boiler manual 3x135mw
TRANSCRIPT
-
7/25/2019 Boiler Manual 3x135MW
1/61
REV.
A
INSTRUCTION FOR BOILER OPERATION
SG-420/13.9-M2305MODEL OF PRODUCT
420t/hNAME OF PRODUCT 420t/h Circulating Fluidized Bed Boiler
2305-1-8603SERIES No.
-
7/25/2019 Boiler Manual 3x135MW
2/61
Instruction For Boiler Operation 2305-1-8603 P 2/61
Table of Contents
INSTRUCTION ....................................................................................................................... 5
1 GENERAL CONDITIONS OF BOILER ............................................................................. 6
1.1BRIEF INTRODUCTION OF BOILER..................................................................................... 6
1.2MAIN TECHNICAL PARAMETERS OF BOILER..................................................................... 7
1.3MAIN PERFORMANCE INDEXES OF BOILERDESIGN COAL,TMCRWORKING CONDITION
.............................................................................................................................................. 8
1.4FUEL ................................................................................................................................ 8
1.5LIMESTONE (IN BRIEF)..................................................................................................... 9
2. COMMISSIONING TEST OF BOILER ............................................................................. 9
2.1IMPORTANCE OF BOILER COMMISSIONING........................................................................ 9
2.2PREPARATION BEFORE BOILER OVERALL STARTUP........................................................ 10
3. HYDROSTATIC TEST ..................................................................................................... 10
3.1TEST REQUIREMENTS ..................................................................................................... 10
3.2MAINTENANCE AFTER HYDROSTATIC TEST.................................................................... 11
4. WATER TREATMENT (IN BRIEF) ................................................................................ 11
5BOILER DRY-OFF ......................................................................................................... 11
5 1 PURPOSE OF BOILER DRY OFF 11
-
7/25/2019 Boiler Manual 3x135MW
3/61
Instruction For Boiler Operation 2305-1-8603 P 3/61
8.6PURGING OF MAIN STEAM PIPELINE................................................................................ 25
8.7PURGING OF REHEATER INLET PIPELINE......................................................................... 25
9. NORMAL PRINCIPLES FOR BOILER OPERATION ................................................... 25
9.1GENERAL RULES ............................................................................................................ 25
9.2WATER FILLING AND VENTING...................................................................................... 26
9.3STARTUP ........................................................................................................................ 26
9.4BOILER SHUTDOWN ....................................................................................................... 27
9.5WATER LEVEL............................................................................................................... 28
9.6BOILER WARM-UP AND EXPANSION............................................................................... 29
9.7AIR PREHEATER............................................................................................................. 29
9.8SOOT BLOWING .............................................................................................................. 29
9.9REGULATION OF STEAM TEMPERATURE......................................................................... 30
9.10SUPERHEATER AND REHEATER.................................................................................... 30
9.11BLOW-OFF ................................................................................................................... 32
9.12TUBE DAMAGE ............................................................................................................. 32
9.13FURNACE EXPLOSION ................................................................................................... 33
9.14FLY ASH WEAR............................................................................................................ 34
9.15INSPECTION................................................................................................................. 34
9.16MAINTENANCE OF BOILER AND FREEZING PREVENTION............................................... 35
10 BOILER OPERATION PROCEDURE ............................................................................ 36
10.1STARTUP AND OPERATION OF BOILER.......................................................................... 36
10.2PREPARATION BEFORE BOILER STARTUP...................................................................... 37
10 3 COLD/WARM STATE STARTUP 38
-
7/25/2019 Boiler Manual 3x135MW
4/61
Instruction For Boiler Operation 2305-1-8603 P 4/61
12.4FIGURE 4 HOT-STATE STARTUP CURVE...................................................................... 60
12.5FIGURE 5 SHUTDOWN CURVE.................................................................................... 61
-
7/25/2019 Boiler Manual 3x135MW
5/61
Instruction For Boiler Operation 2305-1-8603 P 5/61
Instruction
Combining the experience in design, manufacture and operation of dozens of
ultra-supercritical circulating fluidized bed boiler, the 420t/h class circulating fluidized bed
boiler is completely designed by Shanghai Boiler Works Co., Ltd, which is developed by
Shanghai Boiler Works Co., Ltd using advanced technology of circulating fluidized bed.
This instruction for boiler operation, based on the design features of circulating
fluidized bed boiler, introduces the utilization requirements, operation procedures and
matters needing attention of the boiler body. The various contents of the instruction are basic
requirements proposed for the boiler utilization process to ensure the safe operation and
service life of the boiler. The boiler startup and shutdown procedures are closely related to
the other units of the boiler, e.g. turbine, various auxiliary equipment, control system, etc.
Therefore, the specific operation specifications for the complete set of generator unit to
match with the boiler shall be prepared by the user with reference to the applicable
specifications of the industry. This instruction is only for information when the user prepares
boiler startup and operation specifications.
-
7/25/2019 Boiler Manual 3x135MW
6/61
Instruction For Boiler Operation 2305-1-8603 P 6/61
1General conditions of boiler
1.1 Brief introduction of boiler
SG-420/13.9-M2305 circulating fluidized bed boiler is an ultra-supercritical
intermediate reheat, natural circulation boiler with single drum, which is designed and
manufactured by Shanghai Boiler Works Co., Ltd using advanced technology of circulating
fluidized bed. Balanced draft, centralized downcomer and water-cooling cyclone separator
are adopted in the boiler, and 2 slag discharge tubes and 1 accident slag discharge tube are
arranged at the bottom of furnace combustion chamber. Membrane waterwall is adopted in
furnace and the lower part uses refractory furnace lining. The boiler has 4 coal feeding points
and 4 limestone feeders, which are all set at the front wall. For this boiler, on-bed startup
ignition mode is adopted. Totally 4 high-power ignition oil guns (2 for each of the left and
right side walls respectively) are arranged on the bed. Convection heating surface is arranged
in the boiler rear pass and two-stage water spray temperature adjustment is adopted in
superheater. Reheater mainly uses flue gas damper temperature adjustment, supplemented by
accident water spray device.
1.1.1 Steam-water system of boiler
The steam-water system of the boiler includes tail economizer, boiler drum, evaporation
-
7/25/2019 Boiler Manual 3x135MW
7/61
Instruction For Boiler Operation 2305-1-8603 P 7/61
the primary air fan is heated in the steam air heater and primary air preheater. Then one route
enters the primary air chamber in the bottom of the furnace and the bed material is fluidized
through the wind cowl on the air distribution board, forming solid circulation going upwards
through the furnace. For the second route, an air pipe is led from the primary air duct to the
furnace coal falling tube as coal spreading air. For the third route, a stream of high-pressure
cold air is led from the cold air duct behind the outlet of the primary air fan as the sealing air
for the furnace coal falling tube and coal feeder. After the secondary air is heated by the air
heater and secondary air preheater, a certain number of branch tubes are led from the
secondary air chamber. The air enters the furnace combustion chamber from front and back
wall of the furnace and upper dense-phase zone as two layers. Meanwhile, the secondary air
is also used for ignition of the on-bed oil guns and oil gun cooling.
After the gas with solid particles left the furnace, it tangentially enters the cyclone
separator through two inlet duct respectively. Coarse particles are separated from the gas in
the separator, and gas enters rear pass through separator center cylinder. After cooled by
heating surface, the gas enters dust collector through tubular air preheater to remove fine
particles and finally discharges into the atmosphere through stack by induced draft fan.
One stream of the high-pressure fluidization air is used as fluidization air for the
-
7/25/2019 Boiler Manual 3x135MW
8/61
Instruction For Boiler Operation 2305-1-8603 P 8/61
Superheater outlet steam temperature 543 543
Reheater steam flow t/h 351.108 351.108
Reheater inlet steam pressure MPa(g) 2.757 2.757
Reheater outlet steam pressure MPa(g) 2.632 2.632
Reheater inlet steam temperature 319.6 319.6
Reheater outlet steam temperature 543 543
Feedwater temperature 252.1 252.1
1.3 Main performance indexes of boilerDesign coal, TMCR working condition
Item Unit Value
Computational efficiency of boiler (as
per net calorific power)% 93.29
Guaranteed efficiency of boiler (as per
net calorific power)% 92.5
Solid incomplete combustion heat loss % 1
D t di h t ti t
-
7/25/2019 Boiler Manual 3x135MW
9/61
Instruction For Boiler Operation 2305-1-8603 P 9/61
As-received gross calorific value
HHVQgr.ar Kcal/kg 4500
1.4.2 Ignition and combustion supporting oil
Light diesel oil is adopted in this project as ignition and combustion supporting oil. The
analysis data of the oil are as follows.
-
7/25/2019 Boiler Manual 3x135MW
10/61
Instruction For Boiler Operation 2305-1-8603 P 10/61
exist in boiler and auxiliary equipment, in order to take effective measures in time. To train
the operating personnel concerned about equipment performance and primary adjustments of
operation, which lays a good foundation for pilot production and commercial operation.
2.2 Preparation before boiler overall startup
Besides separated commissioning of the main equipment of each system, hydrostatic
test, dry-off, cold aerodynamic characteristic test, boiler body cleaning, steam pipeline
purging, boiler ignition test, boiler safety valve setting, auxiliary equipment interlock
protection test and boiler main protection test should be done before the boiler overall
startup commissioning. A complete inspection of boiler proper and its steam-water system,
flue gas and air system, combustion system, relevant auxiliary equipment, thermal control,
chemical water treatment equipment and site environment should be carried out according to
the commissioning program, operating standard and boiler operation instruction before cold
start, to meet the requirements of boiler safe startup.
3. Hydrostatic test
Hydrostatic test should be carried out according to the requirements of relevant boiler
regulations.
3.1 Test requirements
-
7/25/2019 Boiler Manual 3x135MW
11/61
-
7/25/2019 Boiler Manual 3x135MW
12/61
Instruction For Boiler Operation 2305-1-8603 P 12/61
that results in cracking, deformation and damage of the refractory materials, or even
peeling-off of the wear-resistant materials in severe case. Therefore, before the boiler is put
into operation officially, it is necessary to dry off the boiler with controlled heating method.
Meanwhile, boiler dry-off can accelerate the physical/chemical variation process of the
boiler wall materials, making the performances stable so that it can work for long term under
high temperature.
5.2 Preparation required before boiler dry-off and conditions
1) The installation work for the boiler proper, material returning system and gas/air
system is completed. The construction of the wear-proof refractory materials is
completed. The air leakage and air pressure test is passed.
2) Open the door holes in the various positions and allow it to dry naturally for more than
72 hours.
3) Carry out internal inspection of the furnace, flue gas/air duct, cyclone separator,
material returning device, etc. Remove the foreign matters.
4) Temporary exhaust valve is installed on the top cover of the cyclone separator, and
temporary partition is installed in outlet duct of the separator.
5)
The fuel oil system is installed. All the jobs such as hydrostatic test and instrument test
-
7/25/2019 Boiler Manual 3x135MW
13/61
Instruction For Boiler Operation 2305-1-8603 P 13/61
boiler with controlled heating method. The boiler dry-off curve of wear-resistant refractory
materials should be made by insulating material manufacturer, user and boiler manufacturer.
This instruction recommends the dry-off methods which uses extra burner to heat CFB
boiler. In this method, extra burners are arranged through the manhole doors and observation
eyes in the furnace and gas ducts at the positions laid with wear-resistant refractory materials
for heating and temperature control, the heat source generated is hot gas, which will not
flush the refractory insulation materials directly or generate local high temperature.
Moreover, with this method, it is easier to control the furnace and the gas duct at different
temperature.
Drying of the refractory materials is only a stage for accomplishing the engineering
plan. However, for CFB boiler, it is a very important link. This job is usually implemented
and accomplished by the refractory material installer by providing with temporary burners.
Once the refractory material drying procedure starts, it must proceed continuously as
per the temperature control curve without interruption until the boiler dry-off is completed.
This is critical for drying the refractory materials thoroughly and for ensuring the
performances of the refractory materials.
After a period of insulation, the furnace temperature cooled down is about 370. The
-
7/25/2019 Boiler Manual 3x135MW
14/61
Instruction For Boiler Operation 2305-1-8603 P 14/61
10) The door holes in the furnace and separator shall be closed to prevent heat from
escaping out of the door hole.
11)
Feed water into the boiler drum to the normal operation level.
12) Adjust the main steam exhaust and drain valve before starting boiler dry-off.
13) Drum exhaust door Open/Pressure up to 175Pa Close
14)
Main steam exhaust/drain Open
15) Startup exhaust valve Open 25%
16) Reheater exhaust/drain Open
17)
Adjust the openness of the fan inlet movable vane to be consistent with that of the
baffle.
18) Primary air fan inlet movable vane 5%-10%
19) Secondary air fan inlet movable vane 5%-10%
20) Induced draft fan inlet movable vane 5%-10%
21) Secondary air fan upper/lower baffle Close
22) During the drying of refractory materials, maintain the steam drum at normal water
pressure.
23)
During the boiler dry-off, monitor the temperature of the gas entering the preheater
-
7/25/2019 Boiler Manual 3x135MW
15/61
Instruction For Boiler Operation 2305-1-8603 P 15/61
5Recorder for recording the temperature of each thermocouple.
6Operating personnel 24 hour uninterrupted shift.
7Provide boiler dry-off report (including summary, copy and electronic edition of original
boiler dry-off record)
5.3.4 Duration
1) Preparation time is about four weeks from the delivery of boiler dry-off equipment.
2) About one week to install pipe to burner position.
3) About three day for equipment startup preparation.
5.3.5 Other requirements
1) Elevator/crane for lifting boiler dry-off machine (800kg).
2)
Compressed air used during boiler dry-off (3m3/h/burner0.25Mpa), atomized fuel oil.
3)
Electric power 18kw/220/380 volt power, 50
100kg/h fuel 14 boiler dry-off machine.4) Oil supply pipe connected to boiler dry-off machine, use hose for the tube at about 15
inches near the end the boiler.
5)
Set aside a plane space of 3 inches 3 inches for temporary boiler dry-off machine area.
5.3.6 Position of burner and thermocouple for boiler dry-off
B t
-
7/25/2019 Boiler Manual 3x135MW
16/61
Instruction For Boiler Operation 2305-1-8603 P 16/61
Storage areatemporary storage area is arranged beside the boiler or between two
boilers.
Temporary storage tankthis is sign on and beside temporary storage tank (truck oil
tank)
Temporary pipelinefrom storage tank to boiler area and then to the connection of
temporary burner.
In addition, where there is oil return line, there is isolating valve.
5.3.8 Boiler dry-off heating/cooling rate (see Figure 1).
5.3.9Temperature rising requirements for the first startup
After the boiler dry-off with dry-off machines is completed, all the dry-off machines
and the related devices shall be removed. When the complete-group startup conditions are
met and the boiler is started for the first time, in order to protect refractory material, boiler
main oil gun should be used to heat up as per the curve below. To meet the requirements of
heating curve, the oil quantity for the oil guns and the number of oil guns put into use shall
be controlled strictly.
50/h rises to
670 , keep at 670
f 4 h
50/h rises to
500 , keep at
00 f 2 h
Tubes
must be
fill d
-
7/25/2019 Boiler Manual 3x135MW
17/61
Instruction For Boiler Operation 2305-1-8603 P 17/61
critical fluidization air volume, and provide with references for the hot-state operation of the
boiler to ensure the combustion safety of the boiler, to prevent coking on the bed and to
protect the equipment from being damaged.
Caution
Cold aerodynamic characteristic test is the foundation and
reference basis for boiler startup commissioning, boiler
combustion adjustment and boiler safe and economical
operation. It should be done in accordance with the relevant
regulations. Relevant data collection should be done as well.
6.2 Main content of test
Furnace ventilation circuit test
1)
Performance examination of primary/secondary air fans and high-pressure fluidizationair fan;
2)
Test of coal feeder air quantity distribution features;
3) Calibration for measuring devices of primary/secondary air volume and fluidized air
volume of material-returning machine;
4)
D i i f h l i f f h i i d b ffl
-
7/25/2019 Boiler Manual 3x135MW
18/61
Instruction For Boiler Operation 2305-1-8603 P 18/61
in-furnace dense-phase zone. The difference between the two is the resistance of the air
distribution board. Draw the relationship curve between the primary air volume and the air
distribution board resistance in cold state. Through temperature correction, the relationship
curve between the primary air volume and the air distribution board resistance in hot state
can be obtained. During the operation of the boiler, if failure occurs at the bed pressure
measurement point, the quantity of on-bed materials can also be judged on the basis of the
relationship curve between air chamber pressure & air volume and air distribution board
resistance, thereby reducing the operation blindness.
6.5 Test of critical fluidization air volume
The various cold-state measurement tests before this test are carried out with no bed
materials filled. The critical fluidization air volume refers to the minimum air volume
necessary for the bed materials to turn from fixed state to fluidized state. It is the minimum
primary air volume during the operation of the boiler. Method for determine the critical
fluidization air volume: Select 0~1mm or 0~1.5mm river sand or CFB boiler slag as bed
materials. Add bed materials to static height of 1100 mm (sand) or1200mm (ash). Increase
the primary air volume. On the initial stage, the bed pressure increases gradually along with
the increment of primary air volume. When the air volume exceeds a certain value, continue
-
7/25/2019 Boiler Manual 3x135MW
19/61
Instruction For Boiler Operation 2305-1-8603 P 19/61
There are various kinds of chemical cleaning. Users can choose the appropriate method
according to relevant standards.
This chapter only introduces the cleaning method with low-temperature low-foam
cleanser by virtue of out-laid circulating pump for forced circulation. It is an effective, quick
and economical cleaning method.
The concentration recommended by merchant should be checked, since commercial
cleanser concentration is changed (for example, diluted with water). Normally, the
recommended cleanser concentration is 0.6 percent by volume at 21 ambient temperature
(i.e. to add 1L cleanser into 167L water). If the boiler is cleaned at above 65.6, the
recommended cleanser concentration is 0.3 percent by volume.
7.1Preparation for cleaning
1)
All the water/steam separation devices in the steam drum have been removed.
2) Provide with a temporary circulating pump with a capacity of 14 t/h to circulate the
solution in the furnace. This pump shall suck the solution from the bottoms of the
furnace lower header and of the evaporation screen header. The solution is discharged
from the economizer inlet header. The size of the pipes from the pump to such positions
on the boiler shall match. All the high-pressure pipes connecting to the boiler and all the
-
7/25/2019 Boiler Manual 3x135MW
20/61
Instruction For Boiler Operation 2305-1-8603 P 20/61
7) Provide with a sampling connection complete with valve, and attach an appropriate tag.
8) Before cleaning, remove the residues in the boiler drum and header mechanically as
long as possible. Check all the bolt sealing components in the boiler drum.
9) All the pressured parts must be checked carefully for any blockage. If any, carry out
necessary hydrostatic test. Inspect the blow-off pipes and dosing pipes inside the boiler
drum and make sure the interiors are smooth and clean.
10) During the cleaning, the operators on duty shall be familiar with the normal combustion
and operational procedures, as well as preventive actions, and learn safety operation
procedures for cleaning. This is very important. Special care shall be employed when
taking any measures that may cause leakage. Take appropriate measures to protect the
personal safety in case of any accidental leakage event.
11) Desalted water is used to fill reversely the SH to ensure that the SH is fulfilled, for ease
of observing the increase of drum water level.
7.2 Flushing with cleanser under ambient temperature
Fill the boiler, evaporation screen and economizer with water until the bottom water
level of the level gauge is in visible range. Through the temporary chemical pipeline, inject
the cleaning liquor slowly. Again add water until the water level is higher than the boiler
-
7/25/2019 Boiler Manual 3x135MW
21/61
Instruction For Boiler Operation 2305-1-8603 P 21/61
7.3 Matters needing attention
1) Discharge of the cleanser does not need to be done under the presence of nitrogen.
Nitrogen is a nontoxic gas, but is unfavorable for human respiration. If nitrogen-filling
is adopted for draining the boiler and a man needs to enter it after the drainage,
appropriate ventilation must be carried out before a man is allowed in.
2)
If the boiler will be left free fora couple of days after the cleaning, the boiler and the
superheater need to be maintained as described in the maintenance procedure.
3) Before the counter-flushing of the superheater is completed, perform chemical analysis
for the water used (conductivity, pH and chlorine) to confirm that no pollution exists.
4) After the cleaning and before the ignition of the boiler, the water in the superheater and
steam pipeline shall be sampled, analyzed and inspected for any contamination.
5) If cleanser overflows into the superheater due to carelessness during the chemical
cleaning, carry out thorough counter-flushing with sufficient flow before ignition is
allowed in order to ensure that the various contaminants are all removed.
6) In the chemical treatment process, take special care to prevent the cleanser from doing
harm to human being.
7)
Inspect the steam drum and remove any loose deposit from the inner surface of the
-
7/25/2019 Boiler Manual 3x135MW
22/61
Instruction For Boiler Operation 2305-1-8603 P 22/61
of steam pipe purging, as well as the protection against over-pressure or over-temperature,
are all the responsibilities of the user.
Warning
Because the water level of the steam drum fluctuates greatly
during the purging, the operator shall do the preparation work
sufficiently in advance to avoid any steam drum overflow or
water shortage accidents. Pipe purging can cause certain
damage to the boiler. So the number of purging times shall be
minimized while meeting to the applicable examination
standards.
8.3 General rules
To achieve the best purging effect, when purging the steam pipelines, the steam flowconditions of system should equal to normal operation conditions at maximum load. Because
the purging conditions when discharging into the atmosphere is unlikely to be repeatedly in
accordance with operation conditions, equivalent operation conditions is expected to be
achieved, i.e. steam flow when purging under low pressure multiplies velocity is normal
i di i f ll l d h fl h b b i d b d i d
-
7/25/2019 Boiler Manual 3x135MW
23/61
Instruction For Boiler Operation 2305-1-8603 P 23/61
If a cut-off valve is installed in the main steam pipeline of the boiler, if the design of
valve allows such operation mode, this valve can also be used as purging valve.
For any component with more than one route of steam pipeline, it is necessary to
consider installation of temporary pipeline so that every route of pipeline could be purged
independently. In this case, make sure to resolve the flow unbalance and expansion problems
at the connections of the pipeline system.
The cleanliness of the components being purged is shown by the target plate provided
at the outlet of the purging pipeline on the final stage of the purging.
The pitting level of the target plate after the purging is used to determine the purging
cycle of certain components.
8.4 Matters needing attention
1) The purging process may result in abnormal and severe conditions for the boiler and
steam pipeline. During every purging cycle, tremendous and quick temperature change
will occur. This change causes much severer damage as compared with normal
operation. In the thick-wall parts of the system such as boiler drum, header and pipeline,
excessive thermal stress may be generated. Therefore, during the purging, such
conditions shall be considered carefully. While meeting the system cleanliness
-
7/25/2019 Boiler Manual 3x135MW
24/61
Instruction For Boiler Operation 2305-1-8603 P 24/61
8) To ensure that the hot gas will not leak out of the furnace, the furnace shall be operated
in vacuum state (-50Pa).
9)
To make the tubes in furnace and convection pass heating surface overheated or
dry-burned, the gas temperature of the furnace and cyclone separator shall be kept below
538.
8.5 Operation procedure
Due to the requirement for low ignition rate, the fluid bed may be not started during
steam purging. Fire the startup burner steadily, and assume that burner adjustment is good,
dust collector is not necessary.
To avoid excessively high thermal load that may cause thermal corrosion of the
refractory material, the mean rising rate of the steam drum water temperature shall not
exceed 50/h. Start up induced draft fan firstly, then start up primary fan and secondary fan,
thus the startup procedure begins. As long as the material-returning machine nozzle is cover
by ash or sand, the high-pressure fluid fan in not necessary.
Start the boiler as per cold-state startup procedure in normal way. Formal suggestion
and regulation about fuel burning equipment, air treatment equipment, drainage and exhaust
shall be followed. If the boiler start up in normal operation mode, for any newly-built boiler,
-
7/25/2019 Boiler Manual 3x135MW
25/61
Instruction For Boiler Operation 2305-1-8603 P 25/61
generate the purging flow required, the purging process can start.
8.6 Purging of main steam pipeline
1)
Turn off or hold startup burners. Open the temporary discharge valve gradually. Purge
through the superheater and main steam pipelines and discharge through the temporary
discharge pipe (refer to Matters needing attention). The initial purging is normally
carried out under depressurization in order to inspect the supporting and fixing devices
of the temporary piping system.
2)
When the steam drum pressure drops to about 1.38MPa, close the temporary discharge
valve and re-ignite the unit to establish the purging conditions.
3) Repeat the above operation cycle until the inspection to the flushing target plate on the
final stage shows that the cleanliness is qualified.
8.7 Purging of reheater inlet pipeline
1)
Turn off or hold startup burners. Open the temporary discharge valve gradually. Purge
through the superheater and main steam pipelines and discharge and the pipes
temporarily connected to the reheater and exhaust through temporary discharge pipe
(refer to Matters needing attention). Important note: The initial purging is normally
carried out under depressurization in order to inspect the supporting and fixing devices
-
7/25/2019 Boiler Manual 3x135MW
26/61
Instruction For Boiler Operation 2305-1-8603 P 26/61
fuel property and the equipment used for measurement. Representative fuel samples shall be
taken regularly to analyze the chemical component, calorific value, viscosity (liquid fuel)
particle size distribution and other physical features of the fuel. All these can cause effect on
the operation and efficiency.
As an index for measuring the economical efficiency of boiler operation, the discharged
gas analysis of the boiler is of important value. The combustion shall be completed before
the gas departs from the cyclone separator. Adoption of the optimal excess air factor depends
on the fuel properties, design of fuel combustion equipment and other factors. And, the
optimized excess air factors shall be established under different loads.
When the heat conduction surface is kept clean, at the given percentages of steam and
excess air, the gas temperature at the outlet of the preheater and the resistance of the gas
passing through the gas duct shall generally be kept constant. To record these operation data
starting from the startup is necessary. The operation data shall be recorded in the tables in
order to compare with the data obtained under the various similar operation conditions.
Standard value for judging the operation satisfaction shall be established when the
equipment is new. In this way, when the operation conditions deviate from the standard,
steps shall be taken to determine and correct the cause of the deviation.
-
7/25/2019 Boiler Manual 3x135MW
27/61
Instruction For Boiler Operation 2305-1-8603 P 27/61
When the pressure rises, the drainage valve can be throttled, but shall not be shut
completely. Refer to the operation instructions of the valve (Refer to instruction for valve
operation).
During the startup, burning rate should be controlled to keep the highest gas temperaure
of rear pass under 538 (inspected by the temperature element in cyclone separator and
rear pass) until ranked with turbine. After turbine running, the rise of turbine throttle valve
steam temperature and pressure shall always comply with the regulations made by the
turbine manufacturers.
When a new boiler unit is started for the first time, the combustion rate must be
controlled. The increment of combustion rate shall be maintained at a relatively slow rate in
order to inspect the expansion displacement and clearance. The later startup rate can be
relatively quicker, but the temperature rise of the saturated steam shall not exceed 93
(refer to boiler startup procedures) or the limited gas temperature of cyclone separator outlet
mentioned above. The temperature rise of the saturated steam can be slow depending on the
heating rate of the insulation material, refer to the instructions of the insulation material
manufacturer. In this period, combustion regulation is normally carried out manually. Never
try to start up with the combustion control or feed water equipment in automatic status.
-
7/25/2019 Boiler Manual 3x135MW
28/61
Instruction For Boiler Operation 2305-1-8603 P 28/61
water.
Whatever shutdown mode is chosen, cooling rate cannot make saturated-steam
temperature drop exceed 85 per hour.
9.5 Water level
Prior to the ignition, the operator shall check the steam drum water level with the water
meter column and level gauge blow-off method. Normally, slowly opening drain valve of
high pressure gauge is enough. Normally, an unblocked blow down can clean the foreign
matters probably exist on drain valve seat. When warm up the new unit, the gauges shall be
blown off for several times under low pressure and verify the consistency of remote and
local level gauges. During the operation of boiler, the water level gauges shall be inspected
once per shift (refer to the instructions for the water level gauges). If the water in water
gauge is stagnant when open or close the drain valve, investigate for the cause and correct
the conditions immediately. To protect the glass of the water level gauges, the blow-off
volume shall be kept to minimum during the normal operation.
During the normal operation, the water level of the water level gauge shall also be
observed regularly even if the boiler may be provided with reliable water level regulator or
remote water level indicator.
-
7/25/2019 Boiler Manual 3x135MW
29/61
Instruction For Boiler Operation 2305-1-8603 P 29/61
out the visible range of the gauge, except the instant water level fluctuation caused by rapid
and sharp variation of load, proper action shall be taken immediately to flame out the boiler.
9.6 Boiler warm-up and expansion
When the pressure of the boiler is raised, it is necessary to take measures in the
beginning to open all the drain valves and bypasses (if any) to drain the cold steam pipes
sufficiently.
During the initial ignition, check the expansion conditions of the boiler regularly and
make records, and make sure that the guard plates, headers and pipes can expand freely
relative to the steel structure. The expansion indicator shall be installed at appropriate
position to facilitate inspection (refer to the arrangement diagram or expansion displacement
diagram of pressured components). During the service life of boiler, inspect its expansion
regularly to determine whether the expansion is normal and uniform. All the hanger rods and
the related pipes shall be inspected regularly for their appropriate displacement and function.
9.7 Air preheater
Abnormal increment of the ventilation resistance in the gas side or air side of the air
preheater indicates that the ash blockage is increasing and various measures shall be taken
immediately. Especially when the unit is started, observe closely the temperature of the gas
-
7/25/2019 Boiler Manual 3x135MW
30/61
Instruction For Boiler Operation 2305-1-8603 P 30/61
important to the prevention of pressure parts erosion. In no case should plash be in the
pipeline. Normally, a hole at the drain valve can continuously discharge the water. Before
the soot blower put into operation, steam shall be used to purge freely, and enough long time
is needed to heat the pipelines.
9.9 Regulation of steam temperature
Steam side regulates through firing in the furnace and control furnace outlet gas
temperature to regulate and keep outlet steam temperature. The medium side normally keeps
final superheater and final reheater design temperature with desuperheating water. Only
when the outlet temperature of reheater cannot be kept within the specified range of outlet
temperature, spray desuperheating is used.
Whatever method is used to control the temperatuer of superheater and reheater, there
are some factors which may cause abnormal fluctuation of steam temperature:
Causes for abnormal low steam temperature:
1) Insufficient excess air;
2) Feed water temperature higher than design value;
3) Boiler fuel carries excessive moisture;
4)
Contamination on superheater/reheater outer surface or inner surface;
-
7/25/2019 Boiler Manual 3x135MW
31/61
Instruction For Boiler Operation 2305-1-8603 P 31/61
and reheater shall be as even as possible, and the maximum temperature where gas flows
through the superheater tubes (gas temperature at outlet of cyclone separator) shall be
monitored and controlled.
The gas temperature at outlet of cyclone separator is usually measured with the
thermocouples installed in the outlet gas duct of the cyclone separator. The maximum
temperature at outlet of cyclone separator shall be limited at 538, until the turbine carries
loads and the reheater establish normal steam flow.
To ensure that the condensation water in superheater coil is removed, steam flow
through the superheater shall have appropriate flow when start up. Before the ignition and
firing of the boiler, the drainage valves and vent valves in the outlet headers and/or main
steam pipes shall be opened and shall be kept open until the boiler generates steam and is
loaded. When the boiler drum pressure increases, these startup drainage valves and/or vent
valves can be throttled gradually to make sure that sufficient steam flows through the
superheater throughout the startup. When the turbine is in line with load and appropriate
steam flow is ensured, the startup drainage valves and/or vent valves of the superheater can
be closed.
All drain valves of reheaters shall be open before ignitions. When boiler pressure rises,
-
7/25/2019 Boiler Manual 3x135MW
32/61
Instruction For Boiler Operation 2305-1-8603 P 32/61
of steam carrying water is doubtable, take measures immediately and investigate to remove
the causes that result in steam carrying water. If the research show that steam carrying water
is not caused by poor water quality, internal device of steam-water separation, water level
control and indicating equipment where problem may probably occur shall first inspected.
From the heat conduction and corrosion point of view, deposition of solid substances on
the superheater and reheater is harmful. Under the presence of chemical substance like
caustic alkali and chlorine, stainless steel pipes of superheater and reheater are much more
likely to be eroded. Therefore, whether during carrying or filling water (hydrostatic test,
chemical cleaning), solid matter shall be prevented from getting inside.
9.11Blow-off
Continuous blow-off is the best method to control and keep the relative stable
concentration of the soluble solid substances in the boiler water. The blow-off data shall be
recorded. Total blow-off quantity is better to be determined according to the boiler water
chemical analysis. Because each power plant has a different water treatment system, person
in charge of water condition shall specify the water treatment system according to the
feedwater analysis and give necessary instruction of blow-off.
However, the blow-off quantity will affect the heat loss and water supplement volume
-
7/25/2019 Boiler Manual 3x135MW
33/61
Instruction For Boiler Operation 2305-1-8603 P 33/61
load condition requires to keep operating, the boiler can keep operating until the chance of
shut-down for necessary overhaul. Under such circumstance, other tubes are often damaged
when the boiler operate for quite some time. When the tube damage is more than one and
affect the water gauge losing water level, the boiler shall be shut down in normal mode. The
purpose is to prevent all equipment from suffering sudden temperature change.
Low water level, various measures shall be taken to make water level approach the
normal level until the boiler is fully cooled down and allowed for drainage.
When leakage of superheater or reheater components happens, it shall be analyzed as
soon as possible. The boiler shall be shut down in normal mode.
The above information is only for suggestion, and cannot take the place of the correct
judgment of the stokers responsible for operating these equipment.
Bear in mind that prolonging the operation of the tubes with leakage may cause the
damage to adjacent tubes and increase maintenance works, exceeding the former short scope
of maintenance.
9.13 Furnace explosion
Furnace explosion is usually result of the following conditions:
1)
Unburned fuel accumulates in the furnace due to incomplete combustion.
-
7/25/2019 Boiler Manual 3x135MW
34/61
Instruction For Boiler Operation 2305-1-8603 P 34/61
4) It is absolutely unallowable to ignite the oil burner when the ignition energy source
needed is lost. Ensure that the air in air atomization oil gun is dry, do not use heavy
oil/mechanical atomization oil gun for boiling out, ignition and boiler warm-up, while
light oil/ air atomization or heavy oil/steam atomization oil gun is preferred.
5) Prior to any startup and during the normal operation, inspect the functions of the furnace
safety supervision system regularly, including interlock, tripping, etc.
6) During the downtime of the furnace, regulate, inspect and maintain the furnace safety
control system thoroughly.
9.14 Fly ash wear
Fly ash wear refers to the wear of the residual ash particles carried over in the gas to the
metal surfaces. Wear normally occurs in local zones with high gas speed. The wear level is
related to the ash content of the fuel (quantity and component). Firing coal with high wear
characteristics and high ash content makes boiler wear a main problem.
Caution: Wear usually occurs in: the end and bend of economizer tube and
low-temperature superheater and around soot blowing area, gas duct and induced draft fan
(fan blade and shell).
The boiler design parameters are based on conservative mean gas velocity and normal
-
7/25/2019 Boiler Manual 3x135MW
35/61
Instruction For Boiler Operation 2305-1-8603 P 35/61
section of superheater and reheater panel where water cannot be drained, and measures shall
be taken to prevent getting frozen.
Before entering the steam drum, make sure that all the valves in the steam drum
connection pipes are closed tightly (feed water, auxiliary steam, dosing pipe, blow-off,
drainage, sampling, level gauge drainage, etc.). Open the manhole cover to inspect the
tightness and cleanliness of the interiors of the steam drum. Inspect the steam drum for
corrosion and surface pit. Oxidized pit is a common form of corrosion, and normally occurs
in the steam drum above the normal water level, and sometimes in the tubes and lower
headers. Open sufficient number of hand hole covers in the various headers of the water wall
to remove the dirt.
Check the heating face of the preheater for cleanliness. If there is corrosion, it should
occur in the cold end part of the preheater, especially in the places where ash and filth tend
to accumulate.
Inspect the gas side thoroughly and clean it as necessary. Check if the soot blower is
deflective. Inspect the equipments such as coal spreading trough, igniter, oil gun, scanning
air fan, connection rod and air door for cleanliness and damage, and carry out operation and
flexibility inspection. For the FSSS system, inspect and test the control valve, relay,
-
7/25/2019 Boiler Manual 3x135MW
36/61
Instruction For Boiler Operation 2305-1-8603 P 36/61
4) Cold boiler shall not be switched to dry type corrosion prevention. If it is necessary,
ignite and raise the pressure to 30% of the rated pressure and then reduce the pressure.
Adopt the afterheat drying method for the maintenance.
9.16.2 Maintenance method
Select the maintenance method according to the maintenance principle. The
maintenance and operation can be implemented depending on the specific conditions of the
power plant with reference to the applicable specifications of the power authorities.
9.16.3 Freezing prevent for boiler
The freezing prevention measures shall be checked before winter begins. No pipe is
allowed to be bare. Anti-freezing and heating devices for each part of pipeline proper shall
be put into operation. Heating tubes of fuel line are in operation whole year and cannot be
overhauled in winter. Water in gauge pipe shall be drawn off. Hole door and damper of spare
boiler shall be closed, and measures shall be taken to prevent cold air from entering into the
boiler in overhaul.
In winter, during the shutdown of boiler, adopt dry-type maintenance as can as possible,
and air heater shall be put into use when the wall temperature of superheater is below
20.
-
7/25/2019 Boiler Manual 3x135MW
37/61
Instruction For Boiler Operation 2305-1-8603 P 37/61
10.2 Preparation before boiler startup
10.2.1 Inspection and cleaning before boiler startup
Before initial ignition and every cold startup or after service of the boiler, the interior
and exterior of furnace shall be inspected and cleaned. And all foreign maters shall be
removed completely from the pressure parts, all pipes and conduit tubes, which may limit
the normal expansion of the boiler, shall be removed. All person shall leave, and all doors
and openings shall be closed. Check whether the indication of the boiler drum water level
gauge is consist with the reading of local glass water level gauge, whether there is any block
at air distribution boards of the furnace and material-returning machine, and inspect and start
the atomization nozzle of the burner. And all these check shall be prepared by the
departments which is in charge of operation. Be familiar with the startup and operational
procedures for boiler and auxiliary machines.
10.2.2 Steam pipeline purging
For a new boiler or a boiler the main pressure parts of which has been repaired, the
purging of main steam pipeline and reheating steam pipeline shall be done before startup to
remove the rust and foreign matters in order to avoid the damage ti turbine. The purging of a
new boiler shall be done after pickling and before the setting of drum and reheater safety
-
7/25/2019 Boiler Manual 3x135MW
38/61
Instruction For Boiler Operation 2305-1-8603 P 38/61
10.2.5 Filling bed materials into boiler
Before the CFB boiler is started, inert substances (appropriate sand particles or CFB
bed ash) are loaded into the furnace as bed materials. Used CFB bed ash is optimal due to its
excellent fluidization features. To ensure appropriate heat transfer and system insulation,
sufficient bed materials must be introduced. Each boiler needs about 200t bed materials
(including the furnace and material-returning machine). The particle size of the bed materials
loaded shall meet the particle size limits allows by the design. If no ash is unloaded from the
system or if the bed materials exist before the operation, no further loading is needed.
10.3 Cold/warm-state startup
When the turbine high pressure rotor probe temperature is lower than 100, or when
the boiler starts up in cold state with no pressure, it is called cold-state startup. When the bed
temperature (the average temperature shown in the middle-level thermocouple) is lower than
680, coal cannot be put into the furnace directly; instead, it is necessary to purge the
furnace according to the cold-state startup mode and then to put the startup burners into
service to increase the be bed temperature. The startup mode in such state is called
warm-state startup. In case of cold-state or warm-state startup, the furnace must be purged.
Only after the purging is completed can the startup burners be put into service. After the
-
7/25/2019 Boiler Manual 3x135MW
39/61
Instruction For Boiler Operation 2305-1-8603 P 39/61
10.3.2.1 Starting of induced draft fan
Induced draft fan is the first air fan in circulating fluidization air and gas system during
boiler start-up. Before the induced draft fan is started, its inlet baffle is regulated to the
minimum position to avoid over-current of the motor of the induced draft fan during the
startup. After the induced draft fan is started, check the outlet baffle which shall be open,
note that the vibration indication value of the air fan bearing, the voltage and current values
and the temperature should be within the specified range. Open the vane control baffle at the
inlet of the induced draft fan slowly. Put the furnace vacuum (separator outlet) control to
automatic. Monitor the furnace pressure. Subsequently, the air volume of the induced draft
fan will regulate the control baffle automatically for operation, maintaining appropriate
furnace pressure at the outlet of the combustion chamber.
If tripping or downtime of induced draft fan for any reason occurs during boiler start-up,
primary air fan and secondary air fan shall be shutdown.
10.3.2.2 Starting of high-pressure fluidization air fan
During boiler start-up, after the induced draft fan is started, start the high-pressure
fluidization air fan and check the air volume of every chamber of the material returning
valve.
-
7/25/2019 Boiler Manual 3x135MW
40/61
Instruction For Boiler Operation 2305-1-8603 P 40/61
out. The furnace purging air volume shall, as a minimum, be more than 30% of the total air
volume under the rated load. For the detailed purging steps when the boiler is started up or
shut down, refer to the boiler operational procedures provided by FSSS suppliers.
10.3.4 Boiler ignition startup and temperature/pressure raising
Before the ignition of startup burner, cold/warm-state boiler shall have periodic purging
according to the permissive ignition condition of start-up burner.
1) Electrify the electrostatic precipitator
2)
Start up the induced air fan.
3)
Put the furnace pressure control to automatic, and keep the furnace pressure at -125Pa.
4) Start up the high-pressure fluidization air fan, ensure that there is at least one
high-pressure fluidization air fan under operation.
5) Start up the secondary air fan.
6)
Start up the primary air fan, ensure that there is at least one primary air fan under
operation.
7) Put the boiler air flow to automatic. Adjust the set value of total air flow to be no less
than 30% of the air flow at full load. Inspect all equipment until they meet furnace
purging. Control the primary, secondary air volume at 50% of air volume at rated load.
-
7/25/2019 Boiler Manual 3x135MW
41/61
Instruction For Boiler Operation 2305-1-8603 P 41/61
13) Along with the increasing furnace temperature, the temperature difference between
material-returning machine and upper furnace shall be kept with 38, in order to
prevent the damage of heat insulating material of cyclone separator and material
returning machine. When the temperature of material-returning machine is 38 or
much lower than upper furnace, primary air volume shall be added as needed to reduce
temperature difference.
14) When the steam drum pressure achieves 0.17MPa, close the steam discharge valve and
vent valve in the boiler drum connection pipe.
15)
Along with the increasing boiler drum pressure, regulate the drainage of the superheater
outlet header gradually or start other discharge valves or drainage valves. During the
startup, sufficient steam flow must be maintained to remove the condensate on the
superheater components.
16) Blow the boiler off as necessary during boiler warm-up. Maintain the water level within
the visible range during the blow-off.
17)
Maintain the water level of boiler drum at normal valve, and inspect the concentration
and composition of boiler water as needed, to maintain qualified boiler water condition.
18) Before the condenser forms vacuum, make sure that the exhaust valves and drain valves
-
7/25/2019 Boiler Manual 3x135MW
42/61
Instruction For Boiler Operation 2305-1-8603 P 42/61
1. Temperature of main steam or reheat steam pipelines suddenly drops without rhyme or
reason.
2.
Steam line vibrates and causes water shock.
3. Abnormal vibration and expansion reading record shown in turbine monitoring
equipment.
Operating personnel shall take necessary measures to prevent water from entering and
damaging the turbine. Refer to the specification provided by turbine manufacturer.
21)
When bed temperature (average temperature of middle-level thermocouple) achieves
575, the first coal feeder can be started manually to load coal at the minimum rate.
After coal is loaded, observe the variation of bed temperature. When the bed
temperature rises gradually while the oxygen quantity decreases continuously, it can be
identified that the coal is in combustion. To spread the fuel evenly on the bed face,
firstly load coal through the middle coal feeding tube. Now attention shall be paid to the
air quantity in the coal feeding tube. If the bed pressure is low and the air quantity is
small, the dampers in the two sides can be turned down appropriately. However, in the
beginning when coal is loaded, increase or decrease gradually depending on the
combustion conditions in the furnace. For further heating and temperature rising, follow
-
7/25/2019 Boiler Manual 3x135MW
43/61
Instruction For Boiler Operation 2305-1-8603 P 43/61
boiler when the bed temperature(average temperature measured by the lower thermocouple)
is more than 650. If the bed temperature is higher than the allowable coal feeding
temperature after the fan is started, it is not necessary to purge the furnace or to put the
startup burners into operation. After feeding coal directly and igniting with the coal feeder at
the minimum rotary speed, the boiler can be brought to the full load rapidly. It is also not
necessary to consider the limit in temperature rising rate for the wear-resistant refractory
materials in the furnace. This is because there is quite high accumulation of heat in the
furnace and cyclone separator in this time.
10.5 Regulation during normal operation of boiler
The boiler will be put to automatic control during operation, however opertaing
personnel shall pay attention to the operating condition of the unit to ensure the safety and
economics of boiler operation and to the control of emmssion in fuel gas. Steam flow,
temperature and pressure parameter of superheater and reheater shall be kept within the
allowable range of normal operation.
10.5.1Regulation of boiler load
The regulation of boiler load is mainly achieved by changing the coal feeding quantity
and the corresponding air volume. When the load increases, increase the air volume firstly
-
7/25/2019 Boiler Manual 3x135MW
44/61
Instruction For Boiler Operation 2305-1-8603 P 44/61
maintained. However, because the bed temperature is restricted by multiple factors, the
variation amplitude is limited.
10.5.2 Regulation of bed temperature of boiler
The design value of the bed layer temperature of the boiler is 892 under the rated
load. Considering the load variation and the requirements in other aspects, the bed layer
temperature is controlled at 850~910. When the bed temperature exceeds this range, it
must be regulated in time.
Regulate the bed temperature by changing the ratio of primary air to secondary air.
When the primary air volume is increased or the secondary air volume is reduced, the bed
temperature will decrease. Conversely, the bed temperature will increase.
By increasing the quantity of bed materials to improve the circulation of the materials,
the bed temperature can be increased. By increasing the slag discharge quantity to reduce the
bed pressure and the quantity of bed materials, the bed temperature will rise.
If the mean size of the bed materials is excessively large, relatively speaking, the
useable materials that can participate in the internal and external circulations of the boiler
will decrease, causing the boiler to operate at relatively high bed temperature. By increasing
the slag discharge quantity, removing the bed materials with larger particle size and adding
-
7/25/2019 Boiler Manual 3x135MW
45/61
Instruction For Boiler Operation 2305-1-8603 P 45/61
10.5.4 Regulation of steam temperature
Primary and secondary spray type desuperheater are set respectively between platen
superheater cold section, platen superheater hot section and high-temperature superheater in
superheater system, to regulate steam temperature, primary for coarse control and secondary
for fine tuning.
Reheater regulate steam temperature mainly by gas damper, supplemented by
emergency water spray device.
The steam temperature is regulated with water spray. The operators shall pay close
attention to the water spray quantity and the steam temperature before and after water spray
to ensure that the desuperheated steam temperature should be higher than the saturation
temperature under such pressure by 11.
10.5.5 Control of SOx emission quantity
If the control of SOx emission quantity is not needed, please skip this section.
The SOx emission quantity is normally controlled by controlling limestone feed rate
automatically and manually, i.e. to increase or decrease the mole ratio of calcium and sulfur.
However, many other factors like bed temperature, limestone granularity will affect the
desulfurization efficiency of a CFB boiler.
-
7/25/2019 Boiler Manual 3x135MW
46/61
Instruction For Boiler Operation 2305-1-8603 P 46/61
the nitrogen oxides generated from the organic nitrogen compounds in the fuel which are
oxidized in the combustion process. For the fluidized bed boiler, the NOx emission quantity
is controlled through control of bed temperature and segmental combustion.
When the bed temperature is controlled in 790~900, the NOx emission quantity is the
lowest.
The primary/secondary air ratio affects the NOx emission. While the bed temperature
and the normal combustion in the furnace are guaranteed, regulating the primary/secondary
air ratio within a certain range can bring the NOx emission to a relatively low level.
10.5.7 Protection of reheater
Turbine bypass shall remain hot stand-by during boiler normal operation, in order to
protect the reheater heating surface when unexpected accidents such as turbine tripping
happen. CFB boiler is different from conventional PC boiler, when accidents such as turbine
tripping happen and cause MFT, huge heat storage still exists in the furnace and the
temperature is high in the furnace, even higher than the anti-oxidation temperature of tube
material. Therefore, bypass is needed to start up to make a certain amount of steam flowing
through superheater and reheater to cool the heating surface.
10.5.8 Re-fluidization of bed materials
-
7/25/2019 Boiler Manual 3x135MW
47/61
Instruction For Boiler Operation 2305-1-8603 P 47/61
5) Recover the normal control.
10.5.9 Use and maintenance of bed temperature thermocouple
Bed temperature is the average temperature of each thermocouple at different place of
the bed. If the temperature of a thermocouple differs by more than 170from average
temperature, the temperature will not be included in the calculation.
Bed temperature thermocouple passes through wear-resisting material layer for about
150mm. If the length is exceeded, the wear will be increased and the service life will be
shortened.
10.5.10 Maintenance of bed temperature measuring equipment
Bed temperature measuring equipment is different from conventional pressure
measurement. Purging air shall be arranged, because pressure measuring point and pressure
measuring pipeline can be easily blocked by fluid bed material.
In order to remove the accumulated bed material at pressure measuring hole, purging
shall be continuous. It is realized by zero transferring at site.
Instruction: Pressure measuring holes shall be inspected on by one for blockage before
boiler is put into operation. Because of the error of construction, the distance between each
hole and air distributor may deviate from design location and causes large pressure
-
7/25/2019 Boiler Manual 3x135MW
48/61
Instruction For Boiler Operation 2305-1-8603 P 48/61
furnace temperature drop curve.
Steam temperature drop speed shall be in line with the requirements of turbine
manufacturer.
Steam temperature control, combustion control and water feeding control can keep
using automatic way until manual way is better, change into manual way.
Caution: During and after shutdown, carefully prevent water from entering into main
steam pipeline, hot reheat pipeline and cold reheat pipeline, in order to prevent the damage
to turbine in future restart. Water may come from:
1Overflow into superheater from drum because of high water level.
2Enter into superheater from desuperheater because of desuperheating control
valve open or leakage.
2) Reduce the coal feeding quantity
When the middle-level thermocouples show that the temperature is near 680, put the
startup burners into service. Control the boiler reducing rate according to the shutdown curve.
When the middle-level thermocouples show that the temperature is below 680 without
startup burners running or when startup burners is in operation and the middle-level
thermocouples temperature is lower than 630, coal feeding must be stopped. Once coal
-
7/25/2019 Boiler Manual 3x135MW
49/61
Instruction For Boiler Operation 2305-1-8603 P 49/61
8) If the boiler to be emptied, boiler water temperature shall be below 90 before
drainage.
9)
When an appropriate operating temperature is realized for boiler shutdown, continue to
purge the furnace, cyclone separator, material-returning leg and material-returning
machine for around 30mins to protect the refractory materials, then shut off the air fan.
10)
The stop subsequence of fans: primary air fan-- secondary air fan-- induced air
fan--high-pressure fluidized air fan.
10.6.2 Normal boiler shutdown to hot standby
Boiler shutdown time is short (below 8 hours) and certain pressure and temperature are
maintained. Furnace bed temperature shall be kept higher than the allowable temperature of
pulverized coal ignition during operation as far as possible. The pressure of superheater
pipeline shall be reduced to an expected value, and it shall be kept by using superheater
outlet exhaust valve or reheater protection system.
The procedure similar to that for normal shutdown to cold state shall be observed
except for the following conditions:
With the decrease of unit load, do not lower the drum pressure. The pressure decrease
rate shall be much smaller than the rate of normal boiler shutdown. Referring to the
-
7/25/2019 Boiler Manual 3x135MW
50/61
Instruction For Boiler Operation 2305-1-8603 P 50/61
Under the condition that the coal powder ignition is allowed, maintain the bed
temperature as high as possible.
4)
Turn off the secondary air fan when the gas temperature of cyclone separator is lowered
to 538. Continue with the purging with high-pressure fluidization air fan for 10
minutes to remove the combustible gas in the material returner and the solid substances
in the cyclone separator, material returner and material-returning leg. Then turn off the
induced draft fan and close the baffles in all the air ducts to minimize the heat loss in the
furnace.
5)
The boiler can be re-started in hot-state or warm-state mode depending on the bed
temperature.
10.7 Slag-cooling system
There are slag notches at the bottom of the furnace. Bottom slag enters into slag cooler
through slag notches, and is discharged after being cooled. Discharge quantity is controlled
by variable frequency motor speed, and inlet quantity is controlled by the pressure
difference between the inlet air pressure of hot primary air chamber at the bottom and
furnace outlet air pressure. Slagging begins when bed pressure is beyond 13.5Kpa
(tentative, the specific value is determined after site commissioning).
-
7/25/2019 Boiler Manual 3x135MW
51/61
Instruction For Boiler Operation 2305-1-8603 P 51/61
6) Limestone system doesnt run normally.
Countermeasures:
1)
Inspect the bed temperature thermocouples;
2) Check if the operation and control of the coal feeder are normal;
3) Distribute the air reasonably, and regulate the primary-secondary air ratio;
4)
Adjust the particle size of the coal fed into the furnace;
5) If necessary, increase the slag discharge quantity and add bed materials of appropriate
particle size.
11.2 Excessively high or low bed pressure
Phenomenon:
1) Excessively high or low display of CRT interface; Excessively high or low display of
bed pressure;
2)
Bed pressure high or low alarm;
3) Severe increment of slag discharge load of slag cooler, or slag discharge almost stopped;
4) Excessively high or low pressure at bottom of air box.
Cause:
1)
Bed pressure measurement failure;
-
7/25/2019 Boiler Manual 3x135MW
52/61
Instruction For Boiler Operation 2305-1-8603 P 52/61
1) In case of slight cracking or weld leakage, hiss of steam can occur and the feed water
flow increases slightly;
2)
In case of severe conditions, obvious popping and steam spraying sound appears at the
tube cracking place, the negative pressure in the furnace turns positive, the feed water
flow becomes abnormally higher than the steam flow, and keeping of water level
becomes difficult in severe case.
3) Atomization phenomenon occurs in the non-tight boiler wall places;
4)
In severe case, the current of the induced draft fan increases and white steam is emitted
from the chimney;
5) The bed temperature and the temperature at the inlet/outlet of the cyclone separator
decrease.
Cause:
1)
The quality of boiler water and feed water exceeds the standard for long term, causing
scaling in the tubes, increment of local thermal resistance and over-temperature;
2) The water circulation is not good, resulting in local over-temperature;
3) Unqualified tube material, poor welding quality, or severe wear of external wall of
tubes;
-
7/25/2019 Boiler Manual 3x135MW
53/61
Instruction For Boiler Operation 2305-1-8603 P 53/61
2) The furnace vacuum reduces or turns positive, and the pressure of the superheated steam
decreases.
Cause:
1) Scaling on the inner wall of the tube or blockage of the tube with foreign materials,
resulting in deteriorated heat conduction;
2)
Wear of outer wall of tubes, or high-temperature corrosion;
3) The steam temperature or wall temperature exceeds the limit for long term;
4)
Unqualified tube material, improper welding quality, or improper steam soot blowing.
Countermeasures:
1) If the tube blasting is not severe, it is allowed to operate for a certain period. However,
reduce the load appropriately and prepare for shutdown.
2) In case of severe tube blasting;
1.
With the induced draft fan running, control the bed temperature decreasing rate not
to exceed the specified value;
2.Maintain small quantity of feed water and keep normal water level;
3.Proceed with the other operations as per the normal boiler shutdown procedure.
11.5 Coking on bed surface
-
7/25/2019 Boiler Manual 3x135MW
54/61
Instruction For Boiler Operation 2305-1-8603 P 54/61
3) If it the condition does not improve after the regulation, shut down the boiler
immediately.
11.6 Power interruption of system
Phenomenon:
1) The water level in the steam drum is relatively low or is invisible;
2)
Collapse of the bed materials in the furnace bed face or in the bed face of the material
returning valve;
3)
Power interruption causes all the auxiliary machines to stop.
Countermeasures:
1) Close the main steam valve and open the atmosphere vent valve of the superheater.
Avoid tripping of the safety valve as long as possible. Control the steam flow at
approximately 2kg/s;
2)
Open the connection between the drainage of the economizer and the concentrated
downcomer so that the water of the economizer could be supplemented into the water
wall;
3) Because of the high heat accumulation in the boiler, open the baffles of the various air
ducts to reduce the temperature level in the boiler at the maximum speed;
-
7/25/2019 Boiler Manual 3x135MW
55/61
Instruction For Boiler Operation 2305-1-8603 P 55/61
Countermeasures:
1) Firstly, compare the indication conditions of all the level gauges to judge the
truthfulness of the water shortage accident and the water shortage extent;
2) If relatively severe water shortage is caused by severe failure of electrical equipment,
judge quickly and request for instructions for emergency shutdown;
3)
When water shortage is not serious, generally, there is no failure which may affect the
operation of boiler, such shortage is caused by improper operation probably. Water
supply shall be enhanced by manual operation to restore normal water level.
11.8 Water fullness accident
Phenomenon:
1) Water level is invisible at the sight glass of the level gauge, and the boiler water
becomes dark;
2)
The water level alarm gives high-level alarm signal;
3) The superheated steam temperature drops and the salt content of the steam increases;
4) The feed water flow becomes higher than the steam flow suddenly.
Cause:
1)
The operators omits in monitoring the water level;
-
7/25/2019 Boiler Manual 3x135MW
56/61
Instruction For Boiler Operation 2305-1-8603 P 56/61
In case of water attack in the steam pipeline, start the drainage valve of the superheater
system. Drain sufficiently and vent the remaining air out of the pipeline. For the feed water
pipeline, stabilize the water pressure and eliminate the air.
-
7/25/2019 Boiler Manual 3x135MW
57/61
Instruction For Boiler Operation 2305-1-8603 P 57 / 61
,
THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION
OF SBWL..
12 Appendix
12.1 Figure 1 Boiler dry-off heating/cooling rate
-
7/25/2019 Boiler Manual 3x135MW
58/61
Instruction For Boiler Operation 2305-1-8603 P 58 / 61
,
THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION
OF SBWL..
12.2 Figure 2 Cold-state startup curve
-
7/25/2019 Boiler Manual 3x135MW
59/61
Instruction For Boiler Operation 2305-1-8603 P 59 / 61
,
THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION
OF SBWL..
12.3 Figure 3 Warm-state startup curve
-
7/25/2019 Boiler Manual 3x135MW
60/61
Instruction For Boiler Operation 2305-1-8603 P 60 / 61
,
THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION
OF SBWL..
12.4 Figure 4 Hot-state startup curve
-
7/25/2019 Boiler Manual 3x135MW
61/61
Instruction For Boiler Operation 2305-1-8603 P 61 / 61
,
THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION
OFSBWL
12.5 Figure 5 Shutdown curve