1 Overview of Composite Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow Composite Materials & Process Engineering 14 September 2010

Upload: trankhuong

Post on 02-Aug-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

1

Overview of CompositeMaterial & Process Control Rotorcraft OEM Perspective

Mark ChrisAssociate Technical Fellow

Composite Materials & Process Engineering

14 September 2010

Page 2: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering2

Overview

Requirements Control of Materials Control of Processes

Methods of Compliance Integrating Extended Supply Chain Raw Material Suppliers OEM fabricated parts Subcontractor/Partner fabricated parts

Page 3: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering3

Composite Part Fabrication Steps Requiring control

Material Tooling

Layup

CompactionCureComposite Part

Basics

Page 4: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering4

Requirements Commercial Programs - Code of Federal Regulations (CFRs) Military Programs - DOD System Design Specifications

PER Bell SPI 431...”Bell Helicopter will fully comply with applicable regulations”

14 CFR 21.123 Production under a type certificate: “…establish and maintain an (FAA) approved production inspection system that insures that each product conforms to the type design…”

14 CFR 21.125(b1) Production inspection system, MRB:“Incoming materials used in the finished product must be as specified in the type design data…”

Page 5: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering5

Requirements 14 CFR 21.165(a) Responsibility of holder: “Maintain the

quality control system in conformity with the data and procedures approved for the production certificate.”

Approved Data and Procedures: Engineering Drawing specifies -

• Materials by the controlling Material Specification.

• Processes by the controlling Process Specification.

• Inspection and acceptance criteria.

Material Specifications14 CFR 29.603(b) Materials must meet approved specifications that ensure their having the strength and other properties assumed in design data.

Design Values14 CFR 29.613(a) Material strength properties must be based on enough tests of material meeting specifications to establish design values on a statistical basis.

Process Specifications14 CFR 29.605(a) The methods of fabrication used must produce consistently sound structures. If a fabrication process (such as gluing, spot welding, or heat-treating) requires close control to reach this objective, the process must be performed according to an approved process specification.

Page 6: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering

Start at the base of the building block

approach -(Materials/Coupons)

FAA Material & Process Control WorkshopWichita KS

6

Page 7: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering7

Guidance: Advisory Circular AC No. 21-26 Quality Control for the Manufacture of Composite Structures

FAA approved Bell M&P Specifications & Quality Systems follow this Model:

Incoming material acceptance plan - Ensures conformity and uniformity of purchased composite materials to specifications identified in the approved type design.

Supplier laboratory test reports (Certificate of Conformity) -Actual test results that accompany each batch of material received

Purchaser Receiving Inspection - Samples taken on a batch-to-batch basis and tested by end user.

Allowance for reduced testing - After confidence in the quality of products from a particular source has been established by the production approval holder

Methods of Compliance

Page 8: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering8

Reduced Testing – Source InspectionBell approved Agent or Representative observes all

required supplier quality conformance testing at the source facility:

Mitigates need for duplicate testing at purchaser facilities. Material System specific – Approval noted on QPL Requires Statistical Basis – Historical purchaser and

supplier data analyzed to demonstrate long term stability. Source Inspection Plan – Formalized written process for

data evaluation, training & approval of agents (delegates), audit requirements, audit schedules, inspection work plans/reports and “Authorization to Ship”.

Typically applied to “high volume” material systems/parts. Web based “SMART” system developed by Bell to manage

delegated source inspection process (Materials & Parts).

Methods of Compliance

Page 9: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering

Higher levels of the building block -

(Details/Components)

FAA Material & Process Control WorkshopWichita KS

9

Page 10: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering10

Inspection of Composite Parts/AssembliesFirst Article Inspection required to demonstrate all

engineering requirements are met: Locks production configuration (materials, processes,

tooling and inspection). Creates baseline conformity data set. Non-destructive & destructive testing (depends on Class)Production Inspection Non-Destructive Inspection (NDI) – Formalized written

inspection procedures and acceptance criteria. General and/or part specific.

Scheduled Destructive Test – Primary Dynamic structures (may be mitigated by advanced NDI capability).

Unscheduled Destructive Test – Significant changes in process, tooling, location of manufacture etc.

Methods of Compliance

Page 11: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering11

MRB System for Composite Parts/AssembliesMaterial Review Board System required to assess and

disposition all non-conforming materials and parts: Formalized written review and disposition procedures. Specific personnel requirements must be met to be placed

on approved MRB list (Rigorous In-house & Offsite delegation process).

Requires development of corrective and preventative action plans as part of the review/disposition process.

Requires periodic audit of the MRB process to ensure: Awareness of known issue areas Validation/Analytical requirements are met Accuracy of dispositions Standardization of the process

Methods of Compliance

Page 12: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering12

ATLM

Hydro-abrasive Water Jet5-Axis Machining

Fiber Placement(Unique Fiber Forms)

Opportunities for reduced process variability (automation)

Page 13: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering13

Integration Challenge - Establish and monitor M&P controls across an extended supply chain. Equivalence of test results between Material Supplier,

OEM and Subcontractors/Partners - mitigate “false positives” (lab-to-lab variation).

Consistent interpretation of Material & Process Specifications.

Consistent Training across the supply chain. Understanding/addressing cultural differences. Managing ECCN and ITAR requirements on materials,

parts and data (International programs).Oversight & scheduled auditing of all the above.

Page 14: Bell Material and Process Control - Wichita State … and... · Material & Process Control Rotorcraft OEM Perspective Mark Chris Associate Technical Fellow ... PER Bell SPI 431...”Bell

Engineering14

Rotorcraft Damage “Tolerance”

Bell OH 58D –Kiowa Warrior Operation Iraqi Freedom

Thank You