before the board of inquiry in the matter of the … · a concrete face rockfill dam (“cfrd”)...
TRANSCRIPT
Sainsbury Logan & Williams Ref: Lara J Blomfield Solicitors Fax: 06-835 6746 Cnr Tennyson Street and Cathedral Lane Phone: 06-835 3069 PO Box 41 Napier
BEFORE THE BOARD OF INQUIRY
IN THE MATTER of the Resource Management Act 1991
AND
IN THE MATTER
of the Tukituki Catchment Proposal
STATEMENT OF EVIDENCE OF
Phillip Richard CARTER
TABLE OF CONTENTS
1. INTRODUCTION ................................................................................................... 1 2. SUMMARY AND CONCLUSIONS ......................................................................... 2 3. OVERVIEW OF REPORT ..................................................................................... 4 4. COMMENTS ON SUBMISSIONS .........................................................................23 5. REFERENCES .....................................................................................................26
Page 1
1. INTRODUCTION
1.1 My name is Phillip Richard Carter
1.2 My formal engineering qualifications consist of a Bachelor of Engineering, 1967,
University of NSW and a Master of Engineering Science, 1972, University of
NSW in water engineering. I have 47 years of continuous experience in dam
engineering and hydraulic structures such as large gated weirs, irrigation
structures and river management works. This has included direct site
investigation and design experience with most types of major dams including
earthfill, earthcore rockfill, concrete face rockfill and mass concrete including
prestressed dams. I have directed multi-disciplinary project teams for a number
of major dam engineering projects.
1.3 Until August 2004, I was Principal Engineer & Manager Water Technologies for
the NSW Department of Public Works. This required overall management and
direction of a team of 100 professional and technical staff providing a
commercial engineering consultancy service covering water supply and
irrigation infrastructure, urban drainage and flood protection, river management,
roads, bridges and tunnels.
1.4 Since August 2004, I have worked as a consulting engineer on dam and
irrigation projects working for various clients including several major consulting
firms such as Tonkin & Taylor.
1.5 Purpose and scope of evidence
1.6 I assisted with preparation of the report entitled “Ruataniwha Water Storage
Scheme Project Description” (“PD”) in relation to the proposed Ruataniwha
Water Storage Scheme (“RWSS”) comprising part of the Tukituki Catchment
Proposal (“TCP”) being considered by the Board of Inquiry. In particular, my
involvement was centred on the development of the concept, feasibility and in
turn Application Design (as described in the PD) for the dam component of the
RWSS.
1.7 The purpose of my evidence is to provide an overview of the PD in relation to
the dam, and to address issues raised by submitters to the RWSS component
of the TCP in relation to the dam. Given the relationship between issues raised
in submissions and the considerations applied in the development of the
Application Design, I have integrated much of the response I consider needs to
Page 2
be made to submissions within the overview of the PD in relation to the dam set
out below.
1.8 I note for assistance of the Board that the discussion in this evidence of the
principal design considerations for the dam and its auxiliary structures and
components, along with the construction sequence, essentially covers the
information in Section 4 of the PD, commencing at page 44 though to page 57.
Where relevant, e.g. to respond to issues raised by submissions, I go into more
detail than the PD on a given topic, with reference to background assessments
and reports that informed that document. On other topics, the converse applies,
and the PD is more detailed in its account.
Expert Code of Conduct
1.9 I have read the Code of Conduct for Expert Witnesses in section 5 of the
Environment Court’s Practice Note (2011). I agree to comply with that Code of
Conduct. Except where I state that I am relying upon the specified evidence of
another person, my evidence in this statement is within my area of expertise. I
have not omitted to consider material facts known to me that might alter or
detract from the opinions which I express.
2. SUMMARY AND CONCLUSIONS
2.1 The proposed total water storage requirement of 90 million m3 at the site results
in a dam of approximately 83 m height at the river’s deepest point. A Concrete
Face Rockfill Dam (“CFRD”) has been selected for the Application Design. The
crest is 505 m long and 8 m wide.
2.2 Two spillways are provided to pass flood flows. A concrete lined chute spillway
controlled by a 25 m wide arc-crested concrete ogee crest is located on the
right abutment. This spillway terminates in a hydraulic jump dissipator located
within the rockfill quarry for the embankment. An outlet channel excavated into
the quarry floor takes flows back to the river. This channel is located well away
from any rockfall that may result from earthquake induced damage to the area
of dilated, potentially unstable rock on the left bank wall of the gorge.
2.3 A secondary (auxiliary) spillway consisting of a simple 50 m wide unlined
excavated channel is located on the left abutment. This spillway has a crest
level that is 3.25 m above the primary spillway and does not operate for normal
Page 3
flood inflows. Discharges commence for floods that exceed the 1 in 200 AEP
inflow with a full storage.
2.4 The general design criteria for the works are based on the New Zealand Society
of Large Dams (NZSOLD) Dam Safety Guidelines and also consideration of the
Building (Dam Safety) Regulations (2008). Where the NZSOLD Dam Safety
Guidelines do not cover specific design details, the design is based on
international guidelines and practice documents.
2.5 The Ruataniwha Dam will have a high potential impact classification (PIC) and
therefore the design ground motion is required to be taken equal to the 84th
percentile level of the ground shaking associated with rupture of the Mohaka
fault. This standard is also applied to other high risk projects like nuclear power
plants.
2.6 The effect of earthquakes on concrete faced rockfill dams is to deform the
embankment with flattening of the slopes due to ravelling and sliding of shallow
materials. This produces a permanent slumping and spreading of the dam
rather than a failure along a distinct surface, i.e. a large crack or rupture.
2.7 My assessments along with preliminary theoretically based analyses of the
expected effects of earthquake ground motion on the dam undertaken by
Tonkin & Taylor indicate only moderate deformations under the Maximum
Credible Earthquake expected for the Ruataniwha Dam.
2.8 Given the close proximity of the Mohaka Fault to the dam site, there is a
possibility of secondary or sympathetic movement on pre-existing shears or
secondary faults within the footprint of the embankment itself. GNS have
investigated this weakness and have confirmed that there is no evidence of
movement along this weakness in the last 10,000 years.
2.9 Notwithstanding this, GNS consider that the possibility of secondary movement
of 0.1 m to 0.5 m here or elsewhere in the foundation remains. Defensive
measures have been applied as a precautionary measure despite there being
no evidence of movement at this feature.
2.10 Seiche effects from potential rupture of the Mohaka Fault where it crosses the
reservoir would be expected. GNS have advised that a single event vertical
displacement of 0.4 m to 1.0 m should be considered as possible. This has
Page 4
been allowed for by providing adequate freeboard that includes a factor of
safety of 2 for the GNS upper limit of 1.0 m
2.11 Freeboard requirements have been determined to cater for three separate
scenarios, an extreme flood event, an extreme earthquake event and a post-
earthquake condition with a 1 in 20 AEP flood.
2.12 A river diversion strategy is outlined to ensure a diversion capacity of at least 1
in 1000 AEP at any stage where public safety and major damage are at risk.
Hold points for reservoir filling are not considered necessary from a dam
stability point of view and rapid filling of the storage is not considered a dam
safety issue.
2.13 In response to the matters raised by the submitters, I remain of the opinion that
the Application Design for the dam is appropriate, and that all reasonable
alternatives have been considered.
3. OVERVIEW OF DESIGN RATIONALE
3.1 Overview of Dam Design
(a) The proposed total water storage requirement of 90 million m3 at the
site results in a dam of approximately 83 m height at the river’s deepest
point. A Concrete Face Rockfill Dam (“CFRD”) has been selected for
the Application Design. The crest is 505 m long and 8 m wide. The top
of the parapet wall is RL 475.5 m (minimum) and extends 1.2 m above
the top of the embankment.
(b) A concrete lined primary spillway on the right abutment of the dam
passes flood inflows through a concrete lined chute to a concrete lined
stilling basin. The spillway capacity is supplemented by an unlined
auxiliary spillway located on the left abutment of the dam.
(c) A concrete intake structure located within the reservoir allows for
irrigation and flushing flows to be drawn from two levels within the
reservoir through the high level intake tower into a penstock located in a
tunnel beneath the dam. The upper tower ports can take water from the
top 4 m of storage while the lower ports would access the top 22 m of the
storage or the upper 68% of the storage volume. In addition, the lower
portion of the storage can be discharged through the outlet works by
Page 5
opening a gate in the low level outlet structure. The outlet works and
hydro power station are located at the downstream end of the tunnel and
discharge into a tailrace canal that joins the spillway outlet channel.
(d) The general design criteria for the works are based on the New Zealand
Society of Large Dams (NZSOLD) Dam Safety Guidelines and also
consideration of the Building (Dam Safety) Regulations (2008). These
provide guidance on general dam design and construction practice
including the assessment of flood and seismic hazards and the provision
of appropriate spillway and diversion works and adequate defence
against earthquake events. They also provide guidance on the
establishment of dam safety surveillance practices to be adopted for
initial filling of the reservoir and subsequent operation, and for the
provision of emergency action plans.
(e) Where the NZSOLD Dam Safety Guidelines do not cover specific
design details, the design is based on international guidelines and
practice documents. The International Commission on Large Dams
(ICOLD) publications provide a wide range of guidelines that reflect
current international practice. Specific to the CFRD detailed in the
Application Design ICOLD Bulletin 141 (2010) is a primary reference for
dam design and construction. Other sources include appropriate
guidelines and standards from the US Federal Energy Regulatory
Commission (FERC), the US Bureau of Reclamation (USBR), the US
Army Corps of Engineers (USACE) and the Australian National
Committee on Large Dams (ANCOLD).
(f) These organisations are recognised both internationally and in New
Zealand as producing authoritative standards and guidelines that
represent current best practice.
3.2 Dam Design in General
(a) The primary consideration for the embankment was the ability to handle
high earthquake loadings and possible secondary movement on rock
mass weaknesses within the embankment footprint. The CFRD
embankment was adopted on the basis that it provided the best solution
for the site’s geotechnical issues with the materials available.
Page 6
3.3 Seismic Design Loadings
(a) The dam site is located around 750 m from the primary active Mohaka
Fault which has an average recurrence of fault movement of around
1300 years and this together with other active faults in the vicinity, pose
a credible shaking hazard to the dam site. GNS has recommended a
maximum credible earthquake (MCE) of magnitude Mw 7.5, equivalent
to 7.1 on the Richter scale. This would produce an estimated 84th
percentile peak ground acceleration at the dam site of 0.77 g.
(b) The MCE is defined as the largest earthquake that can reasonably be
expected to be generated by a specific source on the basis of the
available seismological and geological evidence. It represents the
earthquake hazard level used for design and evaluation of critical
features of high hazard projects.
(c) Modern dam design guidelines, including the New Zealand Society on
Large Dams (NZSOLD), adopt a two level design approach. A dam must
be able to withstand the effects of earthquake shaking that could
reasonably be expected to occur in the life of the dam with none or
minimal, easily repairable damage. This level is known as the
Operational Basis Earthquake (OBE) and is taken equal to earthquake
shaking with an average return period of 150 years. The dam must also
be able to withstand, without uncontrolled release of the reservoir,
earthquake shaking associated with the earthquake source capable of
generating the highest level of ground shaking at the site (in this case
the Mohaka Fault). This is known as the Maximum Design Earthquake
(MDE). This design standard is assessed applying inputs from the MCE
scenario advised by GNS. The Ruataniwha Dam will have a high
potential impact classification (PIC) and therefore the design ground
motion is required to be taken equal to the 84th percentile level of the
ground shaking associated with rupture of the Mohaka fault. This
standard is also applied to other high risk projects like nuclear power
plants.
3.4 Concrete Face Rockfill Dam
(a) The Ruataniwha Dam is a rockfill dam constructed on a hard rock
foundation. Reviews of embankment dam performance during major
Page 7
earthquakes show that there have been no complete failures of
embankment dams constructed on clay or rock foundations. Well
constructed earth dams can suffer very severe cracking but have
withstood extremely strong shaking from earthquakes of up to
magnitude 8.25 with peak ground accelerations ranging from 0.35 to
0.8 g.
(b) Dams which have suffered complete failure have been constructed with
saturated silt and/or sand materials or on saturated silt/sand
foundations, neither of which apply at Ruataniwha.
(c) The CFRD embankment was adopted on the basis that it provided the
best solution for the site’s geotechnical issues with the materials
available. J Barry Cooke (Cooke & Sherard, 1987), who was the driving
force behind the development of CFRD’s notes:
The CFRD embankment is considered to have the highest
fundamental conservatism against earthquakes
(d) This view that CFRD is inherently resistant to seismic loading is widely
supported by dam engineering specialists (Fell et al, 2005 and Materon
& Fernandez, 2011) and by organisations such as the International
Committee on Large Dams (ICOLD, 2010).
(e) The main factors supporting this view are that the CFRD embankment is
dry, preventing the development of significant water pressures within the
voids in the rockfill embankment (known as pore pressures) that would
adversely affect the embankment stability, it has a rock foundation that
does not magnify the incoming acceleration force, and the rockfill is
compacted in thin layers to a dense state with vibrating rollers.
(f) In addition, the construction has the very significant advantage that it is
stable even without the concrete face. The rockfill embankment can
handle ‘flow through’ conditions without instability issues. By that I mean
that the rate of water flow through the dam will be controlled by the
upstream zones, such that the dam will not suffer from internal erosion
as water flows through the embankment and the downstream rockfill
batter slopes will not fail. These embankments are designed to
accommodate large flood inflows that may fill the dam prior to
construction of the concrete face.
Page 8
3.5 Effect of Earthquakes on Rockfill Dams
(a) The effect of earthquakes on concrete faced rockfill dams is to deform
the embankment with flattening of the slopes due to ravelling and sliding
of shallow materials. This produces a permanent slumping and
spreading of the dam rather than a failure along a distinct surface, i.e. a
large crack or rupture. Analyses are required to ensure that this
slumping of the dam is not excessive and that sufficient embankment
height above the normal water surface level (freeboard) is provided to
retain the storage.
(b) The magnitude of an earthquake and the peak ground acceleration
produced are often combined to give the Earthquake Severity Index
(ESI). The Mw 7.5 magnitude and the 0.77 g ground acceleration for
Ruataniwha give an ESI of 20.8. This index is used to estimate the likely
crest settlement of rockfill dams as outlined in ICOLD (2010). The higher
the ESI, the greater the crest settlement.
(c) As an example of rockfill dam stability under earthquake loading, ICOLD
(2010) provides data to demonstrate that a 200 m high CFRD subjected
to a MCE of 7.8 on a fault located 26 km from the dam site is stable.
This has an ESI of 21.6 and ICOLD predict a crest settlement of around
2 m.
(d) The capability of rockfill dams to safely handle extreme earthquakes
was demonstrated by the performance of the 156 m Zipingpu CFRD in
the May 2008 Sichuan earthquake (Xu Zeping, 2008). The Zipingpu
Dam is located 17 km from the epicentre of the magnitude 8.0
earthquake and was subjected to very severe shaking with a peak
ground acceleration of 0.5 g to 0.6 g and acceleration at the dam crest
of 2.0 g. The corresponding ESI ranges between 21 and 26. The dam
crest settled about 730 mm and the maximum lateral displacement was
reported to be close to 200 mm at the crest. The estimated crest
settlement using the ICOLD method is 2.0 m, much larger than the
actual settlement of 0.73 m.
Page 9
(e) As would be expected, the dam suffered extensive spalling of concrete
at face slab joints but performance was considered adequate for an
extreme earthquake with no indication of a major failure.
(f) Ruataniwha has a similar ESI to these two examples but at 83 m is only
a fraction of the height. The estimated settlement using the ICOLD
method is 0.7 m, much less than predicted for the other two examples
and similar to that which occurred at Zipingpu.
(g) The above data indicates only moderate deformations under the MCE
are expected for the Ruataniwha Dam. A conservative freeboard is
provided to accommodate this settlement with a factor of safety of 2
applied to the assumed settlement of 0.8 m, giving a total of 1.6 m.
(h) It is noted that this movement would be expected to cause considerable
damage to the concrete face and result in substantial leakage. This
damage is not a dam safety issue and the embankment would remain
stable. The concrete face and toe slab is accessible for post-earthquake
repairs.
3.6 Detailed Analysis for Earthquake Loadings
(a) Preliminary theoretically based analyses of the expected effects of
earthquake ground motion on the dam have been undertaken by Tonkin
& Taylor. The analyses allow estimation of the permanent deformation
that may occur. Under the OBE minor deformations (<10 mm) are
estimated. These deformations would result in no damage or easily
repairable damage. Under the MDE estimates of permanent
deformations, using methodologies considered to be the most reliable,
are up to about 1 m. In making the latter comment, I am relying on
information sourced from Dr. Matuschka. These estimates are in line
with the estimates discussed above. Damage would be expected but
would not be expected to result in breach of the dam.
(b) The above data provides only a general assessment of the expected
earthquake effects on the dam. The PD notes that detailed dynamic
analysis of the dam will be required during detail design. This is an
expensive exercise that takes some time and is beyond the scope of the
feasibility studies that form the basis for the PD.
Page 10
(c) This analysis will determine whether the design provisions proposed are
adequate or whether additional provisions such as reinforcement with
geogrids are required. As such, this is an appropriate level of analysis to
leave to detailed design.
3.7 Potential for Secondary Movement
(a) Given the close proximity of the Mohaka Fault to the dam site, there is a
possibility of secondary or sympathetic movement on pre-existing
shears or secondary faults within the footprint of the embankment itself.
The geotechnical investigations located a zone of rock mass weakness,
referred to as SZ1, on the left abutment of the dam running roughly
parallel to the river and described in Paragraph 4.2 of the PD. GNS have
investigated this weakness and have confirmed that there is no
evidence of movement along this weakness in the last 10,000 years.
(b) Notwithstanding this, GNS consider that the possibility of secondary
movement of 0.1 m to 0.5 m here or elsewhere in the foundation
remains. While construction across such a feature is an unusual
procedure with limited international precedent, there is general
agreement on the types of defensive measures that should be provided
to handle such a movement.
(c) These defensive measures have been provided at SZ1 as a
precautionary measure despite there being no evidence of movement at
this feature. The dam alignment has been carefully selected to ensure
the SZ1 zone passes through the dam abutment at terrace level rather
than on the steep face of the gorge. This allows a more economical
detail for toe slab construction across the SZ1 zone. Upstream of the toe
slab the zone is exposed on the left wall of the gorge and will be
covered by a zone of fine silty material (Zone 1A) held in place by
random fill (Zone 1B). This material will feed into any cracks that
develop in the zone during earthquake activity and provide a seal.
Downstream of the toe slab the zone will be covered by filter compatible
material that will allow any leakage through the lineament to emerge in
the rockfill in a controlled manner without piping (i.e. internal erosion) of
foundation material.
Page 11
(d) Other measures nominated in the Technical Feasibility Study Report1 for
this area to address potential secondary movement include a
substantially longer toe slab, additional grouting, wider filter zones, half
width face slabs that will better adapt to movement, additional toe and
face slab seals and instrumentation to monitor any movement. I note
these measures are in addition to those described in the PD (Section
4.4.3) and applied relative to seismic loadings generally, i.e. flatter dam
slopes, greater crest width, and freeboard measures addressed below in
my evidence .
(e) There is some possibility that a weakness will exist somewhere else in
the foundation that has not been identified by geotechnical
investigations. Full geological mapping of the exposed foundation during
construction is normal practice. Any similar weakness to SZ1 found
during the construction phase would be investigated and similar
defensive measures provided, as is achievable during the construction
phase within the parameters of the Application Design.
3.8 Other Earthquake Related Issues
(a) In addition to shaking at the dam site, major earthquakes at this site
have a number of other impacts that need to be considered.
(b) Seiche effects from potential rupture of the Mohaka Fault where it
crosses the reservoir would be expected. GNS have advised that a
single event vertical displacement of 0.4 m to 1.0 m should be
considered as possible. This has been allowed for by providing
adequate freeboard that includes a factor of safety of 2 for the GNS
upper limit of 1.0 m.
( c ) Investigations have located a 90 m high landslide on the right bank of
the reservoir approximately 0.5 km upstream of the dam that could
remobilise during reservoir filling or be triggered by a major earthquake.
(d) Based on the information currently available, this is expected to involve
a volume in the order of 360,000 m3. The key concern is the impact that
a further landslide failure would have on the storage water, particularly
associated with the probability of the landslide failure occurring at the
1 Tonkin & Taylor, (August 2012)
Page 12
same time as a nearby rupture of the Mohaka fault. This could cause a
seiche capable of overtopping the dam.
(e) The Application Design assumes the landslide would be stabilised to
eliminate this problem. If it is left in situ, additional freeboard would need
to be considered.
(f) An area of dilated, potentially unstable rock has been identified on the
left bank wall of the gorge extending from the downstream toe of the
embankment a further 200 to 250 m downstream. Part of this area has
failed sometime in the past, most likely as a result of earthquake
shaking. There is an expectation, based on visual inspection that the
remaining area of dilated rock mass could mobilise during the maximum
design earthquake.
(g) While failure of the rock mass does not directly affect the dam, it may
contain sufficient material to partially block the gorge. If operational and
spillway flows were released upstream of the fallen rock mass, water
would build up behind the blockage, submerging the outlet works and
substantially reducing outlet capacity at a time that emergency storage
drawdown is required. It would also submerge the embankment rockfill
roughly up to half the height of the embankment at a time when after-
shocks would be expected.
(h) The Application Design ensures that the spillway and outlet works return
flow to the Makaroro River downstream of this potential rockfall area.
This will allow normal operation of the spillway and outlet works during
such an event.
3.9 Freeboard Requirements for Flood and Earthquake
(a) Freeboard requirements have been determined to cater for three
separate scenarios, an extreme flood event, an extreme earthquake
event and a post-earthquake condition with a 1 in 20 AEP flood.
(b) The extreme flood event assumes a flood inflow equal to the Probable
Maximum Flood (PMF) occurring on a full storage. The PMF is the
Page 13
largest flood that may reasonably be expected to occur from the most
severe combination of critical meteorological and hydrologic conditions
that are reasonably possible. By definition, the PMF does not have a
probability associated with it. However, a conservative approximation
can be obtained by extrapolating flood frequency distributions as a linear
relationship and if climate change is assumed this gives a nominal AEP
of 4x10-6 (1 in 250,000 years). The corresponding AEP without climate
change is 6.8x10-7 (1 in 1,500,000 years).
(c) The PMF with a peak inflow of 795 m3/sec produces outflow discharges
of 585 m3/sec in the primary spillway and 167 m3/sec in the secondary
spillway. The storage level rises 4.9 m from the full supply level (FSL) of
RL 469.5. An additional 1.0 m freeboard is provided for potential wave
action, giving a total requirement of 5.9 m above FSL.
(d) The extreme earthquake event has the potential to produce settlement
in the rockfill dam, a seiche generated by vertical or horizontal
displacement across the Mohaka Fault and a vertical displacement
within the embankment due to secondary movement on SZ1 zone or
other zone of weakness in the left abutment. The seismic parameters
used for the MDE have an AEP of approximately 2x10-4 (1 in 5,000).
Note that this is the probability of the event the dam is designed for, not
the probability of failure.
(e) As noted above, settlement of the rockfill dam has been estimated at 0.8
m and a factor of safety of 2 has been applied to this estimate. The
upper bound displacements produced by GNS of 1.0 m for the Mohaka
Fault vertical displacement and 0.5 m for secondary movement have
been adopted with a factor of safety of 2 for calculation of the freeboard
requirement , giving a total freeboard requirement of 4.6 m.
(f) The post-earthquake scenario requires provision for settlement of the
rockfill embankment (0.8 m as above with the safety factor of 2) and
displacement due to secondary movement (0.5 m as above with the
safety factor of 2). It also provides for a 2.5 m flood rise due to the 1 in
20 AEP inflow giving a total freeboard requirement of 5.1 m.
(g) The extreme flood event proved to be the critical scenario with a greater
freeboard of 5.9 m. This has been rounded off to 6.0 m and the parapet
Page 14
crest on the embankment is set at RL 475.5 m, 6.0 m above the FSL of
RL 469.5 m.
3.10 Other New Zealand Dams
(a) Four NZ dams have been referred to in relation to RWSS (including by
submitters), Opuha, Matahina, Marlborough (Haldon Ranges Dam), and
Clyde. Brief descriptions of the issues involved and comparisons with
the RWSS are provided below together with comment on other relevant
NZ dams.
Opuha Dam
(b) Opuha Dam is a zoned earthfill dam located at the entry to the Opuha
George, about 12 km upstream from the township of Fairlie (Pickens &
Grimston, 2001 and Lees & Thompson, 2003). The dam was partly
constructed to a height of 29 m in February 1997 when it was filled by
flood flows. River diversion flows were provided by a 1.8 m diameter
pipe through the embankment and it is understood this was designed for
a flood with an AEP of 1 in 10.
(c) As the dam was being overtopped, the contractor cut a channel in one
side of the dam to prevent overtopping but this channel eroded rapidly
and the dam failed with one-third to half of the embankment fill being
lost.
(d) The flood was estimated to have an AEP of 1 in 12 to 1 in 14. There
were no injuries or fatalities but the breach caused substantial stock
losses and damage to farms adjacent the river. River protection works
were extensively damaged and about 200 residents were evacuated.
(e) The dam was reconstructed with much greater diversion capacity. A
series of open channels cut through the left abutment provided the
ability to cope with an AEP of 1 in 100 at lower embankment levels to 1
in 300 at higher embankment levels.
(f) The Ruataniwha river diversion proposal is described at Paragraph 3.13.
The dam is provided with a 4.0 m diameter diversion tunnel and the
embankment rockfill is protected with steel reinforcement to pass
extreme flood inflows over the embankment. The river diversion capacity
Page 15
equivalent to a flood with an AEP of 1 in 1,000 compares with an AEP of
1 in 10 for the Opuha Dam prior to failure.
Matahina Dam
(g) The original 82 m high Matahina Dam is a zoned rockfill dam with a
sloping earth core flanked by transition zones. The core and inner
transition zones are founded on rock while the outer transitions and
rockfill zones are founded on a 20 m thick deposit of dense, coarse
alluvium. The core material is a sandy, clayey silt that is stiff and
susceptible to cracking and readily erodible. The inner and outer
transitions zones and the core material were not filter compatible and
the dam did not meet modern design standards. Any crack in the core
material could allow seepage to erode the core and inner transition
material through the rockfill and potentially fail the dam.
(h) Investigations had shown that this process had occurred to some extent
on two previous occasions, one of which was associated with the 1987
Edgecumbe earthquake. The basic problem with Matahina was a lack of
filter compatibility between adjacent zones and the dam was at risk
under normal operating conditions. Being subjected to strong
earthquake ground motion increased this risk.
(i) The maximum credible earthquake for Matahina is a magnitude Mw 7.2
event with peak horizontal and vertical ground accelerations of 1.25g
and 1.3 g respectively. There are several fault traces through the dam
site and the possible fault displacement is 3 m.
(j) The dam underwent a major upgrade in 1998 that provided a leak
resistant downstream buttress that would prevent any internal erosion of
the core and inner transition zones from leading to uncontrolled erosion
and failure of the dam. In addition, the dam freeboard was increased by
3 m to 6 m.
(k) The Ruataniwha proposal requires the various rockfill zones to be filter
compatible in accordance with modern engineering practice to prevent
occurrence of the internal erosion problem that occurred at Matahina.
The impervious element of the CFRD is an upstream concrete face
rather than the erodible clay core used at Matahina. The CFRD can
Page 16
withstand large leakage through the dam without any concerns as to the
long term stability. Like the upgraded Matahina Dam, the Ruataniwha
proposal has generous freeboard to accommodate possible effects of an
earthquake on the Mohaka Fault.
(l) The other critical difference between the two dams is that Matahina Dam
is constructed across an active fault with potential fault displacement
estimated to be 3 m. Ruataniwha is not constructed across an active
fault although there is a possibility that secondary movement may occur
on a weak zone passing through the embankment. The only such weak
zone located to date is stable with no movement in the last 10,000
years. If secondary movement does occur, the maximum displacement
is estimated by GNS to be up to 0.5 m and similar defensive
mechanisms to those adopted at the SZ1 feature mentioned above
would be required to cater for this level of movement.
Haldon Ranges Dam
(m) The Haldon Ranges Dam is a water storage dam (capacity of about
250,000m3) located near Seddon in Marlborough. The embankment is
approximately 17 m high and is a zoned earthfill embankment. A
magnitude ML6.5 earthquake on 21 July 2013, located in Cook Strait,
resulted in some cracking along the upstream side of the crest of the
dam. A MW6.6 earthquake on 16 August 2013, located beneath Lake
Grassmere and much closer to the dam, resulted in additional
deformation and cracking on the upstream shoulder and crest. Although
the risk of a breach was assessed as unlikely the reservoir was lowered
as a precaution and to allow inspection and assessment of repairs. The
observed behaviour is not outside the range of possibilities for an
earthfill embankment when subjected to strong earthquake ground
motion. There were a number of other dams in the area that
experienced no damage. In making these comments, I am relying on
information sourced from Dr. Matuschka.
Clyde Dam
(n) The Clyde Dam is a 102 m high concrete gravity dam on the Clutha
River. It is located approximately 3 km from the active Dunstan Fault.
There is a possibility that rupture of Dunstan Fault could result in
sympathetic movement on a river channel fault that was encountered in
Page 17
the dam foundations during construction. As a consequence the dam
design incorporates a special slip joint that can accommodate up to 2 m
of movement. This is a similar situation to Ruataniwha, except that the
Clyde Dam is a different type of dam (not CFRD) and in the Ruataniwha
case, the potential for sympathetic secondary movement has been
anticipated.
Other NZ Dams
(o) In addition to the Matahina and Clyde Dams, there are other existing
large dams in New Zealand that either overlie active faults or are very
close to active faults where secondary faulting is expected. Dr.
Matuschka provided the following examples and comment:
Aviemore Hydropower Dam (Waitaki River). The Waitangi Fault
underlies one side of the dam. Strengthening works have been
undertaken and analyses have been undertaken that provide
confidence that the dam will not fail due to rupture of the fault.
Ohakuri Hydropower Dam (Waikato River). The Maleme Fault Zone
is an active fault and is evident immediately north and south of the
dam
Aratiatia Dam (Waikato River). The Aratiatia Fault is inferred to pass
very close or under this dam.
Ruataniwha Dam (Upper Waitaki), located close to Ostler fault
(p) In the last 15-20 years more detailed studies have been undertaken to
assess the potential for fault displacement hazards for the design of new
dams as well as for safety assessments of existing dams. It is now not
uncommon to have to consider the potential for secondary faulting as a
result of movement on nearby active faults.
3.11 Spillways
(a) Two spillways are provided to pass flood flows. A concrete lined chute
spillway controlled by a 25 m wide arc-crested concrete ogee crest is
located on the right abutment. This spillway terminates in a hydraulic
jump dissipator located within the rockfill quarry for the embankment. An
outlet channel excavated into the quarry floor takes flows back to the
river. This channel is located well away from any rockfall that may result
Page 18
from earthquake induced damage to the area of dilated, potentially
unstable rock on the left bank wall of the gorge.
(b) A secondary (auxiliary) spillway consisting of a simple 50 m wide
unlined excavated channel is located on the left abutment. This spillway
has a crest level that is 3.25 m above the primary spillway and does not
operate for normal flood inflows. Discharges commence for floods that
exceed the 1 in 200AEP inflow with a full storage. For a 1 in 1,000 AEP
inflow the discharge through this spillway is limited to 21 m3/sec. The
maximum discharge of 167 m3/sec occurs for the PMF inflow on a full
storage.
(c) The secondary spillway channel discharges into a steep gully and
through a large stand of trees before returning to the river. Considerable
scour would be expected in the gully during such an extreme event and
damage to the stand of trees. There has been no sub-surficial
investigation in this area but a preliminary estimate of scour has been
made and is shown in Figure 200 (Appendix C) of the PD.
(d) The auxiliary spillway does not operate until inflows exceed the 1 in 200
AEP flood event and little damage is anticipated for inflows up to the 1 in
300 AEP flood. The PD notes (page 52) that a rainstorm and
consequent flood event of this magnitude would be expected to mobilise
massive amounts of debris upstream of the dam, much of which would
be trapped by the dam. Detritus eroded from the auxiliary spillway area
would be expected to be a small proportion of that trapped by the dam.
(e) Further geotechnical investigation is required in the spillway channel
area to confirm that the spillway channel will not erode back through the
spillway crest. Further geotechnical investigation is also required in the
gully to provide better estimates of potential downstream scour in an
extreme flood event. If geotechnical investigations predict excessive
erosion, the auxiliary spillway dimensions can be reduced or the spillway
eliminated and the primary spillway enlarged to compensate.
3.12 Outlet Works
(a) The outlet works are located in the diversion tunnel and comprise:
Page 19
A low level submerged intake structure at the upstream portal of the
diversion tunnel controlled by a vertical slide gate to provide an outlet
at low storage levels.
A free standing high level wet intake tower founded at RL 440m at a
high point above the tunnel. The tower is connected to the tunnel
with a steel lined raised bore shaft. Intake ports are provided at two
levels operated by a baulk and trashrack system. Access to the
tower is by boat and a system of ladders and platforms.
A 2100 mm diameter steel pipe liner within the tunnel lining is
provided as the main outlet from the grout curtain to the downstream
portal.
A 600 mm diameter bypass pipe located within the tunnel lining
provides an independent discharge facility. This allows flow
maintenance releases during construction of the main penstock and
during subsequent maintenance of the main outlet.
A bifurcation of the main 2100 mm diameter outlet at the
downstream tunnel portal with one 1500 mm diameter penstock
leading to the main outlet and a second 1500 mm diameter penstock
leading to the hydro power plant.
(b) The main outlet has been proportioned to allow dewatering of the
reservoir within a 3 month period based on the criteria developed by the
USBR (ACER, 1990). This sizing also limits head losses to an
acceptable level for the power station operation and provides for
irrigation releases and environmental flushing releases.
3.13 River Diversion during Construction
(a) International practice for river diversion is to provide a relatively simple
and low cost diversion capacity during the early stages of construction
where work mainly consists of river bed excavation and low level
embankment construction. At this stage of the project there is no risk to
downstream interests and failure of the river diversion system is a
business risk to the contractor.
Page 20
(b) As the embankment construction continues, the dam stores increasing
volumes of water during a large flood event and failure can cause major
damages at the construction site and in the river downstream. This
requires an increasing degree of conservatism in the provision of
diversion flood handling capacity.
(c) The diversion works provide a 4.0 m diameter diversion tunnel in the
right abutment and a 10.5 m high upstream cofferdam for the initial
diversion works. The cofferdam controls the river during river bed
excavation and initial embankment construction. Once the main
embankment rises above cofferdam level (RL 408 m), the cofferdam is
no longer relevant to the diversion works and the main embankment
with a steel reinforced downstream face controls the river. This provides
a diversion capacity of at least 1 in 1000 AEP at any stage where public
safety and major damage are at risk. Simply put, the dam crest can be
safely overtopped (without failure) by the greater water depths than will
occur at 1 in 1000 AEP at any stage of construction before the crest
height is above the flood level (at RL 439 m). As construction levels rise
above RL 439 m the tunnel outlet capacity and the dam storage capacity
progressively increase and the dam is capable of handling progressively
larger inflows greater than the 1 in 1,000 AEP event.
3.14 Initial Filling of the Storage
(a) As noted at Paragraph 3.12, the outlet works is constructed in the
diversion tunnel. This requires the diversion tunnel to be closed off after
completion of the embankment and spillway for outlet construction. The
maintenance of river flows during this construction period is provided by
a 600 mm bypass pipe that is located in the tunnel lining and is not
affected by outlet construction activities. It has a limited discharge
capacity and only a marginal impact on the rate at which the storage
fills. Should the dam fill during this period, the spillway can safely pass
excess inflows.
(b) As part of the Feasibility Study, a probabilistic assessment was
completed on the length of time needed for the reservoir to fill from the
time the diversion tunnel is closed. The time is heavily dependent on the
month that filling commences. If filling commences in August to
December it would likely take between 7 and 12 months. If filling begins
Page 21
in April to July it would likely take 3 to 5 months. Commencement in
January to March would take an intermediate duration.
(c) It is common practice to construct the permanent outlet works in the
diversion tunnel once the dam and spillway construction have been
completed. International practice is to place no restraint on filling rates
and as noted in the project Description there are numerous examples of
fast filling storages. These include:
140 m high Alto Anchicaya Dam, Columbia; 1 week
202 m high Campos Novus Dam, Brazil; 1 week to 90% height
110 m high Cethana Dam, Tasmania, Australia; 10 weeks
85 m high Cogswell Dam, USA; 71 hours
148 m high El-Infiernillo Dam, Mexico; 17 weeks.
125 m high Ita Dam Brazil; 10.4 weeks.
160 m Foz Do Areia Dam, Brazil; 21 weeks
94 m high Murchison Dam, Tasmania, Australia; 2.6 weeks
122 m high Reece Dam, Tasmania, Australia; 7 weeks
(d) In a few cases where there have been problems with extensive face
slab cracking and large leakage volumes at CFRD dams, no action has
been taken to lower the reservoir. The concrete face rockfill dam can
safely handle large leakage through the rockfill and is stable even
without the concrete face in place.
(e) Hold points for reservoir filling are not considered necessary from a dam
stability point of view and rapid filling of the storage is not considered a
dam safety issue.
3.15 Construction Program and Cost Estimate
(a) The total construction time from contract award to project completion is
estimated at 54 months. This includes an 11 month period for
construction of the outlet works and powerhouse which is an unusually
long time for outlet works construction and is largely due to leaving valve
installation until after completion of the powerhouse. A minor adjustment
Page 22
to the construction schedule would make it possible to have the river
outlet operating within 6 months of tunnel closure.
(b) Construction cost estimates were developed by Tonkin & Taylor
together with Bond Construction Management and with input from the
Regional Council. The process included risk and opportunity workshops
to identify risks that may increase the construction and opportunities that
may exist to reduce the cost. Bond Construction Management
subsequently carried out a simplified risk analysis to determine the
appropriate contingency and then the Target Out Turn Cost.
(c) The cost estimate included allowances for the various defensive
measures mentioned above to provide a structure capable of handling
flood and seismic loads.
3.16 Design and Review Procedures
(a) The Application Design has been peer reviewed by independent
experts. The independent review reports are reproduced at Appendix H
of the Technical Feasibility Study Report produced by Tonkin & Taylor
(August 2012).
(b) The RWSS Conditions Schedule 1 requires that the final design for the
dam structure and related diversion tunnel, spillway and power station
structures be designed by a professionally qualified engineer
experienced in large dam design in areas subject to seismic activity.
This designer is required to certify that any variations to the Application
Design meet or exceed the dam design criteria relevant to dam safety
underpinning the Application Design.
(c) It is also required that a second professionally qualified engineer
experienced in large dam design in areas subject to seismic activity
approved by HBRC and CHBDC certifies agreement with that opinion.
(d) These requirements are in accordance with the requirements of the
NZSOLD Dam Safety Guidelines.
(e) As noted at paragraph 3.6, detailed dynamic analysis of the dam will be
required during detail design. This analysis will determine whether the
Page 23
design provisions proposed are adequate or whether additional
provisions are required. This analysis will be subject to the peer review.
4. COMMENTS ON SUBMISSIONS
4.1 I have been provided with copies of the submissions received on the RWSS.
Relevant to my area of expertise I address the following issues raised by the
submitters
(a) Submitters Jenny Baker (#216), Ngai Te Upokoiri ki Omahu Marae
(#357), NZ Federation of Freshwater Anglers (#237), Operation Patiki
(#252), Craig Preston Trust (#295), Eugenie Sage (#362), Catherine
Schillinger (#137), Daniel Stabler (#138), Phylis Tichinin (#215) and
Waipatu Marae (#395) all express concern that the dam is to be located
on or near known faults, consider that this poses an unacceptable
hazard to the community and the environment, and are not satisfied this
has (or can be) accounted for in the design.
(b) Arden Properties Ltd. (#118) considers that the project is high risk, to be
constructed on unstable bedrock, that no independent feasibility study
has been done and queries which independent person signed off on
Makaroro as a good place to build a dam.
(c) Andrew Gifford (#297) and Leo-Hylton–Slater (#205) submit that there
has been inadequate consideration, ‘apprehension’ or investigation of
seismic risks,
(d) Brian Chambers (#335) has raised the issue of potential earthquake risk
and the increased costs needed to adequately mitigate these.
(e) The Council of Outdoor Recreation Associates (#396) and Eugenie
Sage (#362), express concern that the dam is to be located adjacent
fault lines and raise the issue of the failed Opuha Dam, which they
suggest the Ruataniwha dam is ‘modelled’ on or would have similar
risks to. NZ Federation of Freshwater Anglers may be referring to this
dam as well.
(f) The Environmental Defence Society (#304) expresses concern that
information on probability of failure is not provided and submitters are
unable to comment on the risk posed by the dam.
Page 24
(g) Patrick Maloney (#314) expresses concern that the dam is to be located
in an area surrounded by earthquake fault lines and considers that third
party reviews independent of Tonkin & Taylor are required for the
seismic risk and the dam design required to handle this risk.
(h) Angus Robson (#259), expresses concern that the dam is to be built on
or adjacent to 3 known faults, considers that the GNS studies are
inadequate, and that the dam should not be built until it can be proved to
be an order stronger than the Matahina and Marlborough Dams.
4.2 My response is that the issues raised are addressed in my evidence.
(a) The general issues with safety of the dam under seismic load are dealt
with in Paragraphs 3.2 to 3.10 of my evidence. The dam is not located
on known faults but is located close to three known faults. The MDE has
been selected as the MCE in accordance with the NZSOLD Dam Safety
Guidelines. Under and after the MDE level shaking, damage to the dam
is expected but no uncontrolled release of the storage water. The
embankment displacements under the MDE obtained from initial
assessments are not large. The CFRD embankment was adopted on
the basis that it provided the best solution for the site’s geotechnical
issues with the materials available.
(b) The freeboard adopted for earthquake scenarios has been
conservatively estimated, assuming the upper bound values obtained
from initial assessments and those provided by GNS take place in the
most critical direction and then applying a factor of safety of 2.
(c) The Ruataniwha Dam has the potential to undergo a similar degree of
earthquake shaking to other New Zealand Dams such as Matahina,
Clyde and Aviemore Dams. Unlike Matahina and Aviemore dams it is
not constructed across an active fault. There is a possibility of
secondary or sympathetic movement on a pre-existing shear zone or
secondary fault as at the Clyde dam. The only such weakness located to
date has been stable for 10,000 years. Detailed foundation mapping
during construction will locate any other foundation weaknesses and
defensive measures would be provided.
(d) The issues of peer review, an independent study and an independent
person to sign off are addressed at Paragraph 3.15(c) of my evidence.
Page 25
(e) The issue with the potential for increased costs is addressed at
paragraph 3.15 of my evidence. The various defensive methods and the
provision of adequate freeboard have been included in the cost
estimates.
(f) The issue of the failed Opuha Dam is addressed at paragraph 3.10 of
my evidence. The failure was due to inadequate river diversion capacity
during construction. The Opuha Dam river diversion capacity catered for
an AEP of 1 in 10 years. The corresponding capacity for the Ruataniwha
Dam is a minimum of 1 in 1,000 years at any time where public safety
and major damage are at risk.
(g) The issue of probability of failure is addressed at paragraph 3.9 of my
evidence.
(h) The issue with Matahina and Marlborough (Haldon Ranges) Dams is
addressed in Paragraph 3.10 of my evidence. Dr. Villamor comments
about the adequacy of the GNS studies in her evidence.
Phillip Richard Carter September 2013
Page 26
5. REFERENCES
Cooke & Sherard
(1987)
Cooke, J.B., Sherard J.L., 1987, Concrete face Rockfill Dams;
Parts I & II , American Society of Civil Engineers, Journal of
Geotechnical Engineering, Vol. 113, No. 10, October 1987.
Fell et al (2005) Fell, R., MacGregor, P., Stapleton, D., Bell, G. Geotechnical
Engineering of Dams, 2005
ICOLD (2010) International Committee on Large Dams, 2010. Bulletin 141,
Concrete Face Rockfill Dams – Concepts for Design and
Construction, ICOLD 2010, Paris, France.
Lees & Thomson
(1997)
Lees, P. and Thomson, D., (2003) Emergency management,
Opuha Dam collapse, Waitangi Day 1997, NZSOLD
Symposium on Dams – Consents and Current Practice,
Proceedings of Technical Groups, Volume 30, Issue 2 (LD),
pp84-89.
Materon &
Fernandez (2011)
Materon, M., Fernandez, G., 2011. Considerations on the
Seismic Design of High Concrete face Rockfill Dams
(CFRD’s), Second International Symposium on Rockfill Dams,
Rio de Janeiro, Brazil, October 27 to 28.
Pickens &
Grimston (2001)
Pickens, G.A. and Grimston, J.D. (2001) The Opuha Dam
Project, Dams –Development, Sustainability and Performance,
Proceedings NZSOLD/ANCOLD 2001 Conference on Dams,
Auckland