bid and contract documents major equipment …

304
BID AND CONTRACT DOCUMENTS FOR MAJOR EQUIPMENT PROCUREMENT CITY OF STEVENSON, WASHINGTON WASTEWATER TREATMENT PLANT IMPROVEMENTS – PHASE 1 RELEASED FOR BID SEPTEMBER 2021 PREPARED BY Esvelt Environmental Engineering, LLC Spokane, Washington (509) 926‐3049 IN ASSOCIATION WITH: Wallis Engineering 215 West 4 th Street, Suite 200 Vancouver, WA 98660 (360) 695‐7041 FUNDING: Funded in part by the Washington State Department of Ecology's Centennial Clean Water Fund and Clean Water State Revolving Fund

Upload: others

Post on 18-Apr-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

BID AND CONTRACT DOCUMENTS FOR 

MAJOR EQUIPMENT PROCUREMENT  

CITY OF STEVENSON, WASHINGTON WASTEWATER TREATMENT PLANT IMPROVEMENTS – PHASE 1 

  

RELEASED FOR BID SEPTEMBER 2021 

 

 PREPARED BY 

 Esvelt Environmental Engineering, LLC Spokane, Washington (509) 926‐3049 

 

IN ASSOCIATION WITH:  Wallis Engineering 215 West 4th Street, Suite 200 Vancouver, WA 98660 (360) 695‐7041 

 

FUNDING: Funded in part by the Washington State Department of Ecology's Centennial Clean Water Fund and 

Clean Water State Revolving Fund 

Page 2: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

THIS PAGE INTENTIONALLY LEFT BLANK 

Page 3: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐00 01 05 Certificate of Engineer for Procurement.doc  00 01 05‐1 

SECTION 00 01 05 CERTIFICATE OF ENGINEER 

The  technical material and specifications  listed below were prepared by or prepared under  the direct supervision  of  the  undersigned,  whose  seal,  as  professional  engineer  licensed  to  practice  as  such,  is affixed below. 

Specification Sections  01 33 00  Submittal Procedures 01 60 00  Product Requirements 01 75 00  Testing and Commissioning Procedures 01 78 00  Close Out Submittals 01 79 00   Training 40 05 93  Common Motor Requirements for Process Equipment 43 11 33  Rotary Lobe Blowers 43 25 00  Submersible Screw Centrifugal Pumps 46 21 33  In‐Channel Rotary Drum Screen 46 23 00   Grit Removal Equipment 46 41 34   Vertical Turbine Mixers 46 51 33   Fine Bubble Diffusers 46 66 56  Ultraviolet Disinfection System  

 ALLISON M. Z. ESVELT, P.E., BCEE   Esvelt Environmental Engineering LLC Spokane, WA 99217 509‐926‐3049 [email protected] 

9/10/2021 

Page 4: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐00 01 05 Certificate of Engineer for Procurement.doc  00 01 05‐2 

THIS PAGE INTENTIONALLY LEFT BLANK 

Page 5: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐00 01 10 Table of Contents for Procurement.doc  00 01 10‐1   

SECTION 00 01 10 TABLE OF CONTENTS FOR CONTRACT DOCUMENTS 

 

Section  Title  VOLUME 1  BID DOCUMENTS AND CONTRACT REQUIREMENTS  DIVISION 0   00 01 01  Project Title Page (Cover) 00 01 05  Certificate of Engineer 00 01 10  Table of Contents 00 10 00  Advertisement  for Bids  00 20 00  Instructions to Bidders for Procurement Contracts, EJCDC P‐200 (2019) 00 22 00  State Revolving Fund (SRF) Pre‐Selection Specification Insert (10‐24‐2014)   Bid Forms: (To be torn out and submitted with Bid Proposal) 00 40 00  Bid Form for Procurement Contracts EJCDC P‐400 (2019)  00 43 00  Bid Bond Form, EJCDC C‐430 (2018) 00 45 10  Bidder’s Qualification Statement Form  Contract Forms: (To be completed after award) 00 51 00  Notice of Award Form, EJCDC C‐510 (2018) 00 52 00  Agreement for Procurement Contracts, EJCDC P‐520 (2019) 00 55 00  Notice to Proceed Form, EJCDC C‐550 (2018)  00 61 00  Performance Bond for Procurement Contracts, EJCDC P‐610 (2019) 00 61 50  Payment Bond for Procurement Contracts, EJCDC P‐615 (2019) 00 62 50  Buyer’s Acknowledgment Receipt of Goods, EJCDC P‐625 (2019) 00 62 60  Buyer’s Notice Regarding Conformity of Goods and Special Services, EJCDC P‐626 (2019) 00 94 00  Work Change Directive Form, EJCDC C‐940 (2018) 00 94 10  Change Order Form, EJCDC C‐941 (2018)  General and Supplemental General Conditions:  00 70 00  Standard General Conditions for Procurement Contracts, EJCDC P‐700 (2019) 00 80 00  Supplementary General Conditions for Procurement Contracts, EJCDC P‐800 (2019)  

TECHNICAL SPECIFICATIONS  DIVISION 1 ‐ GENERAL REQUIREMENTS 01 33 00  Submittal Procedures 01 60 00  Product Requirements 01 75 00  Testing and Commissioning Requirements 01 78 00  Close Out Submittals 01 79 00   Training   

Page 6: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐00 01 10 Table of Contents for Procurement.doc  00 01 10‐2   

  Section   Title    DIVISIONS 2 THROUGH 39 (NOT USED)  DIVISION 40 ‐ PROCESS INTERCONNECTIONS 

40 05 93  Common Motor Requirements for Process Equipment  DIVISION 41 (NOT USED)  DIVISION 43 ‐ PROCESS GAS AND LIQUID HANDLING EQUIPMENT 43 11 33  Rotary Lobe Blowers 43 25 00  Submersible Screw Centrifugal Pumps  DIVISIONS 44 THROUGH 45 (NOT USED)  DIVISION 46 ‐ WATER AND WASTEWATER EQUIPMENT 46 21 33  In‐Channel Rotary Drum Screen 46 23 00   Grit Removal Equipment  46 41 34   Vertical Turbine Mixers  46 51 33   Fine Bubble Diffusers  46 66 56  Ultraviolet Disinfection System   

VOLUME 2  City of Stevenson Wastewater Treatment Plant Improvements Phase 1, WA Department of Ecology Review Drawings, June 2020    

Page 7: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐00 10 00 Advertisement for Bids for Procurement.docx 00 10 00‐1

CITY OF STEVENSON, WA ADVERTISEMENT FOR BIDS 

Sealed bids for the supply of major equipment for the City of Stevenson WWTP Improvements Phase I – Major Equipment Procurement will be received by the City of Stevenson (City) at the City Hall at 7121 East Loop Road, Stevenson, Washington 98648, until 2:00 P.M. local time on October 13, 2021, at which time the Bids received will be publicly opened and read via Zoom Meeting ID 823 3474 7416.   Join Zoom Meeting 1‐253‐215‐8782 Meeting ID: 823 3474 7416 Passcode: 553365  Description  of  Work:  This  work  includes  fabrication  and  delivery  of  the  following  equipment  under separate procurement contracts: rotary lobe blowers, submersible screw centrifugal pumps, in‐channel rotary  drum  screen,  grit  removal  equipment,  vertical  turbine  mixers,  fine  bubble  diffusers,  and  an ultraviolet  disinfection  system.  The  work  shall  also  include  furnishing  design  and  operation documentation; on‐site start‐up, testing, and training; and post‐commissioning assistance. The work is to be completed by November 1, 2022.    The City will  execute multiple equipment procurement  contracts.  The materials  and equipment  to be provided through the procurement contracts are to be furnished and delivered to the Site for installation by the City’s Contractor. The City will assign the procurement contracts to the installation Contractor as set forth in the Agreement.   Obtaining the Bidding Documents: Information and Bidding Documents for the Project can be found at the following designated website:  https://walliseng.net/contact‐us/projects‐out‐to‐bid/  Bidding Documents may be downloaded from the designated website. Prospective Bidders are required to complete the “Plan Holder Registration Form”, even if Bidding Documents are obtained from a plan room or source other than the designated website in either electronic or paper format. The designated website will be updated periodically with addenda.  Once a potential bidder or proposer has completed, signed, and returned to the Engineer the “Plan Holder Registration Form”, the Engineer will automatically forward  them any and all  subsequent  addendums,  amendments,  or other documents  relevant  to  the solicitation. All official notifications, addenda, and other Bidding Documents will be offered through the designated website. Neither Owner nor Engineer will be responsible  for Bidding Documents,  including addenda, if any, obtained from sources other than the designated website.  Bid Proposals: Bid Proposals will be received for separate equipment procurement contracts for each type of major equipment. Bid Proposals must be submitted on the forms provided in the Contract Documents. Bid security shall be furnished in accordance with the Instructions to Bidders.   Rejection of Bids: The City shall have the right to reject any or all bids not accompanied by bid security, or data required by the bidding documents, a bid in any way incomplete or irregular, or if the bid amount exceeds the amount of funds available for the project.  Funding: It is anticipated that this project will be funded in part by the Washington State Department of Ecology's Centennial Clean Water Fund and Clean Water State Revolving Fund (SRF). Neither the Federal Government, State of Washington, nor any of their departments or employees are, or shall be, a party to any contract or any subcontract resulting from this solicitation for bids.   Owner:  City of Stevenson By:  Leana Kinley Title:  City Administrator Date:  September 10, 2021 

*** END OF SECTION *** 

Page 8: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐00 10 00 Advertisement for Bids for Procurement.docx 00 10 00‐2

THIS PAGE INTENTIONALLY LEFT BLANK  

Page 9: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐200, Instructions to Bidder for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. TOC Page 1 of 1 

STV‐00 20 00 Instructions to Bidders for Procurement 2019.docx  00 20 00‐i 

SECTION 00 20 00 ‐ INSTRUCTIONS TO BIDDERS  FOR PROCUREMENT CONTRACT 

TABLE OF CONTENTS 

Page 

Article 1— Defined Terms ............................................................................................................................. 1 

Article 2— Procurement Bidding Documents ............................................................................................... 1 

Article 3— Qualifications of Bidders ............................................................................................................. 1 

Article 4— Site Visit; Pre‐Bid Conference ..................................................................................................... 1 

Article 5— Interpretations and Addenda ..................................................................................................... 2 

Article 6— Bid Security ................................................................................................................................. 2 

Article 7— Procurement Contract Times ...................................................................................................... 3 

Article 8— Liquidated Damages .................................................................................................................... 3 

Article 9— Confidentiality of Bid Information .............................................................................................. 3 

Article 10— “Or‐Equal” Items ....................................................................................................................... 4 

Article 11— Preparation of Bid ..................................................................................................................... 4 

Article 12— Basis of Bid; Comparison of Bids ............................................................................................... 5 

Article 13— Submittal of Bid ......................................................................................................................... 5 

Article 14— Modification or Withdrawal of Bid ........................................................................................... 6 

Article 15— Opening of Bids ......................................................................................................................... 6 

Article 16— Bids to Remain Subject to Acceptance ..................................................................................... 6 

Article 17— Evaluation of Bids and Award of Procurement Contract .......................................................... 6 

Article 18— Bonds and Insurance ................................................................................................................. 6 

Article 19— Signing of Procurement Agreement ......................................................................................... 7 

Article 20— Sales and Use Taxes .................................................................................................................. 7 

Article 21— Procurement Contract to be Assigned ...................................................................................... 7 

 

Page 10: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐200, Instructions to Bidders for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 7 

STV‐00 20 00 Instructions to Bidders for Procurement 2019.docx 00 20 00‐1 

INSTRUCTIONS TO BIDDERS FOR PROCUREMENT CONTRACT 

ARTICLE 1—DEFINED TERMS 

1.01 Terms  used  in  these  Instructions  to  Bidders  will  have  the meanings  indicated  in  the  General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below. 

A. Issuing Office—The office from which the Procurement Bidding Documents are to be issued and where the bidding procedures are to be administered. 

ARTICLE 2—PROCUREMENT BIDDING DOCUMENTS 

2.01 Bidder may obtain complete sets of the Procurement Bidding Documents, in the number and for the deposit sum, if any, stated in the advertisement or invitation to bid, from the Issuing Office. The deposit will be refunded to each document holder of record who returns a complete set of Procurement Bidding Documents in good condition within 30 days after opening of Bids. Bidders must obtain a complete set of the Procurement Contract Documents as listed in the Procurement Agreement. 

2.02 Bidder must use a  complete  set of  the Procurement Bidding Documents  in preparing  the Bid; neither Buyer nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Procurement Bidding Documents. 

2.03 Buyer and Engineer make copies of Procurement Bidding Documents available on the above terms only for obtaining Bids for furnishing Goods and Special Services, and do not authorize or confer a license for any other use. 

ARTICLE 3—QUALIFICATIONS OF BIDDERS 

3.01 Buyer may at any time conduct such  investigations as Buyer deems necessary to establish the responsibility, qualifications, and  financial ability of Bidder, and after  the opening of Bids may require  a  Bidder  to  submit  documentation  of  its  qualifications,  including  but  not  limited  to financial  data  and  documentation  of  previous  experience  providing  goods  and  services comparable to the specified Goods and Special Services. 

3.02 Bidder is to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications. 

3.03 Bidder  shall  submit  a  qualifications  statement  with  the  Bid,  including  financial  data  and documentation of previous experience providing comparable goods and services, to demonstrate Bidder’s qualifications to furnish the specified Goods and Special Services. 

ARTICLE 4—SITE VISIT; PRE‐BID CONFERENCE 

4.01 Buyer recommends that Bidder visit the Point of Destination and the site where the Goods are to be installed and Special Services will be provided, taking into account observable local and site 

Page 11: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐200, Instructions to Bidders for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 7 

STV‐00 20 00 Instructions to Bidders for Procurement 2019.docx 00 20 00‐2 

conditions that may affect the delivery, cost, progress, and furnishing of the Goods and Special Services. Arrangements for such a visit may be made through Engineer. 

4.02 A pre‐bid conference will not be held for this procurement. 

ARTICLE 5—INTERPRETATIONS AND ADDENDA 

5.01 All  questions  about  the meaning  or  intent  of  the  Procurement  Bidding  Documents  are  to  be submitted to Engineer in writing at the address in the Bid advertisement. 

5.02 Interpretations or  clarifications  considered necessary by  Engineer  in  response  to  such written questions will be issued by Addenda mailed or delivered to all parties recorded as having received the Procurement Bidding Documents. Questions received less than 10 days prior to the date for opening  of  Bids  will  not  be  answered.  Only  answers  in  the  Addenda  will  be  binding.  Oral statements, interpretations, and clarifications may not be relied upon in the preparation of a Bid, and will not be binding or legally effective. 

5.03 Addenda may be  issued  to  clarify,  correct, or  change  the Procurement Bidding Documents as deemed advisable by Buyer or Engineer. 

ARTICLE 6—BID SECURITY 

6.01 A Bid must be accompanied by Bid security made payable to Buyer in an amount of 5 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates). If a Bid bond is provided for Bid security, it must be in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 5.01 of the General Conditions. Such Bid bond will be  issued in the form included in the Procurement Bidding Documents. 

6.02 The Bid security of the apparent Successful Bidder will be retained until Buyer (Project Owner) awards the Procurement Contract to such Bidder, and such Bidder has executed the Procurement Contract, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Procurement Contract and furnish the required contract security within 15 days after the Notice of Award, Buyer (Project Owner) may consider Bidder to be in default and annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Buyer’s damages in the case of a damages‐form bond. Such forfeiture will be Buyer’s exclusive remedy if Bidder defaults. 

6.03 The Bid security of other Bidders that Buyer believes to have a reasonable chance of receiving the award  may  be  retained  by  Buyer  until  the  earlier  of  7 days  after  the  Effective  Date  of  the Procurement Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released. 

6.04 Bid security of other Bidders that Buyer believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening. 

Page 12: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐200, Instructions to Bidders for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 3 of 7 

STV‐00 20 00 Instructions to Bidders for Procurement 2019.docx 00 20 00‐3 

ARTICLE 7—PROCUREMENT CONTRACT TIMES 

7.01 See applicable provisions in the Procurement Agreement. 

ARTICLE 8—LIQUIDATED DAMAGES 

8.01 Any  provisions  for  liquidated  damages,  such  as  those  for  Seller’s  failure  to  attain  a  specified Milestone such as the delivery of the Goods, are set forth in the Procurement Agreement. 

ARTICLE 9—CONFIDENTIALITY OF BID INFORMATION 

9.01 Confidential information is information in the Bid, or in documents submitted by Bidder with the Bid or submitted subsequent to the opening of Bids in support of the Bid, that Bidder clearly and prominently labels in writing to be a trade secret, proprietary, or confidential. Bids will be opened and accompanying documents,  if any, will be maintained in a manner that endeavors to avoid disclosing confidential information to third parties, to the extent allowed by Laws and Regulations. 

9.02 Bidder  shall  clearly  and  prominently  mark  confidential  information  with  the  word “CONFIDENTIAL”  on  each  page  or  sheet  or  on  the  cover  of  bound  documents.  Place “CONFIDENTIAL”  stamps  or  watermarks  so  that  they  do  not  obscure  any  of  the  required information on the document, either  in the original or  in a way that would obscure any of the required information in a photocopy of the document. 

9.03 If Buyer is requested to disclose confidential information, becomes legally compelled to disclose confidential  information, or  is  required by a  regulatory body, governing agency, or  controlling authority to disclose confidential information, or make any other disclosure that is prohibited or otherwise constrained by  these Procurement Bidding Requirements, Buyer will provide Bidder with prompt notice so Bidder may seek a protective order or other appropriate remedy. Bidder will be solely responsible for submitting to the regulatory body, governing agency, or controlling authority  any  arguments,  briefs,  memoranda,  motions,  authorities,  or  other  information  in opposition to disclosure. 

9.04 Buyer’s  obligations  with  respect  to  confidential  information  are  nullified  by  the  following exceptions: 

A. Confidential  information  becomes  a  part  of  the  public  domain  through  publication  or otherwise, through no fault of the Buyer; 

B. Buyer can demonstrate through suitable documentation that the confidential  information was already  in  the Buyer’s possession, and not previously marked as confidential, or was otherwise publicly available prior to the date of Bid submittal; 

C. The confidential information is subsequently and independently disclosed to the Buyer by a third party who has a lawful right to disclose such information; 

D. Buyer concludes in good faith that the information is not confidential, or that disclosure is required or justified; or 

E. Buyer  is  required  to disclose  the confidential  information by court order or by applicable Laws and Regulations. 

Page 13: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐200, Instructions to Bidders for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 4 of 7 

STV‐00 20 00 Instructions to Bidders for Procurement 2019.docx 00 20 00‐4 

9.05 Notwithstanding any other provision of the Procurement Bidding Documents, it is stipulated and agreed that by accepting a Bid, Buyer has not and does not waive its legal immunity (if any) from suit or liability. 

ARTICLE 10—“OR‐EQUAL” ITEMS 

10.01 The Procurement Contract,  if awarded, will be based on materials and equipment specified or described in the Procurement Bidding Documents. Bidders may propose "or equal" materials and equipment, which  if approved by Engineer will be  identified by Addendum. The materials and equipment described  in  the Procurement Bidding Documents establish a  standard of  required type, function, and quality to be met by any proposed “or‐equal” item. No item of material or equipment will be considered by Engineer as an “or‐equal” unless written request for approval has been submitted by Bidder and has been received by Engineer no later than 15 days after the advertisement  or  invitation  to  bid  is  first  issued.  Each  such  request  shall  conform  to  the requirements of Paragraph 7.04 of the General Conditions. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item  as  an  equal  will  be  final.  Bidders  shall  not  rely  upon  approvals  unless  set  forth  in  an Addendum.  

ARTICLE 11—PREPARATION OF BID 

11.01 The  Bid  Form  is  included  with  the  Procurement  Bidding  Documents.  Additional  copies  of Procurement Bidding Documents may be obtained from the Issuing Office. 

11.02 All blanks on the Bid Form must be completed and the Bid Form must be signed by an individual authorized to act on behalf of the Bidder. Alterations must be initialed by an individual authorized to act on behalf of the Bidder. A Bid price must be indicated for each item in the Bid Form. In the case of optional alternates, the words “No Bid” may be entered. 

11.03 Bidder must acknowledge all Addenda by filling in the number and date of each Addendum in the Bid Form and sign where indicated to verify that the Addenda were received. A Bid that does not acknowledge receipt of all Addenda may be considered non‐responsive. 

11.04 Bidder shall: 

A. Sign the Bid Form as indicated in the Bid Form. 

B. Include evidence of authority to sign. 

C. Provide information on the individual to be contacted for any communications regarding the Bid. 

D. Provide evidence of the Bidder’s authority and qualification to do business in the locality of the  Project,  to  the  extent  required,  or  indicate  the  ability  to  obtain  such  authority  and qualification prior to award of the Procurement Contract. 

Page 14: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐200, Instructions to Bidders for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 5 of 7 

STV‐00 20 00 Instructions to Bidders for Procurement 2019.docx 00 20 00‐5 

11.05 The responsibilities of each Bidder submitting a Bid are described in the Bidder’s representations and certifications set forth in Article 6 of the Bid Form. 

ARTICLE 12—BASIS OF BID; COMPARISON OF BIDS 

12.01 Lump Sum 

A. Bidder shall submit a Bid on a lump sum basis as set forth in the Bid Form. 

B. The apparent low Bid will be determined on the basis of the lump sum bid amount. 

12.02 Base Bid with Alternates 

A. The “Base Bid” is the sum stated in the Bid for which the Bidder offers to furnish the Goods and Special Services described in the Procurement Bidding Documents as the base, to which work may be added for sums stated in Alternate Bids. An “Alternate Bid” (or Alternate) is an amount stated in the Bid to be added to the amount of the Base Bid if the corresponding change  in  the  Goods  and  Special  Services,  as  described  in  the  Procurement  Bidding Documents, is accepted. 

B. As set forth in the Bid Form, Bidder shall enter an amount for the Lump Sum Base Bid, and enter  a  separate  amount  for  each  Alternate  Bid  described  in  the  Procurement  Bidding Documents. 

C. The apparent low Bid will be determined on the basis of the total amount of the Base Bid, plus  (in  the order  listed on  the Bid Form)  the Alternate Bids providing  the most  features within the funds determined by the Buyer to be available. If the addition of another Alternate Bid item listed in the Bid Form would make the total amount exceed the available funds, it will  be  skipped and  the next  subsequent Alternate Bid  in a  lower amount will  be added, provided the total amount does not exceed the available funds. 

D. Award will be made to the responsible Bidder that provides the lowest Bid amount for any combination  of  Base  Bid  plus  selected  additive  Alternate  Bids  which  Buyer  determines provides the most beneficial combination of alternatives within the funds available. 

12.03 Buyer’s Contingency Allowance 

A. If  Buyer  has  stipulated  a  Buyer’s  Contingency  Allowance  in  the  Bid  Form,  such  Buyer’s Contingency Allowance  is  the  same  for all Bidders and  is not a  factor  in determining  the apparent low Bid. 

ARTICLE 13—SUBMITTAL OF BID 

13.01 Bidder shall refer to the Advertisement for Bids for specific identification of the date, time, and place where Bids are to be submitted. 

13.02 Bidder must submit one separate unbound copy of the completed Bid Form, and, if required, the Bid Security and the other documents required to be submitted under the terms of Article 4 of the Bid Form. 

13.03 A Bid must be submitted no later than the date and time prescribed and at the place indicated in the advertisement or  invitation to bid. Submit  the Bid  in an envelope plainly marked with  the Project  title  (and,  if  applicable,  the  designated  portion  of  the  Project  for  which  the  Bid  is 

Page 15: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐200, Instructions to Bidders for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 6 of 7 

STV‐00 20 00 Instructions to Bidders for Procurement 2019.docx 00 20 00‐6 

submitted) and the name and address of Bidder. Enclose the Bid security and other documents required to be submitted with the Bid as listed in the Bid Form. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” 

ARTICLE 14—MODIFICATION OR WITHDRAWAL OF BID 

14.01 A Bid may be modified or withdrawn by a document duly signed in the same manner that a Bid must be signed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. 

14.02 If, within 24 hours after Bids are opened, any Bidder files a duly signed written notice with Buyer and promptly thereafter demonstrates to the reasonable satisfaction of Buyer that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. 

ARTICLE 15—OPENING OF BIDS 

15.01 Bids will be publicly opened at the time and place indicated in the advertisement or invitation to bid and read aloud, unless obviously non‐responsive. An abstract of the amounts of the Base Bids and Alternate Bids,  if any, will be made available  to Bidders after Bids have been opened and reviewed by the Buyer. 

ARTICLE 16—BIDS TO REMAIN SUBJECT TO ACCEPTANCE 

16.01 All Bids will remain subject to acceptance for the period stated in the Bid Form, but Buyer may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period. 

ARTICLE 17—EVALUATION OF BIDS AND AWARD OF PROCUREMENT CONTRACT 

17.01 Buyer reserves the right to reject any and all Bids, including without limitation, nonconforming, nonresponsive,  unbalanced,  or  conditional  Bids.  Buyer  also  reserves  the  right  to  waive  all informalities not involving price, time, or changes in the Goods and Special Services. 

17.02 Buyer will reject the Bid of any Bidder that Buyer finds, after reasonable inquiry and evaluation, to not be responsible. 

17.03 In evaluating Bids, Buyer will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data as may be requested in the Bid Form or may be requested from Bidders prior to a Notice of Award. 

17.04 If  Buyer  awards  the  Procurement  Contract,  such  award  will  be  to  the  responsible  Bidder submitting the lowest responsive Bid. 

ARTICLE 18—BONDS AND INSURANCE 

18.01 Article 5 of the General Conditions and Article 5 of the Supplementary Conditions set forth Buyer’s requirements as to performance and payment bonds and insurance. When the Successful Bidder 

Page 16: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐200, Instructions to Bidders for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 7 of 7 

STV‐00 20 00 Instructions to Bidders for Procurement 2019.docx 00 20 00‐7 

delivers the signed Procurement Agreement to Buyer, it must be accompanied by such bonds and acceptable evidence of insurance. 

ARTICLE 19—SIGNING OF PROCUREMENT AGREEMENT 

19.01 When Buyer  issues a Notice of Award  to  the Successful Bidder,  it will be accompanied by  the unsigned  counterparts  of  the  Procurement  Agreement  along  with  the  other  Procurement Contract  Documents  identified  in  the  Procurement  Agreement.  Within  21 days  thereafter, Successful  Bidder  must  execute  and  deliver  the  required  number  of  counterparts  of  the Procurement Agreement and any bonds and insurance documentation required to be delivered by the Procurement Contract Documents to Buyer. Within 10 days thereafter, Buyer will deliver one  fully  executed  counterpart of  the Procurement Agreement  to  Successful Bidder,  together with  printed  and  electronic  copies  of  the  Procurement  Contract  Documents  as  stated  in Paragraph 2.02 of the General Conditions. 

ARTICLE 20—SALES AND USE TAXES 

20.01 Buyer  is NOT  exempt  from Washington  State  sales  taxes  on materials  and  equipment  to  be incorporated in the Project.  

ARTICLE 21—PROCUREMENT CONTRACT TO BE ASSIGNED 

21.01 Bidder’s attention is directed to the provisions of Article 5 of the Procurement Agreement which provide for the assignment of the Procurement Contract to a construction contractor designated by the Buyer to construct the Project. Successful Bidder (Seller) will be required to perform the Procurement  Contract  after  it  has  been  assigned  to  the  construction  contractor  (Contractor Assignee)  in  accordance  with  the  provisions  in  the  Procurement  Contract.  Timing  of  the assignment is addressed in the Procurement Agreement. Forms documenting the assignment of the Procurement Contract and for the agreement of the Seller’s surety to such assignment are included as attachments to the Procurement Agreement. 

 

Page 17: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

SRF Specification Insert 1 Revised 10/24/2014

WASHINGTON STATE DEPARTMENT OF ECOLOGY

WATER POLLUTION CONTROL REVOLVING FUND

PRE SELECTION INSERT

Revised 10/24/14

The following clauses will be incorporated into equipment pre-selection contracts receiving financial assistance from the Washington State Department of Ecology Water Pollution Control Revolving Fund. In the event of conflict within the contract these clauses shall take precedence Compliance with State and Local Laws The SELLER shall assure compliance with all applicable federal, state, and local laws, requirements, and ordinances as they pertain to the design, implementation, and administration of the approved project. State Interest Exclusion Partial funding of this project is being provided through the Washington State Department of Ecology Water Pollution Control Revolving Fund. Neither the State of Washington nor any of its departments or employees are, or shall be, a party to this contract or any subcontract. Third Party Beneficiary Partial funding of this project is being provided through the Washington State Department of Ecology Water Pollution Control Revolving Fund. All parties agree that the State of Washington shall be, and is hereby, named as an express third-party beneficiary of this contract, with full rights as such. Protection of the Environment No construction related activity shall contribute to the degradation of the environment, allow material to enter surface or ground waters, or allow particulate emissions to the atmosphere, which exceed state or federal standards. Any actions that potentially allow a discharge to state waters must have prior approval of the Washington State Department of Ecology. Use of American Iron and Steel This provision applies to projects for the construction, alteration, maintenance, or repair of a “treatment works” as defined in the Federal Water Pollution Control Act (33 USC 1381 et seq.). This provision does not apply if the engineering plans and specifications for the project were approved by the Ecology prior to January 17, 2014. The SELLER acknowledges to and for the benefit of the Project Owner and the State of Washington that it understands the goods and services under this Agreement are being funded with monies made available by the Water Pollution Control Revolving Fund which contains provisions commonly known as “American Iron and Steel” that requires all of the iron and steel products used in the project be produced in the United States (“American Iron and Steel

Page 18: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

SRF Specification Insert 2 Revised 10/24/2014

Requirements”). “Iron and Steel products” means the following products made primarily of iron or steel: lined or unlined pipes and fittings, manhole covers and other municipal castings, hydrants, tanks, flanges, pipe clamps and restraints, valves, structural steel, reinforced precast concrete, and construction materials. The SELLER hereby represents and warrants to and for the benefit of the Project Owner and the State that:

(a) the SELLER has reviewed and understands the American Iron and Steel Requirements, (b) all of the iron and steel products used in the project will be and/or have been produced in the United States in a manner that complies with the American Iron and Steel Requirements, unless a waiver of the requirements is approved, and (c) the SELLER will provide any further verified information, certification or assurance of compliance with this paragraph, or information necessary to support a waiver of the American Iron and Steel Requirements, as may be requested by the Project Owner or the State.

Notwithstanding any other provision of this Agreement, any failure to comply with this paragraph by the SELLER shall permit the Project Owner or State to recover as damages against the SELLER any loss, expense or cost (including, without limitation, attorney’s fees) incurred by the Project Owner or State resulting from any such failure (including, without limitation, any impairment or loss of funding, whether in whole or in part, from the State or any damages owed to the State by the Project Owner). While the SELLER has no direct contractual privity with the State, as a lender to the Project Owner for the funding of its project, the Project Owner and the SELLER agree that the State is a third-party beneficiary and neither this paragraph (nor any other provision of the Agreement necessary to give this paragraph force or effect shall be amended or waived without the prior written consent of the State. Certification Regarding Suspension, Debarment, Ineligibility Or Voluntary Exclusion

1. The SELLER, by signing this agreement, certifies that it is not suspended, debarred, proposed for debarment, declared ineligible or otherwise excluded from contracting with the federal government, or from receiving contracts paid for with federal funds. If the SELLER is unable to certify to the statements contained in the certification, they must provide an explanation as to why they cannot.

2. The SELLER shall provide immediate written notice to the Washington State Department

of Ecology if at any time the SELLER learns that its certification was erroneous when submitted or had become erroneous by reason of changed circumstances.

3. The terms covered transaction, debarred, suspended, ineligible, lower tier covered

transaction, participant, person, primary covered transaction, principal, proposal, and voluntarily excluded, as used in this clause, have the meaning set out in the Definitions and Coverage sections of rules implementing Executive Order 12549. You may contact the Washington State Department of Ecology for assistance in obtaining a copy of the

Page 19: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

SRF Specification Insert 3 Revised 10/24/2014

regulations.

4. The SELLER agrees it shall not knowingly enter into any lower tier covered transaction with a person who is proposed for debarment under the applicable Code of Federal Regulations, debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction.

5. The SELLER further agrees by signing this agreement, that it will include this clause

titled “Certification Regarding Suspension, Debarment, Ineligibility Or Voluntary Exclusion” without modification in all lower tier covered transactions and in all solicitations for lower tier covered transactions.

6. Pursuant to 2CFR180.330, the SELLER is responsible for ensuring that any lower tier

covered transaction complies with certification of suspension and debarment requirements.

7. The SELLER acknowledges that failing to disclose the information required in the Code

of Federal Regulations may result in the delay or negation of this funding agreement, or pursuance of legal remedies, including suspension and debarment.

8. The SELLER agrees to keep proof in its agreement file that it and all lower tier recipients

or SELLERs are not suspended or debarred and will make this proof available to the Washington State Department of Ecology upon request. The RECIPIENT/SELLER must run a search in http://www.sam.gov/ and print a copy of completed searches to document proof of compliance.

This term and condition supersedes EPA Form 5700-49, “Certification Regarding Debarment, Suspension, and Other Responsibility Matters.” Disadvantaged Business Enterprises General Compliance (40 CFR Part 33). The SELLER shall comply with the requirements of the Environmental Protection Agency’s Program for Participation By Disadvantaged Business Enterprises (DBE) 40 CFR Part 33. Non-discrimination Provision (40CFR Appendix A to Part 33). The SELLER shall not discriminate on the basis of race, color, national origin or sex in the performance of this contract. The SELLER shall carry out applicable requirements of 40 CFR part 33 in the award and administration of contracts awarded under EPA financial assistance agreements. Failure by the SELLER to carry out these requirements is a material breach of this contract which may result in the termination of this contract or other legally available remedies. The SELLER shall comply with all federal and state nondiscrimination laws, including, but not limited to Title VI and VII of the Civil Rights Act of 1964, Section 504 of the Rehabilitation Act of 1973, Title IX of the Education Amendments of 1972, the Age Discrimination Act of 1975, and Chapter 49.60 RCW, Washington’s Law Against Discrimination, and 42 U.S.C. 12101 et seq, the Americans with Disabilities Act (ADA).

Page 20: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

SRF Specification Insert 4 Revised 10/24/2014

Six Good Faith Efforts (40 CFR Part 33 Subpart C). The SELLER agrees to make the following good faith efforts whenever procuring subcontracts, equipment, services and supplies. The SELLER shall retain records documenting compliance with the following six good faith efforts. Ensuring Disadvantaged Business Enterprises are made aware of contracting

opportunities to the fullest extent practicable through outreach and recruitment activities. For Indian Tribal, State and Local and Government recipients, this will include placing Disadvantaged Business Enterprises on solicitation lists and soliciting them whenever they are potential sources. Qualified Women and Minority business enterprises may be found on the Internet at www.omwbe.wa.gov or by contacting the Washington State Office of Minority and Women’s Enterprises at (866) 208-1064.

Making information on forthcoming opportunities available to Disadvantaged Business Enterprises and arrange time frames for contracts and establish delivery schedules, where the requirements permit, in a way that encourages and facilitates participation by Disadvantaged Business Enterprises in the competitive process. This includes, whenever possible, posting solicitations for bids or proposals for a minimum of thirty (30) calendar days before the bid or proposal closing date.

Considering in the contracting process whether firms competing for large contracts could subcontract with Disadvantaged Business Enterprises. For Indian Tribal, State and local Government recipients, this will include dividing total requirements when economically feasible into smaller tasks or quantities to permit maximum participation by Disadvantaged Business Enterprises in the competitive process.

Encourage contracting with a consortium of Disadvantaged Business Enterprises when a contract is too large for one of these firms to handle individually.

Using services and assistance of the Small Business Administration and the Minority Business Development Agency of the Department of Commerce.

If the prime SELLER awards subcontracts, requiring the subcontractors to take the six good faith efforts in paragraphs 1 through 5 above.

Page 21: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-400, Bid Form for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. TOC Page 1 of 1

STV-00 40 00 Bid Form for Procurement 2019.docx 00 40 00 - i

SECTION 00 40 00 - BID FORM FOR PROCUREMENT CONTRACT

TABLE OF CONTENTS

Page

Article 1— Buyer and Bidder ........................................................................................................................ 1

Article 2— Basis of Bid .................................................................................................................................. 1

Article 3— Time of Completion .................................................................................................................... 2

Article 4— Attachments to this Bid .............................................................................................................. 2

Article 5— Bidder’s Acknowledgments......................................................................................................... 2

Article 6— Bidder’s Representations and Certifications............................................................................... 3

Page 22: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-400, Bid Form for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 1 of 5

STV-00 40 00 Bid Form for Procurement 2019.docx 00 40 00 - 1

SECTION 00 40 00 - BID FORM FOR PROCUREMENT CONTRACT

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—BUYER AND BIDDER

1.01 This Bid is submitted to: City of Stevenson

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into a Procurement Contract with Buyer in the form included in the Procurement Bidding Documents, and to furnish the Goods and Special Services as specified or indicated in the Procurement Bidding Documents, for the prices and within the times indicated in this Bid, and in accordance with the other terms and conditions of the Procurement Bidding Documents.

ARTICLE 2—BASIS OF BID

2.01 Bidder will furnish the Goods and Special Services in accordance with the Procurement Contract Documents for the following Procurement Contract Price(s) in the Bid Schedule below. Refer to the Specification Sections for descriptions of the Bid Items. Bidder acknowledges that each unit price includes an amount considered by Bidder to be adequate to cover Bidder’s overhead and profit for each separately identified item.

Major Equipment Bid Item (Enter Bid for One Specification Section Only and Submit a Separate Bid Form and Attachments for each Major Equipment Item to be Bid. A single Bid Form shall be submitted for both Paragraphs 1.05.B and 1.05.C for Section 46 51 33 - Fine Bubble Diffusers. All Bids must include all requirements from Divisions 0 and 1.) Price – Numerals

Section 43 11 33 Rotary Lobe Blowers $

Section 43 25 00 Submersible Screw Centrifugal Pumps $

Section 46 21 33 In-Channel Rotary Drum Screen $

Section 46 23 00 Grit Removal Equipment $

Section 46 41 34 Vertical Turbine Mixers $ Section 46 51 33 Fine Bubble Diffusers – Paragraph 1.05.B New Aeration Basin $ Alternate 1: Section 46 51 33 Fine Bubble Diffusers – Paragraph 1.05.C Oxidation Ditch $

Section 46 66 56 Ultraviolet Disinfection System $

PLUS SALES TAX 7.7% $

TOTAL BID PRICE Total Sum $

Page 23: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-400, Bid Form for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 2 of 5

STV-00 40 00 Bid Form for Procurement 2019.docx 00 40 00 - 2

ARTICLE 3—TIME OF COMPLETION

3.01 Bidder agrees that the furnishing of Goods and Special Services will conform to the schedule of Procurement Contract Times set forth in Article 2 of the Procurement Agreement.

3.02 Bidder accepts the provisions of the Procurement Agreement as to liquidated damages.

ARTICLE 4—ATTACHMENTS TO THIS BID

4.01 The following documents are attached to and made a condition of this Bid:

A. Required Bid security in the form prescribed in the Instructions to Bidders.

B. Evidence of authority to do business in the state of the Project; or a written covenant to obtain such authority within the time for acceptance of Bids.

C. Bidder Qualification Statement Form with supporting data.

D. The following information described in Specification Section 01 33 00, Submittals:

1. Paragraph 2.03.B.2: Mechanical drawings including equipment layout drawings and equipment dimensions.

2. Paragraph 2.03.C.1: Manufacturer’s catalog information.

3. Paragraph 2.03.C.2: Manufacturer’s specifications for materials and manufacturing.

4. Paragraph 2.03.C.6: Design calculations and performance curves demonstrating compliance with the performance and design criteria of the specifications.

5. Paragraph 2.03.C.15: List of all variances from the Specifications. (Note: Failure to specifically identify and fully explain all variances will be cause for rejection.)

ARTICLE 5—BIDDER’S ACKNOWLEDGMENTS

5.01 Bidder accepts all terms and conditions of the Instructions to Bidders. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period that Bidder may agree to in writing upon request of Buyer.

5.02 Bidder has examined and carefully studied the Procurement Bidding Documents, the related data identified in the Procurement Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:

Addendum No. Addendum Date

Page 24: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-400, Bid Form for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 3 of 5

STV-00 40 00 Bid Form for Procurement 2019.docx 00 40 00 - 3

5.03 Bidder acknowledges the provisions of the Agreement as to the assignment of the specified contract for procurement of goods and special services.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents that:

1. Bidder has examined and carefully studied the Procurement Contract Documents.

2. If required by the Instructions to Bidders to visit the Point of Destination and the site where the Goods are to be installed or Special Services will be provided, or if, in Bidder’s judgment, any observable local or site conditions may affect the delivery, cost, progress, or furnishing of the Goods and Special Services, then Bidder has visited the Point of Destination and site where the Goods are to be installed or Special Services will be provided (as applicable) and become familiar with and is satisfied as to the observable local and site conditions that may affect delivery, cost, progress, and furnishing of the Goods and Special Services.

3. Bidder is familiar with and is satisfied as to all Laws and Regulations that may affect the cost, progress, and performance of Seller's obligations under the Procurement Contract.

4. Bidder has carefully studied, considered, and correlated the information known to Bidder with respect to the effect of such information on the cost, progress, and performance of Seller's obligations under the Procurement Contract.

5. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Procurement Contract Documents, and the written resolution (if any) thereof by Engineer is acceptable to Bidder.

6. The Procurement Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance of Seller's obligations under the Procurement Contract.

7. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of the Bidding Requirements, that without exception the Bid (including all Bid prices) is premised upon furnishing the Goods and Special Services as required by the Procurement Contract Documents.

6.02 Bidder’s Certifications

A. Bidder certifies that:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

3. Bidder has not solicited or induced any individual or entity to refrain from bidding; and

Page 25: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-400, Bid Form for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 4 of 5

STV-00 40 00 Bid Form for Procurement 2019.docx 00 40 00 - 4

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Procurement Contract. For the purposes of this Paragraph 6.02.A.4:

a. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process;

b. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Buyer, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Buyer of the benefits of free and open competition;

c. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of Buyer, a purpose of which is to establish bid prices at artificial, non-competitive levels; and

d. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process.

Page 26: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-400, Bid Form for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 5 of 5

STV-00 40 00 Bid Form for Procurement 2019.docx 00 40 00 - 5

This Bid is offered by:

Bidder:

(typed or printed name of organization)

By: (individual’s signature) Date: (date signed) Name: (typed or printed)

Title: (typed or printed) (If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)

Attest: (individual’s signature)

Title: (typed or printed)

Address for giving notices:

Designated Representative:

Name: (typed or printed)

Title: (typed or printed) Address:

Phone:

Email:

License No.:

Classification:

Limitation:

Page 27: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐430, Bid Bond (Penal Sum Form). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 2 

STV‐00 43 00 Bid Bond Penal Sum Form 2018.docx  00 43 00 ‐ 1 

SECTION 00 43 00 ‐ BID BOND FORM 

Bidder  Surety 

Name:    Name:   

Address (principal place of business):  Address (principal place of business): 

   

Buyer  Bid 

Name:    Project (name and location): 

Address (principal place of business):   

 

Bid Due Date:   

Bond 

 Penal Sum:   

Date of Bond:   

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative. 

Bidder    Surety 

     (Full formal name of Bidder)  (Full formal name of Surety) (corporate seal)

By:      By:   

  (Signature)  (Signature) (Attach Power of Attorney)

Name:      Name:   (Printed or typed)  (Printed or typed)  

Title:      Title:   

Attest:      Attest:   (Signature)  (Signature) 

Name:      Name:   (Printed or typed)   (Printed or typed)  

Title:    Title: 

Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary. 

   

Page 28: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐430, Bid Bond (Penal Sum Form). Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 2 

STV‐00 43 00 Bid Bond Penal Sum Form 2018.docx  00 43 00 ‐ 2 

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns  to pay  to Owner upon default of Bidder  the penal sum set  forth on the  face of  this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond will be Owner’s sole and exclusive remedy upon default of Bidder. 

2. Default of Bidder occurs upon  the  failure of Bidder  to deliver within  the  time  required by  the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents. 

3. This obligation will be null and void if: 

3.1. Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or 

3.2. All Bids are rejected by Owner, or 

3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and,  if applicable, consented to by Surety when required by Paragraph 5 hereof). 

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default  from Owner, which notice will  be given with reasonable promptness,  identifying this Bond and the Project and including a statement of the amount due. 

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions does not in the aggregate exceed 120 days from the Bid due date without Surety’s written consent. 

6. No suit or action will be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety, and in no case later than one year after the Bid due date. 

7. Any suit or action under this Bond will be commenced only in a court of competent jurisdiction located in the state in which the Project is located. 

8. Notices required hereunder must be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Postal Service registered or certified mail, return receipt requested, postage pre‐paid, and will be deemed to be effective upon receipt by the party concerned. 

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby. 

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond will be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute governs and the remainder of this Bond that is not in conflict therewith continues in full force and effect. 

11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable. 

Page 29: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC C‐451, Qualifications Statement. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 6 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 1 

SECTION 00 45 10 – BIDDER QUALIFICATIONS STATEMENT 

ARTICLE 1—GENERAL INFORMATION 

1.01 Provide contact information for the Business: 

Legal Name of Business:   

Corporate Office 

Name:    Phone number:   

Title:    Email address:   

Business address of corporate office:   

 

 

Local Office 

Name:    Phone number:   

Title:    Email address:   

Business address of local office:   

 

 

1.02 Provide information on the Business’s organizational structure: 

Form of Business:  ☐ Sole Proprietorship ☐ Partnership ☐ Corporation 

☐ Limited Liability Company ☐ Joint Venture comprised of the following companies: 

  1. 

  2. 

  3. 

Provide a separate Qualification Statement for each Joint Venturer. 

Date Business was formed:    State in which Business was formed:   

Is this Business authorized to operate in the Project location?  ☐ Yes ☐ No ☐ Pending 

1.03 Identify all businesses that own Business in whole or in part (25% or greater), or that are wholly or partly (25% or greater) owned by Business: 

Name of business:    Affiliation:   

Address:   

Name of business:    Affiliation:   

Address:   

Name of business:    Affiliation:   

Address:   

Page 30: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC C‐451, Qualifications Statement. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 6 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 2 

1.04 Provide information regarding the Business’s officers, partners, and limits of authority. 

Name:    Title:  

Authorized to sign contracts:  ☐ Yes ☐ No  Limit of Authority:  $ 

Name:    Title:  

Authorized to sign contracts:  ☐ Yes ☐ No  Limit of Authority:  $ 

Name:    Title:  

Authorized to sign contracts:  ☐ Yes ☐ No  Limit of Authority:  $ 

Name:    Title:  

ARTICLE 2—LICENSING 

2.01 Provide information regarding licensure for Business: 

Name of License:   

Licensing Agency:   

License No:    Expiration Date:   

Name of License:   

Licensing Agency:   

License No:    Expiration Date:   

ARTICLE 3—DIVERSE BUSINESS CERTIFICATIONS 

3.01 Provide information regarding Business’s Diverse Business Certification, if any.  

Certification  Certifying Agency Certification 

Date 

☐ Disadvantaged Business Enterprise     

☐ Minority Business Enterprise     

☐ Woman‐Owned Business Enterprise     

☐ Small Business Enterprise     

☐ Disabled Business Enterprise     

☐ Veteran‐Owned Business Enterprise     

☐ Service‐Disabled Veteran‐Owned Business     

☐ HUBZone Business (Historically Underutilized) Business 

   

☐ Other       

☐ None 

Page 31: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC C‐451, Qualifications Statement. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 3 of 6 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 3 

ARTICLE 4—SURETY INFORMATION 

4.01 Provide information regarding the surety company that will issue required bonds on behalf of the Business, including but not limited to performance and payment bonds. 

Surety Name:   

Surety is a corporation organized and existing under the laws of the state of:   

Is surety authorized to provide surety bonds in the Project location?  ☐ Yes ☐ No 

Is surety listed in “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsuring Companies” published in Department Circular 570 (as amended) by the Bureau of the Fiscal Service, U.S. Department of the Treasury? 

☐ Yes ☐ No 

Mailing Address (principal place of business): 

 

 

 

Physical Address (principal place of business): 

 

 

 

Phone (main):    Phone (claims):   

ARTICLE 5—INSURANCE 

5.01 Provide information regarding Business’s insurance company(s), including but not limited to its Commercial General Liability carrier. Provide information for each provider. 

Name of insurance provider, and type of policy (CLE, auto, etc.):   

Insurance Provider  Type of Policy (Coverage Provided) 

   

   

   

   

Are providers licensed or authorized to issue policies in the Project location?  ☐ Yes ☐ No 

Does provider have an A.M. Best Rating of A‐VII or better?  ☐ Yes ☐ No 

Mailing Address (principal place of business): 

 

 

 

Physical Address (principal place of business): 

 

 

 

Phone (main):    Phone (claims):   

Page 32: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC C‐451, Qualifications Statement. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 4 of 6 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 4 

ARTICLE 6—CAPACITY, EXPERIENCE, AND PROJECT ORGANIZATION  

6.01 Provide information that will identify the overall size and capacity of the Business. 

Average number of current full‐time employees:   

Estimate of revenue for the previous year:   

Existing Production Utilization:   

Manufacturing Quality Assurance Program:   

6.02 Provide information regarding the Business’s previous contracting experience. 

Years of experience with projects like the proposed project: 

Has Business, or a predecessor in interest, or an affiliate identified in Paragraph 1.03: 

Been disqualified as a bidder by any local, state, or federal agency within the last 5 years? 

☐ Yes ☐ No 

Been barred from contracting by any local, state, or federal agency within the last 5 years? 

☐ Yes ☐ No 

Been released from a bid in the past 5 years? ☐ Yes ☐ No  

Defaulted on a project or failed to complete any contract or purchase order awarded to it? 

Refused to construct or refused to provide materials defined in the contract documents or 

in a change order? ☐ Yes ☐ No  

Been a party to any currently pending litigation or arbitration? ☐ Yes ☐ No 

Provide full details in a separate attachment if the response to any of these questions is Yes. 

6.03 Provide information on key individuals whom Business intends to assign to the Project.  

Team Member  Name, Title, Phone Number 

Project Manager:   

Design/Submittals:   

Manufacturing/Delivery:   

Field Services:   

 

Page 33: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC C‐451, Qualifications Statement. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 5 of 6 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 5 

6.04 List a minimum of 50 projects in Schedule A that are on‐going or have been completed for which the Seller has sold the same or similar make and model equipment proposed in Seller’s Bid and provide indicated information to demonstrate the experience and qualifications with furnishing the proposed equipment. 

ARTICLE 7—REQUIRED ATTACHMENTS 

7.01 Provide the following information with the Statement of Qualifications: 

A. If Business is a Joint Venture, separate Qualifications Statements for each Joint Venturer, as required in Paragraph 1.02. 

B. Attachments providing additional information as required by Paragraph 6.02. 

C. Schedule A (Qualifying Projects) as required by Paragraph 6.04. 

   

Page 34: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC C‐451, Qualifications Statement. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 6 of 6 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 6 

This Statement of Qualifications is offered by: 

Business:   

  (typed or printed name of organization)

By:   (individual’s signature)

Name:   (typed or printed)

Title:   (typed or printed)

Date:   (date signed)

(If Business is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.)  

Attest:   (individual’s signature)

Name:   (typed or printed) 

Title:   

  (typed or printed) 

Address for giving notices:    

   

   

Designated Representative: 

Name:   (typed or printed)

Title:   (typed or printed)

Address:    

   

   

Phone:   

Email:   

Page 35: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐451, Qualifications Statement—Schedule A—Current and Previous Contracts. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 7 

Schedule A ‐ Current and Previous Contracts for Proposed Equipment Make and Model 

Project Name  Buyer's Contact Person  Contract/PO Date and Status 

Contract/PO Amount 

Equipment Make and Model 

Peak Equipment Capacity (MGD, SCFM, or HP) 

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

Page 36: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐451, Qualifications Statement—Schedule A—Current and Previous Contracts. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 8 

Project Name  Buyer's Contact Person  Contract/PO Date and Status 

Contract/PO Amount 

Equipment Make and Model 

Peak Equipment Capacity (MGD, SCFM, or HP) 

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

Page 37: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐451, Qualifications Statement—Schedule A—Current and Previous Contracts. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 9 

Project Name  Buyer's Contact Person  Contract/PO Date and Status 

Contract/PO Amount 

Equipment Make and Model 

Peak Equipment Capacity (MGD, SCFM, or HP) 

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

Page 38: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐451, Qualifications Statement—Schedule A—Current and Previous Contracts. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 10 

Project Name  Buyer's Contact Person  Contract/PO Date and Status 

Contract/PO Amount 

Equipment Make and Model 

Peak Equipment Capacity (MGD, SCFM, or HP) 

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

Page 39: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐451, Qualifications Statement—Schedule A—Current and Previous Contracts. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 11 

Project Name  Buyer's Contact Person  Contract/PO Date and Status 

Contract/PO Amount 

Equipment Make and Model 

Peak Equipment Capacity (MGD, SCFM, or HP) 

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

  Name: Address: Telephone: 

       

Page 40: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐451, Qualifications Statement—Schedule A—Current and Previous Contracts. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. 

STV‐00 45 10 Bidder Qualifications Statement 2018.docx  00 45 10 ‐ 12 

 

 

 

 

 

 

 

PAGE INTENTIONALLY LEFT BLANK 

Page 41: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐510, Notice of Award. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 2 

STV‐00 51 00 Notice of Award 2018.docx  00 51 00 ‐ 1 

SECTION 00 51 00 ‐ NOTICE OF AWARD 

Date of Issuance:   

Buyer:    Buyer’s Project No.:   

Engineer:    Engineer’s Project No.:   

Project:   

Contract Name:   

Bidder:   

Bidder’s Address:   

You are notified that Buyer has accepted your Bid dated [    ] for the above Contract, and that you are the Successful Bidder and are awarded a Contract for: 

 

The Contract Price of the awarded Contract is $[       ]. Contract Price is subject to adjustment based on the provisions of the Contract, including but not limited to those governing changes, Unit Price Work, and Work performed on a cost‐plus‐fee basis, as applicable. 

Two (2) unexecuted counterparts of the Agreement accompany this Notice of Award, and one copy of the Contract Documents accompanies this Notice of Award, or has been transmitted or made available to Bidder electronically. 

☐ Drawings will be delivered separately from the other Contract Documents. 

You must comply with the following conditions precedent within 21 days of the date of receipt of this Notice of Award: 

1. Deliver to Buyer two (2) copies counterparts of the Agreement, signed by Bidder (as Seller). 

2. Deliver with the signed Agreement(s) the Contract security (such as required performance and payment bonds) and insurance documentation, as specified in the Instructions to Bidders and in the General Conditions, Articles 2 and 6. 

3. Other conditions precedent (if any): [              ] 

Failure to comply with these conditions within the time specified will entitle Buyer to consider you in default, annul this Notice of Award, and declare your Bid security forfeited. 

Within 10 days after you comply with the above conditions, Buyer will return to you one fully signed counterpart of the Agreement, together with any additional copies of the Contract Documents as indicated in Paragraph 2.02 of the General Conditions. 

Buyer:   

By (signature):   

Name (printed):   

Title:   

Copy:  Engineer 

Page 42: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐510, Notice of Award. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 2 

STV‐00 51 00 Notice of Award 2018.docx  00 51 00 ‐ 2 

THIS PAGE INTENTIONALLY LEFT BLANK 

Page 43: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page i of 1 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ i 

SECTION 00 52 00 ‐ AGREEMENT BETWEEN BUYER AND SELLER FOR PROCUREMENT CONTRACT 

TABLE OF CONTENTS 

Page 

Article 1— Procurement Contract ................................................................................................................ 1 1.01  Goods and Special Services ........................................................................................................... 1 1.02  The Project .................................................................................................................................... 1 1.03  Engineer ........................................................................................................................................ 1 1.04  Point of Destination ...................................................................................................................... 1 

Article 2— Procurement Contract Times ...................................................................................................... 1 2.01  Time of the Essence ....................................................................................................................... 1 2.02  Schedule of Procurement Contract Times ..................................................................................... 1 2.03  Shop Drawings and Product Data ................................................................................................. 2 2.04  Liquidated Damages ..................................................................................................................... 2 

Article 3— Procurement Contract Price ....................................................................................................... 3 3.01  Procurement Contract Price and Total Price—Based on Attached Bid ......................................... 3 

Article 4— Payment Procedures ................................................................................................................... 3 4.01  Submittal and Processing of Applications for Payment ................................................................ 3 4.02  Progress Payments; Final Payment ............................................................................................... 3 4.03  Interest .......................................................................................................................................... 4 

Article 5— Assignment of Procurement Contract ........................................................................................ 4 

Article 6— Procurement Contract Documents ............................................................................................. 6 6.01  List of Procurement Contract Documents ..................................................................................... 6 

Article 7— Seller’s Representations and Certifications ................................................................................ 7 7.01  Seller’s Representations ................................................................................................................ 7 7.02  Seller’s Certifications ..................................................................................................................... 8 

Article 8— Confidentiality ............................................................................................................................. 8 8.01  Confidential Information ............................................................................................................... 8 8.02  Disclosure of Confidential Information ......................................................................................... 9 8.03  Waiver of Immunity ...................................................................................................................... 9 

Article 9— Mutual Waiver ............................................................................................................................ 9 9.01  Mutual Waiver of Consequential Damages .................................................................................. 9 

Exhibit A— Assignment of Procurement Contract, Consent to Assignment, and Acceptance of Assignment.................................................................................................................................................. 12 

Exhibit B— Surety’s Consent to Assignment............................................................................................... 13 

 

Page 44: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 1 

AGREEMENT BETWEEN BUYER AND SELLER FOR PROCUREMENT CONTRACT 

This Procurement Agreement is by and between the City of Stevenson (“Buyer”) and [                 ] (“Seller”). 

Terms used in this Procurement Agreement have the meanings stated in the General Conditions of the Procurement Contract and the Supplementary Conditions of the Procurement Contract. 

Buyer and Seller hereby agree as follows: 

ARTICLE 1—PROCUREMENT CONTRACT 

1.01 Goods and Special Services 

A. Seller  shall  furnish  the  Goods  and  Special  Services  as  specified  or  indicated  in  the Procurement Contract Documents. The Goods and Special Services are generally described as follows:                    . 

1.02 The Project 

A. The Project, of which the Goods and Special Services are a part,  is generally described as follows: Wastewater Treatment Plant Improvements – Phase 1. 

1.03 Engineer 

A. Buyer  has  retained  Wallis  Engineering  ("Engineer"),  to  prepare  Procurement  Contract Documents  and  act  as  Buyer's  representative.  Engineer  assumes  all  duties  and responsibilities and has the rights and authority assigned to Engineer  in  the Procurement Contract Documents in connection with Seller’s furnishing of Goods and Special Services. 

1.04 Point of Destination 

A. The Point of Destination is designated as: Wastewater Treatment Plant, 686 Southwest Rock Creek Drive, Stevenson, WA 98648. 

ARTICLE 2—PROCUREMENT CONTRACT TIMES 

2.01 Time of the Essence 

A. All  time  limits  for Milestones,  including the submittal of Shop Drawings and Samples,  the delivery  of  Goods,  and  the  furnishing  of  Special  Services  as  stated  in  the  Procurement Contract Documents, are of the essence of the Procurement Contract. 

2.02 Schedule of Procurement Contract Times 

A. The following schedule sets forth the Procurement Contract Times: 

Page 45: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 2 

Milestone   Date or Days  Notes 

Submit  Shop  Drawings  and Product Data 

42 days  After Contract Times commence. 

Submit  Revisions  or  Additions  to Shop Drawings and Product Data 

14 days  After  receipt  of  each  Engineer’s Review. 

Deliver acceptable Goods to Point of Destination 

154 days  After  approval  of  shop  drawings. Delivery may  be made  in  the  15‐day period before delivery date. 

Commence  Special  Services  for Goods 

14 days  After  delivery,  date  of  Buyer’s acknowledgment of receipt. 

Complete  Special  Services  and Readiness for Final Inspection and Acceptance  of  Goods  and  Special Services 

14 days  After  commencement  of  Special Services. 

2.03 Shop Drawings and Product Data 

A. Submittal  of  Shop Drawings  and Product Data:  Seller  shall  submit  all  Shop Drawings  and Samples required by the Procurement Contract Documents to Engineer for  its review and approval. 

B. Engineer’s Review: It is the intent of the parties that Engineer will conduct its review of Shop Drawings  and  Samples  and  issue  its  approval,  or  a  denial  accompanied  by  substantive comments  regarding  information  needed  to  gain  approval,  within  14  days  after  Seller's submittal of such Shop Drawings and Samples, or within such longer period that is needed because of the quantity and quality of such submittals. Resubmittals will be limited whenever possible. 

2.04 Liquidated Damages 

A. Buyer and Seller recognize that time is of the essence as stated in Paragraph 2.01, and that Buyer will  suffer  financial and other  losses  if  the Goods are not delivered  to  the Point of Destination  and  ready  for  receipt  of  delivery  by  Buyer  within  the  time  specified  in Paragraph 2.02, plus any extensions thereof allowed in accordance with this Procurement Contract.  The  parties  also  recognize  that  the  timely  performance  of  services  by  others involved  in the Project  is materially dependent upon Seller’s specific compliance with the delivery requirements of Paragraph 2.02. Further, the parties recognize the time, expense, and difficulties  involved  in proving,  in a  legal or arbitration proceeding,  the  loss  (whether direct, consequential, or otherwise) suffered by Buyer if complete, acceptable Goods are not delivered on time. Accordingly, instead of requiring any such proof, Buyer and Seller agree that as liquidated damages for delay (but not as a penalty) Seller shall pay Buyer $1,000 for each  day  that  expires  after  the  time  specified  in  Paragraph 2.02  for  submission  of  Shop Drawings  and  Product  Data  and  delivery  of  acceptable  Goods.  Seller’s  obligation  to  pay liquidated damages shall be limited to an amount equal to ten percent (10%) of the Seller’s Contract Price. 

Page 46: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 3 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 3 

ARTICLE 3—PROCUREMENT CONTRACT PRICE 

3.01 Procurement Contract Price and Total Price—Based on Attached Bid 

A. For furnishing the Goods and Special Services in accordance with the Procurement Contract Documents, Buyer  shall pay Seller  the prices  stated  in Seller’s Bid, attached hereto as an exhibit, subject to final adjustments for Unit Price Goods and Special Services and Buyer’s Contingency Allowance, if any, and subject to the following Buyer‐accepted alternates: _____        . 

ARTICLE 4—PAYMENT PROCEDURES 

4.01 Submittal and Processing of Applications for Payment 

A. Seller  shall  submit Applications  for Payment  in accordance with Article 13 of  the General Conditions and the following paragraphs. Engineer and Buyer will process such Applications for Payment in accordance with said Article 13. 

4.02 Progress Payments; Final Payment 

A. Seller  may  submit  an  Application  for  Payment  requesting  the  stated  percentage  of Procurement Contract Price upon attainment of each of the following Payment Line Items: 

Payment Line Item (Lump Sum) Percentage of Lump Sum 

1. Receipt of Approval of Shop Drawings and Product Data  10 

2. Completion of acceptable factory testing (if any)]  5 

3. Delivery  of  Goods  to  Point  of  Destination  in  accordance  with  the Procurement Contract Documents 

70 

4. Completion  of  Special  Services  in  accordance  with  Procurement Contract Documents 

10 

5. Final  Payment:  Correction  of  non‐conformities,  provision  of  final Operations  and Maintenance manuals,  submittal  of warranties  and other  final  documentation  required  by  the  Procurement  Contract Documents 

Total Procurement Contract Price (Lump Sum)  100 

B. For Unit Price Goods and Special Services, if any, or for payments owed to Seller as a result of  authorizations  by Buyer  under  the  Buyer’s  Contingency Allowance  (if  any),  Seller  shall submit a separate Application for Payment, no more frequently than monthly, that states (1) the  actual  quantities  of  such  Unit  Price  Goods  and  Special  Services  that  have  been furnished,  and  the  applicable  unit  prices;  and  (2) the  services  or  items  performed  or furnished under the Buyer’s Contingency Allowance, and the amounts owed. If practical, and at Seller’s option, Seller may apply for such unit price and Buyer’s Contingency Allowance payments  in  a  separate  section  of  an  Application  for  Payment  submitted  under Paragraph 4.02.A for lump sum items. 

Page 47: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 4 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 4 

C. Buyer shall pay Seller the amount owed under an Application for Payment within 30 days after  Engineer’s  presentation  to  Buyer  of  the  Application  for  Payment  and  Engineer’s recommendation. 

4.03 Interest 

A. All amounts not paid when due will bear interest at the state statutory rate. 

ARTICLE 5—ASSIGNMENT OF PROCUREMENT CONTRACT 

A. Buyer has  the  right  to assign  this Procurement Contract  for  furnishing Goods and Special Services, but only to a person or entity with sufficient apparent ability to satisfy all of Buyer's obligations under this Procurement Contract, and Seller hereby consents to such assignment. Forms documenting  the assignment of  the Procurement Contract, and consent of Seller’s surety to the assignment, have been executed by Buyer, Seller, and Seller's surety, and are attached as exhibits to this Procurement Agreement. If so, assigned the following provisions apply: 

1. The  Procurement  Contract  is  initially  executed  in  the  name  of  the  entity  identified herein  as  Buyer,  and will  be  assigned  by  such  Buyer  (as  assignor)  to  a  construction contractor (Contractor/Assignee) designated by such Buyer. The assignment will occur on the effective date of the construction contract between such Buyer (Project Owner) and  the  Contractor/Assignee,  which  is  expected  to  occur  on  or  about  3/1/2022. Commencing on the date of acceptance of assignment by the Contractor/Assignee, all references  in  the  Procurement  Contract  to  “Buyer”  shall  mean  the  designated Contractor/Assignee. 

2. The  assignment  of  this  Procurement  Contract  relieves  the  assignor  from  all  further obligations  and  liabilities  under  this  Procurement  Contract.  After  assignment,  Seller shall  become a  subcontractor  or  supplier  to  the Contractor/Assignee  and,  except  as noted  herein,  all  rights,  duties,  and  obligations  of  Buyer  under  the  Procurement Contract become the rights, duties, and obligations of the Contractor/Assignee. 

3. After assignment: 

a. The  Procurement  Drawings  and  Procurement  Specifications,  and  any modifying Addenda will become “Contract Documents” under the construction contract. 

b. If  the  Procurement  Drawings  or  Procurement  Specifications,  as  “Contract Documents”  under  the  construction  contract,  are  duly  modified  under  such construction  contract,  then  Seller  and  Contractor/Assignee  shall  enter  into  a corresponding Change Order under the applicable provisions of this Procurement Contract. 

c. The Procurement Drawings and Procurement Specifications may not be modified by Seller or Contractor/Assignee, singly or in tandem, except as such Procurement Drawings  or  Procurement  Specifications,  as  “Contract  Documents”  under  the construction contract, have been duly modified under such construction contract. 

d. All  performance  warranties,  guarantees,  and  indemnifications  required  by  the Procurement  Contract  will  continue  to  run  for  the  benefit  of  assignor  (Project 

Page 48: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 5 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 5 

Owner) and,  in addition,  for the benefit of the Contractor/Assignee. However,  if assignor  (Project  Owner)  and  Contractor/Assignee make  the  same  warranty  or guarantee claim, then Seller shall only be liable once for such claim. Other than its remedies under such warranties, guarantees, and  indemnifications, assignor will not retain direct rights under this Procurement Contract, but will have rights and remedies  as  a  party  to  the  construction  contract,  whose  scope  of  work  will encompass the Procurement Drawings, Procurement Specifications, and modifying Addenda;  provided,  however,  that  any  limitations  on  Seller’s  liability  in  this Procurement  Contract  will  continue  to  bind  the  original  Buyer  (assignor)  after assignment. 

e. The  Contractor/Assignee  shall  have  all  the  rights  of  the  Buyer  under  the Performance Bond and Payment Bond. 

f. Seller shall submit all Applications for Payment directly to Contractor/Assignee. 

1) Contractor/Assignee  shall  review  each  Application  for  Payment  promptly, determine the amount that Contractor/Assignee approves for payment, and then  include  the  amount  approved  in  the  next  application  for  payment submitted to Project Owner (or Engineer) under the construction contract. 

2) Contractor/Assignee shall pay Seller within 30 days of receipt of payment from the Project Owner under the construction contract. 

3) After  assignment  Engineer  will  review,  approve,  or  deny  the  content  of Applications for Payment under the Procurement Contract only to the extent that Contractor/Assignee, as construction contractor, has incorporated such content  into  payment  applications  that  Engineer  reviews  under  the construction contract. 

g. The Contractor/Assignee shall have all the rights of the Buyer under any pending Claim by Buyer. 

h. All Claims and supporting documentation will be submitted directly by the claimant party (either Contractor/Assignee or Seller), to the other party, without submittal to Engineer. 

1) The other party will render a response in writing within 30 days of receipt of the last submittal of claimant. 

2) If the other party does not render a written response to a Claim within 30 days after  receipt  of  the  last  submittal  of  the  claimant,  the other  party  shall  be deemed to have approved the Claim in its entirety. 

3) The other party’s written response to a Claim, or the approval of the Claim in its entirety as a function of failure to respond within 30 days, will be final and binding upon Buyer and Seller 30 days after it is issued, unless within such 30 days  of  issuance  either  Buyer  or  Seller  appeals  the  result  by  initiating  the mediation of the Claim in accordance with the dispute resolution procedures set forth in Paragraph 12.02 of the General Conditions. 

Page 49: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 6 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 6 

4) Any Claim by Seller that Contractor/Assignee may choose to submit, present, or forward to Project Owner must be submitted to Buyer within sufficient time for Contractor/Assignee to preserve its rights under the construction contract, notwithstanding any procedures or time limits in this Procurement Contract. 

i. Seller’s  recovery  of  additional  cost,  time,  or  both  cost  and  time  for  any  Claim attributable to the Project Owner will be limited to the proportionate recovery by Contractor/Assignee against Project Owner  for  such Claim.  Seller will  cooperate and  assist  Contractor/Assignee  in  pursuing  any  Claim  by  Contractor/Assignee against  Project Owner  on behalf  of  Seller,  including  the  timely  preparation  and delivery of supporting documentation. 

j. If the pursuit of any claim by Contractor/Assignee against Project Owner on Seller’s behalf requires the expenditure by Contractor/Assignee of legal or consulting fees, or  results  in  litigation,  arbitration,  or  any  dispute  resolution  procedures,  Seller agrees  to pay  for a proportionate  share of attorneys’  fees,  consultant  fees, and litigation, arbitration, and other resolution costs incurred by Contractor/Assignee in pursuing the claim on behalf of Seller, based upon the amount claimed by Seller as compared to the total value of the claim pursued by the Contractor/Assignee. 

k. All  rights,  duties,  and  obligations  of  Engineer  to  Contractor/Assignee  and  Seller under this Procurement Contract will cease. 

l. Subject to the foregoing provisions, all references in the Procurement Contract to submitting  items  to Engineer, or  to Engineer having  tasks or obligations, will be read after such an assignment as requiring submittal to Contractor/Assignee, or as Contractor/Assignee having such tasks or obligations (which Contractor/Assignee may delegate when appropriate). 

m. If  the  Procurement  Contract  includes  a  Buyer’s  Contingency  Allowance,  upon assignment such allowance will be automatically reduced to the amount previously authorized by Buyer (Project Owner), and cease to be operational. 

B. No other assignment by a party hereto of any rights under or interests in the Procurement Contract will be binding on another party hereto without the written consent of the party sought to be bound. Specifically, but without limitation, Procurement Contract payments or other money that may become due, and Procurement Contract payments or other money that are due, may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by Laws and Regulations). Unless specifically stated to the contrary in any written consent to such an assignment, such an assignment will not release or discharge the assignor from any duty or responsibility under the Procurement Contract Documents. 

ARTICLE 6—PROCUREMENT CONTRACT DOCUMENTS 

6.01 List of Procurement Contract Documents 

A. The Procurement Contract Documents consist of the following: 

1. This Procurement Agreement. 

Page 50: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 7 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 7 

2. General Conditions of the Procurement Contract. 

3. Supplementary Conditions of the Procurement Contract. 

4. Procurement  Specifications  as  listed  in  the  Procurement  Specifications  table  of contents. 

5. Procurement Drawings. 

6. Addenda Numbers     to      inclusive. 

7. Bonds:  

a. Performance bond (together with power of attorney). 

b. Payment bond (together with power of attorney). 

8. Exhibits to this Procurement Agreement (enumerated as follows): 

a. Exhibit,  Assignment  of  Contract,  Consent  to  Assignment,  and  Acceptance  of Assignment 

b. Exhibit, Surety’s Consent to Assignment 

c. Exhibit A, Seller’s Bid, solely as to the prices set forth therein (pages    1     to    5, inclusive); and 

9. The following which may be delivered or  issued on or after the Effective Date of the Procurement Contract and are not attached hereto: 

a. Change Orders; 

b. Change Directives; and 

c. Field Orders. 

B. The  documents  listed  in  Paragraph 6.01.A  are  attached  to  this  Procurement  Agreement (except as expressly noted otherwise above). 

C. There are no Procurement Contract Documents other than those listed above. 

D. The Procurement Contract Documents may only be amended or supplemented as provided in Paragraph 11.01 of the Procurement General Conditions. 

ARTICLE 7—SELLER’S REPRESENTATIONS AND CERTIFICATIONS 

7.01 Seller’s Representations 

A. In  order  to  induce  Buyer  to  enter  into  this  Procurement  Agreement,  Seller  makes  the following representations: 

1. Seller has examined and carefully studied the Procurement Contract Documents. 

2. If required by the Instructions to Bidders to visit the Point of Destination and the site where the Goods are to be installed or Special Services will be provided, or if, in Seller’s judgment, any observable local or site conditions may affect the delivery, cost, progress, or  furnishing  of  the Goods  and  Special  Services,  then  Seller  has  visited  the  Point  of Destination  and  site where  the Goods  are  to  be  installed or  Special  Services will  be 

Page 51: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 8 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 8 

provided (as applicable) and become familiar with and is satisfied as to the observable local and site conditions that may affect delivery, cost, progress, and furnishing of the Goods and Special Services. 

3. Seller is familiar with and is satisfied as to all Laws and Regulations that may affect the cost, progress, and performance of Seller's obligations under the Procurement Contract. 

4. Seller has carefully studied, considered, and correlated the information known to Seller with respect to the effect of such information on the cost, progress, and performance of Seller's obligations under the Procurement Contract. 

5. Seller  has  given  Engineer  written  notice  of  all  conflicts,  errors,  ambiguities,  or discrepancies that Seller has discovered in the Procurement Contract Documents, and the written resolution (if any) thereof by Engineer is acceptable to Seller. 

6. The Procurement Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance of Seller's obligations under the Procurement Contract. 

7. Seller’s  entry  into  this  Procurement  Contract  constitutes  an  incontrovertible representation  by  Seller  that  without  exception  all  prices  in  the  Procurement Agreement are premised upon furnishing the Goods and Special Services as required by the Procurement Contract Documents. 

7.02 Seller’s Certifications 

A. Seller certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in  competing  for  or  in  executing  the  Procurement  Contract.  For  the  purposes  of  this Paragraph 7.02: 

1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely  to  influence  the  action  of  a  public  official  in  the  bidding  process  or  in  the Procurement Contract execution; 

2. “fraudulent  practice”  means  an  intentional  misrepresentation  of  facts  made  (a) to influence  the  bidding  process  or  the  execution  of  the  Procurement  Contract  to  the detriment of Buyer, (b) to establish bid or contract prices at artificial non‐competitive levels, or (c) to deprive Buyer of the benefits of free and open competition; 

3. “collusive practice” means a  scheme or arrangement between  two or more Bidders, with or without the knowledge of Buyer, a purpose of which is to establish bid prices at artificial, non‐competitive levels; and 

4. “coercive  practice”  means  harming  or  threatening  to  harm,  directly  or  indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Procurement Contract. 

ARTICLE 8—CONFIDENTIALITY 

8.01 Confidential Information 

A. Confidential information is information in documents submitted by Seller that Seller clearly and  prominently  labels  in writing  to  be  a  trade  secret,  proprietary,  or  confidential.  Such 

Page 52: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 9 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 9 

documents,  if  any,  will  be  maintained  in  a  manner  that  endeavors  to  avoid  disclosing confidential information to third parties, to the extent allowed by Laws and Regulations. 

B. Seller  shall  clearly  and  prominently  mark  confidential  information  with  the  word “CONFIDENTIAL”  on  each  page  or  sheet  or  on  the  cover  of  bound  documents.  Place “CONFIDENTIAL”  stamps or watermarks  so  that  they do not obscure  any of  the  required information on the document, either in the original or in a way that would obscure any of the required information in a photocopy of the document. 

8.02 Disclosure of Confidential Information 

A. If Buyer is requested to disclose confidential information, or becomes legally compelled (by oral questions,  interrogatories,  requests  for  information or documents,  subpoena, civil or criminal  investigative demand, public  information requests, or other requests under Laws and Regulations) to disclose confidential  information, or  is required by a regulatory body, governing agency, or controlling authority to disclose confidential information, or make any other disclosure that is prohibited or otherwise constrained by the Procurement Contract, Buyer will provide Seller with prompt notice so Seller may seek an appropriate protective order or other remedy. Seller will be solely responsible for submitting to the regulatory body, governing  agency,  or  controlling  authority  any  arguments,  briefs,  memoranda,  motions, authorities, or other information in opposition to disclosure. 

B. Buyer’s obligations with  respect  to  confidential  information are nullified by  the  following exceptions: 

1. Confidential information becomes a part of the public domain through publication or otherwise, through no fault of the Buyer; 

2. Buyer  can  demonstrate  through  suitable  documentation  that  the  confidential information  was  already  in  the  Buyer’s  possession,  and  not  previously  marked  as confidential,  or  was  otherwise  publicly  available  prior  to  the  Effective  Date  of  the Procurement Contract; 

3. The confidential information is subsequently and independently disclosed to the Buyer by a third party who has a lawful right to disclose such information; 

4. Buyer has a good faith belief that disclosure is required or justified; or 

5. Buyer is required to disclose the confidential information by court order or by applicable Laws and Regulations. 

8.03 Waiver of Immunity 

A. Notwithstanding any other provision of the Procurement Contract, it is stipulated and agreed that  by  accepting  confidential  information,  Buyer  has  not  and  does  not  waive  its  legal immunity (if any) from suit or liability. 

ARTICLE 9—MUTUAL WAIVER 

9.01 Mutual Waiver of Consequential Damages 

A. Buyer  and  Seller  waive  against  each  other,  and  against  the  other’s  officers,  directors, members, partners, employees, agents, consultants, and subcontractors, any and all claims 

Page 53: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 10 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 10 

for or entitlement to incidental, indirect, or consequential damages arising out of, resulting from,  or  related  to  the  Procurement  Contract.  If  Buyer  (Project  Owner)  assigns  this Procurement Contract to a construction contractor (Contractor/Assignee), then the terms of this Paragraph 9.01.A will be binding upon the Contractor/Assignee with respect  to Seller and assignor. The terms of this mutual waiver do not apply to or limit any claim by either Buyer  or  Seller  against  the  other  based  on  any  of  the  following:  (a) contribution  or indemnification,  (b) liquidated  damages,  (c) costs,  losses,  or  damages  attributable  to personal or bodily  injury, sickness, disease, or death, or  to  injury to or destruction of  the tangible  property  of  others,  (d) intentional  or  reckless  wrongful  conduct,  or  (e) rights conferred by any bond provided by Seller under this Procurement Contract. 

   

Page 54: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 11 of 14 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 11 

IN WITNESS WHEREOF, Buyer and Seller have signed this Procurement Agreement. Counterparts have been delivered to Buyer and Seller. 

The Effective Date of the Procurement Contract is       . 

Buyer    Seller 

     (typed or printed name of organization) (typed or printed name of organization)

By:      By:   (individual’s signature)  (individual’s signature)

Date:      Date:   (date signed)  (date signed) 

Name:      Name:   (typed or printed)  (typed or printed) 

Title:      Title:   (typed or printed)  (typed or printed) 

 (If Seller is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.) 

Attest:      Attest:   (individual’s signature)  (individual’s signature)

Title:      Title:   (typed or printed)  (typed or printed) 

Address for giving notices:    Address for giving notices: 

     

     

     

Designated Representative:    Designated Representative: 

Name:      Name:   (typed or printed)  (typed or printed) 

Title:      Title:   (typed or printed)  (typed or printed) 

Address:    Address: 

     

     

     

Phone:      Phone:   

Email:      Email:   (If Buyer is a corporation, attach evidence of authority to sign. If Buyer is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of this Agreement.)   

 

Page 55: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

Exhibit A—Assignment of Procurement Contract, Consent to Assignment, and Acceptance of Assignment. EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. 

Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 

Page 12 of 1 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 12 

EXHIBIT A—ASSIGNMENT  OF  PROCUREMENT  CONTRACT,  CONSENT  TO  ASSIGNMENT,  AND ACCEPTANCE OF ASSIGNMENT 

This assignment will be effective on the effective date of the construction contract between Buyer (as “Owner”) and Contractor/Assignee (as “Contractor”). 

The Procurement Contract between [insert name of original Buyer] (“Buyer”) and [insert name of Seller] (“Seller”)  for furnishing Goods and Special Services entitled  [insert name/designation of Procurement Contract] (Procurement Contract) is hereby assigned, transferred, and set over to Contractor/Assignee, as assignee, by Buyer, as assignor. Upon assignment the Contractor/Assignee shall have the duties, rights, and obligations of Buyer under the terms of the Procurement Contract, and will be responsible to Owner under  the  construction  contract  for  the  performance  of  obligations  by  Seller,  which  will  become  a Subcontractor  or  Supplier  to  Contractor/Assignee.  Buyer,  Seller,  and  Contractor/Assignee  hereby acknowledge and agree to be bound by the terms and conditions of assignment set forth in Article 5 of the Agreement Between Buyer and Seller for Procurement Contract. 

Assignment Made by Buyer 

 (typed or printed name of organization)

By:    Date:   (individual’s signature) (date signed) 

Name:    Title:   (typed or printed) (typed or printed) 

If Buyer is a corporation, attach evidence of authority to sign. If Buyer is a public body, attach evidence of authority to sign and resolution or other documents authorizing execution of Buyer‐Seller Agreement. 

 

Assignment Acknowledged and Accepted by Seller 

 (typed or printed name of organization)

By:    Date:   (individual’s signature) (date signed) 

Name:    Title:   (typed or printed) (typed or printed) 

If Seller is a corporation, attach evidence of authority to sign. 

 

Assignment Accepted by Contractor/Assignee 

 (typed or printed name of organization)

By:    Date:   (individual’s signature) (date signed) 

Name:    Title:   (typed or printed) (typed or printed) 

If Contractor/Assignee is a corporation, attach evidence of authority to sign. 

Page 56: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

Exhibit B—Surety’s Consent to Assignment. EJCDC® P‐520, Agreement between Buyer and Seller for Procurement Contract. 

Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. 

Page 13 of 1 

STV‐00 52 00 Agreement for Procurement 2019.docx  00 52 00 ‐ 13 

EXHIBIT B—SURETY’S CONSENT TO ASSIGNMENT 

Surety hereby acknowledges, agrees, and consents that the Procurement Contract for furnishing Goods and Special Services entitled [Name of Procurement Contract] by and between [Name of Buyer] (“Buyer”) and  [Name  of  Seller]  (“Seller”)  may  be  assigned,  transferred,  and  set  over  to  [Name  of Contractor/Assignee]  (“Contractor/Assignee”),  in  accordance  with  Article 5  and  Exhibit  A  of  the Agreement between Buyer and Seller for Procurement Contract. 

Surety further agrees that, upon assignment of the Procurement Contract, the Contractor/Assignee shall have all  the rights of the Buyer under the Procurement Performance Bond and Procurement Payment Bond. 

Agreement to Assignment Acknowledged and Accepted by Surety 

 (typed or printed name of organization)

By:    Date:   (individual’s signature) (date signed) 

Name:    Title:   (typed or printed) (typed or printed) 

Attach Power of Attorney. 

 

Page 57: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐550, Notice to Proceed. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 2 

STV‐00 55 00 Notice to Proceed 2018.docx  00 55 00 ‐ 1 

SECTION 00 55 00 ‐ NOTICE TO PROCEED 

Buyer:    Buyer’s Project No.:   

Engineer:    Engineer’s Project No.:   

Seller:    Seller’s Project No.:   

Project:   

Contract Name:   

Effective Date of Contract:   

Buyer hereby notifies Seller that the Contract Times under the above Contract will commence to run on        . 

On that date, Seller shall start performing its obligations under the Contract Documents. No Work will be done prior to such date. 

In accordance with the Agreement: 

The number of days from the commencement date of the Contract Times to submit Shop Drawings and Product Data is 42 days. 

The number of days from Shop Drawing and Product Data approval to deliver the Goods is 154 days. 

Before starting any Work, Seller must comply with the following: 

 

 

 

Buyer:   

By (signature):   

Name (printed):   

Title:   

Date Issued:   

Copy:  Engineer 

   

Page 58: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C‐550, Notice to Proceed. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 2 

STV‐00 55 00 Notice to Proceed 2018.docx  00 55 00 ‐ 2 

THIS PAGE INTENTIONALLY LEFT BLANK 

Page 59: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐610, Performance Bond for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 4 

STV‐00 61 00 Performance Bond for Procurement 2019.docx  00 61 00 ‐ 1 

SECTION 00 61 00 ‐ PERFORMANCE BOND FOR PROCUREMENT CONTRACT 

Seller  Surety 

Name:    Name:   

Address (principal place of business):  Address (principal place of business): 

   

Buyer  Procurement Contract 

Name:    Description (name and location): 

Mailing address (principal place of business):   

 

Procurement Contract Price: 

 

Effective Date of Procurement Contract: 

 

Bond   

Bond Amount:   

Date of Bond:   (Date of Bond cannot be earlier than Effective Date of Procurement Contract) 

Modifications to this Bond form: 

☐ None ☐ See Paragraph 15 

Surety and Seller, intending to be legally bound hereby, subject to the terms set forth in this Performance Bond, do each cause this Performance Bond to be duly executed by an authorized officer, agent, or representative. 

Seller as Principal    Surety 

     

(Full formal name of Seller)  (Full formal name of Surety) (corporate seal)

By:      By:   (Signature)  (Signature)(Attach Power of Attorney)

Name:      Name:   (Printed or typed)  (Printed or typed) 

Title:      Title:   

Attest:      Attest:   (Signature)  (Signature) 

Name:      Name:   (Printed or typed)  (Printed or typed) 

Title:      Title:   

Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to Seller, Surety, Buyer, or other party is considered plural where applicable. 

Page 60: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐610, Performance Bond for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 4 

STV‐00 61 00 Performance Bond for Procurement 2019.docx  00 61 00 ‐ 2 

The Seller and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, 

successors, and assigns to the Buyer for the performance of the Procurement Contract, which is 

incorporated herein by reference. 

1. If the Seller performs the Procurement Contract, the Surety and the Seller shall have no obligation under this Bond, except when applicable to participate in a conference as provided in Paragraph 2. 

2. If there is no Buyer Default under the Procurement Contract, the Surety’s obligation under this Bond will arise after: 

2.1. The  Buyer  first  provides  notice  to  the  Seller  and  the  Surety  that  the  Buyer  is  considering declaring  a  Seller  Default.  Such  notice  may  indicate  whether  the  Buyer  is  requesting  a conference among the Buyer, Seller, and Surety to discuss the Seller’s performance. If the Buyer does not request a conference, the Surety may, within five (5) business days after receipt of the Buyer’s notice, request such a conference. If the Surety timely requests a conference, the Buyer shall  attend.  Unless  the  Buyer  agrees  otherwise,  any  conference  requested  under  this Paragraph will be held within ten (10) business days of the Surety’s receipt of the Buyer’s notice. If the Buyer, the Seller, and the Surety agree, the Seller shall be allowed a reasonable time to perform the Procurement Contract, but such an agreement does not waive the Buyer’s right, if any, subsequently to declare a Seller Default; 

2.2. The  Buyer  declares  a  Seller  Default,  terminates  the  Procurement  Contract,  and  notifies  the Surety; and 

2.3. The Buyer has agreed to pay the Balance of the Procurement Contract Price in accordance with the  terms of  the Procurement Contract  to  the Surety or  to a  seller  selected  to perform  the Procurement Contract. 

3. Failure on the part of  the Buyer to comply with the notice requirement  in Paragraph 2.1 does not constitute a failure to comply with a condition precedent to the Surety’s obligations, or release the Surety from its obligations, except to the extent the Surety demonstrates actual prejudice. 

4. When  the Buyer has  satisfied  the  conditions of Paragraph 2,  the Surety  shall  promptly and at  the Surety’s expense take one of the following actions: 

4.1. Arrange for the Seller, with the consent of the Buyer, to perform and complete the Procurement Contract; 

4.2. Undertake  to  perform  and  complete  the  Procurement  Contract  itself,  through  its  agents  or independent contractors; 

4.3. Obtain bids or negotiated proposals from qualified sellers acceptable to the Buyer for a contract for performance and  completion of  the Procurement Contract,  arrange  for  a  contract  to be prepared for execution by the Buyer and a seller selected with the Buyer’s concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the bonds issued on the Procurement Contract, and pay to the Buyer the amount of damages as described in Paragraph 7 in excess of the Balance of the Procurement Contract Price incurred by the Buyer as a result of the Seller Default; or 

Page 61: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐610, Performance Bond for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 3 of 4 

STV‐00 61 00 Performance Bond for Procurement 2019.docx  00 61 00 ‐ 3 

4.4. Waive its right to perform and complete, arrange for completion, or obtain a new seller, and with reasonable promptness under the circumstances: 

4.4.1. After investigation, determine the amount for which Surety may be liable to the Buyer and,  as  soon  as  practicable  after  the  amount  is  determined, make  payment  to  the Buyer; or 

4.4.2. Deny liability in whole or in part and notify the Buyer, citing the reasons for denial. 

5. If the Surety does not proceed as provided in Paragraph 4 with reasonable promptness, the Surety shall be deemed to be in default on this Bond seven (7) days after receipt of an additional written notice  from the Buyer  to  the Surety demanding that  the Surety perform  its obligations under  this Bond, and  the Buyer  shall be entitled  to enforce any  remedy available  to  the Buyer.  If  the Surety proceeds as provided in Paragraph 4.4, and the Buyer refuses the payment, or the Surety has denied liability, in whole or in part, without further notice, the Buyer shall be entitled to enforce any remedy available to the Buyer. 

6. If the Surety elects to act under Paragraph 4.1, 4.2, or 4.3, then the responsibilities of the Surety to the  Buyer will  not  be  greater  than  those  of  the  Seller  under  the  Procurement  Contract,  and  the responsibilities  of  the  Buyer  to  the  Surety will  not  be  greater  than  those  of  the  Buyer  under  the Procurement  Contract.  Subject  to  the  commitment  by  the  Buyer  to  pay  the  Balance  of  the Procurement Contract Price, the Surety is obligated, without duplication for: 

6.1. the  responsibilities  of  the  Seller  for  correction  of  defective  or  non‐conforming  Goods  and Special Services, and completion of the Procurement Contract; 

6.2. additional  legal, design professional, and delay costs  resulting  from the Seller’s Default, and resulting from the actions or failure to act of the Surety under Paragraph 5; and 

6.3. liquidated damages, or  if  no  liquidated damages are  specified  in  the Procurement Contract, actual damages caused by delayed performance or non‐performance of the Seller. 

7. If the Surety elects to act under Paragraph 4.1, 4.3, or 4.4, the Surety’s liability is limited to the amount of this Bond. 

8. The Surety shall not be liable to the Buyer or others for obligations of the Seller that are unrelated to the Procurement Contract, and the Balance of the Procurement Contract Price will not be reduced or set off on account of any such unrelated obligations. No right of action will accrue on this Bond to any person or entity other than the Buyer or its heirs, executors, administrators, successors, and assigns. 

9. The  Surety  hereby  waives  notice  of  any  change,  including  changes  of  time,  to  the  Procurement Contract or to related subcontracts, purchase orders, and other obligations. 

10. Any proceeding,  legal or equitable, under  this Bond must be  instituted  in any court of competent jurisdiction where the Point of Destination is located and must be instituted within two years after a declaration of Seller Default, or within two years after the Seller ceased working, or within two years after the Surety refuses or fails to perform its obligations under this Bond, whichever occurs first. If the provisions of this Paragraph are void or prohibited by  law, the minimum periods of  limitations available to sureties as a defense in the jurisdiction of the suit will be applicable. 

11. Notice to the Surety, the Buyer, or the Seller must be mailed or delivered to the address shown on the page on which their signature appears. 

12. When  this Bond has been  furnished  to comply with a  statutory or other  legal  requirement  in  the location of the Point of Destination, any provision in this Bond conflicting with said statutory or legal 

Page 62: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐610, Performance Bond for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 4 of 4 

STV‐00 61 00 Performance Bond for Procurement 2019.docx  00 61 00 ‐ 4 

requirement will be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement will be deemed incorporated herein. When so furnished, the intent is that this Bond will be construed as a statutory bond and not as a common law bond. 

13. Definitions 

13.1. Balance of the Procurement Contract Price—The total amount payable by the Buyer to the Seller under  the  Procurement  Contract  after  all  proper  adjustments  have  been  made  including allowance for the Seller for any amounts received or to be received by the Buyer in settlement of insurance or other claims for damages to which the Seller is entitled, reduced by all valid and proper payments made to or on behalf of the Seller under the Procurement Contract. 

13.2. Buyer Default—Failure of the Buyer, which has not been remedied or waived, to pay the Seller as required under the Procurement Contract or to perform and complete or comply with the other material terms of the Procurement Contract. 

13.3. Goods and Special Services—The full scope of materials, equipment, other items, and services to be furnished by Seller, as defined in the Procurement Contract. 

13.4. Point of Destination—The location where delivery of the Goods shall be made, as stated in the Procurement Contract. 

13.5. Procurement Contract—The contractual agreement between the Buyer and Seller identified on the  cover  page,  including  all  Procurement  Contract  Documents  and  changes  made  to  the Procurement Contract. 

13.6. Seller Default—Failure of  the Seller, which has not been remedied or waived,  to perform or otherwise to comply with a material term of the Procurement Contract. 

13.7. Procurement  Contract  Documents—All  the  documents  that  comprise  the  contractual agreement between the Buyer and Seller. 

14. Modifications to this Bond are as follows: [Describe modification or enter “None”] 

Page 63: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐615, Payment Bond for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 4 

STV‐00 61 50 Payment Bond for Procurement 2019.docx  00 61 50 ‐ 1 

SECTION 00 61 50 ‐ PAYMENT BOND FOR PROCUREMENT CONTRACT 

Seller  Surety 

Name:    Name:   

Address (principal place of business):  Address (principal place of business): 

   

Buyer  Procurement Contract 

Name:    Description (name and location): 

Mailing address (principal place of business):   

 

Procurement Contract Price: 

 

Effective Date of Procurement Contract: 

 

Bond   

Bond Amount:   

Date of Bond:   (Date of Bond cannot be earlier than Effective Date of Procurement Contract) 

Modifications to this Bond form: 

☐ None ☐ See Paragraph 17 

Surety and Seller, intending to be legally bound hereby, subject to the terms set forth in this Payment Bond, do each cause this Payment Bond to be duly executed by an authorized officer, agent, or representative. Seller as Principal    Surety 

     (Full formal name of Seller)  (Full formal name of Surety) (corporate seal)

By:      By:   (Signature)  (Signature)(Attach Power of Attorney)

Name:      Name:   (Printed or typed)  (Printed or typed) 

Title:      Title:   

Attest:      Attest:   (Signature)  (Signature) 

Name:      Name:   (Printed or typed)  (Printed or typed) 

Title:      Title:   

Notes: (1) Provide supplemental execution by any additional parties, such as joint venturers. (2) Any singular reference to Seller, Surety, Buyer, or other party is considered plural where applicable. 

   

Page 64: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐615, Payment Bond for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 4 

STV‐00 61 50 Payment Bond for Procurement 2019.docx  00 61 50 ‐ 2 

1. The Seller and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to the Buyer to pay for labor, materials, and equipment furnished for use in the performance of the Procurement Contract, which is incorporated herein by reference, subject to the following terms. 

2. If the Seller promptly makes payment of all sums due to Claimants, and defends,  indemnifies, and holds  harmless  the  Buyer  from  claims,  demands,  liens,  or  suits  by  any  person  or  entity  seeking payment for labor, materials, or equipment furnished for use in the performance of the Procurement Contract, then the Surety and the Seller shall have no obligation under this Bond. 

3. If  there  is no Buyer Default under  the Procurement Contract,  the Surety’s obligation  to  the Buyer under  this Bond will  arise after  the Buyer has promptly notified  the Seller  and  the Surety  (at  the address described in Paragraph 13) of claims, demands, liens, or suits against the Buyer or the Buyer’s property by any person or entity seeking payment for labor, materials, or equipment furnished for use in the performance of the Procurement Contract, and tendered defense of such claims, demands, liens, or suits to the Seller and the Surety. 

4. When  the Buyer has  satisfied  the  conditions  in Paragraph 3,  the  Surety  shall  promptly and at  the Surety’s  expense  defend,  indemnify,  and  hold  harmless  the  Buyer  against  a  duly  tendered  claim, demand, lien, or suit. 

5. The Surety’s obligations to a Claimant under this Bond will arise after the following: 

5.1. Claimants who do not have a direct contract with the Seller 

5.1.1. have furnished a written notice of non‐payment to the Seller, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were, or equipment was, furnished or supplied or for whom the labor was done or performed, within ninety (90) days after having last performed labor or last furnished materials or equipment included in the Claim; and 

5.1.2. have sent a Claim to the Surety (at the address described in Paragraph 13). 

5.2. Claimants who are employed by or have a direct contract with the Seller have sent a Claim to the Surety (at the address described in Paragraph 13). 

6. If a notice of non‐payment required by Paragraph 5.1.1  is given by  the Buyer  to  the Seller,  that  is sufficient  to  satisfy  a  Claimant’s  obligation  to  furnish  a  written  notice  of  non‐payment  under Paragraph 5.1.1. 

7. When a Claimant has satisfied the conditions of Paragraph 5.1 or 5.2, whichever  is applicable,  the Surety shall promptly and at the Surety’s expense take the following actions: 

7.1. Send an answer to the Claimant, with a copy to the Buyer, within sixty (60) days after receipt of the Claim, stating the amounts that are undisputed and the basis for challenging any amounts that are disputed; and 

7.2. Pay or arrange for payment of any undisputed amounts. 

7.3. The Surety’s failure to discharge its obligations under Paragraph 7.1 or 7.2 will not be deemed to constitute a waiver of defenses the Surety or Seller may have or acquire as to a Claim, except as  to  undisputed  amounts  for  which  the  Surety  and  Claimant  have  reached  agreement.  If, however, the Surety fails to discharge its obligations under Paragraph 7.1 or 7.2, the Surety shall indemnify  the Claimant  for  the  reasonable attorney’s  fees  the Claimant  incurs  thereafter  to recover any sums found to be due and owing to the Claimant. 

Page 65: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐615, Payment Bond for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 3 of 4 

STV‐00 61 50 Payment Bond for Procurement 2019.docx  00 61 50 ‐ 3 

8. The Surety’s total obligation will not exceed the amount of this Bond, plus the amount of reasonable attorney’s fees provided under Paragraph 7.3, and the amount of this Bond will be credited for any payments made in good faith by the Surety. 

9. Amounts  owed  by  the  Buyer  to  the  Seller  under  the  Procurement  Contract  will  be  used  for  the performance  of  the  Procurement  Contract  and  to  satisfy  claims,  if  any,  under  any  procurement performance bond. By  the Seller  furnishing and the Buyer accepting this Bond,  they agree that all funds earned by the Seller in the performance of the Procurement Contract are dedicated to satisfying obligations of the Seller and Surety under this Bond, subject to the Buyer’s priority to use the funds for the completion of the Goods and Special Services. 

10. The Surety shall not be liable to the Buyer, Claimants, or others for obligations of the Seller that are unrelated to the Procurement Contract. The Buyer shall not be liable for the payment of any costs or expenses of any Claimant under  this Bond, and shall have under  this Bond no obligation  to make payments to or give notice on behalf of Claimants, or otherwise have any obligations to Claimants under this Bond. 

11. The  Surety  hereby  waives  notice  of  any  change,  including  changes  of  time,  to  the  Procurement Contract or to related subcontracts, purchase orders, and other obligations. 

12. No suit or action will be commenced by a Claimant under this Bond other than in a court of competent jurisdiction in the state in which the Point of Destination is located or after the expiration of one year from the date (1) on which the Claimant sent a Claim to the Surety pursuant to Paragraph 5.1.2 or 5.2, or (2) on which the last labor or service was performed by anyone or the last materials or equipment were furnished by anyone under the Procurement Contract, whichever of (1) or (2) first occurs. If the provisions of this paragraph are void or prohibited by law, the minimum period of limitation available to sureties as a defense in the jurisdiction of the suit will be applicable. 

13. Notice and Claims to the Surety, the Buyer, or the Seller must be mailed or delivered to the address shown on  the page on which  their  signature appears. Actual  receipt of notice or Claims, however accomplished, will be sufficient compliance as of the date received. 

14. When this Bond has been furnished to comply with a statutory or other legal requirement where the Point  of  Destination  is  located,  any  provision  in  this  Bond  conflicting with  said  statutory  or  legal requirement will be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement will be deemed incorporated herein. When so furnished, the intent is that this Bond will be construed as a statutory bond and not as a common law bond. 

15. Upon requests by any person or entity appearing to be a potential beneficiary of this Bond, the Seller and Buyer shall promptly furnish a copy of this Bond or shall permit a copy to be made. 

16. Definitions 

16.1. Buyer Default—Failure of the Buyer, which has not been remedied or waived, to pay the Seller as required under the Procurement Contract or to perform and complete or comply with the other material terms of the Procurement Contract. 

16.2. Claim—A written statement by the Claimant including at a minimum: 

16.2.1. The name of the Claimant; 

16.2.2. The name of  the person  for whom  the  labor was done, or materials or equipment furnished; 

Page 66: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐615, Payment Bond for Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 4 of 4 

STV‐00 61 50 Payment Bond for Procurement 2019.docx  00 61 50 ‐ 4 

16.2.3. A copy of  the  agreement or purchase order pursuant  to which  labor, materials,  or equipment was furnished for use in the performance of the Procurement Contract; 

16.2.4. A brief description of the labor, materials, or equipment furnished; 

16.2.5. The date on which the Claimant  last performed  labor or  last  furnished materials or equipment for use in the performance of the Procurement Contract; 

16.2.6. The total amount earned by the Claimant for labor, materials, or equipment furnished as of the date of the Claim; 

16.2.7. The total amount of previous payments received by the Claimant; and 

16.2.8. The total amount due and unpaid to the Claimant for labor, materials, or equipment furnished as of the date of the Claim. 

16.3. Claimant—An individual or entity having a direct contract with the Seller or with a subcontractor of  the  Seller  to  furnish  labor,  materials,  or  equipment  for  use  in  the  performance  of  the Procurement  Contract.  The  term  Claimant  also  includes  any  individual  or  entity  that  has rightfully asserted a claim under an applicable mechanic’s lien or similar statute against the real property upon which the Point of Destination is located or where the Goods and Special Services are to be installed or furnished. The intent of this Bond is to include without limitation in the terms of “labor, materials, or equipment” that part of the water, gas, power,  light, heat, oil, gasoline,  telephone  service,  or  rental  equipment  used  in  the  Procurement  Contract, architectural and engineering services required for performance of the work of the Seller and the Seller’s subcontractors, and all other items for which a mechanic’s lien may be asserted in the jurisdiction where the labor, materials, or equipment were furnished. 

16.4. Goods and Special Services—The full scope of materials, equipment, other items, and services to be furnished by Seller, as defined in the Procurement Contract. 

16.5. Point of Destination—The location where delivery of the Goods shall be made, as stated in the Procurement Contract. 

16.6. Procurement Contract—The contractual agreement between the Buyer and Seller identified on the cover page,  including all Procurement Contract Documents and all  changes made to the Procurement Contract. 

16.7. Procurement  Contract  Documents—All  the  documents  that  comprise  the  contractual agreement between the Buyer and Seller. 

17. Modifications to this Bond are as follows: [Describe modification or enter “None”] 

Page 67: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐625, Buyer’s Acknowledgment of Receipt of Goods. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 1 

STV‐00 62 50 Buyer Acknowledgment of Receipt of Goods 2019.docx  00 62 50 ‐ 1 

SECTION 00 62 50 ‐ BUYER’S ACKNOWLEDGMENT RECEIPT OF GOODS 

Buyer:    Buyer’s Project No.:   Engineer:    Engineer’s Project No.:   Seller:    Seller’s Project No.:   Project:   Contract Name:   

This Buyer’s Acknowledgment of Receipt of Goods (Acknowledgment) applies to:  

☐ All Goods  ☐ The following specified portions of the Goods:  

Date of delivery of the Goods to the Point of Destination:  

Date of Buyer’s visual inspection of the Goods:  

Date of this Acknowledgment:  

Buyer acknowledges: 

1. The Goods to which this notice applies have been delivered to the Point of Destination. 

2. Buyer has visually inspected such Goods pursuant to Paragraph 9.02.B.1 of the General Conditions of the Procurement Contract.  

3. Based  on  the  visual  inspection,  such  Goods  appear  to  comply  with  the  requirements  of  the Procurement Contract Documents as to quantities and condition, subject to any exceptions and limitations in this Acknowledgment. 

4. Such Goods are deemed received for purposes of Paragraph 9.02.B.2 of the General Conditions of the Procurement Contract. 

5.  Seller may submit its Application for Payment for the delivered Goods, subject to the terms of the Procurement Agreement. 

Exceptions (if any) to this Acknowledgment: ☐ None  ☐ As follows: 

The responsibilities between Buyer and Seller for securing and storing the Goods, maintaining the Goods during storage, and for furnishing the Special Services, shall be as provided in the Procurement Contract.  

The following documents are attached to and made a part of this Acknowledgement: 

 

This  Acknowledgment  does  not  constitute  an  acceptance  of  any Goods  not  in  conformance with  the Procurement Contract Documents, nor is it a release of Seller's obligation to furnish all Goods and Special Services in accordance with the Procurement Contract. 

  Buyer Engineer, on behalf of Buyer

By (signature):       

Name (Printed):       

Title:       

Date:       

 

Page 68: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐626, Buyer’s Notice Regarding Conformity of Goods and Special Services. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 1 

STV‐00 62 60 Buyer Notice Regarding Conformity of Goods 2019.docx  00 62 60 ‐ 1 

SECTION 00 62 60 ‐ BUYER’S NOTICE REGARDING CONFORMITY OF GOODS AND SPECIAL SERVICES 

Buyer:    Buyer’s Project No.:   Engineer:    Engineer’s Project No.:   Seller:    Seller’s Project No.:   Project:   Contract Name:   Notice Date:    Effective Date of the Procurement Contract:   

Buyer hereby gives notice to Seller that, to the best of Buyer’s knowledge, information, and belief, the Goods and Special Services: 

☐  Are in conformance with the Procurement Contract Documents. Upon Seller’s submittal of its final Application for Payment in accordance with the Procurement Contract Documents, Seller will be eligible for final payment, except as expressly indicated in the Procurement Contract. 

☐  Are nonconforming with the Procurement Contract Documents for the following reason(s): 

1.   

Seller’s Special Services were completed on:  

Buyer  has  consulted with  and  received  Engineer’s  recommendation  on  conformity  of  the  Goods  and Special Services. 

This Buyer’s Notice Regarding Conformity of Goods and Special Services (Notice) is made expressly subject to the following terms and conditions to which all who receive and rely on said Notice agree:  

1. This Notice is expressly subject to the terms and conditions set forth in the Procurement Contract. 

2. This Notice is not a guarantee or warranty of Seller’s performance under the Procurement Contract, an acceptance of Goods and Special Services that are not in accordance with the related Procurement Contract  Documents,  including  but  not  limited  to  nonconforming  Goods  and  Special  Services discovered after final inspection, nor an assumption of responsibility for any failure of Seller to furnish the  Goods  and  Special  Services  thereunder  in  accordance  with  the  Procurement  Contract,  or  to otherwise comply with the Procurement Contract Documents or the terms of any special guarantees specified therein. 

3. This Notice does not relieve Seller of any surviving obligations under the Procurement Contract and is subject to Buyer’s reservations of rights with respect to completion and final payment. 

  Buyer 

By (signature):    Name (Printed):  

Date:    Title:  

 

Page 69: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. TOC Page i of 3 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ i 

SECTION 00 70 00 ‐ STANDARD GENERAL CONDITIONS OF THE PROCUREMENT CONTRACT 

TABLE OF CONTENTS 

Page 

Article 1— Definitions and Terminology ....................................................................................................... 1 

1.01  Defined Terms ............................................................................................................................... 1 

1.02  Terminology .................................................................................................................................. 4 

Article 2— Preliminary Matters .................................................................................................................... 5 

2.01  Delivery of Bonds and Evidence of Insurance ............................................................................... 5 

2.02  Copies of Documents .................................................................................................................... 6 

2.03  Electronic Transmittals ................................................................................................................. 6 

2.04  Preliminary Schedules ................................................................................................................... 6 

2.05  Preliminary Conference ................................................................................................................ 6 

2.06  Safety ............................................................................................................................................ 7 

Article 3— Procurement Contract Documents ............................................................................................. 7 

3.01  Intent ............................................................................................................................................. 7 

3.02  Reference Standards ..................................................................................................................... 7 

3.03  Reporting and Resolving Discrepancies ........................................................................................ 8 

3.04  Requirements of the Procurement Drawings and Procurement Specifications ........................... 8 

3.05  Reuse of Documents ..................................................................................................................... 9 

Article 4— Commencement and Schedule ................................................................................................... 9 

4.01  Commencement of Procurement Contract Times ........................................................................ 9 

4.02  Continuing Performance ............................................................................................................... 9 

4.03  Adjustments to Progress Schedule ............................................................................................. 10 

4.04  Delays .......................................................................................................................................... 10 

Article 5— Bonds and Insurance ................................................................................................................. 11 

5.01  Performance, Payment, and Other Bonds .................................................................................. 11 

5.02  Insurance ..................................................................................................................................... 12 

5.03  Surety or Insurance Companies .................................................................................................. 12 

Article 6— Licenses and Fees ...................................................................................................................... 13 

6.01  Intellectual Property and License Fees ....................................................................................... 13 

Page 70: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. TOC Page ii of 3 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ ii 

6.02  Seller’s Infringement ................................................................................................................... 13 

6.03  Buyer’s Infringement .................................................................................................................. 14 

Article 7— Seller’s Responsibilities ............................................................................................................. 14 

7.01  Performance of Obligations ........................................................................................................ 14 

7.02  Labor, Materials and Equipment ................................................................................................ 14 

7.03  Laws and Regulations .................................................................................................................. 15 

7.04  “Or Equals” .................................................................................................................................. 15 

7.05  Taxes ........................................................................................................................................... 16 

7.06  Submittals ................................................................................................................................... 16 

7.07  Indemnification ........................................................................................................................... 19 

7.08  Concerning Subcontractors and Suppliers .................................................................................. 19 

Article 8— Shipping and Delivery ............................................................................................................... 19 

8.01  Shipping ....................................................................................................................................... 19 

8.02  Delivery ....................................................................................................................................... 19 

8.03  Risk of Loss .................................................................................................................................. 20 

Article 9— Buyer’s Rights ............................................................................................................................ 20 

9.01  Seller’s Warranties and Guarantees ........................................................................................... 20 

9.02  Inspections and Testing .............................................................................................................. 21 

9.03  Non‐Conforming Goods and Special Services ............................................................................. 22 

9.04  Correction Period ........................................................................................................................ 24 

Article 10— Engineer’s Status ..................................................................................................................... 24 

10.01  Engineer’s Role Defined .......................................................................................................... 24 

10.02  Duties and Responsibilities; Authority; Limitations ................................................................ 24 

Article 11— Changes ................................................................................................................................... 25 

11.01  Amending and Supplementing the Procurement Contract .................................................... 25 

11.02  Change Orders ........................................................................................................................ 25 

11.03  Change Directives ................................................................................................................... 26 

11.04  Field Orders ............................................................................................................................. 26 

11.05  Buyer‐Authorized Changes in the Goods and Special Services ............................................... 26 

11.06  Buyer’s Contingency Allowance .............................................................................................. 26 

11.07  Unauthorized Changes in the Goods and Special Services ..................................................... 27 

11.08  Change of Procurement Contract Price .................................................................................. 27 

Page 71: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. TOC Page iii of 3 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ iii 

11.09  Change of Procurement Contract Times ................................................................................. 27 

11.10  Notification to Surety .............................................................................................................. 27 

Article 12— Claims, Disputes, and Dispute Resolution .............................................................................. 27 

12.01  Claims ...................................................................................................................................... 27 

12.02  Dispute Resolution Method .................................................................................................... 29 

Article 13— Payment .................................................................................................................................. 29 

13.01  Applications for Progress Payments ....................................................................................... 29 

13.02  Review of Applications for Progress Payments....................................................................... 30 

13.03  Basis and Amount of Progress Payments ............................................................................... 31 

13.04  Suspension of or Reduction in Payment ................................................................................. 31 

13.05  Final Payment .......................................................................................................................... 32 

13.06  Waiver of Claims ..................................................................................................................... 33 

Article 14— Cancellation, Suspension, and Termination ........................................................................... 33 

14.01  Cancellation............................................................................................................................. 33 

14.02  Suspension of Performance by Buyer ..................................................................................... 33 

14.03  Suspension of Performance by Seller ..................................................................................... 34 

14.04  Breach and Termination.......................................................................................................... 34 

Article 15— Miscellaneous ......................................................................................................................... 35 

15.01  Giving Notice ........................................................................................................................... 35 

15.02  Controlling Law ....................................................................................................................... 35 

15.03  Computation of Time .............................................................................................................. 35 

15.04  Cumulative Remedies ............................................................................................................. 35 

15.05  Survival of Obligations ............................................................................................................ 35 

15.06  Entire Agreement .................................................................................................................... 35 

15.07  No Waiver ............................................................................................................................... 36 

15.08  Headings .................................................................................................................................. 36 

15.09  Successors and Assigns ........................................................................................................... 36 

 

 

Page 72: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 1 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 1 

ARTICLE 1—DEFINITIONS AND TERMINOLOGY 

1.01 Defined Terms 

A. Whenever  used  in  the  Procurement  Bidding  Requirements  or  Procurement  Contract Documents  and  printed  with  initial  capital  letters,  the  terms  listed  below  will  have  the meanings  indicated, which  are  applicable  to  the  singular or plural  thereof.  In  addition  to terms  specifically  defined,  terms  with  initial  capital  letters  in  the  Procurement  Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms. 

1. Addenda—Written or  graphic  instruments  issued prior  to  the opening of Bids which clarify,  correct,  or  change  the  Bidding  Requirements  or  the  proposed  Procurement Contract Documents. 

2. Application  for Payment—The document prepared by Seller,  in a  form acceptable  to Buyer, to request progress or final payments, and which is to be accompanied by such supporting documentation as is required by the Procurement Contract Documents. 

3. Bid—An offer  or  proposal  of  a  prospective  Seller  submitted  on  the  prescribed  form setting forth the prices for the Goods and Special Services to be provided. 

4. Bidder—An individual or entity that, as a prospective Seller, submits a Bid to Buyer. 

5. Buyer—The individual or entity purchasing the Goods and Special Services. 

6. Change  Directive—A  written  directive  from  Buyer  to  Seller  issued  on  or  after  the Effective Date of the Procurement Contract, ordering an addition, deletion, or revision in the Goods and Special Services. 

7. Change  Order—A  document  which  is  signed  by  Seller  and  Buyer  and  authorizes  an addition,  deletion,  or  revision  to  the  Procurement  Contract  Documents  or  an adjustment  in  the  Procurement  Contract  Price  or  the  Procurement  Contract  Times, issued on or after the Effective Date of the Procurement Contract. Change Orders may be the result of mutual agreement by Buyer and Seller, or of resolution of a Claim. 

8. Claim—A demand or assertion by Buyer or Seller seeking an adjustment of Procurement Contract Price or Procurement Contract Times, or both, or other relief with respect to the terms of the Procurement Contract. A demand for money or services by a third party is not a Claim. 

9. Contractor/Assignee—A construction contractor with which Project Owner enters into a  construction  contract,  and  to  which  Project  Owner,  as  initial  Buyer,  assigns  this Procurement Contract. 

10. Effective Date  of  the  Procurement  Contract—The date  indicated  in  the Procurement Agreement on which the Procurement Contract becomes effective. 

11. Electronic  Document—Any  Project‐related  correspondence,  attachments  to correspondence, data, documents, drawings, information, or graphics, including but not limited  to  Shop  Drawings  and  other  Submittals,  that  are  in  an  electronic  or  digital format. 

Page 73: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 2 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 2 

12. Electronic  Means—Electronic  mail  (e‐mail),  upload/download  from  a  secure  Project website,  or  other  communications  methods  that  allow:  the  transmission  or communication  of  Electronic  Documents;  the  documentation  of  transmissions, including sending and receipt; printing of the transmitted Electronic Document by the recipient; the storage and archiving of the Electronic Document by sender and recipient; and  the use by  recipient of  the Electronic Document  for purposes permitted by  this Procurement Contract. Electronic Means does not include the use of text messaging, or of  Facebook,  Twitter,  Instagram,  or  similar  social media  services  for  transmission  of Electronic Documents. 

13. Engineer—The individual or entity designated as such in the Procurement Agreement. 

14. Field Order—A written order issued by Engineer which requires minor changes in the Goods or  Special  Services,  but which does not  involve  a  change  in  the Procurement Contract Price or Procurement Contract Times. 

15. Goods—The  tangible  and  movable  personal  property  that  is  described  in  the Procurement Contract Documents,  regardless of whether  the property  is  to be  later attached to realty. 

16. Goods and Special Services—The full scope of materials, equipment, other items, and services  to  be  furnished  by  Seller,  including  Goods,  as  defined  herein,  and  Special Services, if any, as defined herein. This term refers to both the Goods and the Special Services, or to either the Goods or the Special Services, and to any portion of the Goods or the Special Services, as the context requires. 

17. Laws and Regulations; Laws or Regulations—Any and all applicable laws, statutes, rules, regulations, ordinances, codes, and binding decrees, resolutions, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction. 

18. Milestone—A principal  event  specified  in  the Procurement Contract  that  Seller must attain by the date or within the number of days indicated, including but not limited to the delivery of the Goods and the furnishing of Special Services. 

19. Notice of Award—The written notice, by Buyer to a Bidder, of Buyer’s acceptance of the Bid. 

20. Point of Destination—The specific address of the location where delivery of the Goods will be made, as stated in the Procurement Agreement. 

21. Procurement Agreement—The written instrument, executed by Buyer and Seller, that sets forth the Procurement Contract Price and Procurement Contract Times, identifies the parties and the Engineer, and designates the specific items that are Procurement Contract Documents. 

22. Procurement  Bidding  Documents—The  Procurement  Bidding  Requirements  and  the proposed Procurement Contract Documents (including all Addenda). 

23. Procurement  Bidding  Requirements—The  advertisement  or  invitation  to  bid, Instructions to Bidders, Bid security of acceptable form, if any, and Bid Form with any supplements. 

Page 74: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 3 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 3 

24. Procurement Contract—The entire and  integrated written agreement between Buyer and Seller concerning the Goods and Special Services. 

25. Procurement  Contract  Documents—Those  items  so  designated  in  the  Procurement Agreement,  and which  together  comprise  the Procurement Contract.  Shop Drawings and other Seller submittals are not Procurement Contract Documents, even if accepted, reviewed, or approved by Engineer or Buyer. 

26. Procurement  Contract  Price—The  money  that  Buyer  has  agreed  to  pay  Seller  for furnishing the Goods and Special Services in accordance with the Procurement Contract Documents. 

27. Procurement  Contract  Times—The  times  stated  in  the  Procurement  Agreement  by which  the  Goods must  be  delivered,  Special  Services must  be  furnished,  and  other Milestones must be attained. 

28. Procurement Drawings—That part of the Procurement Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Goods and Special Services to be furnished by Seller. Shop Drawings and other Seller submittals are not Procurement Drawings as so defined. 

29. Procurement  Specifications—That  part  of  the  Procurement  Contract  Documents consisting of written  requirements  for materials, equipment,  systems,  standards and workmanship as applied to the furnishing of the Goods and Special Services, and certain administrative requirements and procedural matters applicable thereto. 

30. Project—The  total  undertaking  to  be  accomplished  for  Project  Owner  by  engineers, contractors,  and  others,  including  planning,  study,  design,  construction,  testing, commissioning, and start‐up, and of which the Goods and Special Services are a part. 

31. Project Owner—The entity that has retained (or will retain) engineers, contractors, and others for the planning, study, design, construction, testing, commissioning, and start‐up of facilities and improvements. As of the Effective Date of the Procurement Contract, the Project Owner is the Buyer. 

32. Samples—Physical  examples  of  materials,  equipment,  or  workmanship  that  are representative of some portion of the Goods and Special Services and which establish the standards by which such portion of the Goods and Special Services will be judged. 

33. Schedule  of  Submittals—A schedule,  prepared  and maintained by  Seller,  of  required Submittals and the time requirements for Engineer’s review of the Submittals. 

34. Seller—The individual or entity furnishing the Goods and Special Services. 

35. Shop  Drawings—All  drawings,  diagrams,  illustrations,  schedules,  and  other  data  or information which are specifically prepared or assembled by or for Seller and submitted by Seller to illustrate some portion of the Goods and Special Services. Shop Drawings, whether  approved  or  not,  are  not  Procurement  Drawings  and  are  not  Procurement Contract Documents. 

36. Special Services—Services to be performed by Seller (or its agents or subcontractors) in association with the Goods to be furnished by Seller, as required by the Procurement Contract Documents. 

Page 75: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 4 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 4 

37. Submittal—A  written  or  graphic  document,  prepared  by  or  for  Seller,  which  the Procurement  Contract  Documents  require  Seller  to  submit  to  Engineer,  or  that  is indicated as a Submittal in the Schedule of Submittals accepted by Engineer. Submittals may include Shop Drawings and Samples; schedules; product data; sustainable design information;  information  on  special  procedures;  testing  plans;  results  of  tests  and evaluations,  source  quality‐control  testing  and  inspections,  and  field  or  site  quality‐control testing and inspections; warranties and certifications; suppliers’ instructions and reports; records of delivery of spare parts and tools; operations and maintenance data; record documents; and other such documents required by the Procurement Contract Documents.  Submittals,  whether  or  not  approved  or  accepted  by  Engineer,  are  not Procurement Contract Documents. Change proposals, Change Orders, Claims, notices, Applications  for  Payment,  and  requests  for  interpretation  or  clarification  are  not Submittals. 

38. Successful Bidder—The Bidder whose Bid the Buyer accepts, and to which Buyer makes an award of the Procurement Contract. 

39. Supplementary  Conditions—The  part  of  the  Procurement  Contract  that  amends  or supplements these General Conditions. 

40. Unit Price Goods and Special Services—Goods and Special Services to be paid for on the basis of unit prices (if any). 

1.02 Terminology 

A. The words and terms discussed in Paragraphs 1.02.B and 1.02.C are not defined, but have the indicated meanings when used in the Bidding Requirements or Procurement Contract Documents. 

B. Intent of Certain Terms or Adjectives 

1. The Procurement Contract Documents include the terms “as allowed,” “as approved,” “as ordered,” “as directed” or terms of like effect or import to authorize an exercise of professional judgment by Engineer. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,” “satisfactory,” or adjectives of like effect or import are used to describe an action or determination of Engineer as to the Goods and Special Services. It is intended that such exercise of professional judgment, action, or determination will be commercially  reasonable  and  will  be  solely  to  evaluate,  in  general,  the  Goods  and Special  Services  for  compliance  with  the  requirements  of  and  information  in  the Procurement  Contract  Documents  and  conformance with  the  design  concept  of  the completed Project as a functioning whole, as shown or  indicated in the Procurement Contract Documents (unless there is a specific statement indicating otherwise). The use of any such  term or adjective will not be effective  to assign  to Engineer any duty or authority to supervise or direct the furnishing of Goods or Special Services or any duty or  authority  to  undertake  responsibility  contrary  to  any  other  provision  of  the Procurement Contract Documents. 

2. The word “non‐conforming” when modifying the words “Goods and Special Services,” “Goods,”  or  “Special  Services,”  refers  to  Goods  and  Special  Services  that  are unsatisfactory, faulty, or deficient in that they: 

Page 76: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 5 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 5 

a. do not conform to or comply with the requirements of the Procurement Contract Documents; 

b. do not meet  the requirements of any applicable  inspection, reference standard, test, or approval referred to in the Procurement Contract Documents; or 

c. in the case of Special Services, have not been completed. 

3. The  word  “receipt”  when  referring  to  the  Goods,  means  the  physical  taking  and possession by the Buyer under the conditions specified in Paragraph 9.02.B.2. 

4. The word “day” means a calendar day of 24 hours measured from midnight to the next midnight. 

5. The  word  "furnish,"  when  used  in  connection  with  the  Goods  and  Special  Services means  to  supply  and  deliver  said Goods  to  the  Point  of Destination  (or  some other specified location) and to perform said Special Services fully, all in accordance with the Procurement Contract Documents. 

C. Procurement  Contract  Price  or  Procurement  Contract  Times:  References  to  a  change  in “Procurement  Contract  Price  or  Procurement  Contract  Times”  or  “Procurement  Contract Times  or  Procurement  Contract  Price”  or  similar,  indicate  that  such  change  applies  to (1) Procurement Contract Price,  (2) Procurement Contract Times, or  (3) both Procurement Contract Price and Procurement Contract Times, as warranted, even if the term “or both” is not expressed. 

D. Unless  stated otherwise  in  the Procurement Contract Documents, words  or  phrases  that have  a  well‐known  technical  or  construction  industry  or  trade  meaning  are  used  in  the Procurement Contract Documents in accordance with such recognized meaning. 

ARTICLE 2—PRELIMINARY MATTERS 

2.01 Delivery of Bonds and Evidence of Insurance 

A. When Seller delivers the executed counterparts of the Procurement Agreement to Buyer, the Seller  also  shall  deliver  to  Buyer  the  performance  bond  and  payment  bond  (if  the Procurement Contract requires Seller to furnish such bonds). 

B. Evidence  of  Seller’s  Insurance:  When  Seller  delivers  the  signed  counterparts  of  the Procurement Agreement to Buyer, the Seller also shall deliver to Buyer, with copies to each additional  insured  (as  identified  in  the  Procurement  Contract),  the  certificates, endorsements,  and  other  evidence  of  insurance  required  to  be  provided  by  Seller  in accordance with  Article 5.  Evidence  of  insurance  to  be  obtained  at  a  later  date,  such  as insurance relating to transit or storage of the Goods, will be provided to Buyer at the time of such insurance is obtained. 

C. Evidence of Buyer’s Insurance: After receipt of the signed counterparts of the Procurement Agreement  and  all  required  bonds  and  insurance  documentation,  Buyer  shall  promptly deliver  to Seller, with copies  to each additional  insured  (as  identified  in  the Procurement Contract), certificates and other evidence of  insurance (if any) required to be provided by Buyer. 

Page 77: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 6 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 6 

2.02 Copies of Documents 

A. Buyer shall furnish to Seller four printed copies of the Procurement Contract (including one fully  executed  counterpart  of  the  Procurement  Agreement),  and  one  copy  in  electronic portable document format (PDF). Additional printed copies will be furnished upon request at the cost of reproduction. 

2.03 Electronic Transmittals 

A. Except as otherwise stated elsewhere in the Procurement Contract, the Buyer, Seller, and Engineer may send, and shall accept, Electronic Documents transmitted by Electronic Means. 

B. If the Procurement Contract does not establish protocols for Electronic Means, then Buyer, Seller, and Engineer shall jointly develop such protocols. 

C. Subject  to  any  governing  protocols  for  Electronic  Means,  when  transmitting  Electronic Documents by Electronic Means, the transmitting party makes no representations as to long‐term compatibility, usability, or readability of the Electronic Documents resulting from the recipient’s use of software application packages, operating systems, or computer hardware differing from those used in the drafting or transmittal of the Electronic Documents. 

2.04 Preliminary Schedules 

A. Within 15 days after the Effective Date of the Procurement Contract, Seller shall submit to Buyer and Engineer for timely review: 

1. a  progress  schedule  of  activities,  consistent  with  the  Procurement  Contract  Times, including at a minimum, Shop Drawing and Sample submittals, tests, and deliveries as required by the Procurement Contract Documents. 

a. The progress schedule will be acceptable to Buyer and Engineer if  it provides an orderly progression of  the Submittals,  tests, and deliveries to completion within the specified Milestones of the Procurement Contract Times. 

b. Such  acceptance  will  not  impose  on  Buyer  or  Engineer  responsibility  for  the progress schedule, for sequencing, scheduling, or progress of Seller’s performance of  its obligations under  the Procurement Contract,  nor  interfere with or  relieve Seller from Seller’s full responsibility therefor. 

c. Such acceptance will not be deemed as an acknowledgment of the reasonableness and attainability of the schedule. 

2. a preliminary schedule of Submittals. 

B. No  progress  payment  will  be  made  to  Seller  until  an  acceptable  progress  schedule  and acceptable  schedule  of  Submittals  are  submitted  to  Buyer  and  Engineer  (and  other conditions applicable to progress payments are met). 

2.05 Preliminary Conference 

A. Within 20 days after the Procurement Contract Times start to run, a conference attended by Seller,  Buyer,  Engineer  and  others  as  appropriate  will  be  held  to  establish  a  working understanding among the parties as to the Goods and Special Services and to discuss the schedules referred to in Paragraph 2.04.A, procedures for handling Shop Drawings and other Submittals, processing Applications for Payment, and maintaining required records. 

Page 78: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 7 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 7 

2.06 Safety 

A. Buyer and Seller shall comply with all applicable Laws and Regulations relating to the safety of persons or property, and to the protection of persons or property from damage, injury, or loss. 

B. When Seller's personnel, or the personnel of any subcontractor to Seller, are present at the Point  of  Destination  or  any  work  area  or  site  controlled  by  Buyer,  the  Seller  shall  be responsible  for  the  compliance  by  such  personnel  with  any  applicable  requirements  of Buyer's safety programs that are made known to Seller. 

C. If Buyer or its representatives visit the Seller’s manufacturing or storage facilities, for testing, inspection,  or  other  purposes,  Seller  shall  inform  Buyer  in  advance  of  any  safety preparations, standards, or programs with which Buyer and its representatives must comply. 

ARTICLE 3—PROCUREMENT CONTRACT DOCUMENTS 

3.01 Intent 

A. The Procurement Contract Documents are complementary; what is called for by one is as binding as if called for by all. 

B. Any labor, documentation, services, materials, or equipment that may reasonably be inferred from  the  Procurement  Contract Documents  or  from prevailing  custom or  trade  usage  as being  required  to  produce  or  furnish  the  indicated  Goods  and  Special  Services  will  be provided, whether or not specifically called for, at no additional cost to Buyer. 

C. Unless otherwise stated in the Procurement Contract Documents, if there is a discrepancy between the electronic or digital versions of the Procurement Contract Documents (including any printed copies derived from such electronic or digital versions) and the printed record version, the printed record version will govern. 

D. The Procurement Contract supersedes prior negotiations, representations, and agreements, whether written or oral. 

E. Engineer  will  issue  clarifications  and  interpretations  of  the  Procurement  Contract Documents, as provided in Paragraph 3.04. 

F. Any  provision  or  part  of  the  Procurement  Contract  Documents  held  to  be  void  or unenforceable  under  any  Law  or  Regulation  will  be  deemed  stricken,  and  all  remaining provisions will continue to be valid and binding upon Buyer and Seller. 

3.02 Reference Standards 

A. Reference  to  standards,  specifications,  manuals,  or  codes  of  any  technical  society, organization, or association, or to Laws and Regulations, whether such reference be specific or by implication, means the standard, specification, manual, code, or Laws and Regulations in  effect  at  the  time  of  opening  of  Bids  (or  on  the  Effective  Date  of  the  Procurement Agreement  if  there were  no  Bids),  except  as may  be  otherwise  specifically  stated  in  the Procurement Contract Documents. 

B. No provision of any such standard specification, manual, reference standard, or code, and no instruction of a supplier, will be effective to change the duties or responsibilities of Buyer, 

Page 79: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 8 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 8 

Seller, or Engineer from those set forth in the part of the Procurement Contract Documents prepared by or for Engineer. No such provision or instruction will be effective to assign to Buyer or Engineer any duty or authority to supervise or direct the performance of Seller’s obligations,  or  any  duty  or  authority  to  undertake  responsibility  inconsistent  with  the provisions of the part of the Procurement Contract Documents prepared by or for Engineer. 

3.03 Reporting and Resolving Discrepancies 

A. Reporting Discrepancies 

1. Seller’s  Review  of  Procurement  Contract  Documents:  If,  before  or  during  the performance of Seller’s obligations,  Seller discovers any conflict, error, ambiguity, or discrepancy within the Procurement Contract Documents, or between the Procurement Contract  Documents  and  (a) any  applicable  Law  or  Regulation,  (b) actual  field conditions,  (c) any  standard  specification,  manual,  reference  standard,  or  code,  or (d) any  instruction  of  any  supplier  to  Seller,  then  Seller  shall  promptly  report  it  to Engineer  (or  if  the  Procurement  Contract  is  assigned,  then  directly  to Contractor/Assignee)  in writing.  Seller  shall  not proceed with  the Goods  and  Special Services affected thereby until the conflict, error, ambiguity, or discrepancy is resolved, by  a  clarification  or  interpretation  by  Engineer  (or  if  the  Procurement  Contract  is assigned,  then  by  Contractor/Assignee)  or  by  an  amendment  or  supplement  to  the Procurement Contract Documents issued pursuant to Article 11. 

2. Seller shall not be liable to Buyer or Engineer for failure to report any conflict, error, ambiguity, or discrepancy  in  the Procurement Contract Documents unless Seller had actual knowledge thereof. 

B. Resolving Discrepancies: Except as may be otherwise specifically stated in the Procurement Contract  Documents,  the  provisions  of  the  Procurement  Contract  Documents  will  take precedence in resolving any conflict, error, ambiguity, or discrepancy between the provisions of the Procurement Contract Documents and: 

1. the provisions of any standard, specification, manual, code, or instruction (whether or not specifically incorporated by reference in the Procurement Contract Documents); or 

2. the provisions of any Laws or Regulations applicable to the furnishing of the Goods and Special  Services  (unless  such an  interpretation of  the provisions of  the Procurement Contract Documents would result in violation of such Law or Regulation). 

3.04 Requirements of the Procurement Drawings and Procurement Specifications 

A. During the performance of Seller’s obligations and until final payment, Seller and Buyer shall submit  to  the  Engineer  all  matters  in  question  concerning  the  requirements  of  the Procurement Drawings and Procurement Specifications (sometimes referred to as requests for  information or  interpretation—RFIs), or relating  to the acceptability of  the Goods and Special  Services,  as  soon  as  possible  after  such matters  arise.  Engineer will  be  the  initial interpreter  of  the  requirements  of  the  Procurement  Drawings  and  Procurement Specifications, and judge of the acceptability of the Goods and Special Services thereunder. 

1. After  assignment  (if  any)  Seller  shall  submit  such  matters  directly  to Contractor/Assignee  for  response  or  administration,  and  the  Procurement  Contract provisions in Paragraphs 3.04.B and C will not apply. 

Page 80: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 9 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 9 

B. Engineer will  issue with  reasonable  promptness  a  written  clarification,  interpretation,  or decision on the issue submitted, and if necessary, initiate an amendment or supplement to the Procurement Drawings or Procurement Specifications. Engineer’s written clarification, interpretation,  or  decision will  be  consistent  with  the  overall  intent  of  the  Procurement Contract Documents, and will be  final and binding on Seller and Buyer.  If either Buyer or Seller  believes  that  a written  clarification or  interpretation  justifies  an  adjustment  in  the Procurement Contract Price or Procurement Contract Times, either may make a Claim for such adjustment as provided in Article 12. 

C. If  a  submitted  matter  in  question  concerns  terms  and  conditions  of  the  Procurement Contract Documents that do not involve (1) the performance or acceptability of the Goods and  Services,  (2) the  design  (as  set  forth  in  the  Procurement  Drawings,  Procurement Specifications, or otherwise), or  (3) other engineering or  technical matters,  then Engineer will promptly give written notice to Buyer and Seller  that Engineer  is unable  to provide a decision or interpretation. 

3.05 Reuse of Documents 

A. Seller and its subcontractors and suppliers shall not: 

1. have or acquire any title to or ownership rights in any of the Procurement Drawings, Procurement Specifications, or other documents (or copies of any thereof) prepared by or bearing the seal of Engineer or its consultants, including electronic media editions, or reuse any such Procurement Drawings, Procurement Specifications, other documents, or copies thereof, on extensions of  the Project or any other project, without written consent  of  Buyer  and  Engineer  and  specific  written  verification  or  adaptation  by Engineer; or 

2. have  or  acquire  any  title  or  ownership  rights  in  any  other  Procurement  Contract Documents, reuse any such Procurement Contract Documents for any purpose without Buyer’s  express  written  consent,  or  violate  any  copyrights  pertaining  to  such Procurement Contract Documents. 

B. The  prohibitions  of  this  Paragraph 3.05 will  survive  final  payment,  or  termination  of  the Procurement  Contract.  Nothing  herein  precludes  Seller  from  retaining  copies  of  the Procurement Contract Documents for record purposes. 

ARTICLE 4—COMMENCEMENT AND SCHEDULE 

4.01 Commencement of Procurement Contract Times 

A. The  Procurement  Contract  Times  will  commence  to  run  on  the  Effective  Date  of  the Procurement Contract. 

4.02 Continuing Performance 

A. Seller  shall  adhere  to  the  progress  schedule  established  in  accordance  with Paragraph 2.04.A., as duly adjusted, and the Goods will be delivered and the Special Services furnished within the Procurement Contract Times. 

B. Seller shall carry on furnishing of the Goods and Special Services and adhere to the progress schedule during all disputes or disagreements with Buyer. No furnishing of Goods and Special 

Page 81: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 10 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 10 

Services will be delayed or postponed pending resolution of any disputes or disagreements, except as expressly permitted herein, or as Buyer and Seller may otherwise agree in writing. 

4.03 Adjustments to Progress Schedule 

A. The progress schedule established in accordance with Paragraph 2.04 may be adjusted from time to time as provided below. 

1. Seller shall submit to Buyer for acceptance (to the extent indicated in Paragraph 2.04) proposed  adjustments  in  the  progress  schedule  that  will  not  result  in  changing  the Procurement  Contract  Times.  Such  adjustments  will  comply  with  any  applicable provisions of the Procurement Specifications. 

2. Proposed  adjustments  in  the  progress  schedule  that  will  change  the  Procurement Contract Times must be submitted in accordance with the requirements of Article 11. Adjustments in Procurement Contract Times may only be made by a Change Order. 

4.04 Delays 

A. If Buyer, Engineer, or anyone for whom Buyer is responsible, delays, disrupts, or interferes with  Seller’s  performance  or  progress,  then  Seller  shall  be  entitled  to  an  equitable adjustment in Procurement Contract Price or Procurement Contract Times. 

B. Seller shall not be entitled to an adjustment in Procurement Contract Price or Procurement Contract Times for delay, disruption, or interference caused by or within the control of Seller or anyone for whom Seller is responsible. 

C. If Seller’s performance or progress is delayed, disrupted, or interfered with by unanticipated causes not the fault of and beyond the control of Buyer, Seller, and those for which they are responsible, then Seller shall be entitled to an equitable adjustment in Procurement Contract Times.  Such  an  adjustment  will  be  Seller’s  sole  and  exclusive  remedy  for  the  delays, disruption,  and  interference  described  in  this  paragraph.  Causes  of  delay,  disruption,  or interference that may give rise to an adjustment in Procurement Contract Times under this paragraph include but are not limited to the following: 

1. severe  and  unavoidable  natural  catastrophes  such  as  fires,  floods,  epidemics,  and earthquakes; 

2. abnormal weather conditions; 

3. inspection delays by governmental authorities, and custom delays; 

4. international shipping delays; 

5. acts or failures to act of third‐party entities; and 

6. acts of war or terrorism. 

D. Adjustments  of  Procurement  Contract  Times  or  Procurement  Contract  Price—General Provisions:  Seller’s  entitlement  to  an  adjustment  of  Procurement  Contract  Times  or Procurement Contract Price is limited as follows: 

1. Seller’s entitlement to an adjustment of the Procurement Contract Times is conditioned on the delay, disruption, or  interference adversely affecting an activity on the critical 

Page 82: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 11 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 11 

path  to completion of Seller’s obligations, as of  the  time of  the delay, disruption, or interference. 

2. Seller shall not be entitled to an adjustment in Procurement Contract Price for any delay, disruption,  or  interference  if  such  delay  is  concurrent  with  a  delay,  disruption,  or interference caused by or within the control of Seller. Such a concurrent delay by Seller does  not  preclude  an  adjustment  of  Procurement  Contract  Times  to which  Seller  is otherwise entitled. 

3. Adjustments of Procurement Contract Times or Procurement Contract Price are subject to the provisions of Articles 11 and 12. 

E. Each  Seller  request  seeking  a  delay‐related  increase  in  Procurement  Contract  Times  or Procurement Contract  Price must  be  supplemented by  supporting data  that  sets  forth  in detail the following: (1) the circumstances that form the basis for the requested adjustment; (2) the  date  upon which  each  cause  of  delay,  disruption,  or  interference  began  to  affect Seller’s progress; (3) the date upon which each cause of delay, disruption, or  interference ceased to affect Seller’s progress; (4) the number of days’ increase in Procurement Contract Times claimed as a consequence of each such cause of delay, disruption, or interference; and (5) the  impact  on  Procurement  Contract  Price.  Seller  shall  also  furnish  such  additional supporting documentation as Buyer or Engineer may require including, where appropriate, a revised progress schedule indicating all the activities affected by the delay, disruption, or interference, and an explanation of the effect of the delay, disruption, or interference on the critical path to completion. 

ARTICLE 5—BONDS AND INSURANCE 

5.01 Performance, Payment, and Other Bonds 

A. Seller shall  furnish a performance bond and a payment bond, each  in an amount at  least equal  to  the  Procurement  Contract  Price,  as  security  for  the  faithful  performance  and payment of Seller’s obligations under the Procurement Contract. These bonds must remain in effect until one year after the date when final payment becomes due or until completion of the correction period specified in Paragraph 9.04, whichever is later, except as provided otherwise by Laws or Regulations, the terms of a prescribed bond form, the Supplementary Conditions, or other provisions of the Procurement Contract. 

B. Seller  shall  also  furnish  such  other  bonds  (if  any)  as  are  required  by  the  Supplementary Conditions or other provisions of the Procurement Contract. 

C. All bonds must be in the form included in the Bidding Documents or otherwise specified by Buyer prior to execution of the Procurement Contract, except as provided otherwise by Laws or Regulations, and must be  issued and signed by a surety named in “Companies Holding Certificates  of  Authority  as  Acceptable  Sureties  on  Federal  Bonds  and  as  Acceptable Reinsuring  Companies”  as  published  in  Department  Circular  570  (as  amended  and supplemented) by the Bureau of the Fiscal Service, U.S. Department of the Treasury. A bond signed  by  an  agent  or  attorney‐in‐fact must  be  accompanied  by  a  certified  copy  of  that individual’s  authority  to  bind  the  surety.  The  evidence  of  authority must  show  that  it  is effective on the date the agent or attorney‐in‐fact signed the accompanying bond. 

Page 83: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 12 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 12 

D. Seller  shall  obtain  the  required  bonds  from  surety  companies  that  are  duly  licensed  or authorized, in the state or jurisdiction in which the Project is located, to issue bonds in the required amounts. 

E. If the surety on a bond furnished by Seller is declared bankrupt or becomes insolvent, or the surety ceases to meet the requirements above, then Seller shall promptly notify Buyer and Engineer and shall, within 20 days after the event giving rise to such notification, provide another bond and surety, both of which shall comply with the bond and surety requirements of this Procurement Contract. 

F. If Seller has failed to obtain a required bond, Buyer may exercise Buyer’s termination rights under Article 14. 

G. Upon request to Buyer from any subcontractor, supplier, or other person or entity claiming to have furnished labor, services, materials, or equipment used in the performance of Seller’s obligations, Buyer shall provide a copy of the payment bond to such person or entity. 

H. Upon request to Seller from any subcontractor, supplier, or other person or entity claiming to have furnished labor, services, materials, or equipment used in the performance of Seller’s obligations, Seller shall provide a copy of the payment bond to such person or entity. 

5.02 Insurance 

A. Seller shall provide insurance of the types and coverages and in the amounts stipulated in the Supplementary Conditions. 

B. Failure  of  Buyer  to  demand  certificates  of  insurance  or  other  evidence  of  Seller's  full compliance with these insurance requirements or failure of Buyer to identify a deficiency in compliance  from  the  evidence  provided  will  not  be  construed  as  a  waiver  of  Seller’s obligation to maintain such insurance. 

C. Upon assignment of this Procurement Contract, Seller shall name the Contractor/Assignee as  an  additional  insured  and  comply with  the written  request  of  Contractor/Assignee  to provide evidence of insurance. 

D. Buyer does not represent that insurance coverage and limits established in this Procurement Contract necessarily will be adequate to protect Seller. 

E. The  insurance and  insurance  limits required herein will not be deemed as a  limitation on Seller’s liability under the indemnities and other rights granted to Buyer in the Procurement Contract. 

5.03 Surety or Insurance Companies 

A. All bonds and insurance required by the Procurement Contract Documents to be purchased and maintained by Buyer or Seller shall be obtained from surety or insurance companies that are duly  licensed or authorized  in  the  jurisdiction  in which  the Project  is  located  to  issue bonds  or  insurance  policies  for  the  limits  and  coverages  so  required.  Such  surety  and insurance companies must also meet such additional requirements and qualifications as may be provided in the Supplementary Conditions. 

Page 84: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 13 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 13 

ARTICLE 6—LICENSES AND FEES 

6.01 Intellectual Property and License Fees 

A. Except to the extent stated elsewhere in the Procurement Contract Documents, Seller is not transferring any patent rights, copyrights, or other intellectual property rights for the Goods delivered. 

B. To  the  extent  Seller  is  manufacturing  to  Buyer’s  design,  Buyer  retains  all  patent  rights, copyrights, and other intellectual property rights in such design. 

C. If an invention, design, process, product, or device is specified in the Procurement Contract Documents for incorporation in the Goods or for the performance of Special Services, and if, to the actual knowledge of Buyer or Engineer, its use is subject to patent rights, copyrights, or other  intellectual property  rights  calling  for  the payment of  a  license  fee or  royalty  to others, then the existence of such rights and payment obligations will be disclosed to Seller in the Procurement Contract Documents. 

D. Seller shall pay all license fees and royalties and assume all costs incident to the use or the furnishing  of  the  Goods,  unless  specified  otherwise  by  the  Procurement  Contract Documents. 

6.02 Seller’s Infringement 

A. Subject to Paragraph 6.01, to the fullest extent permitted by Laws and Regulations, Seller shall indemnify and hold harmless Buyer, Engineer, and their officers, directors, members, partners, employees, agents, consultants, contractors, and subcontractors, from and against all claims, costs, losses, damages, and judgments (including but not limited to all reasonable fees and charges of engineers, architects, attorneys and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to any infringement or alleged infringement of any patent, copyright, or other intellectual property right by any of the Goods as delivered or Special Services as performed. 

B. Buyer will promptly notify Seller in writing of any claim, suit, or threat of suit by a third party for any infringement or alleged infringement of any patent, copyright, or other intellectual property right with respect to the Goods as delivered or Special Services as performed. 

C. Seller shall promptly defend or settle the claim or suit. Seller shall have control over such claim or suit, bear all expenses, and satisfy any adverse judgment. 

1. If Seller fails to defend such suit or claim after written notice by Buyer, Seller will be bound,  in  any  subsequent  suit  or  claim  against  Seller  by  Buyer,  by  any  factual determination in the prior suit or claim. 

2. If Buyer fails to provide Seller the opportunity to defend such suit or claim, Buyer shall be barred from any remedy against Seller for such suit or claim. 

D. If a determination is made that Seller has infringed upon the intellectual property rights of another,  Seller  may,  at  Seller’s  own  expense,  obtain  the  necessary  licenses  for  Buyer’s benefit, or replace the Goods and provide related design and construction, consistent with the requirements of the Procurement Contract Documents, to avoid the infringement. 

Page 85: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 14 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 14 

6.03 Buyer’s Infringement 

A. Subject  to  Paragraph 6.01,  and  to  the  fullest  extent  permitted  by  Laws  and  Regulations, Buyer  shall  be  responsible  to  Seller  for  any  infringement  or  alleged  infringement  of  any patent, copyright, or other intellectual property right caused by Seller’s compliance with the Procurement  Drawings  or  Procurement  Specifications,  and  will  reimburse  Seller  for  any license fee or royalties paid by Seller to others if such payment resulted from any invention, design,  process,  product,  or  device  specified  to  be  furnished  or  performed  in  the Procurement Drawings or Procurement Specifications, but not identified as being subject to payment of such license fee or royalty. 

B. Seller will promptly notify Buyer in writing of any claim, suit, or threat of suit by a third party for intellectual property infringement arising from Seller’s compliance with the Procurement Drawings or Procurement Specifications. 

C. Buyer shall defend or settle the claim or suit. Buyer shall have control over such claim or suit, bear all expenses, and satisfy any adverse judgment. 

1. If Buyer fails to defend such suit or claim after written notice by Seller, Buyer will be bound,  in  any  subsequent  suit  or  claim  against  Buyer  by  Seller,  by  any  factual determination in the prior suit or claim. 

2. If Seller fails to provide Buyer the opportunity to defend such suit or claim, Seller shall be barred from any remedy against Buyer for such suit or claim. 

ARTICLE 7—SELLER’S RESPONSIBILITIES 

7.01 Performance of Obligations 

A. Seller  shall  be  solely  responsible  for  the  means,  methods,  techniques,  sequences,  and procedures  necessary  to  perform  its  obligations  in  accordance  with  the  Procurement Contract Documents. 

B. Seller shall supervise,  inspect, and direct  the furnishing of the Goods and Special Services competently  and efficiently, devoting  such attention  thereto and applying  such  skills  and expertise as may be necessary to perform its obligations in accordance with the Procurement Contract Documents. 

C. Seller  shall  coordinate  the  provision  of  Special  Services  to  avoid  or  limit  interference  or disruption of other activities at the location where the Special Services are to occur, including but not limited to ongoing facility operations and construction activities. 

7.02 Labor, Materials and Equipment 

A. Seller  shall  provide  competent,  qualified  and  trained  personnel  in  all  aspects  of  its performance of the Procurement Contract. 

B. All Goods, and all equipment and material incorporated into the Goods, must be as specified, and unless specified otherwise in the Procurement Contract Documents, must be: 

1. new, and of good quality; 

2. protected,  assembled,  connected,  cleaned,  and  conditioned  in  accordance  with  the original manufacturer’s instructions; and 

Page 86: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 15 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 15 

3. shop‐assembled to the greatest extent practicable. 

7.03 Laws and Regulations 

A. Seller  shall  give  all  notices  required  by  and  shall  comply  with  all  Laws  and  Regulations applicable  to  the  performance  of  its  obligations  in  accordance  with  the  Procurement Contract  Documents.  Except  where  otherwise  expressly  required  by  such  Laws  and Regulations,  neither  Buyer  nor  Engineer  shall  be  responsible  for  monitoring  Seller’s compliance with any Laws or Regulations. 

B. If Seller furnishes Goods and Special Services knowing or having reason to know that such furnishing is contrary to Laws or Regulations, Seller shall bear all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to such performance. It will not be Seller’s responsibility to make certain that the Procurement Specifications and Procurement Drawings are in accordance with Laws and  Regulations,  but  this  provision  will  not  relieve  Seller  of  Seller’s  obligations  under Paragraph 3.03. 

C. Changes in Laws or Regulations not known at the time of opening of Bids (or, on the Effective Date of the Procurement Contract if there were no Bids) that have a direct effect on the cost or time of Seller’s performance will be the subject of an adjustment in Procurement Contract Price or Procurement Contract Times. If Buyer and Seller are unable to agree on entitlement to or on the amount or extent, if any, of any such adjustment, a Claim may be made therefor as provided in Article 12. 

7.04 “Or Equals” 

A. Whenever an item of material or equipment to be incorporated into the Goods is specified or described in the Procurement Contract Documents by using the names of one or more proprietary items or specific suppliers or manufacturers, the specification or description is intended  to  establish  the  type,  function,  appearance,  and  quality  required.  Unless  the specification or description contains or is followed by words reading that no like, equivalent, or  “or  equal”  item  is  permitted,  other  items  of  material  or  equipment  or  material  or equipment of other suppliers or manufacturers may be submitted to Buyer for Engineer’s review. 

1. If in Engineer’s sole discretion, such an item of material or equipment proposed by Seller is functionally equal to that named and sufficiently similar so that no change in related work will be required, it may be considered by Engineer as an “or equal” item. 

2. For the purposes of this paragraph, a proposed item of material or equipment may be considered functionally equal to an item so named only if in the exercise of reasonable judgment,  Engineer  determines  that:  1) it  is  at  least  equal  in  quality,  durability, appearance,  strength,  and  design  characteristics;  2) it  will  reliably  perform  at  least equally well the function imposed by the design concept of the completed Project as a functioning whole;  3) it  has  an  acceptable  record  of  performance  and  availability  of responsive service; and (4) Seller certifies that if approved: a) there will be no increase in  any  cost,  including  capital,  installation  or  operating  costs,  to  Buyer;  and  b) the proposed  item  will  conform  substantially  to  the  detailed  requirements  of  the  item named in the Procurement Contract Documents. 

Page 87: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 16 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 16 

B. Engineer’s Evaluation: Engineer will be allowed a reasonable time within which to evaluate each proposal or Submittal made pursuant  to Paragraph 7.04.A. Engineer will be  the sole judge of whether  to accept or  reject  such a proposal or  Submittal. No  “or equal” will  be ordered,  manufactured  or  utilized  until  Engineer’s  review  is  complete,  which  will  be evidenced by an approved Shop Drawing. Engineer will advise Buyer and Seller in writing of any  negative  determination.  Notwithstanding  Engineer’s  approval  of  an  “or‐equal”  item, Seller shall remain obligated to comply with the requirements of the Procurement Contract Documents. 

C. Special  Guarantee:  Buyer  may  require  Seller  to  furnish  at  Seller’s  expense  a  special performance guarantee or other surety with respect to any such proposed “or‐equal.” 

D. Data:  Seller  shall  provide  all  data  in  support  of  any  such  proposed  “or  equal”  at  Seller’s expense. 

7.05 Taxes 

A. Seller shall pay all taxes and duties arising out of the sale of the Goods and the performance of  Special  Services.  All  taxes  and  duties  are  included  in  the  Procurement  Contract  Price, except as noted in the Supplementary Conditions. 

7.06 Submittals 

A. Shop Drawing and Sample Requirements 

1. Before submitting a Shop Drawing or Sample, Seller shall: 

a. review and coordinate the Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Procurement Contract Documents; 

b. determine and verify: 

1) all  field measurements,  quantities,  dimensions,  specified  performance  and design  criteria,  installation  requirements,  materials,  catalog  numbers,  and similar information with respect to the Submittal; and 

2) the  suitability  of  all  materials  and  equipment  offered  with  respect  to  the indicated application, fabrication, shipping, handling, storage, assembly, and installation pertaining to the performance of Seller’s obligations. 

c. confirm that the Submittal is complete with respect to all related data included in the Submittal. 

2. Each Shop Drawing or Sample must bear a stamp or specific written certification that Seller  has  satisfied  its  obligations  under  the  Procurement  Contract  Documents with respect to Seller’s review of that Submittal, and that Seller approves the Submittal. 

3. With each Shop Drawing or Sample, Seller shall give Engineer specific written notice of any variations that the Submittal may have from the requirements of the Procurement Contract Documents. This notice will be set forth in a written communication separate from the Submittal; and, in addition, in the case of a Shop Drawing by a specific notation made on the Shop Drawing itself. 

Page 88: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 17 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 17 

B. Submittal  Procedures  for  Shop Drawings  and  Samples:  Seller  shall  label  and  submit  Shop Drawings and Samples to Engineer for review and approval in accordance with the accepted Schedule of Submittals. 

1. Shop Drawings 

a. Seller  shall  submit  the  number  of  copies  required  in  the  Procurement Specifications. 

b. Data shown on the Shop Drawings must be complete with respect to quantities, dimensions, specified performance and design criteria, materials, and similar data to  show  Engineer  the  services,  materials,  and  equipment  Seller  proposes  to provide, and to enable Engineer to review the information for the limited purposes required by Paragraph 7.06.C. 

2. Samples 

a. Seller  shall  submit  the  number  of  Samples  required  in  the  Procurement Specifications. 

b. Seller shall clearly identify each Sample as to material, supplier, pertinent data such as catalog numbers, the use for which intended and other data as Engineer may require  to  enable  Engineer  to  review  the  Submittal  for  the  limited  purposes required by Paragraph 7.06.C. 

3. Where a Shop Drawing or Sample is required by the Procurement Contract Documents or the Schedule of Submittals, any related work performed by Seller prior to Engineer’s review  and  approval  of  the  pertinent  Submittal  will  be  at  the  sole  expense  and responsibility of Seller. 

C. Engineer’s Review of Shop Drawings and Samples 

1. Engineer will provide timely review of Shop Drawings and Samples in accordance with the accepted Schedule of  Submittals.  Engineer’s  review and approval will  be only  to determine if the items covered by the Submittals will, after installation or incorporation in the Goods, comply with the requirements of the Procurement Contract Documents, and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Procurement Contract Documents. 

2. Engineer’s  review  and  approval  will  not  extend  to  means,  methods,  techniques, sequences, or procedures of construction, manufacturing,  fabrication,  installation, or shipping, or to safety precautions or programs incident thereto. 

3. Engineer’s review and approval of a separate item as such will not indicate approval of the assembly in which the item functions. 

4. Engineer’s review and approval of a Shop Drawing or Sample will not relieve Seller from responsibility  for  any  variation  from  the  requirements  of  the  Procurement  Contract Documents unless Seller has complied with the requirements of Paragraph 7.06.A.3 and Engineer has given written approval of each such variation by specific written notation thereof  incorporated  in or accompanying  the Shop Drawing or Sample. Engineer will document  any  such  approved  variation  from  the  requirements  of  the  Procurement 

Page 89: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 18 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 18 

Contract  Documents  in  a  Field  Order  or  other  appropriate  Procurement  Contract modification. 

5. Engineer’s review and approval of a Shop Drawing or Sample will not relieve Seller from responsibility for complying with the requirements of Paragraphs 7.06.A and B. 

6. Engineer’s review and approval of a Shop Drawing or Sample, or of a variation from the requirements  of  the  Procurement  Contract  Documents,  will  not,  under  any circumstances, change the Procurement Contract Times or Procurement Contract Price, unless such changes are included in a Change Order. 

7. Neither Engineer’s receipt, review, acceptance or approval of a Shop Drawing or Sample will result in such item becoming a Procurement Contract Document. 

8. Seller  shall  furnish  Goods  that  comply with  the  requirements  and  commitments  set forth  in  approved  Shop  Drawings  and  Samples,  subject  to  the  provisions  of Paragraph 7.06.C.4. 

D. Resubmittal Procedures for Shop Drawings and Samples 

1. Seller shall make corrections required by Engineer and shall return the required number of corrected copies of Shop Drawings and submit, as required, new Samples for review and approval. Seller shall direct specific attention in writing to revisions other than the corrections called for by Engineer on previous Submittals. 

2. Seller  shall  furnish  required  Shop  Drawing  and  Sample  Submittals  with  sufficient information and accuracy to obtain required approval of an item with no more than two resubmittals. Engineer will record Engineer’s time for reviewing a third or subsequent resubmittal of a Shop Drawing or Sample, and Seller shall be responsible for Engineer’s charges to Buyer for such time. Buyer may impose a set‐off against payments due Seller to secure reimbursement for such charges. 

3. If Seller requests a change of a previously approved Shop Drawing or Sample, Seller shall be  responsible  for  Engineer’s  charges  to  Buyer  for  its  review  time,  and  Buyer  may impose a set‐off against payments due Seller to secure reimbursement for such charges, unless the need for such change is beyond the control of Seller. 

E. Submittals Other than Shop Drawings and Samples 

1. The following provisions apply to all Submittals other than Shop Drawings and Samples: 

a. Seller  shall  submit  all  such  Submittals  to  the  Engineer  in  accordance  with  the schedule of Submittals and pursuant to the applicable terms of the Procurement Contract Documents. 

b. Engineer will provide timely review of all such Submittals in accordance with the schedule  of  Submittals  and  return  such  Submittals  with  a  notation  of  either Accepted or Not Accepted. Any such Submittal that is not returned within the time established in the schedule of Submittals will be deemed accepted. 

c. Engineer’s review will be only to determine if the Submittal is acceptable under the requirements  of  the  Procurement  Contract  Documents  as  to  general  form  and content of the Submittal. 

Page 90: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 19 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 19 

d. If any such Submittal is not accepted, Seller shall confer with Engineer regarding the reason for the non‐acceptance, and resubmit an acceptable document. 

2. Procedures for the submittal and acceptance of the Progress Schedule, the Schedule of Submittals, and the Schedule of Values are set forth in Paragraphs 2.04 and 2.05. 

7.07 Indemnification 

A. To  the  fullest  extent  permitted  by  Laws  and Regulations,  Seller  shall  indemnify  and hold harmless  Buyer,  Engineer,  Project  Owner,  and  any  assignee  of  Buyer,  including Contractor/Assignee, and  their officers, directors, members, partners, employees, agents, consultants, contractors, and subcontractors, from and against all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) arising out of or relating to the performance of Seller's obligations under the Procurement Contract, provided that any such claim, cost, loss, or damage is attributable to bodily injury, sickness, disease, or death, or to injury to or destruction of tangible property (other than the Goods themselves), including the loss of use resulting therefrom, but only to the extent caused by any  negligent  act  or  omission  of  Seller,  or  any  individual  or  entity  directly  or  indirectly employed by Seller or anyone for whose acts Seller may be liable. 

B. In  any  and  all  claims  against  Buyer,  Engineer,  Project  Owner,  or  any  assignee  of  Buyer, including Contractor/Assignee, or  their officers, directors, members, partners, employees, agents,  consultants,  contractors,  or  subcontractors,  by  any  employee  (or  the  survivor  or personal representative of such employee) of Seller, any subcontractor, any supplier, or any individual or entity directly or indirectly employed by any of them to furnish any of the Goods and Special Services, or anyone for whose acts any of them may be liable, the indemnification obligation under Paragraph 7.07.A will not be  limited  in any way by any  limitation on the amount or type of damages, compensation, or benefits payable by or for Seller or any such subcontractor,  supplier,  or  other  individual  or  entity  under  workers’  compensation  acts, disability benefit acts, or other employee benefit acts. 

7.08 Concerning Subcontractors and Suppliers 

A. Seller may retain subcontractors and suppliers for the performance of parts of the furnishing of the Goods and Special Services. The Seller’s retention of a subcontractor or supplier will not relieve Seller’s obligation to Buyer to perform and complete the furnishing the Goods and Special Services in accordance with the Procurement Contract Documents. 

ARTICLE 8—SHIPPING AND DELIVERY 

8.01 Shipping 

A. Seller  shall  select  the  carrier  and  bear  all  costs  of  packaging,  transportation,  insurance, special handling, and all other costs associated with shipment and delivery. 

8.02 Delivery 

A. Seller shall deliver the Goods free on board (FOB) to the Point of Destination, freight prepaid, in  accordance  with  the  Procurement  Contract  Times  set  forth  in  the  Procurement Agreement, or other date agreed to by Buyer and Seller. 

Page 91: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 20 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 20 

B. At least 10 days before shipment, Seller shall provide written notice to Buyer of the manner of shipment and the anticipated delivery date. The notice must also include any instructions concerning special equipment or services required at the Point of Destination to unload and care for the Goods. Seller shall also require the carrier to give Buyer at least 24 hours’ notice by telephone prior to the anticipated time of delivery. 

C. Buyer will be responsible and bear all costs for unloading the Goods from carrier. 

D. Buyer will assure that adequate facilities are available to receive delivery of the Goods at the time established for delivery, or on another date agreed to by Buyer and Seller. 

E. No  partial  deliveries  will  be  allowed,  unless  permitted  or  required  by  the  Procurement Contract Documents or agreed to in writing by Buyer. 

F. Provisions governing inspection on delivery are set forth in Paragraph 9.02. 

8.03 Risk of Loss 

A. Risk of loss and insurable interests transfer from Seller to Buyer upon Buyer’s receipt of the Goods. 

B. Notwithstanding  the  provisions  of  Paragraph 8.03.A,  if  Buyer  rejects  the  Goods  as  non‐conforming, the risk of  loss on such Goods will remain with Seller until Seller corrects the non‐conformity  or  Buyer  accepts  the  Goods.  If  rejected  Goods  remain  at  the  Point  of Destination  pending  modification  and  acceptance,  then  Seller  shall  be  responsible  for arranging adequate protection and maintenance of the Goods at Seller's expense. 

ARTICLE 9—BUYER’S RIGHTS 

9.01 Seller’s Warranties and Guarantees 

A. Seller warrants and guarantees to Buyer that the title to the Goods conveyed will be proper, its transfer rightful, and free from any security interest, lien, or other encumbrance. Seller shall  defend,  indemnify,  and  hold  Buyer  harmless  against  any  liens,  claims,  or  demands contesting or affecting title of the Goods conveyed. 

B. Seller warrants and guarantees to Buyer that all Goods and Special Services will conform with the Procurement Contract Documents, and with the standards established by any Samples approved by Engineer. Engineer shall be entitled to rely on Seller’s warranty and guarantee. If the Procurement Contract Documents do not otherwise specify the characteristics or the quality of the Goods, the Goods must comply with the requirements of Paragraph 7.02.B. 

C. Seller’s warranty and guarantee hereunder excludes defects or damage caused by: 

1. abuse,  improper  modification,  improper  maintenance,  or  improper  operation  by persons other than Seller; 

2. excessive  corrosion  or  chemical  attack,  unless  corrosive  or  chemically‐damaging conditions were disclosed by Buyer  in the Procurement Contract Documents and the Procurement Contract Documents required the Goods to withstand such conditions; 

3. use in a manner contrary to Seller's written instructions for installation, operation, and maintenance; or 

Page 92: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 21 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 21 

4. normal wear and tear under normal usage. 

D. Seller's  obligation  to  furnish  the  Goods  and  Special  Services  in  accordance  with  the Procurement Contract Documents will be absolute. None of the following will constitute an acceptance of Goods and Special Services that are non‐conforming, or a release of Seller’s obligation  to  furnish  the Goods and Special Services  in accordance with  the Procurement Contract Documents: 

1. observations by Buyer, Engineer, or Project Owner; 

2. recommendation by Engineer or payment by Buyer of any progress or final payment; 

3. use of the Goods by Buyer or Project Owner; 

4. any acceptance by Buyer, Engineer, or Project Owner, or any failure to do so; 

5. the end of the correction period established in Paragraph 9.04; 

6. the issuance of a notice of acceptance; 

7. any inspection, test or approval by others; or 

8. any  correction  of  non‐conforming  Goods  and  Special  Services  by  Buyer  or  Project Owner. 

E. Buyer shall promptly notify Seller of any breach of Seller’s warranties or guarantees. 

9.02 Inspections and Testing 

A. General Provisions 

1. The  Procurement  Contract  Documents  specify  required  inspections  and  tests.  Buyer shall have the right to perform, or cause to be performed, reasonable inspections and require reasonable tests of the Goods at Seller’s facility, and at the Point of Destination. Seller shall allow Buyer a reasonable time to perform such inspections or tests. 

2. Seller shall reimburse Buyer for all expenses, except for travel, lodging, and subsistence expenses of Buyer’s and Engineer's representatives, for inspections and tests specified in the Procurement Contract Documents. If as the result of any such specified testing the Goods are determined to be non‐conforming, then Seller shall also bear the travel, lodging,  and  subsistence expenses of Buyer’s  and Engineer's  representatives,  and all expenses of re‐inspection or retesting. 

3. Buyer  shall  bear  all  expenses  of  inspections  and  tests  that  are  not  specified  in  the Procurement Contract Documents (other than any re‐inspection or retesting resulting from  a  determination  of  non‐conformity,  as  set  forth  in  Paragraph 9.03);  provided, however, that if as the result of any such non‐specified inspections or testing the Goods are  determined  to  be  non‐conforming,  then  Seller  shall  bear  all  expenses  of  such inspections and testing, and of any necessary re‐inspection and retesting. 

4. Seller  shall provide Buyer  timely written notice of  the  readiness of  the Goods  for all inspections, tests, or approvals which the Procurement Contract Documents specify are to be observed by Buyer prior to shipment. 

Page 93: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 22 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 22 

5. Buyer will give Seller timely notice of all specified tests, inspections, and approvals of the Goods which are to be conducted at the Point of Destination, and a representative of Seller will attend such tests, inspections, and approvals. 

6. If, on the basis of inspections or testing, the Goods appear to be conforming, Buyer will give Seller prompt notice thereof. If on the basis of  inspections or testing, the Goods appear  to  be  non‐conforming,  Buyer  will  give  Seller  prompt  notice  thereof  and will advise Seller of the remedy Buyer elects under the provisions of Paragraph 9.03. 

7. Neither payments made by Buyer to Seller prior to any tests or inspections, nor any tests or  inspections,  will  constitute  acceptance  of  non‐conforming  Goods,  or  prejudice Buyer’s rights under the Procurement Contract. 

B. Visual Inspection on Delivery 

1. Buyer will visually inspect the Goods upon delivery solely for purposes of identifying the Goods, general verification of quantities, and observation of apparent condition. Such visual inspection will not be construed as final or as receipt of any Goods and Special Services that, as a result of subsequent inspections and tests, are determined to be non‐conforming. 

2. If, on the basis of the visual inspection specified in Paragraph 9.02.B.1, the Goods appear to  comply  with  the  requirements  of  the  Procurement  Contract  Documents  as  to quantities  and  condition,  then  within  10 days  of  delivery  Buyer  shall  issue  to  Seller Buyer’s acknowledgment of the receipt of Goods. 

C. Final Inspection 

1. After all of  the Goods have been  incorporated  into the Project,  tested  in accordance with such testing requirements as are specified, and are functioning as required, and Seller  has  performed  and  completed  all  Special  Services,  Buyer  will  make  a  final inspection. 

2. If, on  the basis of  the  final  inspection, Buyer determines  that  the Goods and Special Services are conforming, Buyer’s notice thereof will constitute Buyer’s acceptance of the Goods and Special Services, subject to any limitations stated in the notice. 

3. If,  on  the  basis  of  the  final  inspection,  the  Goods  and  Special  Services  are  non‐conforming, Buyer will identify the non‐conformity in writing. 

9.03 Non‐Conforming Goods and Special Services 

A. If, on the basis of inspections and testing prior to delivery, the Goods and Special Services are found to be non‐conforming, or if at any time after Buyer has acknowledged receipt of delivery  and  before  the  expiration  of  the  correction  period  described  in  Paragraph 9.04, Buyer determines that the Goods and Special Services are non‐conforming, then Seller shall promptly, without cost to Buyer and in response to written instructions from Buyer, either correct such non‐conforming Goods and Special Services, or, if Goods are rejected by Buyer, remove and replace the non‐conforming Goods with conforming Goods, including all work required for reinstallation. 

B. Buyer’s Rejection of Non‐Conforming Goods 

Page 94: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 23 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 23 

1. If  Buyer  elects  to  reject  the  Goods  in whole  or  in  part,  Buyer’s  notice  to  Seller will describe in sufficient detail the non‐conforming aspect of the Goods. If Goods have been delivered to Buyer, Seller shall promptly, and within the Procurement Contract Times, remove and replace the rejected Goods. 

2. Seller shall bear all costs, losses and damages attributable to the removal, replacement, reinspection, and retesting of the non‐conforming Goods. 

3. Upon rejection of the Goods, Buyer retains a security interest in the Goods to the extent of any payments made and expenses incurred in their testing and inspection. 

C. Buyer’s Rejection of Non‐Conforming Special Services 

1. If at any  time Buyer elects  to  reject  the Special Services  in whole or  in part, Buyer’s notice to Seller will describe in sufficient detail the non‐conforming aspect of the Special Services. 

2. Seller shall promptly provide conforming Special Services acceptable to Buyer. 

3. If  Seller  fails  to  provide  conforming  Special  Services,  Buyer may  remove  the  Special Services  from  the  scope  of  the  Procurement  Contract,  and  equitably  reduce  the Procurement Contract Price. 

D. Remedying Non‐Conforming Goods: If Buyer elects to permit the Seller to modify the Goods to  correct  the  non‐conformance,  then  Seller  shall  promptly  provide  a  schedule  for  such modifications and shall make the Goods conforming within a reasonable time. 

E. Buyer’s Acceptance of Non‐Conforming Goods:  Instead of  requiring correction or  removal and replacement of non‐conforming Goods discovered either before or after final payment, Buyer may accept the non‐conforming Goods. Seller shall bear all reasonable costs, losses, and damages attributable to Buyer’s evaluation of and determination to accept such non‐conforming Goods. 

F. Seller Obligations: Seller shall pay all claims, costs,  losses, and damages,  including but not limited to all fees and charges for re‐inspection, retesting and for any engineers, architects, attorneys and other professionals, and all  court or arbitration or other dispute resolution costs arising out of or relating to the non‐conforming Goods and Special Services. Seller's obligations will include the costs of the correction or removal and replacement of the non‐conforming Goods and the replacement of property of Buyer and others destroyed by the correction  or  removal  and  replacement  of  the  non‐conforming  Goods,  and  obtaining conforming Special Services from others. 

G. Buyer's Rejection of Conforming Goods: If Buyer asserts that Goods and Special Services are non‐conforming and such Goods and Special Services are determined to be conforming, or if Buyer rejects as non‐conforming Goods and Special Services that are later determined to be conforming, then Seller shall be entitled to reimbursement from Buyer of costs incurred by Seller  in  inspecting,  testing, correcting,  removing, or  replacing  the conforming Goods and Special  Services,  including  but  not  limited  to  fees  and  charges  of  engineers,  architects, attorneys and other professionals, and all  court or arbitration or other dispute resolution costs associated with the incorrect assertion of non‐conformance or rejection of conforming Goods and Special Services. 

Page 95: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 24 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 24 

9.04 Correction Period 

A. Seller’s responsibility for correcting all non‐conformities in the Goods and Special Services will extend for a period of one year after the acceptance of the Goods and Special Services in accordance with Paragraph 9.02.C.2. 

B. Where non‐conforming Goods and Services (and damage to other work resulting therefrom) have been corrected or removed and replaced under this paragraph, the correction period hereunder with respect to such Goods and Services will be extended for an additional period of  one  year  after  such  correction  or  removal  and  replacement  has  been  satisfactorily completed. 

C. Seller’s  obligations  under  this  paragraph  are  in  addition  to  all  other  obligations  and warranties. The provisions of this paragraph may not be construed as a substitute for, or a waiver of, the provisions of any applicable statute of limitation or repose. 

ARTICLE 10—ENGINEER’S STATUS 

10.01 Engineer’s Role Defined 

A. Engineer  will  be  Buyer’s  representative  until  assignment  (if  any)  of  the  Procurement Contract. 

B. The  duties  and  responsibilities  and  the  limitations  of  authority  of  Engineer  prior  to assignment, if any, of the Procurement Contract, are set forth in the Procurement Contract Documents. 

C. Engineer’s responsibilities, if any, after an assignment (if any) of the Procurement Contract, are set forth in the Procurement Agreement. 

10.02 Duties and Responsibilities; Authority; Limitations 

A. As set forth in Article 3, Engineer will be the initial interpreter of the Procurement Contract Documents and judge of the acceptability of the Goods and Special Services, and will issue clarifications, interpretations, and decisions regarding such issues. 

B. Acting on behalf of Buyer under  the provisions of Article 9, Engineer has  the authority  to disapprove or reject Goods and Special Services that Engineer believes to be non‐conforming. Engineer also has the authority to require special inspection or testing of the Goods or Special Services as provided in Paragraph 9.02, whether or not the Goods are fabricated or installed, or the Special Services are completed. 

C. Engineer  may  authorize  minor  deviations  or  variations  in  the  Procurement  Contract Documents by: 1) written approval of specific variations set  forth  in Shop Drawings when Seller has duly noted such variations as required in Paragraph 7.06.A.3, or 2) a Field Order. 

D. As set forth in Article 12, Engineer will review Claims, and render decisions on Claims. 

E. In  rendering  any  interpretations,  clarifications,  reviews,  decisions,  disapprovals, acceptances, rejections, authorizations, and judgments, Engineer will not show partiality to Buyer or Seller. Engineer will not be liable to Buyer, Seller, or others in connection with any interpretations,  clarifications,  reviews,  decisions,  disapprovals,  acceptances,  rejections, authorizations, or judgments conducted or rendered by Engineer in good faith. 

Page 96: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 25 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 25 

F. Engineer will not supervise, direct, control, or have authority over or be responsible for the means,  methods,  techniques,  sequences,  or  procedures  used  by  Seller  to  perform  its obligations  under  this  Procurement  Contract,  or  the  safety  precautions  and  programs incident thereto, or for any failure of Seller to comply with Laws and Regulations applicable to the performance of its obligations. Engineer will not be responsible for Seller’s failure to furnish  the  Goods  and  Special  Services  in  accordance  with  the  Procurement  Contract Documents. 

ARTICLE 11—CHANGES 

11.01 Amending and Supplementing the Procurement Contract 

A. The Procurement Contract may be amended or supplemented by a Change Order, a Change Directive, or a Field Order. 

B. If  an  amendment  or  supplement  to  the  Procurement  Contract  includes  a  change  in  the Procurement  Contract  Price  or  the  Procurement  Contract  Times,  such  amendment  or supplement must be set forth in a Change Order. 

C. All changes to the Procurement Contract that involve (1) the conformance or acceptability of the Goods and Special Services,  (2) the design (as set forth  in the Procurement Drawings, Procurement  Specifications,  or  otherwise),  or  (3) other  engineering  or  technical matters, must be supported by Engineer’s recommendation. Buyer and Seller may amend other terms and conditions of the Procurement Contract without the recommendation of the Engineer. 

11.02 Change Orders 

A. Buyer and Seller shall execute appropriate Change Orders covering: 

1. Changes  in  Procurement  Contract  Price  or  Procurement  Contract  Times  which  are agreed to by the parties, including any undisputed sum or amount of time for Goods and Special Services furnished in accordance with a Change Directive; 

2. Changes in Procurement Contract Price resulting from a Buyer set‐off, unless Seller has duly contested such set‐off; 

3. Changes in the Goods and Special Services which are: (a) ordered by Buyer pursuant to Paragraph 11.05, (b) required because of Buyer’s acceptance of non‐conforming Goods and Services under Paragraph 9.03 or (c) agreed to by the parties, subject to the need for Engineer’s recommendation if the change in the Goods and Special Services involves the design (as set forth in the Procurement Drawings, Procurement Specifications, or otherwise) or other engineering or technical matters; and 

4. Changes  that  embody  the  substance  of  any  final  and  binding  results  under: Paragraph 11.03.B, resolving the impact of a Change Directive; Article 12, Claims; and similar provisions. 

B. If Buyer or Seller refuses to execute a Change Order that is required to be executed under the terms of Paragraph 11.02.A,  it will be deemed to be of full force and effect, as if fully executed. 

Page 97: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 26 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 26 

11.03 Change Directives 

A. A  Change  Directive will  not  change  the  Procurement  Contract  Price  or  the  Procurement Contract  Times  but  is  evidence  that  the  parties  expect  that  the modification  ordered  or documented by a Change Directive will be  incorporated  in a  subsequently  issued Change Order, following negotiations by the parties as to the Change Directive’s effect, if any, on the Procurement  Contract  Price  and  Procurement  Contract  Times;  or,  if  negotiations  are unsuccessful, by a determination under the terms of the Procurement Contract Documents governing  adjustments,  expressly  including  Paragraph 11.08  regarding  change  of Procurement Contract Price. 

B. If Buyer has  issued a Change Directive and Buyer or Seller believes that an adjustment  in Procurement Contract Times or Procurement Contract Price  is necessary,  then such party shall submit a Claim seeking such an adjustment no later than 30 days after the completion of the Goods and Services set out in the Change Directive. 

11.04 Field Orders 

A. Engineer may  authorize minor  changes  in  the Goods  and  Services  if  the  changes  do  not involve an adjustment in the Procurement Contract Price or the Procurement Contract Times and  are  compatible  with  the  design  concept  as  indicated  by  the  Procurement  Contract Documents. Such changes will be accomplished by a Field Order and will be binding on Buyer and also on Seller, which shall perform the Goods and Special Services involved promptly. 

B. If Seller believes that a Field Order justifies an adjustment in the Procurement Contract Price or Procurement Contract Times, then before proceeding with the Goods and Special Services at issue, Seller shall submit a Claim as provided herein. 

11.05 Buyer‐Authorized Changes in the Goods and Special Services 

A. Without invalidating the Procurement Contract and without notice to any surety, Buyer may, at any time or from time to time, order additions, deletions, or revisions in the Goods and Special Services. Changes  involving  the design  (as set  forth  in  the Procurement Drawings, Procurement Specifications, or otherwise) or other engineering or technical matters will be supported by Engineer’s recommendation. 

B. Such changes in the Goods and Special Services may be accomplished by a Change Order, if Buyer and Seller have agreed as to the effect, if any, of the changes on Procurement Contract Times or Procurement Contract Price; or by a Change Directive. Upon receipt of any such document, Seller shall promptly proceed with the Goods and Special Services involved; or, in the  case  of  a  deletion  in  the  Goods  and  Special  Services,  promptly  cease  activities  with respect to such deletion. Added or revised Goods and Special Services must be performed under the applicable conditions of the Procurement Contract Documents. 

11.06 Buyer’s Contingency Allowance 

A. The Buyer’s Contingency Allowance, if any such is set forth in the Procurement Agreement, is for the sole use of Buyer to cover unanticipated costs. 

B. If  Buyer  exercises  its  unilateral  right  to  use  all  or  a  portion  of  the  Buyer’s  Contingency Allowance,  Buyer  will  issue  a  written  directive  that  documents  the  costs  to  which  the 

Page 98: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 27 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 27 

allowance is applied, Seller’s entitlement to compensation, and the consequent reduction in such allowance. 

C. Prior to final payment, the Total Price, as set forth in the Procurement Agreement, will be duly adjusted to account for any unused portion of the Buyer’s Contingency Allowance. 

D. The  Procurement  Agreement,  Article 5,  addresses  the  impact  on  Buyer’s  Contingency Allowance of an assignment of the Procurement Contract. 

11.07 Unauthorized Changes in the Goods and Special Services 

A. Seller shall not be entitled to an increase in the Procurement Contract Price or an extension of the Procurement Contract Times with respect to any work performed that is not required by the Procurement Contract Documents, as amended, modified, or supplemented. 

11.08 Change of Procurement Contract Price 

A. The Procurement Contract Price may only be changed by a Change Order. Any Claim for an adjustment of Procurement Contract Price must comply with the provisions of Article 12. 

B. An adjustment in the Procurement Contract Price will be determined as follows: 

1. For changes in Unit Price Goods and Special Services, by application of the unit prices to the quantities of the items involved;  

2. To the extent the cost of the change is not covered by unit prices, then by a mutually agreed lump sum; or 

3. To the extent the cost of the change is not covered by unit prices and the parties do not reach mutual agreement to a lump sum, then on the basis of documented costs plus a Seller’s fee for overhead and profit of 15%. 

11.09 Change of Procurement Contract Times 

A. The Procurement Contract Times may only be changed by a Change Order. Any Claim for an adjustment  in  the  Procurement  Contract  Times  must  comply  with  the  provisions  of Article 12. 

11.10 Notification to Surety 

A. If the provisions of any bond require notice to be given to a surety of any change affecting the general scope of the Goods and Special Services or the provisions of the Procurement Contract (including, but not limited to, Procurement Contract Price or Procurement Contract Times),  the  giving  of  any  such  notice  will  be  Seller’s  responsibility.  The  amount  of  each applicable bond will be adjusted to reflect the effect of any such change. 

ARTICLE 12—CLAIMS, DISPUTES, AND DISPUTE RESOLUTION 

12.01 Claims 

A. The  parties  agree  to  endeavor  to  avoid  or  resolve  Claims  through  direct,  good  faith discussions and negotiations whenever practicable. Such discussions and negotiations should at  the outset address whether  the parties mutually agree to suspend  the Claims process, including the time periods established in this Paragraph 12.01; if so, a written record of such mutual agreement should be made and jointly executed. 

Page 99: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 28 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 28 

B. Claimant shall deliver to Engineer and the other party to the Procurement Contract written notice of each Claim within 15 days after the occurrence of the event giving rise to the Claim. 

C. Claimant shall deliver written supporting data to Engineer and the other party within 45 days after such occurrence unless Engineer allows an additional period of time. 

D. Engineer will review each such Claim and render a decision in writing within 30 days after receipt of the last submittal of the claimant or the last submittal of the opposing party, if any. 

E. If Engineer does not render a formal written decision on a Claim within the time stated in Paragraph 12.01.D., Engineer shall be deemed to have issued a decision denying the Claim in its entirety 31 days after receipt of the last submittal of the claimant or the last submittal of the opposing party, if any. 

F. The rendering of a decision by Engineer pursuant to this Paragraph 12.01 with respect to any such Claim, dispute, or other matter (except any which have been waived by the making or acceptance of final payment) will be a condition precedent to any exercise by Buyer or Seller of such rights or remedies as either may otherwise have under the Procurement Contract Documents or by Laws or Regulations in respect of any such Claim, dispute, or other matter. If the exercise of such rights or remedies will imminently be time‐barred, a party may take actions  necessary  to  preserve  such  rights  and  remedies  notwithstanding  the  lack  of  the condition precedent referred to in this paragraph. 

G. If  a  submitted  matter  in  question  concerns  terms  and  conditions  of  the  Procurement Contract Documents that do not involve (1) the performance or acceptability of Goods and Special Services under the Procurement Contract Documents, (2) the design (as set forth in the Procurement Drawings, Procurement Specifications, Addenda, or otherwise), or (3) other engineering or technical matters, then Engineer will promptly give written notice to Buyer and Seller that Engineer is unable to provide a decision or interpretation. If Buyer and Seller are unable  to agree on  resolution of  such a matter  in question, either party may pursue resolution as provided in Paragraph 12.02. 

H. Engineer’s written decision on such Claim or a decision denying the Claim in its entirety that is deemed to have been issued pursuant to Paragraph 12.01, will be final and binding upon Buyer and Seller 30 days after it is issued unless within 30 days of issuance Buyer or Seller appeals Engineer’s decision by initiating the mediation of such Claim in accordance with the dispute resolution procedures set forth in Paragraph 12.02. 

I. If Article 12 has been amended to delete the mediation requirement, then Buyer or Seller may  appeal  Engineer's  decision  within  30 days  of  issuance  by  following  the  alternative dispute  resolution  process  set  forth  in  Article 12,  as  amended;  or  if  no  such  alternative dispute resolution process has been set forth, Buyer or Seller may appeal Engineer's decision by 1) delivering to the other party within 30 days of the date of such decision a written notice of intent to submit the Claim to a court of competent jurisdiction, and 2) within 60 days after the date of such decision instituting a formal proceeding in a court of competent jurisdiction. 

J. No Claim for an adjustment in Procurement Contract Price or Procurement Contract Times will be valid if not submitted in accordance with Article 12. 

K. The  effect  on  Claims  of  an  assignment  of  the  Procurement  Contract  by  Buyer  to  a Contractor/Assignee is addressed in the Procurement Agreement, Article 5. 

Page 100: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 29 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 29 

12.02 Dispute Resolution Method 

A. Either  Buyer  or  Seller  may  initiate  the  mediation  of  (1) any  Claim  decided  in  writing  by Engineer under Paragraph 12.01 before such decision becomes final and binding, or (2) any other dispute between the parties, including but not limited to any dispute arising after final inspection of the Goods and Services. The mediation will be governed by the Construction Industry Mediation Rules of the American Arbitration Association in effect as of the Effective Date of the Procurement Contract. The request for mediation must be submitted in writing to the American Arbitration Association and the other party to the Procurement Contract. Timely  submission  of  the  request  will  stay  Engineer's  decision  from  becoming  final  and binding. 

B. Mediation  is  a  condition  precedent  to  seeking  final  dispute  resolution  under Paragraph 12.01.C. Buyer and Seller shall participate in the mediation process in good faith. The  process  must  be  concluded  within  60 days  of  filing  of  the  request.  The  date  of termination  of  the  mediation  will  be  determined  by  application  of  the  mediation  rules referenced above. 

C. If the mediation process does not result in resolution of the dispute, then Engineer’s written Claim  decision  under  Paragraph 12.01.D  or  a  Claim  denial  pursuant  to  Paragraph 12.01.E becomes final and binding, or if applicable such other dispute is deemed resolved in favor of respondent, unless, within 30 days after termination of the mediation, Buyer or Seller: 

1. elects  in  writing  to  invoke  any  final  dispute  resolution  process  provided  for  in  the Supplementary Conditions, or 

2. agrees with  the other  party  to  submit  the Claim or  dispute  to  another  final  dispute resolution process, or 

3. if  no  final  dispute  resolution  process  has  been  provided  for  in  the  Supplementary Conditions, delivers to the other party written notice of the intent to submit the Claim or dispute to a court of competent jurisdiction, and within 60 days of the termination of the mediation institutes such formal proceeding. 

ARTICLE 13—PAYMENT 

13.01 Applications for Progress Payments 

A. Seller shall  submit  to Buyer  for Engineer’s  review Applications  for Payment  filled out and signed by Seller and accompanied by such supporting documentation as is required by the Procurement Contract Documents and also as Buyer or Engineer may reasonably require. 

B. The  timing  and  amounts  of  progress  payments will  be  as  stipulated  in  the  Procurement Agreement. 

C. Any Application for Payment that is based in whole or in part on the delivery of Goods must be accompanied by a bill of sale, invoice, or other documentation reasonably satisfactory to Buyer warranting that Buyer has rightfully received good title to the Goods from Seller and that, upon payment, the Goods will be free and clear of all liens. Such documentation will include releases and waivers from all parties with viable lien rights. 

D. Buyer shall notify Seller promptly of any deficiency in the required documentation. 

Page 101: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 30 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 30 

13.02 Review of Applications for Progress Payments 

A. Review of Applications 

1. Engineer will, within 10 days after receipt of each Application for Payment,  including each resubmittal, either indicate in writing a recommendation of payment and present the  Application  to  Buyer,  or  return  the  Application  to  Seller  indicating  in  writing Engineer’s reasons for refusing to recommend payment. 

2. Engineer’s recommendation of any payment requested in an Application for Payment will constitute a representation by Engineer to Buyer, based on Engineer’s observations of  Seller’s  progress,  as  an  experienced  and  qualified  design  professional,  and  on Engineer’s  review  of  the  Application  for  Payment  and  the  accompanying  data  and schedules, that to the best of Engineer’s knowledge, information and belief: 

a. the Goods and Special Services or other obligations of Seller have progressed to the point indicated; 

b. the  quality  of  the Goods  and  Special  Services  or  other  obligations  of  Seller  are generally in accordance with the Procurement Contract Documents; and 

c. the conditions precedent to Seller being entitled to such payment appear to have been  fulfilled  in  so  far  as  it  is  Engineer’s  responsibility  to  observe  the  Seller’s progress. 

3. By  recommending  any  such  payment  Engineer will  not  thereby  be  deemed  to  have represented that: 

a. inspections made  to check  the quality or  the quantity of  the Goods and Special Services or other obligations of  Seller  have been exhaustive,  extended  to every aspect of the Goods and Special Services or other obligations of Seller in progress, or  involved  detailed  inspections  of  the  Goods  and  Special  Services  or  other obligations of Seller beyond the responsibilities specifically assigned to Engineer in the Procurement Contract; or 

b. there may not be other matters or issues between the parties that might entitle Seller  to be paid additionally by Buyer, or entitle Buyer  to withhold payment  to Seller. 

4. Neither  Engineer’s  review  of  Seller’s  progress  for  the  purposes  of  recommending payments nor Engineer’s recommendation of any payment, including final payment, will impose responsibility on Engineer: 

a. to supervise, direct, or control the Seller’s performance or furnishing of Goods and Special Services or other obligations of Seller; or 

b. for  the means, methods,  techniques,  sequences, or procedures of  construction, manufacturing, fabrication, installation, or shipping, or the safety precautions and programs incident thereto; or 

c. for  Seller’s  failure  to  comply  with  Laws  and  Regulations  applicable  to  Seller’s performance under the Procurement Contract; or 

Page 102: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 31 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 31 

d. to make any examination to ascertain how or for what purposes Seller has used the money paid for the Procurement Contract Price; or 

e. to determine that  title  to any of  the Goods or component parts have passed to Buyer free and clear of any Liens. 

5. Engineer  may  refuse  to  recommend  the  whole  or  any  part  of  any  payment  if,  in Engineer’s opinion, it would be incorrect to make the representations to Buyer stated in Paragraph 13.02.A.2. 

6. Engineer  will  recommend  reductions  in  payment  (set‐offs)  necessary  in  Engineer’s opinion to protect Buyer from loss because: 

a. the Goods and Services are non‐conforming, requiring correction or replacement; 

b. the Procurement Contract Price has been reduced by Change Orders; 

c. Buyer has been required to correct non‐conforming Goods and Special Services in accordance with  Paragraph 9.03.C,  or  has  accepted  non‐conforming  Goods  and Special Services pursuant to Paragraph 9.03.E; or 

d. Engineer has actual knowledge of the occurrence of any of the events that would constitute a default by Seller and therefore justify termination for cause under the Procurement Contract Documents. 

13.03 Basis and Amount of Progress Payments 

A. The basis and amounts of  the progress payments will be as provided  in  the Procurement Agreement, subject to the provisions of this Article 13 regarding reductions in payment. 

13.04 Suspension of or Reduction in Payment 

A. Buyer may temporarily cease making progress payments, or reduce the amount of a progress payment,  even  though  recommended  for  payment  by  Engineer,  under  the  following circumstances: 

1. Buyer has reasonable grounds to conclude that Seller will not furnish the Goods or the Special Services in accordance with the Procurement Contract Documents, and 

2. Buyer  has  requested  in  writing  assurances  from  Seller  that  the  Goods  and  Special Services will be delivered or  furnished  in accordance with  the Procurement Contract Documents,  and Seller has  failed  to provide adequate assurances within  ten days of Buyer’s written request. 

3. In addition to any reductions in payment (set‐offs) recommended by Engineer, Buyer is entitled to impose a set‐off against payment based on any of the following: 

a. claims have been made against Buyer based on Seller’s conduct in the performance or furnishing of the Goods and Special Services, or has  incurred costs,  losses, or damages resulting from Seller’s conduct  in the performance or furnishing of  the Goods and Special  Services,  including but not  limited  to claims, costs,  losses, or damages from workplace injuries, adjacent property damage, non‐compliance with Laws and Regulations, and patent infringement; 

Page 103: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 32 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 32 

b. Seller  has  failed  to  take  reasonable  and  customary measures  to  avoid  damage, delay, disruption, and interference with other work at or adjacent to the Point of Destination or the worksite; 

c. Seller has failed to provide and maintain required bonds or insurance; 

d. Buyer has incurred extra charges or engineering costs related to Submittal reviews, evaluations  of  proposed  substitutes,  tests  and  inspections,  or  return  visits  to manufacturing or assembly facilities; 

e. the  Goods  and  Special  Services  are  non‐conforming,  requiring  correction  or replacement; 

f. Buyer has been required to correct non‐conforming Goods and Special Services, in accordance with  Paragraph 9.03.C,  or  has  accepted  non‐conforming  Goods  and Special Services pursuant to Paragraph 9.03.E; 

g. the Procurement Contract Price has been reduced by Change Orders; 

h. an  event  that  would  constitute  a  default  by  Seller  and  therefore  justify  a termination for cause has occurred; 

i. liquidated or other damages have accrued as a result of Seller’s failure to achieve Milestones, Substantial Completion, or final completion of the Goods and Special Services; or 

j. liens have been filed in connection with the Procurement Contract, except where Seller has delivered a specific bond satisfactory to Buyer to secure the satisfaction and discharge of such liens. 

B. If Buyer refuses to make payment of the full amount recommended by Engineer, Buyer will provide Seller and Engineer immediate written notice stating the reason for such action and promptly pay Seller any amount remaining after deduction of the amount withheld. Buyer shall  promptly  pay  Seller  the  amount withheld when  Seller  corrects  the  reason  for  such action to Buyer’s satisfaction. 

13.05 Final Payment 

A. After Seller has corrected all non‐conformities to the reasonable satisfaction of Buyer and Engineer  and  furnished  all  Special  Services,  Seller  may  submit  its  final  Application  for Payment following the procedures for progress payments. 

B. The final Application for Payment will be accompanied by all documentation called for in the Procurement  Contract  Documents  (including  but  not  limited  to  all  final  operations  and maintenance manuals,  and any  special warranties),  a  list  of  all  unsettled Claims,  and  the written consent of surety to the making of final payment. 

C. If, on the basis of final inspection and the review of the final Application for Payment and accompanying documentation, Engineer is reasonably satisfied that Seller has furnished the Goods and Special Services in accordance with the Procurement Contract Documents, and that  Seller has  fulfilled all other obligations under  the Procurement Contract Documents, then Engineer will, within 10 days after receipt of the final Application for Payment, indicate in  writing  Engineer’s  recommendation  of  final  payment  subject  to  the  provisions  of 

Page 104: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 33 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 33 

Paragraph 13.02,  and  present  the  final  Application  for  Payment  to  Buyer.  Such recommendation  will  account  for  any  set‐offs  against  payment  that  are  necessary  in Engineer’s opinion to protect Buyer from loss for the reasons stated in Paragraph 13.02. 

D. If Engineer does not recommend final payment, Engineer will return the final Application for Payment to Seller, indicating the reasons for refusing to recommend final payment, in which case  Seller  shall  make  the  necessary  corrections  and  resubmit  the  final  Application  for Payment. 

E. In support of its recommendation of final payment Engineer will also give written notice to Buyer  and  Seller  that  the  Goods  and  Special  Services  are  acceptable,  subject  to  stated limitations in the notice and to the provisions of Paragraph 13.06. 

F. If the final Application for Payment and accompanying documentation are appropriate as to form and substance, Buyer shall, within 30 days after receipt thereof, pay Seller the amount recommended  by  Engineer,  less  any  sum  Buyer  is  entitled  to  set  off  against  Engineer's recommendation, pursuant to the provisions of Paragraph 13.04. 

G. Buyer will not make final payment, or return or release  included retainage (if any) at any time, unless Seller submits written consent of the surety to such payment, return, or release. 

13.06 Waiver of Claims 

A. By making  final  payment,  Buyer waives  its  claim or  right  to  liquidated  damages or  other damages for late completion by Seller, except as set forth in an outstanding Claim, appeal, set‐off, or express reservation of rights by Buyer. Buyer reserves all other claims or rights after final payment. 

B. The acceptance of final payment by Seller will constitute a waiver by Seller of all claims and rights against Buyer other  than  those pending matters  that have been duly  submitted or appealed under the provisions of Article 12. 

ARTICLE 14—CANCELLATION, SUSPENSION, AND TERMINATION 

14.01 Cancellation 

A. Buyer has the right to cancel the Procurement Contract, without cause, at any time prior to delivery of the Goods by written notice. Cancellation pursuant to the terms of this paragraph will not constitute a breach of contract by Buyer. Upon cancellation: 

1. Buyer shall pay Seller for the direct costs incurred in producing any Goods that Seller has  specially  manufactured  for  the  Project,  plus  a  fair  and  reasonable  amount  for overhead and profit. 

2. For Goods that are not specially manufactured for the Project, Seller shall be entitled to a  restocking  charge of 10 percent of  the unpaid Procurement Contract Price of  such Goods. 

14.02 Suspension of Performance by Buyer 

A. Buyer has the right to suspend performance of the Procurement Contract for up to 90 days, without  cause,  by written  notice.  Upon  suspension  under  this  paragraph,  Seller  shall  be entitled to an increase in the Procurement Contract Times and Procurement Contract Price 

Page 105: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 34 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 34 

caused by the suspension, provided that performance would not have been suspended or delayed for causes attributable to Seller. 

14.03 Suspension of Performance by Seller 

A. Seller may suspend the furnishing of the Goods and Special Services only under the following circumstance: 

1. Seller  has  reasonable  grounds  to  conclude  that  Buyer  will  not  perform  its  future payment obligations under the Procurement Contract; and 

2. Seller  has  requested  in writing  assurances  from  Buyer  that  future  payments will  be made  in accordance with the Procurement Contract, and Buyer has failed to provide such assurances within ten days of Seller’s written request. 

14.04 Breach and Termination 

A. Buyer’s Breach 

1. Seller shall have the right to terminate the Procurement Contract for cause by declaring a  breach  if  Buyer  fails  to  comply  with  any  material  provision  of  the  Procurement Contract. Upon termination, Seller shall be entitled to all remedies provided by Laws and Regulations. 

2. If Seller believes Buyer is in breach of its obligations under the Procurement Contract, Seller  shall  provide  Buyer  with  reasonably  prompt  written  notice  setting  forth  in sufficient detail the reasons for declaring that it believes a breach has occurred. Buyer shall have 7 days from receipt of the written notice declaring the breach (or such longer period  of  time  as  Seller  may  grant  in  writing)  within  which  to  cure  or  to  proceed diligently to cure such alleged breach. 

B. Seller’s Breach 

1. Buyer may terminate Seller’s right to perform the Procurement Contract for cause by declaring  a  breach  should  Seller  fail  to  comply  with  any  material  provision  of  the Procurement  Contract  Documents.  Upon  termination,  Buyer  shall  be  entitled  to  all remedies provided by Laws and Regulations. 

2. In the event Buyer believes Seller is in breach of its obligations under the Procurement Contract, Buyer shall provide Seller with reasonably prompt written notice setting forth in sufficient detail the reasons for declaring that it believes a breach has occurred. Seller shall have 7 days from receipt of the written notice declaring the breach (or such longer period  of  time  as  Buyer  may  grant  in  writing)  within  which  to  cure  or  to  proceed diligently to cure such alleged breach. 

3. If and to the extent that Seller has provided a performance bond under the provisions of Paragraph 5.01, the notice and cure procedures of that bond, if any, will supersede the notice and cure procedures of Paragraph 14.04.B.2. 

Page 106: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 35 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 35 

ARTICLE 15—MISCELLANEOUS 

15.01 Giving Notice 

A. Whenever any provision of the Procurement Contract requires the giving of written notice to Buyer, Seller, or Engineer, it will be deemed to have been validly given if delivered: 

1. in  person,  by  a  commercial  courier  service  or  otherwise,  to  the  recipient’s  place  of business; 

2. by registered or certified mail, postage prepaid, to the recipient’s place of business; or 

3. by e‐mail  to  the  recipient, with  the words  “Formal Notice” or  similar  in  the e‐mail’s subject line. 

15.02 Controlling Law 

A. This Procurement Contract is to be governed by the law of the state in which the Goods are to be installed. 

B. In the case of any conflict between the express terms of this Procurement Contract and the Uniform Commercial Code, as adopted in the state whose law governs, it is the intent of the parties that the express terms of this Procurement Contract will apply. 

15.03 Computation of Time 

A. When any period of time is referred to in the Procurement Contract by number of days, it will be computed to exclude the first and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day will be omitted from the computation. 

15.04 Cumulative Remedies 

A. The duties and obligations imposed by these General Conditions and the rights and remedies available hereunder to the parties hereto are in addition to, and are not to be construed in any way as a limitation of, any rights and remedies available to any or all of them which are otherwise imposed or available by Laws or Regulations, by special warranty or guarantee, or by other provisions of the Procurement Contract, and the provisions of this paragraph will be as effective as  if  repeated specifically  in  the Procurement Contract  in connection with each particular duty, obligation, right, and remedy to which they apply. 

15.05 Survival of Obligations 

A. All representations, indemnifications, warranties, and guarantees made in, required by, or given  in  accordance with  the  Procurement  Contract,  as well  as  all  continuing  obligations indicated  in  the  Procurement  Contract,  will  survive  final  payment,  completion,  and acceptance  of  the  Goods  and  Special  Services  or  termination  or  completion  of  the Procurement Contract or of the services of Seller. 

15.06 Entire Agreement 

A. Buyer and Seller agree that this Procurement Contract is the complete and final agreement between them, and supersedes all prior negotiations, representations, or agreements, either written or oral. This Procurement Contract may not be altered, modified, or amended except in writing signed by an authorized representative of both parties. 

Page 107: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 36 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 36 

15.07 No Waiver 

A. A party’s non‐enforcement of any provision will not constitute a waiver of that provision, nor will  it  affect  the enforceability of  that provision or of  the  remainder of  this Procurement Contract. 

15.08 Headings 

A. Article and paragraph headings are inserted for convenience only and do not constitute parts of these General Conditions. 

15.09 Successors and Assigns 

A. Buyer and Seller each binds itself, its partners, successors, assigns, and legal representatives to  the  other  party  hereto,  its  partners,  successors,  assigns,  and  legal  representatives  in respect  to  all  covenants,  agreements,  and  obligations  contained  in  the  Procurement Contract. 

   

Page 108: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P‐700, Standard General Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies, 

and American Society of Civil Engineers. All rights reserved. Page 37 of 37 

STV‐00 70 00 General Conditions of the Procurement Contract 2019.docx  00 70 00 ‐ 37 

THIS PAGE INTENTIONALLY LEFT BLANK 

Page 109: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-800, Supplementary Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. TOC Page 1 of 1

STV-00 80 00 Supplementary Conditions for Procurement 2019.docx 00 80 00 - i

SECTION 00 80 00 - SUPPLEMENTARY CONDITIONS OF THE PROCUREMENT CONTRACT

TABLE OF CONTENTS

Page

Article 1— Definitions and Terminology ....................................................................................................... 1

Article 2— Preliminary Matters .................................................................................................................... 1

Article 3— Procurement Contract Documents ............................................................................................. 1

Article 4— Commencement and Schedule ................................................................................................... 1

Article 5— Bonds and Insurance ................................................................................................................... 2

Article 6— Licenses and Fees ........................................................................................................................ 4

Article 7— Seller’s Responsibilities ............................................................................................................... 5

Article 8— Shipping and Delivery ................................................................................................................. 5

Article 9— Buyer’s Rights .............................................................................................................................. 6

Article 10— Engineer’s Status ....................................................................................................................... 6

Article 11— Changes ..................................................................................................................................... 6

Article 12— Claims, Disputes, and Dispute Resolution ................................................................................ 6

Article 13— Payment .................................................................................................................................... 6

Article 14— Cancellation, Suspension, and Termination ............................................................................. 7

Article 15— Miscellaneous ........................................................................................................................... 7

Page 110: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-800, Supplementary Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 1 of 7

STV-00 80 00 Supplementary Conditions for Procurement 2019.docx 00 80 00 - 1

SUPPLEMENTARY CONDITIONS OF THE PROCUREMENT CONTRACT

These Supplementary Conditions amend or supplement EJCDC® P-700, Standard General Conditions of the Procurement Contract (2019). The General Conditions remain in full force and effect except as amended.

Supplementary Conditions are also included in the following Sections:

1. Section 00 22 00 - Washington State Department of Ecology (Ecology) Water Pollution Control State Revolving Fund (SRF) Pre-Selection Specification Insert.

The terms used in these Supplementary Conditions have the meanings stated in the General Conditions. Additional terms used in these Supplementary Conditions have the meanings stated below, which are applicable to both the singular and plural thereof.

The address system used in these Supplementary Conditions is the same as the address system used in the General Conditions, with the prefix "SC" added.

ARTICLE 1—DEFINITIONS AND TERMINOLOGY

1.01 Defined Terms

SC-1.01.A Add the following new paragraphs immediately after Paragraph 1.01.A.40:

41. Owner: The Buyer. Refer to Section 00 70 00, Paragraph 1.01.A.5.

42. Site: The Point of Destination. Refer to Section 00 70 00, Paragraph 1.01.A.20.

43. Manufacturer: Seller. Refer to Section 00 70 00, Paragraph 1.01.A.34.

44. Work: The Goods and Special Services. Refer to Section 00 70 00, Paragraph 1.01.A.16.

ARTICLE 2—PRELIMINARY MATTERS

2.02 Copies of Documents

SC-2.02 Delete Paragraph 2.02.A in its entirety and insert the following in its place:

Buyer shall furnish to Seller one (1) fully signed counterpart of the Procurement Agreement, and one (1) copy of the Procurement Contract Documents in electronic portable document format (PDF).

ARTICLE 3—PROCUREMENT CONTRACT DOCUMENTS

No Supplementary Conditions in this Article.

ARTICLE 4—COMMENCEMENT AND SCHEDULE

No Supplementary Conditions in this Article.

Page 111: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-800, Supplementary Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 2 of 7

STV-00 80 00 Supplementary Conditions for Procurement 2019.docx 00 80 00 - 2

ARTICLE 5—BONDS AND INSURANCE

5.01 Performance, Payment, and Other Bonds

SC-5.01 Add the following paragraphs immediately after Paragraph 5.01.A:

1. Required Performance Bond Form: The performance bond that Seller furnishes will be in the form of EJCDC® P-610, Performance Bond (2019 edition).

2. Required Payment Bond Form: The payment bond that Seller furnishes will be in the form of EJCDC® P-615, Payment Bond (2019 edition).

5.02 Insurance

SC-5.02 Add the following new paragraphs immediately after Paragraph 5.02.E:

F. Seller shall purchase and maintain such liability and other insurance as is appropriate for the furnishing of Goods and Special Services and as will provide protection from claims set forth below which may arise out of or result from Seller’s furnishing of the Goods or Special Services and Seller’s other obligations under the Procurement Contract Documents, whether the furnishing of Goods and Special Services or other obligations are to be performed by Seller, any subcontractor or supplier, or by anyone directly or indirectly employed by any of them to furnish the Goods and Special Services, or by anyone for whose acts any of them may be liable:

1. claims under workers’ compensation, disability benefits, and other similar employee benefit acts;

2. claims for damages because of bodily injury, occupational sickness or disease, or death of Seller’s employees;

3. claims for damages because of bodily injury, sickness or disease, or death of any person other than Seller’s employees;

4. claims for damages insured by reasonably available personal injury liability coverage which are sustained: (a) by any person as a result of an offense directly or indirectly related to the employment of such person by Seller, or (b) by any other person for any other reason;

5. claims for damages, other than to the Goods, because of injury to or destruction of tangible property wherever located, including loss of use resulting therefrom; and

6. claims for damages because of bodily injury or death of any person or property damage arising out of the ownership, maintenance or use of any motor vehicle.

G. The policies of insurance so required by this Paragraph 5.02 to be purchased and maintained must:

1. with respect to insurance required by Paragraphs SC-5.02.F.3 through SC-5.02.F.6 inclusive, include as additional insureds (subject to any customary exclusion in respect of professional liability) Buyer, Engineer, their consultants, and

Esvelt Environmental Engineering, LLC, 8812 East Redwood Lane, Spokane, WA 99217,

Page 112: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-800, Supplementary Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 3 of 7

STV-00 80 00 Supplementary Conditions for Procurement 2019.docx 00 80 00 - 3

all of whom must be listed as additional insureds, and include coverage for the respective officers, directors, partners, employees, agents, and other consultants and subcontractors of each and any of all such additional insureds, and the insurance afforded to these additional insureds must provide primary coverage for all claims covered thereby;

2. include at least the specific coverages and be written for not less than the limits of liability provided below or required by Laws or Regulations, whichever is greater;

3. include completed operations insurance;

4. include contractual liability insurance covering Seller’s indemnity obligations under Paragraph 7.07;

5. contain a provision or endorsement that the coverage afforded will not be canceled, or renewal refused, until at least 10 days prior written notice has been given to the purchasing policyholder. Within three days of receipt of any such written notice, the purchasing policyholder will provide a copy of the notice to the other party, each other insured, and Engineer;

6. remain in effect at least until final payment and at all times thereafter when Seller may be correcting, removing, or replacing non-conforming Goods in accordance with Paragraph 9.03 and 9.04; and

7. with respect to completed operations insurance, and any insurance coverage written on a claims-made basis, remain in effect for at least two years after final payment (and Seller shall furnish Buyer and each other additional insured identified in these Supplementary Conditions, to whom a certificate of insurance has been issued, evidence satisfactory to Buyer and any such additional insured of continuation of such insurance at final payment and one year thereafter).

H. The limits of liability for the insurance required by Paragraph SC-5.02.F must provide coverage for not less than the following amounts or greater where required by Laws and Regulations:

1. Workers’ Compensation, and related coverages under Paragraphs SC-5.02.F.1 and F.2:

Workers’ Compensation and Related Policies Policy limits of not less than

Workers’ Compensation State Statutory Applicable Federal (e.g., Longshoreman’s) Statutory Foreign voluntary workers’ compensation (employer’s responsibility coverage), if applicable

Statutory

Jones Act (if applicable) Bodily injury by accident—each accident (for maritime occupations)

$ N/A

Bodily injury by disease—aggregate (for maritime occupations) $ N/A Employer’s Liability Each accident $100,000

Page 113: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-800, Supplementary Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 4 of 7

STV-00 80 00 Supplementary Conditions for Procurement 2019.docx 00 80 00 - 4

Workers’ Compensation and Related Policies Policy limits of not less than

Each employee $100,000 Policy limit $500,000 Stop-gap Liability Coverage For work performed in monopolistic states, stop-gap liability coverage must be endorsed to either the worker’s compensation or commercial general liability policy with a minimum limit of:

$1,000,000

2. Seller’s General Liability under Paragraphs SC-5.02.F.3 through F.6 which must include completed operations and product liability coverages and eliminate the exclusion with respect to property under the care, custody and control of Seller:

Commercial General Liability Policy limits of not less than

General Aggregate $2,000,000 Products—Completed Operations Aggregate $2,000,000 Personal and Advertising Injury $1,000,000 Bodily Injury and Property Damage—Each Occurrence $1,000,000

3. Automobile Liability under Paragraph SC-5.02.F.6:

Automobile Liability Policy limits of not less than

Bodily Injury Each Person $1,000,000 Each Accident $1,000,000 Property Damage Each Accident $1,000,000

4. Professional Liability (if the Special Services include professional services):

Seller’s Professional Liability Policy limits of not less than

Each Claim $ N/A Annual Aggregate $ N/A

I. Seller shall deliver to Buyer, with copies to each additional insured identified in these Supplementary Conditions, certificates of insurance (and other evidence of insurance requested by Buyer or any other additional insured) which Seller is required to purchase and maintain.

ARTICLE 6—LICENSES AND FEES

No Supplementary Conditions in this Article.

Page 114: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-800, Supplementary Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 5 of 7

STV-00 80 00 Supplementary Conditions for Procurement 2019.docx 00 80 00 - 5

ARTICLE 7—SELLER’S RESPONSIBILITIES

7.06 Submittals

SC-7.06 Add the following new paragraph immediately after Paragraph 7.06.E:

F. This section shall be supplemented with Section 01 33 00 Submittal Procedures and Section 01 78 00 Close-Out Submittals of the Technical Specifications.

7.07 Indemnification

SC-7.07 Add the following new paragraphs immediately after Paragraph 7.07.B:

C. Seller assumes responsibility for and shall defend, indemnify and hold the City, its agents, employees and officials (hereinafter “Indemnitee”) harmless from any and all claims, demands, damages, expenses, losses, fines, penalties or liabilities, including loss of use, arising from, resulting in any manner directly or indirectly from or connected with or in the course of the performance of the Work and the obligations herein, including without limitation claims of subcontractors and suppliers contracting with Seller. Seller’s obligation to defend, indemnify and hold Indemnitee harmless shall include, but is not limited to, Indemnitee’s personnel-related costs, attorney and expert fees, court costs, and all other claim-related expenses, to the fullest extent permitted by law, even though such claims may prove to be false, groundless, or fraudulent, subject only to the limitations provided below.

D. Seller’s duty to indemnify shall not apply to liability for damages arising out of bodily injury to persons or damage to property caused by or resulting from: (a) the sole negligence of Indemnitee or (b) the concurrent negligence of (i) Indemnitee, its agents or employees and (ii) Seller, its agents or employees with such liability limited to the extent of Seller or Seller’s agents or employees negligence. RCW 4.24.115

E. Seller specifically and expressly waives any immunity that may be granted it under the worker’s compensation laws under the Washington State Industrial Insurance Act, Title 51 RCW; provided that such waiver shall be expressly limited to Seller’s indemnity obligations herein and shall not be intended as a benefit to any third party. Further, the indemnification obligation under this Contract shall not be limited in any way by any limitation on the amount or type of damages, compensation or benefits payable to or for any third party under workers compensation acts, disability benefits acts, or other employee benefits acts. This waiver was mutually negotiated.

F. The partial or complete invalidity of any one or more provisions of this Section shall not affect the validity or continuing force and effect of any other provision. If any provision is invalid, in whole or in part, the balance of the provisions shall be considered reformed to reflect the intent of the parties to the greatest extent possible consistent with the law. The provisions of this section shall survive termination of this Agreement.

ARTICLE 8—SHIPPING AND DELIVERY

No Supplementary Conditions in this Article.

Page 115: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-800, Supplementary Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 6 of 7

STV-00 80 00 Supplementary Conditions for Procurement 2019.docx 00 80 00 - 6

ARTICLE 9—BUYER’S RIGHTS

9.01 Seller’s Warranties and Guarantees

SC-9.01 Add the following new paragraphs immediately after Paragraph 9.01.E:

F. This section shall be supplemented with the warranties specified in the Technical Specifications. All materials and equipment found defective within the warranty period shall be replaced or repaired, with all cost of replacement or repair, including shipping charges, to be borne by the Seller, except for those items which are normally consumed in service, such as oil, grease, etc.

9.02 Inspections and Testing

SC-9.02 Add the following new paragraph immediately after Paragraph 9.02.C:

D. This section shall be supplemented with Section 01 75 00 Testing and Commissioning Procedures of the Technical Specifications.

9.04 Correction Period

SC-9.04 Amend Paragraph 9.04.A to read as follows:

A. Seller’s responsibility for correcting all non-conformities in the Goods and Special Services will extend for a period of one two years after the acceptance of the Goods and Special Services in accordance with Paragraph 9.02.C.2.

ARTICLE 10—ENGINEER’S STATUS

No Supplementary Conditions in this Article.

ARTICLE 11—CHANGES

11.02 Change Orders

SC-11.02.C Add the following new paragraph immediately after Paragraph 11.02.B:

C. The Change Order Form to be used on this Project is EJCDC No. C-941.

11.03 Change Directives

SC-11.03.C Add the following new paragraph immediately after Paragraph 11.03.B:

C. The Work Change Directive Form to be used on this Project is EJCDC No. C-940.

ARTICLE 12—CLAIMS, DISPUTES, AND DISPUTE RESOLUTION

No Supplementary Conditions in this Article.

ARTICLE 13—PAYMENT

No Supplementary Conditions in this Article.

Page 116: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® P-800, Supplementary Conditions of the Procurement Contract. Copyright© 2019 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 7 of 7

STV-00 80 00 Supplementary Conditions for Procurement 2019.docx 00 80 00 - 7

ARTICLE 14—CANCELLATION, SUSPENSION, AND TERMINATION

No Supplementary Conditions in this Article.

ARTICLE 15—MISCELLANEOUS

15.02 Controlling Law

SC-15.02 Add the following new paragraphs immediately after Paragraph 15.02.B:

C. This Agreement is entered into in Skamania County, Washington. Venue shall be in Skamania County, State of Washington.

15.10 Anti-kickback

SC-15.10 Add the following new paragraph immediately after Paragraph 15.09:

SC-15.10 Anti-kickback

A. No officer or employee of the City, having the power or duty to perform an official act or action related to this Agreement, shall have, or acquire, any interest in this Agreement, or have solicited, accepted, or granted, a present or future gift, favor, service, or other thing of value from any person with an interest in this Agreement.

Page 117: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C-940, Work Change Directive. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,

and American Society of Civil Engineers. All rights reserved. Page 1 of 1

STV-00 94 00 Work Change Directive 2018.docx 00 94 00 - 1

SECTION 00 94 00 - WORK CHANGE DIRECTIVE

Buyer: Work Change Directive No.: Engineer: Buyer’s Contract No.: Seller: Seller’s Contract No.: Project: Contract Name: Date Issued: Effective Date of Work Change Directive:

Seller is directed to proceed promptly with the following change(s):

Description:

Attachments:

Purpose for the Work Change Directive:

Directive to proceed promptly with the Work described herein, prior to agreeing to change in Contract Price and Contract Time, is issued due to:

☐ Non-agreement on pricing of proposed change. ☐ Necessity to proceed for schedule or other reasons.

Estimated Change in Contract Price and Contract Times (non-binding, preliminary):

Contract Price: $ [increase] [decrease] [not yet estimated].

Contract Time: days [increase] [decrease] [not yet estimated].

Basis of estimated change in Contract Price:

☐ Lump Sum ☐ Unit Price ☐ Cost of the Work ☐ Other

Recommended by Engineer Authorized by Buyer

By:

Title:

Date:

Page 118: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

EJCDC® C-941, Change Order. Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies

and American Society of Civil Engineers. All rights reserved. Page 1 of 1

STV-00 94 10 Change Order 2018.docx 00 94 10 - 1

SECTION 00 94 10 - CHANGE ORDER

Buyer: Change Order No.: Engineer: Buyer’s Project No.: Seller: Seller’s Project No.: Project: Contract Name: Date Issued: Effective Date of Change Order:

The Contract is modified as follows upon execution of this Change Order:

Description:

Attachments:

Change in Contract Price

Change in Contract Times [State Contract Times as either a specific date or a

number of days] Original Contract Price: Original Contract Times: Substantial Completion: $ Ready for final payment: [Increase] [Decrease] from previously approved Change Orders No. 1 to No.:

[Increase] [Decrease] from previously approved Change Orders No.1 to No.:

Substantial Completion: $ Ready for final payment: Contract Price prior to this Change Order: Contract Times prior to this Change Order: Substantial Completion: $ Ready for final payment: [Increase] [Decrease] this Change Order: [Increase] [Decrease] this Change Order: Substantial Completion: $ Ready for final payment: Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: Substantial Completion: $ Ready for final payment:

Recommended by Engineer (if required) Authorized by Buyer

By:

Title:

Date:

Authorized by Buyer Approved by Funding Agency (if applicable)

By:

Title:

Date:

Page 119: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐1   

SECTION 01 33 00 SUBMITTAL PROCEDURES  

PART 1 GENERAL 

1.01 DESCRIPTION 

A. This section specifies procedures for submittals.   

B. The  Seller  shall  submit  descriptive  information  which  will  enable  the  Engineer  to determine whether  the  proposed materials,  equipment,  testing,  and  schedules  are  in general  conformance  with  the  design  concept  and  in  compliance  with  the  Contract Documents.  

C. The  information  to  be  submitted  shall  consist  of  schedules,  shop  drawings, specifications,  product  data,  test  procedures,  certified  test  reports,  certificates  of conformance,  certificates  of  installation  and  testing,  warranties,  operating  and maintenance manuals, lesson plans, and such other information, as specifically required in the Contract Documents. 

1.02 RELATED WORK 

A. Article 10 of the Instructions to Bidders, Paragraph 10.01 – “Or Equal” Items 

B. Article 1 of the Standard General Conditions, Paragraph 1.01.A.32 – Samples 

C. Article 1 of the Standard General Conditions, Paragraph 1.01.A.35 – Shop Drawings 

D. Article 2 of the Standard General Conditions, Paragraph 2.04 – Preliminary Schedules 

E. Article 7 of the Standard General Conditions, Paragraph 7.04 – “Or Equals” 

F. Article 7 of the Standard General Conditions, Paragraph 7.06 – Submittals 

G. Division 1 ‐ General Requirements 

H. Division 40 ‐ Process Interconnections 

I. Division 43 ‐ Process Gas and Liquid Handling Equipment 

J. Division 46 ‐ Water and Wastewater Equipment 

1.03 SELLER RESPONSIBILITIES 

A. The  Seller  shall  be  responsible  for  the  accuracy  and  completeness  of  the  information contained in each submittal and shall ensure that the material, equipment, testing, and schedules shall be as described in the submittal.  

Page 120: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐2   

B. The  Seller  shall  verify  that  the  material  and  equipment  described  in  each  submittal conforms  to  the  requirements  of  the  Contract  Documents.  If  the  information  shows deviations  from  the  Contract  Documents,  the  Seller  shall,  by  statement  in  writing accompanying the submittal, identify the deviations and state the reason and notify the Engineer in each case for approval.   

C. The  Seller  shall  ensure  that  there  is  no  conflict  with  other  submittals  and  notify  the Engineer in each case where such submittal may affect the work. 

D. The  Seller  shall  not  order  any materials  prior  to  receipt  of  the  Engineer's  approval  of Shop Drawings and Product Data. Work performed before acceptance of Shop Drawings and  Products  shall  be  at  the  Seller’s  own  risk.  In  the  event  of  termination  for convenience,  the  Buyer  will  not  be  responsible  for  any  materials  ordered  prior  to submittal approval.  

1.04 OR EQUALS 

A. Determination of “or equal” materials and equipment shall be  in accordance with  the Standard General Conditions with the following paragraphs. 

B. Seller shall provide a submittal with all data in support of any proposed “or equal” item at Seller’s expense. Data shall at minimum meet the requirements of Shop Drawings and Product Data of this specification section.  

C. Seller may submit a qualification package meeting the requirements of Shop Drawings and  Product  Data  of  this  specification  section  per  Article  10  of  the  Instructions  to Bidders with a deadline prior to the Bid Opening date for a pre‐bid determination on the suitability of the material and equipment from Engineer.  

D. After  the  deadline  in  the  above  paragraph,  Seller  assumes  all  liability  and  expense related  to  the  Engineer’s  evaluation  and  incorporation  of  “or  equals”  items  into  the work. 

1.05 SUBSTITUTIONS 

A. Any  substitutions  proposed  by  the  Seller  shall  require  submittals  to  fully  enable  the Engineer to evaluate the proposed substitution.  

B. All submittals shall clearly note and explicitly describe all details of any proposed and/or Engineer approved substitutions or deviations from the Contract Documents.  

C. The Engineer’s approval of any Shop Drawing or Product Data shall not release the Seller from responsibility for deviations from the Contract Documents.   

D. The approval of any Shop Drawing that substantially deviates from the requirement of the Contract Documents shall require a change order. 

Page 121: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐3   

PART 2 PRODUCTS 

2.01 PROGRESS SCHEDULE 

A. Submit Schedule per Article 2 of the Standard General Conditions, Paragraph 2.04. 

2.02 SAMPLES 

A. Samples, where required in the Technical Specifications, or requested by the Engineer, shall be submitted for approval.  

B. The approved samples  shall be  identified as  to  their  intended use and  the  transmittal shall be accompanied by a letter of certification from the Seller stating that the samples comply with the contract drawings and specifications.  

C. All samples shall be individually and indelibly  labeled or tagged,  indicating thereon the project  name,  contract  number,  Manufacturer's  name,  equipment  name,  equipment specification number, and all specified physical characteristics. 

2.03 SHOP DRAWINGS AND PRODUCT DATA 

A. Shop Drawing Format  

1. Seller shall  identify each copy of the Shop Drawings with the contract drawing number in the lower right hand corner, shall make all shop drawings accurately to  a  scale  sufficiently  large  enough  to  show all  pertinent  features  of  the  item and  it's  method  of  connection  to  the  work,  and  shall  make  all  shop  drawing prints in blue or black on white background.   

2. Shop Drawings  shall be bound  in a 3‐ring or 3‐clip,  loose  leaf binder or  folder with  the  equipment  title,  specification  number(s),  and  manufacturer  name clearly printed on the front of the binder or folder.  

3. All drawings should be 11 by 17 inches or 8 1/2 x 11 inches.  If drawings larger than 11 by 17 inches are required (drawings larger than 11x17 are discouraged), drawings shall be folded neatly and placed inside transparent inserts within the binder or folder.  

4. When  revised  for  resubmission,  Seller  shall  clearly  identify  drawings  with changes made since previous submission. 

5. Each item listed in the paragraphs below shall be included and be appropriately identified.  

B. Shop Drawing Content: Seller shall submit the following minimum information as part of their Shop Drawing Submittal for each model or type of unit supplied by the Seller:  

Page 122: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐4   

1. Process  and  Instrumentation  Diagram  of  the  system,  detailing  the  equipment supplied and showing equipment that shall interface with the system. 

2. Mechanical Drawings – General Arrangement Plans, Sections, and Details  

a. Concrete channels.  

b. Instrumentation. 

c. Equipment and skids. 

d. Enclosures and panels for equipment and controls. 

3. Electrical and Controls Drawings:  

a. Control schematics, single‐line, and list of all input/output signals for control panels. 

b. Electrical single‐line diagram including power distribution requirements, transformers, drives, panel boards, meters and protective devices. 

c. Panel layout diagrams including control devices and auxiliary devices and wiring diagrams. 

4. Drawings  shall  be  to  a  level  of  detail  sufficient  for  a  contractor  to  install  the system. 

5. Drawings shall show the general dimensions of the equipment and shall confirm the size of the unit.  

6. Drawings  shall  include:  size  and  location  of  required  piping  and  utility connections,  structural  supports,  construction  details,  weights  of  major components, materials of construction of all components,  including all buy‐out items. 

C. Product  Data:  Seller  shall  submit  the  following minimum  information  as  part  of  their Product Data Submittal for each model or type of unit supplied by the Seller: 

1. Manufacturer’s catalog information. 

2. Manufacturer’s specifications for materials and manufacturing. 

3. Detailed  information  for  all  ancillary  items  such  as  hardware  and  mounting frames, etc. 

4. Information on equipment field erection requirements including total weight of assembled components and weight of each subassembly. 

5. Installation and storage instructions. 

Page 123: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐5   

6. Design calculations and performance curves demonstrating compliance with the performance and design criteria of the specifications. 

7. Manufacturer’s coating system technical data sheets. 

8. Manufacturer's warranty as specified. 

9. Manufacturer's recommended spare parts. 

10. A  maintenance  schedule  showing  the  required  maintenance,  frequency  of maintenance,  lubricants,  and  other  items  required  at  each  regular  preventive maintenance period. 

11. Information and location of nearest parts, service crews, and repair facilities to the Buyer. 

12. Installation  list  for  installations  in  the  U.S.  with  location,  contact  names,  and phone numbers, if requested by the Engineer.   

13. Any additional information listed elsewhere in the Specifications and required to be submitted.  

14. List all design modifications for Engineer’s approval, if any, to accommodate the equipment proposed. 

15. List of all variances from Specifications (Note:  Failure to specifically list and fully explain all variance will be cause for rejection of submittal.) 

16. Any other required  information to clearly and readily demonstrate compliance with all parts of the Specifications. 

17. A bill of materials for all equipment, tagged devices, components, special tools, and  spare  parts  supplied  with  the  system,  including  component  original  part numbers  identifying  each  furnished  component  and  corresponding  to  the number provided on the drawings. 

D. For instrumentation and controls, submit the following: 

1. A  detailed  instrument  list  for  all  field  instruments  that  includes  tag  number, service, manufacturer, type, range, hazardous area classification and connection type.  

2. Narrative  description  for  all  control  systems,  summary  of  control  functions, summary  of  monitoring  functions,  description  of  alarms,  control  set  points, alarm set‐points, graphic interface screens. 

3. Detailed Programmable  Logic Controller  (PLC)  system network  communication architecture, control panel layouts, input/output lists. 

Page 124: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐6   

4. Detailed bill of materials for all Control Panel and PLC hardware. 

5. Control  system  programming.  Program  documentation  printout  with  tag numbers, ladder logic, program and function listing, and descriptive comments. 

E. For process connected instruments: 

1. Manufacturer's technical data sheet  

2. Wiring diagram 

3. Bill of materials 

4. Manufacturer’s warranty as specified 

5. Installation instructions and details including: tube material and size, connection size, fitting size, material, and rating, isolation or other valve type and material as applicable, pipe stand size and material, required elevations and dimensions. 

6. List of spare parts and calibration standards as applicable. 

F. Copies  of  the  final  approved  and  conformed  Shop  Drawings  and  Product  Data  are required to be submitted with the operation and maintenance manuals. 

2.04 MANUFACTURER’S WARRANTY 

A. The Manufacturer’s Warranty shall be submitted to the Engineer with the Product Data submittal  and  shall  be  in  conformance  with  the  respective  equipment  and  materials specification sections.  

B. All submitted warranties shall state in writing that the warranty period will begin from the Date of Substantial Completion and will end as may be prescribed by the terms of any applicable special guarantee required by the Contract Documents or by any specific provision of the Contract Documents from this date. 

2.05 FACTORY TEST REPORTS 

A. At minimum 15 days prior to delivery of materials and equipment, certified copies of the reports of all tests listed in the technical sections (and referenced publications) shall be submitted and approved.  

B. Test  reports  shall  be  accompanied  by  notarized  certificates  from  the  manufacturer certifying that the material and equipment proposed to be supplied is of the same type, quality, manufacture and make as that tested.  

C. Test results shall cite the contract requirements, the test or analytical procedures used, the actual results, and include a statement that the item tested or analyzed conforms or fails to conform to the specification requirements.   

Page 125: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐7   

D. All test reports shall be signed by a testing laboratory representative authorized to sign certified test reports. 

E. If  test results are required to be witnessed by an  independent  testing  laboratory,  that laboratory shall certify the Test Report. 

2.06 BILL OF MATERIALS 

A. Bill of materials and/or shipping manifest shall be submitted with shipment prior to or upon delivery of products to point of destination. 

B. Bill of materials shall include the equipment, part, or tool name, identification numbers, and number of units supplied. 

2.07 TESTING AND TRAINING SUBMITTALS 

A. Submit testing and commissioning submittals in accordance with Section 01 75 00. 

B. Submit training submittals in accordance with Section 01 79 00. 

PART 3 EXECUTION 

3.01 GENERAL 

A. Paper Copies: Seller shall submit four (4) paper copies of all submittals plus the number of copies the Seller wants returned, unless otherwise approved by the Engineer. 

B. Electronic Copies: Seller shall upload one (1) Adobe® Reader® (pdf) copy to the project ftp site. The pdf must contain a duplicate copy of all the paper copy information. 

C. Certification: All submittals shall be approved and certified by the Seller as conforming to the drawings and specifications.   

D. Schedule: All required Shop Drawings and Samples shall be submitted to the Engineer by not later than as required in Article 2 of the Agreement.   

E. Transmittal  Sheet:  All  submittals  shall  be  submitted  in  a  bound  volume  shall  include Transmittal Form 01 33 00‐1. The transmittal form shall indicate the date of submission and whether the Engineer’s or Buyer’s approval is required.   

F. Submittal  Identification and Status: Each item of submittal to be incorporated into the work  shall  be  cross‐referenced  to  the  contract  drawings  and  specifications  so  as  to clearly identify the use for which it is intended.  

G. Variations: Variations  from contract  requirements  are discouraged.  If  submittals  show variations  from  the  contract  requirements,  the  Seller  shall  describe  and  list  such variations  in  writing  at  the  time  of  submission.  If  the  Engineer  approves  any  such variation,  the Engineer shall  issue an appropriate contract modification, except that,  if 

Page 126: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐8   

the variation is minor or does not involve a change in price or in time or performance, a modification need not be issued. 

3.02 TRANSMITTAL PROCEDURE 

A. General: 

1. Submittals  shall  be  accompanied  by  Transmittal  Form  01  33  00‐1,  included  in this  section,  or  an  approved  substitute  form.  Equipment  or  identification numbers  shall be  listed on  the  form  for  items being  submitted.  Submittals  for various items shall be made with a single form when the items taken together constitute  a  manufacturer's  package  or  are  so  functionally  related  that expediency indicates checking or review of the group or package as a whole. 

2. A unique number, sequentially assigned, shall be noted on the transmittal form accompanying each item submitted. Submittal numbers shall have the following format:  "XXXXX‐Y.Z";  where  "XXXXX"  is  the  specification  section  number assigned to the submittal, “Y” is the sequential item in that section, and Z is the sequential  submittal  number.  Example:  Submittal  01  33  00‐1.1  is  the  first submittal  of  this  section  (e.g.  the  Schedule  of  Submittals).  The  resubmission would be 01 33 00‐1.2.  

B. Submittal Completeness: Submittals which do not have all  the  information required to be submitted are not acceptable and will be returned. 

C. Submittals  returned marked “Revise and Resubmit” or “Rejected” will be reviewed no more than three (3) times at the Buyer’s expense. Additional Engineer reviews, beyond the initial three (3) reviews, will be charged to the Seller at $140 per hour of review time by the Engineer(s) required to review the submittal.   

D. Submittal Priority:  When multiple submittals have been sent to the Engineer for review, Seller shall indicate priority for receipt of reviewed submittals. Engineer will attempt to review  and  reply  to  the  highest  priority  submittals  in  the most  timely manner  when Seller indicates that there is a priority.     

3.03 REVIEW PROCEDURE 

A. Engineer will review and return the submittal indicating one of the following actions on the Submittal Transmittal Form 01 33 00‐1. 

1. If the review indicates that the material, equipment, test or work method is  in general  conformance with  the design  concept and  complies with  the Contract Documents,  submittal  copies will be marked "No Exceptions Taken" and given Review Action 1. In this event the Seller may begin to incorporate the material or equipment covered by the submittal. 

Page 127: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐9   

2. If  the  review  indicates  that  the  submittal  is  insufficient  or  that  limited corrections are  required,  copies will be marked "Furnish as Corrected" and be given  Review  Action  2.  The  Seller  may  begin  incorporating  the  material  and equipment covered by the submittal in accordance with the noted corrections. Where  submittal  information  will  be  incorporated  in  Operation  and Maintenance  data,  a  corrected  copy  shall  be  provided,  otherwise  no  further action is required. 

3. If the review reveals that the submittal is insufficient or contains incorrect data, copies  will  be marked  "Revise  and  Resubmit".  Comments  will  be  provided  to indicate, in part, the deficiencies that must be addressed. The submittal will be given  Review  Action  3.    Except  at  its  own  risk,  the  Seller  shall  not  undertake work  covered  by  such  a  submittal  until  the  submittal  has  been  revised, resubmitted and returned marked either “No Exceptions Taken” or “Furnish as Corrected”. 

4. If the comments require a complete resubmittal, copies will be further marked "Rejected" and given a Review Action 4.  Except at its own risk, the Seller shall not undertake work  covered by  such a  submittal until  the  submittal has been revised,  resubmitted  and  returned  marked  either  "No  Exceptions  Taken"  or "Furnish as Corrected." 

5. If the review indicates that the material, equipment, test or work method is not in  general  conformance  with  the  design  concept  or  in  compliance  with  the Contract Documents, copies of the submittal will be marked "Submit Specified Item"  and  given  Review  Action  5.    This  action  indicates  that  in  the  Engineers opinion  the  equipment  or  material  submitted  does  not  comply  with  that specified.  The Seller should completely review the suitability of the equipment or material  and  seek  out  alternatives  that will meet  the  intent  of  the  design.  Except  at  its  own  risk,  the  Seller  shall  not  undertake  work  covered  by  such submittals  until  a  new  submittal  is  made  and  returned  marked  either  "No Exceptions Taken" or "Furnish as Corrected." 

3.04 EFFECT OF REVIEW OF SELLER'S SUBMITTALS 

A. Review  of  drawings,  tests,  methods  of  work,  or  information  regarding  materials  or equipment the Seller proposes to provide, shall not relieve the Seller of its responsibility for errors therein and shall not be regarded as an assumption of risks or liability by the Buyer  or  by  any  officer  or  employee  of  the  Buyer,  and  the  Seller  shall  have  no  claim under the Contract on account of the failure, or partial failure, of the method of work and test, material, or equipment so reviewed. A mark of "No Exceptions Taken" or "Note Markings" shall mean that  the Buyer, or any officer or employee of  the Buyer, has no objection to the Seller, upon the Seller's own responsibility, providing the materials or equipment proposed. 

* * * END OF SECTION * * * 

Page 128: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 33 00 Submittal Procedures for Procurement.doc  01 33 00‐10   

FORM 01 33 00 SUBMITTAL/TRANSMITTAL  Date Stamp 

 Contractor: _________________________  Contract No.: _______________________  

Submittal No. _______________________  Date: ______________________________ Resubmittal Y/N:_____________________ 

 

This Section To Be Completed By Contractor This Section to be Completed by Engineer

Item No. 

* P/C 

Spec. Paragraph 

Dwg. No. 

 Description of Item 

CopiesSubm. 

Review Action 

 Notes 

               

               

               

               

               

               

               

                

Contractor certifies Review of Submittal, Verification of Field Measurements and Compliance with Contract Documents  By________________________         Date_________________   Deviation:  Yes ____   Substitution:    Yes _____                      No ____                              No  _____ (if “Yes” for either, attach supporting information.) 

Legend ‐ Review Action

1 No exceptions taken   

2 Furnish As Corrected   

3 Revise and Resubmit   

4 Rejected – See Remarks   

5 Submit Specified Item   * P ‐ Partial Submittal   C ‐ Complete Submittal 

Review By  Date 

   

   

Returned to Contractor By   

 

Page 129: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐1 

SECTION 01 60 00 PRODUCT REQUIREMENTS 

PART 1 GENERAL 

1.01 DESCRIPTION OF WORK 

A. This  section  specifies  the  general  requirements  for  Seller’s  equipment  and materials, unless otherwise specified elsewhere in the Specifications. 

B. Product  items,  presented  in  these  specifications,  are  included  for  convenience and  are  not  complete  listings  of  all  equipment  and  materials  to  be  supplied under this Contract. 

1.02 RELATED WORK 

A. Other  divisions  where  these  product  requirements  are  applicable,  unless specified otherwise therein, include, but are not limited to, the following: 

1. Division 40 ‐ Process Interconnections 

2. Division 43 ‐ Process Gas and Liquid Handling Equipment 

3. Division 46 ‐ Water and Wastewater Equipment 

B. Article 7 of the Standard General Conditions, Paragraph 7.04 – Or Equals 

C. Section 01 33 00 – Submittal Procedures 

1.03 REGULATORY REQUIREMENTS  

A. The equipment and materials furnished shall be subject to the requirements of applicable portions of the following regulatory agencies: 

1. Underwriters Laboratories (U.L.) 

a. All equipment and devices shall be listed by and bear the Underwriters Laboratories (U.L.) Inc U.L. label or the CSA‐C/US label.   

2. State of Washington Department of Labor and Industries 

a. Equipment not carrying these labels shall be labeled or listed by an approved agency as required by State of Washington Department of Labor and Industries.  

3. National Fire Protection Association 

Page 130: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐2 

a. National Electrical Code (NEC) 

4. Occupational Safety and Health Administration: 

a. 29 CFR 1910 ‐ Occupational Safety and Health Act (OSHA) 

5. Washington State Department of Labor and Industries  

a. Chapter 49.17 RCW ‐ Washington Industrial Safety and Health Act (WISHA) 

6. International Building Code (IBC) by International Code Council: 

a. All equipment is to be designed for the project seismic zone in accordance with the latest edition of International Building Code.  

b. Calculations demonstrating this requirement shall be furnished to the Engineer if requested. 

1.04 REFERENCE STANDARDS 

A. The work in this section is subject to the requirements of applicable portions of the following standards: 

1. ANSI – American National Standards Institute  

a. ANSI Z535.1 Safety Colors 

2. American Society of Mechanical Engineers 

a. ANSI/ASME B16.1 ‐ Gray Iron Pipe Flanges and Flanged Fittings 

b. ANSI/ASME B1.20.1:2013 ‐ Pipe Threads, General Purpose (Inch) 

3. American Bearing Manufacturers Association: 

a. ABMA 9 ‐ Load Ratings and Fatigue Life for Ball Bearings 

b. ABMA 11 ‐ Load Ratings and Fatigue Life for Roller Bearings 

4. American Welding Society (AWS): 

a. AWS D1.1 ‐ Structural Welding Code 

5. AISI/SAE – American Iron and Steel Institute/Society of Automotive Engineers 

a. AISI/SAE 316 (UNS S31600) – 316 Stainless Steel 

b. AISI/SAE 316L (UNS S31603) – 316L Stainless Steel 

Page 131: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐3 

6. International Standards Organization (ISO) 

a. ISO 1940‐1 ‐ Mechanical Vibration ‐‐ Balance Quality Requirements for Rotors in a Constant (Rigid) State 

b. ISO 2151‐2004 (E) ‐ Noise Test Code for Compressors and Vacuum Pumps 

1.05 SUBMITTALS 

A. Furnish the following data with equipment submittals in accordance with Section 01 33 00, Submittal Procedures. 

1. Seismic Calculations, if requested 

2. Equipment  Bases:  Submit  material,  layout  with  dimensions,  drill  pattern, mounting hardware, and anchor data. 

3. Lifting Eyes: Show location on equipment layout drawings. 

4. Pipe Connections: Call  out pipe  connection  standards on all  equipment  layout drawings. 

5. Bearings:  Provide  ABMA  L‐10  bearing  life  for  all  equipment  bearings.  Show bearing lubrication location and detail on equipment drawings. 

6. V‐belt Drives: Provide calculation of service factor, number of belts. Show belt, sheave, and guard arrangement on equipment drawings. 

7. Drive Shaft Couplings: Provide service  life, product  information. Show coupling and guard arrangement on equipment drawings. 

8. Nameplates: Submit material, layout with dimensions, and data. 

9. Finishes: Provide coating data sheet for all factory applied coatings. 

10. Noise Attenuation: Provide noise attenuation data,  if requested. If enclosure is required, provide product data and details for enclosure. 

11. Delivery: Submit bill of materials or shipping manifest prior to or upon delivery of products to point of destination. 

1.06 PRODUCT SUBSTITUTION PROCEDURES 

A. Requests  for  “or  equal”  (substitution)  determination  shall  be  made  in accordance with the provisions of the Standard General Conditions and Section 01 33 00, Submittal Procedures. 

B. Single Source Products: If material or equipment is specified by only one patent or  proprietary  name,  or  by  the  name  of  only  one  manufacturer,  it  is  for  the 

Page 132: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐4 

purpose  of  standardization,  or  because  the  Owner  knows  of  no  equal.  If standardization  is  the  reason  for  using  one  name  to  specify  any  material  or equipment,  substitutions  will  not  be  considered;  this  may  be  waived  if substitution  is determined by  the Owner  to be  in  the Owner's best  interest.  In other  cases,  the  Seller  may  offer  substitutions  of  products  considered  to  be equal to or better than that specified. 

PART 2 PRODUCTS 

2.01 GENERAL 

A. All equipment is to be designed for the service intended, of rugged construction, of  ample  strength  for  all  stresses,  which  may  occur  during  fabrication, transportation, erection and during continuous or intermittent operation.  

B. All equipment shall be designed, constructed, installed and tested in accordance with the best practices and methods of the industry. 

C. All  equipment  is  to  be  design  for  the  project  seismic  zone.  Calculations demonstrating this requirement shall be furnished to the Engineer if requested. 

D. Where  product  specifications  include  a  named manufacturer,  with  or  without model  number,  and  also  include  performance  requirements,  named manufacturer’s products must meet the performance specifications. 

E. Unless  otherwise  specified,  equipment  or  material  of  the  same  type  or classification  used  for  the  same  purpose  shall  be  the  product  of  the  same manufacturer and shall be the same model. 

F. Mechanical  and  electrical  equipment,  particularly  bearings,  contacts  and  other wearing  parts  shall  be  designed  for  extended  periods  of  operation  without frequent maintenance or attention. 

G. Motors  and  drives  shall  be  furnished with  safety  devices  including  shear  pins, flexible coupling guards and belt guards. 

H. All machinery shall be designed such that all working parts are readily accessible for inspection and repair, and each part is suitable for the service required. 

I. Cathodically compatible materials of construction shall be used for fabrication. 

2.02 STRUCTURAL STEEL 

A. Manufacture parts to United States standard sizes and gauges. 

B. Design structural members for anticipated shock and vibratory loads. 

Page 133: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐5 

C. Use 1/4‐inch minimum thickness unless otherwise specified or approved. 

2.03 EQUIPMENT METAL BASES 

A. Mount equipment assemblies on a  single heavy cast  iron or welded  steel base unless otherwise shown or specified.  

B. The base shall comprise a base plate, perimeter flange, and reinforcements.  

C. Base plate  shall  be  fabricated of  steel  not  less  than ¼”  thick,  unless otherwise specified.  

D. Perimeter  flange  and  reinforcements  shall  be  designed  to  prevent  flexing  or warping under operating conditions.   

E. Base plate and/or flange shall be drilled for hardware used to secure unit base to concrete pad.  

F. Provide  base  plate  and/or  flange  with  machined  support  pads  and  tapered dowels for alignment or mating of adjacent items.  

G. Provide adequate openings to facilitate grouting after  installation and openings for electrical conduits in base plate.  

H. Round or chamfer and grind smooth all corners.  

I. Continuously  weld  seams  and  contact  edges  between  steel  plates  and  shapes AWS D1.1, and grind welds smooth.  

J. Provide jacking screws in equipment bases and bedplates to aid in leveling prior to grouting.  

K. Base shall contain provisions for lifting the complete equipment assembly during shipping and installation. 

L. All  equipment  bases  and  baseplates  shall  be mounted  on  reinforced  concrete pads. 

2.04 ANCHORS 

A. Each  equipment  manufacturer  shall  furnish  an  anchor  bolt  pattern  and  a schedule  of  the  sizes  of  the  required  anchor  bolts,  nuts,  and  washers  of adequate design for securing bases and bedplates to concrete bases.  

B. Provide  anchor  bolt  design  of  a  length  to  allow  for  1‐1/2‐inch  of  grout  under baseplates  and  adequate  anchorage  into  structural  concrete,  unless  otherwise specified.  

Page 134: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐6 

C. Anchor and assembly bolts and nuts shall be of ample size and strength for the purpose intended.  

D. All bolts shall be standard machine bolts, with cold pressed hexagon nuts.  

E. Provide  suitable  degauling  compounds  for  bronze  and  stainless  steel  threaded components.  

F. Any  space wholly  or  partially  underground,  or  having  a wall  or  ceiling  forming part of a water channel,  is classified as a submerged location. Bolts and nuts in submerged locations, corrosive areas, or submerged and embedded in concrete or buried in earth shall be AISI 316/316L stainless steel.  

2.05 HARDWARE 

A. All machine bolts, nuts and cap screws shall be of the hex head type.  Hardware of parts requiring special tools or wrenches shall not be used. 

B. Unless otherwise specified, all hardware shall be AISI 316/316L stainless steel. 

2.06 LIFTING EYES  

A. Supply  all  equipment  weighing  over  100  pounds  with  lifting  eyes.  Parts  of equipment assemblies which are normally  serviced separately,  such as motors, shall have lifting eyes of their own. 

2.07 MOTORS 

A. All  motors,  unless  otherwise  specified,  shall  comply  with  Section  40  05  93  ‐ Common Motor Requirements for Process Equipment. 

2.08 FLANGES AND PIPE THREADS  

A. Unless otherwise noted, all  flanges on equipment and appurtenances provided under this section shall conform in dimensions and drilling to ASME/ANSI B16.1, Class 125.  

B. All pipe threads shall conform in dimension and limits of size ASME/ANSI B1.20.1 NPT, Taper Pipe Thread. 

C. Grooved pipe connections shall be in accordance with AWWA C606. 

2.09 GUARDS  

A. All exposed moving parts shall be provided with guards  in accordance with the requirements of the WISHA and Occupational Safety and Health Act.   

Page 135: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐7 

B. Guards  shall  be  fabricated  of  minimum  12‐gauge  steel  and  expanded  metal screen  to  provide  visual  inspection  of  moving  parts  without  removal  of  the guard.  

C. The guard shall be primed with a minimum of 2.5 to 3.5 Mils of Tnemec 1 primer.  Two  coats of  finish epoxy  coating  Tnemec N69  (minimum 3.0  to  5.0 Mils DFT) shall  be  applied  in  accordance with  the  safety  color  definition  of  ANSI  Z535.1 Safety Color Code for marking physical hazards. 

2.010 BEARINGS  

A. Unless  otherwise  specified,  all  equipment  bearings  shall  be  oil  or  grease lubricated, ball or roller anti‐friction type of standard manufacture.   

B. Bearings shall be conservatively designed to withstand all stresses of the service specified.   

C. Bearing shall be rated in accordance with the latest revisions of ABMA 9 or 11. ABMA L‐10 life shall not be less than 100,000 hours for process equipment, and 50,000 hours for other equipment unless otherwise specified or approved. 

D. All grease lubricated bearings, except those specified to be factory lubricated for life,  shall  be  fitted with  easily  accessible  grease  supply,  flush,  drain  and  relief fittings.  Extension  tubes  shall  be  used when  necessary.    Grease  supply  fittings shall be the standard hydraulic type.  

E. Oil  lubricated  bearings  shall  be  equipped  with  either  a  pressure  lubricating system or a separate oil reservoir type system. Each oil  lubrication system shall be of sufficient size to safely absorb the heat energy normally generated in the bearing under a maximum ambient  temperature of 40 degrees C. and  shall be equipped with a filler pipe and an external level gauge. 

2.011 V‐BELT DRIVES  

A. Pulleys and bushes shall be dynamically and statically balanced. Pulleys shall be separately  mounted  on  their  bushes  by  means  of  three  pull‐up  grub  or  cap tightening screws.  Bushes shall be key seated to the driver shaft.  

B. Belts  shall be  selected  for not  less  than 150% of  rated driver horsepower and, where 2 pulley sizes are specified, shall be capable of operating with either set of pulleys.  Belts  shall  be  of  the  anti‐static  type  where  flame‐proof  equipment  is specified.  

C. The belt tension device must be designed to allow the maintenance personnel to replace  the belts without exerting or  lifting over 40 pounds without  the use of lifting, jacking or pulling tools. 

Page 136: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐8 

D. Each belt‐driven unit shall be furnished with a complete set of spare belts.  Spare belts shall be properly identified as to design, horsepower speed, length, pulley size  and  use  and  shall  be  packaged  and  stored  as  specified  for  spare  parts storage and marking. Where 2 or more belts are involved, matched sets of belts shall be provided. 

2.012 SHAFT COUPLINGS  

A. General:   Shaft couplings for direct connected electric motor‐driven equipment 1/2 HP or  larger shall be Type I or Type II as specified herein.   Type I couplings shall  be  utilized  for  all  reversing  drives,  positive  displacement  pumps  or  high torque  loads.    Type  II  couplings  shall  be employed on all  other drives.   Where requirements  of  the  equipment  dictate  specialized  features,  the manufacturer may substitute the coupling normally supplied for the service.  All couplings shall be non‐lubricated  type, designed  for not  less  than 50,000 hours operating  life. Coupling  sizes  shall  be  as  recommended  by  the manufacturer  for  the  specific application, considering horsepower, speed of rotation and type of service.  The use  of  couplings  as  specified  herein  shall  not  relieve  the  requirement  for precision alignment of all driver‐driven units.  

B. Type  I  couplings:  Positive  displacement  pumps  and  reversing  equipment  or equipment where sudden torque reversals may be expected shall be connected to  their  drivers  by  flexible  couplings  which  can  accommodate  angular misalignment,  and  end  float,  and  which  cushions  shock  loads  and  dampens torsional  vibrations.    The  flexible  member  shall  consist  of  a  built‐up  elastic member  comprised  of  synthetic  rubber,  duck  and  wire  reinforcement  with synthetic  tension  members  bonded  together  in  rubber.    The  flexible  member shall be attached to flanges by means of clamping rings and cap screws and the flanges  shall  be  attached  to  the  stub  fit.    There  shall  be  no  metal‐to‐metal contact between the driver and driven unit.  

C. Type  II  couplings  shall  be  employed  on  normal  torque,  non‐reversing applications.  Type  II  couplings  shall  be  of  the  pin  and  preloaded  neoprene cylinder  type,  designed  to  accommodate  shock  loading,  vibration  and  shaft misalignment or offset.   Stub shafts shall be connected through collar or round flanges,  firmly  keyed  to  their  shafts,  to  neoprene  cylinders  held  to  individual flanges by through pins. Couplings with cylinders pinned to both coupling flanges will not be acceptable. 

2.013 NAMEPLATES  

A. Manufacturer's Nameplate: Furnish nameplate for each piece of equipment and its motor fastened in a readily readable position. 

B. Material: Stainless steel, 0.032 inches thick.  

Page 137: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐9 

C. Identification:  

1. Equipment: Manufacturer's name, model, serial number, size, head or pressure rating, capacity, speed, impeller diameter, frame and bearing numbers.  

2. Motors: Manufacturer's name, model, serial number, running current, starting current, horsepower, voltage, frequency, phase, and speed. 

3. Lettering: Stamped or Etched. 

4. Language: English. 

D. Size: 4” wide x 2” high  

E. Color: Black 

F. Mounting: Four 3/16" diameter side holes. 

G. Fasteners: Stainless steel screwed into inserts, anchor shields or tapped holes in equipment or base. 

H. Location of all data plates shall be easily visible in the completed installation. 

2.014 PROTECTION AGAINST ELECTROLYSIS  

A. Where  dissimilar  metals  are  used  in  conjunction  with  each  other,  provide suitable  insulation between adjacent surfaces, so as to eliminate direct contact and  any  resultant  electrolysis.  Connections  of  dissimilar  piping  materials  shall utilize dielectric unions, flanges, couplings, or bushings. 

2.015 FINISHES 

A. Factory  Painting:  On  self‐contained  or  enclosed  components,  apply  a  factory protective  paint  system  unless  otherwise  noted.  Paint  or  otherwise  protect surfaces  that  are  inaccessible  after  assembly  by  a  method,  which  provides protection for the life of the equipment.  

B. Shop  Priming:  Except where  field  sandblasting  is  required,  apply  one  or more shop  coats  of  metal  primer  on  surfaces  to  be  finish  painted  at  the  site,  of sufficient thickness to protect surfaces until finished. Primer shall be compatible with finish coat, Tnemec 1 or equal. 

C. Rust  Preventive:  Machined,  polished,  other  ferrous  surfaces,  and  non‐ferrous surfaces,  which  are  not  to  be  painted  shall  be  coated  with  a  rust  preventive compound. 

Page 138: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐10 

2.016 NOISE AND VIBRATION  

A. Mechanical and electrical equipment, as installed in this project, shall not create sound levels that are in excess of that permitted by WISHA/OSHA for 8 hours per day worker exposure unless otherwise noted for the specific piece of equipment involved.  

B. Sound  levels  shall  be demonstrated per  ISO 2151‐2004  (E) when  requested by Engineer to verify equipment sound levels. 

C. If  the  required  sound  level  cannot  be  achieved  by  bare  equipment  in  its designated  environment,  provide  sound  attenuating  enclosures.  Sound attenuating  enclosures  shall  have  necessary  ventilation  to  prevent  equipment overheating and shall be constructed  for easy  removal  to permit maintenance. Devices  necessary  for  day‐to‐day  operation  shall  pierce  the  enclosure  or otherwise be accessible without need to remove the enclosure.  

D. Equipment,  which  when  operating  has  obvious  excessive  vibrations,  shall  be repaired  or  replaced  as  directed  by  the  Engineer.  Baseline  vibration measurements shall be made where specified. 

2.017 LUBRICATION 

A. An  adequate  and,  as  far  as  practicable,  automatic means  of  lubrication  for  all working parts shall be provided. Arrange lubrication grease nipples, grease boxes and  other  lubrication  devices  so  that  they  are  readily  accessible  for  routine greasing.  

B. Make  lubrication  points  that  are  not  readily  accessible,  accessible  by  using grease nipples and Type 316 stainless steel tubing extension with plastic tubing where  required  for  flexibility.  Secure  the  nipples  to  the  equipment  at appropriate locations. 

C. Use grease nipples of a consistent type; alemite button head type or equivalent.   

D. A  list  of  all  required  lubricants  shall  be  provided  in  the  operation  and maintenance manuals.  

E. Provide  initial  lubricant recommended by equipment manufacturer  in sufficient quantity  to  fill  lubricant  reservoirs  and  to  replace  consumption  during  testing, startup, and operation until final acceptance by Owner. 

2.018 SPARE PARTS 

A. All  equipment  shall  be  furnished  with  spare  parts  as  specified  and  as recommended by  the manufacturer  and  all  accessories  required  to  place  each 

Page 139: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐11 

item  of  equipment  in  full  operation,  and  for  on‐going  adjustment,  repair  and maintenance of the equipment supplied. 

B. These  spare  parts  include,  but  are  not  limited  to,  adequate  oil  and  grease  (as required for first  lubrication of equipment after field testing),  light bulbs, fuses, and other spare parts as required for maintenance.  

C. Additional  spare  parts  shall  be  furnished  as  specified  elsewhere  in  the Specifications. 

D. All bearings, bushings, and shaft sleeves shall be “export” packaged. 

E. Packaging 

1. Package spare parts to prevent damage in transit and in storage.  

2. Attach an identification label or tag to the part or to its packaging which contains: 

a. The part number; 

b. A reference to the tag number of the equipment component, and 

c. The name and contact information of the supplier. 

3. Attach relevant instructions on the application and method of use of the spare part, special tool, or maintenance material. 

F. Storage Container(s) 

1. Package spare parts and special tools in one or more of hinged, heavy‐duty, weather and impact resistance plastic cargo box(es) for long‐term storage.  

2. The box(es) shall be lockable with a padlock. 

3. The box(es) shall be clearly labeled with the contents and name of manufacturer or supplier. 

2.019 SPECIAL TOOLS 

A. For each type of equipment to be furnished, provide a complete set of all special tools which may be necessary  for  the adjustment, operation, and maintenance of such equipment. These special tools include: grease guns or other lubricating devices, valve keys and operators, and special wrenches. 

Page 140: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐12 

PART 3 EXECUTION 

3.01 FACTORY TESTS 

A. Perform factory tests for each piece of equipment where specifically called for in the  section  specifying  that  equipment.  Note  that  factory  tests  are  inherent  in many  reference  standards.  The  requirement  for  a  factory  test  in  a  referenced standard  is  hereby made  a  part  of  these  Specifications.  Factory  tests  shall  be included in the contract lump sum price for the particular equipment item. 

B. Conduct factory tests at the specified speeds and other conditions at which the equipment will operate in the field, except as noted.  

C. Where  specified,  performance  tests  may  be  witnessed  by  the  Engineer  or  his representative.  Inform  the  Engineer  30‐calendar  days  before  the  test  to  allow arrangements  to be made for witness of such tests. When non‐witnessed tests are performed, supply certified results.  

3.02 PRODUCT SHIPMENT REQUIREMENTS 

A. The  Seller  shall  make  its  own  provisions  for  properly  delivering,  storing,  and protecting all material and equipment against theft,  injury or damage from any and all causes until acceptance of delivery by the Owner. Damaged material and equipment shall not be used in the work. 

B. All  goods  shall  be  transported  and  handled  according  to  manufacturer's instructions. 

C. All products shall be assembled and match marked in the shop prior to shipment. 

D. All loose products shall be carefully packed in strong wooden crates or plastic wrapped as  appropriate  and  clearly  marked  as  to  its  contents,  manufacturer,  and  supplier’s name.   Complete  containers or  trailer‐mounted units  shall  be  shipped with a minimal amount of loose equipment. 

E. All piping shall have ends capped off prior to dispatch and securely fastened to prevent damage during transit. 

F. All  pumps,  compressors  and  blowers  shall  be  shipped  on  their  individual  base plates,  complete  with  wooden  shipping  pieces  and  covers  over  suction  and discharge except where they have been pre‐piped into the system. 

G. Polished and machined metal  surfaces  shall  be protected  from corrosion and damage during  shipment.  All  equipment  shall  be  carefully  packed  and  crated  for  shipment, especially electrical equipment as  to prevent damage to  insulation by moisture. Cover equipment having exposed bearings and glands to prevent intrusion of foreign matter. 

Page 141: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐13 

H. Shipping, delivery, and inspections shall be performed in accordance with these specifications and Articles 8 and 9 of the Standard General Conditions. 

* * * END OF SECTION * * * 

Page 142: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 60 00 Product Requirements for Procurement.doc  01 60 00‐14 

THIS PAGE LEFT BLANK INTENTIONALLY 

Page 143: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 1   

SECTION 01 75 00 TESTING AND COMMISSIONING 

PART 1 GENERAL 

1.01 DESCRIPTION OF WORK 

A. This  section  specifies  the  Special  Services  required  by  Seller  for  providing  a Commissioning Plan and Schedule and performing on‐site installation inspection, on‐site testing  and  commissioning  of  the  equipment  and  appurtenances  specified  in  the technical specifications.  

1.02 RELATED WORK 

A. Other divisions requiring equipment testing and startup include, but are not limited to, the following: 

1. Division 40 ‐ Process Interconnections 

2. Division 43 ‐ Process Gas and Liquid Handling Equipment 

3. Division 46 ‐ Water and Wastewater Equipment 

B. Section 01 33 00 – Submittal Procedures 

1.03 SUBMITTALS 

A. Furnish submittals in accordance with Section 01 33 00, Submittal Procedures. 

B. Submittals include: 

1. Commissioning Schedule 

2. Field and Performance Testing Plan 

3. Field Instrument Calibration Forms 

4. Motor Testing Forms 

5. Certificate of Installation and Testing Forms 

6. Control Panel Testing Forms. 

C. Not  less than thirty (30) days before the Date of Seller’s on‐site  installation  inspection and assistance, the Seller shall submit to the Engineer for approval: 

1. Commissioning Schedule including: 

a. Dates for final factory quality control tests 

b. Dates for shipment of Goods 

Page 144: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 2   

c. Dates for Seller’s on‐site installation inspections 

d. Dates for Seller’s on‐site field instrument calibration testing 

e. Dates for control panel field I/O testing 

f. Dates that plant control system programming will be required for testing. 

g. Dates that water or sewage will be required for testing. 

h. Dates for Seller’s on‐site field testing 

i. Dates for Seller’s on‐site performance testing 

j. Dates for Seller’s on‐site operator training 

2. Field  and  Performance  Testing  Plan.  Plan  for  Seller’s  equipment  including detailed procedures and start‐up requirements (water, power, etc.) for: 

a. Instrumentation calibration and testing. 

b. Control valve and gate testing. 

c. Control panel I/O testing. 

d. Field testing of all Seller supplied or controlled equipment.  

e. Control system testing including all operating sequences, indications, and alarms.  

f. Performance testing to verify if Seller’s system complies with the specified design criteria and operating conditions. 

PART 2 PRODUCTS 

2.01 FACTORY TESTING OF CONTROL PANELS 

A. Perform factory tests of all control panels prior to shipment.   

B. Power Distribution and I/O Checklist 

1. Manufacturer shall submit a power distribution and I/O checklist for all points in the control panel. Refer to Form 01 75 00‐1. 

2. The draft checklist shall be submitted Engineer for review and approval 15 days prior to the scheduled testing date.   

3. The form shall include the Manufacturer's name, project name, contract name, control  panel  identification,  testing  type  (factory),  and  date  and  time  of  the testing.  

Page 145: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 3   

4. The list shall include for each point, the tag name of the point, a description of the  point,  I/O  type,  scale  for  analog  inputs,  rack  number,  slot  number,  point number, factory check off for the person performing the test, and comments. 

C. Control Panel Power and I/O Testing   

1. All  system  elements  will  be  checked  to  verify  that  they  have  been  installed properly and that all terminations have been made correctly. 

2. Control power distribution will be checked for proper wiring and voltage levels. 

3. Circuits not energized shall be tested for continuity. 

4. Energized  circuits  shall  be  tested  through  all  components  from  the  terminal blocks in the control panel to the hardware I/O memory locations in the PLC. 

5. Discrete input signals will be checked by simulating the field device with a wire jumper  connected  to  the  field  wiring  terminals,  and  verifying  the  input  is received at the correct PLC input point. Each digital point shall be set and reset. 

6. Discrete output signals will be checked by forcing the PLC output using a laptop with PLC programming software, and verifying that the output changes state at the field wiring terminals. 

7. Analog points shall be verified at 0%, 25%, 50%, 75%, and 100% of range.  

8. Analog input signals will be checked by simulating the instrument signal with a 2‐wire or 4‐wire current source, connected to the field wiring terminals. 

9. Analog output signals will be checked by forcing a value to the PLC output using a laptop with PLC programming software, and verifying that the output changes to the appropriate level at the field wiring terminals. 

D. Control Panel Functional Testing 

1. After completion of power distribution and I/O testing, the Manufacturer shall conduct subsequent functional testing.   

2. All control functions and all status and alarm monitoring and indication shall be demonstrated under simulated operating conditions.   

3. Simulating equipment shall be provided and wired  into  the control  system for this testing.  

4. The Manufacturer shall revise, modify, and adjust the system as required during the testing period.  

5. The  final  completed  testing  forms and other  functional  testing documentation shall be compiled into the Factory Test Report.  

E. Certified Factory Test Reports shall be submitted to and approved by the Engineer prior to shipment in accordance with Section 01 33 00, Submittal Procedures. 

Page 146: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 4   

PART 3 EXECUTION 

3.01 GENERAL 

A. Testing and  inspection shall consist of  individual  tests and checks made on equipment intended  to  provide  proof  of  performance  of  units  and  proper  operation  of  unit controls.   

B. Testing  and  inspection  are  to  assure  proper  alignment,  size,  condition,  capability, strength, adjustment, lubrication, pressure, flow, leakage and any other checks deemed necessary  by  the  Engineer  to  determine  that  all  materials  and  equipment  are  of specified quality, properly situated, anchored and in all respects ready for use. 

C. Testing  and  inspection will  be  performed  by  the  installing  Contractor  with  assistance with  the  Seller’s  on‐site  representative  in  the  presence  of  the  Engineer’s  on‐site representative.    Records  of  all  official  tests  will  be  signed  by  the  Engineer’s  on‐site representative or the Engineer. 

D. During testing and inspection, the installing Contractor with assistance with the Seller’s on‐site  representative  shall  correct  any  defective  work  that  fails  to  comply  with parameters described in the technical specifications. 

3.02 SELLER’S INSTALLATION INSPECTION 

A. Seller’s on‐site representative shall inspect the installation to verify that the installation is  in  accordance  with  Seller’s  and  other  Original  Equipment  Manufacturer’s  (OEM’s) instructions  and  is  in  compliance  with  the  Contract  Documents  and  approved  Seller submittals.   

B. Seller’s representative shall be experienced and knowledgeable in the equipment being inspected and tested.  

C. Seller’s installation inspection shall consist of: 

1. Process, instrumentation, mechanical, and electrical installation inspection. 

2. Review of onsite issues with installing Contractor, such as: 

a. Installation questions 

b. Identification of components 

c. Assistance with locating or source missing parts 

d. Reviewing any concerns with installation and provide recommendations. 

3. Generate deficiency lists for the installing Contractor  

4. Review  with  installing  Contractor  onsite  commissioning  activities  and  identify resources required for tasks. 

Page 147: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 5   

D. Process, instrumentation, mechanical, and electrical installation inspection shall include verifying at minimum, where applicable: 

1. Supports anchored.   

2. Equipment bases grouted. 

3. Equipment  and  associated  piping  plumbed  and  leak  tested  and  test  form submitted. 

4. Process basins and hydraulic gates leak tested and test form submitted.   

5. Process basins, tanks, and piping cleaned and flushed.   

6. Valves and gates open and close as required. 

7. Shafts and bearings properly aligned.   

8. Equipment lubricated in accordance with manufacturer’s instructions.   

9. Equipment and motor rotate in proper direction.   

10. V‐belt tension adequate. 

11. Guards in place. 

12. Emergency switches and pull cords in place.   

13. Power supply cables connected. 

14. Power supply voltage and phase correct. 

15. Instrumentation is installed properly, and control wiring terminated. 

16. Instrument Calibration Forms submitted.   

17. Control System I‐O Checkout Forms submitted. 

18. Equipment and instrumentation is properly tagged. 

19. All associated equipment and spare parts on‐site. 

3.03 FIELD INSTRUMENT CALIBRATION 

A. Seller’s  Representative  shall  perform  inspection  and  calibrate  all  panel  and  field‐mounted instruments furnished by Seller.  

B. Seller’s Representative  shall  complete  Field  Instrument Calibration  Form  for  all  Seller‐supplied instruments or equipment with analog or discrete inputs or outputs.  

C. Engineer’s representative shall witness all calibration testing. 

Page 148: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 6   

D. All calibration forms must be submitted and approved prior to on‐site functional testing. 

3.04 FIELD CONTROL PANEL TESTING 

A. Seller’s  qualified  service  representative  shall  assist  the  installing  Contractor,  who  is installing  the  instrumentation  and  control  wiring,  to  perform  field  testing  of  the complete  control panels  and  field devices. Contractor will  be  responsible  for  checking and  verifying  each  control  panel,  instrument,  and  equipment  input  and  output termination.  

B. Seller shall submit the power distribution and I/O checklist used for field testing with the check spaces blank to Engineer for review and approval 15 days prior to the scheduled testing date. Any modifications to the form from the factory testing form shall be noted. 

C. Field testing shall include, but not be limited to: 

1. All  system  elements  will  be  checked  to  verify  that  they  have  been  installed properly and that all terminations have been made correctly. 

2. Control power distribution will be checked for proper wiring and voltage levels. 

3. All  instruments  will  be  calibrated  and  checked  according  to  the transmitter/switch calibration forms. 

4. Circuits not energized shall be tested for continuity.  

5. Energized  circuits  shall  be  tested  through  all  components  from  the  field instrument to the hardware I/O memory locations in the PLC.   

6. Discrete input signals will be checked by actuating the field device (hand switch, limit switch, etc.) whenever possible, and verifying the  input  is received at  the correct PLC or remote panel input point. 

7. For field elements that cannot be actuated, the discrete signal will be simulated using a wire jumper connected to the field device. 

8. Discrete output signals will be checked by jumpering the output terminals in the control panel, and verifying that the output changes state at the field device. 

9. Analog points shall be verified at 0%, 25%, 50%, 75%, and 100% of range. 

10. Analog input signals from instruments shall be checked for proper operation by simulating  the  process  whenever  possible,  and  verifying  the  analog  signal  is received at the correct PLC input channel.  

11. For field elements that cannot be operated, the analog signal will be simulated using a current source connected at the field device. 

12. Analog  output  signals  will  be  checked  by  simulating  a  signal  with  a  current source  at  the  control  panel  output  terminals,  and  verifying  that  the  output changes to the appropriate level at the field wiring terminals. 

Page 149: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 7   

D. A  minimum  of  98%  of  terminations  must  be  verified,  witnessed  by  the  Engineer’s representative,  and  signed off  on  the  Control  Panel  Testing  Form 01 75  00‐1 prior  to functional testing. 

E. Final Control Panel Testing Form shall be submitted to the Engineer and approved prior to on‐site equipment field testing. 

3.05 MOTOR TESTING 

A. Contractor  shall perform motor  testing  in accordance with Section 40 05 93 and shall submit Motor Testing Form 40 05 93‐1 to the Engineer for approval.  

B. Motor Testing Form shall be submitted  immediately after equipment  field  testing and before performance testing. 

C. Check for proper rotation before running equipment. 

D. Check each motor for amperage comparison to nameplate value at full equipment load.  

E. Correct  conditions  which  produce  excessive  current  flow  and  which  exist  due  to equipment malfunction.  

3.06 EQUIPMENT FIELD TESTING 

A. General 

1. Seller’s  representative  shall  assist  the  Installing  Contractor  in  adjusting  and testing the equipment. 

2. Installing  Contractor  shall  notify  the  Engineer  a minimum of  ten  (10) working days in advance of running any tests, and no tests shall be accepted unless the Engineer or Engineer’s representative is present to witness testing.  

3. Engineer  and  Installing  Contractor  must  give  permission  to  energize  any equipment during functional testing. 

4. Potable water or secondary effluent shall be used for wet tests. Water shall be supplied by the Owner and metered by the installing Contractor. 

5. Seller shall furnish any special test equipment or measuring devices required for equipment testing. 

6. Seller’s representative shall instruct the Owner’s operating staff in adjusting and operating the equipment during field testing, whenever practicable. 

7. Field  tests  shall  demonstrate  to  the  Engineer  that  all  equipment  operates properly, and specified performance has been attained.  

8. Equipment shall be tested in place with its own motor. The tests shall duplicate all operating modes and failure modes.  

Page 150: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 8   

9. Should tests indicate unsatisfactory operation, conditions shall be corrected and test repeated at the installing Contractor's and/or Seller’s expense.  

10. Seller’s  Representative  shall  complete  and  submit  Certification  of  Installation and  Testing  Form  for  the  equipment  supplied  by  Seller  upon  completion  of testing.  Form  shall  be  submitted  prior  to,  or  within  48‐hours  of,  Seller’s representative leaving the site after the equipment installation and field testing has been completed.  

11. Seller’s  Representative  shall  also  complete  and  submit  its  standard  start‐up testing forms. 

12. When  field  testing  has  been  successfully  completed  to  the  satisfaction  of  the Engineer,  Seller’s  Representative  shall  verify  that  all  field  testing  forms  have been  submitted  to  the  Engineer  signifying  that  all  systems  and  equipment furnished by  Seller  are  properly  installed  and  field  tested.  All  equipment  field testing  forms  shall  be  submitted  and  approved  by  Engineer  prior  to performance testing. 

B. Pumps: 

1. Check mechanical seals for cleanliness and adjustment before running pump.  

2. Inspect shaft sleeves for scoring.  

3. Inspect mechanical faces, chambers and seal rings, replace if defective.  

4. Verify  that  piping  system  is  free  of  dirt  and  scale  before  circulating  liquid through the pump.  

5. Include  measurement  of  suction  and  discharge  pressure  at  the  pump  and measurement  of  pumping  rate  by  volumetric  means  or  through  a  suitably calibrated meter for two points on the performance curve.  

6. For adjustable‐speed pumps, conduct tests at a minimum of two speeds. 

7. Seller shall furnish any test equipment or measuring devices required, which are not part of the permanent installation.  

8. Submersible  pump  installations  shall  be  checked  before  the  pumps  are submerged or the wet wells are filled.  

9. Vibration: Centrifugal pumps shall not exceed the acceptable vibration limits in accordance with the Hydraulic Institute Standards.  

C. Control Valves:  

1. Inspect  both  hand  operated  and  automatic  control  valves,  clean  bonnets  and stems.  

2. Verify  that control valve seats are  free  from foreign material and are properly positioned for intended service.  

Page 151: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00 ‐ 9   

3. Tighten packing glands to assure no leakage, but permit valve stems to operate without galling.  

4. Replace packing in valves to retain maximum adjustment after system is judged complete.  

5. Replace packing on any valve which continues to leak.  

6. Remove and repair bonnets which leak.  

7. Coat packing gland threads and valve stems with a surface preparation of anti‐friction lubricating paint, "Moly‐Cote" or "Fel‐Pro", or equal, after cleaning.  

3.07 PERFORMANCE TESTING 

A. Performance testing shall not commence until all functional tests have been completed and approved by the Engineer. 

B. Performance  testing  shall  consist  of  testing  by  a  simulated  operation,  all  operational equipment and controls.  

C. Performance  testing  shall  verify  that  all  equipment  will  function  under  the  required operating conditions, all  interlocking controls and sequences are properly set, and the facility will function as an operating unit. 

D. Performance  testing  is  considered  to  be  complete  when  all  systems  are  operational without fault and in accordance with the specified performance requirements. 

E. Seller’s  service  representative  shall  assist  installing  Contractor  with  commissioning testing of the system components. 

F. Seller’s  service  representative  shall  also  assist  with  the  control  system  testing  and software  verification  to  insure  that  all  control  functions  and  all  status  and  alarm monitoring and  indications are demonstrated under all operating  conditions, and  that proper communications and programming between the Seller’s control system and the plant supervisory system is demonstrated. 

3.08 COMMISSIONING 

A. Commissioning  of  the  unit  processes  and  operation  by  the  Owner’s  personnel  shall begin immediately after completion and approval of functional and performance testing by the Engineer.  

B. Taking possession and use of the facility or portions of the facility, shall not be deemed an acceptance of any work not completed in accordance with the Contract Documents. 

* * * END OF SECTION * * * 

Page 152: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

 

STV‐01 75 00 Testing and Commissioning for Procurement.doc  01 75 00‐10   

FORM 01 75 00‐1 CONTROL PANEL TESTING FORM  

CONTRACTOR NAME:  

PROJECT NAME AND CONTRACT:  

CONTROL PANEL IDENTIFICATION: 

TESTING (FACTORY OR FIELD): 

CONTROL POWER DISTRIBUTION VERIFICATION 

TAG  DESCRIPTION  PROCEDURE CONTRACTOR CHECK OFF 

WITNESS CHECK  OFF  COMMENTS 

120 VAC POWER DISTRIBUTION 

           

           

           

           

24 VDC POWER DISTRIBUTION 

           

           

           

           

CONTROL PANEL MODULE INPUT‐OUTPUT (I/O) VERIFICATION 

TAG  DESCRIPTION  I/O TYPE   SCALE  RACK  SLOT  POINT CONTRACTOR CHECK OFF 

WITNESS CHECK OFF  COMMENTS 

I/O MODULE NO. 

                   

                   

                   

                   

                   

                   

                   

                   

Notes: This form shall be expanded to include all applicable tag and devices and submitted to Engineer no later than 15 days prior to testing.  

Page 153: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 78 00 Close‐Out Submittals for Procurement.doc  01 78 00‐1   

SECTION 01 78 00 CLOSE‐OUT SUBMITTALS  

PART 1 GENERAL 

1.01 DESCRIPTION 

A. This section specifies the procedures and requirements for contract close‐out submittals including: 

1. Operation and Maintenance Manual (O&M Manual) 

2. Control System Programming 

3. Spare Parts and Special Tools 

4. Certificate of Installation and Testing 

1.02 RELATED WORK 

A. Section 01 33 00 ‐ Submittal Procedures 

B. Division 40 ‐ Process Interconnections 

C. Division 43 ‐ Process Gas and Liquid Handling Equipment 

D. Division 46 ‐ Water and Wastewater Equipment 

1.03 SUBMITTALS 

A. Furnish submittals in accordance with Section 01 33 00, Submittal Procedures. 

PART 2 PRODUCTS 

2.01 OPERATION AND MAINTENANCE MANUAL 

A. The  Seller  shall  furnish  a  complete  instruction  manual  for  installation,  operation, maintenance  and  lubrication  requirements  for  each  component  of  mechanical  and electrical equipment or systems provided by the Seller.  

B. If manufacturer's  standard  instruction and maintenance manuals are used  to describe operating and maintenance procedures, such manuals shall be modified to reflect only the model  or  series  of  equipment  used  on  this  project.  Extraneous material  shall  be crossed out neatly or otherwise annotated or eliminated. 

C. The O&M Manuals shall be comprised of three primary sections: 

Page 154: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 78 00 Close‐Out Submittals for Procurement.doc  01 78 00‐2   

1. Operation and Maintenance (O&M) procedures  

2. Vendor Data Information; and 

3. Controls and Drawings. 

D. The O&M Manuals shall contain: 

1. Summary Sheet: At the front of the first Volume of the O&M Manual, include a page with the following information:  

a. Name of Seller with contact name, phone number and address; 

b. Name of Seller sales representative with contact name, phone number, and address; and 

c. Seller System Model Number and Serial Numbers. 

2. Mechanical  and  Electrical  Equipment  List:  A  complete  list  of  mechanical  and electrical equipment including: 

a. Supplier/sales representative contact name, phone number, and address; 

b. Original Equipment Manufacturer (OEM) contact name, phone number, and address; 

c. OEM list of routine maintenance requirements and frequency; and 

d. List of spare parts list furnished with the contract.  

3. Performance and Nameplate Data List: The O&M Manual shall  include a  list of all  the  nameplate  and  performance  data  required  on  the  equipment  and  the furnishing  of  performance  curves  which  were  the  results  of  factory  tests  or technical specification requirements. 

4. Complete process description, operational information, control documents, and approved  drawings  (Process  and  Instrumentation  Diagrams  (P&IDs),  General Arrangements  (GAs),  and  Electrical  drawings.  Drawings  shall  be  furnished  in Adobe pdf and AutoDesk AutoCAD formats. 

5. HMI (OIT) screens commented and documented. 

6. Lubrication Information: OEM's recommendations regarding the lubricants to be used  and  lubrication  schedule  to  be  followed,  including  a  list  of  acceptable lubricant from at least (3) manufacturers whose products are locally available. 

Page 155: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 78 00 Close‐Out Submittals for Procurement.doc  01 78 00‐3   

7. Electrical  and  Control  Diagrams:  As‐built  diagrams  showing  internal  and connection  wiring  of  enclosure‐contained  assemblies  and  overall  system. Drawings shall be furnished in Adobe® Reader® (pdf) and AutoDesk® AutoCAD® formats. 

8. Installation  and  Start‐up  Procedures:  Manufacturer's  recommendations  for installation,  adjustment,  calibration,  troubleshooting,  and  operating  safety. Installation instructions shall include complete assembly drawings. 

9. Operating  Procedures: Manufacturer's  recommended  step‐by‐step  procedures for  starting,  operating,  and  stopping  the equipment under  specified modes of operation,  including  initial  startup,  automatic  and  manual  operation,  and emergency operation. 

10. Preventive Maintenance Procedures: Equipment manufacturer's recommended steps  and  schedules  for maintaining  the  equipment. Maintenance  procedures shall  include preventive,  corrective maintenance,  troubleshooting and detailed assembly,  disassembly  and  repair  procedures.    Troubleshooting  information shall  include  a  tabular  list  of  typical  informational malfunctions  and  probable remedies. 

11. Overhaul  Instructions:  Manufacturer's  directions  for  the  disassembly,  repair, and  re‐assembly  of  the  equipment  and  any  safety  precautions  that  must  be observed while performing the work. 

12. Exploded  Views:  Exploded  views  of  mechanical  equipment  shall  be  provided, unless  specified  in  the equipment description as not  required; when exploded views are specified as not necessary, cut or section views shall be provided with detailed callouts. 

13. Parts  List  and  Product  Data:  Generic  title  and  identification  number  of  each component part of the equipment and control devices, complete with exploded views  of  each  assembly  and  weights  of  individual  components  weighing  over 100 pounds. 

14. Spare  Parts  List: Manufacturer's  recommendations  for  parts  and maintenance tools that should be stored by the Owner including: 

a. Generic title, identification number and quantity of each component part; 

b. Any special storage precautions that may be required; 

c. Name, address, and phone number of the nearest parts supplier;  

d. Identification of those parts with an anticipated delivery time of greater than two months. 

15. Equipment cleaning, monitoring, and troubleshooting procedures. 

Page 156: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 78 00 Close‐Out Submittals for Procurement.doc  01 78 00‐4   

16. Specific Information: As necessary where items of information are not included in the above list but are required or as otherwise required in the Specifications. 

17. Warranty:  Copy of all guarantees and warranties applicable.  

18. Approved shop drawings and product data. 

2.02 CONTROL SYSTEM PROGRAMMING 

A. A flash drive or SD card with all final control system programs and program settings shall be submitted to the Engineer as specified herein. 

B. This flash drive or SD card shall be sufficient to load the program(s) and setting(s)  into the controller in the event of the loss of program or memory.  

C. When the startup technician returns to the factory, the programs and settings shall be reviewed with the designers of the equipment and program(s) and a final flash drive or SD card along with program loading  instructions shall be submitted to the Engineer as specified herein.  

D. The  flash  drive  or  SD  card  will  be  used  for  reintroduction  of  the  program(s)  and setting(s)  into  the  controllers  in  the  event  that  the  programming  and/or  settings  are lost. 

E. Final  program  documentation  printout  with  tag  numbers  and  descriptive  comments shall be submitted with the final program. 

2.03 SPARE PARTS AND SPECIAL TOOLS 

A. Furnish  adequate  supply  of  spare  parts,  special  (equipment‐specific)  tools,  and maintenance  materials  as  are  required  during  commissioning  and  for  on‐going  cost‐effective adjustment, repair and maintenance of the equipment supplied. 

B. Furnish  adequate  supply  of  maintenance  materials  as  required  during  the commissioning period to maintain the equipment supplied. 

C. Furnish spare parts and special tools specified in other Specification Sections. 

D. Packaging 

1. Package spare parts to prevent damage in transit and in storage.  

2. Attach  an  identification  label  or  tag  to  the  part  or  to  its  packaging  which contains: 

a. The part number; 

b. A reference to the tag number of the equipment component, and 

Page 157: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 78 00 Close‐Out Submittals for Procurement.doc  01 78 00‐5   

c. The name and contact information of the supplier. 

3. Attach relevant instructions on the application and method of use of the spare part, special tool, or maintenance material. 

E. Storage Container(s) 

1. Package  spare  parts  and  special  tools  in  one  or  more  of  hinged,  heavy‐duty, weather and impact resistance plastic cargo box(es) for long‐term storage.  

2. The box(es) shall be lockable with a padlock. 

3. The box(es) shall be clearly labeled with the contents and name of Seller. 

2.04 CERTIFICATE OF INSTALLATION AND TESTING 

A. After the equipment  installation and on‐site performance testing has been completed, the  Seller  shall  submit  the  Certificate  of  Installation  and  Testing  for  all  electrical  and mechanical  equipment  required  to  be  tested  and  in  accordance  with  the  respective specifications and manufacturer standard warranty conditions. 

PART 3 EXECUTION 

3.01 GENERAL 

A. Refer  to  Section  01  33  00,  Submittal  Procedures  for  submitting  procedures,  unless otherwise specified herein. 

3.02 PRELIMINARY O&M MANUALS 

A. Preliminary O&M Manuals shall be submitted to the Engineer for review within the time period indicated in the Agreement.   

B. Paper Copies:  Seller  shall  submit  four  (4)  paper  copies plus  the number of  copies  the Seller wants returned. 

C. Electronic Copies: Seller shall upload one (1) Adobe® Reader® (pdf) copy to the project ftp site. The pdf must contain a duplicate copy of all  the paper copy  information. The pdf shall be formatted with bookmarks for each Volume and section of the manual.  

D. Comments  from  the  Engineer  and  Owner  will  be  transmitted  to  the  Seller.  Unacceptable  preliminary  submittals  shall  be  resubmitted  until  stamped  either  “No Exceptions  Taken”  or  “Furnish  As  Corrected”.  Lack  of  review  comments,  or  partial comments  from  the  Owner  or  Engineer  shall  not  relieve  the  manufacturer  from  the obligation to provide a complete O&M Manual. 

Page 158: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 78 00 Close‐Out Submittals for Procurement.doc  01 78 00‐6   

3.03 FINAL O&M MANUALS  

A. On  or  before  the  Date  designated  for  On‐Site  Commissioning  and  Training  in  the Agreement, Seller shall submit Final O&M Manuals.  

B. Paper Copies: Seller shall submit six (6) paper copies of each Final O&M Manual shall be submitted.  

C. Electronic Copies:  

1. One (1) Adobe® Reader® pdf copy shall be uploaded to the project ftp site.  

2. One (1) Adobe® Reader® copy shall be submitted on USB 3.0 or 3.1 flash drive within each binder of the paper Final O&M Manual (six (6) total).  

3. The pdf copies shall be high quality and must contain a duplicate copy of all the paper copy information. Original documents shall be converted to pdf to create the  pdf  copies.  Pdf  copies  shall  not  be  scanned  copies.  The  pdf  shall  be formatted with bookmarks for each Volume and section of the manual.  

D. Copies shall all be of original quality.  

E. The manufacturer's  manual  shall  be  appropriately  labeled  with  the  equipment  name and equipment number as it appears in the specifications on the cover and the spine of the binder.  

F. The binders  shall  be  provided with  a  table of  contents  and  tab  sheets  to permit  easy location of desired information.  

G. Manuals shall consist of one or more volumes of white, 8 ½‐inch by 11‐inch, or 8 ½‐inch by  17‐inch,  3‐ring,  loose  leaf,  vinyl  plastic  hard  cover  binder  suitable  for  bookshelf storage.  

H. Binder ring size shall not exceed 4 inches.      

I. Final  O&M Manuals  shall  incorporate  all  changes  due  to  modifications,  settings,  and final adjustments following startup and commissioning. 

J. Final O&M Manuals shall incorporate any modifications to the Draft O&M Manuals as a result of the Owner or Engineer review. 

3.04 CONTROL SYSTEM PROGRAMMING 

A. Two  (2)  USB  3.0  or  3.1  flash  drive  or  SD  card  with  all  control  system  programs  and program settings shall be submitted to the Owner 15 days prior to the date for Delivery of the Goods as designated in the Agreement. 

Page 159: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 78 00 Close‐Out Submittals for Procurement.doc  01 78 00‐7   

B. Two  (2) USB 3.0 or 3.1  flash drive or  SD  card with  all  programs and program settings established during startup and testing shall be submitted to the Engineer on or before completion of performance testing. 

C. All programs shall be accessible to the Owner. If programs are password protected, then passwords must be provided to Owner.   

3.05 SPARE PARTS AND SPECIAL TOOLS 

A. Seller’s on‐site representative and the Engineer’s representative shall jointly inspect the spare  parts  and  special  tools  upon  Seller’s  arrival  at  the  time  of  Seller’s  installation inspection services.  

B. Any items missing shall be delivered to the Owner on or before the date for training. 

3.06 CERTIFICATE OF INSTALLATION AND TESTING 

A. The  Certificate  of  Installation  and  Testing  shall  be  submitted  to  the  Engineer  on  or before the date for completion of performance testing. 

* * * END OF SECTION * * * 

Page 160: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

   

STV‐01 78 00 Close‐Out Submittals for Procurement.doc  01 78 00‐8   

THIS PAGE LEFT BLANK INTENTIONALLY 

Page 161: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-01 79 00 Training for Procurement.doc 01 79 00-1

SECTION 01 79 00 TRAINING

PART 1 GENERAL

1.01 DESCRIPTION OF WORK

A. This section contains requirements for training the plant operating and maintenance staff to ensure proper operation and maintenance of the equipment and systems supplied under this contract.

1.02 RELATED WORK

A. Section 01 33 00 – Submittal Procedures

B. Division 40 - Process Interconnections

C. Division 43 - Process Gas and Liquid Handling Equipment

D. Division 46 - Water and Wastewater Equipment

1.03 QUALITY ASSURANCE

A. Instruction shall be performed by qualified, factory-trained engineers and technicians, knowledgeable in the maintenance and operation of the various types of equipment.

1.04 SUBMITTALS

A. Furnish submittals in accordance with Section 01 33 00, Submittal Procedures.

B. Not less than thirty (30) days before the anticipated time for beginning the On-site Training as designated in the Commissioning Plan, the Seller shall submit to the Engineer for approval:

1. Lesson Plan

C. Submit Certificate of Training Form, Form 01 79 00 attached to this Specification Section, for each type of equipment as delineated per the Specification Sections.

PART 2 PRODUCTS

2.01 LESSON PLAN

A. A detailed lesson plan outline describing the course content and learning objectives of each training session complete with a schedule indicating the time allocation for each subject will be prepared and submitted.

B. A copy of the lesson plan outline, training manual, handouts, visual aids and reference materials shall be suitably bound for proper organization and easy reproduction and submitted to the Engineer.

Page 162: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-01 79 00 Training for Procurement.doc 01 79 00-2

C. One complete set of originals of the lesson plans, training manuals, handouts, visual aids, and reference material shall be the property of the Buyer and shall be suitably bound for proper organization and easy reproduction.

D. Seller shall also furnish four (4) copies of necessary training manuals, handouts, visual aids and reference materials to the Buyer’ staff at the time of training.

2.02 LESSON PLAN CONTENT

A. The minimum requirements for instruction are listed below.

1. Operation and Maintenance Manuals: Familiarize with outline, catalog, parts lists, shop drawings, etc.

2. Shop Drawings: Identify equipment components, features, and layout.

3. Safety: Review safety features, requirements, lock-out, and control interlocks.

4. Operation: Describe operating procedures – start-up, shut-down, normal, and emergency.

5. Disassembly: Demonstrate removal, disassembly, assembly, installation, and storage.

6. Normal Maintenance: Instruct on normal preventative maintenance procedures and cleaning. Review maintenance task schedule.

7. Calibration: Instruct on calibration of measuring instruments, as applicable.

8. Lubrication: Identify lubrication requirements and schedule.

9. Troubleshooting: Identify checklist and instruct on troubleshooting procedures.

10. Corrective Maintenance: Provide overview of possible problems and corrective procedures.

11. Parts: Indentify parts list, procedures for ordering, equipment repairs, and replacement of parts.

12. Spare Parts: Identify those that are on-site and those that are recommended.

13. Special Tools: Identify and describe the use of any special tools required.

14. Local Representatives: Identify contacts for ordering parts or servicing equipment.

15. Post Commissioning Services: Review Seller’s quarterly on-site service visits, 24-hour telephone support service, and warranties.

Page 163: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-01 79 00 Training for Procurement.doc 01 79 00-3

PART 3 EXECUTION

3.01 GENERAL

A. Final Operation and Maintenance Manuals shall be made available to operation and maintenance personnel for training on or before the date designated for Training.

B. Prior to, or within 48-hours of, Seller’s representative leaving the Site after Commissioning and Training has been completed, Seller shall submit Certificate of Training Forms for each type of equipment.

3.02 VIDEO RECORDING

A. The Buyer may record each training session. After taping, the material may be edited and supplemented with professionally produced graphics to provide a permanent record.

3.03 TRAINING SESSIONS

A. Seller’s qualified service representative shall provide a minimum of eight (8) hours of training of the Buyer’s staff in the operation and maintenance of the Seller’s equipment, unless otherwise specified.

B. Training shall consist of a combination of class room and field training sessions.

C. Class room training sessions will take place at the Point of Destination at the address listed in the Agreement. The Buyer will provide facilities for classroom training sessions at this location.

D. Field training sessions shall take place at the Site of the equipment delivery.

3.04 CLASSROOM TRAINING

A. Classroom training shall include the topics listed in Paragraph 2.02.

3.05 FIELD TRAINING

A. Field training shall include the topics listed in Paragraph 2.02 as applicable and shall also include:

1. Identify location of equipment and review the purpose.

2. Review the equipment function and theory of operation.

3. Identifying flow options.

4. Identifying gates and their purpose.

5. Identifying instrumentation:

a. Location of primary element.

b. Location of instrument readout.

Page 164: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-01 79 00 Training for Procurement.doc 01 79 00-4

c. Discuss purpose, basic operation, and information interpretation.

6. Discuss, demonstrate, and perform standard operating procedures and checks.

7. Discuss and perform preventative maintenance activities.

8. Discuss and perform start-up, switch-over from dry weather flow treatment to wet weather flow treatment and shutdown procedures.

9. Perform the required equipment exercise procedures.

10. Perform start-up and shutdown procedures.

11. Review normal repair procedures.

12. Identify and review safety items and perform safety procedures.

13. Perform Buyer-approved practice maintenance and repair job(s), including mechanical and electrical adjustments and calibration and troubleshooting equipment problems.

* * * END OF SECTION * * *

Page 165: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-01 79 00 Training for Procurement.doc 01 79 00-5

FORM 01 79 00 CERTIFICATE OF TRAINING

NAME OF EQUIPMENT:

SPECIFICATION SECTION:

NAME OF MANUFACTURER:

EQUIPMENT SCHEDULE #S:

Check if

Complete

1. Operation and Maintenance (O&M) Manuals available – provide one paper copy to each trainee.

2. O&Ms - Familiarize with outline, catalog, parts lists, shop drawings, etc.

3. Drawings - Identify equipment components, features, and layout.

4. Safety – Review safety features, requirements, lock-out, and control interlocks.

5. Operation - Describe operating procedures – start-up, shut-down, normal, and emergency.

6. Disassembly – Demonstrate removal, disassembly, assembly, installation, and storage.

7. Normal Maintenance – Instruct on normal preventative maintenance procedures and cleaning.

8. Calibration – Instruct on calibration of measuring instruments, as applicable.

9. Lubrication – Identify lubrication requirements and schedule.

10. Troubleshooting – Identify checklist and instruct on troubleshooting procedures.

11. Corrective Maintenance – Provide overview of possible problems and corrective procedures.

12. Parts – Identify parts list, procedures for ordering, equipment repairs, and replacement of parts.

13. Spare Parts - Identify those that are on-site and those that are recommended.

14. Special Tools – Identify and describe the use of any special tools required.

15. Local Representatives – Identify contacts for ordering parts or servicing equipment.

Owner’s Staff Receiving Training

1. Date: (Signature) Owner’s Staff 2. Date: (Signature) Owner’s Staff 3. Date: (Signature) Owner’s Staff 4. Date: (Signature) Owner’s Staff 5. Date: (Signature) Owner’s Staff Witnessed By: Date: (Signature) Engineer or Engineer’s Representative

As the Manufacturer’s Representative, I certify that I have instructed the above Owner’s personnel in the proper operation and maintenance of the equipment indicated above and have covered the above topics during training.

Certified By: Date: (Signature) Manufacturer’s Representative

Page 166: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-01 79 00 Training for Procurement.doc 01 79 00-6

THIS PAGE LEFT BLANK INTENTIONALLY

Page 167: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 1 

SECTION 40 05 93 COMMON MOTOR REQUIREMENTS FOR PROCESS EQUIPMENT 

 PART 1 GENERAL 

 1.01 DESCRIPTION OF WORK 

A. Section  specifies  alternating  current  induction  motors  for  application  on equipment specified in other Sections. Application, horsepower, enclosure type, mounting,  shaft  type,  synchronous speed, and deviations  from this  section will be listed in the equipment specification. Where such deviations occur, they shall take precedence over this section.  

1.02 RELATED WORK 

A. Section 01 33 00 – Submittals Procedure 

B. Section 01 60 00 – Product Requirements 

C. Section 01 75 00 – Testing and Commissioning  

D. Division 43 ‐ Process Gas and Liquid Handling Equipment 

E. Division 46 – Water and Wastewater Equipment 

1.03 DEFINITIONS AND ABBREVIATIONS 

A. CISD‐TEFC: Chemical industry, severe‐duty enclosure 

B. DIP: Dust‐ignition‐proof enclosure.  

C. EXP: Explosion‐proof enclosure. 

D. ODP: Open drip‐proof, motor enclosure 

E. RPM: Revolutions per minute 

F. TEFC: Totally Enclosed Fan Cooled, motor enclosure 

G. TENV: Totally Enclosed Non‐Ventilated 

H. T’STAT: Thermostat, automatic reset high temperature thermal protector switch. 

1.04 STANDARDS AND REFERENCES 

A. Motor design and construction shall be in accordance with the latest applicable codes and standards of the following organizations: 

Page 168: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 2 

1. ABMA American Bearing Manufacturers Association 

a. ABMA 9 ‐ Load Ratings and Fatigue Life for Ball Bearings 

b. ABMA 11 ‐ Load Ratings and Fatigue Life for Roller Bearings 

2. IEEE Institute of Electrical and Electronics Engineers 

3. IEC International Electrotechnical Commission 

4. NEC National Electrical Code 

5. NEMA National Electrical Manufacturers Association 

a. NEMA MG 1 Motors and Generators 

6. NFPA National Fire Protection Agency ‐ National Electrical Code 

7. UL Underwriters Laboratories 

B. All motors shall be listed under UL recognized component file and shall bear the UL label. 

C. All motors shall be suitable for installation according to the requirements of NEC. 

1.05 SUBMITTALS 

A. Furnish Shop Drawings and Product Data submittals  in accordance with Section 01 33 00 ‐ Submittal Procedures. For each motor, including the following: 

1. Descriptive information.  

2. Nameplate data in accordance with NEMA MG 1.  

3. Additional Rating Information:  

a. Service factor.  

b. Locked rotor current.  

c. No load current.  

d. Adjustable frequency drive motor load classification (for example, variable  torque)  and  minimum  allowable  motor  speed  for  that load classification.  

e. Guaranteed minimum full load efficiency and power factor.  

Page 169: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 3 

4. Motor performance curve: percent efficiency, power factor, torque, rpm, power  and  current  versus percent of  rated power output  (horsepower) curves. 

5. Insulation rating. 

6. Enclosure type and mounting (such as, horizontal, vertical).  

7. Dimensions and total weight.  

8. Terminal box dimensions and usable volume as defined  in NEMA MG 1 and NFPA 70.  

9. Bearing type.  

10. Bearing lubrication.  

11. Manufacturer’s certified bearing life. 

12. Space heater voltage and watts.  

13. Description, ratings, and wiring diagram of motor thermal protection.  

14. Motor sound power level in accordance with NEMA MG 1.  

15. Maximum  brake  horsepower  required  by  the  equipment  driven  by  the motor.  

16. For  motors  provided  with  cords,  provide  complete  information  on  the cord  including  length, number and size of  conductors, overall diameter, materials, and ratings. 

17. Motor  wiring  and  connection  diagrams  for  all  provided  external connections  including  power,  overtemp  contacts,  space  heaters, moisture sensors, etc. 

18. Physical drawing showing electrical connection. 

19. Motor terminal connection box size. 

20. For motors on VFD’s, 

a. Expected speed range of load being served. 

b. Provide proof of inverter duty rating and insulation rating. 

B. Warranties as specified herein. 

Page 170: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 4 

C. Furnish IEEE 112 Form A‐1 for factory test of each motor. 

D. Furnish  Motor  Testing  Form  40  05  93‐1  for  all  motors,  unless  furnished  by installing Contractor. 

E. Furnish Operation and Maintenance Manuals  in accordance with Section 01 33 00, Close‐Out Submittals as a part of the process equipment manuals.  

1.06 BIDDING AND PAYMENT 

A. The  cost  for  furnishing  motors  shall  be  included  in  the  cost  for  a  specific equipment item for which the motor is a component.  

1.07 WARRANTY 

A. Manufacturer’s Warranty: Manufacturer shall warrant motors for a minimum of two (2) years from the day of shipment. 

PART 2 PRODUCTS  2.01 MANUFACTURERS 

A. ABB Baldor Motor Company, Fort Smith, Arkansas 

B. General Electric, Fairfield, Connecticut 

C. TECO‐Westinghouse, Round Rock, Texas 

D. Siemens Industry, Inc., SIMOTICS, Alpharetta, Georgia 

E. US Motors – Nidec Motor Corporation, St. Louis, Missouri 

F. Engineer‐approved equal. 

2.02 GENERAL 

A. For multiple units of the same type of equipment,  furnish  identical motors and accessories of a single manufacturer. 

B. Motors shall meet the requirements of NEMA MG 1 ‐ Motors and Generators. 

2.03 OPERATING CONDITIONS 

A. All  motors  shall  be  suitable  both  electrically  and  mechanically  to  drive  the connected  equipment  under  any  and  all  modes  of  operation.  The  speed, horsepower,  torque,  base,  bearing,  shaft,  insulation,  and  enclosure  shall  be 

Page 171: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 5 

closely coordinated with equipment requirements specified so as to provide an efficient drive without overloading, overheating, abnormal noise or vibration. 

B. All  motors  shall  be  designed  for  industrial  service  and  shall  be  capable  of operating  successfully  under  the  following  conditions  without  exceeding nameplate rated horsepower or rated temperature rise: 

1. 40  degrees  centigrade  maximum  ambient  temperature  to  ‐20  degrees centigrade minimum ambient temperature 

2. 3,300 ft. maximum altitude 

3. Voltage variations to plus or minus 10% of nameplate rating 

4. Frequency variations to plus or minus 5% of nameplate rating 

5. Overspeed in either direction in accordance with NEMA MG 1. 

C. Motors shall be specifically designed for the use and conditions intended, with a NEMA design letter classification to fit the application. Motors shall be rated for full  voltage  starting,  NEMA  Design  B,  normal  torque,  normal  starting  current, unless otherwise required by the driven equipment or specified. 

D. Provide motors rated for continuous duty unless otherwise specified. 

2.04 HORSEPOWER RATING 

A. Motor  horsepower,  if  indicated  in  the  detailed  equipment  specifications,  are minimum size acceptable.  

B. Frame/hp  relationships  shall  conform  to  the  latest NEMA  standards  for  "T"  or "U" frames, and all dimensions shall meet NEMA standards. 

C. Constant  Speed  Applications:  Brake  horsepower  of  driven  equipment  at  any operating  condition  not  to  exceed  motor  nameplate  horsepower  rating, excluding service factor.  

D. Adjustable Frequency and Adjustable Speed Applications (Inverter Duty Motor): Driven equipment brake horsepower at  any operating  condition not  to exceed motor nameplate horsepower rating, excluding service factor.  

2.05 SYNCHRONOUS SPEED 

A. In general,  the motor  speed  indicated  is  the  rated synchronous  speed. Provide motor  rated  full‐load  speeds  which  are  compatible  with  the  specified performance of the driven equipment. 

Page 172: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 6 

2.06 SERVICE FACTOR  

A. Inverter‐duty  Motors:  1.0  at  rated  ambient  temperature,  unless  otherwise noted.  

B. Other Motors:  1.15 minimum at  rated  ambient  temperature,  unless  otherwise noted.  

2.07 VOLTAGE AND FREQUENCY RATING  

A. System Frequency: 60 Hz.  

B. Voltage Rating: Unless otherwise indicated in motor‐driven equipment specification:  

  Size     Voltage   Phase    1/6 hp and smaller     115   1    1/6 hp through 1/2 HP   115/230   1    1/2 hp through 100 HP   230/460  3  

A. Suitable for full voltage starting. 

B. 40 hp and larger also suitable for reduced voltage starting with 65 percent or 80 percent voltage tap settings on reduced inrush motor starters.  

C. Suitable for accelerating the connected load with supply voltage at motor starter supply terminals dipping to 90 percent of motor rated voltage. 

2.08 EFFICIENCY AND POWER FACTOR  

A. For all motors except single‐phase, under 1 hp:  

1. Efficiency:  

a. Tested in accordance with NEMA MG 1, Paragraph 12.59.  

b. Guaranteed minimum at full load in accordance with NEMA MG 1 Table  12‐12,  Full‐load  Efficiencies  for  NEMA  Premium  Efficiency Electric Motors Rated 600 Volts  or  Less  (Random Wound),  or  as indicated in motor‐driven equipment specification.  

2. Power  Factor:  Guaranteed  minimum  at  full  load  shall  be  0.85  or  as indicated in motor‐driven equipment specification. 

2.09 LOCKED ROTOR RATINGS  

Page 173: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 7 

A. Locked rotor kVA Code F or  lower,  if motor horsepower not covered by NEMA MG 1 tables.  

B. Safe Stall Time: 12 seconds or greater.  

2.010 INSULATION SYSTEMS  

A. Provide  NEMA  Class  B  insulation  with  additional  nonhygroscopic  moisture protection which will maintain a minimum resistance of 1.0 megohms after 168 hours of exposure at 100% humidity. 

B. Class  F  insulation  with  additional  nonhygroscopic  moisture  protection  as specified above may be utilized, however, the temperature rise as measured by resistance when operating at rated service factor and load shall conform to the limiting observable temperatures in NEMA‐MGI, for class B insulation. 

C. Class A insulating materials shall not be utilized. 

2.011 ENCLOSURES  

A. Enclosures to conform to NEMA MG 1.  

B. TEFC and TENV: Furnish with drain hole with porous drain/weather plug.  

C. Explosion‐Proof (EXP): 

1. TEFC listed to meet UL 674 and NFPA 70 requirements for Class I, Division 1, Group C and D hazardous locations. 

2. Drain holes with drain and breather fittings. 

3. Integral  thermostat  opening  on  excessive  motor  temperature  in accordance with UL 2111 and NFPA 70. 

4. Terminate thermostat leads in terminal box separate from main terminal box. 

D. Chemical  Industry,  Severe‐Duty  (CISD‐TEFC):  In  accordance  with  Paragraph 2.019.  

2.012 TERMINAL (CONDUIT) BOXES  

A. Oversize main terminal boxes for all motors by two sizes.  

B. Diagonally split, rotatable to each of four 90‐degree positions. Threaded hubs for conduit attachment.  

Page 174: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 8 

C. Except ODP,  furnish  gaskets  between  box  halves  and  between  box  and motor frame.  

D. Minimum usable volume in percentage of that specified in NEMA MG 1, Section 1, Paragraph 4.19 and NFPA 70, Article 430: 500 percent. 

E. Provide  terminal  for  connection of equipment grounding wire  in each  terminal box. 

F. Provide  conduit  entrance  box  on  the  right‐hand  side  of  all  horizontal  motors, when  facing motor end opposite shaft extension, unless otherwise  required by location. 

2.013 BEARINGS AND LUBRICATION  

A. Horizontal Motors:  

1. 3/4 hp and Smaller: Permanently  lubricated and sealed ball bearings, or regreasable  ball  bearings  in  labyrinth  sealed  end  bells  with  removable grease relief plugs.  

2. 1 hp  through 400 hp: Regreasable ball  bearings  in  labyrinth  sealed end bells with removable grease relief plugs.  

3. Minimum 100,000 hours L‐10 bearing  life  for ball and roller bearings as defined in ABMA 9 and ABMA 11.  

B. Vertical Motors:  

1. Thrust Bearings:  

a. Antifriction bearing.  

b. Manufacturer’s standard lubrication 100 hp and smaller.  

c. Oil lubricated 125 hp and larger.  

d. Minimum 50,000 hours L‐10 bearing life.  

2. Guide Bearings:  

a. Manufacturer’s standard bearing type.  

b.  Manufacturer’s standard lubrication 100 hp and smaller.  

c. Minimum 100,000 hours L‐10 bearing life.  

Page 175: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 9 

C. Regreasable Antifriction Bearings:  

1. Readily accessible, grease injection fittings.  

2. Readily accessible, removable grease relief plugs.  

D. Oil Lubrication Systems:  

1 Oil reservoirs with sight level gauge.  

2 Oil fill and drain openings with opening plugs.  

3 Provisions for necessary oil circulation and cooling.  

E. Inverter  Duty  Rated Motors,  Bearing  Isolation: Motors  larger  than  50  hp  shall have electrically isolated bearings to prevent stray current damage. 

2.014 NOISE  

A. Measured in accordance with NEMA MG 1.  

B. Motors controlled by adjustable frequency drive systems shall not exceed sound levels of 3 dBA higher than NEMA MG 1.  

2.015 BALANCE AND VIBRATION CONTROL  

A. In accordance with NEMA MG 1, Part 7.  

B. Maximum vibration allowed shall be 0.15 inches per second velocity measured at the bearing housings. 

2.016 SHAFT RUNOUT 

A. Rotor  shaft extension  run out  shall be  in accordance with NEMA MG 1, Article 4.9.7.  

B. Rotor shaft extension run out shall not exceed: 

1. 0.002” TIR for shaft diameter 0.1875 ‐ 1.625 inches 

2. 0.003" TIR for shaft diameter over 1.625 ‐ 6.500 inches 

2.017 EQUIPMENT FINISH  

A. External  Finish:  Prime  and  finish  coat  manufacturer’s  standard.  Finish  color manufacturer’s standard.  

B. Internal Finish: Bore and end turns coated with clear polyester or epoxy varnish.  

Page 176: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 10 

2.018 SPECIAL FEATURES AND ACCESSORIES 

A. Screen  Over  Air  Openings:  Stainless  steel  on  motors  with  ODP  enclosures meeting requirements  for guarded machine  in NEMA MG 1, and attached with stainless steel screws.  

B. Winding Thermal Protection:  

1. Thermostats:  

a. Motors for 1 hp through 125 hp.  

b. Bi‐metal  disk  or  rod  type  thermostats  embedded  in  stator windings, one per phase.  

c. Automatic  reset  contacts  rated  120  volts  AC,  5  amps minimum, normally closed, opening on excessive temperature.  

d. Leads extending to separate terminal box for motors 100 hp and larger. 

C. Nameplates:  

1. Provide two engraved stainless steel stamped metal nameplates (one for the motor and one for mounting in the motor starter enclosure or MCC starter bucket), with the information required:  

a. Motor  data  required  by  NEMA  MG  1,  Paragraph  10.39  and Paragraph 10.40 in addition to bearing numbers for both bearings.  

b. Maximum ambient temperature for which motor is rated, class of insulation, service factor, bearing part number, motor connection diagram if more than three leads, voltage and wattage of internal space heaters. 

c. Premium efficiency motor  nameplates  to  display NEMA nominal efficiency, guaranteed minimum efficiency, full load power factor, and  maximum  allowable  kVAR  for  power  factor  correction capacitors.  

D. Anchor  Bolts:  Provide  meeting  manufacturer’s  recommendations  and  of sufficient size and number for specified seismic condition.  

E. Motor  Leads:  Provide  motor  leads  compatible  with  motor  insulation  system, permanently identified. 

Page 177: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 11 

F. Eyebolts: Provide drilling and tapping for eyebolts on all motors weighing more than 83 pounds. 

2.019 CHEMICAL INDUSTRY, SEVERE‐DUTY (CISD‐TEFC) 

A. Where required, these following requirements take precedence:  

1. In accordance with IEEE 841.  

2. TEFC in accordance with NEMA MG 1.  

3. Suitable  for  indoor  or  outdoor  installation  in  severe‐duty  applications including high humidity, chemical (corrosive), dirty, or salty atmospheres.  

4. Motor Frame, End Shields, Terminal Box, and Fan Cover: Cast iron.  

5. Ventilating Fan: Corrosion‐resistant, non‐sparking, external.  

6. Drain and Breather Fittings: Stainless steel.  

7. Nameplate: Stainless steel.  

8. Gaskets between terminal box halves and terminal box and motor frame.  

9. Oversized  terminal  box  rotatable  in  90  degree  increments  with  NPT threaded lead connection. 

10. Extra slinger on rotor shaft to prevent moisture seepage along shaft into motor.  

11. Bearings: 

a. Double shielded bearings.  

b. 150,000 hours L‐10 (B‐10) bearing  life  for direct‐connected  loads and 50,000 hours for belted applications, minimum.  

c. Regreasable  bearings,  positive  pressure  lubrication  system  with automatic relief fittings.   

12. External Finish: Double‐coated epoxy enamel.  

13. Coated rotor and stator air gap surfaces.  

14. Insulation System, Windings, and Connections:  

a. Class F insulation, Class B rise or better at 1.0 service factor.  

Page 178: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 12 

b. Copper magnet wire rated at 200 degrees Celsius minimum. 

c. Multiple  dips  and  bakes  of  nonhygroscopic  polyester  wire insulation  varnish  designed  to  resist  transient  spikes  and  high frequencies produced by inverters.  

15. Service Factor:  

a. At 40 Degrees C Ambient: 1.15.  

b. At 65 Degrees C Ambient: 1.00.  

16. Safe Stall Time Without Injurious Heating: 20 seconds minimum.  

2.020 INVERTER DUTY MOTORS  

A. Where required, these following requirements take precedence: 

1. All  motors  supplied  power  by  adjustable  frequency  drives  shall  be inverter duty rated.  

2. Inverter duty rated motors shall meet the requirements of NEMA MG1‐1993, Part 31.  Insulation rating shall be 2100V minimum. 

3. Motors shall be suitable for operation over entire speed range indicated.  

4. Provide motors with adequate cooling for the lowest expected speed for load served. 

5. Provide  forced  ventilation  where  speed  ratio  is  greater  than  published range for motor provided.  

6. Shaft Grounding Device: Motors  larger than 5 hp shall be provided with circumferential,  conductive  microfiber  shaft  grounding  ring  (SGR)  to discharge shaft currents to ground, AEGIS® SGR bearing protection ring or equal. Shaft grounding device shall be solidly bonded to grounded motor frame per manufacturer’s recommendations.  

2.021 SUBMERSIBLE MOTORS 

A. Where required, these following requirements take precedence: 

1. Submersible motors shall comply with NEC Class 1, Division 1, hazardous locations section 501‐8 (a) requiring explosion proof construction. 

Page 179: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 13 

2. Wet  well  duty:  Continuous  submerged  duty  in  water  and  sewage,  and minimum  15‐minute  duty  continuous  in  air  under  full  load  operating conditions.  

3. Dry  well  duty:  Continuous  operation  in  air  under  full  load  operating conditions. 

4. Controls:  Set  controls  to  permit  operation  only  when  fully  submerged unless specifically rated for non‐submerged dry well duty. 

5. Motor construction shall be designed to withstand 100 psi water pressure at all seal locations.  

6. Maximum submergence depth: 160 feet. 

7. Insulation: Class F rated insulation materials or better. 

8. Mechanical  seals:  Two  silicon  carbide  seals  separated  by  an  oil‐filled chamber. 

9. Moisture sensing probes: Two (2) probes extending into oil chamber. 

10. Moisture sensing probes relay: Provide and install moisture relay, Warrick or equal. 

11. Cap/Cable assembly design: Shall prevent moisture from wicking through cable. Cable entry into lead chamber shall be epoxy encapsulated.  

12. Motor  leads: Nonwicking type, Class F temperature rating or better and permanently numbered for identification. 

13. Embedded thermostats: Two (2) normally closed thermostats connected in series and embedded in adjoining phases. 

14. Provide one or more multiconductor cables of approved construction and suitable  length to extend from the motor to the  indicated receptacle or junction box.  Provide strain relief for the power and control cables. 

15. Separate cables shall be provided for power and alarm conductors. 

16. Provide control wiring connection diagram and all necessary components and  relays  for  the  required  and  proper  control  and  shutdown  of  the motor.   

PART 3 EXECUTION    

Page 180: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 14 

3.01 FACTORY TEST 

A. Factory testing shall be conducted  in accordance with  IEEE 112  (latest edition), Standard  Test  Procedure  for  Polyphase  Induction Motors  and  Generators  and Article  12.55  of  NEMA  MG  1.  Include  measurements  of  winding  resistance, insulation resistance, no  load current, starting current and torque,  locked rotor current  and  torque.  Test  multispeed  motors  at  minimum  25%  to  125%  of maximum speed. Measure % of rated load, power factor, efficiency, speed, and line current for each speed or load.  Submit IEEE 112 Form A for each motor.  

B. Perform  mechanical  inspection  and  test  of  shaft  runout  in  accordance  with Articles 4.9.7 and 4.11 NEMA MG 1. 

C. Perform vibration test in accordance with Article 7 NEMA MG 1.  

D. The  winding  temperature  and  overtemperature  protection  shall  be  tested  at maximum load per Article 12.56 and 12.57 NEMA MG 1. 

E. For energy efficient motors, test efficiency and power factor in accordance with IEEE  112,  Test  Method  B,  and  NEMA  MG  1,  Paragraph  12.59  and  paragraph 12.60.  

F. Certified  copies  of  the  test  forms  shall  be  submitted  to  the  Engineer  prior  to shipment in accordance with Section 01 33 00, Submittals. 

3.02 PRODUCT SHIPMENT AND PROTECTION 

A. The devices shall be packaged and shipped in accordance with Section 01 60 00, Product Requirements. 

3.03 INSTALLATION 

A. Motors  shall  be  installed  on  common  bases,  stands,  etc.,  with  the  driven equipment.  

B. Align  the  motor  shaft  with  driven  equipment  according  to  Manufacturer’s written instructions. 

1. Flexible couplings  for direct drive shall be accurately adjusted according to  machine  Manufacturer’s  guidelines,  use  dial  indicators  to  check alignment to minimize vibrations. Coupling spacing shall be according to coupling manufacturer guidelines. 

2. Belt  drive  sheaves  shall  be  align  according  to  belt  drive manufacturers instructions to minimize belt ware and axial bearings  loads. Belt tension shall be adjusted to prevent slippage at rated speed and rated load. 

Page 181: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 15 

3. Adjust axial position of motor frame with respect to load shaft according to motor manufacturers endplay adjustment guidelines recommended to minimize extensive external axial thrust loads. 

C. Provide  suitable  personnel  guards  over  all  shafts,  couplings,  or  other  exposed moving parts. 

D. Verify  proper motor  branch  circuit  and motor  overload  protection  devices  are installed in motor branch circuit as required by NEC article 430. 

E. Install power cable conduits according to motor terminal box drawing and motor manufacturer’s  instructions.  Install motor  power  supply  cables  and  connect  to motor power. Motor  lead cable  sizes  shall be selected based on NEC and  local code requirements. 

F. Properly  ground  all  equipment  according  to manufacturer’s  recommendations regarding  equipment  grounding  and  noise  attenuation  practices  for  electrical and electromagnetic interference. 

G. Tighten  electrical  connectors  and  terminals  according  to  cable  and  terminal manufacturer's published torque values. 

H. Install  wiring  between  motor  auxiliary  devices  and  associated  controllers  and protective devices according to manufacturer’s  instructions and  information on motor nameplate. 

I. Connections  of  devices  sensitive  to  electromagnetic  interferes  such  as  RTD’s, thermistors,  thermal protector switches, vibration sensors and other applicable instrumentation wiring shall be made per manufacturer’s  instructions. Shielded conductors  shall  be  used  and  routed  in  dedicated  conduits,  all  in  separate conduit runs end to end. 

J. Install wiring  to motor  auxiliaries  such as motor  space heaters, motor blowers motor brake coils according to NEC power wiring requirements and according to motor manufacturer’s instructions. 

3.04 ON‐SITE TESTING 

A. Contractor shall test all motors to be installed. 

B. Prepare for acceptance tests as follows: 

1. Verify mechanical installation is secure and all mounting hardware is tight according to manufacturer’s recommended torque specifications. 

Page 182: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 16 

2. Inspect  all  electrical  connections  for  proper  termination,  electrical clearances, mechanical strength and electrical continuity. 

3. Verify  all  shipping  materials  and  braces  are  removed  from  the  shaft. Verify  that  the motor and the coupled  load are properly aligned,  rotate freely and are not binding. 

4. Verify  that maintenance  information  is  posted.  This  information  should include lubricants needed and preventive maintenance schedule. 

5. Verify that proper lubricants are readily available at the site. 

6. Verify proper rotation and grounding. Motors must be uncoupled during rotation  check  if  equipment  damage  can  occur  from  operating  under incorrect rotation. 

7. Verify that motor overcurrent protection is in accordance with the NEC. 

C. Assure  that  equipment  manufacturer's  representative  is  present  when equipment is placed in operation. 

D. Contractor shall verify that the Motor Testing Form 40 05 93‐1 is included at the end  of  this  section  has  been  completed  for  all  motors  and  submitted  to  the Engineer  for  approval.  The  installing  Contractor  shall  perform  voltage,  current and insulation resistance tests as required to complete the Motor Testing Form. Testing shall include:  

1. Measure winding insulation integrity with a “Megger” or other insulation resistance tester. 

2. Apply  power  and  verify  rotation  direction  of  the  motor.  Change  the rotation direction if necessary and retest. 

3. Measure full load operating voltage for each phase to ground. 

4. Measure full load operating voltage between each phase. 

5. Measure motor circuit resistance between each phase. 

6. Measure full load operating current for each phase. 

7. Compare  motor  operating  amperage  to  nameplate  value  at  full equipment load.  

8. Verify  that  motor  over‐current  protection  is  functional  and  record overload trip setting. 

Page 183: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc            40 05 93 ‐ 17 

E. Engineer’s representative shall witness all motor testing. 

F. All motor testing forms must be submitted and approved prior to or during on‐site functional testing.  

G. During  functional  testing,  the  Manufacturer  shall  simulate  motor  alarm  and shutdown conditions to test that the motor protection functions correctly. These tests shall be witnessed and verified by the Engineer. 

H. If  the  test  results  indicate  corrective  measures  are  required,  the  installing Contractor and Manufacturer shall undertake all such corrective measures until the motor installation is accepted by the Engineer. No additional compensation will be paid for corrective measures. 

3.05 Training  

A. Manufacturer’s  qualified  service  representative  shall  include  training  on  the motors with the training on motor‐driven equipment specified elsewhere.  

*** END OF SECTION *** 

Page 184: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐40 05 93 Common Motor Requirements for Procurement.doc          40 05 93 ‐ 18 

FORM 40 05 93‐1 MOTOR TESTING FORM INSTALLING CONTRACTOR NAME:  PROJECT NAME:  

EQUIPMENT SCHEDULE NO.:  MANUFACTURER NAME: 

NAME OF EQUIPMENT:  LOCATION/SERVICE: 

MOTOR STARTER LOCATION:  EQUIPMENT SPECIFICATION SECTION: 

MOTOR NAMEPLATE DATA 

MANUFACTURER:  MODEL NUMBER: 

SERIAL NO.:  HORSEPOWER: 

VOLTAGE/PHASE/FREQUENCY:  FULL LOAD RPM: 

FULL LOAD AMPERAGE/LOCKED ROTOR AMPERES:  FULL LOAD NOMINAL EFFICIENCY: 

NEMA DESIGN:  LOCKED ROTOR CODE: 

ENCLOSURE TYPE:  FRAME SIZE: 

INSULATION CLASS:  TEMPERATURE RISE: 

DUTY CYCLE:  MAXIMUM AMBIENT TEMPERATURE: 

POWER FACTOR:  SERVICE FACTOR: 

BEARINGS:  THERMAL PROTECTION: 

OTHER MOTOR SERVICE INFORMATION 

STARTER TYPE:  STARTER MANUFACTURER/MODEL: 

SPACE HEATER VOLTAGE/PHASE/WATTS OR AMPS:  MOTOR OVERLOAD TRIP SETTING: 

MOTOR ROTATION DIRECTION VERIFIED:  MOTOR GROUNDING VERIFIED: 

FULL LOAD TESTING DATA 

  L1 TO GROUND  L2 TO GROUND  L3 TO GROUND 

FULL LOAD OPERATING VOLTAGE, V       

INSULATION RESISTANCE, MEGAOHMS       

  L1 TO L2  L2 TO L3  L3 TO L1 

FULL LOAD OPERATING VOLTAGE, V       

MOTOR CIRCUIT RESISTANCE, OHMS       

  L1  L2  L3 

FULL LOAD OPERATING CURRENT, AMPS       

 SELLER/MANUFACTURER  

CHECK OFF  CONTRACTOR CHECK OFF  WITNESS CHECK OFF 

NAME       

SIGNATURE       

DATE       

* VOLTAGE AND CURRENT READINGS SHALL BE TAKEN AT THE CLOSEST ACCESSIBLE POINT TO THE LOAD. 

Page 185: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 1   

SECTION 43 11 33 ROTARY LOBE BLOWERS 

 PART 1 GENERAL 

 1.01 DESCRIPTION OF WORK 

A. Manufacturer shall furnish three (3) positive displacement rotary lobe blowers as specified herein, complete. 

B. The  work  shall  include  fabrication,  factory‐testing,  delivery,  installation inspection,  field  testing,  certification  of  installation  and  field  testing,  and training.  

1.02 RELATED WORK 

A. Division 0 – Bid Documents 

B. Division 1 – General Requirements  

C. Section 40 05 93 ‐ Common Motor Requirements for Process Equipment 

1.03 REFERENCE STANDARDS 

A. American Bearing Manufacturers Association (ABMA): 

1. ABMA 11 ‐ Load Ratings and Fatigue Life for Roller Bearings. 

B. American Gear Manufacturers Association (AGMA): 

1. AGMA 390.01 ‐ Quality Numbering System of the Gear Classification Manual 

C. American Iron and Steel Institute (AISI) 

1. AISI 1043 ‐ Standard for Carbon Steel 

2. AISI  8620  ‐  Steel,  Single  Quenched  and  Tempered  (230°C  (450°F)), Carburized 

D. American Society of Mechanical Engineers (ASME): 

1. ASME B16.1 ‐ Gray Iron Pipe Flanges and Flanged Fittings: Classes 25, 125, and 250. 

2. ASME B40.100 ‐ Pressure Gauges and Gauge Attachments 

Page 186: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 2   

E. American Society of Heating and Air‐Conditioning Engineers (ASHRAE) 

1. ASHRAE Standard 52.2‐2012 ‐ Method of Testing General Ventilation Air‐Cleaning Devices for Removal Efficiency by Particle Size 

F. ASTM International (American Society for Testing and Materials): 

1. ASTM A48 / A48M‐03 ‐ Standard Specification for Gray Iron Castings 

G. EN Standard  

1. GG 20 ‐ Cast Iron 

2. GGG 50 ‐ Cast Iron 

H. International Standards Organization (ISO) 

1. ISO 1217 ‐ Displacement compressors ‐ Acceptance Tests 

2. ISO 1940‐1 ‐ Mechanical Vibration ‐‐ Balance Quality Requirements For Rotors in a Constant (Rigid) State 

3. ISO 2151‐2004 (E) ‐ Noise Test Code for Compressors and Vacuum Pumps 

I. National Electrical Manufacturers Association (NEMA): 

1. NEMA 250 ‐ Enclosures for Electrical Equipment (1000 Volts Maximum) 

2. NEMA MG1 ‐ Motors and Generators 

J. Occupational Safety and Health Administration (OSHA) 

1. Title 29, Part 1910 ‐ Occupational Safety and Health Standards, Code of Federal Regulations 

K. UL Underwriters Laboratories (U.L.) 

1. All equipment and devices shall be listed by and bear the Underwriters Laboratories (U.L.) Inc U.L. label or the CSA‐C/US label.   

2. Sound enclosure acoustic material shall comply with UL94‐HF1 for fire‐retardant, self‐extinguishing, non‐dripping materials. 

1.04 SUBMITTALS 

A. Furnish submittals  in accordance with Section 01 33 00  ‐ Submittal Procedures and including: 

Page 187: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 3   

1. Shop Drawings and Product Data.  

2. Performance curves showing capacity in cubic feet per minute, discharge pressure and blower horsepower from 0 percent to 130 percent of design capacity, dB(A) noise pressure level. 

3. Performance curves of silencers and filters showing capacity in cfm and pressure drop from 0 percent to 130 percent of design capacity. If performance curves are not available, then other such data or guarantee that demonstrates that the silencers are properly sized. 

4. Complete submittals for valves, gauges, filters, and all accessories. 

5. Motor data as required in Section 43 05 93. 

6. Complete noise attenuation data.  

B. Certified Factory Test Reports as specified herein. 

C. Bill of Materials per Section 01 33 00. 

D. Field erection requirements per Section 01 33 00. 

E. Manufacturer's warranties as specified herein. 

F. Operation and Maintenance Manuals: Furnish in accordance with Section 01 78 00, Close‐Out Submittals. 

1.05 QUALIFICATIONS 

A. The  manufacturer  of  the  products  specified  in  the  Section  shall  be  fully experienced, qualified, and reputable in the manufacture of such equipment.   

B. The manufacturer shall have at least 50 installations in the United States of the model specified in satisfactory operation for at least 10 years. 

C. Manufacturer  shall  have  a  qualified  factory‐trained  representative  and  service center qualified in repair of the blowers permanently located within a 300‐mile radius of the project site. 

1.06 WARRANTY 

A. Manufacturer shall warrant the materials and equipment specified herein to be free of defects in materials and workmanship for a period of two (2) years from the Date of Manufacturer’s Certificate of Installation and Field Testing. 

Page 188: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 4   

 PART 2 PRODUCTS  2.01 ROTARY LOBE BLOWERS 

A. Manufacturer: Approved Manufacturers are listed below; however, regardless of being  listed,  the  Manufacturer  must  comply  with  the  specifications,  unless otherwise approved by the Engineer. 

1. Aerzen Generation 5 Delta Blower GM Series  

2. Kaeser Com‐pak Series Package with Omega Rotary‐Lobe Blowers 

3. EASYAIR® X2 ROOTS package with a RAM X™ blowers 

4. Engineer‐approved equal. Refer to Section 00 20 00 Instructions to Bidders Article 10 for procedure for approval. 

B. Equipment Schedule Number: B‐B‐1, ‐2, ‐3 

C. Type:  

1. Positive Displacement Rotary Lobe Blower (blower): 3‐lobe, rotary, constant volume, variable pressure type, positive displacement  

D. Performance Criteria and Operating Conditions:  

1. Maximum blower speed:   

a. Blower: 4,000 RPM 

2. Air flow capacity, maximum, Standard Cubic Feet per Minute (SCFM) (at 14.7 PSIA, 68 deg F, 36% RH):  

a. New Aeration Basin: 1,100 SCFM at 10 psi differential pressure 

b. Existing Oxidation Ditch: 1,800 SCFM at 7 psi differential pressure 

3. Air flow capacity, minimum, SCFM: 300 at 10 psi differential pressure 

4. Inlet air temperature, maximum: 100°F 

5. Site elevation: 99 ft MSL 

6. Inlet relative humidity (RH), maximum: 85% 

E. Casing. 

Page 189: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 5   

1. The blower casing shall be of one‐piece construction, with separate side plates or head plates that are bolted and pinned to the housing.   

2. Materials shall be close‐grained cast iron ASTM A48 or EN GG 20 suitably ribbed to prevent distortion under the specified operating conditions.  

3. Minimum blower casing pressure rating shall be 36 psig.   

4. Inlet and outlet shall be flanged or threaded connections.   

5. The casing shall incorporate a proven means of pulsation cancellation.   

6. The vibration level as measured at the blower casing, in the X/Y planes of the bearings, shall not exceed 0.5”/sec RMS when operating at the specified maximum operating pressure and speed in the actual blower package.  

F. Rotors  

1. Each impeller shall be of the “stiff” design with first lateral critical speed at least 120% of the maximum allowable operating speed.  

2. The rotors shall be three‐lobe type, and shall operate without rubbing or liquid seals or lubrication.  

3. Rotor‐shaft assembly shall be drop forged in one single piece of AISI 1043 or ENGGG 50 carbon steel.   

4. The rotors shall be statically and dynamically balanced per ISO1940‐1/ANSI S2.19 G6.3.  

G. Bearings  

1. Each rotor‐shaft shall be supported by anti‐friction bearings, and fixed to control the axial location of the rotor‐shaft in the unit.   

2. Regardless of theoretical bearing life calculations, the bearings shall be sized for a minimum expected life of 5 years between overhauls. 

H. Timing Gears  

1. The impellers shall be timed by a pair of single helical AGMA (390.01) 12 quality gears with hardened and ground teeth, with a minimum AGMA service factor of 1.70.  Spur gears may be furnished upon approval of the Engineer.  

Page 190: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 6   

2. Gears shall be mounted on the shafts with a tapered interference fit, and secured by a locknut or other Engineer‐approved means.  

I. Seals  

1. Seals shall be designed to prevent lubricant from leaking into the air stream as well as to prevent oil from leaking out of the machine.  

2. Four rotary piston ring shaft seals, an oil slinger, and an O‐ring seal shall be provided at the point where the shaft passes through the sideplates. Alternate seal types may be furnished upon approval by the Engineer. 

3. Further provision shall be made to vent the impeller side of the oil seal to atmosphere to eliminate any possible carry‐over of lubricant into the air stream.   

J. Lubrication 

1. Timing gears and bearings shall be oil splash lubricated. Grease lubrication of any kind shall not be allowed. An oil sight glass shall be provided on each oil sump.  

2. Each blower shall receive its initial oil filling at the factory.  

3. Oil shall be fully synthetic suitable for continuous discharge temperatures up to 250 degrees F or as required for application. 

2.02 INLET FILTER/SILENCER  

A. Each package shall be supplied with one combination inlet filter/silencer.  

B. The  inlet  filter/silencer  shall  be  mounted  directly  to  the  inlet  flange  of  the blower.   

C. The  filter  media  efficiency  must  meet  the  requirements  of  ASHRAE  52.2 Minimum Efficiency Reporting Value (MERV) 7, greater than 50% removal of 3‐10 microns and 99% removal of 10 microns and larger.  

D. The silencer portion shall be located upstream of the inlet filter.   

E. Filter  and  silencer  performance  losses  shall  be  included  in  the  blower performance calculation. 

F. The  filter  element  shall  be  designed  to  trap  dirt  on  the  inside  so  that  upon changing, dirt does not  fall  into  the machinery.   Filters where dirt accumulates on the external surface of the filter will not be permitted. 

Page 191: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 7   

2.03 BASE FRAME/DISCHARGE SILENCER  

A. Each  package  shall  be  supplied  with  one  combination  base  frame/discharge silencer. 

B. The  silencer  shall  be  a  chamber  type  design  for  maximum  sound  attenuation unless  otherwise  approved  by  the  Engineer.  All materials must  be  suitable  for the maximum blower discharge temperature and pressure.   

C. The silencer shall be  fabricated of a single shell of pressure vessel quality steel with continuous welds. 

D. The  silencer must be  subject  to a pressure  test  for  tightness and  strength at a minimum of 1.65 times the maximum blower operating pressure.   

E. The silencer shall have a machined inlet connection where the discharge flange of the blower bolts directly to, with no intermediary pieces.   

F. Discharge silencer performance losses shall be included by the blower vendor in the blower performance calculation. 

G. The base frame shall be constructed from welded carbon steel or cast iron that shall be designed to maintain alignment of the blower internal components and the drive during operation.   

H. The  base  frame  shall  be  designed  to  resist  distortion while  being  installed  on vibration isolating mounts.   

I. The blower manufacturer shall supply a stainless steel grounding lug fully welded to  the  base.  A  ground  connection  shall  be  provided  between  the  blower  base and the sound enclosure to provide grounding for the entire package.  

J. The discharge silencer shall have connection for a drain. 

2.04 INLET AND DISCHARGE FLEXIBLE CONNECTORS  

A. Each  package  shall  be  connected  to  the  plant  piping  via  a  flexible  connector located downstream of the discharge silencer. Flexible connectors shall prevent the  transmission  of  noise  and  vibrations  from  the  blower  package  into  the piping.   

B. Flexible connectors shall be a silicone or reinforced sleeve secured with four (4) stainless steel sleeve clamps.  The process connection will terminate with metal ANSI flange “stub pipe”, axially restrained by the external process piping. 

Page 192: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 8   

C. The  flexible  connectors  shall  be  Unaflex  “Supreme”  Style  189,  with  standard ANSI flange connections, or Engineer‐approved equal. 

D. Minimum  temperature  rating  shall  be  300  degrees  F,  and  minimum  working pressure rating shall be 25 psig.   

2.05 ELECTRIC MOTOR 

A. Motor  shall  comply  with  Specification  Section  43  05  93,  Common  Motor Requirements for Process Equipment. 

B. Type:  Chemical Industry‐Severe Duty (CISD‐TEFC) and Inverter Duty 

C. Efficiency: Premium Efficient per NEMA MG 1 

D. Speed, maximum: 1,800 RPM 

E. Electrical service: 460 Volts, 3 Phase, 60 Hertz current 

F. Torque rating: NEMA B 

G. Speed Range, minimum: 3:1 constant torque 

H. Duty cycle: continuous 

I. F3 top mounted conduit box 

J. Frame type/size: NEMA standard suitable for overhung belt drive  

K. Base: Pivoting to provide automatic tensioning of the belts 

L. Motor Size, minimum: 125 HP 

M. The motor nominal rating after any corrections  for ambient conditions shall be 10% above the maximum operating bHP.   

N. Blower manufacturer  shall  be  responsible  for  coordinating  the  starting  torque requirement of the blower and the motor. 

2.06 V‐BELT DRIVE 

A. Each  package  shall  be  supplied  with  a  v‐belt  drive  that  shall  be  of  the  high capacity type, oil and heat resistant.  

B. Drive shall be designed for a minimum service factor of 1.4 times the maximum operating BHP, or 1.1 times the motor nameplate HP, whichever is larger.   

Page 193: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 9   

C. Belt tensioning shall be automatic without the use of any devices or interaction on the part of the operator.  

D. Sheaves  shall  be  dynamically  balanced  regardless  of  the  operating  speed. Sheaves shall be interchangeable for speed adjustment. 

E. The belt tension device shall be designed to allow the maintenance personnel to replace the belts without exerting or lifting over 40 pounds and without the use of lifting, jacking or pulling tools.  

F. V‐belts shall be banded. 

2.07 V‐BELT GUARD  

A. The belt drive shall be guarded in compliance with OSHA regulations.  

B. Portions of the guard shall be easily removable allowing for belt inspection and replacement.  

C. Guard material shall be perforated or sheet carbon steel. 

2.08 VIBRATION ISOLATION  

A. Each  package  shall  be  supplied  with  vibration  isolating  feet  with  a  minimum efficiency of 80%.   

B. Blower manufacture shall be  responsible  for attenuating noise and vibration  in the blower package such that no special  installation base shall be required, nor shall any additional measures be required to reduce vibrations from the blower package being transmitted to the base or the piping. 

2.09 PRESSURE RELIEF VALVE  

A. Each package shall be supplied with a single pressure safety relief valve on the discharge side of the blower mounted downstream of the discharge silencer and upstream of the check valve.   

B. The safety valve shall be set to protect the blower from exceeding its maximum pressure rating, and shall be sized to pass 100% of the design flow.   

C. The safety valve shall be field adjustable and spring loaded.   

D. The pressure relief valve shall be housed by the sound enclosure and shall relieve into  a  segmented  section  of  the  sound  enclosure  or  outside  of  the  sound enclosure.  

Page 194: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 10   

E. Valve shall be stainless steel or carbon steel, suitable for the maximum discharge temperature of the blower.  

F. Valve  shall  be  preset  to  a  Manufacturer‐selected  pressure  setting  above  the maximum operating pressure to protect the blower and accessories from over‐pressurization.  

G. Manufacturer: Kunkle or Engineer‐approved equal. 

2.010 CHECK VALVE  

A. Each package shall be supplied with one check valve that shall be installed on the discharge line.   

B. The check valve shall be of the full‐bore, low pressure‐drop, flapper type design with a stainless steel body, and steel flap embedded in silicone with full‐contact seal.   

C. The check valve flap shall be removable without disturbing the piping.  

D. Pressure  losses  produced  by  the  check  valve  shall  be  included  in  the  blower performance calculation.  

E. Check valve shall be gas tight at 15 psig. 

F. Check valve have a temperature rating of 300 degrees F. 

2.011 PRESSURE MEASUREMENT DEVICES 

A. Inlet Vacuum Gauge 

1. Provide a differential pressure vacuum gauge on the inlet of each blower. 

2. Gauge shall function as a filter maintenance indicator. 

3. Manufacturer and Model: Dwyer model 2040 or Engineer‐approved equal 

4. Accuracy: 2% full scale 

5. Range: ‐40 to 0 inches water column 

6. Dial size: 4 inch 

7. Temperature limits: 20 to 140 deg F 

8. Enclosure rating: IP67 

Page 195: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 11   

9. Case: Open front 

10. Case material: Die cast aluminum case with acrylic cover 

11. Dial: Aluminum, white background, black figures and graduations 

12. Connection location: Duplicate side and back, high and low pressure taps 

13. Accessories: Air filter gauge accessory kit with isolation valves 

14. Gauge dial face shall be mounted on the acoustic enclosure. 

B. Discharge Pressure Gauge 

1. Provide a pressure gauge on the discharge of each blower.  

2. Manufacturer and Model: Ashcroft Type T5500 or Engineer‐approved equal.  

3. Per ASME B40.100, the full scale pressure range shall be approximately twice the normal operating pressure. The maximum operating pressure should not exceed approximately 75% of the full scale range.  

4. Accuracy: 1% full scale (Grade A, ASME B40.100) 

5. Range: 0 – 20 psi 

6. Dial size: 4 inch  

7. Case: Open front 

8. Case material: Stainless steel 

9. Weather protection: Dry Case IP54 

10. Ring type: Stainless steel, bayonet  

11. Window: Shatterproof glass 

12. Dial: Aluminum, white background, black figures and graduations. 

13. Pointer: Micrometer adjustable 

14. Movement: 400 SS (conventional) 

15. Bourdon tube and socket: Stainless steel 

16. Ambient temperature: ‐20 to 200 deg F 

Page 196: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 12   

17. Process temperature: ‐20 to 250 deg F or the maximum discharge temperature of the blower whichever is greater 

18. Gauge shutoff cocks: Stainless steel 

19. Pulsation dampener: Stainless steel, glycerin‐filled 

20. Gauge dial face shall be mounted on the acoustic enclosure. 

C. Discharge High Pressure Switch 

1. Provide a discharge pressure switch on the discharge of each blower to protect the blower from excessive operating pressure. 

2. Manufacturer and Model: Ashcroft B‐Series or G‐Series, Type 400, or Engineer‐approved equal. 

3. Operating range, inlet: ‐30 to 30 inches of water column (w.c.) 

4. Operating range, discharge: 0 to 15 psig 

5. Pressure setting range: between 15 and 100% of operating range 

6. Factory adjusted setpoint (XFS), vacuum: ‐20 inches w.c., decreasing, Manufacturer to confirm proper setpoint. 

7. Enclosure: NEMA 4X 

8. Housing: Epoxy coated aluminum 

9. Actuator Seal, inlet: Buna‐N 

10. Actuator Seal, discharge: Viton 

11. Process temperature, inlet: 0 to 150 deg F 

12. Process temperature, discharge: 20 to 300 deg F or the maximum discharge temperature of the blower, whichever is greater 

13. Ambient temperature: ‐20 to 150 deg F 

14. Output signal: Two (2) (dual) SPDT 15A, 125/250/480 Vac (not independently adjustable) 

15. Influence of ambient temperature: ± 1% of full scale/50 deg F temperature change 

Page 197: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 13   

16. Mounting bracket: Furnish as required. 

D. Discharge Pressure Transmitter 

1. Provide discharge pressure transmitter on the discharge of each blower. 

2. Manufacturer and Model: Huba Control Model 511, or Engineer‐approved equal. 

3. Pressure range: 0 to 15 psi 

4. Process connection: 1/4” male thread NPT, 303 series stainless steel 

5. Protection Standard: IP65 

6. Housing material: 303 series stainless steel 

7. Measuring cell: Ceramic 

8. Media stopper: Polyphenylene sulfide (PPS) 

9. Seal material: Fluoro‐elastomer (FPM) 

10. Process temperature: 5 to 257 °F, or the maximum discharge temperature of the blower, whichever is greater 

11. Ambient temperature: 0 ‐ 185 °F 

12. Output signal: 4 to 20 mA 

13. Power supply: 8 to 33 VDC  

14. Accuracy: ± 0.5% of full scale 

15. Long‐term drift: ≤ 1% of full scale 

16. Influence of ambient temperature: ≤ 0.15% of full scale/10 deg K of temperature change 

17. Provide isolation valve and pulsation dampener.  

2.012 TEMPERATURE MEASUREMENT DEVICES 

A. Discharge Temperature Gauge/Switch 

1. Provide discharge temperature gauge and switch on the discharge of each blower. 

Page 198: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 14   

2. Manufacturer and Model:  

a. Jumo panel‐mounted combination gauge/switch 

b. Engineer‐approved equal 

3. Process temperature range, minimum: 50 to 500 deg F  

4. Ambient temperature: 0 to 160 deg F 

5. Protection/enclosure: IP65/NEMA 4 

6. Display case material: Stainless steel 

7. Dial size: 4 inch  

8. Window: Shatterproof glass or polycarbonate 

9. Display: Aluminum, white background, black figures and graduations 

10. Mounting: Direct or bayonet connection 

11. Stem material: 316 stainless steel 

12. Output: Two (2) (dual) SPDT switches, 15A or 5A, 125/250 Vac  

13. Accuracy: ± 1.0% of full scale 

14. Accessories: 316 stainless steel thermowell 

2.013 TERMINAL STRIP 

A. The switches, transducer transmitters, and motor thermostat shall be prewired to a labeled terminal junction box inside the blower enclosure. 

2.014 ACOUSTICAL SOUND ENCLOSURE 

A. Each  package  shall  be  supplied  with  a  sound  enclosure  covering  the  entire blower package.   

B. The enclosure shall be designed so as to be able to  install  the blowers side‐by‐side with all maintenance performed from the front or back of the package.   

C. Panels shall be made of galvanized steel sheet, powder coated.  The skid shall be the same color as the sheet.  

D. Sound enclosure acoustic material shall comply with UL94‐HF1 for fire‐retardant, self‐extinguishing, non‐dripping materials. 

Page 199: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 15   

E. The enclosure and the blower package must be both mounted on a skid.  Fork lift channels shall be included to allow for easy transportation and installation. 

F. A grounding strap shall be  installed between the blower base and the package skid to bypass any vibration isolating mounts. 

G. Quick  release  panels,  each  less  than  40  pounds, must  provide  easy  and  quick access for routine maintenance of the blower and the package components. 

H. A high efficiency ventilation fan shall provide ventilation and cooling integral to the sound enclosure.  Cooling fan shall be sized for sufficient heat removal from the  sound  enclosure,  even  when  the  blower  is  operated  with  a  variable frequency drive. The cooling  fan  shall be  independently powered separately  to continue to cool the blower, even if the main blower motor is not running. 

I. Electrical components, instrumentation and instrument connections shall not be mounted or interface with moving panels of the sound enclosure. 

J. Blower  oil  sumps  shall  be  piped  to  fill  and  drain,  located  at  the  front  of  the package  for  easy  maintenance.  Oil  level  indicator(s)  shall  be  mounted  on  the outside of  the enclosure, which gives an accurate oil  level  indication while  the blower is in operation. All oil lines shall be hydraulic hose with fittings. No plastic tubing with compression fittings are allowed. 

K. Blower  system,  including  silencers  and  sound  attenuating  housing,  shall  be designed  for  operation  at  noise  level  not  to  exceed  80  dB(A)  at  3  ft  from  the blower assembly in any direction in free‐field conditions. If special equipment for cooling and/or noise attenuation is required,  it shall be provided by the blower manufacturer. 

2.015 COATINGS 

A. Coatings shall be per supplier’s standard complying with the following criteria.  

B. Excepted  for machined  sealing  and machined mounting  surfaces,  the  package shall be painted.   

C. Aluminum, stainless steel, and brass shall not be painted.   

D. The  supplied  motor  shall  not  be  over  sprayed  and  will  be  supplied  with  the motor manufacturer’s standard protection and paint color.   

E. Painted cast iron and carbon steel shall be alkyd resin or epoxy primer and final coat with a minimum total dry film thickness of 70 µm. Surface preparation shall be SSPC10 or better.   

Page 200: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 16   

F. Sound enclosure shall be powder‐coated polyester base total dry film thickness 80 µm with a process to be proven to pass 500‐hour salt spray test satisfactory with no rust evidence.  

G. Galvanized  components  may  only  be  painted  with  appropriate  surface preparation. Equipment shall be touched up in the field as required. 

2.016 DATA PLATES   

A. All data plates shall be furnished per Section 01 60 00.  

2.017 HARDWARE 

A. Hardware shall be furnished per Section 01 60 00. 

2.018 SPECIAL TOOLS AND SPARE PARTS  

A. Furnish the following spare parts and supplies: 

1. One (1) spare set of sheaves  

2. One (1) spare set of V‐belts  

3. Three (3) spare inlet filter elements  

4. One (1) spare set of shaft seals and gaskets 

5. Two (2) gallons manufacturer’s standard synthetic oil. Each blower shall receive it initial oil filling at the factory. 

6. Other manufacturer recommended spare parts. 

B. Spare  parts  shall  be  packaged  in  accordance  with  Section  01  60  00,  Product Requirements. 

PART 3 EXECUTION 

3.01 FACTORY TESTS  

A. Each blower stage shall be factory tested in accordance with ISO 1217 to verify flow  and  brake  horsepower  at  the  specified  blower  maximum  operating conditions.  Performance shall be within +/‐ 5% of specified operating conditions.  

B. A  package mechanical  run  test  at  the  specified maximum  speed  and  pressure shall  be  performed  for  a  minimum  of  three  (3)  hours  on  each  blower  to document that the blower has achieved the specified performance.  

Page 201: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 17   

C. A  noise  test  shall  be  performed  in  accordance  with  ISO  2151‐2004,  sound pressure  level  only,  with  +/‐  3  dBa  tolerance.  The  measurements  shall  be calculated to a free field environment.   

D. Motor shall be factory tested in accordance with Section 40 05 93. 

E. Manufacturer shall submit certified curves and certified copies of the factory test reports to the Engineer prior to shipment per Section 01 33 00. 

3.02 PRODUCT SHIPMENT AND PROTECTION 

A. The  equipment  specified  herein  shall  be  packaged  and  shipped  in  accordance with Section 01 60 00, Product Requirements. 

3.03 INSTALLATION 

A. Installing Contractor  shall  install  the  equipment  specified herein  in  accordance with the Manufacturer's recommendations and as shown on the Drawings.    

B. Manufacturer’s  representative  shall  inspect  the  installation  as  specified  in Specification  Section  01  75  00,  Testing  and  Commissioning  and  as  specified herein. 

C. Manufacturer’s  qualified  service  representative  shall  provide  a  minimum  of  8 hours for installation inspection.  

D. Manufacturer’s  installation  inspection shall at minimum consist of verifying the following: 

1. Installation is in accordance with Manufacturer’s installation checklist and recommendations. 

2. Blower and motor nameplate data matches approved submittal. 

3. Concrete foundation is even and base alignment has been checked and leveled with alignment plates. 

4. Base is properly anchored (and grouted if required). 

5. The enclosure and base frame are properly grounded. 

6. Blower and motor alignment is checked and adjusted as required. 

7. Pipes and equipment are properly supported and secured. 

8. Valves are properly installed. Check valve flap moves freely. Pressure relief valve is properly set. 

Page 202: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 18   

9. Flexible couplings are provided in piping where required. 

10. Piping is properly cleaned and pressure tested. 

11. Oil levels in sight glass and at the blower are at proper levels. 

12. Blower rotational direction is correct. 

13. V‐belt tension is within the recommended range and v‐belt guard is installed. 

14. Insulation strips are installed at the exhaust duct and the foam mat is placed in the acoustic hood, as required. 

15. The fan for the acoustic hood moves freely. 

16. Instrumentation is properly installed, secured, and wired to control system. Pulsation dampeners, isolation valves, and thermowells are installed where required. 

17. Motor is properly installed in accordance with Section 40 05 93 and motor manufacturer’s instructions. 

3.04 FIELD TESTING 

A. On‐site  field  testing  shall  comply  with  the  requirements  of  Section  01  75  00, Testing and Commissioning.  Testing shall also include: 

1. Testing the emergency stop switch for automatic shutdown. 

2. Testing the inlet high vacuum and discharge high pressure switches for automatic shutdown. 

3. Testing the discharge high temperature switch contacts. 

4. Verifying that the discharge pressure transmitter signals correspond with gauge readings. 

5. Testing the motor thermostat contacts. 

6. Testing the motor current overload setting for automatic shutdown. 

7. Testing the discharge pressure relief valve for the proper setting. 

8. Measuring the speed, inlet vacuum, discharge pressure, air flow, temperature, rotor speed, noise level, motor current, and voltage at a minimum of four speeds within the blower performance range, including 

Page 203: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 19   

the minimum and maximum specified operating conditions. Noise levels shall be measured with a sound level meter that is properly calibrated and complies with the accuracy requirements of OSHA’s noise standard, 29 CFR 1910.95. Each blower shall be operated a minimum of 4 hours during the testing.  

9. Measuring the vibration of the blower and motor at the minimum and maximum specified operating conditions. 

10. Documenting Manufacturer’s recommended variable frequency drive settings including the minimum speed setting, current overload setting, and motor acceleration and deceleration intervals. 

B. Motor field testing shall comply with Section 40 05 93.  

C. Noise  test:  Noise  attenuation  provisions  shall  be  tested  in  the  field  by  the Manufacturer’s  qualified  service  representative.  Engineer  shall  witness  test. Unsatisfactory compliance shall be corrected. 

D. Manufacturer’s  service  representative  shall  certify  the  installation  and  field testing  in  accordance  with  Section  01  75  00,  Testing  and  Commissioning Procedures, and shall submit the completed Certificate of  Installation and Field Testing Form at the end of this Section. 

E. Manufacturer’s  qualified  service  representative  shall  provide  a minimum of  12 hours of on‐site testing of the blowers – 4 hours per blower. 

3.05 TRAINING  

A. Manufacturer’s  qualified  service  representative  shall  provide  a  minimum  of  4 hours of training of the Owner’s staff  in the operation and maintenance of the equipment specified herein.  

B. Training shall meet the requirements of 01 79 00, Training. 

*** END OF SECTION *** 

Page 204: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐43 11 33 Rotary Lobe Blowers.doc    43 11 33 ‐ 20   

FORM 43 11 33‐1 CERTIFICATE OF INSTALLATION AND TESTING OF BLOWERS MANUFACTURER NAME:   PROJECT NAME:  

EQUIPMENT SCHEDULE NO.:  NAME OF EQUIPMENT: 

LOCATION/SERVICE:  SPECIFICATION SECTION: 

MANUFACTURER:  DISCHARGE SIZE (INCHES): 

MODEL NUMBER:  SERIAL NO.: 

AIR FLOW (CFM):  DELTA PRESSURE (PSI):  BLOWER RPM:  GEAR SIZE (INCHES): 

MOTOR HP:  VOLTS:  HERTZ:  PHASE: 

FLA:  MOTOR RPM:  SERVICE FACTOR:  MOTOR EFFICIENCY: 

INSTALLATION INSPECTION (CHECK IF VERIFIED) 

PIPE/EQUIPMENT SUPPORTS:  PIPE CLEANED:  PIPE PRESSURE TESTED/ TEST PRESSURE: 

PRESSURE RELIEF VALVE SETTING 

BASE ANCHORED/ GROUTED/LEVEL: 

PRESSURE/TEMP GAUGES:  EXPANSION COUPLINGS:  CHECK VALVE: 

SHAFT ALIGNMENT:  LUBRICATION:  PROPER ROTATION:  V‐BELT TENSION: 

SUPPLY VOLTAGE:  MOTOR/ENCLOSURE GROUNDING: 

GUARDS/SAFETY:  ENCLOSURE INTEGRITY/ VENTILATION: 

PERFORMANCE TEST 

SPEED 

INLET PRESSURE (PSI/IN.) 

DISCHARGE PRESSURE (GAUGE) (PSI/IN.) 

DISCHARGE PRESSURE 

(TRANSDUCER) (PSI/IN.) 

DISCHARGE AIR FLOW (CFM) 

DISCHARGE TEMP. (DEG. F) 

BLOWER SPEED (RPM) 

NOISE (DBA) 

CURRENT (AMPS) 

VOLTAGE (VOLTS) 

0% (STATIC)        0    0    

0   

MIN.                   

50% /30 HZ                   

75% /45 HZ                   

100%/60 HZ                   VIBRATION TESTS AND SAFETY SWITCHES  VFD SETTINGS 

BLOWER MAX. VIBRATION (IN/S RMS):    VFD MINIMUM SPEED SETTING (HZ):   

MOTOR MAX. VIBRATION (IN/S RMS):    VFD OVERLOAD SETTING (AMPS):   

E‐STOP SWITCH TAG NO.:    VFD TIME TO ACCELERATION SETTING (S):   

E‐STOP SWITCH SHUT OFF/ALARM CHECK:    VFD TIME TO DECELERATION SETTING (S):   

DISCHARGE PRESSURE SWITCH TAG. NO.    DISCHARGE TEMPERATURE SWITCH TAG. NO.:   

PRESSURE SWITCH SHUT OFF/ALARM CHECK:   TEMPERATURE SWITCH SHUT OFF/ALARM CHECK 

 

 SELLER/MANUFACTURER  

CHECK OFF  INSTALLER CHECK OFF  WITNESS CHECK OFF 

NAME       

SIGNATURE       

DATE       

 

Page 205: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 1

SECTION 43 25 00 SUBMERSIBLE SCREW CENTRIFUGAL PUMPS

PART 1 GENERAL

1.01 DESCRIPTION OF WORK

A. Manufacturer shall furnish three (3) wet pit screw centrifugal pumps, with motors, discharge elbows, sliding guide brackets, discharge flanges, and lifting chain/cables and all appurtenances as specified herein.

B. The work shall include fabrication, factory testing, delivery, installation inspection, field testing, certification of installation and field testing, and training.

1.02 RELATED WORK

A. Division 0 – Bid Documents

B. Division 1 – General Requirements

C. Section 40 05 93 - Common Motor Requirements for Process Equipment

1.03 REFERENCE STANDARDS

A. American Iron and Steel Institute/Society of Automotive Engineers (AISI/SAE)

1. AISI/SAE 316 (UNS S31600) – 316 Stainless Steel

2. AISI/SAE 316L (UNS S31603) – 316L Stainless Steel

B. American National Standards Institute (ANSI)

1. ANSI/ASME B16.1 - Gray Iron Pipe Flanges and Flanged Fittings

C. American Society for Testing and Materials (ASTM)

1. ASTM A48 - Specification for Gray Iron Castings

2. ASTM A532 / A532M - Standard Specification for Abrasion-Resistant Cast Irons

D. Hydraulic Institute (HI/ANSI)

1. HI/ANSI 9.6.4 - Rotodynamic Pumps for Vibration Analysis and Allowable Values

Page 206: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 2

2. HI/ANSI 14.6 - Rotodynamic Pumps for Hydraulic Performance Acceptance Tests

3. HIC - Hydraulic Institute Test Code

E. Society for Protective Coatings (SSPC)

1. SSPC-SP 10 - Near-White Metal Blast Cleaning

1.04 SUBMITTALS

A. Furnish submittals in accordance with Section 01 33 00, Submittal Procedures and including:

1. Shop Drawings and Product Data.

2. Performance curves showing capacity in gallons per minute (GPM), net positive suction head (NPSH), total dynamic head, and pump horsepower from 0 GPM to 110 percent of design capacity.

3. Product data on all accessories including discharge elbows, sliding guide brackets, discharge flanges, access frames and guides.

4. Submittal data on motors as required in Section 40 05 93, Common Motor Requirements for Process Equipment.

B. Certified Factory Test Reports as specified herein.

C. Bill of Materials per Section 01 33 00.

D. Manufacturer's warranties as specified herein.

E. Operation and Maintenance Manuals: Furnish in accordance with Section 01 78 00, Close-Out Submittals.

1.05 QUALIFICATIONS

A. The manufacturer of the products specified in the Section shall be fully experienced, qualified, and reputable in the manufacture of such equipment.

B. The manufacturer shall have at least 50 installations in the United States of the model specified in satisfactory operation for at least 10 years.

C. Manufacturer shall have a qualified factory-trained representative and service center qualified in repair of the pumps permanently located within a 300-mile radius of the project site.

Page 207: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 3

1.06 WARRANTY

A. Manufacturer shall warrant the materials and equipment specified herein to be free of defects in materials and workmanship for a minimum period of two (2) years from the Date of Manufacturer’s Certificate of Installation and Field Testing.

PART 2 PRODUCTS 2.01 MANUFACTURER

A. Hayward Gordon, Ontario, Canada, XCS Series Immersible

B. Hidrostal Pumps, Aurora, IL, E5K Series Immersible

C. Engineer-approved equal. Refer to Section 00 20 00 Instructions to Bidders Article 10 for procedure for approval.

2.02 PERFORMANCE CRITERIA

A. Provide pumps as specified herein and shown on the drawings:

1. Pump Schedule Number P-A-MLR-1,-2,-3

2. Capacity at TDH, GPM 883

3. Total Dynamic Head, feet 30

4. Suction and Discharge Size, inches 6

5. Impeller Speed, RPM, maximum 1,500

6. Motor Horsepower, minimum 10

7. Power 3 Phase, 60 Cycle, 480 Volt

8. Minimum B-10 Bearing Life, hours 100,000

2.03 DESIGN

A. Pumps shall be heavy-duty construction for continuous operation.

B. Type: single passage, clog free pump, screw centrifugal impeller.

C. Solids: Passes 3-inch solids, conveys rags or other fibrous material without clogging.

Page 208: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 4

D. The leading edge of the impeller vane shall blend into the impeller body in such a way that any rag or other fibrous material caught on the leading edge and folded over both sides of the vane will be unfolded and released as the textile follows the flow-stream through the pump.

E. The impeller flange or impeller shall contain a spiral groove on the rear face so that any solids in the pumped media are discharged from the space between the backplate and the rear of the impeller.

F. Geometry of the impeller and suction piece shall be conical.

G. Suction and discharge flanges: ANSI Class 125-lb.

H. Sealing. All mating surfaces in pump casing and in motor housing shall be machined and fitted with nitrile O-rings for watertight seal.

2.04 MATERIALS OF CONSTRUCTION

A. Pump volute, backplate and suction piece housing: Cast iron, ASTM A48 Class 30.

B. Impeller: High chrome iron, ASTM A532 Class III Type A1, minimum 450 Brinell hardness.

C. Liner: Replaceable, High chrome iron, ASTM A532 Class III Type A1, minimum 450 Brinell hardness, externally adjustable by stainless steel regulating screws or shims.

2.05 IMMERSIBLE MOTOR

A. Explosion-proof design, approved by Factory Mutual for uses in Class I, Groups C&D, hazardous locations.

B. Type: Immersible, inverter duty

C. Service: Full-load, continuous operation either completely dry or fully submerged in the pumped liquid of up to 65-foot depths.

D. Motor housing: "Air-filled", watertight

E. Cooling system: Heat-exchanger with a shaft-mounted cooling pump circulating oil from a jacket surrounding the stator housing to a heat-exchanger surface cast into the pump backplate. The circulating oil shall transfer excess motor heat directly to the pumped media inside the pump volute, without the need of submergence for motor cooling. The circulating oil shall provide adequate motor cooling at any continuous power output up to and including rated powers in an ambient temperature of up to 40 degrees C.

Page 209: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 5

F. Alternately, motors shall dissipate heat directly by convection from the exposed stator housing to surrounding ambient air, without the need of submergence. The motor surface shall be sized for adequate motor cooling at any continuous power output up to and including rated power in an ambient temperature of up to 40 degrees C.

G. Motor stator windings and leads shall be insulated with moisture-resistant Class F insulation for operation at temperatures up to 155 degrees Celsius.

H. Motors shall have the stator varnish applied by the "vacuum-pressure impregnation" method to ensure thorough and complete varnish penetration. The stator shall be heat-shrink fitted into the stator housing.

I. Motor cable-entry sealing assembly shall consist of the following five components to ensure a positive, redundantly watertight seal:

1. The sealing components shall be mechanically isolated from cable strains by a two-piece restraining clamp, which will securely grip the cable above the moisture-sealing components and bear any mechanical forces applied to the cable.

2. The cable moisture seal shall consist of an elastomer grommet, prevented from extruding past the cable by stainless-steel retaining washers on either side. The grommet shall be compressed tightly against the cable outside diameter (and the entry assembly inner diameter) by a screwed follower gland.

3. Each individual conductor shall be interrupted by a solid-copper isolation dam to prevent wicking of moisture through the conductor strands.

4. The cable insulation shall be sealed by an epoxy poured into the cable entry and totally encapsulating the stripped-back insulation and the individual copper dams. This poured epoxy seal shall also function as a redundant seal for the cable outside diameter.

5. The cable free end shall be sealed from moisture-entry during shipping, storage, and prior to connection to the control panel by a plastic sleeve securely clamped over the cable end.

J. Shaft sealing shall be by independently-mounted, tandem mechanical seals contained in an oil chamber that is formed as an intrinsic part of the motor frame and allows the seals to be completely submerged in and lubricated by the oil bath.

1. The mechanical seal nearest the bearing shall utilize carbon/ceramic faces, and shall isolate the seal cooling oil from the motor frame.

Page 210: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 6

2. The mechanical seal nearest the impeller shall be a stainless steel or rubber bellows-type construction firmly attached to the rotating face and clamped to the shaft, to prevent contaminants from contacting the stainless-steel spring which loads the seal face. The seal faces shall be a solid tungsten-carbide rotating face running against a solid silicon-carbide stationary face.

3. The mechanical seal nearest the impeller shall be contained in a seal chamber formed by the impeller flange and a recess cast into the motor frame. To prevent debris from entering the chamber and to prolong the mechanical seal life, a flush port shall be provided so that an optional external water flush can be supplied directly into the seal chamber.

4. The mechanical seal nearest the impeller shall be isolated from contaminants in the pumped media by a labyrinth-fit between the backside of the impeller and the backplate, as well as by pump-out grooves cast into the impeller back shroud and into the backplate, to minimize debris reaching the shaft seal.

K. The thrust bearings shall be designed to take the full axial load of the impeller.

L. Motors shall comply with Section 40 05 93.

M. Protection Devices:

1. Three thermistor type thermal sensors embedded in the stator windings, wired in parallel to an external relay.

2. Conductivity probe to monitor the moisture content of the oil in the chamber between the outer and the inner mechanical seals wired to a separate protective circuit.

2.06 MOUNTING AND RETRIEVAL

A. Fast Out: Pump cantilevered from discharge flange above floor and supported with:

1. 316 stainless steel base and anchor bolts.

2. 90-degree cast iron elbow with ANSI Class 125-pound flange.

3. Mounts for two stainless steel rails of schedule 40 pipe (provided by others), which will guide the pump into position.

4. Metal-to-metal interlocking guide shoe flange sealed by a leakproof nitrile rubber ring.

Page 211: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 7

B. Each pump shall be fitted with a minimum of 30 feet of stainless steel lifting chain or cable. The working load of the lifting system shall be 50 percent greater than the pump unit weight.

2.07 COATING

A. Exposed cast iron components shall receive surface preparation per SSPC-SP-10 followed by:

1. Primer, open recoat window, Tnemec Series 1 Omnithane Primer, 2.5 - 3.5 mils dry film thickness.

2. First coating: Moisture cure urethane, Tnemec Series 446 PermaShield MCU, 7.0 - 10.0 mils dry film thickness.

3. Second coating: Moisture cure urethane, Tnemec Series 446 PermaShield MCU, 7.0 - 10.0 mils dry film thickness.

B. Alternate coating systems of equivalent performance and thickness may be submitted to the Engineer for approval.

2.08 DATA PLATES

A. All data plates shall be furnished per Section 01 60 00.

2.09 HARDWARE

A. Hardware shall comply with Section 01 60 00 where applicable. All exposed hardware shall be AISI 316/316L stainless steel.

2.010 SPARE PARTS

A. One (1) set of Manufacturer’s standard spare parts shall be furnished.

PART 3 EXECUTION

3.01 FACTORY TESTS

A. The pumps and motors shall be given an operational and factory performance test in accordance with Hydraulic Institute Standard HI/ANSI 14.6.

B. Motor shall be factory tested in accordance with Section 40 05 93.

C. Manufacturer shall submit certified curves and certified copies of the factory test reports to the Engineer prior to shipment per Section 01 33 00.

3.02 PRODUCT SHIPMENT AND PROTECTION

Page 212: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 8

A. The equipment specified herein shall be packaged and shipped in accordance with Section 01 60 00, Product Requirements.

3.03 INSTALLATION

A. Installing Contractor shall install the equipment specified herein in accordance with the Manufacturer's recommendations and as shown on the Drawings.

B. Manufacturer’s representative shall inspect the installation as specified in Specification Section 01 75 00, Testing and Commissioning and shall also verify:

1. Pump base and discharge elbow are properly installed, grouted, secure, and anchor bolts tightened.

2. Discharge piping is properly supported separate from pump.

C. Manufacturer’s qualified service representative shall provide a minimum of 2 hours for installation inspection.

3.04 FIELD TESTING

A. On-site field testing shall comply with the requirements of Section 01 75 00, Testing and Commissioning. Testing shall also include:

1. Testing the motor thermistor and conductivity probe contacts.

2. Testing the motor current overload setting for automatic shutdown.

3. Testing the high and low level switches for shut off and alarm indication.

4. Measuring the speed, discharge pressure, flow, motor current, and voltage at a minimum of four speeds within the pump performance range, including the minimum and maximum specified operating conditions.

5. Documenting Manufacturer’s recommended variable frequency drive settings including the minimum speed setting, current overload setting, and motor acceleration and deceleration intervals.

B. Motor field testing shall comply with Section 40 05 93.

C. Manufacturer’s service representative shall certify the installation and field testing in accordance with Section 01 75 00, Testing and Commissioning Procedures, and shall submit the completed Certificate of Installation and Field Testing Form at the end of this Section.

Page 213: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 9

D. Manufacturer’s qualified service representative shall provide a minimum of 4 hours of on-site testing of the pumps.

3.05 TRAINING

A. Manufacturer’s qualified service representative shall provide a minimum of 2 hours of training of the Owner’s staff in the operation and maintenance of the equipment specified herein.

B. Training shall meet the requirements of Section 01 79 00, Training.

*** END OF SECTION ***

Page 214: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-43 25 00 Submersible Screw Centrifugal Pumps.doc 43 25 00 - 10

FORM 43 25 00-1 CERTIFICATE OF INSTALLATION AND TESTING OF SUBMERSIBLE SCREW CENTRIFUGAL PUMPS

SELLER NAME: PROJECT NAME:

EQUIPMENT SCHEDULE NO.: NAME OF EQUIPMENT:

LOCATION/SERVICE: SPECIFICATION SECTION:

MANUFACTURER: SUCTION/DISCHARGE SIZE (INCHES):

MODEL NUMBER: SERIAL NO.:

DESIGN FLOW (GPM): TDH (FEET/PSI): PUMP RPM: IMPELLER SIZE (INCHES):

MOTOR HP: VOLTS: HERTZ: PHASE:

FLA: MOTOR RPM: SERVICE FACTOR: MOTOR EFFICIENCY:

INSTALLATION INSPECTION (CHECK IF VERIFIED) PIPE SUPPORTS: PIPE FLUSHED: PRESSURE TEST: TEST PRESSURE: BASE ANCHORED/ GROUTED: PRESSURE GAUGES: ISOLATION/CHECK VALVES: PROPER ROTATION:

LUBRICATION: PUMP DISCHARGE SHOE FLANGE SEALED:

PUMP DISCHARGE FLANGE AND GUIDERAILS SECURE:

CONDUCTIVITY PROBE:

SUPPLY VOLTAGE: MOTOR GROUNDING: MOTOR THERMISTOR: OTHER:

MISSING OR DAMAGED PARTS/TOOLS (LIST):

PERFORMANCE TEST

SPEED

INLET PRESSURE

GAUGE (PSI/FT)

DISCHARGE PRESSURE

GAUGE (PSI/FT)

DISCHARGE FLOW (GPM)

PUMP SPEED (RPM)

VFD OUTPUT

CURRENT (AMPS)

VFD OUTPUT

VOLTAGE (VOLTS)

0% (STATIC) N/A 0 0 0 0

MIN. N/A

50% / 30 HZ N/A

75% / 45 HZ N/A

100% / 60 HZ N/A PUMP/MOTOR VIBRATION TEST VFD SETTINGS

HIGH LEVEL SWITCH TAG NO.: VFD MINIMUM SPEED SETTING (HZ):

SWITCH SHUT OFF/ALARM CHECK: VFD OVERLOAD SETTING (AMPS):

LOW LEVEL SWITCH TAG NO.: VFD TIME TO ACCELERATION SETTING (S):

SWITCH SHUT OFF/ALARM CHECK: VFD TIME TO DECELERATION SETTING (S):

As the Manufacturer’s Representative, I certify that I have inspected the installation of the equipment, the equipment has been installed in accordance with the manufacturer's recommendations, I have witnessed all applicable field tests, all proper adjustments have been made, the equipment meets the performance requirements of the Contract Specifications, and the equipment is ready for plant commissioning and operation.

MANUFACTURER’S REP CHECK OFF CONTRACTOR CHECK OFF WITNESS CHECK OFF

NAME

SIGNATURE

DATE

Page 215: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 1   

SECTION 46 21 33 IN‐CHANNEL ROTARY DRUM SCREEN 

 PART 1 GENERAL 

 1.01 DESCRIPTION OF WORK 

A. Manufacturer shall furnish one (1) in‐channel rotary drum screen. 

B. The  work  shall  include  fabrication,  factory‐testing,  delivery,  installation inspection,  field  testing,  certification  of  installation  and  field  testing,  and training. 

1.02 RELATED WORK 

A. Division 0 – Bid Documents 

B. Division 1 – General Requirements  

C. Section 40 05 93 ‐ Common Motor Requirements for Process Equipment 

1.03 REFERENCE STANDARDS 

A. The work in this section is subject to the requirements of applicable provisions of the following standards: 

B. American Gear Manufacturers Association (AGMA) 

C. AISI/SAE – American Iron and Steel Institute/Society of Automotive Engineers 

1. AISI/SAE 316 (UNS S31600) – 316 Stainless Steel 

2. AISI/SAE 316L (UNS S31603) – 316L Stainless Steel 

D. ASTM ‐ American Society for Testing and Materials 

1. ASTM  A193  ‐  Standard  Specification  for  Alloy‐Steel  and  Stainless  Steel Bolting for High Temperature or High Pressure Service and Other Special Purpose Applications 

2. ASTM A276 ‐ Standard Specification for Stainless Steel Bars and Shapes 

3. ASTM A312 / A312M ‐ Standard Specification for Seamless, Welded, and Heavily Cold Worked Austenitic Stainless Steel Pipes 

Page 216: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 2   

4. ASTM A351 ‐ Standard Specification for Castings, Austenitic, for Pressure‐Containing Parts 

5. ASTM  A403  /  A403M  ‐  Standard  Specification  for  Wrought  Austenitic Stainless Steel Piping Fittings 

6. ASTM  A666  Standard  Specification  for  Annealed  or  Cold‐Worked Austenitic Stainless Steel Sheet, Strip, Plate, and Flat Bar 

7. ASTM A967 ‐ Standard Specification for Chemical Passivation Treatments for Stainless Steel Parts 

E. American Welding Society (AWS): 

1. AWS D1.1 ‐ Structural Welding Code 

F. National Electrical Manufacturers Association (NEMA) 

1. NEMA 250 ‐ Enclosures for Electrical Equipment (1000 Volts Maximum) 

G. Underwriters Laboratories (UL) 

1. All equipment and devices  shall  be  listed by and bear  the Underwriters Laboratories (U.L.) Inc U.L. label or the CSA‐C/US label. 

1.04 SUBMITTALS 

A. Furnish submittals  in accordance with Section 01 33 00 ‐ Submittal Procedures, and including: 

1. Shop Drawings and Product Data. 

2. Certification  that  the  torque  and  thrust  rating  for  speed  reducer  are  in accordance with AGMA standards. 

3. AWS  welding  inspector  certifications  in  accordance  with  paragraph 2.013G. 

4. Hydraulic  performance  curves  showing  the  relationship  of  headloss versus the full range of downstream liquid depths for the maximum and average hydraulic capacity noted in paragraph 2.02. 

5. Data from three (3) separate tests proving compliance of the screen with the  "Paint  Filter  Test"  as  described  in  EPA  Publication  SW 846 Method 9095B. 

6. Submittal data on motors as required in Section 40 05 93.  

Page 217: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 3   

B. Certified Factory Test Report as specified herein. 

C. Bill of Materials per Section 01 33 00. 

D. Field erection requirements per Section 01 33 00. 

E. Manufacturer's warranties as specified herein. 

F. Operation and Maintenance Manuals: Furnish in accordance with Section 01 78 00, Close‐Out Submittals.  

1.05 QUALIFICATIONS 

A. The Manufacturer shall be of established good reputation regularly engaged  in the fabrication of such equipment.  

B. The manufacturer shall have at least 50 installations in the United States of the model specified in satisfactory operation for at least 10 years. 

C. Manufacturer  shall  have  a  representative  permanently  located  within  a  300‐ mile radius of the project site, and a factory‐trained representative and service center  qualified  in  the  repair  of  the  equipment  specified  herein  permanently located within the continental United States. 

1.06 WARRANTY 

A. Manufacturer shall warrant the materials and equipment specified herein to be free of defects in materials and workmanship for a period of two (2) years from the Date of Manufacturer’s Certificate of Installation and Field Testing. 

PART 2 PRODUCTS  2.01 MANUFACTURER 

A. Lakeside  Raptor  Rotating  Drum  Screen Model  42RDS  by  Lakeside  Corporation, Bartlett, IL 

B. Huber Rotamat Rotating Screen Model 1000 by Huber Technology, Huntersville, NC 

C. Engineer‐approved  equal.  Refer  to  Section  00  20  00  Instructions  to  Bidders Article 10 for procedure for approval. 

2.02 SYSTEM DESCRIPTION 

 

Page 218: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 4   

A. Each  unit  shall  consist  of  a  rotating  screen  basket,  concentric  screw  conveyor, dewatering  and  compaction  section,  drive  assembly,  pivoting  support  structure, spray  wash  systems,  screenings  bagger  attachment,  weather  protection  system, spare parts, and electrical control panel, and level sensing system. 

 B. Screens  other  than  rotating  cylindrical  screens  will  not  be  considered  for  this 

project.  

C. Design Criteria  

1. Number of Rotating Screens: 1 

2. Average Flow per Screen, MGD: 0.3 

3. Maximum Hydraulic Capacity per Screen, MGD:  3.3 

4. Maximum Upstream Liquid Level, inches: 30 

5. Maximum Clean Water Headloss, inches: 23 

6. Nominal Screening Basket Diameter, inches: 41 

7. Screen Basket Type: Perforated Plate 

8. Orifice Diameter, inches: 0.12 (3 mm) 

9. Screening Channel Width, inches: 42 

10. Nominal Screw Conveyor Diameter, inches: 10 

11. Minimum Screen Invert to Discharge Height, inches : 110 

12. Speed Reducer Minimum Service Factor: 1.63 

13. Speed Reducer Minimum Torque Rating, in.‐lb: 26,900  

14. Speed Reducer Minimum Thrust Rating, lbf: 8,400 

15. Drive Motor Size, hp: 2 

16. Electrical Power Characteristics, VAC‐Phase‐Hertz: 460/3/60 

17. Motor and Solenoid Valve Electrical Classification: Class I, Div 1 – Group D Explosion‐proof) 

18. Maximum Spray Wash System Flow Rate, gal/min: 20 

Page 219: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 5   

19. Minimum Spray Wash System Pressure, psig: 80 

20. Liquid Level Sensing System Type: Float switch 

21. Electrical Enclosure Type: NEMA 4X SS 

22. Channel Depth: 54 inches (excluding grout for screen) 

 2.03 PERFORMANCE 

A. The drum  screen  shall  be designed  to  handle  the maximum hydraulic  capacity noted  in  paragraph  2.02  with  the  maximum  upstream  liquid  level  noted  in paragraph  2.02.    This maximum  upstream  liquid  depth  includes  the maximum allowable clean water headloss noted in paragraph 2.02. 

B. The screen basket type shall be as noted in paragraph 2.02 with screen openings as noted in paragraph 2.02.   

C. The average screen flow through velocity shall not exceed 3.3 ft/sec (1.0 m/sec) under  any  flow  condition  up  to  the  maximum  hydraulic  capacity  noted  in paragraph  2.02.  The  screen  design  shall  minimize  solids  deposition  in  the channel. 

D. The  rotating  drum  screen  shall  include  a  rotating  cylindrical  drum  with  an integral screw conveyor and press.   The rotating drum screen shall use a single drive for screening, conveying, dewatering, and compressing screening material. 

E. The operation of  the  rotating drum screen  shall be automatically  initiated at a preset high liquid level. Screens that operate continuously or via timer only will not  be  acceptable.  The  rotating  drum  screen  shall  remove  solids  from  the wastewater  flow  and  shall  deposit  them  into  the  concentric  screw  conveyor trough.  The screenings shall be transported up the screw conveyor and through a compression chamber. 

F. The screening equipment shall produce dewatered screenings capable of passing the  EPA  Paint  Filter  Test  as  described  in  method  9095B  of  EPA  Publication SW‐486. 

G. The control system shall be designed so that the cleaning characteristics of the screen  and  spray  wash  systems  can  be  changed  via  the  programmable  logic controller.  Systems that do not offer this feature will not be considered for this project.  

2.04 SCREENINGS WASHING 

Page 220: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 6   

A. Each screen shall be furnished with a dual screenings spray wash system to flush organic material from the screenings prior to compaction and dewatering.   The dual  screenings washing  systems  shall  be designed  to minimize  the  amount of organic  material  in  the  screenings  and  to  maximize  solids  dryness  after compaction and dewatering.  The dual screenings washing systems shall include: 

1. Lower basket wash system shall be located on the outside of the basket with a minimum of one  (1)  spray wash header with multiple nozzles  to remove  collected  screenings  from  the  inside  of  the  basket  into  the screenings  collection  trough.  This  wash  system  shall  pre‐wash  the screenings to remove fecal material and to prevent material. 

2. Screenings wash system shall be located just prior to the beginning of the compaction  zone  after  maximum  maceration  of  the  screenings  by  the screenings transport screw conveyor.  At the maximum wash water flow rate  noted  in  paragraph  2.02,  the  screw  conveyor  shall  be  designed  to prevent  screenings  from  being  washed  down  the  screenings  transport tube to the basket.  

2.05 ODOR CONTROL 

A. To minimize  odors  and  nuisance  insect  populations,  the  rotating  drum  screen transport  system  and  compaction/dewatering  system  shall  be  completely enclosed. 

B. The spray wash systems shall be completely enclosed to prevent spray, aerosols, and leakage from coming in contact with the operating floor. 

2.06 MATERIALS QUALITY 

A. All  fabricated  components  of  the  screen  shall  be  AISI  Type  316  stainless  steel including the screen basket, screw conveyor, outer screw conveyor housing and support  structure.  Materials  thicknesses  identified  are  the  minimum requirements  for  this  project.  Materials  with  increased  thicknesses  are acceptable. 

B. All fabricated components shall be manufactured in the United States.  

2.07 ROTATING DRUM SCREEN 

A. Screen  

1. The  rotating  drum  screen  shall  be  designed  and  built  to  withstand maximum possible static and hydraulic forces exerted by the liquid to the screen.    All  structural  and  functional  parts  shall  be  sized  for  the  loads encountered  during  the  screening,  conveying  and  pressing  operations.  

Page 221: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 7   

All  submerged  components  and  all  components  of  the  rotating  drum screen  in  contact  with  the  screened  solids  shall  be  of  stainless  steel construction. 

2. The  screen  basket  shall  be  of  a  cylindrical  shape  and  installed  in  the channel parallel to the direction of liquid flow. 

3. The diameter of the screening basket shall be as noted in paragraph 2.02. 

4. The  basket  diameter  shall  be matched with  a  sufficient  screen opening size  and  spacing  to  ensure  the  maximum  hydraulic  capacity  flow  rate noted  in  paragraph  2.02  is  achieved  and  to  provide  less  than  the maximum headloss noted in paragraph 2.02. 

5. The screen basket shall be  fabricated of material as noted  in paragraph 2.02.  The  basket  shall  have  perforated  plate  openings  with  the  size  as listed in paragraph 2.02 and having a minimum thickness of 11 gauge and a  centerline‐to‐centerline  perforated  hole  spacing  of  3/16‐inch  with staggered centers.   The basket screen material shall be bolted to 1‐inch thick  minimum  upper  and  lower  stainless  steel  support  rings  with  a sufficient number of bolted stainless steel strengthening spokes to allow for field replacement of the basket.   Stainless steel  lifting vanes shall be welded to the  inside of  the basket to  lift  the screenings out of  the  flow and to deposit them into the screenings collection hopper.  Lifting vanes shall be fabricated from 10‐gauge thick minimum stainless steel. 

6. The width of the screening chamber shall be as noted in paragraph 2.02. 

7. A  seal  plate  shall  be  provided  to  enclose  the  circular  screen  and  the rectangular concrete channel. The side seal plate shall be fabricated of 10 gauge minimum stainless steel and shall be of sufficient height to prevent bypassing of flow around the screen at the maximum hydraulic capacity flow rate noted in paragraph 2.02. 

8. The screen shall be provided with a pivoting support  stand allowing  for easy  removal  of  the  screen  basket  from  the  channel  for  maintenance purposes.  To  ensure  operator  safety  during  servicing  of  the  screen, supports  and  support  stand  shall  be  fabricated  from 1/4  inch minimum stainless steel shapes and plates. 

9. A  stainless  steel  lower  screen  basket  support  fabricated  of  1/4‐inch sections shall be provided to support the basket in the channel.  Support shall  allow vertical  adjustment  of  the  screen basket  so  that  it  does  not rest on the channel floor. 

Page 222: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 8   

B. Screenings Conveyor and Screenings Dewatering Press 

1. The screenings screw conveyor transport tube nominal diameter shall be as  noted  in  paragraph  2.02  with  a  minimum  Schedule  10S  pipe  wall thickness.    A  minimum  of  three  (3)  anti  rotation  bars  with  1/4  inch minimum  thickness  shall  be welded  to  the  inside  of  the  transport  tube along the longitudinal axis from the compaction zone to the beginning of the  screenings  collection  trough.    The  screenings  screw  conveyor  shall not  depend  on  support  from  the  anti‐rotation  bars  during  normal operation. 

2. A basket support plate flange shall be a minimum of 3/4‐inch and shall be welded to the lower end of the screenings transport tube complete with strengthening  gussets  to  attach  the  screen  basket  and  to  provide  for attachment  of  the  screenings  collection  hopper.    A  1/2‐inch  minimum thick  drive  support  flange  shall  be  welded  to  the  upper  end  of  the screenings transport tube for attachment of the drive assembly.  After all welding  of  components  to  the  screenings  transport  tube  have  been completed the fabrication shall be placed in a lathe to machine the face of  the  upper  drive  flange,  to  machine  the  face  of  the  lower  basket support  plate  flange  for  mating  the  basket  and  to  machine  the  lower bearing housing  in accordance with paragraph 2.013F.   A 1/2‐inch  thick minimum drive assembly adaptor stainless steel flange shall be provided to bolt to the upper drive support flange.    

3. The  dewatering  screw  shall  be  designed  to  transport  and  dewater  the screened material.  Screw flights shall be stainless steel with a minimum thickness of 3/16‐inch with  increased 3/8‐inch  thick minimum thickness in the screenings collection trough and in the compaction and dewatering zone.  Flight  pitch  distance  shall  be  a  maximum  in  the  screenings collection hopper and shall be reduced along the length of the screenings transport  tube  to  a  minimum  pitch  distance  in  the  compaction  zone.  Constant pitch screenings screw conveyor designs will not be acceptable for this project. 

4. The upper and lower screenings conveyor torque tube shall be fitted with a  solid  stainless  steel  stub  shaft.  The  shafts  and  screenings  screw conveyor  torque  tube  shall  be  accurately machined  in  accordance with paragraph 2.013F  to allow a  shrink‐fit  and welded design  for  the upper drive  end  stub  shaft  and  lower  tail  bearing  stub  shaft.  Bolting  the  stub shafts to the screening transport screw conveyor torque tube will not be acceptable for this project.   

5. The lower end of the screenings conveyor and rotating drum screen shall be  supported  by  a  sealed,  self‐lubricated  lower  polymeric  composite 

Page 223: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 9   

sleeve  bearing  with  stainless  steel  wear  sleeve.    Metallic‐based  lower bearings will not be acceptable for this project.   The lower bearing shall not  take  any  thrust  load  from  the  screw  conveyor.    The  stainless  steel bearing  housing  shall  be  field  replaceable  and  shall  be  machined  in accordance with paragraph 2.013F to mate with the screenings collection housing by a bolted connection.  Designs in which the bearing housing is welded directly to the screen body will not be acceptable for this project. A  seal  plate  shall  be  furnished  to  mate  between  the  stationary  lower bearing support and the rotating drum to prevent material intrusion into the bearing seals. 

6. The upper end of the rotating drum screen basket shall be supported by a minimum of  four  (4) polymide cast nylon  roller  assemblies.    Each  roller assembly  shall be a minimum 4‐inch diameter and  shall be mounted  to the  main  upper  support  flange  to  provide  smooth  operation  of  the rotating drum screen basket. 

7. The  screen  basket  assembly  shall  be  provided with  a  support  frame  to allow for easy removal of the screen basket and deflection plate from the channel for maintenance purposes. 

8. The deflection plate shall have a guide assembly that aligns the deflector plate  seal  with  the  rotating  drum  screen  basket.  The  guide  shall incorporate a self‐lubricated UHMW bearing at  the screen’s  lower shaft to maintain the position of the deflector plate. The guide assembly shall be field replaceable by a bolted connection. 

9. Drainage holes shall be provided along the entire length of the screenings collection  trough  invert  to  allow  for  gravity  drainage  of  washwater without flushing screenings out of the trough.  The width of the drainage section  shall  be  based  upon  a  minimum  65‐degree  arc.    The  drainage section  perforated  plate  material  shall  be  fabricated  from  11  gauge minimum thick stainless steel and shall have a minimum 50% open area for free water drainage. 

10. A  compaction  zone  shall  be  an  integral  part  of  the  screenings  screw conveyor  and  transport  tube  design.    The  compaction  zone  shall  be designed  to  form  a  screenings  plug  of  material  and  to  return  water released  from  the  screened  material  back  to  the  wastewater  channel through  circular  holes  that  are machined  into  the  screenings  transport tube.  Compaction zone shall be fabricated from 12‐gauge minimum thick stainless  steel  welded  to  the  screenings  transport  tube  to  provide  a watertight  screenings  pressate  collection  chamber.  Compaction  zone housings  that  are  non‐metallic  and  which  require  seals  to  prevent leakage around the screenings transport tube will not be acceptable for 

Page 224: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 10   

this  project.  Compaction  zone housing  shall  be  furnished with  a hinged and sealed access cover held in place with stainless steel  latches as well as a removable dewatering section panel inside the dewatering chamber to allow direct access to the screw conveyor should the compaction zone ever  become  plugged.  Designs  that  require  removal  of  the  drive assembly,  discharge  head  or  screw  conveyor  to  gain  access  to  the compaction zone will not be acceptable for this project. 

11. Water  that  is  released  from  the  screenings  shall  be  returned  via  a reinforced rubber hose attached to the dewatering section.  Drain design shall  allow  for  removal  and  cleaning  of  the  drain  hose  should  it  ever become  plugged  without  removing  the  drive,  discharge  head  or  screw conveyor. 

12. Screen minimum invert to discharge height shall be as noted in paragraph 2.02. 

C. Drive Assembly 

1. The  rake  mechanism  and  transport  screw  shall  be  driven  by  a  direct‐connected cycloidal‐helical hollow‐shaft high‐thrust  in‐line  speed  reduc‐er.   The cyclo element of the speed reducer shall be designed to take a 500  percent  shock  load  without  damage.  The  speed  reducer manufacturer shall be a member of AGMA. The speed reducer shall have a  minimum  torque  rating  as  noted  in  paragraph  2.02  and  a  minimum thrust rating as noted in paragraph 2.02. 

2. The  speed  reducer  shall  be bolted  to  the drive adaptor  flange at upper end of the screenings transport tube. 

3. The speed reducer shall be driven by a field replaceable NEMA C‐flanged, 1,800 rev/min, ball bearing, continuous‐duty, totally enclosed, fan‐cooled motor with leads to a large conduit box for outdoor operation.   

4. Motor  size  shall  be  as  noted  in  paragraph  2.02,  shall  be  rated  for electrical power  characteristics  as noted  in paragraph 2.02 and  shall  be rated  for  an  environment  as  noted  in  paragraph  2.02.  Explosion‐proof motors  shall  be  furnished with  thermostats  in  the motor windings  shall be rated T3C for cutout at 160 deg C. 

5. Chain‐drives, belt drives, hydraulic drives or a separate upper bearing for the transport screw will not be acceptable for this project. 

D. Spray Wash Systems 

Page 225: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 11   

1. Three (3) spray systems shall be provided.  Each spray wash system shall be  furnished  with  a  control  solenoid  valve,  stainless  steel  piping  and fittings,  flexible  reinforced  PVC  hose  and  nozzles.    Piping,  fittings  and valves shall be 3/4‐inch diameter minimum. A plant water strainer shall be provided for  the  incoming plant water supply.   The wash water  flow requirements  shall  be  as  noted  in  paragraph  2.02  with  a  minimum pressure at piping connection to the screen and during screen operation as  noted  in  paragraph  2.02.  The  three  (3)  spray  wash  systems  shall include: 

a. Lower  spray wash  system shall  be  located on  the outside of  the screen  basket  and  shall  include  a minimum  of  one  (1)  stainless steel header assembly that shall span the full length of the basket.  Each  lower  spray wash  system  header  shall  have multiple  spray nozzles.  Lower spray wash bars without replaceable spray nozzles will not be acceptable. A 12‐gauge thick minimum stainless steel spray wash header cover shall be provided for each spray header.  

b. Screenings  spray  wash  system  shall  be  located  in  the  upper section  of  the  transport  tube  no more  than  17  inches  from  the beginning of the compaction zone to break up and return organic materials to the flow stream and to ensure maximum screenings washing.  A minimum  of  one  (1)  spray  nozzle  shall  be  provided.  The screenings spray wash system and screenings screw conveyor shall be designed to prevent washing screenings down the center of the screw conveyor. 

c. The  dewatering  chamber  flush  water  system  shall  periodically clean  the  compaction  and  dewatering  zone  via  a  stainless  steel wash nozzle located in the compaction/dewatering chamber.  The dewatering chamber flush water system shall not be a substitute for the screenings washing systems described in paragraphs 2.02 and 2.02. 

2. The  three  (3) wash  system  solenoid  valves  shall  be  3/4  inch minimum, brass  body  suitable  for  120  VAC  operation  with  a  rating  as  noted  in paragraph 2.02.  Solenoid valves shall be normally closed and rated for up to 150 psig.   Solenoid valves shall be slow close type to minimize water hammer. 

3. Solenoid valves  shall be  factory  installed  to a piping manifold  to ensure even pressure distribution to each spray wash system. The solenoid valve wiring shall be  factory  installed to a common  junction box on the spray wash manifold  for wire nut connection to external power.   Conduit and fittings  shall  be  factory  installed  between  the  solenoid  valves  and 

Page 226: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 12   

junction boxes.    Junction box,  conduit  and  fittings  shall  be  rated NEMA 4/7/9 for an explosion‐proof environment as noted in paragraph 2.02. 

4. Water strainer shall be provided suitable for a 3/4‐inch connection and a maximum  flow  rate  as  noted  in  paragraph  2.02  and  suitable  for  a maximum  pressure  as  noted  in  paragraph  2.02. Water  filter  shall  be  a stacked  filter  element  design  with  washable  80‐mesh  (200  micron) polyethylene  or  polypropylene  disc  elements,  polypropylene  head  and bowl and Buna N gaskets. Y‐type strainers will not be acceptable for this project. 

2.08 CONTROL SYSTEM 

A. All  controls  necessary  for  the  fully  automatic  operation  of  the  screen  shall  be provided in accordance with NEMA standards. 

B. The electrical control system shall provide for automatic control of the screen via a  high  liquid  level  using  a  liquid  level  control  system  in  connection  with  an adjustable  time  clock.    The  screen  shall  operate  at  a high  liquid  level  and or  a pre‐determined  time  sequence  to  provide  a  variable  time  between  cleaning operations. 

C. The  float  switches  shall  be  a  hermetically  sealed,  axially  non‐position  sensitive type, mercury‐switch  activated  and  enclosed  in  a  polypropylene  housing.    The switches shall operate over a narrow switching angle and have a minimum rating of 1 amp at 120 volts.  A 20 ft PVC jacketed power cable, weight, grip cord, and stainless  steel  mounting  bracket  shall  be  furnished  as  part  of  the  switch assembly. The level switching circuit shall be rated intrinsically safe by inclusion of a UL approved switch isolator with relay output.  The switch isolator shall be rated  for  120‐volt  service with output  contacts  rated  for  2  amps minimum.   A second high‐level float switch shall be included for alarm indication. 

D. A  local‐mounted  panel  suitable  for  wall  mounting  shall  contain  the  following items: 

1. Door interlocked fused disconnect. 

2. Process controller complete with LCD operator interface panel providing field settable/adjustable/access to process parameters and for providing specific  indications of each  type of  fault  that may occur. Controller  ram shall  be  backed  up  with  non‐volatile  memory  which  will  load automatically if ram is corrupted. 

3. Variable frequency drive (VFD) with line reactor for the screen. 

Page 227: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 13   

4. Control  power  transformer  fused  primary  and  secondary  with  120VAC transient voltage surge suppressor (TVSS) 

5. Full voltage LED pilot lights for the following: 

a. Control power on (White) 

b. Multifunctional overload shutdown/screen fault (Red) 

c. High level (Amber) 

6. E‐stop push button (Red) 

7. Re‐set push button (Black) 

8. Hand‐Off‐Auto selector switches for the following: 

a. Screen drive 

b. Common wash system solenoid valves 

9. Forward‐Off‐Reverse selector switch (spring return to center)  for screen drive 

10. Door‐mounted elapsed time meter 

11. Remote dry contact outputs for the following: 

a. Screen Running 

b. Malfunction alarm 

c. High water level alarm 

12. Weather protection system heat tracing circuit breaker 

13. Plant  water  heat  tracing  (250  WATTS  MAX  BY  CONTRACTOR)  circuit breaker  

14. Flashing alarm light 

15. Set spare fuses 

16. White phenolic nameplates with black lettering 

17. 600 VAC terminal block 

18. U.L. panel label per the application 

Page 228: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 14   

19. Electrical enclosure shall be provided in accordance with paragraph 2.02.   

E. SCREENINGS BAGGER 

1. The discharge chute shall be furnished with a bagging device to contain and encase dewatered screenings. 

2. The  bagging  device  shall  be  fabricated  of  12‐gauge  minimum  stainless steel. 

3. The  screenings  bagger  shall  be designed  to  be  fitted with  a  continuous hose  cassette.    Bagger  shall  be  supplied  with  two  continuous  hose cassettes. 

2.09 COLD WEATHER PROTECTION 

A. The  screenings  discharge  transport  tube  shall  be  furnished with  a  heat  tracing system  for  outdoor  weather  protection  that  shall  completely  enclose  the screenings  transport  tube,  compaction  and  dewatering  zone,  screenings discharge drop chute and all spray wash piping and solenoid valves. 

B. The  cold  weather  protection  system  shall  include  heat  tracing,  adjustable thermostat, insulation and a protective jacket.  Heat tracing shall be suitable for an electrical environment as noted in paragraph 2.02. 

C. The  heat  tracing  system  shall  be  suitable  for  operation  down  to  a  minimum temperature of ‐25oC (‐13oF) and shall be powered from the main control panel. 

D. Weather  protection  system  protective  cover  shall  be  molded  fiberglass reinforced  polyester  laminate,  or  a  custom  fit,  coated  fiberglass  cloth  jacket.  Fabricated metallic or plastic covers that are bolted or riveted together will not be acceptable for this project.  

E. The  molded  fiberglass  reinforced  polyester  laminate,  shall  have  the  exterior surface  gel  coated  for  ultraviolet  radiation  protection.    Fiberglass  shall  have  a glass content of not less than 30%, a tensile strength of not less than 22,000 psi, a  flexural  strength  of  not  less  than  25,000  psi  and Barcol  hardness  of  not  less than  40.    Finished  fiberglass  must  withstand  a  temperature  of  200oF  without blistering,  pinholes,  warping  or  other  defects.  Gel  coat  shall  be  provided with impregnated  pigment  for  exterior  light  gray  color.    The  weather  protection package cover shall be designed to support a wind load of 30 lb per square foot. 

F. The weather protection package fiberglass cover sections shall be split into two sections when mounted  axially  along  the  transport  tube.   Weather  protection system fiberglass cover sections shall extend from the discharge chute over the compaction and dewatering zone and down to  the main basket support  flange 

Page 229: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 15   

gussets.    Each  split  fiberglass  cover  section  shall  be  connected  via  fiberglass flanges  and  no  more  than  six  (6)  stainless  steel  thumb  screws  for  ease  of operator  access.    Each  fiberglass  cover  section  shall  be  designed  so  that  the insulation  is  completely  encapsulated  within  the  fiberglass  to  prevent  water intrusion and damage.  Designs utilizing loose fiberglass or foam insulation that are  not  encapsulated  in  FRP  will  not  be  acceptable  for  this  project.    Each fiberglass half section shall be approximately 2 feet long with molded fiberglass flanges.  Individual  sections  shall  be  connected  via  fiberglass  flanges  and  a stainless steel V‐ring captive clamping system for easy installation and removal. 

G. Where  the  wash  water  supply  and  electrical  wiring  conduit  penetrates  the fiberglass cover, bulkhead adapters shall be provided. 

H. All  fasteners  to  assemble  the  fiberglass  cover  components  shall  be  stainless steel. 

I. The custom fit, coated fiberglass cloth jacket shall be removable and replaceable.  The  inner  and  outer  jacketing  and  the  side  gussets  shall  be  fabricated  from  a minimum of 18 oz/sq yd Teflon coated fiberglass cloth containing a minimum of 1‐inch  thick  insulation  core  of  Type  E  fiberglass  mat.    Seam  closures  shall  be Teflon coated fiberglass thread and fasteners shall be Teflon straps with stainless steel D‐rings.   Weather flaps of Teflon cloth shall cover seams and slits and will be  fastened  with  Velcro  hook  and  loop  closures.  3‐inch  wide  Teflon  cloth terminal end flaps with Nomex drawstrings sewn into the sides of the jacket shall be provided.    Identification tags  in AISI Type 316 stainless steel with embossed lettering shall be provided. 

J. A  fabricated  composite  weather  enclosure  shall  be  provided  for  the  water strainer specified herein.  Enclosure shall be provided with a removable cover. 

K. The  plant  water  supply  system  piping  to  the  screen  and  the  water  strainer specified  herein  shall  be  provided  with  heat  tracing  and  insulation  by  the Contractor.  The Manufacturer’s  control  panel  shall  be  provided with  sufficient low voltage power to handle up to an additional 250 Watts from the Contractor supplied plant water heat tracing system. 

L. A stainless steel weather spray protection housing shall be provided to cover the top of the screen basket to eliminate misting  in the screen basket area (and to minimize wind chill effects for outdoor installations).  The housing sides and top shall be fabricated of 14‐gauge minimum stainless steel.  The top of the housing cover  shall  be  designed  with  two  (2)  sliding  cover  sections  that  have  been reinforced.  Each  cover  section  shall  be  provided  with  four  (4)  1‐1/2  inch minimum diameter wheels that shall roll  in a 14‐gauge minimum thick stainless steel wheel  track.   Each cover shall be provided with a handle  for opening and closing the enclosure. The housing cover shall be designed to work with the FRP 

Page 230: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 16   

screenings transport screw weather protection system specified herein.  Where the screenings transport screw exits the housing, a split cover shall be provided to allow the entire weather protection cover  to be  removed without complete disassembly. 

2.010 ANCHOR BOLTS 

A. Equipment manufacturer  shall  furnish  all  anchor bolts of  ample  size and  strength required to securely anchor each item of equipment.  Bolts, washers and hex nuts shall be AISI Type 316 stainless steel unless noted otherwise.  Anchor bolts shall be drilled‐in wedge or epoxy‐type.  

 B. Anchor  bolts  shall  be  set  by  the  Contractor.  Equipment  shall  be  placed  on  the 

foundations,  leveled,  shimmed,  bolted  down,  and  grouted  with  a  non‐shrinking grout. 

 2.011 SPARE PARTS 

A. The following spare parts shall be provided: 

1. One (1) complete solenoid valve assembly 

2. One (1) lower bearing assembly with wear sleeve and seals 

3. Three (3) spare fuse sets of each size and type 

B. Spare  parts  shall  be  packaged  in  accordance  with  Section  01  60  00,  Product Requirements. 

2.012 SHOP SURFACE PREPARATION AND PAINTING 

A. Electric  motors,  speed  reducers,  and  other  self‐contained  or  enclosed components shall have manufacturer's standard enamel finish. 

B. All  external  non‐wetted  stainless  steel  shall  be  cleaned  to  a  uniform  finish  by glass  bead  blasting  and  chemically  treating  with  Citrisurf  2210  or  2050.  No hazardous wastes shall be produced during fabrication because Citrisurf is a citric acid‐based  product  that  is  non‐toxic.  The  rotating  drum  screen  manufacturer shall  clearly  identify  the  passivation  procedure  methodology  and  shall  certify that no hazardous wastes are produced. 

2.013 SOURCE QUALITY CONTROL 

A. All structural stainless steel components shall be fabricated in the United States and  shall  conform  to  the  requirements  of  "Specifications  for  the  Design, 

Page 231: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 17   

Fabrication  and  Erection  of  Structural  Steel  for  Buildings"  published  by  the American Institute of Steel Construction. 

B. All parts and assemblies shall be fabricated from sheets and plates of AISI Type 316 stainless steel with a  finish conforming to AISI 316 and ASTM A666, unless noted otherwise.  All rolled or extruded shapes shall be fabricated to conform to ASTM A276.   All  tubular products and fittings shall be fabricated to conform to ASTM A312, A351 and A403. 

C. All welding  in  the  factory shall use shielded arc,  inert gas, MIG or TIG method.  Add filler wire to all welds to provide for a cross section equal to or greater than the  parent  metal  does.    All  butt  welds  shall  be  full  penetration  type  to  the interior surface.  Provide gas shielding to interior and exterior of the joint. 

D. Welding of the screen components shall be in accordance with the latest edition of  the  American Welding  Society  (AWS)  standards.    Field  welding  of  stainless steel will not be permitted. 

E. Bolts, nuts and washers shall be AISI 316 stainless steel furnished in accordance with ASTM A193. 

F. All surfaces that are specified to be machined shall be designed and fabricated to provide  a  runout  of  not more  than  0.005  inches  and  a  concentricity  to within 0.005 inches. 

G. Design and  fabrication of  structural  steel members shall be  in accordance with AISC  and  AWS  Standards.    The  manufacturer  shall  comply  with  the  American Welding Society  (AWS) and  the American  Institute of  Steel Construction  (AISC) most current listed standards and qualifications in 2004 D1.1, the criteria per the requirements  of  Section  6  ‐  Inspection  ‐  Structural Welding  Code.  Evidence  of such AWS and AISC compliance shall be submitted with shop drawing submittals as follows: 

1. AWS Certified Welding Inspectors (minimum 2 on staff) shall conform to all  standards,  current  or  previous  as  listed  in  section  6.1.4  AWS  QC1, Standard  and  Guide  for  Qualification  and  Certification  of  Welding Inspectors. 

2. AWS  Non‐Destructive  Testing  Inspectors  (Level  I,  II,  III)  for  Magnetic Particle and Ultra‐Sonic testing (minimum 2 on staff) shall conform to all standards, current or previous as  listed  in and  in conformance with The American Society for Non‐Destructive Testing (ASNT‐TC‐1A). 

  

Page 232: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 18   

PART 3 EXECUTION    

3.01 FACTORY TESTING 

A. Prior to shipment of the equipment the screen shall be operated for a minimum of four (4) hours at the fabrication location with the specific drive motor that will be furnished for the project at the actual operating angle of the screen for the project. 

B. During the shop test the following parameters shall be recorded: 

1. Motor nameplate data 

2. Amperage draw at start‐up, after two hours and after four hours during forward operation 

3. Amperage draw during reverse operation 

C. A  certified  factory  test  report  shall  be  submitted  to  the  Engineer  prior  to shipment per Section 01 33 00. 

3.02 PRODUCT SHIPMENT AND PROTECTION 

A. The  equipment  specified  herein  shall  be  packaged  and  shipped  in  accordance with Section 01 60 00, Product Requirements. 

3.03 INSTALLATION 

A. Installing Contractor  shall  install  the  equipment  specified herein  in  accordance with the Manufacturer's recommendations and as shown on the Drawings.    

B. Manufacturer’s  representative  shall  inspect  the  installation  as  specified  in Specification Section 01 75 00, Testing and Commissioning and shall also verify: 

1. Installation is in accordance with Manufacturer’s installation checklist and recommendations. 

2. Channel is grouted as required. 

3. Screen is properly supported and supports anchored. 

4. Exposed, non‐stainless steel metal components finish coated as required.  

5. All  stainless  steel  bolts  and  nut  threads  coated  with  a  non‐seizing compound. 

6. Wash water piping is properly installed and pressure tested. 

Page 233: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 19   

7. Lubricants are applied as required. 

8. Screen rotational direction is correct. 

9. Float switches are properly installed, secured, and wired to control panel.  

10. Motor nameplate data matches approved submittal. 

11. Motor is properly installed in accordance with Section 40 05 93 and motor manufacturer’s instructions. 

12. Control panel is properly wired and grounded, and I/O tested. 

13. Heat tracing installed and wired to control panel and insulation installed. 

C. Manufacturer’s  qualified  service  representative  shall  provide  a  minimum  of  6 hours for installation inspection.  

3.04 FIELD TESTING 

A. On‐site  field  testing  shall  comply  with  the  requirements  of  Section  01  75  00, Testing and Commissioning.  Testing shall also include: 

1. Testing the motor current overload setting for automatic shutdown. 

2. Testing the float switches for automatic operation and alarm indication. 

3. Testing screen and solenoid valves in manual and automatic operation. 

4. Verifying heat tracing operation. 

5. Three  (3)  tests  conducted  according  to  the  EPA  Paint  Filter  Test  as described in method 9095B of EPA Publication SW 846. 

B. Motor field testing shall comply with Section 40 05 93.  

C. Manufacturer’s  service  representative  shall  certify  the  installation  and  field testing  in  accordance  with  Section  01  75  00,  Testing  and  Commissioning Procedures, and shall submit the completed Certificate of  Installation and Field Testing Form at the end of this Section. 

D. Manufacturer’s  qualified  service  representative  shall  provide  a  minimum  of  8 hours of on‐site testing of the equipment specified herein. 

3.05 TRAINING  

Page 234: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 20   

A. Manufacturer’s  qualified  service  representative  shall  provide  a  minimum  of  2 hours of training of the Owner’s staff  in the operation and maintenance of the equipment specified herein.  

B. Training shall meet the requirements of Section 01 79 00, Training. 

*** END OF SECTION *** 

Page 235: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 21   

FORM 46 21 33‐1 CERTIFICATE OF INSTALLATION AND TESTING OF  IN‐CHANNEL ROTARY SCREEN 

MANUFACTURER NAME:   PROJECT NAME:  

EQUIPMENT SCHEDULE NO.:  NAME OF EQUIPMENT: 

LOCATION/SERVICE:  SPECIFICATION SECTION: 

MANUFACTURER:  SIZE (INCHES): 

MODEL NUMBER:  SERIAL NO.: 

MOTOR HP:  VOLTS:  HERTZ:  PHASE: 

FLA:  MOTOR RPM:  SERVICE FACTOR:  MOTOR EFFICIENCY: 

INSTALLATION INSPECTION (CHECK IF VERIFIED) 

MFR CHECKLIST SUBMITTED:  MOTOR GROUNDED:  FLOAT SWITCHES SET:  PANEL I/O TEST: 

CHANNEL GROUTED:  PIPE/CHANNEL CLEANED:  PIPE/EQUIPMENT SUPPORTS:  PIPE PRESSURE TESTED/NO LEAKS: 

SHAFT ALIGNMENT:  LUBRICATION:  PROPER ROTATION:  GUARDS/SAFETY: 

SUPPLY VOLTAGE:  HEAT TRACING/INSULATION:  STRAINER ON WATER SUPPLY: 

OTHER: 

MISSING OR DAMAGED PARTS/TOOLS (LIST): 

FIELD TEST (CHECK IF VERIFIED) 

HIGH LEVEL FLOAT SWITCH TAG:    TIMER RUN IN AUTO:   

HIGH HIGH LEVEL FLOAT SWITCH TAG:    EMERGENCY STOP:   

MANUAL RUN IN HAND:    HIGH LEVEL ALARM:   

RUN STATUS INDICATION:    MOTOR OT STATUS ALARM:   

FORWARD‐REVERSE OPERATION:   WASHWATER SOLENOIDS OPERATION IN HAND/AUTO: 

 

HIGH LEVEL RUN IN AUTO:    HEAT TRACING IN AUTO:   

COMMENTS: 

As the Manufacturer’s Representative, I certify that I have inspected the installation of the equipment, the equipment has been installed in accordance with the manufacturer's recommendations, I have witnessed all applicable field tests, all proper adjustments have been made, the equipment meets the performance requirements of the Contract Specifications, and the equipment is ready for plant commissioning and operation. 

 SELLER/MANUFACTURER  

CHECK OFF  INSTALLER CHECK OFF  WITNESS CHECK OFF 

NAME       

SIGNATURE       

DATE       

 

Page 236: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 21 33 In‐Channel Rotary Drum Screen.doc  46 21 33 ‐ 22   

THIS PAGE INTENTIONALLY LEFT BLANK 

Page 237: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 1   

SECTION 46 23 00 GRIT REMOVAL EQUIPMENT 

 PART 1 GENERAL 

 1.01 DESCRIPTION OF WORK 

A. Manufacturer  shall  furnish  a  grit  removal  system  with  a  grit  mechanism,  grit pump, grit concentrator, grit washer, vacuum prime panel  (if  required), and all required appurtenances for a complete system. 

B. The  work  shall  include  fabrication,  factory‐testing,  delivery,  installation inspection,  field  testing,  certification  of  installation  and  field  testing,  and training. 

1.02 RELATED WORK 

A. Division 0 – Bid Documents 

B. Division 1 – General Requirements  

C. Section 40 05 93 ‐ Common Motor Requirements for Process Equipment 

1.03 REFERENCE STANDARDS 

A. The work in this section is subject to the requirements of applicable provisions of the following standards: 

B. Anti‐Friction Bearing Manufacturers Association (AFBMA) 

C. American Gear Manufacturers Association (AGMA) 

D. American Iron and Steel Institute/Society of Automotive Engineers (AISI/SAE) 

1. AISI/SAE 316 (UNS S31600) – 316 Stainless Steel 

2. AISI/SAE 316L (UNS S31603) – 316L Stainless Steel 

E. American National Standards Institute (ANSI) 

F. American Society for Testing and Materials (ASTM) 

1. ASTM A967 ‐ Standard Specification for Chemical Passivation Treatments for Stainless Steel Parts 

G. American Welding Society (AWS) 

Page 238: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 2   

H. National Electric Code (NEC) 

I. National Electrical Manufacturers Association (NEMA) 

J. Society for Protective Coatings (SSPC) 

1. SSPC‐SP 6 ‐ Commercial Blast Cleaning. 

K. Underwriters Laboratories (UL) 

1. All equipment and devices  shall  be  listed by and bear  the Underwriters Laboratories (U.L.) Inc U.L. label or the CSA‐C/US label. 

1.04 SUBMITTALS 

A. Furnish submittals  in accordance with Section 01 33 00 ‐ Submittal Procedures, and including: 

1. Five  (5)  grit  removal  efficiency  tests  from  installations  where  similar equipment by the Manufacturer is currently in similar service.   

2. Calculations and supporting information to demonstrate sizing of the grit chamber based on particle size, peak flow, and chamber diameter. Units sized on Surface Overflow Rate (SOR) shall not be allowed.  

3. Submittal data on motors as required in Section 40 05 93.  

B. Certified factory test report. 

C. Bill of Materials per Section 01 33 00. 

D. Field erection requirements per Section 01 33 00. 

E. Manufacturer's warranties as specified herein. 

F. Operation and Maintenance Manuals: Furnish in accordance with Section 01 78 00, Close‐Out Submittals.  

1.05 QUALIFICATIONS 

A. The Manufacturer shall be of established good reputation regularly engaged  in the fabrication of such equipment.  

B. The manufacturer shall have at least 50 installations in the United States of the model specified in satisfactory operation for at least 10 years. 

Page 239: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 3   

C. Manufacturer  shall  have  a  representative  permanently  located  within  a  300‐ mile radius of the project site, and a factory‐trained representative and service center  qualified  in  the  repair  of  the  equipment  specified  herein  permanently located within the continental United States. 

1.06 WARRANTY 

A. Manufacturer shall warrant the materials and equipment specified herein to be free of defects in materials and workmanship for a period of two (2) years from the Date of Manufacturer’s Certificate of Installation and Field Testing. 

PART 2 PRODUCTS  2.01 MANUFACTURER 

A. Smith & Loveless Pista 4.0 Vortex Grit Chamber Smith & Loveless, Lenexa, KS 

B. Lakeside Equipment Corporation SpiraGrit™ Vortex Grit Chamber, Bartlett, IL  

C. Engineer‐approved  equal.  Refer  to  Section  00  20  00  Instructions  to  Bidders Article 10 for procedure for approval. 

2.02 PERFORMANCE CRITERIA 

A. Design each grit chamber for following hydraulic condition. 

1. Minimum Flow:  0.3 MGD. 

2. Maximum Flow While Maintaining Below Removal Efficiency: 4.0 MGD 

B. Construct suitable for extremely humid installation and splash resistant. 

C. Limit headloss through grit chamber to 6 inches or less at 4.0 MGD. 

D. Grit  removal  (%  by  weight)  with  specific  gravity  of  2.65  from  screened  raw wastewater into and out of grit chamber.  

1. 95% greater than 50‐mesh (297‐micron) particle size 

2. 85% greater than 70‐mesh (210‐micron) particle size 

3. 65% greater than 100‐mesh (149‐micron) particle size 

E. Wearing parts readily accessible for inspection, repairs, and replacement. 

F. Replacement parts easily duplicated and attainable. 

Page 240: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 4   

G. No moving parts subject to wear or stoppage below water surface.  

H. No bends or elbows on underwater or inaccessible grit piping.  

I. Provide  drives,  lubrication,  and  support  equipment  bearings  accessible  from operating floor level. 

J. No loss of grit removal efficiency for flows with inlet velocity less than 3.5 ft/s.  

K. Provide  inlet  ramp  to  enhance  coanda  effect  and  direct  grit  downward  to separation chamber.  

L. Grit removal system shall fit in grit tank shown on Drawings.  

M. Storage hopper to have 60‐degree sloped bottom with a maximum diameter of 3’‐0” and a minimum depth of 5’‐0”.  

2.03 GRIT CHAMBER EQUIPMENT 

A. Paddles 

1. Upward or downward adjustable grit scouring intensity. 

2. Four blades. 

3. Material: 316 stainless steel  

B. Drive Tube 

1. Driven by large, totally enclosed spur gear and turntable bearing.  

2. Diameter: 10‐3/4 inches minimum. 

3. Material: 316 stainless steel  

C. Propeller Drive Unit (Gear Motor and Gear Head) 

1. Motor 

a. Helical gear type. 

b. 1 HP, 230/460 Volt, 3‐phae, 60 Hz (NEC Class I, Division 1, Group D, explosion proof). 

c. Steel housing and frame. 

d. Service Factor: 2.0 or greater on reducer, 1.15 on motor. 

Page 241: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 5   

e. Thermostats for motor winding protection. 

f. Conform to requirements of Section 40 05 93. 

2. Gears 

a. Alloy steel, heat treated, and hardened. 

b. Teeth: Hobbed and flame hardened.  

c. Helical Gears: Oil lubricated.  

d. Spur Tooth Bull Gear: Large, driven by pinion mounted on output shaft of helical gear motor, enclosed in cast iron or steel case. 

e. Spur Gear Pinion: Cut from heat‐treated steel.  

f. Bull Gear: Rotate with ±21‐inch diameter turntable bearing. 

g. Service Factor  for Pinion and Bull Gear: 5 or greater at  standard operating speeds.  

3. Bull Gear Box 

a. Specifically designed for this service.  

b. Provide opening for propeller drive table. 

c. Seal with air bell at bottom opening around drive tube.  

d. Provide bolted flanged connection at top for grit pump suction.  

4. General Requirements 

a. Maximum Drive Output Speed: 21 rpm.  

b. Suitable for continuous (24 hrs/day year‐round) service. 

c. Bearings shall have minimum B‐10 bearing  life of 100,000 hours, except  21‐inch  diameter  turntable  bearing  which  shall  have minimum B‐10 life of 20 years. 

5. Grit Well Cover Plates 

a. Maximum  3"  opening  between  cover  plate  and  propeller  drive tube.  

b. Two‐piece with lifting loops. 

Page 242: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 6   

c. Stationary, not part of rotating assembly. 

d. Material: 316 stainless steel. 

D. Flow Control 

1. Flow control shall consist of: 

a. Inlet baffle to direct flow across the bottom of the upper chamber and beneath the horizontal perimeter baffle. 

b. Horizontal  perimeter  baffle  to  prevent  short‐circuiting  and rollover. 

2. Material: 316 stainless steel.  

3. Fabricate to dimensions as shown on approved Shop Drawings.  

4. It shall be designed to direct the inlet flow into the chamber in a manner ensuring the proper vortex flow and to prevent short‐circuiting.   

2.04 GRIT PUMP 

A. Pump: 

1. Centrifugal,  vertical  with  vacuum  priming  panel  or  self‐priming, horizontal, centrifugal.  

2. Self‐priming  pump  (if  used)  shall  be  Gorman‐Rupp  Super  Series  T  with replaceable wear plate. 

3. Ni‐Hard impeller. 

4. Shaft: 4130 alloy steel or stainless steel 

5. Mechanical seal. 

6. Size: 4” suction, 4” discharge. 

7. Capable of passing 3” sphere. 

8. Capacity: 250 GPM at 30 feet TDH.  

B. Motor: 

1. 7.5 HP (minimum), 1760 RPM, 230/460 Volt, 3 phase, 60 hertz (NEC Class I, Division 1, Group D, explosion‐proof). 

Page 243: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 7   

2. Class F insulation, Class B temperature rise, 1.15 service factor. 

3. Thermostats for motor winding protection. 

4. Conform to requirements of Section 40 05 93. 

2.05 CENTRIFUGAL GRIT CONCENTRATOR (CYCLONE) 

A. Mounted on grit washer/dewatering screw with supports by Manufacturer.  

B. Capacity: 250 GPM  

C. Operates on the constant rate vortex principle.  

D. Purpose: Removes water and organics from grit mixture pumped by grit pump to grit dewatering screw. 

E. Flow Pattern: 

1. Pumped flow enters tangentially through side. 

2. Grit  and  small  volume  of  water  exit  out  bottom  into  hopper  of dewatering screw. 

3. Organic material and rest of water exit out top to drain. 

4. Minimum  93%  removal  of  influent  water  and  95%  removal  influent organics. 

5. Less than 5% putrescible material in recovered grit from underflow. 

F. Material: Minimum 1/2" Ni‐Hard, high nickel iron coated with minimum 6 mil dry film thickness epoxy resin or equally abrasion‐resistant material as approved by the Engineer.  

G. No moving parts.  

2.06 GRIT WASHER/DEWATERING SCREW CONVEYOR 

A. General: 

1. Provide  inlet  hopper  to  receive mixture  of  grit  and water  at  250 GPM, sufficiently large to allow grit to settle out of water.  

2. Provide 4” overflow in inlet hopper. 

Page 244: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 8   

3. Provide unit as freestanding with support legs to hold conveyor at 16 or 22 angle from horizontal.  

4. Drive screw conveyor with gear motor mounted on discharge end.  

5. Provide heated jacket for grit hopper and screw trough. 

B. Construction 

1. Screw 

a. Diameter: 9 to 12 inches 

b. Length: 9 to 15 feet 

c. Material: 316 stainless steel 

d. Shaftless screws not allowed due to wear or loss of grit. 

2. Screw Bearings 

a. Outlet End: Anti‐friction type.  

b. Inlet End: Greaseable bronze bushing mounted to outside end.  

3. Screw Trough 

a. Material: 316 stainless steel 

b. Open minimum 3/16” thick steel formed, U‐shaped.  

c. Provide 2” diameter drain at inlet end.  

d. Provide 8” outlet.  

4. Inlet Hopper 

a. Material: 316 stainless steel.  

b. Overflow:  Full‐length,  double‐sided outlet weir  trough with  4‐in. flange.  

c. Slope three sides of hopper at least 50 degrees to horizontal. 

d. Projected Surface Area: 17 square feet, minimum. 

e. Parallel  plates  to  improve  retention  of  fine  grit,  and  to  comply with surface area for settling as required. 

Page 245: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 9   

5. Drive 

a. Provide belt‐driven shaft‐mounted helical gear reducer or direct‐connected cycloidal‐helical speed reducer. 

b. Mount  on  plate  bolted  to  flanges  of  screw  trough  at  discharge end. 

6. Motor 

a. 3  HP,  230/460  Volt,  3‐phase,  60  hertz.  (NEC  Class  I,  Division  1, Group D, explosion proof). 

b. Thermostats for motor winding protection. 

c. Provide in accordance with Section 40 05 93. 

7. Cover 

a. Material: 316 stainless steel 

b. Solid  split  cover  to  prevent  heat  loss  during  the  winter,  and provided with hinges and handles for access.  

c. Opening under concentrator not covered to allow  incoming  flow to enter unit.  

8. Wash Water Requirements: 

a. 20 GPM at 60 psig of plant effluent.  

b. Intermittent.   

2.07 VACUUM PRIMING PANEL (IF REQUIRED FOR GRIT PUMP) 

A. Panel 

1. Suitable  for  outdoor  use  and  NEC  Class  I,  Division  2,  Group  D  area classification, unless suitable non‐classified location (at least 10‐feet from grit  chamber)  is  recommended  by  Manufacturer  and  approved  by  the Engineer. 

2. Mounted  on  paddle  drive  unit,  unless  otherwise  approved  by  the Engineer. 

B. Panel Mounted Devices 

Page 246: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 10   

1. Vacuum Pump: 

a. Corrosion resistant internal components.  

b. Sized to prime pump and piping in less than 60 seconds.  

2. Air Compressor: 

a. Oil‐less 

C. Priming System 

1. Consists  of  vacuum  pump,  vacuum  control  solenoid  valve,  prime  level sensing probe, and float operated check valve. 

2. Positive lubrication of mechanical seal.  

3. Minimum passageway equivalent to 2‐1/2" opening.  

4. Prime from low‐pressure area of pump.  

5. Provide heated jacket for vacuum priming dome and priming sensor. 

D. Pinch Valve 

1. On pump discharge line. 

2. In vertical piping.  

3. 4" diameter.  

4. Pneumatically controlled.  

5. Provide heated jacket for pinch valve. 

2.08 SHOP PAINTING 

A. Surface Preparation 

1. All non‐stainless structural steel surfaces shot blasted with steel grit.  

2. Weld splatter and surface roughness removed by grinding. 

3. Comply with SSPC‐SP6 specifications.  

B. Coating ‐ Grit Mechanism, Concentrator, and Conveyor 

Page 247: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 11   

1. Primer:  open  recoat window,  Tnemec  Series  1 Omnithane Primer,  2.5  ‐ 3.5 mils dry film thickness. 

2. First coating: Epoxy Polyamidoamine Primer, Tnemec Series N69 Hi‐Build Epoxoline II, 3.0 ‐ 5.0 mils dry film thickness. 

3. Second  coating:  Epoxy  Polyamidoamine  Primer,  Tnemec  Series  N69  Hi‐Build Epoxoline II, 3.0 ‐ 5.0 mils dry film thickness. 

4. Finish coating: Polyurethane Finish, Tnemec Series 73, Endura‐Shield   

5. An equivalent VERSAPOX® epoxy resin coating system may be submitted to the Engineer for approval.  

2.09 DATA PLATES   

A. All data plates shall be furnished per Section 01 60 00.  

2.010 HARDWARE 

A. Manufacturer shall furnish all required hardware and anchor bolts per Section 01 60 00. All exposed hardware shall be AISI 316/316L stainless steel. 

2.011 SPARE PARTS 

A. One (1) set of Manufacturer’s standard spare parts shall be furnished. 

B. One (1) complete spare pump rotating assembly  (volute,  impeller, shaft,  speed reducer (if used), bearings, seals, and motor). 

C. Spare  parts  shall  be  packaged  in  accordance  with  Section  01  60  00,  Product Requirements. 

PART 3 EXECUTION    

3.01 FACTORY TESTING 

A. The equipment  specified herein  shall  be  factory  assembles  and  tested prior  to shipment. 

B. A  certified  factory  test  report  shall  be  submitted  to  the  Engineer  prior  to shipment per Section 01 33 00. 

3.02 PRODUCT SHIPMENT AND PROTECTION 

A. The  equipment  specified  herein  shall  be  packaged  and  shipped  in  accordance with Section 01 60 00, Product Requirements. 

Page 248: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 12   

3.03 INSTALLATION 

A. Installing Contractor  shall  install  the  equipment  specified herein  in  accordance with the Manufacturer's recommendations and as shown on the Drawings.    

B. Manufacturer’s  representative  shall  inspect  the  installation  as  specified  in Specification Section 01 75 00, Testing and Commissioning and shall also verify: 

1. Installation is in accordance with Manufacturer’s installation checklist and recommendations. 

2. Grit chamber is grouted as required. 

3. Equipment is properly supported and supports anchored. 

4. Exposed, non‐stainless steel metal components finish coated as required.  

5. Wash water piping is properly installed and pressure tested. 

6. Lubricants are applied as required. 

7. Grit paddle, pump, and grit conveyor rotational direction are correct. 

8. Motor nameplate data matches approved submittals. 

9. Motors are properly installed in accordance with Section 40 05 93 and motor manufacturer’s instructions. 

10. Vacuum priming panel is properly wired and grounded, and wiring tested, as applicable. 

11. Vacuum priming air tubing and pinch valve are properly installed, as applicable. 

12. Heat tracing installed and wired and insulation installed. 

C. Manufacturer’s  qualified  service  representative  shall  provide  a  minimum  of  8 hours for installation inspection.  

3.04 FIELD TESTING 

A. On‐site  field  testing  shall  comply  with  the  requirements  of  Section  01  75  00, Testing and Commissioning.  Testing shall also include: 

1. Testing  the  vacuum priming  system  for  automatic  operation  and  status indication, as applicable. 

Page 249: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 13   

2. Testing  the  entire  the  grit  removal  system  in  manual  and  automatic operation. 

3. Verifying heat tracing operation. 

B. Motor field testing shall comply with Section 40 05 93.  

C. Manufacturer’s  service  representative  shall  certify  the  installation  and  field testing  in  accordance  with  Section  01  75  00,  Testing  and  Commissioning Procedures, and shall submit the completed Certificate of  Installation and Field Testing Form at the end of this Section. 

D. Manufacturer’s  qualified  service  representative  shall  provide  a minimum of  12 hours of on‐site testing of the equipment specified herein. 

3.05 TRAINING  

A. Manufacturer’s  qualified  service  representative  shall  provide  a  minimum  of  4 hours of training of the Owner’s staff  in the operation and maintenance of the equipment specified herein.  

B. Training shall meet the requirements of Section 01 79 00, Training. 

*** END OF SECTION *** 

Page 250: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 23 00 Grit Removal Equipment.doc  46 23 00 ‐ 14   

FORM 46 23 00‐1 CERTIFICATE OF INSTALLATION AND TESTING OF  GRIT REMOVAL EQUIPMENT 

MANUFACTURER NAME:   PROJECT NAME:  

EQUIPMENT SCHEDULE NO.:  NAME OF EQUIPMENT: 

LOCATION/SERVICE:  SPECIFICATION SECTION: 

MANUFACTURER:  SIZE OF CHAMBER: 

MODEL NUMBER:  SERIAL NO.: 

PADDLE MOTOR HP:  VOLTS:  HERTZ:  PHASE: 

FLA:  MOTOR RPM:  SERVICE FACTOR:  MOTOR EFFICIENCY: 

PUMP MOTOR HP:  VOLTS:  HERTZ:  PHASE: 

FLA:  MOTOR RPM:  SERVICE FACTOR:  MOTOR EFFICIENCY: 

WASHER MOTOR HP:  VOLTS:  HERTZ:  PHASE: 

FLA:  MOTOR RPM:  SERVICE FACTOR:  MOTOR EFFICIENCY: 

INSTALLATION INSPECTION (CHECK IF VERIFIED) 

MFR CHECKLIST SUBMITTED:  MOTOR GROUNDED:  VACUUM TUBING INSTALLED:  VACUUM PANEL WIRED: 

CHAMBER GROUTED:  CHAMBER CLEANED:  PIPE/EQUIPMENT SUPPORTS:  PIPE PRESSURE TESTED: 

SHAFT ALIGNMENT:  LUBRICATION:  PROPER ROTATION:  GUARDS/SAFETY: 

SUPPLY VOLTAGE:  HEAT TRACING/INSULATION:  PINCH VALVE TESTED:  OTHER: 

MISSING OR DAMAGED PARTS/TOOLS (LIST): 

FIELD TEST 

PADDLE RUN IN HAND:    SYSTEM RUN IN AUTO:   

RUN STATUS INDICATION:    PADDLE EMERGENCY STOP:   

PUMP AND VACUUM PANEL IN HAND:    WASHER EMERGENCY STOP:   

RUN STATUS INDICATION:    MOTOR OT STATUS ALARMS:   

WASHER RUN IN HAND:   WASHWATER SOLENOIDS OPERATION IN HAND/AUTO: 

 

RUN STATUS INDICATION:    HEAT TRACING IN AUTO:   

COMMENTS: 

As the Manufacturer’s Representative, I certify that I have inspected the installation of the equipment, the equipment has been installed in accordance with the manufacturer's recommendations, I have witnessed all applicable field tests, all proper adjustments have been made, the equipment meets the performance requirements of the Contract Specifications, and the equipment is ready for plant commissioning and operation. 

 SELLER/MANUFACTURER  

CHECK OFF  INSTALLER CHECK OFF  WITNESS CHECK OFF 

NAME       

SIGNATURE       

DATE       

 

Page 251: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 1

SECTION 46 41 34 VERTICAL TURBINE MIXERS

PART 1 GENERAL 1.01 DESCRIPTION OF WORK

A. Manufacturer shall furnish two (2) heavy duty vertical-shaft axial-type mixers.

B. The work shall include fabrication, factory-testing, delivery, installation inspection, field testing, certification of installation and field testing, and training.

1.02 RELATED WORK

A. Division 0 – Bid Documents

B. Division 1 – General Requirements

C. Section 40 05 93 - Common Motor Requirements for Process Equipment

1.03 REFERENCE STANDARDS

A. AFBMA - Anti-Friction Bearing Manufacturers Association

1. AFBMA Standard 11 - Load Ratings and Fatigue Life for Roller Bearings

B. AGMA - American Gear Manufacturers Association

1. AGMA 390.03 - Gear Handbook Volume 1: Gear Classification, Materials and Measuring Methods for Unassembled Gears.

2. AGMA 299.01 - Sound Manual.

C. AGMA 6010.E88 - Spur, Helical, Herringbone and Bevel Enclosed Drives.

D. AIChE - American Institute of Chemical Engineers

1. Method for Evaluating Mixing Equipment, Impeller Type; 2nd. Edition.

E. ANSI - American National Standards Institute

F. ASTM - American Society for Testing and Materials

1. ASTM A36 - Standard Specification for Carbon Structural Steel

Page 252: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 2

2. ASTM A240 - Standard Specification for Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications

3. ASTM A276 - Standard Specification for Stainless Steel Bars and Shapes

4. ASTM A314 - Standard Specification for Stainless Steel Billets and Bars for Forging

5. ASTM A967 - Standard Specification for Chemical Passivation Treatments for Stainless Steel Parts

G. NEMA - National Electrical Manufacturers Association

1. NEMA MG 1 - Motors and Generators

H. OSHA - Occupational Safety and Health Administration, Code of Federal Regulations (CFR 29)

I. SAE International - Society of Automotive Engineers

1. SAE J431 - Automotive Gray Iron Castings

2. SAE 316 (UNS S31600) – 316 Stainless Steel

3. SAE 316L (UNS S31603) – 316L Stainless Steel

J. UL - Underwriters Laboratories

1.04 SUBMITTALS

A. Furnish submittals in accordance with Section 01 33 00 - Submittal Procedures and including:

1. Drawings showing complete dimensional data of the proposed mixer design including the mixer outline dimensions, mixer drive, output coupling, and impeller assembly data and mounting details.

2. The weight of the complete mixer assembly and each component; motor, gearbox, shafting and impellers.

3. Details of the coupling-shaft sleeve arrangement and axial and torque load calculations.

4. Description of surface preparation of all components and shop priming and finish painting of components requiring coating.

Page 253: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 3

5. Mixer design calculations and process design calculations.

6. Design thrust, torque, and bending moment loads.

7. Certified test data demonstrating the specified pumping rate, power, tip speed and velocity gradient. Testing shall be in accordance with the A.I.Ch.E procedure, Method for Evaluating Mixing Equipment, Impeller Type; 2nd. Edition.

8. Warranty as specified herein.

9. Motor data as required in Section 43 05 93.

B. Certified Factory Test Reports as specified herein.

C. Bill of Materials per Section 01 33 00.

D. Field erection requirements per Section 01 33 00.

E. Manufacturer's warranties as specified herein.

F. Operation and Maintenance Manuals: Furnish in accordance with Section 01 78 00, Close-Out Submittals.

1.05 QUALIFICATIONS

A. The manufacturer of the products specified in the Section shall be fully experienced, qualified, and reputable in the manufacture of such equipment.

B. The manufacturer shall have at least 50 installations in the United States of the model specified in satisfactory operation for at least 10 years.

C. Manufacturer shall have a qualified factory-trained representative and service center qualified in repair of the mixers permanently located within a 300-mile radius of the project site.

1.06 WARRANTY

A. Manufacturer shall warrant the materials and equipment specified herein to be free of defects in materials and workmanship for a period of two (2) years from the Date of Manufacturer’s Certificate of Installation and Field Testing.

Page 254: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 4

PART 2 PRODUCTS 2.01 MANUFACTURER

A. ANCO Mixers Series 3000 by Enviropax, Inc., Salt Lake City, Utah.

B. Lightnin Mixers Series 10 by SPX Flow Technology, Rochester, New York.

C. Engineer-approved equal. Refer to Section 00 20 00 Instructions to Bidders Article 10 for procedure for approval.

2.02 GENERAL

A. The mixers shall be complete assemblies including but not limited to the gear reducers, motors, shafting, impellers, couplings, mounting bases, anchor bolts, and other appurtenant equipment necessary to be complete and operable in accordance with the requirements of the contract documents.

2.03 MATERIALS

A. All submerged parts including the mixer shaft and impeller shall be constructed of SAE type 316/316L stainless steel.

B. All fasteners required for assembly of submerged parts shall be SAE type 316/316L stainless steel.

C. The minimum material thickness for impeller fabrication is 3/16 inch.

2.04 DESIGN CRITERIA

A. Equipment Schedule Number: Q-A-1, -2

B. Basins:

1. Number of basins: 2

2. Width: 15’-0”

3. Length: 17’-0”

4. Side water depth (SWD), maximum: 18’-3”

5. Side water depth (SWD), minimum: 17’-9”

6. Freeboard @ maximum SWD: 2’-9”

Page 255: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 5

7. Mounting height above bottom, feet: 21’-0”

8. Volume at maximum SWD, gallons, each: 34,810

9. Flow to each basin, minimum: 0.5 MGD (both basins in service at start-up flow + 100% RAS + 300% MLR)

10. Flow to each basin, maximum: 3 MGD (2 basins in service at peak design flow + 100% RAS + 300% MLR of maximum month design flow)

11. Detention time per basin, maximum: 100 minutes at minimum flow and minimum level

12. Detention time per basin, minimum: 16.7 minutes at maximum flow and level

13. Design water temperature: 10 to 20 deg C (50 to 68 deg F)

14. Design ambient temperature: -35 deg F to 100 deg F

C. Impeller

1. Type: Axial – high efficiency

2. Number per Shaft: 1

3. Number of blades, min.: 3 ea.

4. Diameter, min.: 76”

5. Speed, max.: 19.3 RPM

6. Speed, min.: 1.9 RPM (with Variable Speed Drive)

7. Tip speed (ft/sec), max.: 6.4

8. Tip speed (ft/sec), min.: 0.6

9. Submergence: 147”

10. Impeller centerline distance from bottom, max.: 72 inches

11. Turnover rate, minimum: 0.63 times per minute

12. Pumping rate at maximum speed, min.: 21,983 GPM

D. Shaft

Page 256: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 6

1. Shaft diameter, min.: 2.0”

2. % critical speed, maximum: 40%

E. Support

1. Mechanism weight, maximum: 1,100 lbs

2. Torque at motor HP, maximum: 8,550 in-lb

3. Bending moment, maximum: 15,000 in-lb

4. Supports shall be sized for minimum 2.5 times the weight, torque, and bending moment.

2.05 DRIVE ASSEMBLY

A. Mixer drive mounting:

1. Speed reducer and motor factory-mounted to a common open type factory manufactured extended pedestal base that provides access to the low speed impeller shaft coupling above the mounting platform.

2. Base material: ASTM A36 carbon steel.

B. Speed reducer: Vertical, all helical gear design.

1. Gearbox: AGMA Class II 24-hour continuous service under moderate shock conditions in an outdoor environment.

2. Reducer case: High strength grey cast iron or ductile iron, SAE Class 30.

3. Gears:

a. Carburized to a hardness of 58-62 Rockwell C. b. Finish ground to a minimum AGMA Class 10 quality level. c. Gearbox efficiency, min.: 95 percent d. Gearing shall be designed to withstand normal and shock loads

transmitted from lower shaft and impeller.

4. Lifting lugs: Speed reducer shall be provided with lifting lugs suitable for lifting the complete mixing unit. If lifting lugs are not able to be supplied, Manufacturer shall recommend and submit alternate method for lifting speed reducer.

5. Speed reducer thermal rating shall exceed the mechanical rating to eliminate the need for external coolers.

Page 257: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 7

6. Speed reducer service factor, minimum: AGMA 3.0 based on the motor nameplate horsepower rating.

7. AGMA nameplate shall be required for speed reducer.

8. Full load operating noise level:

a. Per OSHA occupational noise standards or AGMA 299.01.

b. Less than 85 dBA at a distance of 3-feet.

C. Lubrication system:

1. All-weather starting and operation of the unit without external heaters or primers.

2. Dipstick or sight glass to observe oil levels.

3. Oil drain at low point of reducer.

4. Normally accessible fill and drain lines.

5. Oil change frequency: < 8,000-hour intervals.

6. Low speed shaft seals:

a. One internal spring-loaded double lip seal, or equivalent sealing method.

b. Dual external spring-loaded double lip seals and a dry cavity between the seals which shall contain the lower grease lubricated output shaft bearings.

7. Speed reducer breather: located above possible oil foam level.

8. Motor changes and oil changes: shall not require the removal of the speed reducer from its foundation.

9. Drives to be shipped with oil filled to the proper level for operation or filled in the field by the Manufacturer’s Representative.

10. Dry Well: The low-speed shaft design shall incorporate a dry well to prevent oil leakage along the drive output shaft. The top surface of the dry well shall be sufficiently above the dynamic oil level of the gear drive.

D. Bearings:

Page 258: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 8

1. Type: roller, anti-friction, oil-lubricated

2. Mixer drive gearbox bearings: minimum AFBMA L10 life of 100,000 hours.

3. Output bearings: minimum AFBMA L10 life of 300,000 hours.

2.06 MOTOR

A. Motors shall meet the requirements of Section 40 05 93.

B. Motors shall have the following characteristics:

1. Motor horsepower, minimum: 1

2. Duty: Severe duty (CISD), continuous operation

3. Enclosure: TEFC

4. Nominal synchronous (60 hertz speed): 1,800 RPM

5. Voltage: 460 volts

6. Phase: 3

7. Nominal frequency: 60 hertz

8. Efficiency: Premium efficient per NEMA MG 1 Table 12-12

9. Inverter-duty per NEMA MG1

10. Insulation: Class F

11. Motor protection: Imbedded thermostats, one (1) per winding (normally closed)

C. The electric drive motor shall be connected to the speed reducer through a flexible coupling.

2.07 LOW SPEED COUPLING

A. Gearbox Output Shaft and Vertical Impeller Shaft Connection

1. Type 1: Flanged

a. The upper coupling half shall keyed on the speed reducer output shaft and shall be held in place by a retainer washer and bolt in the end of the gearbox output shaft.

Page 259: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 9

b. The lower mixer shaft coupling half shall be welded to the mixer shaft, or by an alternate connection approved by the Engineer.

2. Type 2: Split Coupling

a. The mixer shaft shall be connected to the output shaft of the speed reducer by means of a split removable coupling accessible from outside the tank and located above the reducer.

B. Coupling halves

1. Material: Solid round bar of 316 stainless steel

2. Machining: Couplings shall be turned and faced to provide a precision machined register fit, unless otherwise approved by the Engineer.

3. The coupling halves shall be bolted together through the flanges with plated bolts, unless otherwise approved by the Engineer.

C. Loads: The coupling assembly shall be designed to transmit 200 percent of the full torque and 150 percent of the axial load on the coupling.

2.08 IMPELLER SHAFT

A. Material: Solid round bar of 316 stainless steel

B. Sizing:

1. The impeller shaft shall be sized so the maximum operating speed of the impeller and shaft assembly does not exceed 40% of the first natural critical speed. The weight of both the shaft and the impeller assembly shall be taken into account in calculating the critical speed.

2. The shaft diameter shall be determined by an analysis of shaft stresses caused by torque and bending moments as well as critical speed but shall in no case be less than indicated herein.

3. The combined shaft stress shall not exceed 8,000 psi.

C. Straightening: to within ¼ inch for every ten feet of length.

2.09 IMPELLER ASSEMBLY

A. The impellers shall be of the axial flow type designed with a contoured blade for high efficiency.

Page 260: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 10

B. The impellers shall produce the specified pumping rate with a minimum of turbulence as characterized by a relatively uniform velocity profile across the entire diameter of the impeller.

C. The assembly shall be made up of an impeller hub with the blades being bolted onto the hub.

D. The hub shall have not less than 3 blades evenly spaced on the hub having a minimum outside diameter specified herein.

E. The blades shall be set at an angle close to, but not exceeding, the point at which flow separation occurs.

F. All mill scale, rust, and contaminants shall be removed. Sharp corners, cuts or sheared edges shall by dulled by a power grinder or file.

G. The assembled impeller shall be attached to the shaft using a hook-key design to transmit the torque and support the weight of the impeller.

H. The design of the hook-key feature shall be such that with the impeller hub set screw loosened, the impeller cannot slide down the impeller shaft during installation.

I. An extended keyway shall be provided of sufficient length to permit adjustment of the axial position 18 inches up in three-inch increments from the design location.

J. The impeller shall be of such design, and operate at such rotational speed that dynamic balancing is not required to prevent damaging vibration.

2.010 COATINGS

A. Exposed cast iron or (non-stainless) steel components shall receive surface preparation per SSPC-SP6 followed by:

1. Primer: open recoat window, Tnemec Series 1 Omnithane Primer, 2.5 - 3.5 mils dry film thickness.

2. First coating: Epoxy Polyamidoamine Primer, Tnemec Series N69 Hi-Build Epoxoline II, 3.0 - 5.0 mils dry film thickness.

3. Second coating: Epoxy Polyamidoamine Primer, Tnemec Series N69 Hi-Build Epoxoline II, 3.0 - 5.0 mils dry film thickness.

4. Finish coating: Polyurethane Finish, Tnemec Series 73, Endura-Shield

Page 261: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 11

B. Exterior portions of the steel shaft and the motor coupling shall be protected with a waxy film, moisture-excluding coating.

2.011 DATA PLATES

A. All data plates shall be furnished per Section 01 60 00.

2.012 HARDWARE AND ANCHORS

A. Hardware shall be furnished per Section 01 60 00.

B. Manufacturer shall furnish all required 316 stainless steel anchors.

2.013 SPARE PARTS AND SPECIAL TOOLS

A. Manufacturer shall furnish one (1) set of standard spare parts and special tools.

1. All spare parts for one year’s normal operation and maintenance of the equipment, including lubricants.

2. As minimum, one spare set of seals and gaskets shall be included for each size of drive.

3. Special tools required for the proper servicing of mixers.

B. Spare parts shall be packaged in accordance with Section 01 60 00, Product Requirements.

PART 3 EXECUTION 3.01 FACTORY TESTING

A. Each drive shall be completely shop assembled and factory tested to assure proper fit-up, and acceptable limits of vibration, shaft run out and motor power draw, prior to shipment.

B. A certified factory test report shall be submitted to the Engineer prior to shipment per Section 01 33 00.

3.02 PRODUCT SHIPMENT AND PROTECTION

A. The equipment specified herein shall be packaged and shipped in accordance with Section 01 60 00, Product Requirements.

B. All gears and bearings shall be protected from rusting during storage by the application of a shop applied protective coating.

Page 262: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 12

3.03 INSTALLATION

A. Installing Contractor shall install the equipment specified herein in accordance with the Manufacturer's recommendations and as shown on the Drawings.

B. Manufacturer’s representative shall inspect the installation as specified in Specification Section 01 75 00, Testing and Commissioning and shall also verify:

1. Installation is in accordance with Manufacturer’s installation checklist and recommendations.

2. Basin is cleared of debris.

3. Drive base is level, anchored, and grouted.

4. Anchor bolts tightened and applied with anti-seize compound.

5. Exposed, non-stainless steel metal components finish-coated as required.

6. Lubricants are applied as required.

7. Impeller shaft properly aligned.

8. Impeller rotational direction is correct.

9. Motor nameplate data matches approved submittals.

10. Motors are properly installed and grounded in accordance with Section 40 05 93 and motor manufacturer’s instructions.

C. Manufacturer’s qualified service representative shall provide a minimum of 8 hours for installation inspection.

3.04 FIELD TESTING

A. On-site field testing shall comply with the requirements of Section 01 75 00, Testing and Commissioning. Testing shall also include:

1. Vibration testing to determine that the mixers do not exceed acceptable field vibration limits throughout the mixer operating range.

2. Testing the motor thermostat contacts.

3. Measuring the motor current and voltage at maximum and minimum operating speeds at the specified operating conditions.

B. Motor field testing shall comply with Section 40 05 93.

Page 263: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 13

C. Manufacturer’s service representative shall certify the installation and field testing in accordance with Section 01 75 00, Testing and Commissioning Procedures, and shall submit the completed Certificate of Installation and Field Testing Form at the end of this Section.

D. Manufacturer’s qualified service representative shall provide a minimum of 6 hours of on-site testing of the equipment specified herein.

3.05 TRAINING

A. Manufacturer’s qualified service representative shall provide a minimum of 2 hours of training of the Owner’s staff for operation and maintenance of the equipment specified herein.

B. Training shall meet the requirements of Section 01 79 00, Training.

*** END OF SECTION ***

Page 264: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 41 34 Vertical Turbine Mixers.doc 46 41 34 - 14

FORM 46 41 34-1 CERTIFICATE OF INSTALLATION AND TESTING OF VERTICAL TURBINE MIXER

MANUFACTURER NAME: PROJECT NAME:

EQUIPMENT SCHEDULE NO.: NAME OF EQUIPMENT:

LOCATION/SERVICE: SPECIFICATION SECTION:

MANUFACTURER: IMPELLER SIZE (INCHES):

MODEL NUMBER: SERIAL NO.:

MOTOR HP: VOLTS: HERTZ: PHASE:

FLA: MOTOR RPM: SERVICE FACTOR: MOTOR EFFICIENCY:

INSTALLATION INSPECTION (CHECK IF VERIFIED)

MFR CHECKLIST SUBMITTED: BASIN CLEANED/LEAK TESTED:

BASE LEVEL/ANCHORED: BASE GROUTED:

BOLTS TIGHTENED/ANTI-SEIZE COMPOUND:

SHAFT ALIGNMENT: LUBRICATION: PROPER ROTATION:

SUPPLY VOLTAGE: MOTOR GROUNDED: GUARDS/SAFETY: OTHER:

MISSING OR DAMAGED PARTS/TOOLS (LIST):

FIELD TEST

MANUAL RUN IN HAND: VOLTAGE AT 60 HZ

AUTO RUN IN REMOTE: AMPERAGE AT 60 HZ

RUN STATUS INDICATION: VIBRATION AT 60 HZ

AUTO STATUS INDICATION: VFD MIN SPEED, (10 HZ DEFAULT), HZ

LOCAL STATUS INDICATION: VOLTAGE AT MINIMUM SPEED

MOTOR OT STATUS ALARM INDICATION: AMPERAGE AT MINIMUM SPEED

VFD COMMON ALARM INDICATION: VIBRATION AT MINIMUM SPEED

COMMENTS:

As the Manufacturer’s Representative, I certify that I have inspected the installation of the equipment, the equipment has been installed in accordance with the manufacturer's recommendations, I have witnessed all applicable field tests, all proper adjustments have been made, the equipment meets the performance requirements of the Contract Specifications, and the equipment is ready for plant commissioning and operation.

SELLER/MANUFACTURER

CHECK OFF INSTALLER CHECK OFF WITNESS CHECK OFF

NAME

SIGNATURE

DATE

Page 265: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 1   

SECTION 46 51 33 FINE BUBBLE DIFFUSERS 

 PART 1 GENERAL 

 1.01 DESCRIPTION OF WORK 

A. Manufacturer shall furnish a flexible membrane disc diffuser aeration system in the new aeration basin and a separate flexible membrane disc diffuser aeration system in the existing oxidation ditch as specified herein, complete. 

B. The scope of work shall include fabrication, factory testing, delivery, installation inspection,  field  testing,  certification  of  installation  and  field  testing,  and training. 

C. The  diffuser  aeration  system  to  be  furnished  for  the  new  aeration  basin  per Paragraph 1.05B shall be the Base Bid and the diffuser aeration system for  the oxidation ditch per Paragraph 1.05C shall be the additive alternate. 

1.02 RELATED WORK 

A. Division 0 – Bid Documents 

B. Division 1 – General Requirements 

1.03 REFERENCE STANDARDS 

A. Equipment and materials specified in this section shall comply with the following reference standards as applicable: 

B. ASTM International (American Society for Testing and Materials): 

1. ASTM  A‐240/A240M‐15a  Standard  Specification  for  Chromium  and Chromium‐Nickel  Stainless  Steel  Plate,  Sheet,  and  Strip  for  Pressure Vessels and for General Applications  

2. ASTM A276/A276M‐15 Standard Specification for Stainless Steel Bars and Shapes 

3. ASTM  A380/A380M‐13  Standard  Practice  for  Cleaning,  Descaling,  and Passivation of Stainless Steel Parts, Equipment, and Systems 

4. ASTM  A554‐15a  Standard  Specification  for  Welded  Stainless  Steel Mechanical Tubing 

Page 266: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 2   

5. ASTM  A774/A774M‐14  Standard  Specification  for  As‐Welded  Wrought Austenitic  Stainless  Steel  Fittings  for  General  Corrosive  Service  at  Low and Moderate Temperatures 

6. ASTM  A778/A778M‐15  Standard  Specification  for  Welded,  Unannealed Austenitic Stainless Steel Tubular Products   

7. ASTM  D412‐06a  Standard  Test  Methods  for  Vulcanized  Rubber  and Thermoplastic Elastomers—Tension 

8. ASTM D573‐04 Standard Test Method for Rubber ‐ Deterioration in an Air Oven 

9. ASTM  D1171‐99  Standard  Test  Method  for  Rubber  Deterioration  ‐ Surface Ozone Cracking Outdoors or Chamber (Triangular Specimens) 

10. ASTM  D1784‐11  Standard  Specification  for  Rigid  Poly(Vinyl  Chloride) (PVC)  Compounds  and  Chlorinated  Poly(Vinyl  Chloride)  (CPVC) Compounds 

11. ASTM  D1785‐15  Standard  Specification  for  Poly(Vinyl  Chloride)  (PVC) Plastic Pipe, Schedules 40, 80, and 120 

12. ASTM D2240‐05 Standard Test Method for Rubber Property ‐ Durometer Hardness 

13. ASTM  D2466‐15  Standard  Specification  for  Poly(Vinyl  Chloride)  (PVC) Plastic Pipe Fittings, Schedule 40 

14. ASTM  D2665‐14  Standard  Specification  for  Poly(Vinyl  Chloride)  (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings 

15. ASTM  D2467‐15  Standard  Specification  for  Poly(Vinyl  Chloride)  (PVC) Plastic Pipe Fittings, Schedule 80 

16. ASTM  D3034‐14a  Standard  Specification  for  Type  PSM  Poly(Vinyl Chloride) (PVC) Sewer Pipe and Fittings 

17. ASTM  D3915‐06  Standard  Specification  for  Rigid  Poly(Vinyl  Chloride) (PVC) and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds for Plastic Pipe and Fittings Used in Pressure Applications    

C. American National Standards Institute (ANSI) 

1. ANSI B16.1 ‐ Cast Iron Pipe Flanges and Flanged Fittings   

Page 267: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 3   

D. Military Standard 

1. MIL‐STD‐105E:  Sampling  Procedures  and  Tables  for  Inspection  by Attributes 

E. American Society of Civil Engineers (ASCE) 

1. ASCE Standard for the Measurement of Oxygen Transfer  in Clean Water (2‐06)  

1.04 SUBMITTALS 

A. Furnish submittals in accordance with Section 01 33 00, Submittal Procedures.  

1. Shop Drawings: Shop Drawings shall also include the following:  

a. General  arrangement  drawings  showing  plan  views  and  cross sections of the equipment as installed in the aeration tanks.  

b. Detail drawings of standard system components including diffuser assemblies,  gaskets,  retainer  rings,  supports,  joints,  and  blow‐off/moisture assemblies. 

c. Fabrication drawings showing details of distribution laterals, drop‐legs, manifolds, and pipe joints and couplings.  

d. Detail drawings of pipe supports and hardware. 

e. Detailed layouts of anchor bolt locations and anchor bolt technical information.  

2. Product Data: Product Data Submittal shall include the following: 

a. Manufacturer’s catalog information. 

b. Manufacturer’s specifications for materials and manufacturing. 

c. Detailed information for all ancillary  items such as hardware and supports, etc. 

3. Design  calculations  and  performance  curves  demonstrating  compliance with  all  performance  requirements  specified  in  Paragraphs  1.05B  and 1.05C, such as: 

a. Calculations determining the volumetric air flow rate per diffuser, number  of  diffusers,  diffuser  density,  diffuser  submergence,  to comply with the specified Standard Oxygen Transfer Rate (SOTR). 

Page 268: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 4   

b. Performance curve of SOTE versus SCFM per diffuser. 

c. Calculations  determining  the  entire  pressure  loss  through aeration  system  including  the  pressure  losses  through  the  drop leg, manifold, air distribution laterals, and diffusers. 

d. Calculations  demonstrating  that  the  system  design  will  provide uniform  air  distribution  within  10%  variation  through  lateral piping and diffuser assemblies. 

e. Performance  curve  of  diffuser  pressure  loss  in  inches  water column versus air flow rate per diffuser in standard cubic feet per minute (SCFM at 20 deg C, 14.7 PSIA, and 36% relative humidity). 

4. Certified oxygen transfer test report from factory oxygen transfer tests or procedures for performance testing in accordance with Paragraph 1.05D. 

5. A list of successful operating aeration systems and evidence of adequate oxygen  transfer  test  data  indicating  compliance  with  the  specified experience and testing requirements in Paragraph 1.06. 

B. Calculations stamped by a licensed Professional Engineer demonstrating that the specified  pipe  support  and  expansion/contraction  requirements  are  met including determining the following: 

1. Uplift forces due to buoyancy. 

2. Downward forces due to weight. 

3. Pipe support load capacity. 

4. Support anchor bolt uplift force. 

5. Support anchor bolt load capacity. 

6. Support anchor pullout safety factor. 

7. Pipe support band clamp friction force. 

8. Pipe maximum thermal expansion and contraction. 

9. Pipe allowable thermal expansion and contraction. 

10. Pipe expansion force due to thermal expansion. 

11. Support rod stress due to pipe expansion and band clamp friction force, and support rod yield strength. 

Page 269: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 5   

12. Pipe support band clamp stress and yield strength.   

C. Certified  test  report  verifying  membrane  longevity  as  required  in  Paragraph 2.03E.  In lieu of providing the certified test report verifying membrane longevity, Manufacturer may provide a three (3) year warranty (instead of two (2) year) per Paragraph 1.07A and testing on the installed diffusers per Paragraph 2.03E. 

D. Calculations  determining  the  minimum  submerged  stainless  steel  pipe  length required for air cooling in accordance with Paragraph 2.04D. 

E. Procedures  for  product  quality  control  testing,  as  required  in  Paragraph  3.01, including membrane durometer,  tensile strength, modulus of elasticity, specific gravity, dynamic wet pressure, and air flow uniformity. 

F. Certified Factory Test Reports as specified in Paragraph 3.01. 

G. Bill of Materials per Section 01 33 00. 

H. Field erection requirements per Section 01 33 00. 

I. Manufacturer's warranty as specified in Paragraph 1.07. 

J. Operation and Maintenance Manual: Furnish  in accordance with Section 01 78 00, Close‐Out Submittals. 

1.05 PERFORMANCE CRITERIA 

A. Overall Layout and Design 

1. Diffuser aeration  systems  shall be  installed  in accordance with  the  tank dimensions listed herein and as shown on the Contract Drawings.  

2. Air piping shall enter the basins as shown on the Contract Drawings and Manufacturer shall be responsible for proper connection at the  location shown. 

3. Manufacturer  shall  be  responsible  for  design  and  fabrication  of  entire aeration system from drop leg connection at top of tank wall.  

4. System shall be designed for uniform air release over the entire diffuser coverage area and over the specified volumetric air flow range.  

5. Air  distributors  shall  be  designed  with  centerline  spacing  to  maximize oxygen  transfer  efficiency  and mixing  efficiency  and  to minimize  solids deposition between air distributors. 

Page 270: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 6   

6. Air piping shall be adequately sized to meet the specified oxygen transfer and  pressure  loss  requirements  plus  10%. Manifolds  or  air  distributors shall be upsized as required to meet the additional total system pressure drop.  

B. Design Conditions – New Aeration Basin 

1. Design 

a. Number of Cells: 2 

b. Basin Dimensions 

1) Length, feet: 75 

2) Width, feet: 15 

c. Minimum Side Water Depth (SWD), feet: 18 

d. Volume of Each Cell at SWD, each, gallons: 151,470 

e. Volume of Basin, total, gallons: 302,940 

2. Site Elevation 

a. Tank Bottom Elevation, MSL, feet: 78.0 

b. Minimum Side Water Depth, MSL, feet: 96.0 

c. Tank Top of Wall Elevation, MSL, feet: 99.0 

3. Basin Liquid Temperature 

a. Minimum Temperature, deg C: 10 

b. Maximum Temperature, deg C: 25 

4. Aeration  system  oxygen  transfer  rate  of  not  less  than  the  following pounds of oxygen per day in clean water at 14.7 PSI, 20 deg. C, and zero dissolved oxygen at the specified submergence, air rate, and pressure. 

a. Maximum Standard O2 Transfer Rate  (SOTR)  (lb/hour) Per Basin: 730 

b. Maximum Volumetric Air Flow (SCFM) Per Basin: 2,200 (oxidation ditch out of service) 

Page 271: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 7   

c. Minimum Volumetric Air Flow (SCFM) Per Basin: 370 

d. Maximum Pressure Loss through Manifold, Distribution Pipes, and Diffusers, PSI: 1.5 

e. Minimum Diffuser Submergence (ft): 16.5 

f. Maximum Diffuser Height above floor (ft): 1.5 

5. Minimum  Standard  Oxygen  Transfer  Efficiency  (SOTE)  at  design Maximum SOTR and diffuser submergence: 31.4%  

6. Maximum Volumetric  Air  Rate  per  effective membrane  surface  area  of 7.32 SCFM/SQFT (3 SCFM per 9‐inch disc). 

7. Minimum Volumetric Flow Rate per tank upper area required for mixing: 0.12 SCFM/SQFT (0.5 SCFM per 9‐inch disc). 

C. Design Conditions – Existing Oxidation Ditch 

1. Design 

a. Number of Cells: 1 

b. Basin Area, sqft: ±3,420  

c. Minimum Side Water Depth (SWD), feet: 11.72 

d. Volume of Basin, total, gallons: 300,000 

2. Site Elevation 

a. Tank Bottom Elevation, MSL, feet: 83.4 

b. Minimum Side Water Depth, MSL, feet: 95.12 

c. Tank Top of Wall Elevation, MSL, feet: 97.5 

3. Basin Liquid Temperature 

a. Minimum Temperature, deg C: 10 

b. Maximum Temperature, deg C: 25 

4. Aeration  system  oxygen  transfer  rate  of  not  less  than  the  following pounds of oxygen per day in clean water at 14.7 PSI, 20 deg. C, and zero dissolved oxygen at the specified submergence, air rate, and pressure. 

Page 272: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 8   

a. Maximum Standard O2 Transfer Rate  (SOTR)  (lb/hour) Per Basin: 730 

b. Maximum Volumetric Air Flow (SCFM) Per Basin: 3,600 

c. Minimum Volumetric Air Flow (SCFM) Per Basin: 600 

d. Maximum Pressure Loss through Manifold, Distribution Pipes, and Diffusers, PSI: 1.5 

e. Minimum Diffuser Submergence (ft): 10.22 

f. Maximum Diffuser Height above floor (ft): 1.5 

5. Minimum  Standard  Oxygen  Transfer  Efficiency  (SOTE)  at  design Maximum SOTR and diffuser submergence: 19.4%  

6. Maximum Volumetric  Air  Rate  per  effective membrane  surface  area  of 7.32 SCFM/SQFT (3 SCFM per 9‐inch disc). 

7. Minimum Volumetric Flow Rate per tank upper area required for mixing: 0.12 SCFM/SQFT (0.5 SCFM per 9‐inch disc). 

D. Performance Testing:  Performance of  the  fine bubble  aeration  system  shall  be verified by factory oxygen transfer test conducted  in clean water. Factory tests shall be based on the following criteria: 

1. A  minimum  of  3  tests  for  each  specified  condition  in  complete accordance  with  the  ASCE  Standard  for  the  Measurement  of  Oxygen Transfer in Clean Water (latest edition). 

2. Conduct tests in a full‐scale aeration test tank (minimum of 300 ft²) at the specified  submergence  and  water  depth  with  a  diffuser  density equivalent to the specified tank configuration.  Diffuser density is defined as  the  ratio  of  the  total  tank  surface  area  to  the  total  active  diffuser surface area. 

3. Conduct  factory  test  with  air  rate  and  mass  rate  of  oxygen  transfer directly proportional to the ratio of the factory test tank volume and the design tank volume.  

4. Plot of pounds oxygen per day per 1000 cubic feet of tank volume versus air per 1000 cubic feet of tank volume in tap water at 14.7 psia, 20°C and zero dissolved oxygen at the specified submergence. 

Page 273: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 9   

5. Test  SOTE  results  shall  be  normalized  to  a  TDS  concentration  of  1000 mg/l. 

6. Certify and stamp all tests by a Professional Engineer. 

7. Include all costs for testing in the Bid price.   

8. Submit  all  test  data  from  oxygen  transfer  tests  for  approval  by  the Engineer prior to manufacturing equipment. 

9. In  lieu  of  a  factory  test,  certified  results  from  previous  testing  at  a minimum  of  three  (3)  other  locations  under  similar  conditions  to  that anticipated at this site may be provided.   

a. Certified tests must be acceptable to the Engineer.  

b. Data  provided  shall  be  from  previous  testing  conducted  in accordance with ASCE Standard  for  the Measurement of Oxygen Transfer in Clean Water.  

c. Diffuser  density,  submergence  and  air  rate  per  diffuser  shall  be within ±20% of those specified for this project.   

d. Data  shall  be  presented,  normalized  to  TDS,  certified,  and submitted as required in the above paragraphs D.4 through 8. 

1.06 QUALIFICATIONS 

A. Equipment  shall  be  provided  by  a  company  experienced  and  qualified  in  the design,  manufacture,  and  field  testing  of  fine  bubble  membrane  aeration systems.  

B. Provide  evidence  of  previous  experience  by  submitting  a  list  of  at  least  50 installations  in  the  United  States  of  similar  fine  bubble  aeration  systems  in continuous successful operation for a period of not less than 10 years.  

C. Submit  list  of  installations,  including  project  name,  diffuser  type  and  model, names and phone numbers of key contacts with the product data submittal.  

D. Provide evidence of experience and description of adequate facilities to perform factory oxygen transfer tests. Submit certified copies of previous oxygen transfer test  reports  conducted  in  accordance  with  the  ASCE  Standard  for  the Measurement of Oxygen Transfer in Clean Water that meets the requirements of Paragraph 1.05.C.9 and details of the factory oxygen transfer test facility.  

1.07 WARRANTY 

Page 274: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 10   

A. Manufacturer shall warrant the materials and equipment specified herein to be free of defects in materials and workmanship for a period of two (2) years from the Date of Manufacturer’s Certificate of Installation and Field Testing. 

PART 2 PRODUCTS  2.01 ACCEPTABLE MANUFACTURERS 

A. Aquarius Technologies Inc., Port Washington, WI 

B. Environmental Dynamics International, Inc., Columbia, MO 

C. Sanitaire Division of Xylem Inc., Brown Deer, WI 

D. Engineer‐approved  equal.  Refer  to  Section  00  20  00  Instructions  to  Bidders Article 10 for procedure for approval.     

E. All  Manufacturers  listed  above  must  comply  with  all  of  the  performance  and qualification requirements specified herein for the model of diffuser proposed. 

2.02 SYSTEM COMPONENTS 

A. Droplegs 

B. Manifolds 

C. Air distributors with diffuser holders or diffuser saddle mounts 

D. Air distributor and manifold connection joints 

E. Pipe supports and anchors 

F. Diffuser assemblies  

G. Moisture blow‐off assemblies 

H. All needed gaskets including coupling and flange gaskets and “O” rings, etc. 

I. All needed hardware including bolts, nuts, and washers. 

2.03 MATERIALS, FABRICATION AND FINISHING 

A. Stainless Steel – Pipe, Fittings, Supports, and Hardware 

1. Fabricate all welded parts and assemblies from sheets and plates of 304L (for drop pipe only) and 316L stainless steel with a 2D finish conforming to ASTM A240, A554, A774, and A778. 

Page 275: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 11   

2. Fabricate non‐welded parts and flanges from sheets, plates or bars of 316 stainless steel conforming to ASTM A240 or ASTM A276.  

3. Welds & Welding Procedure 

a. Weld  in  the  factory  with  ER  316L  filler  wire  using  MIG,  TIG  or plasma‐arc  inert  gas welding  processes.    Provide  a  cross  section equal to or greater than the parent metal.  

b. Provide full penetration butt welds to the interior surface with gas shielding of interior and exterior of joint. 

c. Continuously  weld  both  sides  of  face  rings  and  flanges  to eliminate potential for crevice corrosion. 

4. Corrosion  Protection  and  Finishing:  Clean  all  welded  stainless  steel surfaces and welds after fabrication by using the following procedure: 

a. Pre‐clean  all  outside  weld  areas  to  remove  weld  splatter  with stainless  steel  brushes  and/or  deburring  and  finish  grinding wheels. 

b. Finish  clean  all  interior  and  exterior  welds  and  piping  by  full immersion  pickling  and  rinse  with  water  to  remove  all  carbon deposits  and  contaminants  to  regenerate  a  uniform  corrosion resistant  chromium  oxide  film  per  ASTM  A380  Section  6.2.11, Table A2.1 Annex A2 and Section 8.3. 

5. Fasteners, Anchor Bolts, and Hardware: 316 series stainless steel. 

B. Natural Rubber 

1. Furnish all fixed and expansion joint O‐ring gaskets of natural rubber/SBR with a Shore A durometer of 45 ± 5. 

C. Polyvinyl Chloride (PVC) – Pipe and Fittings 

1. Produce all PVC pipe and  fittings  from PVC compound with a minimum tensile strength of 7000 psi. 

2. Provide lower drop pipe, manifold and air distribution headers as follows: 

a. Size: 4 inch, SDR 33.5 per ASTM D3915 and D3034 or Schedule 40 per ASTM D1784, D1785, D2466 

b. Size: 6 inch & larger, Schedule 40 per ASTM D1784, D1785, D2466 

Page 276: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 12   

3. Design  air  distributors  and  manifolds  to  withstand  125°  F  mean  wall temperature. 

4. PVC  compounds  for  manifolds,  air  distributors,  joints  and  PVC  diffuser assembly  components  shall have minimum 1.5 % by weight of  titanium dioxide to minimize ultraviolet light degradation. 

5. Factory solvent‐weld all PVC joints and fittings. Field solvent welding will not be permitted. 

D. EPDM – Disc Membrane Diffusers and Gaskets 

1. Manufacture  circular  membrane  diffuser  discs  with  integral  O‐ring  of EPDM  synthetic  rubber  compound  with  precision  die  formed  slits.  Thermoplastic  materials  (i.e.  plasticized  PVC  or  polyurethane)  are  not acceptable. 

2. Add carbon black to the material for resistance to ultraviolet light.   

3. Design  diffuser  as  one  piece  injection  molded  part  with  a  minimum thickness of 0.080 inches for 9 inch diameter unit. 

4. Limit  the  maximum  tensile  strength  of  the  diffuser  to  10  psi  when operating  at  2.4  SCFM/ft²  of  material.  Furnish  proportionately  thicker material  for  larger diameter disc diffusers  to  limit  the maximum  tensile stress and to resist stretching. 

5. Produce diffusers free of tears, voids, bubbles, creases or other structural defects. 

6. EPDM diffuser material shall have the following properties: 

a. Base Polymer: EPDM per ASTM D573 

b. UV Resistance: Carbon Black 

c. Minimum Thickness:  0.080”  

d. Specific Gravity: <1.25 

e. Shore A Durometer Rating: 58% ± 5% per ASTM D2240  

f. Modulus of Elasticity:  >500 psi per ASTM D412 

g. Ozone  Resistance  (72  hrs:  40°C  pphm):  No  cracks  @  2X magnification  per ASTM D1171 Test A 

Page 277: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 13   

h. Tensile Strength: >1200 psi per ASTM D412 

i. Elongation % Retained 70 hrs @ 100°C: 75% Max per ASTM D573 

j. Elongation % Minimum at break: 350% per ASTM D412 

k. Dynamic Wet Pressure (max): 16 inches WG @ 3 SCFM/SQFT          33 inches WG @ 8 SCFM/SQFT 

E. Membrane Longevity  

1. Longevity  of  the  proposed  membrane  diffusers  shall  have  been demonstrated in a full‐scale municipal installation operating continuously for a minimum of three years. 

2. Test  reports,  prepared  and  certified  by  an  independent  testing  agency, shall confirm membrane longevity through compliance with the following maximum allowed (+/‐) change in each membrane property.   

a. Property and Maximum Change 

1) Durometer: 5% 

2) Weight: 5% 

3) Permanent Set: 0.5%  

4) DWP (clean diffusers):  6.0 in. WG @ 3.5 SCFM/SQFT 

5) DWP (clean diffusers):  12.0 in. WG @ 8 SCFM/SQFT 

6) SOTE (clean diffusers): 10% 

3. Data  for  a  minimum  of  three  diffusers  from  the  installation  shall  be provided. 

2.04 DROPLEGS 

A. Provide a stainless steel dropleg from the air main connection near top of tank wall to the dropleg connection on the manifold. Connection shall be as close to the manifold as possible, but not greater than 2‐feet above the manifold. 

B. Drop  leg  pipe  shall  be  sized  to  provide  a  headloss  of  less  than  3‐inches  of w.c./100  feet  of  length.  This  requires  two  (2)  8‐inch  drop  legs  for  the  new aeration basin and two 10‐inch drop legs for the existing oxidation ditch.  

Page 278: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 14   

C. The pipe shall be schedule 10  (minimum wall  thickness) 304L or 316L  stainless steel. Drop leg configuration shall be as shown on the Contract Drawings unless otherwise approved. 

D. Stainless steel drop leg pipe length shall include a minimum length of submerged stainless  steel  pipe  adequate  to  lower  the  connecting  PVC  pipe  mean  wall temperature to 125 degrees F from an inlet air temperature of 250 degrees F, as calculated by the manufacturer.  

E. Provide  a  flanged  90‐degree  bend  with  a  125‐pound  bolt  pattern  for  the  top connection.  

F. Provide an expansion joint  in the drop pipe  if necessary to prevent excess pipe strain  due  to  thermal  expansion/contraction  over  the  specified  temperature range.  Submit  calculations  verifying  that  the  manifold  is  designed  to accommodate expansion/contraction without excess pipe strain. 

G. Provide a stainless steel band clamp coupling with gasket for the lower dropleg to manifold connection. 

2.05 MANIFOLDS 

A. Provide PVC manifolds for connection to the air distribution headers. 

B. Fabricate manifolds with fixed threaded union or flanged joints for connection to the air distributors. 

C. Design manifold, distributor connections and supports to resist thrust generated by expansion/contraction of the air distributors over a temperature range of 125 deg F.      

D. Support manifold with a minimum of two supports. 

E. Connect manifolds with fixed flanged joints to prevent rotation or blow apart.  

F. Provide  expansion  joints  if  necessary  to  prevent  excess  pipe  strain  due  to thermal  expansion/contraction  over  the  specified  temperature  range.  Submit calculations  verifying  that  the  manifold  is  designed  to  accommodate expansion/contraction without excess pipe strain.   

2.06 AIR DISTRIBUTORS AND DIFFUSER HOLDERS 

A. Provide  minimum  4‐inch  diameter  air  distributors  perpendicular  to  the  air manifold. 

Page 279: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 15   

B. Fabricate distributors with single diffuser holders solvent welded to the crown of the  air  distributor  for  complete  air  seal  and  strength.  Alternate  methods  of securing holders may be accepted, only with approval by the Engineer. 

C. Provide minimum solvent weld area of 13 square inches. 

D. Diffuser holders  shall  be attached  to  the pipe with no more  than +/‐ 1 degree angular  variation  from  top  dead  center,  and  no  greater  than  +/‐  1/8”  lateral spacing variation to insure diffuser uniformity within the grid piping. 

E. Design distributors and holders to resist a dead load of 200 lbs applied vertically to the outer edge of the diffuser holder. 

F. Provide threaded removable end caps complete with gasket, threaded coupling and end plate for clean out at the end of each distributor. 

2.07 AIR DISTRIBUTOR AND MANIFOLD CONNECTION JOINTS 

A. Join air distributor sections with positive  locking fixed threaded union or flange type joints for all submerged header joints to prevent blow apart and rotation. 

B. Design  threaded union  joints with  spigot  section  connected  to  one  end  of  the distribution  header,  a  threaded  socket  section  connected  to  the  mating distribution  header,  an  O‐ring  gasket  and  a  threaded  screw  on  retainer  ring.  Solvent welding shall be done in the factory. 

C. Fixed joints shall be designed to resist 80 ft‐lb torque without joint movement or failure.  

D. Design  flanged  joints with  a  125‐lb  drilling  angle  face  ring,  follower  flange and stainless steel hardware. Flanges shall be provided with full face gaskets. 

E. Expansion Joints,  if  required, shall be Victaulic® “Depond‐O‐Lok” type or equal.  Joints  shall  be  fixed  to  the  end  of  the  pipe  sections.  Gaskets  shall  be  EPDM.  Coupling, housing, end rings and closure Type 316L stainless steel.  Bolts shall be Type 316 stainless steel per ASTM A‐276.   

2.08 SUPPORTS 

A. Limit maximum support spacing to 8 feet. 

B. Design all supports to allow for thermal expansion and contraction forces over a temperature  range  of  125  deg  F  and  to minimize  stress  build  up  in  the  piping system. 

C. Provide a support for every expansion coupling, if coupling is required. 

Page 280: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 16   

D. Design supports to be adjustable without removing the air distributor from the support. 

E. Design  supports  to  allow  for  complete  removal  from  the  tank,  less  the  anchor bolt,  to  facilitate  installation  of  additional  headers  and  in‐tank  maintenance. Support structures which consist of rods epoxied directly into the tank floor are not acceptable. 

F. Manifold and Drop Leg Support – 6‐inch diameter and larger. 

1. Design supports to include hold down guide straps, support structure and anchor bolts. 

2. Design guide straps with a 2‐inch minimum width to eliminate point load on manifold and minimize binding. 

3. Design support for 2 inches plus or minus vertical adjustment for leveling of manifold within ¼‐inch of a common plane. 

4. Attach supports to tank floor with two stainless steel anchor bolts. 

5. Secure drop leg to wall and support lower bend as required. 

G. Air Distributor and Manifold Supports – 4‐inch diameter. 

1. Provide guide and fixed type supports to allow expansion/contraction. 

2. Design  supports  with  hold  down  straps,  support  structure  and  anchor bolt. 

3. Design  support  for  1‐1/2  inch  (plus  or  minus)  vertical  adjustment  for leveling air distributor to within ¼‐inch of a common plane. 

4. Guide support  

a. Guide straps to have 1‐1/2  inch wide top and bottom contoured bearing  surface  with  chamfered  edges  to  minimize  binding  and resistance to movement of air distributor under full buoyant uplift load. 

b. Design strap with 1/8‐inch clearance around distributor so strap is self‐limiting and cannot be over tightened. 

5. Fixed supports  

Page 281: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 17   

a. Fixed  straps  to have 1‐1/2  inch wide  top and bottom contoured bearing  surface  with  punched  burrs  to  positively  grip  the  air distributor when tightened. 

b. Design strap to be self‐limiting to prevent stressing the distributor if the clamp is overtightened. 

6. Attach supports to tank floor with one stainless steel anchor bolt. 

H. Anchor Bolts 

1. Provide a mechanical stainless steel expansion type anchor bolt system. 

2. Design anchor bolts for embedment in 4000 psi concrete with a minimum pullout safety factor of 4. 

2.09 DIFFUSER ASSEMBLIES 

A. Disc Diffusers 

1. Disc  diffuser  assemblies  shall  include  diffuser,  diffuser  gasket,  holder, retaining ring and air flow control orifice. 

2. Membrane Diffuser 

a. Incorporate an integral check valve into the membrane diffuser. 

b. Diffuser Support Plate  

1) Provide a PVC support plate to form an air plenum under the diffuser and support for the membrane when the air is off. 

2) Each baseplate shall  incorporate a control orifice sized  to give  minimum  headloss  while  assuring  proper  air distribution  under  the  horizontal  surface  of  the  diffuser element. 

3. Diffuser Holders and Retainer Rings 

a. Design holder to provide peripheral support for the diffuser. 

b. Design retainer ring to seal the diffuser and o‐ring in the holder to prevent air leakage around gasket and to prevent blow‐off during operation.  The  threaded  retainer  ring  shall  be  designed  to withstand  a  load  at  least  8  times  that  experienced  for  proper sealing of the diffuser or gasket. 

Page 282: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 18   

c. Design  retainer  ring  threads with minimum cross  section of 1/8‐inch and allow for one complete turn to engage threads.  

d. Diffuser  holders  may  also  be  attached  to  the  crown  of  the  air distributor pipe by the use of a mechanical saddle, with approval of  the  Engineer.  Saddle  attachments  shall  provide  complete  air seal and not result in compromise of strength of pipe. Mechanical saddle  attachment  shall  include  the  air  inlet  port  and  positive locking  mechanism  to  locate  and  lock  the  assembly  to  the  air distributor piping.  

e. If  excessive  blow‐off  of  the  membranes  occurs,  manufacturer shall remediate all diffusers with a modified style, such as with a stainless steel retainer ring, designed with a suitable restrainer to prevent  such occurrence.    Excessive blow‐off  is  defined as more than one (1) per basin per year. This remediation shall be covered under the warranty specified herein. 

2.010 MOISTURE BLOW‐OFF ASSEMBLIES   

A. 102BMoisture blow‐off assemblies shall be located to remove all moisture from each grid. Provide at least one (1) moisture blow‐off assembly for each aeration grid.  For  grids with  a  central  air  supply manifold,  provide  at  least  one  (1) moisture blow‐off  assembly  on  the manifold.  Locations  of moisture  blow‐off  assemblies shall  be  as  shown  on  the  Shop  Drawing  submittal  and  as  approved  by  the Engineer. 

B. The  moisture  blow‐off  piping  shall  be  minimum  Schedule  80,  3/4”  minimum diameter PVC in accordance with ASTM D‐2467. Fittings shall be solvent welded socket type Schedule 80.  Field solvent welding shall be permitted for this item.  The vertical piping shall be secured to the tank wall with stainless steel anchors and nylon or stainless steel cable fasteners. Support spacing shall not exceed 5 feet.  The vertical piping shall extend to the top of the aeration tank wall.  

C. Provide  a  3/4”  Schedule  80 PVC  tee  at  the  top of  the  vertical  blow‐off  piping.  One outlet of the tee shall have a threaded cap to allow clean out of the blow‐off piping.    The other outlet  of  the  tee  shall  have a 3/4” PVC  threaded ball  valve.  Ball  valve  shall be easily accessible  from the outside of  the aeration basin or a walkway. If it is necessary to extend the blow‐off piping for accessibility, it shall have a continuous slope to prevent water accumulation, and shall be adequately supported.  

D. The  bottom  of  the  vertical moisture  purge  piping  shall  connect  to  a moisture blow‐off  tee.  The  moisture  blow‐off  tee  shall  be  integral  with  the  aeration 

Page 283: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 19   

manifold piping and shall be provided with a factory‐welded 3/4" minimum PVC drip tube which shall remove moisture from the invert of the piping.  

E. Alternately, a PVC air lift purge system shall be installed to drain the entire piping system  for  each  aeration  grid.  Each  system  shall  consist  of  a  sump  and  an eductor  line with  valve.  The bottom of  the  sump  shall  be  at  a  lower elevation than  the  air  distribution  headers.  The  eductor  line  shall  be  3/4”  minimum diameter Schedule 80 PVC pipe or a 3/4” diameter eductor  line  located  in a 4” PVC SDR 32.5 carrier column. The eductor line must terminate in a PVC ball valve 18 inches above the tank wall but not greater than 5 feet above water level.  PVC eductor lines or carrier columns shall be supported by stainless steel supports. 

2.011 SPARE PARTS AND SPECIAL TOOLS 

A. Diffuser system manufacturer shall provide the following spare parts:  

1. Ten  percent  (10%)  of  the  number  of  installed  diffuser  assemblies, including  membrane  diffusers  and  diffuser  gasket,  diffuser  holder  and retainer rings, bolts, washers, gaskets, supports, retainer clamps, etc.  

2. One (1) primary manifold support  including all hardware such as anchor bolts, nuts, and washers. 

3. Two  (2)  air  distributor  supports  or  five  percent  (5%)  of  the  total  air distributor  supports,  whichever  is  greater,  and  including  all  hardware such as anchor bolts, nuts, and washers. 

4. Two  (2)  air  distributor  laterals  or  five  percent  (5%)  of  the  total  air distributor laterals, whichever is greater. 

5. Two (2) of the total number of expansion fittings (tees and couplings), if required.  

B. Package spare parts in a separate container clearly marked as “Spare Parts” and provide inventory list on exterior of the container. 

C. Special Tools 

1. Diffuser system manufacturer shall provide a tool set for diffuser removal and installation, including wrench for removing and proper installation of diffuser retainers with torque‐limiting device for bolt‐secured diffusers.   

2. Tool  required  for  diffuser  removal  and  replacement  shall  allow  one‐person, with minimal training, to change a diffuser membrane  in a time period  of  5  minutes  or  less,  including  removal  of  membrane  and 

Page 284: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 20   

replacement with a new membrane fully secured in place sufficient that it will not blow out or become dislodged under test or working pressure. 

D. Spare parts shall be packaged in accordance with Specification Section 01 60 00, Product Requirements.  

PART 3 EXECUTION    

3.01 FACTORY TEST 

A. Perform factory quality control testing on the membrane diffusers. 

1. Quality Control: Test membrane properties  in accordance with specified test methods, including membrane durometer, tensile strength, modulas of elasticity, and specific gravity. Sample diffusers using primary sampling criteria outlined in Military Standard 105E. 

2. Dynamic Wet Pressure (DWP): Factory test minimum 4% of the diffusers at 2.4 SCFM/SQFT and 2  inches  submergence  to verify compliance with specifications. 

3. Air  Flow  Visual  Uniformity:  Visually  inspect  minimum  1%  diffusers  for uniform  air  distribution  across  the  active  surface  of  the  diffuser  at  2.4 SCFM/SQFT and 2  inches  submergence. Active  surface  is defined as  the perforated horizontal projected area of the diffuser. 

B. Certified  copies  of  the  test  reports  shall  be  submitted  to  Engineer  prior  to shipment per Section 01 33 00. 

3.02 PRODUCT SHIPMENT AND PROTECTION 

A. The diffused aeration systems shall be packaged and shipped in accordance with Section 01 60 00, Product Requirements. 

B. All  PVC  fittings  and  pipe,  diffusers,  and  gaskets  shall  be  carefully  packaged  to protect  the  components  from dirt  and dust  and  from  the effects  of  ultraviolet light. 

3.03 MANUFACTURER’S INSTALLATION INSPECTION 

A. Manufacturer’s  representative  shall  inspect  the  installation  as  specified  in Specification Section 01 75 00, Testing and Commissioning. 

B. Manufacturer’s qualified service representative shall provide a minimum of: 

Page 285: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 21   

1. One  (1)  trip  for one  (1) 8‐hour day  for assistance during  installation  for the first aeration tank.   

2. One  (1)  trip  for one  (1) 8‐hour day  for assistance during  installation  for the second aeration tank (oxidation ditch). 

3. One  (1)  trip  for  two  (2) 8‐hour days  for  final  installation  inspection and field testing for the first aeration tank.  

4. One  (1)  trip  for  two  (2) 8‐hour days  for  final  installation  inspection and field testing for the second aeration tank (oxidation ditch) plus training. 

C. Manufacturer’s service representative shall arrive on‐site for each trip within 1‐week of notice from Owner of the time required.  

D. Manufacturer’s installation inspection shall consist of: 

1. Installation  review  in  accordance  with  Manufacturer’s  Installation Checklist and checking the following: 

a. Tank leak tested and cleaned. 

b. Layout per approved Shop Drawings. 

c. System and components inspected for damage. 

d. Gaskets installed where required. 

e. Pipe  properly  plumbed  and  fittings/connections  checked  for tightness. 

f. Pipe supports at proper locations and properly anchored.   

g. Diffusers level and at the proper elevation.   

h. Air piping cleaned/flushed and purged of water.   

i. Proper air filter on blower inlet. 

j. Purge system properly installed. 

k. Proper torque applied to all bolts, brackets, clamps, retainer rings. 

3.04 FIELD TESTING 

A. On‐site  field  testing  shall  comply  with  the  requirements  of  Section  01  75  00, Testing and Commissioning.  

Page 286: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 22   

B. Manufacturer’s qualified service representative shall provide on‐site field testing of  the equipment during  the same trip  for  final  installation  inspection  for each aeration tank. 

C. The  following  field  tests  shall  be  performed  by  the  Manufacturer’s Representative and witnessed by the Owner’s Representative.  

1. Upon  installation of  the supports and prior  to  the  installation of piping, 10% of the supports of each type shall be tested for pullout. The supports to  be  tested  shall  be  chosen  at  random by  the Owner’s  representative who  shall  witness  the  tests.  Each  support  chosen  for  test  shall  be attached to a lever, which shall be placed on a fulcrum.  A static load shall be applied  to  the opposite end producing a  vertical  extracting  force on the support equal  to 5  times  the calculated maximum buoyant  force  to which the support will be subjected in normal operation.  

2. The Manufacturer’s Representative shall perform a field leakage test for air  manifolds  and  distribution  headers.  The  procedure  shall  consist  of submerging all piping in clean water, turning the air on at minimum flow and observing and correcting leaks.  

3. The  Manufacturer’s  Representative  shall  test  for  proper  elevation  of diffusers by  filling the tank with clean water  to the top of the diffusers.  Diffusers shall be within ±1/4” of the same elevation. 

4. The Manufacturer’s Representative shall test for uniform air distribution. The tank shall be filled with clean water to a depth 1’‐0” above the top of the  diffusers.  The  system  shall  be  operated  at  an  air  flow  of  2.4 SCFM/SQFT of diffuser, with air flow uniformity being verified by means of visual  inspection. The tank will then be filled to the normal operating level  and  the  surface  shall  be  observed  for  air  flow  uniformity  at maximum air flow per diffuser. Other abnormalities or  inactive diffusers will be identified and repaired during testing.  

D. Manufacturer’s  service  representative  shall  certify  the  installation  and  field testing  in  accordance  with  Section  01  75  00,  Testing  and  Commissioning Procedures, and shall submit the completed Certificate of  Installation and Field Testing Form at the end of this Section. 

3.05 TRAINING  

A. Manufacturer’s  qualified  service  representative  shall  provide  a  minimum  of  4 hours of training of the Owner’s staff  in the operation and maintenance of the equipment specified herein. Training shall be performed during the same trip as field testing. 

Page 287: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 23   

* * * END OF SECTION * * * 

Page 288: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV‐46 51 33 Fine Bubble Diffusers.doc  46 51 33 ‐ 24   

FORM 46 51 33‐1 CERTIFICATE OF INSTALLATION AND TESTING OF  FINE BUBBLE DIFFUSERS 

MANUFACTURER NAME:   PROJECT NAME:  

EQUIPMENT SCHEDULE NO.:  NAME OF EQUIPMENT: 

LOCATION/SERVICE:  SPECIFICATION SECTION: 

MANUFACTURER:  DIFFUSER MODEL: 

DIFFUSER TYPE:  DIFFUSER SIZE: 

INSTALLATION INSPECTION (CHECK IF VERIFIED) 

BASIN LEAK TESTED:  BASIN CLEANED: 

MANUFACTURER’S CHECKLIST SUBMITTED:  LAYOUT PER INSTALLATION DRAWINGS: 

SYSTEM AND COMPONENTS INSPECTED FOR DAMAGE:  GASKETS INSTALLED WHERE REQUIRED: 

PIPE CONNECTIONS CHECKED FOR TIGHTNESS:  PIPE PROPERLY PLUMBED: 

PIPE SUPPORTS PROPERLY ANCHORED:  FIXED/GUIDE PIPE SUPPORTS AT PROPER LOCATIONS: 

DIFFUSER GRIDS ARE LEVEL:    DIFFUSER GRIDS AT THE PROPER ELEVATION: 

AIR PIPING CLEANED/FLUSHED:  AIR PIPING PURGED OF WATER: 

PROPER AIR FILTER ON BLOWER INLET:  PURGE SYSTEM PROPERLY INSTALLED: 

PROPER TORQUE APPLIED TO ALL BOLTS, BRACKETS, CLAMPS, RETAINER RINGS: 

MISSING OR DAMAGED EQUIPMENT/SPARE PARTS (LIST): 

FIELD TEST 

PULL‐OUT TEST PERFORMED ON 10% OF THE SUPPORTS: 

WATER FILLED ABOVE AIR MANIFOLD ‐ DISTRIBUTION LATERALS AND CONNECTIONS CHECKED FOR LEAKS: 

WATER FILLED TO TOP OF DIFFUSERS ‐ DIFFUSERS LEVEL CHECKED (±1/4”): 

WATER FILLED ABOVE DIFFUSERS ‐ WATER SURFACE CHECKED FOR EVEN DISTRIBUTION AT MINIMUM AIR FLOW: 

WATER FILLED TO MAXIMUM LEVEL ‐ WATER SURFACE CHECKED FOR EVEN DISTRIBUTION AT MAXIMUM AIR FLOW: 

WATER SURFACE CHECKED FOR INACTIVE DIFFUSERS OR OTHER ABNORMALITIES DURING OPERATION: 

PURGE SYSTEM TESTED FOR PROPER OPERATIONS: 

Comments:   As the Manufacturer’s Representative, I certify that I have inspected the installation of the equipment, the equipment has been installed in accordance with the manufacturer's recommendations, I have witnessed all applicable field tests, all proper adjustments have been made, the equipment meets the performance requirements of the Contract Specifications, and the equipment is ready for plant commissioning and operation. 

 SELLER/MANUFACTURER  

CHECK OFF  INSTALLER CHECK OFF  WITNESS CHECK OFF 

NAME       

SIGNATURE       

DATE       

 

Page 289: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 1

SECTION 46 66 56 ULTRAVIOLET DISINFECTION SYSTEM

PART 1 GENERAL

1.01 SUMMARY OF WORK

A. Manufacturer shall furnish a complete open-channel, low-pressure low-intensity ultraviolet (UV) disinfection system as specified herein. The scope of work shall include replacement of the existing UV disinfection bank and associated electrical and controls in the existing UV channel, furnishing a new UV disinfection system with UV banks, system control center, power distribution centers, support racks for both channels, and furnishing a new level control weir for the new channel.

B. The work shall include fabrication, factory-testing, delivery, installation inspection, field testing, certification of installation and field testing, performance testing, and training.

1.02 RELATED WORK

A. Division 0 – Bid Documents

B. Division 1 – General Requirements

1.03 REFERENCE STANDARDS

A. AISI/SAE – American Iron and Steel Institute/Society of Automotive Engineers

1. AISI/SAE 304 (UNS S30400) – 304 Stainless Steel

2. AISI/SAE 304L (UNS S30403) – 304L Stainless Steel

3. AISI/SAE 316 (UNS S31600) – 316 Stainless Steel

4. AISI/SAE 316L (UNS S31603) – 316L Stainless Steel

B. National Electrical Manufacturers Association (NEMA)

1. NEMA 250 Enclosures for Electrical Equipment.

C. Underwriters Laboratories (UL)

1. UL 508A Industrial Control Equipment.

2. All equipment and devices shall be listed by and bear the Underwriters Laboratories (U.L.) Inc U.L. label or the CSA-C/US label.

Page 290: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 2

D. U.S. Environmental Protection Agency (EPA)

1. Design Manual – Municipal Wastewater Disinfection (EPA/625/1-86/021), October 1986.

1.04 SUBMITTALS

A. Furnish submittals in accordance with Section 01 33 00, Submittal Procedures including all the requirements listed therein, and including:

1. Installation list demonstrating compliance with Paragraph 1.05C.

2. Headloss calculations demonstrating compliance with the specified hydraulic characteristics.

3. Independent third-party bioassay validation report justifying the reactor size and lamp arrangement specific to the equipment being supplied shall be provided. The bioassay shall follow protocols described in the US EPA Design Manual – Municipal Wastewater Disinfection (EPA/625/1-86/021). The bioassay shall demonstrate that the proposed UV system design and number of lamps shall deliver the specified dose based on the water quality and operating conditions specified herein.

4. UV dose calculations. Dose calculations shall be based on the bioassay validation report.

5. Independent certification of fouling factor (FF) and end of lamp life (EOLL) aging factor must be submitted. The fouling factor shall be determined on municipal wastewater effluent.

6. Power requirements, including voltage, amperage, KW total for system and per bank, for current and future requirements.

7. Detailed description and equation used for dose-pacing and controlling the number of lamps in operation.

8. Shop drawings showing UV module, ballast enclosure, power distribution centers, system control center, UV module support racks, and water level controller.

9. Electrical and control drawings per Section 01 33 00.

10. Warranties as specified herein.

B. Certified Factory Test Report as specified herein.

Page 291: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 3

C. On-site performance testing plan per Section 01 75 00.

D. On-site Performance Test Report as specified herein.

E. Certificate of Installation and Testing Form per Section 01 75 00 and as specified herein.

F. Operation and Maintenance Manuals: Furnish in accordance with Section 01 78 00, Close-Out Submittals.

1.05 QUALIFICATIONS

A. The process design and equipment layout is based upon the following manufacturer:

1. Trojan UV3000B™ as manufactured by Trojan Technologies, London, Ontario, Canada.

2. Engineer-approved equal. Refer to Section 00 20 00 Instructions to Bidders Article 10 for procedure for prequalification for Bidding.

B. The above manufacturer has been prequalified to submit bids for this procurement contact based on matching and replacing the existing UV disinfection system. Systems that do not fit within the existing channel configuration and do not have the same electrical and control requirements shall not be approved.

C. All qualified UV disinfection system manufacturers shall:

1. Have at least 50 installations in the United States of the model proposed in satisfactory operation for at least 10 years.

2. Provide an independent third-party bioassay validation report in accordance with Paragraph 1.04A.3.

1.06 WARRANTY

A. Mechanical and Electrical Warranty:

1. Manufacturer shall warrant the materials and equipment specified herein to be free of defects in materials and workmanship for a period of two (2) years from the Date of Manufacturer’s Certificate of Installation and Field Testing.

B. Ultraviolet Lamp Warranty:

Page 292: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 4

1. UV Lamps to be warranted for a minimum of 12,000 hours, non-prorated. Pro-rated warrantees shall not be accepted. On/off cycles are limited to an average of four (4) per day.

1.07 DESIGN CRITERIA

A. Surface Water Discharge Design Criteria: Provide equipment that shall disinfect domestic wastewater that has undergone secondary treatment (activated sludge plus settling) in compliance with the following criteria:

1. Peak Flow: 1.65 MGD per channel, 3.3 MGD both channels

2. Minimum Flow: 0.2 MGD

3. Total Suspended Solids: ≤30 mg/L (maximum 30-day average)

4. Total Suspended Solids: ≤45 mg/L (maximum 7-day average)

5. Ultraviolet Transmittance @ 253.7 nm: ≥65% (30-day average)

6. Effluent Fecal Coliform Bacteria: ≤200 CFU/100 mL (maximum 30-day geometric mean)

7. Effluent Fecal Coliform Bacteria: ≤400 CFU/100 mL (maximum 7-day geometric mean)

8. Dose: Minimum 30 mJ/cm2 at peak flow and minimum UV transmittance with all UV banks in service.

9. Reliability: The system shall be capable of treating 50% (minimum) of the peak flow with one channel out of service.

B. Dose Calculations

1. The system design dose shall be based on third-party bioassay dose calculations incorporating the following criteria:

a. End of lamp life (EOLL) derating factor after 12,000 hours of service.

b. Sleeve fouling derating factor (FF).

2. The end of lamp life derating factor and the sleeve fouling derating factor shall be validated by a third party and submitted per Paragraph 1.04A.5.

C. Headloss

Page 293: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 5

1. Maximum headloss at peak flow: <2”

2. The system shall be designed to automatically maintain water surface within the design constraints of the system proposed at the specified peak and minimum design flows.

D. Operating Conditions:

1. The system shall be designed for an outdoor installation.

2. Effluent Temperature Range: 33 to 85 °F (1 to 30 °C)

3. Ambient Temperature Range: 10.0 to 100.0 °F

E. Channel Configuration

1. Number of channels: 2

2. Channel length ahead of weir, minimum: 13.5 feet

3. Weir length per channel: 22 feet (11 feet in channel length)

4. Channel width: 48 inches

5. Channel height: 48 inches

6. Effluent depth in channel, minimum: 12 inches

F. Equipment Configuration

1. Designation of Banks: Q-U-1 (channel 1), Q-U-2 (channel 2)

2. Number of Banks per Channel: 1

3. Number of UV Modules per Bank: 16

4. Number of Lamps per UV Module: 4

5. Total Number of Lamps: 128

6. Number of System Control Centers: 1

7. Number of UV Sensors: 2 (one per bank)

8. Number of Power Distribution Centers: 2 (one per bank)

9. Number of Level Controllers: 1 existing and 1 new weir

Page 294: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 6

1.08 PERFORMANCE CRITERIA

A. The system shall comply with the design criteria and effluent limitations listed in Paragraph 1.07 herein.

B. The third-party validated bioassay UV dose produced by the system shall not be less than the doses specified in Paragraph 1.07 with all UV banks in service, at the specified peak flow and UV transmittance at 253.7 nm, and applying the certified end of lamp life derating factor and fouling factor.

C. The system shall be able to continue providing disinfection while replacing UV lamps, quartz sleeves and ballasts, and while cleaning the sleeves.

PART 2 PRODUCTS

2.01 MATERIALS

A. All metal components in contact with effluent shall be Type 304 or Type 316 stainless steel.

B. All wiring exposed to UV light shall be TeflonTM-coated.

C. All material exposed to UV light shall be Type 316 stainless steel, Type 214 quartz, or TeflonTM.

D. All wires connecting the lamps to the ballasts shall be enclosed inside the frame of the UV Module and not exposed to the effluent.

2.02 LAMP ARRAY CONFIGURATION

A. The lamp array configuration shall be uniform with all lamps parallel to each other and to the flow direction. The lamps shall be evenly spaced in horizontal and vertical rows with centerline spacing equal in both directions.

B. The single array pattern shall be continuous and symmetrical throughout the reactor.

C. The system shall be designed for complete immersion of the UV lamps including both electrodes and the full length of the lamp tube in the effluent. Both lamp electrodes shall operate at the same temperature and be cooled by the effluent.

2.03 UV MODULE

A. Each UV module shall consist of UV lamps with an electronic ballast enclosure mounted on the Type 316 stainless steel frame.

Page 295: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 7

B. Each lamp shall be enclosed in its individual quartz sleeve, one end of which shall be closed and the other end sealed by a lamp end seal and compressed O-ring.

C. The closed end of the quartz sleeve shall be held in place by means of a retaining O-ring. The quartz sleeve shall not come in contact with any steel in the frame.

D. The ends of the lamp sleeve shall not protrude beyond the stainless steel frame of the UV Module.

E. Lamp wires shall terminate in the electronic ballast enclosure located at the top of the UV Module.

F. The electronic ballast enclosure shall contain the electronic ballasts and L.E.D. lamp status displays visible through a red plexiglass viewing plate.

G. The ballast enclosure shall be anodized aluminum.

H. All wires connecting the lamps to the ballasts shall be enclosed inside the frame of the UV Module and not exposed to the effluent.

I. All lamp to ballast connections shall be made by and tested by the UV Manufacturer.

J. At the point of exit from the UV Module frame the multiconductor cable shall pass through a waterproof strain relief.

K. Each UV Module shall weigh no more than 40 lbs and shall be individually removable without using mechanical lifting devices.

L. Each UV Module shall be connected to a receptacle on the Power Distribution Center by means of a multiconductor cable with a molded connector.

M. Each UV Module shall have a UL rating of Type 6P.

2.04 UV LAMPS

A. Lamps shall be low pressure mercury slimline of the hot cathode instant start design. The coiled filamentary cathodes shall be heated by the arc current.

B. The filament shall be of the clamped design, significantly rugged to withstand shock and vibration.

C. Electrical connections shall be at one end.

D. Each connection shall have only two pins.

E. 90% of UV output shall be within the wavelengths of 233.7 to 273.7 nm.

Page 296: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 8

F. Lamps shall be rated to produce zero levels of ozone.

G. Lamp bases shall be of a metal and ceramic construction resistant to UV and ozone.

H. The lamp base shall incorporate a dielectric barrier or pin isolator. The pin isolator shall consist of a non-conductive divider placed between the lamp pins to prevent direct arcing across the pins in moist conditions.

2.05 LAMP END SEAL AND LAMP HOLDER

A. The open end of the lamp sleeve shall be sealed by means of a Type 316 stainless steel sleeve nut which threads onto a sleeve cup and compresses the sleeve O-ring.

B. The sleeve nut shall have a knurled surface to allow a hand grip for tightening. The sleeve nut shall not require any tools for removal.

C. The lamp shall be held in place by means of a moulded lampholder that shall incorporate two seals. The lampholder shall seal against the inside of the quartz sleeve to act as a second seal in series with the external O-ring seal.

D. The second seal on the lampholder shall isolate and seal the lamp from the module frame and all other lamps in the module.

E. In the event of a quartz sleeve fracture the two seals of the lamp holder shall prevent moisture from entering the lamp module frame and the electrical connections to the other lamps in the module.

F. The lamp holder shall also incorporate a UV resistant plastic stop that shall prevent the lamp sleeve from touching the steel sleeve cup.

2.06 UV LAMP SLEEVES

A. Lamp sleeves shall be Type 214 clear fused quartz circular tubing as manufactured by General Electric or equal.

B. Lamp sleeves shall be domed at one end.

C. The nominal wall thickness shall be 1.5 mm.

2.07 UV LAMP MODULE SUPPORT RACK

A. The module support rack shall be Type 304 stainless steel and be suspended above the effluent in the channel by means of slotted angles allowing

Page 297: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 9

adjustment to the precise height of the channel and requiring no fastening of the individual UV lamp modules.

B. The module support rack shall be designed so that no ultraviolet light shall radiate above the channel when the UV lamp modules are energized and fully immersed in the effluent.

2.08 LEVEL CONTROL WEIR

A. The level control weir shall be located at the discharge end of the UV channel.

B. The level control weir shall be designed to maintain a minimum channel effluent level as required to keep the lamps submerged.

C. The level control weir shall be constructed of Type 304 stainless steel.

2.09 ELECTRICAL

A. General:

1. Each UV module shall be powered from the Power Distribution Center through a bus bar and shall include a relay board and watertight connectors.

2. Each ballast shall drive two lamps.

3. Maximum power consumption shall be no greater than 11.2 kW.

4. Electrical supply to each System Control Center shall be 120 Volts, single phase, 2 wire (plus ground), 12.5 Amps.

5. Electrical supply to each Power Distribution Center shall be no greater than 208 Volts, 3 phase, 4 wire (plus ground), 6.1 kVA.

B. Power Distribution Center

1. Power distribution shall be through bus bars to environmentally sealed receptacles to allow for local connection of UV Modules.

2. Fusing of each UV module circuit shall be located inside the Power Distribution Center.

3. Enclosure material shall be Type 304 Stainless Steel.

4. Enclosure shall be waterproof.

Page 298: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 10

5. The PDC shall be 8 inches high by 8 inches wide and span the complete channel width.

6. All Power Distribution Centers to be CSA approved with a rating of Type 4X.

7. One separate sealed Power Distribution Center shall be provided per bank of lamps to ensure complete electrical independence.

C. Control and Instrumentation

1. System Control Center – Touch Smart Controller

a. The operation is managed at the SCC by a Microprocessor which continuously monitors and controls the system functions.

b. The operator interface display screen shall be menu driven with automatic fault message windows appearing upon alarm conditions. The operator interface shall be a 7” color screen display

c. Alarms shall be provided to indicate that maintenance attention is required or to indicate an extreme alarm condition in which the disinfection performance may be jeopardized. The alarms shall include but not be limited to:

i. Bank Status

ii. Common Alarm – Major, Minor

iii. Low UV Intensity

d. A major alarm shall automatically result in all available lamps being energized, as required to meet the minimum dose at all times.

e. The 100 most recent alarms shall be recorded in an alarm history register and displayed when prompted

f. Elapsed time of each bank shall be recorded and displayed on the display screen when prompted.

g. Digital I/O modules shall be provided to remotely indicate status and alarms such as:

i. Alarm conditions (major alarm, low UV intensity alarm)

Page 299: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 11

ii. Bank Status (one for each UV bank supplied)

h. Analog input module for external flow signal.

i. SCADA communication shall be through Modbus Ethernet.

j. Panel shall be UL approved, rated Type 4X, and be 20 inches or 50.8 cm high by 20 inches or 50.8 cm wide by 9 inches or 22.9 cm deep. Panel shall be wall or rack mounted.

D. UV Intensity Sensors

1. The UV reactor shall have a minimum of one UV intensity sensor per bank.

2. The sensor shall not degrade after prolonged exposure to the UV light or effluent.

3. The sensor shall measure only the germicidal portion of the light emitted by the UV lamps at 254 nm, and shall have sensitivity at 254 nm of greater than 95%.

4. UV sensor shall be factory-calibrated to US National Institute for Standards and Technology (NIST), unless otherwise approved by the Engineer.

E. Flow Pacing

1. A flow pacing system shall be supplied to turn the UV banks on and off in relationship to a 4-20 mA signal from an effluent flow meter (by others).

2. Bank status shall be capable of being placed either in Manual, Off or Auto mode.

3. Banks shall be cycled for equal wear and timed off to minimize bank cycling.

F. Cleaning Rack

1. A moveable cleaning rack of Type 304 stainless steel shall be provided.

2.010 SPARE PARTS AND SAFETY EQUIPMENT

A. The UV Manufacturer shall furnish as part of the system the following spare parts and safety equipment:

1. 8 - UV Lamps

Page 300: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 12

2. 8 - Lamp Sleeves

3. 8 - Lamp Holder Seals

4. 1 - Operators kit including face shield, gloves.

5. 1 - Spare fuses for control panel (all types)

B. All spare parts and safety equipment shall be packaged in accordance with Section 01 60 00, Product Requirements.

C. Spare parts shall be inspected on site by UV System Manufacturer’s representative.

PART 3 EXECUTION

3.01 FACTORY TEST

A. Perform factory tests of all control panels prior to shipment in accordance with Section 01 75 00, Testing and Commissioning.

B. Certified Factory Test Reports shall be submitted to and approved by the Engineer prior to shipment in accordance with Section 01 33 00, Submittal Procedures.

3.02 PRODUCT SHIPMENT AND PROTECTION

A. The equipment shall be packaged and shipped in accordance with Section 01 60 00, Product Requirements.

3.03 INSTALLATION

A. Installing Contractor shall install the equipment specified herein in accordance with the UV System Manufacturer's recommendations and as shown on the Drawings.

B. UV System Manufacturer’s qualified representative shall inspect the installation as specified in Specification Section 01 75 00, Testing and Commissioning Procedures.

C. UV System Manufacturer’s representative shall provide a minimum of 1/2 day of on-site installation inspection and assistance, on-site field instrument calibration, and control panel testing. Inspection shall verify the following at minimum:

1. Power distribution and grounding testing complete.

Page 301: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 13

2. Control panel input/output and field instrument terminations testing complete.

3. Instruments calibrated.

4. HMI screens display required information including the correct flow, UV intensity, operational dose, and bank and lamp status.

3.04 FIELD TESTING

A. On-site field testing shall comply with the requirements of Section 01 75 00, Testing and Commissioning Procedures and as specified herein.

B. UV System Manufacturer's representative shall provide a minimum of 2 days of on-site field testing of the equipment and initial lamp burn-in.

C. Field Testing:

1. Proposed field-testing procedure shall be developed by the UV System Manufacturer and submitted to the Engineer for approval prior to scheduling and performing the field testing

2. Field testing shall demonstrate that the UV equipment and related control system operate in accordance with the specifications including all operating, monitoring, shutdown, and alarm functions.

3. Tested functions shall include but not be limited to:

a. Manual control of banks/lamps.

b. Automatic flow pacing of system.

c. Power loss and return functions.

d. Communications loss and return functions.

e. Remote access through Modbus Ethernet and plant SCADA.

f. All other control and alarm functions.

D. Performance Testing:

1. UV System Manufacturer's representative shall provide a minimum of 2 days of on-site performance testing of the UV Disinfection System.

2. Performance testing shall be performed to determine the actual system operating conditions and verify that the system meets the guaranteed

Page 302: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 14

design criteria as specified herein, including hydraulic and disinfection performance.

3. The disinfection performance acceptance test shall be conducted by the UV Disinfection System Manufacturer’s representative after approval of the on-site field testing by the Engineer.

4. During the performance testing, the Manufacturer’s qualified service representative shall start up and operate the UV disinfection system continuously for a minimum of 1 day for each channel to demonstrate the required guaranteed treatment performance.

5. Four (4) grab samples of the influent and four (4) grab samples of the effluent of each UV disinfection channel shall be collected by the UV System Manufacturer’s representative and analyzed for fecal coliform. Samples shall be collected on 2-hour intervals. The UV dose applied during the testing shall be as specified in Paragraph 1.07A or as close as practical at the available flows. Manufacturer’s representative shall deliver samples to third-party laboratory for analysis.

6. Sample analysis shall be performed by the third-party laboratory in accordance with Standard Methods for the Examination of Water and Wastewater, American Public Health Association (APHA), the American Water Works Association (AWWA), and the Water Environment Federation (WEF), latest edition.

7. Inlet and outlet level and flow shall be recorded during a simulated peak flow event through each train. The headloss shall be calculated and verified to against the hydraulic model for the train to determine if the system complies with the specified hydraulic performance requirements.

E. Manufacturer’s qualified service representative shall certify the installation and on-site testing in accordance with Section 01 75 00, Testing and Commissioning Procedures and shall submit the completed Certificate of Installation and Field Testing Form at the end of this Section.

F. Manufacturer shall submit a Performance Test Report to the Engineer within 14 days of leaving the site in accordance with Section 01 33 00, Submittal Procedures. Performance Test Report shall document the results of the field and performance testing and document compliance with the specifications.

3.05 TRAINING

Page 303: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 15

A. Manufacturer’s qualified service representative shall provide a minimum of 4 hours of training of the Owner’s staff on the operation and maintenance of the equipment as specified in Section 01 79 00, Training.

B. Training shall meet the requirements of 01 79 00, Training.

*** END OF SECTION ***

Page 304: BID AND CONTRACT DOCUMENTS MAJOR EQUIPMENT …

STV-46 66 56 Ultraviolet Disinfection System.doc 46 66 56 - 16

FORM 46 66 56-1 CERTIFICATE OF INSTALLATION AND TESTING OF UV DISINFECTION EQUIPMENT MANUFACTURER NAME: PROJECT NAME:

EQUIPMENT SCHEDULE/TAG NO.: MODEL NUMBER:

LOCATION/SERVICE: SERIAL NO.:

SYSTEM NAMEPLATE FLA: VOLTS: HERTZ: PHASE:

INSTALLATION INSPECTION (CHECK IF VERIFIED)

UV BANK SUPPORT RACKS INSTALLED/ANCHORED:

GROUNDING TESTED: CONTROL PANEL I/O TESTED: FIELD CONTROL WIRING TESTED:

LEVEL CONTROL WEIR INSTALLED/ANCHORED

POWER SUPPLY TESTED: POWER DISTRIBUTION TESTED:

UV SENSORS TESTED:

FLOW DISPLAY: DOSE DISPLAY: INTENSITY DISPLAYS TRAIN 1: INTENSITY DISPLAYS TRAIN 2:

MISSING OR DAMAGED PARTS/TOOLS (LIST):

FIELD TEST (CHECK IF VERIFIED)

MANUAL CONTROL: BANK 1/LAMP STATUS: MAJOR ALARMS: POWER LOSS/RETURN:

FLOW PACING: BANK 2/LAMP STATUS: MINOR ALARMS: COMMUNICATIONS LOSS/RETURN:

ETHERNET CONNECTION DATA:

OTHER: OTHER: OTHER:

COMMENTS:

As the Manufacturer’s Representative, I certify that I have inspected the installation of the equipment, the equipment has been installed in accordance with the manufacturer's recommendations, I have witnessed all applicable field tests, all proper adjustments have been made, the equipment meets the performance requirements of the Contract Specifications, and the equipment is ready for plant commissioning and operation.

MANUFACTURER/SELLER

CHECK OFF INSTALLATION CONTRACTOR

CHECK OFF WITNESS

CHECK OFF

NAME

SIGNATURE

DATE