bhel - training report punnet

Upload: hellboy130012

Post on 02-Jun-2018

387 views

Category:

Documents


5 download

TRANSCRIPT

  • 8/10/2019 Bhel - Training Report Punnet

    1/30

    INDUSTRIAL TRAINING REPORT

    BHARAT HEAVY ELECTRICALS LIMITED

    RANIPUR, HARIDWAR

    AREA OF TRAINING: ROTOR AND STATOR WINDING ASSEMBLY OF THRI

    AND LSTG

    Submitted to the

    Department of Electrical Engineering

    in partial fulfillment of the requirements for the degree of

    Bachelor of Technology

    in

    Electrical Engineering

    JSS Academy of Technical Education, NOIDA

    U.P. Technical University

    SUBMITTED BY: SUBMITTED TO:

    Puneet Kapoor Mr. Nirmal Kr. Aggarwal

    (1109120122) (Indust. Training Presentation Coordinator)

    VII-EE-B Electrical Engg. Deptt.

    JSSATE, NOIDA

  • 8/10/2019 Bhel - Training Report Punnet

    2/30

    ACKNOWLEDGEMENT

    Training has an important role in exposing the real life situation in an industry. It was

    a great experience for me to work on training at BHARAT HEAVY

    ELECTRICALS LIMITED through which I could learn how to work in aprofessional environment.

    Now, I would like to thank the people who guided me and have been a constant

    source of inspiration throughout the tenure of my summer training.

    I am sincerely grateful to MR. RAJ SINGH (Manager)at HRDC, BHEL Haridwar

    who allowed me to pursue my summer training at the plant and rendered me his

    valuable assistance, constant encouragement and able guidance which made this

    training actually possible.

    I wish my deep sense of gratitude to MR. SANJAY KUMAR (Asst. GeneralManager) whose affectionate guidance has enabled me to complete this training

    successfully. I wish my deep sense of gratitude to Dr. V. K CHANDNA (HOD: EE

    Department)whose guidance and encouragement made my training successful.

    Puneet Kapoor

  • 8/10/2019 Bhel - Training Report Punnet

    3/30

    CONTENTS

    Topic Page No.

    1.

    BHELAn Overview. 1

    2.

    HEAVY ELECTRICAL EQUIPMENT PLANT (HEEP). 5

    3. ELECTRICAL MACHINES (BLOCK1) 11

    I. TURBO-GENERATOR. 12

    II.

    LARGE SIZE TURBO-GENERATOR. 13

    III. COMPONENTS OF TURBO-GENERATOR. 14

    a)

    STATOR

    1)

    STATOR CORE.

    2) STATOR WINDING.

    3)

    END COVERS.

    b) ROTOR

    1) STEPS IN ROTOR MACHINING.

    IV. EXCITATION SYSTEM. 19

    a)

    EXCITER.

    V.

    BAY-4 (SMALL AND MISCALLANEOUS COMPONENTS) 20

    VI. TEST STANDS. 26

    VII. LSTG TEST STANDS. 26

    VIII.

    TESTING. 26

    a) HELIUM LEAK TESTS

    b) HYDROGEN TESTING AND PNEUMATIC TESTING.

    4. CONCLUSION 27

    5. REFERENCES 27

  • 8/10/2019 Bhel - Training Report Punnet

    4/30

    1

    1. BHELAN OVERVIEW

    Bharat Heavy Electricals Limited(BHEL) owned by Government of India, is apower plant equipment manufacturer and operates as engineering and manufacturing

    company based in New Delhi, India. Established in 1964, BHEL is India's largest

    engineering and manufacturing company of its kind. The company has been earning

    profits continuously since 1971-72 and paying dividends uninterruptedly since 1976-

    77.

    BHEL caters to core sectors of the Indian Economy viz., Power Generation's &

    Transmission, Industry, Transportation, Telecommunication, Renewable Energy,

    Defense, etc. The wide network of BHEL's 14 manufacturing division, four power

    Sector regional centres, over 150 project sites, eight service centres and 18 regional

    offices, enables the Company to promptly serve its customers and provide them with

    suitable products, systems and servicesefficiently and at competitive prices. BHEL

    has already attained ISO 9000 certification for quality management, and ISO 14001

    certification for environment management.

    POWER GENERATION

    Power generation sector comprises thermal, gas, hydro and nuclear power plant

    business as of 31.03.2001, BHEL supplied sets account for nearly 64737 MW or 65%

    of the total installed capacity of 99,146 MW in the country, as against nil till 1969-70.

    BHEL has proven turnkey capabilities for executing power projects from concept to

    commissioning, it possesses the technology and capability to produce thermal setswith super critical parameters up to 1000 MW unit rating and gas turbine generator

    sets of up to 240 MW unit rating. Co-generation and combined-cycle plants have been

    introduced to achieve higher plant efficiencies. to make efficient use of the high-ash-

    content coal available in India, BHEL supplies circulating fluidized bed combustion

    boilers to both thermal and combined cycle power plants.

    The company manufactures 235 MW nuclear turbine generator sets and has

    commenced production of 500 MW nuclear turbine generator sets.

    Custom made hydro sets of Francis, Pelton and Kapian types for different head

    discharge combination are also engineering and manufactured by BHEL.

    In all, orders for more than 700 utility sets of thermal, hydro, gas and nuclear have

    been placed on the Company as on date. The power plant equipment manufactured byBHEL is based on contemporary technology comparable to the best in the world and

    is also internationally competitive.

    The Company has proven expertise in Plant Performance Improvement through

    renovation modernisation and uprating of a variety of power plant equipment besides

    specialised know how of residual life assessment, health diagnostics and life

    extension of plants.

  • 8/10/2019 Bhel - Training Report Punnet

    5/30

    2

    POWER TRANSMISSION & DISTRIBUTION (T & D)

    BHEL offer wide ranging products and systems for T & D applications. Products

    manufactured include power transformers, instrument transformers, dry type

    transformers, seriesand stunt reactor, capacitor tanks, vacuumand SF circuitbreakers gas insulated switch gears and insulators.

    A strong engineering base enables the Company to undertake turnkey delivery of

    electric substances up to 400 kV level series compensation systems (for increasing

    power transfer capacity of transmission lines and improving system stability and

    voltage regulation), shunt compensation systems (for power factor and voltage

    improvement) and HVDC systems (for economic transfer of bulk power). BHEL has

    indigenously developed the state-of-the-art controlled shunt reactor (for reactive

    power management on long transmission lines). Presently a 400 kV Facts (Flexible

    AC Transmission System) project under execution.

    INDUSTRIES

    BHEL is a major contributor of equipment and systems to industries. Cement, sugar,

    fertilizer, refineries, petrochemcials, paper, oil and gas, metallurgical and other

    process industries lines and improving system stability and voltage regulation, shunt

    compensation systems (for power factor and voltage improvement) and HVDC

    systems (for economic transfer of bulk power) BHEL has indigenously developed the

    state-of-the-art controlled shunt reactor (for reactive power management on long

    transmission lines). Presently a 400 kV FACTS (Felxible AC Transmission System)

    projects is under execution.

    ACTIVITY PROFILE

    PRODUCTS - Industrial Fans

    Power Generation & Transmission - Seamless steel Tubes

    - Steam Turbine-Generator Sets &

    Auxiliaries

    - Fabric Filters

    - Boiler and Boiler Auxiliaries - AC DC Motors, Variable speed

    - Once-through Boilers - AC Drive

    - Nuclear Power Generation Equipment - Electronic Control Gear &

    Automation

    - Hydro Turbine-Generator Sets & Auxiliaries - Equipment- Mini/Micro Hydro Generator Sets - DDC for Process Industry

    - Gas Turbine-Generator Sets - Thruster Equipment

    - Waste Heat Recovery Boilers - Power Devices

    - Heat Exchangers - Energy Meters

    - Condensers - Transformer

    - Bowi Mills and Tube Mills - Switch gear

    - Gravimetric Feeders - Insulator

    - Regenerative Air Pre-Heaters - Capacitors

    - Electrostatic Precipitators - Broad Gauge AC, AC/DC Loco

    Motives

    - Bag Filters - Diesel-Electric ShuntingLocomotives

  • 8/10/2019 Bhel - Training Report Punnet

    6/30

    3

    - Valves - Traction Motors & Control

    Equipment

    - Pumps - Electric Trolley Buses

    - Electrical Machines - AC/DC Electric Multiple Units

    - Piping Systems - Drives and Controls for Metro

    Systems- Power, Distribution & Instrument Transformers - Battery-Operated Passengers

    Vans

    - Reactors - X-Mas Trees and Well Heads

    - Synchronous Condensers - Cathodic Protection Equipment

    - Switchgear - Digital Switching Systems

    - Control gear - Rural Automatic Exchange

    - Distributed Digital Control for Power

    Stations

    - Simulators

    - Bus Ducts - Wind Electric Generators

    - Rectifiers - Solar Powered Water Pumps

    - Porcelain Insulators - Solar Water Heating Systems- Ceralin - Photo Votaic Systems

    - Defense Equipment

    Industries/Transportation/Oil & Gas/ - Reverse Osmoses Desalination

    Plants

    Telecommunication/Renewable Energy SYSTEMS & SERVICES- Steam Turbine-Generator Sets - Turkey Utility Power Stations/

    EPC

    - Gas Turbine-Generator Sets - Contracts

    - Diesel Engine-Based Generators - Captive Power Plants

    - Industrial Steam Generators - Co-generation Systems

    - Heat Recovery Steam Generators - Combined Cycle Power Plants

    - Fluidised Bed Combustion Boilers - Modernisation & Renovation of

    Power

    - Drive Turbine Stations and FLA Studies

    - Manne Turbines - Switch yards and Substations

    - Industrial Heat Exchangers - HVDC Transmission Systems

    - Centrifugal Compressor - Shorts sines condensation

    Systems

    - Industrial Valves - Power system analysis

    - Reactors - Electron comissionly and

    Operation- Columns - Consultancy services

    - Pressure Vessels - Consultancy Services

    - Pumps

    SUMMARY OF BHEL'S CONTRIBUTION TO VARIOUS CORE SECTORS

    POWER GENERATION

    THERMAL RATING (MW) NO. OF

    SETS

    TOTAL

    CAPACITY (MW)500 30 15000

    250 9 2250210/200 138 28570

  • 8/10/2019 Bhel - Training Report Punnet

    7/30

    4

    120/125/130 20 2420

    195 1 195

    110 38 4180

    100 6 600

    70/67.5 6 410

    60 14 84030 5 150

    TOTAL

    (THERMAL)

    267 54615

    GAS FRAME SIZE/

    SCOPE

    NO. OF

    SETS

    TOTAL

    CAPACITY (MW)9 5 730

    6 17 580

    5 13 309

    3 6 48

    V 94.2 2 2866FA 3 207

    STG 24 1190

    GEN 4 87

    TOTAL (GAS) 74 3437

    NUCLEAR RATING (MW) NO. OF

    SETS

    TOTAL

    CAPACITY (MW)500 2 1000

    220 10 2200

    TOTAL

    (NUCLEAR)

    12 3200

    TOTAL (THERMAL+GAS+NUCLEAR) 353 61252

    HYDRO 402 18735

    GRAND TOTAL 755 79987

  • 8/10/2019 Bhel - Training Report Punnet

    8/30

    5

    2. HEAVY ELECTRICAL EQUIPMENT PLANT (HEEP)

    At Hardwar, against the picturesque background of Shivalik Hills, two

    important manufacturing units of BHEL are located viz. Heavy Electrical Equipment

    Plant (HEEP) & Central Foundry Forge Plant (CFFP). The hum of the construction

    machinery working started under Shivalik Hills during early 60s and sowed the seeds

    of one of the greatest symbol of Indo Soviet Collaboration Heavy Electrical

    Equipment Plant.

    Consequent upon the technical collaboration between India and USSR in

    1959, BHELs prestigious unit, Heavy Electrical Equipment plant (HEEP), was

    established in October, 1963, at Hardwar. It started manufacturing thermal sets in

    1967 and now thermal sets of 210, 250 and 500 MW, including steam turbines, turbo-

    generators, condensers and all associated equipments, are being manufactured. This

    unit is capable of manufacturing thermal sets up to 1000 MW. HEEP-manufactured

    gas turbines, hydro turbines and generators, etc., are not only successfully generating

    electrical energy within and outside the country, but have also achieved a historic

    record of the best operational availability and plant load factor.

    The Company is embarking upon an ambitions growth path through clearvision, mission and committed values to sustain and augment its image as a world

    class enterprise.

    VISION

    World-class, innovative, competitive and profitable engineering enterprise providing

    total business solutions.

    MISSION

    The leading Indian engineering enterprise providing quality products systems and

  • 8/10/2019 Bhel - Training Report Punnet

    9/30

    6

    services in the fields of energy, transportation, infrastructure and other potential areas.

    VALUES

    Meeting commitments made to external and internal customers.

    Foster learning creativity and speed of response.

    Respect for dignity and potential of individuals.

    Loyalty and pride in the company.

    Team playing

    Zeal to excel.

    Integrity and fairness in all matters.

    ESTABLISHMENT AND DEVELOPMENT STAGES

    Established in 1960s under the Indo-Soviet Agreements of 1959 and 1960 in the area

    of Scientific, Technical and Industrial Cooperation.

    DRRprepared in 1963-64, construction started from October '63

    Initial production of Electric started from January, 1967.

    Major construction / erection / commissioning completed by 1971-72 as per original

    DPR scope.

    Stamping Unit added later during 1968 to 1972.

    Annual Manufacturing capacity for Thermal sets was expanded from 1500 MW to

    3500 MW under LSTG. Project during 1979-85 (Sets up to 500 MW, extensible to

    1000/1300 MW unit sizes with marginal addition in facilities with the collaboration of

    M/s KWU-Siemens, Germany.

    Motor manufacturing technology updated with Siemens collaboration during 1984-87.

    S.No. Area/ Block Major Facilities Products

    1. BlockI

    (Electrical

    Machines)

    Machine Shop., Windings bar

    preparation assembling, painting

    section, packing& preservation,

    over speed balancing, test bed test

    stand, babbiting, micalastic

    impregnation etc.

    Turbo Generator,

    Generator exciters,

    motors (AC& DC)

  • 8/10/2019 Bhel - Training Report Punnet

    10/30

    7

    2. BlockII

    (Fabrication

    Block)

    Markings, welding ,Cutting,

    straightening, gas cutting press, ,

    grinding, assembly, heat

    treatment, cleaning & Shotblasting, machining, fabrication of

    pipe coolers, painting

    Large size fabricated

    assemblies/

    components for power

    equipments

    3. BlockIII

    (Turbines &

    Auxiliary Block)

    Machining, facing wax melting,

    broaching, assembly preservation

    & packing, test stands/ station,

    painting grinding, milling,

    polishing etc.

    Stem turbines, hydro

    turbines, gas turbines,

    turbine bladders,

    special tooling.

    4. BlockIV

    (Feeder Block)

    Bar winding, mechanical

    assembly, armature winding,

    sheet metal working marching,

    copper profile drawing

    electroplating, impregnation,

    machining & preparation of

    insulating components plastic

    molding, press molding

    Windings for turbo

    generators, hydro

    generators insulation

    for AC & DC motors,

    insulating components

    for TG, HG & Motors

    control panel, contact

    relays master control

    etc.

    5. BlockV Fabrication, pneumatic hammer

    for forgings, gas fired furnaces,

    hydraulic manipulators

    Fabricated parts of

    steam turbine, water

    box, storage tankhydro turbine parts,

    hydro turbines

    assemblers &

    Components

    6. BlockVI Welding, drilling, shot blasting,

    CNC flame cutting ,CNC deep

    Fabricated parts of

    steam turbine water

  • 8/10/2019 Bhel - Training Report Punnet

    11/30

    8

    (Fabrication) drilling, Shot basting, sheet metal

    work, assembly

    box, stronger tanks,

    hydro turbine parts,

    Hydro turbines

    assemblies &components,

    7. Block- VI

    (Stamping & Die

    Manufacturing)

    Machining, turning, grinding, jig

    boring stamping presses, de

    varnishing, degreasing & de

    rusting, varnishing sport welding,

    painting.

    Wooden packing,

    spacers etc.

    8. Block- VII (wood

    working)

    Wood Cutting, machines,

    grinding , packing

    Wooden packing,

    spacers etc.

    9. BlockVIII Drilling ,turning, saw, cutting,

    welding, tig welding

    LP Heater ejectors

    glad, steam cooler oil

    coolers, ACG collers,

    oil tanks, bearing

    covers.

    10. Services plat TPS : Power generation

    equipment & auxiliaries plat

    capacity 12 MW

    Power generation

    PGP Plat : Boiler Type gasgenerators

    Producer gas

    Acetylene Plat : A fully

    automated plant for acetylene

    generation & filling in cylinder

    Acetylene gas

    Compressor House: 4 No.

    Compressors of rating 100 m2 /

    min

    Compressed air

  • 8/10/2019 Bhel - Training Report Punnet

    12/30

    9

    Oxygen Plat : 3 air separation unit

    4 air compressors

    Oxygen gas

    Nitrogen gas

    132 KV substation : 2 Nose 16.7

    MVA/ 11 KV, one no. 20 MVA

    & one no. 12.5 MVA 132/6.6 KV

    transformer & other allied

    equipment

    Power supply

    11. Motor transport A fleet of vehicles comprising of

    cars, jeeps trekkers, buses, mini

    buses motorcycles , fire tenders

    trucks etc.

    Transport service

    12. Telecommunication A 2000 line main exchange for

    internal communication

    3 no Satellite exchange

    Telephone service

    13. Hydro Turbine Lab 3 test beds with electronic

    instrumentation. It consists of

    cavitations test bed for reactions

    turbine & hydrodynamic test bed

    for Impulse turbines facilities for

    carrying out filed test at hydro

    power sets.

    Testing of turbine

    models

    14. HRDC Class room with audiovisual

    facilities workshop with facilities

    for turnings fitting machining,

    weeding, electrical work

    carpentry work

    Training to

    Employees, VTs

    Apprentices,

    Contractors &

    Customers

  • 8/10/2019 Bhel - Training Report Punnet

    13/30

    10

    CLIMATIC AND GEOGRAPHICAL CONDITIONS

    Hardwar is in extreme weather zone of the Western Uttar Pradesh of India and

    temperature varies from 2oC in Winter (December to January) to 45oC in Summer

    (April-June); Relative humidity 20% during dry season to 95-96% during rainyseason.

    Longitude 78o3' East, Latitude 29o55'5" North.

    Height above Mean Sea Level = 275 meters.

    Situated within 60 to 100 KMs of Foot-hills of the Central Himalayan Ranges;

    Ganges flows down within 7 KMs from the Factory area.

    HEEP is located around 7 KMs on the Western side of Hardwar city.

    POWER & WATER SUPPLY SYSTEM

    40 MVA sanctioned Electric Power connection from UP Grid (132 KV / 11KV / 6.6

    KV) (Connected loadaround 185 MVA)

    26 deep submersible Tube Wells with O.H. Tanks for water supply.

    A 12 MW captive thermal power station is located in the factory premises.

    15. Engineering CAD Work stations, personal

    computer reprographic facilities

    like ammonia printing, semi dry

    printing machine, Xerox process,micro filming facilities

    Design and drawings

    of all products

    16. Computer Center ICIMs series 39 DX level 270-

    320 computer system HCL

    magnum mini compute system ,

    ESPL SM32 mini computer

    Nexus3500 CAE work station,

    PCs etc.

    IT services

    17. CPL (Central plant

    Lab.)

    Testing Lab for new materials &

    sample components

    Testing of components

  • 8/10/2019 Bhel - Training Report Punnet

    14/30

    11

    3. ELECTRICAL MACHINES BLOCK (BLOCK-I)

    INTRODUCTION

    Block-I is designed to manufacturing Turbo Generators, Hydro generators and

    large and medium size AC and DC Electrical machines.

    The Block consist of 4 bays: Bay-1 (36*482 meters), Bay-2 (36*360 meters) and

    Bay-3 and Bay-4 of size 24 *360 meters each. For handling and transporting the

    various components over-head Crane facilities are available, depending upon the

    products manufactured in each Bay. There are also a number of self-propelled

    electrically-driven transfer trolleys for the inter-bay movement of components

    /assemblies.

    Conventional bay -wise broad distribution of products is as follows :

    BAY1 ROTOR

    SHAFT

    MACHINI

    NG

    ROTOR SHAFT

    SLOTTING

    ROTOR

    WINDING

    OVER SPEED

    AND

    BALANCING

    TUNNEL

    LARGE SIZE

    TURBO

    GENERATOR

    S

    BAY2 EXCITER

    SHAFT

    MACHINI

    NG

    STATOR BODY

    MACHINING

    STATOR

    WINDING

    TOTAL

    IMPREGNATION

    TEST BED

    BAY--3 ROTOR

    SUPPORT

    BEARING

    SHAFT SEAL

    BODY

    DC

    MOTOR

    WINDING

    (EARLIER)

    BAY--4 COOLING

    FANS

    MACHINI

    NG

    ARRANGEMEN

    T AND OTHER

    PARTS

    BASIC TRAINING DEPARTMENTS: -

    MACHINE SHOP.

    T/G ROTOR WINDING.

    H/G IRON ASSEMBLY.

    EXCITER. T/G STATOR WINDING.

  • 8/10/2019 Bhel - Training Report Punnet

    15/30

    12

    TOTAL IMPREGNATION TECHNIQUE.

    T/G IRON ASSEMBLY.

    T/G MAIN ASSEMBLY.

    L.S.T.G ROTOR WINDING.

    L.S.T.G STATOR WINDING.

    L.S.T.G MAIN ASSEMBLY. TEST BED.

    I. TURBO GENERATOR

    Turbo generator or A.C. generators or alternators operates on the fundamental

    principles of ELECTROMAGNETIC INDUCTION. In them the standard

    construction consists of armature winding mounted on stationary element called stator

    and field windings on rotating element called rotor. The stator consists of a cast-iron

    frame , which supports the armature core , having slots on its inner periphery for

    housing the armature conductors. The rotor is like a flywheel having alternating north

    and south poles fixed to its outer rim. The magnetic poles are excited with the help of

    an exciter mounted on the shaft of alternator itself. Because the field magnets are

    rotating the current is supplied through two slip rings. As magnetic poles are

    alternately N and S, they induce an e.m.f and hence current in armature conductors.

    The frequency of e.m.f depends upon the no. of N and S poles moving past a

    conductor in 1 second and whose direction is given by Fleming s right hand rule.

    SYNOPSIS OF THE FUNCTION OF T.G.:

    1.

    The generator is driven by a prime mover which is steam turbine in this case.2.

    The other side of generator is provided by a rotating armature of an exciter which

    produces A.C. voltage. This is rectified to D.C. by using a rotating diode wheel.

    3. The rear end of above exciter armature is mounted by a permanent magnet

    generator rotor.

    4.

    As the above system is put into operation, the PMG produces A.C. voltage.

    5. The voltage is rectified by thyristor circuit to D.C.

    6.

    This supply is given to exciter field. This field is also controlled by taking

    feedback from main generator terminal voltage, to control exciter field variation by

    automatic voltage regulator. The rectified DC supply out of exciter is supplied to

    turbo generator rotor winding either through brushes or central which will be

    directly connected to turbo generator. This depends on the type of exciter viz. DCcommutator machines or brushes exciter.

    7. The main A.C. voltage is finally available at the stator of Turbo Generator.

  • 8/10/2019 Bhel - Training Report Punnet

    16/30

    13

    LSTG AREA

    II. LARGE SIZE TURBO GENERATOR (LSTG)

    In these types of generators steam turbine does the function of prime mover which

    rotates the rotor of LSTG and the field winding is supplied D.C. by an exciter.

    Main types of T.G. are:-

    1. THRI2.

    TARI

    3. THDI

    4. THDD

    5. THDF

    6. THFF

    1stLETTER= (here-T)

    = 3-phase turbo generator

    2nd

    LETTER= (here H or A)

    =Medium present for generator cooling

    (H= hydrogen, A or L=air)

    3rdLETTER=type of rotor cooling employed

  • 8/10/2019 Bhel - Training Report Punnet

    17/30

    14

    R= radial,

    F= direct water cooling

    D= direct axial gas cooling)

    4th

    LETTER= type of as used for stator winding cooling

    I= indirect gas cooling

    D= direct gas cooling

    F= direct water cooling

    III. COMPONENTS OF T.G. :-

    STATOR

    1. Stator frame

    2. Stator core

    3. Stator winding

    4. End covers.

    ROTOR

    1.

    Rotor shaft

    2. Rotor windings

    3.

    Rotor retaining rings

    BEARINGS

    COOLING SYSTEM

    EXCITATION SYSTEM

    STATOR

    The generator stator is a tight construction supporting and enclosing stator winding,

    core and hydrogen cooling medium. Hydrogen is contained within the frame and

    circulated by fans mounted at either end of rotor. The generator is driven by a direct

    coupled steam turbine at the speed of 3000 rpm.

  • 8/10/2019 Bhel - Training Report Punnet

    18/30

    15

    The generator is designed for continuous rated output. Temperature detector or other

    devices installed or connected within the machine, permits the winding core and

    hydrogen temperature, pressure and purity in machine.

    STATOR FRAME

    The stator frame is used for housing armature conductors. It is made of cylindrical

    section with two end shields which are gas tight and pressure resistant. The stator

    frame accommodates the electrically active parts of stator i.e. the stator core and the

    stator winding.

    The fabricated inner cage is inserted in the outer frame after the stator has been

    constructed and the winding completed.

    STATOR CORE

    The stator core is stacked from the insulated electrical sheet steel lamination and

    mounted in supporting rings over the insulated dovetail guide bars. In order to

    minimize eddy current losses core is made of thin laminations. Each lamination layer

    is made of individual sections. The ventilation ducts are imposed so as to distribute

    the gas accurately over the core and in particularly to give adequate support to the

    teeth.

  • 8/10/2019 Bhel - Training Report Punnet

    19/30

    16

    The main features of core are

    1. To provide mechanical support.

    2.

    To carry efficiently electric, magnetic flux.

    3. To ensure the perfect link between the core and rotor.

    STATOR WINDING

    Each conductor must be capable of carrying rated current without over heating.

    The stator winding consists of two layers made up of individual bars. Windings for

    the stators are made of copper strips wound with insulated tape which is impregnated

    with varnish, dried under vacuum and hot pressed to form a solid insulation bar.

    These bars are then placed in the stator slots and held in with wedges to form the end

    turns. These end turns are rigidly placed and packed with blocks of insulation material

    to withstand heavy pressure.

    The stator bar consists of hollow (in case of 500 MW generators) solid strands

    distributed over the entire bar cross-section, so that good heat dissipation is ensured.

    In the straight slot portion the strands are transposed by 540 degrees. The

    transposition provides for mutual neutralization of the voltage induced in the

    individual strands due to slot cross field and end winding flux leakage and ensure that

    minimum circulating current exists. The current flowing through the conductors is

    thus uniformly distributed over the entire cross section so that the current dependent

    losses will be reduced.

    The alternate arrangement of one hollow strand and two solid strands ensures

    optimum heat removal capacity and minimum losses. The electrical connection

    between top and bottom bars is made by connecting sleeve.

    Class F insulation is used.

    The no. of layer of insulation depends on machine voltage. The bars are brought under

    vacuum and impregnated with epoxy resin, which has very good penetration property

    due to low viscosity. After impregnation bars are subjected to pressure with nitrogen

    being used as pressurizing medium (VPI process). The impregnated bars are formed

    to the required shape on moulds and cured in an oven at high temperature to minimize

    the corona discharge between the insulation and slot wall a final coat of

    semiconducting varnish is applied to the surface of all bars within the slot range. Inaddition all bars are provided with an end corona protection to control the electric

    field at the transition from the slot to end winding. The bars consist of a large no. of

    separately insulated strands which are transposed to reduce the skin effect.

  • 8/10/2019 Bhel - Training Report Punnet

    20/30

    17

    INSULATION OF BARS

    A. Vacuum pressed impregnated micaclastic high voltage insulation:-

    The voltage insulation is provided according to the proven resin poor mice base of

    thermo setting epoxy system. Several half overlapped continuous layer of resin poor

    mica tape are applied over the bars. The number of layers or thickness of insulation

    depends on the machine voltage. To minimize the effect of radial forces windingshold and insulated rings are used to support the overhang.

    B. Corona Protection:-

    To prevent the potential difference and possible corona discharge between the slot

    wall and the insulation, the section of bars are provided with outer corona protection.

    The protection consists of polyester fluce tape impregnated in epoxy resin with carbon

    and graphite as fillers. At the transition from the slot to the end winding portion of the

    stator bars a semiconductor tape is impregnated.

  • 8/10/2019 Bhel - Training Report Punnet

    21/30

    18

    C. Resistance Temperature Detector:-

    The stator slots are provided with platinum resistant thermometer to record and watch

    the temperature of stator core and tooth region and between the coil sides of machine

    in operation. All AC machines rated for more than 5 MVA or with armature core

    longer, the machine is to be provided with at least 6 resistance thermometers. The

    thermometer should be fixed in the slot but outside the coil insulation. When thewinding has more than one coil side per slot, the thermometer is to be placed between

    the insulated coil sides. The length of resistance thermometer depends upon the length

    of armature. The leads from the detector are brought out and connected to the terminal

    board for connection onto temperature meter or relays. Operation of RTD is based on

    the prime factor that the electric resistance of metallic conductor varies linearly with

    temperature

    END COVERS:-

    The end covers are made up of fabricated steel or aluminum castings. They are

    employed with guide vans on inner side for ensuring uniform distribution of air or

    gas.

  • 8/10/2019 Bhel - Training Report Punnet

    22/30

    19

    IV. EXCITATION SYSTEM:-

    EXCITER:-

    EXCITER ROTOR

    The basic use of given exciter system is to produce necessary DC for

    turbo generator system. Principal behind this is that PMG is mounted on the

    common shaft which generates electricity and that is fed to yoke of main

    exciter. This exciter generates electricity and this is of AC in nature. This ACis that converted into DC and is that fed to turbo generator via C/C bolt. For

    rectifying purpose we have RC block and diode circuit. The most beautiful

    feature is of this type of exciter is that is automatically divides the magnitude

    of current to be circulated in rotor circuit. This happens with the help of AVR

    regulator which means automatic voltage regulator. A feedback path is given

    to this system which compares theoretical value to predetermine and than it

    sends the current to rotor as per requirement.

  • 8/10/2019 Bhel - Training Report Punnet

    23/30

    20

    The brushless exciter mainly consists of:-

    1. rectifier wheels

    2. three phase main exciter

    3. three phase pilot exciter

    4.

    Metering and supervisory equipment.

    The brushes exciter is an AC exciter with rotating armature and

    stationery field. The armature is connected to rotating rectifier bridges forrectifying AC voltage induced to armature to DC voltage. The pilot exciter is a

    PMG (permanent magnet generator). The PMG is also an AC machine with

    stationery armature and rotating field. When the generator rotates at the rated

    speed, the PMG generates 220 V at 50 hertz to provide power supply to

    automatic voltage regulator.

    A common shaft carries the rectifier wheels the rotor of main exciter

    and the permanent magnet rotor of pilot exciter. The shaft is rigidly coupled to

    generator rotor and exciter rotors are than supported on these bearings.

    V. BAY IV (SMALL AND MISCELLANEOUS COMPONENTS)

    Facilities available in the various sections are as follows:-

    MACHINE SECTION:-

    The machine section of Bay-4 is equipped with small and medium sizeCNC & conventional machine tools like centre lathes, milling, radial drilling,

  • 8/10/2019 Bhel - Training Report Punnet

    24/30

    21

    cylindrical grinding, slotting, copy turning lathe, internal grinding and surface

    grinding machines. Small-size and miscellaneous components for Turbo-

    generators, Hydro generators and Motors are machined in this section.

    POLE COIL SECTION

    COILING SECTION

    This section is equipped with baking oven , pneumatic shearingmachines , semi-automatic winding machines , pole straightening installations

    , electric furnace for bright annealing of copper , tinning installation and

    hydraulic press (800 Ton capacity ) for manufacturing Pole Coils of DC

    motors , AC synchronous motors and hydro generators . Pole assembly is also

    carried out in this section.

    Manufacturing of coils (hydro generators) taken in this section.

    German copper coils are initially in the form of rolls. These rolls are then

    undergoes following processes to change into copper coils which are then

    mounted with poles-

    1. ANNEALING PROCESS:-

    This is the process of hardening or softening any metal.

    Initially copper rolls are hard & if it undergoes annealing then it may

    breaks so firstly to make it soft so that it can easily change to winding.

    This process is carried out in the annealing furnace.

  • 8/10/2019 Bhel - Training Report Punnet

    25/30

    22

    WINDING PROCESS:-

    This process undergo following steps:-

    Take out the softened copper rolls for pole coil winding. Winding is done with the help of change plate & winding template so

    ensure major working dimensions of change plate & winding template

    with respect to tool drawing.

    Adjust & set the winding machine as per the product standards using

    gear rack, change plate & winding template. Ensure parallelity of

    winding template with respect to machine platform. Maintain height of

    winding template with platform. Wind the coil in anticlockwise

    direction.

    NOTE:-

    The joint in the copper coil shall be located in the straight part of

    longer side.

    If required heating by gas torch of copper profile at corner zone at

    temperature between 100-150 degree centigrade is allowed. This is

    to make easier bending.

    2. BRAZING:-

    Braze the joint with brazing alloy Ag40Cd.

    Remove the coil with machine with 2 to 3 turns extra than the actual

    number of turns for preparation of end-half turns.

    3. Carry out bright annealing of the coil. Take out the coil from the oven

    after annealing.

    4.

    PRESSING:-

    Pressing of coil is done by hydraulic pressure of 800 tons.

    This process is carried out in order to remove wrinkles from the coil.

    This process is carried out after every process. In this process, set the

    coil on the mandrel for pressing then slide the coil under press and

    press the coil.

    Take out the coil from press.

    5.

    FIXING:-

  • 8/10/2019 Bhel - Training Report Punnet

    26/30

    23

    Fix the accessory on the stretching machine.

    Put the coil on the stretching machine& pull the coil to the drawing

    dimensions.

    Dress the conductors along periphery & take out the coil.

    Check window dimensions as per drawing.

    6. SEPARATION:-

    Remove the buckling of each coil manually.

    Grind the bulging of the copper at place of binding (inner side) with

    pneumatic grinder.

    Check the thickness of the profiled copper with the gauge. Grinding

    shall be uniform & of smooth finish.

    Round of sharp edges.

    ** Again press the coil as in pt.5 & take out the coil from the press.

    7. PICKLING:-

    Send the coil for pickling to block 4 & check the quality of pickling.

    Press the coil again after pickling then remove pressure and take out

    the coil.

    8. Prepare end half turn as per drawing with template.

    9. Braze item 2 & 3 corresponding to the variant with end half turn with

    brazing alloy

    Ag 40 Cd.

    Remove extra material, clean and check with gauge.

    Adjust the end half turn with top & bottom turn of coil braze the joint.

    Remove extra material and check thickness of the gauge.

    Check the distance from center axis of pole coil as per drawing.

    10. FINISHING:-

    Hang the coil on stand and separate out turns

  • 8/10/2019 Bhel - Training Report Punnet

    27/30

    24

    Remove black spots, burrs the sharp edges and clean the coil turns with

    cotton dipped in thinner.

    Press the coil again and check the height of the coil under press to

    check dimensions as per drawing.

    11.Take out the coil from the press and send for insulation.

    12. INSULATION:-

    Hang the coil on stand and separate out the turn.

    Clean each turn with cotton dipped in thinner.

    Apply Epoxy varnish on both sides of each turn with brush uniformly

    all over the leaving top & bottom turn.

    Cut strips of Nomax paper as per contour of coil with technologicalallowance 3 to 5 mm on either side.

    Stick two layers of Nomax strips between each turn.

    Coat varnish layer between two layers of Nomax also.

    Let the excess varnish to flow out some time

    13. BAKING AND PRESSING OF COIL:-

    Place the coil on mandrel putting technological washer at top & bottom

    of the coil.

    Heat the coil by DC up to 100 +/-5o C , and maintain for 30 to 40

    minutes.

    Switch off the supply and elongate the coil and tight the pressing

    blocks from sides.

    Start heating coil again and raise temperature gradually in steps up to

    130 +/- 5o C , with in 10 +/- 10 minutes.

    Apply 110 tones pressure and maintain for 20 to 30 minutes. Then after

    every half an hour, increases the pressure and temperature according to

    product requirement.

    Stop heating and then allow cooling the coil under pressure below 50oC, and taking out the coil from the press.

    14.CLEANING AND DRYING:-

    Clean outer and inner surface of projected insulation by means of shop

    made scrubber.

    Flow dry compressed air after cleaning.

    Check height and window dimensions as per drawing.

    Check no gap between the turns.

  • 8/10/2019 Bhel - Training Report Punnet

    28/30

    25

    Test the coil from inter turn test at 116 volts AC at a pressure of 480

    tons in 5 minutes.

    15.Coat the coil with two layers of epoxy red gel.

    TURBO ROTOR COIL SECTION:-

    This section is equipped with copper straightening and cutting

    machines, edge bending machines, installation for forming and brazing, 10-

    block hydraulic press and installation for insulation filling. Rotor coils for

    water cooled generators (210 /235 MW) are manufactured in this section.

    IMPREGNATION SECTION:-

    This section is equipped with electric drying ovens, Air drying booths,

    Bath for armature / rotor impregnation. Rotors / armatures of AC and DC

    motors are impregnated in this section.

    BABBITING SECTION:-

    This section is equipped with alkaline degreasing baths, hot and cold

    rinsing baths, pickling baths, tinning bath, and electric furnaces and centrifugal

    Shot Blasting

    babbitting machines, Babbitting of bearing liners for Turbo generators,

    Turbines, Hydro generators, AC motors and DC motors is carried out in this

    section.

  • 8/10/2019 Bhel - Training Report Punnet

    29/30

    26

    VI. TEST STANDS:-

    Turbo-generators Test Bed -The Test Bed for Turbo-generators and Heavy

    motors is equipped with one no. 6 MW drive motor and a test pit for carrying

    out testing of Turbo-generators and Heavy motors. Open circuit, short circuit,temperature rise, hydraulic and hydrogen leakage test etc., are carried out here

    for Turbo-generators. AC motors up to 11 MVA capacity and DC machines up

    to 5000 amps and 850 volt can also be tested. Two DC drive motors of 2200

    KW and one of 1500 KW are available for type testing of motors. Data

    logging equipment is also available.

    VII. LARGE SIZE TURBO GENERATOR TEST STAND (LSTG):-

    It is equipped with a 12 MW drive motor and two number test pits. Open

    circuit ,short circuit , sudden short circuit , temperature rise , hydraulic &hydrogen leakage tests are carried out here Large size Turbo-generators. This

    test bed can presently test Tgs of unit capacity up to 500 MW. With certain

    addition in facilities (Higher capacity Drive motor and EOT cranes and

    modification in controls and auxiliary systems), Turbo-generators of unit size

    up to1000 MW can be tested.

    HELIUM LEAK TEST

    PURPOSE

    To check any leakage of gas from stator and rotor as if there is any leakage of

    gas used for cooling such as hydrogen then it may cause an explosion.

    VIII. Testing of stator frame involves two types of testing:

    HYDRAULIC TESTING AND PNEUMATIC TESTING

    Hydraulic testing involves in empty stator frame with attached end shields and

    terminal box is subjected to a hydraulic test at 10 bar to ensure that it will be

    capable of withstanding maximum explosion pressure.

    The pneumatic testing involves filling of hydrogen in the sealed stator frame

    and then soap water is used to check the leakage of welding.

  • 8/10/2019 Bhel - Training Report Punnet

    30/30

    4. CONCLUSION

    The Vocational training at BHEL Hardwar helped me in improving my practical

    knowledge and awareness regarding Turbo Generator to a large extent.

    Here I came to know about the technologies and material used in manufacturing ofturbo generators. Besides this, I also visualized the parts involved or equipments used

    in the power generation.

    Here I learnt about how the electrical equipments are being manufactured and how

    they tackle the various problems under different circumstances. At least I could say

    that the training at BHEL Hardwar is great experience for me and it really helped me

    in making or developing my knowledge about turbo generator and other equipment

    used in power generation.

    5.REFERENCES

    1. Material provided by the training Incharge.

    2. Internet