  • 8/11/2019 BL Schedule

    1/1

    Date: 8 19 2014

    Immediate Short term Wed

    sturc insp -> Thurs casting

    Sat scan all insp form (to request forms

    from RTO)lift delivery on 28th sept

    Substation preliminary inspection (Me to

    take notes of all the comments. (Wed,

    2.30 m

    Nparks to come @ (Wed, 9.30am)

    To ask LED lighting from Wei RongRead about technical meeting &

    submission attached

    Once receive color code as approval from

    Archie for our services color

    To confirm the PABX system with NTC GM

    Thurs 9am

    1 pm insp for 1st storey services @

    column to 2nd storeInsp GL1-3 (Wed) @ lvl 3

    this month to target to clear level 3 &

    level 4 CSD Li htin mock u Fri 7 m

    10am BCA come (all must sign

    CORETRADE)

    After skimming & painting (2week later/

    early Sept) Fire & Elec can start do their

    work

    GH to submit 1 trade foreman toda

    Read about safety procedure for

    excavation

    Date: 8 20 2014

    Immediate Short term 1.2m awhile then fast slo e to 1.5m

    Clarification date for NTC Energy

    Modelling

    Time: 2pm

    Venue: BCA office at Maxwell road

    Date: 28th Aug, 2014

    Inspection on penetration GL 15-22-> Wed

    sturc insp -> Thurs casting (cleared PT

    area

    Sat scan all insp form (to request forms

    from RTO)lift delivery on 28th sept

    Substation preliminary inspection (Me to

    take notes of all the comments. (Wed,

    2.30 m

    Nparks to come @ (Wed, 9.30am)

    Read about safety procedure for

    excavation !!

    Read about technical meeting &

    submission attached

    Once receive color code as approval from

    Archie for our services color

    To confirm the PABX system with NTC GM

    Thurs 9am

    GH to submit 1 trade foreman todaythis month to target to clear level 3 &

    Lighting mock up (Fri,7pm)

    Inspection later close to 4pm for pvc

    concealed pipe (write an email at 3pm toAfter skimming & painting (early Sept) Fire

    & Elec can start do their work

    to complete the schedule for substation

    take over

    remember to print out Ah Lim CET doc

    and certificates

    To hel Ms Lee submit stuff to H

    Date: 8 21 2014

    Immediate Short term Wed

    sturc insp -> Thurs casting (cleared PT

    area

    Sat scan all insp form (to request formsfrom RTO)

    lift delivery on 28th sept Lighting mock up (Fri,7pm)

    Read about safety procedure for

    excavation !!

    Read about technical meeting &

    submission attached

    Once receive color code as approval from

    Archie for our services color

    GH to submit 1 trade foreman todaythis month to target to clear level 3 &

    Inspection later close to 4pm for pvc

    concealed pipe (write an email at 3pm to

    arran e the ins ection ?

    After skimming & painting (early Sept) Fire

    & Elec can start do their work

    to complete the schedule for substation

    remember to print out Ah Lim CET doc

    and certificates

    To hel Ms Lee submit stuff to H

    Date: 8 22 2014

    Immediate Short term