Development And Implementation Of A Customized ERP System For ConstructionBert DebruinPresident of Alta Pro Electric Ltd.

Page 2: Bert Debruin President of Alta Pro Electric Ltd

HISTORY OF ALTAPRO ELECTRIC LTD.

Introductions Beginnings Of Our Journey Changes And Adaptations Through Our Journey Where Our Journey Brings Us Today

ERP- 4 - CON

Page 3: Bert Debruin President of Alta Pro Electric Ltd

GROWTH HISTORYCalendar

Year%

Change in Sales

% Change in Profit

% Change in Labor

Costs

$$$ Loss/Gain in Productivity

2007 +24% +2% +.32 -$22,601.00

2008 +49% Same -.22% +$23,135.00

2009 -21% +2% +4.6% -$383,502.00

2010 +25% -4% +.37% -$38,528.00

2011 +27% -8% +.85% -$112,314.00

2012 +14% Same +4.3% -$645,980.00

2013 +.01% +8% -.016% +$292,500.00

ERP- 4 - CON

Page 4: Bert Debruin President of Alta Pro Electric Ltd

PROBLEMS WITH CURRENT OPERATIONS

Lack Of Costing Control And Project Analysis Inconsistent Materials Acquisition Processes Communication Gap Between Office And Field Time Spent To Manually Input Duplicate Information Laborious Manual Process To Transfer Useful Data

From Estimates To Projects

ERP- 4 - CON

Page 5: Bert Debruin President of Alta Pro Electric Ltd

TARGETED SOLUTIONS

Integrated Timesheets And Purchase Orders That Automatically Apply Costs To The Relevant Project

Integrated Materials Database With Up To Date Purchase Costs

Full Access For Crew Leaders To All Project Documentation

Information Is Input Once And Carried Forward To All Areas Needed

Integrated Solution That Pairs Estimating And Project Management Software

ERP- 4 - CON

Page 6: Bert Debruin President of Alta Pro Electric Ltd

BENEFITS ACHIEVED WITH AN ERP

Accurate Daily Job Costing With Key Performance Indicators

Ability To Manage Costs More Effectively Increased Efficiency And Accuracy Of Information

Sharing More Accurate Manpower Forecasting Stronger Feedback To Estimating Department With

Actual Project Information

ERP- 4 - CON

Page 7: Bert Debruin President of Alta Pro Electric Ltd

REASONS FOR A CUSTOM ERP

Adapt The Tools To Your Existing Workflows Grows Fluidly With Company Growth New Tools And Workflows Can Be Integrated More

Effectively Competitive Edge – Proprietary Workflows Developing A ERP Tests Existing Operations Exposes Current Limitations Providing Growth

Opportunities

ERP- 4 - CON

Page 8: Bert Debruin President of Alta Pro Electric Ltd

REASONS AGAINST CUSTOM ERP

Extended Duration Before Implementation Testing New Practices In An Un-finalized State Unfamiliarity With New IT Terminology And

Programming Development Larger Financial Investment Up Front Disconnect Between Developer And Company

ERP- 4 - CON

Page 9: Bert Debruin President of Alta Pro Electric Ltd

MAJOR HURDLES

Finding The Right Developers Do You Speak The Same Language? Does Your Interpretation Match Their Interpretation?

Image Credit: freedigitalphotos.com

ERP- 4 - CON

Page 10: Bert Debruin President of Alta Pro Electric Ltd

MAJOR HURDLES

Understanding Software Design and Limitations Differing Operating Systems Differing Programming Languages Differing Communication Environments

Image Credit: freedigitalphotos.com

ERP- 4 - CON

Page 11: Bert Debruin President of Alta Pro Electric Ltd

MAJOR HURDLES

Understanding Hardware and Infrastructure Requirements Internet Bandwidth-Existing Infrastructure Remote User Accessibility Security Protocols

Image Credit: freedigitalphotos.com

ERP- 4 - CON

Page 12: Bert Debruin President of Alta Pro Electric Ltd

ERP REQUIREMENTS FOR SUCCESS

Full Analysis Of Current Workflows Before CMS Development Began Cross Department Collaboration On Analysis Asses Effectiveness Of Current Procedures Employee Input On Ways To Increase Effectiveness

ERP- 4 - CON

Page 13: Bert Debruin President of Alta Pro Electric Ltd

ERP REQUIREMENTS FOR SUCCESS

Analysis Of Current Interface Options How Are Employees Going To Access The Software? What Are The Limitations?

Image Credits: freedigitalphotos.com

ERP- 4 - CON

Page 14: Bert Debruin President of Alta Pro Electric Ltd

TRUTHS ALONG THE WAY

We Didn’t Necessarily Do It Right On The First Try

ERP- 4 - CON

Page 15: Bert Debruin President of Alta Pro Electric Ltd

WORKFLOW ANALYSIS

ERP- 4 - CON

Page 16: Bert Debruin President of Alta Pro Electric Ltd

INTERFACE DESIGN

ERP- 4 - CON

Page 17: Bert Debruin President of Alta Pro Electric Ltd

CHALLENGES

Assuming Our Current Documentation Styles Would Easily Translate Into An Automated System

Assuming The Developers Will Know How To Address Every Design Request Easily

ERP- 4 - CON

Page 18: Bert Debruin President of Alta Pro Electric Ltd

SUMMARY OF AFFECTED SYSTEMS

Human Resources Contacts And Communications Estimating And Proposals Pre-project Planning Project Management In Office Site Project Management Materials Acquisition And Control Labor Management And Control Quality Assurance And Quality Control Project Close Out

ERP- 4 - CON

Page 19: Bert Debruin President of Alta Pro Electric Ltd

PROGRAM HUMAN RESOURCES

Manual Entry Of Faxed In And Dropped Off Timesheets

Employee Training Records Not Accessible

Employee Records Kept In Excel With Limited Access

Contact Database In Reference Documents

Direct Input Of Timesheet Entry By Employees

Employee Training Records Visible To All Employees

Integrated Employee Database

Contact Database Directly Integrated

EXISTING NEW PROGRAM

ERP- 4 - CON

Page 20: Bert Debruin President of Alta Pro Electric Ltd

ESTIMATING AND PROPOSALS

Estimating Department And General Manager Discuss Gaps In Future Work

Low Level History Of Bid Success

Estimating Documents Need Manually Moved In To Project Files

Estimating Department Has Direct Access To All Project Scheduling

Fully Detailed And Searchable Bid History

Estimating Files Linked Directly To Project In System

EXISTING NEW PROGRAM

ERP- 4 - CON

Page 21: Bert Debruin President of Alta Pro Electric Ltd

PRE-PROJECT PLANNING

Project Manager Approximates Manpower Timelines

Manual Loading Of Estimate Data For Cost And Productivity Tracking

Automated Project Labour Duration Projection

Integrated Information Loading For Cost And Productivity Tracking

EXISTING NEW PROGRAM

ERP- 4 - CON

Page 22: Bert Debruin President of Alta Pro Electric Ltd

ERP- 4 - CON

Page 23: Bert Debruin President of Alta Pro Electric Ltd

PROJECT MANAGEMENT - OFFICE

Need To Manually Input Same Information Multiple Times

Various Excel Documents To Track Project Details

Critical Tasks Recorded Manually

All Information Is Entered Once

All Project Details In One System

Critical Task Procedures Produce Automatic Reminders

EXISTING NEW PROGRAM

ERP- 4 - CON

Page 24: Bert Debruin President of Alta Pro Electric Ltd

PROJECT MANAGEMENT - FIELD

Access To Project Changes Through Printed Documents

Reliance On Email From Project Manager For Status Updates

Reliance On Office Staff To Load Current Material Pricing Into Project Folders

Online Access To All Current Change Documentation

Automatic Alert When A Change Is Approved

Access To Integrated Materials Database With All Current Pricing

EXISTING NEW PROGRAM

ERP- 4 - CON

Page 25: Bert Debruin President of Alta Pro Electric Ltd

MATERIAL ACQUISITIONS AND CONTROL

Call Or Email Suppliers For Latest Prices

History Of Cost Not Searchable

Shipment Shortages And Damages Not Reported Immediately

Long Term Pricing Agreements

Full History Of All Material Cost Adjustments

Immediate Notification To The Office For Shipment Issues

EXISTING NEW PROGRAM

ERP- 4 - CON

Page 26: Bert Debruin President of Alta Pro Electric Ltd

LABOR MANAGEMENT AND CONTROL

Labor Allocation Based On Personal Experience

Labor Issues Not Readily Apparent Until Project End

Excel Document Used To Project Number Of People Needed

Requests For Hiring Personnel Done Through Emails

Exact Labor History Of Projected Vs. Actual

Exact Numbers On Labor Overages

Project Overages / Shortages For Specific Type Of Employee

Integrated Detailed Personnel Shortage Alerts Sent To HR

EXISTING NEW PROGRAM

CMS-4-PAP

Page 27: Bert Debruin President of Alta Pro Electric Ltd

ERP- 4 - CON

Page 28: Bert Debruin President of Alta Pro Electric Ltd

ERP- 4 - CON

Page 29: Bert Debruin President of Alta Pro Electric Ltd

ERP- 4 - CON

Page 30: Bert Debruin President of Alta Pro Electric Ltd

QUALITY ASSURANCE AND CONTROL

Company Standards On Paper In Binders

Access To Updated Standards Through Email Or Printed Documents

Crew Leaders Send Training Requests To Office When Needed

Company Standards Filed Electronically

Online Access To Latest Company Standards

Integrated Training History With Alerts

EXISTING NEW PROGRAM

ERP- 4 - CON

Page 31: Bert Debruin President of Alta Pro Electric Ltd

PROJECT CLOSEOUT

Project Manager Must Call Or Email Crew Leaders

Project Manager To Discuss Project Completion With Accounting

Online Access / Alerts To Dates Of Completion

Integrated Notifications To Accounting For Project Completion

EXISTING NEW PROGRAM

ERP- 4 - CON

Page 32: Bert Debruin President of Alta Pro Electric Ltd

COSTS TO DEVELOP NEW ERP

Capitalized Costs Hardware Costs Payroll For Employee Working With Developers Revisions During Development

ERP- 4 - CON

Page 33: Bert Debruin President of Alta Pro Electric Ltd

COSTS TO DEVELOP NEW ERP

Non Capitalized Costs Evaluation Of Alternatives Research And Development Training Costs

ERP- 4 - CON

Page 34: Bert Debruin President of Alta Pro Electric Ltd

HOW DO WE IMPLEMENT NEW ERP?

Parallel Adoption Simultaneous Use Of New And Old Systems

Triple Training Company Wide Group Training Individual Site Training Individual Employee Training

ERP- 4 - CON

Page 35: Bert Debruin President of Alta Pro Electric Ltd

HOW DO WE CONTROL IMPLEMENTATION?

Gradual Rollout Improved Standard Operating Procedures Gather Employee Feedback And Monitor Pain Points Consistent Support For Employee Adaptation

ERP- 4 - CON

Page 36: Bert Debruin President of Alta Pro Electric Ltd

HOW DO WE MEASURE SUCCESS?

Increased Productivity Increased Efficiency Increased Capacity Increased Employee Satisfaction Increased Client Satisfaction

ERP- 4 - CON

Page 37: Bert Debruin President of Alta Pro Electric Ltd

VALIDATION OF CUSTOM ERP

Measureable Decrease in Wasted Overhead Improved Quality and Consistency of Information Ease of Operations For Employees

ERP- 4 - CON

Page 38: Bert Debruin President of Alta Pro Electric Ltd

HOW CAN THE NEW ERP BE IMPROVED?

Practical Testing of New Workflows Implement Native Estimating, Accounting, and Inventory

Software. Leverage Cloud Based Computing Power

ERP- 4 - CON

Page 39: Bert Debruin President of Alta Pro Electric Ltd

TAKE AWAY MOMENTS...FUTURE

More Frequent And More Accurate Information Tighter Integration Of The Entire Organization Streamlined Workflows Company Wide Uniformity – Higher Quality

Image Credit: freedigitalphotos.com

ERP- 4 - CON

Page 40: Bert Debruin President of Alta Pro Electric Ltd

ERP- 4 - CON

This technology adoption project was supported in part by the National Research Council of