blackout in sweden and eastern part of denmark 2003-09-23
DESCRIPTION
Blackout in Sweden and Eastern Part of Denmark 2003-09-23. Sture Lindahl 2003-1 0 - 05 Industrial Electrical Engineering and Automation [email protected]. The Nordel System. The Affected Region. Outage Cost. Interrupted power 5 000 MW Average outage time 4 hours - PowerPoint PPT PresentationTRANSCRIPT
Blackout in Sweden andEastern Part of Denmark
2003-09-23
Sture Lindahl
2003-10-05Industrial Electrical Engineering and Automation
Sture Lindahl, LTH/IEA 2
The Nordel System
Sture Lindahl, LTH/IEA 3
The Affected Region
Sture Lindahl, LTH/IEA 4
Outage Cost
• Interrupted power 5 000 MW
• Average outage time 4 hours
• Outage cost 50 SEK/kWh
• Total outage cost 1000 MSEK
Sture Lindahl, LTH/IEA 5
Consumption in Sweden
• Before outage 15 000 MW
• Winter peak 25 000 - 27 000 MW
• Section-4 power flow 2 200 MW
Sture Lindahl, LTH/IEA 6
Situation before Disturbance
Sture Lindahl, LTH/IEA 7
Generation Outages
G1 & G2
G1, G2 & G3
G1 & G2
Gx
Sture Lindahl, LTH/IEA 8
Transmission Outages
Sture Lindahl, LTH/IEA 9
The First Event (12:30)
• The nuclear unit Oskarshamn G3 was ramped down from 1 135 MW to zero because of a problem with a valve in the feed-water system.
• The ramping down of Oskarshamn G3 was initiated manually
• The reduction of power took about one minute
Sture Lindahl, LTH/IEA 10
The First Event (12:30)
G3
Sture Lindahl, LTH/IEA 11
The System Frequency
Frekvensstörning 2003-09-23 12:30:20 (CET) max: 50,022 Hz min: 49,670 Hz
49.650
49.700
49.750
49.800
49.850
49.900
49.950
50.000
50.050
0.0 50.0 100.0 150.0 200.0 250.0 300.0
Tid (s)
Fre
kven
s (H
z)
Oskarshamn G3kopplas bort
Frekvensregistrering SvK (Beckomberga 220 kV)
Bilaga 1 1(2)
Sture Lindahl, LTH/IEA 12
The System Frequency
Frequency in the South-Eastern Part of Sweden
49.5
49.6
49.7
49.8
49.9
50.0
50.1
0 10 20 30 40 50 60
Time [seconds]
Fre
qu
enc
y H
z]
Sture Lindahl, LTH/IEA 13
The Second Event (12:35)
• A disconnector in the 400 kV substation Horred failed (reason unknown) and caused a two-phase fault
• Correct clearing of the fault was initiated from the busbar protection
• The circuit breakers operated correctly
Sture Lindahl, LTH/IEA 14
R R RT
Var
mgå
ng
Bila
ga 3
Sture Lindahl, LTH/IEA 15
Damaged Disconnector
Sture Lindahl, LTH/IEA 16
Damaged Disconnector
Sture Lindahl, LTH/IEA 17
The Second Event (12:35)
Busbar Fault
Sture Lindahl, LTH/IEA 18
The Second Event (12:35)
Sture Lindahl, LTH/IEA 19
Voltage Level
Voltage Simpevarp Busbar A+B
0
100
200
300
400
500
0 60 120 180 240 300 360 420
Time [seconds]
Vo
lta
ge
[kV
]
Sture Lindahl, LTH/IEA 20
Voltage Level
Voltage Simpevarp Busbar D
0
100
200
300
400
500
0 60 120 180 240 300 360 420
Time [seconds]
Vo
lta
ge
[kV
]
Sture Lindahl, LTH/IEA 21
Voltage Level
Voltage Alvesta
0
100
200
300
400
500
0 60 120 180 240 300 360 420
Time [seconds]
Vo
lta
ge
[kV
]
Sture Lindahl, LTH/IEA 22
Voltage Level
Voltage Söderåsen
0
100
200
300
400
500
0 60 120 180 240 300 360 420
Time [seconds]
Vo
lta
ge
[kV
]
Sture Lindahl, LTH/IEA 23
Power Flow
Active (Real) Power Horred-Söderåsen
0
500
1000
1500
2000
0 60 120 180 240 300 360 420
Time [seconds]
Po
wer
[M
W]
Sture Lindahl, LTH/IEA 24
Power Flow
Active (Real) Power Horred-Tenhult
0
500
1000
1500
2000
0 60 120 180 240 300 360 420
Time [seconds]
Po
wer
[M
W]
Sture Lindahl, LTH/IEA 25
Power Flow
Active (Real) Power Horred-Kilanda
-1000
-500
0
500
1000
0 60 120 180 240 300 360 420
Time [seconds]
Po
wer
[M
W]
Sture Lindahl, LTH/IEA 26
Power Flow
Active (Real) Power Ringhals G3+G4
0
500
1000
1500
2000
0 60 120 180 240 300 360 420
Time [seconds]
Po
wer
[M
W]
Sture Lindahl, LTH/IEA 27
Tap Changers
TC-position Breared
0
5
10
15
20
25
30
0 60 120 180 240 300 360 420
Time [seconds]
Tap
Sture Lindahl, LTH/IEA 28
Tap Changers
TC-position Alvesta
0
5
10
15
20
25
30
0 60 120 180 240 300 360 420
Time [seconds]
Tap
Sture Lindahl, LTH/IEA 29
Tap Changers
TC-position Simpevarp
0
5
10
15
20
25
30
0 60 120 180 240 300 360 420
Time [seconds]
Sture Lindahl, LTH/IEA 30
Sture Lindahl, LTH/IEA 31
The System Frequency
Frekvensstörning 2003-09-23 12:35:00 (CET) max: 50,414 Hz min: 49,279 Hz
49.200
49.400
49.600
49.800
50.000
50.200
50.400
50.600
0.0 50.0 100.0 150.0 200.0 250.0
Tid (s)
Fre
kven
s (H
z)
Frekvensregistrering SvK (Beckomberga 220 kV)Horred fel 12:37:03Ringhals block 3 och 4 kopplas bort
Sammanbrott
Bilaga 1 2(2)
Sture Lindahl, LTH/IEA 32
The System Frequency
Frequency in the South-Eastern Part of Sweden
49.0
49.2
49.4
49.6
49.8
50.0
300.0 300.2 300.4 300.6 300.8 301.0 301.2 301.4 301.6 301.8 302.0
Time [seconds]
Fre
qu
enc
y H
z]
What we saw of the black-out
Voltages and frequency recorded on 23 September 2003 at
Chalmers
(Math Bollen, 24-9-2003)
Sture Lindahl, LTH/IEA 34
First a few words about the measurements.
These measurements were obtained by two different instrumentsat two different locations in our building.
a Medcal monitor connected to the wall-outlet in my office (singlephase). This monitor records min, mean and max every minute. Upon triggering a two-cycle sample of the waveform is obtained.
a Unipower monitor connected to the main busbar in our laboratory(three phases). This monitor records min, mean and max every minute. Upon triggering a 2.5-second record of the rms voltages is stored.
The clocks of the two monitors are not synchronous. The main voltagedip (12:35 according to SvK) had the following time stamps:Medcal: 12:41:06Unipower: 12:31:11
Sture Lindahl, LTH/IEA 35
Ställverk: Sags/SwellsRMS trend for sag/swell #67 at P3: 2003-09-23 12:31:11
U[V
]
Time
150
160
170
180
190
200
210
220
230
240
0,0 0,5 1,0 1,5 2,0 2,5
U1 U2 U3
0.5-cycle rms voltages during and after the main dip
normal dip due to two-phase-to-ground fault
oscillation points to instability!
time stamp: 12:31:11
Unipower
Sture Lindahl, LTH/IEA 36
Ställverk: Sags/SwellsRMS trend for sag/swell #68 at P1: 2003-09-23 12:31:17
U[V
]
Time
150
160
170
180
190
200
210
220
230
240
0,0 0,5 1,0 1,5 2,0 2,5
U1 U2 U3
rms voltages six seconds later
time stamp: 12:31:17
cause of dips is unclear.
Unipower
Sture Lindahl, LTH/IEA 37
Timeplot chart
2003-09-23 12:00:00,00 - 2003-09-23 19:00:00,00
CHA Freq
12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00
Hz
49.25
49.50
49.75
50.00
50.25
50.50
frequency recordings during the whole afternoon: the three curves showmaximum, minimum and average over each 1-minute period
the main disturbance around 12:30 minor disturbancearound 18:00
MedCal
Sture Lindahl, LTH/IEA 38
Timeplot chart
2003-09-23 12:20:00,00 - 2003-09-23 13:00:00,00
CHA Freq
12:20 12:25 12:30 12:35 12:40 12:45 12:50 12:55 13:00
Hz
49.25
49.50
49.75
50.00
50.25
50.50
This shows the frequency variations during the first disturbancein more detail
MedCal
the main dipwas recorded here
loss of Oskarhamn 3
loss of Ringhals 3+4
loss of South Sweden
frequency remains highdue to loss of load
Sture Lindahl, LTH/IEA 39
Recordings from Odensala
t/s0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
A400/kV
340
360
380
400
t/s0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
B400/kV
340
360
380
400
t/s0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
FL4 S4 P/GW
0,50
0,75
1,00
t/s0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
FL4 S4 Q/Var
0,000e+000
2,000e+008
4,000e+008
t/s0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
FREKVENS A400/mHz
0
250
500
t/s0 10 20 30 40 50 60 70 80 90 100 110 120 130 140
FREKVENS B400/mHz
0
250
500
Frekvensfall Frekvensstegring
Sture Lindahl, LTH/IEA 40
Voltage Restoration
• The 400 kV network was essentially restored after 1 hour
Sture Lindahl, LTH/IEA 41
Genopretningen minut for minut
12.38 Elkraft System forbereder at sætte spænding på hele højspændingsnettet
13.20 Elkraft System venter på, at Kyndbyværket starter
13.41 Vi får tilladelse til at koble os til Sverige – men kun med et meget lille forbrug (max. 200 MW)
13.46 Østdanmark kobler til Sverige. Højspændingsnettet er i gang
Sture Lindahl, LTH/IEA 42
Genopretningen minut for minut
13.54 Elkraft System giver tilladelse til, at en del af forbrugerne får strøm igen:
• Københavns Energi kan tilkoble forbrugere svarende til 50 MW
• NESA kan tilkoble forbrugere svarende til 50 MW
• SEAS kan tilkoble forbrugere svarende til 25 MW
• NVE kan tilkoble forbrugere svarende til 25 MW
Sture Lindahl, LTH/IEA 43
Genopretningen minut for minut
14.15 Første kraftværksblok kører igen (Kyndbyværket)
14.16 Svenska Kraftnät melder, at vi kun må trække 100 MW fra Sverige
14.31 Asnæsværket blok 5 forsøger at starte, men kan ikke. Asnæsværket blok 2 forsøges herefter startet
14.53 Stigsnæsværket blok 2 havarerer ved opstart
14.57 Gasturbine på Masnedø kommer i gang (55 MW)
Sture Lindahl, LTH/IEA 44
Genopretningen minut for minut
15.00 Københavns Energi får lov at give ekstra 10 procent af forbrugerne strøm
15.22 Gasturbine på Kyndbyværket kommer i gang
15.25 Yderligere 10 procent af forbrugerne hos SEAS tilkobles
15.29 Endnu en gasturbine på Kyndbyværket kommer i gang
16.42 Københavns Energi får tilladelse til at give DSB’s fjerntog strøm
Sture Lindahl, LTH/IEA 45
Genopretningen minut for minut
16.57 Systemet er stabilt nok, til at vindmøllerne gradvist kan tilkobles
18.18 En dieselgenerator på Kyndbyværket sætter ud
18.25 Asnæsværket blok 2 kommer i gang
18.33 Asnæsværket blok 5 havarerer ved opstart og er ikke kommet i gang endnu
19.05 NVE, NESA, KE og SEAS får tilladelse til at tilkoble resten af forbrugerne
Sture Lindahl, LTH/IEA 46
Conclusion
• Outage of 20% of Sweden
• Outage of 50% of Denmark
• Voltage restoration time 1 hour
• Load restoration was depending on start-up time of generating units
• Outage cost about 1 000 MSEK
Sture Lindahl, LTH/IEA 47
Additional Information
http://www.elkraft-system.dk/elkraft/dk/Nyheder.nsf
http//www.svk.se/
http://www.abebooks.com/