specifications • Handover to operations & maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
• Formalise institutional arrangements • Secure funding• Procurement procedures• Engineering design and construction documentation
Phases for the Raising of Tzaneen dam
16
A percentage is allocated to each phase and the total of all phases is 100%
• Procurement• Resettlement & compensation • Construction • Impounding
• Dam operator on site• Testing to verify if performance is according to design objectives or specifications • Handover to operations & maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
• Formalise institutional arrangements • Secure funding• Procurement procedures• Engineering design and construction documentation
Phases for the Lesotho Highlands Water project (phase 2)
17
A percentage is allocated to each phase and the total of all phases is 100%
• Procurement• Resettlement & compensation • Construction • Impounding
• Dam operator on site• Testing to verify if performance is according to design objectives or specifications • Handover to operations & maintenance• Closure
Opera
tions
& m
ain
tenance
Phase 1 to 4 constitutes planning
Phase 5 to 7 constitutes implementation
COMPLETED
• Formalise institutional arrangements • Secure funding• Procurement procedures• Engineering design and construction documentation
PART 2: OVERVIEW OF WATER SERVICES (I.E. REGIONAL BULK) INFRASTRUCTURE
18
Overview of progress to dateStatus Numb
erComments
Projects completed during 2012/13
7 Totalling 32 since 2007
Projects in construction phase
76 Of which 23 were started in 2012/13
Projects in design / tender phase
19
Projects in feasibility phase 27
TOTAL OF PROJECTS SINCE INCEPTION
154
19
IMPACT FROM THE COMPLETED PROJECTS1.Water for the provision of basic services2.Water for economic growth and development3.Increase assurance of supply4.Improve quality of effluent discharge and prevent environmental pollution5.Remove water restrictions
Overview of completed projects to date
Completed projects to date per financial year• 2007/2008: 3 projects• 2008/2009: 2 projects• 2009/2010: 6 projects• 2010/2011: 9 projects• 2011/2012: 5 projects• 2012/2013: 7 projects
TOTAL COMPLETED: 32
List of projects completed during 2012/13 financial year1. Hermanus wastewater
treatment works2. Tsomo RDP2 Northern3. Middleburg Bulk Water Supply4. Jagersfontein / Fauresmith Bulk
Water Supply (Phase 1) 5. Colesberg wastewater
treatment works6. Emadlangeni Bulk Water Supply 7. Drakenstein wastewater
treatment works
20
Medium term investment on water services infrastructure
Type Definition Rand thousand
2013/14
2014/15
2015/16
Small infrastructure
Cost less than R90 million per annum and not totalling more than R250 million over the medium term
1 452 069
1 946 888
2 146 500
Large infrastructure
Cost between R90 and R 400 million per year totalling at least R250 million but less than R1 billion
1 114 517
1 579 924
1 626 354
Mega infrastructure
Cost over R400 million per year for a minimum of three years or totalling at least R 1 billion
636 811 956 084 1 098 800
TOTAL 3 203 397
4 482 896
4 871 654
21
Budget allocation per provinceProvince Project
costExpenditure from inception until 31 Mar 2012
Proposed budget allocation over the medium term
2013/14 2014/15 2015/16
Eastern Cape 6 328 812 574 486 033 116 582 741 497 960 501 083 1 032 000 000
Free State 1 923 034 218 342 251 155 225 100 000 285 896 000 303 654 000
Gauteng 438 425 000 204 000 798 241 200 000 337 700 000 355 000 000
KwaZulu-Natal 5 269 729 919 722 367 645 593 563 275 1 167 000 000
1 280 000 000
Limpopo 3 618 448 000 614 365 239 593 536 725 717 499 000 784 667 000
Mpumalanga 1 181 297 000 135 673 747 137 752 752 225 000 000 234 000 000
Northern Cape 3 095 303 491 149 917 582 270 400 000 309 500 000 340 500 000
North West 2 275 114 000 219 392 054 390 200 000 347 000 000 388 600 000
Western Cape 1 033 317 571 110 954 651 170 802 891 132 800 000 153 233 151
Head Office 0 65 691 050 83 040 860 89 015 917 93 110 849
TOTAL 25 163 481 773
3 050 647 038
3 288 338 000
4 571 912 000
4 964 765 000
22