Design for Operations Space Shuttle vs. Sea Launch Bo Bejmuk

Upload: nasapmc

Post on 25-May-2015

13.267 views

Category:

Technology


0 download

TRANSCRIPT

Page 1: Bejmuk bo

Design for OperationsSpace Shuttle vs. Sea Launch

Bo Bejmuk

Page 2: Bejmuk bo

2

Shuttle Sea Launch

Space Shuttle designed for ascent performance, multi functionality and minimum development cost

Result:

Costly ground operationsCostly mission planningCostly flight operations

Zenit Rocket designed to strict operational requirements

Result:

Automation and robust designSimple and cost effective operationsGreat benefit to cost of ownership

Courtesy of the Sea Launch Company

Page 3: Bejmuk bo

3

Space Shuttle – Magnificent flying system but difficult and costly to operate

Page 4: Bejmuk bo

4

Initial Naive Concept of Ground Operations

Page 5: Bejmuk bo

5

Operational Reality

NASA, KSC Photo, dated September 25, 1979, index number “KSC-79PC-500”

Page 6: Bejmuk bo

6

Lack of Robustness and Design Margins Complicated flight Planning and Increased Cost

Problem• The launch probability predictions for early Shuttle flights was less than

50%– More than half of the measured winds aloft violated the vehicle’s certified

boundariesCorrective Actions• System Integration led the evolution from a single ascent I-load, through

seasonal I-loads, alternate I-loads, and finally arriving at DOLILU• This process extended over a 10+ year period• Concurrently the Program executed 3 load cycles (Integrated Vehicle

Baseline Characterization - IVBC) combined with hardware modifications to expand vehicle certified envelopes

• Current launch probability is well in excess of 95%Lesson• Commit to a DOLILU approach during early development

– Significantly improves margins• Use additional margins on not well understood environments• Will enhance robustness and simplify operations

Page 7: Bejmuk bo

7

Ascent Design Operations Evolution

1975 1985 1995 2005

50

0

100

Med

High

Low

Ope

ratio

ns O

verh

ead

Perc

ent o

f Win

ds V

iola

ting

Cer

tific

atio

n (%

)

AnnualSeasonal

MonthlyAlternate

Day-of-Launch

Lesson Learned: Reliance on Operations Process to Maintain Margin is Expensive

Certification Violations

Ascent OperationsOverhead

Page 8: Bejmuk bo

8

Early FlightsSingle I-Loads

Present FlightsDOLILU

Qb

3-Hour Wind Variation

DOLILU drives toward center of Qa – Qbenvelope and reduces winds violation to < 5%

Certified Envelope

Expanded Certified Envelope

Over 50% of winds violated certified envelope

Annual Wind Variation

Qa

Qb

Qa

Day-of-Launch I-Loads Evolution(10 years +)

Page 9: Bejmuk bo

9

Where did We go Wrong?Problem• Insufficient definition of operational requirements during

development phase– Concentration on performance requirements but not on operational

considerations– Shuttle design organizations were not responsible for operational cost– Very few incentives for development contractors

Result• Very labor intensive (high operational cost) vehicle was developed

and put into operationsLesson• Must have the Concept of Operations defined• Define and levy the operational requirements on contractors to

support the Concept of Operations• Must have continuity and integration between designers, ground

operations, and flight operations requirements during the developmental phase

Page 10: Bejmuk bo

10

Sea Launch Zenit Rocket Very Efficient and Easy to Operate

Courtesy of the Sea Launch Company

Page 11: Bejmuk bo

11

Launch Platform

Courtesy of the Sea Launch Company

Page 12: Bejmuk bo

12

Assembly and Command Ship

Courtesy of the Sea Launch Company

Page 13: Bejmuk bo

13

Launch

Courtesy of the Sea Launch Company

Page 14: Bejmuk bo

14

Sea Launch – Zenit Derived Launch System • Major integration of existing and new

elements– Two stage Ukrainian Zenit

– 3rd stage Russian Block DM

– New payload accommodation & composite fairing

– Modified semi-submersible oil drilling platform into a launch pad

– New command and control and rocket assembly ship

• System was built and brought to operational state in less than 3.5 years – 24 flights to date

Courtesy of the Sea Launch Company

Page 15: Bejmuk bo

15

Sea Launch Operations • Integration of rocket stages

and payload at home port in Long Beach, CA

• Launches performed from the Equator, 154 degrees west (south of Hawaii)

300405Totals

401405070

802005075

AmericansRussiansUkrainiansNorwegians

Launch Team*

Ground ProcessingTeam

* Launch Team is a subset of the Ground Processing Team; GroundProcessing team members that are not required to participate in launch at sea are sent back to their companies and are off the Sea Launch payroll

Small Team performs ground checkout and launchCourtesy of the Sea Launch Company

Page 16: Bejmuk bo

16

Lessons Learned from Sea Launch

• Zenit extremely automated launch vehicle – Very little interaction with crew during checkout, pre-launch, and

flight

• Single string accountability, no duplications of effort (to some extent driven by export compliance restrictions)

• Low operational cost benefited from original design criteria of Zenit– Rollout to pad, fuel and launch in 90 minutes

– Allows very little time for ground or flight crew involvement

– Imposes requirements for automatic processes

Page 17: Bejmuk bo

17

The Big Lesson

• If we want simple and cost effective operations we must design for operations– Shuttle designed for performance and minimum

development cost– Sea Launch Zenit Rocket designed to strict

operational requirements

• NASA is in control of operations destiny of new programs– Narrow window of opportunity