bgcapp year in review dec. 11, 2012

14
Presented to: Kentucky Chemical Demilitarization Citizens’ Advisory Commission/ Chemical Destruction Community Advisory Board Meeting Presented by: Jeff Brubaker Tom McKinney Site Project Manager Project Manager Year In Review Dec. 11, 2012

Category:

Documents


3 download

DESCRIPTION

Presented to: Kentucky Chemical Demilitarization Citizens’ Advisory Commission/ Chemical Destruction Community Advisory Board Meeting Presented by: Jeff Brubaker Tom McKinney Site Project Manager Project Manager

TRANSCRIPT

Page 1: BGCAPP Year in Review Dec. 11, 2012

Presented to:

Kentucky Chemical Demilitarization Citizens’ Advisory Commission/ Chemical Destruction Community Advisory Board Meeting

Presented by:

Jeff Brubaker Tom McKinneySite Project Manager Project Manager

Year In ReviewDec. 11, 2012

Page 2: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

2012 Accomplishments

2

Main Plant Construction

Support Infrastructure

Systemization Activities

Begin

Munitions Reverse-Assembly Equipment

MDB neutralization equipment installed

MDB concrete completion milestone

SCWO Process Building structural steel completion

CSB civil infrastructure complete

Laboratory complete

Nitrogen generation plant vessel installed, foundation complete

Hydrolysate Storage Area foundation complete

Began exterior utility pipe-rack steel

Laboratory Building

Maintenance Building

Personnel Support Building

Utility Power Centers

Rocket Cutting Machine fabrication and testing complete

Rocket Shear Machine fabrication and testing complete

Munitions Washout System begins testing

MDB = Munitions Demilitarization Building CSB = Control and Support Building SCWO = Supercritical Water Oxidation

Page 3: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Control and Support Building• Electrical, piping and fire detection systems• Heating, ventilation and air conditioning (HVAC)• Facility control system cabinets and infrastructure

Munitions Demilitarization Building • Structural steel, paneling, protective coating• HVAC, electrical, piping, mechanical systems• MDB filter area foundations

Construction 60 percent completeSystemization 4 percent complete

• Utility Building• Exterior pipe rack support steel• Interior electrical and piping systems• Nitrogen generation plant equipment

Supercritical Water OxidationProcess Building (not visible in photo)• Exterior siding

Laboratory Building (not visible in photo)• Systemization activities

12

1

2

3

4

5

345

3

Page 4: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Construction Progress

A Fisher Tank subcontractor works on the installation of one of the Hydrolysate Storage tanks.

A team installs and fits embeds in the walls of the Munitions Demilitarization Building blast-containment area.

Piping work continues in the Control and Support Building.

Workers prepare to lift and install a component of the Nitrogen Processing System.

4

Page 5: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Munitions Demilitarization Building (MDB)

Inside, electricians are installing the wiring for the Metal Parts Treater (MPT, above left), while outside, ironworkers “fly in” the first of the many housings for the MDB filter banks (above right). The MPT will thermally decontaminate the metal parts of the munitions after the chemical agent has been drained, and the filter banks will clean the air exiting the main processing building. Installation of structural steel also continues on the MDB.

5

Page 6: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Control and Support Building (CSB)

Deputy Site Project Manager Anthony Reed discusses the project with a group of Eastern Kentucky University honors students in the Control Room (CON, above left). During plant operations, CON operators will observe and control all aspects of the automated processing of the chemical agent munitions. Meanwhile, rolls of some of the 177 miles of wiring to be installed in the CSB are staged for installation (above right).

6

Page 7: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Utility Building (UB)

The UB is surrounded by the pipe rack that will convey processing chemicals to plant operations activities (above left). Inside the UB, sheet metal workers install air compressor heating, ventilation and air conditioning ductwork (above right). Outside the UB, installation of the Nitrogen Processing System continues.

7

Page 8: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Supercritical Water Oxidation Processing Building (SPB)

Project workers started installing insulated siding on the SPB in November 2011. The building should be fully enclosed by the end of the calendar year, allowing the workforce to focus on interior work. Workers prepare insulated panels for installation on the building (above, left) and fly the panels in with a crane workers to install (above, right).

8

Page 9: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Laboratory Building (Lab)

Laboratory Building construction has been completed and the building has been turned over for systemization activities. Systemization of the building should be complete in 2013.

9

Page 10: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Systemization at BGCAPP

10

Blue Grass team completed the Systemization Implementation Plan in 2012

− Maps out construction priorities so we complete projects in most efficient manner

− Allows team to prepare for hiring schedule and plan out key milestone dates

Construction team turned over 15 systems and three facilities in 2012

Systemization is four percent complete

Systemization is the process by which BGCAPP workers make sure the procedures, people and the plant itself are prepared to begin chemical weapons destruction operations

Page 11: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Project Safety

11

3.9

1.5

2.85

0.28

Recordable Injuries Lost-Time Injuries

Construction IndustryBechtel Parsons

Our goal remains Zero Accidents January OSHA Voluntary Protection Program

Star Status workforce celebration May “Safety Pause” reinforced positive safety culture Continuing to address safety concerns

• OSHA VPP Program, worker-based safety teams• Brothers’ Keeper mindset

Our safety record consistently compares favorably to industry standards

Our goal remains Zero Accidents January OSHA Voluntary Protection Program

Star Status workforce celebration May “Safety Pause” reinforced positive safety culture Continuing to address safety concerns

• OSHA VPP Program, worker-based safety teams• Brothers’ Keeper mindset

Our safety record consistently compares favorably to industry standards

Page 12: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

Economic Impact

Acquisitions to date― $102.7 million spent with

Kentucky companies― $62.8 million spent in Madison

and surrounding counties

Local payroll to date― $373 million paid― $437 million more to be paid

during the remainder of project

Held vendor forums, job fairs

Staffing in Richmond now exceeds 990

12

Page 13: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

A Look Ahead

13

Installation of Rocket Cutting and Rocket Shear Machines

Complete testing and delivery of the Munitions Washout System

Completion of Hydrolysate Storage Area tank installation

Set Munitions Demilitarization Building (MDB) filter banks

Complete MDB structural steel Enclose Supercritical Water Oxidation Processing

Building Continue construction focus shift from

civil/structural to large-scale pipe and electrical commodity installation

Page 14: BGCAPP Year in Review Dec. 11, 2012

A Partnership for Safe Chemical Weapons Destruction

14

Questions?

For more information about the Blue Grass Chemical Agent-Destruction Pilot Plant project, please contact the Blue Grass Chemical Stockpile Outreach Office

at (859) 626-8944 or [email protected]