book 1 terms and conditions for construction - chicago make joints wider for re-pointing in one...
TRANSCRIPT
![Page 1: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/1.jpg)
CDWM 1 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
January 11, 2017
Addendum #1/Bid Postponement
PARTIAL DEMOLITION OF WILSON AVENUE AND FOUR-MILE WATER INTAKE CRIBS
DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
For which bids which were to be opened in the office of the Department of Procurement Services, Room 103, City Hall Chicago, Illinois 60602, on Tuesday, January 17, 2017 at 11:00 am Chicago time.
BIDDER WILL ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED ON THE PROPOSAL PAGE
NOTICE OF Addendum #1/Bid Postponement
1. Please note that the date of bid opening has been rescheduled to Thursday, January
26, 2017 at 11:00 am Chicago time.
Book 1 – Terms and Conditions for Construction
1. None.
Book 2 – Instructions and Execution Documents 1. On Page 21, Article 4 Submission of Proposal, First Paragraph:
See revised page 26 in this addendum.
Book 3 – Technical Specifications
1. The following paragraphs will be added to SECTION 35 10 00:
3.2 TEMPORARY BUOYS, POST CONSTRUCTION A. Clean buoys and accessories of all algae and bird waste. B. Restore light, horn, bell, bridle, chain, and sinker to “like new” condition. C. Crate as initially received from the manufacturer and deliver to the Jardine Plant.
2. The following reference will be added to SECTIONS 05 12 00 Structural Steel Framing,
05 50 00 Metal Fabrications, and 05 51 00 Metal Stairs:
ASTM A252 Standard Specification for Welded and Seamless Steel Pipe Piles
3. SECTION 31 08 13 CONCRETE FILLED STEEL PILES, paragraphs 2.1, F, 2. Is reworded as follows, “Fabricate as long as practical to minimize splicing during driving.”
![Page 2: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/2.jpg)
CDWM 2 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
Drawings
1. Drawing FA-200 as bubbled, attached, 2. Drawing FS-201 as bubbled, attached, 3. Drawing WA-200 as bubbled, attached. 4. Drawing WS-201 as bubbled, attached. Bidder’s Questions and Answers:
1. Question: It was mentioned at the Pre-bid that Jardine Water Treatment Plant cannot
be used as a staging & launch area for men & material for the project. It was then suggested that the City would inquire if Jardine could be used to shuttle labor only from the cribs locations. Please confirm if Jardine could be used as a staging point for Labor and/or Equipment & Materials.
Answer: The Contractor will not be allowed to use Jardine as a staging point.
2. Question: Note on page 6 of 122 & 33 of 122 says "Clean ports of debris prior to filling
with concrete. Please clarify what is "Debris"? Please clarify how much "debris" can be anticipated, so we can price this scope of work.
Answer: Debris is Lake Bottom sand and gravel transported there by wave action caused currents. The geometry of the debris deposits is shown and described in the July 23, 2014, Summary Report for Field Investigations provided on the CD in Appendix C. Those descriptions are reiterated as notes on drawings FS-100 and WS-100. The quantities can be estimated as 1 cy and 4 cy for ports #1 and #4 at Four-Mile and 9 cy for port #1 at Wilson. Underwater inspection video is available on DVD at the Department of Procurement Services, Room 103.
3. Question: Regarding using Lake Michigan water for concrete the specs state the
following. All other sources, such as use of Lake Michigan water shall be approved by the Representative of the Commissioner. Can filtered lake water be used for the production of concrete. Hinging it on a future approval is akin to “not approved” for bidding purposes.
Answer: Yes, it is the intent of the specifications that filtered lake water can be used in mixing concrete. Approval by the commissioner’s representative is required because environmental conditions such as algal blooms or accidental spills may make the lake water temporarily unsuitable for use.
4. Question: Please clarify if there is any aquatic wildlife removal within the project limits.
If so, what is the procedure to remove the wildlife?
Answer: There is no known aquatic wildlife at the cribs except for algae and a few zebra mussels. If inside the ports they should be scraped off and left on the lake bottom
![Page 3: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/3.jpg)
CDWM 3 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
exterior to the crib for food for fish prior to placing the grout bags. Note that any sand and gravel debris within the ports shall also be removed before placing the grout bags.
5. Question: Clarify if we are to include any wildlife habit permits with the bid. If so, which
permits are to be included?
Answer: There are no wildlife habitat permits to be acquired. The Contractor will be required to commence his bird discouragement activities on April 1.
6. Question: Confirm the Chicago residency requirement is zero percent.
Answer: Page 3 of Book 2 states the Project Area Participation Goal is 0%, however there is a provision for Chicago based firms, with affidavit for execution.
7. Question: Refer to Section 01 50 00. Confirm we are to have field offices at both the Wilson crib and Four Mile crib, as well as two more locations on land.
Answer: Field offices are to be provided at, at least 3 locations: Wilson Crib, Four Mile Crib, and the Land based office convenient to the Boat Landing Site. If more than one Landing Site will be used by the Contractor, an office shall be provided at the/each additional Landing Site.
8. Question: Clarify if the contractor is to provide boat/boats for use by the owner. If so, how often will boat access be needed by the owner?
Answer: Boats are not to be provided for use by the Owner. However, the Contractor shall allow Owner personnel to travel to and from the Cribs with Contractor personnel upon request. SECTION 01 14 00 specifies, “Contractor shall also provide transportation for up to three members of DWM staff when required.”
9. Question: Under Schedule of Prices, please elaborate on how the measurement for
items G-3 and G-4 is calculated. Quantities are listed in linear feet for each. Length of parapet (circumference) is shown as 370 ft. at Four-Mile and 220 ft. at Wilson. The estimates of quantities are 1,240 ft. and 730 ft. respectively. Do estimated lengths include both vertical and horizontal joints? As an extensive scaffolding system will be necessary to reach all the existing stonework, shall this scaffolding encompass each structure in entirety for examination and observation by the representative of the Commissioner? Is the pressure water cleaning/rinsing intended for the complete stonework area of each Crib or for only the portions to be designated for raking out and re pointing?
Answer: Estimate of pointing is approximately 10% of the total length of the Joints, not 25% as stated on the drawing in note 3. Joints requiring pointing may be either horizontal or vertical. Access to the masonry by the Commissioner’s representative will utilize the scaffolding utilized for pressure washing. Pressure water cleaning/rinsing is intended for the complete stonework area of each Crib. Such cleaning will help the Commissioner’s representative determine the location of joints to be repointed. The entire stone masonry parapet must be washed and inspected. The amount of
![Page 4: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/4.jpg)
CDWM 4 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
scaffolding required to perform the scope of work is the contractor’s means and methods.
10. Question: Specifications for Maintenance of Stone Masonry prohibit the use of grinding
to make joints wider for re-pointing in one location (1.5) and in another location (3.5) it directs to cut out center of mortar beds using angle grinders with diamond impregnated metal blades. Which is to be followed? Can pneumatic tools be used to remove existing mortar/grout?
Answer: Power tools are allowed to touch only the center of the mortar bed. Hand and chisel the remainder. Do not grind the stones.
11. Question: Will there be a source of electric power at each Crib location for using
tools/equipment throughout the duration of the project?
Answer: The Contractor shall provide all power and equipment needed to perform the work. There is no existing power source at the cribs.
12. Question: Which Pay Item number is the work at the Jardine Plant paid under?
Answer: Work at the Jardine Plant paid under G-1 and G-2. 13. Question: Confirm no industrial docking will be available to the contractor from the
Jardine Plant.
Answer: No industrial docking will be allowed at the Jardine Plant. 14. Question: Confirm working hours between sunset to sunrise will be allowed.
Answer: In accordance with Book 2, page 13: “The Contractor is to limit his working hours from sunrise to sunset seven days a week. Any variation from these restricted working hours to include extended shift hours can only be permitted with the written approval of the Commissioner.”
15. Question: Confirm no asbestos abatement should be included for the Wilson Avenue Crib. Answer: There is no asbestos at the Wilson Avenue Crib.
16. Question: Confirm there are no items of historical significance. Answer: The existing lighthouse beacons are historically significant and shall be salvaged and delivered to a location as directed by representative of the Commissioner. The existing solar collecting systems, while not historically significant, shall also be salvaged and delivered to a location as directed by representative of the Commissioner.
![Page 5: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/5.jpg)
CDWM 5 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
17. Question: Confirm all rebar is not epoxy coated. Answer: There is no requirement to use epoxy coated rebar. However, it is allowed.
18. Question: Refer to Spec 35 10 00 Part 1.1.C. Please clarify what needs to be renovated on each buoy. Answer: The following paragraphs will be added to SECTION 35 10 00: 3.2 TEMPORARY BUOYS, POST CONSTRUCTION
A. Clean buoys and accessories of all algae and bird waste. B. Restore light, horn, bell, bridle, chain, and sinker to “like new” condition. C. Crate as initially received from the manufacturer and deliver to the Jardine Plant.
19. Question: Is there any underwater video footage of the inspection of both cribs? If so
can it be made available to the bidders. Answer: Underwater inspection video is available on DVD at the Department of Procurement Services, Room 103.
20. Question: If bidding as a JV does the JV need a General Contractor’s licenses at the time of the bid or just if the project is awarded to the JV? Answer: To be answered by Procurement Services.
21. Question: If bidding as a JV does the JV need a Certificate of Eligibility from IDOT at the time of the bid or just if the project is awarded to the JV? Answer: To be answered by Procurement Services.
22. Question: If bidding as a JV does the JV need an IL Dept. of Human Rights Vendor number at the time of the bid or just if the project is awarded to the JV? Answer: To be answered by Procurement Services.
23. Question: Can the bid due date be extended for another two weeks?
Answer: See page 1 of Addendum No. 1.
24. Question: Regarding slope on geofoam blocks of 1%. Sheets 13 and 40 of the plan drawings. Speaking with the manufacturers, making up that slope is complicated / expensive. Are there other options for just making up the required capping slab slope in the pour with a flat geofoam level? Or can they be stepped using thin pieces? Thanks. Answer: Details shown are constructible. The 1% slope is to prevent ponding of water and frost heave. Bid per plans and specifications.
![Page 6: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/6.jpg)
CDWM 6 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
25. Question: Is there an Environmental Procedure for cutting steel coated with Lead Paint Underwater with Divers? Answer: There is no paint left on the submerged steel.
26. Question: Is the armored submarine power cable between the Wilson Ave Crib and the C.H. Harrison Crib still Active/Energized? Is the Contractor required to de-energize and remove the power cable? If so, what are the Removal Requirements and Limits of Removal? Answer: It is our understanding that there is no power or energy at the cribs other than existing solar power and battery system. It is also our understanding that the cable is not energized. The Contractor is required to remove it from the intake port and wet well.
27. Question: Are the Power Cables in the Crib Active/Energized? Answer: Possibly energized from the local solar power panels or batteries.
28. Question: Do any of the Power Cables; Submarine or w/in the Crib, contain an Oil Product to insulate/cool the Power Cables? If so, is the Oil Product a Hazardous Product? Answer: No liquid oil in cables.
29. Question: Do the Existing Transformers contain an Oil Product for insulation/cooling? If so, is the Oil Product a Hazardous Product? Answer: If oil is found, treat it as hazardous.
30. Question: Is the Fill inside the Wilson Landing Structure, Sand, Poured in Place Concrete, "Concrete Rubble Masonry"? Answer: Rubble Masonry
31. Question: Please provide a description of "Concrete Rubble Masonry" Answer: Stone rubble with concrete dumped over it and placed in it via tremie pipes.
32. Question: Hand written Comments on reference drawing CB-19 say "This Plan Not Followed". Should the Contractor disregard the Drawing, or the Hand Written Notes? Answer: It is our understanding that CB-19 was a design drawing and CB-21 was a record drawing.
33. Question: Is there an Existing/Functional Fire Suppression System? If so, what type of Suppression Agents are Present? Answer: No fire suppression system exists.
![Page 7: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/7.jpg)
CDWM 7 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
34. Question: A Reference drawing CB- 21 Landing Structure note states "Pipes are placed into the new concrete in order to grout the underlying material now in place". Is the "New Concrete" only a slab at elev. +7.0? Answer: It is our understanding that the top 7' is a slab placed in the dry and under that is rubble masonry. The intent of the specifications is to require removal of the entire 7’ thick slab and any rubble masonry down to elevation -30.0. Riprap and rubble below water level may be repositioned underwater to a location below -30.0. No material currently above water level or brought above water level may be repositioned and must be removed.
35. Question: What type of material was used to fill the dock structure, after the Timber Piles, Steel Sheet Piles, and Bracing Cables were installed? Answer: It is our understanding that fill is stone rubble with lean concrete tremied in as noted on the reference drawing.
36. Question: Regarding demolition of the Wilson roof, based on the Photos and Site Walk, it is apparent that the Roof Trusses & Framing are in various stages of deterioration and failure. Additionally, in their current configuration they are stabilizing the existing Masonry Walls, preventing both inward/Outward Failure. If removing the Roof Structure causes the Failure of the Existing Masonry Walls beyond the Limits of Removal, will the Contractor be compensated for the re-construction of the Masonry Walls?
Answer: No. The roof does not stabilize the masonry walls. Care shall be taken to protect the stone masonry walls from damage.
37. Question: Were the Repairs to the Four-Mile Landing Structure (Dock) shown on
reference drawing CF-2 actually performed?
Answer: Our inspection of the dock above and below water indicated the exterior matched CF-2.
38. Question: Regarding Four-Mile reference drawing CF 12, the Plan Elev. at 21'-8''
shows a "Future Power Cable" entering the Crib on the northeast side. Does the "Future Power Cable" exist, and is it still Active/Energized? Is the Contractor required to De-Energize and Remove the Power Cable? If so, what are the Removal Requirements and Limits of Removal? Are the Power Cables in the Crib Active/Energized? Do any of the Power Cables; Submarine or within the Crib, contain an Oil Product to insulate/cool the Power Cables? If so, is the Oil Product a Hazardous Product? Answer: The un-energized cable shown on drawing FS-100 shall be severed and removed from the intake port and wet well as part of demolition. The only electrical energy existing on the crib is the existing solar power and battery system. Cables do not contain liquid oil products.
39. Question: Reference drawing for the Machinery Plan, Four Mile Crib, shows a 3'' dia. Pipe coming out of the Compressor going 9 ft. above the floor heading to the west side of the Wet Well. From there the 3'' line runs both North & South around the perimeter. It
![Page 8: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/8.jpg)
CDWM 8 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
terminates at the NNE, and SE sides of the Wet well. At six Intake Ports the 3'' pipe is reduced to a 2-1/2'' pipe and drops vertically down to the horizontal centerline of the Intake Port (-33.0 CCD), and extends horizontally (supported on brackets anchored in the Intake Port) to the Exterior Radius of the Crib. Is this Piping a "gas line" as shown in the section? Or is it a "steam line"? Does this Piping Still Exist? Can this Piping be abandoned in place? Does this piping need to be removed before plugging the Intake Ports? Answer: Boilers were constructed and are part of the demolition. Port gates and hot water piping for deicing was not constructed. All existing piping is non active, has been abandoned, and shall be removed and disposed of.
40. Question: Drawing FS 100, Intake Port Bulkheads does not show the 2-1/2'' Pipes going through the Six Intake Ports that are shown on the Reference Drawings. Which drawing should the Contractor rely on in its Priced Proposal?
Answer: Referenced piping no longer exists.
41. Question: Drawing FS 500, Dock Platform new 4 ft. dia. Pipe Piles being driven less than 2 ft. from the Crib Substructure and +/- 35 ft. below the lake Bottom. Who will be responsible for damage to the Crib (ex. Remaining Masonry Joints) that is created from the Impact Driving Energy necessary to Drive this Large Pipe Pile into the Clay Hardpan? Answer: Care shall be taken to protect the portion of the crib to remain from damage. The Contractor is responsible for damage caused by its operations to portions of the structure to remain.
42. Question: What is the “Bird Nesting Season” that needs to be taken into account when developing the construction schedule?
Answer: Bird nesting season begins April 1.
43. Question: Regarding SECTION 31 08 13 CONCRETE FILLED STEEL PILES,
paragraphs 2.1, D. Specifies a ‘’internally tapered for friction fit driving.” Paragraph 2.1, F, 2. “Fabricate full-length piles to eliminate splicing during driving.” Which specification applies? Can Friction Splice Couplers be used during the Pile Driving? Answer: 2.1, F, 2 will be reworded to say “Fabricate as long as practical to minimize splicing during driving.” 2.1, D is intended if splices are necessary.
44. Question: Regarding SECTION 31 08 13 CONCRETE FILLED STEEL PILES, Part 3, paragraph A, 4. Driving Equipment, is a boot plate required on the bottom of the pipe piles? Is the Contractor required to bottom drive the pipe piles? Is mandrel driving Required? Can the pipe piles be top driven? Answer: Boot Plates shall not be used. All other questions are Contractor means and methods. Supply and install as shown and specified.
45. Question: Fill and compaction specification 31 23 23 1.1 B 2 states “The suggested method of compaction of the granular fill material is vibro compaction”. Are we required to dewater the structure to the lake bottom, and drop the sand in and vibro compact the
![Page 9: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/9.jpg)
CDWM 9 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
sand in lifts? Will the joints of the structure be able to withstand the pressure in the absence of water? Or will it be permissible to fill the structure dropping it through the water? Answer: No dewatering will be allowed.
46. Question: On the exterior stonework to remain, there are openings (ice chute for example) that is scheduled to be plugged with concrete. There are several smaller openings and voids throughout the wall that appear to be too large to fill with pointing mortar alone. Should these holes be filled with pieces of stone or other material to flush out to the face of the wall? Answer: The other holes are existing drainage openings which are no longer needed and recent stone fallouts. Penetrations through stone masonry parapet wall with a cross sectional area greater than 9 square inches shall be filled with concrete. Smaller penetrations and partial penetrations shall be repaired by pointing.
47. Question: Will class F fly ash be allowed in lieu of class C? Class F is not available. If Class C fly ash is not allowed (we would like an explanation why so we can potentially reply and answer questions to overcome) then is GGBFS allowed? The use of SCM's will be required to maintain workability and decrease set times with long hauls required on this project. Answer: Class F or Class C fly ash is acceptable.
48. Questions: Structural notes call for 4.5 lbs./cy of micro fiber. This is over the manufacturers recommended dosage rate. Ozinga proposes 1.0 lb./cy based on attached letter from manufacturer. Answer: The capping slab concrete mix shall contain synthetic micro fiber at the dosage rate of 1.0 pounds/cy.
49. Question: Structural notes state that corrosion inhibitor is required in capping slab concrete but dosage is not specified. Please specify dosage rate. Answer: The capping slab concrete mix shall contain corrosion inhibitor, meeting the requirements of ASTM C1582, at the dosage rate of 4.0 gallons/cy.
50. Question: Structural notes state maximum w/c ratio of 0.45 and 033100 states maximum w/c ratio is 0.42. What is the maximum allowable w/c ratio? Answer: Maximum w/c ratio shall be 0.45.
51. Question: On drawing sheet WS-101, plan notes #1 states to remove marine growth and sediment from the shaft walls at the concrete plug prior to placing riprap. Would scarping and or pressure washing the area clean be consider adequate for this? Answer: Scraping and pressure washing are acceptable methods for the removal of marine growth.
52. Question: On drawing sheet WS-101, plan notes #1 states to remove marine growth and sediment from the shaft walls at the concrete plug prior to placing riprap but doesn’t
![Page 10: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/10.jpg)
CDWM 10 Addendum #1/Bid Postponement DWM PROJECT NO. 13-107 SPECIFICATION NO. 221436
clearly state that the material need to be removed from the invert area of the shaft when shaft walls are clean. Can the sediment and marine growth stay in the bottom of the shaft or does the bottom of the shaft have to be cleaned out to solid invert? Answer: Sediment and marine growth that falls to the bottom of the shaft and is not moved down the tunnel toward shore by pressure washing may remain.
53. Question: When sealing the intake ports of both cribs with fabric grout filled bags what will be the determination of clean before the bags can be place? Answer: Scraping and pressure washing of the steel and wood surfaces.
54. Question: Before filling the shaft above the plug and the wet well areas of both cribs, does the sediment and wood, steel, concrete or brick debris need to be removed from these areas? Answer: Wood, steel, concrete and/or brick debris need to be removed prior to filling. Mineral sediment of gravel size or smaller may remain.
55. Question: If demolition work is performed before the shaft and wet well areas are completely filled with compacted material and some debris such as bricks or steel fall into area, does this debris need to be removed? Answer: See Question No. 54 answer.
End of Addendum #1/Bid Postponement
![Page 11: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/11.jpg)
![Page 12: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/12.jpg)
6"
VIF
4'-0"
VIF
7'-
0"
MIN
6"
HO
LL
OW
ME
TA
L
DO
OR
HEIG
HT
7'-
0"
HO
LL
OW
ME
TA
L
DO
OR
HEIG
HT
7'-
0"
OF ENTRANCE
1'-1" AT CENTER
30°
10•
"
HO
LL
OW
ME
TA
L
DO
OR
HEIG
HT
7'-
0"
3'-0"1'-6"
3"
9'-
2'
7'-
0"
5'-0" VIF
1'-6"
10'-0" }
1'-
7"
1'-
7"
4"
TOWER 37 122
SECTIONS
WS-201WILSON AVENUE CRIB
1' 2'0 4'
SCALE: 1/2"=1'-0"
NOTES:
SCALE: 1/2"=1'-0"
SCALE: 1/2"=1'-0"SCALE: 1/2"=1'-0"
NORTH ELEVATION
SECTIONSECTION1 2
3
WS-200 WS-200
WS-200
AM
FR
AS
AS
SEE SHEET DT-136 FOR ELECTRICAL BONDING INSIDE OF TOWER.9.
TOWER.
SEE SHEET WE-101 FOR ELECTRICAL EQUIPMENT MOUNTED INSIDE OF 8.
SYSTEM SW-1 OR T-2. COLOR SHALL BE A MEDIUM TONE GRAY.
PREPARATION. PAINTED PER SPECIFICATION SECTION 09 91 00
PREPARATION AND CLEANED PER SPECIFICATION FOR SHOP
TOOL CLEANED PER SSPC-SP2 OR SSPC-SP3 FOR IN-PLACE
THE EXISTING CRIB ENTRANCE DOOR SHALL BE HAND OR POWER 7.
G-002.
STEEL OF THE TOWER TO BE GALVANIZED AND PAINTED. SEE SHEET 6.
FOR OBSTRUCTION LIGHT POLE SEE DETAIL D ON DT-135.5.
FOR LIGHTNING PROTECTION POLE SEE DETAIL A ON DT-137.4.
SEE DT-070 FOR TYPICAL STAIR DETAILS.3.
PLATE STRUCTURE, SEE SHEET DT-136.
BONDING OF DOOR, DOOR FRAME, STAIRS PLATFORMS, AND STEEL
SEE TYPICAL GROUNDING AND LIGHTNING PROTECTION DETAILS FOR 2.
SEE GENERAL NOTES ON SHEET G-002 AND G-003.1.
10/7/2016
OF
PN
PERCENT COMPLETE DATE
BULLETIN
100
90
75
60
30
DRAWN:
DESIGNED:
CHECKED:
REVIEWED:
BUREAU OF ENGINEERING SERVICES
DEPARTMENT OF WATER MANAGEMENT
CITY OF CHICAGO
P:\
Rm
105413\
Desig
n\
Dw
g\
Structural\
CA
DD_Sheets\
CD
WM
19344-
WS-201-
TW
R_S
EC.d
gn
13-107
6/29/2016
10/10/2016
WS-200
1
WS-200
2
WS-200
3
WS-200
3
2
WS-200
1
WS-200
WS-200
3
WS-200
4
TO REMAIN
MASONRY
EXISTING
(TYP)
STAIR STRINGER
SPIRALING PLATE
BEYOND
ENTRANCE
LINE OF
SEE 8/WS-202
STAIR SUPPORT
PLATE (TYP)
STEEL TOWER WALL
AIR TERMINAL
LIGHTNING PROTECTION
MOUNTING POST FOR
T/BASE FLOOR
EL +12.00' CCD VIF
SEE 8/WS-202
STAIR SUPPORT
DETAILS
FRAME
FOR DOOR
DT-070
SEE DWG
BEYOND
DOOR
DETAILS
DOOR FRAME
DT-070 FOR
SEE DWG
DOOR BEYOND
(TYP)
WALL PLATE
STEEL TOWER
SEE WS-300
CONC CURB (TYP)
SEE WS-300
SLAB (TYP)
REINFORCED
T/BASE FLOOR
EL +12.00'CCD VIF
SEE PLAN
STEEL LADDER
SEE PLAN
DOOR
2'-0‚" ID
PORTHOLE
GEOFOAM
GEOFOAM
STEEL LADDER
OBSTRUCTION LIGHT
MOUNTING POSTS FOR
TERMINAL
PROTECTION AIR
FOR LIGHTNING
MOUNTING POST
7/FS-203
SEE DETAIL
CONDUIT SUPPORT
SEE PLAN
STEEL LADDER BEYOND
LIGHT
FOR OBSTRUCTION
MOUNTING POSTS
ELECTRICAL DWGS
JBOX LOCATION SEE
SEE ELECT DWGS
120VAC POWER,
SHIP BASED
RECEPTACLE FOR
SEE ELECT DWGS
TOP OF POST
GEOFOAM
OF C8
BOTTOM
STRINGER (TYP)
SPIRALING PLATE STAIR
ELECT DWGS TYP
TOP OF POST SEE
AIR TERMINAL
LIGHTNING PROTECTION
MOUNTING POST FOR
ON SHEET S-200
SEE PLAN NOTE 5
DOOR. SEE NOTE 7
PAINT EXISTING
VIF
EL +41.61'
T/ROOF HP
VIF
EL +41.86'
PLATFORM
T/STEEL
VIF
EL +41.61'
T/ROOF HP
VIF
EL +41.86'
PLATFORM
T/STEEL
VIF
EL +41.61'
T/ROOF HP
VIF
EL +41.86'
PLATFORM
T/STEEL
T/EXIT DOOR
STEEL PLATFORM
HP EL +30.83'
VIF
VIF
EL +21.16'
T/LANDING T/LANDING
EL +21.16'
VIF
VIF
EL +30.33'
T/LANDING
GEOFOAM
GUARD
4" TOE
42" AFF
STEEL GUARDRAIL
T/LANDING
EL +30.33'
WALKING
SURFACE
SHEET WG-100, TYP
GEOFOAM, SEE
GUARDRAIL
CENTERED ON
OBSTRUCTION LIGHT
MOUNTING POST FOR
(1.66 OD) STD, TYP
PIPES 1-1/4" DIA
VERTICAL POST
HORIZONTAL RAIL &
42" AFF.
STEEL GUARDRAIL
@4'-0" OC MAX
VERTICAL POST
AT LANDING
4" TOE GUARD
GUARD, TYP
4" TOE
CDWM19344-WS-201-TWR_SEC.dgn 10/7/2016 11:10:23 AM
10. STEEL TOWER WALL PLATE SHALL BE A252 GRADE 2 OR A36 STEEL.
![Page 13: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/13.jpg)
GR
ANIT
E
18'|
LI
MES
TO
NE
2'|
220'| PROJECTED LENGTH ALONG TOP OF PARAPET
220'| PROJECTED LENGTH ALONG BOTT. OF PARAPET
1.
PLAN NOTES:
20' 0 20'
10' 0 10'
0 1'1'
20' 0 20'
05' 5'
10/7/2016
OF
PN
LK
ACF
MRI
GL
PERCENT COMPLETE DATE
BULLETIN
100
90
75
60
30
DRAWN:
DESIGNED:
CHECKED:
REVIEWED:
6/29/2016
10/10/2016
BUREAU OF ENGINEERING SERVICES
DEPARTMENT OF WATER MANAGEMENT
CITY OF CHICAGO
pw:\\hntb
w356.h
ntb.org:P
WGreat_
Lakes\
Docu
me
nts\
Chic
ago
Projects\48555
CD
WM
Crib
s
De
mo\48555
Wilso
n
Ave
&
Fo
ur-
Mile
Water Intake\
Desig
n\
CA
DD\
CA
DD_Sheets\
CD
WM
19344-sht-
WA-200.d
gn
WA-200
13-107
WILSON AVENUE CRIBMASONRY REPAIRS
49 122
2.
3.
4.
ADDITIONAL WORK AT THE UNIT PRICE BID.
GREATER THAN THE PLAN QUANTITY, THE DEPARTMENT WILL PAY FOR THE
AND PAID FOR. IF THE ACTUAL QUANTITY OF EITHER REPOINTING ITEM IS
THE PLAN QUANTITIES SHOWN ARE THE MINIMUM THAT WILL BE MEASURED
MASONRY UNIT SIZE AND 25% OF JOINT LENGTHS REQUIRING REPOINTING.
THE QUANTITIES ARE ESTIMATED VALUES BASED ON A 5' X 2' AVERAGE
730 L.F. STONE MASONRY REPOINTING
ESTIMATED QUANTITIES OF REPOINTING:
THE COMMISSIONER.
REPOINT MORTAR JOINTS AS DIRECTED BY THE REPRESENTATIVE OF
DATUM
EL. 0.00
NO
RT
H
SO
UT
H
NO
RT
H
WES
T
EA
ST
B
REPOINTING
LIMESTONE MASONRY
B/PARAPET
EL. +9.00 V.I.F.
DETAIL D
SEE REPOINTING
SCALE:
PROJECTED WALL ELEVATION
1" = 5' VERTICAL1" = 20' HORIZONTAL
C
WA-200
WA-200
T/PARAPET
EL. +29.00 V.I.F.
EXIST. DOCK
ENTRANCE DOOR
EXIST. CRIB
REPOINTING
GRANITE MASONRY
DATUM
EL. 0.00
DEMOLITION DWGS.
TO BE REMOVED, SEE
EXIST. SUPERSTRUCTURE
THE COMMISSIONER
THE REPRESENTATIVE OF
AS DIRECTED BY
TO BE REPOINTED
EXIST. STONE MASONRY
T/PARAPET
EL. +29.00| V.I.F.
B/PARAPET
EL. +9.00 V.I.F.
NN
C
WA-200
SCALE:
PLAN
1" = 20'
A
WA-200
C
WA-200
CRIB ENTRANCE
EXIST. DOCK
SHAFT
LIMESTONE MASONRY
EXIST. GRANITE OR
THE SOUND SECTIONS OF THE WALL.
AND TOOL THE JOINTS TO MATCH THOSE IN
WITH WATER. FILL THE JOINTS WITH MORTAR
MORTAR OR SAND FROM JOINT AND FLUSH
OF THE COMMISSIONER, RAKE OUT LOOSE
AS DIRECTED BY THE REPRESENTATIVE
SCALE:
REPOINTING DETAIL
1" = 1'-0"
D
WA-200
10
![Page 14: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/14.jpg)
10"
2'-9ƒ"1'-8‚"
30.0
0°
HO
LL
OW
ME
TA
L
DO
OR
HEIG
HT
7'-
0"
10•
"
7'-
0"
7'-
Ž"
7'-
0"
VIF
7'-10"
VIF
1'-
0"
3"
6"
10•
"
10•
"
HO
LL
OW
ME
TA
L
DO
OR
HEIG
HT
7'-
0"
10'-0" DIA
10•
"
7'-
6"
VIF
1'-6"
1'-
7"
1'-
7"
4"
OF
PN
FOUR-MILE CRIBTOWER 10 122
SECTIONS
FS-201
1' 2'0 4'
SCALE: 1/2"=1'-0"
SECTION SECTION
NORTH ELEVATIONSCALE: 1/2"=1'-0"
SCALE: 1/2"=1'-0"SCALE: 1/2"=1'-0"
NOTES:
1
FS-200
1 2
FS-200
3
FS-200
AM
FR
AS
AS
TOWER.
SEE SHEET DT-136 FOR ELECTRICAL BONDING INSIDE OF 8.
INSIDE OF TOWER.
SEE SHEET FE-101 FOR ELECTRICAL EQUIPMENT MOUNTED 7.
SHEET G-002.
STEEL OF THE TOWER TO BE GALVANIZED AND PAINTED. SEE 6.
FOR OBSTRUCTION LIGHT POLE SEE DETAIL D ON DT-135.5.
FOR LIGHTNING PROTECTION POLE SEE DETAIL A ON DT-137.4.
SEE DT-070 FOR TYPICAL STAIR DETAILS.3.
DT-136.
PLATFORMS, AND STEEL PLATE STRUCTURE, SEE SHEET
DETAILS FOR BONDING OF DOOR, DOOR FRAME, STAIRS
SEE TYPICAL GROUNDING AND LIGHTNING PROTECTION 2.
SEE GENERAL NOTES ON SHEET G-002 AND G-003.1.
10/7/2016
OF
PN
PERCENT COMPLETE DATE
BULLETIN
100
90
75
60
30
DRAWN:
DESIGNED:
CHECKED:
REVIEWED:
BUREAU OF ENGINEERING SERVICES
DEPARTMENT OF WATER MANAGEMENT
CITY OF CHICAGO
P:\
Rm
105413\
Desig
n\
Dw
g\
Structural\
CA
DD_Sheets\
CD
WM
19344-FS-201-
TW
R_S
EC.d
gn
13-107
6/29/2016
10/10/2016
TERMINAL
PROTECTION AIR
FOR LIGHTNING
MOUNTING POST
OF C8
BOTTOM
GEOFOAM
DOOR
(TYP)
WALL PLATE
STEEL TOWER
SEE PLAN
STEEL LADDER
SEE FS-300
CONC CURB (TYP)
TO REMAIN
MASONRY
EXISTING
SEE FA-100
DOOR,
NEW STEEL
(TYP)
STAIR STRINGER
SPIRALING PLATE
SEE 8/FS-202
STAIR SUPPORT
BEYOND
ENTRANCE
LINE OF
SEE 8/FS-202
STAIR SUPPORT
3
FS-200
2
FS-200
FS-200
1
1
FS-200
2
FS-200
FS-200
3
3
FS-200
FS-200
4
EL +8.33' VIF
SEE ELECT DWGS, TYP
TOP OF POST
DWGS
SEE ELECT
TOP OF POST
7/FS-203
SEE DETAIL
CONDUIT SUPPORT
2'-0‚" ID
PORTHOLE
FOR CLARITY
NOT SHOWN
DOOR FRAME
SEE PLAN.
DOOR BEYOND
SEE FS-300
SLAB (TYP)
REINFORCED
GEOFOAMGEOFOAM
SEE PLAN
STEEL LADDER BEYOND
OBSTRUCTION LIGHT
MOUNTING POSTS FOR
AIR TERMINAL
LIGHTNING PROTECTION
MOUNTING POST FOR
LIGHT
FOR OBSTRUCTION
MOUNTING POSTS
RING L3x2 1/2 LLV
TERMINAL
PROTECTION AIR
LIGHTING
MOUNTING POST FOR
CONC CURB
@ 42"AFF
STEEL GUARDRAIL
NOSING
@36"ABOVE
STAIR RAIL
NOSING
@36"ABOVE
STAIR RAIL
@42"
GUARDRAIL
@42"
GUARDRAIL
@42"
GUARDRAIL
DWGS
SEE ELECT
JBOX LOCATION
(TYP)
STAIR STRINGER
SPIRALING PL
PL (TYP)
STEEL TOWER WALL
WALL PL(TYP)
STEEL TOWER
VIF
EL +36.32'
T/ROOF H.P.
VIF
EL +36.32'
T/ROOF HP
VIF
EL +36.32'
T/ROOF HP
VIF
EL +36.57'
PLATFORM
T/STEEL
HP EL +25.54' VIF
STEEL PLATFORM
T/EXIT DOOR
EL +36.57' VIF
T/STEEL PLATFORM
VIF
EL +25.04'
T/LANDING
VIF
EL +17.18'
T/LANDING
EL +9.33' CCD VIF
T/BASE FLOOR
VIF
EL +17.18'
T/LANDING
EL +9.33' CCD VIF
T/BASE FLOOR
EL +36.57' VIF
T/STEEL PLATFORM
CLARITY
NOT SHOWN FOR
DOOR FRAME
DOOR SEE PLAN.
4" TOE GUARD
WALKING SURFACE
EL +25.04'
T/LANDING
SEE ELECT DWGS
120VAC POWER,
RECEPTACLE FOR
SHEET FG-100, TYP
GEOFOAM, SEE
GUARDRAIL
CENTERED ON
OBSTRUCTION LIGHT
MOUNTING POST FOR
(1.66 OD) STD, TYP
PIPES 1-1/4" DIA
& VERTICAL POST
HORIZONTAL RAIL
@42" AFF.
STEEL GUARDRAIL
@4'-0" OC MAX
VERTICAL POST
STEEL LADDER
AT LANDING
4" TOE GUARD
4" TOE GUARD, TYP
CDWM19344-FS-201-TWR_SEC.dgn 10/7/2016 11:10:15 AM
9. STEEL TOWER WALL PLATE SHALL BE A252 GRADE 2 or A36.
![Page 15: Book 1 Terms and Conditions for Construction - Chicago make joints wider for re-pointing in one location (1.5) ... B. Restore light, horn, bell, bridle, chain, and sinker to “like](https://reader031.vdocuments.us/reader031/viewer/2022030814/5b22be687f8b9ab8298b461f/html5/thumbnails/15.jpg)
GR
ANIT
E
9'|
LI
MES
TO
NE
9'|
367'| PROJECTED LENGTH ALONG TOP OF PARAPET
371'| PROJECTED LENGTH ALONG BOTT. OF PARAPET
1.
2.
3.
4.
PLAN NOTES:
20' 0 20'
10' 0 10'
0 1'1'
20' 0 20'
05' 5'
10/7/2016
OF
PN
LK
MPM
ACF
GL
PERCENT COMPLETE DATE
BULLETIN
100
90
75
60
30
DRAWN:
DESIGNED:
CHECKED:
REVIEWED:
6/29/2016
10/10/2016
BUREAU OF ENGINEERING SERVICES
DEPARTMENT OF WATER MANAGEMENT
CITY OF CHICAGO
pw:\\hntb
w356.h
ntb.org:P
WGreat_
Lakes\
Docu
me
nts\
Chic
ago
Projects\48555
CD
WM
Crib
s
De
mo\48555
Wilso
n
Ave
&
Fo
ur-
Mile
Water Intake\
Desig
n\
CA
DD\
CA
DD_Sheets\
CD
WM
19344-sht-F
A-200.d
gn
FA-200
13-107
FOUR-MILE CRIBMASONRY REPAIRS
24 122
ADDITIONAL WORK AT THE UNIT PRICE BID.
GREATER THAN THE PLAN QUANTITY, THE DEPARTMENT WILL PAY FOR THE
AND PAID FOR. IF THE ACTUAL QUANTITY OF EITHER REPOINTING ITEM IS
THE PLAN QUANTITIES SHOWN ARE THE MINIMUM THAT WILL BE MEASURED
MASONRY UNIT SIZE AND 25% OF JOINT LENGTHS REQUIRING REPOINTING.
THE QUANTITIES ARE ESTIMATED VALUES BASED ON A 5' X 2' AVERAGE
1,240 L.F. STONE MASONRY REPOINTING
ESTIMATED QUANTITIES OF REPOINTING:
THE COMMISSIONER.
REPOINT MORTAR JOINTS AS DIRECTED BY THE REPRESENTATIVE OF
DATUM
EL. 0.00
NO
RT
H
SO
UT
H
NO
RT
H
WES
T
EA
ST
B
REPOINTING
LIMESTONE MASONRY
REPOINTING
GRANITE MASONRY
ENTRANCE DOOR
EXIST. CRIB
EXIST. DOCK
B/PARAPET
EL. +5.33 V.I.F.
DETAIL D
SEE REPOINTING
SCALE:
PROJECTED WALL ELEVATION
1" = 5' VERTICAL1" = 20' HORIZONTAL
C
FA-200
FA-200
CONC., SEE FS-101
TO BE PLUGGED WITH
EXIST. ICE CHUTE
T/PARAPET
EL. +23.58 V.I.F.
DATUM
EL. 0.00
DEMOLITION DWGS.
TO BE REMOVED, SEE
EXIST. SUPERSTRUCTURE
THE COMMISSIONER
THE REPRESENTATIVE OF
AS DIRECTED BY
TO BE REPOINTED
EXIST. STONE MASONRY
T/PARAPET
EL. +23.58| V.I.F.
B/PARAPET
EL. +5.33 V.I.F.
SCALE:
TYPICAL WALL SECTION
1" = 10'
B
FA-200
NN
C
EXIST. DOCK
SHAFT
FA-200
SCALE:
PLAN
1" = 20'
A
FA-200
ENTRANCE
CRIB
C
FA-200
LIMESTONE MASONRY
EXIST. GRANITE OR
THE SOUND SECTIONS OF THE WALL.
AND TOOL THE JOINTS TO MATCH THOSE IN
WITH WATER. FILL THE JOINTS WITH MORTAR
MORTAR OR SAND FROM JOINT AND FLUSH
OF THE COMMISSIONER, RAKE OUT LOOSE
AS DIRECTED BY THE REPRESENTATIVE
SCALE:
REPOINTING DETAIL
1" = 1'-0"
D
FA-200
10