be benchmark project cost allocation
TRANSCRIPT
![Page 1: BE benchmark project cost allocation](https://reader038.vdocuments.us/reader038/viewer/2022100504/5a66bcf87f8b9a7c6f8b4885/html5/thumbnails/1.jpg)
2.11 Benchmark Project Cost Allocation
Office Tower 166,756,200.00 Structure Architecture M&E Infrastructure**
Structures* 24% 40,273,180.00 63,909,512.80 73,838,137.00 69,279,400.00 1,523,925.00
Architecture* 40% 66,993,820.00
M&E 36% 59,489,200.00 TOTAL CONTRACT SUM (excluding prelim)
100% 166,756,200.00 207,027,049.80
Air-Conditioned Link Bridge 2,694,849.80 Percentage
Structure 73% 1,979,332.80 Structure Architecture M&E
Architecture 23% 611,317.00 31% 36% 33%
M&E 4% 104,200.00
100% 2,694,849.80 *External wall and Façade: Allocates RM47,649,820 as curtain wall, Architectural Element
**Infrastructural Works not included in main building works
Carpark 26,484,000.00
Structure 58% 15,377,000.00
Architecture 17% 4,460,000.00
M&E 25% 6,647,000.00
100% 26,484,000.00
Infrastructure 1,523,925.00
Road 26% 402,250.00
Drainage 25% 383,250.00
Water Recticulation 38% 579,150.00
Sewerage 10% 159,275.00
100% 1,523,925.00
Basement 11,093,000.00
Structure 57% 6,280,000.00
Architecture 16% 1,773,000.00
M&E 27% 3,039,000.00
100% 11,092,000.00
![Page 2: BE benchmark project cost allocation](https://reader038.vdocuments.us/reader038/viewer/2022100504/5a66bcf87f8b9a7c6f8b4885/html5/thumbnails/2.jpg)
Item
Sum of Building
Works (RM)
Percentage of Building
Works (%)
Sum of Total Contract
(RM)
Percentage of Total
Contract (%)
Preliminaries 14,125,352.49 5%
Structural 63,909,512.80 31% 63,909,512.80 21%
Architectural 73,838,137.00 36% 73,838,137.00 25%
M&E 69,279,400.00 33% 69,279,400.00 23%
Other Costs 75,480,000.00 25%
282,507,049.80
add prelim @ 5% 14,125,352.49
207,027,049.80 296,632,402.29 100%
Preliminaries5%
Structural22%
Architectural25%
M&E23%
Other Costs25%
Cost Allocation Based on Benchmark Project
Preliminaries Structural Architectural M&E Other Costs
![Page 3: BE benchmark project cost allocation](https://reader038.vdocuments.us/reader038/viewer/2022100504/5a66bcf87f8b9a7c6f8b4885/html5/thumbnails/3.jpg)
Item
Percentage of Total
Contract (%)
Sum of Total
Contract (RM)
Preliminaries 5% 22,057,000.00
Structural 21% 93,395,074.58
Architectural 25% 110,945,660.86
M&E 23% 102,772,015.11
Other Costs 25% 111,970,249.46
Total Contract Sum 441,140,000.00