AFRICA EQUIPMENT & ENGINEERING, S.A.

BRIEF WORK DESCRIPTION

PAGE 1

Page 2: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 2/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

WORK DESCRIPTION

1. - OVER HEAD TRANSMISSION LINE (DANI)

2. - WORK DESCRIPTION – KUTUS SUBSTATION

Substation description

 The 132/33 kV substation will be located at Kutus. The new substation is being

constructed with the intention of reinforcing the Mt. Kenya North System.

S ubstation configuration :

PAGE 2

Page 3: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 3/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

- Two 132 kV incoming bays.

- One single 132 kV bus section.

- Two 132/33 kV, 23 MVA Transformer bays.

- Single bus bar arrangement and bus section.(33kV)

- Six 33 KV outgoing feeders.

- Two 33 KV fused isolator feeder for auxiliary service supply

Auxiliary system

AC System

Auxiliary system will consist of TWO (2) 100 kVA 33/0.4KV station transformers

that supplies through an AC Distribution Board.

DC System

DC supplies shall be provides by a double 125 DC battery and charger with his

corresponding DC Distribution Panel. A double 48V DC and charger will be also

supplied.

Control and protection system

 The integrated protection and control system (substation automation system

SAS) will be installed. Space provision will be taken into account for future bays.

For data processing and communication facility, new IEC61850 protocol shall be

used. Protections shall be latest on numerical technology.

Other Works

Access road, internal road, exterior, interior lighting as air conditioning is part of 

substation design.

Special attention shall be given to environment.

PROJECT OR GANISATION

AEE project organisation will be as follows:

PAGE 3

Page 4: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 4/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

In Spain (Madrid) a department for technical support will be created for, project

management, overseas purchasing, carrying out preliminary and final

engineering, preparing staff to be sent to job site etc.

  This team will consist of a General Project Manager, Technical Manager,

Administrative Manager and an Engineering team.

 The Engineering team will be responsible for definition and development of 

project in terms of technical characteristics, safety, environmental requirements

etc. According to activities this teams will be organised and distributed in

electrical, electromechanical, civil, HSE (Health, Safety and Environment), etc.

All documents generated by engineering will be sent to client for approval. Once

the materials and the equipment have been approved by Client, purchasing of 

equipment will take place.

 The engineering team will be made up of people with appropriate educational

level and experience in similar projects in Africa.

In KENIA the project will be organised in the following way:

A general project office with the following structure will be installed, made up of 

expatriate and local people.

- Local Manager

- Planning & Controller Manager

- Financial Responsible

- Engineering Responsible

- Warehouse Responsible

- Civil Works Supervisor

- Erection Supervisor

- Control & Protection Responsible

- Health & Safety & Environmental

- Quality Responsible

- Materials & Local Transport Responsible.

ORGANISATION – MATERIALS, EQUIPMENT AND SUPPLIES

PAGE 4

Page 5: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 5/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

 The proposed materials and equipment shall be analysed and sent for approval

to customer, with the specifications of each one and documentation of the

possible supplier.

Materials and equipment have to match on the whole with ones in the proposal.

If costumer is interested in new supplier or suppliers, the relevant

documentation will be presented in order to be approved.

Suppliers will participate in the transport of the materials from their country of 

origin to the warehouse.

 To carry out all transport steps, the project execution structure will consider one

logistic team, of which the larger part will be located in Spain and the rest in the

AEE´s offices at site.

After arrival of materials at warehouse, these will be classified and organised for

their correct distribution for substation or line work.

ORGANISATION OF ENGINEERING TEAM

As previously mentioned, preliminary and definitive engineering will be carried

out in Spain. Some engineering will be complemented by engineers located at

site. These personnel will be in charge of presenting all documents to client and

carrying out all of the small changes, transmitting them for execution and to the

central engineering department:

For greater agility in the execution of these tasks, all small engineering tasks

arriving from unforeseen situations at site will be carried out by local engineers

and supervised by the Client.

WORK ORGANISATION

 The project execution organisation shall have two separated team

• Kutus Substation

• Transmission lines

PAGE 5

Page 6: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 6/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

AEE QUALITY MANAGEMENT SYSTEM

 The ISO standards are the leading European quality certifications that are

Awarded to organisations that rigorously adopt Quality Control and

Improvement processes that ensure optimum service and output quality is

Delivered to clients.

AEE´s Quality Policy constitutes a cornerstone of our Management Quality

System (QMS). Independent of projects, AEE’s programme ensures that

our processes are followed and best practices applied.

AEE has established a structure to document and implement

Methodologies so as to organize; control and direct resources to ensure

Effectiveness operation control of identified processes and continually improves

Its effectiveness. This ensures that products and services of the Company are

produced to define requirement and help to achieve organizational policy &

objectives.

 The adoption of the QMS described in this manual is strategic to the interest

and emphasised that this manual is mandatory for all the employees of the Unit

towards commitment and adherence of applicable requirements.

WORK METHODOLOGY

GENERAL

Work method statements, procedures or work instructions, can assist relevant

people to consider how certain activities will be carried out safely and will be

issued once project starts.

A relevant person doing construction work needs to prepare a work method

statement for high-risk activities including, but not limited to:

• where a person is –

o to enter a trench more than 1.5 meters deep

o using explosives

o

using a confined spaceo using a hazardous substance

PAGE 6

Page 7: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 7/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

• if a person could fall–

o at least 3 meters for housing construction work, or

o at least 2 meters for other construction work

• working on a roof with a pitch greater than 26°

• where the principal contractor concludes an activity could

result in death or bodily harm

• demolition work or asbestos removal work

A work method statement is also required for high-risk activities which include:

• tilt-up and precast construction work• structural alterations that require temporary support to

prevent collapse

• moving powered mobile plant at the workplace

• working on a telecommunications tower

• working in, over or adjacent to water where there is a risk of 

drowning

working on, or adjacent to, a road or railway• working on or near a pressurized gas distribution mains and

consumer piping

• working on or near a chemical, fuel or refrigerant line

• work near an exposed energized electrical installation

• work in an area that may have a contaminated or flammable

atmosphere

Work in an area where there are artificial extremes of temperature.

 The work method statement must take into account the principal contractor’s

construction safety plan and also state:

• the high-risk construction activity

• the control measures to be used

• the way the activity will be performed

• how the control measures will be monitored and reviewed

PAGE 7

Page 8: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 8/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

• Any relevant prescribed occupations.

For demolition work and asbestos removal work the work method statement

must also state:

• the relevant certificate number

• the arrangements for appropriate training and supervision

Work method statements must be easy to understand, signed and dated.

 The work method statement must be amended if there is a change in the

activity and a copy must be given to the principal contractor. All people affected

by changes must be advised of amendments to the work method statement.

 The work method statement must be readily available for inspection. It must

also be reviewed each year and amended if necessary.

PURPOSE.

 The purpose of this document will be to summarize the Methodology of Work

that AEE will implement for the Project. It is intended as a guide.

  To ensure continuing suitability and effectiveness, to meet quality system

requirement, this document may be modified from time to time.

Engineering development, procurement and construction will be based on

documents mentioned in point 3.0 References.

Using the Work Program as a guide, and following directions on documents in

reference, for each stage of project, will insure that same will be completed on

schedule, with due quality and on budget.

REFERENCES (TO BE PREPARED ONCE PROJECT STARTS)

PAGE 8

Page 9: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 9/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

2.1 SITE MANAGEMENT PROCEDURES

2.2 WORK INSTRUCTIONS

2.3 QUALITY PLAN

2.4 QUALITY ASSURANCE PLAN

2.5 ENVIROLMENTAL MANAGEMENT PLAN

2.6 HSES MANAGEMENT PLAN

DOCUMENTATION MANAGEMENT SYSTEM

AEE, as contractor obligations with regards to preparation and submission of 

drawings, calculations, samples, patterns etc shall be stated in Contract.

AEE shall prepare and submit to the Project manager for approval, dimensioned

general and detailed design drawings and other pertinent information of all

plant and equipment specified in BID document.

Approval of drawings shall not relieve AEE of his obligations to supply the plant

in accordance with specifications. AEE will be responsible of any error appear in

drawings and as soon as detected will deliver the correct documentation.

All documents shall be in English. Dimensions will be in millimetres.

  The list of documents that shall be presented and be updated whenever

needed. The list of documentations shall include the date of original issue of 

each document submitted as well as the dates of revision. The list of 

documentation shall also include a time schedule for each submittal of 

documentation.

Symbols used for electrical equipment shall be in accordance of IEC60617.The

coherent system for physical and functional reference shall be designed in

accordance with IEC61346.A similar systematic scheme shall be defined for

cable numeration.TheseSchemes shall be used throughout on the drawings and

documentations and designation shall be labelled on the components and

cables.

PAGE 9

Page 10: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 10/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

 The sizes of all documents and drawings shall conform to the ISO standard.

(A1,A2,A3,A4) The sizes larger than A1 shall be avoided.

 The schematic diagrams and apparatus and cable list shall be of size A4 except

for the Original and possible transparency copies of schematic diagrams that

shall be inA3.Scales that shall be used in drawings shall be 1:10, 1:20, 1:40, 1:

50 and multiples of this series.

All drawings made special for this project including civil work, mechanical

drawings, layout drawings and circuit drawings shall be compiled on computer

aided design and as part of as built drawings shall be handed over on CD with

format readable in AUTOCAD version or in other format to be agreed upon in

addition to the paper copies.

  The drawings shall show the dimensions, main working principles, internal

components and fixing methods to a detailed level allowing the employer to

evaluate the functionality and completeness of the plant and equipment.

Engineering Coordination

An Engineering Coordinator will be assigned to :

1. Checking survey result and documents prepared by engineeringdepartment.

2. Verifying the supplier documents with respect to contract specifications.3. Verifying the suitability of the equipment proposed in specifications.4. Checking structure design calculation.5. Verifying foundation designs for various equipment foundations.6. Integrating control and protection features along with existing substation

system.

7. Checking electrical schematic drawings for control and protection panel,Substation management system and 33kV switchgear panel.Completing “As Built" Documentation on completion of commissioning work.

CIVIL WORKS

Before starting civil works in the new Substations, a detailed investigation of the

soil conditions will be carried out. The soil investigation will be carried out in

accordance with BS 5930, IEEE 80 or other approved standard.

 These studies have will cover all parameters needed for appropriate design of 

civil works (foundations, pits, buildings, drainage) as well as the earthing grid.

PAGE 10

Page 11: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 11/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

For tendering purposes (quotation) it has been considered a normal ground (soil

resistance 1.5 – 2 kg/m2).

Likewise a ground resistivity of 30 Ohm-metre has been assumed.

Prior to excavation the topography team will mark the exact place for the

excavation. The excavation of the land will depend upon the data obtained from

the geotechnical studies and the depth necessary for excavation or filled; it

should be done in order to obtain land level which is required by previously

done studies.

 The necessary team for the carrying out of the excavation work will be made up

of:

1 foreman

2 workers (excavator support)

1 operator (bulldozer)

Equipped with:

- Bulldozer

- Small tools (spades, picks, etc)

 The next phase of the excavation will be the earthworks — the levelling of the

land and the redesign of the axes of the switchyard with the help of the

topography.

Earthing System

According to the data obtained for the soil conductivity and the later

calculations, the earth conductor will be buried. An approximate depth of 60 –

80 cm below the level of switchyard and an external distance of 1m from the

fence has been considered

 The conductor will be laid together with the pile-driving of the rods for the

formation of the earthing mesh. Thermo welded joints will be used for the

buried grid. Connections between exposed earth conductors shall be made

using

Crimping terminals. Connections to the earth terminals shall be made using a

bolted connection.

PAGE 11

Page 12: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 12/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

On completion of installation, the following tests shall be performed:

Earth resistance test, voltage gradient test, step voltage test and touch voltage

test.

 The necessary team, for carrying out of the work is made up of:

1 foreman

2 specialist Technicians

2 unskilled workers

1 operator (Backhoe)

Equipped with:

- Backhoe

- Small tools (spades, picks, etc)

Drainage System

 The drainage system of S/S shall be done according to approved design of 

drainage. A drainage pipe will be placed for the sub-soil as well as storm

drainage for the switchyard.

After digging has been carried out the following step should be the filling of the

ditches with earth left over from the excavation and it compacting.

In order to prevent flow of water into the buildings, cable trenches shall be

sloped and drained away.

 The necessary for carrying out of drainage works is made up of:

1 foreman

2 specialist technicians

3 unskilled workers

1 operator (backhoe)

Equipped with:

- Backhoe

- Small tools (spades, picks, etc)

Control Building

PAGE 12

Page 13: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 13/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

In parallel to above mentioned jobs will start building of the control building

according to dimensions and characteristics of the technical drawings and

specifications issued by KPCL.

 The Control Building will be divided into the following compartments:

- Battery Room

- Kitchen

- Store room

- Telecommunications Room

- Relay and Control room

- Four offices

- Rest room

Also a gate guard house should be constructed in the Substation according to

tender drawing.

A potable water supply to buildings including an overhead water tank shall be

installed. Also a Sewerage system to drain foul water shall be designed.

Foundations Phase 1

According to the engineering plans and with support of the topography, the

exact positioning for the excavation of the foundations will be carried out.

 The excavation will be carried out according to the volumes calculated by the

engineers, for the efforts of each type of structure. Further the formwork tasks

will be carried out. Once this work is completed the placing of the templates for

the positioning of anchor bolts for the holding of the metallic structures will be

carried out. After fixing anchor bolts in the exact position the work will be

moved to the pouring and spreading of concrete for the formation of the

foundations.

 Transformer foundations

 The transformer foundations will be constructed in reinforced concrete.

Foundations Phase 2

PAGE 13

Page 14: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 14/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

Once the metallic structure and the switchgear have been plumbed and

levelled, the following step is the filling of the concrete for the cementing of 

phase 2.

Cable Trenches

At the same time to these jobs, the ditches for the building the channels for the

cable trenches in the switch yard will be dug.

 The cable trenches will be of two types:

Primary Cable trench serving as the main cable collector to the control

building.

Secondary Cable trench normally feeding cables at right angles at the

primary trench.

Cable trenches will be of reinforced concrete, the trenches will be of different

size equal or less than 900 mm wide by 800 mm deep and 700 mm wide by 500

mm deep for primary and secondary trenches respectively.

All cable trenches will be provided with removable, suitably sized galvanized

steel chequered cover plates.

Pits and manholes in driveways shall he provided with heavy-duty cast iron

covers.

 The type of cable trenches and dimensions shall be dimensioned on base of 

quantity and their separation in particular trench.

 The necessary team for the carrying out of the foundations cable trenches

works will be:

3 specialist technicians (form workers)

4 unskilled workers

1 operator (backhoe)

Equipped with:

- Backhoe

- Small tools (spades, picks, etc)

Fencing

PAGE 14

Page 15: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 15/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

Around the outside of the switch yard of the new substation chain link fencing

will be built. AH framing and Bates consist of structural steel sections and the

wire for the fencing mesh will be plastic coated.

 The earthing of fencing shall be studied as part of the earthing system.

Outdoor lighting

  The lighting installation will be designed to achieve the specified levels of 

illumination. The connection shall be as single phase, between phase and

neutral. All poles shall be connected to the main earth wire system by a

separate earth conductor.

Grave

Once the Switchyard works have been finished, a stone layer will be uniformly

spread over the finished surface of the platform, of a thickness around 100nun.

 The stone will be hard and durable crushed rock with a maximum particle size

of 60.

 The necessary team for the carrying out of the foundations, cable trenches and

gravel works will be made up of:

1 foreman

3 specialist technicians

3 assistants

Equipped with:

10 ton lorry crane

- Small tools

MOUNTING OF SUPPORT STRUCTURES

Depending upon the time taken by setting of foundation phase 1, the work will

proceed with raising, levelling and plumbing of the metallic structures and

gantries with their connections to the earthing system. Design and calculation

have to be approved previously the manufacturing.

For the raising of the structures we shall need one brigade made up of:

1 foreman

3 specialist technicians

PAGE 15

Page 16: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 16/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

3 assistants

Equipped with:

10 Ton. Lorry crane

- Small tools

Electrical equipment erection

Outdoor-Once the metallic structures have been built; we shall progress to the

—plumbing of the electrical equipment open the structures.

 The electrical equipment to be installed in the switchyard: circuit breakers,

disconnecting switches, voltage and current transformers, surge arresters etc.

Indoor- Erection of control, protection panels, telecommunication panels,

medium voltage cells, auxiliary service panels, lighting panels etc shall be done

fixing and levelling on the control building floor.

Cabling

Once the equipment is mounted in the switchyard and in the control building

(batteries, rectifier, auxiliary transformer, protection, control and

telecommunication equipment), the cabling and connecting will be carried out

with its corresponding labelling.

For the mounting of equipment and cabling we shall need one brigade for

substation made up of:

I foreman

4 specialist technicians

4 assistants

Equipped with:

10 ton lorry crane

- Small tools

Commissioning

Prior to taking over the Works or any section, the test on completion shall be

carrying out in presence of the Engineer.

PAGE 16

Page 17: Brief Description of Works KUTUS

8/8/2019 Brief Description of Works KUTUS

http://slidepdf.com/reader/full/brief-description-of-works-kutus 17/17

AFRICA EQUIPMENT & ENGINEERING, S.A.

 The tests will be done to all HV and LV equipment, with calculated set values for

protections, telecommunications and all other equipment that require set

parameter.

For commissioning we shall need:

1 Commissioning engineer

2 Assistants

Manuals for operation and maintenance:

AEE shall deliver manuals for operation and maintenance. These will contain,

but not limited to:

-Detailed description of all equipment. Individual components, relevant

clearances, tolerances, allowable temperature, settings etc.

-Detailed of main principles including flow diagrams, single line diagrams,

circuit diagrams, connection diagrams.

-Operation instructione.These shall illustrate operational sequences in a clear

and concise way.

-Test and adjustment procedures containing instruction for test and adjustment

of the equipment under operation, after inspection and maintenance

 The documentation shall leave the operators and maintenance personnel in

position to operate the plant in safe and optimal way and to perform repairs

usual to be done by such personal. CLIENT has to approve the manuals before

final submission.

Management Commitment Statement

 The organization is committed to provide all its services corresponding to the

customer’s requirement and all necessary measures to keep quality conformity

to international standard.

PAGE 17