blossom street, e1...blossom street warehouses structural method statement november 2015 100 st john...
TRANSCRIPT
-
blossom street, e1blossom street Warehouses structural method statement
november 2015
-
100 St John Street London EC1M 4EH
T +44 (0)20 7250 7777
F +44 (0)20 7250 7555
www.akt-uk.com
NOTE: UNDERPINNING OF EXISTING BLOSSOM
STREET WAREHOUSES
Project Name Blossom Street Project No. 3461
Rev: 04 Date 19/11/2015
PURPOSE
This note has been prepared to accompany the planning addendum for the retention of the
existing Blossom Street warehouses no. 12-13. These two buildings will now be retained as
existing, where as the previous application involved re-setting the floor levels. In line with the
previous planning application and extant scheme, the façade of numbers 14-15 Blossom Street
will also be retained.
As with the previous application, it is proposed to lower the level of the basement slab in the
warehouses to provide adequate head height in the basement floor. Neighbouring works adjacent
to the rear of the warehouses also involve the excavation of a lower basement level. In order to
carry out these excavations safely, without undermining the existing footings, it is necessary to
underpin all existing vertical load bearing structure and façade being retained. The main load
bearing elements of the warehouses are the masonry walls, façades and the cast iron columns.
This revised scheme retains more of the existing structure at basement level therefore the extent
of underpinning required has grown proportionally. Underpinning brings the level of the base for
the existing footings down to a lower level than the proposed excavations in proximity so that the
stability of the footings is maintained. It is carried out in a hit and miss sequence, in small sections
typically 1m long, using mass concrete which is quick to place so that the stability of the existing
masonry above can be maintained during the works.
This note sets out the assumed method for underpinning in the preparation of the permanent
works design. The extent of the works will be developed during the following design stages and
the final method statement will be prepared by the contractor.
ASSUMED METHOD
- Confirm locations and type of incoming services that may be affected by the works, get any
permissions required and carry out disconnection before commencing underpinning works
- Monitoring of neighbouring/retained structures so be set up and initial readings taken
before commencing works
- Underpinning to be carried out in a hit and miss sequence of 1 in 5 for sound supported
structure above, this may be reduced to 1 in 7 for heavily loaded structure or weak cracked
wall. It is proposed to adopt 1 in 5 here, alternative to be proposed by the contractor.
- Underpinning width to match existing footing width unless specified otherwise.
- Underpinning to be carried out in 1m lengths.
- Depth of underpinning required will be developed during the next design stage considering
the depth of neighbouring excavation required. It is anticipated that this will not be more
that 2m therefore the works can be carried out in single pins. Should site conditions require
a depth of more than 2.5m the contractor may wish to carry out underpinning in 2 layers.
-
100 St John Street London EC1M 4EH
T +44 (0)20 7250 7777
F +44 (0)20 7250 7555
www.akt-uk.com
- Excavate block and work space together. Temporary stability of structure and retained
ground during underpinning works is the contractor’s responsibility, propping to be
provided.
- Remove or compact loose material.
- Protect the area with a cover of 50mm thick concrete if there will be a delay of more than 4
hours between completion of excavating and casting of concrete underpinning.
- Provide front shutter, dowels, and protection to any services passing through underpin
where required.
- Cast pin in one lift leaving a gap for packing/pinning up beneath existing foundation.
- On completion of concrete curing period, hard pack gap between underpinning block and
existing foundation. Allow packing to cure before commencing excavation for next
sequence of pins.
- Minimum period for curing of 24 hrs between casting underpin and pinning up. Minimum
period for curing of 24 hrs between pinning up and commencement of excavation for next
sequence of underpinning. Extended curing periods to be allowed for inclement weather.
- Shear connection to be provided between underpinning blocks using reinforcement dowels
- Should any perched ground water be encountered during the works the contractor must
take adequate measures to exclude the water from excavations and stop flow. Depending
on flow rate proposals may include tight boarding where flow rates are low, de-watering, or
grouting of the gravels where flow rates are higher, contractor to send proposals.
A detailed method statement will be prepared and submitted to the Structural Engineer by the
contractor prior to any works commencing on site.
EXAMPLE OF AN UNDERPININGSEQUENCE ON PLAN
SEQUENCE NUMBER OF PINS BEINGEXCAVATED SIMULTANEOUSLY
UNDERPINNING WIDTHTO MATCH EXISTINGWALL FOUNDATION
EXISTING WALL
6 1 4 2 5 3 6 1 4 2 5 31 2 34 55
EXISTING INTERNAL LEVEL +17.500
EXTERNAL LEVEL VARIES
T.O.C. +17.00
630
TOOK’S COURT
TO MATCH EXISTING BOUNDARY WALL FOUNDATION
50mm BLINDING
+16.550
C ATION
B.O.C. +15.500
INTERNAL
B.O.C.
TYPICAL SECTION THROUGHUNDERPINNED WALL
MASS CONCRETEUNDERPINNING
-
Application Documents
Application forms
CIL Additional Information form
Addendum Planning Drawings
Addendum Design and Access Statement
Addendum Planning Statement
Replacement Environmental Statement I
Replacement Environmental Statement II(Townscape and Visual Impact Assessement)
Replacement Environmental Statement III
Replacement Environmental Statement Non-Technical Summary
Addendum Heritage Appraisal
Addendum Regeneration Statement
Energy Statement Update
Addendum Sustainability Statement
Addendum Transport Assessment
blossom street Warehouses structural method statement