bridge

61
MAB1053 Bridge Engineering Introduction Prof. Dr. Azlan Abdul Rahman Faculty of Civil Engineering, UTM,

Upload: illpa

Post on 27-Jan-2015

12.005 views

Category:

Technology


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Bridge

MAB1053 Bridge Engineering

IntroductionProf. Dr. Azlan Abdul Rahman

Faculty of Civil Engineering, UTM,

Page 2: Bridge

Course Objectives

Upon completion of the course, participants will be able to: Identify types, structural forms & design process of

common concrete bridges. Perform basic calculations of bridge live loading based on

BS5400, BD37/01 & JKR Specification. Use LUSAS finite element program for basic analysis of

concrete bridge deck. Perform calculations for the basic design of prestressed

concrete bridge beam, bridge abutment and pier.

Page 3: Bridge

CONTENT WEEK/DATE LECTURER CONTENT WEEK/DATE LECTURER

1. INTRODUCTION

- Introduction to Bridges

- Choice of Bridge Decks

W1 (12/7/07)

W2 (19/7/07)

Ir. Dr. Wahid

Prof. Azlan

4.0 METHODS FOR BRIDGE DECK ANALYSIS

- Introduction to Bridge Deck Analysis

- Orthotropic Plate Theory- Grillage Analysis- Finite Element Analysis- LUSAS Software- Worked Example

W8 (30/8/07)

W9 (6/9/07)

W10 (13/9/07)W11 (20/9/07)W12(27/9/07)

Dr. Redzuan

Dr. Redzuan

1st RamadhanDr. RedzuanDr. Redzuan

2.0 BRIDGE SUB-STRUCTURE- Bridge Abutments & Piers- Bridge Bearings & Joints- General Bridge Loading

W3 (26/7/07)W4 (2/8/07)W5 (9/8/07)

Prof. AzlanProf. AzlanProf. Azlan

5.0 PRESTRESSED CONCRETE BRIDGE

- Fundamentals of Prestressed Concrete

- Design of Post-Tensioned Concrete Beam

- Composite Prestressed Concrete

W13 (4/10/07)

W14(11/10/07)

W15(18/10/07)

Ir. Dr. Wahid

Ir. Dr. Wahid

Ir. Dr. Wahid

3.0 BRIDGE LOADING- General Bridge Loading- Live Loads to BS5400 &

BD37/01 & JKR Live Loads

- Examples

W6 (16/8/07)

W7 (23/8/07)

Prof. Azlan

Sem. Break

Lecture Time Table

Page 4: Bridge

Introduction to Bridges

MAB1053

Bridge Engineering

Page 5: Bridge

What is a bridge?

A bridge is a structure that spans a divide such as:• A stream/river/ravine/valley

• Railroad track/roadway/waterway The traffic that uses a bridge

may include:• Pedestrian or cycle traffic

• Vehicular or rail traffic

• Water/gas pipes

• A combination of all the above

Page 6: Bridge

Function of A Bridge

A bridge has to carry a service (which may be highway or railway traffic, a footpath, public utilities, etc.) over an obstacle (which may be another road or railway, a river, a valley, etc.) and to transfer the loads from the service to the foundations at ground level.

Page 7: Bridge

Classification of Bridges According to functions : aqueduct, viaduct, highway,

pedestrian etc. According to materials of construction : reinforced concrete,

prestressed concrete, steel, composite, timber etc. According to form of superstructure : slab, beam, truss,

arch, suspension, cable-stayed etc. According to interspan relation : simple, continuous,

cantilever. According to the position of the bridge floor relative to the

superstructure : deck, through, half-through etc. According to method of construction : pin-connected,

riveted, welded etc.

Page 8: Bridge

Classification of Bridges According to road level relative to highest flood

level : high-level, submersible etc. According to method of clearance for

navigation : movable-bascule, movable-swing, transporter

According to span : short, medium, long, right, skew, curved.

According to degree of redundancy : determinate, indeterminate

According to type of service and duration of use : permanent, temporary bridge, military

Page 9: Bridge

General Span Types

Page 10: Bridge

Materials for Construction

Page 11: Bridge

A Typical Single Span Bridge

Page 12: Bridge

Basic Components of a Bridge

Page 13: Bridge

Bridges which Carry Loads Mainly in Flexure By far the majority of bridges are of this type.

The loads are transferred to the bearings and piers and hence to the ground by slabs or beams acting in flexure, i.e. the bridges obtain their load-carrying resistance from the ability of the slabs and beams to resist bending moments and shear forces.

Only for the very shortest spans is it possible to adopt a slab without any form of beam. This type of bridge will thus be referred to generally as a girder bridge.

Page 14: Bridge

Typical Beam/Girder Bridge

Page 15: Bridge

Bridges which Carry their Loads Mainly as Axial Forces

This type can be further subdivided into those bridges in which the primary axial forces are compressive (arches) and those in which these forces are tensile (suspension bridges and cable-stayed bridges). Such forces normally have to be resisted by members carrying forces of the opposite sense.

It must not be thought that flexure is immaterial in such structures. Certainly, in most suspension bridges, flexure of the stiffening girder is not a primary loading in that overstress is unlikely to cause overall failure; however, in cable stayed bridges (particularly if the stays are widely spaced) flexure of the girder is a primary loading.

Page 16: Bridge

Bridges which Carry their Loads Mainly as Axial Forces

Page 17: Bridge

Bridges which Carry their Loads Mainly as Axial Forces

Page 18: Bridge

Basic Types of Bridges

Girder/Beam Bridge Truss Bridge Rigid Frame Bridge Arch Bridge Cable Stayed Bridge Suspension Bridge

Page 19: Bridge

Girder/Beam Bridge

• The most common and basic type

• Typical spans : 10m to 200m

Page 20: Bridge

Truss Bridge

• Truss is a simple skeletal structure.

• Typical span lengths are 40m to 500m.

Page 21: Bridge

Forces in a Truss Bridge

In design theory, the individual members of a simple truss are only subject to tension and compression and not bending forces. For most part, all the beams in a truss bridge are straight.

Page 22: Bridge

Arch Bridges Arches used a curved

structure which provides a high resistance to bending forces.

Both ends are fixed in the horizontal direction (no horizontal movement allowed in the bearings).

Arches can only be used where ground is solid and stable.

Hingeless arch is very stiff and suffers less deflection.

Two-hinged arch uses hinged bearings which allow rotation and most commonly used for steel arches and very economical design.

Hinge-less Arch

Two hinged Arch

Page 23: Bridge

Arch Bridges

The three-hinged arch adds an additional hinge at the top and suffers very little movement in either foundation, but experiences more deflection. Rarely used.

The tied arch allows construction even if the ground is not solid enough to deal with horizontal forces.

Three-hinged Arch

Tied Arch

Page 24: Bridge

Forces in an Arch

Arches are well suited to the use of stone because they are subject to compression.

Many ancient and well-known examples of stone arches still stand to this today.

Page 25: Bridge

Cable Stayed

A typical cable-stayed bridge is a continuous deck with one or more towers erected above piers in the middle of the span.

Cables stretch down diagonally from the towers and support the deck. Typical spans 110m to 480m.

Page 26: Bridge

Cable Stay Towers

Cable stayed bridges may be classified by the number of spans, number and type of towers, deck type, number and arrangement of cables.

Page 27: Bridge

Cable Stay Arrangements

Page 28: Bridge

Cable Stayed Bridges

Page 29: Bridge

Suspension Bridge

A typical suspension bridge is a continuous deck with one or more towers erected above piers in the middle of span. The deck maybe of truss or box girder.

Cables pass over the saddle which allows free sliding. At both ends large anchors are placed to hold the ends of the

cables.

Page 30: Bridge

Forces in Suspension Bridge

Page 31: Bridge

Site Information

Survey - existing ground level and site details. Soil investigation - at least one bore-hole for each support

position to determine safe bearing pressure, aggressive conditions and predict settlement.

Mining - details of old working and future seams. River Board – navigation requirements, maximum flood

levels and scour problems around foundations. Railways – frequency of trains, available track possession,

minimum headroom, position of supports and piling techniques.

Statutory Undertakers – diversion of existing services, provision for future services in the deck.

Page 32: Bridge

Site Information

Planning Authorities – normally concerned with aesthetic appeal and the effect on local amenities.

Road Geometry – details of horizontal and vertical alignment together with the road cross-section.

Design Standards – design live loading, visibility distances, headroom standards and horizontal clearances.

Time – the time for design and the phasing of construction in relation to other work.

Atmospheric Conditions – an aggressive environment may involve high maintenance costs for steel construction and special precautions in the detailed specification.

Page 33: Bridge

Conceptual Choice Considerations

Initial conceptual choice should take account of: clearance requirements and the avoidance of

impact damage type & magnitude of loading topography and geology of the site possible erection methods local skills and materials future inspection and maintenance aesthetic and environmental aspects

Page 34: Bridge

Factors Affecting Conceptual Choice

The functional considerations that have greatest influence on conceptual choice are:

The clearance requirements (both vertically and horizontally) and avoidance of impact

The type and magnitude of the loading to be carried

The topography and geology of the site

Page 35: Bridge

Clearance Requirements All bridges must be designed to ensure, as far as is

possible, that they are not struck by vehicles, vessels or trains which may pass below them. This requirement is normally met by specifying minimum clearances.

It must be remembered that designed values must take into account deflections due to any loading that may occur on the bridge structure.

Clearance requirements may thus determine the span of a bridge and also have a significant bearing on the construction depth. Whilst the requirements will not normally determine precisely the type of bridge, it may well eliminate some possibilities.

Page 36: Bridge

Clearance Requirements

Typically, for example, a bridge over a major highway would be expected to have a minimum vertical clearance of about 5,3 metres; even this may not protect it from accidental impact

In addition, pier positions must be such that the likelihood of impact from errant vehicles is minimised, both to protect the pier and the vehicle itself. This requirement is usually achieved by setting the pier back a reasonable distance from the edge of the carriageway.

Page 37: Bridge

Clearance Requirements Navigation authorities specify clearances over rivers,

to allow not only for the mast height and width of vessels below the bridge, but also for particular requirements for piers in the waterway (or on a flood plain) to avoid excessive flow velocity and scour of river banks.

In considering vertical clearance, a designer must bear in mind the problems of attaining them. The approach gradient for a highway bridge should not normally exceed about 4% and a railway bridge much less. This is of great importance when comparing fixed with moving bridges.

Page 38: Bridge

Loading

The type and magnitude of loading has a significant bearing on the form of bridge. Highway loading by its nature is impossible to determine exactly, either in disposition or in magnitude.

A highway bridge requires a deck on which the traffic can run and (unless the span is so short that a simple slab is adequate to span between abutments) the deck must be strong enough to distribute the loading to the main girders.

Page 39: Bridge

Loading Every country has its own specification for the magnitude of

loading on highway and railway bridges. For highway bridges most national codes have in common a uniform loading together with a line load (or series of point loads) to represent isolated heavy axles. In many codes, the uniform load is of decreasing intensity as the length of bridge increases, to allow for the reduced probability of a concentration of heavy lorries.

Furthermore, there are rules for multiple lane loadings, frequently assuming that not more than two lanes are fully loaded at any one time, again based on a probabilistic approach. Many authorities also specify checks for a single very heavy abnormal vehicle. In many codes, the effect of impact (dynamic magnification) of highway loads is implicitly taken into account by the static load specification.

Page 40: Bridge

Loading Additionally, forces arising from braking or

acceleration of vehicles, centrifugal effects on curved bridges, temperature effects and wind have to be taken into account where relevant.

Whilst the details of applied loads are appropriate to the detailed design, rather than the conceptual design of a bridge, certain aspects enter into the concept. For example, where heavy abnormal vehicles are specified, the bridge will require good transverse load distribution.

Page 41: Bridge

Topography & Geology of Bridge Site

The overall topography of the site will probably determine the line of the road or railway. Not infrequently this may mean that bridges will have to cross other roads, railways or rivers at a substantial angle, resulting in skew spans. Generally, the bridge site is fixed by the geometry of the obstacle and local terrain.

The road may be on a curve; whilst it is possible to curve a bridge to follow this, it is frequently expensive and structurally inefficient, usually dictating the use of torsionally stiff girders even for short spans. If the curve is slight, it may be preferable to construct the bridge as a series of straight spans.

Poor foundation conditions will favour fewer foundations and hence longer spans. A balance has to be found between the cost of foundations and superstructure to minimise the total cost.

Page 42: Bridge

Other Factors

Method of Erection It has long been appreciated that a designer must

consider at the design stage the method by which a bridge will be erected. Indeed it is not infrequently the case that such consideration should be made even at the time of conceptual choice, since it can happen that the superficially most attractive design is impossible to erect in a particular location.

For example, a design that relies on being erected in large pieces (such as a major box girder), may be ruled out because of the impossibility of transporting such pieces to a remote site with inadequate access roads.

Page 43: Bridge

Other FactorsLocal Constructional Skills and Materials A bridge should be suited to local technology. It is not sensible

to specify a sophisticated design if all the material and labour has to be imported.

Future Inspection and Maintenance Lack of attention to future maintenance both at the conceptual

design and the detailed design stages would results in many bridges, otherwise satisfactory, have deteriorated because of difficulty in inspection and maintenance. It is particularly important that in locations where access is difficult (either physically or because it would cause disruption of services) details which deteriorate should be avoided as far as possible. This will be considered further in various respects, for example whether a bridge should be a series of simple spans or should be continuous.

Page 44: Bridge

Other FactorsAesthetic and Environmental Aspects The appearance of bridges has in recent years become a

matter of considerable importance. Frequently, a scheme takes a road or railway through an area of great natural beauty and it is important that any structures are in keeping with these surroundings and do not adversely affect them.

For example, it is commonly accepted that a bridge is more aesthetically pleasing with an odd number of spans than an even number. In addition, a degree of deepening at piers can add to the attraction.

The 3-span structures are more attractive than the two span ones. Hence, unless there are other contra-indications, the conceptual choice should probably tend towards a 3-span solution.

Page 45: Bridge

Estimated Bridge Costs

Page 46: Bridge

Detailed Design Considerations

The design development needs to make the correct choices for:

deck structure layout i.e. spans and structural arrangements continuous or simple construction proportions, i.e. span/depth ratios reducing fabrication labour to a minimum design for ease of construction

Page 47: Bridge

Basic Components of a Bridge

The two basic parts are: Substructure - includes the piers, the abutments and the

foundations. Superstructure - consists of the deck structure itself,

which support the direct loads due to traffic and all the other permanent and variable leads to which the structure is subjected.

The connection between the substructure and the superstructure is usually made through bearings. However, rigid connections between the piers (and sometimes the abutments) may be adopted, particularly in frame bridges with tall (flexible) piers.

Page 48: Bridge

Substructure : Piers

Piers are of two basic types:

Column piers - Concrete column piers may have a solid cross-section, or a box section may be the shape chosen for the cross-section for structural and aesthetic reasons.

Wall piers - generally less economical and less pleasing from an aesthetic point of view. They are very often adopted in cases where particular conditions exist, e.g. piers in rivers with significant hydrodynamic actions or in bridges with tall piers where box sections are adopted.

Page 49: Bridge

Basic Types of Bridge Piers

Page 50: Bridge

Substructure : Abutments The abutments establish the connection between

the bridge superstructure and the embankments. They are designed to support the loads due to the superstructure which are transmitted through the bearings and to the pressures of the soil contained by the abutment.

The abutments must include expansion joints, to accommodate the displacements of the deck, i.e. the longitudinal shortening and expansion movements of the deck due to temperature.

Page 51: Bridge

Basic Types of Abutments

Two basic types of abutments may be considered: Wall (counterfort) abutments and Open abutments. Counterfort wall abutments are adopted only when the

topographic conditions and the shapes of the backfill are such that an open abutment cannot be used. They are generally adopted when the required height of the front wall is above 5.0 to 8.0m. If the depth is below this order of magnitude, counterfort walls may not be necessary and a simple wall cantilevering from the foundation may be adopted.

The connection between the abutments and the backfill may include an approach slab which ensures a smooth surface of the pavement even after settlement of the adjacent backfill.

Page 52: Bridge

Basic Types of Bridge Abutments – Wall & Counterfort

Wall Abutment Counterfort

Page 53: Bridge

Types of Wall Abutments

Page 54: Bridge

Basic Types of Bridge Abutments – Open Type

Page 55: Bridge

Superstructure – Structural Systems The longitudinal system of a bridge may be one

of the following types: beam, frame, arch, cable stayed or suspension.

There are three main types of bridge transverse systems, slab, beam-slab or box girder.

Bridge superstructures may use the beam and plate girder, truss girder or box girder structural systems.

Deck systems use a reinforced concrete slab, with or without cross-girders, or a partially prestressed concrete slab, or an orthotropic steel plate.

Page 56: Bridge

Bridge Longitudinal Structural Systems

Page 57: Bridge

Bridge Deck The principal function of a bridge deck is to

provide support to local vertical loads (from highway traffic, railway or pedestrians) and transmit these loads to the primary superstructure of the bridge.

As a result of its function, the deck will be continuous along the bridge span and (apart from some railway bridges) continuous across the span. As a result of this continuity, it will act as a plate (isotropic or orthotropic depending on construction) to support local patch loads.

Page 58: Bridge

Design Case Study

MAB1053

Bridge Engineering

Page 59: Bridge

Bridge Layout Plan

Page 60: Bridge

Longitudinal & Transverse Sections

Page 61: Bridge

Deck and Piers