brentwood union free school district 2006 bond referendum capital improvement program pool phase,...

10
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Upload: norma-walters

Post on 29-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Brentwood Union Free School District

2006 Bond Referendum

Capital Improvement Program Pool Phase, Phase IA, II, III, and IV.

April 28, 2008

Prepared by:

Page 2: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Pool Phase “Ross House Pool”

Ceramic tile and painting in the new changing areas and First Aid office are complete.

New plumbing fixtures are ready to be installed in these areas.

Brentwood UFSD

Page 3: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Pool Phase “Ross House Pool”

The Illumawave lighting system has been installed in the main pool room.

New ceramic tile in the main pool room is currently being installed.

Brentwood UFSD

Page 4: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Pool Phase “Ross House Pool”

The installation of the new filtration system is nearing completion.

Brentwood UFSD

Page 5: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Phase IA

Brentwood UFSD

Phase IA Fire Alarm, Exterior Door, and Bleacher replacement projects are complete.

Contractors have completed punch list work and are currently in the closeout process.

Page 6: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Phase II

- North Elem. School - Ross Center

- Northeast Elem. School - Oak Park Elem. School

- North Middle School - E. Kindergarten Center

- Twin Pines Elem. School - West Middle School

Brentwood UFSD

The following buildings are associated with Phase II which will begin this summer.

Page 7: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Phase II (cont’d)

Brentwood UFSD

The scope of work in Phase II will include: Window replacements Electrical, HVAC system, Plumbing upgrades Fuel tank replacementsExterior bleachers and Site workExterior door replacementsLocker room renovations Space expansion at selected buildings

Phase II is currently in the Planning/Design phase. Drawings were to submitted to S.E.D. in December, 2007.

Page 8: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Phase III

Brentwood UFSD

• Phase III includes work at all schools.

• The scope of work is limited to district-wide Technology and Security upgrades.

• Technology bids have been awarded and work has begun at the High School.

Security bids have been received and are currently being evaluated by the Architect, Construction Manager and District.

Page 9: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Phase IV

- Pine Park Elem. School - South Middle School

- Freshman Center - East Middle School

- Ross Center - Southeast Elem. School

- Sonderling Center - Laurel Park School

- Loretta Park School - Southwest Elementary

- Hemlock Park School

Brentwood UFSD

The following buildings are associated with Phase IV which is scheduled to begin in the summer of 2009.

Page 10: Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:

Phase IV (continued)

Brentwood UFSD

The scope of work in Phase IV will include: Window replacements Electrical, HVAC system, Plumbing upgrades Fuel tank replacementsExterior bleachers, Tennis courts, and Site workLocker room renovationsMisc. exterior door replacementsMisc. flooring replacementsAuditorium renovationsRoofing replacementSpace expansion at selected buildings.

Phase IV is currently in the Planning/Design phase.