boiler manual 3x135mw

Upload: harrisonic-serande

Post on 27-Feb-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Boiler Manual 3x135MW

    1/61

    REV.

    A

    INSTRUCTION FOR BOILER OPERATION

    SG-420/13.9-M2305MODEL OF PRODUCT

    420t/hNAME OF PRODUCT 420t/h Circulating Fluidized Bed Boiler

    2305-1-8603SERIES No.

  • 7/25/2019 Boiler Manual 3x135MW

    2/61

    Instruction For Boiler Operation 2305-1-8603 P 2/61

    Table of Contents

    INSTRUCTION ....................................................................................................................... 5

    1 GENERAL CONDITIONS OF BOILER ............................................................................. 6

    1.1BRIEF INTRODUCTION OF BOILER..................................................................................... 6

    1.2MAIN TECHNICAL PARAMETERS OF BOILER..................................................................... 7

    1.3MAIN PERFORMANCE INDEXES OF BOILERDESIGN COAL,TMCRWORKING CONDITION

    .............................................................................................................................................. 8

    1.4FUEL ................................................................................................................................ 8

    1.5LIMESTONE (IN BRIEF)..................................................................................................... 9

    2. COMMISSIONING TEST OF BOILER ............................................................................. 9

    2.1IMPORTANCE OF BOILER COMMISSIONING........................................................................ 9

    2.2PREPARATION BEFORE BOILER OVERALL STARTUP........................................................ 10

    3. HYDROSTATIC TEST ..................................................................................................... 10

    3.1TEST REQUIREMENTS ..................................................................................................... 10

    3.2MAINTENANCE AFTER HYDROSTATIC TEST.................................................................... 11

    4. WATER TREATMENT (IN BRIEF) ................................................................................ 11

    5BOILER DRY-OFF ......................................................................................................... 11

    5 1 PURPOSE OF BOILER DRY OFF 11

  • 7/25/2019 Boiler Manual 3x135MW

    3/61

    Instruction For Boiler Operation 2305-1-8603 P 3/61

    8.6PURGING OF MAIN STEAM PIPELINE................................................................................ 25

    8.7PURGING OF REHEATER INLET PIPELINE......................................................................... 25

    9. NORMAL PRINCIPLES FOR BOILER OPERATION ................................................... 25

    9.1GENERAL RULES ............................................................................................................ 25

    9.2WATER FILLING AND VENTING...................................................................................... 26

    9.3STARTUP ........................................................................................................................ 26

    9.4BOILER SHUTDOWN ....................................................................................................... 27

    9.5WATER LEVEL............................................................................................................... 28

    9.6BOILER WARM-UP AND EXPANSION............................................................................... 29

    9.7AIR PREHEATER............................................................................................................. 29

    9.8SOOT BLOWING .............................................................................................................. 29

    9.9REGULATION OF STEAM TEMPERATURE......................................................................... 30

    9.10SUPERHEATER AND REHEATER.................................................................................... 30

    9.11BLOW-OFF ................................................................................................................... 32

    9.12TUBE DAMAGE ............................................................................................................. 32

    9.13FURNACE EXPLOSION ................................................................................................... 33

    9.14FLY ASH WEAR............................................................................................................ 34

    9.15INSPECTION................................................................................................................. 34

    9.16MAINTENANCE OF BOILER AND FREEZING PREVENTION............................................... 35

    10 BOILER OPERATION PROCEDURE ............................................................................ 36

    10.1STARTUP AND OPERATION OF BOILER.......................................................................... 36

    10.2PREPARATION BEFORE BOILER STARTUP...................................................................... 37

    10 3 COLD/WARM STATE STARTUP 38

  • 7/25/2019 Boiler Manual 3x135MW

    4/61

    Instruction For Boiler Operation 2305-1-8603 P 4/61

    12.4FIGURE 4 HOT-STATE STARTUP CURVE...................................................................... 60

    12.5FIGURE 5 SHUTDOWN CURVE.................................................................................... 61

  • 7/25/2019 Boiler Manual 3x135MW

    5/61

    Instruction For Boiler Operation 2305-1-8603 P 5/61

    Instruction

    Combining the experience in design, manufacture and operation of dozens of

    ultra-supercritical circulating fluidized bed boiler, the 420t/h class circulating fluidized bed

    boiler is completely designed by Shanghai Boiler Works Co., Ltd, which is developed by

    Shanghai Boiler Works Co., Ltd using advanced technology of circulating fluidized bed.

    This instruction for boiler operation, based on the design features of circulating

    fluidized bed boiler, introduces the utilization requirements, operation procedures and

    matters needing attention of the boiler body. The various contents of the instruction are basic

    requirements proposed for the boiler utilization process to ensure the safe operation and

    service life of the boiler. The boiler startup and shutdown procedures are closely related to

    the other units of the boiler, e.g. turbine, various auxiliary equipment, control system, etc.

    Therefore, the specific operation specifications for the complete set of generator unit to

    match with the boiler shall be prepared by the user with reference to the applicable

    specifications of the industry. This instruction is only for information when the user prepares

    boiler startup and operation specifications.

  • 7/25/2019 Boiler Manual 3x135MW

    6/61

    Instruction For Boiler Operation 2305-1-8603 P 6/61

    1General conditions of boiler

    1.1 Brief introduction of boiler

    SG-420/13.9-M2305 circulating fluidized bed boiler is an ultra-supercritical

    intermediate reheat, natural circulation boiler with single drum, which is designed and

    manufactured by Shanghai Boiler Works Co., Ltd using advanced technology of circulating

    fluidized bed. Balanced draft, centralized downcomer and water-cooling cyclone separator

    are adopted in the boiler, and 2 slag discharge tubes and 1 accident slag discharge tube are

    arranged at the bottom of furnace combustion chamber. Membrane waterwall is adopted in

    furnace and the lower part uses refractory furnace lining. The boiler has 4 coal feeding points

    and 4 limestone feeders, which are all set at the front wall. For this boiler, on-bed startup

    ignition mode is adopted. Totally 4 high-power ignition oil guns (2 for each of the left and

    right side walls respectively) are arranged on the bed. Convection heating surface is arranged

    in the boiler rear pass and two-stage water spray temperature adjustment is adopted in

    superheater. Reheater mainly uses flue gas damper temperature adjustment, supplemented by

    accident water spray device.

    1.1.1 Steam-water system of boiler

    The steam-water system of the boiler includes tail economizer, boiler drum, evaporation

  • 7/25/2019 Boiler Manual 3x135MW

    7/61

    Instruction For Boiler Operation 2305-1-8603 P 7/61

    the primary air fan is heated in the steam air heater and primary air preheater. Then one route

    enters the primary air chamber in the bottom of the furnace and the bed material is fluidized

    through the wind cowl on the air distribution board, forming solid circulation going upwards

    through the furnace. For the second route, an air pipe is led from the primary air duct to the

    furnace coal falling tube as coal spreading air. For the third route, a stream of high-pressure

    cold air is led from the cold air duct behind the outlet of the primary air fan as the sealing air

    for the furnace coal falling tube and coal feeder. After the secondary air is heated by the air

    heater and secondary air preheater, a certain number of branch tubes are led from the

    secondary air chamber. The air enters the furnace combustion chamber from front and back

    wall of the furnace and upper dense-phase zone as two layers. Meanwhile, the secondary air

    is also used for ignition of the on-bed oil guns and oil gun cooling.

    After the gas with solid particles left the furnace, it tangentially enters the cyclone

    separator through two inlet duct respectively. Coarse particles are separated from the gas in

    the separator, and gas enters rear pass through separator center cylinder. After cooled by

    heating surface, the gas enters dust collector through tubular air preheater to remove fine

    particles and finally discharges into the atmosphere through stack by induced draft fan.

    One stream of the high-pressure fluidization air is used as fluidization air for the

  • 7/25/2019 Boiler Manual 3x135MW

    8/61

    Instruction For Boiler Operation 2305-1-8603 P 8/61

    Superheater outlet steam temperature 543 543

    Reheater steam flow t/h 351.108 351.108

    Reheater inlet steam pressure MPa(g) 2.757 2.757

    Reheater outlet steam pressure MPa(g) 2.632 2.632

    Reheater inlet steam temperature 319.6 319.6

    Reheater outlet steam temperature 543 543

    Feedwater temperature 252.1 252.1

    1.3 Main performance indexes of boilerDesign coal, TMCR working condition

    Item Unit Value

    Computational efficiency of boiler (as

    per net calorific power)% 93.29

    Guaranteed efficiency of boiler (as per

    net calorific power)% 92.5

    Solid incomplete combustion heat loss % 1

    D t di h t ti t

  • 7/25/2019 Boiler Manual 3x135MW

    9/61

    Instruction For Boiler Operation 2305-1-8603 P 9/61

    As-received gross calorific value

    HHVQgr.ar Kcal/kg 4500

    1.4.2 Ignition and combustion supporting oil

    Light diesel oil is adopted in this project as ignition and combustion supporting oil. The

    analysis data of the oil are as follows.

  • 7/25/2019 Boiler Manual 3x135MW

    10/61

    Instruction For Boiler Operation 2305-1-8603 P 10/61

    exist in boiler and auxiliary equipment, in order to take effective measures in time. To train

    the operating personnel concerned about equipment performance and primary adjustments of

    operation, which lays a good foundation for pilot production and commercial operation.

    2.2 Preparation before boiler overall startup

    Besides separated commissioning of the main equipment of each system, hydrostatic

    test, dry-off, cold aerodynamic characteristic test, boiler body cleaning, steam pipeline

    purging, boiler ignition test, boiler safety valve setting, auxiliary equipment interlock

    protection test and boiler main protection test should be done before the boiler overall

    startup commissioning. A complete inspection of boiler proper and its steam-water system,

    flue gas and air system, combustion system, relevant auxiliary equipment, thermal control,

    chemical water treatment equipment and site environment should be carried out according to

    the commissioning program, operating standard and boiler operation instruction before cold

    start, to meet the requirements of boiler safe startup.

    3. Hydrostatic test

    Hydrostatic test should be carried out according to the requirements of relevant boiler

    regulations.

    3.1 Test requirements

  • 7/25/2019 Boiler Manual 3x135MW

    11/61

  • 7/25/2019 Boiler Manual 3x135MW

    12/61

    Instruction For Boiler Operation 2305-1-8603 P 12/61

    that results in cracking, deformation and damage of the refractory materials, or even

    peeling-off of the wear-resistant materials in severe case. Therefore, before the boiler is put

    into operation officially, it is necessary to dry off the boiler with controlled heating method.

    Meanwhile, boiler dry-off can accelerate the physical/chemical variation process of the

    boiler wall materials, making the performances stable so that it can work for long term under

    high temperature.

    5.2 Preparation required before boiler dry-off and conditions

    1) The installation work for the boiler proper, material returning system and gas/air

    system is completed. The construction of the wear-proof refractory materials is

    completed. The air leakage and air pressure test is passed.

    2) Open the door holes in the various positions and allow it to dry naturally for more than

    72 hours.

    3) Carry out internal inspection of the furnace, flue gas/air duct, cyclone separator,

    material returning device, etc. Remove the foreign matters.

    4) Temporary exhaust valve is installed on the top cover of the cyclone separator, and

    temporary partition is installed in outlet duct of the separator.

    5)

    The fuel oil system is installed. All the jobs such as hydrostatic test and instrument test

  • 7/25/2019 Boiler Manual 3x135MW

    13/61

    Instruction For Boiler Operation 2305-1-8603 P 13/61

    boiler with controlled heating method. The boiler dry-off curve of wear-resistant refractory

    materials should be made by insulating material manufacturer, user and boiler manufacturer.

    This instruction recommends the dry-off methods which uses extra burner to heat CFB

    boiler. In this method, extra burners are arranged through the manhole doors and observation

    eyes in the furnace and gas ducts at the positions laid with wear-resistant refractory materials

    for heating and temperature control, the heat source generated is hot gas, which will not

    flush the refractory insulation materials directly or generate local high temperature.

    Moreover, with this method, it is easier to control the furnace and the gas duct at different

    temperature.

    Drying of the refractory materials is only a stage for accomplishing the engineering

    plan. However, for CFB boiler, it is a very important link. This job is usually implemented

    and accomplished by the refractory material installer by providing with temporary burners.

    Once the refractory material drying procedure starts, it must proceed continuously as

    per the temperature control curve without interruption until the boiler dry-off is completed.

    This is critical for drying the refractory materials thoroughly and for ensuring the

    performances of the refractory materials.

    After a period of insulation, the furnace temperature cooled down is about 370. The

  • 7/25/2019 Boiler Manual 3x135MW

    14/61

    Instruction For Boiler Operation 2305-1-8603 P 14/61

    10) The door holes in the furnace and separator shall be closed to prevent heat from

    escaping out of the door hole.

    11)

    Feed water into the boiler drum to the normal operation level.

    12) Adjust the main steam exhaust and drain valve before starting boiler dry-off.

    13) Drum exhaust door Open/Pressure up to 175Pa Close

    14)

    Main steam exhaust/drain Open

    15) Startup exhaust valve Open 25%

    16) Reheater exhaust/drain Open

    17)

    Adjust the openness of the fan inlet movable vane to be consistent with that of the

    baffle.

    18) Primary air fan inlet movable vane 5%-10%

    19) Secondary air fan inlet movable vane 5%-10%

    20) Induced draft fan inlet movable vane 5%-10%

    21) Secondary air fan upper/lower baffle Close

    22) During the drying of refractory materials, maintain the steam drum at normal water

    pressure.

    23)

    During the boiler dry-off, monitor the temperature of the gas entering the preheater

  • 7/25/2019 Boiler Manual 3x135MW

    15/61

    Instruction For Boiler Operation 2305-1-8603 P 15/61

    5Recorder for recording the temperature of each thermocouple.

    6Operating personnel 24 hour uninterrupted shift.

    7Provide boiler dry-off report (including summary, copy and electronic edition of original

    boiler dry-off record)

    5.3.4 Duration

    1) Preparation time is about four weeks from the delivery of boiler dry-off equipment.

    2) About one week to install pipe to burner position.

    3) About three day for equipment startup preparation.

    5.3.5 Other requirements

    1) Elevator/crane for lifting boiler dry-off machine (800kg).

    2)

    Compressed air used during boiler dry-off (3m3/h/burner0.25Mpa), atomized fuel oil.

    3)

    Electric power 18kw/220/380 volt power, 50

    100kg/h fuel 14 boiler dry-off machine.4) Oil supply pipe connected to boiler dry-off machine, use hose for the tube at about 15

    inches near the end the boiler.

    5)

    Set aside a plane space of 3 inches 3 inches for temporary boiler dry-off machine area.

    5.3.6 Position of burner and thermocouple for boiler dry-off

    B t

  • 7/25/2019 Boiler Manual 3x135MW

    16/61

    Instruction For Boiler Operation 2305-1-8603 P 16/61

    Storage areatemporary storage area is arranged beside the boiler or between two

    boilers.

    Temporary storage tankthis is sign on and beside temporary storage tank (truck oil

    tank)

    Temporary pipelinefrom storage tank to boiler area and then to the connection of

    temporary burner.

    In addition, where there is oil return line, there is isolating valve.

    5.3.8 Boiler dry-off heating/cooling rate (see Figure 1).

    5.3.9Temperature rising requirements for the first startup

    After the boiler dry-off with dry-off machines is completed, all the dry-off machines

    and the related devices shall be removed. When the complete-group startup conditions are

    met and the boiler is started for the first time, in order to protect refractory material, boiler

    main oil gun should be used to heat up as per the curve below. To meet the requirements of

    heating curve, the oil quantity for the oil guns and the number of oil guns put into use shall

    be controlled strictly.

    50/h rises to

    670 , keep at 670

    f 4 h

    50/h rises to

    500 , keep at

    00 f 2 h

    Tubes

    must be

    fill d

  • 7/25/2019 Boiler Manual 3x135MW

    17/61

    Instruction For Boiler Operation 2305-1-8603 P 17/61

    critical fluidization air volume, and provide with references for the hot-state operation of the

    boiler to ensure the combustion safety of the boiler, to prevent coking on the bed and to

    protect the equipment from being damaged.

    Caution

    Cold aerodynamic characteristic test is the foundation and

    reference basis for boiler startup commissioning, boiler

    combustion adjustment and boiler safe and economical

    operation. It should be done in accordance with the relevant

    regulations. Relevant data collection should be done as well.

    6.2 Main content of test

    Furnace ventilation circuit test

    1)

    Performance examination of primary/secondary air fans and high-pressure fluidizationair fan;

    2)

    Test of coal feeder air quantity distribution features;

    3) Calibration for measuring devices of primary/secondary air volume and fluidized air

    volume of material-returning machine;

    4)

    D i i f h l i f f h i i d b ffl

  • 7/25/2019 Boiler Manual 3x135MW

    18/61

    Instruction For Boiler Operation 2305-1-8603 P 18/61

    in-furnace dense-phase zone. The difference between the two is the resistance of the air

    distribution board. Draw the relationship curve between the primary air volume and the air

    distribution board resistance in cold state. Through temperature correction, the relationship

    curve between the primary air volume and the air distribution board resistance in hot state

    can be obtained. During the operation of the boiler, if failure occurs at the bed pressure

    measurement point, the quantity of on-bed materials can also be judged on the basis of the

    relationship curve between air chamber pressure & air volume and air distribution board

    resistance, thereby reducing the operation blindness.

    6.5 Test of critical fluidization air volume

    The various cold-state measurement tests before this test are carried out with no bed

    materials filled. The critical fluidization air volume refers to the minimum air volume

    necessary for the bed materials to turn from fixed state to fluidized state. It is the minimum

    primary air volume during the operation of the boiler. Method for determine the critical

    fluidization air volume: Select 0~1mm or 0~1.5mm river sand or CFB boiler slag as bed

    materials. Add bed materials to static height of 1100 mm (sand) or1200mm (ash). Increase

    the primary air volume. On the initial stage, the bed pressure increases gradually along with

    the increment of primary air volume. When the air volume exceeds a certain value, continue

  • 7/25/2019 Boiler Manual 3x135MW

    19/61

    Instruction For Boiler Operation 2305-1-8603 P 19/61

    There are various kinds of chemical cleaning. Users can choose the appropriate method

    according to relevant standards.

    This chapter only introduces the cleaning method with low-temperature low-foam

    cleanser by virtue of out-laid circulating pump for forced circulation. It is an effective, quick

    and economical cleaning method.

    The concentration recommended by merchant should be checked, since commercial

    cleanser concentration is changed (for example, diluted with water). Normally, the

    recommended cleanser concentration is 0.6 percent by volume at 21 ambient temperature

    (i.e. to add 1L cleanser into 167L water). If the boiler is cleaned at above 65.6, the

    recommended cleanser concentration is 0.3 percent by volume.

    7.1Preparation for cleaning

    1)

    All the water/steam separation devices in the steam drum have been removed.

    2) Provide with a temporary circulating pump with a capacity of 14 t/h to circulate the

    solution in the furnace. This pump shall suck the solution from the bottoms of the

    furnace lower header and of the evaporation screen header. The solution is discharged

    from the economizer inlet header. The size of the pipes from the pump to such positions

    on the boiler shall match. All the high-pressure pipes connecting to the boiler and all the

  • 7/25/2019 Boiler Manual 3x135MW

    20/61

    Instruction For Boiler Operation 2305-1-8603 P 20/61

    7) Provide with a sampling connection complete with valve, and attach an appropriate tag.

    8) Before cleaning, remove the residues in the boiler drum and header mechanically as

    long as possible. Check all the bolt sealing components in the boiler drum.

    9) All the pressured parts must be checked carefully for any blockage. If any, carry out

    necessary hydrostatic test. Inspect the blow-off pipes and dosing pipes inside the boiler

    drum and make sure the interiors are smooth and clean.

    10) During the cleaning, the operators on duty shall be familiar with the normal combustion

    and operational procedures, as well as preventive actions, and learn safety operation

    procedures for cleaning. This is very important. Special care shall be employed when

    taking any measures that may cause leakage. Take appropriate measures to protect the

    personal safety in case of any accidental leakage event.

    11) Desalted water is used to fill reversely the SH to ensure that the SH is fulfilled, for ease

    of observing the increase of drum water level.

    7.2 Flushing with cleanser under ambient temperature

    Fill the boiler, evaporation screen and economizer with water until the bottom water

    level of the level gauge is in visible range. Through the temporary chemical pipeline, inject

    the cleaning liquor slowly. Again add water until the water level is higher than the boiler

  • 7/25/2019 Boiler Manual 3x135MW

    21/61

    Instruction For Boiler Operation 2305-1-8603 P 21/61

    7.3 Matters needing attention

    1) Discharge of the cleanser does not need to be done under the presence of nitrogen.

    Nitrogen is a nontoxic gas, but is unfavorable for human respiration. If nitrogen-filling

    is adopted for draining the boiler and a man needs to enter it after the drainage,

    appropriate ventilation must be carried out before a man is allowed in.

    2)

    If the boiler will be left free fora couple of days after the cleaning, the boiler and the

    superheater need to be maintained as described in the maintenance procedure.

    3) Before the counter-flushing of the superheater is completed, perform chemical analysis

    for the water used (conductivity, pH and chlorine) to confirm that no pollution exists.

    4) After the cleaning and before the ignition of the boiler, the water in the superheater and

    steam pipeline shall be sampled, analyzed and inspected for any contamination.

    5) If cleanser overflows into the superheater due to carelessness during the chemical

    cleaning, carry out thorough counter-flushing with sufficient flow before ignition is

    allowed in order to ensure that the various contaminants are all removed.

    6) In the chemical treatment process, take special care to prevent the cleanser from doing

    harm to human being.

    7)

    Inspect the steam drum and remove any loose deposit from the inner surface of the

  • 7/25/2019 Boiler Manual 3x135MW

    22/61

    Instruction For Boiler Operation 2305-1-8603 P 22/61

    of steam pipe purging, as well as the protection against over-pressure or over-temperature,

    are all the responsibilities of the user.

    Warning

    Because the water level of the steam drum fluctuates greatly

    during the purging, the operator shall do the preparation work

    sufficiently in advance to avoid any steam drum overflow or

    water shortage accidents. Pipe purging can cause certain

    damage to the boiler. So the number of purging times shall be

    minimized while meeting to the applicable examination

    standards.

    8.3 General rules

    To achieve the best purging effect, when purging the steam pipelines, the steam flowconditions of system should equal to normal operation conditions at maximum load. Because

    the purging conditions when discharging into the atmosphere is unlikely to be repeatedly in

    accordance with operation conditions, equivalent operation conditions is expected to be

    achieved, i.e. steam flow when purging under low pressure multiplies velocity is normal

    i di i f ll l d h fl h b b i d b d i d

  • 7/25/2019 Boiler Manual 3x135MW

    23/61

    Instruction For Boiler Operation 2305-1-8603 P 23/61

    If a cut-off valve is installed in the main steam pipeline of the boiler, if the design of

    valve allows such operation mode, this valve can also be used as purging valve.

    For any component with more than one route of steam pipeline, it is necessary to

    consider installation of temporary pipeline so that every route of pipeline could be purged

    independently. In this case, make sure to resolve the flow unbalance and expansion problems

    at the connections of the pipeline system.

    The cleanliness of the components being purged is shown by the target plate provided

    at the outlet of the purging pipeline on the final stage of the purging.

    The pitting level of the target plate after the purging is used to determine the purging

    cycle of certain components.

    8.4 Matters needing attention

    1) The purging process may result in abnormal and severe conditions for the boiler and

    steam pipeline. During every purging cycle, tremendous and quick temperature change

    will occur. This change causes much severer damage as compared with normal

    operation. In the thick-wall parts of the system such as boiler drum, header and pipeline,

    excessive thermal stress may be generated. Therefore, during the purging, such

    conditions shall be considered carefully. While meeting the system cleanliness

  • 7/25/2019 Boiler Manual 3x135MW

    24/61

    Instruction For Boiler Operation 2305-1-8603 P 24/61

    8) To ensure that the hot gas will not leak out of the furnace, the furnace shall be operated

    in vacuum state (-50Pa).

    9)

    To make the tubes in furnace and convection pass heating surface overheated or

    dry-burned, the gas temperature of the furnace and cyclone separator shall be kept below

    538.

    8.5 Operation procedure

    Due to the requirement for low ignition rate, the fluid bed may be not started during

    steam purging. Fire the startup burner steadily, and assume that burner adjustment is good,

    dust collector is not necessary.

    To avoid excessively high thermal load that may cause thermal corrosion of the

    refractory material, the mean rising rate of the steam drum water temperature shall not

    exceed 50/h. Start up induced draft fan firstly, then start up primary fan and secondary fan,

    thus the startup procedure begins. As long as the material-returning machine nozzle is cover

    by ash or sand, the high-pressure fluid fan in not necessary.

    Start the boiler as per cold-state startup procedure in normal way. Formal suggestion

    and regulation about fuel burning equipment, air treatment equipment, drainage and exhaust

    shall be followed. If the boiler start up in normal operation mode, for any newly-built boiler,

  • 7/25/2019 Boiler Manual 3x135MW

    25/61

    Instruction For Boiler Operation 2305-1-8603 P 25/61

    generate the purging flow required, the purging process can start.

    8.6 Purging of main steam pipeline

    1)

    Turn off or hold startup burners. Open the temporary discharge valve gradually. Purge

    through the superheater and main steam pipelines and discharge through the temporary

    discharge pipe (refer to Matters needing attention). The initial purging is normally

    carried out under depressurization in order to inspect the supporting and fixing devices

    of the temporary piping system.

    2)

    When the steam drum pressure drops to about 1.38MPa, close the temporary discharge

    valve and re-ignite the unit to establish the purging conditions.

    3) Repeat the above operation cycle until the inspection to the flushing target plate on the

    final stage shows that the cleanliness is qualified.

    8.7 Purging of reheater inlet pipeline

    1)

    Turn off or hold startup burners. Open the temporary discharge valve gradually. Purge

    through the superheater and main steam pipelines and discharge and the pipes

    temporarily connected to the reheater and exhaust through temporary discharge pipe

    (refer to Matters needing attention). Important note: The initial purging is normally

    carried out under depressurization in order to inspect the supporting and fixing devices

  • 7/25/2019 Boiler Manual 3x135MW

    26/61

    Instruction For Boiler Operation 2305-1-8603 P 26/61

    fuel property and the equipment used for measurement. Representative fuel samples shall be

    taken regularly to analyze the chemical component, calorific value, viscosity (liquid fuel)

    particle size distribution and other physical features of the fuel. All these can cause effect on

    the operation and efficiency.

    As an index for measuring the economical efficiency of boiler operation, the discharged

    gas analysis of the boiler is of important value. The combustion shall be completed before

    the gas departs from the cyclone separator. Adoption of the optimal excess air factor depends

    on the fuel properties, design of fuel combustion equipment and other factors. And, the

    optimized excess air factors shall be established under different loads.

    When the heat conduction surface is kept clean, at the given percentages of steam and

    excess air, the gas temperature at the outlet of the preheater and the resistance of the gas

    passing through the gas duct shall generally be kept constant. To record these operation data

    starting from the startup is necessary. The operation data shall be recorded in the tables in

    order to compare with the data obtained under the various similar operation conditions.

    Standard value for judging the operation satisfaction shall be established when the

    equipment is new. In this way, when the operation conditions deviate from the standard,

    steps shall be taken to determine and correct the cause of the deviation.

  • 7/25/2019 Boiler Manual 3x135MW

    27/61

    Instruction For Boiler Operation 2305-1-8603 P 27/61

    When the pressure rises, the drainage valve can be throttled, but shall not be shut

    completely. Refer to the operation instructions of the valve (Refer to instruction for valve

    operation).

    During the startup, burning rate should be controlled to keep the highest gas temperaure

    of rear pass under 538 (inspected by the temperature element in cyclone separator and

    rear pass) until ranked with turbine. After turbine running, the rise of turbine throttle valve

    steam temperature and pressure shall always comply with the regulations made by the

    turbine manufacturers.

    When a new boiler unit is started for the first time, the combustion rate must be

    controlled. The increment of combustion rate shall be maintained at a relatively slow rate in

    order to inspect the expansion displacement and clearance. The later startup rate can be

    relatively quicker, but the temperature rise of the saturated steam shall not exceed 93

    (refer to boiler startup procedures) or the limited gas temperature of cyclone separator outlet

    mentioned above. The temperature rise of the saturated steam can be slow depending on the

    heating rate of the insulation material, refer to the instructions of the insulation material

    manufacturer. In this period, combustion regulation is normally carried out manually. Never

    try to start up with the combustion control or feed water equipment in automatic status.

  • 7/25/2019 Boiler Manual 3x135MW

    28/61

    Instruction For Boiler Operation 2305-1-8603 P 28/61

    water.

    Whatever shutdown mode is chosen, cooling rate cannot make saturated-steam

    temperature drop exceed 85 per hour.

    9.5 Water level

    Prior to the ignition, the operator shall check the steam drum water level with the water

    meter column and level gauge blow-off method. Normally, slowly opening drain valve of

    high pressure gauge is enough. Normally, an unblocked blow down can clean the foreign

    matters probably exist on drain valve seat. When warm up the new unit, the gauges shall be

    blown off for several times under low pressure and verify the consistency of remote and

    local level gauges. During the operation of boiler, the water level gauges shall be inspected

    once per shift (refer to the instructions for the water level gauges). If the water in water

    gauge is stagnant when open or close the drain valve, investigate for the cause and correct

    the conditions immediately. To protect the glass of the water level gauges, the blow-off

    volume shall be kept to minimum during the normal operation.

    During the normal operation, the water level of the water level gauge shall also be

    observed regularly even if the boiler may be provided with reliable water level regulator or

    remote water level indicator.

  • 7/25/2019 Boiler Manual 3x135MW

    29/61

    Instruction For Boiler Operation 2305-1-8603 P 29/61

    out the visible range of the gauge, except the instant water level fluctuation caused by rapid

    and sharp variation of load, proper action shall be taken immediately to flame out the boiler.

    9.6 Boiler warm-up and expansion

    When the pressure of the boiler is raised, it is necessary to take measures in the

    beginning to open all the drain valves and bypasses (if any) to drain the cold steam pipes

    sufficiently.

    During the initial ignition, check the expansion conditions of the boiler regularly and

    make records, and make sure that the guard plates, headers and pipes can expand freely

    relative to the steel structure. The expansion indicator shall be installed at appropriate

    position to facilitate inspection (refer to the arrangement diagram or expansion displacement

    diagram of pressured components). During the service life of boiler, inspect its expansion

    regularly to determine whether the expansion is normal and uniform. All the hanger rods and

    the related pipes shall be inspected regularly for their appropriate displacement and function.

    9.7 Air preheater

    Abnormal increment of the ventilation resistance in the gas side or air side of the air

    preheater indicates that the ash blockage is increasing and various measures shall be taken

    immediately. Especially when the unit is started, observe closely the temperature of the gas

  • 7/25/2019 Boiler Manual 3x135MW

    30/61

    Instruction For Boiler Operation 2305-1-8603 P 30/61

    important to the prevention of pressure parts erosion. In no case should plash be in the

    pipeline. Normally, a hole at the drain valve can continuously discharge the water. Before

    the soot blower put into operation, steam shall be used to purge freely, and enough long time

    is needed to heat the pipelines.

    9.9 Regulation of steam temperature

    Steam side regulates through firing in the furnace and control furnace outlet gas

    temperature to regulate and keep outlet steam temperature. The medium side normally keeps

    final superheater and final reheater design temperature with desuperheating water. Only

    when the outlet temperature of reheater cannot be kept within the specified range of outlet

    temperature, spray desuperheating is used.

    Whatever method is used to control the temperatuer of superheater and reheater, there

    are some factors which may cause abnormal fluctuation of steam temperature:

    Causes for abnormal low steam temperature:

    1) Insufficient excess air;

    2) Feed water temperature higher than design value;

    3) Boiler fuel carries excessive moisture;

    4)

    Contamination on superheater/reheater outer surface or inner surface;

  • 7/25/2019 Boiler Manual 3x135MW

    31/61

    Instruction For Boiler Operation 2305-1-8603 P 31/61

    and reheater shall be as even as possible, and the maximum temperature where gas flows

    through the superheater tubes (gas temperature at outlet of cyclone separator) shall be

    monitored and controlled.

    The gas temperature at outlet of cyclone separator is usually measured with the

    thermocouples installed in the outlet gas duct of the cyclone separator. The maximum

    temperature at outlet of cyclone separator shall be limited at 538, until the turbine carries

    loads and the reheater establish normal steam flow.

    To ensure that the condensation water in superheater coil is removed, steam flow

    through the superheater shall have appropriate flow when start up. Before the ignition and

    firing of the boiler, the drainage valves and vent valves in the outlet headers and/or main

    steam pipes shall be opened and shall be kept open until the boiler generates steam and is

    loaded. When the boiler drum pressure increases, these startup drainage valves and/or vent

    valves can be throttled gradually to make sure that sufficient steam flows through the

    superheater throughout the startup. When the turbine is in line with load and appropriate

    steam flow is ensured, the startup drainage valves and/or vent valves of the superheater can

    be closed.

    All drain valves of reheaters shall be open before ignitions. When boiler pressure rises,

  • 7/25/2019 Boiler Manual 3x135MW

    32/61

    Instruction For Boiler Operation 2305-1-8603 P 32/61

    of steam carrying water is doubtable, take measures immediately and investigate to remove

    the causes that result in steam carrying water. If the research show that steam carrying water

    is not caused by poor water quality, internal device of steam-water separation, water level

    control and indicating equipment where problem may probably occur shall first inspected.

    From the heat conduction and corrosion point of view, deposition of solid substances on

    the superheater and reheater is harmful. Under the presence of chemical substance like

    caustic alkali and chlorine, stainless steel pipes of superheater and reheater are much more

    likely to be eroded. Therefore, whether during carrying or filling water (hydrostatic test,

    chemical cleaning), solid matter shall be prevented from getting inside.

    9.11Blow-off

    Continuous blow-off is the best method to control and keep the relative stable

    concentration of the soluble solid substances in the boiler water. The blow-off data shall be

    recorded. Total blow-off quantity is better to be determined according to the boiler water

    chemical analysis. Because each power plant has a different water treatment system, person

    in charge of water condition shall specify the water treatment system according to the

    feedwater analysis and give necessary instruction of blow-off.

    However, the blow-off quantity will affect the heat loss and water supplement volume

  • 7/25/2019 Boiler Manual 3x135MW

    33/61

    Instruction For Boiler Operation 2305-1-8603 P 33/61

    load condition requires to keep operating, the boiler can keep operating until the chance of

    shut-down for necessary overhaul. Under such circumstance, other tubes are often damaged

    when the boiler operate for quite some time. When the tube damage is more than one and

    affect the water gauge losing water level, the boiler shall be shut down in normal mode. The

    purpose is to prevent all equipment from suffering sudden temperature change.

    Low water level, various measures shall be taken to make water level approach the

    normal level until the boiler is fully cooled down and allowed for drainage.

    When leakage of superheater or reheater components happens, it shall be analyzed as

    soon as possible. The boiler shall be shut down in normal mode.

    The above information is only for suggestion, and cannot take the place of the correct

    judgment of the stokers responsible for operating these equipment.

    Bear in mind that prolonging the operation of the tubes with leakage may cause the

    damage to adjacent tubes and increase maintenance works, exceeding the former short scope

    of maintenance.

    9.13 Furnace explosion

    Furnace explosion is usually result of the following conditions:

    1)

    Unburned fuel accumulates in the furnace due to incomplete combustion.

  • 7/25/2019 Boiler Manual 3x135MW

    34/61

    Instruction For Boiler Operation 2305-1-8603 P 34/61

    4) It is absolutely unallowable to ignite the oil burner when the ignition energy source

    needed is lost. Ensure that the air in air atomization oil gun is dry, do not use heavy

    oil/mechanical atomization oil gun for boiling out, ignition and boiler warm-up, while

    light oil/ air atomization or heavy oil/steam atomization oil gun is preferred.

    5) Prior to any startup and during the normal operation, inspect the functions of the furnace

    safety supervision system regularly, including interlock, tripping, etc.

    6) During the downtime of the furnace, regulate, inspect and maintain the furnace safety

    control system thoroughly.

    9.14 Fly ash wear

    Fly ash wear refers to the wear of the residual ash particles carried over in the gas to the

    metal surfaces. Wear normally occurs in local zones with high gas speed. The wear level is

    related to the ash content of the fuel (quantity and component). Firing coal with high wear

    characteristics and high ash content makes boiler wear a main problem.

    Caution: Wear usually occurs in: the end and bend of economizer tube and

    low-temperature superheater and around soot blowing area, gas duct and induced draft fan

    (fan blade and shell).

    The boiler design parameters are based on conservative mean gas velocity and normal

  • 7/25/2019 Boiler Manual 3x135MW

    35/61

    Instruction For Boiler Operation 2305-1-8603 P 35/61

    section of superheater and reheater panel where water cannot be drained, and measures shall

    be taken to prevent getting frozen.

    Before entering the steam drum, make sure that all the valves in the steam drum

    connection pipes are closed tightly (feed water, auxiliary steam, dosing pipe, blow-off,

    drainage, sampling, level gauge drainage, etc.). Open the manhole cover to inspect the

    tightness and cleanliness of the interiors of the steam drum. Inspect the steam drum for

    corrosion and surface pit. Oxidized pit is a common form of corrosion, and normally occurs

    in the steam drum above the normal water level, and sometimes in the tubes and lower

    headers. Open sufficient number of hand hole covers in the various headers of the water wall

    to remove the dirt.

    Check the heating face of the preheater for cleanliness. If there is corrosion, it should

    occur in the cold end part of the preheater, especially in the places where ash and filth tend

    to accumulate.

    Inspect the gas side thoroughly and clean it as necessary. Check if the soot blower is

    deflective. Inspect the equipments such as coal spreading trough, igniter, oil gun, scanning

    air fan, connection rod and air door for cleanliness and damage, and carry out operation and

    flexibility inspection. For the FSSS system, inspect and test the control valve, relay,

  • 7/25/2019 Boiler Manual 3x135MW

    36/61

    Instruction For Boiler Operation 2305-1-8603 P 36/61

    4) Cold boiler shall not be switched to dry type corrosion prevention. If it is necessary,

    ignite and raise the pressure to 30% of the rated pressure and then reduce the pressure.

    Adopt the afterheat drying method for the maintenance.

    9.16.2 Maintenance method

    Select the maintenance method according to the maintenance principle. The

    maintenance and operation can be implemented depending on the specific conditions of the

    power plant with reference to the applicable specifications of the power authorities.

    9.16.3 Freezing prevent for boiler

    The freezing prevention measures shall be checked before winter begins. No pipe is

    allowed to be bare. Anti-freezing and heating devices for each part of pipeline proper shall

    be put into operation. Heating tubes of fuel line are in operation whole year and cannot be

    overhauled in winter. Water in gauge pipe shall be drawn off. Hole door and damper of spare

    boiler shall be closed, and measures shall be taken to prevent cold air from entering into the

    boiler in overhaul.

    In winter, during the shutdown of boiler, adopt dry-type maintenance as can as possible,

    and air heater shall be put into use when the wall temperature of superheater is below

    20.

  • 7/25/2019 Boiler Manual 3x135MW

    37/61

    Instruction For Boiler Operation 2305-1-8603 P 37/61

    10.2 Preparation before boiler startup

    10.2.1 Inspection and cleaning before boiler startup

    Before initial ignition and every cold startup or after service of the boiler, the interior

    and exterior of furnace shall be inspected and cleaned. And all foreign maters shall be

    removed completely from the pressure parts, all pipes and conduit tubes, which may limit

    the normal expansion of the boiler, shall be removed. All person shall leave, and all doors

    and openings shall be closed. Check whether the indication of the boiler drum water level

    gauge is consist with the reading of local glass water level gauge, whether there is any block

    at air distribution boards of the furnace and material-returning machine, and inspect and start

    the atomization nozzle of the burner. And all these check shall be prepared by the

    departments which is in charge of operation. Be familiar with the startup and operational

    procedures for boiler and auxiliary machines.

    10.2.2 Steam pipeline purging

    For a new boiler or a boiler the main pressure parts of which has been repaired, the

    purging of main steam pipeline and reheating steam pipeline shall be done before startup to

    remove the rust and foreign matters in order to avoid the damage ti turbine. The purging of a

    new boiler shall be done after pickling and before the setting of drum and reheater safety

  • 7/25/2019 Boiler Manual 3x135MW

    38/61

    Instruction For Boiler Operation 2305-1-8603 P 38/61

    10.2.5 Filling bed materials into boiler

    Before the CFB boiler is started, inert substances (appropriate sand particles or CFB

    bed ash) are loaded into the furnace as bed materials. Used CFB bed ash is optimal due to its

    excellent fluidization features. To ensure appropriate heat transfer and system insulation,

    sufficient bed materials must be introduced. Each boiler needs about 200t bed materials

    (including the furnace and material-returning machine). The particle size of the bed materials

    loaded shall meet the particle size limits allows by the design. If no ash is unloaded from the

    system or if the bed materials exist before the operation, no further loading is needed.

    10.3 Cold/warm-state startup

    When the turbine high pressure rotor probe temperature is lower than 100, or when

    the boiler starts up in cold state with no pressure, it is called cold-state startup. When the bed

    temperature (the average temperature shown in the middle-level thermocouple) is lower than

    680, coal cannot be put into the furnace directly; instead, it is necessary to purge the

    furnace according to the cold-state startup mode and then to put the startup burners into

    service to increase the be bed temperature. The startup mode in such state is called

    warm-state startup. In case of cold-state or warm-state startup, the furnace must be purged.

    Only after the purging is completed can the startup burners be put into service. After the

  • 7/25/2019 Boiler Manual 3x135MW

    39/61

    Instruction For Boiler Operation 2305-1-8603 P 39/61

    10.3.2.1 Starting of induced draft fan

    Induced draft fan is the first air fan in circulating fluidization air and gas system during

    boiler start-up. Before the induced draft fan is started, its inlet baffle is regulated to the

    minimum position to avoid over-current of the motor of the induced draft fan during the

    startup. After the induced draft fan is started, check the outlet baffle which shall be open,

    note that the vibration indication value of the air fan bearing, the voltage and current values

    and the temperature should be within the specified range. Open the vane control baffle at the

    inlet of the induced draft fan slowly. Put the furnace vacuum (separator outlet) control to

    automatic. Monitor the furnace pressure. Subsequently, the air volume of the induced draft

    fan will regulate the control baffle automatically for operation, maintaining appropriate

    furnace pressure at the outlet of the combustion chamber.

    If tripping or downtime of induced draft fan for any reason occurs during boiler start-up,

    primary air fan and secondary air fan shall be shutdown.

    10.3.2.2 Starting of high-pressure fluidization air fan

    During boiler start-up, after the induced draft fan is started, start the high-pressure

    fluidization air fan and check the air volume of every chamber of the material returning

    valve.

  • 7/25/2019 Boiler Manual 3x135MW

    40/61

    Instruction For Boiler Operation 2305-1-8603 P 40/61

    out. The furnace purging air volume shall, as a minimum, be more than 30% of the total air

    volume under the rated load. For the detailed purging steps when the boiler is started up or

    shut down, refer to the boiler operational procedures provided by FSSS suppliers.

    10.3.4 Boiler ignition startup and temperature/pressure raising

    Before the ignition of startup burner, cold/warm-state boiler shall have periodic purging

    according to the permissive ignition condition of start-up burner.

    1) Electrify the electrostatic precipitator

    2)

    Start up the induced air fan.

    3)

    Put the furnace pressure control to automatic, and keep the furnace pressure at -125Pa.

    4) Start up the high-pressure fluidization air fan, ensure that there is at least one

    high-pressure fluidization air fan under operation.

    5) Start up the secondary air fan.

    6)

    Start up the primary air fan, ensure that there is at least one primary air fan under

    operation.

    7) Put the boiler air flow to automatic. Adjust the set value of total air flow to be no less

    than 30% of the air flow at full load. Inspect all equipment until they meet furnace

    purging. Control the primary, secondary air volume at 50% of air volume at rated load.

  • 7/25/2019 Boiler Manual 3x135MW

    41/61

    Instruction For Boiler Operation 2305-1-8603 P 41/61

    13) Along with the increasing furnace temperature, the temperature difference between

    material-returning machine and upper furnace shall be kept with 38, in order to

    prevent the damage of heat insulating material of cyclone separator and material

    returning machine. When the temperature of material-returning machine is 38 or

    much lower than upper furnace, primary air volume shall be added as needed to reduce

    temperature difference.

    14) When the steam drum pressure achieves 0.17MPa, close the steam discharge valve and

    vent valve in the boiler drum connection pipe.

    15)

    Along with the increasing boiler drum pressure, regulate the drainage of the superheater

    outlet header gradually or start other discharge valves or drainage valves. During the

    startup, sufficient steam flow must be maintained to remove the condensate on the

    superheater components.

    16) Blow the boiler off as necessary during boiler warm-up. Maintain the water level within

    the visible range during the blow-off.

    17)

    Maintain the water level of boiler drum at normal valve, and inspect the concentration

    and composition of boiler water as needed, to maintain qualified boiler water condition.

    18) Before the condenser forms vacuum, make sure that the exhaust valves and drain valves

  • 7/25/2019 Boiler Manual 3x135MW

    42/61

    Instruction For Boiler Operation 2305-1-8603 P 42/61

    1. Temperature of main steam or reheat steam pipelines suddenly drops without rhyme or

    reason.

    2.

    Steam line vibrates and causes water shock.

    3. Abnormal vibration and expansion reading record shown in turbine monitoring

    equipment.

    Operating personnel shall take necessary measures to prevent water from entering and

    damaging the turbine. Refer to the specification provided by turbine manufacturer.

    21)

    When bed temperature (average temperature of middle-level thermocouple) achieves

    575, the first coal feeder can be started manually to load coal at the minimum rate.

    After coal is loaded, observe the variation of bed temperature. When the bed

    temperature rises gradually while the oxygen quantity decreases continuously, it can be

    identified that the coal is in combustion. To spread the fuel evenly on the bed face,

    firstly load coal through the middle coal feeding tube. Now attention shall be paid to the

    air quantity in the coal feeding tube. If the bed pressure is low and the air quantity is

    small, the dampers in the two sides can be turned down appropriately. However, in the

    beginning when coal is loaded, increase or decrease gradually depending on the

    combustion conditions in the furnace. For further heating and temperature rising, follow

  • 7/25/2019 Boiler Manual 3x135MW

    43/61

    Instruction For Boiler Operation 2305-1-8603 P 43/61

    boiler when the bed temperature(average temperature measured by the lower thermocouple)

    is more than 650. If the bed temperature is higher than the allowable coal feeding

    temperature after the fan is started, it is not necessary to purge the furnace or to put the

    startup burners into operation. After feeding coal directly and igniting with the coal feeder at

    the minimum rotary speed, the boiler can be brought to the full load rapidly. It is also not

    necessary to consider the limit in temperature rising rate for the wear-resistant refractory

    materials in the furnace. This is because there is quite high accumulation of heat in the

    furnace and cyclone separator in this time.

    10.5 Regulation during normal operation of boiler

    The boiler will be put to automatic control during operation, however opertaing

    personnel shall pay attention to the operating condition of the unit to ensure the safety and

    economics of boiler operation and to the control of emmssion in fuel gas. Steam flow,

    temperature and pressure parameter of superheater and reheater shall be kept within the

    allowable range of normal operation.

    10.5.1Regulation of boiler load

    The regulation of boiler load is mainly achieved by changing the coal feeding quantity

    and the corresponding air volume. When the load increases, increase the air volume firstly

  • 7/25/2019 Boiler Manual 3x135MW

    44/61

    Instruction For Boiler Operation 2305-1-8603 P 44/61

    maintained. However, because the bed temperature is restricted by multiple factors, the

    variation amplitude is limited.

    10.5.2 Regulation of bed temperature of boiler

    The design value of the bed layer temperature of the boiler is 892 under the rated

    load. Considering the load variation and the requirements in other aspects, the bed layer

    temperature is controlled at 850~910. When the bed temperature exceeds this range, it

    must be regulated in time.

    Regulate the bed temperature by changing the ratio of primary air to secondary air.

    When the primary air volume is increased or the secondary air volume is reduced, the bed

    temperature will decrease. Conversely, the bed temperature will increase.

    By increasing the quantity of bed materials to improve the circulation of the materials,

    the bed temperature can be increased. By increasing the slag discharge quantity to reduce the

    bed pressure and the quantity of bed materials, the bed temperature will rise.

    If the mean size of the bed materials is excessively large, relatively speaking, the

    useable materials that can participate in the internal and external circulations of the boiler

    will decrease, causing the boiler to operate at relatively high bed temperature. By increasing

    the slag discharge quantity, removing the bed materials with larger particle size and adding

  • 7/25/2019 Boiler Manual 3x135MW

    45/61

    Instruction For Boiler Operation 2305-1-8603 P 45/61

    10.5.4 Regulation of steam temperature

    Primary and secondary spray type desuperheater are set respectively between platen

    superheater cold section, platen superheater hot section and high-temperature superheater in

    superheater system, to regulate steam temperature, primary for coarse control and secondary

    for fine tuning.

    Reheater regulate steam temperature mainly by gas damper, supplemented by

    emergency water spray device.

    The steam temperature is regulated with water spray. The operators shall pay close

    attention to the water spray quantity and the steam temperature before and after water spray

    to ensure that the desuperheated steam temperature should be higher than the saturation

    temperature under such pressure by 11.

    10.5.5 Control of SOx emission quantity

    If the control of SOx emission quantity is not needed, please skip this section.

    The SOx emission quantity is normally controlled by controlling limestone feed rate

    automatically and manually, i.e. to increase or decrease the mole ratio of calcium and sulfur.

    However, many other factors like bed temperature, limestone granularity will affect the

    desulfurization efficiency of a CFB boiler.

  • 7/25/2019 Boiler Manual 3x135MW

    46/61

    Instruction For Boiler Operation 2305-1-8603 P 46/61

    the nitrogen oxides generated from the organic nitrogen compounds in the fuel which are

    oxidized in the combustion process. For the fluidized bed boiler, the NOx emission quantity

    is controlled through control of bed temperature and segmental combustion.

    When the bed temperature is controlled in 790~900, the NOx emission quantity is the

    lowest.

    The primary/secondary air ratio affects the NOx emission. While the bed temperature

    and the normal combustion in the furnace are guaranteed, regulating the primary/secondary

    air ratio within a certain range can bring the NOx emission to a relatively low level.

    10.5.7 Protection of reheater

    Turbine bypass shall remain hot stand-by during boiler normal operation, in order to

    protect the reheater heating surface when unexpected accidents such as turbine tripping

    happen. CFB boiler is different from conventional PC boiler, when accidents such as turbine

    tripping happen and cause MFT, huge heat storage still exists in the furnace and the

    temperature is high in the furnace, even higher than the anti-oxidation temperature of tube

    material. Therefore, bypass is needed to start up to make a certain amount of steam flowing

    through superheater and reheater to cool the heating surface.

    10.5.8 Re-fluidization of bed materials

  • 7/25/2019 Boiler Manual 3x135MW

    47/61

    Instruction For Boiler Operation 2305-1-8603 P 47/61

    5) Recover the normal control.

    10.5.9 Use and maintenance of bed temperature thermocouple

    Bed temperature is the average temperature of each thermocouple at different place of

    the bed. If the temperature of a thermocouple differs by more than 170from average

    temperature, the temperature will not be included in the calculation.

    Bed temperature thermocouple passes through wear-resisting material layer for about

    150mm. If the length is exceeded, the wear will be increased and the service life will be

    shortened.

    10.5.10 Maintenance of bed temperature measuring equipment

    Bed temperature measuring equipment is different from conventional pressure

    measurement. Purging air shall be arranged, because pressure measuring point and pressure

    measuring pipeline can be easily blocked by fluid bed material.

    In order to remove the accumulated bed material at pressure measuring hole, purging

    shall be continuous. It is realized by zero transferring at site.

    Instruction: Pressure measuring holes shall be inspected on by one for blockage before

    boiler is put into operation. Because of the error of construction, the distance between each

    hole and air distributor may deviate from design location and causes large pressure

  • 7/25/2019 Boiler Manual 3x135MW

    48/61

    Instruction For Boiler Operation 2305-1-8603 P 48/61

    furnace temperature drop curve.

    Steam temperature drop speed shall be in line with the requirements of turbine

    manufacturer.

    Steam temperature control, combustion control and water feeding control can keep

    using automatic way until manual way is better, change into manual way.

    Caution: During and after shutdown, carefully prevent water from entering into main

    steam pipeline, hot reheat pipeline and cold reheat pipeline, in order to prevent the damage

    to turbine in future restart. Water may come from:

    1Overflow into superheater from drum because of high water level.

    2Enter into superheater from desuperheater because of desuperheating control

    valve open or leakage.

    2) Reduce the coal feeding quantity

    When the middle-level thermocouples show that the temperature is near 680, put the

    startup burners into service. Control the boiler reducing rate according to the shutdown curve.

    When the middle-level thermocouples show that the temperature is below 680 without

    startup burners running or when startup burners is in operation and the middle-level

    thermocouples temperature is lower than 630, coal feeding must be stopped. Once coal

  • 7/25/2019 Boiler Manual 3x135MW

    49/61

    Instruction For Boiler Operation 2305-1-8603 P 49/61

    8) If the boiler to be emptied, boiler water temperature shall be below 90 before

    drainage.

    9)

    When an appropriate operating temperature is realized for boiler shutdown, continue to

    purge the furnace, cyclone separator, material-returning leg and material-returning

    machine for around 30mins to protect the refractory materials, then shut off the air fan.

    10)

    The stop subsequence of fans: primary air fan-- secondary air fan-- induced air

    fan--high-pressure fluidized air fan.

    10.6.2 Normal boiler shutdown to hot standby

    Boiler shutdown time is short (below 8 hours) and certain pressure and temperature are

    maintained. Furnace bed temperature shall be kept higher than the allowable temperature of

    pulverized coal ignition during operation as far as possible. The pressure of superheater

    pipeline shall be reduced to an expected value, and it shall be kept by using superheater

    outlet exhaust valve or reheater protection system.

    The procedure similar to that for normal shutdown to cold state shall be observed

    except for the following conditions:

    With the decrease of unit load, do not lower the drum pressure. The pressure decrease

    rate shall be much smaller than the rate of normal boiler shutdown. Referring to the

  • 7/25/2019 Boiler Manual 3x135MW

    50/61

    Instruction For Boiler Operation 2305-1-8603 P 50/61

    Under the condition that the coal powder ignition is allowed, maintain the bed

    temperature as high as possible.

    4)

    Turn off the secondary air fan when the gas temperature of cyclone separator is lowered

    to 538. Continue with the purging with high-pressure fluidization air fan for 10

    minutes to remove the combustible gas in the material returner and the solid substances

    in the cyclone separator, material returner and material-returning leg. Then turn off the

    induced draft fan and close the baffles in all the air ducts to minimize the heat loss in the

    furnace.

    5)

    The boiler can be re-started in hot-state or warm-state mode depending on the bed

    temperature.

    10.7 Slag-cooling system

    There are slag notches at the bottom of the furnace. Bottom slag enters into slag cooler

    through slag notches, and is discharged after being cooled. Discharge quantity is controlled

    by variable frequency motor speed, and inlet quantity is controlled by the pressure

    difference between the inlet air pressure of hot primary air chamber at the bottom and

    furnace outlet air pressure. Slagging begins when bed pressure is beyond 13.5Kpa

    (tentative, the specific value is determined after site commissioning).

  • 7/25/2019 Boiler Manual 3x135MW

    51/61

    Instruction For Boiler Operation 2305-1-8603 P 51/61

    6) Limestone system doesnt run normally.

    Countermeasures:

    1)

    Inspect the bed temperature thermocouples;

    2) Check if the operation and control of the coal feeder are normal;

    3) Distribute the air reasonably, and regulate the primary-secondary air ratio;

    4)

    Adjust the particle size of the coal fed into the furnace;

    5) If necessary, increase the slag discharge quantity and add bed materials of appropriate

    particle size.

    11.2 Excessively high or low bed pressure

    Phenomenon:

    1) Excessively high or low display of CRT interface; Excessively high or low display of

    bed pressure;

    2)

    Bed pressure high or low alarm;

    3) Severe increment of slag discharge load of slag cooler, or slag discharge almost stopped;

    4) Excessively high or low pressure at bottom of air box.

    Cause:

    1)

    Bed pressure measurement failure;

  • 7/25/2019 Boiler Manual 3x135MW

    52/61

    Instruction For Boiler Operation 2305-1-8603 P 52/61

    1) In case of slight cracking or weld leakage, hiss of steam can occur and the feed water

    flow increases slightly;

    2)

    In case of severe conditions, obvious popping and steam spraying sound appears at the

    tube cracking place, the negative pressure in the furnace turns positive, the feed water

    flow becomes abnormally higher than the steam flow, and keeping of water level

    becomes difficult in severe case.

    3) Atomization phenomenon occurs in the non-tight boiler wall places;

    4)

    In severe case, the current of the induced draft fan increases and white steam is emitted

    from the chimney;

    5) The bed temperature and the temperature at the inlet/outlet of the cyclone separator

    decrease.

    Cause:

    1)

    The quality of boiler water and feed water exceeds the standard for long term, causing

    scaling in the tubes, increment of local thermal resistance and over-temperature;

    2) The water circulation is not good, resulting in local over-temperature;

    3) Unqualified tube material, poor welding quality, or severe wear of external wall of

    tubes;

  • 7/25/2019 Boiler Manual 3x135MW

    53/61

    Instruction For Boiler Operation 2305-1-8603 P 53/61

    2) The furnace vacuum reduces or turns positive, and the pressure of the superheated steam

    decreases.

    Cause:

    1) Scaling on the inner wall of the tube or blockage of the tube with foreign materials,

    resulting in deteriorated heat conduction;

    2)

    Wear of outer wall of tubes, or high-temperature corrosion;

    3) The steam temperature or wall temperature exceeds the limit for long term;

    4)

    Unqualified tube material, improper welding quality, or improper steam soot blowing.

    Countermeasures:

    1) If the tube blasting is not severe, it is allowed to operate for a certain period. However,

    reduce the load appropriately and prepare for shutdown.

    2) In case of severe tube blasting;

    1.

    With the induced draft fan running, control the bed temperature decreasing rate not

    to exceed the specified value;

    2.Maintain small quantity of feed water and keep normal water level;

    3.Proceed with the other operations as per the normal boiler shutdown procedure.

    11.5 Coking on bed surface

  • 7/25/2019 Boiler Manual 3x135MW

    54/61

    Instruction For Boiler Operation 2305-1-8603 P 54/61

    3) If it the condition does not improve after the regulation, shut down the boiler

    immediately.

    11.6 Power interruption of system

    Phenomenon:

    1) The water level in the steam drum is relatively low or is invisible;

    2)

    Collapse of the bed materials in the furnace bed face or in the bed face of the material

    returning valve;

    3)

    Power interruption causes all the auxiliary machines to stop.

    Countermeasures:

    1) Close the main steam valve and open the atmosphere vent valve of the superheater.

    Avoid tripping of the safety valve as long as possible. Control the steam flow at

    approximately 2kg/s;

    2)

    Open the connection between the drainage of the economizer and the concentrated

    downcomer so that the water of the economizer could be supplemented into the water

    wall;

    3) Because of the high heat accumulation in the boiler, open the baffles of the various air

    ducts to reduce the temperature level in the boiler at the maximum speed;

  • 7/25/2019 Boiler Manual 3x135MW

    55/61

    Instruction For Boiler Operation 2305-1-8603 P 55/61

    Countermeasures:

    1) Firstly, compare the indication conditions of all the level gauges to judge the

    truthfulness of the water shortage accident and the water shortage extent;

    2) If relatively severe water shortage is caused by severe failure of electrical equipment,

    judge quickly and request for instructions for emergency shutdown;

    3)

    When water shortage is not serious, generally, there is no failure which may affect the

    operation of boiler, such shortage is caused by improper operation probably. Water

    supply shall be enhanced by manual operation to restore normal water level.

    11.8 Water fullness accident

    Phenomenon:

    1) Water level is invisible at the sight glass of the level gauge, and the boiler water

    becomes dark;

    2)

    The water level alarm gives high-level alarm signal;

    3) The superheated steam temperature drops and the salt content of the steam increases;

    4) The feed water flow becomes higher than the steam flow suddenly.

    Cause:

    1)

    The operators omits in monitoring the water level;

  • 7/25/2019 Boiler Manual 3x135MW

    56/61

    Instruction For Boiler Operation 2305-1-8603 P 56/61

    In case of water attack in the steam pipeline, start the drainage valve of the superheater

    system. Drain sufficiently and vent the remaining air out of the pipeline. For the feed water

    pipeline, stabilize the water pressure and eliminate the air.

  • 7/25/2019 Boiler Manual 3x135MW

    57/61

    Instruction For Boiler Operation 2305-1-8603 P 57 / 61

    ,

    THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION

    OF SBWL..

    12 Appendix

    12.1 Figure 1 Boiler dry-off heating/cooling rate

  • 7/25/2019 Boiler Manual 3x135MW

    58/61

    Instruction For Boiler Operation 2305-1-8603 P 58 / 61

    ,

    THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION

    OF SBWL..

    12.2 Figure 2 Cold-state startup curve

  • 7/25/2019 Boiler Manual 3x135MW

    59/61

    Instruction For Boiler Operation 2305-1-8603 P 59 / 61

    ,

    THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION

    OF SBWL..

    12.3 Figure 3 Warm-state startup curve

  • 7/25/2019 Boiler Manual 3x135MW

    60/61

    Instruction For Boiler Operation 2305-1-8603 P 60 / 61

    ,

    THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION

    OF SBWL..

    12.4 Figure 4 Hot-state startup curve

  • 7/25/2019 Boiler Manual 3x135MW

    61/61

    Instruction For Boiler Operation 2305-1-8603 P 61 / 61

    ,

    THIS DRAWING OR DOCUMENT BELONGS TO SBWL AND MAY NOT BE REPRODUCED OR DISCLOSED TO ANY THIRD PARTY IN ANY FORM WITHOUT THE PRIOR WRITTEN PERMISSION

    OFSBWL

    12.5 Figure 5 Shutdown curve