    PROJECT CONTROL

    PRINCIPLESBernd Madauss

    I nternational Space University

    [email protected]

    2010

    mailto:[email protected]:[email protected]
  • 8/13/2019 Bernd Madauss_Project Control Principles

    2/30

    2

    PPerformance Dependence of

    Parameters

    SSchedule

    CCosts

    Optimization of Project Parameters:Performance (P), Schedule (S) and Cost (C)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    3/30

    3

    Project Management & Control

    Status Control Technical Achievements Critical Areas

    Documentation Engineering Changes Schedule (Actual vs. Plan, Critical Path) Actions Financial Status Contractual

    Status vs. Planning Deviations to Plan Corrective Actions & Resolutions

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    4/30

    4

    Project Management & Control

    Analysis Impact to entire Project Consequences to Project Goal Decisions to be taken

    Management Decisions Change of Project Baseline

    Technical Requirements Schedule Restraints Financial Contractual

    Change of Project Plans

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    5/30

    5

    Integrated Project Control Process(Project Feedback Solution)

    PROJECTBASELINE

    PROJECTPLANS

    ANALYSIS

    FORECAST

    PM

    DECISIONS

    PROJECTATP

    STATUS

    REVIEW

    TASK

    PERFORMANCE

    COMPARE

    TO PLAN

    P

    S

    C

    At CTR AwardR&D, Organization

    AIV, Test, Operations

    Total Project, Dedicated

    WPs, Subcos & Supplier

    Status ReviewDeviation AnalysisPropose

    Corrective Actions

    Actions,

    Changes,

    Redirection

    ATP = Authority to Proceed

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    6/30

  • 8/13/2019 Bernd Madauss_Project Control Principles

    7/307

    Work Breakdown Structure(sample only)

    1st Stage

    Contractor "D"

    Russia

    2nd Stage

    Contractor "E"

    Ukrain

    Fairing

    Contractor "I"

    Switzerland

    Launch Campaign

    Contractor "K"

    Kasakstan

    Supply of

    Launch Vehicle

    Contractor "A"

    USA

    Payload

    Contractor "H"

    USA

    Bus

    Contractor "G"

    France

    Propulsion

    Contractor "H"

    Germany

    Interface

    Contractor "F"

    Japan

    Supply of

    Satellite

    Contrctor "B"

    France

    TT&C Station

    Contractor "L"

    Italy

    Up-Link

    Contractor "M"

    Spain

    Data Processing

    Contractor "N"

    Belgium

    Telemetry

    Contractor "O"

    UK

    Supply of

    Ground Station

    Contrctor "C"

    UK

    Tracking

    Company "P"

    Germany

    Monitoring

    Company "D"

    Holland

    Evaluation

    Company "Q"

    Ireland

    Relay

    Company "R"

    China

    Satellite

    Operations

    Contractor "D"

    Holland

    Satellite

    System

    Customer

    Luxembourg

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    8/308

    Work Breakdown Structure (WBS)A Key to Successful Project Management !!!The WBS serves several important Purposes, such as:

    Subdivision of Work

    Identification of Project Levels

    Work Sharing between Companies

    Economic Geographical Distribution of Funds

    Implementation of WBS Numbering System (Code) applicable to the entire Project

    Definition of Cost Account Structure

    Allocation of Funds

    Implementation of Project Control in line with the WBS Code

    Assignment of Responsibilities to Companies & Individual Managers Identification of Interfaces at all Levels

    Implementation of Documentation Numbers related to WBS Code

    Identification of Work Packages

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    9/309

    Content of Work Package Description

    Work Package (WP) Identification Title Identification of the WP in the WBS (WP Number) Date of the Start and End of the WP Company or Entity in charge of the WP Performance

    Assign Work Package Manager

    Description of WP Tasks to be Performed

    Tasks Explicitly Excluded

    WP Inputs (Documents, Hardware, Software)

    WP Outputs (Products: Hardware, Software, Documents)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    10/3010

    Project Milestones

    Identify Project Milestones

    Major Milestones

    Payment Milestones

    Other Milestones

    Planned Achievements Important Key Events for Control

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    11/3011

    1. Establish Schedule Baseline

    project task

    time

    Input * Output **

    *Objective, requirements,

    mission plan, etc.

    **Deliverables (HW, SW,

    documentation

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    12/3012

    Specification

    Design

    Production

    Test

    1. Establish Schedule Baseline(Sequence of Events)

    Activity

    Dummy Activity

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    13/3013

    1. Establish Schedule Baseline(Sequence of Events and Durations)

    Specification

    Design

    Production

    Test

    4 w

    8 w

    6 w

    2 wto + 20

    to

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    14/3014

    Baseline Milestone ScheduleA INSTALLATION

    B APPROVAL RESPONSiBILITY

    C ACCOMPLISHMENT RESPONSiBILITY

    H SCHEDULE TITLE

    J CONTRACTORG PROJECT

    I SCHEDULE NO. (LEAVE BLANK)

    D ORIG. SCHEDULE APPR.

    E LAST SCHEDULE CHANGE

    F STATUS AS OF

    K LEVEL

    MILESTONES

    L KEY MILESTONES

    M INTERNAL MILESTONES

    N INTERFACES

    O NOTES

    TIME SCALE

    (DATE)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    15/3015

    1. Prepare Schedule Baseline(sample schedule)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    16/3016

    1. Establish Schedule Baseline(Critical Path Analysis)

    Specification

    Design

    Production

    Test

    4 w

    8 w

    6 w

    2 wto + 26

    to

    Material

    20 w

    Critical Path of Project

    Positive Slack

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    17/3017

    Specification

    Design

    Product.

    Test

    2. Establish Schedule Targets(Definition of Milestones)

    Activity

    Dummy Activity

    Complete

    Complete

    Complete

    Complete

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    18/3018

    Identify Project Milestones

    Major Milestones

    Payment Milestones

    Other Milestones

    Describe Planned Achievements

    Perform Control

    2. Establish Schedule Targets(Definition of Milestones)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    19/3019

    Baseline Planning

    Measurement of Achievements

    Comparison of Planned and Actual

    Deviations to Plan

    Corrective Actions

    4. Provide Schedule Control(Status Monitoring)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    20/3020

    Aufgaben

    Konstruktion

    Fertigung

    Zusammenbau

    und Test

    1 2 3 4 5 6 7 8 9 121110

    -2

    - 4

    +2

    4. Provide Schedule Control(Status Monitoring)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    21/3021

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    14

    13

    12

    11

    0 1 2 3 4 5 6 7 8 9 10 14131211

    3

    4

    1

    5

    2G

    eplanterTermin*

    Berichterstattung *

    Berichterstattungfr 3 bis 5 nichtrealistisch

    Problem -Erkennung

    Terminverzge von1 bis 3 haben vollauf 4 und 5 durch-geschlagen

    * Monate nach Projektbeginn (0)

    4. Provide Schedule Control(Schedule Trend Charts)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    22/30

    22

    5. Identify Schedule Problem Areas

    Activities and/or Milestones are not

    Completed in Time

    Progress Information not Available

    Work Forecast Shows Delay of Deliverables

    Critical Path Analysis not Performed

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    23/30

    23

    6. Implement Corrective Actions

    Requesting Additional resources to Complete

    Activities and/or Milestones on theCritical Path

    Provide Constantly Progress Information

    Introduce Work Around Solutions

    Perform Critical Path Analysis

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    24/30

    24

    7. Implement Schedule Reporting

    Activities and Milestones Completed

    Work Forecast of Activities to be Completed

    including Time to Completion (TTC)

    Schedule Problem Areas and Solutions

    Results of Critical Path Analysis

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    25/30

    25

    Project Cost Plans

    Cost Account Structure

    Manpower & Cost Plan

    Travel & Subsistence

    Overall Cost Summary

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    26/30

    26

    Planning Of Project Resources

    Manpower Requirements

    Material Requirement

    Requirements for Machines

    Facility Requirements

    Travel Requirements

    Others (TBD)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    27/30

  • 8/13/2019 Bernd Madauss_Project Control Principles

    28/30

    28

    RESOURCE MANPOPWER & COST STATUS REPORT

    Manpower andCostElements

    a. Budget b. Actual c. PO d. CTC e.Forec

    ast(b + c + d)

    f. Variance(e a)

    Manpower(Hours)

    1 200 900 0 400 1 300 - 100

    Costs (Euro):o Manpowero Travelo Materialo Equipmento Supplierso Others

    120152535

    90580

    001329

    401130

    130162429

    - 10- 1+ 1+ 6

    Grand Total 195 103 42 54 199 - 4

    Manpower and Cost Control

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    29/30

    29

    arned Value Methodology

    e:\pmt\seminare\s_10\s_10gf02.cdr Fo-03

    100

    500

    300

    700 Statuskontrolle ( 01.07.XX )

    Akkumulierte Kosten (TDM)

    Plankosten ( PK )

    Zeitplan

    KostenplanAkk. Kosten

    Ist-Kosten

    Akk. Ist-Kosten

    Terminplan

    Ist-Kosten ( IK )

    Cost to Completion ( CTC )

    Arbeitswert ( AW )200

    600

    400

    1 10 115 153 1372 126 164 148 9

    20 45 45 70 70 75 65 65 40 --65 40 --40 -- --65 110 180 250 325 390 520 600 --455 560 --640 -- --15 40 40 45 50 60

    55 95 140 190 250

    Accumulated

    Costs

    Time Now (TN)

    BCWS

    BCWP

    ACWP

    Cost Plan

    Actual Costs

    Time Schedule

    ACWPActual Cost Work Performed

    BCWPBudgeted Cost Work Performed

    BCWSBudgeted Cost Work Scheduled

    Cost at Completion (CAC)

    Project Control Pr inciples

  • 8/13/2019 Bernd Madauss_Project Control Principles

    30/30

    RecommendedProject Management Literature

    Kerzner, Project Management & Study Guide, 8thEdition

    Madauss, Projektmanagement, 6th Edition, 2000,German

    Verzuh, The Fast Forward MBA in Project

    Management, 1999 Terry, Principles of Management, 7th Edition ESA, Space Project Management, ECSS-M

    Project Control Pr inciples