bridge project presentation group #2 alex odle matt simon salim hamed micael thiodet
Post on 21-Dec-2015
216 views
TRANSCRIPT
Bridge Project Presentation
Group #2Alex Odle
Matt SimonSalim Hamed
Micael Thiodet
Outline of Presentation
• Introduction– Group Members– Goals and Constrictions– Group Goal
• Prototype Testing– Design Process
• Final Design– Changes Made To Final Project
• Conclusion• Final Thoughts and Suggestions
Introduction
• Group Members:– Salim Hamed– Alex Odle– Matt Simon– Micael Thiodet
Goals and Constrictions• Goal:
– Build an efficient bridge
• Constrictions:– Limited Materials– Limited dimensions– Limited Time
Group Goal
Our group initially decided that we were going to focus on efficiency rather than overall weight the bridge can support. For these reasons both the prototype bridge and the final bridge was created using fishing line as substantial material.
Prototype Testing
Types of Considered Bridges:
Cable Stay Bridge
Suspension Bridge
Our Choice… Cable-Stay Bridge
Reasons why we picked a cable-stay:– The supported weight will be forced down to
the sides of the jig– Less materials because we will utilize the
fishing line– Aesthetically pleasing a.k.a. “sexy”
The Completed Prototype
Before the Test After the Test
FAILURE POINT
Results of the Prototype Test
Weight: 0.685 lbs Max. Load: 70 lbs Efficiency: 102
The prototype bridge failed because the fishing line was not under tension. Therefore all the weight was being supported by the deck, which was not designed to support all the weight on its own.
Final Design
Changes made to the final design:– Complete redesign of the bridge– Final bridge will have a string based structure
Reasons for the changes:– More efficient than prototype– Less complicated than prototype–
And still “sexy”
The Final Bridge
Carlos Santana(named for obvious reasons)
Results of the Final Test
Weight: 0.04 lbs Max. Load: 75 lbs Efficiency: 1875
The results of the final test were very pleasing. The bridge didn’t actually fail, instead as the string flexed the metal plate that was resting on the string interfered with the jig. As a result we had to stop the test. Our improvement worked just as we had planned. The bridge was very efficient as seen by the efficiency rating.
Irony?... I think not
In Conclusion…
Carlos Santana
Final Thoughts and Suggestions
Final Thoughts:• We would have used a different size metal platform so
Carlos Santana could have tested until failure
Suggestions:• Have good group communication• Budget materials wisely• Spend plenty of time at the drawing board designing the
bridge• When gluing, don’t use too much glue and clamp the
wood while it is drying
THANK YOU Very Much… Are there any questions?
Good! Because I want to go check and see if my hair
still looks as good as it does in this picture