beam form work takeoff sheet, quantity surveying
TRANSCRIPT
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
1/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
Description Description
FOURTH FLOOR ROOF BEAM FWK1.00 6.30 Axis A (B1), b/n axis 1&2 1.00 5.70 Axis A (B2B), b/n axis 10&11
0.60 external 0.60 external3.78m2 3.42
1.00 5.55 1.00 5.40 0.45 internal 0.45 internal
2.50m2 2.43 1.00 5.55 1.00 5.40
0.30 soffit 0.30 soffit1.67m2 1.62
1.00 6.00 Axis A (B1A), b/n axis 2&3 1.00 7.20 Axis A (B3), b/n axis 11&140.60 external 0.60 external
3.60m2 4.32 1.00 5.40 1.00 6.25
0.45 internal 0.45 internal2.43m2 2.81
1.00 5.40 1.00 6.25 0.30 soffit 0.23 soffit
1.62m2 1.44 1.00 6.30 Axis A (B1B), b/n axis 3&4 2.00 5.85 Axis B (B6), b/n axis 1 & 2
0.60 external 0.45 internal3.78m2 5.27
1.00 5.25 1.00 5.85 0.45 internal 0.30 soffit
2.36m2 1.76 1.00 5.25 2.00 5.55 Axis B (B6A), b/n axis 2 & 3
0.30 soffit 0.45 internal1.58m2 5.00
1.00 9.30 Axis A (B4), b/n axis 4 &7 1.00 5.55 0.60 external 0.30 soffit
5.58m2 1.67 1.00 9.90 2.00 5.70 Axis B (B6B), b/n axis 3 & 4
0.45 internal 0.45 internal4.46m2 5.13
1.00 9.30 1.00 5.70 0.30 soffit 0.30 soffit
2.79 1.71 1.00 6.30 Axis A (B2), b/n axis 7 & 9 2.00 9.60 Axis B (B6C), b/n axis 4 & 7
0.60 external 0.45 internal3.78 8.64
1.00 5.25 1.00 9.90 0.45 internal 0.30 soffit
2.36 2.97 1.00 5.25 2.00 5.70 Axis B (B6D), b/n axis 7 & 9
0.30 soffit 0.45 internal1.58 5.13
1.00 6.00 Axis A (B2A), b/n axis 9 & 10 1.00 5.70 0.60 external 0.30 soffit
3.60 1.71 1.00 5.40 2.00 5.40 Axis B (B6E), b/n axis 9 & 10
0.45 internal 0.45 internal2.43 4.86
1.00 5.40 1.00 5.40 0.30 soffit 0.30 soffit
1.62 1.62 113.03 m
2 Sub total
ITP/TS/ 04
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
2/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
con't
Description DescriptionFOURTH FLOOR ROOF BEAM FWK 1.00 5.03
2.00 5.70 Axis B (B6F), b/n axis 10 & 11 0.30 soffit0.45 internal 1.51
5.13 2.00 5.25 Axis D (B8E), b/n axis 9&101.00 5.70 0.45 internal
0.30 soffit 4.73 1.71 1.00 5.25
1.00 6.22 Axis B (B5), b/n axis 11 & 14 0.30 soffit0.45 internal 1.58
2.80 2.00 5.33 Axis D (B8F), b/n axis 10&111.00 6.22 external 0.45 internal
0.60 4.79 3.73 1.00 5.33
1.00 6.22 0.30 soffit0.23 soffit 1.60
1.43 2.00 2.10 Axis D (B9), b/n axis 11&121.00 2.00 Axis C (B7), b/n axis 11&12 0.45 internal
0.45 internal 1.89 0.90 1.00 2.10
1.00 2.00 external 0.20 soffit0.60 0.42
1.20 1.00 1.70 Axis E (B10), b/n axis 11&121.00 2.00 0.30 internal
0.20 soffit 0.51 0.40 1.00 1.70 external
2.00 3.85 Axis C (B7A), b/n axis 12&13 0.45 0.45 internal 0.77
3.47 1.00 1.70 1.00 3.85 0.23 soffit
0.23 soffit 0.39 0.89 2.00 3.85 Axis E (B10A), b/n axis 12&14
2.00 5.40 Axis D (B8), b/n axis 1&2 0.45 internal0.45 internal 3.47
4.86 1.00 3.85 1.00 5.40 0.23 soffit
0.30 soffit 0.89 1.62 2.00 1.10 Axis E (B10B), b/n axis 14&14
2.00 5.33 Axis D (B8A), b/n axis 2&3 0.45 external0.45 internal 0.99
4.79 1.00 1.10 1.00 5.33 0.23 soffit
0.30 soffit 0.25 1.60 2.00 5.85 Axis F (B11), b/n axis 1&2
2.00 5.03 Axis D (B8B), b/n axis 3&4 0.45 internal0.45 internal 5.27 4.52 1.00 5.85
1.00 5.03 0.30 soffit0.30 soffit 1.76
1.51 2.00 5.55 Axis F (B11A), b/n axis 2&32.00 9.00 Axis D (B8C), b/n axis 4&7 0.45 internal
0.45 internal 5.00 8.10 1.00 5.55
1.00 9.30 0.30 soffit0.30 soffit 1.67
2.79 2.00 5.70 Axis F (B11B), b/n axis 3&42.00 5.03 Axis D (B8D), b/n axis 7&9 0.45 internal
0.45 internal 5.13 4.53 97.09 m 2 Sub total
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
3/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
con't
Description DescriptionFOURTH FLOOR ROOF BEAM FWK 2.00 2.55 Axis G (B13C), b/n axis 4&5
1.00 5.70 Axis F (B11B), b/n axis 3&4 0.45 internal0.30 soffit 2.30
1.71 1.00 2.06 0.30 soffit
2.00 4.80 Axis F (B11C), b/n axis 4&6 0.62 0.45 internal 1.00 2.26 Axis G (B14), b/n axis 5&6
4.32 0.60 internal1.00 4.80 1.35
0.30 soffit 1.00 2.50 1.44 0.75 external
2.00 4.80 Axis F (B11D), b/n axis 6&7 1.88 0.45 internal 1.00 2.50
4.32 0.30 soffit1.00 4.80 0.75 0.30 soffit 1.00 5.90 Axis G (B14A), b/n axis 6&8
1.44 0.75 external2.00 5.70 Axis F (B11E), b/n axis 7&9 4.43
0.45 internal 1.00 6.50 5.13 0.60 internal
1.00 5.70 3.90 0.30 soffit 1.00 6.43
1.71 0.30 soffit2.00 5.40 Axis F (B11F), b/n axis 9&10 1.93
0.45 internal 2.00 4.00 Axis G (B15), b/n axis 8&94.86 0.45 internal
1.00 5.40 3.60 0.30 soffit 1.00 3.21
1.62 0.30 soffit2.00 5.70 Axis F (B11G), b/n axis 10&11 0.96
0.45 internal 2.00 5.40 Axis G (B15A), b/n axis 9&105.13 0.45 internal
1.00 5.70 4.86 0.30 soffit 1.00 5.25
1.71 0.30 soffit2.00 6.08 Axis F' (B12), b/n axis 11&14 1.58
0.09 internal 2.00 5.70 Axis G (B15B), b/n axis 10&111.09 0.45 internal
1.00 6.08 5.13 0.75 soffit 1.00 5.33
4.56 0.30 soffit2.00 5.55 Axis G (B13), b/n axis 1&2 1.60
0.45 internal 2.00 6.08 Axis G (B15C), b/n axis 11&14
5.00 0.45 internal1.00 5.55 5.47
0.30 soffit 1.00 5.18 1.67 0.30 soffit
2.00 5.40 Axis G (B13A), b/n axis 2&3 1.55 0.45 internal 1.00 0.93 Axis G (B15D), b/n axis 14&14'
4.86 0.60 external1.00 5.40 0.56
0.30 soffit 1.00 0.70 1.62 0.45 internal
2.00 5.40 Axis G (B13B), b/n axis 3&4 0.31 0.45 internal 2.00 0.93
4.86 0.30 soffit1.00 5.40 0.56
0.30 soffit 102.01 m 2 Sub total1.62
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
4/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
con't
Description DescriptionFOURTH FLOOR ROOF BEAM FWK 1.00 5.55 Axis J (B19A), b/n axis 3&4
2.00 2.55 Axis H (B16), b/n axis 4&5 0.30 soffit0.30 internal 1.67
1.53 1.00 6.02 Axis J (B20), b/n axis 6&81.00 2.36 0.60 external
0.23 soffit 3.61 0.54 1.00 6.10
1.00 2.50 Axis H (B16A), b/n axis 5&6 0.45 internal0.30 internal 2.75
0.75 1.00 6.34 1.00 2.50 0.23 soffit
0.45 external 1.46 1.12 2.00 4.00 Axis J (B21), b/n axis 8&9
1.00 2.50 0.45 internal0.23 soffit 3.60
0.58 1.00 3.83 2.00 0.53 Axis H (B17), b/n axis 6&7 0.23 soffit
0.30 internal 0.88 0.32 1.00 5.70 Axis J (B23), b/n axis 11&13
1.00 0.53 0.60 internal0.23 soffit 3.42
0.12 1.00 5.70 2.00 5.40 Axis H' (B22), b/n axis 9&10 0.45 external
0.45 internal 2.57 4.86 1.00 5.70
1.00 5.40 0.30 soffit0.30 soffit 1.71
1.62 2.00 0.77 Axis J (B23A), b/n axis 14&14'2.00 6.00 Axis H' (B22A), b/n axis 10&11 0.45 internal
0.45 internal 0.69 5.40 1.00 0.77
1.00 6.00 0.23 soffit0.30 soffit 0.18
1.80 1.00 2.50 Axis K (B24), b/n axis 4&51.00 5.85 Axis J (B18), b/n axis 1&2 0.45 internal
0.60 external 1.13 3.51 1.00 2.50
1.00 5.85 0.60 external0.45 internal 1.50
2.63 1.00 2.50 1.00 5.70 0.20 soffit
0.23 soffit 0.50 1.31 1.00 2.50 Axis K (B24A), b/n axis 5&6
1.00 6.30 Axis J (B19), b/n axis 2&3
0.45 internal
0.60 external 1.13 3.78 1.00 2.73
1.00 5.55 0.45 external0.45 internal 1.23
2.50 1.00 2.50 1.00 5.55 0.20 soffit
0.30 0.50 1.67 2.00 4.14 Axis K (B24B), b/n axis 6&7
1.00 5.70 Axis J (B19A), b/n axis 3&4 0.45 internal0.60 external 3.73
3.42 1.00 4.14 1.00 5.55 0.23 soffit
0.45 internal 0.95 2.50 73.17 m 2 Sub total
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
5/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
con't
Description DescriptionFOURTH FLOOR ROOF BEAM FWK
1.00 6.30 Axis L (B25), b/n axis 7&9 1.00 - Axis 1 (B27), b/n axis G&J0.60 external - external
3.78 - 1.00 5.40 1.00 4.27
0.45 internal 0.45 internal2.43 1.92
1.00 6.00 1.00 3.95 0.30 soffit 0.30 soffit
1.80 1.19 1.00 6.00 Axis L (B25A), b/n axis 9&10 1.00 - Axis 1 (B27A), b/n axis D&G
0.60 external - external3.60 -
1.00 5.40 1.00 8.46 0.45 internal 0.45 internal
2.43 3.80 1.00 6.00 1.00 8.39
0.30 soffit 0.30 soffit1.80 2.52
1.00 6.30 Axis L (B25B), b/n axis 9&10 1.00 - Axis 1 (B27B), b/n axis D&A0.60 external - external
3.78 - 1.00 5.40 1.00 8.10
0.45 internal 0.45 internal2.43 3.65
1.00 6.30 1.00 8.25 0.30 soffit 0.30 soffit
1.89 2.48 1.00 1.45 Axis L (BR), b/n axis 14&14' 4.00 4.72 Axis 2&3 (B28), b/n axis G&J
0.60 external 0.45 internal0.87 8.49
1.00 0.77 2.00 4.27 0.45 internal 0.30 soffit
0.35 2.56 1.00 0.74 4.00 8.46 Axis 2&3 (B28A), b/n axis G&D
0.30 soffit 0.45 internal0.22 15.22
1.00 5.83 Axis M (B26-B26A), b/n axis 4&6 2.00 8.09 0.45 external 0.30 soffit
2.62 4.85 1.00 5.20 4.00 8.40 Axis 2&3 (B28B), b/n axis D&A
0.30 internal 0.45 internal1.56 15.12
1.00 5.00 2.00 8.10 0.23 soffit 0.30 soffit
1.15 4.86 97.37 m
2 Sub total
Description1.00 2.73 Axis 6 (B32), b/n axis M&K
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
6/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
con't 0.60 externalDescription 1.64
FOURTH FLOOR ROOF BEAM FWK 1.00 2.56 1.00 2.96 Axis 4 (B29), b/n axis K&M 0.45 internal
0.60 external 1.15 1.78 1.00 1.76
1.00 2.43 0.23 soffit
0.45 internal 0.40
1.09 1.00 3.59 Axis 6 (B32A), b/n axis H&K
1.00 1.76 0.45 internal0.20 soffit 1.62
0.35 1.00 3.39 1.00 1.25 Axis 4 (B30), b/n axis K&G 0.45 internal
0.60 external 1.53 0.75 1.00 3.59
1.00 4.72 0.23 soffit0.45 internal 0.83 2.12 2.00 2.58 Axis 6 (B32B), b/n axis G&H
1.00 6.04 0.60 external0.45 internal 3.10
2.72 1.00 1.48 1.00 5.95 0.23 soffit
0.30 soffit 0.34 1.79 2.00 8.46 Axis 6 (B34), b/n axis D&G
2.00 8.46 Axis 4 (B30A), b/n axis G&D 0.45 internal0.45 internal 7.61
7.61 1.00 8.69 1.00 8.33 0.30 soffit
0.30 soffit 2.61 2.50 2.00 7.65 Axis 6 (B34A), b/n axis A&D
2.00 7.58 Axis 4 (B30B), b/n axis D&A 0.45 internal0.45 internal 6.89
6.82 1.00 8.25 1.00 7.88 0.30 soffit
0.30 soffit 2.48 2.36 1.00 4.61 Axis 6' (B33), b/n axis G&J
1.00 2.54 Axis 5 (B31), b/n axis G&H 0.45 external0.45 external 2.07
1.14 1.00 4.44 1.00 2.45 0.30 internal
0.30 internal 1.33 0.74 1.00 4.59
1.00 1.48 0.23 soffit0.23 soffit 1.06
0.34 2.00 2.50 Axis 7 (B35), b/n axis L&J
0.30 internal1.50
1.00 2.00 0.23 soffit
con't 0.46 Description 68.73 m 2 Sub total
FOURTH FLOOR ROOF BEAM FWK2.00 7.93 Axis 7 (B36), b/n axis G&D
0.60 internal Description9.52 2.00 11.04 Axis 10 (B39), b/n axis L&F
2.00 8.16 0.45 internal0.30 soffit 9.93
4.90 1.00 10.59 2.00 7.55 Axis 7 (B36A), b/n axis D&A 0.30 soffit
0.60 internal 3.18 9.06 2.00 4.19 Axis 10 (B39A), b/n axis F&G2.00 7.85 0.45 internal
0.30 soffit 3.77 4.71 1.00 4.04
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
7/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
1.00 4.61 Axis 8 (B37), b/n axis G & J 0.30 soffit
0.60 external 1.21 2.77 2.00 8.10 Axis 10 (B39B), b/n axis D&A
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
8/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
1.00 4.61 0.45 internal
0.45 internal 7.29 2.07 1.00 8.03
1.00 3.72 0.30 soffit0.23 soffit 2.41
0.86 1.00 6.54 Axis 11 (B40), b/n axis L&G1.00 - Axis 8' (B39), b/n axis K & M 0.45 internal
- internal 2.94 - 1.00 6.54
1.00 - external 0.45 internal- 2.94
- 1.00 6.39 1.00 - 0.30 soffit
- soffit 1.92 - 2.00 6.88 Axis 11 (B41), b/n axis E&G
1.00 6.84 Axis 9 (B38), b/n axis L&G 0.45 internal0.45 internal 6.19
3.08 1.00 7.00 1.00 6.84 0.30 soffit
0.45 internal 2.10 3.08 1.00 3.73 Axis 11 (B42), b/n axis C&E
1.00 6.39 0.60 external0.30 soffit 2.24
1.92 1.00 3.80 2.00 8.01 Axis 9 (B38A), b/n axis G&D 0.45 internal
0.45 internal 1.71 7.20 1.00 2.98
1.00 8.24 0.20 soffit0.30 soffit 0.60
2.47 2.00 5.80 Axis 11 (B42A), b/n axis A&C2.00 8.10 Axis 9 (B38B), b/n axis D&A 0.45 internal
0.45 internal 5.22 7.29 1.00 5.92
1.00 8.03 0.23 soffit0.30 soffit 1.36
2.41 1.00 3.73 Axis 12 (B43), b/n axis C&E2.00 - Axis 9 (B40C), b/n axis A&D 0.45 external
- internal 1.68 - 1.00 3.87
1.00 - 0.30 internal- soffit 1.16
- 1.00 2.83 0.20 soffit
con't 0.57 Description 119.76 m 2 Sub total
FOURTH FLOOR ROOF BEAM FWK1.00 2.60 Axis 13 (B46), b/n axis L&G
0.60 external Description1.56
1.00 4.54 1.00 - Axis 14 (B48), b/n axis J&L0.45 internal - external
2.04 - 1.00 6.08 1.00 -
0.45 internal - internal2.73 -
1.00 6.39 1.00 - 0.30 soffit - soffit
1.92 - 1.00 6.25 Axis 13 (B46A), b/n axis G&E 1.00 - Axis 14 (B48A), b/n axis G&J
0.45 internal - external2.81 -
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
9/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
1.00 6.05 1.00 -
0.45 internal - external2.72 -
1.00 7.00 1.00 - 0.23 soffit - soffit
1.61 - 1.00 3.87 Axis 13 (B43), b/n axis E&C 3.00 1.28 Axis 14' b/n axis D & G
0.30 internal 0.45 RB1.16 1.73 side
1.00 3.55 3.00 0.53 0.30 internal 0.45 soffit
1.07 0.72 1.00 3.87 1.00 1.00 BR B/N AXIS 13&14'
0.20 soffit 0.60 external0.77 0.60
1.00 7.74 Axis 14 (B47), b/n axis L&G 1.00 0.62 0.60 external 0.45 internal
4.64 0.28 1.00 6.54 1.00 0.62
0.45 internal 0.30 soffit2.94 0.19
1.00 7.14 1.00 1.20 RB AXIS M&L0.30 soffit 0.45 side
2.14 0.54 1.00 3.69 Axis 14 (B45), b/n axis C&E 1.00 0.38
0.60 external 0.45 soffit2.21 0.17
1.00 3.22 1.00 1.65 RB1 AXIS J&20.45 internal 0.45 side
1.45 0.74 1.00 3.53 1.00 0.16
0.23 soffit 0.15 soffit0.81 0.02
1.00 2.40 Axis 14 (B45A), b/n axis B&C 2.00 1.70 RB3,RB3A 13 b/n D&C0.60 external 0.45 side
1.44 1.53 1.00 2.17 1.00 1.70
0.45 internal 0.20 soffit0.98 0.34
1.00 2.17 2.00 0.77 RB2 B/N Axis J&H And Axis 13&140.23 soffit 0.45 side
0.50 0.69 1.00 4.23 Axis 14 (B45B), b/n axis A&B 1.00 0.77
0.60 external 0.23 soffit2.54 0.18
1.00 3.87 48.27 m 2 Sub total0.45 internal
1.74 1.00 3.30
0.23 soffit0.76 Description
con'tDescription
1.00 5.52 RB40.45 side
2.48
1.00 2.55
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
10/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
0.20 soffit
0.51
2.99 m 2 Sub total
113.03 97.09
102.01 73.17 97.37 68.73
119.76 48.27
2.99 722.42 m 2 TOTAL for FF Roof Beam
TOTALfor first
floor roof
beam
CONTRACTOR:______________ SUPERVISOR:______________
-
7/30/2019 Beam Form Work Takeoff Sheet, quantity surveying
11/11
Project: IT PARK BUSINESS INCUBATION CENTER BUILDING Takeoff Sheet: GF Roof Beam fwk.
Building: INCUBATION Page No. : __________________ Item No.: 1.3c
ITP/TS/ 04
CONTRACTOR:______________ SUPERVISOR:______________