biennial report on impacts of distributed generation · 12/19/2014 · the previous “impact of...
TRANSCRIPT
BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION Prepared in Compliance with AB 578 – With Data through 2011 and Selected 2012 Data
California Public Utilities Commission MAY 2013
FINAL REPORT
BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
Prepared in Compliance with AB 578 – With Data through 2011 and Selected 2012 Data
B&V PROJECT NO. 176365
PREPARED FOR
California Public Utilities Commission
18 MARCH 2013
®
®
©Black & Veatch Holding Company 2012. A
ll rights reserved.
©Black & Veatch Holding Company 2013. A
ll rights reserved.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Table of Contents i
Table of Contents 1.0 ExecutiveSummary............................................................................................................................1‐1
1.1 Introduction...........................................................................................................................................1‐11.2 OverviewofDistributedGeneration............................................................................................1‐11.3 ImpactsofDGontheTransmissionandDistributionSystem...........................................1‐41.4 IssuesandBarriersImpactingDGDeployment......................................................................1‐81.5 EmergingTechnologies.....................................................................................................................1‐81.6 RecommendationsforFutureStudy............................................................................................1‐9
2.0 Introduction..........................................................................................................................................2‐12.1 Background............................................................................................................................................2‐12.2 DistributedGenerationPolicy........................................................................................................2‐22.3 ApproachandMethodology............................................................................................................2‐32.4 ReportOrganization...........................................................................................................................2‐3
3.0 DistributedGenerationOverview.................................................................................................3‐13.1 DescriptionofDGTechnologies.....................................................................................................3‐13.2 DGCurrentlyInstalledinCalifornia.............................................................................................3‐3
4.0 DGImpactsontheTransmissionandDistributionSystem.................................................4‐14.1 DistributionSystemReliabilityandOperation........................................................................4‐24.2 TransmissionSystemReliabilityandOperation.....................................................................4‐74.3 SizeandLocationDependentImpactofDG............................................................................4‐104.4 PeakDemandImpactAnalysis.....................................................................................................4‐12
5.0 IssuesandBarriersImpactingDGDeployment.......................................................................5‐15.1 FinancingandEconomics.................................................................................................................5‐35.2 PolicyandRegulatory........................................................................................................................5‐65.3 GridAccessandInterconnection.................................................................................................5‐125.4 Integration............................................................................................................................................5‐195.5 Miscellaneous......................................................................................................................................5‐215.6 KeyIssuesandBarriers...................................................................................................................5‐24
6.0 EmergingTechnologies.....................................................................................................................6‐16.1 SmartInverters.....................................................................................................................................6‐16.2 EnergyStorage......................................................................................................................................6‐36.3 AdvancedGridManagement/SmartGridTechnologies....................................................6‐66.4 Microgrids...............................................................................................................................................6‐8
7.0 RecommendationsforFutureStudy............................................................................................7‐1AppendixA. InstalledCapacityData.......................................................................................................A‐1AppendixB. PeakDemandImpactAnalysisMethodology..............................................................B‐1AppendixC. FutureDGStudy.....................................................................................................................C‐1AppendixD. January31,2013ReportPresentation,IncludingSelected2012Data
Updates...................................................................................................................................................D‐1
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Table of Contents ii
LIST OF TABLES Table1‐1 SummaryofCustomer‐SideDGInstalledinCaliforniabyTechnology(All
IncentivePrograms)through2011..............................................................................................1‐3Table1‐2 KeyRemainingIssuesandBarriersforCustomer‐sideDG................................................1‐8Table3‐1 DescriptionofPrevalentCustomer‐sideDGTechnologies*..............................................3‐2Table3‐2 SummaryofDGProgramCharacteristics..................................................................................3‐4Table3‐3 SummaryofCustomer‐SideDGInstalledinCaliforniabyTechnology(All
IncentivePrograms)through2011..............................................................................................3‐6Table3‐4 SummaryofCSIInstallationsbyProgramandUtility(AllSolarPV)...........................3‐10Table3‐5 SummaryofSGIPInstallationsbyTechnologyandUtility...............................................3‐11Table3‐6 SummaryofERPInstallationsbyTechnologyandUtility................................................3‐12Table3‐7 SummaryofNSHPInstallationsbyUtility...............................................................................3‐12Table3‐8 SummaryofSB1POUInstallationsbyUtility........................................................................3‐13Table3‐9 SummaryofNEMDGInstallationsbyTechnologyandUtility........................................3‐14Table3‐10 SummaryofNon‐NEMDGInstallationsbyTechnologyandUtility..............................3‐15Table3‐11 SummaryofFIT–AB1969InstallationsbyTechnology..................................................3‐16Table3‐12 SummaryofIOUSolarPVProgramInstallationsbyOwnership...................................3‐17Table4‐1 PeakDemandImpactbyTechnology........................................................................................4‐16Table5‐1 IssuesandBarriersImpactingDGDeployment......................................................................5‐2Table5‐2 NumberofInterconnectionApplicationsandAverageInterconnection
ApplicationProcessingTimesforCSIPVSystemsbyIOU................................................5‐15Table5‐3 KeyRemainingIssuesandBarriersforCustomer‐sideDG..............................................5‐25
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Table of Contents iii
LIST OF FIGURES Figure1‐1 GoalsforCalifornia'sActiveDGPrograms................................................................................1‐4Figure1‐2 OperatingDGCapacitybyProgram,andCAISODemand,onSeptember7th,
2011...........................................................................................................................................................1‐7Figure3‐1 GoalsforCalifornia'sActiveDGPrograms................................................................................3‐5Figure3‐2 CumulativeDGCapacityInstalledbyProgram........................................................................3‐7Figure3‐3 CumulativeDGCapacityInstalledbyTechnology..................................................................3‐8Figure3‐4 CumulativeNon‐SolarDGCapacityInstalledbyTechnology............................................3‐8Figure4‐1 TypicalElectricPowerSystemSingle‐LineDiagram............................................................4‐1Figure4‐2 SampleSolarResourceDataforOneDay..................................................................................4‐5Figure4‐3 SolarIrradianceVariability–OneLocationvs.25Locations..........................................4‐11Figure4‐4 ImpactofCustomer‐SideDGonCAISODemandonSeptember7th,2011................4‐13Figure4‐5 OperatingDGCapacitybyProgramandCAISODemandonSeptember7th,
2011.........................................................................................................................................................4‐14Figure4‐6 HourlyDGCapacityFactorsbyProgramandCAISODemandonSeptember
7th,2011................................................................................................................................................4‐15Figure4‐7 PeakDemandImpactofSolarPVonTypicalSCEResidentialDistribution
Feeder.....................................................................................................................................................4‐18Figure4‐8 PeakDemandImpactofSolarPVonTypicalSCENon‐Residential
DistributionFeeder...........................................................................................................................4‐19Figure5‐1 PercentageofPVSystemswithThird‐PartyOwnershipinCSI,2007‐2012...............5‐4Figure5‐2 SolarModulePricesfromDecember2001–March2012..................................................5‐5Figure5‐3 PG&EResidentialRateTierStructure(January2012)........................................................5‐8Figure5‐4 ExampleImpactofRateStructuresonSDG&ECustomerElectricBills........................5‐9Figure5‐5 AverageInterconnectionApplicationProcessingTimesforCSIPVSystems
byIOU.....................................................................................................................................................5‐16Figure5‐6 ExampleInterconnectionCapacityMappingToolfromPG&E.......................................5‐17Figure6‐1 EnergyStorageDischargeTimeandRatedPowerGraph...................................................6‐4Figure6‐2 PotentialApplicationsofEnergyStorage(Black&Veatch)...............................................6‐6Figure6‐3 EmergingSmartGridInfrastructureinSupportofHighPenetrationDGPV..............6‐7Figure6‐4 Re‐sectionalizationExample...........................................................................................................6‐8
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Table of Contents iv
LEGAL NOTICE ThisreportwaspreparedasanaccountofworksponsoredbytheCaliforniaPublicUtilitiesCommission.ItdoesnotnecessarilyrepresenttheviewsoftheCommissionoranyofitsemployeesexcepttotheextent,ifany,thatithasformallybeenapprovedbytheCommissionatapublicmeeting.Forinformationregardinganysuchaction,communicatedirectlywiththeCommissionat505VanNessAvenue,SanFrancisco,California94102.NeithertheCommissionnortheStateofCalifornia,noranyofficer,employee,oranyofitscontractorsorsubcontractorsmakesanywarranty,expressorimplied,orassumesanylegalliabilitywhatsoeverforthecontentsofthisdocument.
ACKNOWLEDGEMENTS TheauthorsofthisreportwouldliketoacknowledgethesignificantcontributionsmadetothisreportbyCPUCstaff(MeliciaCharles,JamesLoewen,HazelMiranda,NealReardonandRachelPeterson),andrepresentativesfromthethreeinvestor‐ownedutilities(PacificGasandElectric,SouthernCaliforniaEdison,andSanDiegoGas&Electric),andtheCaliforniaCenterforSustainableEnergy.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐1
1.0 Executive Summary ThisreportispreparedinresponsetoAssemblyBill(AB)578(Blakeslee,2008)whichrequirestheCaliforniaPublicUtilitiesCommission(CPUC)tosubmittothelegislatureabiennialreportontheimpactsofdistributedgeneration(DG)onCalifornia’stransmissionanddistribution(T&D)systems.Thisreportissummarizedinthesectionsbelow.
1.1 INTRODUCTION TheCPUCoverseesdistributedgenerationpoliciesandprogramsonboththecustomerandutility(wholesale)sideoftheelectricmeterwithintheserviceterritoriesofCalifornia’sinvestor‐ownedutilities.Thisreportisfocusedprimarilyontheimpactsandbarriersofcustomer‐sideDG,ratherthanwholesaledistributedgeneration.ManyimpactsandbarriersforwholesaleDGarealsoprevalentforcustomer‐sideDG.Whereappropriatethisreportdiscussesbothcustomer‐sideandwholesalesystems;however,unlessindicated,“DG”referstocustomer‐sidesystemsinthisreport.
Theprevious“ImpactofDistributedGeneration”report,preparedbyItron,Inc.,wasissuedinJanuaryof2010(2010Report).Forthisreport,anupdateofDGinstallationsresultingfromvariousCaliforniaprogramsisprovidedforcustomer‐sideDGinstallationsthroughtheendof2011.Selectedinformationinthisreporthasbeenupdatedthroughtheendof2012inAppendixD.Thereportalsocoversbrieflythevariousnewprogramsforwholesalegenerationthathavebeenimplementedsincethe2010Report.
Indevelopingthisreport,Black&Veatchreliedonseveralsourcesofinformation,including:
Gatheringandusingprimarydatafromexistingincentiveprograms
InterviewswithutilitydistributionengineersandprogrammanagersofCSIandSGIPprograms
RecentCSIandSGIPreportsandotherpublishedCPUCreportsonDG
Generalliteraturereviewofpaststudiesontheseissues
1.2 OVERVIEW OF DISTRIBUTED GENERATION GovernorBrownhasestablishedahigh‐levelgoalforCaliforniatoachieve12,000megawattsofrenewableDGby2020.Californiahashadahistoryofencouragingthedevelopmentofsmallergenerationfacilitiesthatconnecteddirectlyatthedistributionleveloftheelectricitysystem.DGgrowthhasbeenspurredbyseveralgovernment‐sponsoredincentiveprograms.TheCaliforniaEnergyCommission’sEmergingRenewablesProgram(ERP)wasfundedasaresultofAB1890,andprovidedsupporttoemergingrenewableprojectsonthecustomer‐sideofthemeter.TheCPUC’sSelf‐GenerationIncentiveProgram(SGIP),whichwasstartedinresponsetotheenergycrisisin2001,offeredincentivesforDGprojectslocatedatutilitycustomersites.TheSGIPprogramsupportedavarietyofdistributedgenerationtechnologiesincludingsolarphotovoltaic(PV),wind,fuelcells,andotherconventionaltechnologies.WhentheCaliforniaSolarInitiative(CSI)programandseveralrelatedprogramsbeganin2007asaresultofSenateBill(SB)1(Murray,2006),withagoalofpromoting3,000MWofdistributedsolarinthestate,supportforsolarPVtechnologieswasshiftedfromtheSGIPprogramtotheCSIprogram.
The2010ReportaddressedtheinstalledDGinCaliforniaundertheSGIPandCSIprogramsaswellasnetenergymetering(NEM)andnon‐NEMprojectsinterconnectedtothethreeinvestor‐owned
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐2
utilities(IOUs)throughSeptemberof2009.Sincethen,newprogramshavebeenlaunchedtopromotemoreDGinthestate;bothonthecustomersideofthemeterandonthewholesaleside,andinstallationshaveincreaseddramaticallyunderexistingprograms.Black&VeatchreviewedprogramdatatodeterminethetotalamountofDGthathasbeeninstalled.Theeightcustomer‐sideprogramsinclude:
CaliforniaSolarInitiative(CSI)
● GeneralMarket(GM)
● Multi‐familyAffordableSolarHousing(MASH)
● Single‐familyAffordableSolarHousing(SASH)
SB1Publicly‐OwnedUtility(POU)Programs
NewSolarHomesPartnership(NSHP)
Self‐GenerationIncentiveProgram(SGIP)
EmergingRenewablesProgram(ERP)–nolongeractiveasofJune2012
RenewableEnergySelf‐GenerationBillCreditTransfer(RES‐BCT)Program
NearlyallDGsystemsinstalledundertheseeightprogramsparticipateintheNEMtariff.EachIOUmaintainsaninterconnectiondatabasethattracksDGinstallationsontheNEMtariffandthosenotontheNEMtariff.BasedonthesedatabasesBlack&VeatchsummarizedtheamountofDGinstalledthroughoutthestateundertheNEMtariff(plusnon‐NEMDGinstallations)aswellastheDGinstallationsresultingfromthestate’swholesaleDGprograms.ItshouldbenotedthattheCPUChasrecentlyexpandedthestatewidevirtualnetmeteringtariffaswell,althoughthatprogramisnotdiscussedinthisreportastheexpansionofthatprogramwasnotyetcompleteatthetimethisstudybegan.ThewholesaleDGprogramsconsistof1:
Feed‐inTariff(FIT)
● AssemblyBill1969(AB1969)
● SenateBill32(SB32)
SolarPVPrograms(SPVP)
RenewablesAuctionMechanism(RAM)
Thetotalcustomer‐sideDGinstallationsthrough2011aresummarizedinTable1‐1belowbyutilityandtechnology.ThetotalamountinstalledundertheNEMtariff,inadditiontonon‐NEMDG,isapproximately1,580MW(thisisnotadditivetothecustomer‐sidetotalnotedinTable1‐1).ThetotalamountinstalledunderthewholesaleDGprogramsthrough2011is101MW.Thesenumbersareincreasingquickly.Asoftheendof2012,customer‐sideDGinstallationshadreachedatotalof1,785MW,andwholesaleDGinstallationshadreached177MW.2
Theprimaryfocusofthisreportistoevaluatetheimpactsofcustomer‐sideDGonthetransmissionanddistributionsystems.ManyimpactsandbarriersforwholesaleDGarealsoprevalentfor
1 In addition to these wholesale DG programs, AB 1613 established a FIT for efficient combined heat and power (CHP) systems. SB 1122 also established a FIT for 250 MW of bioenergy, which was signed into law September 27th, 2012. SB 1122 is planned to go into effect in 2013. Neither the AB 1613 program nor the SB 1122 programs were investigated in detail in this report. 2 Additional selected information for 2012 is provided in Appendix D.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐3
customer‐sideDG.Whereappropriate,thisreportdiscussesbothcustomer‐sideandwholesalesystems;however,“DG”generallyreferstocustomer‐sideDGinthisreport.
Table 1‐1 Summary of Customer‐Side DG Installed in California by Technology (All Incentive Programs) through 2011
TECH‐NOLOGY
PG&E SCE SDG&E* SCG POU TOTAL
# MW # MW # MW # MW # MW # MW
SolarPV 57,069 558 26,897 297 13,482 111 264 14 10,360 110 108,072 1,090
Wind 253 7 369 5 35 0 5 0 0 0 662 12
RF** 52 19 23 9 12 7 14 9 0 0 101 44
Non‐RF*** 210 79 81 33 44 24 121 75 0 0 456 211
AES 1 1 0 0 0 0 0 0 0 0 1 1
Total 57,585 663 27,370 345 13,573 142 404 98 10,360 110 109,292 1,357
Thisinformationisthrough2011.Selecteddatahasbeenupdatedthrough2012andisprovidedinAppendixD.Notes:*CaliforniaCenterforSustainableEnergy(CCSE)istheCSIandSGIPprogramadministratorforSDG&E.**RenewableFuels(RF)includesbiomass,digestergas,andlandfillgas.***Non‐RenewableFuels(Non‐RF)includesnaturalgas,propanegas,wastegas,andanyinstallationsforwhichthefueltypeisnotspecified.AES=AdvancedEnergyStorage
AsshowninFigure1‐1below,thegoalsforCalifornia’scurrentlyactiveDGprogramstotalalmost6,000MW,abouthalfoftheGovernor’sstatedgoalof12,000MWby2020.3Notably,thetimeframeformostoftheseprogramsisbeforetheendof2016.About3,750MWofthe6,000MWisrestrictedtosolarPV.Abouthalfofthetotalisrestrictedtocustomer‐sidegenerationonly.
3 Note that additional DG outside these programs would likely be counted towards meeting the Governor’s goal, because the definition of “localized electricity generation” under the Governor’s goal may or may not fall under the definition of “DG” used in this report. Governor Brown’s goal is described at http://www.jerrybrown.org/jobs‐california%E2%80%99s‐future.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐4
Figure 1‐1 Goals for California's Active DG Programs
1.3 IMPACTS OF DG ON THE TRANSMISSION AND DISTRIBUTION SYSTEM TheimpactsofDGonthedistributionandtransmissionsystemtodayarenotadequatelyquantified,butarebelievedtoberelativelylow.Thelackofobservedimpactscanbeattributedtoseveralreasons:
Currentlyabout90percentofconnectedDGcapacityisonthecustomer‐sideofthemeter
Customer‐sideDGsystemsaretypicallysmall
ThecurrentpenetrationlevelofDGislow
Atthegivenpenetrationlevels,theinterconnectionprocessandrequirementshavesuccessfullymitigatedimpactsbeforetheyoccur
ThereisagenerallackofmonitoringDGsystemoutput4andoftheeffectsofDGsystemsonthegrid(thatis,utilitiesdonothavetheappropriatetoolstosystematicallycollectandevaluatedataonproblemsorbenefitsattributabletoDG).
4 Currently, telemetering requirements are imposed only on DG systems 1 MW or larger. Smaller units do not have this requirement since at lower penetrations the expectation was that the impacts would be minimal, the cost to collect the data would be relatively high, and processing of this additional data may not be necessary. This
California Solar Initiative1,940 MW
New Solar Homes360 MW
Public Utility PV SB 1700 MW
Utility Solar PV Programs776 MW
Feed‐in Tariff750 MW
Renewable Auction Mechanism1,299 MW
0 MW
1,000 MW
2,000 MW
3,000 MW
4,000 MW
5,000 MW
6,000 MW
Program
Goals, M
W
System‐side (Wholesale)
Customer‐side
Open to All Renewables
Solar PV Only
+ SGIP (no MW Goal)
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐5
Forthesereasons,itisdifficulttoquantifytheimpactsofcustomer‐sideDGonthegrid.ItisexpectedbymanythatimpactswillincreaseasDGpenetrationincreases.However,tobeabletoquantifytheimpacts,theutilitieswillneedtobeginsystematicallymonitoring,evaluating,andassociatingsuchimpactswithDGsystems.
TheexpectedimpactswouldfirstoccuronthedistributionsystembecauseofthedirectconnectionofDGtothedistributionsystem.However,asthepenetrationofDGincreases,theimpactswillrolluptothetransmissionsystem.Whatmanyindustryobserversagreeonis“DGthatisatthe‘rightplaceattherighttime’willcreatethegreatestvalue,whileadditionalelectricitysupplyinthewrongplaceatthewrongtimecouldresultinaddedcoststothesystem,”asstatedinareportpublishedbyRockyMountainInstituteandPG&EinMarch2012.5However,itisdifficulttodevelopquantitativemeasuringandmonitoringprotocolstosystematicallygaugewhetherDGisbeingdeployedattherightplaceattherighttime,andtherehasbeennoeffortyetinCaliforniatodoso.
ImpactsofDGhavebeensplitintodistributionandtransmission.Belowisalistofimpacts,bothpositiveandnegative,thatDGcanhaveonthedistributionsystem,someofwhichhavealreadybeenobservedonIOUsystems.
Distributionsystemlinelosses
Peakdemandreduction
Deferreddistributionsystemupgrades
Frequencycontrol6
Voltageregulation
Reversepowerflow
Operationalflexibility
Todate,transmissionsystemimpactsduetoDGinstallationshavebeensmall.Theissueslistedbelowarelargelyanticipated,althoughsomehavebeenobservedontheIOUsystems.
Transmissionsystemlinelosses
Reversepowerflowfromthedistributionsystem
Operationalprocedures
Voltageregulation
Reliabilitycapacityandplanning
assumption should be revisited as penetration increases, or the operational requirements for DG change. For example, California utilities have recently proposed telemetering requirements for certain wholesale DG systems smaller than 1 MW that will export power to be aggregated and scheduled into CAISO’s market. As of this writing, the CPUC has not yet evaluated those proposals. 5 “Net Energy Metering, Zero Net Energy, and the Distributed Energy Resource Future: Adapting Electric Utility Business Models for the 21st Century,” Rocky Mountain Institute, Snowmass, CO, March 2012. 6 It should be noted that the frequency of the distribution system and transmission system is the same, and therefore impacts to frequency on the distribution system similarly affect the transmission system. For simplicity, the frequency control impact is listed and discussed under distribution system impacts here.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐6
Capacitymargin
Systemstability
SizeandLocationImpactsThesizeandlocationofDGsystemsinrelationtothedistributionsystemdictatestheirimpactonthegrid.ThougheachdistributioncircuitisdifferentinitscapacitytoaccommodateDG,inmostcasesalargernumberofsmallDGsystemsspreadoverawideareawillhavelessnegativeimpactthanasmallernumberoflargeDGsystemsconcentratedinasinglearea.ThisisespeciallytrueforvariableresourceslikesolarPVandwind,whosevariabilityis“smoothedout”tosomeextentwhenaggregatingtheoutputofmanygeneratorsoverwidegeographicareas.
PeakDemandImpactsInadditiontoexaminingtheimpactsofDGonthetransmissionanddistributionsystems,Black&VeatchanalyzedtheimpactofDGonCAISOpeakdemand.InestimatingtheimpactofthetotalamountofinstalledDGcapacityoperatingontheCAISOgridduringthe2011peakdemandperiod,twoseparateapproachesweretakenforsolarPVandnon‐solarinstallations.TodeterminetheimpactofsolarPVcapacityduringthesystempeakdemand,Black&VeatchusedmetereddatafromalargesamplingofsolarPVsystems.Fornon‐solartechnologies,Black&Veatchuseddatafromthe“CPUCSelf‐GenerationIncentiveProgramEleventh‐YearImpactEvaluation”preparedbyItroninJune2012.
ThetotalamountofDGoperatingduringtheCAISOpeakdemandday(September7th,2011)isdisplayedinFigure1‐2,alongwithCAISOload.Duringthepeakdemandhourof4‐5pm,342MWofDGwereoperating,accountingfor0.7percentofCAISOload.OperatingDGpeakedduringthenoonhour(12‐1pm)at728MW,accountingfor1.8percentofCAISOloadatthattime.Overall,theimpactofDGonCAISOpeakloadissmall,andDGsolarPVpeaksmuchearlierinthedaythanCAISOdemand.AccordingtoBlack&Veatchestimates,DGsolarPVachievesanhourlycapacityfactorof0.25(outof1)duringtheCAISOpeakdemandhour,versus0to0.84forotherDGtechnologies.“Hourlycapacityfactor”referstoagenerator’soutputinaparticularhourrelativetoitsnameplatecapacity;anhourlycapacityfactorof0.25meansthatDGsolarPVinthathourwasproducingaboutaquarterofitsnameplatecapacity.
Black&VeatchacknowledgesthattherearelimitationstoonlyestimatingtheimpactofDGonCAISOpeakdemand.CAISOandeachIOUhastoplanforpeakdemandatavarietyoflevels(customertransformer,distributionfeeder,distributionsubstation,subtransmissionnetwork,transmissionsubstation,transmissionline,theutilitysystem,andtheentireCAISOsystem)andthisreportdoesnotattempttomodeltheimpactofDGateverylevel—althoughthatmaybeausefulexercise.Rather,thisreportseekstoshowthemagnitudeofDGoutputrelativetothetotalCAISOloadbecausethisgivesageneralsenseofhowmuchDGisinstalledstatewide.FuturestudiesshouldconductanalysisofDG’speakdemandimpactatotherlevelsbecausetheimpactislikelytobedifferentatlowerlevelsthanattheCAISOlevel.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐7
Figure 1‐2 Operating DG Capacity by Program, and CAISO Demand, on September 7th, 2011
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
0
100
200
300
400
500
600
700
800
900
1,000
CAISO Load
(MW)
DG Operating (M
W)
CSI
SGIP ‐ Solar PV
SGIP ‐ Non‐Solar
ERP/NSHP
All DG
CAISO Load
Peak DG Output: 728 MW
12 am 1 2 3 4 5 6 7 8 9 10 11 12pm 1 2 3 4 5 6 7 8 9 10 11 12am
CAISOPeak Load: 45,569 MW
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐8
1.4 ISSUES AND BARRIERS IMPACTING DG DEPLOYMENT TherateofDGinstallationsinCalifornia,inparticularsolarPV,hasincreasedsignificantlyoverthepastseveralyears.Thisincreasecanlargelybeattributedtoincentives,theavailabilityofnewleasingandfinancingoptions,thedeclineinsolarPVcosts,andincreasedmarketingefforts.Inmanyrespects,CaliforniahasledthenationinidentifyingandremovingbarrierstoDGdeployment.InitiativessuchasimplementationofNEM,reformofRule21,andcompletionofonlinetoolsforrebateprocessinghaveallowedCaliforniatosuccessfullyadvancethelargestDGmarketintheU.S.Despitethissuccess,therearestillbarrierstoadditionaldeploymentofDGfromtheutility’sperspective,aswellasthecustomerand/ordeveloper’sperspective.
Black&VeatchprovidesanupdateddiscussionofDGbarriersinthisreport.NumerousissuesmaylimitthedeploymentofDG,butmanyhavebeenatleastpartiallyresolved,leavingsomewithmoreimpactthanothers.Thekeyremainingissuesandbarriersidentifiedinthisreportarelistedbelow.
Table 1‐2 Key Remaining Issues and Barriers for Customer‐side DG
Financing and Economics
• EquipmentandsoftcostsofDGarehighcomparedtogridelectricity.• Availabilityofgovernmentandutilityfinancialincentivesisbecomingmorelimitedbecausefundsfor
incentiveprogramsaredeclining.
Policy and Regulatory
• PublicresistancetoDGcoulddevelopifnon‐DGcustomersareexcessivelyburdenedwithcoststosubsidizeNEMDGcustomers.
• ThereisalackofincentivestolocateDGinareaswiththegreatestbenefittothegrid;needtoadoptamoretargetedapproach.
Integration
• Lackofmonitoring,forecastingandcontrolcapabilitieslimitstheutilities’abilitytomanageDGintegrationintothedistributionsystem,andabilitytorelyonDGcapacity.
• LackofcapabilitiesintegratingDG(especiallysolarPV)withdistributionandtransmissionmodels.Thisaffectstheutilities’abilitiestoaccuratelysimulateandplanforDG.
• Distributionsystemdesignisnotintendedforinjectionofgenerationleadingtovoltageissues,reversepowerflow,etc.ThisissuewillbecomemorewidespreadasDGpenetrationincreases.
• Inverterstandardsmayneedtobechangedtoallowbettersupportofthegrid.
Miscellaneous
• ProcessingtimesandadministrativedelaysforincentiveapplicationsandinterconnectionapplicationsreducethespeedatwhichDGcanbedeployed.
• LackofsuitableprojectsitespreventsthemajorityofutilitycustomersfrominstallingDGontheirownproperty.
1.5 EMERGING TECHNOLOGIES MuchresearchanddevelopmentisbeingdoneonemergingtechnologieswhichmayalleviatesomeofthenegativeimpactsofDGsystemsandsomeofthebarrierstogreaterDGdeployment.Thesetechnologiesmayemergewithinthenext1to3yearsorthenext5to10years.However,giventherapidpaceofDGdeploymentinCalifornia,itisreasonabletoproactivelydemonstrateanddeployemergingtechnologieswiththegreatestpotentialbenefits.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐9
ThisreportfocusesonemergingtechnologiesthatwouldprimarilybenefitPV,thelargestsourceofDGinCalifornia.Thesetechnologiesaredescribedinthelistbelow:
SmartInverters–Smartinverterscanbeequippedwithfunctionsthatalleviateimpactstothegrid.Forexample,requiringlowvoltageridethroughfunctionforinverterswouldpreventPVsystemsfromtrippingtooquicklyandaggravatingsystemdisturbances.
EnergyStorage–TheintermittencyofrenewableDGtechnologiesisachallengeintermsofintegratingthesystemstothegrid.Energystoragetechnologiescanalleviatesomeoftheintermittencyofthesesystems.
AdvancedGridManagement/SmartGridTechnologies–Avarietyofsmartgridtechnologiescanprovideutilitieswithmorevisibilityandcontrolwithinthedistributionsystem.ThemajorutilitiesinthestatehavebeenmakinglargeinvestmentsinsmartgridtechnologiesthatcouldhelpeaseDGintegrationissues.
Microgrids–Amicrogridisasmallpowersystemthatincorporatesself‐generation,distribution,sensors,energystorage,andenergymanagementsoftwarewithasynchronized,butseparable,connectiontoautilitypowersystem.ItcanenableDGintegrationthroughbettergridmonitoringandcontrolsystems,coordinationwithotherdistributedenergyresourceslikeenergystorage,andmoreactivedemandmanagement.
Other–ThereareseveralothertechnologiesthatareemergingrelatedtoreducingtheimpactsandenhancingthebenefitsofDG.TheseincludeAdvancedModeling,AdvancedDistributionManagementSystems,AdvancedVoltVArControl.Therearemanyothertechnologiesaswell.
1.6 RECOMMENDATIONS FOR FUTURE STUDY DGdeploymentontheCaliforniasystemhasbeenincreasingoverthepastseveralyears.Withthisincrease,thereareseveralunknowns.ThereismuchtobegainedfromamoredetailedinvestigationofthecurrentandfutureimpactsandbenefitsofDGontheelectricgridoftheIOUsinCalifornia.Thistypeofinvestigationwouldaddressthefollowingquestions:
HowisDGaffectingthedistributionsystemcurrently,andhowwillthischangeinthefuture?
HowmuchmoreDGcouldbedeployedonthesystemwithminimalimpactsandenhancedbenefits?
Whatadditionaltoolsareneededtoidentifyoptimallocation,type,andtimingofDG?
Howcananenhancedunderstandingofthecostsofdifferentimpacts,benefitsandsolutionshelpinformeffectivepolicytoenablethedeploymentofmoreDG?
HowcouldthedeploymentofmoreDGbebeneficial?Ifdeployedineffectively,howcoulditbedeleterious?
AnsweringthesequestionscanhelpcreateaclearroadmapofthegrowthpotentialofDG,andtoenableCaliforniatoanticipatepotentialchallengestoDGdeployment.Suchananalysisshouldstudythefiveprimarysectionslistedanddescribedbelow:
1) ExistingConditions2) ImpactsandCostsofDG
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Executive Summary 1‐10
3) PotentialBenefitsofDG4) Solutions5) ScenarioAnalyses
Theanalysisshouldfocusonthestatus,impacts,costs,andbenefitsofDGonthedistributionsystem,aswellasthetransmissionsystem,andshouldbeatechnicalandquantitativeanalysis.
Inadditiontotheabovedescribedanalysis,thefollowingareasshouldalsobestudied:
Reportingissues:reviewNEMinstallationdataandcompareagainstincentiveprogramdatabases
AmountofDG(PVandnon‐PV)penetrationifincentivesandsubsidiesarenotsustainedandwhatothermechanismscanhelpsustainthemarket
Developmentofuser‐friendlymodelstoassistutilitiesinmodelingtransmission,distribution,substationandfeederlevelimpactswithincreasedDGpenetration.ThisshouldincludetransientanddynamicmodelingofDGsystems
UseofaconsistentapproachtodistributionmodelingandmonitoringacrossutilitiesspecificallytargetedtoassessdistributiongridoperationalimpactsofDGsystems
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Introduction 2‐1
2.0 Introduction ThisreportispreparedinresponsetoCaliforniaAssemblyBill(AB)578(Blakeslee,2008)whichrequirestheCaliforniaPublicUtilitiesCommission(CPUC)tosubmittotheLegislatureabiennialreportontheimpactsofdistributedgeneration(DG)onCalifornia’stransmissionanddistribution(T&D)systems.
OnJanuary1,2009,Section321.7ofthePublicUtilitiesCodewascreatedrequiringtheCPUCtodothefollowing:
321.7.(a)OnorbeforeJanuary1,2010,andbienniallythereafter,thecommission,inconsultationwiththeIndependentSystemOperatorandtheStateEnergyResourcesConservationandDevelopmentCommission,shallstudy,andsubmitareporttotheLegislatureandtheGovernor,ontheimpactsofdistributedenergygenerationonthestate'sdistributionandtransmissiongrid.Thestudyshallevaluateallofthefollowing:
(1)Reliabilityandtransmissionissuesrelatedtoconnectingdistributedenergygenerationtothelocaldistributionnetworksandregionalgrid.
(2)Issuesrelatedtogridreliabilityandoperation,includinginterconnection,andthepositionoffederalandstateregulatorstowarddistributedenergyaccessibility.
(3)Theeffectonoverallgridoperationofvariousdistributedenergygenerationsources.
(4)Barriersaffectingtheconnectionofdistributedenergytothestate'sgrid.
(5)Emergingtechnologiesrelatedtodistributedenergygenerationinterconnection.
(6)InterconnectionissuesthatmayarisefortheIndependentSystemOperatorandlocaldistributioncompanies.
(7)Theeffectonpeakdemandforelectricity.
Thetopicscoveredinthisreportaddressesthestudyareashighlightedinthelegislationrelatedtodistributedgenerationandtheissues,barriersandimpactsassociatedwiththeirincreasedpenetrationinCalifornia.
2.1 BACKGROUND ThisreportisthesecondreportpreparedinresponsetoAB578.Theprevious“ImpactofDistributedGeneration”report,preparedbyItron,Inc.,wasissuedinJanuaryof2010(“2010Report”).7The2010ReportprovidedbackgroundonDGinCalifornia,includingbroaddefinitionsofDGandashorthistoryofDGinCaliforniaaswellastheinstalledDGcapacitythroughSeptemberof2009.
The2010Reportprovidedseveraldefinitionsfordistributedgeneration,includingthefollowing:
DGfacilitiesaremostfrequentlydefinedasnon‐centralizedelectricitypowerproductionfacilitieslessthan20MWinterconnectedatthedistributionsideoftheelectricitysystem.DG
7 Itron, “Impacts of Distributed Generation,” Prepared for: California Public Utilities Commission Energy Division Staff, Davis, California, January 2010.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Introduction 2‐2
technologiesincludesolar,windandwater‐poweredenergysystems;andrenewableandfossil‐fueledinternalcombustion(IC)engines,smallgasturbines,micro‐turbinesandfuelcells.8
Forthisreport,DGissimilarlydefined,butwithaspecialfocusonsmallerDGonthecustomersideofthemeter.TheCPUCregulatesdistributedgenerationpoliciesandprogramsonboththecustomerandutility(wholesale)sideoftheelectricmeter.Thisreportisfocusedprimarilyontheimpactsandbarriersofcustomer‐sideDG,ratherthanwholesaledistributedgeneration.ManyimpactsandbarriersforwholesaleDGarealsoprevalentforcustomer‐sideDG.Whereappropriate,thisreportdiscussesbothcustomer‐sideandwholesalesystems;however,“DG”generallyreferstocustomer‐sideDGinthisreport.
Thisreportalsoprovidesanupdateofcustomer‐sideDGinstallationsresultingfromvariousCaliforniaprogramsthroughtheendof2011.Selectedinformationinthisreporthasbeenupdatedthroughtheendof2012inAppendixD.Thereportalsocoversbrieflythevariousnewprogramsdescribedaboveforwholesalegenerationthathavebeenimplementedsincethe2010Report.ForamoregeneralbackgroundonDG,includingitshistoryinCalifornia,readersshouldrefertothe2010Report.
2.2 DISTRIBUTED GENERATION POLICY GovernorBrownhasestablishedahigh‐levelgoalforCaliforniatoachieve12,000MWofrenewableDGby2020.Whilethisgoalhasnotbeenspecificallyprescribedinlaw,CaliforniahasenactedseveralnewlawsandimplementednewrulestopromoteadditionalDGsincetheissuanceofthe2010Report:
AssemblyBill(AB)1969(Yee,Stats.2006,ch.731)createdCalifornia’sFeed‐in‐Tariff(FIT)program,authorizingthepurchaseofupto480MWofrenewablegeneratingcapacityfromrenewablefacilitiessmallerthan1.5MW.Subsequentlegislation,SB32(NegreteMcLeod,2009)andSB2(1X)(Simitian,2011),increasedtheeligibleprojectsizeto3.0MW,andstate‐widetotalprocurementforinvestor‐ownedutilities(IOUs)andpublicownedutilities(POUs)to750MW.
ForDGprojectsfrom3to20MW,theCPUCadoptedD.10‐12‐048,whichinitiallyauthorizedtheIOUstoprocure1,000MW(recentlyexpandedto1,299MWbyD.12‐02‐035andD.12‐02‐002)throughtheRenewableAuctionMechanism(RAM)programbyholdingperiodicauctionstoprocurerenewableenergy.ThefirstRAMauctiontookplaceNovember15,2011.
Inadditiontotheseprograms,in2009/2010,theCPUCalsoauthorizedUtilitySolarPVProgramsforeachoftheIOUstoownandoperatesolarPVfacilitiesaswellastoexecutesolarPVpowerpurchaseagreementswithindependentpowerproducers(IPP)throughacompetitivesolicitationprocess.Intotal,theseprogramshaveagoaltobringonupto1,100MWofnewsolarPVcapacityinCalifornia.
ElectricRule21istheCPUC‐jurisdictionalinterconnectiontariff.Rule21describestheinterconnection,operatingandmeteringrequirementsforgenerationfacilitiestobeconnectedtoandoperateinparallelwithautility’sdistributionsystem.TheCPUCopenedarulemakingtoimplementimprovementstotheRule21interconnectionprocessinSeptember2011,andatthesametimelaunchedamajorsettlementprocesstoaccomplisha
8 Itron, “Impacts of Distributed Generation,” Prepared for: California Public Utilities Commission Energy Division Staff, Davis, California, January 2010.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Introduction 2‐3
setofglobalreformstothetariff.9TheCPUCprioritizedreformsenhancingRule21forDGprojectsinterconnectingontheutilitysideofthemeter,inordertosupporttheCPUC’snewerwholesaleDGprograms.OnMarch16,2012,fourteenpartiestothesettlementnegotiationsfiledasettlementinCPUCRulemaking(R.)11‐09‐011thatcontainedasignificantlyreformedRule21tariff.ThesettlementwasapprovedbytheCPUCinSeptember2012.10Asaresult,Rule21nowprovidestransparentrulesforaclear,predictablepathtointerconnectionforallformsofdistributedgenerationwhilemaintainingthesafetyandreliabilityoftheelectricgrid.
TheCPUCalsoconvenedRenewableDistributedEnergyCollaborative(ReDEC)workshopstostudytheissuesandimpactsofsystem‐siderenewabledistributedgenerationthatisdispersedthroughoutthegridandinterconnectedforexporttotheutility.TwoworkshopshavebeenheldandtheCPUCmayholdadditionalmeetingsinthefuture.
2.3 APPROACH AND METHODOLOGY Indevelopingthisreport,Black&Veatchreliedonseveralsourcesofinformation,including:
Gatheringandusingprimarydatafromexistingincentiveprograms
InterviewswithutilitydistributionengineersandprogrammanagersofCSIandSGIPprograms
RecentCSIandSGIPreportsandotherpublishedCPUCreportsonDG
Generalliteraturereviewofpaststudiesontheseissues
Inassessingtheissuesandimpactstotheexistingtransmissionanddistributionsystemaswellasdetermining barriers, utility programmanagers and distribution engineers were interviewed togather information regardingactual issuesexperiencedbycustomers, installers, and theutilities.ThisapproachprovidedagaugeforthedegreeofimpacttheseDGissueshaveormayhaveinthefutureonthetransmissionanddistributionsystem.
Black&Veatchalsousedsystemoutputdatatomodeltheimpacton2011peakfromDGinstalledontheCaliforniagrid.
2.4 REPORT ORGANIZATION Thereportisorganizedasfollows:
Section3–DistributedGenerationOverview:Providesanoverviewofdistributedgenerationtechnologiesandthetotalinstalledcapacityinthestateresultingfromvariouscustomer‐sideandwholesaleDGprograms.TheinformationusedisthelatestavailableasofAugust2012,withmanydatasetsupdatedonlythroughtheendof2011.Selectedinformationinthisreporthasbeenupdatedthroughtheendof2012inAppendixD.
Section4–DGImpactsontheTransmissionandDistributionSystem:Highlightspotentialimpactsofconnectingdistributedenergygenerationtothelocaldistribution
9 R. 11‐09‐011, Order Instituting Rulemaking on the Commission’s Own Motion to Improve Distribution Level Interconnection Rules and Regulations for Certain Classes of Electric Generators and Electric Storage Resources, filed September 22, 2011. 10 D.12‐09‐018, Decision Adopting Settlement Agreement Revising Distribution Level Interconnection Rules and Regulations – Electric Tariff Rule 21 and Granting Motions to Adopt the Utilities’ Rule 21 Transition Plans, adopted September 13, 2012, in R. 11‐09‐011; see also www.cpuc.ca.gov/PUC/energy/procurement/LTPP/rule21.htm.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Introduction 2‐4
networksandregionalgrid.ThissectionalsodiscussesDGinthecontextof2011Californiapeakdemand.
Section5–IssuesandBarriersImpactingDGDeployment:IdentifieskeyissuesandbarriersaffectingDGdeploymentinthestate.
Section6–EmergingTechnologies:DescribeskeytechnologyadvancesthatmayhelpaddresssomeofthetechnicalissuesassociatedwithDGonthegrid.
Section7–RecommendationsforFutureStudy:Recommendationsforafuturestudytobetterquantifyimpactsandaddresssomeoftheissuesandbarriersidentifiedinthereport.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐1
3.0 Distributed Generation Overview Californiahashadalonghistoryofencouragingthedevelopmentofsmallergenerationfacilitiesthatconnecteddirectlyatthedistributionleveloftheelectricitysystem.DGgrowthhasbeenspurredbyseveralgovernment‐sponsoredincentiveprograms.TheCaliforniaEnergyCommission’sEmergingRenewablesProgram(ERP)wasfundedasaresultofAB1890(Brulte,1996),andprovidedsupporttoemergingrenewableprojectsonthecustomer‐sideofthemeter.TheCPUC’sSelf‐GenerationIncentiveProgram(SGIP)startedinresponsetothe2001energycrisisandoffersincentivesforDGprojectslocatedatutilitycustomersites.TheSGIPprogramsupportedavarietyofdistributedgenerationtechnologiesincludingsolarphotovoltaic(PV),wind,fuelcells,andotherconventionaltechnologies.In2007,supportforsolarPVtechnologieswasshiftedfromtheSGIPprogramtotheCSIprogramasaresultofSB1,withagoalofpromoting3,000MWofdistributedsolarinthestatethroughtheCSIprograms(GeneralMarket,MASH,SASH),theNewSolarHomesPartnership,andtheSB1POUprograms.
Inadditiontothesecustomer‐sideprograms,therehavebeenanumberofotherprogramsinitiatedtosupportwholesaledistributedgenerationinthestate,inparttohelpthestatemeetitsRenewablePortfolioStandard(RPS)goals.ThissectionprovidesanoverviewofthecurrentDGtechnologiesandinstallationsinthestate.
3.1 DESCRIPTION OF DG TECHNOLOGIES AnumberofDGtechnologieshavebeenpromotedthroughvariousincentiveprogramsofferedbythestate.TheseincludesolarPV,wind,fuelcells,advancedenergystorageandotherconventionaltechnologies.Thesetechnologiesaredescribedinthetablebelow.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐2
Table 3‐1 Description of Prevalent Customer‐side DG Technologies *
TECHNOLOGY DESCRIPTION
SolarPV SolarPV,whichconvertssunlightdirectlytoelectricity,hasbeenthemostwidelyadoptedDGtechnologyinCaliforniatodate.Whileitdoesnotproduceanyemissionsandcanbesitedvirtuallyanywhereinthestate,theproductionofelectricitydependsonwhenthesunisshining.ThisvariabilityinoutputmayposechallengesforT&DgridoperationassolarPVpenetrationcontinuestorise.
WindTurbines AswithsolarPV,windturbinesconvertwindpowertoelectricityonlywhenthewindreachesacertainspeed.Thus,windturbinegenerationisalsovariableorintermittentinnature.InstallationsofDG‐scalewindinCaliforniahavebeenlimited.Windfarmsaretypicallycomprisedoflarger,utility‐scaleturbinesandareconnecteddirectlytothetransmissionsystemratherthanthedistributionsystem.
FuelCells(FC) Fuelcelltechnologycanbeutilizedasaconstantorvariablepowergenerationresource.Fuelcellsconverthydrogen‐richfuelsourcesdirectlytoelectricitythroughanelectrochemicalreactionwithverylowemissions.Mostfuelcellinstallationsgeneratelessthan1MW.Commercialfuelcellplantsaretypicallyfueledbynaturalgas,whichisconvertedtohydrogengasinareformer.However,ifavailable,hydrogen,biogas,orotherfuelscanbeused.Naturalgasisnowatrelativelylowprices,whichmaycauseincreasedininterestinfuelcellsfueledbynaturalgas.
ReciprocatingInternalCombustionEngines(IC)
Reciprocatingengines aretheindustrystandardforbiogascombinedheatandpower(CHP)projects.Theoutputoftheseplantsiscontrollableandcanthereforeberampedupordownasneeded,withnaturalgasasanalternativeorbackupfuel.Theengineconfigurationisdesignedtohandleawiderangeofgasflows;theengineoutputcanbeturneddownsignificantlywithoutlosingaconsiderableamountofefficiency.Internalcombustionenginesarebyfarthemostcommongeneratingtechnologychoiceatbiogasfacilities;about75percentofthelandfillsthatgenerateelectricityuseinternalcombustionengines.
Microturbines(MT)andGasTurbines(GT)
MicroturbinesandgasturbinesarefrequentlyusedforlargerDGinstallationsthroughoutCalifornia.TheiroutputisnotintermittentlikesolarPVandwind,whichmakesintegrationofthesetechnologiestechnicallyeasier.Microturbinescanutilizenaturalgasorbiogasbycompressingandburningwithairinthecombustor,generatingheatthatcausesthegasestoexpand.Theexpandinggasesdrivetheturbine,whichinturndrivesageneratorproducingelectricity.Heatfromtheturbineexhaustisrecoveredintherecuperatorandisusedtopreheatincomingcombustionair.Thishelpsimprovetheoverallefficiencyoftheunit.Microturbinesaretypicallyratedatlessthan250kW,butmultipleunitscanbeinstalledinparallelforhighercapacity.Becauseofsizelimitations,microturbineunitscanbeattractiveforsmalltomediumsizedplants.
AdvancedEnergyStorage(AES)
Energystoragetechnologiesconvertandstoreelectricity,increasingthevalueofpowerbyallowingbetterutilizationofoff‐peakgenerationandthemitigationofpowerfluctuationsfromintermittentrenewableenergygeneration.Differenttypesoftechnologiesareavailablethatprovideavarietyofstoragedurations.Storagedurationsrangefrommicroseconds(superconductingmagnets,flywheels,andbatteries),tominutes(flywheelsandbatteries),tohoursandseasonalstorage(pumpedhydroelectric,batteries,andcompressedair).TheusagethroughoutCaliforniaislimited,drivenbytheemergingtechnology,highercost,andlimitedincentives.AcurrentconstraintonAESdeploymentisthedifficultyofmonetizingitsbenefitstotheelectricpowersystem.
*Thistableincludestechnologiesthatarepartofcustomer‐sideprograms inCA.Otherenergytechnologiesexistthatcanbeappliedindistributedapplications,suchassmallhydro,solidbiomass,andgeothermal;however,thesearenotthefocusofthisreport.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐3
3.2 DG CURRENTLY INSTALLED IN CALIFORNIA The2010ReportaddressedtheinstalledDGinCaliforniaundertheSGIPandCSIprogramsaswellasnetenergymetering(NEM)andnon‐NEMprojectsinterconnectedtothethreeinvestor‐ownedutilities(IOUs)throughSeptemberof2009.Sincethen,newprogramshavebeenlaunchedtopromotemoreDGinthestate,onboththecustomersideandutilitysideofthemeter,andinstallationshaveincreasedunderexistingprograms.Black&VeatchreviewedprogramdatafromtheseprogramsinitiatedinthestatetodeterminethetotalamountofDGthathasbeeninstalled.Theeightcustomer‐sideprogramsinclude:
CaliforniaSolarInitiative(CSI)
● GeneralMarket(GM)
● Multi‐familyAffordableSolarHousing(MASH)
● Single‐familyAffordableSolarHousing(SASH)
SenateBill1(SB1)Publicly‐OwnedUtility(POU)Programs
NewSolarHomesPartnership(NSHP)
Self‐GenerationIncentiveProgram(SGIP)
EmergingRenewablesProgram(ERP)–nolongeractiveasofJune2012
RenewableEnergySelf‐GenerationBillCreditTransfer(RES‐BCT)Program
ManyDGsystemsinstalledundertheseeightprogramsparticipateintheNEMtariff.EachIOUmaintainsaninterconnectiondatabasethattracksDGinstallationsontheNEMtariffandthosenotontheNEMtariff.Basedonthesedatabases,Black&VeatchsummarizedtheamountofDGinstalledthroughoutthestateundertheNEMtariff(plusnon‐NEMDGinstallations)aswellastheDGinstallationsresultingfromthestate’swholesaleDGprograms.ThewholesaleDGprogramsconsistof11:
Feed‐inTariff(FIT)
● AssemblyBill1969(AB1969)
● SenateBill32(SB32)
UtilitySolarPVPrograms(SPVP)
RenewablesAuctionMechanism(RAM)
Table3‐2belowsummarizesthebasiccharacteristicsofeachDGprogram.Eachprogramisdescribedinmoredetailinsections3.2.1,3.2.2and3.2.3.
11 In addition to these wholesale DG programs, AB 1613 established a FIT for efficient combined heat and power (CHP) systems. SB 1122 also established a FIT for 250 MW of bioenergy, which was signed into law September 27th, 2012. SB 1122 is planned to go into effect in 2013. Neither the AB 1613 program nor the SB 1122 programs were investigated in detail in this report.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐4
Table 3‐2 Summary of DG Program Characteristics
PROGRAMYEAR
INITIATEDELIGIBLE
TECHNOLOGIESELIGIBLESYSTEMSIZES
PROGRAMGOAL(MW)
CUSTOMERTYPES
NetEnergyMetering 1995 SolarPV,Wind,FC 1kW–1MW Nospecificgoal AllTypesofIOUCustomers
EmergingRenewablesProgram
1998(endedin2012)
Wind,FC(includedSolarPVuntil2007)
Upto30kW Nospecificgoal AllTypesofIOUCustomers
SelfGenerationIncentiveProgram
2001
Wind,FC,MT,GT,IC,AES,pressurereduction
turbines,bottomingcycles(includedPVuntil2007)
Upto100%ofcustomer’sannualconsumption
Nospecificgoal AllTypesofIOUCustomers
CSI–GeneralMarket 2007 SolarPV 1kW–1MW 1,940MWby2016(5%ofbudget
allocatedtoMASHand5%allocatedto
SASH)
AllTypesofIOUCustomers
CSI–Multi‐familyAffordableSolarHousing
2007 SolarPV 1kW–1MWLow‐incomeMulti‐family
Housing
CSI–Single‐familyAffordableSolarHousing
2007 SolarPV 1kW–1MWLow‐incomeSingle‐family
Housing
NewSolarHomesPartnership
2007 SolarPV 1kW–1MW 360MWby2016 NewResidentialHousing
SB1POU 2007 SolarPV 1kW–1MW 700MWby2016 AllTypesofPOUCustomers
Feed‐inTariff‐AB1969,SB380,SB32
2006‐2009SolarPV,Wind,Biomass,Biogas,SmallHydro
Upto3MW 750MW IPPs–WholesaleSide
UtilitySolarPVPrograms 2010 SolarPVVariesbyutilityfrom0.5MW
to20MW776MW
IPPsandutilities– WholesaleSide
RenewableAuctionMechanism
2011SolarPV,Wind,Biomass,Biogas,SmallHydro
3–20MW 1,299MW IPPs–WholesaleSide
Notes:FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines;AES=AdvancedEnergyStorage
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐5
AsshowninFigure3‐1,thegoalsforCalifornia’scurrentlyactiverenewableDGprogramstotalalmost6,000MW,abouthalfoftheGovernor’sstatedgoalof12,000MWby2020.12Notably,thetimeframeformostoftheseprogramsisbeforetheendof2016.About3,750MWofthe6,000MWisrestrictedtosolarPV.Abouthalfofthetotalisrestrictedtocustomer‐sidegenerationonly.Bycomparison,thecurrentDGprogramgoalsarewellabovethecombinedcapacityofCalifornia’snuclearplants,about4,400MW.(Itshouldbenoted,though,thatthesenuclearplantsarebaseloadresourceswithhighcapacityfactors,whileDGsolarPVsystemsarevariableresourceswithlowercapacityfactors.)
Figure 3‐1 Goals for California's Active DG Programs
Thetotalcustomer‐sideDGinstallationsthrough2011aresummarizedinTable3‐3byutilityandtechnology.13SpecificdatasourcesincludedtheCSIWorkingDataSet,CPUCandCaliforniaEnergy
12 Note that additional DG outside these programs would likely be counted towards meeting the Governor’s goal. The Governor’s goal calls for 12,000 new MW of localized electricity generation, sited at customer loads or close to where energy is consumed so that new transmission lines are not required and environmental impacts are minimized. “Localized electricity generation” counted under the Governor’s goal may or may not fall under the same definition as “DG” included in this report. Governor Brown’s goal is described at http://www.jerrybrown.org/jobs‐california%E2%80%99s‐future. 13 In this table and all others below, “#” refers to the number of individual DG installations, and “MW” refers to the combined installed capacity in ac for all DG installations in that category reported in megawatts. The tables report installations under each of the following utilities: Pacific Gas & Electric (PG&E), Southern California Edison (SCE), Southern California Gas (SCG), San Diego Gas & Electric (SDG&E), and Publicly‐Owned Utilities (POU). California
California Solar Initiative1,940 MW
New Solar Homes360 MW
Public Utility PV SB 1700 MW
Utility Solar PV Programs776 MW
Feed‐in Tariff750 MW
Renewable Auction Mechanism1,299 MW
0 MW
1,000 MW
2,000 MW
3,000 MW
4,000 MW
5,000 MW
6,000 MW
Program
Goals, M
W
System‐side (Wholesale)
Customer‐side
Open to All Renewables
Solar PV Only
+ SGIP (no MW Goal)
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐6
Commission(CEC)programdatabases,SB1POUreports,andCPUCinterconnectiondatarequests.Theinstalledcapacity(AC‐rating)presentedhereinreflectstotalDGprojectsinstalledthroughtheendof2011,excludingqualifiedfacilities(QFs).14ThemethodologyindeterminingthetotalinstalledcapacityisdescribedinmoredetailinAppendixA.
Table 3‐3 Summary of Customer‐Side DG Installed in California by Technology (All Incentive Programs) through 2011
TECH‐NOLOGY
PG&E SCE SDG&E* SCG POU TOTAL
# MW # MW # MW # MW # MW # MW
SolarPV 57,069 558 26,897 297 13,482 111 264 14 10,360 110 108,072 1,090
Wind 253 7 369 5 35 0.1 5 0.1 0 0 662 12
RF** 52 19 23 9 12 7 14 9 0 0 101 44
FC 25 10 15 6 7 6 10 6 0 0 57 28
MT 14 2 4 1 4 1 0 0 0 0 22 4
IC 13 7 4 2 1 1 4 3 0 0 22 12
Non‐RF*** 210 79 81 33 44 24 121 75 0 0 456 211
FC 65 11 5 1 9 3 16 2 0 0 95 17
MT 42 8 27 5 13 1 38 6 0 0 120 20
GT 4 5 0 0 3 9 4 16 0 0 11 31
IC 99 55 49 27 19 10 63 50 0 0 230 142
AES 1 1 0 0 0 0 0 0 0 0 1 1
Total 57,585 663 27,370 345 13,573 142 404 98 10,360 110 109,292 1,357
Notes:*CaliforniaCenterforSustainableEnergy(CCSE)istheCSIandSGIPprogramadministratorforSDG&E.**RenewableFuels(RF)includesbiomass,digestergas,andlandfillgas.***Non‐RenewableFuels(Non‐RF)includesnaturalgas,propanegas,wastegas,andanyinstallationsforwhichthefueltypeisnotspecified.FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines;AES=AdvancedEnergyStorage
Basedonthisanalysis,thetotalnumberofDGinstallationsinthestatereachednearly110,000bytheendof2011andprovidedatotalinstalledcapacityofover1,350MWac.Ofthistotal,
Center for Sustainable Energy (CCSE) is the CSI and SGIP program administrator for SDG&E. Renewable Fuels (RF) include biomass, digester gas, and landfill gas; Non‐Renewable Fuels (Non‐RF) include natural gas, propane gas, waste gas, and any installations for which the fuel type was not specified. 14 QFs are facilities designated under the Public Utility Regulatory Policies Act of 1978 (PURPA) to receive special rate and regulatory treatment. They fall into two broad categories: 1) small power production facilities less than 80 MW whose primary energy source is renewable (e.g. hydro, solar, and wind), or 2) cogeneration facilities.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐7
1,090MWacaresolarPVinstallations.Thesenumberscontinuetoincreaserapidly.Forexample,attheendof2012thetotalcustomer‐sideDGinstalledthroughoutthestatewasabout1,800MW;thisinformationisincludedinAppendixD.
Figure3‐2,Figure3‐3,andFigure3‐4belowdisplaythecumulativeDGcapacityinstalledeachyearsince1998,byprogramandbytechnology(Figure3‐4isamoredetaileddisplayofthenon‐solarDGshowninFigure3‐3).Thelargestgroupofadditionssince2009hasbeensolarPVtechnologiesdevelopedthroughtheCSIandSB1POUprograms.Updatedversionsofthefiguresbelowincluding2012dataareincludedinAppendixD.
Figure 3‐2 Cumulative DG Capacity Installed by Program
0
200
400
600
800
1,000
1,200
1,400
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW Installed
California Solar Initiative
Public Utility SB 1
Self‐Generation Incentive Program
CEC Programs (Emerging Renewables Program and New Solar Homes Partnership)
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐8
Figure 3‐3 Cumulative DG Capacity Installed by Technology
Figure 3‐4 Cumulative Non‐Solar DG Capacity Installed by Technology
The following subsections describe the California DG programs inmore detail, and also provideinstalled capacity data for each. Section 3.2.1 covers customer‐side DG programs, Section 3.2.2
0
200
400
600
800
1,000
1,200
1,400
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
MW Installed
Solar PV
Non‐Solar DG
0
50
100
150
200
250
300
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Non‐Solar MW Installed
Advanced Energy Storage
Internal Combustion Engines ‐ Non‐Renewable
Gas Turbines ‐Non‐Renewable
Microturbines ‐Non‐Renewable
Fuel Cells ‐Non‐Renewable
Internal Combustion Engines ‐ Renewable
Microturbines ‐ Renewable
Fuel Cells ‐ Renewable
Wind
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐9
covers the NEM tariff and non‐NEM DG installations, and Section 3.2.3 covers wholesale DGprograms.
3.2.1 Customer‐Side DG Incentive Programs
Thissectiondescribestheeightcustomer‐sideDGprogramsinmoredetail.TheseprogramsprovidefinancialincentivestosupporttheinstallationofDGonthecustomer’ssideofthemetertooffseton‐siteelectricityconsumption.Eachprogramisdescribedbelow,andtheDGcapacityinstalledundereachprogramissummarizedinTable3‐4.
CaliforniaSolarInitiativeTheCSIprogramhasthreecomponentsasdescribedbelow.ItiscurrentlytheprimaryincentiveprogramforsolarPVinthestate,andisoverseenbytheCPUCwitheachutilityadministeringtheCSIinitsownserviceterritory.15ItprovideseitherrebatesintheformofupfrontExpectedPerformance‐BasedBuydown(EPBB)incentivesorongoingperformance‐basedincentives(PBI)tocustomersofthethreemajorinvestor‐ownedelectricutilitiesinCalifornia(PG&E,SCE,andSDG&E)whoinstallsolarPVsystemsbetween1kWand1MW.Itbeganin2007andhasagoalofinstalling1,940MWofsolarPVinCaliforniaby2016.
CSI–GeneralMarketTheGeneralMarket(GM)portionoftheCSIprogramencompassesthemajorityofresidential,commercial,non‐profit,governmentandindustrialcustomers.Throughtheendof2011,almost63,000projectshavebeeninstalledforatotalof689MW.Sincethen,therehasbeensignificantadditionalgrowth,andbyDecember31,2012thetotalreached91,256projectsand1,031MW.ThoughtheCSIGMprogramisnotscheduledtoenduntil2016,allthreeprogramadministratorsarenearingtheendoftheiravailableincentivesasofMarch2013.Therearetenincentivelevels,andasmoreincentivesarereserved,theincentivelevelsaredesignedto“stepdown”overtime.PG&Ehasreachedthetenthandfinalstepforbothresidentialandnon‐residentialcustomers,SCEhasreachedtheninthstepforbothresidentialcustomersandtheeighthstepfornon‐residentialcustomers,andSDG&Ehasreachedthetenthstepforresidentialcustomersandtheeighthstepfornon‐residentialcustomers.16
CSI–Multi‐familyAffordableSolarHousingUnderCSI,therearetwolow‐incomeprograms—Multi‐familyAffordableSolarHousing(MASH)andSingle‐familyAffordableSolarHousing(SASH)—thatpromotesolarPVinstallations.TheMASHprogramprovidesrebatestolow‐incomemulti‐familyhousingunitsthatinstallsolarPVsystems.FivepercentoftheCSIbudgetisallocatedtoMASH.ItsframeworkwasadoptedandtheprogramofficiallybeganinOctober2008.Through2011,143projectshavebeeninstalledforatotalof7MW.
CSI–Single‐familyAffordableSolarHousingTheSASHprogramisalsopartoftheCSIandprovidesrebatestolow‐incomesingle‐familyhousingunitsthatinstallsolarPVsystems.FivepercentoftheCSIbudgetisallocatedtoSASH.ItbeganinNovember2007,andisadministeredbythenon‐profitorganizationGRIDAlternativesonbehalfoftheCPUC.(InTable3‐4,theMWinstalledfortheSASHprogramareallocatedtoeachProgramAdministratorbasedontheshareofthetotalnumberofinstallations.)Through2011,1,185projectshavebeeninstalledforatotalof3MW.
15 California Center for Sustainable Energy (CCSE) is the CSI and SGIP program administrator for SDG&E. 16 http://csi‐trigger.com/, accessed September 26, 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐10
CSISummaryTable3‐4summarizesthestatusoftheCSIprogramthroughtheendof2011byprogramandutility.WhiletheMASHandSASHprogramshave10percentoftheoverallprogrambudgetallocatedtothem,theyonlycomprisedabout1percentoftheMWinstalledthroughtheendof2011.
Table 3‐4 Summary of CSI Installations by Program and Utility (All Solar PV)
PROGRAM
PG&E SCE SDG&E* TOTAL
# MW # MW # MW # MW
GeneralMarket 35,194 384 19,305 226 8,452 79 62,951 689
MASH 74 3 38 3 31 2 143 7
SASH 613 2 410 1 162 0.5 1,185 3
CSITotal 35,881 389 19,753 230 8,645 81 64,279 700
Notes:*CaliforniaCenterforSustainableEnergy(CCSE)istheCSIandSGIPprogramadministratorforSDG&E.
Self‐GenerationIncentiveProgramTheSelf‐GenerationIncentiveProgram(SGIP)wasinitiatedin2001toprovidecustomersincentivestoinstalltheirowngenerationandhelpreducepeakelectricitydemandinthestate.ItisoverseenbytheCPUCwitheachutilityadministeringtheSGIPinitsownserviceterritory.Itprovidesrebatestocustomersoffourinvestor‐ownedutilitiesinCalifornia(PG&E,SCE,SCG,andSDG&E)whoinstallDGsystems.Thecurrentlistofeligibletechnologiesincludes:windturbines,fuelcells,gasturbines,microturbines,internalcombustionengines,advancedenergystorage,pressurereductionturbines,andbottomingcycles.Systemsizescannotexceed100percentofthecustomer’speakload,exceptwindturbinesmaybesizedupto200percentofthecustomer’speakload.SolarPVsystemsover30kWwereaneligibletechnologyuntil2007,whentheCSIprogrambegan;PVsystemsunder30kWwerepartoftheERP.Nearly1,500projectshavereceivedrebatesunderSGIPforatotalof406MW.The2011SGIPImpactEvaluationreportnotesthatthereareanumberofSGIPprojectsthathavebeendecommissioned(i.e.theyhavebeenremovedfromoperation),andalsoanumberwhoseoperatingstatusisunknown.Table3‐5belowshowsthetotalrebatedcapacityunderSGIP,buttherearecurrently20MWofdecommissionedsystemsand45MWofsystemswithunknownoperatingstatus.ThedecommissionedsystemsarenotincludedinthepeakdemandimpactanalysisdescribedinSection4.4.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐11
Table 3‐5 Summary of SGIP Installations by Technology and Utility
TECHNOLOGY
PG&E SCE SDG&E* SCG TOTAL
# MW # MW # MW # MW # MW
SolarPV 493 81 232 36 103 13 90 13 918 143
Wind 7 6 3 2 0 0 0 0 10 8
RF** 52 19 20 9 12 7 14 9 98 44
FC 25 10 12 5 7 6 10 6 54 28
MT 14 2 4 1 4 1 0 0 22 4
IC 13 7 4 2 1 1 4 3 22 12
Non‐RF*** 210 79 81 33 44 24 121 75 456 211
FC 65 11 5 1 9 3 16 2 95 17
MT 42 8 27 5 13 1 38 6 120 20
GT 4 5 0 0 3 9 4 16 11 31
IC 99 55 49 27 19 10 63 50 230 142
AES 1 1 0 0 0 0 0 0 1 1
Total 763 185 336 80 159 44 225 97 1,483 406
Notes:*CaliforniaCenterforSustainableEnergy(CCSE)istheCSIandSGIPprogramadministratorforSDG&E.**RFincludesthefollowingfueltypes:biomass,digestergas,andlandfillgas.***Non‐RFincludesthefollowingfueltypes:naturalgas,propanegas,wastegas,andinstallationsforwhichthefueltypeisnotspecified.ThenumberslistedinthistablerepresentallrebatedsystemsunderSGIP,includingdecommissionedsystemsandsystemswhoseoperatingstatusiscurrentlyunknown.FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines;AES=AdvancedEnergyStorage
EmergingRenewablesProgramTheCECadministerstheEmergingRenewablesProgram(ERP),whichprovidesrebatestocustomersofCaliforniautilitiesforinstallingsolarPV,wind,orfuelcellsystemsunder30kW.Itwasestablishedin1998tostimulatemarketdemandfordistributedgenerationtechnologies,andwastheprimaryincentiveprogramforthesetechnologiesuntilthebeginningoftheSGIP.AftertheCSIprogrambeganin2007,solarPVsystemswerenolongereligiblefortheprogram.TheprogramwasdiscontinuedinlateJune2012inaccordancewithSenateBill1018(Stats.2012,ch.39).Nearly29,000projectshavebeeninstalledunderERPforatotalof128MW.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐12
Table 3‐6 Summary of ERP Installations by Technology and Utility
TECHNOLOGY
PG&E SCE SDG&E OTHER* TOTAL
# MW # MW # MW # MW # MW
SolarPV 17,569 79 6,175 29 4,123 15 174 1 28,041 123
WindTurbines** 246 1 366 3 35 0.1 5 0.1 652 4
FuelCells 0 0 3 0.4 0 0 0 0 3 0.4
Total 17,815 80 6,544 32 4,158 15 179 1 28,696 128
Notes:*Inadditiontothethreelargeinvestor‐ownedelectricutilities,someothersmallutilitiesparticipatedintheERP,andtheseinstallationsareincludedinthe“Other”columns.**Installationscategorizedas“SolarPV&Wind”areincludedinthe“WindTurbines”category.
NewSolarHomesPartnershipTheNewSolarHomesPartnership(NSHP)isadministeredbytheCECandbeganin2007asacomplementaryprogramtotheCSI.ItsfocusistoprovidefinancialincentivesandothersupporttohomebuilderstoencouragethemtointegratesolarPVintohighlyenergy‐efficientnewresidentialhousingbuiltinCalifornia.Theultimategoaloftheprogramis360MWofsolarPVonnewresidentialdevelopmentsby2016.Nearly4,500projectshavebeeninstalledunderNSHPforatotalof14MW.
Table 3‐7 Summary of NSHP Installations by Utility
TECHNOLOGY
PG&E SCE SDG&E TOTAL
# MW # MW # MW # MW
SolarPV 3,126 9 737 2 611 3 4,474 14
SB1POUProgramsSenateBill1,whichtookeffectin2007,requiredallpublicutilitiestoestablishincentiveprogramsforsolarPVsimilartotheCSIprogram.Eachutilityadministersitsownprogram.Theoverallgoalisforpublicutilitiestoinstall700MWby2016.TheCECtracksSB1installationsofeachpublicutility.LosAngelesDepartmentofWater&Power(LADWP)andSacramentoMunicipalUtilityDistrict(SMUD)arethetwolargestpublicutilitiesinCaliforniaandhavethemajorityofPOUcustomerinstallationsinthestate.AllPOUscombinedhaveinstalledover10,000solarPVprojectsforatotalof110MW.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐13
Table 3‐8 Summary of SB 1 POU Installations by Utility
TECHNOLOGY
LADWP SMUD ALLOTHERS TOTAL
# MW # MW # MW # MW
SolarPV 3,027 32 2,952 31 4,381 46 10,360 110
RenewableEnergySelf‐GenerationBillCreditTransferProgramTheRenewableEnergySelf‐GenerationBillCreditTransfer(RES‐BCT)ProgramwascreatedasaresultofAB2466(Laird,2008).ThetariffsapprovedbytheCPUCunderthisprogramallowlocalgovernmentstogenerateelectricityatoneaccountandtransferanyavailableexcessbillcredits(indollars)toanotheraccountownedbythesamelocalgovernment.DGsystemseligibleunderthisprogrammustbelessthan5MW,andthereisastatewideprogramlimitof250MW.Asoftheendof2011,therewerenoknownDGinstallationsparticipatinginthisprogram.
3.2.2 NEM Tariff and Non‐NEM DG Installations
TheNEMtariffwasestablishedbylegislationandisimplementedbytheCPUCforelectriccustomerswhoinstallsolar,wind,biogasorfuelcellsystemsof1MWorless.TobeeligiblefortheNEMtariff,generationmustbesizedtoprimarilyoffseton‐siteelectricalload.UndertheNEMtariff,acustomerisallowedtosendpowertotheutilitywhentheyaregeneratingmorepowerthantheyconsume.Customersreceiveafullretailratecreditforallgenerationexportedtothegridoverthecourseofayear,uptotheamountoftheirannualusage.ThiscreditcanbeusedtooffsetallkWh‐basedchargesexceptminimummonthlychargesorcustomercharges.Ifthecustomer’sexportsoverthecourseofayeararegreaterthanthecustomer’sannualusage,theyarecompensatedfortheexcessattheday‐aheadmarketprice(whichisgenerallylowerthanretailrates).Themajorityofcustomer‐sideDGinstallationstakeadvantageofthistariff(summarizedinTable3‐9),althoughtherearesomewhichdonot(summarizedinTable3‐10),oftenbecausetheydonotanticipateeverexportingpowerbacktothegrid.
EachIOUtracksNEMandnon‐NEMDGinstallationsthroughinterconnectioninformationandreportsthisdatatotheCPUCquarterlythroughthe“DistributedGenerationInterconnectionDataRequests”(DGInterconnectionDataset).Thereareatotalofabout1,580MWofreportedinstallationsinterconnectedtothethreeIOUs,bothNEMandnon‐NEM.TheseinstallationsarenotadditivetotheinstalledcapacityreportedinSection3.2.1.Thedatashowninthetablesbelowarebasedsolelyontheinterconnectiondatasets,andhavenotbeenindependentlyverifiedbyBlack&Veatch.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐14
Table 3‐9 Summary of NEM DG Installations by Technology and Utility
TECHNOLOGY
PG&E SCE SDG&E TOTAL
# MW # MW # MW # MW
SolarPV 59,946 616 27,998 310 13,483 116 101,427 1,042
Wind 149 4 316 5 42 0.1 507 9
FC 79 13 27 5 0 0 106 18
IC 11 94 0 0 0 0 11 94
Multiple/Other* 123 26 65 6 2 0 190 32
Total 60,308 753 28,406 327 13,527 116 102,241 1,196
Notes:*Multiple/otherincludesmultipletechnologiesortechnologiesthatdonotfallintotheDGcategoriescoveredbythecustomer‐sideDGincentiveprogramsabove.FC=FuelCells;IC=InternalCombustionEnginesThistableincludesallNEMinstallations,includingthoseontheStandardNEMtariffandthoseontheNEMW,NEMFC,andNEMBIOtariffs.StandardNEMandNEMWprovidethefullretailrate,whileNEMFCandNEMBIOcoveronlythegenerationportionoftherate.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐15
Table 3‐10 Summary of Non‐NEM DG Installations by Technology and Utility
TECHNOLOGY
PG&E SCE* SDG&E* TOTAL
# MW # MW # MW # MW
SolarPV 249 39 40 15 ‐ ‐ 289 54
Wind 2 2 ‐ ‐ ‐ ‐ 2 2
FC 13 7 ‐ ‐ ‐ ‐ 13 7
MT 44 10 ‐ ‐ ‐ ‐ 44 10
GT 15 89 ‐ ‐ ‐ ‐ 15 89
IC 122 122 ‐ ‐ ‐ ‐ 122 122
Multiple/Other** 19 99 ‐ ‐ ‐ ‐ 19 99
Total 464 368 40 15 ‐ ‐ 504 383
Notes:*SCEandSDG&Edidnotreportanynon‐NEMinstallations(exceptthatSCEreportedasmallnumberofsolarPVsystems),becausetheCPUCdidnotrequirethemtobereported.**Multiple/otherincludesmultipletechnologiesortechnologiesthatdonotfallintotheDGcategoriescoveredbythecustomer‐sideDGincentiveprogramsabove.FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines
3.2.3 Wholesale DG Programs
Inadditiontothecustomer‐sideprogramsdescribedabove,CPUCalsooverseesthreeprimarywholesalerenewableDGprograms,inwhichprojectsareinterconnectedontheutilitysideofthemeter.17TheseprogramsrequiretheIOUsinCaliforniatosignpowerpurchaseagreements(PPA)withlargerDGprojectsbetween1and20MW.Addedtogether,thegoalsofthewholesaleDGprogramsareapproximately3,150MW.Asoftheendof2011,atotalof101MWhavebeeninstalledundertheseprograms.
Feed‐InTariff(AB1969andSB32)Thefeed‐intariff(FIT)programbeganinCaliforniain2006,whenAssemblyBill1969(Yee,2006)waspassedtoauthorizespecialtariffsandstandardcontractsforpublicwaterandwastewaterutilitiestoinstallrenewableenergyprojectsupto1.5MW.ThesetariffsweremadeeffectivebytheCPUCinFebruary2008,andappliedonlytoPG&EandSCE.SenateBill380(Kehoe,2008)createdasingletariffforallutilitycustomersandaddedSDG&E.SenateBill32(Negrete‐McLeod,2009)waspassedin2009andincreasedeligibleprojectsizeto3MW.Allpublicandinvestor‐ownedutilitiesinCaliforniaarerequiredunderSB32todevelopFITprograms.Theoverallstatewidegoalis750MWunderSB32,butthereisnosetdatebywhichutilitiesmustreachthistarget.
17 Qualifying facilities under PURPA (for renewables and gas‐fired generation), efficient combined heat and power under AB 1613, and bioenergy facilities under SB 1122 programs are other programs in which distributed sellers may be interconnected to the utility distribution system, and thus be considered DG. These programs are not included in this report.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐16
Twenty‐oneprojectshavebeencontractedandbroughtonlinethroughAB1969bytheIOUstotaling18MW.ThesearesummarizedinTable3‐11belowbytechnology.TherewerenorecordedinstallationsunderSB32asoftheendof2011.
Table 3‐11 Summary of FIT – AB 1969 Installations by Technology
TECHNOLOGY
PG&E SCE SDG&E TOTAL
# MW # MW # MW # MW
Biogas 3 2 1 1 4 6 8 9
Biomass 1 1 0 0 0 0 1 1
SmallHydro 10 6 0 0 0 0 10 6
SolarPV 0 0 2 2 0 0 2 2
Total 14 8 3 3 4 6 21 18
UtilitySolarPVProgramsIn2009and2010,SCE,PG&EandSDG&EwereauthorizedbytheCPUCtoinitiateSolarPVPrograms(SPVP)toprocuretheoutputfromwholesalesolarPVprojectsthroughtwomechanisms:1)developingtheirownutility‐ownedgeneration(UOG)projects,and2)signingcontractswithindependentpowerproducers(IPP)intheirserviceterritories.Originally,theprogramstotaled1,100MW,butSCEandSDG&EaskedforaportionoftheprogramtobemergedintotheRenewableAuctionMechanismprogram(describedinnextsection).Thecurrentgoalis776MW.Systemsizesvaryacrosstheutilities,butgenerallyrangefrom500kWuptoamaximumof20MW.Thegoalsforeachutilityareasfollows:
PG&Ehasatotalprogramgoalof500MW,splitevenlybetweenUOGandIPPprojects.InDecember2012,PG&EsubmittedarequesttotheCPUCtomove252MWofsolarPVfromthisprogramtotheRAMprogram.
SCEoriginallyhadaprogramgoalof500MW,splitevenlybetweenUOGandIPPprojects.However,SCEsoughtCPUCpermissiontoreducethisto250MW,againsplitevenlybetweenUOGandIPPprojects.SCEsoughtapprovaltomove225MWtotheRAMprogram,whichtheCPUCgranted.18
SDG&Ehadanoriginalprogramgoalof100MWwhichissplitinto26MWofUOGprojectsand74MWofIPPprojects.SimilartoSCE,SDG&Esoughtandreceivedapprovaltomovethe74MWofIPPprojectstotheRAMprogram.19
Table3‐12showsthatasoftheendof2011,83MWhadbeeninstalledtowardthosegoals.20
18 Southern California Edison, “Southern California Edison Company’s (u 338‐e) Third Annual Compliance Report on the Solar
Photovoltaic Program”, July 2, 2012, available at: http://www3.sce.com/sscc/law/dis/dbattach4e.nsf/0/3D14CD4ADEC4C8A488257A2F0080B23D/$FILE/A0803015_R1105005+‐+SCE+3rd+Annual+SPVP+Compliance+Report_Public.pdf 19 CPUC, “RPS Quarterly Report – 1st and 2nd Quarter 2012”, available at: http://www.cpuc.ca.gov/NR/rdonlyres/2060A18B‐CB42‐4B4B‐A426‐E3BDC01BDCA2/0/2012_Q1Q2_RPSReport.pdf
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Distributed Generation Overview 3‐17
Table 3‐12 Summary of IOU Solar PV Program Installations by Ownership
OWNERSHIP
PG&E SCE SDG&E TOTAL
# MW # MW # MW # MW
Utility‐owned 4 52 7 12 0 0 11 64
IndependentPowerProducer 0 0 8 19 0 0 8 19
Total 4 52 15 31 0 0 19 83
RenewableAuctionMechanismTheRenewableAuctionMechanism(RAM)programbeganin2011whentheCPUCapproveditasasimplifiedprocurementmechanismforwholesalerenewableDGprojects.TheCPUCinitiallyauthorizedtheIOUstoprocure1,000MW,whichwasthenexpandedto1,299MWbyCPUCdecisionsD.12‐02‐035andD.12‐02‐002.Projectsbetween3and20MWmustmeetcertaineligibilitycriteria,andmustsignapre‐approvedstandardPPA.Auctionsareheldtwiceperyear,withthefirstauctioninNovember2011.ContractsfromthisfirstauctionwereapprovedbytheCPUCinApril2012,sotherewerenooperationalprojectsasoftheendof2011.Additionalauctionsareplannedin2012andbeyond.
20 The totals are based on the CPUC RPS Contract database. However, at least in the case of SCE, they do not appear to exactly match the numbers in the compliance filing referenced above.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐1
4.0 DG Impacts on the Transmission and Distribution System Asdiscussedinthissection,DGmayhavepositiveandnegativeimpactsonthetransmissionanddistributionsystem.BecauseofthedirectconnectionofDGtothedistributionsystem,impactsareexpectedtobemostprevalentatthedistributionlevel.However,asthepenetrationofDGincreases,theimpactswillbegintobeobservedonthetransmissionsystem.
ManyoftheimpactsofDGareattributabletothefactthatthegridwasnotoriginallydesignedtoacceptgenerationonthedistributionsystem.Traditionally,centralizedgenerationwasconnectedtothetransmissionsystem,whichsuppliedthedistributionsystem,whichinturnfedthemajorityofloads.Thisdesignisdepictedinthefigurebelow,illustratingtheflowofelectricpowerfromgeneration,throughtransmission,throughthedistributionsystem,andontocustomerloads.Thedistributionsystemisgenerallydefinedastheportionofthegridwithavoltageof40kVorless.21Thetransmissionsystemisgenerallytheportionofthegridthatoperatesabove40kV.
Figure 4‐1 Typical Electric Power System Single‐Line Diagram22
Thefollowingtopicsarecoveredinthissection:
Section4.1–ImpactsofDGonthedistributionsystem 21 Distribution voltage definition per the Institute of Electrical and Electronics Engineers (IEEE) Standard 141 is a nominal voltage of 40 kV or less. Often, voltage levels between 40 kV and 138 kV are considered to be “subtransmission;” however, this report discusses both subtransmission and transmission as transmission. Each utility in California operates its own distribution system of varying voltage levels. 22 J. Keller and B. Kroposki, “Understanding Fault Characteristics of Inverter‐Based Distributed Energy Resources,” National Renewable Energy Laboratory, Golden, CO, January 2010, p. 31.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐2
Section4.2–ImpactsofDGonthetransmissionsystem
Section4.3–EffectsofaDGsystem’ssizeandlocationonitsgridimpacts
Section4.4–ImpactthatDGhasontheCAISOpeakdemand
Whileanumberofimpactsaredescribedinthissection,itisimportanttonotefewhavebeenwidelyobserved.Iftheyhavebeenobserved,itisdifficulttoconclusivelyattributethemtocustomer‐sideDGsystems.Theimpactsdescribedherehavebeenidentifiedthroughmodeling,research,orlimitedreal‐worldobservations.Thelackofobservedimpactscanbeattributedtoseveralreasons:
Currentlyabout90percentofconnectedDGcapacityisonthecustomer‐sideofthemeter
Customer‐sideDGsystemsaretypicallysmall
ThecurrentpenetrationlevelofDGislow
Atthegivenpenetrationlevels,theinterconnectionprocessandrequirementshavesuccessfullymitigatedimpactsbeforetheyoccur
ThereisagenerallackofmonitoringDGsystemoutput23andoftheeffectsofDGsystemsonthegrid(thatis,utilitiesdonothavetheappropriatetoolstosystematicallycollectandevaluatedataonproblemsorbenefitsattributabletoDG).
Forthesereasons,itisdifficulttoquantifytheimpactsofcustomer‐sideDGonthegrid.ItisexpectedbymanythatimpactswillincreaseasDGpenetrationincreases.However,tobeabletoquantifytheimpacts,theutilitieswillneedtobeginsystematicallymonitoringforthemandthenassociatingthemwithDGsystems.Furthermore,theutilitieshavenotedthatdatacollectionormonitoringalonewillnotnecessarilyleadtoabetterunderstandingoftheimpactsofDGonthegrid.FormalresearchanddevelopmentisrequiredtofacilitatebetterunderstandingofissuesandbenefitscorrelatedtoDG.
QuantificationofDGimpactsisvitallyimportanttotheDGindustry,utilitiesandpolicymakers.ItwillinformdecisionsthatseektofurtherDGgoalswhileminimizingthenegativeimpactsofDGandmaximizingitsbenefits.
4.1 DISTRIBUTION SYSTEM RELIABILITY AND OPERATION ImpactsofDGondistributionsystemreliabilityandoperationaredescribedinthissection.Itisimportanttonote,however,thatimpactsarehighlydependentonthelocalfeederconfigurationandloadinglevel.24Impactsdiscussedinthissectionincludethefollowing:
Distributionsystemlinelosses
Peakdemandreduction
23 As noted above, currently only units 1 MW or larger have telemetering requirements. Smaller units do not have this requirement since at lower penetrations the expectation was that the impacts would be minimal, the cost to collect the data would be relatively high, and processing of this additional data may not be necessary. This assumption should be revisited as penetration increases or the operational requirements for DG change. In that vein, California utilities have recently proposed telemetering requirements for certain wholesale DG smaller than 1 MW where the power will be exported and scheduled into CAISO’s market. As of this writing, the CPUC has not yet evaluated those proposals. 24 Itron, “Final 2007‐2009 Impact Evaluation,” Submitted to: Southern California Edison and California Public Utilities Commission Energy Division, February 2010, p. 4‐30.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐3
Deferreddistributionsystemupgrades
Frequencycontrol25
Voltagecontrol
Reversepowerflow
Operationflexibility
4.1.1 Distribution System Line Losses
DGsystemshavethepotentialtoreducetheamountofenergylostduetotransmittingenergyoverlongdistancesondistributionlines.Typically,energytravelsfromacentralizedgeneratingsourcethroughsubstationstoload.BecauseDGsupplieslocalloads,lessenergyisrequiredtotravelfromcentralizedsources,anddistributionlossesmaybereduced.However,insomecasesDGmayactuallyincreaselosses.Forexample,ifaDGsystemisinjectingmorepowerontothedistributionsystemthanconductorswereoriginallydesignedfor,lossescouldactuallyincrease.
Someresearchershavemodeleddistributionsystemsandfoundtheretobeanoptimalpenetrationleveltominimizelinelossesonasinglefeeder.Forexample,UCIrvineandPG&Eresearcheshavemodeledtwofeedersandfoundtheoptimalpenetrationleveltoreducelinelossesisapproximately60percent.Abovethoselevelslinelossesbegintoincrease.26Asareference,currentpenetrationlevelsinCaliforniaaregenerallybelow10percent.
DuringinterviewswithIOUs,distributionlinelosseswerenotmentionedasanimpactofDG.WhilereductionindistributionlinelossesshouldtheoreticallybeoccurringasDGincreasesandreversepowerflowislimited,theutilitiesarenotsystematicallyquantifyingthisbenefit,orpossiblecost,andassociatingittoDG.Itmaybepossibletomorecloselytrackthismetricasutilitiesgainmoreintelligenceaboutdistributionsystemperformancethroughsmartgridupgrades.
4.1.2 Peak Demand Reduction
TotheextentDGoutputiscorrelatedwithlocalloads,DGmayreducethepeakloadonsomepartsofthedistributionsystem.TheamountofpeakdemandreductionwilldependonthetypeofDGresource,itsoperatingpattern,andtheloadprofileforthefeederorsubstation.Peakdemandreductionisgenerallyviewedasapositiveimpactasitreducestherequiredcapacityandequipmentforthesystem.PeakdemandreductionisexploredfurtherinSection4.4,whichanalyzestheimpactontotalsystempeakaswellassomeselecteddistributionfeeders.
4.1.3 Deferred Distribution System Upgrades
DGcanreducetheutilizationofthedistributionsystemaslessenergyisrequiredtobetransportedoverthesystem(asdescribedabove),andthisisgenerallyviewedasapotentialpositiveimpactofDG.WithinstallationofDG,thenetloadseenbythedistributionsystemmaynothaveincreasedassignificantlyasexpected,orthesystemmightageslowerthanexpectedbecauseitisusedless.Tosomeextent,plannedupgradestothedistributionsystemforcapacityincreasesorreplacementofdevicesbecauseofwearandtearmaybepartiallydelayedordeferredifDGsystemsarelocated 25 It should be noted that the frequency of the distribution system and transmission system is the same, and therefore impacts to frequency on the distribution system similarly affect the transmission system. For simplicity, the frequency control impact is listed and discussed under distribution system impacts here. 26 J. Payne, F. Gu, J. Brouwer, S. Samuelsen, M. Heling, J. Carruthers, D. Pearson, “Evaluation of High Pen PV in Distribution Circuits”, High Penetration Solar Forum 2013, February 2013.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐4
anddesignedappropriately.27However,systemupgradesandmaintenanceareimpactedbyseveralfactorssuchasage,temperatureandweatherconditions,surroundingequipment,andsoon.
Unfortunately,basedoninterviewswithIOUs,theywereunawareofDGsystemsinCaliforniathathaveprovidedthisbenefit.Infact,IOUsindicatedthattheinstallationofsomeDGsystemscanrequireupgradestothedistributionsystem;forinstance,sinceDGincreasesthevoltageatthepointofinterconnection,IOUsmayneedtoperformupgradestopreventvoltagefromexceedingallowablelimits,particularlyifthereisahighlevelofgenerationduringoff‐peakconditions.Further,increasedcyclingofequipment(suchascapacitorbanks)duetointermittentrenewablesmayincreasemaintenancerequirements.
ToachievethisbenefitwouldrequirestrategiclocationofDGonthedistributionsystem.UtilitiesalsodesirethattheDGbeavailableordispatchable,includingpotentiallycontractualobligationstoprovidereliablepower.However,therearenoincentivesforDGsystemownersordevelopers,specificallywholesaleDG,tolocateDGinlocationsthatprovidethemaximumbenefitintheformofdeferreddistributionsystemupgrades.Thismaybeabarriertofurthercost‐effectivedeploymentofDG,asdiscussedinSection5.2.1.
Inaddition,PG&Ehassuggestedthatdistributiondesignstandardsmayneedtobereviewedtoseeifmodificationstosystemdesigncouldincreasethebenefitsofdistributedgeneration,oratleastmitigatetheimpactssuchthathigherpenetrationscouldbeachievedataloweroverallcost.
4.1.4 Frequency Control
TheCPUCRule21andIEEEstandardsprovidefrequencyrequirementsforDGconnectingtothedistributionsystem.TheserequirementsprovidetheupperandlowerlimitsforthefrequencyoftheDGsystem.Whenthefrequencygoesoutsideofthespecifiedrange,theDGsystemswillautomaticallybetrippedoffline.
Energygeneratingtechnologiesthathaveinertia,suchascombustionturbines,providefrequencysupport–meaningtheycanhelpadjustthefrequencyofthegrid.Thiscanbedonebyeitherspeedinguporslowingdowntherotationofthedevices.
ThemostprevalentDGtechnologies,suchassolarPV,donotprovidefrequencysupport.Infact,thesesystemsarerequiredtotripoffline(UL1741)intheeventofanoverorunderfrequencysituation.TheneteffectofDGsystemstrippingofflinecould,inthefuturewhenhigherpenetrationisachieved,exacerbateanunderfrequencysituation;thisisviewedasanegativeimpactofDG.
Whilefrequencyimpactshavebeenseeninmodelsandactualsystemfrequencydata,theIOUsarenotabletoattributetheseimpactstocustomer‐sideDGsystems.TheexpectationisthatasDGpenetrationincreasesutilitieswillbeabletoattributetheseimpacts,ortheexacerbationoftheseimpacts,toparticularsystems.
Changestoinverterstandards(specificallyIEEE1547),suchasallowingawiderrangeofvoltageandfrequencyconditions,couldhelpalleviatechallengeswithinadvertentvoltageandfrequencytrips.SmartinverterscouldalsohelpmitigatethefrequencyimpactofDG.Smartinvertersmaybeabletoprovidefrequencysupport,oravoidtrippingofflineduringsomeunder/overfrequencyevents. 27 U.S. Department of Energy, “The Potential Benefits of Distributed Generation and Rate‐Related Issues that May Impede Their Expansion,” February 2007, p. 3‐11.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐5
4.1.5 Voltage Regulation
Voltageregulationisacorefunctionofutilityoperations,andDGhasthepotentialtomakevoltageregulationsignificantlymoredifficultforutilities.Voltageistypicallycontrolledlocallyatthedistributionlevel.Addinggenerationonafeederthatnormallyservesloadwillincreasethevoltageatthepointofinterconnection.IftheDGissolar,wind,oranysortofvariableDG,therecouldbevoltagefluctuationsonthefeeder.Figure4‐2belowillustratesanintermittentsolarresource.ThevariabilityofsolarPVgenerationcanbequitehigh,particularlyonpartlycloudydays.
Figure 4‐2 Sample Solar Resource Data for One Day28
PassingcloudcoverandotherdisturbancescanaffectDGoutput,whichaffectsgridvoltage,andmayultimatelyimpactsystemoperationtriggeringprotectiondevices.AnNRELreport,ImpactofSolarSmartSubdivisionsonSMUD’sDistributionSystem,indicatedthatatlowPVpenetrationlevels,noadversevoltageregulationeffectswerefound;however,aspenetrationsincrease,aneffectmaybeseen.29ThevoltagefluctuationmayleadtovoltagesoutsideacceptablerangesimposedbytheCPUCRule2(ConservationVoltageRegulation–CVR)andIEEEstandards.Fluctuationinvoltagecancausewearandteartoelectricalequipmentownedbycustomersandutilities,andisviewedasanegativeimpactthatDGsystemscanhaveonthedistributionsystem.
Atcurrentpenetrationlevels,widespreadvoltageissueshavenotbeenobserved,buttheyareexpectedtooccurmoreoftenasmoreDGsystemsareinstalled.Basedoninterviewswithdistributionengineers,theIOUshaveobservedsomeinstancesofvoltageimpacts.SDG&Eindicatedtheyhaveexperiencedadversevoltagefluctuationonafeederhostingtwo1‐MWNEMsolarPVinstallations.OnaSCEfeeder,a400kWPVsystematfulloutputincreasedvoltageenoughtotriptheinverteroff;becauseofthis,SCEinstalledanewtransformerandchangedthetapsettingtohandlethevoltagefluctuationsatitsowncost.
28 M. Patsalides, A. Stavrou, G. Makrides, V. Efthimiou and G. E. Georghiou, “Harmonic Response of Distributed Grid Connected Photovoltaic Systems,” University of Cyprus, Nicosia, p. 3. 29 P. McNutt, J. Hambrick, M. Keesee, and D. Brown, “Impact of SolarSmart Subdivision on SMUD’s Distribution System,” National Renewable Energy Laboratory, Golden, CO, July 2009, p. 33.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐6
SCEindicatedthattheyhaveobservedinstallationsexperiencingovervoltagesexceedingpermittedvoltagelevelsbyupto200percent.Theseovervoltagecasesarecausedbyaneffectreferredtoas“transientovervoltage.”ForDGsystems,thiseffectistemporaryandoccurswhenaPVDGsysteminverterdisconnectsduringlowloadconditions.Asaresultoftransientovervoltages,thePVsystem’sisolationswitchmayfailifnotsizedappropriately,andcustomerloadmaybeexposedtoovervoltages.SCEisworkingwithinvertermanufacturerstomitigatethisissueandestablishproperdesignprotocolsforDGPVsystems.
Similartofrequencycontrol,aDGsystemisrequiredtotripofflineduringanunder‐orovervoltageevent,perUL1741inverterrequirements.Losinggenerationcausesadecreaseinvoltage;thereforethetrippingofflineofDGsystemscanexacerbateanundervoltagesituation.
Somemitigationapproacheshavebeendevelopedorimplemented,forexampleloadtapchangersontransformershavebeenusedtomitigatevoltageissues.AllowinginverterstoprovideVArsupportorinstallingVArcontrollersisatechnicallyviableoption.However,thismaynotbepracticalforcustomer‐sideDGsystemsgiventheirsmallsizeanddistributedlocations,andthefactthatutilitiesdonotcurrentlyhavecontrolovercustomer‐ownedequipment.Changinginverterstandardstonotrequiredisconnectionduringtemporarylowvoltageeventsisamitigationapproachreferredtoaslow‐voltageride‐through(LVRT).In2008,GermanyrequiredLVRTonthedistributionsystem.30SDG&Eindicatedthatseveralvoltagemitigationapproachesaretechnicallyavailable,butthereislimitedresearchavailabletoindicatethebestapproach.InSection7.0,anapproachisdiscussedforastudytoexaminebestpracticesforaddressingthevariousvoltageandfrequencyimpactsofDGonthedistributionsystem.
4.1.6 Reverse Power Flow
AsDGpenetrationincreases,thelikelihoodofgenerationflowingbackontothedistributiongridincreases.Thisisoftenreferredtoas"reversepowerflow."ReversepowerflowcanpotentiallynegativelyimpactthecoordinationofDGinstallationswithexistingdistributionfeederautomatedprotectionfeaturesandotherequipment.
Distributionsystemsarenotgenerallydesignedtoaccommodatetheinterconnectionofwidespreadparallelgeneration.Rather,theyaredesignedtodistributepowerproducedfromcentralizedgenerationconnectedtothetransmissionsystem.Existingdistributionsystemsaregenerallydesignedtoaccommodatepowerflowoutofthedistributionsystemandmayhaveissueswithexcessivepowerflowingintothesystem.Examplesofissuesthatmightoccurinthissituationinclude:
Sometypesofequipment,suchasloadtapchangersthatregulatevoltage,maynotfunctioncorrectlyifelectricityisflowingoppositetheiroriginaldesign.
PVsystemsmaynotdetectfaultswithlowshortcircuitcurrentonthedistributionsystemandthereforemayremainconnectedtothedistributionsystem.ThismayinterferewiththedistributionsystemoperationasthePVsystemmaybefeedingthefaultandtherestofthedistributionsystemmaynotdetectthefaultasitotherwisewouldwithouttheDGPVsystem.
Networkdistributionsystems,whicharetypicallyusedinurbanareas,generallycannothandlesignificantpowerflowsintothesystem.Thisisbecausethereisadevicespecifically
30 J. Keller and B. Kroposki, “Understanding Fault Characteristics of Inverter‐Based Distributed Energy Resources,” National Renewable Energy Laboratory, Golden, CO, January 2010, p. 31.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐7
usedfornetworksystemsthatinhibitspowerflowintothesystemforsystemprotectionreasons.31ThislimitsthesizeandamountofPVthatcanbeinstalledonthesystem.
OnespecificexampleofpotentialreversepowerflowimpactscomesfromlargerPVsystems(>20kW)thathaveasingle‐phaseoutputbecausetheyareinstalledonasingle‐phaseserviceatamulti‐familyhousingcomplex—thisoccasionallyhappenswithsystemsinstalledundertheMASHprogram.Becauseoftheirsize,systemsover20kWusuallyhaveathree‐phaseoutput.Butinsituationswhereasingle‐phaseoutputisrequiredbecauseofthelocation,thelargeamountofpowerthatmaybeexportedtoonlyoneofthethreephasesonthedistributionnetworkcouldcreateasignificantphaseimbalance.Distributionoperationscouldbenegativelyimpactedifthisweretooccur.
Theneteffectofreversepowerflowispossiblenegativeinteractionwiththedistributionsystem’sprotectionschemes,causingpartsofthesystemtogooffline.Thelevelatwhichreversepowerflowbecomesproblematicforutilitiesisnoteasilydeterminedwithasimplepercentageofcapacitypenetration;manyfactorsmustbetakenintoaccountsuchasmagnitudeofreversepowerflow,capacityoffeeder,relayandrecloser32settings,andlengthoffeeder.Tomitigatetheseissues,utilitiesmayreconfigureorredesigntheirprotectionschemes.Utilitieshaveindicatedthatthishasbeendoneonacasebycasebasistodate.
4.1.7 Operational Flexibility
AsDGpenetrationincreases,thecomplexityofthedistributionsystemincreasesandutilitiesmayhavelessflexibilitytooperatetheirsystem,potentiallynegativelyimpactingthesystem.Thedistributionsystemanditsassociatedprotectionschemes(protectiondevicesandthecoordinationbetweenthem)weredesignedtodistributeorsupplypowertoloads.Withgenerationsourcesspreadacrossthesystem,certainprotectionschemeswillhavetochange.DGbringsadditionalcomplexitytotheoperationandtroubleshootingofthedistributionsystemformanyreasons,includingthefactthattheinterconnectionpointmayactasagenerationsourceoraload.Furthermore,whenproblemsoccuronthedistributionsystem,itmaybemoredifficulttotroubleshootthem.Forthesereasons,itislikelythatutilitieswillhavelessflexibilitywiththeirsystem.Forexample,manydistributionsystemsareradialinnature,whichmeansthereisalonglinerunningfromthesource,andnoloopsorredundancy.IfaDGsystemcausesanissuewiththedistributionsystemsomewherealongthisline,requiringaportionofthelinetobeisolated,thentheutilitymayhavetodisconnecttheDGsystemandanythingbeyonditfromthemainsource.Thislimitonoperationalflexibilitymayreducethereliabilityofthedistributionsysteminsomecases.
4.2 TRANSMISSION SYSTEM RELIABILITY AND OPERATION Transmissionsystemimpactsfromcustomer‐sideDGinstallationsinstalledtodate,particularlythoseinurbanareaswithhigherload,arecharacterizedasminimalinthestudiesconductedbytheCPUCconsultantsandothers.AliteraturesurveyofthetopicrevealsthattheconclusionmostoftenadvancedisthattheissueshavenotbeenexperiencedattheselowlevelsofDGpenetration,butasthepenetrationlevelsgrow,issuesareexpectedtoappear.Theissuesdiscussedinthefollowingparagraphsareonesthatarelargelyanticipated,buthavegenerallynotbeenobservedontheIOUssystemsatthetimeofthisreport.Anticipatedissuesthatwilllikelyneedtobeaddressedastheyariseinclude:
31 M. Coddington, B. Kroposki, T. Basso, K. Lynn, M. Vaziri, T. Yohn, “Photovoltaic Systems Interconnected onto Secondary Network Distribution Systems – Success Stories,” National Renewable Energy Laboratory, Golden, CO, April 2009, p. 8. 32 Relays and reclosers are system protection devices used in distribution and transmission systems.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐8
Transmissionsystemlinelosses
Reverseflowfromthedistributionsystemtothetransmissionsystem
Existingoperationalprocedures
Voltageregulation
Reliablecapacityandplanning
Capacitymargin
Systemstability
4.2.1 Transmission System Line Losses
Aswiththedistributionsystem,DGthatserveslocalloadswilloffsettheneedtoimportpowerthroughthetransmissionsystematthetimethattheDGsystemisproducingenergy.Thisshouldreducetransmissionlinelossesduringthosetimes,andisgenerallyviewedasapositiveimpactofDG.Atthepresenttime,theutilitiesandtheCAISOarenotroutinelyquantifyingthisbenefitandassociatingitwithDG.
4.2.2 Reverse Power Flows from the Distribution System
Reversepowerflows,asmentionedinthedistributionsystemsectionabove,canhavenegativeimpacts.ReversepowerflowscausedbyincreasedDGwouldlikelyoccurwhenDGoutputexceedsloadandtheexcessenergyflowsthroughthedistributionsystemtothetransmissionsystem.Thisisnotawidespreadissuetoday,butIOUengineersanticipatethatatsomelevelofDGpenetration,itmaybecomeaproblem.Whilethisreportspecificallyexaminespeakloadimpacts,theIOUengineersindicatedthattheywilllikelyseereverseflowissuesduringoff‐peakconditionswhentheirloadsareafractionoftheirpeakload,causingexcessenergyfromDGprojectstoflowbackontothesystem.Ifthisweretooccur,itwouldalsoimpacttransmissionoperationsproceduresandtheabilitytobalancesystemloadwithresources.Theimpactsofreversepowerflowonthetransmissionsystemaredifferentthanthedistributionsystem,partiallyduetothedifferentapproachestooperationofthedifferentsystems.Theliteraturesurveyedforthisreportdidnotrevealanyspecificstudiesthathavebeenconductedonthisissue.AnalysesconductedonDGimpactsonthetransmissionsystemhavefoundthatthelowlevelofDGpenetrationlimitsanyconclusionsthatcanbedrawnatthistime.33
4.2.3 Operational Procedures
MuchinthesamewaythatdistributionsystemoperatorswillhavetoadaptasDGpenetrationlevelsgrow,transmissionsystemoperatorswillalsoneedtoadapt,especiallyifactualenergyoutputdifferssignificantlyfromtheforecastedoutput.GridoperationmaybenegativelyimpactedbyboththevariabilityandtheuncertaintyofvariableDGresources.34Instancesofover‐generationhaverecentlyoccurredwithwindgeneration.Similarover‐generationwithsolarDGismostlikelytooccurinthemorningwhileloadsarelow,butshouldacloudpass,generationcandecreaseveryquickly.35SCADAhasbeenseenastooexpensivetoinstallformonitoringoutputfromsmallerDG
33 Itron, “Impacts of Existing Distributed Generation – Final report,” Prepared for CPUC Energy Division Staff, Davis, CA, January 2010. Pages 5‐8; 5‐13. 34 NREL, “Impact of High Solar Penetration in the Western Interconnection,” A Technical Report Prepared by NREL and GE Energy, Golden, CO, December 2010. Page 6. 35 California ISO, “Integration of Renewables Resources: Operational Requirements and Generation Fleet Capability at 20% RPS,” August 31, 2010. Pages 12‐18.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐9
installations,sotheoutputistypicallynettedwithitsnativeload.Asaresult,minute‐by‐minutechangesinDGoutputcanappearasunexpectedincreasesordecreasesinload.Transmissionoperatorsmonitorsystemstatusaroundtheclock,andhaveproceduresformanagingspecificscenarios.ThesewouldneedtobeexpandedtoincludehowtomanageimbalancescausedbyincreasedDGonthesystemasthiswouldbeanewphenomenon.
4.2.4 Voltage Regulation
Voltageregulationissues,asmentionedabove,canhavenegativeimpactsonthesystem.VoltageregulationissuesonthetransmissionsystemasaresultofDGsystemadditionshasnotbeenidentifiedspecificallyinanyoftheliteraturereviewedforthisreport.InterviewswithIOUengineershaverevealedthatthisisnotanexistingissueonthetransmissionlevelsubstationbusesrelatedtocustomer‐sideDG,butitisexpectedtobecomeaprobleminthefuture.36TheDGpenetrationpointatwhichtheIOUengineersthinkthisissuewillmanifestonasystem‐widebasisisunknownatthistimeanditisonetheyhaveexpressedtheywouldlikestudiedandunderstood.
4.2.5 Reliable Capacity and Planning
WhileDGtechnologiesthatarenotvariablecanbereliedontoproducetheircapacityasexpected,mostDGinCaliforniaisPVwhichisnotforecastedinareliablewaytoday.Also,becausetransmissionexpansionplanslookattimehorizonsanywherefrom5to20yearsintothefuture,thequestionofwhatcapacitytoassumefortheseplansisstillatopicofdebate.WhiletechnicalanalyseshavefoundthatPVresourcescontributeupto30percentcapacityvalues,theISOusesacalculationthataveragespeakcapacitiesandusesthosevaluesasreliablecapacityinplanningstudies.37Resourceadequacy,theprocurementofsufficientflexibledemandorgenerationcapacitytomeetfutureloads,iscriticaltoloadservingentities.38Transmissionplannersaretaskedwithstudyingthebulkelectricsystemandidentifyingmitigationprojectsforanyissuesthatwillimpactreliableservicetoutilitycustomersunderpeakloadconditions.TheobligationtoserveacustomerremainswhetherornotthecustomerhasaPVsysteminstallation.Therefore,transmissionplannersassignavalueofzerototheseresourcestobeconfidentthattheyhaveadequateresourcesunderthecriticalpeakloadperiod.39AhigherconfidenceinPVforecasting,forinstance,wouldleadtomorecreditbeingattributedtoPVsystemsasreliablecapacity,apotentialpositiveimpactofDG.Also,athigherpenetrations,geographicdispersionwillprovidehighercapacityassurance.Inotherwords,manysmallsystemsoperatinginadispersedgridwillnotlikelyhavenegativeimpactsasgreataslarger,lessdispersedsystems.
Thereareongoingregulatoryactivitieswhichshouldprovidebettercertaintytothetreatmentofsolarorwindresourcesasdependableresourcesinthefuture.Inparticular,thereareproceedingsunderwayattheCPUCtoconsiderincorporatingflexiblecapacityinthe2014ResourceAdequacyprogram.ThatwouldincludepreparationandreviewofnewstudiesoftheeffectiveloadcarryingcapacityofwindandsolarresourcesinCalifornia.40
36 SCE indicated that larger wholesale DG systems do cause voltage regulation issues today. 37 NREL, “How Do High Levels of Wind and Solar Impact the Grid? The Western Wind and Solar Integration Study,” Technical Report, Golden, CO, December 2010. Page 10. 38 LBNL, “Mass Market Demand Response and Variable Generation Integration Issues: A Scoping Study,” Environmental Energy Technologies Division, Berkeley, CA, October 2011. Page 56. 39 IOU engineers interviewed for this report expressed that the obligation to serve customers is paramount. 40 CPUC Rulemaking 11‐10‐023, Filed October 20, 2011. Available online http://docs.cpuc.ca.gov/PublishedDocs/Efile/G000/M031/K723/31723210.PDF , Accessed December 13, 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐10
4.2.6 Transmission Capacity Margin
Capacitymarginistheunusedcapacityontransmissionlinesbasedontheirratedcapacities.Typically,thiswasduetoload;however,asDGpenetrationincreasesonthesystem,theseadditionscouldpotentiallypositivelyaffectthemargins.ResearchandstudiesconductedontransmissionlineloadingandhowDGaffectsitduringpeakloadconditionshasgenerallyconcludedthattheeffectsareminimal.ThereasonisthatthesystempeakoccurslateintheafternoonatthetimewhenPVoutput,forexample,issharplydeclining.Theresultingeffecthasresembledloadshaving,butnotpeakloadshaving‐‐whichutilitiesgreatlyvalueforreducingtheneedlepeakinload.InterviewswithIOUengineershaverevealedthatratherthanareductioninflowsonlines,theyhaveseenanincreaseinflowswhenDGhasbeeninstalledwhereloadsareminimalornotpresent.Technicalanalysesconductedontransmissioncapacitiesshowedthatimpactsareminimaltoday,andnoconclusionscanbedrawnduetopresentlylowlevelsofDGpenetration.41
4.2.7 System Stability
Systemstabilityistheabilityofthebulkelectricsystemtostayintactbystayingsynchronizedandregainingequilibriumfollowingacontingencyonthesystem.Thisisespeciallyimportantinthefirstfewcyclesandsecondswhenautomaticgenerationcontrol(AGC)respondstothelossofgenerationortransmission.Astheproportionofvariablegenerationwithlimitedsystemresponsecapabilitiesincreasescomparedtolargeconventionalspinninggeneration,itislikelythatsystemstabilitymaybedecreased.InterviewswithIOUengineersidentifiedtheneedtoconductstudiestodeterminethelevelofpenetrationthatmayadverselyimpactsuchissuesassystemstability.
4.3 SIZE AND LOCATION DEPENDENT IMPACT OF DG Inadditiontoalloftheissuesmentionedabove,thesizeandgeographiclocationofaDGsystemareimportantfactorsthatmayaffectitsimpactonthetransmissionanddistributiongrid.Eachoftheseissuesisdiscussedseparatelybelow.
4.3.1 Size Impacts
ThesizeofaparticularDGsystem,relativetothedistributioncircuittowhichitisinterconnected,affectsgridoperationsforanumberofreasons.Allelsebeingequal,asmallersystemhasasmallerriskofhavingnegativeimpactsandcausinggridinstabilitythroughvoltageandfrequencyfluctuations,faults,trippingprotectionschemes,overloadingcircuitsorback‐feedingontothetransmissionsystem.FordistributedsolarPVandwindsystems,thevariabilityoftheiroutputcanbemorechallengingiftheyarelargerandareservingasignificantportionoftheloadonaspecificcircuit;inthatcase,asuddendroporincreaseinoutputwillhaveaproportionallylargerimpactongridoperationthanasimilarsystemofasmallersize.
However,itisimportanttonotethattheseimpactsalsovarybasedonthedistributioncircuit.DistributionengineersfromtheIOUsindicatedthatsomecircuitsmayhavethenecessarycharacteristicsandcapacitytoeasilyaccommodateasinglelargeDGsystem,whileothercircuitsmaybeunabletohandlemorethanasmallamountofDG.Also,theynotedthatthelocationoftheDGsystemalongtheradialdistributioncircuit—i.e.,whetheritisnearthesubstationorattheendoftheline—maybethemostimportantfactor,incombinationwiththeamountofloadintheimmediatevicinity.Overall,theseengineersagreedthatalargernumberofsmallDGsystemswouldhavelessofanegativeimpactongridoperationsthanasmallernumberoflargeDGsystems—with 41 Itron, “Impacts of Existing Distributed Generation – Final report,” Prepared for CPUC Energy Division Staff, Davis, CA, January 2010. Pages 5‐15.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐11
thecaveatthatthereareexceptionsandeachcircuithasspecificcharacteristicsaffectingitsabilitytoaccommodateDG.
4.3.2 Location Impacts
ItiswellknownthatthegeographiclocationsofDGsystemsaffectgridoperations,andtherearetwomainreasonsforthis.First,clusteringofDGsystemsmayposechallengesbecausethosesystemswilltendtoresembleasinglelargeDGsystem,withtheattendantissuesdiscussedabove.Thoughthisisapotentialconcern,programmanagersforthecustomer‐sideDGincentiveprogramsateachIOUnotedthatclusteringisnotcurrentlyhappeningwithcustomer‐sidesystemstotheextentthatpresentsachallengeforgridoperations.Furthermore,theIOUshavealsoprovidedinterconnectionmapswhichdirectdevelopersofwholesaleDGinstallationstoareaswheregridimpactsmaybesmallerduetogreatersystemcapacityandlessexistingDG.
Second,geographicdisbursementofvariableDGresourceslikesolarPVandwindreducestheirshort‐termvariabilitywhenviewedcollectively.Thiseffectiswell‐documented,andtheimpactofgeographicdiversityonsolaroutputvariabilityisdiscussedinarecentstudybyLawrenceBerkeleyNationalLaboratory,aswellasarecentpaperbyCleanPowerResearch.42,43Asshownbelow,theoutputfromagroupof25PVsitesspacedoverawidegeographicareaisconsiderablylessvariablethantheoutputfromasinglesite.
Figure 4‐3 Solar Irradiance Variability – One Location vs. 25 Locations44
LookingatbothsizeandlocationimpactsofDG,theliteraturereviewandinterviewswithutilitypersonnelindicatethatalargenumberofsmallDGsystemsspreadoveralargegeographicareawouldgenerallyhavelessofanegativeimpactongridoperationsthanasmallnumberoflargeDG
42 A. Mills and R. Wiser, “Implications of Wide‐Area Geographic Diversity for Short‐Term Variability of Solar Power,” Lawrence Berkeley National Laboratory, Berkeley, CA, Sept. 2010. 43 T. Hoff and R. Perez, “Modeling PV Fleet Output Variability,” Submitted to: Solar Energy, 2010. 44 T. Hoff, “Advanced Modeling and Verification for High Penetration PV,” DOE High Penetration Solar Forum, San Diego, CA, March 2011.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐12
systemslocatedincloseproximitytoeachother.ThisistrueforanytypeofDGtechnology,butisespeciallytrueforvariableresourceslikesolarandwind.Whiletheseprinciplesmayholdtrue,asdiscussedintheBarrierssection(Section5),therearecurrentlynoincentivestositeDGinamannertominimizenegativeimpactsonthegrid.
4.4 PEAK DEMAND IMPACT ANALYSIS ThissectiondescribestheimpactofinstalledDGcapacityonthepeakelectricdemandoftheCaliforniaIndependentSystemOperator(CAISO)systemin2011.
Peakdemandreferstothetimeofdayandwhenelectricloadonthegridisgreatest,usuallymeasuredonadailyorannualbasis.In2011,theannualpeakdemandontheCAISOgrid,whichservestheterritoriesofPG&E,SCE,andSDG&E,was45,569MWandoccurredat4:30pmonSeptember7th.SincethisstudyanalyzesCAISOloadandDGgenerationonanhourlybasis,the“peakhour”intermsofCAISOdemandwasbetween4and5pmonSeptember7th,2011.
Inestimatingtheimpactofthetotalamountofcustomer‐sideDGcapacityoperatingontheCAISOgridduring2011peakdemandperiod,twoseparateapproachesweretakenforsolarPVandnon‐solarinstallations.TodeterminetheimpactofsolarPVcapacityduringthesystempeakdemand,Black&VeatchdevelopedamethodologythatutilizedactualmetereddatafromalargesamplingofsolarPVsystems.ThisanalysiswasundertakeninplaceofaCSIImpactEvaluationfor2011,inwhichpeakdemandimpacthasbeenreportedinpreviousyears.ThedetailsofthemethodologyanddatasourcesusedaredescribedinAppendixB.
Black&VeatchreliedondatafrommultiplesourcestodeterminethetotalamountofDGcapacityoperatingduringthe2011peakhour.
ForsolarPV,actualproductiondataforalargesetofoperatingPVsystemswasused.TheCPUCcollects15‐minuteintervalproductiondatafrommetersonhundredsofsolarPVsystemsinstalledundertheCSI(bothEPBBandPBI)andSGIPprograms.TheproductiondatawasusedtorepresenttheproductionprofileofallPVinstallationsintheIOUterritoriesforcalculatingthepeakdemandimpactofsolar.TheanalysisdidnotincludetheinstallationsfromthePOUSB‐1programs.Foradetaileddescriptionofthemethodologyemployed,refertoAppendixB.
Fornon‐solartechnologies,Black&Veatchusedthe“CPUCSelf‐GenerationIncentiveProgramEleventh‐YearImpactEvaluation”preparedbyItroninJune2012.Thestudyreportedthepeakdemandcapacityfactorsfornon‐solarSGIPgenerationincludingfuelcells,microturbines,gasturbines,andinternalcombustionengines(separatedbyrenewableandnon‐renewablefuels).ThesecapacityfactorswerethebasisforcalculatingtheamountofgenerationfromthesetechnologiesduringtheCAISOpeakdemandin2011.Nopeakhourcapacityfactorswereprovidedinthereportforwindturbinesoradvancedenergystoragesystems,sincemetereddatawasnotavailableforthesetechnologies.
TheoverallcontributionofDGinstallationsforthepeakdemandday,bothsolarPVandnon‐solar,ispresentedinFigure4‐4andFigure4‐5intermsoftotalMWoperatingineachhour.ThesefiguresdisplaysimilarinformationwiththedifferencebetweenthembeingthatFigure4‐5showsthedisaggregatedimpactofeachprogramonaseparatescalethantheCAISOload.Figure4‐6showsthehourlycapacityfactorforallDGonthepeakdemandday.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐13
Figure 4‐4 Impact of Customer‐Side DG on CAISO Demand on September 7th, 2011
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000Load
(MW)
12 am 1 2 3 4 5 6 7 8 9 10 11 12pm 1 2 3 4 5 6 7 8 9 10 11 12am
CAISO Load
Impact of Customer‐Side DG
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐14
Figure 4‐5 Operating DG Capacity by Program and CAISO Demand on September 7th, 2011
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
0
100
200
300
400
500
600
700
800
900
1,000
CAISO Load
(MW)
DG Operating (M
W)
CSI
SGIP ‐ Solar PV
SGIP ‐ Non‐Solar
ERP/NSHP
All DG
CAISO Load
Peak DG Output: 728 MW
12 am 1 2 3 4 5 6 7 8 9 10 11 12pm 1 2 3 4 5 6 7 8 9 10 11 12am
CAISOPeak Load: 45,569 MW
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐15
Figure 4‐6 Hourly DG Capacity Factors by Program and CAISO Demand on September 7th, 2011
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
12‐1 1‐2 2‐3 3‐4 4‐5 5‐6 AM
6‐7 7‐8 8‐9 9‐10 10‐11 11‐12 12‐1 1‐2 2‐3 3‐4 4‐5 5‐6 PM
6‐7 7‐8 8‐9 9‐10 10‐11 11‐12
CAISO Load
(MW)
DG Capacity Factor
CSI
SGIP ‐ Solar PV
SGIP ‐ Non‐Solar
ERP/NSHP
All DG
CAISO Load
CAISOPeak Load: 45,569 MW
Peak DG Capacity Factor: 0.63
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐16
Overall,thepeakdayprofileofsolarPVshowsthatsolarPVhasasmallbutsignificantimpactontheCAISOgridatmid‐dayandalesssignificantimpactduringtheactualpeakdemandperiod.Thenon‐PVtechnologieshavearelativelyconstantgenerationprofileandthereforeamoreconsistent—thoughsmaller—impactonCAISOdemandthroughouttheday.
ThetotalpeakdemandimpactofinstalledDGontheCAISOgridduringthe2011peakdemandperiod(4to5pmonSeptember7th)was335MWandwasapproximately0.7percentofCAISOload.TotalinstalledDGcapacityontheCAISOgridonthisdatewas1,136MW,ofwhich892MWwassolarPV.ThedetailedresultsareshowninTable4‐1below,brokendownbytechnology.
Table 4‐1 Peak Demand Impact by Technology
TECHNOLOGY MWINSTALLEDPEAKHOURCAPACITY
FACTORPEAKDEMANDIMPACT
(MW)
SolarPV 892 0.25 227
Wind* 12 0.00 0
RF
FC 23 0.84 19
MT 4 0.08 0
GT 0 0.00 0
IC 12 0.49 6
Non‐RF
FC 17 0.54 9
MT 17 0.39 7
GT 31 0.83 26
IC 128 0.32 41
AES* 2 0.00 0
Total 1,136 0.29 335
*NoproductiondatawereavailableforWindandAESinstallations,sotheywereassignedacapacityfactorofzero,i.e.theywereassumedtohavenoimpactonpeakdemand.SeeAppendixBfordetails.RF=RenewableFuels;Non‐RF=Non‐RenewableFuels;FC=FuelCells;MT=Microturbines;GT=GasTurbines;IC=InternalCombustionEngines;AES=AdvancedEnergyStorage
Basedontheseresults,Black&VeatchfoundthatdistributedsolarPVcontributesabout25percentoftotalinstalledcapacityduringthe2011CAISOpeakdemandperiod.SolarPVgenerationtendstopeakaroundmid‐day,whileCAISOdemandtendstopeakmidtolateafternoonwhensolarPVoutputisdeclining,asisclearinFigure4‐5andFigure4‐6above.Thus,thehighestPVdemandimpactwasbetween12pmand1pm,whendistributedPV(plusotherDG)provided728MWofcapacityandaccountedfor1.8percentofCAISOload.ThesolarPVcontributionatthetimeof
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐17
CAISOpeakdemandisaboutaquarteroftheinstalledcapacityratingofPV;allDGaccountsfor0.7percentofCAISOpeakloadfrom4pmto5pm.
AccordingtoBlack&Veatchestimates,DGsolarPVachievesanhourlycapacityfactorof0.25duringtheCAISOpeakdemandhour(4‐5pmonSeptember7th)in2011.The2010Reportestimatedanhourlycapacityfactorof0.65forallDGsolarPVoperatingduringtheCAISOpeakdemandhour(3‐4pmonJune20th)in2008,andthe2010CSIImpactEvaluationreportestimatedanhourlycapacityfactorof0.56forallDGsolarPVoperatingduringtheCAISOpeakdemandhour(3‐4pmonAugust25th)in2010.Theestimatefor2011issignificantlylowerduetoanumberoffactors.First,theCAISOpeakdemandcamelaterinthedayin2011thanin2010and2008—4to5pminsteadof3to4pm—whenPVsystemsareproducinglessenergybecauseitisclosertosunset.Also,theCAISOpeakdemandoccurredlaterintheyearin2011thanin2010and2008,whichagainmeansthatPVsystemsareproducinglessenergy;thesunisclosertosettingat4pminSeptemberthanitisat4pminJune.Finally,itispossiblethatthepeakdemandhourin2011mayhavebeencloudierthanthepeakdemandhourin2010and2008.AllofthesefactorsresultinalowersolarPVcapacityfactorthaninpreviousyears.
Black&VeatchacknowledgesthattherearelimitationstoonlyestimatingtheimpactofDGonCAISOpeakdemand.CAISOandeachIOUhavetoplanforpeakdemandatavarietyoflevels(customertransformer,distributionfeeder,distributionsubstation,subtransmissionnetwork,transmissionsubstation,transmissionline,theutilitysystem,andtheentireCAISOsystem)andthisreportdoesnotattempttomodeltheimpactofDGateverylevel—althoughthatmaybeausefulexercise.Rather,thisreportseekstoshowthemagnitudeofDGoutputrelativetothetotalCAISOloadbecausethisgivesageneralsenseofhowmuchDGcontributestostatewidepeak.FuturestudiesshouldconductanalysisofDG’speakdemandimpactatotherlevelsbecausetheimpactislikelytobedifferentatlowerlevelsthanattheCAISOlevel.
TheIOUsarealreadyconductingsomeresearchintotheimpactofDGatthedistributionfeederlevel,inordertobetterunderstandtheseimpactsandhowtheymightchangeaspenetrationincreasesinthefuture.Inparticular,SCEconductedastudyinOctober2012toassessthepeakdemandimpactofcustomersolarPVonresidential(Figure4‐7)andnon‐residential(Figure4‐8)feederswithabove‐averagePVpenetrationrates.Asshowninthefigures,PVoutputpeaksaround1pminallcases,whileloadpeaksaround7pmontheresidentialfeederandaround3pmonthenon‐residentialfeeder.Whilethesearejustselectedexamples,thisanalysisshowsthatwhilePVcanhaveasignificantimpactintermsofreducingpeakdemandonanon‐residentialfeeder,butithasalmostnoimpactonaresidentialfeeder.ResultslikethisprovethevalueofexaminingDGimpactsatthelevelofindividualdistributionfeeders,becauseitbecomesapparentthattheimpactsofDGdependatleastasmuchonthelocalizedcharacteristicsofthedistributionsystemasonthecharacteristicsoftheDGsystemitself.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐18
Figure 4‐7 Peak Demand Impact of Solar PV on Typical SCE Residential Distribution Feeder45
45 “Coincidence of Solar Production with SCE’s System Load and Distribution Circuits,” SCE Load Research, Oct. 2012, p. 3.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐19
Figure 4‐8 Peak Demand Impact of Solar PV on Typical SCE Non‐Residential Distribution Feeder46
Additionalstudiesinthisareaofpeakdemandimpactarewarranted,evenbeyondtheanalysisofpeakdemandimpactatlevelsotherthantheentireCAISO.TheCPUCdatasetcontaining15‐minutemeteredproductiondataforCSIandSGIPsystemsisverylargeandrich.Thepeakdemandimpactanalysisperformedhereisasimpleexampleofitsuse.PreviousCSIImpactEvaluationreportshaveperformedotheranalysesthatwerebeyondthescopeofthisreport,buttherearestillmanypossibleusesforthedatathathavenotbeenfullyexploredtodate.Thesecouldinclude:
ExtrapolationofresultstodetermineimpactsathigherDGpenetrations
AssessmentofNEMsystems’impactonloadshapeandconsequentialpeakshifting
Analysisofnon‐peakperiodsincludingidentificationofperiodsofmaximumDGexport
CalculationofEffectiveLoadCarryingCapacity(ELCC)ofdifferentDGsources.ELCCrequiresastatisticalprobabilityanalysisofpreferablymultipleyearsofcoincidentloadandgenerationdatatodeterminethecapacityvalueofdifferentgenerationsources.
Analysisoftheimpactsofwest‐facingversussouth‐facingPVsystemsonloadshape
Assessmentoftheeffectsofdecommissioningandperformancedegradationontheresults
46 “Coincidence of Solar Production with SCE’s System Load and Distribution Circuits,” SCE Load Research, Oct. 2012, p. 5.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | DG Impacts on the Transmission and Distribution System 4‐20
Comparisonandvalidationofdifferentforecastingtechniques
Analysisofshort‐termvariabilityofPVoutputbygeographiclocation,systemtype,etc.
Analysisofhowmuchshort‐termvariabilityisreducedbycombiningoutputfromPVsystemsspreadoverawidegeographicarea
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐1
5.0 Issues and Barriers Impacting DG Deployment TherateofDGinstallationsontheCaliforniagrid,inparticularsolarPVsystems,hasincreasedsignificantlyoverthepastseveralyears.Thisincreasecanlargelybeattributedtofinancialandregulatoryincentives,theavailabilityofnewleasingandfinancingoptions,thedeclineinsolarPVcostsglobally,andincreasedmarketingefforts.Inmanyrespects,CaliforniahasledthenationinidentifyingandremovingbarrierstoDGdeployment.InitiativessuchasimplementationofNEM,reformofRule21,andcompletionofon‐linetoolsforrebateprocessinghaveallowedCaliforniatosuccessfullyadvancethelargestDGmarketintheU.S.California’ssuccesshasbeenamodelforotherstatesinimplementingtheirownDGprograms.
DespiteCalifornia’ssuccess,therearestillbarrierstoadditionaldeploymentofDG.Thesebarriersexistfromboththeutility’sperspectiveandthecustomerand/ordeveloper’sperspective.Moreover,thereareanumberofissueswhichaffectDGdeploymentandmeritdiscussion,butarenotactuallybarriers.BarriersinthisreportaredefinedasthosethingswhichdirectlyinhibitgreaterdeploymentofDG—asopposedtoissues,whicharedefinedhereasthosethingswhichaffectbutdonotnecessarilyinhibitit.Thissectionaddressesbothbarriersandissues.
Itron’s2010Reportidentifiedpotentialbarriersrelatedtopolicy,technicalbarriersrelatedtoRule21,distributionsystemunknownswithincreasedpenetration,anduncertaintyaroundenvironmentalrequirementsforDG.Inthisreport,Black&Veatchprovidesanupdateanddiscussionofadditionalissuesandbarriers.ThesearelistedinTable5‐1bycategory,alongwithwhethereachisanissueorabarrier,andwhethereachisconsideredakeyissueorbarrier.
Thefollowingsectionsaddresseachofthesecategories,andalsoprovideaprioritizedlistofthekeyissuesandbarriers.Itshouldbenotedthattheidentificationofabarrierorissueinthisreportdoesnotnecessarilyimplythatitshouldbe,orevencouldbe,addressed.Manybarriershavealreadybeenreduced(suchasinterconnectionissues),andsomearelargelyoutsidethecontrolofthestate(suchashighequipmentcosts).Asnotedintheintroductiontothissection,California’sDGmarketisthelargestinthecountry,andalreadyhasmademuchprogressinaddressingmanyofthelargerbarrierstoDG.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐2
Table 5‐1 Issues and Barriers Impacting DG Deployment
CATEGORY/TOPIC ISSUEORBARRIER? KEYISSUEORBARRIER?
FinancingandEconomics
FinancialIncentives Issue
AccesstoFinancing Barrier
EquipmentCosts Barrier
SoftCosts Barrier
PolicyandRegulatory
IncentivestoLocateDGinBeneficialAreas Issue
RateStructures Issue
EquitableAllocationofCosts Issue
RegulatoryMandates Issue
GridAccessandInterconnection
BarrierstoDGInterconnection Barrier
Integration
Monitoring,Forecasting,andControl Barrier
ModelingToolsforIntegrationofDG Issue
DistributionSystemDesign Issue
InverterStandards Issue
Miscellaneous
ProcessingTimesandCustomerUnderstanding Issue
AllocationofFunds Issue
MultiplePrograms Issue
AvailabilityofInstallers Barrier
MarketingandConsumerEducation Barrier
ForecastingofFutureInstallations Issue
ProjectSiting Barrier
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐3
5.1 FINANCING AND ECONOMICS Perhapsthemostimportantbarriertocontinuedcustomer‐sideDGdeploymentistherelativelyhighfinalcosttocustomers.ThevariousincentivesandprogramsavailableforinstallationofDGsystems(describedinSection3.2.1)haveencouragedwidespreadgrowthofDGthroughoutCalifornia.However,intheabsenceofsubsidies,mostDGtechnologiesarecurrentlyunlikelytobecompetitivewithgridpower.
SeveralfactorscontributetotheultimatecostofDGtocustomersincludingfinancialincentives,accesstofinancing,equipmentcosts,and“soft”costs.
5.1.1 Financial Incentives
BecauseoftherelativelyhighinitialcostofDGtechnologiescomparedtogridelectricity,andbecausepublicpolicyinCaliforniaandnationwidehasshownsignificantsupportforDG,financialincentivesarethemostimmediateanddirectmethodofreducingthecostofDGandincreasingitsdeployment.AtthestatelevelinCalifornia,therearenumerousprogramswhichprovidefinancialincentivesforDG,asdescribedinsection3.2.1.TheNEMtariffisalsoasignificantfinancialbenefitforcustomer‐sideDG,becauseitallowscustomerstobecreditedforgeneration(uptotheirannualconsumption)attheretailrate.Atthefederallevel,themainfinancialincentiveforDGistheinvestmenttaxcredit(ITC),whichprovidesataxcreditofupto30percentoftheinstalledcostforcustomerswhoinstallsolarPV,windorfuelcells,and10percentforthosewhoinstallmicroturbinesorCHPsystems.47
Giventhecurrentlevelsoffinancialincentivesofferedbystateandfederalgovernment,amajorissueforfutureDGdeploymentisthelimited,declining,orexpirationofstateandfederalfundingofincentives.48First,fundingformanyofthestateincentiveprogramsislimited,whichdeterslaterDGcustomersifdemandforincentivesoutpacesavailabilitybeforeaprogramends.Second,programfundingmaydecreasebecauseofoutsideinfluences(e.g.governmentspendingcuts),orper‐unitpaymentstocustomersmaydeclinewithgreaterparticipation.ThislattermechanismisactuallypartofthedesignofprogramssuchasCSI,becausetheyassumethatDGcostswilldecreaseasmoreisinstalledandthatincentivelevelsperkWcandecreaseaccordingly.
Third,manycurrentstateandfederalincentivesaresettoexpireatspecificpointsinthefuture,whichisanissuebecauseoftheuncertaintyitcreateswithintheindustry.Thefederalproductiontaxcredit(PTC)andinvestmenttaxcredit(ITC)forwindwasallowedtoexpireattheendof2012,butwasthenextendedforjustoneyearaslongasconstructionbeginsbeforetheendof2013.Similarly,biomassexpiresin2013andPVexpiresin2016.TheCSIisalsosettoendin2016.49Otherincentiveprogramsfaceexpirationdatesaswell.Duetothepoliticalnatureoftheseprograms,itisnotknownifanyofthemwillbeextendedpasttheirexpirationdate,andiftheyareextendeditisnotknownhowincentivelevelswillchange.Anendorsignificantchangetothesegovernmentincentives(especiallytheITC)wouldlikelyreduceDGdeploymentsincethefinalcostofDGtothecustomercouldabruptlyincreaseandalargeportionofDGprojectsmightnolongerbeeconomic.Thus,alackoffinancialincentivesisoneofthemostimportantpotentialissuesforDGdeployment,andalsoperhapsthemostvisibleissuetocustomers.
47 http://www.dsireusa.org/incentives/incentive.cfm?Incentive_Code=US02F&re=1&ee=1 48 Energy and Environmental Economics, “California Solar Incentive Cost‐Effectiveness Evaluation,” Prepared for: California Public Utilities Commission, San Francisco, CA, April 2011, p. 10. 49 The CPUC has recently begun a market transformation study to determine what the market for customer‐side solar PV will look like post‐CSI.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐4
5.1.2 Access to Financing
DGinstallationsgenerallyinvolvelargeupfrontcosts,andinthecaseofrenewableDGlikesolarPVandwind,theinitialcapitalcostisessentiallytheonlycost(exceptforasmallamountofmaintenanceoverthelifetimeofthesystem).FormostcustomersinterestedininstallingDG,thislargeupfrontinvestmentisabarrierbecausetheymaynothavetherequiredamountofcashimmediatelyavailabletopayforthesystem,anditismuchsimplerandeasiertocontinuepayingtheircomparativelysmallmonthlyelectricbill.ThismayhappendespitethefactthatinmanycasestheycouldpotentiallysavemoneyoverthelongtermwithaDGsystem.
However,overthelastfewyearstheavailabilityofthirdpartyleasingandfinancingoptionsforsolarPVhashelpedtosignificantlyalleviatethisbarrierandhasallowedlessaffluentcustomerstodeploysolarPV.50CompaniesofferingthesethirdpartyfinancingoptionsoftenallowcustomerstoinstallPVwithlittleornoupfrontinvestment,allowingthemtosimplypayamonthlychargelessthantheirpre‐existingelectricbill.Theprevalenceofthesethirdpartyarrangementshasincreasedconsistentlyanddramaticallyinthelastfewyears,asmeasuredbyapplicationstotheCSIprogram,fromabout10percentofCSIapplicationsin2007to68percentin2012.51Thistrendisespeciallystrongamongresidentialcustomers.Figure5‐1showstheincreasingrateineachyearsincetheCSIprogrambeganin2007throughSeptember2012.
Figure 5‐1 Percentage of PV Systems with Third‐Party Ownership in CSI, 2007‐2012
Despitetheriseofleasingandotherinnovativefinancingarrangements,accesstofinancingisstillabarrierformanycustomers.Leasingcompaniesprefercustomerswithhigherelectricitybillsandgoodcredit,whichtendtobemoreaffluentcustomers.Forexample,toqualifyforalease, 50 E. Drury et al., “The Transformation of Southern California Residential Photovoltaics Market Through Third‐Party Ownership,” National Renewable Energy Laboratory, Golden, CO, Jan. 2012. 51 Based on Black & Veatch analysis of the CSI Working Data Set, available at www.californiasolarstatistics.org/current_data_files.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2007 2008 2009 2010 2011 2012
Third‐Party Ownership (%
of All Applications)
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐5
customersofonesolarleasingcompanymusthaveaFICOcreditscoreofatleast700.Justoverhalfofthepopulationhadascorethathighin2011.52Whileotherfinancingstructuresareavailable,theydonotoffertheattractivemonthlypaymenttermswithnoupfrontcosts.
5.1.3 Equipment Costs
FinancialincentivesfrompublicprogramsandnewfinancingoptionscanhelptoreducethecostofDGtocustomers,buttheinitialcostoftheequipmentitselfisalsoamajorfactorinthiscostandcanbeabarrier.Asmentionedabove,theunsubsidizedcostsforDGremainhighrelativetothecostofgridelectricity;althoughinsomecasesthecostofDGequipmentisdecliningbecauseofincreasingadoption,improvingeconomiesofscale,andtechnologicalinnovation.ThecostofsolarPVmodules,inparticular,hasdecreasedsignificantlyinthelastfewyears,asshowninFigure5‐2below.Butevenwiththesedeclines,DGequipmentcostsarestilloneofthelargesteconomicbarrierstogreaterDGdeployment.
Figure 5‐2 Solar Module Prices from December 2001 – March 201253
5.1.4 Soft Costs
InadditiontoDGequipmentcosts,thetotalcostofinstallingaDGsystemincludesanumberoflesstangibleor“soft”costcomponents,whichinmanycasescanbejustassignificantasthe“hard”costsforthephysicalequipment.Softcostsincludeanypermittingfees,administrativecosts,financingandcontractingcosts,designandengineeringcosts,customeracquisitioncosts,incentiveapplicationfees,interconnectionfees,taxes,aswellasthecostsassociatedwithprojectdelaysdue
52 FICO, “FICO® Scores Shift During Recession,” http://bankinganalyticsblog.fico.com/2011/09/fico‐scores‐shift‐during‐recession.html, accessed September 2012. 53 Solarbuzz, PV Module Price Index, available at: http://www.solarbuzz.com/facts‐and‐figures/retail‐price‐environment/module‐prices, accessed September 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐6
topermittingorinterconnectionissues.DGprojectsinCaliforniamustusuallyobtainapprovalfrommultipleentitiesorjurisdictions,includingtheutilitytowhichtheyareinterconnecting,theincentiveprogramtowhichtheyareapplying,thelocaljurisdictionwhichmustinspectthemforpublicsafetyreasons,andpossiblyotherentitiesaswell.
AsequipmentcostsforPVhavedropped,softcostshavestayedrelativelyconstant,thusincreasingtheirshareoftheoverallcosts.ThesesoftcostscanconstitutealargeportionoftotalDGsysteminstalledcosts,andthereforeareabarriertoDGdeployment.LawrenceBerkeleyNationalLaboratoryreleasedastudyinSeptember2012comparingtheinstalledcostsofresidentialrooftopsolarPVinstallationsintheU.S.andGermany.54ThestudyfoundthataverageinstalledcostsperwattinGermanyin2011were45percentlowerthanintheU.S.,mostlyattributabletosoftcosts.Moreover,inGermany,softcostsaccountedforjust20percentoftotalinstalledcosts,whileintheU.S.theyaccountedforover50percentoftotalinstalledcosts.Thestudyexploresanumberofexplanationsforthisdifference,andindicatesthatthemainsoftcostbarriersforgreatersolarPVdeploymentintheU.S.relativetoGermanyinclude:
SmalleroverallsolarPVmarket
Smalleraveragesystemsize
Slowerprojectdevelopment/installationprocess
Highernet‐profitmarginsforinstallersduetolesscompetition
HighersystemsalespricesduetomoregeneroussubsidiesandhigherPVsystemoutput
Highercustomeracquisitioncosts,includingsystemdesigncostsandmarketingandadvertisingcosts
Higherlaborhourrequirementsforpermitting,interconnection,andinspection
Higherpermittingandinterconnectionfees
HighersalestaxesonPVsystems
Manyattemptshavebeenmadeatalllevelsbytradeassociations,localpermittingauthorities,utilities,stateagencies,legislators,andadvocacygroupstoreducesoftcosts,withvaryinglevelsofsuccessdependingonthejurisdiction.ThemostsignificanteffortinthisareaistheU.S.DepartmentofEnergy’sSunshotInitiative,whichisseekingtoreducetheinstalledcostofsolarPVby75percentbetween2010and2020.Thisincludesacomparabledecreaseinsoftcosts,andtheinitiativehasalreadyfundedmultiplestudiesandprojectsinCalifornia.55
5.2 POLICY AND REGULATORY Somecurrentgovernmentalpoliciesandregulationscanaffecttheproliferationofcustomer‐installedDG.Theseissuesarelistedbelow,andfurtherdescribedinthefollowingsubsections.
LackofincentivestolocateDGinareaswiththegreatestbenefittothegrid
CertainratestructuresprovidedifferingincentivestoDG
Equitableallocationofcostsandbenefits
54 J. Seel, G. Barbose, R. Wiser, “Why Are Residential PV Prices in Germany So Much Lower Than in the United States?: A Scoping Analysis,” Lawrence Berkeley National Laboratory, Berkeley, CA, Sept. 2012. Available at http://eetd.lbl.gov/ea/emp/reports/german‐us‐pv‐price‐ppt.pdf. 55 http://www1.eere.energy.gov/solar/sunshot/nonhardware_bos.html
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐7
Regulatorymandates
Itshouldbenotedthatchangesoradditionstopoliciesandregulationswillrequireresearchandclosecollaborationbetweenutilities,industry,andregulators.
5.2.1 Incentives to Locate DG in Beneficial Areas
Fromtheoutset,someofthekeybenefitsofdistributedgenerationhavebeenassociatedwiththeirabilitytobelocatedinareaswheretheycanreducepeakdemand,reducelinelosses,anddeferdistributionandtransmissionsystemupgrades.However,therearecurrentlyverylimitedincentivesprovidedtoDGsystemownersanddeveloperstoactuallysiteDGintheseareas.Instead,DGinstallationsareprimarilydrivenbyotherfactorssuchashostsiteeconomics,landavailability,permitting,andresourcequality.Duetotheseoverridingconsiderationsandthelackofincentives,DGisnotbeingoptimallylocatedonthedistributionsystemandmanyofthepotentialbenefitsarenotfullyrealized.Infact,largerDGsystemsroutinelyarefacedwithdistributionsystemupgradecosts–notbenefits.
AsstatedinareportpublishedbyRockyMountainInstituteandPG&EinMarch2012,“DGthatisatthe‘rightplaceattherighttime’willcreatethegreatestvalue,whileadditionalelectricitysupplyinthewrongplaceatthewrongtimecouldresultinaddedcoststothesystem.”56
ThelackofincentivestolocateDGinareaswiththegreatestbenefittothegridisanissuesimpactingcosteffectivedeploymentofDG.IfCaliforniadoesnotprioritizebeneficialsitingofDG,thencoststoachievethestate’sDGgoalsarelikelytobehigherandbenefitstoconsumersarelikelytobelower.
5.2.2 Rate Structures
Utilityratestructurescanhaveasignificantimpactonthecost‐effectivenessofcustomer‐sideDGinstallations.InsomecasestheymaybefavorabletotheinstallationofDG,whileinothercasestheymaydeterDG.Asaverysimpleexample,customerswhopayhigherratesaremorelikelytosavemorefromDGinstallation.Whilethesecustomersbenefitfromthegreatersavings,totheextentthereisacostshiftassociatedwithcurrentnetenergymeteringpolicy,othercustomerswillabsorbthosecosts(seenextsection).Ratedesigncanthusaffect(1)thedeploymentofDGinCalifornia,and(2)impactnon‐DGcustomersandtheutilities’abilitytorecovercostsofservice.Itshouldbenotedthattheintentofthissectionisnottoassesswhethercertainratedesignsshouldbeencouragedordiscouraged.Itisbeyondthescopeofthisreporttoaddresstheimpactofutilityratestructuresonthecost‐effectivenessofcustomer‐sideDG.57TheexamplesmentionedherearesimplymeanttoillustratespecificwaysinwhichdifferentratestructurescanaffectDGdeployment.
ImpactofRateStructureonDGDeploymentRatestructures,whichareslightlydifferentforeachIOU,determinehowautilitycustomerischargedforelectricityusage.ForresidentialcustomersoftheIOUsinCalifornia,therearemultipleratetiers:uptoacertainamountofusage,onerateischarged,andthenahigherrateappliestousageuptothenextthreshold,etc.Figure5‐3showsPG&E’sresidentialratetierstructureasan
56 “Net Energy Metering, Zero Net Energy, and the Distributed Energy Resource Future: Adapting Electric Utility Business Models for the 21st Century,” Rocky Mountain Institute, Snowmass, CO, March 2012. 57 The CPUC has opened a rate design rulemaking to comprehensively examine utility rate structures. Order Instituting Rulemaking on the Commission’s Own Motion to Conduct a Comprehensive Examination of Investor Owned Electric Utilities’ Residential Rate Structures, the Transition to Time Varying and Dynamic Rates, and Other Statutory Obligations, R.12‐06‐013, Issued June 21, 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐8
example.CustomersinthehighesttierpayamuchhigherrateperkWhthancustomersinthelowertiers.Asshowninthefigure,atalmost$0.35/kWh,theTier4rateisaboutthreetimeshigherthantheTier1rate.Thus,high‐usagecustomershavegreatereconomicincentivetopursueDGoptionsthancustomersinlowertiers.Iftheresidentialrateswerestructureddifferently—e.g.iftheper‐kWhratewerethesameforallcustomersregardlessofusage—theadoptionrateofDGbyvarioustypesofcustomerswouldlikelybedifferent.Intoday’sratestructure,thelowerratepaidbycustomersinthelowertiersmaybeactingasadeterrent,ifsuchcustomersmaybeinterestedininstallingDGbutarenotabletojustifyitcomparedtotheirlowper‐kWhrate.Ofcourse,equalizingthetierswouldalsoruncountertootherpolicygoals,suchasencouragingenergyefficiency.
Figure 5‐3 PG&E Residential Rate Tier Structure (January 2012)58
Forcommercialandindustrialcustomers,thesituationismorecomplicated.Inadditiontotheper‐kWhenergychargetherealsocanbea“demandcharge”paidbasedontheindividualcustomer’speakdemand.Thepeakdemandismeasuredasthehighestaverageusageovera15‐minuteperiodoutofthemonth.Placingachargeonpeakdemandismeanttocoversomeofthecostsoftheinfrastructuretoservethesecustomers;italsogivestheselargercustomersanincentivetoreducetheirpeakdemand.Thedemandchargecanbeasignificantportionofthecustomer’selectricbillifthecustomerhashighpeakenergyuse.
AccordingtoCCSE,thedifferentnon‐residentialtariffsfortheIOUsshiftvaryingamountsofthecustomer’soverallcostsbetweenthedemandchargeandtheper‐kWhcharges,butPG&EandSCE
58 “Net Energy Metering, Zero Net Energy, and the Distributed Energy Resource Future: Adapting Electric Utility Business Models for the 21st Century,” Rocky Mountain Institute, Snowmass, CO, March 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐9
havetariffsthatshiftmorecoststotheper‐kWhchargethanSDG&E.59ThismeansthatcommercialcustomersinSDG&EterritoryhavelessofaneconomicincentivetoinstalldistributedsolarPV.Eventhoughtheymaybeabletoreducetheirper‐kWhcostswithPV,theystillhavetopayarelativelylargerdemandcharges(comparedtoPG&EandSCEterritories)whichDGmaynothelptoreduce,sincePVmaynotpeakwhenthecustomer’sdemandpeaks.Aswiththeresidentialratetiersmentionedabove,iftherelativedistributionofdemandchargesandkWhchargeswereadjustedforcommercial/industrialIOUcustomers,thentheadoptionofDGwouldlikelychange.
Figure5‐4showstheimpactthatdifferentratestructurescanhaveonelectricbillsforcustomersinSDG&E’sterritory.Thechartshowscomparesexamplesofmonthlybillsforacommercialcustomerunderthreescenarios:
“BillsBeforePVInstallation”showsatypicalbillinghistoryforacommercialcustomerwithoutanyDGonthestandardrate.
“BillsAfterPV,onTOURate”showsthebillinghistoryforacommercialcustomerwithsolarPVonatypicaltime‐of‐useratethatincludesasignificantdemandcharge(Rate:AL‐TOU).
“BillsAfterPV,onDGRate”showsthebillinghistoryforacommercialcustomerwithsolarPVonamodifiedratethatincludesamuchlowerdemandcharge(Rate:DG‐R).
Figure 5‐4 Example Impact of Rate Structures on SDG&E Customer Electric Bills.60
59 For example, PG&E’s A‐6 tariff for small general time‐of‐use service does not have a demand charge. Its energy rate for summer peak periods is $0.44/kWh. See http://www.pge.com/tariffs/tm2/pdf/ELEC_SCHEDS_A‐6.pdf. 60 J. Del Real and J. Fortune, “Understanding Non‐Residential Utility Rates,” California Center for Sustainable Energy, May 2010.
$0
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
$7,000
$8,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Customer's Monthly Electricity Bill
Bills Before PV Installation
BillsAfter PV, on TOU Rate
BillsAfter PV, on DG Rate
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐10
AcustomerwithPVonanytypeofratewillhavelowerelectricbillsthanthe“BillsbeforePVInstallation”,becausethePVgenerationisoffsettingconsumptionfromthegrid;thus,both“BillsAfterPV”barsarelowerthanthe“UtilityBillwithoutPV”barineverymonth.ButitisclearfromthedifferencebetweentherateswithPV(i.e.thedifferencebetween“BillsAfterPV,onTOURate”and“BillsAfterPV,onDGRate”)thattheDGratewithlowerdemandchargesresultsinalowerbill,especiallyduringthesummermonthswhenPVproductionisgreatestanddemandchargesarehighest.ThislowerbillwillreducethepaybacktimeforthePVsystem,anditillustratesthatthevalueofDGtothecustomercanbesignificantlyaffectedbytheratestructure.
ImpactofRateStructureonCostofServiceRecoveryWhilealowerutilitybillwillresultinareducedpaybacktimeforthePVsystem,itmayalsohindertheIOUs’abilitytorecoverthecostsofprovidingelectricservicestoresidentialandothercustomerclasseswhoinstallself‐generation.Thisisbecausecostsofservice(i.e.theinfrastructurethatallowsDGcustomerstoreliablyconsumeelectricityfrom,andexportto,theutilitygrid)areembeddedinenergy(kWh)relatedchargesforcertaincustomerclasses.Iftheutilityisunabletofullyrecovercostsfromself‐generators,nonparticipatingcustomersmayhavetoabsorbthosecosts,whichcouldaffecttheirrates.SDG&Eindicatedthataworst‐casesituationcouldarisewhenratesincreaseduetogreaterDGdeployment,andmorecustomersthenbecomeincentivizedtoinstalltheirownDGsystem,whichcouldfurtherexacerbatetherateincreases,creatinganunsustainablefeedbackloop.
5.2.3 Equitable Allocation of Costs
Distributedgenerationsystemsreceivevariousincentivesthroughtheprogramsdescribedinthisreport.Ultimately,allratepayersandtaxpayersfundtheseincentives,whethertheyareparticipantsandnon‐participants,eventhoughonlyarelativelysmallportionofthepopulationcurrentlyparticipatesintheseincentiveprograms.Whilenon‐participantsreceivesomebenefits,suchasreductionofgreenhousegasemissions,thesebenefitsmaynotexceedthecostspaid.Ifthereisconcernthatcostallocationisnon‐equitable,thismayaffectcontinuedproliferationofDG.
Anotherexampleofnon‐equitablecostallocationrelatestodistributionsystemupgradesthatmayberequiredtoinstallDG.Asdiscussedinsection4.1,protectionschemesmayneedtobemodified,additionalequipmentmayberequired,orsystemmodificationsmaybeneeded.Theallocationofcostsforthesenewrequirementsmayfallinequitablyonallratepayers,includingthosewhodonotbenefitdirectlyfromtheupgrade.61Undercurrentlaw,NEMprojectspaylittletonocosttointerconnecttotheutilitygrid.62Fromtheutilities’perspective,thereisconcernthatwithincreasedDGandNEMinstallations,additionalupgradestothedistributionsystemmaybecomenecessary.Thecostsoftheseupgradeswouldbebornebytheutilityandpassedontoallratepayers,meaningthatnon‐NEMcustomerswouldeffectivelybesubsidizingtheNEMcustomers.ThisissueismademorecomplexbythefactthatcustomerswhoinstallDGandtakeadvantageoftheNEMtarifftendtobewealthierthantheaverageratepayer,sopoorercustomerswouldbesubsidizingwealthieronesinthisscenario.63TheequitableallocationofcostsbetweenNEMcustomersandother
61 Itron, “Impacts of Distributed Generation,” Prepared for: California Public Utilities Commission Energy Division Staff, Davis, California, January 2010, p. 4‐5. 62 This exemption for NEM projects derives from Pub. Util. Code § 2827(d) and was interpreted by the CPUC in D.02‐03‐057 to include exemptions from the costs of interconnection application review fees, interconnection studies, and distribution system modifications triggered by the NEM project. 63 “Net Energy Metering, Zero Net Energy, and the Distributed Energy Resource Future: Adapting Electric Utility Business Models for the 21st Century,” Rocky Mountain Institute, Snowmass, CO, March 2012, p. 32.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐11
ratepayersisconsideredbyutilitiestobeamajorconcernforincreasingDGdeployment,andiscurrentlybeingstudiedbytheCPUC.
Paststudiesandnewinitiativesareunderwaytotrytoaddressthisissue.Thesehaveshownmixedresults:someindicatetherearesignificantsubsidiesforNEMcustomers,whileothersindicatetherearesignificantnetbenefitsforallratepayers.TheNEMCost‐EffectivenessEvaluationcompletedfortheCPUCinMarch2010foundthatallNEMPVinstallationsthrough2008resultedinalevelizedcross‐subsidyofapproximately$20millionperyear.SCEin2012completedastudythatestimatedthatNEMcustomersaresubsidizedbynon‐NEMcustomersaround$50millionperyearwithNEMcapacityataboutonepercentofsystempeakdemand.64Conversely,astudycompletedbyCrossborderEnergyonbehalfoftheVoteSolarInitiativeinJanuary2013estimatedthatwhenNEMPVcapacityreachesfivepercentofpeakdemandinCaliforniaitwillprovideapproximately$90millionperyearinnetbenefitstoratepayersofPG&E,SCEandSDG&E;itfoundthatmostofthosenetbenefitswouldresultfromnon‐residentialNEMinstallations.65ItisexpectedthattheupdatedNEMCost‐BenefitEvaluationfor2012‐2013,commissionedbytheCPUC,willaddressthisissueagainandprovidegreaterdetail.66Finally,theUniversityofSanDiegoEnergyPolicyInitiativesCenter,Black&Veatch,andCleanPowerResearcharecurrentlyconductingacost‐benefitstudyfocusedonthenetcostorbenefitofsolarPVNEMsystemsinSDG&E’sterritory.AnobjectiveofthatstudyistodeterminethecostoftheservicesprovidedtoNEMcustomersandthevalueofthebenefitstheyprovidetothesystem.
5.2.4 Regulatory Mandates
CPUC,FERCandotherregulatingbodiesapplycertainoperationalmandatestoutilities.InputfromtheIOUsindicatedthatmandatesthataredifficulttoimplementorlimitautility’soperationscanunintentionallyaffectfurtherDGdeployment.Forexample,SDG&Eindicatedthattheuniqueattributesoftheirsystem,specificallybeingheavilyresidential,arenotoftenconsideredbyregulatorsandcouldimpactfurtherdeploymentofDG.
Asanotherexample,theCPUCrequiresutilitiestomaintainvoltageatacertainstandard(forexample,withina+/‐5percentthreshold).67Asdescribedinsection4.1.5,DGsystemsaffectsystemvoltage,andmayleadtoviolationsoftheCPUCmandatedthresholds.Thus,itispossiblethatthesestandardscouldindirectlyaffectDGdeploymentbydiscouraginginstallationswhichmaycausevoltageissues.PEPCOHoldings,Inc,whichisdealingwithincreasedsolarPVinstallationsinNewJersey,hassuggestedthatvoltagestandardsmightbereviewedandpotentiallyrelaxedtoprovidegreaterflexibilitytoaccommodateDGinitsserviceterritory.Inparticular,Germanyappliesa+/‐10percentthreshold.68However,relaxingvoltagerequirementswouldneedtobecarefullyconsideredandmaynotbeappropriateinCalifornia.Operatingathighervoltagemaybedetrimentaltoexistingcustomerloadequipmentthatwasdesignedandratedfortheexistingvoltagerange.
64 SCE, “Retail Rates and Cost Issues with Renewable Development,” May 2012, available at http://www.energy.ca.gov/2012_energypolicy/documents/2012‐05‐22_workshop/presentations/09_Garwacki_SCE‐Retail_Rate_2012‐05‐22.pdf. 65 Crossborder Energy, “Evaluating the Benefits and Costs of Net Energy Metering in California,” January 2013. Available at: http://votesolar.org/resources‐impacts‐of‐net‐metering‐in‐california/. 66 http://www.cpuc.ca.gov/PUC/energy/Solar/nem_cost_benefit_evaluation.htm 67 Voltage and other service standards are set out in each IOU’s Electric Tariff Rule 2, which is subject to the CPUC’s approval. 68 PEPCO Holdings, Inc., “Challenges for Distribution Feeder Voltage Regulation with Increasing Amounts of PV”, Available at: http://www1.eere.energy.gov/solar/pdfs/hpsp_grid_workshop_2012_steffel_pepco.pdf.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐12
5.3 GRID ACCESS AND INTERCONNECTION ChallengesinobtainingaccesstothedistributiongridandcompletingtheutilityinterconnectionprocessareoftencitedasbarriersforDGdeployment.CaliforniahasmadelargestridesinfacilitatingDGinterconnection.Thissectiondescribesexistinginterconnectionprocesses,barriersrelatedtointerconnection,andfutureinterconnectionpoliciesthatmayaffectthesebarriers.
5.3.1 Existing Interconnection Processes
TherearethreedifferentinterconnectionprocessesthatapplyinCalifornia,dependingonprojectsizeandwhethertheinterconnectionistothetransmissionordistributionsystem.AlthoughthisreportdoesnotfocusonwholesaleDGsystems,theinterconnectionprocessesforthesesystemsaresummarizedinadditiontocustomer‐sideDGbelow.
CAISOInterconnectionProcessWholesaleDGprojectsmayinsomecasesbelargeenoughtointerconnectwiththetransmissionsystem.Ifthisweretobethecase,theywouldgothroughtheCAISOinterconnectionprocess,whichhasfourtracks,listedinorderfromsimplesttomostcomplex:
10kWInverterProcess
FastTrackProcess
IndependentStudyProcess
StandardClusterStudyProcess
WholesaleDistributionAccessTariffProcessIfawholesaleDGprojectistointerconnectwiththedistributionsystemofanIOUandengageincompetitivewholesalecommercialarrangements,thenitwouldlikelygothroughtheinterconnectionprocesssetoutineachIOU’sWholesaleDistributionAccessTariff(WDAT),whichissimilarbutnotidenticalforeachIOU.TherearemultipletrackswithintheWDATprocesssimilartotheCAISOtrackslistedabove.69EachIOU’sWDATisaFERC‐jurisdictionaltariff.
Rule21ProcessCustomer‐sideDGsystemsinterconnectingwiththedistributionsystemandwholesaleDGengaginginanavoided‐costsaletothehostutility,suchasfeed‐intariffparticipants,willtypicallyusetheCPUC‐jurisdictionalRule21interconnectiontariff.Rule21wasinitiallyadoptedbytheCPUCin1982toaddressthesafeandreliableinterconnectionofQualifyingFacilities(QFs)underthePublicUtilityRegulatoryPoliciesAct(PURPA).TheCPUCrevisitedRule21in2000andworkedtosubstantiallystreamlinetheinterconnectionprocessforsmaller,customer‐sideDGsystems,especiallyNEMsystems.Thechangeswereeffective:todate,asshowninTable3‐9above,over100,000NEMsystemshavebeensuccessfullyinterconnected.
However,asthescaleandpenetrationofDGsystemshaveincreased,particularlywiththeadventoftheCPUC’snewerwholesaleDGprograms,additionalreformstofacilitateinterconnectionbecamenecessary.SignificantreformstoRule21enactedinSeptember2012aredesignedtomaketheinterconnectionprocessmoretimely,cost‐effective,andtransparentforwholesaleDGprojectswhileretainingthesameefficiencyforNEMprojects.
69 CAISO, “Resource Interconnection Guide,” July 2012. Available at http://www.caiso.com/participate/Pages/ResourceInterconnectionGuide/default.aspx.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐13
ToserveDGinterconnectingtothedistributionsystemonbothsidesofthemeter,theRule21interconnectionprocessinvolvesthefollowingstudytracks,alsolistedinorderofsimplesttomostcomplex:
FastTrackProcess
DetailedStudies
● IndependentStudyProcess
● DistributionGroupStudyProcess(forthcoming)70
● TransmissionClusterStudyProcess71
AdditionalrecentreformstoRule21include:
Eligibilityforthe“FastTrack”processisexpandedtoincludeexportingfacilitiesupto3MWforPG&EandSCE,andupto1.5MWforSDG&E.
EligibilityforDGpenetrationlevelsisexpandedtothehighestinthenation.Theinitialscreenforaggregategeneratingcapacityupto15percentofpeaklinesectionloadisretained;however,ifanapplicantfailsthisscreen,theaggregategeneratingcapacitymayalternativelybetestedagainst100percentofminimumloadonthelinesection.ThisshouldallowformoreDGtobeconnectedwithintheFastTrackprocess.
Energystorageisincludedwithinthedefinitionof“generatingfacility,”makingstoragetechnologieseligibleforthesameinterconnectionprocesswithinRule21.
StandardInterconnectionAgreementsforNEM,non‐export,andexportinggeneratingfacilitiesareapproved.
Standardapplicationandsupplementalreviewfees(NEMsystemsexemptfromthesefees)areapproved.
Firmtimelinesareestablishedtoensurethatprojectsmakeprogresstowardinterconnection.
DisputeresolutionmechanismsattheIOUsandattheCPUCareestablishedtoaddressinterconnection‐relateddisputesefficiently.
AprocessforobtainingResourceAdequacyvalueisidentifiedthroughtheTransmissionClusterStudyProcess.
Apre‐applicationreportandonlineinterconnectionqueuesareintroducedtoaidsitingdecisions.
70 The Distribution Group Study Process is intended as a more‐efficient study track for groups of electrically interdependent generating facilities interconnecting to the same distribution circuit. The CPUC has identified this additional study track within Rule 21 as an issue to be completed within Phase 2 of the interconnection OIR. See Assigned Commissioner’s Amended Scoping Memo and Ruling Requesting Comments, filed September 26, 2012 in R.11‐09‐011. 71 Applicants under Rule 21 that are found to have electrical interdependence with the transmission network are offered the option of transitioning to the next applicable transmission cluster study process conducted by CAISO.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐14
5.3.2 Barriers Related to DG Interconnection72
TheCPUC’sinterconnectionoversightandreformeffortshavefocusedonRule21,thetariffundertheCPUC’sjurisdiction.ItisimportanttonotethatthereformstoRule21adoptedinSeptember2012wereintendedtoaddressanumberofbarrierstoentryrelatedtotimeliness,transparency,andpredictabilitythathadbeenidentifiedbeforethestartoftheCPUC’sinterconnectionrulemaking.Thus,theCPUCwillbemonitoringthesuccessofthereformsinreducingoreliminatingthosebarrierstoentry.
Atthesametime,theCPUChasidentifiedcertainforward‐lookinginterconnectionpoliciestoaddressinPhase2oftheinterconnectionproceeding.Thoseinclude:
DetailingtheDistributionGroupStudyProcess,
Developingadditionalstandardizedinterconnectionformsandagreements,
Enhancinginterconnectioncostcertainty,usingtoolssuchastheidentificationofpreferredlocationsforDG,
EvaluationofthesuccessofRule21inreducinginterconnectionasabarriertoentry,and
EvaluatingtechnicaloperatingstandardsthatcanaidinaccommodatingincreasesinDG,includingautonomoussmartinverterfunctionalities.73
TimetoProcessInterconnectionApplicationsTheefficiencyandspeedwithwhichinterconnectionapplicationsareprocessedunderRule21hasbeenidentifiedasabarrierbysome,sincetheamountofDGinstallediscompletelydeterminedbyhowmuchDGisapprovedforinterconnectionbytheutility.Somepointtothefactthatinterconnectionprocessispaper‐basedasasourceofinefficiency.Tohelpaddressthisissue,SDG&Ehasimplementedanonlinedatabaseforinterconnectionapplications,similarinsomewaystothePowerClerksoftwareusedbytheCSIprogramforincentiveapplications.Thishasimprovedapplicationprocessingspeedandallowedgreatercustomervisibilityintotheinterconnectionapprovalprocess,therebyreducingtheperceptionofinterconnectionprocessingasabarriertoDG.However,thefundingforsucheffortsmayhavetobedrawnfromthebudgetforotheractivitieslikeoperationsandmaintenance,whichisabarrierontheutilitysidetofurtherimprovements.
Table5‐2andFigure5‐5showtheaveragetimestakentoprocessinterconnectionapplicationsfordistributedsolarPVintheCSIGeneralMarketprogrambyeachIOU.AlloftheIOUsareonaveragemeetingtheirstatutoryobligationtoprocessNEMinterconnectionapplicationswithin30days.Forbothresidentialandnon‐residentialapplications,SDG&EshowedsignificantlyshorterprocessingtimesthanPG&EandSCE.WhileSDG&Ehasasmallervolumeofinterconnectionrequests,representativesfromCCSEindicatedthatSDG&Efocusesoncompletinginterconnectionsquicklyandthatitsonlineinterconnectiondatabasealsomakestheprocessmoreefficientthantheotherutilities’paper‐basedsystems.SincenearlyalloftheseapplicationsareforDGsolarsystemsthatarealsoreceivingincentives,theinterconnectionapplicationprocessingtimeismerelyonepartoftheprocessthatcancausedelays.However,itisperhapsthemostcriticalpartbecauseacustomer
72 As noted previously, California has successfully addressed many interconnection barriers in the past, and many additional barriers have been addressed through the reforms to Rule 21. This section describes issues which have historically been considered barriers, but which may no longer represent significant obstacles to DG interconnection. 73 Assigned Commissioner’s Amended Scoping Memo, filed September 26, 2012 in R.11‐09‐011.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐15
cannotlegallyinterconnecttothegridandstartproducingelectricitywithoutcompletingtheinterconnectionprocess.
Notably,theaverageinterconnectionapplicationprocessingtimeforallthreeIOUsincreasedinthefirst6monthsof2012comparedtopreviousyears.Aprobableexplanationfortheincreaseistheincreasedvolumeofinterconnectionrequests.Comparedtopreviousyears,therateofinterconnectionapplicationshassubstantiallyincreased,insomecasesdoubling.Addingstaffandimplementinganonlineprocessingsystemmaydecreasetheaverageinterconnectionprocessingtime.
Table 5‐2 Number of Interconnection Applications and Average Interconnection Application Processing Times for CSI PV Systems by IOU74
TIMEPERIOD
PG&E SCE SDG&E
RESIDENTIALNON‐
RESIDENTIAL RESIDENTIALNON‐
RESIDENTIAL RESIDENTIALNON‐
RESIDENTIAL
AverageNumberofApplicationsReceivedperMonth
January–June2012 798 63 889 38 273 8
2009–2011 726 36 453 19 200 6
AverageProcessingTime(Days)
January–June2012
18.4 17.6 12.3 19 4.5 6.9
2009–2011
10.7 12.6 10 17.9 3.6 4.8
74 http://www.californiasolarstatistics.ca.gov/reports/data_annex/ and CSI Working Data Set
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐16
Figure 5‐5 Average Interconnection Application Processing Times for CSI PV Systems by IOU
IdentifyingOptimalInterconnectionLocationsAshasbeennotedthroughoutthisreport,identifyingthe“rightplaceattherighttime”forDGwillcreatethegreatestvalueforratepayersandtheelectricgrid.Achievingthisgoalhasdirectimplicationsforinterconnection.First,asdiscussedinthissection,thereareseveraltoolsnowavailableinCaliforniatoaidDGsitingdecisions.Second,theCPUCisconsideringnext‐generationpolicies,suchasimprovinginterconnectioncostcertaintyandautonomoussmartinverterfunctionalities,tofurtheridentifytheoptimallocationsandtimingofDGonthedistributionsystem.
InterconnectionCapacityMapsInstallersanddevelopersinthepastoftennotedthatitwouldbehelpfultohaveamaporGIStoolwhichwouldallowthemtoidentifyoptimallocationsonthedistributionsystemforlargerDGsystems(generallywholesalesystems)basedoncircuitcapacityorothercharacteristics,ratherthanhavingtofindoutwhichsitesaregoodorbadthroughtheinterconnectionreviewprocess.Fortunately,thisparticularbarrierhasbeenatleastpartiallyaddressedforwholesalesystems,andisgenerallynotachallengeforcustomer‐sidesystems.In2011,pursuanttoCPUCdecisionsimplementingtheRAMprogram,theIOUsreleasedweb‐basedmapsofinterconnectioncapacityontheirdistributionandtransmissionsystemsforjustthispurpose(seeFigure5‐6).PursuanttoCPUCorders,theIOUsactivelymaintainthesemapsontheirwebsitesandupdatethemapproximatelyoncepermonth.
0
2
4
6
8
10
12
14
16
18
20
Residential Non‐Residential Residential Non‐Residential Residential Non‐Residential
PG&E SCE SDG&E
Interconnection Application Processing Time, Days 2009 – 2011
January – June 2012
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐17
Figure 5‐6 Example Interconnection Capacity Mapping Tool from PG&E75
Pre‐ApplicationReportandOnlineIntegratedQueuesInadditiontothemaps,aPre‐ApplicationReportisnowavailableunderRule21,whichprovidesalow‐cost($300)firstlookofthetechnicalpotentialandchallengesofadesiredpointofinterconnectionforaDGproject.Anypotentialapplicantcanrequestareport,regardlessofwhethertheywillapplyforinterconnectionunderRule21ortheWholesaleDistributionAccessTariff.
Rule21alsonowrequiresIOUstomaintainanonlineintegratedqueueoftheDGprojectsseekinginterconnectiontothedistributionsystemunderRule21andtheFERC‐jurisdictionalWholesaleDistributionAccessTariff.Thisonlinespreadsheetprovidesmarketparticipantsameansofevaluatingthenumberofapplicantsqueuedaheadonthesamedistributioncircuit.Thelengthofthequeueimpactsthetimeandriskassociatedwiththeinterconnectionprocess.
5.3.3 Future Interconnection Policies
BecauseoftheincreasingamountofDGandthegrowingfocusonitsroleintheelectricsystem,effortstodevelopthenextgenerationofinterconnection‐relatedpoliciesareunderwayatboththestateandfederallevel.
75 https://www.pge.com/b2b/energysupply/wholesaleelectricsuppliersolicitation/PVRFO/PVRAMMap/index.shtml
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐18
CPUCRule21InitiativesCostcertaintyhasbeenidentifiedasamajorfactoraffectingtheabilityofDGinstallerstocompletetheinterconnectionprocess.Costuncertaintycantaketheformofalackofpredictabilityabouttheupgradesandcoststhatwillbetriggeredatagivenpointofinterconnection,and/orahighdegreeofvariabilityintriggeredcostsduringtheinterconnectionprocess,becauseofdecisionsmadebyqueued‐aheadprojects.76TheCPUCheldafirstworkshoponcostissuesinNovember2012tolaunchPhase2oftheinterconnectionproceeding.
AsdiscussedfurtherinSection6below,DGhasthepotentialtosupport,ratherthandetractfrom,thereliabilityofthegrid.InPhase2oftheinterconnectionproceeding,theCPUCisexaminingthepotentialtointroduceautonomoussmartinverterfunctionalitiesthatwouldbeapplicabletocertainDGsystems.ThepotentialforcontributionsbyDGwithsmartinverterfunctionalitiesisdiscussedfurtherinSection5.4andSection6.0.
CAISODGInitiativesAlsoatthestatelevel,CAISOissuedamemoranduminSeptember2012fortheconsiderationofitsboard,coveringCAISO’sevolvingpoliciestoaddressincreasingDGdeploymentinCalifornia.77Thismemorandumincludesanumberofinitiatives,allofwhicharedesignedtofacilitatetheinterconnectionofDGonthetransmissionanddistributionsystem:
AstreamlinedassessmentprocessforDGprojectsrequestingdeliverabilitystatustosupportresourceadequacyprocurementfor2014
AreviewandstakeholderprocessrelatedtocomplexandcostlytelemetryandmeteringrequirementsforDGprojects
A“non‐generatingresource”modeltoallowenergystorageprojectstoparticipateintheCAISOmarket
Aclarificationthatenergystoragecanprovidebothspinningandnon‐spinningreservesforthegrid
FERCDGInitiativesAtthefederallevel,FERCiscurrentlyconsideringapetitionforrulemakingfiledbytheSolarEnergyIndustriesAssociation(SEIA)inFebruary2012.ThispetitionrequestedthatFERCreviseitssmallgeneratorinterconnectionprocedurestomakeiteasierfordistributedsolarPVtobeinterconnectedtothedistributiongridusingthe“fast‐track”reviewprocess,largelybyraisingtheprojectsizelimitsandbyintroducingthealternativeDGpenetrationlimitof100percentofdaytimeminimumloadnowavailableinRule21.FERCheldatechnicalconferenceinJuly2012todiscussthisparticularissue,atwhichtheCPUCpresentedthenewpenetrationthresholdandotherrelevantadvancesthatwerethenpending(andsinceapproved)inRule21.Asofthiswriting,FERChasnotyetreachedadecisionaboutwhethertoactonSEIA’spetition.WhileitisnotcertainthatFERCcanadoptSEIA’sproposedchangesbecausetheyaresolar‐specific(FERCmustremaintechnology‐neutralinitspolicies),thefactthatthepetitionisbeingconsideredshowsthattheremaybechangeatthefederallevelintermsofinterconnectionprocessesrelatedtoDG,andthatregulatorychangesmayreducebarrierstogreaterDGdeployment.
76 For more on the cost issues associated with interconnection, see Assigned Commissioner’s Amended Scoping Memo and Ruling Requesting Comments, filed September 26, 2012 in R.11‐09‐011. 77 K. Edson, “Briefing on Distributed Energy Resources,” submitted to CAISO Board of Governors, Sept. 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐19
5.4 INTEGRATION TheintegrationofDGintothedistributionsystemandtheoveralloperationoftheutility’sgridisachallenge.ManyDGsystems,predominantlythosewhichimplementwindorsolartechnology,donothavetheabilitytosupplygenerationondemand.AsDGpenetrationincreases,particularlyonthesamedistributionfeeder,theintegrationofDGsystemswillbecomemorechallenging.
ThereareseveralchallengestointegratingDGsystemstothetransmissionanddistributiongrid,particularlyintermittentsystemssuchassolarorwindfacilities.Theseissuesandbarriersarelistedbelow,andarefurtherdescribedinthefollowingsubsections.
Lackofmonitoring,forecastingandcontrolcapabilities
LackofmodelingcapabilitiestoaddressincreasedintegrationofDG
Distributionsystemdesignedforpowerflowtowardsload
Inverterstandardscouldbemore“gridfriendly”
5.4.1 Monitoring, Forecasting, and Control
Currently,muchoftheDGinstalledonthegridinCaliforniaisnot“visible”tothegridoperators.Thisisduetoalackofmonitoringandcontrolcapabilitiescombinedwithlimitedforecastingsystems.AsDGpenetrationgrows,thismaypresentasignificantbarriertoefficientuseoftheoverallsysteminthefuture.
Currently,utilitiesdonotmonitorthereal‐timeoutputofmostcustomer‐sideDGplants.Onlysystemsabove1MWarerequiredtoinstallmeteringandtelemetrythatpermitreal‐timemonitoring.Mostcustomer‐sidesystemsarebehindthemeterandoffsetload,andasaresult,onlythenetloadisvisibletoutilities.ThelackofvisibilityinDGoutputhasnotbeenconsideredaprobleminthepast.Infact,historically,itwasthoughtthatthecosttomonitortensofthousandsofsmallersystemsdidnotjustifythebenefitsatlowpenetrationlevels.Furthermore,giventhelackofstandardcommunicationprotocolsforthevariousDGequipmentdeployed,utilitiesfinditchallengingtocollectandmakeuseofthedata.78
AsdescribedinarecentreportbyExeterAssociatesandGeneralElectric,thelackofvisibilityintoDGoperationcanbedividedintotwomainconcerns:(1)theimpactofDGonloadforecastingand(2)thepotentialforlargeamountsofDGtodropoffthegridinresponsetosystemdisturbances.79TheseconcernsincreaseasDGpenetrationincreases.
78 While smart meters are being deployed through California, all IOUs indicated that smart meters do not currently improve their ability to monitor DG systems. Currently, there is generally no communication between smart meters and customer side PV systems. There are numerous challenges to this, as explained by the utilities in recent reports to the CPUC. See http://www.cpuc.ca.gov/PUC/energy/Solar/UtilityProgramAdministratorsReportsUsingAMIForTrackingRooftopsolarGenerationJuly2012.htm. SMUD and EPRI have just begun work on a pilot program to test a low‐cost inverter‐smart meter communication approach. 79 Exeter Associates and General Electric, “PJM Renewable Integration Study. Task Report: Review of Industry Practice and Experience in the Integration of Wind and Solar Generation”, November 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐20
ForwholesaleDGsystems,thistypeofmonitoringisalreadytypicallypresent.80Forsmallersystems,SCEandSDG&Eindicatedthatvisibilityintoasystem’sstatusandproductionmaybeuseful.SDG&Eindicatedthatthisvisibilitymaypossiblyallowthemtofactoritintotheirtransmissioncapacitymargincalculations(seesection4.2.6).SCEindicatedthatmonitoringofsystems,particularlythoselargerthan250kW,isnecessary.AthigherDGpenetrations,theutilitiesmayneedtorequiremonitoringatsmallerDGsizessincesmallerunitsmayaggregatetoalargercapacityandmayhaveamoresignificantimpact.IOUsrecognizethathavingthiscapabilitywouldlikelyincreasethecomplexityoftheirsystemoperationsignificantly,butthismaybenecessaryfortheefficientandreliableoperationoftheirsystem.
Inadditiontolackofmonitoring,theutilitiesalsodonottypicallyhavecontrolcapabilitiestocurtailtheamountofenergyDGsystemsproduce.Whilesignificantimpactsduetolackofmonitoringandcontrolmaynotappearforseveralyears,itmaybeprudenttobeginconsideringoptionsaheadoftimesoastobeprepared.Germany,whichhasabout30GWofsolarPVconnectedtoitssystem,hasbeendealingwithintegrationissuesforsometime.Ithasrecentlyinstitutedrulechangesthatwillrequireretrofitof315,000olderPVinstallationstoallowvaryinglevelsofcontrol.AccordingtoExeterAssociates:
GermanyrequiresthatallDGunitsequaltoorgreaterthan100kilowatts(kW),withtheexceptionofsolarPV,beremotelyobservableanddispatchableforthetransmissionsystemoperator.SolarPVsystemslessthan100kWareexemptfromrequirementstomeasurepoweroutput.However,solarPVunitsbetween30kWand100kWarerequiredtobeabletoreduceoutputremotelyincaseofgridcongestion.Further,solarlessthan30kWmustbeabletoreduceoutputremotelyincaseofgridcongestionortoreducemaximumpowerto70%ofinstalledcapacity.81
Inadditiontolackofmonitoringandcontrol,reliablemeansofforecastingthenear‐termoutputfromDGsystemsisonlynowemerging.ForecastingofDG,andPVinparticular,maybenecessaryforintegrationofDG.Forecastingmovingcloudcoverandotherweatherchangeswillallowforimprovedcontrolandfunctionofthedistributionsystem,balancingofgenerationinacontrolarea,andmoreeconomicalunitcommitment.Ifforecastingcapabilitiesareachieved,thencontrolcapabilitiesmaybecomemorevaluabletocurtail,increaseorotherwisecontroldistributedgenerationasnecessary.
5.4.2 Modeling Tools for Integration of DG
Thereisalackofeasy‐to‐usemodelingtoolsanddatawhichallowuserssuchasutilitiestodynamicallymodelrenewableresourcesonthedistributionsysteminconjunctionwiththetransmissionsystem.Sometoolsarebeingusedtomeetcurrentneeds,butasSDG&Eindicated,theyarenotuser‐friendlyandoftenrequirespecializedpersonneltorun.Utilitieswouldprefertohavethiscapabilityinhouse.
80 Currently, telemetering requirements are imposed only on DG systems 1 MW or larger. Smaller units do not have this requirement since at lower penetrations the expectation was that the impacts would be minimal, the cost to collect the data would be relatively high, and processing of this additional data may not be necessary. This assumption should be revisited as penetration increases or the operational requirements for DG change. For example, California utilities have recently proposed telemetering requirements for certain wholesale DG systems smaller than 1 MW that will export power to be aggregated and scheduled into CAISO’s market. As of this writing, the CPUC has not yet evaluated those proposals. 81 Exeter Associates and General Electric, “PJM Renewable Integration Study. Task Report: Review of Industry Practice and Experience in the Integration of Wind and Solar Generation”, November 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐21
Inadditiontothelackofmodelingsoftware,certaininputsforthissoftwareareoftenlimited–specifically,modelsforsolarPVinvertersthatrepresentnotonlythestaticbehavior,butalsothedynamicbehavior.SCEindicatedthatinvertermanufacturerstypicallyrequestnon‐disclosureagreementswithutilitiesbeforeprovidingdetailedinformationontheirmachines.Becauseofthislimitation,utilitiesgenerallycreateinvertermodelswithseveralassumptions.Theaccuracyofthemodelsmaybelimitedbecauseofthelackofdata;andwiththelackofdata,utilitiescannotbesurethemodelingsoftwaretheyareusingisappropriate.ThelimitedaccuracycouldhinderfurtherinstallationofDG,specificallysolarPV.
ThereisnotwidespreaduseofhighDGpenetrationmodelsbydistributionandtransmissionengineers,especiallymodelsthatsimultaneouslysimulateintegratedtransmissionanddistributionsystems.TheneedforthistypeofmodelwillbecomemorepressingasthepenetrationofDGincreasesandreversepowerflowfromthedistributionsystemtothetransmissionsystemgrowsmorecommon.
5.4.3 Distribution System Design
Thedistributionsystemwasdesignedtosupplyenergyfromthetransmissionsystemtoloads.DGsystemsintroduceenergysourcesonthedistributionsystem.Becausethedistributionsystemwasnotdesignedforthisfunctionality,therearechallengeswithintegratingDGathighpenetrationlevels,especiallywhentheyarenotgeographicallyspreadoutacrossthedistributionsystem.ThisissueleadstosomeofthenegativeimpactsofDGonthegrid,suchasreversepowerflows.ApotentialbenefitofDGsystemsistoreducethenumberofsystemupgradesneeded;however,thismaynotalwaysbethecaseifDGdeploymentinaparticularareaincreasestheneedforsystemupgrades.
5.4.4 Inverter Standards
IEEE1547isavoluntarystandardforinterconnectingdistributedgenerationtothegrid.Specifically,IEEE1547addressestopicssuchasperformance,operation,testing,safety,andmaintenanceofinterconnection.IEEE1547specificallycallsforinverterstotripofflinequicklyintheeventofagriddisturbancetoavoidislandingofgenerationandotherissues.Initscurrentform,thestandarddoesnotallowfeaturessuchaslow‐voltageride‐through(LVRT),whichcouldbevaluableinhelpingmaintainsystemstabilityinthecaseofsystemdisruptions.Revisingthisaspectofthestandard,andpossiblyothers,mayallowinverterstobemore“gridfriendly”andbetteraccommodatehighDGpenetrationscenarios.Gridfriendlyinvertersmayallowbettersupportorcoordinationwiththegridregardingvoltageandfrequency.
AsnotedbyPG&E,thenationalstandards,suchasIEEE‐1547andUL‐1741arenotcurrentlycompatiblewithsomeofthedesiredinverterfeatures,suchasLVRT.WhiletheIEEE‐1547andUL‐1741wouldneedtobemodifiedtopursuetheseadvancedinverterfeatures,thenationalstandardsmaytakesometimetorevise.Therefore,Rule21wouldneedtobemodifiedinparalleltorevisingthenationalstandards.
5.5 MISCELLANEOUS Inadditiontothetechnicalandeconomicbarriersandissuesdiscussedintheprevioussections,thereareanumberwhicharelesstangibleorquantifiablebutarestillsignificantforcustomer‐sideDGdeployment.Theseissuesandbarriersincludethefollowing,andarediscussedinthesubsectionsbelow:
Processingtimesandcustomerunderstanding
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐22
Allocationoffunds
Multipleprograms
Availabilityofinstallers
Marketingandconsumereducation
Forecastingfutureinstallations
Projectsiting
5.5.1 Processing Times and Customer Understanding
AsignificantbarriertoDGdeploymentfromthecustomerordeveloper’sperspectiveistheadministrativeprocessingtimerequiredtoparticipateinDGincentiveprograms,toapplyforinterconnection,andtoobtainnecessaryinspectionsandsafetychecks.Customersanddevelopersoftencitethisasabarrierbecausethetimeandefforttocompletealltheseprocessescandiminishorevennegatetheexpectedbenefitsoftheproject.Fromtheutilityorprogramadministrator’sperspective,acloselyrelatedbarrieristhefactthatcustomersanddevelopersoftendonothavesufficientbackgroundorexperiencetocompletetheseprocessessuccessfully,andtheirlackofunderstandingcausesadministratorstospendtimeorientingthemtotheprocesses.Thistakesawaystaffresourcesfromreviewingandapprovingapplicationsforincentives,interconnection,etc.AnotherrelatedbarrieristhatDGadministratorsmaybeshort‐staffedrelativetothevolumeofapplicationsreceived,foravarietyofreasons.
5.5.2 Allocation of Funds
ExistingDGincentiveprogramsgenerallyhavetargetsorallocationsforhowmuchfundingshouldbedirectedtocertaintypesofDGinstallations.Forinstance,manyoftheprogramsattempttodividefundsevenlybetweenresidentialandnon‐residential(commercial,industrial,government,non‐profit,etc.),andmanyalsohave“carve‐outs”forlow‐incomeprojects.InthecaseoftheCSIprogram,MASHandSASHwerecreatedasentirelyseparateprogramstoensurethatadesignatedamountoffundingreachedlow‐incomeprojects.
Issuesrelatedtoallocationofprogramfundsareoftenperceivedasaproblembyparticipants,butthenatureoftheproblemdependsontheparticipant’sperspective.Low‐incomehomeownersorrentersmayseethelimitonfundingforlow‐incomeprojectsasaproblemifthereissubstantialcompetitionforthesefunds.Utilitiesmayseethedivisionoffundsbetweenresidentialandnon‐residentialprojectsasanissuepreventingefficientuseoffunds,becausesomefeelthatlargernon‐residentialprojectsareamorecost‐effectiveuseofpublicmoneythansmallerresidentialprojects,duetothelowerper‐kWcostsforlargersystems.Conversely,residentialcustomersmightviewtheallocationsforlargecommercialprojectsashinderingtheirownparticipationsincetheremainingfundsforsmallresidentialprojectsarethenmorelimited.
Totalfundingfornon‐renewableDGsystemsisgenerallylessthanthatforrenewableDG,andtheyoftenreceivealowerincentiveperkW.Sinceitislesslikelytobeinstalled,thismaybeconsideredanissuespecificallyfornon‐renewableDG.
5.5.3 Multiple Programs
Section3.0ofthisreportdescribesanumberofdifferentprogramssupportingDGinCalifornia.Theproliferationoftheseprogramsmaybeanissuetosomedegreeinitself.Fromacustomerorprojectdeveloper’sperspective,theremaybeconfusionabouttheprogram(s)forwhichtheirprojectiseligible.Thiscanleadtoprojectdelaysinsomecases,andalsotofrustrationonthe
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐23
customer’sordeveloper’spart.Fromautilityorprogramadministrator’sperspective,theremaybedifficultyduetolimitedfinancialorstaffresources,suchthatitisnotefficienttoadministeranumberofdifferentprograms.However,DGprogrammanagersdidindicatethatthiswasnotamajorconcernforutilitiesindeployingDG,andthatthearrayofdifferentDGprogramswasappropriatebecauseeachistargetedatadifferentprojecttypeorcustomersegment.Theirmainconcernwasthattheyspendasignificantamountofstafftimeeducatingcustomers,installers,anddeveloperswhoareunfamiliarwiththemultitudeofprograms.
5.5.4 Availability of Installers
Inordertodeploycustomer‐sideDG,skilledandexperiencedinstallersmustbeavailabletosupportvoluntaryDGinstallations.TherateofDGdeploymentdependsinpartontheavailabilityofinstallers,andalackofinstallersinthepastconstitutedabarriertogreaterdeployment.Ingeneral,utilityrepresentativesagreedthatalackofDGinstallersmayhavebeenaproblempreviously,butthatitisnotawidespreadbarriernowbecausethevolumeofinstallationsandinstallershasrisendramaticallyandsohasthenumberandcoverageofexistinginstallers.Intheopinionofutilityrepresentatives,competentinstallersarenowavailableinmostpartsofCalifornia.
5.5.5 Marketing and Consumer Education
BecauseDGinstallationsarevoluntary,customersmustfirstbeawareofDGasanoptionfortheirelectricneeds,andalsoseeitasapotentiallybeneficialoption—intermsofeconomiccost,environmentalimpact,energyindependence,localjobcreation,orsomecombinationofthese.DGincentiveprogrammanagersconfirmedthatthisissuehasbeenandcontinuestobeabarrierforgreaterDGdeploymentinCalifornia,thoughitisnotconsideredsignificantenoughtodaytobelistedasakeybarrier.ThegeneralpublicismuchmoreawareofDGtechnologiesandtheirbenefitsnowthanwasthecaseafewyearsago,duelargelytothefundingandeffortsofthestate’sDGprogramsaswellastheeffortsofinstallersthemselves,whoperformasubstantialamountofmarketingandconsumereducationaspartoftheirsalesprocess.However,moreinvestmentinmarketingandeducationofconsumerswouldlikelyreducethisparticularbarrierfurther.
Therearealsoopportunitiesforbettertargetingofsuchmarketingandeducationefforts,butmanyofthesewouldrequireinformationsharingbetweenentities.Forexample,CCSEadministerstheCSIandSGIPprogramsinSDG&E’sserviceterritory,andalsoleadsmarketingfortheseDGprogramstoSDG&Ecustomers.However,CCSEdoesnothaveaccesstospecificcustomerinformationwhichcouldhelpittotargetitsmarketingtowardthosecustomersmostlikelytoadoptDG,e.g.higherincomecustomers,customerswithrelativelyhighusage,customersondistributioncircuitswithsignificantexcesscapacity,etc.
5.5.6 Forecasting Future DG Installations
TheabilityorinabilitytoforecastfutureDGinstallationsisanissueforutilitiesandprogramadministrators.Programadministratorsneedsuchforecastsofinstallationstoallocatefinancialandstaffresourcesandplanforfuturechangesinbudgetorstaffinglevels.WhentheforecastsareinaccurateitcanleadtoinsufficientresourcesandthereforebacklogsinDGapplicationprocessing.UtilitydistributionplanningprocessesshouldhaveforecastsoffutureDGinstallationsandoutputtodesigntheirsystems.AsDGinstallationsincrease,inaccurateforecastscouldimpactthegrowthofthedistributionsystemsuchthatappropriateinfrastructureisnotavailabletoaccommodategrowthofDGinstallationsinthemostcost‐effectivemanner.Programadministratorsindicatedthatshort‐termDGinstallationforecastshavebecomerelativelyreliablebasedonanalysisofrecentinstallationtrends,butthatlong‐termforecastsaremuchlessreliablebecauseofthevarietyofpolicyandmarketfactorsaffectingDGdeploymentandtherapidpaceatwhichtheychange.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐24
Overall,theyclaimedthatlong‐termforecastingisnotyetasubstantialissue.However,utilitydistributionengineersdidseethisasapotentiallysignificantissueforfutureDGexpansion,althoughithasnotmanifestedtoalargeextentyet.
5.5.7 Project Siting
ThereareseveralaspectsofsitingaDGprojectthatcouldconstituteabarriertofurtherdeploymentofDG.Ithasbeenestimatedthatupto75percentofelectriccustomersdonothavetheabilitytoinstallsolarPVontheirownproperty.82Thereareavarietyofreasonsforthis,including:1)residentialandcommercialrentersoftendonothavethenecessaryauthoritytoinstallpermanentequipmentlikeaPVsystem,2)manyhomesarelocatedinareaswithinadequateresources(e.g.,toomuchshade)orinfrastructure(roofswithanon‐optimalorientation),3)non‐taxableentitiescannottakeadvantageoftheITCorothertaxbenefitsavailableforPV,and4)avarietyofcustomersdonothavethetimeorfinancialcapacitytoinstallPV.Allofthesebarriersapplyinprincipletonon‐solartypesofDGaswell.PG&EindicatedthatDGtechnologiesotherthansolar,suchaswind,areactuallymuchmorecomplexandlesscommon,whichcanbeabarrierforcustomerstositeandsuccessfullyinstallduetotherelativelackoftechnicalexpertise,potentialcommunityreaction,andquestionsfrompermittingauthorities.
Apotentialsolutiontothisbarrieristheuseofvirtualnetmetering,whichallowsmultiplecustomerstoobtainbillcreditforelectricityproducedatanothersiteandcountittowardtheirownelectricityconsumption.IntheU.S.,virtualnetmeteringarrangementsareoftenusedby“communitysolar”projects(whenthepowerisgeneratedbysolarPV),whichreferstoarangeofprogramandprojecttypesthatallowgroupsofcustomerstoreceivebenefitsfromasinglesolardevelopment.ThesamestructurehasbeenusedinotherpartsoftheU.S.andEuropeforsmall‐scalewindsystems.Communitysolarprojectscanbebuiltandfinancedbyindependentdevelopers,inwhichcasethearrangementcanbesimilartoathird‐partysolarleaseorpowerpurchaseagreement,orbyutilities,whichcanoffercustomerstheabilitytodirectlypurchaseaportionoftheproject’soutputortoparticipateina“solarrate”.Theseprojectshavethepotentialtotakeadvantageofbettersites(intermsofresource,easeofinterconnection,publicvisibility,etc.),toreducecoststhrougheconomiesofscale,toeliminatethecustomer’sresponsibilityforfinancingcostsoroperationsandmaintenance,tofacilitateparticipationforthosecustomerswhocouldnototherwisebuildsolarPV,andtoenablecustomerstocontinuebenefitingfromtheprojecteveniftheymove.83
However,itshouldbenotedthatmanyofthesamecostallocationconcernsthatapplytoregularNEMinstallationsalsoapplytovirtualNEMarrangements—customersparticipatinginavirtualNEMarrangementmayreceiveasubsidyfromotherratepayers.
5.6 KEY ISSUES AND BARRIERS CaliforniahasmadesignificantprogressaddressingissuesandbarriersrelatedtoDG.Manyoftheissuesandbarrierslistedinthissectionhavebeenatleastpartiallyaddressed,andtheindustryandregulatorsareworkingonmanyothers.TheissuesandbarriersdescribedinthissectionmaylimitorotherwiseaffectthedeploymentofDG,andseveralofthemimpacttheabilitytoreceivethetoutedbenefitsofDG.Thekeyissuesandbarriersidentifiedinthisreportarelistedbelow.
82 The Vote Solar Initiative, “Community Shared Solar: Bringing Solar to the Masses,” presentation by Hannah Masterjohn, July 2012. 83 Solar Electric Power Association, “Utility Community Solar Programs,” presentation by Bianca Barth, July 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Issues and Barriers Impacting DG Deployment 5‐25
Table 5‐3 Key Remaining Issues and Barriers for Customer‐side DG
Financing and Economics
• EquipmentandsoftcostsofDGarehighcomparedtogridelectricity.• Availabilityofgovernmentandutilityfinancialincentivesisbecomingmorelimitedbecausefundsfor
incentiveprogramsaredeclining.
Policy and Regulatory
• PublicresistancetoDGcoulddevelopifnon‐DGcustomersareexcessivelyburdenedwithcoststosubsidizeNEMDGcustomers.
• ThereisalackofincentivestolocateDGinareaswiththegreatestbenefittothegrid;needtoadoptamoretargetedapproach.
Integration
• Lackofmonitoring,forecastingandcontrolcapabilitieslimitstheutilities’abilitytomanageDGintegrationintothedistributionsystem,andabilitytorelyonDGcapacity.
• LackofcapabilitiesintegratingDG(especiallysolarPV)withdistributionandtransmissionmodels.Thisaffectstheutilities’abilitiestoaccuratelysimulateandplanforDG.
• Distributionsystemdesignisnotintendedforinjectionofgenerationleadingtovoltageissues,reversepowerflow,etc.ThisissuewillbecomemorewidespreadasDGpenetrationincreases.
• Inverterstandardsmayneedtobechangedtoallowbettersupportofthegrid.
Miscellaneous
• ProcessingtimesandadministrativedelaysforincentiveapplicationsandinterconnectionapplicationsreducethespeedatwhichDGcanbedeployed.
• LackofsuitableprojectsitespreventsthemajorityofutilitycustomersfrominstallingDGontheirownproperty.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐1
6.0 Emerging Technologies AlargeamountofresearchanddevelopmentisbeingdoneonemergingtechnologieswhichmayalleviatesomeofthenegativeimpactsandbarrierstogreaterDGdeployment.Themajortechnologiesbeingdevelopedinclude:
Smartinverters
Energystorage
Advancedgridmanagement/smartgridtechnologies
Microgridtechnologies
Thissectiondiscusseseachofthesetechnologiesandtheirpotentialbenefits.
Thedeploymenttimeframeofthesetechnologiesvaries.Therearenumberofdemonstrationprojectscompletedorunderway.GreaterappreciationoftheneedforthesetechnologieswillfollowanincreaseddeploymentofDGsystemsandidentificationofthetechnicalproblemsthatthesenewtechnologiesmaybeabletoresolve.Itisnotknownwhetherthe“tippingpoint”atwhichthesetechnologieswillbecomebeneficial,orevenessential,willoccurwithinthenext1to3yearsorthenext5to10years.However,giventherapidpaceofDGdeploymentinCalifornia,itisreasonabletoproactivelydemonstrateanddeploytheemergingtechnologieswiththegreatestpotentialbenefits.
AlthoughthestatehostsanumberofDGtechnologies,thevastmajorityofDGinCaliforniaissolarPV.SolarPVandwindDGbothhaveissuesassociatedwiththeirvariability,buttheamountofwindDGisverysmallcomparedtosolarPV.OtherDGtechnologiessuchasfuelcellsandinternalcombustionenginesdonotposeallofthesamechallengesasvariablegenerationlikePV.Theyhavetheabilitytobedispatchable,althoughthereiscurrentlynoprocesstoenabledispatchbytheutility.84Thus,becauseofitsdeploymentshareandthecomplexityofissuesassociatedwithvariablegeneration,thissectionwillfocusonemergingtechnologiesrelatedtosolarPV.
6.1 SMART INVERTERS Theinverteristhe“gatekeeper”ofsolarpower,whetherfeddirectlytoanenduser,toanenergystoragesystem,orthroughaninterconnectionontothegrid.Forgridinterconnections,nextgenerationinverters,orsmartinverters,aremachinesthathavespecialfunctionsdesignedtoremedygridfaultsandprotectthequalityofgridpowerbyminimizingtheirimpacttothegrid.Theyareusedforutility‐scalesolarPVsystemsinNorthAmericaandbothutility‐scaleandlargedistributedsolarPVsystemsinGermany.85
Thepotentialforsmartinvertersissignificant.Studieshaveshownthattheymaybeabletomitigatevoltageissuesandincreasethegrid’scapabilitytoaccommodatePVsignificantly.86Smartinvertersmightprovidemanyadvancesincluding:
84 Despite the fact these technologies are more firm than variable renewables, these types of DG systems are typically baseload rather than having dispatch agreements with the utility. This makes it difficult for the utility to curtail these units even during system emergencies. 85 Notholt, “Germany’s New Code for Generation Plants connected to Medium‐Voltage Networks and its Repercussion on Inverter Control”, European Association for the Development of Renewable Energies, Environment and Power Quality, April 2009. 86 Braun, et al., “Is the distribution grid ready to accept large‐scale photovoltaic deployment? State of the art, progress, and future prospects”, Progress in Photovoltaics: Research and Applications, 2010.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐2
Remotemonitoring
Voltageregulation
VArcontrol
Lowvoltageandlowfrequencyride‐through
Rampratecontrol
Curtailmentability
Thesesmartinverterfeatureswouldbeusedincombinationwithdistributedcommunicationinfrastructurestomanagesolarpowerinjectedintodistributionsystemsinamannerthatiscoordinatedamongsolarpowerandconventionalgenerationsources.Theresultcouldbeastrengtheningofdistributionsystemsthroughtheuseofreactivepowertoregulatevoltagealongdistributionfeeders.
Currently,smartinvertersarenotcodecompliantforusewithdistributedPVsystemsintheUnitedStates.Nationalstandards,IEEE‐1547andUL‐1741donotcomportwithmanyofthesmartinverterfeaturesmentioned.However,thesestandardsarevoluntarybyutilitiesandcouldbedecoupledfromRule21toallowuseofsmartinvertersinCalifornia.TheStatecouldwaitfornationalstandardstoberevised,buttheprocessmaytakeyears.Accordingtocode,DGinvertersmustdisconnectfromthegridforfiveminuteswhentheysenseaproblemwiththequalityofgridpowerandnotreconnectuntiltheproblemisresolved.TheintentionofthisrequirementisforPVsystemstobetakenofflinesothegridcanrecoveronitsown.Codealsorequiresthatinvertersdisconnectfromthegridduringpoweroutagestopreventsolarpowerfromharminglinemen.
Inhigh‐penetrationPVscenarios,someresearchersbelievethecurrentU.S.coderequirementscouldcausecascadedisconnectsoflargeswathsofPVsystemsduringgridfaultsandthusexacerbategridinstability.87Smartinvertershavetheabilitytopreventthisbystayingconnectedand“ridingthrough”momentarygridfaults(discussedfurtherinSection4.1.5).Theycanalsoprovidevoltagesupporttothegridduringfaults,thusstrengtheningpowerqualityandthereliabilityofthegrid.Thepowerindustrycallsthistypeofgridsupport“ancillaryservices”.Somesmartinverterscanprovideancillaryservicesatnightinadditiontoduringtheday.
Rampingdownsolarpowersmoothlytoreducesolarpowervariabilityisanotherfeatureassociatedwithsmartinverters.However,smartinvertersalonearenotcapableoframpingdownindividualsolarpowersystems.Energystorageand/oraccuratesolarresourceforecastingcombinedwithautomatedpowercurtailmentarealsoneeded.
Itisimportanttonotethatsmartinverterfeaturesdonotcomewithoutadditionalcost.Thisadditionalcostcouldbequitelargedependingoncommunicationsrequirements(suchasrunninganewfiberopticline)orifenergystorageisincluded.Therefore,smartinvertersarenotasolutiontoallDGissues,andtheircostsmustbeweighedagainstthecostofothermeanstosupporthigherpenetrationPVsuchasreplacingdistributionlineconductors,installingcapacitorbanksinsubstations,etc.
Giventheirreactiveandremedialcapabilities,smartinvertershavegreatpotential;however,therearesignificantchallengestousingsmartinvertersforDG.Inadditiontotheaforementionedstandardsandcostchallengesisthedevelopmentofadistributedcommunicationinfrastructuretosignaltheinverterstodisconnectwhendistributionlinesareseveredorwhengridoperatorsissue 87 “Solar Energy Grid Integration Systems (SEGIS) Program Concept Paper”, US DOE EERE/Sandia, October, 2007.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐3
acommand.Also,aprotocolmayneedtobedevelopedtocoordinatetheoperationofallthesmartinverterssothattheywillworktogetherproperly.Toaddressthecommunicationschallenge,severalsolutionsarebeingexplored:
AsolutionhasbeendemonstratedatLakelandElectricinFloridabySatcon,aninvertermanufacturer,incollaborationwithCooperPowerSystemsandtheFloridaSolarEnergyCenter.ThedemonstrationwaspartoftheDOE’sSolarEnergyGridIntegrationSystemstechnologyaccelerationprogram,usingatechnologycalledpowerlinecommunications.88
Anotherpossibility,mentionedduringBlack&Veatch’sinterviewswiththeutilities,isforutilitiestocontrolinvertersthroughsmartmetersviaZigBeeoranotherwirelesscommunicationprotocol;however,untilthePVindustryhasanapprovedZigBeeinverterprotocolforSmartInverters,thisoptionisnottechnicallyfeasible.
Athirdoptionistoinstituteautonomousorpre‐setfunctionalitiesforsmartinverterstoperforminresponsetocertainvoltageconditions,thusrequiringnocontrolbytheutility.Asnotedinthisreport,thisoptionisbeingexaminedinPhase2oftheCPUC’sinterconnectionproceeding.
Finally,anotherchallengeforsmartinvertersisthatutilitiesarenotrequiredtopayallcustomersfortheancillaryservicestheycouldprovideforgridsupport,especiallyiftheinverterisbehindthecustomer’smeter.
Asnotedabove,theintroductionofautonomoussmartinverterfunctionalitiesoncertainDGsystemsisincludedinPhase2oftheCPUC’sinterconnectionproceeding.
6.2 ENERGY STORAGE Energystoragedevicessuchasbatteries,flywheels,compressedair,ultra‐capacitors,andpumpedstoragehydro,canalsoaidinaccommodatingtheintegrationofvariableDGresourcesintothegrid.WhenPVgenerationdrops,storagedevicescanbebroughtonlinetomitigateoutputswings,toprovidesmoothingorfirming,andtoserveloaduntilotherreservescanbebroughtonline.89Storagetechnologieshavedifferentcharacteristics(suchasstoragecapacity,dischargedurationandcost)thatmakethemmoreorlesssuitedforparticularapplications.Ingeneral,theenergystoragetechnologiesaregroupedintopowerandenergyapplications.Belowaresomepotentialenergystoragesolutionsgroupedbydischargeduration,orenergy,capabilities:
ShortDuration(batteries,flywheel,ultra‐capacitor)
MediumDuration(batteries)
LongDuration(pumpedstorage,compressedairstorage)
88 “Solar Energy Grid Integration Systems: Final Report of the Florida Solar Energy Center Team”, SANDIA REPORT SAND2012‐1395, March 2012. 89 It is also noteworthy that curtailing inverters in advance of steep declines in solar resource using accurate weather forecasting may reduce energy storage capacity required.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐4
Figure 6‐1 Energy Storage Discharge Time and Rated Power Graph90
Energystoragetechnologiescanspanawiderangeofpowercapabilitiesaswell.Figure6‐1aboveisagraphicalrepresentationofpowerandenergycapabilitiesofenergystoragetechnologiescompiledbytheElectricityStorageAssociation(ESA).
Oftheseoptions,batteriesaremostoftendeployedwithPV.Leadacidbatterieshavebeenusedwithoff‐gridPVsystemsfordecades,butarerareamonggrid‐connectedsystems.However,batteriesarenowbeingdemonstratedtoreducethevariabilityofsolarpower,providerampratecontrol,provideancillaryservicessupporttothegrid,improvepowerquality,andforloadshifting—i.e.storingelectricitygeneratedduringoff‐peaktimesandusingitduringpeaktimes.91Batteriesarealsousedincombinationwithothertechnologiestoprovidecontinuoussupportforfacilitiesduringgridoutagesinsystemssometimesreferredtoasmicrogrids,describedlaterinthissection.
Theprincipaltwoimpedimentstobatteriesandotherenergystoragetechnologiesare(1)theirrelativelyhighcosts(exacerbatedbyarelativelackofcostdatapubliclyavailable)and(2)inabilitytofitintoexistingregulatoryandoperationalframeworkthatmakestakingadvantageofmultiplebenefitsfromasinglelocationdifficult.Regulators,includingFERCandtheCPUC,havebeguntorecognizethatenergystoragetechnologiesrequirespecialconsiderationandtomodifytheappropriateproductandcompensationrules.Infact,duetoAssemblyBill2514,theCPUCiscurrentlyconsideringwhethertoimplementspecificprocurementtargetsforenergystoragein
90 Electricity Storage Association 91 “Solar Energy Grid Integration Systems –Energy Storage (SEGIS‐ES) Program Concept Paper”, DOE EERE and Sandia, May 2008.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐5
Californiabyutility,toacceleratedeploymentanddecreasecoststhrougheconomiesofscale.92CAISOhasalsobegunconsideringaprocessforenergystoragetoparticipateintheCAISOwholesalemarket,asdiscussedinSection5.3.3.Inaddition,meteringandmonitoringprotocolsforenergystoragearestillbeingrefined.
Researchersarealsoworkingtobringdownthecostofbatterieswhileimprovingtheirperformancethroughtechnologicalinnovations.Recentadvancesinbatterytechnologieshavebeendrivenbymobileelectronicsandelectricvehicles.LeadacidbatteriesarethetraditionalcomplementtosolarPVsystems,butlithiumionbatterieswithuniquecathode,anodeandproprietaryelectrochemicalvariantsarequicklybecomingpopularoptions.Today’sresearchislargelyfocusedonincreasingtheenergydensityofbatterieswhiledrivingdownthebatterycostandimprovingbatterysafety.Onebatteryoptionunderdevelopmentthatshowspotentialforimprovingtheenergydensityofbatteriesisthezinc‐airbattery.Zinc‐airbatteriesmaybelessexpensivethanlithiumion,andlesstoxicandlighterthanlead‐acidbatteries.Additionally,lithium‐sulfurandlithium‐airbatteriescouldfurtheradvancethebatteryenergydensitybyemployingnanostructuresandnovelelectrodecombinations.93
Energystoragedevicesdonotnecessarilyneedtobeco‐locatedwithPV.Theycouldbewidelydistributedacrossthegridtomeetmultipleneedsindifferentapplicationsatvariousscales—fromlargecentralizedstoragedevicesatsubstations,tocommunityenergystoragedevicesondistributionfeeders,tosmalldevicesatindividualhomes(seeFigure6‐2).Forexample,larger,centralizedenergystoragesystemsdeployedforcommercialpurposesarebeingtestedtoshavepeakloadandcouldbeusedtofirmsolarpower.94,95Centralenergystoragesystemsincludebothmetalionvarietiesandflowbatteries,devicesthatuseelectrolyticfluidstostoreenergy.Batteriesinelectricvehiclesarealsobeingconsideredasanenergystoragecomponent.Thoughtheappropriateinfrastructurewouldneedtobedeveloped,theycouldbeusedtofirmsolarpowerandreducepeakloads.96Understandingtheoptimummixoftechnologiesandtheirplacementisachallengeforthefuturecost‐effectivedeploymentofenergystorage.Inaddition,moreresearchisneededontherampingresponsivenessofvarioustypesofstoragetodeterminewhetheritcouldbewidelydeployedacrossthegridtomeetmultipleneedsindifferentapplicationsatvariousscales—fromlargecentralizedstoragedevicesatsubstations,tocommunityenergystoragedevicesondistributionfeeders,tosmalldevicesatindividualhomes.
92 E. Wesoff, “California Energy Storage Bill AB 2514 Signed Into Law by Governor,” Greentech Media, Sept. 2010. http://www.greentechmedia.com/articles/read/vc‐cmeas‐gunderson‐on‐utility‐scale‐storage/. The CPUC’s storage proceeding is Order Instituting Rulemaking Pursuant to Assembly Bill 2514 to Consider the Adoption of Procurement Targets for Viable and Cost‐Effective Energy Storage Systems, R.10‐12‐007, Issued December 21, 2010. 93 Yang, Y. McDowell, M. Jackson, A. Cha, J. Sae Hong, S. Nano Lett. 2010, 10. 1486‐1491. 94 “Public Interest Energy Research (PIER) Program Final Project Report, Demonstration of ZBB Energy Storage Systems”, July 2012. 95 “Energy Storage Shaping the Future of California’s Electric Power System”, California Energy Storage Alliance (CESA) and Strategen, Intersolar, June 2011. 96 “Vehicle‐To‐Grid Technology Gains Some Traction”, New York Times, July 22, 2009.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐6
Figure 6‐2 Potential Applications of Energy Storage (Black & Veatch)
6.3 ADVANCED GRID MANAGEMENT / SMART GRID TECHNOLOGIES Asmentionedpreviously,thevariablegenerationofsolarPVsystemsmayimpactnormalgridoperations.Gridoperatorsareconstantlyworkingtobalancesupplyanddemandonthegrid.Theymustmaintainpowerqualitybyregulatingvoltage,current,andfrequency.SmartgridtechnologieswouldallowincreasedawarenessandcontrolofthedistributionsystemandmayenablesolutionstomanyDGintegrationissues.SmartinvertersforDGonthecustomersidehavethepotentialtocomplementsmartgridtechnologiesontheutilitysideofthedistributionsystem,andsmartgridtechnologiescanalsosupporttheuseofenergystorage.
AnumberofeffortsintheareasofsmartgridinfrastructureareunderwaytoprepareforhighpenetrationDGPV(Figure6‐3).Thissectiondescribessomepotentialsmartgridsolutions.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐7
Figure 6‐3 Emerging Smart Grid Infrastructure in Support of High Penetration DG PV
EnhancedVoltageMeasurementandAutomatedControl–Voltageregulationisacorefunctionofutilityoperations,butDGhasthepotentialtomakevoltageregulationsignificantlymoredifficult.However,widespreaddeploymentofadvancedmeteringinfrastructure(AMI),or“smartmeters,”hascreatedanewtechnologyenablerthatcanimprovevoltagecontroleffectivenessandhelpmitigatesomeoftheissuesrelatedtoDG.SmartgridandAMIsystemshavelaidthefoundationforimprovedvoltagemanagementbyprovidingreliable,two‐waycommunicationsbetweennumerousfielddevices.Intelligentelectronicdevices(IEDs)incombinationwithsubstation/feedercontrolornewcentralizeddistributionmanagementsystems(DMS)canmeasurevoltagefromeverygridendpointandprovideimprovedvoltagecontrols.SystemssuchasAdvancedVoltVArControl(AVVC)canallowenhancedcontrolofvoltageandVArflow.AVVCallowsamoreefficientuseoffieldcapacitorbanksandotherequipmenttooptimizepowerflow.
LoadControl–Directloadcontrolallowsutilitiestoturnonandoffcertainloads(i.e.facilities,equipment,appliances,etc.)duringcertainperiodswhenelectricitydemandishigh,orwhenintermittentdistributedgenerationrampsupordownsuddenly.Thiscanenableutilitiestomanageandoptimizeanincreasinglydynamicelectricpowergridonwhichpowerisinjectedatdistributedlocationsthroughoutthesystem.
Re‐Sectionalizing–Gridre‐sectionalizinginvolvestheautomaticreroutingofpowerfromonepartofthegridtoanother.Asthedistributionsystembecomesmoredynamic,andvariableDGsourcesareaddedinlargequantities,itwillbeimportantforutilitiestobeabletomanagepowerflowandvoltageamongdifferentsectionsofthegrid.Widespreaduseof
Solar PowerEnergy Storage
Demand Response
Time of Use Pricing Data
Generation & Load
ForecastingData
Central Generation Balancing
SCADA:Supervisory Control & Data
Acquisition
Central Energy Storage Balancing
Distributed GenerationHomes & Buildings
Central GenerationCAISO & Utilities
Emerging Smart Grid Infrastructure in Support of High Penetration DG PV
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐8
automatedswitchingsystemswillbeanimportantcomponentofthissolution.Thefigurebelowillustratesanexampleofre‐sectionalizing.
Figure 6‐4 Re‐sectionalization Example
DistributionManagementSystem(DMS)–DMSisanintegrateddecisionsupportsystemwherebyalloperationalaspectsoftheutility’sdistributionsystemaremadevisibleandoperablefromacentralsource.Advancedalgorithmsareusedtooptimizethesysteminreal‐timebasedonvaluesprovidedbyAMIandsupervisorycontrolanddataacquisition(SCADA)systems.ADMScanbeenhancedwithcentralizedvolt/VARoptimization(VVO)basedonanon‐linepowersystemmodel.97ImplementingaDMSwithVVOisamajorinitiativethatcouldtakemultipleyearstocomplete;however,ithasmanybroadbenefits.ForintegrationofDG,aDMScanhelpautilitymaximizeitsmultipledistributedenergyresourcestakingintoaccountloadforecasts,weatherforecasts,DGoutputforecasts,electricvehicles,andstorage.Thisincludeshandlingresourcedispatching,initiatingdemandresponseprograms,verifyingandvalidatingactivedemandresponseprograms,mitigatingvoltageissues,andmanaginganetworkedpowersystemgridwithbi‐directionalflows.Ifcommunicationprotocolsareharmonized,aDMScouldalsoprovidedirectcommunicationwithDGsmartinvertersthatwouldfurtherenhancegridoperations.
Smartgridtechnology,andtheadvancedgridmanagementsolutionsthatitenables,isanemergingfield.Additionalsmartgridtechnologiesnotcoveredheremayhelpaddressotherchallengesinthefuture.
6.4 MICROGRIDS Onesubsetoftheemergingsmartgridinfrastructureis“microgrids,”whichcouldbeparticularlyimportantforgridintegrationofDGinthefuture.Amicrogridisasmallpowersystemthatincorporatesself‐generation,distribution,sensors,energystorage,andenergymanagementsoftwarewithaseamlessandsynchronizedconnectiontoautilitypowersystem.98Amicrogridcan
97 VVO is a method of optimizing distribution power delivery, which utilizes distribution automation, SCADA, and AMI to reduce energy consumption and peak energy capacity demand by improving system power factor. VVO is based on sophisticated algorithms and logic from the on‐line power flow application, which is another application within the DMS suite. 98 http://www.smartgridlibrary.com/
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐9
operateinparallelwiththeutilityorindependentlyasanislandfromthatsystem.Itspurposeistoincreasereliabilityforcustomerswithinthemicrogridbymaintainingpowerevenwhentheutilitygridisexperiencinganoutage,andalsotoallowlocalizedcontrolofenergyinfrastructure.Theoretically,microgridscanalsosupportthelargerutilitygridbydecreasinglocalloadandsafelyexportingpowerattimeswhentheutilitygridisstressed.Inaddition,microgridshavethepotentialtoprovideanumberofserviceswhichwouldenablegreaterDGpenetration:
Seamlessbidirectionalenergyflow
Voltage,frequencyandVARcontrol
Eliminationofmomentaryoutagesassociatedwithtypicalstandby/backuppowersystems
Pricedrivenloadmanagement,i.e.demandresponsebasedondynamicpricesignals
Self‐healingnetworksthroughintegrationoffeederautomation
Morerobustcommunicationandcontrolofthedistributionsystem
Anumberofutilities—includingSDG&EandSMUD—areinvestigatingthecostsandbenefitsofmicrogridsthroughdemonstrationprojects,usuallyfundedbygrantsfromtheU.S.DOEandtheCEC.SDG&EhassignificantmicrogridprojectsoperatingwithinitsserviceterritorywhichincorporateDGasoneofthecorecomponents:
1) UniversityofCaliforniaSanDiego(UCSD)Microgrid:TheUCSDcampushasinvestedsignificantresourcesintyingtogetherdistributedPVresources,abiogasfuelcell,andanaturalgascentralcogenerationplantwithresponsiveloadsincampusbuildingsthroughanincreasinglysophisticatedcentralcontrolsystem.Itisclaimedthattheflexibilityofthis42MWmicrogridallowsthecampustosavesignificantamountsofmoneyonitsutilitybillsannually,andprovidesupto85percentofcampuselectricity.Also,UCSDhasbeenabletoreduceitslocalloadsandexportpowertotheSDG&EgridduringemergenciessuchastheblackoutofSeptember2011andthewildfiresof2009.99Thecampuswasabletoswitchfromimporting3MWofpowertoexporting2MWofpowerwithin30minutesduringthe2009incidentandtherebyprovidecriticalsupporttothelargergrid.100TheUCSDmicrogridisanevolvingandongoingproject,fundedbytheuniversity,andwillcontinuefortheforeseeablefuture.101
2) BorregoSpringsMicrogridProject:ThisprojectintheSanDiegoareaisdesignedasapilot‐scaleproofofconceptofhowinformation‐basedtechnologiesanddistributedenergyresourcesmayincreaseutilityassetutilizationandreliability,includingcontributionsfromanumberoforganizationsandvendors(IBM,HorizonEnergyGroup,Motorola,PacificNorthwestNationalLabs,Oracle,AdvancedEnergyStorage,UniversityofSanDiego,LockheedMartin,GridPoint,andXanthus).Itsgoalsareto:1)reducefeederpeakloadbymorethan15percentthroughDG,energystorageandloadmanagement;2)demonstrateVARmanagement;and3)developandtestavarietyofdistributionmanagementsystemsandcapabilities—e.g.,advancedmeteringinfrastructure,outagemanagementsystems,feederautomationtechnologies,pricedrivenloadmanagement,andintentionalislanding.Itincorporatesawidevarietyofcustomer‐sidetechnologies,includingrooftopsolarPV,batterystorage,grid‐friendlyappliances,demandresponsethroughremote‐controlledthermostats,andplug‐inhybridelectricvehicles.ThesmalltownofBorregoSprings,eastof
99 http://blog.rmi.org/the_ucsd_microgrid_showing_the_future_of_electricity_today 100 http://www.rmi.org/nations_largest_microgrid_online_esj_article 101 http://sustainability.ucsd.edu/initiatives/energy‐production.html
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Emerging Technologies 6‐10
SanDiego,alreadyhadalargeamountofsolarPVinstalledevenbeforethismicrogridprojectbegan.Theprojectincludesthreedifferenttypesofbatteryenergystorage(alargebatteryatthesubstation,threemedium‐sizedbatteriesonadistributionfeeder,andsixsmallbatteriesatindividualhomes);amicrogridyardatthesubstationwithdieselgenerators,transformers,aSCADAswitch,andacontrolvan;homeareanetworkscapableofrespondingtopricesignalsandreliabilityevents,withsmartappliancesthroughoutthehome;andasignificantamountofdistributedPVthroughoutthecommunity.ThemicrogridwillbeownedbySDG&E.Thisprojectisbilledasthefirstlarge‐scaleutility‐ownedmicrogridintheU.S.,withthegoalofprovinganalternativeservicedeliverymodel,islandingrealcustomers,andestablishingatemplateforotherutilitiestofollow.Designandplanningbeganin2010andtheprojectisexpectedtobecompletedin2013.102
Mostmicrogridprojectstodayinvolvesomedegreeofretrofittoexistingdistributionsystems,andalsoincorporateawiderangeofnewtechnologiesandsoftwareforresearchpurposes.Thus,thereislimiteddataonthecostsofnewcommercialmicrogridsimplementedinrealsettingswithonlythetechnologyneededfortheparticularlocationinquestion.However,gatheringfurtherdataoncommercialmicrogridcostswouldbeusefulfromtheperspectiveofunderstandingthecostofintegratingDG,sincemanyofthefeaturesofmicrogridsmaybenecessaryinfuturedistributionsystemswithhighpenetrationsofDG.
102 SDG&E, “SDG&E Borrego Springs Microgrid Demonstration Project,” presentation by Thomas Bialek, June 2012.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Recommendations for Future Study 7‐1
7.0 Recommendations for Future Study DistributedgenerationdeploymentontheCaliforniadistributionsystemhasbeenincreasingoverthepastseveralyears.Withthisincrease,thereareseveralunknowns.WhilethisreportdescribesmanyoftheimpactsofDG,nearlyalloftheinformationisqualitativeandbasedonlimitedobservations.ThereismuchtobegainedfromamoredetailedandquantitativeinvestigationofthecurrentandfutureimpactsofDGontheelectricgridoftheIOUsinCalifornia.Suchaninvestigationshouldrelyon“real‐world”fielddatatotheextentpossible.QuantificationofDGimpactsisvitallyimportanttotheDGindustry,utilitiesandpolicymakers.ItwillinformdecisionsthatseektofurtherDGgoalswhileminimizingthenegativeimpactsofDGandmaximizingitsbenefits.
Black&Veatchhasdetailedascopeforsuchastudy,includedinAppendixC.Insummary,thistypeofinvestigationwouldaddressthefollowingquestions:
HowisDGaffectingthedistributionandtransmissionsystemcurrently,andhowwillthischangeinthefuture?
HowmuchmoreDGcouldbedeployedonthesystemifsitingwereoptimizedforminimalimpactsandenhancedbenefits?
Whatadditionaltoolsareneededtoidentifyoptimallocation,type,andtimingofDG?
Howcananenhancedunderstandingofthecostsofdifferentimpacts,benefitsandsolutionshelpinformeffectivepolicytoenablethedeploymentofmoreDG?
HowcouldthedeploymentofmoreDGbebeneficial?Ifdeployedineffectively,howcoulditbedeleterious?
AnsweringthesequestionscanhelpcreateaclearroadmapofthegrowthpotentialofDGandenableCaliforniatoanticipatepotentialchallengestoDGdeployment.Acomprehensivestudycanhelpanswerthequestionsbysummarizingtheanalysisthathasbeendonetodate,analyzingtheavailabledataforexistingsystems,andforecastingimpactsoffuturegrowth.
Suchananalysisshouldstudythefiveprimarysectionslistedanddescribedbelow:
1. ExistingConditions–Aliteraturereviewandquantitativeassessmentofthefollowing:
a. StatusofDGonthedistributionsysteminCaliforniab. TrendsinDGdeployment
c. StatusofDGinotherstatesandcountries
2. ImpactsandCostsofDG–CompiledataonDGinCaliforniaandextractmeaningfultrendstoquantifycurrentimpactsandcostsofDGinCalifornia.
3. PotentialBenefitsofDG–Quantifybenefits(or,insomecases,costs)ofDGduring
operationsuchaslinelosses,avoidedenergy,andreducedpeakdemand.4. Solutions–Identifyanddiscusspotentialsolutionsorstrategiesthatmaymitigateimpacts
andenhancebenefitsofDG.
5. ScenarioAnalyses–PerformmodelingthatidentifiesdifferentDGpenetrationscenariosandtheassociatedimpacts.ThismayincludemodelingimpactsatdifferentDGpenetration
levels,differentfeedertypes,theeffectofsolutionsidentifiedinsection4,andvariousDG
technologies.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Recommendations for Future Study 7‐2
Theanalysisshouldfocusonthestatus,impacts,costs,andbenefitsofDGonthedistributionsystem,ratherthanthetransmissionsystem,anditshallbeatechnicalandquantitativeanalysis.
Inadditiontotheabovedescribedanalysis,thefollowingareasshouldalsobestudied:
Reportingissues:reviewNEMinstallationdataandcompareagainstincentiveprogramdatabases
ImpactofDG(PVandnon‐PV)penetrationifincentivesandsubsidiesarenotsustainedandwhatothermechanismscanhelpsustainthemarket
Developmentofuser‐friendlymodelsfortransmission,distribution,substationandfeederlevelimpactswithincreasedDGpenetration.ThisshouldincludetransientanddynamicmodelingofDGsystems.
Developaconsistentapproachtodistributionmodelingacrossutilities
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Installed Capacity Data A‐1
Appendix A. Installed Capacity Data
Toensuretransparency,datasourcesforinstalledDGcapacityineachDGprogramsandthemethodsusedtofiltereachdatasetarelistedinTableA‐1below.Inallcases,theinstalledcapacityreportedbelowforeachprogramiscurrentasoftheendof2011.
Table A‐1 Data Sources and Data Filtering
PROGRAM DATASOURCESTATUS(ES)INCLUDED
DATEFILTERUSED
SYSTEMSIZEFIELDNAME
CSIGeneralMarket
CSIWorkingDataSet(6‐27‐2012)
OnlineIncentiveClaimFormSubmitted,IncentiveClaimRequestReview,SuspendedIncentiveClaimRequestReview,PendingPayment,Completed,PBI‐InPayment
FirstIncentiveClaimRequestReviewDatepriorto2012
CECPTCRating
MASHMASHSemi‐AnnualProgressReport,Feb.2012
N/A N/A CEC‐ACMW
SASH2011Q4SASHProgramStatusReport,Jan.2012
N/A N/A TotalkW(CEC‐AC)
SGIP CPUCDatabaseIncentiveClaimReview,PendingPayment,Completed
IncentiveClaimReviewDatepriorto2012
Capacity[kW]
ERP CECDatabase PaidDatePaidpriorto2012
SystemSize(Watts)
NSHP CECDatabase PaymentApprovalPaymentApprovalDatepriorto2012
SystemCapacity
SB1POUCECSB1POULifeofProgramandYearlyStatisticsfor2011
N/A N/A TotalkWInstalled
NEMCPUCInterconnectionDataRequest,Q12012
N/AInterconnectionYearpriorto2012
“TotalInverterNameplate(kW)”‐PG&E;“NEMCapqualified(kW)”‐SCE;“NameplateRating(kW)”‐SDG&E
FIT‐AB1969IOUAB1969ContractSpreadsheets
Online/Operational
ActualCOD/OperationalDate/NewOnlineDatepriorto2012
Capacity(kW)/MW
FIT‐SB32 N/A N/A N/A N/A
SPVPCPUCRPSContractsDatabase
Operational/OnlineOnlineDatepriorto2012
MinMW
RAM N/A N/A N/A N/A
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Peak Demand Impact Analysis Methodology B‐1
Appendix B. Peak Demand Impact Analysis Methodology
Indeterminingthepeakdemandimpact,Black&VeatchusedthetotalinstalledDGcapacityasofthedateonwhichthepeakdemandoccurred,whichwasSeptember7th,2011.ThetotalinstalledDGcapacityontheCAISOgridasofSeptember7th,2011bytechnologyispresentedinTableB‐1.
Table B‐1 Total Installed DG Capacity on CAISO Grid as of 9/7/2011
TECHNOLOGY MWINSTALLED
SolarPV 892
Wind 12
RF
FC 23
MT 4
ICE 12
Non‐RF
FC 18
MT 20
GT 31
ICE 142
AES 2
Total 1,156
SolarPVPeakDemandImpactBlack&Veatchobtainedactual15‐minuteproductiondataforsolarPVsystemsinstalledundertheCSIprogramandSGIP.MeteredsystemsforwhichthisdatawasavailableconstituteonlyasampleofthetotalPVinstallationsontheCAISOgrid,soitwasnecessarytocalculatepeakhourcapacityfactorsbasedonthisproductiondataandapplythesefactorstotherestofthePVsystemswhichwerenotmetered.Tocapturethediversityincapacityfactorsamongthemeteredsystems,thesystemswerecategorizedaccordingtovarious“strata.”ThesestrataareshowninTableB‐2.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Peak Demand Impact Analysis Methodology B‐2
Table B‐2 Strata Used to Categorize Solar PV Installations
PROGRAMPROGRAM
ADMINISTRATOR
INCENTIVETYPE/SYSTEM
SIZE LOCALEINSTALLATIONYEARGROUP
• CSI(incl.MASH&SASH)
• SGIP• ERP• NSHP
• PG&E• SCE• SDG&E/CCSE• SCG
• EPBB<10kW• EPBB≥10kW• PBI<10kW• PBI≥10kW
• Inland• Coastal
• 2001‐2003• 2004‐2006• 2007‐2009• 2010‐2012
Eachcombinationofstratawasclassifiedasa“bin”,andallmeteredsystemswereassignedtoonespecificbin,e.g.“CSI/SCE/EPBB<10kW/Coastal/2007‐2009”.Thetotalinstalledcapacityineachbinwasthencalculated.TheactualproductioninkWhofallsystemswithineachbinwasthensummedforthefour15‐minuteintervalscomprisingeachhour—e.g.thefourintervalsbeginningat4pm,4:15pm,4:30pm,and4:45pmonthepeakdaywassummedforthehourbeginningat4pm.ThiskWhsumforeachbinduringeachhourwasthendividedbythetotalinstalledcapacityofthatbintocalculatethehourlycapacityfactorforeachbin.
Afterdevelopingrepresentativehourlycapacityfactorsforthebins,thecapacityfactorsweremultipliedbythetotalinstallations,bothmeteredandnon‐metered,ineachcorrespondingbintocalculatethetotalhourlygenerationfromeachbin.Finally,thetotalhourlygenerationwassummedforallbins.TheresultingtotalforthepeakdemanddayisshowninFigureB‐1onthenextpage.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Peak Demand Impact Analysis Methodology B‐3
Figure B‐1 DG Solar PV Operating and CAISO Load on September 7, 2011
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
0
100
200
300
400
500
600
700
800
900
1,000
CAISO Load
(MW)
Solar PV Operating (M
W)
CSI
SGIP
CEC
All Solar PV
CAISO Load
Peak Solar PV Output: 621 MW
12 am 1 2 3 4 5 6 7 8 9 10 11 12pm 1 2 3 4 5 6 7 8 9 10 11 12am
CAISOPeak Load: 45,569 MW
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Peak Demand Impact Analysis Methodology B‐4
TheresultingpeakhourcapacityfactorsforeachprogramandadministratoraresummarizedinandTableB‐4below.
Table B‐3 Peak Hour Capacity Factors for Solar PV by Program
PROGRAM PEAKHOURCAPACITYFACTOR
CSI–EPBB 0.26
CSI–PBI 0.26
SGIP 0.23
ERP 0.23
NSHP 0.26
AllPrograms 0.25
Table B‐4 Peak Hour Capacity Factors for Solar PV by Program Administrator
PROGRAM PEAKHOURCAPACITYFACTOR
PG&E 0.28
SCE 0.23
SDG&E/CCSE 0.18
AllAdministrators 0.25
WhilethissolarPVpeakdemandimpactanalysisreplicatestoalargeextenttheanalysisconductedpreviouslybyItronforthe“CPUCCaliforniaSolarInitiative2010ImpactEvaluationFinalReport”,Black&Veatch’smethodologyisnotidentical.
Non‐SolarPVPeakDemandImpactFornon‐solargeneration(fuelcells,microturbines,gasturbines,andinternalcombustionengines),the“CPUCSelf‐GenerationIncentiveProgramEleventh‐YearImpactEvaluation”providethepeakdaygenerationhourlycapacitycurvesforthesenon‐PVtechnologies.AsshowninFigureB‐2,thegenerationprofileforthesetechnologiesarenearlyflatthroughouttheday.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Peak Demand Impact Analysis Methodology B‐5
Figure B‐2 Peak Day Generation Profiles for Non‐PV Technologies
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
0
20
40
60
80
100
120
140
160
CAISO Load
(MW)
Non‐Solar DG Operating (M
W)
Internal Combustion Engines
Fuel Cells
Microturbines
Gas Turbines
All Non‐Solar DG
CAISO Load
Peak Non‐Solar DG Output: 108 MW
12 am 1 2 3 4 5 6 7 8 9 10 11 12pm 1 2 3 4 5 6 7 8 9 10 11 12am
CAISOPeak Load: 45,569 MW
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Peak Demand Impact Analysis Methodology B‐6
Thepeakdemandcapacityfactorswerealsoreportedinthe“CPUCSelf‐GenerationIncentiveProgramEleventh‐YearImpactEvaluation”preparedbyItroninJune2012.TheseareshownbelowinTableB‐5.
ThetotalinstalledcapacityineachofthesetechnologycategorieswasmultipliedbythecorrespondingpeakcapacityfactortocalculatethepeakdemandimpactofeachinMW.Sincepeakcapacityfactordatawasnotavailableforwindturbinesandadvancedenergystoragesystems,theywereassignedacapacityfactorofzero,i.e.theywereassumedtohavenoimpactonpeakdemand.
Table B‐5 Peak Hour Capacity Factors for Non‐PV Technologies
TECHNOLOGY PEAKHOURCAPACITYFACTOR
WindTurbines 0.00
RenewableFuels
FuelCells 0.84
Micro‐turbines 0.08
GasTurbines 0.00
InternalCombustionEngines 0.49
Non‐RenewableFuels
FuelCells 0.54
Micro‐turbines 0.39
GasTurbines 0.83
InternalCombustionEngines 0.32
AdvancedEnergyStorage 0.00
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Future DG Study C‐1
Appendix C. Future DG Study
ThereismuchtobegainedfromamoredetailedinvestigationofthecurrentandfutureimpactsandbenefitsofDGontheelectricgridoftheinvestor‐ownedutilities(IOUs)inCalifornia.Suchaninvestigationwouldaddressthefollowingquestions:
HowisDGaffectingthedistributionandtransmissionsystemcurrently,andhowwillthischangeinthefuture?
HowmuchmoreDGcouldbedeployedonthesystemifsitingwereoptimizedforminimalimpactsandenhancedbenefits?
Whatadditionaltoolsareneededtoidentifyoptimallocation,type,andtimingofDG?
Howcananenhancedunderstandingofthecostsofdifferentimpacts,benefitsandsolutionshelpinformeffectivepolicytoenablethedeploymentofmoreDG?
HowcouldthedeploymentofmoreDGbebeneficial?Ifdeployedineffectively,howcoulditbedeleterious?
AnsweringthesequestionscanhelpcreateaclearroadmapofthegrowthpotentialofDG,andtoenableCaliforniatoanticipatepotentialchallengestoDGdeployment.Acomprehensivestudycanhelpanswerthem,bysummarizingtheanalysisthathasbeendonetodate,andanalyzingtheavailabledataforexistingsystems,andforecastingimpactsoffuturegrowth.
Thereareanumberofprojectsandexistingstudiesthathavebeenperformedthataddressthestatus,impactsandbenefitsofDG.Thereareseveralstudiescurrentlybeingperformedwithsomenotableeffortsnowunderwaylistedbelow:
CPUCCSIResearch,Development,Demonstration,andDeploymentPrograms
DOE'sHighPenetrationSolarDeploymentProjects
CPUCStatewideCost‐BenefitsAnalysisofNEM(E3)
CSIMarketTransformationStudy(Navigant)
CPUCRenewableDistributedGenerationTechnicalAnalysis(Black&Veatch)
SanDiegoNEMStudy(Black&Veatch)
TheanalysisperformedaspartofthefutureDGstudyproposedshouldnotduplicateanalysisavailablefromotherstudies,butleverageexistinginformationandcompileitinausefulformattoanswerthequestionsabove.Anewanalysisshouldintelligentlyaggregateavailableinformationandprovideacomprehensivereviewtoextractmeaningfultrendsthataddressopenquestions.Thisstudywillincludefiveprimarysections:
1. ExistingConditions2. ImpactsandCostsofDG
3. PotentialBenefitsofDG
4. Solutions5. ScenarioAnalyses
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Future DG Study C‐2
Theanalysisshouldfocusonthestatus,impacts,costs,andbenefitsofDGonthedistributionsystem,ratherthanthetransmissionsystem,anditshallbeatechnicalandquantitativeanalysis.
1) ExistingConditionsAssessment
Tasksunderthisfirstsectionwillconsistlargelyaliteraturereviewofexistingstudies(includingthereportslistedabove)andaquantitativeassessmentoftheexistingsystemtocomprehensivelydocumentthecurrentstatusofCalifornia’sdistributionsystemandDGinCalifornia.
a. First,reviewthestatusofthedistributionsysteminCalifornia;documentthedifferencesbetweenutilitiesinCaliforniaintermsofthevintage(new,old),operationalcharacteristics(automated,manual,un‐operated),andotherrelevantaspectsoftheirdistributionsystems.UnderstandhoweachutilityisdealingwithDGanddifferentapproaches.ReviewandunderstandthetestimonywhichresultedintherecentRule21modifications.
b. Secondly,studythetrendsinDGdeploymenttodate.Generally,thisstudyshouldanswerthefollowingquestions:WhereisDGbeinginstalled?WhatfeederscurrentlyhavethehighestpenetrationofDG,andwhatimpactsaretheyseeing?IsthedeploymentofDGrandomintermsoflocation,orclusteredinawaythatcanbepredicted?IsclusteringcausinganegativeimpactthatcouldpreventfurtherDGfrombeingdeployed?Morespecifically,thisstudyshouldassesstrendsbasedonsystemsizecategories,suchaslarge(3‐20MWthatareutilityownedorownedbyIPPswithcontractswithutilities),medium(1‐3MWthatarelikelypartofthefeedintariffprograms),andsmall(0‐1MWwhicharegenerallyresidentialorcommercialinstallationsundervariousincentiveprograms).Specificquestionsundereachsystemsizecategoryshouldbeanswered:
a. Large:
HowmanyoftheseDGprojectsaretransmissiongridconnectedandhowmanyconnecttodistributionandwherearethey?
HowmanyDGprojectsexceedtheloadsonthedistributionlinestheyareconnectedto?
AreanyoftheselargeDGinstallationslocatedonlongruraldistributionlines?
WhatadditionalupgradeshavebeenrequiredtoaccommodatetheselargeDGprojects?
Arethereanyexampleswheresystemupgradeshavenotbeenrequired?
HaveutilitiessitedanyoftheselargeDGprojectstomaximizebenefits?
Whatneedstobedonetomeasureandunderstandthebenefitsandcostsoflargeinstallations?
b. Medium:
HowmanyoftheseDGprojectsexistandwherearethey?
Whatpenetrationlevelisachieved?
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Future DG Study C‐3
ArethereanyexampleswhereseveralmediumsizeDGprojectsarelocatedononedistributionline?
Towhatextenthavesystemupgradesbeenrequiredformediumsizesystemsoraggregationsofmediumsizesystems?
HaveutilitiessitedanyofthesemediumsizeDGprojectstomaximizebenefits?
Whatneedstobedonetomeasureandunderstandthebenefitsandcostsoftheseinstallations?
c. Small:
Howmanynewsolarhomecommunitiesexist?
Whatpenetrationlevelsexistonthedistributionlinesthesecommunitiesconnectto?
Arethereanylocationswheremultiplehighpenetrationsolarhomecommunitiesconnecttoonetransmissionline?
Whensuchnewsolarhomecommunitiesaredevelopedandimplemented,areanyspecialupgradesmadetooperatedistributionsystemortomeasuretheimpactsofthehighsolarDGpenetrationlevels?
Whatneedstobedonetomeasureandunderstandingthebenefitsandcostsofexistinghighpenetrationsolarcommunities?
c. Finally,includeastudyofthestatusofDGinotherstatesandcountries.HowareothersdealingwithDGimpacts?LikelycandidatesincludeHawaii,GermanyandDenmark.
ThisanalysisshouldprovideausefuldefinitionofDG.ShouldDGincludethosesystemsofacertainsizeconnectedtothetransmissionsystem?ShouldthedefinitionofDGbelimitedtosystems,ofanysize,connectedtothedistributionsystem?
2) ImpactsandCostsofDG
Todate,impactsofDGonthedistributionandtransmissionsystemsarenotwellunderstood.ThereisatremendousamountofdataavailableaboutDGsystemsthroughoutCalifornia,thoughthedataisoftenoutofdate,ofpoorquality,orkeptinobscurelocationsthatlimitaccess.Furthermore,thereappearstobeverylimiteddataabouttheeffectofDGontheutilities’distributionsystems.CompilingthisdataandextractingmeaningfultrendswouldsupportourunderstandingofthecurrentimpactsofDGandtheircosts.Thefollowingdatasetscouldbeused:
Customer‐sideDGsystemsreceivingincentives:
● CSIWorkingDataSet
● SGIPdataset
● ERPdataset
● NSHPdataset
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Future DG Study C‐4
IOUDGinterconnectiondatasetsandincludinganysystemupgradecostsidentifiedineachapplication(includingNEMandnon‐NEMinstallations)
WholesaleDGsystemsundervariousstateprograms:
● FIT–AB1969
● FIT–SB32
● RAM
● SolarPVPrograms
● FIT–AB1613
IOUWholesaleDistributionAccessTariff(WDAT)interconnectionqueues
CAISOinterconnectionqueue
UnderstandingtheimpactsandcostsofDGinvolvescompilingthereal‐worlddataavailablefromthesourceslistedaboveandothers.Inaddition,availabledataondeployedenergystoragesystemsshouldbecollected,datagapsshouldbeidentified,andresearchstrategiesforfillingthosegapsshouldbecreated.Fromthisdataandotherrelevantdatasources,aplotcanthenbecreated,similartothatshowninFigureC‐1.FigureC‐1showsthehypotheticalincrementalcostofinstallingDGonafeederoverarangeofpenetrationlevels.Thisgraphshouldbefilteredfortheappropriateattributesbecauseeachutilityoperatesdifferently,feederdesignsarehighlyvariableandcanbecharacterizedbyanumberoffactors(e.g.urbanvs.rural),andbecausethesizeofaDGsystemhasaneffectonitsimpacttothedistributionsystem.Theseattributesmayinclude,butnotbelimitedtothenameoftheutility,locationoffeeder,andsizeofDGsystem.
FigureC‐1alsoreflectsthehypotheticallevelofeffortneededtointerconnectagivenamountofDG.Forexample,atlowpenetrationlevels,noupgradestotheDGsystemmaybeneeded;however,whenpenetrationincreasestoacertainpoint,itcouldbethatchangestosystemprotectionschemesordevicesmaybenecessary.
TheintentofthisgraphistoconveyanunderstandingofwhatDGpenetrationlevelscauseimpactsandrequireaction.ThedifferentcurvesinthisgraphilluminatechangesinDGintegrationcosts,basedondifferentsystemscenarios,andcanbeextrapolatedtoforecastimpactsandcostsofDG.
However,itshouldbestressedthatthefigureishypothetical.Itpositsthatcostsincreaseaspenetrationonafeederincreases,andthatdifferentfeedertypesmighthavedifferent,discerniblerelationshipsbetweencostsandpenetration.Infact,neitherofthesemaybecorrectassumptions.PenetrationlevelmaynotbealargedriverincostsandimpactsofDG.Akeyobjectiveofthistaskwillbetotesttheseassumptions.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Future DG Study C‐5
Figure C‐1 Sample Graph Showing Interconnection Costs Relative to Penetration Level
3) PotentialBenefitsofDG
ManystudieshavesuggestedawidevarietyofpossiblebenefitsassociatedwithDGsuchasareductioninpeakdemand;reductioninlinelosses;deferralsofdistributionsystemupgrades;andincreasedreliabilitybecauseofthepresenceofredundantenergysources.However,asshowninthisstudy,veryfewofthesebenefitsarecurrentlybeingadequatelyquantified.Infact,someofthepurportedbenefitsmayactuallybemanifestedascosts.Forexample,ratherthandeferringdistributionupgrades,utilitiesmaybeupgradingtheirdistributionsystemstoaccommodateDG.Finally,itisnotknownifthevalueorresponsibilityforthesebenefitsorcostsisbeingproperlyassignedtotheimpactedparties.
ThistaskrequiresthequantificationoftheactualimpactsofDGthatareseentodayonthedistributionsystem.Manystudieshavebeendoneontheseissuesinthepast.However,thesestudieshavegenerallyreliedonsimulatedscenariosorlimitedactualdatafromisolatedcircuits.TheobjectiveofthistaskwouldbetocollectactualdatafromacrossCaliforniatovalidatewhetherthepurportedbenefitsareactuallybeingachieved.Oncethedataonbenefitsiscollected,itcanbeanalyzedinamannersimilartothecostdata.Trendscouldbeplotted,andkeyvariablesmightbeidentifiedwhichtendtodrivethebenefitsofDGhigherincertainscenarios.
ThemagnitudeofdemandreductionfromDGwouldalsobestudiedfurtheraspartofthistask.Howisdemandaffectedduringminimumloadhours?Whatarethedemandimpactdifferencesbyutility?
< 3 MW
> 3 MW
Urban Feeder
SCE
Rural Feeder
PG&E
SDG&E
0
2
4
6
8
10
12
14
16
18
0% 20% 40% 60% 80% 100% 120% 140%
Rel
ativ
e C
ost
(u
nit
s T
BD
)
Feeder Penetration Level
NoChange
SystemProtectionUpgrades
CapacityAddition Unknown
Hypothetical
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Future DG Study C‐6
Finally,thisstudyshouldestimatehowimpactswillchangeasDGgrows.Arecertainregionsreceivingmorebenefitsthanothers?
4) Solutions
Thissectionshouldcoverthefollowingquestions:
HowcannegativeimpactscausedbyDGbemitigated?
HowcanthebenefitsofDGbeenhanced?
WhatmeasurescanbetakentochangetheshapeofthechartsdevelopedintheImpactsandBenefitstasks,andwhatdothesemeasurescost?
Basedontheanalysisintheprevioussections,discusspotentialtechnicalsolutionsorstrategiesthatcouldbetakentomitigateimpactsandenhancebenefits.Thesemayinclude:
OptimallylocatingsystemsgeographicallytolimitnegativeattributesofDG,andenhancepositiveattributes.
Designinga“DGReady”distributionsystemandquantifyingassociatedcosts
Strategicallylocatingenergystoragethroughoutthegrid
Aligningincentiveswiththeknownbenefitsandimpactsindifferentlocations
SmartInvertersandSmartGrid
Electricvehicles
DistributionsysteminfrastructureequipmentcommonlyusedbyothercountriestosupporthighpenetrationofDG.
Createtoolstoallowplanninganddistributionengineertominedata(includingSmartMeterdata)tofacilitateabetterunderstandingandidentificationofthecostsandbenefitsofDGsystems.
Manyofthesolutionsidentifiedmayrequirerevisionofdesignstandardsusedbyutilities.Ofthesolutionsidentified,estimatethecostsandbenefitsoftoimplementingthesesolutions.
5) ScenarioAnalysis
TounderstandthequantitativeimpactsofvariousDGpenetrationlevels,andsolutions,ascenarioanalysisshallbeperformed.ThiswillentailmodelingpartsofthedistributionsystemandshowingtheeffectsonthecurvesproposedfortheImpactsandBenefitssections.
StudydifferentpenetrationlevelsofDG:0,10,15,50,75,100,150and200percent
StudyhowsitingDGsystemsdifferentlyimpactsthesystemonvariouscategoriesofdistributionfeeders,suchasruralandurban.
ModelandstudytheimpactsandbenefitsofdifferentDGtechnologiesthathaveseensignificantdeploymentonthegridtodatewhichare:
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | Future DG Study C‐7
● SolarPV
● Windturbines
● Fuelcells(witheitherrenewableornon‐renewablefuels)
● Gasturbines(witheitherrenewableornon‐renewablefuels)
● Microturbines(witheitherrenewableornon‐renewablefuels)
● Internalcombustionengines(witheitherrenewableornon‐renewablefuels)
ModelandstudytheeffectontheImpactsandBenefitsgraphswhenthesolutionsidentifiedintheabovetaskareimplemented.
ThegoalofthisscenarioanalysiswillbetodescribealikelyrangeofDGpenetrationscenariosondistributionsystemsinCalifornia,andthecostsandbenefitsassociatedwitheach,tohelpinformfutureDGpolicyinthestate.
California Public Utilities Commission | BIENNIAL REPORT ON IMPACTS OF DISTRIBUTED GENERATION
BLACK & VEATCH | January 31, 2013 Report Presentation, Including Selected 2012 Data Updates D‐1
Appendix D. January 31, 2013 Report Presentation, Including Selected 2012 Data Updates