Bill of Quantities - ROAD
Bill No. 1 - Phase 1
ON-SITE ACCESS ROADS, FOOTPATHS AND STORM WATER DRAINAGE
ITEM Description UNIT QTY RATE AMOUNTNo. KShs. Cts
ON-SITE ACCESS ROADS
Earthworks
A101 Clear site of bushes and undergrowth including
grubbing up their roots and disposing. ITEM SUM 100000 100000
A102 Cut down trees girth 500 mm measured 1 metre
from the ground ITEM SUM 50000 50000
A103 Excavate black cotton soil material and cut
to spoil in approved area. Depth n.e. 1m. CM 1040 450 468000
A104 Compaction of base of excavated surface. SM 1040 100 104000
A105 CM 800 700 560000
A106 CM 160 700 112000
A107 CM 104 700 72800
A108 SM 780 150 117000
A109 SM 1040 250 260000
A110 Precast conrete kerbs 250mm x 125mm onclass 15/20 concrete bed 250mm x 180mm andhaunch 125mm thick, laid to straight. LM 260 700 182000
A111 Extra over for kerbs laid to radius. LM 20 700 14000
PAGE TOTALCARRIED FORWARD TO SECTION COLLECTION SHEET 2,039,800
Page 1 of 4
Note: For brevity item description for permanent works generally identify the components of works. The rate must cover for provide, place, compact and all works necessary to complete work as per specification.
Fill in murram or other equal and approved subgrade material compacted to 90 percent Maximum dry Density (M.D.D) to Engineer's approval.
150 mm thick murram or other equal and approved subbase material compacted to 100 percent Maximum Dry Density (M.D.D) to Engineer's approval.
300 mm thick approved handpacked hardcore basecourse compacted to 100 percent Maximum Dry Density (M.D.D) to Engineer's approval.
Provide 50mm thick (average) sand bed to receive paving blocks.
Treat surface of formation with approved persistent herbicide
Bill of Quantities - ROAD
Bill No. 3
ON-SITE ACCESS ROADS, FOOTPATHS AND STORM WATER DRAINAGE
ITEM Description UNIT QTY RATE AMOUNTNo. KShs. Cts
A112 SM 780 1500 1170000
A113 Precast concrete channels 125mm x 100mm on class 15/20 concrete bed 125mm x 180mm thick, laid to straight. LM 130 600 78000
A114 E.O for channels laid to radius. LM 20 600 12000
FOOTPATHSEarthworks
A115 Excavate black cotton soil material and cut
to spoil in approved area. Depth n.e. 0.3m. CM 140 300 42000
A116 Compaction of base of excavated surface. SM 195 300 58500
A117 Fill in selected gravel material, CBR>15, to formation level in layers not exceeding 150mm
compacted thickness. CM 195 300 58500
Base
A118 Provide and lay 150mm thick compacted
natural gravel sub-base material CBR>30. CM 60 450 27000
A119 SM 195 150 29250
SM 195 250 48750
Surfacing in footpath
A120 Precast light duty paving slabs 600mm x 600mm
x 50mm on 50mm graded sand-bed. SM 195 1100 214500
PAGE TOTAL CARRIED FORWARD TO SECTION COLLECTION SHEET 1,738,500
Provide and lay to fall 60 mm thick Heavy duty interlocking precast concrete paving blocks as per "BAMBURI BLOX" catalogue or other equal and approved manufacturer's catalogue including vibrating down with an appoved plate compactor.
Provide 50mm thick (average) sand bed to receive paving slabs.
Treat surface of formation with approved persistent herbicide
Page 2 of 4
Bill of Quantities - ROAD
Bill No. 3
ON-SITE ACCESS ROADS, FOOTPATHS AND STORM WATER DRAINAGE
ITEM Description UNIT QTY RATE AMOUNTNo. KShs. Cts
STORMWATER DRAINAGE
Excavation for lined block drains and earth
A121 Excavate trench for earth drain and for lined drain
as indicated on the drawings from the existing CM 78 450 35100ground level to the bottom of trench Depth 0.5m - 1.0m.
A122 Provide lay and joint precast concreteinvert block drain units (concrete mix 1:2:4) on100mm murram bed. LM 150 1200 180000
Culvert pipes
A123 Excavate trench for pipe culverts to the depth
instructed. Depth n.e. 1.5m. CM 9 450 4050
A124 Provide and lay 300mm DIA precast concreteogee pipes in trenches for culverts depth n.e. LM 9 3000 27000
A125 Mass concrete 100mm thick bed and surround
type 'B' to culverts (concrete mix 1:3:6). CM 9 105 945
A126 100 mm thick base slab 12 100 1200
Sawn formwork as described
A127 Sides of base 0-100 mm girth LM 15 100 1500
Filling
A128 Approved hand packed hardcore to sides of CM 5 700 3500
culvert to engineers details
A129 Smooth dressed quarry stone or equal and SM 12 1200 14400
approved walling in cement:sand (1:4) motar
PAGE TOTAL CARRIED FORWARD TO SECTION COLLECTION SHEET 267,695
Page 3 of 4
Bill of Quantities - ROAD
Bill No. 3
ON-SITE ACCESS ROADS, FOOTPATHS AND STORM WATER DRAINAGE
ITEM Description UNIT QTY RATE AMOUNTNo. KShs. Cts
Page total page 1 2,039,800
page total page 2 1,738,500
Page total page 3 267,695
SUB TOTAL 1 4,045,995
ADD 16 % VAT 647,359
SUB TOTAL 2 4,693,354
Total Inclusive of Taxes 4,693,354
Page 4 of 4