Biogas Potential in Thailand
Renewable Energy Biogas/BiomassMade in Germany
Conrad Hotel, Bangkok9 September 2009
Sirikul PrasitpianchaiProject Manager
German Technical Cooperation (GTZ)
page 2
Sources
Industrial wastewater– Tapioca/Palm Oil/Ethanol– Food canning and process– Frozen Seafood
Agriculture wastewater– Pig/Chicken/Duck/Cow
Municipal Solid Waste (MSW)
page 3
Industrial Wastewater
Source: Chulalongkorn University, http://www.thaibiogas.com
Data: 2008Total factories Biogas systems No Biogas
1. Starch/Tapioca 86 60 26
2. Palm oil 49 22 27
3. Ethanol 24 11 13
4. Rubber 88 4 84
5. Food processing 66 26 50
Industry
page 4
Industry - Starch/Tapioca
2
5
19
7
1
4 4
13
23
7
1
12
0 01
0
32
002468
101214161820
100 150 200 250 270 300 350 400 500 >500
Capacity (Ton/day)
No. o
f fac
tory
W/ biogas No biogas
Starch/tapioca industry has high biogas technology penetration, nearly 70%. Remaining potential is in smaller factories(production capacity 100-200 Ton/day)Potential in tapioca wet cake
Source: Chulalongkorn University, http://www.thaibiogas.com
page 5
Industry – Palm Oil
1
4
10
5
2
9
4
12
20
02468
101214
<30 30 45 60 >60
Capacity (TFFB/hr)
No.
of f
acto
ry
w/ biogas No biogas
40% of Palm oil industry has biogas plantsPotential of EFB for biogas is being studied in GTZ Sustainable Palm Oil Project(Contact: [email protected])
Source: Chulalongkorn University, http://www.thaibiogas.com
page 6
Industry - Ethanol
3
6
2
0
2
54
2
01234567
25,000-100,000 101,001-150,000 150,001-200,000 200,001-500,000
Capacity (Litre/day)
No. o
f Fac
tory
W/ Biogas No Biogas
Source: Chulalongkorn University, http://www.thaibiogas.com
Existing biogas systems are nearly 50% of total potentialEthanol can be produced from cane molasses/cassava
page 7
Industry – Food&Beverage Industry
261
63140
78
185
96
208
5 18 26 3 22 3 30
50100150200250300
Meat processing
Canned fish
Frozen seafood
Aqua products processing
Fruit&Vegetable canning
Dried fruit
Bakery
No. o
f fac
tory
Total factory Potential
66 factories are identified as good potential for biogas production(gas volume > 400 m3)Majority of potential factories are in food canning and frozen seafood
Source: Chulalongkorn University, http://www.thaibiogas.com
page 8
Industry - Rubber
Technical barrier Need research cooperationMay need enforcement of environmental regulations on wastewater
0 02 1 1 0
19
5
13
27
12
7
0
5
10
15
20
25
30
0-300 301-500 501-1000 1001-3000 3001-5000 >5000
Ton/Month
No.
of F
acto
ry
W/ Biogas No Biogas
Source: Chulalongkorn University, http://www.thaibiogas.com
page 9
Agricultural Wastewater
Pig farm is most developed in biogas installation with 20% of potential. With government subsidy target, pig farms will reach 40% of potential in 2013Other farms still behind in biogas development due to technical, financial barriers, collection of sources, and competing use in other sectors
Chicken, 292
Buffalo, 169
Duck, 28
Dairy, 58
Pig, 480
Cow, 1131 mil m3/yr
mil m3/yrmil m3/yr
mil m3/yr
mil m3/yr
mil m3/yr
Installed biogas 89mil m3/yr
Source: Chulalongkorn University, http://www.thaibiogas.com
page 10
MSW and Domestic Wastewater
Good potential for CDM projectsMany landfill biogas projects are now being developed
MSW No. Biogas Potential (mil m3/year) No. (mil m3/year) No. (mil m3/year)
Municipality and Sub-district 7,948 1,218 2 3.5 7,946 1,215
Biogas in operation Remaining Potential
Source: Pollution Control Department, 2004
page 11
Investment Cost
Waste sources Baht/m3 biogas Baht/kWhDried fruit 0.33 0.28Tapioca 0.77 0.64Palm Oil 0.84 0.70Pig farm 0.96 0.80Starch 1.37 1.14Slaughter (pig) 2.65 2.21Paper 3.11 2.60Alcoholic beverage 3.52 2.93Beer 5.12 4.26Solid Waste 5.44 4.53Non-alcoholic beverage 7.19 5.99
Source: A Study on Biogas Potential, KMUTT, 2006
Cost of biogas systems depends on several factors. The above table shown average investment cost regardless of technology from field survey, interview, and secondary data from 190 systems in Thailand.- Only Initial Investment Cost- System life time 15 years- Overall biogas production
page 12
GTZ Biogas Project
Problems/barriers in Thai Biogas sector– Human resource: under qualified operators leads to
inefficient operation of systems/shut down– Lack of mutual agreement on standards– Lack of network for cooperation among several stakeholders
GTZ Biogas Project– Identify incentives/measures for impenetrate sub-sectors– Quality system for operator/planner and human resource
development
– Biogas network/association
Project period: 2 years (October 2009 – September 2011)
page 13
Biogas Network
Biogas Producers– Exchange of experiences– Leverage framework conditions
Research/Academic– Exchange of information and compilation of database– Cooperation on research and testing
Policy Makers– Agreement on standards and regulations
DIW, Ministry of Industry (safety standards)PCD, Ministry of Natural Resources and Environment (environmental standards), DEDE, Ministry of Energy (quality/performance standards)
– Cooperation on database of biogas systems
Private Companies– Contact point for products information– Access to market
page 14
Information Sources
Energy Research Institute (ERI)Chulalongkorn UniversityTel: 02 218 8096-8Website: www.thaibiogas.com, www.eri.chula.ac.th
Waste Utilization and ManagementPilot Plant Development and Training Institute (PDTI)King Mongkut's University of Technology Thonburi (KMUTT)Tel: 02 452 3456Website: www.pdti.kmutt.ac.th
Energy Research and Development Institute (ERDI)Chiang Mai UniversityTel: 053 942 007Website: www.erdi.or.th