Project Name Tug Harbour & Infrastructure Project Client Lendlease Engineering / BHP Billiton Sit e Hunt Point, Port Hedland Contract $17M Duration 9 months Safety Achievement TRIFR of '0' Main Equipment Total Support & FT3 - BHD's Weerdee - Crane Barge Quenda & Wiabuna - Tugs Split Hopper Barges Workboats & Multicats totalams.com.au DETAILS OVERVIEW The Tug Harbour development was essential for the expansion of BHP's Port Hedland Iron Ore exports. Lendlease Engineering was awarded the project with TAMS as a primary subcontractor. The scope included: - Construction and painting of pontoon piles - Dredging approx 100,000m 3 of material from harbour entrance and disposal within spoil ground using BHD FT3 and SHB's - Geofabric layout, with TAMS divers and shore based crane - Rock armour placement with BHD Total Support - Anode installation along the harbour wall - Pontoon installation with crane barge and divers - Concrete mattress removal - Silt removal with suction dredge, spoils to shore The project utilised a wide range of TAMS vessels and almost 100 TAMS personnel. BHP TUG HARBOUR PROJECT PROJECT SPECIFICATION SHEET 4 Mews Road, Fremantle WA 6160 +61 08 9430 5889 Revision 1.0

Upload: others

Post on 09-Dec-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BHP TUG HARBOUR PROJECT - Marine Solutions & Port Services

Project Nam eTug Harbour & Infrastructure Project

Client Lendlease Engineering / BHP Billiton

Sit e Hunt Point, Port Hedland

Cont ract $17M

Durat ion 9 months

Safet y Achievem ent TRIFR of '0'

Main Equipm ent Total Support & FT3 - BHD's Weerdee - Crane BargeQuenda & Wiabuna - Tugs Split Hopper BargesWorkboats & Multicats

t ot alam s.com .au

DETAILSOVERVIEWThe Tug Harbour development was essential for the expansion of BHP's Port Hedland Iron Ore exports. Lendlease Engineering was awarded the project with TAMS as a primary subcontractor.

The scope included:

- Construction and painting of pontoon piles - Dredging approx 100,000m3 of material from

harbour entrance and disposal within spoil ground using BHD FT3 and SHB's

- Geofabric layout, with TAMS divers and shore based crane

- Rock armour placement with BHD Total Support- Anode installation along the harbour wall- Pontoon installation with crane barge and divers- Concrete mattress removal- Silt removal with suction dredge, spoils to shore

The project utilised a wide range of TAMS vessels and almost 100 TAMS personnel.

BHP TUG HARBOUR PROJECT

PROJECT SPECIFICATION SHEET

4 Mews Road, Fremantle WA 6160 +61 08 9430 5889 Revision 1.0