Page 1: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

 

   

BIENNIAL REPORT ON IMPACTS OF  DISTRIBUTED GENERATION Prepared in Compliance with AB 578 –  With Data through 2011 and Selected 2012 Data 

 

California Public Utilities Commission MAY 2013 

Page 2: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

FINAL REPORT 

BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

Prepared in Compliance with AB 578 –  With Data through 2011 and Selected 2012 Data 

B&V PROJECT NO. 176365  

PREPARED FOR 

 

 

 

California Public Utilities Commission 

18 MARCH 2013 

  ®

®

©Black & Veatch Holding Company 2012. A

ll rights reserved. 

©Black & Veatch Holding Company 2013. A

ll rights reserved. 

Page 3: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Table of Contents  i 

Table of Contents 1.0 ExecutiveSummary............................................................................................................................1‐1

1.1 Introduction...........................................................................................................................................1‐11.2 OverviewofDistributedGeneration............................................................................................1‐11.3 ImpactsofDGontheTransmissionandDistributionSystem...........................................1‐41.4 IssuesandBarriersImpactingDGDeployment......................................................................1‐81.5 EmergingTechnologies.....................................................................................................................1‐81.6 RecommendationsforFutureStudy............................................................................................1‐9

2.0 Introduction..........................................................................................................................................2‐12.1 Background............................................................................................................................................2‐12.2 DistributedGenerationPolicy........................................................................................................2‐22.3 ApproachandMethodology............................................................................................................2‐32.4 ReportOrganization...........................................................................................................................2‐3

3.0 DistributedGenerationOverview.................................................................................................3‐13.1 DescriptionofDGTechnologies.....................................................................................................3‐13.2 DGCurrentlyInstalledinCalifornia.............................................................................................3‐3

4.0 DGImpactsontheTransmissionandDistributionSystem.................................................4‐14.1 DistributionSystemReliabilityandOperation........................................................................4‐24.2 TransmissionSystemReliabilityandOperation.....................................................................4‐74.3 SizeandLocationDependentImpactofDG............................................................................4‐104.4 PeakDemandImpactAnalysis.....................................................................................................4‐12

5.0 IssuesandBarriersImpactingDGDeployment.......................................................................5‐15.1 FinancingandEconomics.................................................................................................................5‐35.2 PolicyandRegulatory........................................................................................................................5‐65.3 GridAccessandInterconnection.................................................................................................5‐125.4 Integration............................................................................................................................................5‐195.5 Miscellaneous......................................................................................................................................5‐215.6 KeyIssuesandBarriers...................................................................................................................5‐24

6.0 EmergingTechnologies.....................................................................................................................6‐16.1 SmartInverters.....................................................................................................................................6‐16.2 EnergyStorage......................................................................................................................................6‐36.3 AdvancedGridManagement/SmartGridTechnologies....................................................6‐66.4 Microgrids...............................................................................................................................................6‐8

7.0 RecommendationsforFutureStudy............................................................................................7‐1AppendixA. InstalledCapacityData.......................................................................................................A‐1AppendixB. PeakDemandImpactAnalysisMethodology..............................................................B‐1AppendixC. FutureDGStudy.....................................................................................................................C‐1AppendixD. January31,2013ReportPresentation,IncludingSelected2012Data

Updates...................................................................................................................................................D‐1

Page 4: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Table of Contents  ii 

LIST OF TABLES  Table1‐1 SummaryofCustomer‐SideDGInstalledinCaliforniabyTechnology(All

IncentivePrograms)through2011..............................................................................................1‐3Table1‐2 KeyRemainingIssuesandBarriersforCustomer‐sideDG................................................1‐8Table3‐1 DescriptionofPrevalentCustomer‐sideDGTechnologies*..............................................3‐2Table3‐2 SummaryofDGProgramCharacteristics..................................................................................3‐4Table3‐3 SummaryofCustomer‐SideDGInstalledinCaliforniabyTechnology(All

IncentivePrograms)through2011..............................................................................................3‐6Table3‐4 SummaryofCSIInstallationsbyProgramandUtility(AllSolarPV)...........................3‐10Table3‐5 SummaryofSGIPInstallationsbyTechnologyandUtility...............................................3‐11Table3‐6 SummaryofERPInstallationsbyTechnologyandUtility................................................3‐12Table3‐7 SummaryofNSHPInstallationsbyUtility...............................................................................3‐12Table3‐8 SummaryofSB1POUInstallationsbyUtility........................................................................3‐13Table3‐9 SummaryofNEMDGInstallationsbyTechnologyandUtility........................................3‐14Table3‐10 SummaryofNon‐NEMDGInstallationsbyTechnologyandUtility..............................3‐15Table3‐11 SummaryofFIT–AB1969InstallationsbyTechnology..................................................3‐16Table3‐12 SummaryofIOUSolarPVProgramInstallationsbyOwnership...................................3‐17Table4‐1 PeakDemandImpactbyTechnology........................................................................................4‐16Table5‐1 IssuesandBarriersImpactingDGDeployment......................................................................5‐2Table5‐2 NumberofInterconnectionApplicationsandAverageInterconnection

ApplicationProcessingTimesforCSIPVSystemsbyIOU................................................5‐15Table5‐3 KeyRemainingIssuesandBarriersforCustomer‐sideDG..............................................5‐25 

Page 5: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Table of Contents  iii 

LIST OF FIGURES  Figure1‐1 GoalsforCalifornia'sActiveDGPrograms................................................................................1‐4Figure1‐2 OperatingDGCapacitybyProgram,andCAISODemand,onSeptember7th,

2011...........................................................................................................................................................1‐7Figure3‐1 GoalsforCalifornia'sActiveDGPrograms................................................................................3‐5Figure3‐2 CumulativeDGCapacityInstalledbyProgram........................................................................3‐7Figure3‐3 CumulativeDGCapacityInstalledbyTechnology..................................................................3‐8Figure3‐4 CumulativeNon‐SolarDGCapacityInstalledbyTechnology............................................3‐8Figure4‐1 TypicalElectricPowerSystemSingle‐LineDiagram............................................................4‐1Figure4‐2 SampleSolarResourceDataforOneDay..................................................................................4‐5Figure4‐3 SolarIrradianceVariability–OneLocationvs.25Locations..........................................4‐11Figure4‐4 ImpactofCustomer‐SideDGonCAISODemandonSeptember7th,2011................4‐13Figure4‐5 OperatingDGCapacitybyProgramandCAISODemandonSeptember7th,

2011.........................................................................................................................................................4‐14Figure4‐6 HourlyDGCapacityFactorsbyProgramandCAISODemandonSeptember

7th,2011................................................................................................................................................4‐15Figure4‐7 PeakDemandImpactofSolarPVonTypicalSCEResidentialDistribution

Feeder.....................................................................................................................................................4‐18Figure4‐8 PeakDemandImpactofSolarPVonTypicalSCENon‐Residential

DistributionFeeder...........................................................................................................................4‐19Figure5‐1 PercentageofPVSystemswithThird‐PartyOwnershipinCSI,2007‐2012...............5‐4Figure5‐2 SolarModulePricesfromDecember2001–March2012..................................................5‐5Figure5‐3 PG&EResidentialRateTierStructure(January2012)........................................................5‐8Figure5‐4 ExampleImpactofRateStructuresonSDG&ECustomerElectricBills........................5‐9Figure5‐5 AverageInterconnectionApplicationProcessingTimesforCSIPVSystems

byIOU.....................................................................................................................................................5‐16Figure5‐6 ExampleInterconnectionCapacityMappingToolfromPG&E.......................................5‐17Figure6‐1 EnergyStorageDischargeTimeandRatedPowerGraph...................................................6‐4Figure6‐2 PotentialApplicationsofEnergyStorage(Black&Veatch)...............................................6‐6Figure6‐3 EmergingSmartGridInfrastructureinSupportofHighPenetrationDGPV..............6‐7Figure6‐4 Re‐sectionalizationExample...........................................................................................................6‐8

Page 6: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Table of Contents  iv 

LEGAL NOTICE  ThisreportwaspreparedasanaccountofworksponsoredbytheCaliforniaPublicUtilitiesCommission.ItdoesnotnecessarilyrepresenttheviewsoftheCommissionoranyofitsemployeesexcepttotheextent,ifany,thatithasformallybeenapprovedbytheCommissionatapublicmeeting.Forinformationregardinganysuchaction,communicatedirectlywiththeCommissionat505VanNessAvenue,SanFrancisco,California94102.NeithertheCommissionnortheStateofCalifornia,noranyofficer,employee,oranyofitscontractorsorsubcontractorsmakesanywarranty,expressorimplied,orassumesanylegalliabilitywhatsoeverforthecontentsofthisdocument.

ACKNOWLEDGEMENTS TheauthorsofthisreportwouldliketoacknowledgethesignificantcontributionsmadetothisreportbyCPUCstaff(MeliciaCharles,JamesLoewen,HazelMiranda,NealReardonandRachelPeterson),andrepresentativesfromthethreeinvestor‐ownedutilities(PacificGasandElectric,SouthernCaliforniaEdison,andSanDiegoGas&Electric),andtheCaliforniaCenterforSustainableEnergy.

Page 7: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐1 

1.0 Executive Summary ThisreportispreparedinresponsetoAssemblyBill(AB)578(Blakeslee,2008)whichrequirestheCaliforniaPublicUtilitiesCommission(CPUC)tosubmittothelegislatureabiennialreportontheimpactsofdistributedgeneration(DG)onCalifornia’stransmissionanddistribution(T&D)systems.Thisreportissummarizedinthesectionsbelow.

1.1 INTRODUCTION TheCPUCoverseesdistributedgenerationpoliciesandprogramsonboththecustomerandutility(wholesale)sideoftheelectricmeterwithintheserviceterritoriesofCalifornia’sinvestor‐ownedutilities.Thisreportisfocusedprimarilyontheimpactsandbarriersofcustomer‐sideDG,ratherthanwholesaledistributedgeneration.ManyimpactsandbarriersforwholesaleDGarealsoprevalentforcustomer‐sideDG.Whereappropriatethisreportdiscussesbothcustomer‐sideandwholesalesystems;however,unlessindicated,“DG”referstocustomer‐sidesystemsinthisreport.

Theprevious“ImpactofDistributedGeneration”report,preparedbyItron,Inc.,wasissuedinJanuaryof2010(2010Report).Forthisreport,anupdateofDGinstallationsresultingfromvariousCaliforniaprogramsisprovidedforcustomer‐sideDGinstallationsthroughtheendof2011.Selectedinformationinthisreporthasbeenupdatedthroughtheendof2012inAppendixD.Thereportalsocoversbrieflythevariousnewprogramsforwholesalegenerationthathavebeenimplementedsincethe2010Report.

Indevelopingthisreport,Black&Veatchreliedonseveralsourcesofinformation,including:

Gatheringandusingprimarydatafromexistingincentiveprograms

InterviewswithutilitydistributionengineersandprogrammanagersofCSIandSGIPprograms

RecentCSIandSGIPreportsandotherpublishedCPUCreportsonDG

Generalliteraturereviewofpaststudiesontheseissues

1.2 OVERVIEW OF DISTRIBUTED GENERATION GovernorBrownhasestablishedahigh‐levelgoalforCaliforniatoachieve12,000megawattsofrenewableDGby2020.Californiahashadahistoryofencouragingthedevelopmentofsmallergenerationfacilitiesthatconnecteddirectlyatthedistributionleveloftheelectricitysystem.DGgrowthhasbeenspurredbyseveralgovernment‐sponsoredincentiveprograms.TheCaliforniaEnergyCommission’sEmergingRenewablesProgram(ERP)wasfundedasaresultofAB1890,andprovidedsupporttoemergingrenewableprojectsonthecustomer‐sideofthemeter.TheCPUC’sSelf‐GenerationIncentiveProgram(SGIP),whichwasstartedinresponsetotheenergycrisisin2001,offeredincentivesforDGprojectslocatedatutilitycustomersites.TheSGIPprogramsupportedavarietyofdistributedgenerationtechnologiesincludingsolarphotovoltaic(PV),wind,fuelcells,andotherconventionaltechnologies.WhentheCaliforniaSolarInitiative(CSI)programandseveralrelatedprogramsbeganin2007asaresultofSenateBill(SB)1(Murray,2006),withagoalofpromoting3,000MWofdistributedsolarinthestate,supportforsolarPVtechnologieswasshiftedfromtheSGIPprogramtotheCSIprogram.

The2010ReportaddressedtheinstalledDGinCaliforniaundertheSGIPandCSIprogramsaswellasnetenergymetering(NEM)andnon‐NEMprojectsinterconnectedtothethreeinvestor‐owned

Page 8: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐2 

utilities(IOUs)throughSeptemberof2009.Sincethen,newprogramshavebeenlaunchedtopromotemoreDGinthestate;bothonthecustomersideofthemeterandonthewholesaleside,andinstallationshaveincreaseddramaticallyunderexistingprograms.Black&VeatchreviewedprogramdatatodeterminethetotalamountofDGthathasbeeninstalled.Theeightcustomer‐sideprogramsinclude:

CaliforniaSolarInitiative(CSI)

● GeneralMarket(GM)

● Multi‐familyAffordableSolarHousing(MASH)

● Single‐familyAffordableSolarHousing(SASH)

SB1Publicly‐OwnedUtility(POU)Programs

NewSolarHomesPartnership(NSHP)

Self‐GenerationIncentiveProgram(SGIP)

EmergingRenewablesProgram(ERP)–nolongeractiveasofJune2012

RenewableEnergySelf‐GenerationBillCreditTransfer(RES‐BCT)Program

NearlyallDGsystemsinstalledundertheseeightprogramsparticipateintheNEMtariff.EachIOUmaintainsaninterconnectiondatabasethattracksDGinstallationsontheNEMtariffandthosenotontheNEMtariff.BasedonthesedatabasesBlack&VeatchsummarizedtheamountofDGinstalledthroughoutthestateundertheNEMtariff(plusnon‐NEMDGinstallations)aswellastheDGinstallationsresultingfromthestate’swholesaleDGprograms.ItshouldbenotedthattheCPUChasrecentlyexpandedthestatewidevirtualnetmeteringtariffaswell,althoughthatprogramisnotdiscussedinthisreportastheexpansionofthatprogramwasnotyetcompleteatthetimethisstudybegan.ThewholesaleDGprogramsconsistof1:

Feed‐inTariff(FIT)

● AssemblyBill1969(AB1969)

● SenateBill32(SB32)

SolarPVPrograms(SPVP)

RenewablesAuctionMechanism(RAM)

Thetotalcustomer‐sideDGinstallationsthrough2011aresummarizedinTable1‐1belowbyutilityandtechnology.ThetotalamountinstalledundertheNEMtariff,inadditiontonon‐NEMDG,isapproximately1,580MW(thisisnotadditivetothecustomer‐sidetotalnotedinTable1‐1).ThetotalamountinstalledunderthewholesaleDGprogramsthrough2011is101MW.Thesenumbersareincreasingquickly.Asoftheendof2012,customer‐sideDGinstallationshadreachedatotalof1,785MW,andwholesaleDGinstallationshadreached177MW.2

Theprimaryfocusofthisreportistoevaluatetheimpactsofcustomer‐sideDGonthetransmissionanddistributionsystems.ManyimpactsandbarriersforwholesaleDGarealsoprevalentfor

                                                            1 In addition to these wholesale DG programs, AB 1613 established a FIT for efficient combined heat and power (CHP) systems.  SB 1122 also established a FIT for 250 MW of bioenergy, which was signed into law September 27th, 2012.  SB 1122 is planned to go into effect in 2013.  Neither the AB 1613 program nor the SB 1122 programs were investigated in detail in this report.   2 Additional selected information for 2012 is provided in Appendix D.   

Page 9: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐3 

customer‐sideDG.Whereappropriate,thisreportdiscussesbothcustomer‐sideandwholesalesystems;however,“DG”generallyreferstocustomer‐sideDGinthisreport.

Table 1‐1  Summary of Customer‐Side DG Installed in California by Technology (All Incentive Programs) through 2011 

TECH‐NOLOGY

PG&E SCE SDG&E* SCG POU TOTAL

# MW # MW # MW # MW # MW # MW

SolarPV 57,069 558 26,897 297 13,482 111 264 14 10,360 110 108,072 1,090

Wind 253 7 369 5 35 0 5 0 0 0 662 12

RF** 52 19 23 9 12 7 14 9 0 0 101 44

Non‐RF*** 210 79 81 33 44 24 121 75 0 0 456 211

AES 1 1 0 0 0 0 0 0 0 0 1 1

Total 57,585 663 27,370 345 13,573 142 404 98 10,360 110 109,292 1,357

Thisinformationisthrough2011.Selecteddatahasbeenupdatedthrough2012andisprovidedinAppendixD.Notes:*CaliforniaCenterforSustainableEnergy(CCSE)istheCSIandSGIPprogramadministratorforSDG&E.**RenewableFuels(RF)includesbiomass,digestergas,andlandfillgas.***Non‐RenewableFuels(Non‐RF)includesnaturalgas,propanegas,wastegas,andanyinstallationsforwhichthefueltypeisnotspecified.AES=AdvancedEnergyStorage

AsshowninFigure1‐1below,thegoalsforCalifornia’scurrentlyactiveDGprogramstotalalmost6,000MW,abouthalfoftheGovernor’sstatedgoalof12,000MWby2020.3Notably,thetimeframeformostoftheseprogramsisbeforetheendof2016.About3,750MWofthe6,000MWisrestrictedtosolarPV.Abouthalfofthetotalisrestrictedtocustomer‐sidegenerationonly.

                                                            3 Note that additional DG outside these programs would likely be counted towards meeting the Governor’s goal, because the definition of “localized electricity generation” under the Governor’s goal may or may not fall under the definition of “DG” used in this report.  Governor Brown’s goal is described at http://www.jerrybrown.org/jobs‐california%E2%80%99s‐future.   

Page 10: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐4 

Figure 1‐1  Goals for California's Active DG Programs  

1.3 IMPACTS OF DG ON THE TRANSMISSION AND DISTRIBUTION SYSTEM TheimpactsofDGonthedistributionandtransmissionsystemtodayarenotadequatelyquantified,butarebelievedtoberelativelylow.Thelackofobservedimpactscanbeattributedtoseveralreasons:

Currentlyabout90percentofconnectedDGcapacityisonthecustomer‐sideofthemeter

Customer‐sideDGsystemsaretypicallysmall

ThecurrentpenetrationlevelofDGislow

Atthegivenpenetrationlevels,theinterconnectionprocessandrequirementshavesuccessfullymitigatedimpactsbeforetheyoccur

ThereisagenerallackofmonitoringDGsystemoutput4andoftheeffectsofDGsystemsonthegrid(thatis,utilitiesdonothavetheappropriatetoolstosystematicallycollectandevaluatedataonproblemsorbenefitsattributabletoDG).

                                                            4 Currently, telemetering requirements are imposed only on DG systems 1 MW or larger.   Smaller units do not have this requirement since at lower penetrations the expectation was that the impacts would be minimal, the cost to collect the data would be relatively high, and processing of this additional data may not be necessary. This 

California Solar Initiative1,940 MW

New Solar Homes360 MW

Public Utility PV SB 1700 MW

Utility Solar PV Programs776 MW

Feed‐in Tariff750 MW

Renewable Auction Mechanism1,299 MW

0 MW

1,000 MW

2,000 MW

3,000 MW

4,000 MW

5,000 MW

6,000 MW

Program

 Goals, M

W

System‐side (Wholesale)

Customer‐side 

Open to All Renewables

Solar PV Only

+ SGIP (no MW Goal)

Page 11: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐5 

Forthesereasons,itisdifficulttoquantifytheimpactsofcustomer‐sideDGonthegrid.ItisexpectedbymanythatimpactswillincreaseasDGpenetrationincreases.However,tobeabletoquantifytheimpacts,theutilitieswillneedtobeginsystematicallymonitoring,evaluating,andassociatingsuchimpactswithDGsystems.

TheexpectedimpactswouldfirstoccuronthedistributionsystembecauseofthedirectconnectionofDGtothedistributionsystem.However,asthepenetrationofDGincreases,theimpactswillrolluptothetransmissionsystem.Whatmanyindustryobserversagreeonis“DGthatisatthe‘rightplaceattherighttime’willcreatethegreatestvalue,whileadditionalelectricitysupplyinthewrongplaceatthewrongtimecouldresultinaddedcoststothesystem,”asstatedinareportpublishedbyRockyMountainInstituteandPG&EinMarch2012.5However,itisdifficulttodevelopquantitativemeasuringandmonitoringprotocolstosystematicallygaugewhetherDGisbeingdeployedattherightplaceattherighttime,andtherehasbeennoeffortyetinCaliforniatodoso.

ImpactsofDGhavebeensplitintodistributionandtransmission.Belowisalistofimpacts,bothpositiveandnegative,thatDGcanhaveonthedistributionsystem,someofwhichhavealreadybeenobservedonIOUsystems.

Distributionsystemlinelosses

Peakdemandreduction

Deferreddistributionsystemupgrades

Frequencycontrol6

Voltageregulation

Reversepowerflow

Operationalflexibility

Todate,transmissionsystemimpactsduetoDGinstallationshavebeensmall.Theissueslistedbelowarelargelyanticipated,althoughsomehavebeenobservedontheIOUsystems.

Transmissionsystemlinelosses

Reversepowerflowfromthedistributionsystem

Operationalprocedures

Voltageregulation

Reliabilitycapacityandplanning

                                                                                                                                                                                                assumption should be revisited as penetration increases, or the operational requirements for DG change. For example, California utilities have recently proposed telemetering requirements for certain wholesale DG systems smaller than 1 MW that will export power to be aggregated and scheduled into CAISO’s market. As of this writing, the CPUC has not yet evaluated those proposals. 5 “Net Energy Metering, Zero Net Energy, and the Distributed Energy Resource Future: Adapting Electric Utility Business Models for the 21st Century,” Rocky Mountain Institute, Snowmass, CO, March 2012.   6 It should be noted that the frequency of the distribution system and transmission system is the same, and therefore impacts to frequency on the distribution system similarly affect the transmission system.  For simplicity, the frequency control impact is listed and discussed under distribution system impacts here.   

Page 12: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐6 

Capacitymargin

Systemstability

SizeandLocationImpactsThesizeandlocationofDGsystemsinrelationtothedistributionsystemdictatestheirimpactonthegrid.ThougheachdistributioncircuitisdifferentinitscapacitytoaccommodateDG,inmostcasesalargernumberofsmallDGsystemsspreadoverawideareawillhavelessnegativeimpactthanasmallernumberoflargeDGsystemsconcentratedinasinglearea.ThisisespeciallytrueforvariableresourceslikesolarPVandwind,whosevariabilityis“smoothedout”tosomeextentwhenaggregatingtheoutputofmanygeneratorsoverwidegeographicareas.

PeakDemandImpactsInadditiontoexaminingtheimpactsofDGonthetransmissionanddistributionsystems,Black&VeatchanalyzedtheimpactofDGonCAISOpeakdemand.InestimatingtheimpactofthetotalamountofinstalledDGcapacityoperatingontheCAISOgridduringthe2011peakdemandperiod,twoseparateapproachesweretakenforsolarPVandnon‐solarinstallations.TodeterminetheimpactofsolarPVcapacityduringthesystempeakdemand,Black&VeatchusedmetereddatafromalargesamplingofsolarPVsystems.Fornon‐solartechnologies,Black&Veatchuseddatafromthe“CPUCSelf‐GenerationIncentiveProgramEleventh‐YearImpactEvaluation”preparedbyItroninJune2012.

ThetotalamountofDGoperatingduringtheCAISOpeakdemandday(September7th,2011)isdisplayedinFigure1‐2,alongwithCAISOload.Duringthepeakdemandhourof4‐5pm,342MWofDGwereoperating,accountingfor0.7percentofCAISOload.OperatingDGpeakedduringthenoonhour(12‐1pm)at728MW,accountingfor1.8percentofCAISOloadatthattime.Overall,theimpactofDGonCAISOpeakloadissmall,andDGsolarPVpeaksmuchearlierinthedaythanCAISOdemand.AccordingtoBlack&Veatchestimates,DGsolarPVachievesanhourlycapacityfactorof0.25(outof1)duringtheCAISOpeakdemandhour,versus0to0.84forotherDGtechnologies.“Hourlycapacityfactor”referstoagenerator’soutputinaparticularhourrelativetoitsnameplatecapacity;anhourlycapacityfactorof0.25meansthatDGsolarPVinthathourwasproducingaboutaquarterofitsnameplatecapacity.

Black&VeatchacknowledgesthattherearelimitationstoonlyestimatingtheimpactofDGonCAISOpeakdemand.CAISOandeachIOUhastoplanforpeakdemandatavarietyoflevels(customertransformer,distributionfeeder,distributionsubstation,subtransmissionnetwork,transmissionsubstation,transmissionline,theutilitysystem,andtheentireCAISOsystem)andthisreportdoesnotattempttomodeltheimpactofDGateverylevel—althoughthatmaybeausefulexercise.Rather,thisreportseekstoshowthemagnitudeofDGoutputrelativetothetotalCAISOloadbecausethisgivesageneralsenseofhowmuchDGisinstalledstatewide.FuturestudiesshouldconductanalysisofDG’speakdemandimpactatotherlevelsbecausetheimpactislikelytobedifferentatlowerlevelsthanattheCAISOlevel.

Page 13: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐7 

 

Figure 1‐2  Operating DG Capacity by Program, and CAISO Demand, on September 7th, 2011 

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000

0

100

200

300

400

500

600

700

800

900

1,000

CAISO Load

 (MW)

DG Operating (M

W)

CSI

SGIP ‐ Solar PV

SGIP ‐ Non‐Solar

ERP/NSHP

All DG

CAISO Load

Peak DG Output: 728 MW

12 am   1 2       3      4      5       6     7     8        9   10     11   12pm 1        2       3    4      5       6     7     8        9   10     11    12am   

CAISOPeak Load: 45,569 MW

Page 14: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐8 

1.4 ISSUES AND BARRIERS IMPACTING DG DEPLOYMENT TherateofDGinstallationsinCalifornia,inparticularsolarPV,hasincreasedsignificantlyoverthepastseveralyears.Thisincreasecanlargelybeattributedtoincentives,theavailabilityofnewleasingandfinancingoptions,thedeclineinsolarPVcosts,andincreasedmarketingefforts.Inmanyrespects,CaliforniahasledthenationinidentifyingandremovingbarrierstoDGdeployment.InitiativessuchasimplementationofNEM,reformofRule21,andcompletionofonlinetoolsforrebateprocessinghaveallowedCaliforniatosuccessfullyadvancethelargestDGmarketintheU.S.Despitethissuccess,therearestillbarrierstoadditionaldeploymentofDGfromtheutility’sperspective,aswellasthecustomerand/ordeveloper’sperspective.

Black&VeatchprovidesanupdateddiscussionofDGbarriersinthisreport.NumerousissuesmaylimitthedeploymentofDG,butmanyhavebeenatleastpartiallyresolved,leavingsomewithmoreimpactthanothers.Thekeyremainingissuesandbarriersidentifiedinthisreportarelistedbelow.

Table 1‐2  Key Remaining Issues and Barriers for Customer‐side DG 

Financing and Economics 

• EquipmentandsoftcostsofDGarehighcomparedtogridelectricity.• Availabilityofgovernmentandutilityfinancialincentivesisbecomingmorelimitedbecausefundsfor

incentiveprogramsaredeclining.

Policy and Regulatory 

• PublicresistancetoDGcoulddevelopifnon‐DGcustomersareexcessivelyburdenedwithcoststosubsidizeNEMDGcustomers.

• ThereisalackofincentivestolocateDGinareaswiththegreatestbenefittothegrid;needtoadoptamoretargetedapproach.

Integration 

• Lackofmonitoring,forecastingandcontrolcapabilitieslimitstheutilities’abilitytomanageDGintegrationintothedistributionsystem,andabilitytorelyonDGcapacity.

• LackofcapabilitiesintegratingDG(especiallysolarPV)withdistributionandtransmissionmodels.Thisaffectstheutilities’abilitiestoaccuratelysimulateandplanforDG.

• Distributionsystemdesignisnotintendedforinjectionofgenerationleadingtovoltageissues,reversepowerflow,etc.ThisissuewillbecomemorewidespreadasDGpenetrationincreases.

• Inverterstandardsmayneedtobechangedtoallowbettersupportofthegrid.

Miscellaneous 

• ProcessingtimesandadministrativedelaysforincentiveapplicationsandinterconnectionapplicationsreducethespeedatwhichDGcanbedeployed.

• LackofsuitableprojectsitespreventsthemajorityofutilitycustomersfrominstallingDGontheirownproperty.

1.5 EMERGING TECHNOLOGIES MuchresearchanddevelopmentisbeingdoneonemergingtechnologieswhichmayalleviatesomeofthenegativeimpactsofDGsystemsandsomeofthebarrierstogreaterDGdeployment.Thesetechnologiesmayemergewithinthenext1to3yearsorthenext5to10years.However,giventherapidpaceofDGdeploymentinCalifornia,itisreasonabletoproactivelydemonstrateanddeployemergingtechnologieswiththegreatestpotentialbenefits.

Page 15: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐9 

ThisreportfocusesonemergingtechnologiesthatwouldprimarilybenefitPV,thelargestsourceofDGinCalifornia.Thesetechnologiesaredescribedinthelistbelow:

SmartInverters–Smartinverterscanbeequippedwithfunctionsthatalleviateimpactstothegrid.Forexample,requiringlowvoltageridethroughfunctionforinverterswouldpreventPVsystemsfromtrippingtooquicklyandaggravatingsystemdisturbances.

EnergyStorage–TheintermittencyofrenewableDGtechnologiesisachallengeintermsofintegratingthesystemstothegrid.Energystoragetechnologiescanalleviatesomeoftheintermittencyofthesesystems.

AdvancedGridManagement/SmartGridTechnologies–Avarietyofsmartgridtechnologiescanprovideutilitieswithmorevisibilityandcontrolwithinthedistributionsystem.ThemajorutilitiesinthestatehavebeenmakinglargeinvestmentsinsmartgridtechnologiesthatcouldhelpeaseDGintegrationissues.

Microgrids–Amicrogridisasmallpowersystemthatincorporatesself‐generation,distribution,sensors,energystorage,andenergymanagementsoftwarewithasynchronized,butseparable,connectiontoautilitypowersystem.ItcanenableDGintegrationthroughbettergridmonitoringandcontrolsystems,coordinationwithotherdistributedenergyresourceslikeenergystorage,andmoreactivedemandmanagement.

Other–ThereareseveralothertechnologiesthatareemergingrelatedtoreducingtheimpactsandenhancingthebenefitsofDG.TheseincludeAdvancedModeling,AdvancedDistributionManagementSystems,AdvancedVoltVArControl.Therearemanyothertechnologiesaswell.

1.6 RECOMMENDATIONS FOR FUTURE STUDY DGdeploymentontheCaliforniasystemhasbeenincreasingoverthepastseveralyears.Withthisincrease,thereareseveralunknowns.ThereismuchtobegainedfromamoredetailedinvestigationofthecurrentandfutureimpactsandbenefitsofDGontheelectricgridoftheIOUsinCalifornia.Thistypeofinvestigationwouldaddressthefollowingquestions:

HowisDGaffectingthedistributionsystemcurrently,andhowwillthischangeinthefuture?

HowmuchmoreDGcouldbedeployedonthesystemwithminimalimpactsandenhancedbenefits?

Whatadditionaltoolsareneededtoidentifyoptimallocation,type,andtimingofDG?

Howcananenhancedunderstandingofthecostsofdifferentimpacts,benefitsandsolutionshelpinformeffectivepolicytoenablethedeploymentofmoreDG?

HowcouldthedeploymentofmoreDGbebeneficial?Ifdeployedineffectively,howcoulditbedeleterious?

AnsweringthesequestionscanhelpcreateaclearroadmapofthegrowthpotentialofDG,andtoenableCaliforniatoanticipatepotentialchallengestoDGdeployment.Suchananalysisshouldstudythefiveprimarysectionslistedanddescribedbelow:

1) ExistingConditions2) ImpactsandCostsofDG

Page 16: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Executive Summary  1‐10 

3) PotentialBenefitsofDG4) Solutions5) ScenarioAnalyses

Theanalysisshouldfocusonthestatus,impacts,costs,andbenefitsofDGonthedistributionsystem,aswellasthetransmissionsystem,andshouldbeatechnicalandquantitativeanalysis.

Inadditiontotheabovedescribedanalysis,thefollowingareasshouldalsobestudied:

Reportingissues:reviewNEMinstallationdataandcompareagainstincentiveprogramdatabases

AmountofDG(PVandnon‐PV)penetrationifincentivesandsubsidiesarenotsustainedandwhatothermechanismscanhelpsustainthemarket

Developmentofuser‐friendlymodelstoassistutilitiesinmodelingtransmission,distribution,substationandfeederlevelimpactswithincreasedDGpenetration.ThisshouldincludetransientanddynamicmodelingofDGsystems

UseofaconsistentapproachtodistributionmodelingandmonitoringacrossutilitiesspecificallytargetedtoassessdistributiongridoperationalimpactsofDGsystems

   

 

Page 17: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Introduction  2‐1 

2.0 Introduction  ThisreportispreparedinresponsetoCaliforniaAssemblyBill(AB)578(Blakeslee,2008)whichrequirestheCaliforniaPublicUtilitiesCommission(CPUC)tosubmittotheLegislatureabiennialreportontheimpactsofdistributedgeneration(DG)onCalifornia’stransmissionanddistribution(T&D)systems.

OnJanuary1,2009,Section321.7ofthePublicUtilitiesCodewascreatedrequiringtheCPUCtodothefollowing:

321.7.(a)OnorbeforeJanuary1,2010,andbienniallythereafter,thecommission,inconsultationwiththeIndependentSystemOperatorandtheStateEnergyResourcesConservationandDevelopmentCommission,shallstudy,andsubmitareporttotheLegislatureandtheGovernor,ontheimpactsofdistributedenergygenerationonthestate'sdistributionandtransmissiongrid.Thestudyshallevaluateallofthefollowing:

(1)Reliabilityandtransmissionissuesrelatedtoconnectingdistributedenergygenerationtothelocaldistributionnetworksandregionalgrid.

(2)Issuesrelatedtogridreliabilityandoperation,includinginterconnection,andthepositionoffederalandstateregulatorstowarddistributedenergyaccessibility.

(3)Theeffectonoverallgridoperationofvariousdistributedenergygenerationsources.

(4)Barriersaffectingtheconnectionofdistributedenergytothestate'sgrid.

(5)Emergingtechnologiesrelatedtodistributedenergygenerationinterconnection.

(6)InterconnectionissuesthatmayarisefortheIndependentSystemOperatorandlocaldistributioncompanies.

(7)Theeffectonpeakdemandforelectricity.

Thetopicscoveredinthisreportaddressesthestudyareashighlightedinthelegislationrelatedtodistributedgenerationandtheissues,barriersandimpactsassociatedwiththeirincreasedpenetrationinCalifornia.

2.1 BACKGROUND ThisreportisthesecondreportpreparedinresponsetoAB578.Theprevious“ImpactofDistributedGeneration”report,preparedbyItron,Inc.,wasissuedinJanuaryof2010(“2010Report”).7The2010ReportprovidedbackgroundonDGinCalifornia,includingbroaddefinitionsofDGandashorthistoryofDGinCaliforniaaswellastheinstalledDGcapacitythroughSeptemberof2009.

The2010Reportprovidedseveraldefinitionsfordistributedgeneration,includingthefollowing:

DGfacilitiesaremostfrequentlydefinedasnon‐centralizedelectricitypowerproductionfacilitieslessthan20MWinterconnectedatthedistributionsideoftheelectricitysystem.DG

                                                            7 Itron, “Impacts of Distributed Generation,” Prepared for: California Public Utilities Commission Energy Division Staff, Davis, California, January 2010. 

Page 18: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Introduction  2‐2 

technologiesincludesolar,windandwater‐poweredenergysystems;andrenewableandfossil‐fueledinternalcombustion(IC)engines,smallgasturbines,micro‐turbinesandfuelcells.8

Forthisreport,DGissimilarlydefined,butwithaspecialfocusonsmallerDGonthecustomersideofthemeter.TheCPUCregulatesdistributedgenerationpoliciesandprogramsonboththecustomerandutility(wholesale)sideoftheelectricmeter.Thisreportisfocusedprimarilyontheimpactsandbarriersofcustomer‐sideDG,ratherthanwholesaledistributedgeneration.ManyimpactsandbarriersforwholesaleDGarealsoprevalentforcustomer‐sideDG.Whereappropriate,thisreportdiscussesbothcustomer‐sideandwholesalesystems;however,“DG”generallyreferstocustomer‐sideDGinthisreport.

Thisreportalsoprovidesanupdateofcustomer‐sideDGinstallationsresultingfromvariousCaliforniaprogramsthroughtheendof2011.Selectedinformationinthisreporthasbeenupdatedthroughtheendof2012inAppendixD.Thereportalsocoversbrieflythevariousnewprogramsdescribedaboveforwholesalegenerationthathavebeenimplementedsincethe2010Report.ForamoregeneralbackgroundonDG,includingitshistoryinCalifornia,readersshouldrefertothe2010Report.

2.2 DISTRIBUTED GENERATION POLICY  GovernorBrownhasestablishedahigh‐levelgoalforCaliforniatoachieve12,000MWofrenewableDGby2020.Whilethisgoalhasnotbeenspecificallyprescribedinlaw,CaliforniahasenactedseveralnewlawsandimplementednewrulestopromoteadditionalDGsincetheissuanceofthe2010Report:

AssemblyBill(AB)1969(Yee,Stats.2006,ch.731)createdCalifornia’sFeed‐in‐Tariff(FIT)program,authorizingthepurchaseofupto480MWofrenewablegeneratingcapacityfromrenewablefacilitiessmallerthan1.5MW.Subsequentlegislation,SB32(NegreteMcLeod,2009)andSB2(1X)(Simitian,2011),increasedtheeligibleprojectsizeto3.0MW,andstate‐widetotalprocurementforinvestor‐ownedutilities(IOUs)andpublicownedutilities(POUs)to750MW.

ForDGprojectsfrom3to20MW,theCPUCadoptedD.10‐12‐048,whichinitiallyauthorizedtheIOUstoprocure1,000MW(recentlyexpandedto1,299MWbyD.12‐02‐035andD.12‐02‐002)throughtheRenewableAuctionMechanism(RAM)programbyholdingperiodicauctionstoprocurerenewableenergy.ThefirstRAMauctiontookplaceNovember15,2011.

Inadditiontotheseprograms,in2009/2010,theCPUCalsoauthorizedUtilitySolarPVProgramsforeachoftheIOUstoownandoperatesolarPVfacilitiesaswellastoexecutesolarPVpowerpurchaseagreementswithindependentpowerproducers(IPP)throughacompetitivesolicitationprocess.Intotal,theseprogramshaveagoaltobringonupto1,100MWofnewsolarPVcapacityinCalifornia.

ElectricRule21istheCPUC‐jurisdictionalinterconnectiontariff.Rule21describestheinterconnection,operatingandmeteringrequirementsforgenerationfacilitiestobeconnectedtoandoperateinparallelwithautility’sdistributionsystem.TheCPUCopenedarulemakingtoimplementimprovementstotheRule21interconnectionprocessinSeptember2011,andatthesametimelaunchedamajorsettlementprocesstoaccomplisha

                                                            8 Itron, “Impacts of Distributed Generation,” Prepared for: California Public Utilities Commission Energy Division Staff, Davis, California, January 2010. 

Page 19: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Introduction  2‐3 

setofglobalreformstothetariff.9TheCPUCprioritizedreformsenhancingRule21forDGprojectsinterconnectingontheutilitysideofthemeter,inordertosupporttheCPUC’snewerwholesaleDGprograms.OnMarch16,2012,fourteenpartiestothesettlementnegotiationsfiledasettlementinCPUCRulemaking(R.)11‐09‐011thatcontainedasignificantlyreformedRule21tariff.ThesettlementwasapprovedbytheCPUCinSeptember2012.10Asaresult,Rule21nowprovidestransparentrulesforaclear,predictablepathtointerconnectionforallformsofdistributedgenerationwhilemaintainingthesafetyandreliabilityoftheelectricgrid.

TheCPUCalsoconvenedRenewableDistributedEnergyCollaborative(ReDEC)workshopstostudytheissuesandimpactsofsystem‐siderenewabledistributedgenerationthatisdispersedthroughoutthegridandinterconnectedforexporttotheutility.TwoworkshopshavebeenheldandtheCPUCmayholdadditionalmeetingsinthefuture.

2.3 APPROACH AND METHODOLOGY Indevelopingthisreport,Black&Veatchreliedonseveralsourcesofinformation,including:

Gatheringandusingprimarydatafromexistingincentiveprograms

InterviewswithutilitydistributionengineersandprogrammanagersofCSIandSGIPprograms

RecentCSIandSGIPreportsandotherpublishedCPUCreportsonDG

Generalliteraturereviewofpaststudiesontheseissues

Inassessingtheissuesandimpactstotheexistingtransmissionanddistributionsystemaswellasdetermining barriers, utility programmanagers and distribution engineers were interviewed togather information regardingactual issuesexperiencedbycustomers, installers, and theutilities.ThisapproachprovidedagaugeforthedegreeofimpacttheseDGissueshaveormayhaveinthefutureonthetransmissionanddistributionsystem.

Black&Veatchalsousedsystemoutputdatatomodeltheimpacton2011peakfromDGinstalledontheCaliforniagrid.

2.4 REPORT ORGANIZATION Thereportisorganizedasfollows:

Section3–DistributedGenerationOverview:Providesanoverviewofdistributedgenerationtechnologiesandthetotalinstalledcapacityinthestateresultingfromvariouscustomer‐sideandwholesaleDGprograms.TheinformationusedisthelatestavailableasofAugust2012,withmanydatasetsupdatedonlythroughtheendof2011.Selectedinformationinthisreporthasbeenupdatedthroughtheendof2012inAppendixD.

Section4–DGImpactsontheTransmissionandDistributionSystem:Highlightspotentialimpactsofconnectingdistributedenergygenerationtothelocaldistribution

                                                            9 R. 11‐09‐011, Order Instituting Rulemaking on the Commission’s Own Motion to Improve Distribution Level Interconnection Rules and Regulations for Certain Classes of Electric Generators and Electric Storage Resources, filed September 22, 2011. 10 D.12‐09‐018, Decision Adopting Settlement Agreement Revising Distribution Level Interconnection Rules and Regulations – Electric Tariff Rule 21 and Granting Motions to Adopt the Utilities’ Rule 21 Transition Plans, adopted September 13, 2012, in R. 11‐09‐011; see also www.cpuc.ca.gov/PUC/energy/procurement/LTPP/rule21.htm. 

Page 20: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Introduction  2‐4 

networksandregionalgrid.ThissectionalsodiscussesDGinthecontextof2011Californiapeakdemand.

Section5–IssuesandBarriersImpactingDGDeployment:IdentifieskeyissuesandbarriersaffectingDGdeploymentinthestate.

Section6–EmergingTechnologies:DescribeskeytechnologyadvancesthatmayhelpaddresssomeofthetechnicalissuesassociatedwithDGonthegrid.

Section7–RecommendationsforFutureStudy:Recommendationsforafuturestudytobetterquantifyimpactsandaddresssomeoftheissuesandbarriersidentifiedinthereport.

Page 21: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐1 

3.0 Distributed Generation Overview Californiahashadalonghistoryofencouragingthedevelopmentofsmallergenerationfacilitiesthatconnecteddirectlyatthedistributionleveloftheelectricitysystem.DGgrowthhasbeenspurredbyseveralgovernment‐sponsoredincentiveprograms.TheCaliforniaEnergyCommission’sEmergingRenewablesProgram(ERP)wasfundedasaresultofAB1890(Brulte,1996),andprovidedsupporttoemergingrenewableprojectsonthecustomer‐sideofthemeter.TheCPUC’sSelf‐GenerationIncentiveProgram(SGIP)startedinresponsetothe2001energycrisisandoffersincentivesforDGprojectslocatedatutilitycustomersites.TheSGIPprogramsupportedavarietyofdistributedgenerationtechnologiesincludingsolarphotovoltaic(PV),wind,fuelcells,andotherconventionaltechnologies.In2007,supportforsolarPVtechnologieswasshiftedfromtheSGIPprogramtotheCSIprogramasaresultofSB1,withagoalofpromoting3,000MWofdistributedsolarinthestatethroughtheCSIprograms(GeneralMarket,MASH,SASH),theNewSolarHomesPartnership,andtheSB1POUprograms.

Inadditiontothesecustomer‐sideprograms,therehavebeenanumberofotherprogramsinitiatedtosupportwholesaledistributedgenerationinthestate,inparttohelpthestatemeetitsRenewablePortfolioStandard(RPS)goals.ThissectionprovidesanoverviewofthecurrentDGtechnologiesandinstallationsinthestate.

3.1 DESCRIPTION OF DG TECHNOLOGIES AnumberofDGtechnologieshavebeenpromotedthroughvariousincentiveprogramsofferedbythestate.TheseincludesolarPV,wind,fuelcells,advancedenergystorageandotherconventionaltechnologies.Thesetechnologiesaredescribedinthetablebelow.

Page 22: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐2 

Table 3‐1  Description of Prevalent Customer‐side DG Technologies * 

TECHNOLOGY DESCRIPTION

SolarPV SolarPV,whichconvertssunlightdirectlytoelectricity,hasbeenthemostwidelyadoptedDGtechnologyinCaliforniatodate.Whileitdoesnotproduceanyemissionsandcanbesitedvirtuallyanywhereinthestate,theproductionofelectricitydependsonwhenthesunisshining.ThisvariabilityinoutputmayposechallengesforT&DgridoperationassolarPVpenetrationcontinuestorise.

WindTurbines AswithsolarPV,windturbinesconvertwindpowertoelectricityonlywhenthewindreachesacertainspeed.Thus,windturbinegenerationisalsovariableorintermittentinnature.InstallationsofDG‐scalewindinCaliforniahavebeenlimited.Windfarmsaretypicallycomprisedoflarger,utility‐scaleturbinesandareconnecteddirectlytothetransmissionsystemratherthanthedistributionsystem.

FuelCells(FC) Fuelcelltechnologycanbeutilizedasaconstantorvariablepowergenerationresource.Fuelcellsconverthydrogen‐richfuelsourcesdirectlytoelectricitythroughanelectrochemicalreactionwithverylowemissions.Mostfuelcellinstallationsgeneratelessthan1MW.Commercialfuelcellplantsaretypicallyfueledbynaturalgas,whichisconvertedtohydrogengasinareformer.However,ifavailable,hydrogen,biogas,orotherfuelscanbeused.Naturalgasisnowatrelativelylowprices,whichmaycauseincreasedininterestinfuelcellsfueledbynaturalgas.

ReciprocatingInternalCombustionEngines(IC)

Reciprocatingengines aretheindustrystandardforbiogascombinedheatandpower(CHP)projects.Theoutputoftheseplantsiscontrollableandcanthereforeberampedupordownasneeded,withnaturalgasasanalternativeorbackupfuel.Theengineconfigurationisdesignedtohandleawiderangeofgasflows;theengineoutputcanbeturneddownsignificantlywithoutlosingaconsiderableamountofefficiency.Internalcombustionenginesarebyfarthemostcommongeneratingtechnologychoiceatbiogasfacilities;about75percentofthelandfillsthatgenerateelectricityuseinternalcombustionengines.

Microturbines(MT)andGasTurbines(GT)

MicroturbinesandgasturbinesarefrequentlyusedforlargerDGinstallationsthroughoutCalifornia.TheiroutputisnotintermittentlikesolarPVandwind,whichmakesintegrationofthesetechnologiestechnicallyeasier.Microturbinescanutilizenaturalgasorbiogasbycompressingandburningwithairinthecombustor,generatingheatthatcausesthegasestoexpand.Theexpandinggasesdrivetheturbine,whichinturndrivesageneratorproducingelectricity.Heatfromtheturbineexhaustisrecoveredintherecuperatorandisusedtopreheatincomingcombustionair.Thishelpsimprovetheoverallefficiencyoftheunit.Microturbinesaretypicallyratedatlessthan250kW,butmultipleunitscanbeinstalledinparallelforhighercapacity.Becauseofsizelimitations,microturbineunitscanbeattractiveforsmalltomediumsizedplants.

AdvancedEnergyStorage(AES)

Energystoragetechnologiesconvertandstoreelectricity,increasingthevalueofpowerbyallowingbetterutilizationofoff‐peakgenerationandthemitigationofpowerfluctuationsfromintermittentrenewableenergygeneration.Differenttypesoftechnologiesareavailablethatprovideavarietyofstoragedurations.Storagedurationsrangefrommicroseconds(superconductingmagnets,flywheels,andbatteries),tominutes(flywheelsandbatteries),tohoursandseasonalstorage(pumpedhydroelectric,batteries,andcompressedair).TheusagethroughoutCaliforniaislimited,drivenbytheemergingtechnology,highercost,andlimitedincentives.AcurrentconstraintonAESdeploymentisthedifficultyofmonetizingitsbenefitstotheelectricpowersystem.

*Thistableincludestechnologiesthatarepartofcustomer‐sideprograms inCA.Otherenergytechnologiesexistthatcanbeappliedindistributedapplications,suchassmallhydro,solidbiomass,andgeothermal;however,thesearenotthefocusofthisreport.

Page 23: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐3 

3.2 DG CURRENTLY INSTALLED IN CALIFORNIA The2010ReportaddressedtheinstalledDGinCaliforniaundertheSGIPandCSIprogramsaswellasnetenergymetering(NEM)andnon‐NEMprojectsinterconnectedtothethreeinvestor‐ownedutilities(IOUs)throughSeptemberof2009.Sincethen,newprogramshavebeenlaunchedtopromotemoreDGinthestate,onboththecustomersideandutilitysideofthemeter,andinstallationshaveincreasedunderexistingprograms.Black&VeatchreviewedprogramdatafromtheseprogramsinitiatedinthestatetodeterminethetotalamountofDGthathasbeeninstalled.Theeightcustomer‐sideprogramsinclude:

CaliforniaSolarInitiative(CSI)

● GeneralMarket(GM)

● Multi‐familyAffordableSolarHousing(MASH)

● Single‐familyAffordableSolarHousing(SASH)

SenateBill1(SB1)Publicly‐OwnedUtility(POU)Programs

NewSolarHomesPartnership(NSHP)

Self‐GenerationIncentiveProgram(SGIP)

EmergingRenewablesProgram(ERP)–nolongeractiveasofJune2012

RenewableEnergySelf‐GenerationBillCreditTransfer(RES‐BCT)Program

ManyDGsystemsinstalledundertheseeightprogramsparticipateintheNEMtariff.EachIOUmaintainsaninterconnectiondatabasethattracksDGinstallationsontheNEMtariffandthosenotontheNEMtariff.Basedonthesedatabases,Black&VeatchsummarizedtheamountofDGinstalledthroughoutthestateundertheNEMtariff(plusnon‐NEMDGinstallations)aswellastheDGinstallationsresultingfromthestate’swholesaleDGprograms.ThewholesaleDGprogramsconsistof11:

Feed‐inTariff(FIT)

● AssemblyBill1969(AB1969)

● SenateBill32(SB32)

UtilitySolarPVPrograms(SPVP)

RenewablesAuctionMechanism(RAM)

Table3‐2belowsummarizesthebasiccharacteristicsofeachDGprogram.Eachprogramisdescribedinmoredetailinsections3.2.1,3.2.2and3.2.3.

                                                            11 In addition to these wholesale DG programs, AB 1613 established a FIT for efficient combined heat and power (CHP) systems.  SB 1122 also established a FIT for 250 MW of bioenergy, which was signed into law September 27th, 2012.  SB 1122 is planned to go into effect in 2013.  Neither the AB 1613 program nor the SB 1122 programs were investigated in detail in this report.   

Page 24: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐4 

Table 3‐2  Summary of DG Program Characteristics 

PROGRAMYEAR

INITIATEDELIGIBLE

TECHNOLOGIESELIGIBLESYSTEMSIZES

PROGRAMGOAL(MW)

CUSTOMERTYPES

NetEnergyMetering 1995 SolarPV,Wind,FC 1kW–1MW Nospecificgoal AllTypesofIOUCustomers

EmergingRenewablesProgram

1998(endedin2012)

Wind,FC(includedSolarPVuntil2007)

Upto30kW Nospecificgoal AllTypesofIOUCustomers

SelfGenerationIncentiveProgram

2001

Wind,FC,MT,GT,IC,AES,pressurereduction

turbines,bottomingcycles(includedPVuntil2007)

Upto100%ofcustomer’sannualconsumption

Nospecificgoal AllTypesofIOUCustomers

CSI–GeneralMarket 2007 SolarPV 1kW–1MW 1,940MWby2016(5%ofbudget

allocatedtoMASHand5%allocatedto

SASH)

AllTypesofIOUCustomers

CSI–Multi‐familyAffordableSolarHousing

2007 SolarPV 1kW–1MWLow‐incomeMulti‐family

Housing

CSI–Single‐familyAffordableSolarHousing

2007 SolarPV 1kW–1MWLow‐incomeSingle‐family

Housing

NewSolarHomesPartnership

2007 SolarPV 1kW–1MW 360MWby2016 NewResidentialHousing

SB1POU 2007 SolarPV 1kW–1MW 700MWby2016 AllTypesofPOUCustomers

Feed‐inTariff‐AB1969,SB380,SB32

2006‐2009SolarPV,Wind,Biomass,Biogas,SmallHydro

Upto3MW 750MW IPPs–WholesaleSide

UtilitySolarPVPrograms 2010 SolarPVVariesbyutilityfrom0.5MW

to20MW776MW

IPPsandutilities– WholesaleSide

RenewableAuctionMechanism

2011SolarPV,Wind,Biomass,Biogas,SmallHydro

3–20MW 1,299MW IPPs–WholesaleSide

Notes:FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines;AES=AdvancedEnergyStorage

Page 25: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐5 

AsshowninFigure3‐1,thegoalsforCalifornia’scurrentlyactiverenewableDGprogramstotalalmost6,000MW,abouthalfoftheGovernor’sstatedgoalof12,000MWby2020.12Notably,thetimeframeformostoftheseprogramsisbeforetheendof2016.About3,750MWofthe6,000MWisrestrictedtosolarPV.Abouthalfofthetotalisrestrictedtocustomer‐sidegenerationonly.Bycomparison,thecurrentDGprogramgoalsarewellabovethecombinedcapacityofCalifornia’snuclearplants,about4,400MW.(Itshouldbenoted,though,thatthesenuclearplantsarebaseloadresourceswithhighcapacityfactors,whileDGsolarPVsystemsarevariableresourceswithlowercapacityfactors.)

Figure 3‐1  Goals for California's Active DG Programs  

Thetotalcustomer‐sideDGinstallationsthrough2011aresummarizedinTable3‐3byutilityandtechnology.13SpecificdatasourcesincludedtheCSIWorkingDataSet,CPUCandCaliforniaEnergy

                                                            12 Note that additional DG outside these programs would likely be counted towards meeting the Governor’s goal.  The Governor’s goal calls for 12,000 new MW of localized electricity generation, sited at customer loads or close to where energy is consumed so that new transmission lines are not required and environmental impacts are minimized.  “Localized electricity generation” counted under the Governor’s goal may or may not fall under the same definition as “DG” included in this report.  Governor Brown’s goal is described at http://www.jerrybrown.org/jobs‐california%E2%80%99s‐future.   13 In this table and all others below, “#” refers to the number of individual DG installations, and “MW” refers to the combined installed capacity in ac for all DG installations in that category reported in megawatts. The tables report installations under each of the following utilities: Pacific Gas & Electric (PG&E), Southern California Edison (SCE), Southern California Gas (SCG), San Diego Gas & Electric (SDG&E), and Publicly‐Owned Utilities (POU). California 

California Solar Initiative1,940 MW

New Solar Homes360 MW

Public Utility PV SB 1700 MW

Utility Solar PV Programs776 MW

Feed‐in Tariff750 MW

Renewable Auction Mechanism1,299 MW

0 MW

1,000 MW

2,000 MW

3,000 MW

4,000 MW

5,000 MW

6,000 MW

Program

 Goals, M

W

System‐side (Wholesale)

Customer‐side 

Open to All Renewables

Solar PV Only

+ SGIP (no MW Goal)

Page 26: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐6 

Commission(CEC)programdatabases,SB1POUreports,andCPUCinterconnectiondatarequests.Theinstalledcapacity(AC‐rating)presentedhereinreflectstotalDGprojectsinstalledthroughtheendof2011,excludingqualifiedfacilities(QFs).14ThemethodologyindeterminingthetotalinstalledcapacityisdescribedinmoredetailinAppendixA.

Table 3‐3  Summary of Customer‐Side DG Installed in California by Technology (All Incentive Programs) through 2011 

TECH‐NOLOGY

PG&E SCE SDG&E* SCG POU TOTAL

# MW # MW # MW # MW # MW # MW

SolarPV 57,069 558 26,897 297 13,482 111 264 14 10,360 110 108,072 1,090

Wind 253 7 369 5 35 0.1 5 0.1 0 0 662 12

RF** 52 19 23 9 12 7 14 9 0 0 101 44

FC 25 10 15 6 7 6 10 6 0 0 57 28

MT 14 2 4 1 4 1 0 0 0 0 22 4

IC 13 7 4 2 1 1 4 3 0 0 22 12

Non‐RF*** 210 79 81 33 44 24 121 75 0 0 456 211

FC 65 11 5 1 9 3 16 2 0 0 95 17

MT 42 8 27 5 13 1 38 6 0 0 120 20

GT 4 5 0 0 3 9 4 16 0 0 11 31

IC 99 55 49 27 19 10 63 50 0 0 230 142

AES 1 1 0 0 0 0 0 0 0 0 1 1

Total 57,585 663 27,370 345 13,573 142 404 98 10,360 110 109,292 1,357

Notes:*CaliforniaCenterforSustainableEnergy(CCSE)istheCSIandSGIPprogramadministratorforSDG&E.**RenewableFuels(RF)includesbiomass,digestergas,andlandfillgas.***Non‐RenewableFuels(Non‐RF)includesnaturalgas,propanegas,wastegas,andanyinstallationsforwhichthefueltypeisnotspecified.FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines;AES=AdvancedEnergyStorage

Basedonthisanalysis,thetotalnumberofDGinstallationsinthestatereachednearly110,000bytheendof2011andprovidedatotalinstalledcapacityofover1,350MWac.Ofthistotal,

                                                                                                                                                                                                Center for Sustainable Energy (CCSE) is the CSI and SGIP program administrator for SDG&E.  Renewable Fuels (RF) include biomass, digester gas, and landfill gas; Non‐Renewable Fuels (Non‐RF) include natural gas, propane gas, waste gas, and any installations for which the fuel type was not specified. 14 QFs are facilities designated under the Public Utility Regulatory Policies Act of 1978 (PURPA) to receive special rate and regulatory treatment.  They fall into two broad categories: 1) small power production facilities less than 80 MW whose primary energy source is renewable (e.g. hydro, solar, and wind), or 2) cogeneration facilities.   

Page 27: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐7 

1,090MWacaresolarPVinstallations.Thesenumberscontinuetoincreaserapidly.Forexample,attheendof2012thetotalcustomer‐sideDGinstalledthroughoutthestatewasabout1,800MW;thisinformationisincludedinAppendixD.

Figure3‐2,Figure3‐3,andFigure3‐4belowdisplaythecumulativeDGcapacityinstalledeachyearsince1998,byprogramandbytechnology(Figure3‐4isamoredetaileddisplayofthenon‐solarDGshowninFigure3‐3).Thelargestgroupofadditionssince2009hasbeensolarPVtechnologiesdevelopedthroughtheCSIandSB1POUprograms.Updatedversionsofthefiguresbelowincluding2012dataareincludedinAppendixD.

Figure 3‐2  Cumulative DG Capacity Installed by Program 

 

0

200

400

600

800

1,000

1,200

1,400

1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011

MW Installed

California Solar Initiative

Public Utility SB 1

Self‐Generation Incentive Program

CEC Programs (Emerging Renewables Program and New Solar Homes Partnership)

Page 28: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐8 

Figure 3‐3  Cumulative DG Capacity Installed by Technology 

 

Figure 3‐4  Cumulative Non‐Solar DG Capacity Installed by Technology 

The following subsections describe the California DG programs inmore detail, and also provideinstalled capacity data for each. Section 3.2.1 covers customer‐side DG programs, Section 3.2.2

0

200

400

600

800

1,000

1,200

1,400

1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011

MW Installed

Solar PV

Non‐Solar DG

0

50

100

150

200

250

300

1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011

Non‐Solar MW Installed

Advanced Energy Storage

Internal Combustion Engines ‐ Non‐Renewable

Gas Turbines ‐Non‐Renewable

Microturbines ‐Non‐Renewable

Fuel Cells ‐Non‐Renewable

Internal Combustion Engines ‐ Renewable

Microturbines ‐ Renewable

Fuel Cells ‐ Renewable

Wind

Page 29: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐9 

covers the NEM tariff and non‐NEM DG installations, and Section 3.2.3 covers wholesale DGprograms.

3.2.1 Customer‐Side DG Incentive Programs 

Thissectiondescribestheeightcustomer‐sideDGprogramsinmoredetail.TheseprogramsprovidefinancialincentivestosupporttheinstallationofDGonthecustomer’ssideofthemetertooffseton‐siteelectricityconsumption.Eachprogramisdescribedbelow,andtheDGcapacityinstalledundereachprogramissummarizedinTable3‐4.

CaliforniaSolarInitiativeTheCSIprogramhasthreecomponentsasdescribedbelow.ItiscurrentlytheprimaryincentiveprogramforsolarPVinthestate,andisoverseenbytheCPUCwitheachutilityadministeringtheCSIinitsownserviceterritory.15ItprovideseitherrebatesintheformofupfrontExpectedPerformance‐BasedBuydown(EPBB)incentivesorongoingperformance‐basedincentives(PBI)tocustomersofthethreemajorinvestor‐ownedelectricutilitiesinCalifornia(PG&E,SCE,andSDG&E)whoinstallsolarPVsystemsbetween1kWand1MW.Itbeganin2007andhasagoalofinstalling1,940MWofsolarPVinCaliforniaby2016.

CSI–GeneralMarketTheGeneralMarket(GM)portionoftheCSIprogramencompassesthemajorityofresidential,commercial,non‐profit,governmentandindustrialcustomers.Throughtheendof2011,almost63,000projectshavebeeninstalledforatotalof689MW.Sincethen,therehasbeensignificantadditionalgrowth,andbyDecember31,2012thetotalreached91,256projectsand1,031MW.ThoughtheCSIGMprogramisnotscheduledtoenduntil2016,allthreeprogramadministratorsarenearingtheendoftheiravailableincentivesasofMarch2013.Therearetenincentivelevels,andasmoreincentivesarereserved,theincentivelevelsaredesignedto“stepdown”overtime.PG&Ehasreachedthetenthandfinalstepforbothresidentialandnon‐residentialcustomers,SCEhasreachedtheninthstepforbothresidentialcustomersandtheeighthstepfornon‐residentialcustomers,andSDG&Ehasreachedthetenthstepforresidentialcustomersandtheeighthstepfornon‐residentialcustomers.16

CSI–Multi‐familyAffordableSolarHousingUnderCSI,therearetwolow‐incomeprograms—Multi‐familyAffordableSolarHousing(MASH)andSingle‐familyAffordableSolarHousing(SASH)—thatpromotesolarPVinstallations.TheMASHprogramprovidesrebatestolow‐incomemulti‐familyhousingunitsthatinstallsolarPVsystems.FivepercentoftheCSIbudgetisallocatedtoMASH.ItsframeworkwasadoptedandtheprogramofficiallybeganinOctober2008.Through2011,143projectshavebeeninstalledforatotalof7MW.

CSI–Single‐familyAffordableSolarHousingTheSASHprogramisalsopartoftheCSIandprovidesrebatestolow‐incomesingle‐familyhousingunitsthatinstallsolarPVsystems.FivepercentoftheCSIbudgetisallocatedtoSASH.ItbeganinNovember2007,andisadministeredbythenon‐profitorganizationGRIDAlternativesonbehalfoftheCPUC.(InTable3‐4,theMWinstalledfortheSASHprogramareallocatedtoeachProgramAdministratorbasedontheshareofthetotalnumberofinstallations.)Through2011,1,185projectshavebeeninstalledforatotalof3MW.

                                                            15 California Center for Sustainable Energy (CCSE) is the CSI and SGIP program administrator for SDG&E. 16 http://csi‐trigger.com/, accessed September 26, 2012.   

Page 30: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐10 

CSISummaryTable3‐4summarizesthestatusoftheCSIprogramthroughtheendof2011byprogramandutility.WhiletheMASHandSASHprogramshave10percentoftheoverallprogrambudgetallocatedtothem,theyonlycomprisedabout1percentoftheMWinstalledthroughtheendof2011.

Table 3‐4  Summary of CSI Installations by Program and Utility (All Solar PV) 

PROGRAM

PG&E SCE SDG&E* TOTAL

# MW # MW # MW # MW

GeneralMarket 35,194 384 19,305 226 8,452 79 62,951 689

MASH 74 3 38 3 31 2 143 7

SASH 613 2 410 1 162 0.5 1,185 3

CSITotal 35,881 389 19,753 230 8,645 81 64,279 700

Notes:*CaliforniaCenterforSustainableEnergy(CCSE)istheCSIandSGIPprogramadministratorforSDG&E.

Self‐GenerationIncentiveProgramTheSelf‐GenerationIncentiveProgram(SGIP)wasinitiatedin2001toprovidecustomersincentivestoinstalltheirowngenerationandhelpreducepeakelectricitydemandinthestate.ItisoverseenbytheCPUCwitheachutilityadministeringtheSGIPinitsownserviceterritory.Itprovidesrebatestocustomersoffourinvestor‐ownedutilitiesinCalifornia(PG&E,SCE,SCG,andSDG&E)whoinstallDGsystems.Thecurrentlistofeligibletechnologiesincludes:windturbines,fuelcells,gasturbines,microturbines,internalcombustionengines,advancedenergystorage,pressurereductionturbines,andbottomingcycles.Systemsizescannotexceed100percentofthecustomer’speakload,exceptwindturbinesmaybesizedupto200percentofthecustomer’speakload.SolarPVsystemsover30kWwereaneligibletechnologyuntil2007,whentheCSIprogrambegan;PVsystemsunder30kWwerepartoftheERP.Nearly1,500projectshavereceivedrebatesunderSGIPforatotalof406MW.The2011SGIPImpactEvaluationreportnotesthatthereareanumberofSGIPprojectsthathavebeendecommissioned(i.e.theyhavebeenremovedfromoperation),andalsoanumberwhoseoperatingstatusisunknown.Table3‐5belowshowsthetotalrebatedcapacityunderSGIP,buttherearecurrently20MWofdecommissionedsystemsand45MWofsystemswithunknownoperatingstatus.ThedecommissionedsystemsarenotincludedinthepeakdemandimpactanalysisdescribedinSection4.4.

Page 31: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐11 

Table 3‐5  Summary of SGIP Installations by Technology and Utility 

TECHNOLOGY

PG&E SCE SDG&E* SCG TOTAL

# MW # MW # MW # MW # MW

SolarPV 493 81 232 36 103 13 90 13 918 143

Wind 7 6 3 2 0 0 0 0 10 8

RF** 52 19 20 9 12 7 14 9 98 44

FC 25 10 12 5 7 6 10 6 54 28

MT 14 2 4 1 4 1 0 0 22 4

IC 13 7 4 2 1 1 4 3 22 12

Non‐RF*** 210 79 81 33 44 24 121 75 456 211

FC 65 11 5 1 9 3 16 2 95 17

MT 42 8 27 5 13 1 38 6 120 20

GT 4 5 0 0 3 9 4 16 11 31

IC 99 55 49 27 19 10 63 50 230 142

AES 1 1 0 0 0 0 0 0 1 1

Total 763 185 336 80 159 44 225 97 1,483 406

Notes:*CaliforniaCenterforSustainableEnergy(CCSE)istheCSIandSGIPprogramadministratorforSDG&E.**RFincludesthefollowingfueltypes:biomass,digestergas,andlandfillgas.***Non‐RFincludesthefollowingfueltypes:naturalgas,propanegas,wastegas,andinstallationsforwhichthefueltypeisnotspecified.ThenumberslistedinthistablerepresentallrebatedsystemsunderSGIP,includingdecommissionedsystemsandsystemswhoseoperatingstatusiscurrentlyunknown.FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines;AES=AdvancedEnergyStorage

EmergingRenewablesProgramTheCECadministerstheEmergingRenewablesProgram(ERP),whichprovidesrebatestocustomersofCaliforniautilitiesforinstallingsolarPV,wind,orfuelcellsystemsunder30kW.Itwasestablishedin1998tostimulatemarketdemandfordistributedgenerationtechnologies,andwastheprimaryincentiveprogramforthesetechnologiesuntilthebeginningoftheSGIP.AftertheCSIprogrambeganin2007,solarPVsystemswerenolongereligiblefortheprogram.TheprogramwasdiscontinuedinlateJune2012inaccordancewithSenateBill1018(Stats.2012,ch.39).Nearly29,000projectshavebeeninstalledunderERPforatotalof128MW.

Page 32: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐12 

Table 3‐6  Summary of ERP Installations by Technology and Utility 

TECHNOLOGY

PG&E SCE SDG&E OTHER* TOTAL

# MW # MW # MW # MW # MW

SolarPV 17,569 79 6,175 29 4,123 15 174 1 28,041 123

WindTurbines** 246 1 366 3 35 0.1 5 0.1 652 4

FuelCells 0 0 3 0.4 0 0 0 0 3 0.4

Total 17,815 80 6,544 32 4,158 15 179 1 28,696 128

Notes:*Inadditiontothethreelargeinvestor‐ownedelectricutilities,someothersmallutilitiesparticipatedintheERP,andtheseinstallationsareincludedinthe“Other”columns.**Installationscategorizedas“SolarPV&Wind”areincludedinthe“WindTurbines”category.

NewSolarHomesPartnershipTheNewSolarHomesPartnership(NSHP)isadministeredbytheCECandbeganin2007asacomplementaryprogramtotheCSI.ItsfocusistoprovidefinancialincentivesandothersupporttohomebuilderstoencouragethemtointegratesolarPVintohighlyenergy‐efficientnewresidentialhousingbuiltinCalifornia.Theultimategoaloftheprogramis360MWofsolarPVonnewresidentialdevelopmentsby2016.Nearly4,500projectshavebeeninstalledunderNSHPforatotalof14MW.

Table 3‐7  Summary of NSHP Installations by Utility 

TECHNOLOGY

PG&E SCE SDG&E TOTAL

# MW # MW # MW # MW

SolarPV 3,126 9 737 2 611 3 4,474 14

SB1POUProgramsSenateBill1,whichtookeffectin2007,requiredallpublicutilitiestoestablishincentiveprogramsforsolarPVsimilartotheCSIprogram.Eachutilityadministersitsownprogram.Theoverallgoalisforpublicutilitiestoinstall700MWby2016.TheCECtracksSB1installationsofeachpublicutility.LosAngelesDepartmentofWater&Power(LADWP)andSacramentoMunicipalUtilityDistrict(SMUD)arethetwolargestpublicutilitiesinCaliforniaandhavethemajorityofPOUcustomerinstallationsinthestate.AllPOUscombinedhaveinstalledover10,000solarPVprojectsforatotalof110MW.

Page 33: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐13 

Table 3‐8  Summary of SB 1 POU Installations by Utility 

TECHNOLOGY

LADWP SMUD ALLOTHERS TOTAL

# MW # MW # MW # MW

SolarPV 3,027 32 2,952 31 4,381 46 10,360 110

RenewableEnergySelf‐GenerationBillCreditTransferProgramTheRenewableEnergySelf‐GenerationBillCreditTransfer(RES‐BCT)ProgramwascreatedasaresultofAB2466(Laird,2008).ThetariffsapprovedbytheCPUCunderthisprogramallowlocalgovernmentstogenerateelectricityatoneaccountandtransferanyavailableexcessbillcredits(indollars)toanotheraccountownedbythesamelocalgovernment.DGsystemseligibleunderthisprogrammustbelessthan5MW,andthereisastatewideprogramlimitof250MW.Asoftheendof2011,therewerenoknownDGinstallationsparticipatinginthisprogram.

3.2.2 NEM Tariff and Non‐NEM DG Installations 

TheNEMtariffwasestablishedbylegislationandisimplementedbytheCPUCforelectriccustomerswhoinstallsolar,wind,biogasorfuelcellsystemsof1MWorless.TobeeligiblefortheNEMtariff,generationmustbesizedtoprimarilyoffseton‐siteelectricalload.UndertheNEMtariff,acustomerisallowedtosendpowertotheutilitywhentheyaregeneratingmorepowerthantheyconsume.Customersreceiveafullretailratecreditforallgenerationexportedtothegridoverthecourseofayear,uptotheamountoftheirannualusage.ThiscreditcanbeusedtooffsetallkWh‐basedchargesexceptminimummonthlychargesorcustomercharges.Ifthecustomer’sexportsoverthecourseofayeararegreaterthanthecustomer’sannualusage,theyarecompensatedfortheexcessattheday‐aheadmarketprice(whichisgenerallylowerthanretailrates).Themajorityofcustomer‐sideDGinstallationstakeadvantageofthistariff(summarizedinTable3‐9),althoughtherearesomewhichdonot(summarizedinTable3‐10),oftenbecausetheydonotanticipateeverexportingpowerbacktothegrid.

EachIOUtracksNEMandnon‐NEMDGinstallationsthroughinterconnectioninformationandreportsthisdatatotheCPUCquarterlythroughthe“DistributedGenerationInterconnectionDataRequests”(DGInterconnectionDataset).Thereareatotalofabout1,580MWofreportedinstallationsinterconnectedtothethreeIOUs,bothNEMandnon‐NEM.TheseinstallationsarenotadditivetotheinstalledcapacityreportedinSection3.2.1.Thedatashowninthetablesbelowarebasedsolelyontheinterconnectiondatasets,andhavenotbeenindependentlyverifiedbyBlack&Veatch.

Page 34: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐14 

Table 3‐9  Summary of NEM DG Installations by Technology and Utility 

TECHNOLOGY

PG&E SCE SDG&E TOTAL

# MW # MW # MW # MW

SolarPV 59,946 616 27,998 310 13,483 116 101,427 1,042

Wind 149 4 316 5 42 0.1 507 9

FC 79 13 27 5 0 0 106 18

IC 11 94 0 0 0 0 11 94

Multiple/Other* 123 26 65 6 2 0 190 32

Total 60,308 753 28,406 327 13,527 116 102,241 1,196

Notes:*Multiple/otherincludesmultipletechnologiesortechnologiesthatdonotfallintotheDGcategoriescoveredbythecustomer‐sideDGincentiveprogramsabove.FC=FuelCells;IC=InternalCombustionEnginesThistableincludesallNEMinstallations,includingthoseontheStandardNEMtariffandthoseontheNEMW,NEMFC,andNEMBIOtariffs.StandardNEMandNEMWprovidethefullretailrate,whileNEMFCandNEMBIOcoveronlythegenerationportionoftherate.

Page 35: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐15 

Table 3‐10  Summary of Non‐NEM DG Installations by Technology and Utility 

TECHNOLOGY

PG&E SCE* SDG&E* TOTAL

# MW # MW # MW # MW

SolarPV 249 39 40 15 ‐ ‐ 289 54

Wind 2 2 ‐ ‐ ‐ ‐ 2 2

FC 13 7 ‐ ‐ ‐ ‐ 13 7

MT 44 10 ‐ ‐ ‐ ‐ 44 10

GT 15 89 ‐ ‐ ‐ ‐ 15 89

IC 122 122 ‐ ‐ ‐ ‐ 122 122

Multiple/Other** 19 99 ‐ ‐ ‐ ‐ 19 99

Total 464 368 40 15 ‐ ‐ 504 383

Notes:*SCEandSDG&Edidnotreportanynon‐NEMinstallations(exceptthatSCEreportedasmallnumberofsolarPVsystems),becausetheCPUCdidnotrequirethemtobereported.**Multiple/otherincludesmultipletechnologiesortechnologiesthatdonotfallintotheDGcategoriescoveredbythecustomer‐sideDGincentiveprogramsabove.FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines

3.2.3 Wholesale DG Programs 

Inadditiontothecustomer‐sideprogramsdescribedabove,CPUCalsooverseesthreeprimarywholesalerenewableDGprograms,inwhichprojectsareinterconnectedontheutilitysideofthemeter.17TheseprogramsrequiretheIOUsinCaliforniatosignpowerpurchaseagreements(PPA)withlargerDGprojectsbetween1and20MW.Addedtogether,thegoalsofthewholesaleDGprogramsareapproximately3,150MW.Asoftheendof2011,atotalof101MWhavebeeninstalledundertheseprograms.

Feed‐InTariff(AB1969andSB32)Thefeed‐intariff(FIT)programbeganinCaliforniain2006,whenAssemblyBill1969(Yee,2006)waspassedtoauthorizespecialtariffsandstandardcontractsforpublicwaterandwastewaterutilitiestoinstallrenewableenergyprojectsupto1.5MW.ThesetariffsweremadeeffectivebytheCPUCinFebruary2008,andappliedonlytoPG&EandSCE.SenateBill380(Kehoe,2008)createdasingletariffforallutilitycustomersandaddedSDG&E.SenateBill32(Negrete‐McLeod,2009)waspassedin2009andincreasedeligibleprojectsizeto3MW.Allpublicandinvestor‐ownedutilitiesinCaliforniaarerequiredunderSB32todevelopFITprograms.Theoverallstatewidegoalis750MWunderSB32,butthereisnosetdatebywhichutilitiesmustreachthistarget.

                                                            17 Qualifying facilities under PURPA (for renewables and gas‐fired generation), efficient combined heat and power under AB 1613, and bioenergy facilities under SB 1122 programs are other programs in which  distributed sellers may be interconnected to the utility distribution system, and thus be considered DG.  These programs are not included in this report.   

Page 36: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐16 

Twenty‐oneprojectshavebeencontractedandbroughtonlinethroughAB1969bytheIOUstotaling18MW.ThesearesummarizedinTable3‐11belowbytechnology.TherewerenorecordedinstallationsunderSB32asoftheendof2011.

Table 3‐11  Summary of FIT – AB 1969 Installations by Technology 

TECHNOLOGY

PG&E SCE SDG&E TOTAL

# MW # MW # MW # MW

Biogas 3 2 1 1 4 6 8 9

Biomass 1 1 0 0 0 0 1 1

SmallHydro 10 6 0 0 0 0 10 6

SolarPV 0 0 2 2 0 0 2 2

Total 14 8 3 3 4 6 21 18

UtilitySolarPVProgramsIn2009and2010,SCE,PG&EandSDG&EwereauthorizedbytheCPUCtoinitiateSolarPVPrograms(SPVP)toprocuretheoutputfromwholesalesolarPVprojectsthroughtwomechanisms:1)developingtheirownutility‐ownedgeneration(UOG)projects,and2)signingcontractswithindependentpowerproducers(IPP)intheirserviceterritories.Originally,theprogramstotaled1,100MW,butSCEandSDG&EaskedforaportionoftheprogramtobemergedintotheRenewableAuctionMechanismprogram(describedinnextsection).Thecurrentgoalis776MW.Systemsizesvaryacrosstheutilities,butgenerallyrangefrom500kWuptoamaximumof20MW.Thegoalsforeachutilityareasfollows:

PG&Ehasatotalprogramgoalof500MW,splitevenlybetweenUOGandIPPprojects.InDecember2012,PG&EsubmittedarequesttotheCPUCtomove252MWofsolarPVfromthisprogramtotheRAMprogram.

SCEoriginallyhadaprogramgoalof500MW,splitevenlybetweenUOGandIPPprojects.However,SCEsoughtCPUCpermissiontoreducethisto250MW,againsplitevenlybetweenUOGandIPPprojects.SCEsoughtapprovaltomove225MWtotheRAMprogram,whichtheCPUCgranted.18

SDG&Ehadanoriginalprogramgoalof100MWwhichissplitinto26MWofUOGprojectsand74MWofIPPprojects.SimilartoSCE,SDG&Esoughtandreceivedapprovaltomovethe74MWofIPPprojectstotheRAMprogram.19

Table3‐12showsthatasoftheendof2011,83MWhadbeeninstalledtowardthosegoals.20

                                                            18 Southern California Edison, “Southern California Edison Company’s (u 338‐e) Third Annual Compliance Report on the Solar 

Photovoltaic Program”, July 2, 2012, available at: http://www3.sce.com/sscc/law/dis/dbattach4e.nsf/0/3D14CD4ADEC4C8A488257A2F0080B23D/$FILE/A0803015_R1105005+‐+SCE+3rd+Annual+SPVP+Compliance+Report_Public.pdf  19 CPUC, “RPS Quarterly Report – 1st and 2nd Quarter 2012”, available at: http://www.cpuc.ca.gov/NR/rdonlyres/2060A18B‐CB42‐4B4B‐A426‐E3BDC01BDCA2/0/2012_Q1Q2_RPSReport.pdf  

Page 37: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Distributed Generation Overview  3‐17 

Table 3‐12  Summary of IOU Solar PV Program Installations by Ownership 

OWNERSHIP

PG&E SCE SDG&E TOTAL

# MW # MW # MW # MW

Utility‐owned 4 52 7 12 0 0 11 64

IndependentPowerProducer 0 0 8 19 0 0 8 19

Total 4 52 15 31 0 0 19 83

RenewableAuctionMechanismTheRenewableAuctionMechanism(RAM)programbeganin2011whentheCPUCapproveditasasimplifiedprocurementmechanismforwholesalerenewableDGprojects.TheCPUCinitiallyauthorizedtheIOUstoprocure1,000MW,whichwasthenexpandedto1,299MWbyCPUCdecisionsD.12‐02‐035andD.12‐02‐002.Projectsbetween3and20MWmustmeetcertaineligibilitycriteria,andmustsignapre‐approvedstandardPPA.Auctionsareheldtwiceperyear,withthefirstauctioninNovember2011.ContractsfromthisfirstauctionwereapprovedbytheCPUCinApril2012,sotherewerenooperationalprojectsasoftheendof2011.Additionalauctionsareplannedin2012andbeyond.

                                                                                                                                                                                                20 The totals are based on the CPUC RPS Contract database.  However, at least in the case of SCE, they do not appear to exactly match the numbers in the compliance filing referenced above.   

Page 38: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐1 

4.0 DG Impacts on the Transmission and Distribution System Asdiscussedinthissection,DGmayhavepositiveandnegativeimpactsonthetransmissionanddistributionsystem.BecauseofthedirectconnectionofDGtothedistributionsystem,impactsareexpectedtobemostprevalentatthedistributionlevel.However,asthepenetrationofDGincreases,theimpactswillbegintobeobservedonthetransmissionsystem.

ManyoftheimpactsofDGareattributabletothefactthatthegridwasnotoriginallydesignedtoacceptgenerationonthedistributionsystem.Traditionally,centralizedgenerationwasconnectedtothetransmissionsystem,whichsuppliedthedistributionsystem,whichinturnfedthemajorityofloads.Thisdesignisdepictedinthefigurebelow,illustratingtheflowofelectricpowerfromgeneration,throughtransmission,throughthedistributionsystem,andontocustomerloads.Thedistributionsystemisgenerallydefinedastheportionofthegridwithavoltageof40kVorless.21Thetransmissionsystemisgenerallytheportionofthegridthatoperatesabove40kV.

Figure 4‐1  Typical Electric Power System Single‐Line Diagram22

Thefollowingtopicsarecoveredinthissection:

Section4.1–ImpactsofDGonthedistributionsystem                                                            21 Distribution voltage definition per the Institute of Electrical and Electronics Engineers (IEEE) Standard 141 is a nominal voltage of 40 kV or less. Often, voltage levels between 40 kV and 138 kV are considered to be “subtransmission;” however, this report discusses both subtransmission and transmission as transmission. Each utility in California operates its own distribution system of varying voltage levels. 22 J. Keller and B. Kroposki, “Understanding Fault Characteristics of Inverter‐Based Distributed Energy Resources,” National Renewable Energy Laboratory, Golden, CO, January 2010, p. 31. 

Page 39: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐2 

Section4.2–ImpactsofDGonthetransmissionsystem

Section4.3–EffectsofaDGsystem’ssizeandlocationonitsgridimpacts

Section4.4–ImpactthatDGhasontheCAISOpeakdemand

Whileanumberofimpactsaredescribedinthissection,itisimportanttonotefewhavebeenwidelyobserved.Iftheyhavebeenobserved,itisdifficulttoconclusivelyattributethemtocustomer‐sideDGsystems.Theimpactsdescribedherehavebeenidentifiedthroughmodeling,research,orlimitedreal‐worldobservations.Thelackofobservedimpactscanbeattributedtoseveralreasons:

Currentlyabout90percentofconnectedDGcapacityisonthecustomer‐sideofthemeter

Customer‐sideDGsystemsaretypicallysmall

ThecurrentpenetrationlevelofDGislow

Atthegivenpenetrationlevels,theinterconnectionprocessandrequirementshavesuccessfullymitigatedimpactsbeforetheyoccur

ThereisagenerallackofmonitoringDGsystemoutput23andoftheeffectsofDGsystemsonthegrid(thatis,utilitiesdonothavetheappropriatetoolstosystematicallycollectandevaluatedataonproblemsorbenefitsattributabletoDG).

Forthesereasons,itisdifficulttoquantifytheimpactsofcustomer‐sideDGonthegrid.ItisexpectedbymanythatimpactswillincreaseasDGpenetrationincreases.However,tobeabletoquantifytheimpacts,theutilitieswillneedtobeginsystematicallymonitoringforthemandthenassociatingthemwithDGsystems.Furthermore,theutilitieshavenotedthatdatacollectionormonitoringalonewillnotnecessarilyleadtoabetterunderstandingoftheimpactsofDGonthegrid.FormalresearchanddevelopmentisrequiredtofacilitatebetterunderstandingofissuesandbenefitscorrelatedtoDG.

QuantificationofDGimpactsisvitallyimportanttotheDGindustry,utilitiesandpolicymakers.ItwillinformdecisionsthatseektofurtherDGgoalswhileminimizingthenegativeimpactsofDGandmaximizingitsbenefits.

4.1 DISTRIBUTION SYSTEM RELIABILITY AND OPERATION  ImpactsofDGondistributionsystemreliabilityandoperationaredescribedinthissection.Itisimportanttonote,however,thatimpactsarehighlydependentonthelocalfeederconfigurationandloadinglevel.24Impactsdiscussedinthissectionincludethefollowing:

Distributionsystemlinelosses

Peakdemandreduction

                                                            23 As noted above, currently only units 1 MW or larger have telemetering requirements.  Smaller units do not have this requirement since at lower penetrations the expectation was that the impacts would be minimal, the cost to collect the data would be relatively high, and processing of this additional data may not be necessary. This assumption should be revisited as penetration increases or the operational requirements for DG change. In that vein, California utilities have recently proposed telemetering requirements for certain wholesale DG smaller than 1 MW where the power will be exported and scheduled into CAISO’s market. As of this writing, the CPUC has not yet evaluated those proposals.   24 Itron, “Final 2007‐2009 Impact Evaluation,” Submitted to: Southern California Edison and California Public Utilities Commission Energy Division, February 2010, p. 4‐30.  

Page 40: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐3 

Deferreddistributionsystemupgrades

Frequencycontrol25

Voltagecontrol

Reversepowerflow

Operationflexibility

4.1.1  Distribution System Line Losses 

DGsystemshavethepotentialtoreducetheamountofenergylostduetotransmittingenergyoverlongdistancesondistributionlines.Typically,energytravelsfromacentralizedgeneratingsourcethroughsubstationstoload.BecauseDGsupplieslocalloads,lessenergyisrequiredtotravelfromcentralizedsources,anddistributionlossesmaybereduced.However,insomecasesDGmayactuallyincreaselosses.Forexample,ifaDGsystemisinjectingmorepowerontothedistributionsystemthanconductorswereoriginallydesignedfor,lossescouldactuallyincrease.

Someresearchershavemodeleddistributionsystemsandfoundtheretobeanoptimalpenetrationleveltominimizelinelossesonasinglefeeder.Forexample,UCIrvineandPG&Eresearcheshavemodeledtwofeedersandfoundtheoptimalpenetrationleveltoreducelinelossesisapproximately60percent.Abovethoselevelslinelossesbegintoincrease.26Asareference,currentpenetrationlevelsinCaliforniaaregenerallybelow10percent.

DuringinterviewswithIOUs,distributionlinelosseswerenotmentionedasanimpactofDG.WhilereductionindistributionlinelossesshouldtheoreticallybeoccurringasDGincreasesandreversepowerflowislimited,theutilitiesarenotsystematicallyquantifyingthisbenefit,orpossiblecost,andassociatingittoDG.Itmaybepossibletomorecloselytrackthismetricasutilitiesgainmoreintelligenceaboutdistributionsystemperformancethroughsmartgridupgrades.

4.1.2 Peak Demand Reduction 

TotheextentDGoutputiscorrelatedwithlocalloads,DGmayreducethepeakloadonsomepartsofthedistributionsystem.TheamountofpeakdemandreductionwilldependonthetypeofDGresource,itsoperatingpattern,andtheloadprofileforthefeederorsubstation.Peakdemandreductionisgenerallyviewedasapositiveimpactasitreducestherequiredcapacityandequipmentforthesystem.PeakdemandreductionisexploredfurtherinSection4.4,whichanalyzestheimpactontotalsystempeakaswellassomeselecteddistributionfeeders.

4.1.3 Deferred Distribution System Upgrades 

DGcanreducetheutilizationofthedistributionsystemaslessenergyisrequiredtobetransportedoverthesystem(asdescribedabove),andthisisgenerallyviewedasapotentialpositiveimpactofDG.WithinstallationofDG,thenetloadseenbythedistributionsystemmaynothaveincreasedassignificantlyasexpected,orthesystemmightageslowerthanexpectedbecauseitisusedless.Tosomeextent,plannedupgradestothedistributionsystemforcapacityincreasesorreplacementofdevicesbecauseofwearandtearmaybepartiallydelayedordeferredifDGsystemsarelocated                                                            25 It should be noted that the frequency of the distribution system and transmission system is the same, and therefore impacts to frequency on the distribution system similarly affect the transmission system.  For simplicity, the frequency control impact is listed and discussed under distribution system impacts here.   26 J. Payne, F. Gu, J. Brouwer, S. Samuelsen, M. Heling, J. Carruthers, D. Pearson, “Evaluation of High Pen PV in Distribution Circuits”, High Penetration Solar Forum 2013, February 2013. 

Page 41: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐4 

anddesignedappropriately.27However,systemupgradesandmaintenanceareimpactedbyseveralfactorssuchasage,temperatureandweatherconditions,surroundingequipment,andsoon.

Unfortunately,basedoninterviewswithIOUs,theywereunawareofDGsystemsinCaliforniathathaveprovidedthisbenefit.Infact,IOUsindicatedthattheinstallationofsomeDGsystemscanrequireupgradestothedistributionsystem;forinstance,sinceDGincreasesthevoltageatthepointofinterconnection,IOUsmayneedtoperformupgradestopreventvoltagefromexceedingallowablelimits,particularlyifthereisahighlevelofgenerationduringoff‐peakconditions.Further,increasedcyclingofequipment(suchascapacitorbanks)duetointermittentrenewablesmayincreasemaintenancerequirements.

ToachievethisbenefitwouldrequirestrategiclocationofDGonthedistributionsystem.UtilitiesalsodesirethattheDGbeavailableordispatchable,includingpotentiallycontractualobligationstoprovidereliablepower.However,therearenoincentivesforDGsystemownersordevelopers,specificallywholesaleDG,tolocateDGinlocationsthatprovidethemaximumbenefitintheformofdeferreddistributionsystemupgrades.Thismaybeabarriertofurthercost‐effectivedeploymentofDG,asdiscussedinSection5.2.1.

Inaddition,PG&Ehassuggestedthatdistributiondesignstandardsmayneedtobereviewedtoseeifmodificationstosystemdesigncouldincreasethebenefitsofdistributedgeneration,oratleastmitigatetheimpactssuchthathigherpenetrationscouldbeachievedataloweroverallcost.

4.1.4 Frequency Control 

TheCPUCRule21andIEEEstandardsprovidefrequencyrequirementsforDGconnectingtothedistributionsystem.TheserequirementsprovidetheupperandlowerlimitsforthefrequencyoftheDGsystem.Whenthefrequencygoesoutsideofthespecifiedrange,theDGsystemswillautomaticallybetrippedoffline.

Energygeneratingtechnologiesthathaveinertia,suchascombustionturbines,providefrequencysupport–meaningtheycanhelpadjustthefrequencyofthegrid.Thiscanbedonebyeitherspeedinguporslowingdowntherotationofthedevices.

ThemostprevalentDGtechnologies,suchassolarPV,donotprovidefrequencysupport.Infact,thesesystemsarerequiredtotripoffline(UL1741)intheeventofanoverorunderfrequencysituation.TheneteffectofDGsystemstrippingofflinecould,inthefuturewhenhigherpenetrationisachieved,exacerbateanunderfrequencysituation;thisisviewedasanegativeimpactofDG.

Whilefrequencyimpactshavebeenseeninmodelsandactualsystemfrequencydata,theIOUsarenotabletoattributetheseimpactstocustomer‐sideDGsystems.TheexpectationisthatasDGpenetrationincreasesutilitieswillbeabletoattributetheseimpacts,ortheexacerbationoftheseimpacts,toparticularsystems.

Changestoinverterstandards(specificallyIEEE1547),suchasallowingawiderrangeofvoltageandfrequencyconditions,couldhelpalleviatechallengeswithinadvertentvoltageandfrequencytrips.SmartinverterscouldalsohelpmitigatethefrequencyimpactofDG.Smartinvertersmaybeabletoprovidefrequencysupport,oravoidtrippingofflineduringsomeunder/overfrequencyevents.                                                            27 U.S. Department of Energy, “The Potential Benefits of Distributed Generation and Rate‐Related Issues that May Impede Their Expansion,” February 2007, p. 3‐11. 

Page 42: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐5 

4.1.5 Voltage Regulation 

Voltageregulationisacorefunctionofutilityoperations,andDGhasthepotentialtomakevoltageregulationsignificantlymoredifficultforutilities.Voltageistypicallycontrolledlocallyatthedistributionlevel.Addinggenerationonafeederthatnormallyservesloadwillincreasethevoltageatthepointofinterconnection.IftheDGissolar,wind,oranysortofvariableDG,therecouldbevoltagefluctuationsonthefeeder.Figure4‐2belowillustratesanintermittentsolarresource.ThevariabilityofsolarPVgenerationcanbequitehigh,particularlyonpartlycloudydays.

Figure 4‐2  Sample Solar Resource Data for One Day28 

PassingcloudcoverandotherdisturbancescanaffectDGoutput,whichaffectsgridvoltage,andmayultimatelyimpactsystemoperationtriggeringprotectiondevices.AnNRELreport,ImpactofSolarSmartSubdivisionsonSMUD’sDistributionSystem,indicatedthatatlowPVpenetrationlevels,noadversevoltageregulationeffectswerefound;however,aspenetrationsincrease,aneffectmaybeseen.29ThevoltagefluctuationmayleadtovoltagesoutsideacceptablerangesimposedbytheCPUCRule2(ConservationVoltageRegulation–CVR)andIEEEstandards.Fluctuationinvoltagecancausewearandteartoelectricalequipmentownedbycustomersandutilities,andisviewedasanegativeimpactthatDGsystemscanhaveonthedistributionsystem.

Atcurrentpenetrationlevels,widespreadvoltageissueshavenotbeenobserved,buttheyareexpectedtooccurmoreoftenasmoreDGsystemsareinstalled.Basedoninterviewswithdistributionengineers,theIOUshaveobservedsomeinstancesofvoltageimpacts.SDG&Eindicatedtheyhaveexperiencedadversevoltagefluctuationonafeederhostingtwo1‐MWNEMsolarPVinstallations.OnaSCEfeeder,a400kWPVsystematfulloutputincreasedvoltageenoughtotriptheinverteroff;becauseofthis,SCEinstalledanewtransformerandchangedthetapsettingtohandlethevoltagefluctuationsatitsowncost.

                                                            28 M. Patsalides, A. Stavrou, G. Makrides, V. Efthimiou and G. E. Georghiou, “Harmonic Response of Distributed Grid Connected Photovoltaic Systems,” University of Cyprus, Nicosia, p. 3. 29 P. McNutt, J. Hambrick, M. Keesee, and D. Brown, “Impact of SolarSmart Subdivision on SMUD’s Distribution System,” National Renewable Energy Laboratory, Golden, CO, July 2009, p. 33. 

Page 43: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐6 

SCEindicatedthattheyhaveobservedinstallationsexperiencingovervoltagesexceedingpermittedvoltagelevelsbyupto200percent.Theseovervoltagecasesarecausedbyaneffectreferredtoas“transientovervoltage.”ForDGsystems,thiseffectistemporaryandoccurswhenaPVDGsysteminverterdisconnectsduringlowloadconditions.Asaresultoftransientovervoltages,thePVsystem’sisolationswitchmayfailifnotsizedappropriately,andcustomerloadmaybeexposedtoovervoltages.SCEisworkingwithinvertermanufacturerstomitigatethisissueandestablishproperdesignprotocolsforDGPVsystems.

Similartofrequencycontrol,aDGsystemisrequiredtotripofflineduringanunder‐orovervoltageevent,perUL1741inverterrequirements.Losinggenerationcausesadecreaseinvoltage;thereforethetrippingofflineofDGsystemscanexacerbateanundervoltagesituation.

Somemitigationapproacheshavebeendevelopedorimplemented,forexampleloadtapchangersontransformershavebeenusedtomitigatevoltageissues.AllowinginverterstoprovideVArsupportorinstallingVArcontrollersisatechnicallyviableoption.However,thismaynotbepracticalforcustomer‐sideDGsystemsgiventheirsmallsizeanddistributedlocations,andthefactthatutilitiesdonotcurrentlyhavecontrolovercustomer‐ownedequipment.Changinginverterstandardstonotrequiredisconnectionduringtemporarylowvoltageeventsisamitigationapproachreferredtoaslow‐voltageride‐through(LVRT).In2008,GermanyrequiredLVRTonthedistributionsystem.30SDG&Eindicatedthatseveralvoltagemitigationapproachesaretechnicallyavailable,butthereislimitedresearchavailabletoindicatethebestapproach.InSection7.0,anapproachisdiscussedforastudytoexaminebestpracticesforaddressingthevariousvoltageandfrequencyimpactsofDGonthedistributionsystem.

4.1.6 Reverse Power Flow 

AsDGpenetrationincreases,thelikelihoodofgenerationflowingbackontothedistributiongridincreases.Thisisoftenreferredtoas"reversepowerflow."ReversepowerflowcanpotentiallynegativelyimpactthecoordinationofDGinstallationswithexistingdistributionfeederautomatedprotectionfeaturesandotherequipment.

Distributionsystemsarenotgenerallydesignedtoaccommodatetheinterconnectionofwidespreadparallelgeneration.Rather,theyaredesignedtodistributepowerproducedfromcentralizedgenerationconnectedtothetransmissionsystem.Existingdistributionsystemsaregenerallydesignedtoaccommodatepowerflowoutofthedistributionsystemandmayhaveissueswithexcessivepowerflowingintothesystem.Examplesofissuesthatmightoccurinthissituationinclude:

Sometypesofequipment,suchasloadtapchangersthatregulatevoltage,maynotfunctioncorrectlyifelectricityisflowingoppositetheiroriginaldesign.

PVsystemsmaynotdetectfaultswithlowshortcircuitcurrentonthedistributionsystemandthereforemayremainconnectedtothedistributionsystem.ThismayinterferewiththedistributionsystemoperationasthePVsystemmaybefeedingthefaultandtherestofthedistributionsystemmaynotdetectthefaultasitotherwisewouldwithouttheDGPVsystem.

Networkdistributionsystems,whicharetypicallyusedinurbanareas,generallycannothandlesignificantpowerflowsintothesystem.Thisisbecausethereisadevicespecifically

                                                            30 J. Keller and B. Kroposki, “Understanding Fault Characteristics of Inverter‐Based Distributed Energy Resources,” National Renewable Energy Laboratory, Golden, CO, January 2010, p. 31.  

Page 44: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐7 

usedfornetworksystemsthatinhibitspowerflowintothesystemforsystemprotectionreasons.31ThislimitsthesizeandamountofPVthatcanbeinstalledonthesystem.

OnespecificexampleofpotentialreversepowerflowimpactscomesfromlargerPVsystems(>20kW)thathaveasingle‐phaseoutputbecausetheyareinstalledonasingle‐phaseserviceatamulti‐familyhousingcomplex—thisoccasionallyhappenswithsystemsinstalledundertheMASHprogram.Becauseoftheirsize,systemsover20kWusuallyhaveathree‐phaseoutput.Butinsituationswhereasingle‐phaseoutputisrequiredbecauseofthelocation,thelargeamountofpowerthatmaybeexportedtoonlyoneofthethreephasesonthedistributionnetworkcouldcreateasignificantphaseimbalance.Distributionoperationscouldbenegativelyimpactedifthisweretooccur.

Theneteffectofreversepowerflowispossiblenegativeinteractionwiththedistributionsystem’sprotectionschemes,causingpartsofthesystemtogooffline.Thelevelatwhichreversepowerflowbecomesproblematicforutilitiesisnoteasilydeterminedwithasimplepercentageofcapacitypenetration;manyfactorsmustbetakenintoaccountsuchasmagnitudeofreversepowerflow,capacityoffeeder,relayandrecloser32settings,andlengthoffeeder.Tomitigatetheseissues,utilitiesmayreconfigureorredesigntheirprotectionschemes.Utilitieshaveindicatedthatthishasbeendoneonacasebycasebasistodate.

4.1.7 Operational Flexibility 

AsDGpenetrationincreases,thecomplexityofthedistributionsystemincreasesandutilitiesmayhavelessflexibilitytooperatetheirsystem,potentiallynegativelyimpactingthesystem.Thedistributionsystemanditsassociatedprotectionschemes(protectiondevicesandthecoordinationbetweenthem)weredesignedtodistributeorsupplypowertoloads.Withgenerationsourcesspreadacrossthesystem,certainprotectionschemeswillhavetochange.DGbringsadditionalcomplexitytotheoperationandtroubleshootingofthedistributionsystemformanyreasons,includingthefactthattheinterconnectionpointmayactasagenerationsourceoraload.Furthermore,whenproblemsoccuronthedistributionsystem,itmaybemoredifficulttotroubleshootthem.Forthesereasons,itislikelythatutilitieswillhavelessflexibilitywiththeirsystem.Forexample,manydistributionsystemsareradialinnature,whichmeansthereisalonglinerunningfromthesource,andnoloopsorredundancy.IfaDGsystemcausesanissuewiththedistributionsystemsomewherealongthisline,requiringaportionofthelinetobeisolated,thentheutilitymayhavetodisconnecttheDGsystemandanythingbeyonditfromthemainsource.Thislimitonoperationalflexibilitymayreducethereliabilityofthedistributionsysteminsomecases.

4.2 TRANSMISSION SYSTEM RELIABILITY AND OPERATION  Transmissionsystemimpactsfromcustomer‐sideDGinstallationsinstalledtodate,particularlythoseinurbanareaswithhigherload,arecharacterizedasminimalinthestudiesconductedbytheCPUCconsultantsandothers.AliteraturesurveyofthetopicrevealsthattheconclusionmostoftenadvancedisthattheissueshavenotbeenexperiencedattheselowlevelsofDGpenetration,butasthepenetrationlevelsgrow,issuesareexpectedtoappear.Theissuesdiscussedinthefollowingparagraphsareonesthatarelargelyanticipated,buthavegenerallynotbeenobservedontheIOUssystemsatthetimeofthisreport.Anticipatedissuesthatwilllikelyneedtobeaddressedastheyariseinclude:

                                                            31 M. Coddington, B. Kroposki, T. Basso, K. Lynn, M. Vaziri, T. Yohn, “Photovoltaic Systems Interconnected onto Secondary Network Distribution Systems – Success Stories,” National Renewable Energy Laboratory, Golden, CO, April 2009, p. 8. 32 Relays and reclosers are system protection devices used in distribution and transmission systems. 

Page 45: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐8 

Transmissionsystemlinelosses

Reverseflowfromthedistributionsystemtothetransmissionsystem

Existingoperationalprocedures

Voltageregulation

Reliablecapacityandplanning

Capacitymargin

Systemstability

4.2.1 Transmission System Line Losses 

Aswiththedistributionsystem,DGthatserveslocalloadswilloffsettheneedtoimportpowerthroughthetransmissionsystematthetimethattheDGsystemisproducingenergy.Thisshouldreducetransmissionlinelossesduringthosetimes,andisgenerallyviewedasapositiveimpactofDG.Atthepresenttime,theutilitiesandtheCAISOarenotroutinelyquantifyingthisbenefitandassociatingitwithDG.

4.2.2 Reverse Power Flows from the Distribution System 

Reversepowerflows,asmentionedinthedistributionsystemsectionabove,canhavenegativeimpacts.ReversepowerflowscausedbyincreasedDGwouldlikelyoccurwhenDGoutputexceedsloadandtheexcessenergyflowsthroughthedistributionsystemtothetransmissionsystem.Thisisnotawidespreadissuetoday,butIOUengineersanticipatethatatsomelevelofDGpenetration,itmaybecomeaproblem.Whilethisreportspecificallyexaminespeakloadimpacts,theIOUengineersindicatedthattheywilllikelyseereverseflowissuesduringoff‐peakconditionswhentheirloadsareafractionoftheirpeakload,causingexcessenergyfromDGprojectstoflowbackontothesystem.Ifthisweretooccur,itwouldalsoimpacttransmissionoperationsproceduresandtheabilitytobalancesystemloadwithresources.Theimpactsofreversepowerflowonthetransmissionsystemaredifferentthanthedistributionsystem,partiallyduetothedifferentapproachestooperationofthedifferentsystems.Theliteraturesurveyedforthisreportdidnotrevealanyspecificstudiesthathavebeenconductedonthisissue.AnalysesconductedonDGimpactsonthetransmissionsystemhavefoundthatthelowlevelofDGpenetrationlimitsanyconclusionsthatcanbedrawnatthistime.33

4.2.3 Operational Procedures 

MuchinthesamewaythatdistributionsystemoperatorswillhavetoadaptasDGpenetrationlevelsgrow,transmissionsystemoperatorswillalsoneedtoadapt,especiallyifactualenergyoutputdifferssignificantlyfromtheforecastedoutput.GridoperationmaybenegativelyimpactedbyboththevariabilityandtheuncertaintyofvariableDGresources.34Instancesofover‐generationhaverecentlyoccurredwithwindgeneration.Similarover‐generationwithsolarDGismostlikelytooccurinthemorningwhileloadsarelow,butshouldacloudpass,generationcandecreaseveryquickly.35SCADAhasbeenseenastooexpensivetoinstallformonitoringoutputfromsmallerDG

                                                            33 Itron, “Impacts of Existing Distributed Generation – Final report,” Prepared for CPUC Energy Division Staff, Davis, CA, January 2010. Pages 5‐8; 5‐13. 34 NREL, “Impact of High Solar Penetration in the Western Interconnection,” A Technical Report Prepared by NREL and GE Energy, Golden, CO, December 2010. Page 6. 35 California ISO, “Integration of Renewables Resources: Operational Requirements and Generation Fleet Capability at 20% RPS,” August 31, 2010. Pages 12‐18. 

Page 46: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐9 

installations,sotheoutputistypicallynettedwithitsnativeload.Asaresult,minute‐by‐minutechangesinDGoutputcanappearasunexpectedincreasesordecreasesinload.Transmissionoperatorsmonitorsystemstatusaroundtheclock,andhaveproceduresformanagingspecificscenarios.ThesewouldneedtobeexpandedtoincludehowtomanageimbalancescausedbyincreasedDGonthesystemasthiswouldbeanewphenomenon.

4.2.4 Voltage Regulation 

Voltageregulationissues,asmentionedabove,canhavenegativeimpactsonthesystem.VoltageregulationissuesonthetransmissionsystemasaresultofDGsystemadditionshasnotbeenidentifiedspecificallyinanyoftheliteraturereviewedforthisreport.InterviewswithIOUengineershaverevealedthatthisisnotanexistingissueonthetransmissionlevelsubstationbusesrelatedtocustomer‐sideDG,butitisexpectedtobecomeaprobleminthefuture.36TheDGpenetrationpointatwhichtheIOUengineersthinkthisissuewillmanifestonasystem‐widebasisisunknownatthistimeanditisonetheyhaveexpressedtheywouldlikestudiedandunderstood.

4.2.5 Reliable Capacity and Planning 

WhileDGtechnologiesthatarenotvariablecanbereliedontoproducetheircapacityasexpected,mostDGinCaliforniaisPVwhichisnotforecastedinareliablewaytoday.Also,becausetransmissionexpansionplanslookattimehorizonsanywherefrom5to20yearsintothefuture,thequestionofwhatcapacitytoassumefortheseplansisstillatopicofdebate.WhiletechnicalanalyseshavefoundthatPVresourcescontributeupto30percentcapacityvalues,theISOusesacalculationthataveragespeakcapacitiesandusesthosevaluesasreliablecapacityinplanningstudies.37Resourceadequacy,theprocurementofsufficientflexibledemandorgenerationcapacitytomeetfutureloads,iscriticaltoloadservingentities.38Transmissionplannersaretaskedwithstudyingthebulkelectricsystemandidentifyingmitigationprojectsforanyissuesthatwillimpactreliableservicetoutilitycustomersunderpeakloadconditions.TheobligationtoserveacustomerremainswhetherornotthecustomerhasaPVsysteminstallation.Therefore,transmissionplannersassignavalueofzerototheseresourcestobeconfidentthattheyhaveadequateresourcesunderthecriticalpeakloadperiod.39AhigherconfidenceinPVforecasting,forinstance,wouldleadtomorecreditbeingattributedtoPVsystemsasreliablecapacity,apotentialpositiveimpactofDG.Also,athigherpenetrations,geographicdispersionwillprovidehighercapacityassurance.Inotherwords,manysmallsystemsoperatinginadispersedgridwillnotlikelyhavenegativeimpactsasgreataslarger,lessdispersedsystems.

Thereareongoingregulatoryactivitieswhichshouldprovidebettercertaintytothetreatmentofsolarorwindresourcesasdependableresourcesinthefuture.Inparticular,thereareproceedingsunderwayattheCPUCtoconsiderincorporatingflexiblecapacityinthe2014ResourceAdequacyprogram.ThatwouldincludepreparationandreviewofnewstudiesoftheeffectiveloadcarryingcapacityofwindandsolarresourcesinCalifornia.40

                                                            36 SCE indicated that larger wholesale DG systems do cause voltage regulation issues today. 37 NREL, “How Do High Levels of Wind and Solar Impact the Grid? The Western Wind and Solar Integration Study,” Technical Report, Golden, CO, December 2010. Page 10. 38 LBNL, “Mass Market Demand Response and Variable Generation Integration Issues: A Scoping Study,” Environmental Energy Technologies Division, Berkeley, CA, October 2011. Page 56. 39 IOU engineers interviewed for this report expressed that the obligation to serve customers is paramount. 40 CPUC Rulemaking 11‐10‐023, Filed October 20, 2011. Available online  http://docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M031/K723/31723210.PDF , Accessed December 13, 2012.  

Page 47: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐10 

4.2.6 Transmission Capacity Margin 

Capacitymarginistheunusedcapacityontransmissionlinesbasedontheirratedcapacities.Typically,thiswasduetoload;however,asDGpenetrationincreasesonthesystem,theseadditionscouldpotentiallypositivelyaffectthemargins.ResearchandstudiesconductedontransmissionlineloadingandhowDGaffectsitduringpeakloadconditionshasgenerallyconcludedthattheeffectsareminimal.ThereasonisthatthesystempeakoccurslateintheafternoonatthetimewhenPVoutput,forexample,issharplydeclining.Theresultingeffecthasresembledloadshaving,butnotpeakloadshaving‐‐whichutilitiesgreatlyvalueforreducingtheneedlepeakinload.InterviewswithIOUengineershaverevealedthatratherthanareductioninflowsonlines,theyhaveseenanincreaseinflowswhenDGhasbeeninstalledwhereloadsareminimalornotpresent.Technicalanalysesconductedontransmissioncapacitiesshowedthatimpactsareminimaltoday,andnoconclusionscanbedrawnduetopresentlylowlevelsofDGpenetration.41

4.2.7  System Stability 

Systemstabilityistheabilityofthebulkelectricsystemtostayintactbystayingsynchronizedandregainingequilibriumfollowingacontingencyonthesystem.Thisisespeciallyimportantinthefirstfewcyclesandsecondswhenautomaticgenerationcontrol(AGC)respondstothelossofgenerationortransmission.Astheproportionofvariablegenerationwithlimitedsystemresponsecapabilitiesincreasescomparedtolargeconventionalspinninggeneration,itislikelythatsystemstabilitymaybedecreased.InterviewswithIOUengineersidentifiedtheneedtoconductstudiestodeterminethelevelofpenetrationthatmayadverselyimpactsuchissuesassystemstability.

4.3 SIZE AND LOCATION DEPENDENT IMPACT OF DG  Inadditiontoalloftheissuesmentionedabove,thesizeandgeographiclocationofaDGsystemareimportantfactorsthatmayaffectitsimpactonthetransmissionanddistributiongrid.Eachoftheseissuesisdiscussedseparatelybelow.

4.3.1 Size Impacts 

ThesizeofaparticularDGsystem,relativetothedistributioncircuittowhichitisinterconnected,affectsgridoperationsforanumberofreasons.Allelsebeingequal,asmallersystemhasasmallerriskofhavingnegativeimpactsandcausinggridinstabilitythroughvoltageandfrequencyfluctuations,faults,trippingprotectionschemes,overloadingcircuitsorback‐feedingontothetransmissionsystem.FordistributedsolarPVandwindsystems,thevariabilityoftheiroutputcanbemorechallengingiftheyarelargerandareservingasignificantportionoftheloadonaspecificcircuit;inthatcase,asuddendroporincreaseinoutputwillhaveaproportionallylargerimpactongridoperationthanasimilarsystemofasmallersize.

However,itisimportanttonotethattheseimpactsalsovarybasedonthedistributioncircuit.DistributionengineersfromtheIOUsindicatedthatsomecircuitsmayhavethenecessarycharacteristicsandcapacitytoeasilyaccommodateasinglelargeDGsystem,whileothercircuitsmaybeunabletohandlemorethanasmallamountofDG.Also,theynotedthatthelocationoftheDGsystemalongtheradialdistributioncircuit—i.e.,whetheritisnearthesubstationorattheendoftheline—maybethemostimportantfactor,incombinationwiththeamountofloadintheimmediatevicinity.Overall,theseengineersagreedthatalargernumberofsmallDGsystemswouldhavelessofanegativeimpactongridoperationsthanasmallernumberoflargeDGsystems—with                                                            41 Itron, “Impacts of Existing Distributed Generation – Final report,” Prepared for CPUC Energy Division Staff, Davis, CA, January 2010. Pages 5‐15.  

Page 48: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐11 

thecaveatthatthereareexceptionsandeachcircuithasspecificcharacteristicsaffectingitsabilitytoaccommodateDG.

4.3.2 Location Impacts 

ItiswellknownthatthegeographiclocationsofDGsystemsaffectgridoperations,andtherearetwomainreasonsforthis.First,clusteringofDGsystemsmayposechallengesbecausethosesystemswilltendtoresembleasinglelargeDGsystem,withtheattendantissuesdiscussedabove.Thoughthisisapotentialconcern,programmanagersforthecustomer‐sideDGincentiveprogramsateachIOUnotedthatclusteringisnotcurrentlyhappeningwithcustomer‐sidesystemstotheextentthatpresentsachallengeforgridoperations.Furthermore,theIOUshavealsoprovidedinterconnectionmapswhichdirectdevelopersofwholesaleDGinstallationstoareaswheregridimpactsmaybesmallerduetogreatersystemcapacityandlessexistingDG.

Second,geographicdisbursementofvariableDGresourceslikesolarPVandwindreducestheirshort‐termvariabilitywhenviewedcollectively.Thiseffectiswell‐documented,andtheimpactofgeographicdiversityonsolaroutputvariabilityisdiscussedinarecentstudybyLawrenceBerkeleyNationalLaboratory,aswellasarecentpaperbyCleanPowerResearch.42,43Asshownbelow,theoutputfromagroupof25PVsitesspacedoverawidegeographicareaisconsiderablylessvariablethantheoutputfromasinglesite.

Figure 4‐3  Solar Irradiance Variability – One Location vs. 25 Locations44 

LookingatbothsizeandlocationimpactsofDG,theliteraturereviewandinterviewswithutilitypersonnelindicatethatalargenumberofsmallDGsystemsspreadoveralargegeographicareawouldgenerallyhavelessofanegativeimpactongridoperationsthanasmallnumberoflargeDG

                                                            42 A. Mills and R. Wiser, “Implications of Wide‐Area Geographic Diversity for Short‐Term Variability of Solar Power,” Lawrence Berkeley National Laboratory, Berkeley, CA, Sept. 2010.  43 T. Hoff and R. Perez, “Modeling PV Fleet Output Variability,” Submitted to: Solar Energy, 2010.  44 T. Hoff, “Advanced Modeling and Verification for High Penetration PV,” DOE High Penetration Solar Forum, San Diego, CA, March 2011.  

Page 49: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐12 

systemslocatedincloseproximitytoeachother.ThisistrueforanytypeofDGtechnology,butisespeciallytrueforvariableresourceslikesolarandwind.Whiletheseprinciplesmayholdtrue,asdiscussedintheBarrierssection(Section5),therearecurrentlynoincentivestositeDGinamannertominimizenegativeimpactsonthegrid.

4.4 PEAK DEMAND IMPACT ANALYSIS ThissectiondescribestheimpactofinstalledDGcapacityonthepeakelectricdemandoftheCaliforniaIndependentSystemOperator(CAISO)systemin2011.

Peakdemandreferstothetimeofdayandwhenelectricloadonthegridisgreatest,usuallymeasuredonadailyorannualbasis.In2011,theannualpeakdemandontheCAISOgrid,whichservestheterritoriesofPG&E,SCE,andSDG&E,was45,569MWandoccurredat4:30pmonSeptember7th.SincethisstudyanalyzesCAISOloadandDGgenerationonanhourlybasis,the“peakhour”intermsofCAISOdemandwasbetween4and5pmonSeptember7th,2011.

Inestimatingtheimpactofthetotalamountofcustomer‐sideDGcapacityoperatingontheCAISOgridduring2011peakdemandperiod,twoseparateapproachesweretakenforsolarPVandnon‐solarinstallations.TodeterminetheimpactofsolarPVcapacityduringthesystempeakdemand,Black&VeatchdevelopedamethodologythatutilizedactualmetereddatafromalargesamplingofsolarPVsystems.ThisanalysiswasundertakeninplaceofaCSIImpactEvaluationfor2011,inwhichpeakdemandimpacthasbeenreportedinpreviousyears.ThedetailsofthemethodologyanddatasourcesusedaredescribedinAppendixB.

Black&VeatchreliedondatafrommultiplesourcestodeterminethetotalamountofDGcapacityoperatingduringthe2011peakhour.

ForsolarPV,actualproductiondataforalargesetofoperatingPVsystemswasused.TheCPUCcollects15‐minuteintervalproductiondatafrommetersonhundredsofsolarPVsystemsinstalledundertheCSI(bothEPBBandPBI)andSGIPprograms.TheproductiondatawasusedtorepresenttheproductionprofileofallPVinstallationsintheIOUterritoriesforcalculatingthepeakdemandimpactofsolar.TheanalysisdidnotincludetheinstallationsfromthePOUSB‐1programs.Foradetaileddescriptionofthemethodologyemployed,refertoAppendixB.

Fornon‐solartechnologies,Black&Veatchusedthe“CPUCSelf‐GenerationIncentiveProgramEleventh‐YearImpactEvaluation”preparedbyItroninJune2012.Thestudyreportedthepeakdemandcapacityfactorsfornon‐solarSGIPgenerationincludingfuelcells,microturbines,gasturbines,andinternalcombustionengines(separatedbyrenewableandnon‐renewablefuels).ThesecapacityfactorswerethebasisforcalculatingtheamountofgenerationfromthesetechnologiesduringtheCAISOpeakdemandin2011.Nopeakhourcapacityfactorswereprovidedinthereportforwindturbinesoradvancedenergystoragesystems,sincemetereddatawasnotavailableforthesetechnologies.

TheoverallcontributionofDGinstallationsforthepeakdemandday,bothsolarPVandnon‐solar,ispresentedinFigure4‐4andFigure4‐5intermsoftotalMWoperatingineachhour.ThesefiguresdisplaysimilarinformationwiththedifferencebetweenthembeingthatFigure4‐5showsthedisaggregatedimpactofeachprogramonaseparatescalethantheCAISOload.Figure4‐6showsthehourlycapacityfactorforallDGonthepeakdemandday.

Page 50: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐13 

Figure 4‐4  Impact of Customer‐Side DG on CAISO Demand on September 7th, 2011 

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000Load

 (MW)

12 am     1 2         3        4         5         6        7         8         9       10      11     12pm 1        2         3          4         5        6        7         8         9        10      11    12am    

CAISO Load

Impact of Customer‐Side DG

Page 51: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐14 

 

Figure 4‐5  Operating DG Capacity by Program and CAISO Demand on September 7th, 2011 

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000

0

100

200

300

400

500

600

700

800

900

1,000

CAISO Load

 (MW)

DG Operating (M

W)

CSI

SGIP ‐ Solar PV

SGIP ‐ Non‐Solar

ERP/NSHP

All DG

CAISO Load

Peak DG Output: 728 MW

12 am   1 2       3      4      5       6     7     8        9   10     11   12pm 1        2       3    4      5       6     7     8        9   10     11    12am   

CAISOPeak Load: 45,569 MW

Page 52: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐15 

Figure 4‐6  Hourly DG Capacity Factors by Program and CAISO Demand on September 7th, 2011 

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

12‐1 1‐2 2‐3 3‐4 4‐5 5‐6 AM

6‐7 7‐8 8‐9 9‐10 10‐11 11‐12 12‐1 1‐2 2‐3 3‐4 4‐5 5‐6 PM

6‐7 7‐8 8‐9 9‐10 10‐11 11‐12

CAISO Load

 (MW)

DG Capacity Factor

CSI

SGIP ‐ Solar PV

SGIP ‐ Non‐Solar

ERP/NSHP

All DG

CAISO Load

CAISOPeak Load: 45,569 MW

Peak DG Capacity Factor: 0.63

Page 53: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐16 

Overall,thepeakdayprofileofsolarPVshowsthatsolarPVhasasmallbutsignificantimpactontheCAISOgridatmid‐dayandalesssignificantimpactduringtheactualpeakdemandperiod.Thenon‐PVtechnologieshavearelativelyconstantgenerationprofileandthereforeamoreconsistent—thoughsmaller—impactonCAISOdemandthroughouttheday.

ThetotalpeakdemandimpactofinstalledDGontheCAISOgridduringthe2011peakdemandperiod(4to5pmonSeptember7th)was335MWandwasapproximately0.7percentofCAISOload.TotalinstalledDGcapacityontheCAISOgridonthisdatewas1,136MW,ofwhich892MWwassolarPV.ThedetailedresultsareshowninTable4‐1below,brokendownbytechnology.

Table 4‐1  Peak Demand Impact by Technology 

TECHNOLOGY MWINSTALLEDPEAKHOURCAPACITY

FACTORPEAKDEMANDIMPACT

(MW)

SolarPV 892 0.25 227

Wind* 12 0.00 0

RF

FC 23 0.84 19

MT 4 0.08 0

GT 0 0.00 0

IC 12 0.49 6

Non‐RF

FC 17 0.54 9

MT 17 0.39 7

GT 31 0.83 26

IC 128 0.32 41

AES* 2 0.00 0

Total 1,136 0.29 335

*NoproductiondatawereavailableforWindandAESinstallations,sotheywereassignedacapacityfactorofzero,i.e.theywereassumedtohavenoimpactonpeakdemand.SeeAppendixBfordetails.RF=RenewableFuels;Non‐RF=Non‐RenewableFuels;FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines;AES=AdvancedEnergyStorage

Basedontheseresults,Black&VeatchfoundthatdistributedsolarPVcontributesabout25percentoftotalinstalledcapacityduringthe2011CAISOpeakdemandperiod.SolarPVgenerationtendstopeakaroundmid‐day,whileCAISOdemandtendstopeakmidtolateafternoonwhensolarPVoutputisdeclining,asisclearinFigure4‐5andFigure4‐6above.Thus,thehighestPVdemandimpactwasbetween12pmand1pm,whendistributedPV(plusotherDG)provided728MWofcapacityandaccountedfor1.8percentofCAISOload.ThesolarPVcontributionatthetimeof

Page 54: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐17 

CAISOpeakdemandisaboutaquarteroftheinstalledcapacityratingofPV;allDGaccountsfor0.7percentofCAISOpeakloadfrom4pmto5pm.

AccordingtoBlack&Veatchestimates,DGsolarPVachievesanhourlycapacityfactorof0.25duringtheCAISOpeakdemandhour(4‐5pmonSeptember7th)in2011.The2010Reportestimatedanhourlycapacityfactorof0.65forallDGsolarPVoperatingduringtheCAISOpeakdemandhour(3‐4pmonJune20th)in2008,andthe2010CSIImpactEvaluationreportestimatedanhourlycapacityfactorof0.56forallDGsolarPVoperatingduringtheCAISOpeakdemandhour(3‐4pmonAugust25th)in2010.Theestimatefor2011issignificantlylowerduetoanumberoffactors.First,theCAISOpeakdemandcamelaterinthedayin2011thanin2010and2008—4to5pminsteadof3to4pm—whenPVsystemsareproducinglessenergybecauseitisclosertosunset.Also,theCAISOpeakdemandoccurredlaterintheyearin2011thanin2010and2008,whichagainmeansthatPVsystemsareproducinglessenergy;thesunisclosertosettingat4pminSeptemberthanitisat4pminJune.Finally,itispossiblethatthepeakdemandhourin2011mayhavebeencloudierthanthepeakdemandhourin2010and2008.AllofthesefactorsresultinalowersolarPVcapacityfactorthaninpreviousyears.

Black&VeatchacknowledgesthattherearelimitationstoonlyestimatingtheimpactofDGonCAISOpeakdemand.CAISOandeachIOUhavetoplanforpeakdemandatavarietyoflevels(customertransformer,distributionfeeder,distributionsubstation,subtransmissionnetwork,transmissionsubstation,transmissionline,theutilitysystem,andtheentireCAISOsystem)andthisreportdoesnotattempttomodeltheimpactofDGateverylevel—althoughthatmaybeausefulexercise.Rather,thisreportseekstoshowthemagnitudeofDGoutputrelativetothetotalCAISOloadbecausethisgivesageneralsenseofhowmuchDGcontributestostatewidepeak.FuturestudiesshouldconductanalysisofDG’speakdemandimpactatotherlevelsbecausetheimpactislikelytobedifferentatlowerlevelsthanattheCAISOlevel.

TheIOUsarealreadyconductingsomeresearchintotheimpactofDGatthedistributionfeederlevel,inordertobetterunderstandtheseimpactsandhowtheymightchangeaspenetrationincreasesinthefuture.Inparticular,SCEconductedastudyinOctober2012toassessthepeakdemandimpactofcustomersolarPVonresidential(Figure4‐7)andnon‐residential(Figure4‐8)feederswithabove‐averagePVpenetrationrates.Asshowninthefigures,PVoutputpeaksaround1pminallcases,whileloadpeaksaround7pmontheresidentialfeederandaround3pmonthenon‐residentialfeeder.Whilethesearejustselectedexamples,thisanalysisshowsthatwhilePVcanhaveasignificantimpactintermsofreducingpeakdemandonanon‐residentialfeeder,butithasalmostnoimpactonaresidentialfeeder.ResultslikethisprovethevalueofexaminingDGimpactsatthelevelofindividualdistributionfeeders,becauseitbecomesapparentthattheimpactsofDGdependatleastasmuchonthelocalizedcharacteristicsofthedistributionsystemasonthecharacteristicsoftheDGsystemitself.

Page 55: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐18 

Figure 4‐7  Peak Demand Impact of Solar PV on Typical SCE Residential Distribution Feeder45 

 

                                                            45 “Coincidence of Solar Production with SCE’s System Load and Distribution Circuits,” SCE Load Research, Oct. 2012, p. 3.  

Page 56: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐19 

Figure 4‐8  Peak Demand Impact of Solar PV on Typical SCE Non‐Residential Distribution Feeder46 

Additionalstudiesinthisareaofpeakdemandimpactarewarranted,evenbeyondtheanalysisofpeakdemandimpactatlevelsotherthantheentireCAISO.TheCPUCdatasetcontaining15‐minutemeteredproductiondataforCSIandSGIPsystemsisverylargeandrich.Thepeakdemandimpactanalysisperformedhereisasimpleexampleofitsuse.PreviousCSIImpactEvaluationreportshaveperformedotheranalysesthatwerebeyondthescopeofthisreport,buttherearestillmanypossibleusesforthedatathathavenotbeenfullyexploredtodate.Thesecouldinclude:

ExtrapolationofresultstodetermineimpactsathigherDGpenetrations

AssessmentofNEMsystems’impactonloadshapeandconsequentialpeakshifting

Analysisofnon‐peakperiodsincludingidentificationofperiodsofmaximumDGexport

CalculationofEffectiveLoadCarryingCapacity(ELCC)ofdifferentDGsources.ELCCrequiresastatisticalprobabilityanalysisofpreferablymultipleyearsofcoincidentloadandgenerationdatatodeterminethecapacityvalueofdifferentgenerationsources.

Analysisoftheimpactsofwest‐facingversussouth‐facingPVsystemsonloadshape

Assessmentoftheeffectsofdecommissioningandperformancedegradationontheresults

                                                            46 “Coincidence of Solar Production with SCE’s System Load and Distribution Circuits,” SCE Load Research, Oct. 2012, p. 5. 

Page 57: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | DG Impacts on the Transmission and Distribution System  4‐20 

Comparisonandvalidationofdifferentforecastingtechniques

Analysisofshort‐termvariabilityofPVoutputbygeographiclocation,systemtype,etc.

Analysisofhowmuchshort‐termvariabilityisreducedbycombiningoutputfromPVsystemsspreadoverawidegeographicarea

Page 58: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐1 

5.0 Issues and Barriers Impacting DG Deployment TherateofDGinstallationsontheCaliforniagrid,inparticularsolarPVsystems,hasincreasedsignificantlyoverthepastseveralyears.Thisincreasecanlargelybeattributedtofinancialandregulatoryincentives,theavailabilityofnewleasingandfinancingoptions,thedeclineinsolarPVcostsglobally,andincreasedmarketingefforts.Inmanyrespects,CaliforniahasledthenationinidentifyingandremovingbarrierstoDGdeployment.InitiativessuchasimplementationofNEM,reformofRule21,andcompletionofon‐linetoolsforrebateprocessinghaveallowedCaliforniatosuccessfullyadvancethelargestDGmarketintheU.S.California’ssuccesshasbeenamodelforotherstatesinimplementingtheirownDGprograms.

DespiteCalifornia’ssuccess,therearestillbarrierstoadditionaldeploymentofDG.Thesebarriersexistfromboththeutility’sperspectiveandthecustomerand/ordeveloper’sperspective.Moreover,thereareanumberofissueswhichaffectDGdeploymentandmeritdiscussion,butarenotactuallybarriers.BarriersinthisreportaredefinedasthosethingswhichdirectlyinhibitgreaterdeploymentofDG—asopposedtoissues,whicharedefinedhereasthosethingswhichaffectbutdonotnecessarilyinhibitit.Thissectionaddressesbothbarriersandissues.

Itron’s2010Reportidentifiedpotentialbarriersrelatedtopolicy,technicalbarriersrelatedtoRule21,distributionsystemunknownswithincreasedpenetration,anduncertaintyaroundenvironmentalrequirementsforDG.Inthisreport,Black&Veatchprovidesanupdateanddiscussionofadditionalissuesandbarriers.ThesearelistedinTable5‐1bycategory,alongwithwhethereachisanissueorabarrier,andwhethereachisconsideredakeyissueorbarrier.

Thefollowingsectionsaddresseachofthesecategories,andalsoprovideaprioritizedlistofthekeyissuesandbarriers.Itshouldbenotedthattheidentificationofabarrierorissueinthisreportdoesnotnecessarilyimplythatitshouldbe,orevencouldbe,addressed.Manybarriershavealreadybeenreduced(suchasinterconnectionissues),andsomearelargelyoutsidethecontrolofthestate(suchashighequipmentcosts).Asnotedintheintroductiontothissection,California’sDGmarketisthelargestinthecountry,andalreadyhasmademuchprogressinaddressingmanyofthelargerbarrierstoDG.

Page 59: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐2 

Table 5‐1  Issues and Barriers Impacting DG Deployment 

CATEGORY/TOPIC ISSUEORBARRIER? KEYISSUEORBARRIER?

FinancingandEconomics

FinancialIncentives Issue

AccesstoFinancing Barrier

EquipmentCosts Barrier

SoftCosts Barrier

PolicyandRegulatory

IncentivestoLocateDGinBeneficialAreas Issue

RateStructures Issue

EquitableAllocationofCosts Issue

RegulatoryMandates Issue

GridAccessandInterconnection

BarrierstoDGInterconnection Barrier

Integration

Monitoring,Forecasting,andControl Barrier

ModelingToolsforIntegrationofDG Issue

DistributionSystemDesign Issue

InverterStandards Issue

Miscellaneous

ProcessingTimesandCustomerUnderstanding Issue

AllocationofFunds Issue

MultiplePrograms Issue

AvailabilityofInstallers Barrier

MarketingandConsumerEducation Barrier

ForecastingofFutureInstallations Issue

ProjectSiting Barrier

Page 60: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐3 

5.1 FINANCING AND ECONOMICS Perhapsthemostimportantbarriertocontinuedcustomer‐sideDGdeploymentistherelativelyhighfinalcosttocustomers.ThevariousincentivesandprogramsavailableforinstallationofDGsystems(describedinSection3.2.1)haveencouragedwidespreadgrowthofDGthroughoutCalifornia.However,intheabsenceofsubsidies,mostDGtechnologiesarecurrentlyunlikelytobecompetitivewithgridpower.

SeveralfactorscontributetotheultimatecostofDGtocustomersincludingfinancialincentives,accesstofinancing,equipmentcosts,and“soft”costs.

5.1.1 Financial Incentives 

BecauseoftherelativelyhighinitialcostofDGtechnologiescomparedtogridelectricity,andbecausepublicpolicyinCaliforniaandnationwidehasshownsignificantsupportforDG,financialincentivesarethemostimmediateanddirectmethodofreducingthecostofDGandincreasingitsdeployment.AtthestatelevelinCalifornia,therearenumerousprogramswhichprovidefinancialincentivesforDG,asdescribedinsection3.2.1.TheNEMtariffisalsoasignificantfinancialbenefitforcustomer‐sideDG,becauseitallowscustomerstobecreditedforgeneration(uptotheirannualconsumption)attheretailrate.Atthefederallevel,themainfinancialincentiveforDGistheinvestmenttaxcredit(ITC),whichprovidesataxcreditofupto30percentoftheinstalledcostforcustomerswhoinstallsolarPV,windorfuelcells,and10percentforthosewhoinstallmicroturbinesorCHPsystems.47

Giventhecurrentlevelsoffinancialincentivesofferedbystateandfederalgovernment,amajorissueforfutureDGdeploymentisthelimited,declining,orexpirationofstateandfederalfundingofincentives.48First,fundingformanyofthestateincentiveprogramsislimited,whichdeterslaterDGcustomersifdemandforincentivesoutpacesavailabilitybeforeaprogramends.Second,programfundingmaydecreasebecauseofoutsideinfluences(e.g.governmentspendingcuts),orper‐unitpaymentstocustomersmaydeclinewithgreaterparticipation.ThislattermechanismisactuallypartofthedesignofprogramssuchasCSI,becausetheyassumethatDGcostswilldecreaseasmoreisinstalledandthatincentivelevelsperkWcandecreaseaccordingly.

Third,manycurrentstateandfederalincentivesaresettoexpireatspecificpointsinthefuture,whichisanissuebecauseoftheuncertaintyitcreateswithintheindustry.Thefederalproductiontaxcredit(PTC)andinvestmenttaxcredit(ITC)forwindwasallowedtoexpireattheendof2012,butwasthenextendedforjustoneyearaslongasconstructionbeginsbeforetheendof2013.Similarly,biomassexpiresin2013andPVexpiresin2016.TheCSIisalsosettoendin2016.49Otherincentiveprogramsfaceexpirationdatesaswell.Duetothepoliticalnatureoftheseprograms,itisnotknownifanyofthemwillbeextendedpasttheirexpirationdate,andiftheyareextendeditisnotknownhowincentivelevelswillchange.Anendorsignificantchangetothesegovernmentincentives(especiallytheITC)wouldlikelyreduceDGdeploymentsincethefinalcostofDGtothecustomercouldabruptlyincreaseandalargeportionofDGprojectsmightnolongerbeeconomic.Thus,alackoffinancialincentivesisoneofthemostimportantpotentialissuesforDGdeployment,andalsoperhapsthemostvisibleissuetocustomers.

                                                            47 http://www.dsireusa.org/incentives/incentive.cfm?Incentive_Code=US02F&re=1&ee=1  48 Energy and Environmental Economics, “California Solar Incentive Cost‐Effectiveness Evaluation,” Prepared for: California Public Utilities Commission, San Francisco, CA, April 2011, p. 10. 49 The CPUC has recently begun a market transformation study to determine what the market for customer‐side solar PV will look like post‐CSI. 

Page 61: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐4 

5.1.2 Access to Financing 

DGinstallationsgenerallyinvolvelargeupfrontcosts,andinthecaseofrenewableDGlikesolarPVandwind,theinitialcapitalcostisessentiallytheonlycost(exceptforasmallamountofmaintenanceoverthelifetimeofthesystem).FormostcustomersinterestedininstallingDG,thislargeupfrontinvestmentisabarrierbecausetheymaynothavetherequiredamountofcashimmediatelyavailabletopayforthesystem,anditismuchsimplerandeasiertocontinuepayingtheircomparativelysmallmonthlyelectricbill.ThismayhappendespitethefactthatinmanycasestheycouldpotentiallysavemoneyoverthelongtermwithaDGsystem.

However,overthelastfewyearstheavailabilityofthirdpartyleasingandfinancingoptionsforsolarPVhashelpedtosignificantlyalleviatethisbarrierandhasallowedlessaffluentcustomerstodeploysolarPV.50CompaniesofferingthesethirdpartyfinancingoptionsoftenallowcustomerstoinstallPVwithlittleornoupfrontinvestment,allowingthemtosimplypayamonthlychargelessthantheirpre‐existingelectricbill.Theprevalenceofthesethirdpartyarrangementshasincreasedconsistentlyanddramaticallyinthelastfewyears,asmeasuredbyapplicationstotheCSIprogram,fromabout10percentofCSIapplicationsin2007to68percentin2012.51Thistrendisespeciallystrongamongresidentialcustomers.Figure5‐1showstheincreasingrateineachyearsincetheCSIprogrambeganin2007throughSeptember2012.

Figure 5‐1  Percentage of PV Systems with Third‐Party Ownership in CSI, 2007‐2012 

Despitetheriseofleasingandotherinnovativefinancingarrangements,accesstofinancingisstillabarrierformanycustomers.Leasingcompaniesprefercustomerswithhigherelectricitybillsandgoodcredit,whichtendtobemoreaffluentcustomers.Forexample,toqualifyforalease,                                                            50 E. Drury et al., “The Transformation of Southern California Residential Photovoltaics Market Through Third‐Party Ownership,” National Renewable Energy Laboratory, Golden, CO, Jan. 2012.  51 Based on Black & Veatch analysis of the CSI Working Data Set, available at www.californiasolarstatistics.org/current_data_files.   

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

2007 2008 2009 2010 2011 2012

Third‐Party Ownership (% 

of All Applications)

Page 62: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐5 

customersofonesolarleasingcompanymusthaveaFICOcreditscoreofatleast700.Justoverhalfofthepopulationhadascorethathighin2011.52Whileotherfinancingstructuresareavailable,theydonotoffertheattractivemonthlypaymenttermswithnoupfrontcosts.

5.1.3 Equipment Costs 

FinancialincentivesfrompublicprogramsandnewfinancingoptionscanhelptoreducethecostofDGtocustomers,buttheinitialcostoftheequipmentitselfisalsoamajorfactorinthiscostandcanbeabarrier.Asmentionedabove,theunsubsidizedcostsforDGremainhighrelativetothecostofgridelectricity;althoughinsomecasesthecostofDGequipmentisdecliningbecauseofincreasingadoption,improvingeconomiesofscale,andtechnologicalinnovation.ThecostofsolarPVmodules,inparticular,hasdecreasedsignificantlyinthelastfewyears,asshowninFigure5‐2below.Butevenwiththesedeclines,DGequipmentcostsarestilloneofthelargesteconomicbarrierstogreaterDGdeployment.

Figure 5‐2  Solar Module Prices from December 2001 – March 201253 

 

5.1.4 Soft Costs 

InadditiontoDGequipmentcosts,thetotalcostofinstallingaDGsystemincludesanumberoflesstangibleor“soft”costcomponents,whichinmanycasescanbejustassignificantasthe“hard”costsforthephysicalequipment.Softcostsincludeanypermittingfees,administrativecosts,financingandcontractingcosts,designandengineeringcosts,customeracquisitioncosts,incentiveapplicationfees,interconnectionfees,taxes,aswellasthecostsassociatedwithprojectdelaysdue

                                                            52 FICO, “FICO® Scores Shift During Recession,” http://bankinganalyticsblog.fico.com/2011/09/fico‐scores‐shift‐during‐recession.html, accessed September 2012.   53 Solarbuzz, PV Module Price Index, available at: http://www.solarbuzz.com/facts‐and‐figures/retail‐price‐environment/module‐prices, accessed September 2012.   

Page 63: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐6 

topermittingorinterconnectionissues.DGprojectsinCaliforniamustusuallyobtainapprovalfrommultipleentitiesorjurisdictions,includingtheutilitytowhichtheyareinterconnecting,theincentiveprogramtowhichtheyareapplying,thelocaljurisdictionwhichmustinspectthemforpublicsafetyreasons,andpossiblyotherentitiesaswell.

AsequipmentcostsforPVhavedropped,softcostshavestayedrelativelyconstant,thusincreasingtheirshareoftheoverallcosts.ThesesoftcostscanconstitutealargeportionoftotalDGsysteminstalledcosts,andthereforeareabarriertoDGdeployment.LawrenceBerkeleyNationalLaboratoryreleasedastudyinSeptember2012comparingtheinstalledcostsofresidentialrooftopsolarPVinstallationsintheU.S.andGermany.54ThestudyfoundthataverageinstalledcostsperwattinGermanyin2011were45percentlowerthanintheU.S.,mostlyattributabletosoftcosts.Moreover,inGermany,softcostsaccountedforjust20percentoftotalinstalledcosts,whileintheU.S.theyaccountedforover50percentoftotalinstalledcosts.Thestudyexploresanumberofexplanationsforthisdifference,andindicatesthatthemainsoftcostbarriersforgreatersolarPVdeploymentintheU.S.relativetoGermanyinclude:

SmalleroverallsolarPVmarket

Smalleraveragesystemsize

Slowerprojectdevelopment/installationprocess

Highernet‐profitmarginsforinstallersduetolesscompetition

HighersystemsalespricesduetomoregeneroussubsidiesandhigherPVsystemoutput

Highercustomeracquisitioncosts,includingsystemdesigncostsandmarketingandadvertisingcosts

Higherlaborhourrequirementsforpermitting,interconnection,andinspection

Higherpermittingandinterconnectionfees

HighersalestaxesonPVsystems

Manyattemptshavebeenmadeatalllevelsbytradeassociations,localpermittingauthorities,utilities,stateagencies,legislators,andadvocacygroupstoreducesoftcosts,withvaryinglevelsofsuccessdependingonthejurisdiction.ThemostsignificanteffortinthisareaistheU.S.DepartmentofEnergy’sSunshotInitiative,whichisseekingtoreducetheinstalledcostofsolarPVby75percentbetween2010and2020.Thisincludesacomparabledecreaseinsoftcosts,andtheinitiativehasalreadyfundedmultiplestudiesandprojectsinCalifornia.55

5.2 POLICY AND REGULATORY Somecurrentgovernmentalpoliciesandregulationscanaffecttheproliferationofcustomer‐installedDG.Theseissuesarelistedbelow,andfurtherdescribedinthefollowingsubsections.

LackofincentivestolocateDGinareaswiththegreatestbenefittothegrid

CertainratestructuresprovidedifferingincentivestoDG

Equitableallocationofcostsandbenefits

                                                            54 J. Seel, G. Barbose, R. Wiser, “Why Are Residential PV Prices in Germany So Much Lower Than in the United States?: A Scoping Analysis,” Lawrence Berkeley National Laboratory, Berkeley, CA, Sept. 2012.  Available at http://eetd.lbl.gov/ea/emp/reports/german‐us‐pv‐price‐ppt.pdf.   55 http://www1.eere.energy.gov/solar/sunshot/nonhardware_bos.html  

Page 64: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐7 

Regulatorymandates

Itshouldbenotedthatchangesoradditionstopoliciesandregulationswillrequireresearchandclosecollaborationbetweenutilities,industry,andregulators.

5.2.1 Incentives to Locate DG in Beneficial Areas 

Fromtheoutset,someofthekeybenefitsofdistributedgenerationhavebeenassociatedwiththeirabilitytobelocatedinareaswheretheycanreducepeakdemand,reducelinelosses,anddeferdistributionandtransmissionsystemupgrades.However,therearecurrentlyverylimitedincentivesprovidedtoDGsystemownersanddeveloperstoactuallysiteDGintheseareas.Instead,DGinstallationsareprimarilydrivenbyotherfactorssuchashostsiteeconomics,landavailability,permitting,andresourcequality.Duetotheseoverridingconsiderationsandthelackofincentives,DGisnotbeingoptimallylocatedonthedistributionsystemandmanyofthepotentialbenefitsarenotfullyrealized.Infact,largerDGsystemsroutinelyarefacedwithdistributionsystemupgradecosts–notbenefits.

AsstatedinareportpublishedbyRockyMountainInstituteandPG&EinMarch2012,“DGthatisatthe‘rightplaceattherighttime’willcreatethegreatestvalue,whileadditionalelectricitysupplyinthewrongplaceatthewrongtimecouldresultinaddedcoststothesystem.”56

ThelackofincentivestolocateDGinareaswiththegreatestbenefittothegridisanissuesimpactingcosteffectivedeploymentofDG.IfCaliforniadoesnotprioritizebeneficialsitingofDG,thencoststoachievethestate’sDGgoalsarelikelytobehigherandbenefitstoconsumersarelikelytobelower.

5.2.2 Rate Structures 

Utilityratestructurescanhaveasignificantimpactonthecost‐effectivenessofcustomer‐sideDGinstallations.InsomecasestheymaybefavorabletotheinstallationofDG,whileinothercasestheymaydeterDG.Asaverysimpleexample,customerswhopayhigherratesaremorelikelytosavemorefromDGinstallation.Whilethesecustomersbenefitfromthegreatersavings,totheextentthereisacostshiftassociatedwithcurrentnetenergymeteringpolicy,othercustomerswillabsorbthosecosts(seenextsection).Ratedesigncanthusaffect(1)thedeploymentofDGinCalifornia,and(2)impactnon‐DGcustomersandtheutilities’abilitytorecovercostsofservice.Itshouldbenotedthattheintentofthissectionisnottoassesswhethercertainratedesignsshouldbeencouragedordiscouraged.Itisbeyondthescopeofthisreporttoaddresstheimpactofutilityratestructuresonthecost‐effectivenessofcustomer‐sideDG.57TheexamplesmentionedherearesimplymeanttoillustratespecificwaysinwhichdifferentratestructurescanaffectDGdeployment.

ImpactofRateStructureonDGDeploymentRatestructures,whichareslightlydifferentforeachIOU,determinehowautilitycustomerischargedforelectricityusage.ForresidentialcustomersoftheIOUsinCalifornia,therearemultipleratetiers:uptoacertainamountofusage,onerateischarged,andthenahigherrateappliestousageuptothenextthreshold,etc.Figure5‐3showsPG&E’sresidentialratetierstructureasan

                                                            56 “Net Energy Metering, Zero Net Energy, and the Distributed Energy Resource Future: Adapting Electric Utility Business Models for the 21st Century,” Rocky Mountain Institute, Snowmass, CO, March 2012.   57 The CPUC has opened a rate design rulemaking to comprehensively examine utility rate structures.  Order Instituting Rulemaking on the Commission’s Own Motion to Conduct a Comprehensive Examination of Investor Owned Electric Utilities’ Residential Rate Structures, the Transition to Time Varying and Dynamic Rates, and Other Statutory Obligations, R.12‐06‐013, Issued June 21, 2012. 

Page 65: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐8 

example.CustomersinthehighesttierpayamuchhigherrateperkWhthancustomersinthelowertiers.Asshowninthefigure,atalmost$0.35/kWh,theTier4rateisaboutthreetimeshigherthantheTier1rate.Thus,high‐usagecustomershavegreatereconomicincentivetopursueDGoptionsthancustomersinlowertiers.Iftheresidentialrateswerestructureddifferently—e.g.iftheper‐kWhratewerethesameforallcustomersregardlessofusage—theadoptionrateofDGbyvarioustypesofcustomerswouldlikelybedifferent.Intoday’sratestructure,thelowerratepaidbycustomersinthelowertiersmaybeactingasadeterrent,ifsuchcustomersmaybeinterestedininstallingDGbutarenotabletojustifyitcomparedtotheirlowper‐kWhrate.Ofcourse,equalizingthetierswouldalsoruncountertootherpolicygoals,suchasencouragingenergyefficiency.

Figure 5‐3  PG&E Residential Rate Tier Structure (January 2012)58 

Forcommercialandindustrialcustomers,thesituationismorecomplicated.Inadditiontotheper‐kWhenergychargetherealsocanbea“demandcharge”paidbasedontheindividualcustomer’speakdemand.Thepeakdemandismeasuredasthehighestaverageusageovera15‐minuteperiodoutofthemonth.Placingachargeonpeakdemandismeanttocoversomeofthecostsoftheinfrastructuretoservethesecustomers;italsogivestheselargercustomersanincentivetoreducetheirpeakdemand.Thedemandchargecanbeasignificantportionofthecustomer’selectricbillifthecustomerhashighpeakenergyuse.

AccordingtoCCSE,thedifferentnon‐residentialtariffsfortheIOUsshiftvaryingamountsofthecustomer’soverallcostsbetweenthedemandchargeandtheper‐kWhcharges,butPG&EandSCE

                                                            58 “Net Energy Metering, Zero Net Energy, and the Distributed Energy Resource Future: Adapting Electric Utility Business Models for the 21st Century,” Rocky Mountain Institute, Snowmass, CO, March 2012.   

Page 66: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐9 

havetariffsthatshiftmorecoststotheper‐kWhchargethanSDG&E.59ThismeansthatcommercialcustomersinSDG&EterritoryhavelessofaneconomicincentivetoinstalldistributedsolarPV.Eventhoughtheymaybeabletoreducetheirper‐kWhcostswithPV,theystillhavetopayarelativelylargerdemandcharges(comparedtoPG&EandSCEterritories)whichDGmaynothelptoreduce,sincePVmaynotpeakwhenthecustomer’sdemandpeaks.Aswiththeresidentialratetiersmentionedabove,iftherelativedistributionofdemandchargesandkWhchargeswereadjustedforcommercial/industrialIOUcustomers,thentheadoptionofDGwouldlikelychange.

Figure5‐4showstheimpactthatdifferentratestructurescanhaveonelectricbillsforcustomersinSDG&E’sterritory.Thechartshowscomparesexamplesofmonthlybillsforacommercialcustomerunderthreescenarios:

“BillsBeforePVInstallation”showsatypicalbillinghistoryforacommercialcustomerwithoutanyDGonthestandardrate.

“BillsAfterPV,onTOURate”showsthebillinghistoryforacommercialcustomerwithsolarPVonatypicaltime‐of‐useratethatincludesasignificantdemandcharge(Rate:AL‐TOU).

“BillsAfterPV,onDGRate”showsthebillinghistoryforacommercialcustomerwithsolarPVonamodifiedratethatincludesamuchlowerdemandcharge(Rate:DG‐R).

Figure 5‐4  Example Impact of Rate Structures on SDG&E Customer Electric Bills.60 

                                                            59 For example, PG&E’s A‐6 tariff for small general time‐of‐use service does not have a demand charge.  Its energy rate for summer peak periods is $0.44/kWh.  See http://www.pge.com/tariffs/tm2/pdf/ELEC_SCHEDS_A‐6.pdf.   60 J. Del Real and J. Fortune, “Understanding Non‐Residential Utility Rates,” California Center for Sustainable Energy, May 2010.   

$0

$1,000

$2,000

$3,000

$4,000

$5,000

$6,000

$7,000

$8,000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Customer's Monthly Electricity Bill

Bills Before PV Installation

BillsAfter PV, on TOU Rate

BillsAfter PV, on DG Rate

Page 67: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐10 

AcustomerwithPVonanytypeofratewillhavelowerelectricbillsthanthe“BillsbeforePVInstallation”,becausethePVgenerationisoffsettingconsumptionfromthegrid;thus,both“BillsAfterPV”barsarelowerthanthe“UtilityBillwithoutPV”barineverymonth.ButitisclearfromthedifferencebetweentherateswithPV(i.e.thedifferencebetween“BillsAfterPV,onTOURate”and“BillsAfterPV,onDGRate”)thattheDGratewithlowerdemandchargesresultsinalowerbill,especiallyduringthesummermonthswhenPVproductionisgreatestanddemandchargesarehighest.ThislowerbillwillreducethepaybacktimeforthePVsystem,anditillustratesthatthevalueofDGtothecustomercanbesignificantlyaffectedbytheratestructure.

ImpactofRateStructureonCostofServiceRecoveryWhilealowerutilitybillwillresultinareducedpaybacktimeforthePVsystem,itmayalsohindertheIOUs’abilitytorecoverthecostsofprovidingelectricservicestoresidentialandothercustomerclasseswhoinstallself‐generation.Thisisbecausecostsofservice(i.e.theinfrastructurethatallowsDGcustomerstoreliablyconsumeelectricityfrom,andexportto,theutilitygrid)areembeddedinenergy(kWh)relatedchargesforcertaincustomerclasses.Iftheutilityisunabletofullyrecovercostsfromself‐generators,nonparticipatingcustomersmayhavetoabsorbthosecosts,whichcouldaffecttheirrates.SDG&Eindicatedthataworst‐casesituationcouldarisewhenratesincreaseduetogreaterDGdeployment,andmorecustomersthenbecomeincentivizedtoinstalltheirownDGsystem,whichcouldfurtherexacerbatetherateincreases,creatinganunsustainablefeedbackloop.

5.2.3 Equitable Allocation of Costs 

Distributedgenerationsystemsreceivevariousincentivesthroughtheprogramsdescribedinthisreport.Ultimately,allratepayersandtaxpayersfundtheseincentives,whethertheyareparticipantsandnon‐participants,eventhoughonlyarelativelysmallportionofthepopulationcurrentlyparticipatesintheseincentiveprograms.Whilenon‐participantsreceivesomebenefits,suchasreductionofgreenhousegasemissions,thesebenefitsmaynotexceedthecostspaid.Ifthereisconcernthatcostallocationisnon‐equitable,thismayaffectcontinuedproliferationofDG.

Anotherexampleofnon‐equitablecostallocationrelatestodistributionsystemupgradesthatmayberequiredtoinstallDG.Asdiscussedinsection4.1,protectionschemesmayneedtobemodified,additionalequipmentmayberequired,orsystemmodificationsmaybeneeded.Theallocationofcostsforthesenewrequirementsmayfallinequitablyonallratepayers,includingthosewhodonotbenefitdirectlyfromtheupgrade.61Undercurrentlaw,NEMprojectspaylittletonocosttointerconnecttotheutilitygrid.62Fromtheutilities’perspective,thereisconcernthatwithincreasedDGandNEMinstallations,additionalupgradestothedistributionsystemmaybecomenecessary.Thecostsoftheseupgradeswouldbebornebytheutilityandpassedontoallratepayers,meaningthatnon‐NEMcustomerswouldeffectivelybesubsidizingtheNEMcustomers.ThisissueismademorecomplexbythefactthatcustomerswhoinstallDGandtakeadvantageoftheNEMtarifftendtobewealthierthantheaverageratepayer,sopoorercustomerswouldbesubsidizingwealthieronesinthisscenario.63TheequitableallocationofcostsbetweenNEMcustomersandother

                                                            61 Itron, “Impacts of Distributed Generation,” Prepared for: California Public Utilities Commission Energy Division Staff, Davis, California, January 2010, p. 4‐5.  62 This exemption for NEM projects derives from Pub. Util. Code § 2827(d) and was interpreted by the CPUC in D.02‐03‐057 to include exemptions from the costs of interconnection application review fees, interconnection studies, and distribution system modifications triggered by the NEM project. 63 “Net Energy Metering, Zero Net Energy, and the Distributed Energy Resource Future: Adapting Electric Utility Business Models for the 21st Century,” Rocky Mountain Institute, Snowmass, CO, March 2012, p. 32.   

Page 68: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐11 

ratepayersisconsideredbyutilitiestobeamajorconcernforincreasingDGdeployment,andiscurrentlybeingstudiedbytheCPUC.

Paststudiesandnewinitiativesareunderwaytotrytoaddressthisissue.Thesehaveshownmixedresults:someindicatetherearesignificantsubsidiesforNEMcustomers,whileothersindicatetherearesignificantnetbenefitsforallratepayers.TheNEMCost‐EffectivenessEvaluationcompletedfortheCPUCinMarch2010foundthatallNEMPVinstallationsthrough2008resultedinalevelizedcross‐subsidyofapproximately$20millionperyear.SCEin2012completedastudythatestimatedthatNEMcustomersaresubsidizedbynon‐NEMcustomersaround$50millionperyearwithNEMcapacityataboutonepercentofsystempeakdemand.64Conversely,astudycompletedbyCrossborderEnergyonbehalfoftheVoteSolarInitiativeinJanuary2013estimatedthatwhenNEMPVcapacityreachesfivepercentofpeakdemandinCaliforniaitwillprovideapproximately$90millionperyearinnetbenefitstoratepayersofPG&E,SCEandSDG&E;itfoundthatmostofthosenetbenefitswouldresultfromnon‐residentialNEMinstallations.65ItisexpectedthattheupdatedNEMCost‐BenefitEvaluationfor2012‐2013,commissionedbytheCPUC,willaddressthisissueagainandprovidegreaterdetail.66Finally,theUniversityofSanDiegoEnergyPolicyInitiativesCenter,Black&Veatch,andCleanPowerResearcharecurrentlyconductingacost‐benefitstudyfocusedonthenetcostorbenefitofsolarPVNEMsystemsinSDG&E’sterritory.AnobjectiveofthatstudyistodeterminethecostoftheservicesprovidedtoNEMcustomersandthevalueofthebenefitstheyprovidetothesystem.

5.2.4 Regulatory Mandates 

CPUC,FERCandotherregulatingbodiesapplycertainoperationalmandatestoutilities.InputfromtheIOUsindicatedthatmandatesthataredifficulttoimplementorlimitautility’soperationscanunintentionallyaffectfurtherDGdeployment.Forexample,SDG&Eindicatedthattheuniqueattributesoftheirsystem,specificallybeingheavilyresidential,arenotoftenconsideredbyregulatorsandcouldimpactfurtherdeploymentofDG.

Asanotherexample,theCPUCrequiresutilitiestomaintainvoltageatacertainstandard(forexample,withina+/‐5percentthreshold).67Asdescribedinsection4.1.5,DGsystemsaffectsystemvoltage,andmayleadtoviolationsoftheCPUCmandatedthresholds.Thus,itispossiblethatthesestandardscouldindirectlyaffectDGdeploymentbydiscouraginginstallationswhichmaycausevoltageissues.PEPCOHoldings,Inc,whichisdealingwithincreasedsolarPVinstallationsinNewJersey,hassuggestedthatvoltagestandardsmightbereviewedandpotentiallyrelaxedtoprovidegreaterflexibilitytoaccommodateDGinitsserviceterritory.Inparticular,Germanyappliesa+/‐10percentthreshold.68However,relaxingvoltagerequirementswouldneedtobecarefullyconsideredandmaynotbeappropriateinCalifornia.Operatingathighervoltagemaybedetrimentaltoexistingcustomerloadequipmentthatwasdesignedandratedfortheexistingvoltagerange.

                                                            64 SCE, “Retail Rates and Cost Issues with Renewable Development,” May 2012, available at http://www.energy.ca.gov/2012_energypolicy/documents/2012‐05‐22_workshop/presentations/09_Garwacki_SCE‐Retail_Rate_2012‐05‐22.pdf.   65 Crossborder Energy, “Evaluating the Benefits and Costs of Net Energy Metering in California,” January 2013.  Available at: http://votesolar.org/resources‐impacts‐of‐net‐metering‐in‐california/.   66 http://www.cpuc.ca.gov/PUC/energy/Solar/nem_cost_benefit_evaluation.htm 67 Voltage and other service standards are set out in each IOU’s Electric Tariff Rule 2, which is subject to the CPUC’s approval. 68 PEPCO Holdings, Inc., “Challenges for Distribution Feeder Voltage Regulation with Increasing Amounts of PV”, Available at: http://www1.eere.energy.gov/solar/pdfs/hpsp_grid_workshop_2012_steffel_pepco.pdf.   

Page 69: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐12 

5.3 GRID ACCESS AND INTERCONNECTION ChallengesinobtainingaccesstothedistributiongridandcompletingtheutilityinterconnectionprocessareoftencitedasbarriersforDGdeployment.CaliforniahasmadelargestridesinfacilitatingDGinterconnection.Thissectiondescribesexistinginterconnectionprocesses,barriersrelatedtointerconnection,andfutureinterconnectionpoliciesthatmayaffectthesebarriers.

5.3.1 Existing Interconnection Processes 

TherearethreedifferentinterconnectionprocessesthatapplyinCalifornia,dependingonprojectsizeandwhethertheinterconnectionistothetransmissionordistributionsystem.AlthoughthisreportdoesnotfocusonwholesaleDGsystems,theinterconnectionprocessesforthesesystemsaresummarizedinadditiontocustomer‐sideDGbelow.

CAISOInterconnectionProcessWholesaleDGprojectsmayinsomecasesbelargeenoughtointerconnectwiththetransmissionsystem.Ifthisweretobethecase,theywouldgothroughtheCAISOinterconnectionprocess,whichhasfourtracks,listedinorderfromsimplesttomostcomplex:

10kWInverterProcess

FastTrackProcess

IndependentStudyProcess

StandardClusterStudyProcess

WholesaleDistributionAccessTariffProcessIfawholesaleDGprojectistointerconnectwiththedistributionsystemofanIOUandengageincompetitivewholesalecommercialarrangements,thenitwouldlikelygothroughtheinterconnectionprocesssetoutineachIOU’sWholesaleDistributionAccessTariff(WDAT),whichissimilarbutnotidenticalforeachIOU.TherearemultipletrackswithintheWDATprocesssimilartotheCAISOtrackslistedabove.69EachIOU’sWDATisaFERC‐jurisdictionaltariff.

Rule21ProcessCustomer‐sideDGsystemsinterconnectingwiththedistributionsystemandwholesaleDGengaginginanavoided‐costsaletothehostutility,suchasfeed‐intariffparticipants,willtypicallyusetheCPUC‐jurisdictionalRule21interconnectiontariff.Rule21wasinitiallyadoptedbytheCPUCin1982toaddressthesafeandreliableinterconnectionofQualifyingFacilities(QFs)underthePublicUtilityRegulatoryPoliciesAct(PURPA).TheCPUCrevisitedRule21in2000andworkedtosubstantiallystreamlinetheinterconnectionprocessforsmaller,customer‐sideDGsystems,especiallyNEMsystems.Thechangeswereeffective:todate,asshowninTable3‐9above,over100,000NEMsystemshavebeensuccessfullyinterconnected.

However,asthescaleandpenetrationofDGsystemshaveincreased,particularlywiththeadventoftheCPUC’snewerwholesaleDGprograms,additionalreformstofacilitateinterconnectionbecamenecessary.SignificantreformstoRule21enactedinSeptember2012aredesignedtomaketheinterconnectionprocessmoretimely,cost‐effective,andtransparentforwholesaleDGprojectswhileretainingthesameefficiencyforNEMprojects.

                                                            69 CAISO, “Resource Interconnection Guide,” July 2012. Available at http://www.caiso.com/participate/Pages/ResourceInterconnectionGuide/default.aspx.  

Page 70: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐13 

ToserveDGinterconnectingtothedistributionsystemonbothsidesofthemeter,theRule21interconnectionprocessinvolvesthefollowingstudytracks,alsolistedinorderofsimplesttomostcomplex:

FastTrackProcess

DetailedStudies

● IndependentStudyProcess

● DistributionGroupStudyProcess(forthcoming)70

● TransmissionClusterStudyProcess71

AdditionalrecentreformstoRule21include:

Eligibilityforthe“FastTrack”processisexpandedtoincludeexportingfacilitiesupto3MWforPG&EandSCE,andupto1.5MWforSDG&E.

EligibilityforDGpenetrationlevelsisexpandedtothehighestinthenation.Theinitialscreenforaggregategeneratingcapacityupto15percentofpeaklinesectionloadisretained;however,ifanapplicantfailsthisscreen,theaggregategeneratingcapacitymayalternativelybetestedagainst100percentofminimumloadonthelinesection.ThisshouldallowformoreDGtobeconnectedwithintheFastTrackprocess.

Energystorageisincludedwithinthedefinitionof“generatingfacility,”makingstoragetechnologieseligibleforthesameinterconnectionprocesswithinRule21.

StandardInterconnectionAgreementsforNEM,non‐export,andexportinggeneratingfacilitiesareapproved.

Standardapplicationandsupplementalreviewfees(NEMsystemsexemptfromthesefees)areapproved.

Firmtimelinesareestablishedtoensurethatprojectsmakeprogresstowardinterconnection.

DisputeresolutionmechanismsattheIOUsandattheCPUCareestablishedtoaddressinterconnection‐relateddisputesefficiently.

AprocessforobtainingResourceAdequacyvalueisidentifiedthroughtheTransmissionClusterStudyProcess.

Apre‐applicationreportandonlineinterconnectionqueuesareintroducedtoaidsitingdecisions.

                                                            70 The Distribution Group Study Process is intended as a more‐efficient study track for groups of electrically interdependent generating facilities interconnecting to the same distribution circuit.  The CPUC has identified this additional study track within Rule 21 as an issue to be completed within Phase 2 of the interconnection OIR. See Assigned Commissioner’s Amended Scoping Memo and Ruling Requesting Comments, filed September 26, 2012 in R.11‐09‐011.  71 Applicants under Rule 21 that are found to have electrical interdependence with the transmission network are offered the option of transitioning to the next applicable transmission cluster study process conducted by CAISO. 

Page 71: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐14 

5.3.2 Barriers Related to DG Interconnection72 

TheCPUC’sinterconnectionoversightandreformeffortshavefocusedonRule21,thetariffundertheCPUC’sjurisdiction.ItisimportanttonotethatthereformstoRule21adoptedinSeptember2012wereintendedtoaddressanumberofbarrierstoentryrelatedtotimeliness,transparency,andpredictabilitythathadbeenidentifiedbeforethestartoftheCPUC’sinterconnectionrulemaking.Thus,theCPUCwillbemonitoringthesuccessofthereformsinreducingoreliminatingthosebarrierstoentry.

Atthesametime,theCPUChasidentifiedcertainforward‐lookinginterconnectionpoliciestoaddressinPhase2oftheinterconnectionproceeding.Thoseinclude:

DetailingtheDistributionGroupStudyProcess,

Developingadditionalstandardizedinterconnectionformsandagreements,

Enhancinginterconnectioncostcertainty,usingtoolssuchastheidentificationofpreferredlocationsforDG,

EvaluationofthesuccessofRule21inreducinginterconnectionasabarriertoentry,and

EvaluatingtechnicaloperatingstandardsthatcanaidinaccommodatingincreasesinDG,includingautonomoussmartinverterfunctionalities.73

TimetoProcessInterconnectionApplicationsTheefficiencyandspeedwithwhichinterconnectionapplicationsareprocessedunderRule21hasbeenidentifiedasabarrierbysome,sincetheamountofDGinstallediscompletelydeterminedbyhowmuchDGisapprovedforinterconnectionbytheutility.Somepointtothefactthatinterconnectionprocessispaper‐basedasasourceofinefficiency.Tohelpaddressthisissue,SDG&Ehasimplementedanonlinedatabaseforinterconnectionapplications,similarinsomewaystothePowerClerksoftwareusedbytheCSIprogramforincentiveapplications.Thishasimprovedapplicationprocessingspeedandallowedgreatercustomervisibilityintotheinterconnectionapprovalprocess,therebyreducingtheperceptionofinterconnectionprocessingasabarriertoDG.However,thefundingforsucheffortsmayhavetobedrawnfromthebudgetforotheractivitieslikeoperationsandmaintenance,whichisabarrierontheutilitysidetofurtherimprovements.

Table5‐2andFigure5‐5showtheaveragetimestakentoprocessinterconnectionapplicationsfordistributedsolarPVintheCSIGeneralMarketprogrambyeachIOU.AlloftheIOUsareonaveragemeetingtheirstatutoryobligationtoprocessNEMinterconnectionapplicationswithin30days.Forbothresidentialandnon‐residentialapplications,SDG&EshowedsignificantlyshorterprocessingtimesthanPG&EandSCE.WhileSDG&Ehasasmallervolumeofinterconnectionrequests,representativesfromCCSEindicatedthatSDG&Efocusesoncompletinginterconnectionsquicklyandthatitsonlineinterconnectiondatabasealsomakestheprocessmoreefficientthantheotherutilities’paper‐basedsystems.SincenearlyalloftheseapplicationsareforDGsolarsystemsthatarealsoreceivingincentives,theinterconnectionapplicationprocessingtimeismerelyonepartoftheprocessthatcancausedelays.However,itisperhapsthemostcriticalpartbecauseacustomer

                                                            72 As noted previously, California has successfully addressed many interconnection barriers in the past, and many additional barriers have been addressed through the reforms to Rule 21.  This section describes issues which have historically been considered barriers, but which may no longer represent significant obstacles to DG interconnection.    73 Assigned Commissioner’s Amended Scoping Memo, filed September 26, 2012 in R.11‐09‐011. 

Page 72: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐15 

cannotlegallyinterconnecttothegridandstartproducingelectricitywithoutcompletingtheinterconnectionprocess.

Notably,theaverageinterconnectionapplicationprocessingtimeforallthreeIOUsincreasedinthefirst6monthsof2012comparedtopreviousyears.Aprobableexplanationfortheincreaseistheincreasedvolumeofinterconnectionrequests.Comparedtopreviousyears,therateofinterconnectionapplicationshassubstantiallyincreased,insomecasesdoubling.Addingstaffandimplementinganonlineprocessingsystemmaydecreasetheaverageinterconnectionprocessingtime.

Table 5‐2  Number of Interconnection Applications and Average Interconnection Application Processing Times for CSI PV Systems by IOU74 

TIMEPERIOD

PG&E SCE SDG&E

RESIDENTIALNON‐

RESIDENTIAL RESIDENTIALNON‐

RESIDENTIAL RESIDENTIALNON‐

RESIDENTIAL

AverageNumberofApplicationsReceivedperMonth

January–June2012 798 63 889 38 273 8

2009–2011 726 36 453 19 200 6

AverageProcessingTime(Days)

January–June2012

18.4  17.6  12.3  19  4.5  6.9 

2009–2011

10.7  12.6  10  17.9  3.6  4.8 

                                                            74 http://www.californiasolarstatistics.ca.gov/reports/data_annex/ and CSI Working Data Set 

Page 73: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐16 

Figure 5‐5  Average Interconnection Application Processing Times for CSI PV Systems by IOU 

IdentifyingOptimalInterconnectionLocationsAshasbeennotedthroughoutthisreport,identifyingthe“rightplaceattherighttime”forDGwillcreatethegreatestvalueforratepayersandtheelectricgrid.Achievingthisgoalhasdirectimplicationsforinterconnection.First,asdiscussedinthissection,thereareseveraltoolsnowavailableinCaliforniatoaidDGsitingdecisions.Second,theCPUCisconsideringnext‐generationpolicies,suchasimprovinginterconnectioncostcertaintyandautonomoussmartinverterfunctionalities,tofurtheridentifytheoptimallocationsandtimingofDGonthedistributionsystem.

InterconnectionCapacityMapsInstallersanddevelopersinthepastoftennotedthatitwouldbehelpfultohaveamaporGIStoolwhichwouldallowthemtoidentifyoptimallocationsonthedistributionsystemforlargerDGsystems(generallywholesalesystems)basedoncircuitcapacityorothercharacteristics,ratherthanhavingtofindoutwhichsitesaregoodorbadthroughtheinterconnectionreviewprocess.Fortunately,thisparticularbarrierhasbeenatleastpartiallyaddressedforwholesalesystems,andisgenerallynotachallengeforcustomer‐sidesystems.In2011,pursuanttoCPUCdecisionsimplementingtheRAMprogram,theIOUsreleasedweb‐basedmapsofinterconnectioncapacityontheirdistributionandtransmissionsystemsforjustthispurpose(seeFigure5‐6).PursuanttoCPUCorders,theIOUsactivelymaintainthesemapsontheirwebsitesandupdatethemapproximatelyoncepermonth.

0

2

4

6

8

10

12

14

16

18

20

Residential Non‐Residential Residential Non‐Residential Residential Non‐Residential

PG&E SCE SDG&E

Interconnection Application Processing Time, Days 2009 – 2011

January – June 2012

Page 74: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐17 

Figure 5‐6  Example Interconnection Capacity Mapping Tool from PG&E75 

Pre‐ApplicationReportandOnlineIntegratedQueuesInadditiontothemaps,aPre‐ApplicationReportisnowavailableunderRule21,whichprovidesalow‐cost($300)firstlookofthetechnicalpotentialandchallengesofadesiredpointofinterconnectionforaDGproject.Anypotentialapplicantcanrequestareport,regardlessofwhethertheywillapplyforinterconnectionunderRule21ortheWholesaleDistributionAccessTariff.

Rule21alsonowrequiresIOUstomaintainanonlineintegratedqueueoftheDGprojectsseekinginterconnectiontothedistributionsystemunderRule21andtheFERC‐jurisdictionalWholesaleDistributionAccessTariff.Thisonlinespreadsheetprovidesmarketparticipantsameansofevaluatingthenumberofapplicantsqueuedaheadonthesamedistributioncircuit.Thelengthofthequeueimpactsthetimeandriskassociatedwiththeinterconnectionprocess.

5.3.3 Future Interconnection Policies  

BecauseoftheincreasingamountofDGandthegrowingfocusonitsroleintheelectricsystem,effortstodevelopthenextgenerationofinterconnection‐relatedpoliciesareunderwayatboththestateandfederallevel.

                                                            75 https://www.pge.com/b2b/energysupply/wholesaleelectricsuppliersolicitation/PVRFO/PVRAMMap/index.shtml 

Page 75: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐18 

CPUCRule21InitiativesCostcertaintyhasbeenidentifiedasamajorfactoraffectingtheabilityofDGinstallerstocompletetheinterconnectionprocess.Costuncertaintycantaketheformofalackofpredictabilityabouttheupgradesandcoststhatwillbetriggeredatagivenpointofinterconnection,and/orahighdegreeofvariabilityintriggeredcostsduringtheinterconnectionprocess,becauseofdecisionsmadebyqueued‐aheadprojects.76TheCPUCheldafirstworkshoponcostissuesinNovember2012tolaunchPhase2oftheinterconnectionproceeding.

AsdiscussedfurtherinSection6below,DGhasthepotentialtosupport,ratherthandetractfrom,thereliabilityofthegrid.InPhase2oftheinterconnectionproceeding,theCPUCisexaminingthepotentialtointroduceautonomoussmartinverterfunctionalitiesthatwouldbeapplicabletocertainDGsystems.ThepotentialforcontributionsbyDGwithsmartinverterfunctionalitiesisdiscussedfurtherinSection5.4andSection6.0.

CAISODGInitiativesAlsoatthestatelevel,CAISOissuedamemoranduminSeptember2012fortheconsiderationofitsboard,coveringCAISO’sevolvingpoliciestoaddressincreasingDGdeploymentinCalifornia.77Thismemorandumincludesanumberofinitiatives,allofwhicharedesignedtofacilitatetheinterconnectionofDGonthetransmissionanddistributionsystem:

AstreamlinedassessmentprocessforDGprojectsrequestingdeliverabilitystatustosupportresourceadequacyprocurementfor2014

AreviewandstakeholderprocessrelatedtocomplexandcostlytelemetryandmeteringrequirementsforDGprojects

A“non‐generatingresource”modeltoallowenergystorageprojectstoparticipateintheCAISOmarket

Aclarificationthatenergystoragecanprovidebothspinningandnon‐spinningreservesforthegrid

FERCDGInitiativesAtthefederallevel,FERCiscurrentlyconsideringapetitionforrulemakingfiledbytheSolarEnergyIndustriesAssociation(SEIA)inFebruary2012.ThispetitionrequestedthatFERCreviseitssmallgeneratorinterconnectionprocedurestomakeiteasierfordistributedsolarPVtobeinterconnectedtothedistributiongridusingthe“fast‐track”reviewprocess,largelybyraisingtheprojectsizelimitsandbyintroducingthealternativeDGpenetrationlimitof100percentofdaytimeminimumloadnowavailableinRule21.FERCheldatechnicalconferenceinJuly2012todiscussthisparticularissue,atwhichtheCPUCpresentedthenewpenetrationthresholdandotherrelevantadvancesthatwerethenpending(andsinceapproved)inRule21.Asofthiswriting,FERChasnotyetreachedadecisionaboutwhethertoactonSEIA’spetition.WhileitisnotcertainthatFERCcanadoptSEIA’sproposedchangesbecausetheyaresolar‐specific(FERCmustremaintechnology‐neutralinitspolicies),thefactthatthepetitionisbeingconsideredshowsthattheremaybechangeatthefederallevelintermsofinterconnectionprocessesrelatedtoDG,andthatregulatorychangesmayreducebarrierstogreaterDGdeployment.

                                                            76 For more on the cost issues associated with interconnection, see Assigned Commissioner’s Amended Scoping Memo and Ruling Requesting Comments, filed September 26, 2012 in R.11‐09‐011. 77 K. Edson, “Briefing on Distributed Energy Resources,” submitted to CAISO Board of Governors, Sept. 2012. 

Page 76: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐19 

5.4 INTEGRATION  TheintegrationofDGintothedistributionsystemandtheoveralloperationoftheutility’sgridisachallenge.ManyDGsystems,predominantlythosewhichimplementwindorsolartechnology,donothavetheabilitytosupplygenerationondemand.AsDGpenetrationincreases,particularlyonthesamedistributionfeeder,theintegrationofDGsystemswillbecomemorechallenging.

ThereareseveralchallengestointegratingDGsystemstothetransmissionanddistributiongrid,particularlyintermittentsystemssuchassolarorwindfacilities.Theseissuesandbarriersarelistedbelow,andarefurtherdescribedinthefollowingsubsections.

Lackofmonitoring,forecastingandcontrolcapabilities

LackofmodelingcapabilitiestoaddressincreasedintegrationofDG

Distributionsystemdesignedforpowerflowtowardsload

Inverterstandardscouldbemore“gridfriendly”

5.4.1 Monitoring, Forecasting, and Control 

Currently,muchoftheDGinstalledonthegridinCaliforniaisnot“visible”tothegridoperators.Thisisduetoalackofmonitoringandcontrolcapabilitiescombinedwithlimitedforecastingsystems.AsDGpenetrationgrows,thismaypresentasignificantbarriertoefficientuseoftheoverallsysteminthefuture.

Currently,utilitiesdonotmonitorthereal‐timeoutputofmostcustomer‐sideDGplants.Onlysystemsabove1MWarerequiredtoinstallmeteringandtelemetrythatpermitreal‐timemonitoring.Mostcustomer‐sidesystemsarebehindthemeterandoffsetload,andasaresult,onlythenetloadisvisibletoutilities.ThelackofvisibilityinDGoutputhasnotbeenconsideredaprobleminthepast.Infact,historically,itwasthoughtthatthecosttomonitortensofthousandsofsmallersystemsdidnotjustifythebenefitsatlowpenetrationlevels.Furthermore,giventhelackofstandardcommunicationprotocolsforthevariousDGequipmentdeployed,utilitiesfinditchallengingtocollectandmakeuseofthedata.78

AsdescribedinarecentreportbyExeterAssociatesandGeneralElectric,thelackofvisibilityintoDGoperationcanbedividedintotwomainconcerns:(1)theimpactofDGonloadforecastingand(2)thepotentialforlargeamountsofDGtodropoffthegridinresponsetosystemdisturbances.79TheseconcernsincreaseasDGpenetrationincreases.

                                                            78 While smart meters are being deployed through California, all IOUs indicated that smart meters do not currently improve their ability to monitor DG systems.  Currently, there is generally no communication between smart meters and customer side PV systems.  There are numerous challenges to this, as explained by the utilities in recent reports to the CPUC.  See http://www.cpuc.ca.gov/PUC/energy/Solar/UtilityProgramAdministratorsReportsUsingAMIForTrackingRooftopsolarGenerationJuly2012.htm.  SMUD and EPRI have just begun work on a pilot program to test a low‐cost inverter‐smart meter communication approach. 79 Exeter Associates and General Electric, “PJM Renewable Integration Study.  Task Report: Review of Industry Practice and Experience in the Integration of Wind and Solar Generation”, November 2012.   

Page 77: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐20 

ForwholesaleDGsystems,thistypeofmonitoringisalreadytypicallypresent.80Forsmallersystems,SCEandSDG&Eindicatedthatvisibilityintoasystem’sstatusandproductionmaybeuseful.SDG&Eindicatedthatthisvisibilitymaypossiblyallowthemtofactoritintotheirtransmissioncapacitymargincalculations(seesection4.2.6).SCEindicatedthatmonitoringofsystems,particularlythoselargerthan250kW,isnecessary.AthigherDGpenetrations,theutilitiesmayneedtorequiremonitoringatsmallerDGsizessincesmallerunitsmayaggregatetoalargercapacityandmayhaveamoresignificantimpact.IOUsrecognizethathavingthiscapabilitywouldlikelyincreasethecomplexityoftheirsystemoperationsignificantly,butthismaybenecessaryfortheefficientandreliableoperationoftheirsystem.

Inadditiontolackofmonitoring,theutilitiesalsodonottypicallyhavecontrolcapabilitiestocurtailtheamountofenergyDGsystemsproduce.Whilesignificantimpactsduetolackofmonitoringandcontrolmaynotappearforseveralyears,itmaybeprudenttobeginconsideringoptionsaheadoftimesoastobeprepared.Germany,whichhasabout30GWofsolarPVconnectedtoitssystem,hasbeendealingwithintegrationissuesforsometime.Ithasrecentlyinstitutedrulechangesthatwillrequireretrofitof315,000olderPVinstallationstoallowvaryinglevelsofcontrol.AccordingtoExeterAssociates:

GermanyrequiresthatallDGunitsequaltoorgreaterthan100kilowatts(kW),withtheexceptionofsolarPV,beremotelyobservableanddispatchableforthetransmissionsystemoperator.SolarPVsystemslessthan100kWareexemptfromrequirementstomeasurepoweroutput.However,solarPVunitsbetween30kWand100kWarerequiredtobeabletoreduceoutputremotelyincaseofgridcongestion.Further,solarlessthan30kWmustbeabletoreduceoutputremotelyincaseofgridcongestionortoreducemaximumpowerto70%ofinstalledcapacity.81

Inadditiontolackofmonitoringandcontrol,reliablemeansofforecastingthenear‐termoutputfromDGsystemsisonlynowemerging.ForecastingofDG,andPVinparticular,maybenecessaryforintegrationofDG.Forecastingmovingcloudcoverandotherweatherchangeswillallowforimprovedcontrolandfunctionofthedistributionsystem,balancingofgenerationinacontrolarea,andmoreeconomicalunitcommitment.Ifforecastingcapabilitiesareachieved,thencontrolcapabilitiesmaybecomemorevaluabletocurtail,increaseorotherwisecontroldistributedgenerationasnecessary.

5.4.2 Modeling Tools for Integration of DG 

Thereisalackofeasy‐to‐usemodelingtoolsanddatawhichallowuserssuchasutilitiestodynamicallymodelrenewableresourcesonthedistributionsysteminconjunctionwiththetransmissionsystem.Sometoolsarebeingusedtomeetcurrentneeds,butasSDG&Eindicated,theyarenotuser‐friendlyandoftenrequirespecializedpersonneltorun.Utilitieswouldprefertohavethiscapabilityinhouse.

                                                            80 Currently, telemetering requirements are imposed only on DG systems 1 MW or larger.   Smaller units do not have this requirement since at lower penetrations the expectation was that the impacts would be minimal, the cost to collect the data would be relatively high, and processing of this additional data may not be necessary. This assumption should be revisited as penetration increases or the operational requirements for DG change. For example, California utilities have recently proposed telemetering requirements for certain wholesale DG systems smaller than 1 MW that will export power to be aggregated and scheduled into CAISO’s market. As of this writing, the CPUC has not yet evaluated those proposals. 81 Exeter Associates and General Electric, “PJM Renewable Integration Study.  Task Report: Review of Industry Practice and Experience in the Integration of Wind and Solar Generation”, November 2012.   

Page 78: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐21 

Inadditiontothelackofmodelingsoftware,certaininputsforthissoftwareareoftenlimited–specifically,modelsforsolarPVinvertersthatrepresentnotonlythestaticbehavior,butalsothedynamicbehavior.SCEindicatedthatinvertermanufacturerstypicallyrequestnon‐disclosureagreementswithutilitiesbeforeprovidingdetailedinformationontheirmachines.Becauseofthislimitation,utilitiesgenerallycreateinvertermodelswithseveralassumptions.Theaccuracyofthemodelsmaybelimitedbecauseofthelackofdata;andwiththelackofdata,utilitiescannotbesurethemodelingsoftwaretheyareusingisappropriate.ThelimitedaccuracycouldhinderfurtherinstallationofDG,specificallysolarPV.

ThereisnotwidespreaduseofhighDGpenetrationmodelsbydistributionandtransmissionengineers,especiallymodelsthatsimultaneouslysimulateintegratedtransmissionanddistributionsystems.TheneedforthistypeofmodelwillbecomemorepressingasthepenetrationofDGincreasesandreversepowerflowfromthedistributionsystemtothetransmissionsystemgrowsmorecommon.

5.4.3 Distribution System Design 

Thedistributionsystemwasdesignedtosupplyenergyfromthetransmissionsystemtoloads.DGsystemsintroduceenergysourcesonthedistributionsystem.Becausethedistributionsystemwasnotdesignedforthisfunctionality,therearechallengeswithintegratingDGathighpenetrationlevels,especiallywhentheyarenotgeographicallyspreadoutacrossthedistributionsystem.ThisissueleadstosomeofthenegativeimpactsofDGonthegrid,suchasreversepowerflows.ApotentialbenefitofDGsystemsistoreducethenumberofsystemupgradesneeded;however,thismaynotalwaysbethecaseifDGdeploymentinaparticularareaincreasestheneedforsystemupgrades.

5.4.4 Inverter Standards 

IEEE1547isavoluntarystandardforinterconnectingdistributedgenerationtothegrid.Specifically,IEEE1547addressestopicssuchasperformance,operation,testing,safety,andmaintenanceofinterconnection.IEEE1547specificallycallsforinverterstotripofflinequicklyintheeventofagriddisturbancetoavoidislandingofgenerationandotherissues.Initscurrentform,thestandarddoesnotallowfeaturessuchaslow‐voltageride‐through(LVRT),whichcouldbevaluableinhelpingmaintainsystemstabilityinthecaseofsystemdisruptions.Revisingthisaspectofthestandard,andpossiblyothers,mayallowinverterstobemore“gridfriendly”andbetteraccommodatehighDGpenetrationscenarios.Gridfriendlyinvertersmayallowbettersupportorcoordinationwiththegridregardingvoltageandfrequency.

AsnotedbyPG&E,thenationalstandards,suchasIEEE‐1547andUL‐1741arenotcurrentlycompatiblewithsomeofthedesiredinverterfeatures,suchasLVRT.WhiletheIEEE‐1547andUL‐1741wouldneedtobemodifiedtopursuetheseadvancedinverterfeatures,thenationalstandardsmaytakesometimetorevise.Therefore,Rule21wouldneedtobemodifiedinparalleltorevisingthenationalstandards.

5.5 MISCELLANEOUS Inadditiontothetechnicalandeconomicbarriersandissuesdiscussedintheprevioussections,thereareanumberwhicharelesstangibleorquantifiablebutarestillsignificantforcustomer‐sideDGdeployment.Theseissuesandbarriersincludethefollowing,andarediscussedinthesubsectionsbelow:

Processingtimesandcustomerunderstanding

Page 79: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐22 

Allocationoffunds

Multipleprograms

Availabilityofinstallers

Marketingandconsumereducation

Forecastingfutureinstallations

Projectsiting

5.5.1 Processing Times and Customer Understanding 

AsignificantbarriertoDGdeploymentfromthecustomerordeveloper’sperspectiveistheadministrativeprocessingtimerequiredtoparticipateinDGincentiveprograms,toapplyforinterconnection,andtoobtainnecessaryinspectionsandsafetychecks.Customersanddevelopersoftencitethisasabarrierbecausethetimeandefforttocompletealltheseprocessescandiminishorevennegatetheexpectedbenefitsoftheproject.Fromtheutilityorprogramadministrator’sperspective,acloselyrelatedbarrieristhefactthatcustomersanddevelopersoftendonothavesufficientbackgroundorexperiencetocompletetheseprocessessuccessfully,andtheirlackofunderstandingcausesadministratorstospendtimeorientingthemtotheprocesses.Thistakesawaystaffresourcesfromreviewingandapprovingapplicationsforincentives,interconnection,etc.AnotherrelatedbarrieristhatDGadministratorsmaybeshort‐staffedrelativetothevolumeofapplicationsreceived,foravarietyofreasons.

5.5.2 Allocation of Funds 

ExistingDGincentiveprogramsgenerallyhavetargetsorallocationsforhowmuchfundingshouldbedirectedtocertaintypesofDGinstallations.Forinstance,manyoftheprogramsattempttodividefundsevenlybetweenresidentialandnon‐residential(commercial,industrial,government,non‐profit,etc.),andmanyalsohave“carve‐outs”forlow‐incomeprojects.InthecaseoftheCSIprogram,MASHandSASHwerecreatedasentirelyseparateprogramstoensurethatadesignatedamountoffundingreachedlow‐incomeprojects.

Issuesrelatedtoallocationofprogramfundsareoftenperceivedasaproblembyparticipants,butthenatureoftheproblemdependsontheparticipant’sperspective.Low‐incomehomeownersorrentersmayseethelimitonfundingforlow‐incomeprojectsasaproblemifthereissubstantialcompetitionforthesefunds.Utilitiesmayseethedivisionoffundsbetweenresidentialandnon‐residentialprojectsasanissuepreventingefficientuseoffunds,becausesomefeelthatlargernon‐residentialprojectsareamorecost‐effectiveuseofpublicmoneythansmallerresidentialprojects,duetothelowerper‐kWcostsforlargersystems.Conversely,residentialcustomersmightviewtheallocationsforlargecommercialprojectsashinderingtheirownparticipationsincetheremainingfundsforsmallresidentialprojectsarethenmorelimited.

Totalfundingfornon‐renewableDGsystemsisgenerallylessthanthatforrenewableDG,andtheyoftenreceivealowerincentiveperkW.Sinceitislesslikelytobeinstalled,thismaybeconsideredanissuespecificallyfornon‐renewableDG.

5.5.3 Multiple Programs 

Section3.0ofthisreportdescribesanumberofdifferentprogramssupportingDGinCalifornia.Theproliferationoftheseprogramsmaybeanissuetosomedegreeinitself.Fromacustomerorprojectdeveloper’sperspective,theremaybeconfusionabouttheprogram(s)forwhichtheirprojectiseligible.Thiscanleadtoprojectdelaysinsomecases,andalsotofrustrationonthe

Page 80: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐23 

customer’sordeveloper’spart.Fromautilityorprogramadministrator’sperspective,theremaybedifficultyduetolimitedfinancialorstaffresources,suchthatitisnotefficienttoadministeranumberofdifferentprograms.However,DGprogrammanagersdidindicatethatthiswasnotamajorconcernforutilitiesindeployingDG,andthatthearrayofdifferentDGprogramswasappropriatebecauseeachistargetedatadifferentprojecttypeorcustomersegment.Theirmainconcernwasthattheyspendasignificantamountofstafftimeeducatingcustomers,installers,anddeveloperswhoareunfamiliarwiththemultitudeofprograms.

5.5.4 Availability of Installers 

Inordertodeploycustomer‐sideDG,skilledandexperiencedinstallersmustbeavailabletosupportvoluntaryDGinstallations.TherateofDGdeploymentdependsinpartontheavailabilityofinstallers,andalackofinstallersinthepastconstitutedabarriertogreaterdeployment.Ingeneral,utilityrepresentativesagreedthatalackofDGinstallersmayhavebeenaproblempreviously,butthatitisnotawidespreadbarriernowbecausethevolumeofinstallationsandinstallershasrisendramaticallyandsohasthenumberandcoverageofexistinginstallers.Intheopinionofutilityrepresentatives,competentinstallersarenowavailableinmostpartsofCalifornia.

5.5.5 Marketing and Consumer Education 

BecauseDGinstallationsarevoluntary,customersmustfirstbeawareofDGasanoptionfortheirelectricneeds,andalsoseeitasapotentiallybeneficialoption—intermsofeconomiccost,environmentalimpact,energyindependence,localjobcreation,orsomecombinationofthese.DGincentiveprogrammanagersconfirmedthatthisissuehasbeenandcontinuestobeabarrierforgreaterDGdeploymentinCalifornia,thoughitisnotconsideredsignificantenoughtodaytobelistedasakeybarrier.ThegeneralpublicismuchmoreawareofDGtechnologiesandtheirbenefitsnowthanwasthecaseafewyearsago,duelargelytothefundingandeffortsofthestate’sDGprogramsaswellastheeffortsofinstallersthemselves,whoperformasubstantialamountofmarketingandconsumereducationaspartoftheirsalesprocess.However,moreinvestmentinmarketingandeducationofconsumerswouldlikelyreducethisparticularbarrierfurther.

Therearealsoopportunitiesforbettertargetingofsuchmarketingandeducationefforts,butmanyofthesewouldrequireinformationsharingbetweenentities.Forexample,CCSEadministerstheCSIandSGIPprogramsinSDG&E’sserviceterritory,andalsoleadsmarketingfortheseDGprogramstoSDG&Ecustomers.However,CCSEdoesnothaveaccesstospecificcustomerinformationwhichcouldhelpittotargetitsmarketingtowardthosecustomersmostlikelytoadoptDG,e.g.higherincomecustomers,customerswithrelativelyhighusage,customersondistributioncircuitswithsignificantexcesscapacity,etc.

5.5.6 Forecasting Future DG Installations  

TheabilityorinabilitytoforecastfutureDGinstallationsisanissueforutilitiesandprogramadministrators.Programadministratorsneedsuchforecastsofinstallationstoallocatefinancialandstaffresourcesandplanforfuturechangesinbudgetorstaffinglevels.WhentheforecastsareinaccurateitcanleadtoinsufficientresourcesandthereforebacklogsinDGapplicationprocessing.UtilitydistributionplanningprocessesshouldhaveforecastsoffutureDGinstallationsandoutputtodesigntheirsystems.AsDGinstallationsincrease,inaccurateforecastscouldimpactthegrowthofthedistributionsystemsuchthatappropriateinfrastructureisnotavailabletoaccommodategrowthofDGinstallationsinthemostcost‐effectivemanner.Programadministratorsindicatedthatshort‐termDGinstallationforecastshavebecomerelativelyreliablebasedonanalysisofrecentinstallationtrends,butthatlong‐termforecastsaremuchlessreliablebecauseofthevarietyofpolicyandmarketfactorsaffectingDGdeploymentandtherapidpaceatwhichtheychange.

Page 81: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐24 

Overall,theyclaimedthatlong‐termforecastingisnotyetasubstantialissue.However,utilitydistributionengineersdidseethisasapotentiallysignificantissueforfutureDGexpansion,althoughithasnotmanifestedtoalargeextentyet.

5.5.7 Project Siting 

ThereareseveralaspectsofsitingaDGprojectthatcouldconstituteabarriertofurtherdeploymentofDG.Ithasbeenestimatedthatupto75percentofelectriccustomersdonothavetheabilitytoinstallsolarPVontheirownproperty.82Thereareavarietyofreasonsforthis,including:1)residentialandcommercialrentersoftendonothavethenecessaryauthoritytoinstallpermanentequipmentlikeaPVsystem,2)manyhomesarelocatedinareaswithinadequateresources(e.g.,toomuchshade)orinfrastructure(roofswithanon‐optimalorientation),3)non‐taxableentitiescannottakeadvantageoftheITCorothertaxbenefitsavailableforPV,and4)avarietyofcustomersdonothavethetimeorfinancialcapacitytoinstallPV.Allofthesebarriersapplyinprincipletonon‐solartypesofDGaswell.PG&EindicatedthatDGtechnologiesotherthansolar,suchaswind,areactuallymuchmorecomplexandlesscommon,whichcanbeabarrierforcustomerstositeandsuccessfullyinstallduetotherelativelackoftechnicalexpertise,potentialcommunityreaction,andquestionsfrompermittingauthorities.

Apotentialsolutiontothisbarrieristheuseofvirtualnetmetering,whichallowsmultiplecustomerstoobtainbillcreditforelectricityproducedatanothersiteandcountittowardtheirownelectricityconsumption.IntheU.S.,virtualnetmeteringarrangementsareoftenusedby“communitysolar”projects(whenthepowerisgeneratedbysolarPV),whichreferstoarangeofprogramandprojecttypesthatallowgroupsofcustomerstoreceivebenefitsfromasinglesolardevelopment.ThesamestructurehasbeenusedinotherpartsoftheU.S.andEuropeforsmall‐scalewindsystems.Communitysolarprojectscanbebuiltandfinancedbyindependentdevelopers,inwhichcasethearrangementcanbesimilartoathird‐partysolarleaseorpowerpurchaseagreement,orbyutilities,whichcanoffercustomerstheabilitytodirectlypurchaseaportionoftheproject’soutputortoparticipateina“solarrate”.Theseprojectshavethepotentialtotakeadvantageofbettersites(intermsofresource,easeofinterconnection,publicvisibility,etc.),toreducecoststhrougheconomiesofscale,toeliminatethecustomer’sresponsibilityforfinancingcostsoroperationsandmaintenance,tofacilitateparticipationforthosecustomerswhocouldnototherwisebuildsolarPV,andtoenablecustomerstocontinuebenefitingfromtheprojecteveniftheymove.83

However,itshouldbenotedthatmanyofthesamecostallocationconcernsthatapplytoregularNEMinstallationsalsoapplytovirtualNEMarrangements—customersparticipatinginavirtualNEMarrangementmayreceiveasubsidyfromotherratepayers.

5.6 KEY ISSUES AND BARRIERS CaliforniahasmadesignificantprogressaddressingissuesandbarriersrelatedtoDG.Manyoftheissuesandbarrierslistedinthissectionhavebeenatleastpartiallyaddressed,andtheindustryandregulatorsareworkingonmanyothers.TheissuesandbarriersdescribedinthissectionmaylimitorotherwiseaffectthedeploymentofDG,andseveralofthemimpacttheabilitytoreceivethetoutedbenefitsofDG.Thekeyissuesandbarriersidentifiedinthisreportarelistedbelow.

                                                            82 The Vote Solar Initiative, “Community Shared Solar: Bringing Solar to the Masses,” presentation by Hannah Masterjohn, July 2012.  83 Solar Electric Power Association, “Utility Community Solar Programs,” presentation by Bianca Barth, July 2012.  

Page 82: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Issues and Barriers Impacting DG Deployment  5‐25 

Table 5‐3  Key Remaining Issues and Barriers for Customer‐side DG 

Financing and Economics 

• EquipmentandsoftcostsofDGarehighcomparedtogridelectricity.• Availabilityofgovernmentandutilityfinancialincentivesisbecomingmorelimitedbecausefundsfor

incentiveprogramsaredeclining.

Policy and Regulatory 

• PublicresistancetoDGcoulddevelopifnon‐DGcustomersareexcessivelyburdenedwithcoststosubsidizeNEMDGcustomers.

• ThereisalackofincentivestolocateDGinareaswiththegreatestbenefittothegrid;needtoadoptamoretargetedapproach.

Integration 

• Lackofmonitoring,forecastingandcontrolcapabilitieslimitstheutilities’abilitytomanageDGintegrationintothedistributionsystem,andabilitytorelyonDGcapacity.

• LackofcapabilitiesintegratingDG(especiallysolarPV)withdistributionandtransmissionmodels.Thisaffectstheutilities’abilitiestoaccuratelysimulateandplanforDG.

• Distributionsystemdesignisnotintendedforinjectionofgenerationleadingtovoltageissues,reversepowerflow,etc.ThisissuewillbecomemorewidespreadasDGpenetrationincreases.

• Inverterstandardsmayneedtobechangedtoallowbettersupportofthegrid.

Miscellaneous 

• ProcessingtimesandadministrativedelaysforincentiveapplicationsandinterconnectionapplicationsreducethespeedatwhichDGcanbedeployed.

• LackofsuitableprojectsitespreventsthemajorityofutilitycustomersfrominstallingDGontheirownproperty.

Page 83: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐1 

6.0 Emerging Technologies  AlargeamountofresearchanddevelopmentisbeingdoneonemergingtechnologieswhichmayalleviatesomeofthenegativeimpactsandbarrierstogreaterDGdeployment.Themajortechnologiesbeingdevelopedinclude:

Smartinverters

Energystorage

Advancedgridmanagement/smartgridtechnologies

Microgridtechnologies

Thissectiondiscusseseachofthesetechnologiesandtheirpotentialbenefits.

Thedeploymenttimeframeofthesetechnologiesvaries.Therearenumberofdemonstrationprojectscompletedorunderway.GreaterappreciationoftheneedforthesetechnologieswillfollowanincreaseddeploymentofDGsystemsandidentificationofthetechnicalproblemsthatthesenewtechnologiesmaybeabletoresolve.Itisnotknownwhetherthe“tippingpoint”atwhichthesetechnologieswillbecomebeneficial,orevenessential,willoccurwithinthenext1to3yearsorthenext5to10years.However,giventherapidpaceofDGdeploymentinCalifornia,itisreasonabletoproactivelydemonstrateanddeploytheemergingtechnologieswiththegreatestpotentialbenefits.

AlthoughthestatehostsanumberofDGtechnologies,thevastmajorityofDGinCaliforniaissolarPV.SolarPVandwindDGbothhaveissuesassociatedwiththeirvariability,buttheamountofwindDGisverysmallcomparedtosolarPV.OtherDGtechnologiessuchasfuelcellsandinternalcombustionenginesdonotposeallofthesamechallengesasvariablegenerationlikePV.Theyhavetheabilitytobedispatchable,althoughthereiscurrentlynoprocesstoenabledispatchbytheutility.84Thus,becauseofitsdeploymentshareandthecomplexityofissuesassociatedwithvariablegeneration,thissectionwillfocusonemergingtechnologiesrelatedtosolarPV.

6.1 SMART INVERTERS Theinverteristhe“gatekeeper”ofsolarpower,whetherfeddirectlytoanenduser,toanenergystoragesystem,orthroughaninterconnectionontothegrid.Forgridinterconnections,nextgenerationinverters,orsmartinverters,aremachinesthathavespecialfunctionsdesignedtoremedygridfaultsandprotectthequalityofgridpowerbyminimizingtheirimpacttothegrid.Theyareusedforutility‐scalesolarPVsystemsinNorthAmericaandbothutility‐scaleandlargedistributedsolarPVsystemsinGermany.85

Thepotentialforsmartinvertersissignificant.Studieshaveshownthattheymaybeabletomitigatevoltageissuesandincreasethegrid’scapabilitytoaccommodatePVsignificantly.86Smartinvertersmightprovidemanyadvancesincluding:

                                                            84 Despite the fact these technologies are more firm than variable renewables, these types of DG systems are typically baseload rather than having dispatch agreements with the utility.  This makes it difficult for the utility to curtail these units even during system emergencies. 85 Notholt, “Germany’s New Code for Generation Plants connected to Medium‐Voltage Networks and its Repercussion on Inverter Control”, European Association for the Development of Renewable Energies, Environment and Power Quality, April 2009. 86 Braun, et al., “Is the distribution grid ready to accept large‐scale photovoltaic deployment? State of the art, progress, and future prospects”, Progress in Photovoltaics: Research and Applications, 2010. 

Page 84: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐2 

Remotemonitoring

Voltageregulation

VArcontrol

Lowvoltageandlowfrequencyride‐through

Rampratecontrol

Curtailmentability

Thesesmartinverterfeatureswouldbeusedincombinationwithdistributedcommunicationinfrastructurestomanagesolarpowerinjectedintodistributionsystemsinamannerthatiscoordinatedamongsolarpowerandconventionalgenerationsources.Theresultcouldbeastrengtheningofdistributionsystemsthroughtheuseofreactivepowertoregulatevoltagealongdistributionfeeders.

Currently,smartinvertersarenotcodecompliantforusewithdistributedPVsystemsintheUnitedStates.Nationalstandards,IEEE‐1547andUL‐1741donotcomportwithmanyofthesmartinverterfeaturesmentioned.However,thesestandardsarevoluntarybyutilitiesandcouldbedecoupledfromRule21toallowuseofsmartinvertersinCalifornia.TheStatecouldwaitfornationalstandardstoberevised,buttheprocessmaytakeyears.Accordingtocode,DGinvertersmustdisconnectfromthegridforfiveminuteswhentheysenseaproblemwiththequalityofgridpowerandnotreconnectuntiltheproblemisresolved.TheintentionofthisrequirementisforPVsystemstobetakenofflinesothegridcanrecoveronitsown.Codealsorequiresthatinvertersdisconnectfromthegridduringpoweroutagestopreventsolarpowerfromharminglinemen.

Inhigh‐penetrationPVscenarios,someresearchersbelievethecurrentU.S.coderequirementscouldcausecascadedisconnectsoflargeswathsofPVsystemsduringgridfaultsandthusexacerbategridinstability.87Smartinvertershavetheabilitytopreventthisbystayingconnectedand“ridingthrough”momentarygridfaults(discussedfurtherinSection4.1.5).Theycanalsoprovidevoltagesupporttothegridduringfaults,thusstrengtheningpowerqualityandthereliabilityofthegrid.Thepowerindustrycallsthistypeofgridsupport“ancillaryservices”.Somesmartinverterscanprovideancillaryservicesatnightinadditiontoduringtheday.

Rampingdownsolarpowersmoothlytoreducesolarpowervariabilityisanotherfeatureassociatedwithsmartinverters.However,smartinvertersalonearenotcapableoframpingdownindividualsolarpowersystems.Energystorageand/oraccuratesolarresourceforecastingcombinedwithautomatedpowercurtailmentarealsoneeded.

Itisimportanttonotethatsmartinverterfeaturesdonotcomewithoutadditionalcost.Thisadditionalcostcouldbequitelargedependingoncommunicationsrequirements(suchasrunninganewfiberopticline)orifenergystorageisincluded.Therefore,smartinvertersarenotasolutiontoallDGissues,andtheircostsmustbeweighedagainstthecostofothermeanstosupporthigherpenetrationPVsuchasreplacingdistributionlineconductors,installingcapacitorbanksinsubstations,etc.

Giventheirreactiveandremedialcapabilities,smartinvertershavegreatpotential;however,therearesignificantchallengestousingsmartinvertersforDG.Inadditiontotheaforementionedstandardsandcostchallengesisthedevelopmentofadistributedcommunicationinfrastructuretosignaltheinverterstodisconnectwhendistributionlinesareseveredorwhengridoperatorsissue                                                            87 “Solar Energy Grid Integration Systems (SEGIS) Program Concept Paper”, US DOE EERE/Sandia, October, 2007. 

Page 85: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐3 

acommand.Also,aprotocolmayneedtobedevelopedtocoordinatetheoperationofallthesmartinverterssothattheywillworktogetherproperly.Toaddressthecommunicationschallenge,severalsolutionsarebeingexplored:

AsolutionhasbeendemonstratedatLakelandElectricinFloridabySatcon,aninvertermanufacturer,incollaborationwithCooperPowerSystemsandtheFloridaSolarEnergyCenter.ThedemonstrationwaspartoftheDOE’sSolarEnergyGridIntegrationSystemstechnologyaccelerationprogram,usingatechnologycalledpowerlinecommunications.88

Anotherpossibility,mentionedduringBlack&Veatch’sinterviewswiththeutilities,isforutilitiestocontrolinvertersthroughsmartmetersviaZigBeeoranotherwirelesscommunicationprotocol;however,untilthePVindustryhasanapprovedZigBeeinverterprotocolforSmartInverters,thisoptionisnottechnicallyfeasible.

Athirdoptionistoinstituteautonomousorpre‐setfunctionalitiesforsmartinverterstoperforminresponsetocertainvoltageconditions,thusrequiringnocontrolbytheutility.Asnotedinthisreport,thisoptionisbeingexaminedinPhase2oftheCPUC’sinterconnectionproceeding.

Finally,anotherchallengeforsmartinvertersisthatutilitiesarenotrequiredtopayallcustomersfortheancillaryservicestheycouldprovideforgridsupport,especiallyiftheinverterisbehindthecustomer’smeter.

Asnotedabove,theintroductionofautonomoussmartinverterfunctionalitiesoncertainDGsystemsisincludedinPhase2oftheCPUC’sinterconnectionproceeding.

6.2 ENERGY STORAGE Energystoragedevicessuchasbatteries,flywheels,compressedair,ultra‐capacitors,andpumpedstoragehydro,canalsoaidinaccommodatingtheintegrationofvariableDGresourcesintothegrid.WhenPVgenerationdrops,storagedevicescanbebroughtonlinetomitigateoutputswings,toprovidesmoothingorfirming,andtoserveloaduntilotherreservescanbebroughtonline.89Storagetechnologieshavedifferentcharacteristics(suchasstoragecapacity,dischargedurationandcost)thatmakethemmoreorlesssuitedforparticularapplications.Ingeneral,theenergystoragetechnologiesaregroupedintopowerandenergyapplications.Belowaresomepotentialenergystoragesolutionsgroupedbydischargeduration,orenergy,capabilities:

ShortDuration(batteries,flywheel,ultra‐capacitor)

MediumDuration(batteries)

LongDuration(pumpedstorage,compressedairstorage)

                                                            88 “Solar Energy Grid Integration Systems: Final Report of the Florida Solar Energy Center Team”, SANDIA REPORT SAND2012‐1395, March 2012. 89 It is also noteworthy that curtailing inverters in advance of steep declines in solar resource using accurate weather forecasting may reduce energy storage capacity required.   

Page 86: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐4 

Figure 6‐1  Energy Storage Discharge Time and Rated Power Graph90 

 

Energystoragetechnologiescanspanawiderangeofpowercapabilitiesaswell.Figure6‐1aboveisagraphicalrepresentationofpowerandenergycapabilitiesofenergystoragetechnologiescompiledbytheElectricityStorageAssociation(ESA).

Oftheseoptions,batteriesaremostoftendeployedwithPV.Leadacidbatterieshavebeenusedwithoff‐gridPVsystemsfordecades,butarerareamonggrid‐connectedsystems.However,batteriesarenowbeingdemonstratedtoreducethevariabilityofsolarpower,providerampratecontrol,provideancillaryservicessupporttothegrid,improvepowerquality,andforloadshifting—i.e.storingelectricitygeneratedduringoff‐peaktimesandusingitduringpeaktimes.91Batteriesarealsousedincombinationwithothertechnologiestoprovidecontinuoussupportforfacilitiesduringgridoutagesinsystemssometimesreferredtoasmicrogrids,describedlaterinthissection.

Theprincipaltwoimpedimentstobatteriesandotherenergystoragetechnologiesare(1)theirrelativelyhighcosts(exacerbatedbyarelativelackofcostdatapubliclyavailable)and(2)inabilitytofitintoexistingregulatoryandoperationalframeworkthatmakestakingadvantageofmultiplebenefitsfromasinglelocationdifficult.Regulators,includingFERCandtheCPUC,havebeguntorecognizethatenergystoragetechnologiesrequirespecialconsiderationandtomodifytheappropriateproductandcompensationrules.Infact,duetoAssemblyBill2514,theCPUCiscurrentlyconsideringwhethertoimplementspecificprocurementtargetsforenergystoragein

                                                            90 Electricity Storage Association 91 “Solar Energy Grid Integration Systems –Energy Storage (SEGIS‐ES) Program Concept Paper”, DOE EERE and Sandia, May 2008. 

Page 87: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐5 

Californiabyutility,toacceleratedeploymentanddecreasecoststhrougheconomiesofscale.92CAISOhasalsobegunconsideringaprocessforenergystoragetoparticipateintheCAISOwholesalemarket,asdiscussedinSection5.3.3.Inaddition,meteringandmonitoringprotocolsforenergystoragearestillbeingrefined.

Researchersarealsoworkingtobringdownthecostofbatterieswhileimprovingtheirperformancethroughtechnologicalinnovations.Recentadvancesinbatterytechnologieshavebeendrivenbymobileelectronicsandelectricvehicles.LeadacidbatteriesarethetraditionalcomplementtosolarPVsystems,butlithiumionbatterieswithuniquecathode,anodeandproprietaryelectrochemicalvariantsarequicklybecomingpopularoptions.Today’sresearchislargelyfocusedonincreasingtheenergydensityofbatterieswhiledrivingdownthebatterycostandimprovingbatterysafety.Onebatteryoptionunderdevelopmentthatshowspotentialforimprovingtheenergydensityofbatteriesisthezinc‐airbattery.Zinc‐airbatteriesmaybelessexpensivethanlithiumion,andlesstoxicandlighterthanlead‐acidbatteries.Additionally,lithium‐sulfurandlithium‐airbatteriescouldfurtheradvancethebatteryenergydensitybyemployingnanostructuresandnovelelectrodecombinations.93

Energystoragedevicesdonotnecessarilyneedtobeco‐locatedwithPV.Theycouldbewidelydistributedacrossthegridtomeetmultipleneedsindifferentapplicationsatvariousscales—fromlargecentralizedstoragedevicesatsubstations,tocommunityenergystoragedevicesondistributionfeeders,tosmalldevicesatindividualhomes(seeFigure6‐2).Forexample,larger,centralizedenergystoragesystemsdeployedforcommercialpurposesarebeingtestedtoshavepeakloadandcouldbeusedtofirmsolarpower.94,95Centralenergystoragesystemsincludebothmetalionvarietiesandflowbatteries,devicesthatuseelectrolyticfluidstostoreenergy.Batteriesinelectricvehiclesarealsobeingconsideredasanenergystoragecomponent.Thoughtheappropriateinfrastructurewouldneedtobedeveloped,theycouldbeusedtofirmsolarpowerandreducepeakloads.96Understandingtheoptimummixoftechnologiesandtheirplacementisachallengeforthefuturecost‐effectivedeploymentofenergystorage.Inaddition,moreresearchisneededontherampingresponsivenessofvarioustypesofstoragetodeterminewhetheritcouldbewidelydeployedacrossthegridtomeetmultipleneedsindifferentapplicationsatvariousscales—fromlargecentralizedstoragedevicesatsubstations,tocommunityenergystoragedevicesondistributionfeeders,tosmalldevicesatindividualhomes.

                                                            92 E. Wesoff, “California Energy Storage Bill AB 2514 Signed Into Law by Governor,” Greentech Media, Sept. 2010.  http://www.greentechmedia.com/articles/read/vc‐cmeas‐gunderson‐on‐utility‐scale‐storage/.  The CPUC’s storage proceeding is Order Instituting Rulemaking Pursuant to Assembly Bill 2514 to Consider the Adoption of Procurement Targets for Viable and Cost‐Effective Energy Storage Systems, R.10‐12‐007, Issued December 21, 2010. 93 Yang, Y. McDowell, M. Jackson, A. Cha, J. Sae Hong, S. Nano Lett. 2010, 10. 1486‐1491.   94 “Public Interest Energy Research (PIER) Program Final Project Report, Demonstration of ZBB Energy Storage Systems”, July 2012. 95 “Energy Storage Shaping the Future of California’s Electric Power System”, California Energy Storage Alliance (CESA) and Strategen, Intersolar, June 2011. 96 “Vehicle‐To‐Grid Technology Gains Some Traction”, New York Times, July 22, 2009. 

Page 88: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐6 

Figure 6‐2  Potential Applications of Energy Storage (Black & Veatch) 

6.3 ADVANCED GRID MANAGEMENT / SMART GRID TECHNOLOGIES Asmentionedpreviously,thevariablegenerationofsolarPVsystemsmayimpactnormalgridoperations.Gridoperatorsareconstantlyworkingtobalancesupplyanddemandonthegrid.Theymustmaintainpowerqualitybyregulatingvoltage,current,andfrequency.SmartgridtechnologieswouldallowincreasedawarenessandcontrolofthedistributionsystemandmayenablesolutionstomanyDGintegrationissues.SmartinvertersforDGonthecustomersidehavethepotentialtocomplementsmartgridtechnologiesontheutilitysideofthedistributionsystem,andsmartgridtechnologiescanalsosupporttheuseofenergystorage.

AnumberofeffortsintheareasofsmartgridinfrastructureareunderwaytoprepareforhighpenetrationDGPV(Figure6‐3).Thissectiondescribessomepotentialsmartgridsolutions.

Page 89: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐7 

Figure 6‐3  Emerging Smart Grid Infrastructure in Support of High Penetration DG PV 

EnhancedVoltageMeasurementandAutomatedControl–Voltageregulationisacorefunctionofutilityoperations,butDGhasthepotentialtomakevoltageregulationsignificantlymoredifficult.However,widespreaddeploymentofadvancedmeteringinfrastructure(AMI),or“smartmeters,”hascreatedanewtechnologyenablerthatcanimprovevoltagecontroleffectivenessandhelpmitigatesomeoftheissuesrelatedtoDG.SmartgridandAMIsystemshavelaidthefoundationforimprovedvoltagemanagementbyprovidingreliable,two‐waycommunicationsbetweennumerousfielddevices.Intelligentelectronicdevices(IEDs)incombinationwithsubstation/feedercontrolornewcentralizeddistributionmanagementsystems(DMS)canmeasurevoltagefromeverygridendpointandprovideimprovedvoltagecontrols.SystemssuchasAdvancedVoltVArControl(AVVC)canallowenhancedcontrolofvoltageandVArflow.AVVCallowsamoreefficientuseoffieldcapacitorbanksandotherequipmenttooptimizepowerflow.

LoadControl–Directloadcontrolallowsutilitiestoturnonandoffcertainloads(i.e.facilities,equipment,appliances,etc.)duringcertainperiodswhenelectricitydemandishigh,orwhenintermittentdistributedgenerationrampsupordownsuddenly.Thiscanenableutilitiestomanageandoptimizeanincreasinglydynamicelectricpowergridonwhichpowerisinjectedatdistributedlocationsthroughoutthesystem.

Re‐Sectionalizing–Gridre‐sectionalizinginvolvestheautomaticreroutingofpowerfromonepartofthegridtoanother.Asthedistributionsystembecomesmoredynamic,andvariableDGsourcesareaddedinlargequantities,itwillbeimportantforutilitiestobeabletomanagepowerflowandvoltageamongdifferentsectionsofthegrid.Widespreaduseof

Solar PowerEnergy Storage

Demand Response

Time of Use Pricing Data

Generation & Load 

ForecastingData

Central Generation Balancing

SCADA:Supervisory Control & Data 

Acquisition

Central Energy Storage Balancing

Distributed GenerationHomes & Buildings

Central GenerationCAISO & Utilities

Emerging Smart Grid Infrastructure in Support of High Penetration DG PV

Page 90: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐8 

automatedswitchingsystemswillbeanimportantcomponentofthissolution.Thefigurebelowillustratesanexampleofre‐sectionalizing.

Figure 6‐4  Re‐sectionalization Example 

DistributionManagementSystem(DMS)–DMSisanintegrateddecisionsupportsystemwherebyalloperationalaspectsoftheutility’sdistributionsystemaremadevisibleandoperablefromacentralsource.Advancedalgorithmsareusedtooptimizethesysteminreal‐timebasedonvaluesprovidedbyAMIandsupervisorycontrolanddataacquisition(SCADA)systems.ADMScanbeenhancedwithcentralizedvolt/VARoptimization(VVO)basedonanon‐linepowersystemmodel.97ImplementingaDMSwithVVOisamajorinitiativethatcouldtakemultipleyearstocomplete;however,ithasmanybroadbenefits.ForintegrationofDG,aDMScanhelpautilitymaximizeitsmultipledistributedenergyresourcestakingintoaccountloadforecasts,weatherforecasts,DGoutputforecasts,electricvehicles,andstorage.Thisincludeshandlingresourcedispatching,initiatingdemandresponseprograms,verifyingandvalidatingactivedemandresponseprograms,mitigatingvoltageissues,andmanaginganetworkedpowersystemgridwithbi‐directionalflows.Ifcommunicationprotocolsareharmonized,aDMScouldalsoprovidedirectcommunicationwithDGsmartinvertersthatwouldfurtherenhancegridoperations.

Smartgridtechnology,andtheadvancedgridmanagementsolutionsthatitenables,isanemergingfield.Additionalsmartgridtechnologiesnotcoveredheremayhelpaddressotherchallengesinthefuture.

6.4 MICROGRIDS Onesubsetoftheemergingsmartgridinfrastructureis“microgrids,”whichcouldbeparticularlyimportantforgridintegrationofDGinthefuture.Amicrogridisasmallpowersystemthatincorporatesself‐generation,distribution,sensors,energystorage,andenergymanagementsoftwarewithaseamlessandsynchronizedconnectiontoautilitypowersystem.98Amicrogridcan

                                                            97 VVO is a method of optimizing distribution power delivery, which utilizes distribution automation, SCADA, and AMI to reduce energy consumption and peak energy capacity demand by improving system power factor. VVO is based on sophisticated algorithms and logic from the on‐line power flow application, which is another application within the DMS suite. 98 http://www.smartgridlibrary.com/  

Page 91: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐9 

operateinparallelwiththeutilityorindependentlyasanislandfromthatsystem.Itspurposeistoincreasereliabilityforcustomerswithinthemicrogridbymaintainingpowerevenwhentheutilitygridisexperiencinganoutage,andalsotoallowlocalizedcontrolofenergyinfrastructure.Theoretically,microgridscanalsosupportthelargerutilitygridbydecreasinglocalloadandsafelyexportingpowerattimeswhentheutilitygridisstressed.Inaddition,microgridshavethepotentialtoprovideanumberofserviceswhichwouldenablegreaterDGpenetration:

Seamlessbidirectionalenergyflow

Voltage,frequencyandVARcontrol

Eliminationofmomentaryoutagesassociatedwithtypicalstandby/backuppowersystems

Pricedrivenloadmanagement,i.e.demandresponsebasedondynamicpricesignals

Self‐healingnetworksthroughintegrationoffeederautomation

Morerobustcommunicationandcontrolofthedistributionsystem

Anumberofutilities—includingSDG&EandSMUD—areinvestigatingthecostsandbenefitsofmicrogridsthroughdemonstrationprojects,usuallyfundedbygrantsfromtheU.S.DOEandtheCEC.SDG&EhassignificantmicrogridprojectsoperatingwithinitsserviceterritorywhichincorporateDGasoneofthecorecomponents:

1) UniversityofCaliforniaSanDiego(UCSD)Microgrid:TheUCSDcampushasinvestedsignificantresourcesintyingtogetherdistributedPVresources,abiogasfuelcell,andanaturalgascentralcogenerationplantwithresponsiveloadsincampusbuildingsthroughanincreasinglysophisticatedcentralcontrolsystem.Itisclaimedthattheflexibilityofthis42MWmicrogridallowsthecampustosavesignificantamountsofmoneyonitsutilitybillsannually,andprovidesupto85percentofcampuselectricity.Also,UCSDhasbeenabletoreduceitslocalloadsandexportpowertotheSDG&EgridduringemergenciessuchastheblackoutofSeptember2011andthewildfiresof2009.99Thecampuswasabletoswitchfromimporting3MWofpowertoexporting2MWofpowerwithin30minutesduringthe2009incidentandtherebyprovidecriticalsupporttothelargergrid.100TheUCSDmicrogridisanevolvingandongoingproject,fundedbytheuniversity,andwillcontinuefortheforeseeablefuture.101

2) BorregoSpringsMicrogridProject:ThisprojectintheSanDiegoareaisdesignedasapilot‐scaleproofofconceptofhowinformation‐basedtechnologiesanddistributedenergyresourcesmayincreaseutilityassetutilizationandreliability,includingcontributionsfromanumberoforganizationsandvendors(IBM,HorizonEnergyGroup,Motorola,PacificNorthwestNationalLabs,Oracle,AdvancedEnergyStorage,UniversityofSanDiego,LockheedMartin,GridPoint,andXanthus).Itsgoalsareto:1)reducefeederpeakloadbymorethan15percentthroughDG,energystorageandloadmanagement;2)demonstrateVARmanagement;and3)developandtestavarietyofdistributionmanagementsystemsandcapabilities—e.g.,advancedmeteringinfrastructure,outagemanagementsystems,feederautomationtechnologies,pricedrivenloadmanagement,andintentionalislanding.Itincorporatesawidevarietyofcustomer‐sidetechnologies,includingrooftopsolarPV,batterystorage,grid‐friendlyappliances,demandresponsethroughremote‐controlledthermostats,andplug‐inhybridelectricvehicles.ThesmalltownofBorregoSprings,eastof

                                                            99 http://blog.rmi.org/the_ucsd_microgrid_showing_the_future_of_electricity_today  100 http://www.rmi.org/nations_largest_microgrid_online_esj_article  101 http://sustainability.ucsd.edu/initiatives/energy‐production.html  

Page 92: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Emerging Technologies  6‐10 

SanDiego,alreadyhadalargeamountofsolarPVinstalledevenbeforethismicrogridprojectbegan.Theprojectincludesthreedifferenttypesofbatteryenergystorage(alargebatteryatthesubstation,threemedium‐sizedbatteriesonadistributionfeeder,andsixsmallbatteriesatindividualhomes);amicrogridyardatthesubstationwithdieselgenerators,transformers,aSCADAswitch,andacontrolvan;homeareanetworkscapableofrespondingtopricesignalsandreliabilityevents,withsmartappliancesthroughoutthehome;andasignificantamountofdistributedPVthroughoutthecommunity.ThemicrogridwillbeownedbySDG&E.Thisprojectisbilledasthefirstlarge‐scaleutility‐ownedmicrogridintheU.S.,withthegoalofprovinganalternativeservicedeliverymodel,islandingrealcustomers,andestablishingatemplateforotherutilitiestofollow.Designandplanningbeganin2010andtheprojectisexpectedtobecompletedin2013.102

Mostmicrogridprojectstodayinvolvesomedegreeofretrofittoexistingdistributionsystems,andalsoincorporateawiderangeofnewtechnologiesandsoftwareforresearchpurposes.Thus,thereislimiteddataonthecostsofnewcommercialmicrogridsimplementedinrealsettingswithonlythetechnologyneededfortheparticularlocationinquestion.However,gatheringfurtherdataoncommercialmicrogridcostswouldbeusefulfromtheperspectiveofunderstandingthecostofintegratingDG,sincemanyofthefeaturesofmicrogridsmaybenecessaryinfuturedistributionsystemswithhighpenetrationsofDG.

                                                            102 SDG&E, “SDG&E Borrego Springs Microgrid Demonstration Project,” presentation by Thomas Bialek, June 2012.   

Page 93: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Recommendations for Future Study  7‐1 

7.0 Recommendations for Future Study DistributedgenerationdeploymentontheCaliforniadistributionsystemhasbeenincreasingoverthepastseveralyears.Withthisincrease,thereareseveralunknowns.WhilethisreportdescribesmanyoftheimpactsofDG,nearlyalloftheinformationisqualitativeandbasedonlimitedobservations.ThereismuchtobegainedfromamoredetailedandquantitativeinvestigationofthecurrentandfutureimpactsofDGontheelectricgridoftheIOUsinCalifornia.Suchaninvestigationshouldrelyon“real‐world”fielddatatotheextentpossible.QuantificationofDGimpactsisvitallyimportanttotheDGindustry,utilitiesandpolicymakers.ItwillinformdecisionsthatseektofurtherDGgoalswhileminimizingthenegativeimpactsofDGandmaximizingitsbenefits.

Black&Veatchhasdetailedascopeforsuchastudy,includedinAppendixC.Insummary,thistypeofinvestigationwouldaddressthefollowingquestions:

HowisDGaffectingthedistributionandtransmissionsystemcurrently,andhowwillthischangeinthefuture?

HowmuchmoreDGcouldbedeployedonthesystemifsitingwereoptimizedforminimalimpactsandenhancedbenefits?

Whatadditionaltoolsareneededtoidentifyoptimallocation,type,andtimingofDG?

Howcananenhancedunderstandingofthecostsofdifferentimpacts,benefitsandsolutionshelpinformeffectivepolicytoenablethedeploymentofmoreDG?

HowcouldthedeploymentofmoreDGbebeneficial?Ifdeployedineffectively,howcoulditbedeleterious?

AnsweringthesequestionscanhelpcreateaclearroadmapofthegrowthpotentialofDGandenableCaliforniatoanticipatepotentialchallengestoDGdeployment.Acomprehensivestudycanhelpanswerthequestionsbysummarizingtheanalysisthathasbeendonetodate,analyzingtheavailabledataforexistingsystems,andforecastingimpactsoffuturegrowth.

Suchananalysisshouldstudythefiveprimarysectionslistedanddescribedbelow:

1. ExistingConditions–Aliteraturereviewandquantitativeassessmentofthefollowing:

a. StatusofDGonthedistributionsysteminCaliforniab. TrendsinDGdeployment

c. StatusofDGinotherstatesandcountries

2. ImpactsandCostsofDG–CompiledataonDGinCaliforniaandextractmeaningfultrendstoquantifycurrentimpactsandcostsofDGinCalifornia.

3. PotentialBenefitsofDG–Quantifybenefits(or,insomecases,costs)ofDGduring

operationsuchaslinelosses,avoidedenergy,andreducedpeakdemand.4. Solutions–Identifyanddiscusspotentialsolutionsorstrategiesthatmaymitigateimpacts

andenhancebenefitsofDG.

5. ScenarioAnalyses–PerformmodelingthatidentifiesdifferentDGpenetrationscenariosandtheassociatedimpacts.ThismayincludemodelingimpactsatdifferentDGpenetration

levels,differentfeedertypes,theeffectofsolutionsidentifiedinsection4,andvariousDG

technologies.

Page 94: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Recommendations for Future Study  7‐2 

Theanalysisshouldfocusonthestatus,impacts,costs,andbenefitsofDGonthedistributionsystem,ratherthanthetransmissionsystem,anditshallbeatechnicalandquantitativeanalysis.

Inadditiontotheabovedescribedanalysis,thefollowingareasshouldalsobestudied:

Reportingissues:reviewNEMinstallationdataandcompareagainstincentiveprogramdatabases

ImpactofDG(PVandnon‐PV)penetrationifincentivesandsubsidiesarenotsustainedandwhatothermechanismscanhelpsustainthemarket

Developmentofuser‐friendlymodelsfortransmission,distribution,substationandfeederlevelimpactswithincreasedDGpenetration.ThisshouldincludetransientanddynamicmodelingofDGsystems.

Developaconsistentapproachtodistributionmodelingacrossutilities

Page 95: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Installed Capacity Data  A‐1 

Appendix A. Installed Capacity Data 

Toensuretransparency,datasourcesforinstalledDGcapacityineachDGprogramsandthemethodsusedtofiltereachdatasetarelistedinTableA‐1below.Inallcases,theinstalledcapacityreportedbelowforeachprogramiscurrentasoftheendof2011.

Table A‐1  Data Sources and Data Filtering 

PROGRAM DATASOURCESTATUS(ES)INCLUDED

DATEFILTERUSED

SYSTEMSIZEFIELDNAME

CSIGeneralMarket

CSIWorkingDataSet(6‐27‐2012)

OnlineIncentiveClaimFormSubmitted,IncentiveClaimRequestReview,SuspendedIncentiveClaimRequestReview,PendingPayment,Completed,PBI‐InPayment

FirstIncentiveClaimRequestReviewDatepriorto2012

CECPTCRating

MASHMASHSemi‐AnnualProgressReport,Feb.2012

N/A N/A CEC‐ACMW

SASH2011Q4SASHProgramStatusReport,Jan.2012

N/A N/A TotalkW(CEC‐AC)

SGIP CPUCDatabaseIncentiveClaimReview,PendingPayment,Completed

IncentiveClaimReviewDatepriorto2012

Capacity[kW]

ERP CECDatabase PaidDatePaidpriorto2012

SystemSize(Watts)

NSHP CECDatabase PaymentApprovalPaymentApprovalDatepriorto2012

SystemCapacity

SB1POUCECSB1POULifeofProgramandYearlyStatisticsfor2011

N/A N/A TotalkWInstalled

NEMCPUCInterconnectionDataRequest,Q12012

N/AInterconnectionYearpriorto2012

“TotalInverterNameplate(kW)”‐PG&E;“NEMCapqualified(kW)”‐SCE;“NameplateRating(kW)”‐SDG&E

FIT‐AB1969IOUAB1969ContractSpreadsheets

Online/Operational

ActualCOD/OperationalDate/NewOnlineDatepriorto2012

Capacity(kW)/MW

FIT‐SB32 N/A N/A N/A N/A

SPVPCPUCRPSContractsDatabase

Operational/OnlineOnlineDatepriorto2012

MinMW

RAM N/A N/A N/A N/A

Page 96: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Peak Demand Impact Analysis Methodology  B‐1 

Appendix B. Peak Demand Impact Analysis Methodology 

Indeterminingthepeakdemandimpact,Black&VeatchusedthetotalinstalledDGcapacityasofthedateonwhichthepeakdemandoccurred,whichwasSeptember7th,2011.ThetotalinstalledDGcapacityontheCAISOgridasofSeptember7th,2011bytechnologyispresentedinTableB‐1.

Table B‐1  Total Installed DG Capacity on CAISO Grid as of 9/7/2011 

TECHNOLOGY MWINSTALLED

SolarPV 892

Wind 12

RF

FC 23

MT 4

ICE 12

Non‐RF

FC 18

MT 20

GT 31

ICE 142

AES 2

Total 1,156

SolarPVPeakDemandImpactBlack&Veatchobtainedactual15‐minuteproductiondataforsolarPVsystemsinstalledundertheCSIprogramandSGIP.MeteredsystemsforwhichthisdatawasavailableconstituteonlyasampleofthetotalPVinstallationsontheCAISOgrid,soitwasnecessarytocalculatepeakhourcapacityfactorsbasedonthisproductiondataandapplythesefactorstotherestofthePVsystemswhichwerenotmetered.Tocapturethediversityincapacityfactorsamongthemeteredsystems,thesystemswerecategorizedaccordingtovarious“strata.”ThesestrataareshowninTableB‐2.

Page 97: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Peak Demand Impact Analysis Methodology  B‐2 

Table B‐2  Strata Used to Categorize Solar PV Installations 

PROGRAMPROGRAM

ADMINISTRATOR

INCENTIVETYPE/SYSTEM

SIZE LOCALEINSTALLATIONYEARGROUP

• CSI(incl.MASH&SASH)

• SGIP• ERP• NSHP

• PG&E• SCE• SDG&E/CCSE• SCG

• EPBB<10kW• EPBB≥10kW• PBI<10kW• PBI≥10kW

• Inland• Coastal

• 2001‐2003• 2004‐2006• 2007‐2009• 2010‐2012

Eachcombinationofstratawasclassifiedasa“bin”,andallmeteredsystemswereassignedtoonespecificbin,e.g.“CSI/SCE/EPBB<10kW/Coastal/2007‐2009”.Thetotalinstalledcapacityineachbinwasthencalculated.TheactualproductioninkWhofallsystemswithineachbinwasthensummedforthefour15‐minuteintervalscomprisingeachhour—e.g.thefourintervalsbeginningat4pm,4:15pm,4:30pm,and4:45pmonthepeakdaywassummedforthehourbeginningat4pm.ThiskWhsumforeachbinduringeachhourwasthendividedbythetotalinstalledcapacityofthatbintocalculatethehourlycapacityfactorforeachbin.

Afterdevelopingrepresentativehourlycapacityfactorsforthebins,thecapacityfactorsweremultipliedbythetotalinstallations,bothmeteredandnon‐metered,ineachcorrespondingbintocalculatethetotalhourlygenerationfromeachbin.Finally,thetotalhourlygenerationwassummedforallbins.TheresultingtotalforthepeakdemanddayisshowninFigureB‐1onthenextpage.

Page 98: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Peak Demand Impact Analysis Methodology  B‐3 

Figure B‐1   DG Solar PV Operating and CAISO Load on September 7, 2011 

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000

0

100

200

300

400

500

600

700

800

900

1,000

CAISO Load

 (MW)

Solar PV Operating (M

W)

CSI

SGIP

CEC

All Solar PV

CAISO Load

Peak Solar PV Output: 621 MW

12 am   1 2      3      4      5       6     7     8        9   10     11   12pm 1      2       3    4      5       6     7     8        9   10     11    12am   

CAISOPeak Load: 45,569 MW

Page 99: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Peak Demand Impact Analysis Methodology  B‐4 

 

TheresultingpeakhourcapacityfactorsforeachprogramandadministratoraresummarizedinandTableB‐4below.

Table B‐3  Peak Hour Capacity Factors for Solar PV by Program 

PROGRAM PEAKHOURCAPACITYFACTOR

CSI–EPBB 0.26

CSI–PBI 0.26

SGIP 0.23

ERP 0.23

NSHP 0.26

AllPrograms 0.25

Table B‐4  Peak Hour Capacity Factors for Solar PV by Program Administrator 

PROGRAM PEAKHOURCAPACITYFACTOR

PG&E 0.28

SCE 0.23

SDG&E/CCSE 0.18

AllAdministrators 0.25

WhilethissolarPVpeakdemandimpactanalysisreplicatestoalargeextenttheanalysisconductedpreviouslybyItronforthe“CPUCCaliforniaSolarInitiative2010ImpactEvaluationFinalReport”,Black&Veatch’smethodologyisnotidentical.

Non‐SolarPVPeakDemandImpactFornon‐solargeneration(fuelcells,microturbines,gasturbines,andinternalcombustionengines),the“CPUCSelf‐GenerationIncentiveProgramEleventh‐YearImpactEvaluation”providethepeakdaygenerationhourlycapacitycurvesforthesenon‐PVtechnologies.AsshowninFigureB‐2,thegenerationprofileforthesetechnologiesarenearlyflatthroughouttheday.

Page 100: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Peak Demand Impact Analysis Methodology  B‐5 

Figure B‐2  Peak Day Generation Profiles for Non‐PV Technologies 

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

50,000

0

20

40

60

80

100

120

140

160

CAISO Load

 (MW)

Non‐Solar DG Operating (M

W)

Internal Combustion Engines

Fuel Cells

Microturbines

Gas Turbines

All Non‐Solar DG

CAISO Load

Peak Non‐Solar DG Output: 108 MW

12 am   1 2     3      4      5       6     7     8        9   10     11   12pm 1      2       3    4      5       6     7     8        9   10     11    12am   

CAISOPeak Load: 45,569 MW

Page 101: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Peak Demand Impact Analysis Methodology  B‐6 

Thepeakdemandcapacityfactorswerealsoreportedinthe“CPUCSelf‐GenerationIncentiveProgramEleventh‐YearImpactEvaluation”preparedbyItroninJune2012.TheseareshownbelowinTableB‐5.

ThetotalinstalledcapacityineachofthesetechnologycategorieswasmultipliedbythecorrespondingpeakcapacityfactortocalculatethepeakdemandimpactofeachinMW.Sincepeakcapacityfactordatawasnotavailableforwindturbinesandadvancedenergystoragesystems,theywereassignedacapacityfactorofzero,i.e.theywereassumedtohavenoimpactonpeakdemand.

Table B‐5  Peak Hour Capacity Factors for Non‐PV Technologies 

TECHNOLOGY PEAKHOURCAPACITYFACTOR

WindTurbines 0.00

RenewableFuels

FuelCells 0.84

Micro‐turbines 0.08

GasTurbines 0.00

InternalCombustionEngines 0.49

Non‐RenewableFuels

FuelCells 0.54

Micro‐turbines 0.39

GasTurbines 0.83

InternalCombustionEngines 0.32

AdvancedEnergyStorage 0.00

 

Page 102: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Future DG Study  C‐1 

Appendix C. Future DG Study 

ThereismuchtobegainedfromamoredetailedinvestigationofthecurrentandfutureimpactsandbenefitsofDGontheelectricgridoftheinvestor‐ownedutilities(IOUs)inCalifornia.Suchaninvestigationwouldaddressthefollowingquestions:

HowisDGaffectingthedistributionandtransmissionsystemcurrently,andhowwillthischangeinthefuture?

HowmuchmoreDGcouldbedeployedonthesystemifsitingwereoptimizedforminimalimpactsandenhancedbenefits?

Whatadditionaltoolsareneededtoidentifyoptimallocation,type,andtimingofDG?

Howcananenhancedunderstandingofthecostsofdifferentimpacts,benefitsandsolutionshelpinformeffectivepolicytoenablethedeploymentofmoreDG?

HowcouldthedeploymentofmoreDGbebeneficial?Ifdeployedineffectively,howcoulditbedeleterious?

AnsweringthesequestionscanhelpcreateaclearroadmapofthegrowthpotentialofDG,andtoenableCaliforniatoanticipatepotentialchallengestoDGdeployment.Acomprehensivestudycanhelpanswerthem,bysummarizingtheanalysisthathasbeendonetodate,andanalyzingtheavailabledataforexistingsystems,andforecastingimpactsoffuturegrowth.

Thereareanumberofprojectsandexistingstudiesthathavebeenperformedthataddressthestatus,impactsandbenefitsofDG.Thereareseveralstudiescurrentlybeingperformedwithsomenotableeffortsnowunderwaylistedbelow:

CPUCCSIResearch,Development,Demonstration,andDeploymentPrograms

DOE'sHighPenetrationSolarDeploymentProjects

CPUCStatewideCost‐BenefitsAnalysisofNEM(E3)

CSIMarketTransformationStudy(Navigant)

CPUCRenewableDistributedGenerationTechnicalAnalysis(Black&Veatch)

SanDiegoNEMStudy(Black&Veatch)

TheanalysisperformedaspartofthefutureDGstudyproposedshouldnotduplicateanalysisavailablefromotherstudies,butleverageexistinginformationandcompileitinausefulformattoanswerthequestionsabove.Anewanalysisshouldintelligentlyaggregateavailableinformationandprovideacomprehensivereviewtoextractmeaningfultrendsthataddressopenquestions.Thisstudywillincludefiveprimarysections:

1. ExistingConditions2. ImpactsandCostsofDG

3. PotentialBenefitsofDG

4. Solutions5. ScenarioAnalyses

Page 103: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Future DG Study  C‐2 

Theanalysisshouldfocusonthestatus,impacts,costs,andbenefitsofDGonthedistributionsystem,ratherthanthetransmissionsystem,anditshallbeatechnicalandquantitativeanalysis.

1) ExistingConditionsAssessment

Tasksunderthisfirstsectionwillconsistlargelyaliteraturereviewofexistingstudies(includingthereportslistedabove)andaquantitativeassessmentoftheexistingsystemtocomprehensivelydocumentthecurrentstatusofCalifornia’sdistributionsystemandDGinCalifornia.

a. First,reviewthestatusofthedistributionsysteminCalifornia;documentthedifferencesbetweenutilitiesinCaliforniaintermsofthevintage(new,old),operationalcharacteristics(automated,manual,un‐operated),andotherrelevantaspectsoftheirdistributionsystems.UnderstandhoweachutilityisdealingwithDGanddifferentapproaches.ReviewandunderstandthetestimonywhichresultedintherecentRule21modifications.

b. Secondly,studythetrendsinDGdeploymenttodate.Generally,thisstudyshouldanswerthefollowingquestions:WhereisDGbeinginstalled?WhatfeederscurrentlyhavethehighestpenetrationofDG,andwhatimpactsaretheyseeing?IsthedeploymentofDGrandomintermsoflocation,orclusteredinawaythatcanbepredicted?IsclusteringcausinganegativeimpactthatcouldpreventfurtherDGfrombeingdeployed?Morespecifically,thisstudyshouldassesstrendsbasedonsystemsizecategories,suchaslarge(3‐20MWthatareutilityownedorownedbyIPPswithcontractswithutilities),medium(1‐3MWthatarelikelypartofthefeedintariffprograms),andsmall(0‐1MWwhicharegenerallyresidentialorcommercialinstallationsundervariousincentiveprograms).Specificquestionsundereachsystemsizecategoryshouldbeanswered:

a. Large:

HowmanyoftheseDGprojectsaretransmissiongridconnectedandhowmanyconnecttodistributionandwherearethey?

HowmanyDGprojectsexceedtheloadsonthedistributionlinestheyareconnectedto?

AreanyoftheselargeDGinstallationslocatedonlongruraldistributionlines?

WhatadditionalupgradeshavebeenrequiredtoaccommodatetheselargeDGprojects?

Arethereanyexampleswheresystemupgradeshavenotbeenrequired?

HaveutilitiessitedanyoftheselargeDGprojectstomaximizebenefits?

Whatneedstobedonetomeasureandunderstandthebenefitsandcostsoflargeinstallations?

b. Medium:

HowmanyoftheseDGprojectsexistandwherearethey?

Whatpenetrationlevelisachieved?

Page 104: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Future DG Study  C‐3 

ArethereanyexampleswhereseveralmediumsizeDGprojectsarelocatedononedistributionline?

Towhatextenthavesystemupgradesbeenrequiredformediumsizesystemsoraggregationsofmediumsizesystems?

HaveutilitiessitedanyofthesemediumsizeDGprojectstomaximizebenefits?

Whatneedstobedonetomeasureandunderstandthebenefitsandcostsoftheseinstallations?

c. Small:

Howmanynewsolarhomecommunitiesexist?

Whatpenetrationlevelsexistonthedistributionlinesthesecommunitiesconnectto?

Arethereanylocationswheremultiplehighpenetrationsolarhomecommunitiesconnecttoonetransmissionline?

Whensuchnewsolarhomecommunitiesaredevelopedandimplemented,areanyspecialupgradesmadetooperatedistributionsystemortomeasuretheimpactsofthehighsolarDGpenetrationlevels?

Whatneedstobedonetomeasureandunderstandingthebenefitsandcostsofexistinghighpenetrationsolarcommunities?

c. Finally,includeastudyofthestatusofDGinotherstatesandcountries.HowareothersdealingwithDGimpacts?LikelycandidatesincludeHawaii,GermanyandDenmark.

ThisanalysisshouldprovideausefuldefinitionofDG.ShouldDGincludethosesystemsofacertainsizeconnectedtothetransmissionsystem?ShouldthedefinitionofDGbelimitedtosystems,ofanysize,connectedtothedistributionsystem?

2) ImpactsandCostsofDG

Todate,impactsofDGonthedistributionandtransmissionsystemsarenotwellunderstood.ThereisatremendousamountofdataavailableaboutDGsystemsthroughoutCalifornia,thoughthedataisoftenoutofdate,ofpoorquality,orkeptinobscurelocationsthatlimitaccess.Furthermore,thereappearstobeverylimiteddataabouttheeffectofDGontheutilities’distributionsystems.CompilingthisdataandextractingmeaningfultrendswouldsupportourunderstandingofthecurrentimpactsofDGandtheircosts.Thefollowingdatasetscouldbeused:

Customer‐sideDGsystemsreceivingincentives:

● CSIWorkingDataSet

● SGIPdataset

● ERPdataset

● NSHPdataset

Page 105: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Future DG Study  C‐4 

IOUDGinterconnectiondatasetsandincludinganysystemupgradecostsidentifiedineachapplication(includingNEMandnon‐NEMinstallations)

WholesaleDGsystemsundervariousstateprograms:

● FIT–AB1969

● FIT–SB32

● RAM

● SolarPVPrograms

● FIT–AB1613

IOUWholesaleDistributionAccessTariff(WDAT)interconnectionqueues

CAISOinterconnectionqueue

UnderstandingtheimpactsandcostsofDGinvolvescompilingthereal‐worlddataavailablefromthesourceslistedaboveandothers.Inaddition,availabledataondeployedenergystoragesystemsshouldbecollected,datagapsshouldbeidentified,andresearchstrategiesforfillingthosegapsshouldbecreated.Fromthisdataandotherrelevantdatasources,aplotcanthenbecreated,similartothatshowninFigureC‐1.FigureC‐1showsthehypotheticalincrementalcostofinstallingDGonafeederoverarangeofpenetrationlevels.Thisgraphshouldbefilteredfortheappropriateattributesbecauseeachutilityoperatesdifferently,feederdesignsarehighlyvariableandcanbecharacterizedbyanumberoffactors(e.g.urbanvs.rural),andbecausethesizeofaDGsystemhasaneffectonitsimpacttothedistributionsystem.Theseattributesmayinclude,butnotbelimitedtothenameoftheutility,locationoffeeder,andsizeofDGsystem.

FigureC‐1alsoreflectsthehypotheticallevelofeffortneededtointerconnectagivenamountofDG.Forexample,atlowpenetrationlevels,noupgradestotheDGsystemmaybeneeded;however,whenpenetrationincreasestoacertainpoint,itcouldbethatchangestosystemprotectionschemesordevicesmaybenecessary.

TheintentofthisgraphistoconveyanunderstandingofwhatDGpenetrationlevelscauseimpactsandrequireaction.ThedifferentcurvesinthisgraphilluminatechangesinDGintegrationcosts,basedondifferentsystemscenarios,andcanbeextrapolatedtoforecastimpactsandcostsofDG.

However,itshouldbestressedthatthefigureishypothetical.Itpositsthatcostsincreaseaspenetrationonafeederincreases,andthatdifferentfeedertypesmighthavedifferent,discerniblerelationshipsbetweencostsandpenetration.Infact,neitherofthesemaybecorrectassumptions.PenetrationlevelmaynotbealargedriverincostsandimpactsofDG.Akeyobjectiveofthistaskwillbetotesttheseassumptions.

Page 106: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Future DG Study  C‐5 

Figure C‐1  Sample Graph Showing Interconnection Costs Relative to Penetration Level 

3) PotentialBenefitsofDG

ManystudieshavesuggestedawidevarietyofpossiblebenefitsassociatedwithDGsuchasareductioninpeakdemand;reductioninlinelosses;deferralsofdistributionsystemupgrades;andincreasedreliabilitybecauseofthepresenceofredundantenergysources.However,asshowninthisstudy,veryfewofthesebenefitsarecurrentlybeingadequatelyquantified.Infact,someofthepurportedbenefitsmayactuallybemanifestedascosts.Forexample,ratherthandeferringdistributionupgrades,utilitiesmaybeupgradingtheirdistributionsystemstoaccommodateDG.Finally,itisnotknownifthevalueorresponsibilityforthesebenefitsorcostsisbeingproperlyassignedtotheimpactedparties.

ThistaskrequiresthequantificationoftheactualimpactsofDGthatareseentodayonthedistributionsystem.Manystudieshavebeendoneontheseissuesinthepast.However,thesestudieshavegenerallyreliedonsimulatedscenariosorlimitedactualdatafromisolatedcircuits.TheobjectiveofthistaskwouldbetocollectactualdatafromacrossCaliforniatovalidatewhetherthepurportedbenefitsareactuallybeingachieved.Oncethedataonbenefitsiscollected,itcanbeanalyzedinamannersimilartothecostdata.Trendscouldbeplotted,andkeyvariablesmightbeidentifiedwhichtendtodrivethebenefitsofDGhigherincertainscenarios.

ThemagnitudeofdemandreductionfromDGwouldalsobestudiedfurtheraspartofthistask.Howisdemandaffectedduringminimumloadhours?Whatarethedemandimpactdifferencesbyutility?

< 3 MW

> 3 MW

Urban Feeder

SCE

Rural Feeder

PG&E

SDG&E

0

2

4

6

8

10

12

14

16

18

0% 20% 40% 60% 80% 100% 120% 140%

Rel

ativ

e C

ost

(u

nit

s T

BD

)

Feeder Penetration Level

NoChange

SystemProtectionUpgrades

CapacityAddition Unknown

Hypothetical

Page 107: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Future DG Study  C‐6 

Finally,thisstudyshouldestimatehowimpactswillchangeasDGgrows.Arecertainregionsreceivingmorebenefitsthanothers?

4) Solutions

Thissectionshouldcoverthefollowingquestions:

HowcannegativeimpactscausedbyDGbemitigated?

HowcanthebenefitsofDGbeenhanced?

WhatmeasurescanbetakentochangetheshapeofthechartsdevelopedintheImpactsandBenefitstasks,andwhatdothesemeasurescost?

Basedontheanalysisintheprevioussections,discusspotentialtechnicalsolutionsorstrategiesthatcouldbetakentomitigateimpactsandenhancebenefits.Thesemayinclude:

OptimallylocatingsystemsgeographicallytolimitnegativeattributesofDG,andenhancepositiveattributes.

Designinga“DGReady”distributionsystemandquantifyingassociatedcosts

Strategicallylocatingenergystoragethroughoutthegrid

Aligningincentiveswiththeknownbenefitsandimpactsindifferentlocations

SmartInvertersandSmartGrid

Electricvehicles

DistributionsysteminfrastructureequipmentcommonlyusedbyothercountriestosupporthighpenetrationofDG.

Createtoolstoallowplanninganddistributionengineertominedata(includingSmartMeterdata)tofacilitateabetterunderstandingandidentificationofthecostsandbenefitsofDGsystems.

Manyofthesolutionsidentifiedmayrequirerevisionofdesignstandardsusedbyutilities.Ofthesolutionsidentified,estimatethecostsandbenefitsoftoimplementingthesesolutions.

5) ScenarioAnalysis

TounderstandthequantitativeimpactsofvariousDGpenetrationlevels,andsolutions,ascenarioanalysisshallbeperformed.ThiswillentailmodelingpartsofthedistributionsystemandshowingtheeffectsonthecurvesproposedfortheImpactsandBenefitssections.

StudydifferentpenetrationlevelsofDG:0,10,15,50,75,100,150and200percent

StudyhowsitingDGsystemsdifferentlyimpactsthesystemonvariouscategoriesofdistributionfeeders,suchasruralandurban.

ModelandstudytheimpactsandbenefitsofdifferentDGtechnologiesthathaveseensignificantdeploymentonthegridtodatewhichare:

Page 108: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | Future DG Study  C‐7 

● SolarPV

● Windturbines

● Fuelcells(witheitherrenewableornon‐renewablefuels)

● Gasturbines(witheitherrenewableornon‐renewablefuels)

● Microturbines(witheitherrenewableornon‐renewablefuels)

● Internalcombustionengines(witheitherrenewableornon‐renewablefuels)

ModelandstudytheeffectontheImpactsandBenefitsgraphswhenthesolutionsidentifiedintheabovetaskareimplemented.

ThegoalofthisscenarioanalysiswillbetodescribealikelyrangeofDGpenetrationscenariosondistributionsystemsinCalifornia,andthecostsandbenefitsassociatedwitheach,tohelpinformfutureDGpolicyinthestate.

Page 109: BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION · 12/19/2014  · The previous “Impact of Distributed Generation” report, prepared by Itron, Inc., was issued in January

California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION 

BLACK & VEATCH | January 31, 2013 Report Presentation, Including Selected 2012 Data Updates  D‐1 

Appendix D. January 31, 2013 Report Presentation, Including Selected 2012 Data Updates