bila spur report final
TRANSCRIPT
-
8/12/2019 Bila Spur Report Final
1/32
Pavement design of Heavy duty pavement of coal haul road in coalmines area Gevra Bilaspur
General: India is rich in natural resources and these resources are both superficial andunderneath the earth. While forest are the main superficial assets, minerals fuels
and precious metals constitute the assets underground. All these resources areuseful in building our life and hence continued efforts are being made to explore,extract and utilize these resources to a greater extent.
The fuel resources are of great importance as these help in extracting the potencyof other resources. Also there are vital re uisites industry, transport and po!ersectors. With this importance all the forms of fuels have commercial value, be itsolid "coal#, li uid "petroleum# and gas "natural gas methane#. It is for this reasonmining for these resources has been a ma$or activity at these region !here they areabundantly available. %any of the Indian states are the hubs of mining of coal,petroleum and gas. &har'hand, parts of (.). *rissa, +hattisgarh, and %adhya
)radesh are the production centers of coal.
Gevra cola mines area near ilaspur in %adhya )radesh is controlled andmanaged by -outh astern +oal /ields "- +0#. It is a ma$or coal production minebeing explored for huge uantities of coal in near future. The mining activitiesre uire a good road net!or' !ith satisfactory service to facilitate smooth movementof mining machines, dozers, excavators, haul truc's etc.
This is essential to maximise the production !ith increased efficiency in handlingthe activities. 1aul roads used for carrying overburden materials and coal transportroads need a uplift.
The Gevra mine area is comprised of t!o mining fields 2 Gevra and 3ipi'a. WhileGevra area has got a haul road, 3ipi'a is yet to get this road, for !hich the planninghas been made. The condition of the existing haul road and coal transport road isalso not good. -ince the - +0 is proposing to ac uire a fleet of hauling truc's of456 tonnes capacity, it is imminent to complete and upgrade the road net!or' tomeet the re uirement. It is !ith this bac'ground, - +0 had re uested +77I tocarryout the re uired studies and ma'e recommendations for the design of ne!road and betterment of existing haul road !ide their letter no.G%"4#8- +08 -)8466984494 dated ;64;69. The details of the coal field in bothGevra and 3ip'a area and road net!or' is sho!n in /igure and 4, respectively.
1.2 Objectives and Scope
The main ob$ective of the study is to design haul roads for these areas and ma'erecommendations. Thus, the scope included the follo!ing :
i# A preliminary site visit and discussions
1
-
8/12/2019 Bila Spur Report Final
2/32
ig 1! layout "ap of road net#or$ in Gevra coalmines area
2
-
8/12/2019 Bila Spur Report Final
3/32
ig 2! layout "ap of road net#or$ in %ip$a coalmines area
3
-
8/12/2019 Bila Spur Report Final
4/32
ii# /ield studies and sample collectioniii# 0aboratory evaluation of material samplesiv# Analysis of data and interpretationsv# 7eport !ith recommendations
1.& '(isting )oad *et#or$
The 3ip'a area has to develop the haul road, but the Gevra area has got a haulroad, !hich needs to be extended and improved. Thus both need a proper designand construction. In addition the existing coal transport road is poor in conditionand needs to be structurally and functionally upgraded. Thus, the study needed afocus on evaluation of subgrade soil8existing earth and available road buildingmaterials.
The existing haul road also has been made up of only layers of earth and stoneboulders added at different times. 3ue to heavy vehicle movement, the structure
gets affected repeatedly and this accumulated damage has rendered the road verypoor to meet the re uirements. The coal transport road !ith heavy and continuoustruc' traffic is also damaged by repeated loads and !ater that is being continuouslysprin'led to arrest the coal dust. It is therefore, immediately re uired to design,construct and improve these roads accordingly.
2. +',% +*-'S +G/ +O*S2.1 General
A field visit !as made to assess the situation by !ay of discussions !ith theconcerned officials of - +0 and visual inspection of existing condition. Test pits!ere cut and field density of granular layer and subgrade !ere ta'en. collection of
samples of materials !ere done .A number of field tests and surveys !ereunderta'en !ith a vie! to evaluate the present condition of roads and to determinethe uality of road construction materials used in construction of various pavementslayers, !hich included bituminous, granular and sub;grade. The field investigations!ere done to determine the structural ade uacy of the existing pavement, to findout the nature and extent of distress and to recommend appropriate measures forits rehabilitation. The various field studies that !ere underta'en during the courseof field visits are:
)avement condition assessment Test pit observations
Traffic volume studyThe detailed methodology adopted for carrying out the above activities in the field ispresented in the follo!ing sub;sections.
2.2 Soil Sample 0ollection-amples of the existing soil and fill material !ere collected from the site to betested for the follo!ing properties:
4
-
8/12/2019 Bila Spur Report Final
5/32
i. Atterberg; ? sho! vie! of test pit cutting in progress. 0ocation of test pit and density
measurements are given in Table
0ocation @ear !eigh
bridge in
3ip'a area
@ear border of
old 3ip'a and
Gevra
+orner of
+entral
7amp
+orner of ne!
approach haul
road
+oal
transport
road
&unction of
central and
south ramp)it no. 4 = 9 5/ield density 4.499 4. 99 +ould notdone
+ould notdone . >
+ould notdone
/ield
%oisturecontent
B.9 4.6 >.6
/ield dry
density4.69B .B4 .4?
2. raffic -olume and %ata
The haul road net!or' is expected to cater for routine traffic in addition to movementof 456 T capacity dumpers under the *perational areas for = ?66 repetitions peryear. The dumpers carrying coal generally move on the roads indicated in the layoutmay. The daily traffic of these dumpers are 46 vehicles per day and their payloadis generally in the range of 4=6 tons to 456 tons.
5
-
8/12/2019 Bila Spur Report Final
6/32
ig 1 ! -ie# of 0oal "ines
Photo 1 -ie# of open cast mines
Photo 2 /nother vie# of open cast mines
6
-
8/12/2019 Bila Spur Report Final
7/32
ig & General vie# of the Haul )oad
ig ! General -ie# of the Haul )oad
7
-
8/12/2019 Bila Spur Report Final
8/32
ig -ie# of 123 t %umper
ig 4 ransportation of 0oal in progress
8
-
8/12/2019 Bila Spur Report Final
9/32
ig 5 "ovement of 0oal Hauler along the e(isting blac$topped road
ig 6 Proposed /lignment of ne# road in front of #or$shop #ith appearanceof crac$s on e(isting shale material
9
-
8/12/2019 Bila Spur Report Final
10/32
ig 7 0ondition of e(isting 0oal Haul road
ig 13 / vie# of overburden haul road in Gevra area
10
-
8/12/2019 Bila Spur Report Final
11/32
ig 11 Surface condition of coal haul road
ig 12 Surface condition at starting point of coal haul road
11
-
8/12/2019 Bila Spur Report Final
12/32
ig 1& %istressed locations on haul road
ig 1 0ondition of turning areas of haul road
12
-
8/12/2019 Bila Spur Report Final
13/32
ig 1 ailure due to poor drainage condition and lac$ of proper0amber
ig 14 %evelopment of Potholes due to inade8uate maintenance and poordrainage
13
-
8/12/2019 Bila Spur Report Final
14/32
ig 15 -ie# of pit cutting in progress on overburden haul road
ig 16 est pit cutting on haul road
14
-
8/12/2019 Bila Spur Report Final
15/32
&.3 ,/BO)/ O)9 'S +*G /*% /*/,9S+S
&.1 General
The laboratory investigations are carried out primarily for assessment of overallconstruction uality. 0aboratory evaluation of uality of materials collected from
various test pits, includes mechanical and engineering characteristics. In order toevaluate different characteristics of various road building materials used duringconstruction of study stretches a number of relevant tests on subgrade soils,aggregates, !ere carried out. 0ocation of test pits dug on different road stretches!ith details of samples collected from each test pit for detailed laboratory evaluationin Institute
-
8/12/2019 Bila Spur Report Final
16/32
0ocationof soil
sample
- a n d
+ o n
t e n
t
" ) e r c e n
t # 0 i u i d 0 i m i t
" ) e r c e n
t # ) l a s t
i c l i m i t
" ) e r c e n
t # ) l a s t
i c i t y I n d e x
" ) e r c e n
t #
*
% +
" ) e r c e n
t #
% o
d i f i e
d ) r o c t o r
3 e n s i
t y
" g m
8 c c #
+ a
l i f o r n
i a
, e a r i n g
7 a
t i o
" C #
- a t u r a
t i o n
% o
i s t u r e
" C #
3ip'axtn )it 4 = 45.5 >.5 B B.9 .?>= 4.5 63ip'a
xtn )it ? 4>. 5.6 6.5 .?45 =.? 6.5
Table 2 Test 7esults of %oorum, -hale D 3ebris -amples
Type ofsample -
a n
d +
o n
t e n
t
" ) e r c e n
t # 0 i u i d
0 i m i t
" ) e r c e n
t # ) l a s t
i c l i m i t
" ) e r c e n
t # ) l a s t
i c i t y I n d e x
" ) e r c e n
t #
* %
+
" ) e r c e n
t #
% o
d i f i e
d ) r o c t o r
3 e n s i
t y
" g m
8 c c #
+ a
l i f o r n
i a
, e a r i n g
7 a
t i o
" C #
- a
t u r a
t i o n
% o
i s t u r e
" C #
Gevramoorum 55 46 ; @) B 4. 95
B.> 4.5
+rushed-hale 9> 4 ; @) ?.9 4.6B4 9.= .4+oal
debris"Gevra#
5> 4? ; @) .> > 4 5
Table 2= Test 7esults of Aggregate -amples
16
-
8/12/2019 Bila Spur Report Final
17/32
-ource of aggregate sample Aggregate-ample
Agg ImpactEalue C
Water Absorption
C
WetImpact
Ealue C7atanpur aggregate 4 6.>9 9+ho!daha aggregate 4 4> .9= 4
%a'hanpur aggregate = 9.9 5
able ! est results of 0oarse Sand for %rainage ,ayer
Sieve Si;e Percent passing=.>9 mm B94.6 mm B
.6 mm ??>9 micron =
4.3. Pavement %esign
/or handling of coal and overburden material, use of heavy dumpers is essential.
+onse uently for operation of such dumpers, it is necessary to design appropriate
pavement systems other!ise there is a possibility of undesirably large settlement
under the !or'ing loads.
/or the safe !or'ing of a dumper, the pavement thic'ness should be ade uate for
the magnitudes of imposed load and the sub;grade soil support should be ade uate
to prevent excessive settlement. The pavement should be constructed !ith properspecifications ensuring ade uate uality control.
The relationship curves for flexible pavement thic'ness vs. +. .7. of sub;grade soil
had been !or'ed out, for a 456 t )ayload +apacity dumper !hich is expected to
operate !ithin the coal mine.
4.1 Parameters for %evelopment of le(ible Pavement %esign < hic$ness -s.
0.B.). )elationship= for 243 t Payload 0apacity %umper
The 456 %T )ayload +apacity dumper consists of pneumatic tyres carrying
45B,?= t on the rear axle and =,5B= t on the front axle and a tyre pressure of
.4 'g8 cm 4 "/igure #. /or 6 9 repetitions of the !heel load the load repetition
factor is 6.?. The design of flexible pavement consists essentially of t!o steps:
17
-
8/12/2019 Bila Spur Report Final
18/32
"i# 3evelopment of relationship bet!een e uivalent single !heel load " -W0#
and depth of construction for different values of +. .7. "/igure =#
"ii# 3evelopment of + 7 +urves for 3esign of /lexible )avement for 456 t
)ayload +apacity 3umper. "/igure 9#.
"iii# The thic'ness of pavement crust for different values of + 7 are indicated in
Table >.
4.2 Parameters for %evelopment of le(ible Pavement %esign for 0oal
ransportation road
Traffic volume data !as collected by covering all categories of vehicles includingnon;motorized traffic at one location. The data !as collected by employing trainedfield personnel !ho recorded counts in a prescribed proforma. The traffic volume
surveys !ere carried out for 4= hours continuously in three shift.
The survey covered counting of different category of vehicles viz., light vehicles and
commercial vehicles li'e truc's, buses, 0+E "goods# etc. The location of traffic
count points !as near old #or$shop on coal transportation road . The data on
classified volume counts, for both directions of traffic, is given in Table 5
Table 5 +lassified volume counts on coal transportation roadEehicle Type -hift -hift 4 -hift Total
T!o !heeler 6>4 564 =54 4 5&eep8Tempo B= 4 5 4 >
Truc' single Axles =6> 46 4B9 B69
Truc' Tandem Axles 566 6B 5? = B6
Truc' Three Axles =6 ? =9 >>5
Tan'er 4? tonne 59 9? B> 446Truc' 9 Axles ?5 5? == 5B?+rane B ? =6Grader 49 = 5 93ozer B 5 5
46 ton 3umper 6 9 >9 =6
18
-
8/12/2019 Bila Spur Report Final
19/32
)ro$ected 3esign Traffic 0oading in Terms of +umulative -tandard Axles
/or design purposes, variation in axle loads is usually handled by converting8reducing the actual axle load to an F uivalent -tandard Axle 0oad " -A0# . An
e uivalency is simply a convenient means for indexing the !ide spectrum of actualloads to one selected value, !hich is ?.4 tonnes for single axle load and 9.tonnes for tandem axle "? tyres# load. The relative damaging effect of different axleloads is determined based on a characteristic relationship termed as the F/ourth)o!er 0a! . The rule states that the damaging po!er of an axle load increasesroughly as the fourth po!er !ith the increasing !eight of the axle. Any single axleload less than ?466 'g is therefore some fraction of e uivalent single axle load" -A0#, !hereas a load greater than single axle load is some multiple of -A0.-imilarly for tandem axles !ith ? tyres assembly, the rule states that the damagingpo!er of tandem axle increases as the fourth po!er !ith regard to the !eight of thestandard tandem axle, !hich is 9. tonnes.
The design traffic in terms of +umulative -tandard Axles is !or'ed out by
considering the heavy commercial traffic and their damaging effects"E3/# as
explained in the earlier section, for a convenient design life duly accounting for the
anticipated traffic gro!th. In the present case, the cumulative standard axles are
!or'ed out for 6 years design life, assuming an annual gro!th rate of >.9C per
year.
@s H / r
@s: The cumulative number of standard axles to be catered for in the design A: Initial traffic, in the year of completion of construction, in terms of the
number of commercial vehicles per day duly modified to account for lane
distribution.r: Annual gro!th rate of commercial vehiclesx: 3esign life in years/: Eehicle damage factor
%esign of 0oal Haul )oad+ 7H43esign trafficH 5B?B +E)3
59 x A J" Kr#x 2 L
19
-
8/12/2019 Bila Spur Report Final
20/32
E3/H =.93esign 0ife H 6 years0ane distribution factor H6.>9Total Traffic H 6? %-A)avement thic'nessH B56 mm
xisting +rust H 566 mm*verlay re uired H 56 mm "detail is given in table of 7ecommendation#
The value of cumulative standard axles covering different categories of commercial
vehicles is pro$ected to be about 6? million standard axles, over a rehabilitation
design life of 6 years
20
-
8/12/2019 Bila Spur Report Final
21/32
/ig . 3imensions of 456 t )ayload +apacity 3umper
21
-
8/12/2019 Bila Spur Report Final
22/32
3
3333
133333
1 3333
233333
2 3333
3 3 133 1 3 233 2 3 &33 & 3 33
%epth of 0onstruction> cm
' 8 u i v a l e n t S i n g l e ? h e e l , o a d
> $ g
0B) 2
0B) &0B)
0B) 0B) 4
0B) 5
0B) 60B) 13
/
B
igure ! )elationship bet#een 'S?, and %epth of 0onstruction for 243 tPayload 0apacity %umper
22
-
8/12/2019 Bila Spur Report Final
23/32
3
3
133
1 3
233
2 3
2 & 4 5 6 7 130B)> Percent
% e p t h o
f 0 o n
s t r u c t i o n
> c m
igure ! 0B) 0urves for %esign of le(ible Pavement for 243 tonne %umper igure ! 0B) 0urves for %esign of le(ible Pavement for 243 t Payload
0apacity %umper
Table > : Ealues of + 7 vs 3epth of +onstruction for 456 t payload capacity dumper
+ 7 3 )T1 */ +*@-T7(+TI*@,+%
= 4 6
9 ?95 56> =6? 46B 66 66
23
-
8/12/2019 Bila Spur Report Final
24/32
5.3 %iscussion of test results
ased on the observations recorded during the field visit of +oal mines in Gevra
area and subse uent testing of high!ay material such as sub grade soil,
aggregates, moorum, shale and coarse sand, interim recommendations for the
pavement design of over burden haul road and for maintenance of coal haul road
are given belo!:
. The design + 7 for design of the pavement crust shall be assumed as =.
4. The roads shall be designed on the follo!ing criteria:
i. 7oads for movement of coal dumpers
ii. 7oads for haulage of *verburden material
. +oal haul roads are badly distressed due to poor drainage. +oal dust has been
deposited at edges and shoulder portion of the pavement, !hich preventsdrainage of !ater from pavements to edges. Therefore first the coal dust should
be removed from shoulder portion and one layer of Water bound %acadam
"W %# GII as profile corrective course. The additional layers may be provide as
under.
=. The shale material " sand!iched layer bet!een overburden earth and coal#
may be used for raising emban'ment and ma'ing sub grade. This material can
not be used in sub base layer or in W % layer as a filler, being plastic in nature.It is advisable not to use this material for, maintenance of potholes or distressed
area in granular layer.
9. The overburden earth is of varying uality in nature place to place and some of
!hich can be used for preparing sub grade for overburden haul road.
5. )roper camber is re uired in all the existing roads as the existing camber is
inade uate.
>. +oal haul road is badly distressed due to poor drainage. +oal dust has been
deposited at edges and shoulder portion of the pavement, !hich prevents
drainage of !ater from pavements to edges. Therefore first the coal dust should
be removed from shoulder portion and surface profile should be corrected and
thereafter various layers should be made as given in Table belo!.
24
-
8/12/2019 Bila Spur Report Final
25/32
?. Aggregates to be used in W % should have aggregates impact value less than
6. Aggregates from uerry of 7atanpur and +ho!daha may be used but
Aggregates from uerry of %a'hanpur should not be used.
B. %oorum is non plastic having )I less than 5 so it can be used in W % layer.
6.Ade uate hard shoulder of 4 meter !idth on both side is to be made. %aterial
used in shoulder should be non plastic in nature. +ross fall of percent should
be made to uic' run off of sprin'ling !ater on the pavement.
.)roper drainage along the pavement is needed to drain off !ater immediately.
4.Total road !idth of = m includes !idth of +arriage!ay 4 m, !idth of 3ozer
path 9 m, and shoulders of 4 m each on both side.
6.3 )'0O""'*%/ +O*S
6.1 General )ecommendations
. The present drainage system is inade uate and should be improved by
constructing side drains at missing locations. -houlders shall be corrected to
C camber so that the !ater drains off immediately. 3rains should be
cleared off bushes to improve the existing drain system.
4. 0ocations !here the section is badly crac'ed needs to be removed and a
fresh layer should be placed.
6.2 )ecommendations for Pavement design and rehabilitation
)ecommendations
Type of 7oad @e!8 xisting
pavement
7ecommendation
*verburden haul
road in Gevra Area
xisting
)avement
*ne layer of W % GII 66mm
*ne layer of W % GIII 66 mm*verburden haul
road in 3ipi'a Area
@e!
)avement
Total pavement thic'ness H4 66 mm
/ourteen layers of W % GII each 66 mm
T!elve layers of W % GIII each >9 m+oal Transportation
7oad in Gevra Area
xisting
)avement
one layer of % 66 mm as per %o-7T1
Grading Table 966;= "as profile corrective course#
one layer of 3 % 66 mm as per %o-7T1
25
-
8/12/2019 Bila Spur Report Final
26/32
Grading Table 966; 6
one layer of 0-A%M 66 mm Grading given belo!
one layer of -3 + 96 mm
0-A%M 0arge size Aggregate %ix grading is effective as rut resistant mix
-pecified Aggregate Gradation for 0arge -ize Aggregate %ix "0-A%#
-ieve size "mm# )er cent passing=9.6 mm 66
>.9 mm B6; 6649.6 mm ?4;B6
B.6 mm 5?;B6B.9 mm ==;>4=.>9 mm 4?;944. 5 mm 46;=6
566 micron 5;4466 micron 9; 996 micron 4; 6
>9 micron 4;>
+ross section of *verburden haul road in 3ip'a area
/ppendi(@1Specification for 5 mm ?B"
/. Properties of 0oarse /ggregate
DozerPathShoul er
32 !5 !
26
-
8/12/2019 Bila Spur Report Final
27/32
i. 0os Angeles Abrasion Ealue, per cent max. =6ii. Aggregate Impact value, per cent, max. 6iii. /la'iness and longation Index, combined , max. 6
B. Grading )e8uirement for 0oarse /ggregate
-ieve-ize mm
>9mm W %Grade ; II
>9mm W %Grade ; III
49 ; ;B6 66 ;5 B6; 66 669 49;>9 B9; 66=9 6; 9 59;B6
44.= 6;9 6; 6.4 6;9
0. Grading )e8uirement for Screening
-ieve-ize
mm>9mm W %
.4 ;
.4 669.5 B6; 66?6 N 9; 9
%. Auantities for 5. cm thic$ness
i. +oarse Aggregate for >.9 cm compacted thic'ness per 6 m 4 H 6.B 2 .6>m
ii. -tone screening type for 6.4 ; 6.44 m for GII and 6. ? ; 6.4 m for GIII
iii. inding material of plasticity index less than 5C H 6.65 ; 6.6B m
"##en $%&2
27
-
8/12/2019 Bila Spur Report Final
28/32
Specification for 3 mm Bituminous "acadam
/. Properties of 0oarse /ggregate
i. 0os Angeles Abrasion Ealue, per cent max. =6
ii. Aggregate Impact value, per cent, max. 6iii. /la'iness and longation Indices "Total# 6iv. -tripping Ealue per cent, max. 9v. Water Absorption per cent, max. 4vi. 7etained tensile strength, minimum, per cent ?6
B. Grading of /ggregates-ieve -ize, mm )ercent by Weight )assing the -ieve
45.9 66B B6; 66.4 95;??
=.>9 5; 54. 5 =; B
66 micron 4; 6>9 micron 6;?
0. Auantities of binder i. )rime +oat for 6 - .m 5'gii. Tac' +oat for 6 s .m. Area "+ationic bitumen emulsion#:
4.9 'g for primed W % surface
ii. Binder 0ontent for aggregates! &.& to &. per cent by #eight of mi(. %. 0onstruction Operation
Apply prime coat of cationic emulsion O 5 'g8s m Apply tac' coat of cationic emulsion O 4.9 'g8s mTemperature of bitumen at the time of mixing shall be 96; 5 P+ and that of
aggregate shall be 99; 5 P+.Temperature of mix at the time of laying shall be minimum 49P+.+ompaction of mix shall be completed before temperature of mix falls belo! 66P+.
Appendix-4
28
-
8/12/2019 Bila Spur Report Final
29/32
Specifications for 3 mm hic$ %ense Bituminous "acadam %esign0riteria
i# @o of blo!s on each face >9 ii# %arshall -tability "%in#, 'g B66
iii# %arshall flo! , mm 4 ; =iv# C voids in the mix ; 566666666 v# C voids in mineral aggregate filled by the
binder 59 ; >9
B. Grading of /ggregate-ieve -ize mm )ercent )assing
>.9 6645.9 B6; 66
B > ;B9.4 95;?6
=.>9 ?;9=4. 5 4?;=466N >;4
>9N 4;?
0. Physical properties of aggregatesi. 0os Angeles Abrasion Ealue, per cent max. 9ii. Aggregate Impact value, per cent, max 4>iii. /la'iness and longation Indices "Total# 6iv. -tripping Ealue percent, max. 9
v. Water Absorption percent, max. 4vi. -oundness lossa# !ith -odium -ulphate, 9 cycles per cent 4
b# !ith %ag. -ulphate, 9 cycles per cent ?vii. 7etained tensile strength min. percent ?6
%. Auantity of binder for!inder for mix design, per cent @ot less than =.9 per cent
'. Permissible -ariations from ob "i( ormula)assing B mm sieve D large, per cent ?)assing .4 mm sieve D B.9 mm sieve, per cent >
)assing =.>9mm sieve, per cent 5)assing 4. 5 mm sieve D 566 micron sieve, per cent 9)assing 66 micron sieve and retained on 96 micron sieve, percent
=
)assing >9 micron sieve, per cent 4itumen, per cent 6.
%ixing Temperature 6 +
29
-
8/12/2019 Bila Spur Report Final
30/32
. emperatures for 0onstruction Operations
i. Temperature of bitumen at the time of mixing 96 ; 5 P+ii. Temperature of Aggregate at the time of mixing 99 ; 5 P+iii. Temperature of mix at the time of laying 46 ; 56P+iv. 7olling operations shall be completed before the temperature of the mix falls
belo! 66P+
C*ote! %ifference in temperature bet#een aggregate and bitumen should notbe more than 1 P0
30
-
8/12/2019 Bila Spur Report Final
31/32
/ppendi(@Specifications for 3 mm hic$ Bituminous 0oncrete %esign 0riteria
i# @o of blo!s on each face >9ii# %arshall -tability "%in#, 'g B66
iii# %arshall flo! , mm 4 2 =iv# C voids in the mix 2 566666666 v# C voids in mineral aggregate filled by the
binder 59 2 >9
vi# 0oss of stability on immersion in !ater at 56 P+, minimum retained strength, per cent
>9
B. Grading of /ggregateSieve Si;e mm Percent Passing
B 66.4 >B; 66
B.9 >6;??=.>9 9 ;>4. 5 =4;9?
. ? =;=?566N 45; ?
66N ?;4?96N 4;46
>9N =; 6
0. Physical properties of aggregatesi. 0os Angeles Abrasion Ealue, per cent max. 6ii. Aggregate Impact value, per cent, max 4=iii. /la'iness and longation Indices "Total# 6iv. -tripping Ealue percent, max. 9v. Water Absorption percent, max. 4vi. -oundness loss
a# !ith -odium -ulphate, 9 cycles per cent "max# 4 b# !ith %ag. -ulphate, 9 cycles per cent "max# ?
vii. 7etained tensile strength min. percent ?6viii. +leanliness, Grain size analysis, per cent passing >9 micron "max# 9
%. Auantities of binder!
inder for mix design, per cent @ot less than 9 per cent
31
-
8/12/2019 Bila Spur Report Final
32/32
'. Permissible -ariations from ob "i( ormula)assing B mm sieve D large, per cent ?
)assing .4 mm sieve D B.9 mm sieve, per cent >)assing =.>9mm sieve, per cent 5)assing 4. 5 mm sieve D 566 micron sieve, per cent 9)assing 66 micron sieve and retained on 96 micron sieve, per cent =)assing >9 micron sieve, per cent 4
itumen, per cent 6.%ixing Temperature 6 +
. emperatures for 0onstruction Operations
i. Temperature of bitumen at the time of mixing 96 ; 5 P+ii. Temperature of Aggregate at the time of mixing 99 ; 5 P+iii. Temperature of mix at the time of laying 46 ; 56P+iv. 7olling operations shall be completed before the temperature of the mix falls
belo! 66P+
C*ote! %ifference in temperature bet#een aggregate and bitumen should notbe more than 1 P0