big horn lake sediment management study. us army corps of engineers omaha district study background...

24
Big Horn Lake Sediment Management Study

Upload: alvin-jeffry-goodman

Post on 29-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Big Horn LakeSediment Management Study

Page 2: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Study Background

• Bureau of Reclamation and Omaha District Interagency Agreement

• Compare sediment management alternatives and provide future recommendations

• PM/Technical Lead– Reclamation – Stephanie Hellekson– COE – Dan Pridal

Page 3: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Scope

• Initial appraisal level of detail

• Focus on screening and alternative comparison

• Highlight constraints/issues/impacts of the sediment management challenge

• Technical focus – define what is technically feasible

Page 4: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Alternatives

• A) Higher pool level during recreation season

• B) Trap sediments upstream of Horseshoe Bend

• C) Flush sediment through Horseshoe Bend

• D) Manage sediment within Horseshoe Bend

• E) Manage sediments within the watershed (not part of this study)

• F) Dredging/Removal (evaluate previous)

Page 5: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Progress Update

• Completed items include background report review, site visit, alternative development, meetings/coordination

• Ongoing efforts on HEC-RAS model development for base and alternative conditions

• Some study delay, about 4 weeks

Page 6: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Schedule

• Kickoff Meeting – Jan 2008

• Site Visit and Data Collection – May 2008

• Initial model assembly – June 2008

• 60% Alternatives Analysis – August 2008 (revised to September)(revised to September)

• 90% Draft Report – October 2008

• Study Complete – November 2008

Page 7: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Questions ?

Page 8: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Delta Formation Overview

Page 9: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Alternative AA) Higher pool levels during recreation season

Change Yellowtail operation to alter pool level – examine past records with respect to pool level vs. sediment inflow

Modifies deposition location, probably increase in southern end of reservoir, eventually worsen conditions at Horseshoe Bend

Does not solve problem but may buy some time for Horseshoe Bend

Page 10: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Alternative B

B) Trap sediments upstream of Horseshoe Bend

Alter causeway east of Lovell to serve as impoundment

Area is wide and shallow, more effective for coarse material than fine

Trapped sediment could be removed if funds available

Identify construction issues, policy issues, O&M

Page 11: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Alternative C

C) Flush sediment through Horseshoe Bend

Maintain lower pool level during high sediment runoff period to flush sediment past Horseshoe Bend

Likely some deposition still occurs within Horseshoe Bend

Does not solve sediment problem but spreads to entire project to buy time, long term impact may be detrimental and worse than without change

Risk that pool may be impacted during lower runoff years, other similar impacts

Page 12: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Alternative D

D) Manage sediment within Horseshoe Bend

Implement local features to control and alter sediment deposition and transport through Horseshoe Bend

May require berm construction to separate flowing river from recreation area

Sediments move past Horseshoe Bend with minimal impact to recreation area

Alternative is most independent of other actives, least impacted by hydrology

Other alternatives may also require some implementation of local sediment management activities

Page 13: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency
Page 14: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Evaluation Method

• Collect available data

• Construct hydraulic model

• Verify model with existing conditions

• Modify model for alternative

• Evaluate and compare

• Basis for recommendations

Page 15: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Modeling Options

• Simple sediment transport for a cross section

• HEC-RAS / HEC-6 / GSTARS Hydraulic Models

• More complex models (2d and 3d)

• Model complexity and analysis limited

• Will select model consistent with alternatives and available data

Page 16: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Model Input

• Hydraulic Model Data Requirements– River/Reservoir Geometry Data – Roughness and Loss Coefficients– Bed Gradation Data for River and Reservoir

Reaches – Upstream Inflow– Sediment Inflow and Gradation – Pool Level

Page 17: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Data Sources

• Reservoir rangeline surveys (numerous years)

• Sediment sampling

• USGS gage stations

• Other Agencies– Sediment data?– Historical topo data?– Aerial photos?– Previous Studies

Page 18: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Reclamation Range Line Location

Horseshoe Bend Vicinity

14

15

16

Page 19: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Range Line 14

3540

3560

3580

3600

3620

3640

3660

3680

3700

0 200 400 600 800 1000 1200 1400 1600 1800 2000

Distance - Feet

Ele

vati

on

- F

eet

Original Survey 1982 Survey 2000 Survey

D/S Horseshoe Bend

Summer – Top of Joint Use

2000 Bighorn Lake Sed. Survey –

Reclamation Sed. Group

Safe Launch Elev at Horseshoe Bend

Page 20: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Range Line 15

3540

3560

3580

3600

3620

3640

3660

3680

3700

0 500 1000 1500 2000 2500

Distance - Feet

Ele

vati

on

- F

eet

Original Survey 1982 Survey 2000 Survey

Lower Horseshoe Bend2000 Bighorn Lake Sed. Survey –

Reclamation Sed. Group

Summer – Top of Joint Use

Safe Launch Elev at Horseshoe Bend

Page 21: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

Range Line 16

3540

3560

3580

3600

3620

3640

3660

3680

0 500 1000 1500 2000 2500 3000 3500 4000

Distance - Feet

Ele

vati

on

- F

eet

Orginal Survey 1982 Survey 2000 Survey

Upper Horseshoe Bend2000 Bighorn Lake Sed. Survey –

Reclamation Sed. Group

Summer – Top of Joint Use

Safe Launch Elev at Horseshoe Bend

Page 22: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

ExampleDelta Progression at Gavins Point Dam

Page 23: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Schedule

• Kickoff Meeting – Jan 2008

• Site Visit and Data Collection – Spring 2008

• Initial model assembly – June 2008

• 60% Alternatives Analysis – August 2008

• 90% Draft Report – October 2008

• Study Complete – November 2008

Page 24: Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency

US Army Corpsof EngineersOmaha District

Summary

• Compare Sediment Management Alternatives

• Initial assessment level of detail to screen and compare alternatives

• Provide technical report and recommendations