box excavation
TRANSCRIPT
-
8/12/2019 box excavation
1/6
User Guide
Backhoe Boxes - Issue 2 - Apr 2012
Backhoe Boxes
Important Notes
All excavation work must be thoroughly planned before work commences onsite to identify hazards and assess risk.
These instructions form guidance for backhoe manhole and trench boxes.Non-standard applications should be approved by a suitably qualified
engineer.
Ensure all personnel engaged in installation operations are properly briefedand adequately supervised by a competent person.
All hires for this equipment will usually be accompanied by a generalarrangement or scheme specific drawing. This must be read in conjunction
with these instructions
IF IN ANY DOUBT SEEK FURTHER ADVICE:
ON FREEPHONE - 0800 000 345
-
8/12/2019 box excavation
2/6
User Guide
Backhoe Boxes - Issue 2 - Apr 2012
Introduction
Equipment Identification
Type Length(m)
Height(m)
InternalWidth (m)
PanelThickness
(mm)
Clearancebetween
struts (m)
Clearanceunder
struts (m)
PanelWeight
(kg)
ApproxWeight ofbox (kg)
Trench Base 2.85 2.0 0.3 - 2.35 63 2.65 1.3 310 740*
Trench Top 2.85 1.0 0.3 - 2.35 63 2.65 1.3 175 394*
2.5m ManholeBase
2.5 2.0 2.38 60 2.35 1.2 427 1116**
2.5m ManholeTop
2.5 1.0 2.38 60 2.35 N/A 225 526**
3.0m ManholeBase
3.0 2.0 2.88 60 2.87 1.2 487 1305**
3.0m ManholeTop
3.0 1.0 2.88 60 2.87 N/A 280 605**
* Typical value, the weight will vary with strut configuration supplied** Weights for Square set up. Other widths are possible if trench box struts are used.
2.0m Manhole
Base
2.0 2.0 1.88 60 1.85 1.2 420 912**
2.0m ManholeTop
2.0 1.0 1.88 60 1.85 N/A 220 456**
The Backhoe Box range has been developed to meet the needs of the contractor when using smaller 180 O
backhoe or rubber tyred excavator. With minimum weights of 645kg for the trench version, and 960kg forthe 2.5m manhole version, most small excavators can handle these boxes. The load capacity of 20 kN/m2allows the box to be used to depths of 4 metres in most soil types.
Lifting Chains: The end-user has a responsibility under LOLER to ensure that all lifting equipment is fit for use
Never snatch at the chain during removal of the box whilst using the four-legchain. If the box becomes stuck, seek further advice from Groundforce
Note:Handrail unitsare available for most
box types. ContactFreephone
0800 000 345 fordetails
-
8/12/2019 box excavation
3/6
User Guide
Backhoe Boxes - Issue 2 - Apr 2012
Assembly Instructions
MAIN BOX ASSEMBLY (applies to both types)
Using a certified sling connected to the four corners lifting points, place both box plates on firm level groundone facing up, and one facing down.
Place all four struts onto the bosses protruding from the panel facing upwards, and secure them using the20mm pin and retaining clip supplied.
Reconnect the sling to the lifting points of the panel facing downwards, and lift it into position above thestruts.
Lower the plate carefully, guiding the bosses into the ends of the upstanding struts.
Secure the struts to the panel with the remaining 4 pins and retaining clips.
Disconnect the lifting sling legs from the two lower lifting points, and lift the box to the upright working po-sition. Note: when not in use, it is essential that the boxes are stored on flat stable ground. If indoubt, they should be dug into the ground by at least 0.5m or stored flat on their side.
Connect the two free legs of the lifting sling to the upper lifting points of the other panel before lifting thebox into the trench.
Top extension boxes can be assembled in the same way, but only 2 struts are installed.
Always adopt safe working practices during assembly and use.
Connection Details and Width Arrangements
Strut LengthL (mm)
Strut Weight(kg)
InternalClearance
I (mm)
ExternalWidth
W (mm)250 5 300 430
375 8 425 555
425 9 475 605
550 12 600 730
700 15 750 880
850 18 900 1030
1150 * 24 1200 1330
1280 27 1330 1460
1780 ** 38 1830 1960
* denoted strut extension required forsquare set up on 2.5m manhole box
** denoted strut extension requiredfor square set up on 3m manhole box
-
8/12/2019 box excavation
4/6
User Guide
Backhoe Boxes - Issue 2 - Apr 2012
Connection Details and Width Ranges (cont)Connection Details and Width Ranges (cont)
The range of widths available can be increased by the use of the Strut Connector shown below. This allowsthe standard struts to be used in pairs in three combinations as shown below right. The assembledarrangement for the minimum configuration is shown below left, and the table shows the box dimensions for
all combinations in ascending width order.
Strut 1 Strut 2
Internal Dimension I (mm) External Dimension W (mm)
Configuration
Minimum Intermediate Maximum Minimum Intermediate Maximum
250 250 600 750 900 730 880 1030
250 375 725 875 1025 855 1005 1155
250 425 775 925 1075 905 1055 1205
250 550 850 1000 1150 980 1130 1280
375 425 900 1050 1200 1030 1180 1330
425 425 900 1050 1200 1030 1180 1330
375 550 950 1100 1250 1080 1230 1380
250 700 1025 1175 1325 1155 1305 1455
425 550 1050 1200 1350 1180 1330 1480375 700 1075 1225 1375 1205 1355 1505
550 550 1175 1325 1475 1305 1455 1605
250 850 1200 1350 1500 1330 1480 1630
425 700 1200 1350 1500 1330 1480 1630
375 850 1225 1375 1525 1355 1505 1655
550 700 1325 1475 1625 1455 1605 1755
425 850 1350 1500 1650 1480 1630 1780
700 700 1375 1525 1675 1505 1655 1805
550 850 1500 1650 1800 1630 1780 1930
700 850 1650 1800 1950 1780 1930 2080
850 850 1800 1950 2100 1930 2080 2230
NOTE: Struts above 850mm should NOT be used with the connector
Configuration
-
8/12/2019 box excavation
5/6
User Guide
Backhoe Boxes - Issue 2 - Apr 2012
Installation Procedures
After the ground has been excavated to about 1m or deeper as ground conditions permits, the box is lowered intothe trench using a 4-leg chain sling of the correct capacity. (Do notenter an unsupported excavation)
The excavator driver then progressively excavates between the two faces of the box plates and pushes down oneach of the four corners of the box in turn using the back of the machine bucket. The difference in heightbetween panel corners must not exceed 100mm during this operation otherwise damage to the boxmay occur This method continues until the desired depth is reached. Where top extensions are used, theseshould be attached to the base using the connectors supplied at each corner. This should be done when the topof the base is approximately 200mm above ground level. Each connector is secured using a pair of pins andretaining clips.
Extraction of the units is simply a reverse of the process, back filling the trench and then progressively pulling thebox upwards using the chain sling. If top extensions have been used, these should be disconnected as the jointbecomes clear of the ground, and then lifted clear before reconnecting the sling and continuing the extraction.
Note on flying the box above formationIt is recommended hat the box panels extend over the full height of the dig and not be flown
above the base of the excavation unless both the following conditions are met. a) The box isadequately supported and b) has been approved as a safe method of work by a risk assessmentundertaken by a competent person. In any case, the maximum height of unsupported ground
should always be minimised and never exceed 1m.
NOTE: ALWAYS USE A SECURED LADDERTO ENTER OR EXIT THE BOX.
NEVER ENTER AN UNSUPPORTED TRENCH
-
8/12/2019 box excavation
6/6
User Guide
Backhoe Boxes - Issue 2 - Apr 2012
Dos and Donts
Do Do Not
Inspect all components at start of every shift Assess weights correctly and use
appropriately certified lifting equipment. Toe-out base boxes by 50mm Provide support over the full height of the
dig Ensure all pins & clips are correctly fitted Use four panel connectors for upper box
attachment
Use only lifting points for chain attachment Provide edge protection or handrail panels Push the plates at the corner positions only Keep personnel clear of excavator slewing
zone Always use a banksman Locate underground services before
excavating Lay box flat before dismantling. Store assembled boxes on firm, level ground
only or lay flat on their sides
Exit the box into an unsupported area
Push plates down by more that 150mm at a
time Snatch the chain during removal
Climb on the struts always use a secured
ladder
Hang/store materials on the struts
Excessively force the box into the ground
Permit personnel in the box during installation
Accidentally strike the struts
Drag the box by any means
Use more than four extension bars per strut
Use more than two top extension boxes
unless specified by Groundforce
Load the struts laterally or vertically
Fly the boxes above the base of the
excavation unless approved by a competentperson