Bay of Plenty West Joint NZTA/WBoPDC One Network
Maintenance Contract
Contract No: NZTA 2/14-002/601
Appendices (WBoPDC Local Roads)
1 Contents
Page 1 of 157
1 Contract Works 3 1.1 Definitions 3 1.2 Acronyms 4
2 Value Management Proposition 5 2.1 Guide to the KRA Performance Framework 5
2.2 OPM Monthly Evaluation Example 20
3 Contract Management 23 3.1 Sections of the Network under the Current or Future Control of Separate Contractors 23
3.2 Standard Specifications 24 3.3 Other Publications 28 3.4 Stockpile Sites 31 3.5 Stockpile Management Plan 32
3.6 Resource Consents 33
4 Management Performance Measures 36 4.1 Meetings and Reporting 36 4.2 Quality Control – Management Plans 40
4.3 MMP Minimum Scope Content 48 4.4 Asset Management 51 4.5 Treatment Design 54
4.6 Planning 61
4.7 Network Control 62 4.8 Customer Satisfaction Index (CSI) 68
5 Key Performance Measures 69 5.1 High Speed Data Collection 69
5.2 Traffic Speed Deflection Data Collection 70 5.3 RAMM Condition Rating Data Collection 71 5.4 Traffic Counting Data Collection 75 5.5 Network Video 80 5.6 Roughness 84
5.7 Texture 94 5.8 Rutting 95
5.9 Surfacing Defects Index (Sealed) 96 5.10 Surfacing Defects Index (Unsealed) 99 5.11 Average Remaining Surfacing Life 103 5.12 Bridge Structures 106 5.13 Drainage Structures: Culverts 110
5.14 Drainage Structures: Surface Water Channels (Lined) 112 5.15 Drainage Structures: Surface Water Channels (Unlined) 116 5.16 Other Structures 119 5.17 Carriageway Lighting 122 5.18 Rural Bus Shelters 124 5.19 Footpaths 127 5.20 Safety Performance Index 128
Appendices (WBoPDC Local Roads)
1 Contents
Page 2 of 157
5.21 Accidents 129 5.22 Visibility 131
6 Operational Performance Measures 132 6.1 Vulnerable Flooding Areas 132 6.2 Type of Vegetation Control 133
6.3 Extent of Control 135 6.4 Maintenance of Gardens, Planted Areas and Street Trees 138 6.5 Urban Vegetation Control 139 6.6 Urban Trees 142
6.7 Spray Free Frontage 145 6.8 Litter Removal (Rural) 154 6.9 Litter Control (Urban) 155 6.10 Urban Street Cleaning 156
Appendices (WBoPDC Local Roads)
1 Contract Works
Page 3 of 157
1 1
Contract W orks
1.1 Definitions
In addition to First Schedule, Part B. Clause 1.2, Definitions and Appendix (State
Highways) 1.1, the table below provides clarification on definitions used within the
Contract Documents – CAPITALS are defined further as a separate entry.
Table 1.1: WBoPDC Local Roads Definitions
Term Definition
Carriageway Section
As defined in the RAMM database
Contract Standard In respect of MANAGEMENT PERFORMANCE MEASURES, are the minimum requirements and standards the Contractor is required to comply with at all times. In addition to the Contract Standards defined in this Maintenance Specification (WBoPDC Local Roads), the requirements and PERFORMANCE CRITERIA of the Contractor’s own management plans are also Contract Standards.
In respect of KEY PERFORMANCE MEASURES, means the minimum standard that the Contractor must demonstrate compliance with at specific times throughout the Contract.
Delivery Time In respect of MANAGEMENT PERFORMANCE MEASURES, means the time in which the Contractor must provide deliverables required by the CONTRACT STANDARDS. In addition to the Delivery Times defined in this Maintenance Specification (WBoPDC Local Roads), the timing requirements of the Contractor’s own management plans are also Delivery Times.
Litter As defined in the Litter Act 1979 and includes organic litter (such as dog droppings, dead animals, and leaves in urban areas) and inorganic litter (such as broken glass, bottles, paper and cans).
Excludes fly dumping and items unable to be removed by a single person, and or without special plant (e.g. abandoned vehicles, dead horse). Fly dumping is defined as an item or items of litter that could not be reasonably expected to be contained within a domestic refuse bag.
Performance Criteria
The MANAGEMENT PERFORMANCE MEASURES, KEY PERFORMANCE MEASURES and OPERATIONAL PERFORMANCE MEASURES relating to the WBoPDC Local Roads Network
Rehabilitation Any full width pavement treatment including area wide treatment. Note that this definition differs from that in Section 2 of the NZTA Planning, Programme and Funding Manual
Response Time In respect of OPERATIONAL PERFORMANCE MEASURES, means the time in which the Contractor must rectify any particular instance of a DEFECT. Response Time commences from the time at which the DEFECT is first identified by any party.
Appendices (WBoPDC Local Roads)
1 Contract Works
Page 4 of 157
1 1.2 Acronyms
In addition to Appendix (State Highways) 1.2, the table below provides to certain
acronyms used within the Contract Documents.
Table 1.2: WBoPDC Local Road Acronyms
Acronym Meaning
AC Asphaltic Concrete
ADT Average Daily Traffic
BoPRC Bay of Plenty Regional Council
CCP Customer Care Plan
CQP Contract Quality Plan
EPP Environmental Protection Plan
HSD High Speed Data
KPM Key Performance Measure
MPM Management Performance Measure
RRPM Raised Reflective Pavement Marker
SMP Safety Management and Intervention Plan
SSSD Safe Sight Stopping Distance
WBoPDC Western Bay of Plenty District Council
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 5 of 157
2 2
Value Management Proposition
2.1 Guide to the KRA Performance Framework
2.1.1 Introduction
Refer Appendix (State Highways) 2.1.1.
2.1.2 Objectives
The performance framework will support achievement of the aspirations and goals of the
contract in the following Key Result Areas:
• Safety
• Customer
• Assurance and Value
• Network Performance
2.1.3 Levels of Reporting
There are two main levels of reporting. This is designed so that each team member‟s role,
at each level will have maximum effect on the areas they are accountable for.
Table 2.1.1: Levels of Reporting
Level Key Focus Measured Against
Reporting Interval
Impact
Contract Management Team
Operational elements of the contract
OPM Monthly Financial pain (At-risk payment)
Contract Board Review KRAs KPIs aggregated into the KRAs
Annually Financial reward and contract tenure
2.1.4 Key Result Areas
The four Key Result Areas are presented in Table 2.1.2.
Table 2.1.2: Key Result Areas
KRA Weighting Reasoning
Safety 25% Safety is of paramount importance on the journey to zero harm.
Measure achievement and commitment to health and safety outcomes.
Measure performance towards improving safety outcomes for road users.
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 6 of 157
2 Table 2.1.2: Key Result Areas
KRA Weighting Reasoning
Customer 15% Respond to customers’ requests and manage their expectations.
Assurance and Value
30% Quality outcomes underpinned by accurate Network information and knowledge.
Network Performance
30% Ensure the physical indicators of service quality have been met.
TOTAL 100%
2.1.5 Key Performance Indicators
The tables presented in Appendix (WBoPDC Local Roads) 2.1.8 indicate the Key
Performance Iindicators and measures aligned to each of the four KRAs, and the
weighting of each. The weightings may change if the Principal determines that other
business priorities need a higher level of focus.
Each KPI and its associated KPI measure will be scored in one of the performance bands
indicated in Appendix (WBoPDC Local Roads) Table 2.13.
2.1.6 Scoring
Each KRA is broken down into one or more KPIs, which are specifically assigned to one
KRA only; the KPIs are used to determine a KRA score.
Each KRA is made up of one or more KPI measures that demonstrate the Contractor‟s
level of performance achievement for that specific KPI. The measures will be evaluated
against condition criteria such as Network data, asset condition measures, customer
responses or stakeholder survey results. The Contractor must develop a mechanism for
recording and reporting their achievement against each stated measure that can withstand
Principal or independent scrutiny.
Each KPI will be one of the following:
• Aggregation of a number of measures that then add up to a clear quantitative range to
categorise the performance level
• Individual KPI measure that has a clear quantitative range to categorise the
performance level
Once a KPI performance level has been derived, it is assigned a normalised score as
detailed in Table 2.1.3.
Each individual KPI can have a different weight assigned in relation to other KPIs within
a specific KRA, depending on its importance or focus.
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 7 of 157
2 A KRA score is derived from the individual KPI normalised score and then the sum of all
the KPIs for that KRA is averaged.
The assigned performance level for a KRA will be based on where the resulting KRA
score falls within the score range stated in the Measure Scoring Table 2.1.3. Once a KRA
performance level has been identified, it will then be assigned the normalised score.
Reporting to the CB should detail the KRA performance level, the KRA normalised score
and corresponding KPI normalised scores.
Once a year, an annual overall performance KRA score for the contract is to be developed.
The outcome of the overall performance KRA score will confirm what level of entitlement
and reward the Contractor has earned for the year, as stated in the Measure Scoring Table
2.1.3. Note the Contractor can earn both additional tenure and financial reward; however,
the additional tenure is limited to a maximum term as set out in the Conditions of
Contract.
Each individual KRA can have a different weight assigned in relation to other KRAs
depending on its importance or focus.
The annual overall performance KRA score is derived from the weighted sum of all the
KRA results for the year.
The annual overall performance KRA score is categorised according to the score range in
Table 2.1.3 and assigned a performance level. It is this final performance level which will
confirm the level of entitlement and reward the Contractor has earned.
There are four overriding exceptions to the scoring system outlined above:
• If the performance level is Poor for any KPI measure relating to pavement condition
in three or more consecutive years, the annual overall performance KRA score shall
be Poor
• If the performance level is Poor for three or more KPI measures in any one year, the
annual overall performance KRA score shall be Poor
• If the Contractor fails to collect the data required to report KPM or OPM compliance,
the annual overall performance KRA score shall be Poor
• If the Contractor fails to deliver a KPM Compliance Report, or demonstrates a pattern
of failure to produce monthly OPM compliance reports, the annual overall
performance KRA score shall be Poor
An example of a KRA calculation score is represented in Appendix (WBoPDC Local
Roads) 2.1.10.
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 8 of 157
2 Table 2.1.3: Measure Scoring Table
Score Range Normalised Score Performance Level Outcome
≥ 3 3.6 Outstanding Tenure adjusted in accordance with Conditions of Contract,
First Schedule Part B, Clause 10.8
KRA Reward determined in accordance with Basis of
Payment (State Highways), Preamble Item iii
2 < and < 3 2.6 Best Practice
1.45 < and ≤ 2 1 Minimum Condition of Satisfaction
≤ 1.45 0 Poor Loss of Tenure
The Principal and Contractor may provide additional information in their CB performance
report on extenuating circumstances which may have affected the Contractor‟s ability to
achieve a higher performance level. Additional information in no way allows the
performance level to be changed.
The Contractor and Engineer‟s Representative will work together to develop a
specification for each KPI that indicates:
• What is being measured, how and when it is measured, and by whom
• The performance targets for each individual measure and the measurement band it
relates to: Poor, Minimum Condition of Satisfaction, Best Practice and Outstanding
• The business rules for the provision of the KPI information
• The data sets, data specifications, data calculation and data delivery for each measure
• The supporting information the Contractor must provide and retain on record to
support the KPI score given
Table 2.1.4: Performance Levels and Descriptions
Level of Performance Description of Performance
Poor Significant performance failures and serious gaps in service delivery
Minimum condition of satisfaction An adequate standard of performance with improvement required
Best practice Results reflecting consistent performance achievement underpinned by constructive behaviours that enhance the relationship and deliver innovative solutions for both parties
Outstanding The Contractor is exceeding the Principal’s expectation of performance and has consistently delivered results at a level not previously achieved by suppliers.
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 9 of 157
2 2.1.7 Performance Evaluation and Monitoring
The results obtained from the monitoring of the KPIs and KRAs will be evaluated to:
• Measure performance and ascertain a score for each KPI for the year under
consideration, in accordance with the performance framework guidelines
• Identify the reasons for poor performance and jointly learn from them
• Create an environment where the behaviours and results associated with poor
performance are considered unacceptable by both the Contractor and the Principal
• Address the potential likelihood of future poor performance and reaffirm the
Principal‟s expectations of performance
• Determine the contract tenure and financial impact outcomes annually
Performance will be measured by each of the operational tiers as specified in the reporting
intervals in Appendix (WBoPDC Local Roads) Table 2.11. It is expected that there will be
a grace period (between three to six months dependent on contract commencement date)
from the time of contract commencement so that the Contractor can complete the
implementation of the system that scores Contractor performance. This will enable the
Principal and the Contractor to ensure there are systems and processes in place that
support the collection and verification of the data and information required for effective
evaluation of performance.
It is expected that the Principal and Contractor will work collaboratively to fully
implement the system in the allocated time frame.
Each KPI within a given KRA will be formally reported in the CB annual report. The
format of the report will be developed jointly between the Contractor and the Principal to
ensure visibility to all, and to enable the provision of clear assessment of performance
over the Contract Period.
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 10 of 157
2
2.1.8 Contract Performance Framework
KRA: Safety
Outcome:
Safety is of paramount importance on the journey to zero harm.
Measure achievement and commitment to health and safety outcomes.
Measure performance towards improving safety outcomes for road users.
KPI Class KPI Measure Weighting Poor MCOS Best Practice Outstanding
Health and Safety
1. Overall Safety triangle score
A. Total recordable injury frequency rate
B. No. of non-compliances
C. Close out of non-compliances
D. No. of safety presentations
E. No. of near misses reported
100% Overall safety triangle score <0
Overall safety triangle score 0 < to < 10
Overall safety triangle score < 10 to < 20
Overall safety triangle score < 20
Road User Safety 1
1. KPM 118: Percent Accidents with Road Related Factors
100% > 110% Control Group
110% Control Group ≤ to < 90% Control
Group
90% Control Group ≤ to < 80% Control
Group
≤ 80% Control Group
Road User Safety 2
1. KPM 22: Percent with Mean Profile Depth < 0.7mm
20% > 1.5% 1.5% ≤ to < 1.0%
1.0% ≤ to < 0.5%
≤ 0.5%
2. KPM 23 to KPM 26: Percent with Mean Profile Depth < 0.7mm
80% > 2.5% 2.5% ≤ to < 2.0%
2.0% ≤ to < 1.5%
≤ 1.5%
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 11 of 157
2 KRA: Safety
Outcome:
Safety is of paramount importance on the journey to zero harm.
Measure achievement and commitment to health and safety outcomes.
Measure performance towards improving safety outcomes for road users.
KPI Class KPI Measure Weighting Poor MCOS Best Practice Outstanding
Road User Safety 3
1. KPM 110 to KPM 116: Safety Performance Index (Sealed)
100% > 2.0 2.0 ≤ to < 1.5 1.5 ≤ to < 1.0 ≤ 1.0
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 12 of 157
2
KRA: Customer
Outcome:
Respond to customers’ requests and manage their expectations.
KPI Class KPI Measure Weighting Poor MCOS Best Practice Outstanding
Customer Satisfaction
1. Customer Satisfaction Index 100% < 85% ≥ 85% to ≥ 90% > 90% to ≥ 95% > 95%
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 13 of 157
2
KRA: Assurance and Value
Outcome:
Quality outcomes underpinned by accurate Network information and knowledge.
KPI Class KPI Measure Weighting Poor MCOS Best Practice Outstanding
All Remaining KPMs
1. KPMs compliant with Contract
Standard, excluding:
A. KPMs taken into account in other KPIs/KRAs)
B. KPMs that do not have a Contract Standard
100% < 96% ≥ 96% to ≥ 98% > 98% to < 100% 100%
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 14 of 157
2
KRA: Network Performance
Outcome:
Ensure the physical indicators of service quality have been provided.
Demonstrate that promises made during tendering add value and are delivered.
KPI Class KPI Measure Weighting Poor MCOS Best Practice Outstanding
Network Condition and Integrity
1. KPM 1: Roughness – Mean NAASRA (Road Group 1 - Urban)
7% > 86 86 ≤ to < 84 84 ≤ to ≤ 80 < 80
2. KPM 2: Roughness – Mean NAASRA (Road Group 1 - Rural)
10% > 80 80 ≤ to < 78 78 ≤ to ≤ 76 < 76
3. KPM 3: Roughness – Mean NAASRA (Road Group 2 - Urban)
6% > 100 100 ≤ to < 98 98 ≤ to ≤ 94 < 94
4. KPM 4: Roughness – Mean NAASRA (Road Group 2 - Rural)
10% > 82 82 ≤ to < 80 80 ≤ to ≤ 78 < 78
5. KPM 5: Roughness – Mean NAASRA (Road Group 3 - Urban)
6% > 100 100 ≤ to < 98 98 ≤ to ≤ 94 < 94
6. KPM 6: Roughness – Mean NAASRA (Road Group 3 - Rural)
10% > 86 86 ≤ to < 84 84 ≤ to ≤ 82 < 82
7. KPM 29 to KPM 30: Surfacing Defect Index (Sealed) (Road Group 1)
10% > 0.6 0.6 ≤ to < 0.5 0.5 ≤ to ≤ 0.4 < 0.4
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 15 of 157
2 KRA: Network Performance
Outcome:
Ensure the physical indicators of service quality have been provided.
Demonstrate that promises made during tendering add value and are delivered.
KPI Class KPI Measure Weighting Poor MCOS Best Practice Outstanding
8. KPM 31 to KPM 32: Surfacing Defect Index (Sealed) (Road Group 2)
10% > 0.6 0.6 ≤ to < 0.5 0.5 ≤ to ≤ 0.4 < 0.4
9. KPM 33 to KPM 34: Surfacing Defect Index (Sealed) (Road Group 3)
10% > 0.6 0.6 ≤ to < 0.5 0.5 ≤ to ≤ 0.4 < 0.4
10. KPM 52: Surfacing Defect Index (Unsealed)
5% > 3.1 3.1 ≤ to < 2.9 2.9 ≤ to ≤2.4 < 2.4
11. KPM 53: Surfacing Defect Index (Unsealed)
5% > 2.9 2.9 ≤ to < 2.7 2.7 ≤ to ≤2.2 < 2.2
12. KPM 54: Surfacing Defect Index (Unsealed)
5% > 2.9 2.9 ≤ to < 2.7 2.7 ≤ to ≤2.2 < 2.2
13. KPM 55: Surfacing Defect Index (Unsealed)
5% > 3.0 3.0 ≤ to < 2.8 2.8 ≤ to ≤2.3 < 2.3
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 16 of 157
2 2.1.9 Safety Triangle
The safety triangle is a combination of several of the safety elements measures to give an
overall score. It has both positive and negative elements combined. The aggregated safety
triangle formula represents the safety score. Within the overall score is the opportunity to
recognise positive performance as represented in the triangle and an incentive to minimise
negative performance.
Total Recordable Injuries (TRI)
Total Recordable Injury includes Serious Harm Injury, Lost Time Injury, Medical
Treatment Injury and employees on restricted work duties. It excludes First Aid Injury.
The Contractor maintains records of all TRIs for each year. For the year measured, the
score is calculated based on the number of TRIs reported multiplied by (-20) to give the
overall TRI score for that year.
Safety non-compliances
The Contractor maintains records of all safety non-compliances for each year. For the year
measured, the score is calculated based on the number of safety non-compliances reported
multiplied by (-10) to give the overall safety non-compliance score for that year.
Close out of Safety non-compliances
The Contractor maintains records of all safety non-compliances closed out for each year
and the number of safety non-compliances still open. For the year measured, the score is
calculated based on the number of safety non-compliances closed out multiplied by (+20)
plus the number of safety non-compliances still open multiplied by (+0.5) to give the
overall safety non-compliance close-out score for that year.
TRI
Safety Non-Compliance
Close out of safety non- compliances
Safety training, safety workshops, safety
presentations
Near-Miss Reporting
-20
-10
+20 if
closed,
0.5 if
open
+1
+0.5
per
event
#
#
#
#
#
-20x#
-10x#
(20x#)
+
(0.5x#)
1x#
0.5x#
Calc Event Score
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 17 of 157
2 Safety training, workshops, presentations
The Contractor maintains records of all safety training, workshops, and presentations for
each year multiplied by the number of FTEs attended. For the year measured, the score is
calculated based on the number of safety training, workshops, and presentations multiplied
by FTE attendance multiplied by (+1) to give the overall safety training, workshops, and
presentations score for that year.
Near-miss reporting
The Contractor maintains records of all near-miss reports for each year multiplied by the
number of different FTEs who provided near misses. For the year measured the score is
calculated based on the number of near misses reported multiplied by number of different
FTEs who provided near-miss reports multiplied by (+0.5) to give the overall near-miss
report score for that year.
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 18 of 157
2 2.1.10 Example Calculation of KRA Score
There are 4 Key Result Areas (KRAs). Each KRA is evaluated annually. The annual
overall performance level determines the contract‟s outcome, for example additional
tenure and financial reward.
KPI
Each Key Performance Indicator (KPI) can have more than one measure. Each measure
has a different weighting. The KPI performance level is dependent on the relevant KPI
measures performance levels. In this example, KPI 1 has three relevant measures
(Measure 1, Measure 2 and Measure 3). The KPI measure performance level has been pre-
determined for this example.
Weighting Performance Level Normalised Score
(see Table 2.1.3)
KPI 1 Measure 1 30% Outstanding 3.6
Measure 2 50% MCoS 1
Measure 3 20% Best Practice 2.6
Average (3.6*0.3)+(1*0.5)
+(2.6*0.2)
= 2.1
Range (see Table 2.1.3)
2 < and < 3
Performance Level Best Practice
KRA Each KRA can have more than one KPI. The KRA performance level is dependent on the
relevant KPIs‟ performance levels. In this example, KRA 1 has two relevant KPIs (KPI 1
and KPI 2). All KPIs have equal weighting (1).
Performance Level Normalised Score
(see Table 2.1.3)
KRA 1 KPI 1 Best Practice 2.6
KPI 2 MCoS 1
Average [(2.6*1)+(1*1)] / 2
= 1.8
Range (see Table 2.1.3)
1.45 < and < 2
Performance Level MCoS
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 19 of 157
2 Annual overall performance score
The annual overall performance score, derived from all the annualised KRA scores
determines the outcome for the year. Each KRA has a different weighting.
Weighting Performance Level Range
(see Table 2.1.3)
Normalised Score
KRA 1 25% MCoS 1.45 < and < 2 1
KRA 2 15% Best Practice 2 < and < 3 2.6
KRA 3 30% MCoS 1.45 < and < 2 1
KRA 4 30% Outstanding > 3 3.6
Weighted Performance
score (all KRAs)
(1*0.25) + (2.6*0.15) + (1*0.3) +
(3.6*0.3)
= 2.02
Range
(see Table 2.1.3) 2 < and < 3
Annual Overall
Performance Level
Best Practice
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 20 of 157
2 2.2 OPM Monthly Evaluation Example
Part A: Establishing the At-Risk Payment Value for the Contract Period
Monthly At-Risk Payment
Tendered lump sum for Schedule Item 1
$109.2M
Annual tendered lump sum for Schedule Item 1
$109.2M / 7 years = $15.6M
Monthly tendered lump sum for Schedule Item 1
(1/12) * $15.6M =$1.3M
Maximum monthly at-risk payment
$109.2M / 2,500
= $43,680
For further information on payment, see Basis of Payment (WBoPDC Local Roads),
Section 1.
The value of the monthly at-risk payment is vulnerable to change dependent on the level
of non-conformance.
Part B: Monthly Network Compliance Evaluation
Occurrences
The OPM non-compliances for the full Network length are summarised. All these OPMs
evaluate non-compliant response times for a calendar month.
Sealed Pavements Litter Control (Urban) Pedestrian Lighting
OPM 201 205 213 336 339 340 342 331 332 333 334
Occurrences
(OPM) 1 1 2 2 1 2 3 2 3 1 3
OPM Category Safety-related OPMs Customer-related OPMs All other OPMs
Occurrences
(OPM Category) 4 8 3
Total Responses
(OPM Category) 100 53 50
%Non-compliance 4% 15% 6%
Weighting Depending on the nature and context of each OPM, they may have different weighting
consequences for not achieving the response time. The following table lists the weightings
by each of the OPM categories as listed in Maintenance Specification (WBoPDC Local
Roads), Section 2.
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 21 of 157
2 OPM Category Weighting
Safety-related OPMs 0.25
Customer-related OPMs 0.20
All other OPMs 0.15
OPM Non-compliance identified by Service Request or Principal and not previously identified by Contractor
0.20
MPMs not delivered to acceptable standard or not delivered within specified Delivery Time
0.20
Number of non-compliance notices issued by the Engineer’s Representative during the previous month plus the number of non-compliance notices still open from previous months
1.00
Types of non-compliances and their corresponding weightings
Sealed Pavements Litter Control (Urban) Pedestrian Lighting
OPM Category Safety-related OPMs Customer-related OPMs All other OPMs
%Non-compliance 4% 15% 6%
Weighting 0.25 0.20 0.15
Total The Monthly Network Compliance score (MNCS) is calculated using the following
equation:
𝑀𝑁𝐶𝑆 = (%𝑁𝑜𝑛 − 𝐶𝑜𝑚𝑝𝑙𝑖𝑎𝑛𝑐𝑒 × 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
OPM Category %Non-Compliance Weighting MNCS
Safety-related OPMs 4% 0.25 = 4% * 0.25 1
Customer related OPMs 15% 0.20 = 15% * 0.20 3
All other OPMs 6% 0.15 = 6% * 0.15 0.9
OPM Non-compliance
identified by Principal
0% 0.20 = 0% * 0.20 0
MPMs not delivered to
specification
0% 0.20 = 0% * 0.20 0
Number of non-compliance
notices open
2 1.00 = 5 * 1.00 2
6.9
Appendices (WBoPDC Local Roads)
1 Value Management Proposition
Page 22 of 157
2 In this example the MNCS is less than 7; therefore no financial penalty is imposed
assuming an equivalent high level of performance on the State Highway network. If the
MNCS was between 7 and 25 a variable financial penalty would result assuming an
equivalent level of performance on the State Highway OPM evaluation. If MNCS was
over 25, or if the %Non-Compliance for any OPM Category was over 35%, then 100%
financial penalty would be imposed.
If the overall monthly score was 21
The following equation determines the proportion of payment that is adjusted, where x =
21, which is the MNCS:
Proportion adjustment = −0.2865x2 + 3.804x + 87.414
Proportion adjustment (%) = 100 − (−0.2865 21 2 + 3.804 21 + 87.414)
= 100 − ( −126.3 + 79.9 + 87.414)
= 59.0
Maximum monthly at-risk payment: $43,680
Proportion adjustment: 59.0%
Monthly at-risk payment post-
adjustment:
$43,680 * 59.0%
= $25,771
Payment for month post-adjustment: = $(1,300,000-25,771)
$1,274,229
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 23 of 157
3 3
Contract Management
3.1 Sections of the Network under the Current or Future Control of Separate Contractors
Table 3.1: Sections of the Network under the Current or Future Control of Separate Contractors
Type of Work Start Date Completion Date and/or Period of Defects Liability
Contact Person and Contact Numbers
Contract No. 13/1011: Western Urbanisation Road Improvement Works
Island View, Waihi Beach
Dolphin Avenue
Broadway Road
Albacore Avenue
Waiti Avenue
Katikati
Beach Road
Wills Road
10 Dec 2013 Due Date for Completion: 30 June 2015
12 months defects liability
Higgins Contractors Ltd
Rowan Meredith
027 588 2022
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 24 of 157
3 3.2 Standard Specifications
3.2.1 NZTA Standard Specifications
The following NZTA Standard Specifications apply to this contract.
Table 3.2.1: NZTA Standard Specifications
Specification Reference
Issue Specification Description
NZTA HM/09 2006 Incident Response
NZTA M/10 2012 Asphalt Concrete
NZTA P/9 1975 Construction of Asphalt Concrete Pavement
NZTA P/11 2007 Open-Graded Porous Asphalt
NZTA P/22 2006 Reflectorised Pavement Marking
Other NZTA HM Series Standard Specifications will apply only for the provision of
definitions and good practice relevant to this Contract.
3.2.2 Underslip Minimum Repair Standard Specification
The Contractor is required to repair any underslip to a minimum width of 0.3m from the
outside of the original edge of the seal or carriageway (prior to the slip) plus an additional
width determined in accordance with Table 3.2.3. The objective of the additional width is
to take into account environment factors associated with the Carriageway Section
including terrain, width, and road group and speed zone. The repair is to be completed at
grade with the existing seal.
For the derivation of the additional width the terrain type, existing width, road group and
speed zone are taken from the RAMM carriageway table current at the time of the
underslip. The number of metres underwidth are determined as the difference between the
required width, determined in accordance with the WBoPDC Development Code, and the
existing width.
The additional repair width is determined as the maximum width from Table 3.2.2 from
the four environmental factors.
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 25 of 157
3
Table 3.2.2: Underslip Repair Requirement in addition to 0.3m
Terrain Type Mountainous Hilly Level
0.5m 0.3m 0.0m
Underwidth >2m underwidth 1 to 2m underwidth < 1m underwidth
0.4m 0.2m 0.0m
Road Group 1, 2 & 3 4 & 5 6 & 7
0.5m 0.3m 0.0m
Speed Zone >80 km/hr 50 to 80 km/hr <50 km/hr
0.5m 0.3m 0.0m
The following example is provided for the avoidance of doubt. Where an underslip has
occurred at a road segment categorised as:
Mountainous terrain
0.5m underwidth
Road group 4
80km/hr speed zone
From Table 3.2.2, the additional width is determined as 0.5m required as a result of the
mountainous terrain being greater than the 0m required for the 0.5m underwidth, the 0.3m
for the road group 4 and the 0.3m for the 80km/hr speed zone. The total repair width
required from the outside edge of the original seal or carriageway (prior to the slip) is
therefore the minimum 0.3m plus the additional 0.5m (total 0.8m).
3.2.3 Unsealed Aggregate Material Specification
Introduction
Materials used in the construction and maintenance of unsealed roads in the Network shall
comply with this specification immediately prior to laying on a particular road.
The unsealed aggregate (metal) to be used on unsealed roads shall have a high clay
content as detailed in this specification.
Definitions
Subgrade: The soil foundation on which the road pavement is built.
Subbase: A layer of aggregate placed between the subgrade and the basecourse layer.
Basecourse: The main structural layer in a pavement constructed using a dense, stable,
well-graded aggregate.
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 26 of 157
3 Wearing Course: The wearing course (or top layer) shall conform to the basecourse
specification.
Subbase
Subbase aggregate shall comprise crushed quarried rock or river gravel that is well graded
with a maximum particle size not exceeding 100mm. When compacted in a mould and
after soaking for 4 days it shall have a CBR value not less than 25%.
Basecourse
Basecourse aggregate shall comprise of crushed quarried rock or river gravel that is well
graded. Two grades of aggregate may be used according to the circumstances, one with a
maximum particle size of 25mm and the other with 40mm. The particle size range shall
fall within one of the following envelopes
25mm Basecourse
Sieve Size (mm) Percent Passing
26.5 100
19.0 85 – 100
9.5 70 – 100
4.75 53 – 85
2.36 40 – 70
0.425 25 – 45
0.075 12 - 26
40mm Basecourse
Sieve Size (mm) Percent Passing
37.5 100
19.0 65 – 90
9.5 50 – 73
4.75 35 – 60
2.36 27 – 48
0.425 17 – 32
0.075 10 - 20
The aggregate shall comprise of a mixture of crushed rock particles, sand, silt and clay
manufactured from quarried rock or river gravel. Blending of materials from a variety of
sources will be acceptable.
The Crushing Resistance of Aggregate (NZS 4407:1991 Test 3.10) shall be such that not
more than 10% fines are produced when a load of 130KN is applied.
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 27 of 157
3 The fines shall be plastic and when tested in accordance with NZS 4402:1988, Tests 2.2 –
2.6, the product (Plasticity Index X percentage passing 0.425 mm sieve) shall be in the
range 300 to 400. In addition the Shrinkage Product which is the product (Linear
Shrinkage X percentage passing the 0.425mm sieve) shall be in the range 100 – 250.
The aggregate shall be supplied at a moisture content in the range of -2% to +0 % of the
optimum water content for Standard Compaction NZS 4402:1988 Test 4.1.1. The CBR of
a compacted sample of the aggregate, which has been soaked for 4 days, shall be not less
than 25%.
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 28 of 157
3 3.3 Other Publications
The following publications apply to this contract.
Table 3.3: Other Publications
Specification Reference
Specification Description
WBoPDC Accident KPM Analysis
WBoPDC Bridge Rating Standards and Definitions (Bridge Condition Form 01, Bridge Word Picture Condition 01, Bridge Risk Rating Form 01, Bridge Word Picture Risk Form 01)
WBoPDC Compensation for Land Acquired for Road
WBoPDC Culvert Rating Standards and Definitions
WBoPDC Cultural Monitoring Protocols 2014
WBoPDC Customer Satisfaction Index Questionnaire
WBoPDC Customer Satisfaction Index Calculation Methodology
WBoPDC Development Code
WBoPDC District Plan
WBoPDC Drainage Risk Rating and Assessment Guidelines
WBoPDC Financial Plan Process and Procedures Manual
WBoPDC Group 3 Roads – Available Sight Distance Review (2002)
WBoPDC Health and Safety – 112 Contractor’s Policy
WBoPDC Long Term Plan
WBoPDC Minor Structure Rating Standards and Definitions (Retaining Wall Word Picture Condition Form 01, Retaining Wall Condition Risk Form 01, Retaining Wall Word Picture Risk Form 01)
WBoPDC Policy on Compensation for Land Acquired for Road
WBoPDC Policy on Consultation for Roading Projects
WBoPDC Safety Performance Index Model
WBoPDC Safety Provisions for Road Works Policy
WBoPDC Street Lighting Rating Standards and Definitions
WBoPDC Street Trees Maintenance Policy
WBoPDC Transportation Asset Management Plan
WBoPDC Urban Tree Rating Standards and Definitions
BoPRC Air Plan 2012
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 29 of 157
3 Table 3.3: Other Publications
Specification Reference
Specification Description
BoPRC Plant Pest Management Strategy (2011 – 2016)
SP/M/016 NZTA Bridge Inspection and Maintenance Manual
SP/M/022 NZTA Bridge Manual
CoPTTM NZTA Code of Practice for Temporary Traffic Management (4th Edition November 2012)
EEM NZTA Economic Evaluation Manual
SM051 NZTA Location Referencing Management System Manual
MOTSAM NZTA Manual of Traffic Signs and Markings
NLTP NZTA National Land Transport Programme
NZTA Network Outcomes Contract Visual Intervention Guide
NZTA Planning and Investment Knowledge Base
NZTA Process Manual for Network Standards and Guidelines
NZTA RAMM Road Condition Rating Manual
SM020 NZTA State Highway Asset Management Manual
SM050 NZTA State Highway Database Operation Manual
SHGDM NZTA State Highway Geometric Design Manual
SP/M002 NZTA State Highway Safety Management System Manual
TCD Manual NZTA Traffic Control Devices Manual
AustRoads Guide to Road Design: Part 3
AustRoads Rural Road Design – Guide to the Geometric Design of Rural Roads
AustRoads Guide to Pavement Technology: Parts 2 and 5
NZ Supplement to AustRoads Pavement Design Guide
New Zealand Bitumen Contractors Association Safe Handling of Bituminous Materials
New Zealand National Roads Board Road Condition Rating Manual
Road Safety Manufacturers Association Standards for the Manufacture and Maintenance of Traffic Signs, Posts and Fittings
National Code of Practice for Utility Operators Access to Transport Corridors
International Infrastructure Management Manual 2011 Edition
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 30 of 157
3 Table 3.3: Other Publications
Specification Reference
Specification Description
KiwiRail/NZTA Road Controlling Authority Level Crossing Agreement
Urban Maintenance Areas: Waihi Beach Area (February 2014) Volume 1
Urban Maintenance Areas: Katikati Area (February 2014) Volume 2
Urban Maintenance Areas: Omokoroa Area (February 2014) Volume 3
Urban Maintenance Areas: Te Puke (February 2014) Volume 4
Urban Maintenance Areas : Maketu, Paengaroa and Pukehina (February 2014) Volume 5
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 31 of 157
3 3.4 Stockpile Sites
Table 3.4: Stockpile Sites
Location Name
Road Name Displ. (m) Side
Mountain Road 50 RHS
Wainui Road South 120 RHS
Wairoa Road 180 LHS
Young Road 280 RHS
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 32 of 157
3 3.5 Stockpile Management Plan
Table 3.5: Stockpile Management Plan
Mountain Road Wainui South Road Wairoa Road Young Road
RP 50 120 180 280
Side Right Right Left Right
Distance from road edge Stockpiled material not to encroach within 2.5m of edge line/edge of seal
Stockpiled material not to encroach within 2.5m of edge line/edge of seal
Stockpiled material not to encroach within 2.5m of edge line/edge of seal
Stockpiled material not to encroach within 2.5m of edge line/edge of seal
Material restriction Sealing chip/base course material Sealing chip/base course material Sealing chip/base course material Sealing chip/base course material
Volume 150m3 150m3 250m3 300m3
Time limit One month One month One month One month
Required Traffic Management Plans Stockpiling of material:
Operations> 2.5m from E of S
Operations < 2.5m from E of S
Operations on Live Lane:
Stockpiling of material:
Operations> 2.5m from E of S
Operations < 2.5m from E of S
Operations on Live Lane:
Stockpiling of material:
Operations> 2.5m from E of S
Operations < 2.5m from E of S
Operations on Live Lane:
Stockpiling of material:
Operations> 2.5m from E of S
Operations < 2.5m from E of S
Operations on Live Lane:
Sightline encroachment
Intersection sightlines 160m must be maintained at all times N/A 160m must be maintained at all times N/A
Vehicle Entrance
Construction Traffic Movement – stockpiling and removing material
Truck and/or trailer/loader movements should be planned so as they do not encroach within 2.5m of the road edge. Any traffic movements that encroach within 1 metre of the trafficable lane will require a shoulder closure. Traffic movements that encroach into the trafficable lane will require stop/go.
Refer to Required Traffic Management Plans
Truck and/or trailer/loader movements should be planned so as they do not encroach within 2.5m of the road edge. Any traffic movements that encroach within 1 metre of the trafficable lane will require a shoulder closure. Traffic movements that encroach into the trafficable lane will require stop/go.
Refer to Required Traffic Management Plans
Truck and/or trailer/loader movements should be planned so as they do not encroach within 2.5m of the road edge. Any traffic movements that encroach within 1 metre of the trafficable lane will require a shoulder closure. Traffic movements that encroach into the trafficable lane will require stop/go.
Refer to Required Traffic Management Plans
Truck and/or trailer/loader movements should be planned so as they do not encroach within 2.5m of the road edge. Any traffic movements that encroach within 1 metre of the trafficable lane will require a shoulder closure. Traffic movements that encroach into the trafficable lane will require stop/go.
Refer to Required Traffic Management Plans
Maintenance of stockpile areas
Stockpile in use Contractor to keep stockpile area clean and tidy with no loose material encroaching onto the sealed pavement
Contractor to keep stockpile area clean and tidy with no loose material encroaching onto the sealed pavement
Contractor to keep stockpile area clean and tidy with no loose material encroaching onto the sealed pavement
Contractor to keep stockpile area clean and tidy with no loose material encroaching onto the sealed pavement
Stockpile not in use Contractor to keep clean and tidy including vegetation control (Types 6 and 9)
Contractor to keep clean and tidy including vegetation control (Types 6 and 9)
Contractor to keep clean and tidy including vegetation control (Types 6 and 9)
Contractor to keep clean and tidy including vegetation control (Types 6 and 9)
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 33 of 157
3 3.6 Resource Consents
Table 3.6: Resource Consents
Reference Location Description/Comments
40179 Maketu Estuary Right to reclaim area of foreshore for roading Beach Road
40191 Beach Road Maketu Right to deposit rock and form seawall to reclaim for road
50902 Waipapa River Remove, replace and use a structure over the bed of a tributary of the Waipapa River
50903 Ohourere Stream Remove an existing bridge to construct a new bridge across the Ohourere Stream
50904 To disturb and erect and use a bridge over a river
60419 Waimapu Stream Alter and use bridge number 31 over the Waimapu Stream
60975 Waiorohi Stream Alter and use the existing structure over the bed of the Waiorohi Stream
61014 Omanawa River To replace and use a culvert to extend an existing culvert. To divert an unnamed tributary of the Omanawa River
61211 Pongakawa Bush Road, Pongakawa
To install a 1200mm diameter culvert in a dry watercourse beneath Pongakawa Bush Road, Pongakawa
61380 Raparapahoe Stream Erect and use gabion structures and disturb the bed of the Raparapahoe Stream
61381 Kopurereroa Stream Erect and use gabion structures and disturb the bed of the Kopurereroa Stream
20743 Minden Road Discharge Stormwater
20815 Maruia Place Discharge Stormwater
21188 Minden Road Discharge Stormwater
40160 Ongare Point Construct a Culvert
50244 Wharawhara Stream Repair/Const/Maint/Structure: Wharawhara
50391 No 1 Road Construct/Maintain 3 structures Wairi
50602 No 1 Road Reconstruct/Maintain 3 structures
50902 Waipapa Block Road Replacement of single span bridge
50903 Crawford Road Bridge Replacement of single span bridge
50904 Rangiuru Road Bridge Disturb the bed and erect and use a bridge
60414 60 Main Road, SH2 Construct footbridge over Uretara Stream
60419 Waimapu Stream Alter & use bridge 31 over Waimapu Stream
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 34 of 157
3 Table 3.6: Resource Consents
Reference Location Description/Comments
60544 Omanawa Road Dis collected stormwater from Omanawa Road
60697 Mc Millan Road Reserve Erosion protection works at McMillan Reserve
60863 Castles Road Discharge stormwater to land
60975 Bridge 27, Oropi Gorge Road
Replace bridge deck over Waiorohi Stream
61014 Belk Road Divert stream; construct/extend culverts
61027 106 No 3 Road Discharge stormwater to water
61211 Pongakawa Bush Road Install culvert in dry watercourse
61216 Corner Westwood Road & SH2
Dis stormwater to tributary of Waiau River
61258 Muir Place & Raymond Ave
Carry out embankment protection works
61260 Hall Road Dis stormwater to Kaikokopu Drainage system
61331 Manoeka Road Kirikiri Stream erosion protection works
61380 Bridge 83, No 4 Road Bridge 83-stream bank protection works
61381 Taumata Road Bridge 6-gabion remedial emergency works
61466 311 Minden Road Permanent stormwater discharge
61556 Pyes Pa Road Extend existing twin culverts for new Road
61774 Wairoa River and Oturu Creek
Place structures over water courses
62142 302 and 308 Pukehina Parade
Permanent stormwater dis from roadway
62270 50 Ocean View Road Permanent stormwater discharge
62271 2 Ocean View Road Erect structure, gabion & reno mattress
62636 Bridge 12, Tuapiro Road Earthworks to widen bridge
62638 Joyce Road Replace culvert in unnamed tributary
62962 Wharawhara Road Attach steel pipeline to existing bridge
63175 Wharwhara Road to Lockington Road
L/S earthworks to attach pipe to bridge
63292 Poripori Road & Crawford Road
Earthworks to extend culvert
63308 Wilson Road Install culvert & gabion basket
Appendices (WBoPDC Local Roads)
1 Contract Management
Page 35 of 157
3 Table 3.6: Resource Consents
Reference Location Description/Comments
63748 Emerton Road Dis stormwater to water
63795 Emeny Road Earthworks for widening Road
63940 Kaituna River, at end of Bell Road
Alter a structure in the Kaituna River
64054 Beach Road Replace bridge over Waihi Stream
64055 Kaiate Falls Reserve Works to replace decked bridge
65098 No 1 Road Discharge stormwater to water
65381 Wilson Road North Replace culvert
65757 75 Omokoroa Road Earthworks for slip remediation
65920 Whakamarama Road Earthworks for roading improvements
65946 from 3.9km to 5.8km up Work Road, Apata
Earthworks for road widening & discharge
66933 Welcome Bay Road Welcome Bay Road rehabilitation project
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 36 of 157
4 4
Management Performance Measures
4.1 Meetings and Reporting
4.1.1 Meetings
The Contractor shall prepare for and attend with the appropriate number and level of
personnel, all meetings as necessary to effectively meet the requirements and objectives of
the Contract, including but not limited to the following:
a) Meetings of the CB
b) Meetings of the WBoPDC, TCC Joint Road Safety Committee
c) Liaison meetings with other stakeholders, including service authorities and NZTA
d) Consultation meetings associated with planning functions under the Contract
e) Meetings with WBoPDC Elected Members
The Delivery Time for meetings is such that all meetings must be attended on time and for
the full duration of the meeting, and that the contractor is adequately prepared for the
meeting.
4.1.2 Handover Reports
The Contractor shall compile all relevant reports, databases, videos and other information
relating to the assets and deliver them to the Principal.
The Contractor shall make available facilities for the Principal to view video at such times
as required by the Principal.
The Delivery Times for the reports are two months from commencement of the Contract
for the incoming report and one month prior to Practical Completion for the outgoing
report.
4.1.3 Monthly Reports
Monthly Reports must include the:
a) Monthly progress claim
b) Updated programmes – including a minor capital works programme for the
Principal‟s funding consideration and review
c) Updated cashflow – this must show, on a year to date basis the actual percentage of
the annual contract value expended against each work category, as defined in the
NZTA Planning and Investment Knowledge Base, and the forecast cash flow for the
balance of the year.
d) Evidence of compliance with the Performance Criteria
The report shall either clearly separate information relating to NZTA and WBoPDC or
separate reports shall be provided for each Principal. Three copies shall be provided to
WBoPDC and one copy to the Engineer‟s Representative.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 37 of 157
4 The Delivery Time for the reports shall be 4:00pm on the 8
th Business Day of the month
following.
4.1.4 Accident Reports
In addition to the detailed accident reports required under the Contractors Safety
Management Strategy, interim Accident Reports must be received by the Engineer‟s
Representative for every fatal accident, any accident where there is a possibility or
allegation of Contractor initiated actions being associated with the accident or where there
is a possibility or allegation that the road condition was a major contributing factor, and
for any serious accident for which the Engineer‟s Representative requests a report,
including those reported by the New Zealand Police.
Accident Reports shall include the following information:
a) Date, time, location, nature and extent of crash
b) Weather conditions
c) Condition of surfacing and traffic services
d) Possible causes
e) Damage caused to the Assets
f) Suggested improvements
Electronic copies shall be emailed to WBoPDC staff and Engineer‟s Representative.
The Delivery Time shall be 24 hours following the accident, or as soon as practicable
thereafter.
4.1.5 WBoPDC District Roading Programmes
The Contractor shall provide the WBoPDC district roading programme deliverables for
the NZTA Annual Achievement Reporting.
The Delivery Times for the various reports shall be 10 July of each year of the Contract.
4.1.6 WBoPDC 30 Year Rolling Programme
The Contractor shall provide, on an annual basis, a 30 year rolling programme to meet the
requirements of the WBoPDC Financial Plan for all maintenance and capital improvement
works associated with the Contract. The programme must include sufficient information to
inform the Principal of the Contractor‟s activities and to provide the Principal with the
opportunity to add value to the Assets in conjunction with the Contractor‟s activities,
should it choose to do so.
The Delivery Time shall be 1 September of each year of the Contract.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 38 of 157
4 4.1.7 Comments on Submissions to WBoPDC Annual and Long Term Plan
The Contractor shall provide comment on public submissions (relevant to the Services)
generated during WBoPDC Annual and Long Term Plans.
The Delivery Time shall be 10 days from the receipt of a request by the Engineer‟s
Representative.
4.1.8 Asset Register Data
WBoPDC staff will be given access to view all data and have reporting capability in the
Contractor‟s RAMM database.
4.1.9 Pavement Deterioration Modelling
The Principal has implemented pavement deterioration modelling to supplement treatment
intelligence currently limited to the RAMM Treatment Selection Algorithm and data
analysis, as detailed in the NZTA State Highway Asset Management Manual. It is
expected that the outputs of these models will form a significant input into the
development of the Forward Work Programme.
In order to achieve the above outputs, the Contractor is required to:
Purchase and maintain the appropriate New Zealand dTIMS software license through
Infrastructure Decision Support (IDS)
Agree the modelling procedure with the Principal on an annual basis prior to the
commencement of the annual planning cycle
Implement the latest IDS NZ dTIMs CT template and calibrate this for local
conditions prior to the first modelling run
Recalibrate the model annually following each Forward Works Programme cycle
Reporting Requirements
Input Parameters
Comments are required on any significant changes made to the default input parameters.
Outputs
Outputs from the predictive modelling should include:
Forecasting of maintenance needs; and
Prediction of future Network condition
Reporting will be on an as required basis as requested by the Engineer‟s Representative.
Reliability Statement
A statement on the reliability and usefulness of the system shall be included.
Utilisation of Outputs
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 39 of 157
4 Interpretation and/or explanation must support all graphical outputs and should highlight:
The message illustrated with the figure (e.g. the roughness prediction suggests that the
current maintenance effort will maintain the current roughness across the Network);
Whether the graph supports actual expectations of the Network performance in the
opinion of the Contractor‟s expert asset managers.
Commercial Interest
Similar to the recording of maintenance cost in RAMM, actual unit cost rates to the
Contractor do not have to be used in the dTIMS modelling process. For this purpose the
Contractor is allowed to use typical unit rates expected of such a Network, which
realistically reflect cost differences between treatment types. The Principal is only
interested in global quantities of work and the impact of maintenance on the future
condition.
4.1.10 KPM Compliance Reports
The Contractor shall supply an annual KPM Compliance Report. The report shall
compare actual performance against relevant Contract Standards in both tabular and
graphical form using the most recent condition data gathered in the year of the report.
Ongoing performance reporting will be summarised to allow year on year comparison.
The report will also include any relevant commentary.
The Delivery Time shall be 30 June of each year of the Contract.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 40 of 157
4 4.2 Quality Control – Management Plans
4.2.1 Health and Safety Management Plan
In developing the Health and Safety Management Plan required under Maintenance
Specification (State Highways), Section 4.1, the Contractor shall take into consideration
and comply with the requirements of the WBoPDC Health and Safety Policy 112.
4.2.2 Quality Management Plan
The purpose of the Contract Quality Plan (CQP) is to integrate the Contract Document‟s
requirements and the Contractor‟s quality systems to deliver the Services.
The CQP describes those aspects of the Contractor‟s quality system that will be adopted
on the Contract, including how the Contractor will:
a) Identify the quality requirements specific to the Contract
b) Plan the work to satisfy those requirements
c) Control (manage) the work to comply with the planning
d) Inspect/test the work to ensure compliance with the quality requirements
e) Record the results as evidence of compliance using data management and presentation
and video recording
f) Ensure prompt action is taken to correct non-compliance
The CQP must:
i) Clearly describe the systems, procedures and methods that will be used to deliver and
monitor compliance of the Services
ii) Include documented procedures for at least the following:
CQP implementation and management
Programming including routine maintenance and annual programmes and the
maintenance management strategy
Reporting
Quality standards
Compliance monitoring
iii) Be certified for the site to the ISO 9001 Quality Standards and AS/NZS 4801 by an
independent third party certification body.
The Delivery Time for the initial CQP shall be as nominated in the Contractor‟s tender and
for CQP reviews and audits, as required by the plan.
The Delivery Time for certification shall be as nominated in the Contractor‟s tender.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 41 of 157
4 4.2.3 Traffic Management Plan
The Traffic Management Plan (TMP) establishes the practices for traffic management at
work sites. The TMP must be developed by the Contractor and agreed with the Engineer‟s
Representative.
The objectives of the TMP are to:
a) Clearly define and document the responsibilities and chain of command for the
development, implementation and management of traffic control measures and
systems
b) Establish the minimum requirements for temporary traffic control
c) Establish the minimum geometric, cross section and surfacing standards for
temporary works
d) Provide appropriate transitions and enable safe and efficient traffic flow into, through
and out of work sites
e) Protect the Contractor‟s personnel at all times
f) Protect the Assets and the Contractor‟s resources at all times
g) Meet the operational requirements as set out below.
The TMP must at include at least the following:
A documented process for preparation, review and approval of the TMP
A document tracking and control system to ensure that only the latest operative copy
of the TMP is in circulation
Contact details for Contractor, WBoPDC, emergency services and other stakeholders
Layout diagrams, method statements etc. for implementation of traffic control while
undertaking each aspect of the Services (including site specific layout diagrams and
method statements if the Services require traffic control measures not covered by
standard codes of practice)
Input from the police, emergency services and other stakeholders to ensure „buy in‟
from these parties
The Delivery Time for the first TMP issue will be before undertaking any works requiring
traffic management. The Delivery Time for subsequent TMP will be prior to any works
requiring a revised TMP.
Operational Requirements The Contractor is required to use the current version of CoPTTM, being 4
th Edition
November 2012.
Pilot Vehicles Pilot Vehicles must:
Be registered for normal use on the road by the Land Transport Safety Authority
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 42 of 157
4 Have at least 4 rubber tyred road wheels
Be capable of travelling at the speed of the fastest of the working vehicles
Four wheel farm bikes are not permitted as pilot vehicles.
Parking and Access
The Contractor shall manage its operations so that disruption to parking in urban areas is
minimised. Approval of the Engineer‟s Representative is required in advance for works
resulting in any loss of parking or loss of access to parking adjacent to retail shopping
areas in the months of December and January.
The Contractor shall ensure that access is available to property at all times.
4.2.4 Environmental Protection Plan
The purpose of the Environmental Protection Plan (EPP) is to foster an environmentally
responsible attitude on the part of the Contractor and its subcontractors and employees,
and to ensure compliance with relevant environmental protection laws and especially the
Resource Management Act 1991.
Because of the nature of the Services, the Contractor may from time to time be exposed to
environmentally sensitive situations which could involve contamination of air, soil, and/or
water systems. Situations will arise when there is a need to use appropriate environmental
protection measures. In these cases, the provisions of the Resource Management Act 1991
and other similar Acts or Regulations must be strictly observed. The Contractor needs to
be aware of environmental laws and regulations and to understand the requirements
therein.
In undertaking work which involves environmental risks, emphasis should be on the
fundamentals such as how to avoid offences of:
Air and water pollution (by screening, filtering, channelling and washing at approved
sites)
Unlawful hazardous waste disposal, by containment, storage and dumping by
approved methods at approved sites
Chemical spills (by appropriate maintenance of suitable equipment)
Contamination (by cleaning equipment at an approved site after each job)
The EPP must:
a) Identify all obligations with respect to environmental matters in accordance with the
BoPRC and legislative requirements
b) Detail systems, work practices and actions to manage environmental outcomes
c) Identify the hazards to which the environment may be exposed in the process of
carrying out work
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 43 of 157
4 d) Identify activities for which permission must be obtained before undertaking any
work
e) Identify the appropriate protective measures to be used
f) Identify any standard practices for environmental risk mitigation
g) Identify any emergency procedures for dealing with accidental pollution or imminent
danger.
The EPP shall as a minimum address:
i) Each specific consent requirement and condition
ii) Dust control at work sites including:
Highlighting that one of the most likely causes of dust damage is sweeping before
sealing is carried out
The particular susceptibility of kiwifruit grown within the region to dust damage
The requirement for the Contractor to locate the presence of any horticultural or
other susceptible crops within the vicinity of the work site.
iii) Sediment and stormwater control
iv) Noise control
v) Pest control
vi) Control of application of herbicides
vii) Storage of hazardous substances
viii) Refuelling of plant
The EPP must ensure reporting and recording of environmental incidents. It is a
requirement of this Contract that any such incident be advised promptly to the Engineer‟s
Representative.
The Delivery Time for the initial EPP shall be prior to commencement of Services and for
reviews, as required by the plan.
Resource consents held in respect of the Services are identified in Appendix (WBoPDC
Local Roads) 3.6
Further environmental information is available locally from:
Ministry for the Environment
Environmental Management Division of the local Regional Council (Pollution
Hotline)
National Poisons Information Centre – 0800 764 766 (24/7)
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 44 of 157
4 4.2.5 Customer Care Plan
Introduction
The following is a summary of the way we do things at WBoPBC.
WBoPDC‟s Customer Focus Approach aims to provide an environment where:
Customer needs are understood
Information is accurate and user-friendly
Advice and services are provided in a timely and professional manner
WBoPDC‟s customers and communities do not necessarily make a distinction between
service provided by a contractor or service provider, and services provided directly by
WBoPDC. Consequently customer care and service provided through a contractor or
service provider should display the same values and care that WBoPDC would provide.
How we do it
The customer is our first and most important priority at WBoPDC. We try very hard to
provide outstanding customer service every time. This is done by meeting clearly stated
customer service performance levels that encourage us to:
Be easy to contact
Listen and learn from customers
Work with customers to find solutions
Explain our decisions
Respond and update customers accurately and promptly
Give consistent and reliable service
Keep our promises
Learn from our mistakes
Continuously improve our services
Be friendly and professional
What will the Contractor need to know and do, to meet our Customer Focus
requirements?
Have knowledge of and a commitment to, our Customer Focus Charter
http://www.westernbay.govt.nz/Documents/CustomerFocusCharter.pdf. Be prepared
to participate in Customer Focus training where appropriate
Be supportive of actions required to be taken to improve processes (by WBoPDC), as
a result of customer feedback
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 45 of 157
4 As an agent of WBoPDC we expect the Contractor to provide a similar level of customer
service. It is essential that the community can rely on consistent performance from
WBoPDC and anyone acting on our behalf.
Customer Care Plan (CCP) The CCP will as a minimum address the following issues:
External Customer Care Strategy
1. Identification of external customers and their interface with WBoPDC on roading
issues
2. Use of technology to facilitate communication between the customer, Contractor and
WBoPDC on roading issues
3. Integration of WBoPDC‟s service request system in order to provide a seamless
interface with the WBoPDC, management of information and customer care
4. Identification of critical roading issues and appropriate response times
5. Customer satisfaction monitoring and reviews
6. Development of corporate standards for customer care
Internal Customer Care Strategy
1. Customer interface analysis.
2. Training needs analysis for enhancing customer care.
3. Recruitment and training issues
4. Information pamphlets on customer care issues.
5. Action plans or operational strategies to enhance customer care.
6. WBoPDC/Contractor Service Delivery
Public Interface and Hours of Business The Principal intends remaining the point of contact for local roading issues, and will pass
enquires either directly or indirectly to the Contractor. The Principal reserves the right to
contact any or all persons making contact in any particular day to check on the quality of
service and/or information provided.
The Contractor shall develop systems for capturing the appropriate information in order
that the Principal remains informed.
To this end, the Contractor premises will remain open to respond to customers during the
hours of 08:00am to 5:00pm, Monday to Friday, but will maintain a 24 hour after hours
contact to respond to emergency issues.
The Contractor will develop a system and customer care protocols that capture into the
WBoPDC Service Request and customer contact systems by way of any one of the
following;
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 46 of 157
4 Telephone
Facsimile
Personal contact
Written correspondence
The protocols will include but not be limited to:
1. Telephone protocols, including ringing times, greeting style, use of 0800 numbers
2. Voicemail protocols, including greeting style and standard information supplied,
acknowledgments and clearance times
3. Email protocols, and the use of a web page
4. Correspondence protocols, including the ability to respond within 10 working days,
the style of language, “jargon” avoidance, recording and filing
5. Counter and field contact protocols, including providing the customer with full
attention and accurate information, contact recording
Delivery Times The Delivery Times relating to the determination and/or identification of issues and
responding to the customer with information on the intended response should be based on
the following broad criteria:
The proposed Service Delivery Agreement is to be made available to the Engineer‟s
Representative for the initial meeting of the CB.
Level 1 Response (less than 30minutes)
Probability of failure very high and will result in injury or damage to a significant asset
(public or private)
Level 2 Response (less than 24 hours )
Probability of failure high, but consequence unlikely to result in injury, but might result in
damage to property
Level 3 Response (less than 3 working days)
Probability of failure low and unlikely to result in damage to property.
Level 4 Response (less than 10 working days)
Probability of failure very low, or the consequence of the failure low.
Level 5 Response (no response required)
Information only, for example a letter of thanks.
Customer Care Staff The CCP will demonstrate how the selection and training of customer care staff will
ensure that they are able to:
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 47 of 157
4 1. Understand their role in the context of the contract, including the extent of their
delegated authority to provide the information requested
2. Display technical competence on issues relating to the roading industry
3. Use a full range of listening and speaking techniques
4. Know when their explanation is not being understood and be able to rephrase their
response in a manner that enables understanding and accurate interpretation of the
issues and effective communication of the proposed actions
4.2.6 Emergency Procedures and Preparedness Plan
The scope of the Emergency Procedures and Preparedness Plan required under
Maintenance Specification (State Highways), Section 4.7 shall include WBoPDC Local
Roads.
4.2.7 Maintenance Management Plan
Maintenance Specification (State Highways) Section 4.8 applies in respect of WBoPDC
Local Roads, with the following modifications:
a) The following references do not apply:
1. State Highway Asset Management Manual (SM020)
2. Annual Plan Instructions (SM018)
3. NZTA T/10 Skid Resistance Investigation and Treatment
b) “Base level of specified renewals” is replaced with “renewal quantities nominated in
the Contractor‟s tender”
c) A detailed Maintenance Intervention Strategy is not required for WBoPDC Local
Roads. It should be more generic in nature and describe how it relates to the renewals
programme, and how observation of network condition during inspections will affect
maintenance interventions
d) Add new item 12) as follows:
12. The unsealed pavement minimum quantities stating the annual quantities of
maintenance metal that will be applied throughout the Contract Period.
The minimum scope content of the MMP in respect of WBoPDC Local Roads is specified
in Appendix (WBoPDC Local Roads) 4.3.
4.2.8 Safety Management and Intervention Plan
The purpose of the Safety Management and Intervention Plan (SMP) is to proactively:
a) Identify existing and potential safety problems on the road Network
b) Eliminate, reduce or address safety problems in an appropriate manner
c) Manage information and data relating to road safety
d) Give effect to the Safer Journeys Action Plan
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 48 of 157
4 4.3 MMP Minimum Scope Content
The Contractor shall, at a minimum, cover the following WBoPDC Local Roads
components within its MMP.
Strategic
How the Contractor will optimise maintenance activities across the different
classifications assigned across the network
Use of data in decision making and achieving advanced asset management
Linkage with the Contract Quality Plan
Resource management including number of full time equivalents for contract and
network management, operational management and workforce delivery staff
Critical success factors
Proposed measures and targets
Stakeholder engagement
Use of systems and processes
Recognise the network differences for WBoPDC Local Road components
Display knowledge of the (joint) Principals planning processes and timeframes to be
able to contribute the required inputs to them
Recognise the relationships between customer levels of service and technical asset
management levels of service
Development and Maintenance of Forward Works Programmes
Detailing the process for developing a forward view of needs over a 10-year planning
period for all assets including:
o Pavements and surfacing
o Drainage systems including pavement drainage
o High value assets (Railings and barriers, minor structures, large signs etc.)
o Other assets
Optimising against classification
Optimise interventions against levels of service for WBoPDC Local Road KPM and
OPM delivery
Failure mode analysis
Programming, risk management and prioritisation
The use of performance modelling
Periodic treatment justification process
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 49 of 157
4 Consider safety improvement intervention opportunities in association with the FWP
Pavement Strategies
Identification of preventive maintenance opportunities
The impact of pavement classification
Pavement and surfacing preservation strategies (maximising life) for sealed and
unsealed roads
WBoPDC Local Road KPM and OPM relationships and their impacts on each other
Pavement design methodologies
Treatment investigation (binder/stone analysis etc.).
Surfacing Strategies
First coat/second coat sealing strategies
Surfacing treatment selection process
Resurfacing design process
Material selection (e.g. skid resistance performance)
Urban treatment including environmental treatment cost minimisation
Strategies for high traffic demand environments
Material application, for example intended use of emulsion and PMBs
Drainage Strategies
Condition monitoring
Analysis and prioritisation
Forward works programming
Input into maximising life of pavement and surfacing assets
Input into minimising emergency works response and reinstatement activity
Maintenance Activity Requirements
Integration of maintenance activities
The impact of classification
Intervention strategies and thresholds
Monthly and annual programming procedures
Cyclic maintenance management
Inspection and defect management
Treatment selection process and repair methods
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 50 of 157
4 Programming and management of preventive maintenance work
Maintenance design process
Material selection criteria
Equipment sizing considerations (to minimise pavement effects)
Standard operating procedures for maintenance activities
Maintenance activity delivery
Defect liability management
Implementation of the MIS
Maintenance Performance Management
Utilising data trend analysis
Monitoring the effectiveness of the MMP
Monitoring maintenance effectiveness
Monitoring the effectiveness of the MIS
The use of maintenance cost activity in decision making
Baseline Plans
The Minimum Pavement Rehabilitation Plan, stating the Contractor‟s tendered annual
quantities for the Contract Period, clearing itemising pavement strengthening,
smoothing and thin AC smoothing lengths
The Minimum Resurfacing Plan, stating the Contractor‟s tendered annual quantities
for the Contract period, clearly itemising chip seal lengths from Asphaltic Concrete
lengths
The Minimum Unsealed Metal quantities (loose or truck measure) and material
specification for the Contract Period
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 51 of 157
4 4.4 Asset Management
4.4.1 Conservancy of WBoPDC Datasets
The Contractor shall maintain all WBoPDC datasets in a condition of accuracy, currency
and completeness appropriate to the uses for which the datasets are intended.
The Contractor shall provide hard and/or electronic copy of inventories and asset
information, in colour if applicable, to the Principal as reasonably requested.
RAMM database updates must be 100% accurate.
The Delivery Times are as follows:
a) For changes following the completion of capital works – 2 months
b) For changes to the database supplied by others – 2 months
c) For condition rating and validation – 1 month
d) For updating of the District Wide Street Tree Inventory, 1 October on each year of the
Contract
e) For hard copy requested by the Engineer‟s Representative, 1 week
4.4.2 RAMM Validation
By the end of year 2 of the contract, the Contractor shall carry out a detailed validation
check on 20% of the Network.
For the following years of the contract, the Contractor shall carry out a detailed validation
check on a different 20% of the Network annually such that over the first six-year period
all data will have been validated.
Upon completion, of each annual validation, the Contractor shall provide the Principal
with a report advising any problems or anomalies identified, the recommended steps to be
taken to prevent future issues and to correct data errors. Following the Principal‟s review
and acceptance of the report the Contractor shall rectify problems and data issues
identified in the validation exercise.
4.4.3 Maintenance of dTIMS Input File
The Contractor shall maintain the dTIMS input file in accordance with the Infrastructure
Decision Support setup and best practice current at the time and shall have access to
competent dTIMS modelling staff for the duration of the contract.
The Delivery Time is 1 September of each year of the Contract for delivery of the 30 year
programme based on dTIMS modelling.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 52 of 157
4 4.4.4 WBoPDC Roading Asset Valuation
The Contractor shall snapshot a complete database at 30th
June of each year of the
Contract and from it provide the Optimised Replacement Cost, the Optimised Depreciated
Replacement Cost and the Annual Depreciation using the WBoPDC Asset Valuation
dTIMs module. The valuations provided shall meet the requirements of both Audit New
Zealand and WBoPDC.
The Delivery Time is 1 August of each year of the Contract.
4.4.5 Asset/Network Management
The Contractor is required to develop credible systems to manage the Assets, with the
planning period being 30 years.
The Contractor shall be able to demonstrate to the Engineer‟s Representative when
required:
a) The proposed maintenance strategies that will achieve the contracted KPMs
b) That maintenance interventions and treatments are being forecast with a reasonable
„hit rate‟
c) That the Network condition will meet the requirements of the Contract for the term of
the Contract
d) The forecast Network condition for a 30 year period beyond the term of the Contract
The Delivery Time for such asset management information is two weeks following a
request by the Engineer‟s Representative for a report.
4.4.6 Bridge Assessment and Posting
The Contractor is required to manage the bridge stock in accordance with WBoPDC
policy and the Transportation Asset Management Plan, including assessment and posting
in accordance with NZTA Bridge Manual, Chapter 6.
All weight restrictions shall be advertised in accordance with Heavy Motor Vehicle
Regulations 1974, by 30 July each year of the Contract.
4.4.7 Information Technology Routine Change
Information technology associated with asset management is in a state of rapid expansion,
such that the information systems may be substantially different at the end of the Contract
to that which they were at the start. The Contractor shall continually maintain and improve
its systems in accordance with best practice and to be compatible with WBoPDC systems
at any time throughout the duration of the Contract. This shall include changes to the
nature and quantity of the data gathered and the software and hardware platforms
providing information from the data.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 53 of 157
4 Delivery Times for implementation of information technology changes shall be within 6
months of systems being operational within WBoPDC or within 12 months of substantial
uptake of a system by the road maintenance industry in New Zealand.
4.4.8 Setting of Speed Limits
The Contractor is required to develop and maintain a system of reviews, analysis,
processing and documentation to ensure compliance with NZTA rule on the setting of
speed limits. The scope includes but is not limited to:
a) Designation of urban traffic areas in which roads are subject to a 50kph speed limit
b) Validations of all speed limits except for 50kph limits on roads within a designated
urban traffic area or 100kph limits on roads within a rural area
c) Initial and ongoing validation of the appropriate sections of the traffic bylaw
d) The keeping of text based and diagrammatic speed limit registers
e) Taking account of the changing road environment land use patterns and community
concerns to ensure the posted speed limits remain safe and appropriate
f) Investigate and make recommendation to the WBoPDC, on an annual basis, any
additional speed limits that are deemed appropriate
g) Review speed limits in accordance with the Rule
h) Provide and maintain the appropriate signage (up to 20 new speed limit signs per
year) and all new markings
4.4.9 Updating WBoPDC Transportation Asset Management Plan
The Contractor shall update the WBoPDC Transportation Asset Management Plan
annually to reflect changes in the inventory and database, WBoPDC funding and policy
decisions, changing national strategies and the annual dTIMs modelling of the Network.
Planning is to be to a 30 year horizon to meet current legislated requirements. All asset
management plan documents are to be updated and reissued to listed document holders.
All updating must meet NZTA requirements and the annual financial audit requirements
of Section 14 of the Public Audit Act 2001 and comply with the current International
Infrastructure Management Manual.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 54 of 157
4 4.5 Treatment Design
Pavement design and geometric design standards for pavement renewals (strengthening),
seal extensions, seal widening, and any other new pavement works (e.g. intersection
improvement) shall be undertaken in accordance with the latest Austroads Guide to
Pavement Technology: Parts 2 and 5 together with the N.Z. Supplements to the Austroads
Guides, and the WBoPDC Development Code. Design life is to be 25 years.
4.5.1 Pavement Treatment
A specific design and technical specification shall be produced by the Contractor prior to;
The construction of any seal extension, seal widening, or other capital works
Any maintenance activity or treatment that changes the RAMM carriageway width at
year 0 by more than 300mm on either side of the road
Any pavement Rehabilitation in excess of 100m length
4.5.2 Geometric Standards
Prior to undertaking Rehabilitation works, the Contractor shall identify and seek an
instruction from the Engineer‟s Representative to perform the following and any other
asset improvements:
a) Camber correction above 2
b) Provision of super-elevation from a camber cross-section
c) Overlay above 200mm depth extra to the design overlay thickness to correct shape in
the longitudinal direction
d) Seal widening
e) Flattening of shoulder, berm and side slopes
Consequential works arising from any aspect of Rehabilitation that are not defined as part
of the Services are also to become part of the Services. Consequential works include, but
are not limited to:
a) Earthworks
b) Drain recutting, and consequential scour protection
c) Raising or lowering of service covers, kerbs, sight rails and guardrails
d) Culvert extensions
e) Construction or extension of retaining walls
The Contractor shall take care to ensure that shoulder, berm and side slopes within the
clear zone are not made steeper by the Rehabilitation treatment, and that the width of such
slopes that can safely be traversed by errant vehicles is not reduced.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 55 of 157
4 4.5.3 Construction Requirements
Rehabilitation shall not result in more than 1000m of traffic lane (having been sealed prior
to the Rehabilitation works) remaining unsealed for a period exceeding four weeks at any
single project site, unless specific approval has been provided by the Engineer‟s
Representative; such approval shall not be unreasonably withheld.
The Contractor shall ensure, through attention to design and construction methodology,
that:
a) Pavement works do not unravel and that detritus and loose or surplus material does
not create a traffic hazard
b) There is no flushing, bleeding, scabbing or stripping and that binder is not picked up
on any tyres. There must be no accidents associated with surfacing performance
c) In urban areas, detritus and loose or surplus material shall not be tracked into
adjoining properties and businesses.
All pavement markings and raised pavement markers shall be reinstated after completing
resurfacing or Rehabilitation work within one week, and before the removal of temporary
traffic control.
Worksites that affect property frontages must be left in the same or better condition and
berms that are mowable must be reseeded to provide a result that matches the pre-existing
condition. Rural berms must provide for safe cutting of shelter belts where reasonably
possible. Access should be reinstated on a like for like basis. The Contractor needs to
take sufficient photographs before and after construction to demonstrate compliance with
this requirement.
4.5.4 Quality Assurance and Post Construction Demonstration of Pavement Design Life Achievement
The minimum design life of any Rehabilitation (strengthening) carried out by the
Contractor shall be 25 years, unless stipulated otherwise by the Engineer‟s Representative
in writing.
For short pavement repairs having a total length less than 100m, the minimum design life
shall equal or exceed the remaining life of the adjoining pavement.
In order to provide the Principal with assurance that the required design life for both
pavement renewals and new pavements is likely to be achieved the following quality
assurance process is to be followed.
Design Report At least 2 months for capital works including seal extension, seal widening and minor
improvements, and at least 1 month prior to the programmed start date for
renewal/Rehabilitations, a detailed design, and a design report shall be provided to the
Principal which incorporates:
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 56 of 157
4 The geometric design standards previously approved by the Principal. This may or
may not comply with the current Austroads Guide to Road Design Part 3: Geometric
Design depending on site constraints, and funding provisions, and value for money
considerations
The design report is to document the investigations, predicted failure mechanism, and
is to include a quality plan setting out sampling and testing requirements, and critical
hold points
Risks are to be identified and mitigation measures presented
Communications with adjacent residents, Iwi, road users, and emergency services are
to be noted and taken into account in the design
The Contractor‟s Physical Works Manager is to be responsible for ensuring that all
the quality assurance requirements have been met
A road safety audit waiver (NZTA May 2013 Road Safety Audit Exemption Form)
completed for the Principal acceptance.
Pavement Rehabilitation/New Pavement - Construction Completion Report Within 2 months of the construction of the 1
st coat seal, the Contractor shall supply to the
Principal a Construction Completion Report for each Site which shall include, as a
minimum, the following:
Key original design assumptions
The renewal/new pavement quality plan
Evidence of construction compliance with key original design assumptions as well as
any deviation from the design
All quality assurance results
All compliance results (e.g. NZTA B/2 shape)
Photographs of the Site during treatment and on completion;
Customer engagement, issues , technical or construction challenges and any ongoing
commitments
As-built extracts from RAMM
New Pavement / Pavement Rehabilitation Post Construction Design Assessment
Post-construction design assessment will be used as the tool for verification of value
assurance.
Between 10 and 15 months after construction, the Principal will have undertaken high-
speed data surveys over road groups 1 to 3 and less frequently for other roads groups as
outlined in Appendix (WBoPDC Local Roads) Table 5.1.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 57 of 157
4 Within 2 months of receipt of this data, and in conjunction with other Contractor-sourced
inputs, the Contractor shall assess the success of the renewal/new work outcomes and
supply to the Principal a Post-Construction Design Assessment Report. The report shall
include:
Construction Completion Report
Photographs of areas of concern
Roughness condition, see below
Rutting condition, see below
Shape condition, see below.
The Principal is seeking confirmation and assurance of the original treatment selection and
design through the evaluation of the above inputs, including cross-verification of outputs
and conclusions from these multiple data sources.
Annually thereafter, by 30th
June, the latest source information on roughness, rutting and
shape condition, for each project, shall be provided by the Contractor to the Principal. The
information will ideally be presented in a spreadsheet showing all of the projects involving
pavement renewals and new pavement undertaken under the contract for the duration of
the Contract. This information shall form a critical component for ongoing design
consideration in developing future optimal design solutions.
The post-construction design assessment period will be the lesser of:
5 years from the date of the first coat seal or
Contract Period left to run at the time of the first coat seal plus any additional tenure
reward
Roughness
Roughness will be assessed annually throughout the assessment period based on the
Principal‟s annual HSD survey. Assessment for compliance with the roughness criteria
shall be in terms of the 100m moving average NAASRA. The 100m moving average shall
be calculated from the HSD roughness measurements recorded at 20m intervals in each
lane.
The extent of survey shall include an additional 40m at each end of the treatment Site.
The progression in annual roughness shall be monitored and compared with the Principal‟s
expectation that roughness on new works should not exceed 75 NAASRA in the first 5
years following date of 1st coat seal, and 65 NAASA for asphalt.
Where more than 50% of the calculated moving averages exceed these values, the
Principal may conclude that the work is unlikely to achieve its design life and cannot be
counted as contributing towards meeting of the Contractor‟s nominated quantity
obligations.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 58 of 157
4 Rutting
Rutting will be assessed annually throughout the assessment period based on the
Principal‟s annual HSD survey of road groups 1 to 3 and less frequently for other roads
groups as outlined in Appendix (WBoPDC Local Roads) Table 5.1.
Assessment for compliance with the rutting criteria shall be in terms of the 20m mean rut
depth by wheel path.
For each wheel path the characteristic rut value shall be determined as follows:
Rx = ϻx +K □x
Where: Rx = Characteristic rut value for wheel path (e.g. RLWP or RRWP) x (mm)
ϻx = Mean of the 20m wheel path means for wheel path x
K = 1.28
□x = Standard deviation of the 20m wheel path means for wheel path x
x = Either left wheel path (LWP) or the right wheel path (RWP)
Note that the above assessment is based on wheel paths by site not by lane.
The rutting progression shall be assessed annually for projects within road groups 1 to 3,
and at the interval that HSD is collected for projects within the remaining road groups.
Where after 3 years following the first coat seal, the characteristic rut value of any
pavement construction or rehabilitation project exceeds 15mm in any wheel path and is
continuing to increase, the Principal will conclude that the work is unlikely to achieve its
required design life, and that unless major rework approved by the Principal is undertaken,
that particular project cannot be counted as contributing towards provision of the
nominated preservation quantity or the capital work programme.
Surface Shape and Condition
The surface shape requirements outlined in this clause shall be complied with throughout
the pavement assessment period.
Surface shape shall be measured with a straight edge and wedge. Using the methodology
set out in NZTA B/2, NZTA B/5, NZTA M/10 and NZTA P/11 depending on the
pavement type and layer. Surface shape measurements will be performed at transverse
construction joints, service covers and in any other area where the Principal considers the
limits may have been exceeded.
The surface shall meet the requirements of (or as agreed with the Principal):
a) NZTA B/2 for unbound granular pavements with chip seal
b) NZTA B/5 for modified pavements with chip seal
c) NZTA M/10 for Dense Graded Asphalt and Stone Mastic Asphalt layers
d) NZTA P/11 for OGPA layers
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 59 of 157
4 In addition, the surface shape shall be such that there is no visible cracking or ravelling (or
fretting) within three years of the second coat seal or AC surface.
If any of the annual assessments of roughness, rutting or shape fail to achieve these
criteria, the Contractor shall agree with the Principal an appropriate repair methodology in
order to achieve compliance.
4.5.5 Carriageway Lighting
General Design Principles As a minimum, new and replacement carriageway lighting design must comply with the
requirements of AS/NZS 1158: 1999.
The design of street lighting must also meet the requirements of AS/NZS 1158.3.1: 1999
clause 2.3.3.4 in relation to “Light spilled onto abutting properties”.
Exemptions A large proportion of the existing lighting inventory have been designed in accordance
with the minor road provisions of NZS 6701 that has been superseded by AS/NZS 1158.
There are also a number of subdivisions that have decorative type fixtures. The
replacement of lighting fixtures, brackets, poles or decorative fixtures for the sole purpose
of meeting the AS/NZS1158 standard is not within the scope of the Contract.
In subdivisions, where the use of different installation types would compromise aesthetic
consistency, the Contractor shall make every effort to retain and procure installations
consistent with those existing. This may involve replacement of badly corroded or
discoloured components, minor modifications, painting or strengthening as appropriate.
The Contractor may replace decorative lights with agreed alternative AS/NZS 1158.3.1
category P3 or P4 compliant lighting after consultation with all local residents, including
residents adjacent to the adjacent carriageways 100m beyond the last light to be upgraded
and the Engineer‟s Representative. In such cases residents and the Engineer‟s
Representative shall be given full details of the proposed new installation, including
drawings of the lighting installation and plans of the proposed location of each installation.
The notification shall include the name and contact details of the Contractor‟s
Representative.
The demarcation points between types of lighting installation shall be at appropriate
locations, for example intersections, limit of residential area, or edge of reserve.
Power Network Company Undergrounding In the event of under grounding of any particular area, the ownership of reticulation poles
supporting street light installations will transfer to the Principal when the main power lines
are removed. At that time the condition rating of the lighting installations may change as a
result of the condition of the poles. As soon as notification of an under grounding project
is received, arrangements shall be made with the Engineer‟s Represnetative for the pole
condition to be surveyed.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 60 of 157
4 The CB may consider a recommendation to the Principal for additional funding for the
new cabling, renewals and capital works involved with replacing the light installations.
Previous condition ratings with the poles excluded will be consulted and where
replacement of brackets and/or luminaires could be expected under the Contract, the CB
will negotiate an appropriate reduction to the Contract Price.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 61 of 157
4 4.6 Planning
4.6.1 Investigation and Reporting of Planning Issues
The Contractor shall identify, investigate and report on all planning issues that might
affect the safety or efficiency of the Network. This shall include:
a) Review of planning issues referred to it by the Principal, including resource consent
applications/proposals, reviews, changes and variations to District and Regional
Plans, Policy Statements and strategy documents of District and Regional Councils
and government bodies
b) Site inspection
c) Preparation of requests for additional information
d) Preparation of submissions
The Contractor shall prepare evidence and appear for the Principal at planning hearings as
the need arises. This shall include hearings before district and regional councils, but
exclude High Court and Environment Court proceedings.
The Delivery Times in respect of actions required by the Contractor shall be such that all
planning issues can be responded to by the Principal 10 working days prior to the statutory
deadlines for close of submissions.
4.6.2 Consent Monitoring
The Contractor shall:
a) Monitor the Network to ensure that all consent conditions relating to protection of the
Network are being complied with
b) Monitor the Network to ensure that all necessary consents are being requested
c) Where applicable, on behalf of the Principal, certify compliance with consents on
completion of any works affecting the Network
d) Maintain an up to date database of all consents issued.
The Contractor shall report all incidences of non compliance with consent conditions to
the Principal.
The Delivery Times in respect of notification to the Principal of any incidence of non
compliance shall be within 10 days of the incidence of non compliance occurring.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 62 of 157
4 4.7 Network Control
In performing all network control activities the Contractor is expected to take ownership
of responses and managing customers‟ reasonable expectations within the bounds of
policies. The Principal is to be consulted where there may be uncertainty in terms of
policy and must be informed immediately of issues likely to be escalated to elected
members or be taken to the media. The Contractor will remain responsible for issues that
may arise unless the Principal advises the Contractor in writing that the Principal has taken
over the matter in question.
4.7.1 Processing of Applications for Activities within the Road Corridor
Applications include, but are not limited to, requests by other parties to:
a) Close a road
b) Hold sporting, recreational or other events on the road
c) Perform works on or below the road surface including the installation of utilities
d) Declare a Limited Access Road
e) Declare a Construction Zone
f) Construct an access onto a road
g) Authorise a fence encroachment
h) Authorise a stock crossing
i) Plant or remove a street tree
j) Install a service
k) Approve temporary Traffic Management Plans.
The Contractor shall appoint staff to act as Engineer and Traffic Management Coordinator
for the purposes of approving temporary Traffic Management Plans on behalf of the
Principal.
The Contractor shall process (including undertaking site visits and inspections; calculation
of impact fees etc) 100% of all applications and report to the Principal as required.
Delivery Times shall be as follows:
i) Application information sent to applicant – one week from request
ii) Any further information requested – one week from receipt of application
iii) Site visit (if required) – two weeks from receipt of application
iv) Application (including any deed or agreement) forwarded to Engineer‟s
Representative – one week from receipt of further information or site visit, whichever
is the later
v) Processed application forwarded to applicant – one week from receipt of processed
application
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 63 of 157
4 vi) Initial inspection of any completed works – two weeks from receipt of notification of
completion
vii) Final inspection of any completed works – one month prior to the expiry of any
period of defects liability
4.7.2 Land Acquisition
Where acquisition of land for roading purposes is necessary to enable the Contractor to
carry out the Services, the Contractor shall initiate and administer the land acquisition
process and recommend compensation in accordance with the WBoPDC procedures
detailed below.
The Delivery Time for the survey plan of the land required for road to be delivered to the
WBoPDC Legal Property Officer shall be 2 months following completion of the physical
works for which land acquisition was required.
The WBoPDC procedure for acquisition of land for roading purposes is as follows:
1. The Contractor shall provide preliminary drawings to the landowner/occupier and the
WBoPDC Legal Property Officer indicating the area required for construction
purposes.
2. The Contractor shall calculate the amount of compensation on a per square metre
basis being offered by WBoPDC for the land required for construction purposes and
advise the WBoPDC Legal Property Officer of the proposed compensation. Once
WBoPDC has approved the compensation the Contractor will advise the
landowner/occupier, and advise them also of the alternatives available if the amount is
not acceptable.
3. The Contractor shall obtain a signed land entry agreement to enter from the
landowner/occupier prior to finalising the design and proceeding with construction.
Once the construction has been completed the Contractor will notify the WBoPDC
Legal Property Officer who will arrange for the works to be surveyed.
4. The WBoPDC Legal Property Officer will on receipt of the approved survey plan
write to all landowners providing a copy of the plan with the final land area required
along with the amount of compensation assessed. At this point landowners will need
to indicate whether they are registered for GST and whether there are any outstanding
issues relating to the construction.
5. The WBoPDC Legal Property Officer will then obtain WBoPDC‟s formal consent to
the acquisition of the land.
6. An agreement to acquire the land will be then sent to landowners for their perusal and
signatures. Landowners are to return the signed document along with an invoice to
WBoPDC for the compensation payable for the land.
7. On receipt of the agreement, WBoPDC will execute the document and subject to
Compensation Certificate being registered against the landowners title will then pay
the compensation to the landowners.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 64 of 157
4 8. Once the agreement has been lodged with LINZ, WBoPDC will undertake to
discharge the Compensation Certificate off the landowners‟ title.
9. In the case of multiple owned land where WBoPDC may have to become involved at
an early stage in the complex communication and protracted negotiation commonly
required when dealing with these situations, the Contractor is required to put in a
similar input as would be needed for purchase of land from any cautious, reluctant
landowner and WBoPDC would then provide the rest of the input required.
IMPORTANT NOTE: The Contractor shall advise the owner/occupier that, should at
any time during this process the landowner/occupier seek to on sell all or part of their
land, they must inform the WBoPDC Legal Property Officer of their intent and ensure a
clause is placed in their agreement for sale and purchase that the area to vest in WBoPDC
as road is excluded from the sale.
The WBoPDC procedure for negotiation of compensation follows. Under no
circumstances shall the Contractor offer or provide any form of compensation or payment
whether monetary or otherwise which has the intention or effect of inducing
landowners/occupiers to sign land entry consents other than compensation duly payable in
strict accordance with the procedure below:
1. The Contractor will obtain from the WBoPDC Legal Property Officer all necessary
valuation and GIS information held by WBoPDC, including a calculation of either
100% or 150% of property‟s unimproved land value on a per square metre basis – see
WBoPDC Policy Compensation for Land Acquired for Road.
2. Subject to WBoPDC approval, the Contractor is to supply landowners/occupiers with
an offer of compensation at either 100% or 150% of the unimproved land value per
square metre for the proposed land take area plus GST where the landowner is
registered for GST in respect of land, and subject to final survey.
3. The Contractor will supply to the landowner/occupier the above process summary,
laying out the process for the acquisition and the involvement of the Contractor and
WBoPDC in the process.
4. Should the landowner/occupier accept the above offer of compensation, the
calculation of the amount of compensation per square metre shall be included in the
land entry consent and a copy of the consent provided to the WBoPDC.
5. Should the landowner/occupier not accept the above offer of compensation, the matter
will be referred to the WBoPDC Legal Property Officer.
4.7.3 Access Control
The Contractor shall:
a) Monitor the Network to ensure no unauthorised or illegal accesses are constructed
b) Review and report on the traffic engineering implications of all applications for new
accesses or upgrading of accesses, including liaison with applicants to explain
WBoPDC‟s objectives and policies.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 65 of 157
4 c) The Contractor is to review and report on resource consent and development
applications, where access to the Network is affected and advise and recommend on
requirements which may include:
Road widening
Intersection or access improvements
Right turn bays
Shoulder widening
Parking requirements
Manoeuvring space
Structural strengthening of the road pavement
Sight line deficencies
The Contractor‟s assessment does not include detailed design, provision of a road
safety audit or peer reviews as part of the Services, as this is the responsibility of the
applicant. However, the Contractor has a responsibility to express concerns or
reservations which would be acted on by WBoPDC as part of the consenting process.
d) Monitor and report on segregation strips
e) Monitor and record condition of all stock crossings, noting compliance with safety
requirements (if stock are crossing) and commenting on the road surface. Pollution of
road is to be photographed with a date stamped image and reported to the Principal.
The Contractor will provide information as required by the Principal on the location
and use of stock crossings for the purposes of updating the Principal‟s Stock Crossing
database.
f) Process applications for vehicle crossings in accordance with WBoPDC processes,
including inspections as required before and after construction of the vehicle crossing.
Minimum requirements for reporting on access proposals and administering of
declarations shall be those contained in the NZTA Professional Services Contracts
Proforma Manual, “State Highway Network Management”, clause 3.2.4.
The Delivery Times for plans, schedules, certificates of title and Crossing Place Licence
Notices required for declarations shall be 20 days following such request by the Principal.
The Delivery Times in respect of notification to the Principal of any incidence of
unauthorised or illegal access shall be within 10 days of the incidence of non compliance
occurring.
4.7.4 Hazard Monitoring and Control
The Contractor shall identify and report all hazards which may have an adverse effect on
the condition of the Assets or the safety or road users. Hazards may include, but are not
limited to:
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 66 of 157
4 a) Abandoned vehicles
b) Live animals, generally horses cows and/or cattle
c) Unauthorised works or newly planted vegetation
d) Unauthorised and/or non-complying signs
e) Structures, signs or vegetation/trees which are unsafe, unstable or cause obstruction
f) Roadside trading
g) Fences and encroachments
h) Illegal crossings and services
i) Drainage and land stability problems
j) Land use activities and/or special events which might give rise to increased vehicle
movements, heavy vehicle movements, or parking and manoeuvring problems
Hazards within the Site posing an immediate threat to safety shall be removed by the
Contractor or reported immediately to the appropriate authority. The Delivery Time for
removal shall be in accordance with the Response Times for the Incident Response OPM.
All other hazards within the Site shall be removed after every reasonable attempt has been
made to inform the owner and request removal. The Delivery Time shall be not less than
two weeks after the first attempt to inform the owner and not more than three weeks.
Further Contract Standards and Delivery Times for specific hazards are given below:
i) For all roads, upon the sighting of, or on receipt of a report about wandering stock
within the Site, the Contractor shall approach the stock owner and ask for the
immediate removal off the road of the stock in question. Where this is not possible
due to the inability to locate the legal owner of the stock, the Contractor shall ensure
the animal access on the carriageway is prevented and shall notify the WBoPDC
Livestock Control Officer in order to remove the stock off the road.
Where the WBoPDC Livestock Control Officer is unable to perform his duty, the
Contractor shall proceed and remove the animal off the road and into the WBoPDC
pound.
The NZ Police shall be called upon to help and protect the public in a situation where
the animal is wild and/or out of control.
ii) Abandoned vehicles: These should be reported to the Principal. A Separate Contractor
is responsible for the removal of abandoned vehicles
4.7.5 Management and Coordination of Utility Contractors
The Contractor shall manage and coordinate service related works.
The Contractor shall provide liaison and monitoring in a prompt and courteous manner in
accordance with the service authority or contractor‟s programme for the works. The
Delivery Time for reporting to the Principal in the event of any problems with the
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 67 of 157
4 performance of the service authority or contractor shall be 24 hours in relation to safety
matters and one week in relation to any other matter.
4.7.6 Overweight and Overdimensioned Vehicles
The Contractor shall process and assess such applications and issue permits, in accordance
with WBoPDC policy and procedures.
For all overweight or overdimensioned vehicle movements the Contractor shall provide
suitably trained and experienced personnel to supervise the movement where required by
the permit issued to the operator.
The Contractor shall provide such supervision in a prompt and courteous manner. The
Delivery Time shall be such that there is no disruption to the operator‟s timetable.
4.7.7 High Productivity Motor Vehicles
Applications for High Productivity Motor Vehicle permits are to be referred to NZTA.
Following processing by NZTA, the Contractor may be required to review the application
with respect to the Local Road component and provide recommendations to NZTA.
Appendices (WBoPDC Local Roads)
1 Management Performance Measures
Page 68 of 157
4 4.8 Customer Satisfaction Index (CSI)
The Contractors customer care performance with respect to service requests will be
assessed by customer survey carried out by an independent research company selected and
engaged by the Principal using the sampling methodology, survey questionnaire and CSI
calculation detailed below.
4.8.1 Sampling Method
Sample Size 600 interviews per annum or 50 per month
1 interview will be conducted monthly per possible service request problem.
Interview Frequency Interviews will be distributed throughout the month.
Method of Interview Telephone interviewing
Sampling Frame Respondent contact details supplied – by way of Service Request raised by WBoPDC.
These shall be supplied in electronic format directly to the research provider on a weekly basis.
Service requests shall be selected from those that are off and for which customers have been informed of actions to be taken, if any. It is possible that at the time of interview works may be programmed in response to the request but not completed, or no further action may be required.
Reporting Monthly – appropriate format to be determined
Annually
4.8.2 Questionnaire
The Contractor will be provided with the questionnaire.
4.8.3 Index Calculation
The Contractor will be provided with the index calculation methodology.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 69 of 157
5 5
Key Performance Measures
5.1 High Speed Data Collection
NZTA‟s national High Speed Data (HSD) supplier is the Nominated Subcontractor for
HSD collection. The data collection and validation will be conducted in accordance with
the requirements of that contract, and supplied to the Contractor.
Invoices from this Nominated Subcontractor will be paid under a Provisional Sum in
accordance with the Basis of Payment (WBoPDC Local Roads). Coordination and
processing of data in accordance with the Contract is part of the Services.
High Speed Data surveys must:
a) Be completed in accordance with the requirements of the NZTA contract for HSD
collection
b) Be completed in the final quarter of each year (Mar/Apr/May)
c) Cover 100% of sealed carriageway sections, in the years defined below
Table 5.1: High Speed Data Collection Frequency
Road Group Year 1 (14/15)
Year 2 (15/16)
Year 3 (16/17)
Year 4 (17/18)
Year 5 (18/19)
Year 6 (19/20)
Year 7 (20/21)
1 to 3
4 to 5
6 to 7
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 70 of 157
5 5.2 Traffic Speed Deflection Data Collection
NZTA‟s national Traffic Speed Deflectometer supplier is the Nominated Subcontractor for
traffic speed deflection data collection. The data collection and validation will be
conducted in accordance with the requirements of that contract, and supplied to the
Contractor.
Invoices from this Nominated Subcontractor will be paid under a Provisional Sum in
accordance with the Basis of Payment (WBoPDC Local Roads). Coordination and
processing of data in accordance with the Contract is part of the Services.
Traffic Speed Deflection surveys must:
a) Be completed in accordance with the NZTA contract for Traffic Speed Deflectometer
data collection
b) Cover the nominated length, as agreed with the Engineer‟s Representative, of the
sealed rural carriageway sections, in the years defined below
Table 5.2: Traffic Speed Deflection Data Collection Frequency
Road Group Year 1 (14/15)
Year 2 (15/16)
Year 3 (16/17)
Year 4 (17/18)
Year 5 (18/19)
Year 6 (19/20)
Year 7 (20/21)
1 to 3
4 to 5
6 to 7
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 71 of 157
5 5.3 RAMM Condition Rating Data Collection
The Contractor may nominate their own independent team to undertake data collection
surveys. In any case the composition of rating teams shall comply with Maintenance
Specification (State Highways), Section 2.3.3 with respect to independence, objectivity
and links to the Quality Plan.
5.3.1 General Requirements
All personnel completing RAMM condition rating surveys shall be suitably qualified and
shall have attended a road condition rating workshop approved by the Engineer‟s
Representative within the previous 24 months. Copies of rating accreditation certificates
must be provided to the Engineer‟s Representative prior to survey work commencing.
All personnel completing RAMM condition rating surveys shall be independent of the
delivery team. For the avoidance of doubt, personnel who work for the Contractor (or its
suppliers) but are not located in the contract office and are not directly engaged in contract
delivery may be considered to be independent of the delivery team.
All data must be provided in a format that can be directly loaded into the WBoPDC
RAMM database without the need for further processing or modification. To demonstrate
this, the Contractor must process the data and ensure that the processed data meets the
requirements of the RAMM Input Validation Rules.
5.3.2 Survey Requirements (Roads)
Road condition rating surveys must:
a) Be completed in accordance with the version of the NZTA RAMM Road Condition
Rating Manual current at the time of tender
b) Cover 10% of the sealed carriageway sections each year in each of road groups 1 to 7,
using a sampling methodology agreed with the Engineer‟s Representative
c) Cover 10km of the unsealed carriageway sections each month in each of road groups
1 to 7, using a sampling methodology agreed with the Engineer‟s Representative, and
combined into a total survey length of 120km each year
5.3.3 Survey Requirements (Drainage)
Drainage condition (lined and unlined) rating surveys must:
a) Be completed in accordance with the version of the NZTA RAMM Road Condition
Rating Manual current at the time of tender
b) Cover 100% of the sealed carriageway sections each year in each of road groups 1 to
7
c) Include all surface kerb and channel items (e.g. kerb, kerb and channel, mountable
kerb, dish channel), other than where they are part of a raised island not designed to
collect water
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 72 of 157
5 5.3.4 Survey Requirements (Footpaths)
Footpath condition rating surveys must:
a) Be completed in accordance with this specification and supplemented by the
definitions and descriptions in the New Zealand National Roads Board Road
Condition Rating Manual
b) Cover 100% of all footpaths in the Waihi Beach, Athenree, Pios Beach, Tanners
Point, Ongare Point, Katikati, Omokoroa, Te Puke, Makatu, Paengaroa, Pukehina and
rural communities each year, irrespective of road group
The question that the rater must ask is: could this footpath present a hazard to pedestrian
traffic?
A brief review of faults to be inspected for are as follows:
Table 5.3.4: Footpath Faults
Fault Type Assessment Rating
Settlement No settlement
Settlement > 10mm
Settlement > 20mm
0
3
5
Bumps No bumps
Minor bumps > 10mm
Major bumps > 20mm
0
3
5
Depressions No depressions
Minor depressions > 10mm
Major depressions > 20mm
0
3
5
Cracks No cracks
Minor cracks (2 cracks within 2m or single crack with width > 10mm)
Major cracks
0
3
5
Each footpath section shall have a length to be replaced recorded (0m is acceptable).
A fault shall be recorded against all sections where replacement length >0m. Each fault
shall have a number (0, 3, 5) and the fault is relative only to the length to be replaced.
No length to be replaced means no faults.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 73 of 157
5 Settlement, bumps, depressions or cracks that result in a 10mm to 20mm vertical
difference in height under a 0.5m straight edge would result in a 3 rating and be measured
at approximately 1m per fault.
Settlement, bumps, depressions or cracks that result in a greater than 20mm vertical
difference in height under a 0.5m straight edge would result in a 5 rating and be measured
at approximately 1m per fault.
Faults are to be marked and identified by a “T” or ““” mark on all grade 3‟s, and a
double stalk “∏” or a “∐” on all grade 5‟s, to enable faults to be found and verified in the
field.
5.3.5 Data Requirements
Data must:
a) Be provided in an ASCII delimited format agreed with the Engineer‟s Representative
b) Be stored in individual files by road number and carriageway section
The Contractor must supply the following data:
i) All information for sealed roads required by the NZTA RAMM Road Condition
Rating Manual current at the time of tender
ii) All information for unsealed roads required by the NZTA RAMM Road Condition
Rating Manual current at the time of tender
iii) All information for footpaths required by Maintenance Specification (WBoPDC Local
Roads), Section 5.15, by community
iv) The graded width for each rated carriageway section on unsealed roads
v) The length of footpath to be replaced in each rated carriageway section
5.3.6 Reporting Requirements
All data delivered for each survey must be accompanied by a Survey Data Report
containing the following information:
a) Results of compliance monitoring completed
b) Data quality check sheets
c) Inconsistencies or error trends between the rated values and the audited values
d) The actions to address the above problems and steps taken to ensure the quality and
reliability of the supplied data
e) Comment on the effect any differences between the rated values and audited values
would have on the outputs from the treatment selection programme
The Survey Data Report must be signed off by the Contractor‟s Representative to confirm
that all survey and data processing has been completed in accordance with this
specification and the Contractor‟s quality assurance procedures.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 74 of 157
5 At the completion of each year in which a survey is required, the Contractor shall prepare
a survey report summarising the issues encountered during the survey and actions taken.
The report should cover:
i) Notable events
ii) Traffic management
iii) Report of any accidents or incidents
iv) Public complaints received and actions taken
v) Daily operations (e.g. average daily achievement, operational problems)
vi) Delays due to weather
vii) Variations completed
viii) Quality assurance and non-conformances raised
ix) Recommendations for changes to future surveys
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 75 of 157
5 5.4 Traffic Counting Data Collection
5.4.1 General Requirements
The Contractor shall provide and maintain all traffic counting equipment, including tubes,
clips, chains, locks and other hardware. For classified counting, a GK5000 or similar shall
be used to give detailed breakdowns of traffic mix, type and speed, and to enable hourly
splits over the counting period.
All data must be provided in an electronic format that can be directly loaded into the
WBoPDC RAMM database without the need for further processing or modification. To
demonstrate this, the Contractor must process the data and ensure that the processed data
meets the requirements of the RAMM Input Validation Rules. Where data must be
provided in a format that cannot be directly loaded into the WBoPDC RAMM database,
due to the structure of the WBoPDC RAMM database, it must be forwarded to the
Engineer‟s Representative in a form that allows it to be indexed and analysed.
5.4.2 Survey Requirements (Control Roads)
A 7 day classified ADT count shall be undertaken on the following roads every 3 months
at the same location and on a similar day to previous classification counts:
Table 5.4.2: Control Traffic Counts
No. Road Name Displacement
1 Waihi Beach Road 2.50km
2 Athenree Road 0.11km
3 Busby Road 0.36km
4 Wharawhara Road 0.10km
5 Esdaile Road 0.08km
6 Omokoroa Road 0.16km
7 Barrett Road 0.33km
8 Minden Road 0.38km
9 Te Puna Road 0.40km
10 Te Puna Station Road 0.20km
11 Wairoa Road 1.00km
12 Omanawa Road 0.67km
13 Poripori Road 0.67km
14 McLaren Falls Road 0.32km
15 Oropi Gorge Road 0.24km
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 76 of 157
5 Table 5.4.2: Control Traffic Counts
No. Road Name Displacement
16 Oropi Road 3.30km
17 Ohauiti Road 3.90km
18 Kaitemako Road 3.56km
19 Welcome Bay Road 0.18km
20 Welcome Bay Road 8.04km
21 Bell Road 0.16km
22 No. 3 Road 1.02km
23 No. 2 Road 6.90km
24 Te Matai Road 0.15km
25 Te Matai Road 26.16km
26 Rangiuru Road 0.01km
27 Maketu Road 0.03km
28 Wilson Road South 1.38km
29 Old Coach Road 1.053km
30 Maungarangi Road 0.20km
31 Pongakawa Bush Road 0.10km
32 Maketu Road 0.40km
33 Pukehina Beach Road 0.07km
34 Rotoehu Road 0.20km
35 Maniatutu Road West 0.20km
The Contractor shall record any occurrence that may have affected the result, such as local
or seasonal events, weather, public or school holidays. In the event of equipment
malfunction or vandalism, the Contractor shall repeat the measurement at no additional
cost to the Principal.
5.4.3 Survey Requirements (Routine)
Routine traffic counts must be performed:
a) Over a seven day period at each site
b) Once every two years on each sealed rural carriageway section in road groups 1 to 7,
including all sections of any road that is predominantly rural but which begins or ends
in an urban area. Counts must be conducted at the same location and at the same each
year (within two weeks) to avoid seasonal swings in traffic
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 77 of 157
5 c) Once annually on each unsealed rural carriageway section in road groups 1 to 7,
including all sections of any road that is predominantly rural but which begins or ends
in an urban area. Counts must be conducted at the same location and at the same each
year (within two weeks) to avoid seasonal swings in traffic
d) Once annually on all carriageway sections of the following urban roads:
Table 5.4.3: Routine Traffic Counts
No. Urban Area Road Name
1 Waihi Beach Beach Road
2 Waihi Beach Seaforth Road
3 Waihi Beach Wilson Road
4 Waihi Beach Athenree Road
5 Katikati Park Road
6 Katikati Beach Road
7 Katikati Tetley Road
8 Katikati Wills Rd
9 Omokoroa Omokoroa Road
10 Omokoroa Tralee Road
11 Omokoroa Hamurana Road
12 Paengaroa Old Coach Road
13 Paengaroa Wilson Road South
14 Te Puke No. 1 Road
15 Te Puke No. 2 Road
16 Te Puke No. 3 Road
17 Te Puke Boucher Avenue
18 Maketu Wilson Road
19 Maketu Maketu Road
5.4.4 Data Requirements
Data must:
a) Be provided in an ASCII delimited format agreed with the Engineer‟s Representative
b) Be stored in individual files by road number and carriageway section
The Contractor must supply the following data:
i) The average daily traffic count over the survey period for each carriageway section
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 78 of 157
5 ii) In respect of control road surveys, the following traffic flow information for each
carriageway section
Separated bi-directional traffic volumes
Vehicle classification (light / medium / heavy as a minimum)
60 minute time interval between data sets
Speed
5.4.5 Reporting Requirements
All data delivered for each survey must be accompanied by a Survey Data Report
containing the following information:
a) Results of compliance monitoring completed
b) Data quality check sheets
c) Equipment failures or replacements
d) The actions to address the above problems and steps taken to ensure the quality and
reliability of the supplied data
The Survey Data Report must be signed off by the Contractor‟s Representative to confirm
that all survey and data processing has been completed in accordance with this
specification and the Contractor‟s quality assurance procedures.
To provide a record of the „extreme events‟, the Contractor shall prepare an exception
report recording:
a) The locations of all carriageway sections with abnormally high or low traffic volumes
of %HCV
b) Notes on the likely reason for the extreme event, such as a local or seasonal event,
weather, public holidays or school holidays
At the completion of each year in which a survey is required, the Contractor shall prepare
a survey report summarising the issues encountered during the survey and actions taken.
The report should cover:
i) Notable events
ii) Report of any accidents or incidents
iii) Public complaints received and actions taken
iv) Delays
v) Equipment failures
vi) Variations completed
vii) Quality assurance and non-conformances raised
viii) Issues relating to data processing
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 79 of 157
5 ix) Results of any special studies completed
x) Seasonal correction results
xi) Recommendations for changes to future surveys
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 80 of 157
5 5.5 Network Video
A video of the entire network, both sealed and unsealed shall be collected by the
Contractor each year. The purpose of the video is:
a) To have a historical record of the roading network
b) To have them available for consultants and other interested parties to use for
obtaining further information within the roading corridor
c) Provide evidence of road condition and deterioration
A sample video shall be provided to the Engineer‟s Representative for acceptance prior to
surveys commencing.
5.5.1 General Requirements
Video shall be captured using a minimum of one 3-CCD digital camera with wide angle
lens (60-70° horizontal field of view). All equipment used is to provide high quality colour
recording at normal survey speeds. The camera shall be dipped at 3°- 6° and aligned
parallel to the centre of the vehicle axis. The camera is to be fixed focus, with an
accurately calibrated lens-camera-image combination to allow height/width measurements
to within 0.2 metres). The shutter speed must be sufficient to minimise motion blur.
Particular consideration must be given to the mounting of the camera to minimise
vibration.
The minimum requirements for the network video survey equipment are:
Table 5.5.1 a): Network Video Minimum Requirements
Parameter Minimum Requirement
File format Current technology
Image height 768 pixels
Image width 1360 pixels
Audio recording No
Video interlacing Non-interlaced (i.e. progressive scan with no duplicated lines and no “field motion”)
Video quality High
The images are to be recorded with time stamp capabilities in a separate electronic file.
Images are to be indexed by either frame numbers or time stamp which are stored on the
video and synchronised to the true position data of the vehicle at all times (i.e.
displacement is to be rubberbanded to true network length). The file created shall be an
ASCII file in the following format, with the frequency of record creation agreed with the
Engineer‟s Representative:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 81 of 157
5 Table 5.5.1 b): Time Stamp Requirements
Field Description Field Information
1 Road ID integer (4) no nulls
2 Displacement integer (5) no nulls
3 Direction (I, D or null) char (1)
4 File reference char (25) no nulls
5 Frame number or time stamp no nulls
6 Date of recording ddmmyyy no nulls
All distance measuring equipment must be validated on an odometer calibration test track
in accordance with the NZTA Location Referencing Management System Manual. If an
already established odometer calibration test track is to be used, the Contractor must
supply confirmation from a Registered Surveyor that the calibration test track meets the
dimensional tolerances specified in the NZTA Location Referencing Management System
Manual. The Contractor must then measure the length of the test track at least 5 times
using the distance measuring equipment. The distance measuring equipment is validated
when all the measurements are within ±0.05% of the reference distance.
5.5.2 Survey Requirements
Network videos of all WBoPDC Local Roads must be performed:
a) Once annually on each sealed and unsealed carriageway in road groups 1 to 7
b) In each lane direction as a continuous survey
c) During period of fine weather with light conditions appropriate to provide good
quality video
d) Such that the lane width and roadside furniture are captured
e) Such that no part of the survey vehicle appears in the video
f) To be completed in the final quarter of each period (Mar/Apr/May)
The Contractor must record and report the route position of all network video survey data
to an accuracy of:
±(0.3% x D + 10m), for 100% of roads
±(0.25% x D + 10m), for 95% of roads
where:
D = the distance from the start of the road as defined in the WBoPDC RAMM
database.
The surveys must start at the commencement of the road as defined in the WBoPDC
RAMM database. The start point must be recorded and the distance measuring equipment
set to the start point distance, usually 0. If the distance measurement at the end of the road
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 82 of 157
5 is not within the specified tolerance, the Contractor must resurvey the road. The re-survey
must note any difference in the measurement point locations. If the second survey
confirms the initial survey, the Contractor must notify the Engineer‟s Representative
immediately and develop a remedial proposal for agreement with the Engineer‟s
Representative.
All data collected for each road is to be rubber-banded to adjust for the difference between
the measured length and the true length.
5.5.3 Data Requirements
Three sets of all data for each survey must be provided on media agreed with the
Engineer‟s Representative.
If review of the data by the Engineer‟s Representative reveals discrepancies, quality issues
or other problems in the data, the Contractor must correct the error and redeliver the data
within 5 working days, which may include resurvey if directed by the Engineer‟s
Representative.
5.5.4 Reporting Requirements
All data delivered for each survey must be accompanied by a Survey Data Report
containing the following information:
a) Results of compliance monitoring completed
b) Data quality check sheets
c) Distance measurement discrepancies (i.e. any roads where the measured distance was
outside the allowed tolerance and actions taken to verify true length)
d) Equipment failures or replacements
e) The actions to address the above problems and steps taken to ensure the quality and
reliability of the supplied data
The Survey Data Report must be signed off by the Contractor‟s Representative to confirm
that all survey and data processing has been completed in accordance with this
specification and the Contractor‟s quality assurance procedures.
The Contractor shall prepare a report detailing:
i) Equipment descriptions, specifications and configuration
ii) Distance rubber banding procedures
iii) Format and description of all raw data
iv) Correction procedures that were applied and how
5.5.5 Viewing Software Requirements
The Contractor shall provide a video viewer software package to enable the video to be
viewed. Minimum requirements for the software are:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 83 of 157
5 a) Ability to select video file by road
b) Ability to enter the route position and to jump to this location on the video
c) Ability to vary the video speed
d) Ability to flip between increasing and decreasing directions or view both at same time
e) Ability to capture images from the video and to set the file path for photo storage
f) Ability to display roadname, displacement, direction and GPS coordinates on the
video display, and to be able to toggle these displays on or off separately
g) Ability to import, select and view latest RAMM data concurrently either in tabular or
graphical form
h) Windows compatible
The Contractor shall provide technical support for the video viewer software.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 84 of 157
5 5.6 Roughness
5.6.1 Data Analysis
Roughness is to be analysed using the high speed data collected in accordance with
Appendix (WBoPDC Local Roads) 5.1.
The analysis shall exclude the following:
a) Records for roads owned by parties other than WBoPDC (e.g. Crown, Tauranga City
Council, Maori or privately-owned)
b) Records for roads less than 200m long
c) Records with the following event codes:
A (Post-Survey Added Value)
D (Detour Route)
H (Speed Humps)
U (Unsealed road begins/ends)
W (Road Works)
X (Railway crossings)
d) Records that were collected while the survey vehicle was travelling at 25km/hr or less
e) Records for the roads in the following table:
Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Adela Stewart Drive 1014 0 87 87
Adrine Lane 1930 0 112 112
Albacore Avenue 1008 0 100 100
Allanah Place (Te Puke) 1951 0 120 120
Alley Road 1489 0 106 106
Angus Lane 1830 0 62 62
Aran Place 1770 0 83 83
Ashwood Grove 1851 0 66 66
Astelia Drive 1871 0 125 125
Athenree Heights Slip (North Lane) 7160 0 75 75
Athenree Slip Road (RS3679) 7253 0 57 57
Atlanta Court 1891 0 76 76
Ayr Street 1836 0 105 105
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 85 of 157
5 Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Baigent Place 1038 0 183 183
Baker Road 1121 0 145 145
Barnett Place 1769 0 44 44
Barrow Place 1743 0 112 112
Bayly Place 1740 0 83 83
Beach Grove 1268 0 188 188
Belmont Rise 1887 0 183 183
Bert Wall Drive 1983 0 192 192
Binnie Road 1072 0 192 192
Birch Lane 7147 0 107 107
Blundell Place 1095 0 193 193
Bonito Avenue 1003 0 137 137
Bonnieglen Road 1595 0 69 69
Boucher Avenue Service Lane (RP31 LHS) 7176 0 65 65
Boucher Avenue Service Lane (RP41 LHS) 7204 0 109 109
Bramley Drive 1277 0 149 149
Bransley Grove 1915 0 106 106
Breakers Crescent 1941 0 55 55
Brookby Place 1919 0 63 63
Burd Road 1607 0 41 41
Carberry Crescent 1734 0 85 85
Church Road 1555 0 148 148
Clifden Terrace 1796 0 80 80
Coleman Place 1954 0 133 133
Collins Lane (72-87) 2498 0 112 112
Commerce Lane Carpark 7205 0 174 174
Conifer Place 1785 0 136 136
Cooney Place 1777 0 100 100
Cresta Drive 1962 0 49 49
Crossley Street South 1839 0 60 60
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 86 of 157
5 Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Dawson Road 1878 0 54 54
Denby Close 1015 0 41 41
Dolphin Avenue 1007 0 100 100
Donegal place 1896 0 141 141
Donelle Place 1939 0 68 68
Dowman Place 1926 0 78 78
Dunlop Road Service Lane (RP55 RHS) 7230 0 80 80
Edwards Street 1841 0 135 135
Elizabeth Street 1821 0 111 111
Emeny Road North 2219 0 60 60
Fairlie Grove 1228 0 99 99
Farm Road 1828 0 65 65
Farnell Court 1269 0 66 66
Fencourt Crescent 1093 0 102 102
Fenton Terrace Slip 7067 0 68 68
Fleur Place 1950 0 83 83
Galway Place 1771 0 120 120
Gane Place 1261 0 126 126
Gardiner Place 1578 0 70 70
Garrett Road 1484 270 400 130
Gellibrand Place 1282 0 107 107
Gerald Place 1281 0 49 49
Giles Way 1037 0 129 129
Gisborne Road 1746 0 188 188
Gledstane Road 1090 0 126 126
Glen Isla Place 1837 0 130 130
Goldstone Road 1710 0 56 56
Gordet Drive 1895 0 128 128
Gordon Street 1790 0 123 123
Gray Avenue 1843 0 179 179
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 87 of 157
5 Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Gray Street 1079 0 139 139
Gray Street North 7300 0 66 66
Greystone Place 1975 0 59 59
Grosvenor Place 1888 0 90 90
Gunga Lane 1892 0 135 135
Haden Place 1964 0 169 169
Hansen Place 1862 0 62 62
Harbour View Road Side Road 7210 0 39 39
Harbour View Road Slip #1 7227 0 23 23
Harbour View Road Slip #2 (NOS 29-3 7228 0 45 45
Henry Road Slip (RP 118 RHS) 4020 0 50 50
Herbert Street 1757 0 153 153
Hereford Place 1856 0 195 195
Hillary Street 1826 0 111 111
Hinckley Road 1968 0 74 74
Hinemoa Road 1804 0 177 177
Hoggard Place 1960 0 188 188
Hyde Street 1086 0 100 100
Irwin Court 1067 0 94 94
Island Vista 1885 0 115 115
Jellicoe Street Slip (RP1357 RHS) 7174 0 86 86
Jellicoe Street Slip (RP1374 LHS) 7297 0 167 167
Kaharoa Avenue 1271 0 148 148
Kaimai Lane 7146 0 100 100
Katterns Street 1106 0 173 173
Kauri Place 1556 0 170 170
Kauri Place Slip 7035 0 30 30
Killarney Street 1735 0 107 107
Kiokio Place 1562 0 144 144
Kiri Place 1905 0 69 69
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 88 of 157
5 Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Kowai Grove 1272 0 134 134
Kowhai Avenue 1742 0 161 161
Kowhai Court 1073 0 174 174
Kylemore Place 1767 0 64 64
Lakeside Terrace 1974 0 37 37
Landscape Road Slip 4036 0 117 117
Lenihan Drive 1729 0 155 155
Lindoch Avenue 1231 0 152 152
Links View Drive Slip 7043 0 86 86
Lismore Lane 1873 0 199 199
Longboard Drive 1928 0 150 150
Ludlow Place 1917 0 122 122
Macmillan Street 1097 0 192 192
Magnolia Place 1791 0 63 63
Major Street 1083 0 69 69
Mako Avenue 1001 0 143 143
Mangatoi Road 1675 0 120 120
Mangawhai Place 1976 0 41 41
Marina Way 1016 0 142 142
Marlin Avenue 1006 0 128 128
Marshall Place 1110 0 110 110
Martha Lane 1292 323 395 72
Maruia Place 1424 0 193 193
Mayor View Terrace Side Road 7209 0 45 45
McKenna Lane 1925 0 94 94
McQuade Road (off Ross Road) 1288 0 114 114
Memorial Hall Service Lane 7218 0 75 75
Mends Lane 1572 0 193 193
Mermaid Place 1944 0 58 58
Mickells Drive 1876 0 55 55
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 89 of 157
5 Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Milsom Place 1846 0 157 157
Mountbatten Place 1797 0 106 106
Muir Place 1741 0 134 134
Munro Road East 1307 0 119 119
Nathan Place 1013 0 52 52
Nettlingham Place 1739 0 79 79
Nga Parae Road 1970 0 178 178
Ngamuwahine Road 1425 0 160 160
No. 1 Road High Level Access 7238 0 67 67
Noble Lane 1053 0 92 92
Nolan Place 1977 0 160 160
North Road 1174 0 94 94
Old Coach Road Slip 7155 0 25 25
Olive Close 1949 0 138 138
Omokoroa Road Slip #1 (No.s 74-80) 7225 0 63 63
Omokoroa Road Slip #2 (No.s 64 - 72) 7191 0 93 93
Omokoroa Road Slip #3 (No.s 24-38) 7226 0 99 99
Oropi Road High Level Access 7239 0 141 141
Oroua Street Extension (RP198 RHS) 7117 0 50 50
Otawa Street 1780 0 153 153
Otto Road 1832 0 152 152
Paama Court 1703 0 62 62
Palm Grove 1931 0 151 151
Palmer Place 1798 0 71 71
Park Avenue 1818 0 106 106
Park Lane (Te Puke) 1763 0 51 51
Park Road (Maketu) 1553 0 105 105
Parkland Rise 1963 0 122 122
Patterson Place 1833 0 108 108
Philip Walter Drive 1081 0 188 188
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 90 of 157
5 Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Plom Road 1971 0 49 49
Pokare Road 1580 0 66 66
Post Office Road (Matakana) 7141 0 70 70
Potu Road 1047 0 185 185
Preston Drive Parking Loop 7270 0 54 54
Pukehina Beach Road Slip 7004 0 71 71
Puriri Avenue 1745 0 188 188
Queen Street (Waihi Beach) 1820 0 177 177
Randell Place 1776 0 171 171
Rauporoa Road 1547 0 163 163
Reabrook Place 1920 0 94 94
Reel Road 1942 0 107 107
Reo Crescent 1929 0 166 166
Riverlea Drive 1071 0 184 184
Riverside Place 1965 0 180 180
Rosemary Place 1069 0 89 89
Ruamoana Place (2) 2278 0 71 71
Ruamoana Place (3) 3278 0 112 112
Ruamoana Place (4) 4005 0 90 90
Samantha Place 1907 0 70 70
Sandleigh Drive 1956 0 186 186
Saunders Place 1765 0 161 161
Scarborough Road 1815 0 194 194
Scott Street 1824 0 119 119
Sea Crest Place 1881 0 117 117
Sea Vista 1886 0 144 144
Seafoam Place 1957 0 126 126
Seaforth Slip Road #1 (RP5356 LHS) 7048 0 144 144
Seaforth Slip Road #3 (RP5886 LHS) 7050 0 174 174
Seaforth Slip Road #4 (RP6146 RHS) 7177 0 126 126
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 91 of 157
5 Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Service Lane #3 (Katikati) 7102 0 60 60
Slater Place 1754 0 126 126
Slater Place Service Lane (RP33 RHS) 7236 0 155 155
Stanley Street 1050 0 93 93
Stapleton Place 1847 0 103 103
Stewart Street (Katikati) 1084 0 110 110
Stock Road 1799 0 179 179
Stokes Road 1060 0 135 135
Strathaven Way 1872 0 83 83
Tapsell Road 1530 0 123 123
Te Kanawa Place 1882 0 117 117
Te Karaka Drive 1220 0 99 99
Teihana Road 1252 0 158 158
The Esplanade (Waihi Beach) 1805 90 154 64
The Terrace 1802 0 142 142
Thomas Road South 4012 0 78 78
Thorn Road 1428 0 175 175
Tinopai Drive Slip #1 (No.s 10-16) 7229 0 74 74
Tom Baikie Lane 1927 0 147 147
Tralee Street 1265 0 173 173
Tranquil Grove 1979 0 45 45
Treholme Lane 1244 0 131 131
Troon Drive 1937 0 134 134
Troy Place 1906 0 52 52
Tuhua Place 1860 0 194 194
Tuna Avenue 1005 0 128 128
Tutea Place 1646 0 141 141
Twickenham Close 1899 0 112 112
Uretara Drive 1900 0 104 104
Valley View Road 1589 0 114 114
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 92 of 157
5 Table 5.6.1: Roads Excluded from Calculations Using HSD
Name Road ID Start End Length
Vantage Place 1973 0 93 93
Victoria Street 1052 0 162 162
Waiiti Avenue 1009 0 91 91
Waikaraka Drive East 1235 0 166 166
Wallace Road Cul-De-Sac 7296 0 58 58
Walnut Grove 1279 0 123 123
Waterview Terrace 1870 0 190 190
Wedgewood Lane 7101 0 163 163
Wedgewood Place 7148 0 56 56
West Street 1800 0 77 77
Westbank Drive 1145 0 170 170
Whenuariri Place 1563 0 186 186
Whenuariri Place Slip 7034 0 73 73
William Wood Place 1933 0 109 109
Williams Drive 1768 0 167 167
Wilson Road South Slip 7156 0 75 75
Wilson Road Service Lane (Waihi Beach) 7224 0 49 49
Wiltshire Place 1778 0 118 118
Young Road Slip 7175 0 97 97
Matakana Road 1695 0 2490 2490
Opureora Road 1697 0 1847 1847
Waihirere Road 1696 0 1330 1330
The analysis shall be completed using current high speed data only.
5.6.2 Calculations
The Mean Roughness KPM results are calculated from the 20m lane roughness data in the
RAMM table (hsd_rough) using the following formula:
𝑀𝑒𝑎𝑛 𝑅𝑜𝑢𝑔𝑛𝑒𝑠𝑠 = 𝑁𝐴𝐴𝑆𝑅𝐴 𝑟𝑒𝑎𝑑𝑖𝑛𝑔𝑠 𝑖𝑛 𝑎𝑙𝑙 𝑙𝑎𝑛𝑒𝑠
𝑁𝑜. 𝑜𝑓 𝑁𝐴𝐴𝑆𝑅𝐴 𝑟𝑒𝑎𝑑𝑖𝑛𝑔𝑠 𝑖𝑛 𝑎𝑙𝑙 𝑙𝑎𝑛𝑒𝑠
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 93 of 157
5 The Percent Roughness > Threshold KPM results are calculated from the 100m lane
roughness data in the RAMM table (rough) using the following formula:
𝑃𝑒𝑟𝑐𝑒𝑛𝑡 𝑅𝑜𝑢𝑔𝑛𝑒𝑠𝑠 > 𝑇𝑟𝑒𝑠𝑜𝑙𝑑 = 𝑁𝑜. 𝑜𝑓 𝑁𝐴𝐴𝑆𝑅𝐴 𝑟𝑒𝑎𝑑𝑖𝑛𝑔𝑠 > 𝑡𝑟𝑒𝑠𝑜𝑙𝑑
𝑁𝑜. 𝑜𝑓 𝑁𝐴𝐴𝑆𝑅𝐴 𝑟𝑒𝑎𝑑𝑖𝑛𝑔𝑠 × 100%
The Length with Roughness > Threshold KPM results are calculated from the 100m lane
roughness data in the RAMM table (rough) using the following formula:
𝐿𝑒𝑛𝑔𝑡 𝑤𝑖𝑡 𝑅𝑜𝑢𝑔𝑛𝑒𝑠𝑠 > 𝑇𝑟𝑒𝑠𝑜𝑙𝑑 = 𝑁𝑜. 𝑜𝑓 𝑁𝐴𝐴𝑆𝑅𝐴 𝑟𝑒𝑎𝑑𝑖𝑛𝑔𝑠 > 𝑡𝑟𝑒𝑠𝑜𝑙𝑑
Smooth Travel Exposure KPM results are calculated from the 100m lane roughness data
in the RAMM table (rough) using the following formula:
𝑆𝑚𝑜𝑜𝑡 𝑇𝑟𝑎𝑣𝑒𝑙 𝐸𝑥𝑝𝑜𝑠𝑢𝑟𝑒 = 𝐴𝐷𝑇𝑒𝑠𝑡 /𝑁𝑜. 𝑜𝑓 𝑙𝑎𝑛𝑒𝑠 𝑅𝑒𝑎𝑑𝑖𝑛𝑔𝑠 <𝑡𝑟𝑒𝑠𝑜𝑙𝑑
𝐴𝐷𝑇𝑒𝑠𝑡 /𝑁𝑜. 𝑜𝑓 𝑙𝑎𝑛𝑒𝑠 𝐴𝑙𝑙 𝑟𝑒𝑎𝑑𝑖𝑛𝑔𝑠
× 100%
where ADTest and the number of lanes are taken from the RAMM carriageway table.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 94 of 157
5 5.7 Texture
5.7.1 Data Analysis
Texture is to be analysed using the high speed data collected in accordance with Appendix
(WBoPDC Local Roads) 5.1.
The analysis shall exclude the following:
a) Records for roads owned by parties other than WBoPDC (e.g. Crown, Tauranga City
Council, Maori or privately-owned)
b) Records with the following event codes:
A (Post-Survey Added Value)
D (Detour Route)
H (Speed Humps)
U (Unsealed road begins/ends)
W (Road Works)
X (Railway crossings)
c) Records for roads listed in Appendix (WBoPDC Local Roads) 5.6, Table 5.6.1
The analysis shall be completed using current high speed data only.
5.7.2 Calculations
The Percent Texture < Threshold KPM results are calculated from the 10m wheelpath
texture data in the RAMM table (hsd_texture) using the following formula:
𝑃𝑒𝑟𝑐𝑒𝑛𝑡 𝑀𝑒𝑎𝑛 𝑇𝑒𝑥𝑡𝑢𝑟𝑒 𝐷𝑒𝑝𝑡 < 𝑇𝑟𝑒𝑠𝑜𝑙𝑑 = 𝑙𝑑 + 𝑟𝑑𝑙 + 𝑟
× 100%
where:
ld = No. of 10m intervals in the left wheelpath with a mean profile depth reading less
than the specified threshold
rd = No. of 10m intervals in the right wheelpath with a mean profile depth reading less
than the specified threshold
l = No. of 10m intervals in the left wheelpath with a mean profile depth reading
r = No. of 10m intervals in the right wheelpath with a mean profile depth reading
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 95 of 157
5 5.8 Rutting
5.8.1 Data Analysis
Rutting is to be analysed using the high speed data collected in accordance with Appendix
(WBoPDC Local Roads) 5.1.
The analysis shall exclude the following:
a) Records for roads owned by parties other than WBoPDC (e.g. Crown, Tauranga City
Council, Maori or privately-owned);
b) Records with the following event codes:
A (Post-Survey Added Value)
D (Detour Route)
H (Speed Humps)
U (Unsealed road begins/ends)
W (Road Works)
X (Railway crossings)
c) Records for roads listed in Appendix (WBoPDC Local Roads) 5.6, Table 5.6.1
The analysis shall be completed using current high speed data only.
5.8.2 Calculations
The Percent Rut Depth > Threshold KPM results are calculated from the wheelpath rut
depth data using the following formula:
𝑃𝑒𝑟𝑐𝑒𝑛𝑡 𝑅𝑢𝑡 𝐷𝑒𝑝𝑡 > 𝑇𝑟𝑒𝑠𝑜𝑙𝑑 = 𝑑𝑙 + 𝑑𝑟
𝑙 + 𝑟× 100%
where:
dl = Sum of length in the left wheelpath in each lane with rut depth greater than the
specified threshold. To be calculated by summing LWP_30, LWP_40, LWP_50,
LWP_60, LWP_100 and LWP_100plus bins in the high speed data rutting table
dr = Sum of length in the right wheelpath in each lane with rut depth greater than the
specified threshold. To be calculated by summing RWP_30, RWP_40, RWP_50,
RWP_60, RWP_100 and RWP_100plus bins in the high speed data rutting table
l = Sum of length of left wheelpath in each lane
r = Sum of length of right wheelpath in each lane
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 96 of 157
5 5.9 Surfacing Defects Index (Sealed)
5.9.1 Data Analysis
Pothole, Scabbing, Edge Break and Shoving defects on sealed roads are to be analysed
using the current survey RAMM Rating Data held in the rating table in RAMM, and
collected in accordance with Appendix (WBoPDC Local Roads) 5.3.
Rutting and Flushing defects on sealed roads are to be analysed using the current survey
high speed data held in RAMM (hsd_rutting and hsd_texture tables respectively), and
collected in accordance with Appendix (WBoPDC Local Roads) 5.1.
The analysis shall exclude the following:
a) Records for roads owned by parties other than WBoPDC (e.g. Crown, Tauranga City
Council, Maori or privately-owned);
5.9.2 Calculations
The Surfacing Defects Index (Sealed) KPM is calculated using the following formula:
𝑆𝑢𝑟𝑓𝑎𝑐𝑖𝑛𝑔 𝐷𝑒𝑓𝑒𝑐𝑡𝑠 𝐼𝑛𝑑𝑒𝑥 𝑆𝑒𝑎𝑙𝑒𝑑 = (𝑊𝑒𝑖𝑔𝑡𝑒𝑑 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝐼𝑛𝑑𝑒𝑥 × 𝑇𝑟𝑒𝑎𝑡𝑚𝑒𝑛𝑡 𝐿𝑒𝑛𝑔𝑡)𝑆𝑒𝑎𝑙𝑒𝑑 𝑡𝑟𝑒𝑎𝑡𝑚𝑒𝑛𝑡 𝑙𝑒𝑛𝑔𝑡 𝑠
𝑇𝑟𝑒𝑎𝑡𝑚𝑒𝑛𝑡 𝐿𝑒𝑛𝑔𝑡𝑆𝑒𝑎𝑙𝑒𝑑 𝑡𝑟𝑒𝑎𝑡𝑚𝑒𝑛𝑡 𝑙𝑒𝑛𝑔𝑡 𝑠
where:
The Weighted Condition Index for each treatment length is calculated using the
following formula, and rounded to the nearest whole integer with a maximum value of
5:
𝑊𝑒𝑖𝑔𝑡𝑒𝑑 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝐼𝑛𝑑𝑒𝑥 = (𝐸𝑞𝑢𝑖𝑣𝑎𝑙𝑒𝑛𝑡 𝐹𝑎𝑢𝑙𝑡𝑠 × 𝐹𝑎𝑢𝑙𝑡 𝑊𝑒𝑖𝑔𝑡)
6
1
where:
1. The Fault Weight for each Fault Type is listed in the following table:
Table 5.9.2: Sealed Road Fault Type and Weight
No. Fault Type Fault Weight
1 Potholes 55%
2 Edge Break 10%
3 Shoving 15%
4 Scabbing 5%
5 Rutting 10%
6 Flushing 5%
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 97 of 157
5 2. Equivalent Faults for the Pothole Fault Type are calculated using the following
formula:
𝐸𝑞𝑢𝑖𝑣𝑎𝑙𝑒𝑛𝑡 𝐹𝑎𝑢𝑙𝑡𝑠 = 𝑁𝑜. 𝑜𝑓 𝑃𝑜𝑡𝑜𝑙𝑒𝑠 ×50
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
3. Equivalent Faults for the Edge Break Fault Type are calculated using the
following formula:
𝐸𝑞𝑢𝑖𝑣𝑎𝑙𝑒𝑛𝑡 𝐹𝑎𝑢𝑙𝑡𝑠 = 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝐸𝑑𝑔𝑒 𝐵𝑟𝑒𝑎𝑘 ×50
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
4. Equivalent Faults for the Shoving Fault Type are calculated using the following
formula:
𝐸𝑞𝑢𝑖𝑣𝑎𝑙𝑒𝑛𝑡 𝐹𝑎𝑢𝑙𝑡𝑠 = 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑆𝑜𝑣𝑖𝑛𝑔 ×50
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
5. Equivalent Faults for the Scabbing Fault Type are calculated using the following
formula:
𝐸𝑞𝑢𝑖𝑣𝑎𝑙𝑒𝑛𝑡 𝐹𝑎𝑢𝑙𝑡𝑠 = 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑆𝑐𝑎𝑏𝑏𝑖𝑛𝑔 ×7
𝑊𝑖𝑑𝑡×
50
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
where width is the weighted average carriageway width for the inspection length.
6. Equivalent Faults for the Rutting Fault Type are calculated using the following
formula:
𝐸𝑞𝑢𝑖𝑣𝑎𝑙𝑒𝑛𝑡 𝐹𝑎𝑢𝑙𝑡𝑠 = 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑅𝑢𝑡𝑡𝑖𝑛𝑔 ×50
𝑇𝑟𝑒𝑎𝑡𝑚𝑒𝑛𝑡 𝐿𝑒𝑛𝑔𝑡 (𝑚)
where the length of rutting is the total length of rutting greater than 30mm in all
wheelpaths within the treatment length. This can be calculated by summing
LWP_40, LWP_50, LWP_60, LWP_100 and LWP_100plus bins, and equivalent
RWP bins in the high speed data rutting table. Event codes A, D, H, W, X and U
are to be excluded.
7. Equivalent Faults for the Flushing Fault Type are calculated using the following
formula:
𝐸𝑞𝑢𝑖𝑣𝑎𝑙𝑒𝑛𝑡 𝐹𝑎𝑢𝑙𝑡𝑠 = 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝐹𝑙𝑢𝑠𝑖𝑛𝑔 ×50
𝑇𝑟𝑒𝑎𝑡𝑚𝑒𝑛𝑡 𝐿𝑒𝑛𝑔𝑡 (𝑚)
where the length of flushing is the total length with sand circular diameter texture
≥ 275mm in both wheelpaths within the treatment length. This can be calculated
by summing LWP_300, LWP_400 and LWP_400plus bins, and equivalent RWP
bins, in the HSD Texture table. Event codes A, D, H, W, X and U are to be
excluded.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 98 of 157
5 In addition to the Surfacing Defects Index (Sealed), the Contractor shall also report:
The total treatment length with Weighted Condition Index ≥ 4; and
The total treatment length with Weighted Condition Index = 5.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 99 of 157
5 5.10 Surfacing Defects Index (Unsealed)
5.10.1 Data Analysis
Surfacing defects on unsealed roads are to be analysed using the RAMM data collected in
accordance with Appendix (WBoPDC Local Roads) 5.3.
The analysis shall exclude the following:
b) Records for roads owned by parties other than WBoPDC (e.g. Crown, Tauranga City
Council, Maori or privately-owned)
5.10.2 Calculations
The Surfacing Defects Index (Unsealed) KPM is calculated using the following formula:
𝑆𝑢𝑟𝑓𝑎𝑐𝑖𝑛𝑔 𝐷𝑒𝑓𝑒𝑐𝑡𝑠 𝐼𝑛𝑑𝑒𝑥 𝑈𝑛𝑠𝑒𝑎𝑙𝑒𝑑 = (𝑊𝑒𝑖𝑔𝑡𝑒𝑑 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝐼𝑛𝑑𝑒𝑥 × 𝑆𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡)𝐴𝑙𝑙 𝑢𝑛𝑠𝑒𝑎𝑙𝑒𝑑 𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑠
𝑆𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡𝐴𝑙𝑙 𝑢𝑛𝑠𝑒𝑎𝑙𝑒𝑑 𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑠
where:
The Weighted Condition Index for each rating section is calculated using the
following formula:
𝑊𝑒𝑖𝑔𝑡𝑒𝑑 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝐼𝑛𝑑𝑒𝑥 = 1.75 × (𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝐹𝑎𝑢𝑙𝑡 𝑊𝑒𝑖𝑔𝑡)
9
1
where:
1. The Condition Rating for each Fault Type are listed in the following table:
Table 5.10.2 a): Unsealed Road Fault Type Condition Rating
No. Fault Type Condition Rating
1 2 3 4 5
1 Potholes 0 0≤x<2 2≤x<25 25≤x<50 x ≥50
2 Corrugations 0 0≤x<4 4≤x<50 50≤x<97 x ≥97
3 Graded Width <0.25 0.25≤x<0.5 0.5≤x<0.75 0.75≤x<1 x ≥1
4 Surface Water Channel
0 0≤x<50 50≤x<75 75≤x<100 x =100
5 Rutting 0 0≤x<5 5≤x<50 50≤x<100 x =100
6 Cross-section 0 1 2 3 4
7 Scour 0 0≤x<3 3≤x<50 50≤x<95 x ≥95
8 Shoving 0 0≤x<3 3≤x<9 9≤x<15 x ≥15
9 Loose Aggregate 0 0≤x<50 50≤x<100 100≤x<200 x ≥200
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 100 of 157
5 2. The Condition Rating and Fault Weight for each Fault Type are listed in the
following table:
Table 5.10.2: Unsealed Road Fault Type Weighting
No. Fault Type Fault Weighting
1 Potholes 20%
2 Corrugations 20%
3 Graded Width 10%
4 Surface Water Channel 5%
5 Rutting 5%
6 Cross-section 5%
7 Scour 10%
8 Shoving 20%
9 Loose Aggregate 5%
3. The value for the Pothole Fault Type is calculated using the following formula:
𝑥 = (𝑁𝑜. 𝑜𝑓 𝑃𝑜𝑡𝑜𝑙𝑒𝑠 × 𝑃𝑜𝑡𝑜𝑙𝑒 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔) ×100
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
where the pothole weight is based on pothole diameter and depth as listed in the
following table:
Table 5.10.2 c): Pothole Weighting
Pothole Depth Pothole Diameter
100mm to 300mm
300mm to 600mm
600mm to 900mm
> 900mm
25mm to 50mm 1 1 2 3
50mm to 100mm 1 2 3 3
>100mm 1 2 3 3
4. The value for the Corrugations Fault Type is calculated using the following
formula:
𝑥 = 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝐶𝑜𝑟𝑟𝑢𝑔𝑎𝑡𝑖𝑜𝑛 × 𝐶𝑜𝑟𝑟𝑢𝑔𝑎𝑡𝑖𝑜𝑛 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔 ×100
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
where the corrugation weight is based on corrugation depth as listed in the
following table:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 101 of 157
5 Table 5.10.2 d): Corrugations Weighting
Corrugation Depth Corrugation Weighting
25mm to 75mm 1
> 75mm 2
5. The value for the Graded Width Fault Type is calculated using the following
formula:
𝑥 = 𝑊𝑖𝑑𝑡 𝑓𝑟𝑜𝑚 𝑅𝐴𝑀𝑀 𝐶𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝑇𝑎𝑏𝑙𝑒 − 𝑀𝑒𝑎𝑠𝑢𝑟𝑒𝑑 𝑊𝑖𝑑𝑡
6. The value for the Surface Water Channel Fault Type is calculated using the
following formula:
𝑥 = (𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝐼𝑛𝑎𝑑𝑒𝑞𝑢𝑎𝑡𝑒 𝑆𝑊𝐶 𝐿𝐻𝑆 + 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝐼𝑛𝑎𝑑𝑒𝑞𝑢𝑎𝑡𝑒 𝑆𝑊𝐶 𝑅𝐻𝑆) ×100
2 × 𝑆𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡
7. The value for the Rutting Fault Type is calculated using the following formula:
𝑥 = 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑅𝑢𝑡𝑡𝑖𝑛𝑔 > 30𝑚𝑚 𝑑𝑒𝑒𝑝 ×100
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
8. The value for the Cross-section Fault Type is as recorded through RAMM
condition rating.
9. The value for the Scour Fault Type is calculated using the following formula:
𝑥 = 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑆𝑐𝑜𝑢𝑟 (𝑚2) ×100
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
10. The value for the Shoving Fault Type is calculated using the following formula:
𝑥 = 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑆𝑜𝑣𝑖𝑛𝑔 ×100
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
11. The value for the Loose Aggregate Fault Type is calculated using the following
formula:
𝑥 = (𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝐿𝑜𝑜𝑠𝑒 𝐴𝑔𝑔𝑟𝑒𝑔𝑎𝑡𝑒 × 𝐿𝑜𝑜𝑠𝑒 𝐴𝑔𝑔𝑟𝑒𝑔𝑎𝑡𝑒 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔) ×100
𝐼𝑛𝑠𝑝𝑒𝑐𝑡𝑖𝑜𝑛 𝐿𝑒𝑛𝑔𝑡 (𝑚)
where the loose aggregate weight is based on loose aggregate depth as listed in
the following table:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 102 of 157
5 Table 5.10.2 e): Loose Aggregate Weighting
Loose Aggregate Depth Weighting
< 50mm 0
50mm to 100mm 1
> 100mm 2
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 103 of 157
5 5.11 Average Remaining Surfacing Life
5.11.1 Data Analysis
Average Remaining Surfacing Life is to be analysed in years using the RAMM data
collected in accordance with Appendix (WBoPDC Local Roads) 5.3.
The analysis shall exclude the following:
a) All surfacing types with a width less than 0.5m and/or a length less than 10m
5.11.2 Calculations
The Average Remaining Surfacing Life KPM is calculated using the following formula:
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑆𝑢𝑟𝑓𝑎𝑐𝑖𝑛𝑔 𝐿𝑖𝑓𝑒 = 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑆𝑢𝑟𝑓𝑎𝑐𝑖𝑛𝑔 × 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝐿𝑖𝑓𝑒
𝑇𝑜𝑡𝑎𝑙 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑆𝑢𝑟𝑓𝑎𝑐𝑖𝑛𝑔
The Remaining Life of a surfacing length is calculated using the following formula:
𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝐿𝑖𝑓𝑒 = 𝐸𝑥𝑝𝑖𝑟𝑦 𝐷𝑎𝑡𝑒 − 01/07/𝑦𝑒𝑎𝑟
365
where:
Year is the current year of assessment
Expiry Date is the surfacing date plus the Design Life specified in the following table:
Table 5.11.2: Surfacing Type Design Life
Surfacing Type Grade Pavement Use*
1 2 3 4 5 6 7
Texturising Seal 6 6 5 4 3 2 1 1
Texturising Seal 5 8 7 6 5 4 3 2
Texturising Seal 4 12 10 8 7 6 5 4
Texturising Seal 3 14 12 10 9 8 7 6
Void Fill Seal 6 6 5 4 3 2 1 1
Void Fill Seal 5 8 7 6 5 4 3 2
Void Fill Seal 4 12 10 8 7 6 5 4
Void Fill Seal 3 14 12 10 9 8 7 6
Locking Coat Seal 6 6 5 4 3 2 1 1
Locking Coat Seal 5 8 7 6 5 4 3 2
First Coat Seal: Single Coat 6 1 1 1 1 1 1 1
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 104 of 157
5 Table 5.11.2: Surfacing Type Design Life
Surfacing Type Grade Pavement Use*
1 2 3 4 5 6 7
First Coat Seal: Single Coat 5 1 1 1 1 1 1 1
First Coat Seal: Single Coat 4 3 2 1 1 1 1 1
First Coat Seal: Single Coat 3 4 3 2 1 1 1 1
First Coat Seal: Two Coat 4/6 6 4 3 2 2 1 1
First Coat Seal: Two Coat 3/5 8 6 5 4 3 2 1
First Coat Seal: Two Coat 2/4 10 8 6 5 4 3 2
Second Coat Seal: Single Coat 6 6 5 4 3 2 1 1
Second Coat Seal: Single Coat 5 8 7 6 5 4 3 2
Second Coat Seal: Single Coat 4 12 10 8 7 6 5 4
Second Coat Seal: Single Coat 3 14 12 10 9 8 7 6
Second Coat Seal: Single Coat 2 16 14 12 11 10 9 8
Second Coat Seal: Two Coat 4/6 14 12 10 9 8 6 4
Second Coat Seal: Two Coat 3/5 16 14 12 11 10 8 6
Second Coat Seal: Two Coat 2/4 18 16 14 13 12 10 9
Reseals: Single Coat 6 6 5 4 3 2 1 1
Reseals: Single Coat 5 8 7 6 5 4 3 2
Reseals: Single Coat 4 12 10 8 7 6 5 4
Reseals: Single Coat 3 14 12 10 9 8 7 6
Reseals: Single Coat 2 16 14 12 11 10 9 8
Reseals: Two Coat 4/6 14 12 10 9 8 6 4
Reseals: Two Coat 3/5 16 14 12 11 10 8 6
Reseals: Two Coat 2/4 18 16 14 13 12 10 9
Asphaltic Mixes: Thin Asphaltic Concrete - 12 11 10 9 8 7 6
Asphaltic Mixes: Structural Asphaltic Concrete - 20 20 19 19 18 17 16
Asphaltic Mixes: Open Graded Porous Asphalt - 12 11 10 9 8 7 6
Asphaltic Mixes: Open Graded Emulsion Mix - 12 11 10 9 8 7 6
Portland Cement Concrete - 60 60 50 50 40 40 40
Slurry Seal - 8 7 6 5 4 3 2
Prime and Seal - 7 6 5 4 3 2 1
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 105 of 157
5 Table 5.11.2: Surfacing Type Design Life
Surfacing Type Grade Pavement Use*
1 2 3 4 5 6 7
Metal Running Course - 3 2 1 1 1 1 1
BOLIDT Polyurethane Mix - 18 16 14 12 11 10 8
Bicouche/Sandwich - 14 12 10 9 8 6 4
Interlocking concrete blocks 50 50 50 50 50 50 50
Note that the Pavement Use* is as defined in RAMM and may not be directly linked to the
road group number.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 106 of 157
5 5.12 Bridge Structures
All structural bridge maintenance and renewals (excluding deck replacement, waterway,
substructure, abutment and foundation renewals) are included within the Bridge Structures
KPMs.
For the avoidance of doubt, the following outlines a range of typical activities that may be
required and identifies the party responsible for the implementation of each activity. In the
event that an activity is required and it is not listed, the party responsible for the
implementation shall be in accordance with the intent of the table.
Table 5.12: Typical Bridge Activity and Responsibility
Component Group
Contractor’s Maintenance Responsibility
Principal’s Renewal and Capital Responsibility
General Appearance
Repairing accident damage such as guard rails, signs, general cleaning and painting
Superstructure Concrete
Crack repairs, concrete spalling Replace decks
Superstructure Steel
Cleaning and painting, tightening bolts and fixings
Replace beams
Superstructure Timber
Cleaning and painting, tightening bolts and fixings, replacing deck,
Replace main beams
Foundations and Substructure
Monitor scour and notify Principal of any work required
Erosion of abutment support
Scour and Waterway
Maintaining vegetation clear of waterway within 50 metres of bridge, removing accumulated debris on pile caps and abutments
Replacing concrete lining of culvert, erosion of a bank adjacent to abutments, providing concrete lining to invert of Armco culverts weakened by corrosion
Scour at abutments caused by stormwater runoff from the road surface or associated
drainage system is not classed as waterway scour and is the Contractor‟s maintenance
responsibility.
5.12.1 Component Condition Rating
The Component Condition Rating KPM is calculated using the following formula:
𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.0 × 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 107 of 157
5 where:
The Condition Rating from 1 to 5 (or 0 if not able to be rated) is assigned to each of
the thirty one individual bridge components for each bridge, in accordance with the
following documents, during each required structural inspection:
1. NZTA Bridge Inspection and Maintenance Manual
2. WBoPDC Bridge-condition-form01
3. WBoPDC Bridge-WordPictureConditon-form01
5.12.2 Profile
The Bridge Profile KPM is calculated using the following formula:
𝑃𝑟𝑜𝑓𝑖𝑙𝑒 = 1.5 × 0.5 × 𝐵𝑟𝑖𝑑𝑔𝑒 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 + 0.25 × 𝐵𝑟𝑖𝑑𝑔𝑒 𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Bridge Condition Rating is calculated using the following formula:
𝐵𝑟𝑖𝑑𝑔𝑒 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐺𝑟𝑜𝑢𝑝 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐺𝑟𝑜𝑢𝑝 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔
6
1
where:
1. The Component Group Condition Rating is the average condition rating of each
component group.
Each of the thirty-one individual bridge components are categorised into one of
the following six component groups:
a) General appearance
b) Superstructure concrete
c) Superstructure steel
d) Superstructure timber
e) Foundations and substructure
f) Scour and waterway
2. The Component Group Weighting is specified in the following table:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 108 of 157
5 Table 5.12.2 a): Component Group Weighting
Component Group
Bridge Type
Concrete Bridge
Concrete Deck/ Steel
Beams
Timber Deck/ Steel
beams
Timber Deck/
Timber Beams
Armco Culvert
General Appearance
20% 20% 20% 20% 20%
Superstructure Concrete
30% 15% - - -
Superstructure Steel
- 15% 15% - 30%
Superstructure Timber
- - 15% 30% -
Foundations and Substructure
20% 20% 20% 20% 20%
Scour and Waterway
30% 30% 30% 30% 30%
The Bridge Risk Rating is calculated using the following formula:
𝐵𝑟𝑖𝑑𝑔𝑒 𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔 = 𝐵𝑟𝑖𝑑𝑔𝑒 𝑃𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 + 𝐵𝑟𝑖𝑑𝑔𝑒 𝐶𝑜𝑛𝑠𝑒𝑞𝑢𝑒𝑛𝑐𝑒 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒
where:
1. The probability of failure for each bridge is calculated using the following
formula:
𝐵𝑟𝑖𝑑𝑔𝑒 𝑃𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 = (𝐹𝑎𝑐𝑡𝑜𝑟 𝑃𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 × 𝐹𝑎𝑐𝑡𝑜𝑟 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
3
1
where:
a) The Factor Probability of Failure is rated in accordance with the following
documents during each required structural inspection:
NZTA Bridge Inspection and Maintenance Manual
WBoPDC Bridge_Risk-Rating_form01
WBoPDC Bridge_WordPictureRisk_form01
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 109 of 157
5 b) The Factor Weighting is specified in the following table:
Table 5.12.2 b): Probability of Failure Factor Weighting
No. Factor Factor Weighting
1 Waterway 50%
2 Structural 20%
3 Approach 30%
2. The consequence of failure for each bridge is calculated using the following
formula:
𝐵𝑟𝑖𝑑𝑔𝑒 𝐶𝑜𝑛𝑠𝑒𝑞𝑢𝑒𝑛𝑐𝑒 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 = (𝐹𝑎𝑐𝑡𝑜𝑟 𝐶𝑜𝑛𝑠𝑒𝑞𝑢𝑒𝑛𝑐𝑒 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 × 𝐹𝑎𝑐𝑡𝑜𝑟 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
4
1
where:
a) The Factor Consequence of Failure is rated in accordance with the following
documents during each required structural inspection:
NZTA Bridge Inspection and Maintenance Manual
WBoPDC Bridge_Risk-Rating_form01
WBoPDC Bridge_WordPictureRisk_form01
b) The Factor Weighting is specified in the following table:
Table 5.12.2 c): Consequence of Failure Factor Weighting
No. Factor Factor Weighting
1 Impact on Road User 25%
2 Impact on Property 35%
3 Impact on Environment 15%
4 Reinstatement Cost 25%
5.12.3 Stock Index
The Stock Index KPM is calculated using the following formula:
𝐵𝑟𝑖𝑑𝑔𝑒 𝑆𝑡𝑜𝑐𝑘 𝐼𝑛𝑑𝑒𝑥 = 𝐵𝑟𝑖𝑑𝑔𝑒 𝑃𝑟𝑜𝑓𝑖𝑙𝑒𝑛
1
𝑛
where:
n = number of bridges for which a profile is derived.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 110 of 157
5 5.13 Drainage Structures: Culverts
5.13.1 Component Condition Rating
Each culvert is categorised into the following four components:
1. Pipe
2. Inlet
3. Outlet
4. Associated structures (e.g. flumes, drop structures, grates)
The Component Condition Rating KPM is calculated using the following formula:
𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.0 × 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Condition Rating from 1 to 5 (or 0 if not able to be rated) is assigned to each of
the four components for each culvert, in accordance with the following documents,
during each required structural inspection:
1. WBoPDC Culvert Rating Standards and Definitions.
5.13.2 Profile
The culvert Profile KPM is determined using the following table:
Table 5.13.2 a): Drainage Structure Profile
Condition Rating Risk Rating
1 2 3 4 5
1 1.0 1.5 2.0 2.5 3.0
2 1.5 2.0 2.2 2.6 3.5
3 2.0 2.2 3.0 3.5 4.0
4 2.5 2.6 3.5 4.5 5.0
5 3.0 3.5 4.0 5.0 5.0
where:
The Condition Rating is calculated using the following formula:
𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = (𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
4
1
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 111 of 157
5 where:
1. The Component Condition Rating is calculated in accordance with Appendix
(WBoPDC Local Roads) 5.13.1
2. The Component Weighting is specified in the following table:
Table 5.13.2 b): Culvert Component Weighting
Component Component Weighting
Pipe 40%
Inlet 20%
Outlet 20%
Associated structures (e.g. flumes, drop structures, grates) 20%
The Risk Rating is determined using the following table:
Table 5.13.2 c): Culvert Risk Rating
Culvert Risk Rating Total Component Risk Rating
1 x 3
2 3 < x 6
3 6 < x 13
4 13 < x 23
5 x >23
where:
1. The Total Component Risk Rating is the sum of all component risk ratings for
each culvert rated in accordance with the following documents during each
required structural inspection:
WBoPDC Culvert Rating Standards and Definitions
5.13.3 Stock Index
The Stock Index KPM is calculated using the following formula:
𝐶𝑢𝑙𝑣𝑒𝑟𝑡 𝑆𝑡𝑜𝑐𝑘 𝐼𝑛𝑑𝑒𝑥 = 𝐶𝑢𝑙𝑣𝑒𝑟𝑡 𝑃𝑟𝑜𝑓𝑖𝑙𝑒𝑛
1
𝑛
where:
n = the total number of culverts for which a profile is developed.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 112 of 157
5 5.14 Drainage Structures: Surface Water Channels (Lined)
Data is to be taken from the following tables in RAMM including:
Surface Water Channel excluding the following channel types:
a) SWCS
b) SWCD
Sealed Rating. The latest rating data for the following fault types:
a) Surfaced Broken (LHS & RHS)
b) Surfaced High Lip (LHS & RHS)
c) Surfaced Broken Surface (LHS & RHS)
d) Surfaced Uphill Grade (LHS & RHS)
Rating data and surface water channel (lined) items shall be summarised to carriageway
lengths by grouping by Road ID and Carriageway start m, to give the following
information:
Total length of surfaced channel items per carriageway section
Total of each fault type per carriageway section
Where the length of surface water channel (lined) in any carriageway length is zero the
carriageway length is invalid and should not be considered with respect to the surface
water channel (lined) KPM.
5.14.1 Component Condition Rating
Surface water channel (lined) faults are categorised into the following four groups:
1. Broken channel
2. High lip
3. Broken surface
4. Uphill grade
The Component Condition Rating KPM for each valid carriageway length is calculated
using the following formula:
𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.35 × 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 113 of 157
5 where:
The Condition Rating is determined using the following table:
Table 5.14.1: Surface Water Channel (Lined) Condition Rating
No. Fault Type Condition Rating
1 2 3 4 5
1 Broken Channel 0 0<x 0.4 0.4<x 8.0 8.0<x 15.0 >15.0
2 High Lip 0 0<x 0.3 0.3<x 6.0 6.0<x 11.0 >11.0
3 Broken Surface 0 0<x 0.3 0.3<x 11.0 11.0<x 22.0 >22.0
4 Uphill Grade 0 0 <x 0.3 0.3<x 2.0 2.0<x 4.0 >4.0
where:
𝑥 = 100 ×𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑑𝑒𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑤𝑎𝑡𝑒𝑟 𝑐𝑎𝑛𝑛𝑒𝑙 (𝑙𝑖𝑛𝑒𝑑)
𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑤𝑎𝑡𝑒𝑟 𝑐𝑎𝑛𝑛𝑒𝑙 (𝑙𝑖𝑛𝑒𝑑)
5.14.2 Profile
The surface water channel (lined) Profile KPM for each valid carriageway length is
determined using Table 5.13.2 a).
where:
The Condition Rating is calculated using the following formula and rounded to the
nearest whole integer, with a maximum value of 5:
𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = (𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
4
1
where:
1. The Component Condition Rating is calculated in accordance with Appendix
(WBoPDC Local Roads) 5.14.1
2. The Component Weighting is specified in the following table:
Table 5.14.2 b): Surface Water Channel (Lined) Component Weighting
Component Component Weighting
Broken Channel 20%
High Lip 30%
Broken Surface 30%
Uphill Grade 20%
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 114 of 157
5 The Risk Rating is determined using the following table:
Table 5.14.2 c): Surface Water Channel (Lined) Risk Rating
Surface Water Channel (Lined) Risk Rating
Total Category Risk Rating
1 x 1
2 1 < x 7
3 7 < x 13
4 13 < x 17
5 x >17
where the Total Category Risk Rating is the sum of all category risk ratings rated in
accordance with the following table:
Table 5.14.2 c): Surface Water Channel (Lined) Category Risk Rating
No. Category Category Risk Rating
0 2 4 7 10
1 Channel grade Level 5% 10%
2 Accessways / Obstructions
No obstructions Minor obstructions
Major obstructions
3 Pavement / Soils Not cracked / no signs of scouring
Cracks up to 10mm / some
localised scouring
Major disjointing / extensive
scouring evident
4 Flooding No flooding Water ponds adjacent to the
road
Water ponding encroaches into the wheel path
Water ponds across the road but still drivable
Impassable
0 4 8 14 20
5 Scale of property damage
Property damage will
not occur
Property damage will
be low
Property damage will be moderate
Property damage will
be high
Property damage will be extreme
5.14.3 Stock Index
The Stock Index KPM is calculated using the following formula:
𝑆𝑡𝑜𝑐𝑘 𝐼𝑛𝑑𝑒𝑥 = (𝑆𝑢𝑟𝑓𝑎𝑐𝑒 𝑊𝑎𝑡𝑒𝑟 𝐶𝑎𝑛𝑛𝑒𝑙 𝐿𝑖𝑛𝑒𝑑 𝑃𝑟𝑜𝑓𝑖𝑙𝑒 × 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑆𝑢𝑟𝑓𝑎𝑐𝑒 𝑊𝑎𝑡𝑒𝑟 𝐶𝑎𝑛𝑛𝑒𝑙 𝐿𝑖𝑛𝑒𝑑) 𝑡
1
𝑇𝑜𝑡𝑎𝑙 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑆𝑢𝑟𝑓𝑎𝑐𝑒 𝑊𝑎𝑡𝑒𝑟 𝐶𝑎𝑛𝑛𝑒𝑙 (𝐿𝑖𝑛𝑒𝑑)
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 115 of 157
5 where:
t = the total number of valid carriageway lengths for which a profile has been
developed.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 116 of 157
5 5.15 Drainage Structures: Surface Water Channels (Unlined)
Data is to be taken from the following tables in RAMM:
Surface Water Channel including only the following channel types:
a) SWCS (Shallow, <200mm below seal edge)
b) SWCD (Deep, >200mm below seal edge)
Sealed Rating. The latest rating data for the following fault types:
a) Earth SWC blocked (LHS & RHS)
b) Earth SWC inadequate (LHS & RHS)
c) Earth SWC ineffective shoulder (LHS & RHS)
Carriageway table
a) Terrain type
b) Length of each carriageway section
c) Pavement type (sealed)
Rating data and surface water channel (unlined) items shall be summarised to carriageway
lengths by grouping by Road ID and Carriageway start m, to give the following
information:
Total length of earth surface water channel items per carriageway section
Total of each fault type per carriageway section
Where the length of surface water channel (unlined) in any carriageway length is zero the
carriageway length is invalid and should not be considered with respect to the surface
water channel (unlined) KPM.
5.15.1 Component Condition Rating
Surface water channel (lined) faults are categorised into the following four groups:
1. Blocked
2. Inadequate, including where there is no channel and inadequate drainage
3. Ineffective shoulder
The Component Condition Rating KPM for each valid carriageway length is calculated
using the following formula:
𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.5 × 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 117 of 157
5 where:
The Condition Rating is determined using the following table:
Table 5.15.1: Surface Water Channel (Unlined) Condition Rating
No. Fault Type Condition Rating
1 2 3 4 5
1 Blocked x<0 0<x 0.15 0.15<x 1.1 1.1<x 2.0 x>2.0
2 Inadequate y<0 0<y 8 8<y 50 50<y 95 y>95
3 Ineffective Shoulder
y<0 0<y 0.75 0.75<y 35 35<y 70 y>70
where:
𝑥 = 100 ×𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑑𝑒𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑤𝑎𝑡𝑒𝑟 𝑐𝑎𝑛𝑛𝑒𝑙 (𝑢𝑛𝑙𝑖𝑛𝑒𝑑)
𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑤𝑎𝑡𝑒𝑟 𝑐𝑎𝑛𝑛𝑒𝑙 (𝑢𝑛𝑙𝑖𝑛𝑒𝑑)
𝑦 = 100 ×𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑑𝑒𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑤𝑎𝑡𝑒𝑟 𝑐𝑎𝑛𝑛𝑒𝑙 (𝑢𝑛𝑙𝑖𝑛𝑒𝑑)
2 × 𝑐𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝑐𝑒𝑛𝑡𝑟𝑒𝑙𝑖𝑛𝑒 𝑙𝑒𝑛𝑔𝑡 − 𝐿𝑒𝑛𝑔𝑡 𝑜𝑓 𝑠𝑢𝑟𝑓𝑎𝑐𝑒 𝑤𝑎𝑡𝑒𝑟 𝑐𝑎𝑛𝑛𝑒𝑙 (𝑙𝑖𝑛𝑒𝑑)
5.15.2 Profile
The surface water channel (unlined) Profile KPM for each valid carriageway length is
determined using Table 5.13.2 a).
where:
The Condition Rating is calculated using the following formula and rounded to the
nearest whole integer, with a maximum value of 5:
𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔3
1
3
where the Component Condition Rating is calculated in accordance with Appendix
(WBoPDC Local Roads) 5.15.1
The Risk Rating is calculated using the following formula and rounded to the nearest
whole integer, with a maximum value of 5:
𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔 = 𝐶𝑎𝑡𝑒𝑔𝑜𝑟𝑦 𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔3
1
3
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 118 of 157
5 where the Category Risk Rating is determined using the following table:
Table 5.15.2: Category Risk Rating
No. Category Category Risk Rating
1 2 3 4 5
1 ADT <100 100 - 500 >500
2 Terrain L H M
3 Width > 7 5 - 7 <5
5.15.3 Stock Index
The Stock Index KPM is calculated using the following formula:
𝑆𝑡𝑜𝑐𝑘 𝐼𝑛𝑑𝑒𝑥 = (𝑆𝑢𝑟𝑓𝑎𝑐𝑒 𝑊𝑎𝑡𝑒𝑟 𝐶𝑎𝑛𝑛𝑒𝑙 𝑈𝑛𝑙𝑖𝑛𝑒𝑑 𝑃𝑟𝑜𝑓𝑖𝑙𝑒 × 𝐶𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝐿𝑒𝑛𝑔𝑡)𝑡
1
𝐶𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝐿𝑒𝑛𝑔𝑡𝑡1
where:
t = the total number of valid carriageway lengths for which a profile has been
developed.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 119 of 157
5 5.16 Other Structures
5.16.1 Component Condition Rating
Each other structure is categorised into the following five components:
1. Overall appearance
2. Wall drainage
3. Vehicle barriers / pedestrian handrails
4. Wall structure
5. Wall foundations
The Component Condition Rating KPM is calculated using the following formula:
𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.0 × 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Condition Rating from 1 to 5 (or 0 if not able to be rated) is assigned to each of
the five components for each other structure, in accordance with the following
documents, during each required structural inspection:
1. NZTA Bridge Inspection and Maintenance Manual
2. WBoPDC Retaining Wall-WordPictureConditon-form01
3. WBoPDC Retaining Wall-ConditionRisk-form01
5.16.2 Profile
The Other Structure Profile KPM is calculated using the following formula:
𝑃𝑟𝑜𝑓𝑖𝑙𝑒 = 1.5 × 0.6 × 𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 + 0.2 × 𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Other Structure Condition Rating is calculated using the following formula:
𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = (𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
5
1
where:
1. The Component Condition Rating is calculated in accordance with Appendix
(WBoPDC Local Roads) 5.16.1
2. The Component Weighting is specified in the following table:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 120 of 157
5 Table 5.16.2 a): Other Structure Component Weighting
Component Component Weighting
Overall Appearance 10%
Wall Drainage 15%
Vehicle Barriers / Pedestrian Handrails 15%
Wall Structure 30%
Wall Foundations 30%
The Other Structure Risk Rating is calculated using the following formula:
𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔= 𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑃𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 + 𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝐶𝑜𝑛𝑠𝑒𝑞𝑢𝑒𝑛𝑐𝑒 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒
where:
1. The probability of failure for each other structure is calculated using the
following formula:
𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑃𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 = 1.2 × (𝐹𝑎𝑐𝑡𝑜𝑟 𝑃𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 × 𝐹𝑎𝑐𝑡𝑜𝑟 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
2
1
where:
a) The Factor Probability of Failure is rated in accordance with the following
documents during each required structural inspection:
WBoPDC Retaining Wall_WordPictureRisk_form01
b) The Factor Weighting is specified in the following table:
Table 5.16.2 b): Probability of Failure Factor Weighting
No. Factor Factor Weighting
1 Structural 40%
2 Slope Stability 60%
2. The consequence of failure for each bridge is calculated using the following
formula:
𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝐶𝑜𝑛𝑠𝑒𝑞𝑢𝑒𝑛𝑐𝑒 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 = 1.2 × (𝐹𝑎𝑐𝑡𝑜𝑟 𝐶𝑜𝑛𝑠𝑒𝑞𝑢𝑒𝑛𝑐𝑒 𝑜𝑓 𝐹𝑎𝑖𝑙𝑢𝑟𝑒 × 𝐹𝑎𝑐𝑡𝑜𝑟 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
5
1
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 121 of 157
5 where:
a) The Factor Consequence of Failure is rated in accordance with the following
documents during each required structural inspection:
WBoPDC Retaining Wall_WordPictureRisk_form01
b) The Factor Weighting is specified in the following table:
Table 5.16.2 c): Consequence of Failure Factor Weighting
No. Factor Factor Weighting
1 Impact on Road User 25%
2 Impact on Property 35%
3 Impact on Environment 15%
4 Reinstatement Cost 25%
5.16.3 Stock Index
The Stock Index KPM is calculated using the following formula:
𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑆𝑡𝑜𝑐𝑘 𝐼𝑛𝑑𝑒𝑥 = 𝑂𝑡𝑒𝑟 𝑆𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒 𝑃𝑟𝑜𝑓𝑖𝑙𝑒𝑛
1
𝑛
where:
n = number of minor structures for which a profile is developed.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 122 of 157
5 5.17 Carriageway Lighting
5.17.1 Component Condition Rating
Each carriageway light is categorised into the following three components:
1. Poles
2. Brackets
3. Lanterns
The Component Condition Rating KPM is calculated using the following formula:
𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.0 × 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Condition Rating from 1 to 5 (or 0 if not able to be rated) is assigned to each of
the three components for each carriageway light, in accordance with the following
documents, during each required structural inspection:
a) WBoPDC Street Lighting Rating Standards and Definitions
Note: Where a reticulation pole owned by the lines network company is used, then the
condition of the pole is not taken into consideration. However the bracket condition
assessment must include the integrity of the fixings to the reticulation pole. Hence if the
pole is in a condition that there is any danger of the bracket falling off the pole, then it
must be rated 5. Responsibility for assessing the strength of a wooden pole rests with the
network company, and any concerns regarding poles should be passed on to them in
writing.
5.17.2 Profile
The carriageway light Profile KPM is calculated using the following formula:
𝑃𝑟𝑜𝑓𝑖𝑙𝑒 = 1.5 × 0.6 × 𝐶𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝐿𝑖𝑔𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 + 0.4 × 𝐶𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝐿𝑖𝑔𝑡 𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Carriageway Light Condition Rating is calculated using the following formula:
𝐶𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝐿𝑖𝑔𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔
3
1
where:
1. The Component Condition Rating is calculated in accordance with Appendix
(WBoPDC Local Roads) 5.17.1
2. The Component Weighting is specified in the following table:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 123 of 157
5 Table 5.17.2: Carriageway Light Component Weighting
Component Component Weighting
Poles 30%
Brackets 40%
Lanterns 30%
The Carriageway Light Risk Rating from 1 to 5 is assigned to each carriageway light,
in accordance with the following documents, during each required structural
inspection:
a) WBoPDC Street Lighting Rating Standards and Definitions
When LED light fittings are rated and the lanterns have more than10% of light cells
that do not function, the lantern shall be rated 5. Lanterns rated 5 shall be replaced.
5.17.3 Stock Index
The Stock Index KPM for each community is calculated using the following formula:
𝐶𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝐿𝑖𝑔𝑡 𝑆𝑡𝑜𝑐𝑘 𝐼𝑛𝑑𝑒𝑥 = 𝐶𝑎𝑟𝑟𝑖𝑎𝑔𝑒𝑤𝑎𝑦 𝐿𝑖𝑔𝑡 𝑃𝑟𝑜𝑓𝑖𝑙𝑒𝑛
1
𝑛
where:
n = number of carriageway lights within the community for which a profile is
developed.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 124 of 157
5 5.18 Rural Bus Shelters
5.18.1 Component Condition Rating
Each rural bus shelter is categorised into the following six components:
1. Surrounding area
2. Structure
3. Cladding
4. Seating
5. Painting Requirements
6. Graffiti removal
The Component Condition Rating KPM is calculated using the following formula:
𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.0 × 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Condition Rating from 1 to 5 is assigned to each of the six components for each
rural bus shelter, in accordance with the following table, during each required
inspection:
Table 5.18.1: Rural Bus Shelter Rating Standards
Condition Rating Component Description
1 Very good, 90% of its design life or function remaining requiring no repair maintenance
2 Good, 60-90 % of its design life or function remaining requiring future maintenance scheduling
3 Moderate, 40 – 60% of its design life or function remaining requiring minor repair or replacement scheduling
4 Poor, 10- 40% of its design life or function remaining and requiring major repair or replacement scheduling
5 Very Poor, less than 10% of it design life remaining or function remaining and requiring immediate repair or replacement.
5.18.2 Profile
The rural bus shelter Profile KPM is determined using Table 5.13.2 a).
where:
The Condition Rating is calculated using the following formula:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 125 of 157
5
𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = (𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
6
1
where:
1. The Component Condition Rating is calculated in accordance with Appendix
(WBoPDC Local Roads) 5.18.1
2. The Component Weighting is specified in the following table:
Table 5.18.2 a): Rural Bus Shelter Component Weighting
Component Component Weighting
Surrounding Area 10%
Structure 20%
Cladding 20%
Seating 20%
Painting Requirements 20%
Graffiti Removal 10%
The Risk Rating is determined using the following table:
Table 5.18.2 b): Rural Bus Shelter Risk Rating
Rural Bus Shelter Risk Rating
Total Category Risk Rating
1 x 4
2 4 < x 5
3 x = 6
4 6 < x 8
5 9 < x 10
where the Total Category Risk Rating is the sum of all category risk ratings rated in
accordance with the following table:
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 126 of 157
5 Table 5.18.2 c): Rural Bus Shelter Category Risk Rating
No. Category Category Risk Rating
1 2 3 4 5
1 Traffic Road group 7 Road group 6 Road group 5 Road group 4 Road group 1 to 3
5 Location (distance from edge of carriageway)
> 6m 3m to 6m < 3m Immediately adjacent
without kerb and channel
5.18.3 Stock Index
The Stock Index KPM is calculated using the following formula:
𝑅𝑢𝑟𝑎𝑙 𝐵𝑢𝑠 𝑆𝑒𝑙𝑡𝑒𝑟 𝑆𝑡𝑜𝑐𝑘 𝐼𝑛𝑑𝑒𝑥 = 𝑅𝑢𝑟𝑎𝑙 𝐵𝑢𝑠 𝑆𝑒𝑙𝑡𝑒𝑟 𝑃𝑟𝑜𝑓𝑖𝑙𝑒𝑛
1
𝑛
where:
n = number of rural bus shelters for which a profile is developed.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 127 of 157
5 5.19 Footpaths
5.19.1 Length for Renewal
The footpath length for renewal is determined directly from the Footpath Deficiency
Rating Survey completed in accordance with Appendix (WBoPDC Local Roads) 5.3.4.
The Length for Renewal KPM in each community is calculated using the following
formula:
𝐿𝑒𝑛𝑔𝑡 𝑓𝑜𝑟 𝑅𝑒𝑛𝑒𝑤𝑎𝑙 = 𝐿𝑒𝑛𝑔𝑡 𝑡𝑜 𝑏𝑒 𝑅𝑒𝑝𝑙𝑎𝑐𝑒𝑑
𝑛
1
where:
n = the number of footpath sections in each community
The Length to be Replaced in each footpath section is the length with any fault
recorded against it, and only this length. Where a footpath section has no faults the
Length to be Replaced is 0m.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 128 of 157
5 5.20 Safety Performance Index
The Principal will provide Field Input sheets that identify deficiency items to be recorded.
The field inspection procedure is:
1. Each section of road is based on lengths between junctions, surface changes or width
changes and hence each section varies in length. The Field Input sheets can record up
to 1500m. For sections longer than 1500m, several Field Input sheets will be required.
2. Each road section is considered in 300m portions. Each portion of 300m is driven
over slowly in each direction so that the information can be observed as required.
When the section is complete the entire length is driven at normal speed to record the
speed environment and sight distance deficiencies.
3. After inspection of a 300m length is complete, the Field Input sheets are marked with
the number of deficiencies or a percentage of the 300m length as indicated.
4. Intersection deficiencies relate to the approach leg only. Flag lighting deficiencies
apply when dealing with the main road (i.e. head of the tee section) and must only be
recorded once.
5. Some items relate to both directions (such as centreline markings) whilst others deal
with one side of the road only.
The collected information is entered into the Safety Performance Index model to be
provided by the Principal in the format of an electronic spreadsheet.
The model will produce the Safety Performance Index for each road section by:
Converting the individual row deficiencies to a rating between 0 (good) and 5 (bad)
based on the portion of deficient length
Calculating the road section Safety Performance Index using a weighted mean of the
individual row deficiency rating coupled with other influencing factors.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 129 of 157
5 5.21 Accidents
The NZTA publication on which this KPM is based also publishes, and is linked to the
„crash reporting rate‟ for the Western Bay of Plenty district, which is based on several
factors such as hospital accident rates. To avoid any penalty to the Contractor for
improving the reporting rate, this measure will be standardised for the reported injury
crashes, through an agreed standard statistical technique.
5.21.1 Percent with Road Related Factors
The Percent with Road Related Factors KPM is calculated using the following formula:
𝑃𝑒𝑟𝑐𝑒𝑛𝑡 𝑤𝑖𝑡 𝑅𝑜𝑎𝑑 𝑅𝑒𝑙𝑎𝑡𝑒𝑑 𝐹𝑎𝑐𝑡𝑜𝑟𝑠 =𝑁𝑜. 𝑜𝑓 𝐼𝑛𝑗𝑢𝑟𝑦 𝐶𝑟𝑎𝑠𝑒𝑠 𝑖𝑛 𝑊𝐵𝑜𝑃 × 𝑁𝑜. 𝑜𝑓 𝑇𝐿𝐴𝑠 𝑖𝑛 𝐺𝑟𝑜𝑢𝑝 𝐷
𝑁𝑜. 𝑜𝑓 𝐼𝑛𝑗𝑢𝑟𝑦 𝐶𝑟𝑎𝑠𝑒𝑠 𝑖𝑛 𝐺𝑟𝑜𝑢𝑝 𝐷× 100
where:
No. of Injury Crashes in WBoP is determined by creating a crash list in the Crash
Analysis System with the following parameters for Western Bay of Plenty district:
1. Latest complete 5 year period
2. Injury crashes only
3. Rural roads only
4. Local roads only
5. Crashes with Road Factors as a contributing factor
6. Exclude Matakana Island roads
7. Exclude crashes where wet surface or wet weather has been coded as a “Road
Factor”.
No. of Injury Crashes in Group D is determined by creating a crash list in the Crash
Analysis System with the above parameters for peer Group D, which as at December
2004 consisted of the following Territorial Local Authorities:
1. Ashburton
2. Far North
3. Franklin
4. Horowhenua
5. Manawatu
6. Marlborough
7. Matamata-Piako
8. Rodney
9. Selwyn
10. South Taranaki
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 130 of 157
5 11. South Waikato
12. Southland
13. Tasman
14. Taupo
15. Thames-Coromandel
16. Waikato
17. Waimakariri
18. Waipa
19. Waitaki
20. Western Bay of Plenty
21. Whakatane
No. of TLAs in Group D is the number of Territorial Local Authorities used to create
the above crash list for peer Group D, which as at December 2004 was 21.
The method of analysis is described in the Accident KPM Analysis document to be
provided by the Principal.
5.21.2 Social Cost
The Social Cost KPM is calculated using the following formula:
𝑆𝑜𝑐𝑖𝑎𝑙 𝐶𝑜𝑠𝑡 =𝑆𝑜𝑐𝑖𝑎𝑙 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐼𝑛𝑗𝑢𝑟𝑦 𝐶𝑟𝑎𝑠𝑒𝑠 𝑖𝑛 𝑊𝐵𝑂𝑃 × 𝑉𝐾𝑇 𝑖𝑛 𝑇𝐿𝐴𝑠 𝑖𝑛 𝐺𝑟𝑜𝑢𝑝 𝐷
𝑉𝐾𝑇 𝑖𝑛 𝑊𝐵𝑜𝑃 × 𝑆𝑜𝑐𝑖𝑎𝑙 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐼𝑛𝑗𝑢𝑟𝑦 𝐶𝑟𝑎𝑠𝑒𝑠 𝑖𝑛 𝑇𝐿𝐴𝑠 𝑖𝑛 𝐺𝑟𝑜𝑢𝑝 𝐷× 100
where:
Social Cost of Injury Crashes in WBoP is determined from the crash list created
for Western Bay of Plenty to calculate the Percent with Road Related Factors KPM
Social Cost of Injury Crashes in TLAs in Group D is determined from the crash list
created for Territorial Local Authorities in peer Group D to calculate the Percent
with Road Related Factors KPM
The method of analysis is described in the Accident KPM Analysis document to be
provided by the Principal.
Appendices (WBoPDC Local Roads)
1 Key Performance Measures
Page 131 of 157
5 5.22 Visibility
5.22.1 Length with Inadequate Available Sight Distance
The objective of the Length with Inadequate Sight Distance KPM is to drive an
improvement in forward visibility and thus safety over the network by changing the
roading environment (e.g. sight benches, curve easing, land purchase and/or vegetation
control)
The Length with Inadequate Sight Distance KPM is calculated using the following
formula:
𝐿𝑒𝑛𝑔𝑡 𝑤𝑖𝑡 𝐼𝑛𝑎𝑑𝑒𝑞𝑢𝑎𝑡𝑒 𝑆𝑖𝑔𝑡 𝐷𝑖𝑠𝑡𝑎𝑛𝑐𝑒 = 𝐿𝑒𝑛𝑔𝑡 𝑤𝑒𝑟𝑒 𝑆𝑆𝑆𝐷 < 𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 𝑆𝑖𝑔𝑡 𝐷𝑖𝑠𝑡𝑎𝑛𝑐𝑒
where:
Safe Sight Stopping Distance (SSSD) is determined for each 250m section using the
Mean Free Speed (as recorded in the RAMM database at 250m intervals for rural
sealed roads) less 10km/hr in accordance with AustRoads Rural Road Design – Guide
to the Geometric Design of Rural Roads (1993), Section 6
Available Sight Distance is determined by measuring the distance between targets
1.15m in height from the road surface continuously along the centre of each lane, as
described in the WBoPDC Group 3 Roads – Available Sight Distance Review –
Revision 1 (February 2002)
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 132 of 157
6 6
Operational Performance Measures
6.1 Vulnerable Flooding Areas
Table 6.1: Vulnerable Flooding Areas
Community Road
Katikati Beach Road (SH 2 to Wills Road)
Blundell Place
Fairview Road (Carisbrooke Street to Alexander Street)
Gilfillan Drive
Kea Street
Tui Place
Te Puke Belvedere Street
Oroua Street
Te Puna Minden Road (SH2 to RP 200)
Waihi Beach Urban Area
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 133 of 157
6 6.2 Type of Vegetation Control
Table 6.2.1: Vegetation Control – General
Location Control Types Approx. Area (m²) Comments
All lengths of Road Group 1 to 3;
Lengths of Road Group 4 having edge marker posts
5, 6, 9 Various Refer to vegetation extent of control templates in Appendix (WBoPDC Local Roads) 6.3
Lengths of Road Group 4 not having edge marker posts
Road Groups 5 to 7
5, 6, 8 Various Refer to vegetation extent of control templates in Appendix (WBoPDC Local Roads) 6.3
Table 6.2.2: Vegetation Control – Urban Areas
Location Control Types Approx. Area (m²) Comments
Waihi Beach
Katikati
Omokoroa
Te Puke
Maketu
Eastern Areas
1, 5, 7, 10 mowing types
A to G
Various Locations defined in Urban Maintenance Areas
Te Puke Main Street
Katikati Main Street
1, 5, 7, 10 mowing types
A
Various Locations defined in Urban Maintenance Areas
Table 6.2.3: Vegetation Control – Stockpile Sites
Location RP Side Control Types Comments
Mountain Road 50 RHS 6, 9 To be maintained and controlled in accordance with the Stockpile Management Plan. See Appendix (WBoPDC Local Roads) 3.5
Wainui South Road 120 RHS 6, 9
Wairoa Road 180 LHS 6, 9
Young Road 280 RHS 6, 9
Table 6.2.4: Vegetation Control – Rural Footpaths
Location Start Finish Side Control Type Approx. Length (m)
Borell Road 0 1550 LHS 9 1,550
Minden Road 0 420 LHS 9 420
Oropi Road 11,620 12,110 Varies 9 400
Te Puna Road 40 3100 LHS 9 3,060
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 134 of 157
6 Rereatukahia Road 0 170 RHS 9 170
Table 6.2.5: Omissions
Location Description
All urban areas No boom chemical spraying
Road frontages of orchards displaying organic signs
No chemical control of any type
Spray Free Frontages listed in Appendix (WBoPDC Local Roads) 6.7
No chemical control of any type
Trees listed in the Operational District Plans Appendix 3: Significant Heritage Features
On written instruction from the Principal with approved Resource Consent
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 135 of 157
6 6.3 Extent of Control
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 136 of 157
6
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 137 of 157
6
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 138 of 157
6 6.4 Maintenance of Gardens, Planted Areas and Street Trees
Further to Maintenance Specification (WBoPDC Local Roads) Section 6.7.1 j), Type 7
maintenance including maintenance of gardens, planted areas and street trees includes:
a) Weeding of planted areas (including but not limited to perennials, roses, shrubberies
and juvenile trees)
b) Raking areas of bark and gravel chips. Bark must be maintained to a minimum depth
of 75mm
c) Mulching, fertilising and irrigation. Mulch must be maintained at a minimum depth
of 75mm
d) Maintaining and providing stakes and other supports
e) Replacement of dead, aged, diseased or unsuitable plant material with similar or
improved species
f) Control of pests and diseases
g) Trimming and/or pruning of trees, hedges, scrubs and ground cover to maintain:
All plants in a healthy condition
Sight distances
Appearance
Clearance to pedestrians, traffic, and encroachment on private property
h) Street tree maintenance as detailed in the Street Tree Inventory
i) Callouts to repair tree damage
j) All replacement trees must meet the requirements of the WBoPDC Development
Code and must in particular conform to the “Approved Street Tree Species List”.
All planted areas and adjacent pavement must be maintained free of weeds and litter so
they are neat and tidy at all times.
The Principal encourages the Contractor to employ a fulltime “Townsman/Janitor” in Te
Puke to carry out open space management and to ensure that compliance is maintained
with the relevant OPMs.
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 139 of 157
6 6.5 Urban Vegetation Control
Further to Appendix (WBoPDC Local Roads) 6.2, Table 6.2.2, the requirements for
vegetation control in urban areas are detailed below.
6.5.1 Sealed and Paved Areas
The following standards shall be achieved within urban metalled areas, sealed and
concrete areas, vehicle and pedestrian access, pavement and footpath edges and kerbs:
a) Grass shall not encroach more than 100mm onto the paved surface, except isolated
strands of kikuyu may encroach 200mm.
b) All joints and cracks in paved surfaces on roads shall be kept weed free at all times,
including:
The joint between kerb channel and sealed carriageway
The joint between kerb and footpath
Construction joints in footpaths or kerbs
c) The trafficable shoulder on unkerbed roads shall be maintained in a vegetation free
condition.
d) Footpaths, parking areas and hard surfaces in the CBD areas of Te Puke and Katikati
must be vegetation free. Edges around all structures, gardens, footpaths, kerblines
and trees must be maintained and the vegetation shall be trimmed flush with the
edges.
6.5.2 Watertables and Drainage, Culvert Inlets and Outlets
Treatment shall ensure the free flow of water by eliminating rank growth and aquatic
growth in side drains. If any watertable or drain becomes subject to erosion, treatment
shall be modified to minimise instability of the drain.
6.5.3 Roadside Sign Posts, Manholes, Cesspits, Poles, Switchgear Boxes and Transformers
Vegetation around these items (and under structures supported by them) shall be treated
for a clearance of 200mm round each item.
6.5.4 Herbicides and Application of Sprays
Should the Contractor elect to use herbicides for temporary control of vegetation within
recreational reserves, public spaces and along roadsides and drains, the following
standards shall apply:
a) In general, the Contract is restricted to cosmetic spraying, that is spot spraying and
edge spraying using low pressure equipment (less than 3200 kPa or 40 psi). Where
practical, contact weed control should be used.
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 140 of 157
6 b) Any chemical spraying outside these limits shall be done only by a Registered
Applicator under the Pesticides Act 1979 (and amendments).
c) The Contractor shall not spray more than 100mm behind the edge of kerb, footpath or
pavement.
d) Special care must be exercised to prevent damage to adjoining vegetation through
carrying out operations incorrectly. Damage caused by spray operations must be
reported to the Engineer‟s Representative and shall immediately be made good by the
Contractor at its expense.
e) Special care will be necessary in all landscaped areas and areas adjacent to private
property. Frontages in urban areas that are maintained by private individuals in a neat
and tidy condition shall not be sprayed.
f) In areas which are bounded by grassed or planted batters, any spraying shall be done
in a manner that minimises the risk of creating instability in the batter through loss of
vegetative cover.
g) To reduce the potential for fluvial erosion, herbicides shall not be used on the erodible
volcanic soils bounded within the area east of the Mangorewa River and South of
SH2.
6.5.5 Mowing
Mowing of each area shall conform to one of the following type definitions. The
Contractor shall work within the specified mowing tolerances without causing significant
damage to the ground or reducing grass height to less than 20mm.
Litter including glass shall be removed immediately prior to mowing. Any litter
subsequently shredded as a result of mowing shall be removed by the Contractor.
Type A
The height of grass must be maintained between a minimum height of 20mm and a
maximum height of 75mm. Clippings shall be removed. Grass clippings falling onto
paths, drives and carparks or other such similar areas shall be swept from the surface
before the Contractor leaves the site.
Type B
The height of the grass must be maintained between a minimum height of 20mm and a
maximum height of 75mm. Grass clippings shall lie where they fall except clippings
falling onto paths and drives, roadways and lined surface water channels or other such
similar areas shall be swept from the surface before the Contractor leaves the site.
Type C
The height of grass must be maintained between a minimum height of 20mm and a
maximum height of 75mm.
Type D
The height of grass must be maintained between a minimum height of 20mm and a
maximum height of 75mm. Grass clippings shall lie where they fall.
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 141 of 157
6 In general, this relates to street berms. Typically these areas are being mown 20-30 times
per year.
Type E
The height of grass must be maintained between a minimum height of 25mm and a
maximum height of 200mm. The Contractor shall use equipment from which grass is
spread evenly over the cut surface, without windrows.
In general this applies to more remote street berms.
Type F
The height of grass must be maintained between a minimum height of 100mm and a
maximum height of 400mm.
In general this applies to large areas of unused reserves where a lesser standard of control
than Type E is required. Typically these areas are mown 1-5 times a year with a flail or
slasher type mower.
Type G Scrub Cutting
The Contractor‟s responsibility is limited to the cutting of light scrub growth and branches
of a nominal trunk diameter of less than 75mm located within the legal road reserve. Any
treatment which is required beyond the scope of this section because of location or size
shall be reported to the Engineer‟s Representative for further investigation.
On completion of a scrub cutting the following clearances shall have been provided:
a) Clear in a horizontal line 5.0m from the left edge of the carriageway for a height of
4.5m
b) Clear of the surface water channel
c) Clear to within 200mm of the bank, where the bank is within 3.0m of the carriageway
d) Clear to within 200mm of any banks, either above or below the carriageway, where
items a), b) and c) do not apply
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 142 of 157
6 6.6 Urban Trees
6.6.1 Condition Rating
Trees within urban areas are categorised into the following five components:
1. Health
2. Suitability
3. Hazard evaluation
4. Safe pruning period
5. Maintenance priority
The Component Condition Rating is calculated using the following formula:
𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.0 × 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Condition Rating is rated in accordance with the WBoPDC Urban Tree Rating
Standards and Definitions and the following table, during each required structural
inspection:
Table 6.6.1 a): Urban Tree Condition Rating
No. Component Condition Rating
1 2 3 4 5
1 Health Excellent Good Average Poor Very Poor
2 Suitability Ideal Average Less than ideal
Unsuitable Totally unsuitable
3 Hazard Evaluation
No potential hazard
No existing hazard
Minor potential hazard
Potential hazard
Hazardous
4 Safe Pruning Period
> 24 months
12-24 months
6 to 12 months
< 6 months
5 Maintenance Priority
Annual 3 to 9 months
Less than 3 months
The Tree Condition Rating is calculated using the following formula:
𝑇𝑟𝑒𝑒 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 = (𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝐶𝑜𝑛𝑑𝑖𝑡𝑖𝑜𝑛 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝐶𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
5
1
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 143 of 157
6 where:
The Component Condition Rating is determined as above
The Component Weighting is specified in the following table:
Table 6.6.1 b): Tree Component Weighting
Component Component Weighting
Health 10%
Suitability 20%
Hazard Evaluation 20%
Safe Pruning Period 30%
Maintenance Priority 20%
6.6.2 Risk Rating
Trees within urban areas are categorised into the following six risk factors:
1. Tree height
2. Deciduous species
3. Invasive root species
4. Wire conflict
5. ADT (estimate)
6. Offset from the edge of the seal (offset seal road)
The Risk Factor Rating is calculated using the following formula:
𝑅𝑖𝑠𝑘 𝐹𝑎𝑐𝑡𝑜𝑟 𝑅𝑎𝑡𝑖𝑛𝑔 = 1.0 × 𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔
where:
The Risk Rating is rated in accordance with the WBoPDC Urban Tree Rating
Standards and Definitions and the following table, during each required structural
inspection:
Table 6.6.2 a): Urban Tree Risk Rating
No. Component Risk Rating
1 2 3 4 5
1 Tree Height < 3m 3m to 6m > 6m
2 Deciduous Species
No Yes
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 144 of 157
6 Table 6.6.2 a): Urban Tree Risk Rating
No. Component Risk Rating
1 2 3 4 5
3 Invasive Root Species
No Yes
4 Wire Conflict No Yes
5 ADT (estimate) < 100 100 to 500 > 500
6 Offset Seal Road
> 4m 1m to 4m ≤ 1m
The Tree Risk Rating is calculated using the following formula:
𝑇𝑟𝑒𝑒 𝑅𝑖𝑠𝑘 𝑅𝑎𝑡𝑖𝑛𝑔 = (𝑅𝑖𝑠𝑘 𝐹𝑎𝑐𝑡𝑜𝑟 𝑅𝑎𝑡𝑖𝑛𝑔 × 𝑅𝑖𝑠𝑘 𝐹𝑎𝑐𝑡𝑜𝑟 𝑊𝑒𝑖𝑔𝑡𝑖𝑛𝑔)
6
1
where:
The Risk Factor Rating is determined as above
The Risk Factor Weighting is specified in the following table:
Table 6.6.2 b): Urban Tree Risk Factor Weighting
Risk Factor Risk Factor Weighting
Tree Height 20%
Deciduous Species 10%
Invasive Root Species 10%
Wire Conflict 10%
ADT (estimate) 30%
Offset Seal Road 20%
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 145 of 157
6 6.7 Spray Free Frontage
Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
Donald Paterson 24 Arawa Avenue
1546/2395 30/11/05 C/- Natural Therapies, 28 Jellicoe St, Te Puke 3119
S & A McNutt 67 Armstrong Road
1250/18 PO Box 15-224 Tauranga 3030
Manatomo Partners 481 Belk Road 1321/5 481 Belk Rd,, Rd 1, Tauranga 3171
RHL Limited Huakiwi Orchard
516 Belk Road 1321/72 Tauranga Fruit Packers
PO Box 9121, Tauranga 3142
M Sjardin 637 Belk Road 1321/6391 Tauranga Fruit Packers
637 Belk Rd, RD 1, Tauranga 3171
Mr R J Armstrong Armstrong No 2 Trust
566 Belk Road 1321/5630 Tauranga Fruit Packers
7 Oliver Rd, RD1, Te Puna 3021
Jill Nutsford 26 Bridgman Lane (both sides of the road)
1030/222 1/12/04 New owners:
M & L Sydenham, 209 14th Ave, Tga South Tauranga 3112
B & H Baggenstos 47 Bruntwood Drive
1208/4 PO Box 4028 Mt Maunganui
Tauranga 3149
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 146 of 157
6 Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
R Graveley 319 Busby Rd, RD 1, Katikati 3177
1065/3241 11 Dec 2013
166m Inroads installed markers in an effort to minimise erosion at RP 3190 and 4870.
Ms T Neill 17 Coppelia Avenue (boundary walkway))
1270/125 7/4/06 PO Box 17-007, Omokoroa 3154
Mrs A Gordon 70 Crawford Rd, RD1, Tauranga
1304/66 CCR 180270: 10/10/13
23/10/13 7/11/13 350m 70 Crawford Road, RD1, Tauranga 3171
No Spray posts installed to prevent bank erosion from .
Mr C Booth 130 Crawford Road
1304/83 9/3/07 Signed letter
130 Crawford Rd, RD 1, Tauranga 3171
Mr Brian Marriner 182 Crawford Road
1304/1642 CCR 143769 4/8/10
23/8/10 230m frontage
Robert Burns 437 Crawford Road
1304/113 437 Crawford Rd, RD 1, Tauranga 3171
NL Trebilco SH 2
(south of Hikurangi Rd)
3000/4537 76 Emeny Road, RD 2, Tauranga 3172
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 147 of 157
6 Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
JE & CA Ballard 409 Esdaile Road
1186/151 24 Lindoch Avenue, RD 2 Te Puna, Tauranga 3172
Avalon Training Centre
Gill Lane (Albert Wigley 027 6011 899)
1217/7 Gill Lane, RD 2, Te Puna, Tauranga 3172
Dave Robertson Trust 21 I’Anson Road
1215/7 24/7/07 31/7/07 21 I’anson Rd, RD 6,Tauranga 3176
Donald Paterson 28 Jellicoe Street
3005/14241 30/11/05 Natural Therapies, 28 Jellicoe St, Te Puke 3119
AF & BA Carlyle 141 Joyce Road
1345/65 141 Joyce Road, RD 3, Tauranga 3173
Donald Munro 250 Junction Road
1309/11 22/10/03 250 Junction Rd, RD 1, Tauranga 3171
AF & BA Carlyle 139 Keenan Road
1460/11 141 Joyce Rd, RD 3, Tauranga 3173
P & J Dyer 162 Keenan Road
1460/1470 PO Box 2315 Tauranga 3140
Neil Cavell 194 Keenan Road
1460/6 CCR 146152 26/10/10
26/10/10 Not Yet PO Box 9199, Greerton, Tauranga 3142 130m frontage
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 148 of 157
6 Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
Chris Dunstan 250 Keenan Road (at TCC boundary)
1460/…. TC
17/10/12 31/10/12 6/11/12 170m frontage,lhs
250 Keenan Rd, RD 3, Tauranga 3173
Cheryl Munro 46 – 54 Koutunui Road
1010/500 12/2/08 17/3/08 46 – 54 Koutunui Rd, RD 1, Katikati 3177
Reg Murray 21 Little Waihi Road
1554/124 3/11/10 9/11/10 16/11/10 Reg Murray, Counter Delivery, Maketu Post Centre, Maketu 3138
Gijsbert van Heuckelum
117 Lindemann Rd
1063/1076 CCR 150202 18/2/11
9/3/11 25/3/11 230m frontage
R & J Rassall 100 Lochhead Road
1241/992 100 Lochhead Rd, RD 6, Tauranga 3176
Grant Mayes 62 Lowe Road 1451/11 18/4/05 62 Lowe Road, RD 6, Tauranga 3176
Ian Douglas 47 McMillan Road
1042/289 47 McMillan Rd, RD 1, Katikati 3177
Juliette Brawn 344 Maketu Rd 1528/3264 CCR 151533 30/3/11
29/4/11 3/5/11 300m frontage
Glen Annandale 822 Maungarangi Rd (2km long frontage)
1639/15 21/01/09 822 Maungarangi Rd, RD 9, Te Puke 3189
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 149 of 157
6 Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
Margaret Bentley 1849 Maniatutu Road
1542/10 PO Box 155, Rotorua 3046
Mr B B Pethybridge 634 Maniatutu Road
1542/5875 27/3/06 PB & P G Hermann, 634 Maniatutu Rd, RD 6 Te Puke 3186
Jeremy Barrett 1555 Maniatutu Rd
1542/48 6/11/07 7/11/07 1555 Maniatutu Rd, RD 6, Te Puke 3186
Phillipa Medlock 1706 Maniatutu Road
1542/123 4/8/04 17-6 Maniatutu Rd, RD 6, Te Puke 3186
Shirley Lancaster 112 Matahui Road
1146/56 Reed Estate Ltd, 112 Matahui Rd, RD 2, Katikati 3178
Ronny Neilsen 665 Minden Rd 1301/19 28/10/03 Postal Delivery Centre, Te Puna, Tauranga 3021
B & J Roderick 308 No 1 Road 1505/800 CCR 158566
5/12/11 9/12/11 970m frontage on 2 roads
308 No 1 Rd, RD 2, Te Puke 3182 (970m frontage on 2 roads No 1 and Roderick and (frontage no No1 Road and Roderick Lane)
D & D Robinson 413 No 1 Road 1504/61/2 New owner:
PB &MV Crawford, 413 No 1 Rd, RD 2, Te Puke 3182
Natalie Marsh 775 Old Coach Road
1586/7231 22/9/09 5/11/09 17/11/09 800m Mrs N Marsh, 775 Old Coach Road, RD 6, Te Puke 3186
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 150 of 157
6 Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
D Wanless Everest Orchard
534 Ohauiti Rd (700m frontage)
1352/3376 534 Ohauiti Rd, RD 3, Tauranga 3173
Reiner Bragulla 998 Ohauiti Rd 1352/70 20/10/08 5/2/09 PO Box 3147, Greerton, Tauranga 3112
John Godwin Healing World
1002 Ohauiti Road (short frontage)
1352/146 29/1/09 4/2/09 1002 Ohauiti Rd, RD 3, Tauranga 3173
Carolyn Acworth 1134 Ohauiti Road
1352/112 New owner:
Brumag Trust, C/- B & R McCurdy, 1134 Ohauiti Rd, RD 3, Tauranga 3173
Neville Lowry 1174 Omanawa Road
1439/115 17/9/10 17/9/10 21/9/10 194m frontage
N Lowry, 1174 Omanawa Rd, RD 1, Tauranga 3171
Doreen Grundy 1331 Omanawa Road
1439/13225 10/7/03 31/8/06 1331 Omanawa Rd, RD 1, Tauranga 3171
T & J Williams Pottsbury Farm
244 and 254 Ongare Point Road
1045/15 3/9/07 Refused to sign
244 Ongare Point Road, RD 1, Katikati 3173
AF & BA Carlyle 358 Oropi Road
1347/65 24/1/06 141 Joyce Rd, RD 3, Tauranga 3173
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 151 of 157
6 Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
P S McNamara Kiwicrop Orchard
951 Oropi Road
1347/7963 New owner
M & L Randrup, 586a Oropi Rd, Tauranga 3173
G & A Hollis 107 Pongakawa Stn Rd
1652/809 107 Pongakawa Station Rd, RD 6, Te Puke 3186
Esther Williams 50 Pugh Road 1680/90 CCR158161 4/11/11
23/11/11 1/2/12 550m frontage 50 Pugh Road
Warner Family Trust Belac Orchard
668 Pyes Pa Road
1339/6578 11/12/09 18/12/09 xx/12/09 Property managed by Oropi Management Services, PO Box 9475, Greerton, Tauranga 3142. Attn Bruce MacDiarmid
G Gibbs Pineview Orchard
850 Pyes Pa Road
1339/22 R & T Russell, 850 Pyes Pa Rd, RD 3, Tauranga 3173
Mike Fallows 347 Rangiuru Rd
1521/3246 9/9/10 9/9/10 18/11/10 120m frontage 347 Rangiuru Rd, RD 8, Tauranga 3188
Andrew and Fiona Collins
554 Rangiuru Rd
1521/2 554 Rangiuru Rd, RD 8, Te Puke 3188
B Hudson & M Thomas
Sugar Mountain Orchard
88 Rocky Cutting Road
1373/15 New Owner
TSS Holdings, C/- R & K Ellison, 18a Rota St, Mt Maunganui 3116
Sharon O’Brien 250 Rocky Cutting Road
1373/27 250 Rocky Cutting Road, RD 5, Tauranga 3175
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 152 of 157
6 Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
Audrey (Margaret) Anderton
39a Rowe Road
1477/68 CCR 160353 19/1/12
8/2/12 No 120m frontage 39a Rowe Road, RD 3, Tauranga 3173
Brian Scrafton 394 Te Matai Road
1508/26 New Owner:
TSS Holdings, C/- R & K Ellison, 18a Rota St, Mt Maunganui 3116
Russell Williams 326 Te Puna Station Rd
1247/2912 10/12/10 16/12/10 24/1/11 190m frontage – may erect signs
Heath Smart 2 Tebbutt Road
1311/2 CCR 103906 13/11/06
23/11/06 No 2 Tebbutt Road, RD 1, Tauranga 3171
Susan Butcher 329 Thompsons Track, Katikati
1138/34 CCR 154565 30/6/11
7/7/11 No 150m frontage
S & T Newlands 83 Waiau Road
1028/685 83 Waiau Road, RD 1, Katikati 3177
Janet Dubler-Jacobs 233 Wainui South Rd
1181/2123 CCR112068 14/8/7
30/8/7 No 233 Wainui South Road, RD 2, Apata, Tauranga 3178
R & E Comyn 41 Wallace Road,, RD 4, Tauranga 3174
1230/11 CCR 180942 30/10/13
1/11/13 2/12/13 200m frontage 41 Wallace Road, RD 4, Tauranga
Long property frontage
Hoki Bruce 154 Walford Road
1166/33 23/8/10 CCR144243
26/8/10 1/9/10 285m frontage
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 153 of 157
6 Table 6.7: Spray Free Frontage
Owner Orchard Name
Orchard Address
Property File
Date requested
Letter sent
Letter Returned
Frontage Length
Postal Address
Neville Dunton 375 Whakamarama Rd
1212/231 CCR 171901 1/2/13
4/2/13 4/6/13 112m frontage PO Box 835, Seventh Avenue, Tauranga 3140
Annabel Bracey 634 Whakamarama Rd
1212/6426 CCR160804 8/2/12
3/2/12 No 120m frontage 634 Whakamarama Rd, RD 6, Tauranga 3176
Mary Jenkins 9 Windrigdge Lane (from 50m – 100m, Aongatete
1879/21 CCR148151 23/12/10
No Ms M Jenkins, 24 Aongatete Road, RD2, Katikati 3178
Only part of frontage to be “No Spray”. Will erect signs
Mervyn Stockley 45 Winroy Road (Organic Orchard)
1043/12 CCR 123003 25/8/08
25/8/08 No 45 Winroy Road, RD 1, Katikati 3177
Christopher Muller 462 Wright Rd (corner of Upland Road)
1154/4484 CCR 156056
2/9/11 27/9/11 163m Wright Rd,
75m Upland Rd
462 Wright Rd, R D 2, Katikati 3178
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 154 of 157
6 6.8 Litter Removal (Rural)
The Contractor shall collect Litter on the rural roads nominated in the following table on a
monthly basis. The Contractor shall remove Litter in the same week each month to ensure
Litter removal cycles are not extended beyond the monthly frequency.
Table 6.8: Litter Removal (Rural)
Location Approx. Road Length
Waihi Beach, Seaforth Road (Albacore Avenue to Pio Road) 2,215m
Waihi Beach, Waihi Beach Road (Boundary to Wilson Road) 2,988m
Waihi Beach, Athenree, Steel, Emmerton Route 1,879m + 1,450m + 1,648m
Maketu Road (SH2 to Spenser Road) 6,500m
Pukehina (Pukehina Beach Road and Pukehina Parade) 3,500m + 5,230m
Omokoroa Road (SH2 to The Esplanade) 4,113m
Te Puna Road
Te Puna Station Road
6,590m
Snodgrass Road (SH2 to Borell Road) 2,685m
Borell Road 1,550m
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 155 of 157
6 6.9 Litter Control (Urban)
To ensure fulfilment of the Principal‟s responsibilities under the Litter Act 1979, the
Contractor shall maintain Litter bins provided in public places and make provision to
empty them. The scope of Litter control includes:
1. The removal and suitable disposal of Litter:
Within and around the provided bins
Located within the urban areas as may be brought to the attention of the
Contractor from time to time, termed free Litter
On nominated rural roads (typically at the entrance to urban areas)
2. Uplifting and removing leaves from footpaths and kerb and channel as required from
time to time to meet the Performance Criteria and in particular:
Uplifting and removing autumn fall deciduous leaves from footpaths and kerb
and channel in the defined CBD areas
Uplifting and removing autumn fall deciduous leaves from Beach Road Katikati,
(adjacent to Katikati College), Queen Street Te Puke (from Beatty Avenue to
Cameron Road), and Cameron Road Te Puke (from SH2 to Tui Street) every two
weeks over the leaf fall period or as requested via service request.
3. The maintenance, repair and reinstatement of existing litter receptacles and padlocks,
plus cleaning of Litter bins using fluids and disinfectants, and/or liners. Replacement
of existing Litter bins shall be like for like or agreed equivalent.
4. Where additional bins are required to meet the Performance Criteria, these shall be
provided and maintained by the Contractor. Additional Litter bins shall be the same
bins as existing adjacent bins or agreed equivalent.
5. Where additional bins are requested by the Engineer‟s Representative, the capital cost
shall be a variation to contract.
The Contractor shall determine the frequency of bin maintenance (including emptying) to
meet the intent of the Litter Act 1979.
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 156 of 157
6 6.10 Urban Street Cleaning
Further to Maintenance Specification (WBoPDC Local Roads) Section 6.17, urban street
cleaning is intended to deliver to the commercial areas either washed surface or swept
surface as detailed below, to ensure such areas are clean and presentable to the general
public.
6.10.1 Scope
A washed surface is the process required to clean the required surfaces with a purpose
built scrub washer that removes surface grime, dirt and dust, via applied water, including
the substantial removal of any applied water and contaminants.
A swept surface is the mechanical and/or hand process that collects and removes loose
detritus, debris, leaves, litter, grit and the like, (but excludes adhesives such as chewing
gum), to ensure the required surfaces are fit for their intended purpose and includes
footpaths and kerb and channel: Note that hand sweeping will be required around blisters
to augment suction cleaning of kerb and channel.
Also included in this item is
a) The removal of graffiti to ensure surfaces are restored to a standard acceptable to the
Engineer‟s Representative by painting or graffiti removal
b) Replacement or repair for any damage sustained to existing bollards
6.10.2 Frequency
The minimum frequency of the required activity is presented in the following table:
Table 6.7.2: Urban Street Cleaning: Frequency
Location Sweeping Frequency
Approx. Area (m²) Footpath Washing
Frequency
Waihi Beach
Sweeping frequency to be twice weekly over the period Friday before October Labour Weekend to after Easter weekend. Cleaning days to be Monday and Friday.
Weekly by 8am Mondays. Then
also Fridays during summer season
Street Cleaning Areas defined in
Urban Maintenance Areas Volume 1
March, June, Sept. and Dec.
Katikati Daily by 8am
(7 Days per week)
Street Cleaning Areas defined in
Urban Maintenance Areas Volume 2
March, June, Sept. and Dec
Te Puke Daily by 8am
(7 days per week)
Street Cleaning Areas defined in
Urban Maintenance
March, June, Sept. and Dec
Appendices (WBoPDC Local Roads)
1 Operational Performance Measures
Page 157 of 157
6 Table 6.7.2: Urban Street Cleaning: Frequency
Location Sweeping Frequency
Approx. Area (m²) Footpath Washing
Frequency
Areas Volume 4
Maketu Weekly by 8am Street Cleaning Areas defined in
Urban Maintenance Areas Volume 5
March, June, Sept. and Dec
Te Puke Heritage Walkway Daily by 8am
(7 days per week)
500 Monthly
Talisman Carpark Katikati Weekly 3500 N/A