Project Manager, Stephen Hunter, will be your first point of contact on site.
Your Site Contacts
You can contact him in office hours on:
07849 097 045
7 Merchant Court, Hebburn, NE31 2EX
Meet our Project Manager
Dear Resident,
Bishop Barrington School Kier Regional Building Scotland & North East
Issue 2 - July 2019
Site Update
Since our last communication, our site team have now fully established themselves in our site offices / welfare complex at the entrance to the site, off Woodhouse Lane. As we approach the school Summer break, the works are
progressing well and are on programme. The foundation
works, which comprised the installation of 172 piles,
reinforced concrete pile caps and ground beams, are now
complete and drainage works have commenced.
A “Project Commencement Ceremony” was held on site
on 4th July attended by the Department for Education,
Durham County Council staff, Local County Councillors,
Kier and representatives of the school staff and students.
You can contact him in office hours on:
07841 530 758
7 Merchant Court, Hebburn, NE31 2EX
If you have any concerns or
queries regarding the works
please feel free to contact us
Welcome to the second edition of our newsletter to
keep you informed of progress and key upcoming
works throughout the life of the project.
Site Manager, Peter Farnaby will be your second point of contact on site.
Meet our Site Manager
The next key construction element is the erection of the building’s steel frame. This is planned to commence in line with the start of the school summer break and will be largely complete by the time the school returns in September 2019. This will be followed by the installation of concrete upper floors, pre-cast concrete staircases and roofing works, prior to commencing the external envelope trades.
We appreciate its difficult for you to see how the works are progressing, so we have included below some photo’s of the works in progress:
What works will happen over the next 3 months?
• Foul and storm water drainage works. • New electrical supply connections to the
school and disconnection of redundant services, which currently run across the site.
• Erection of the steel frame / metal decking. • Concrete upper floors and pre-cast concrete
stairs. • Roofing works
• Structural framing works – to support the envelope treatments.
This Site is registered with the Considerate Constructors Scheme and we aim to minimise the impact of our operations on the local community.
Should you have any queries or concerns about the construction activities, please don’t hesitate to contact me.
Stephen Hunter, Project Manager
07849 097 045
Hours of Work Monday to Friday 8am to 6pm
Occasional Saturdays 8am to 1pm (External works) 8am to 5pm (Internal works)
Note: It is not proposed to carry out any works on Sundays or Bank Holidays!