basic generator operations

95
Operations Introduction to GE’s Generators Basic Operations

Upload: walid-salama

Post on 19-Nov-2014

1.463 views

Category:

Education


3 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Basic generator operations

Operations Introduction to GE’s Generators

Basic Operations

Page 2: Basic generator operations

• The following information is intended to be used an introductory guide only and is not intended for actual plant use.

Operations Introduction to GE’s Generators

Page 3: Basic generator operations

Starting the Generator for the first time.

• The following inspections and preliminary checks should be made before the generator is started for the first time.

Page 4: Basic generator operations

• Check all connections IAW the provided Connections Outline.

Starting the Generator for the first time.

Connections

Page 5: Basic generator operations

• See that the voltage on the generator nameplate corresponds with line voltage.

Starting the Generator for the first time.

Voltage

Page 6: Basic generator operations

• Check RTD’s for proper operation IAW provided technical documentation.

Starting the Generator for the first time.

RTD’s

Page 7: Basic generator operations

• Inspect the generator for gas leaks.

Starting the Generator for the first time.

Mechanical Tightness

Page 8: Basic generator operations

• The collector Rings should be carefully inspected for scratches or rough spots.

• Brushes should be seated to the collector rings.

• The position of the brushes and associated rigging should be set IAW applicable technical documentation.

Starting the Generator for the first time.

Collector Rings and Brush Rigging

Page 9: Basic generator operations

• The insulation resistance of the stator and the rotor should be taken IAW applicable technical documentation.

Starting the Generator for the first time.

Insulation Resistance

Page 10: Basic generator operations

• The shaft sealing system must be in operation IAW instructors for the Hydrogen Cooling System.

Starting the Generator for the first time.

Shaft Sealing System

Page 11: Basic generator operations

• The fan and rotor clearances should have been checked during construction. Records should be reviewed to ensure that this has been done.

Starting the Generator for the first time.

Clearances

Page 12: Basic generator operations

• As specified in bringing the generator up to speed, checks should be made to insure that there is no rubbing between rotating and stationary components of the generator, and that operation of both the turbine and and the generator rotors are free of excess vibration.

Starting the Generator for the first time.

Rubbing and Vibration

Page 13: Basic generator operations

• The bearing and seal housing insulation should be checked IAW applicable documentation.

Starting the Generator for the first time.

Bearing and Seal Housing Insulation

Page 14: Basic generator operations

• The exciter should be checked thoroughly IAW applicable excitation technical information.

Starting the Generator for the first time.

Exciter

Page 15: Basic generator operations

• Should be inspected IAW applicable technical documentation.

Starting the Generator for the first time.

Hydrogen System

Page 16: Basic generator operations

• The gas coolers should be checked to ensure that all coolers are full of water and have been vented.

• The water supply to the coolers should be properly throttled to prevent over heating or causing condensation to form.

Starting the Generator for the first time.

Gas Coolers

Page 17: Basic generator operations

Starting the Generator

• When starting the generator, it is recommended that a startup check list be used to ascertain that no items have been over looked. The following items should be included on a checklist.

Page 18: Basic generator operations

Starting the Generator

Conventional Starting Motor

• Armature Circuit Breaker OPEN• Main Field and Spare Breakers OPEN• Voltage Regular selected to Manual • Manual Voltage adjust in the LOW position

Page 19: Basic generator operations

Starting the Generator

Conventional Starting Motor

• When the unit is turning slowing, check for Rubbing.

• As the generator is brought up to speed, check for mechanical balance by monitoring shaft vibration readings.

• Check the position of the collector ring brushes. Ensure that they are riding properly and not sparking.

Page 20: Basic generator operations

Starting the Generator

Conventional Starting Motor

• Regulate the cold liquid flow valves to obtain the rated flow condition.

• Cold gas temperature will be a function of cold liquid temperature.

Page 21: Basic generator operations

Starting the Generator

LCI Starting System

• LCI controls are properly set per Turbine Operating Instructions.

• Generator grounding transformer breaker is OPEN• LCI Safeties are Reset and Operational.• Generator Safeties are Reset and Operational

Page 22: Basic generator operations

Starting the Generator

LCI Starting System

• When the unit is rolling slowly, check for Rubbing.

• Check the position of the collector ring brushes. Ensure that they are riding properly and not sparking.

• Verify that Hydrogen pressure and purity are at rated conditions.

Page 23: Basic generator operations

Starting the Generator

LCI Starting System

WARNING• Startup of a Hydrogen cooled generator in air is

significantly harder on the generator due to the reduced heat transfer properties of air. For this reason any low speed hold points typical of those associated with Water Wash, Purge, and HRSG warm-ups must be eliminated. The transition from turning gear speed to rated speed must be as quick as possible.

Page 24: Basic generator operations

Starting the Generator

LCI Starting System

• Regulate the cold liquid flow valves to obtain the rated flow.

• As the generator is brought up to speed, check for mechanical balance by monitoring shaft vibration readings.

• RTD’s should be checked frequently during startup to determine that winding temperatures are not excessive.

Page 25: Basic generator operations

Starting the Generator

LCI Starting System

• At 90% speed, verify that the LCI is de-energized and that the circuit breaker between it and the generator is OPEN.

• Verify that the LCI breaker is OPEN.• Verify that the breaker between the generator

neutral and the grounding transformer is OPEN.

Page 26: Basic generator operations

Before Synchronizing

Build Up of Generator Voltage

• After the unit is up to 95% rated speed or greater, Close the Main Field Breaker.

• Set the regulator control switch to “Start Up” for approximately 5 seconds ,“Flash the Field” and release.

• Check that the generator’s voltage has built up.

Page 27: Basic generator operations

Before Synchronizing

Set No-Load Excitation

• Adjust machine terminal voltage with the Manual-Volts adjust.

• Set terminal to voltage to match bus voltage.

Page 28: Basic generator operations

Before Synchronizing

Transfer to Automatic Voltage Regulation

• Set the regulator control switch to “TEST”.• Zero the transfer voltmeter by means of the

automatic voltage adjuster.• Set the regulator control switch to “Auto”.• Recheck the generator voltage with bus voltage.

Page 29: Basic generator operations

Synchronizing the Generator

Requirements for Synchronizing

Prior to synchronizing the following requirements must be met.

Frequencies Matched

Voltage Matched

Same Phase Sequence

Page 30: Basic generator operations

Synchronizing the Generator

Match Generator Frequency to Bus Frequency

• Adjust turbine speed to a slow rotation of the synchroscope, or

• Use automatic synchronization.

Page 31: Basic generator operations

Synchronizing the Generator

Match Generator Voltage to Bus Voltage

• Set the automatic voltage adjuster to match generator voltage to bus voltage, or

• Use automatic synchronization.

Page 32: Basic generator operations

Synchronizing the Generator

Match Generator Phase Angle to Bus Phase Angle

• When the synchroscope reads zero, close the generator breaker, or

• Use automatic synchronization.

Page 33: Basic generator operations

Improper Synchronizing

What would happen if the requirements to synchronize

(parallel) were not met and the generator output breaker was

shut?

Page 34: Basic generator operations

Improper Synchronizing

Frequency

If frequency was not matched several things would occur:

1. It would be difficult to match the phase angle between the incoming and running machines.

Remember: For two “machines” to have the same phase sequence, their frequencies must be the same.

Page 35: Basic generator operations

Improper Synchronizing

Frequency

2. If the incoming machine’s frequency (the generator) was less that the running frequency (the power grid), the generator would be a real load on the grid.

Page 36: Basic generator operations

Improper Synchronizing

Voltage

If voltage was not properly matched several things will occur:

1. It would be difficult to match the phase angle between the incoming and running machines.

more importantly

Page 37: Basic generator operations

Improper Synchronizing

Voltage

2. Excessive damage will result to the generator, the output breaker, and possibly the grid due to extremely high circulating currents and uncontrolled power transients.

Page 38: Basic generator operations

Improper Synchronizing

Voltage

“What would happen if the generator output breaker was shut with generator voltage not matched to grid voltage?”

Page 39: Basic generator operations

Improper Synchronizing

Voltage

Initial Conditions

Generator (incoming) is rated for 13.8 kV

Grid (running) is 15.0 kV on the LV side of the HV Step-Up transformer.

Page 40: Basic generator operations

Improper Synchronizing

Voltage

A rough estimation of the voltage difference across the breaker can be

made as follows:

Convert 13.8 KV and 15.0 KV to Peak Voltages.

PK = RMS/.707

Page 41: Basic generator operations

Improper Synchronizing

Voltage

Generator

PK =13,800 volts/.707

PK = 19,519 volts

Page 42: Basic generator operations

Improper Synchronizing

Voltage

Grid

PK =15,000 volts/.707

PK = 21,216 volts

Page 43: Basic generator operations

Improper Synchronizing

Voltage

The voltage difference between the Generator and the Grid is:

Running - Incoming = Volts

21,216 volts - 19,519 volts = 1697 volts

Page 44: Basic generator operations

Improper Synchronizing

Voltage

Using a design resistance of .01 , the amount of instantaneous current and

power can be calculated.

Ohm’s Law

I = E/R

I = 1697 volts/ .01

169,700 amperes

Page 45: Basic generator operations

Improper Synchronizing

Voltage

Power (watts)= I2 x R

Power (watts) = (169,700 amps)2 x .01

Power (KW) = 287,980.9 KW!

Page 46: Basic generator operations

Improper Synchronizing

Phase Angle

Improper phase angle is caused by improperly matched voltages and

frequency.

However, with all of the conditions met, it is still possible to parallel out of phase simply by shutting the breaker at the wrong time during the paralleling sequence.

Page 47: Basic generator operations

Improper Synchronizing

Phase Angle

“What would happen if the generator output breaker were shut when the

“synchroscope” was at the 11 o’clock position.”

Page 48: Basic generator operations

Improper Synchronizing

Phase Angle

Initial Conditions

The Generator (incoming) and Grid (running) voltages are matched and are

at 13.8 KV.

PK =13,800 volts/.707

PK = 19,519 volts

Page 49: Basic generator operations

Improper Synchronizing

Phase Angle

Make the assumption that a synchroscope is similar to a clock.

At the 11 o’clock position, the running and incoming voltage phases are 30o

apart.

Page 50: Basic generator operations

Improper Synchronizing

Phase Angle

Since the generator is being paralleled to the grid, we will assume that the grid

voltage is stable.

Therefore, we must solve what the generator voltage is when it is 30o out of

phase with the grid.

Page 51: Basic generator operations

Improper Synchronizing

Phase Angle

It becomes a simple math problem.

Generator Voltage = PK (cos )

Generator Voltage = 19,519 (cos 30o)

Generator Voltage = 16,903.9 Volts

Page 52: Basic generator operations

Improper Synchronizing

Phase Angle

The difference in voltage between the Grid and the Generator is found as follows:

Grid (running) - Generator (incoming) = Volts

19,519 volts - 16,903.9 volts = 2615 volts

Page 53: Basic generator operations

Improper Synchronizing

Phase Angle

Instantaneous current and power can now be calculated using a design resistance

of .01 ,

Ohm’s Law

I = E/R

I = 2615 volts / .01

261,500 amperes

Page 54: Basic generator operations

Improper Synchronizing

Phase Angle

Power (watts)= I2 x R

Power (watts) = (261,500 amperes)2 x .01

Power (KW) = 683,822.5 KW!

Page 55: Basic generator operations

Initial Loading

• Pick up approximately 3-5% rated load immediately after the generator breaker has shut.

• Adjust the automatic voltage regulator to achieve the desired power factor.

• RTD’s should be checked to ensure that winding temperatures are not excessive.

• Cold Gas temperature should be maintained between 30 to 40 oC (86 to 104 oF) with a maximum of 46 oC at 30 psig (207 kPa) hydrogen pressure.

Page 56: Basic generator operations

Droop operation is used for generators connected to the grid.

Operating on the Power Grid

Page 57: Basic generator operations

Operating on the Power Grid

This allows generators to share load changes that occur in proportion to their maximum rating.

Page 58: Basic generator operations

Operating on the Power Grid

This occurs regardless of what the actual load is on any particular machine at any given time as long as the

unit is “on-line” and does not exceed rated load.

Page 59: Basic generator operations

Operating on the Power Grid

If there is a load change with multiple generators in the system, this formula is used to determine what the new load would be for a single generator based on a particular system load change.

Page 60: Basic generator operations

For Example. In this power system there are three 60 Hz generators with a 4% droop. If the ACME coffee factory creates a sudden 15 MW demand, what will happen to each generator?

Multiple Turbine Operation

Page 61: Basic generator operations

Multiple Turbine Operation

Page 62: Basic generator operations

What would the new load demand be for Generator #2?

Multiple Turbine Operation

Page 63: Basic generator operations

258.8 MW

Multiple Turbine Operation

Page 64: Basic generator operations

Single Turbine Operation

Page 65: Basic generator operations

To see how droop operation affects a single turbine generator connected to a distribution system, the following problem provides an example.

Example: Calculate the new speed when a 25 MW load is started on a 100 MW generator operating at 60 Hz and 3600 RMP with a 4% droop?

Single Turbine Operation

Page 66: Basic generator operations

This problem is simple if you remember that speed droop in linear!

Single Turbine Operation

Page 67: Basic generator operations

From No-Load (NL) to Full Load (FL), the generator will experience a change of 100 MW.

This change should only change running frequency by 4%.

Therefore:

Single Turbine Operation

Page 68: Basic generator operations

NL-FL = 100 MW

60 Hz x .04 (% droop) = 2.4 Hz

25 MW load demand

100 MW = 25 MW

2.4 Hz X

100 MW (X) = 25 MW (2.4 Hz)

100 MW (X) = 60 MW(Hz)

X = 60 MW (Hz)

100 MW

X = .6 Hz

60 Hz - .6Hz = 59 .4 Hz

Single Turbine Operation

Page 69: Basic generator operations

The formula for Frequency is:

F = NP / 120

F (120) =NP

F(120) = N

P

(60 Hz - .6 Hz) x (120) = 3564 RPM

2

Where: F = frequency in Hz

N = Speed in RPM

P = number of machine poles (2)

Single Turbine Operation

Page 70: Basic generator operations

At anytime during this speed reduction, the operator can manually restore frequency to

60 Hz by raising the called-for speed to reach 3600 RPM.

The called - speed set point of the turbine can be adjusted automatically by the use of

automatic control system.

Single Turbine Operation

Page 71: Basic generator operations

Power Factor (pf) Adjustment• If the generator is operating as a single unit, power factor

is determined by the load.

• When the generator is operating on a system with other generators, power factor is determined by the generator field current.

• Power factor maybe adjusted by changing the field current; for over excited operation (Lagging pf), increasing the field current will lower the power factor.

• Lowering the field current will raise the power factor (Leading pf).

Page 72: Basic generator operations

Effects of Leading and Lagging Power Factor

• Because of system conditions, generator’s are usually not operated at rated pf. It is important for operators to understand the limitation of the generator during this type if operation.

Page 73: Basic generator operations

Effects of Leading and Lagging Power Factor

• Capabilities and limitation of a generator are best illustrated using the Reactive Capability Curve.

Page 74: Basic generator operations

Reactive Capability Curve

• This curve shows the relationship of KW, KVAR, and KVA.

• It also shows what generator limitations are at different operating conditions.

Page 75: Basic generator operations

Reactive Capability Curve

• The curve has three outside cures that represent inlet cold gas or air temperatures.

• The colder the temperature, the higher the loading capability.

Page 76: Basic generator operations

Reactive Capability Curve

• There are rated pf limit lines that intersect the cold gas curve.

• Operating points are established based on current pf, Real Power (MW), and temperature.

Page 77: Basic generator operations

Reactive Capability Curve

• The gas curve is broken down into limiting regions.

• Operation outside of these areas can have adverse effects on generator performance and possibly, lead to damage.

Page 78: Basic generator operations

Reactive Capability Curve• The portion of the

curve extending between Rated pf -Lagging and the .95 pf-Leading line is an arc whose radius of 1.0 per unit KVA corresponding to the rating at various hydrogen pressures.

Armature Winding

Limits

Page 79: Basic generator operations

Reactive Capability Curve

• In this region, KVA is limited by armature winding temperature limits.

Armature Winding

Limits

Page 80: Basic generator operations

Reactive Capability Curve

• In the region between the Rated pf-Lagging (over excited) and the zero-pf line, KVA is limited by the temperature rise of the field winding.

Field Winding

Heating Limits

Page 81: Basic generator operations

Reactive Capability Curve

• In the region of Leading-pf, rated KVA can usually be carried to .95-Leading.

• After this point, KVA is limited to minimize end iron heating of the armature core.

End Iron Heating

Page 82: Basic generator operations

Shutting Down the Generator

Page 83: Basic generator operations

Shutting Down the Generator

• Reduce Load on the generator to zero by adjustment of the synchronizing device on the turbine.

• When load has been reduce to zero, open the generator breaker.

• Adjust the transfer voltmeter voltage to zero by use of the manual voltage regulator.

• Switch the regulator to Manual.• Reduce machine terminal voltage to the minimum

value.

Page 84: Basic generator operations

Shutting Down the Generator

• Open the Main Field Breaker.• Secure water to the cooler when the turbine is shut

down.

Page 85: Basic generator operations

Generator Casualties

Page 86: Basic generator operations

Loss of Field

• Operation of the generator connected to a power system without field current will cause excessive field heating.

• The degree of heating depends upon initial load, the manner in which the field was lost, and the manner in which the generator is connected to the system.

Concerns

Page 87: Basic generator operations

Loss of Field

• When excitation is lost, the generator tends to overspeed causing to act as an induction motor.

• This overspeed results in a reduction of load ,an increase in armature current, low voltage at the generator terminals, and very high rotor currents.

• Rotor currents will flow through the field winding (provided that the field winding has been short-circuited or is connected through a field discharge resistor) and through the rotor body, completing a circuit through the rotor coil wedges.

Concerns

Page 88: Basic generator operations

Loss of Field

• Circulating rotor current will cause extremely high and possibly dangerous temperatures in a very short period of time.

• The time required for the heating to become dangerous depend upon the conditions of the loss of excitation.

• Generally, this time is short beginning in a matter of second rather than minutes for a machine with an open field winding.

Concerns

Page 89: Basic generator operations

Loss of Field

• Opening of the field circuit with the machine carry a load, will subject the windings to high and possibly dangerous voltage levels from the inductive effects of the windings.

Concerns

Page 90: Basic generator operations

Loss of Field

• If excitation is lost by accidental tripping of the field breaker, the breaker should immediately be re-closed without shutting down the machine.

Actions - Accidental Tripping

Page 91: Basic generator operations

Loss of Field

• If the machine is discovered to be operating without field for an unknown period of time, it should be immediately be tripped “off-line” and shut down for inspection to determine the degree of rotor damage.

Actions - Unknown Tripping

Page 92: Basic generator operations

Loss of Field

• Relays are know available that determine when a machine has started slipping due to loss of excitation.

• Since the heating effect occurs in a relatively short period of time after the loss of the field, the relays are employed to trip the machine “off-line”.

• Damage will(should) be prevented from overheating and the machine may be placed back in service as soon as the defect in the excitation system has been remedied.

Actions - Unknown Tripping

Page 93: Basic generator operations

Grounded Field Winding

• It is general practice to operate the generator excitation system ungrounded.

• If an accidental single ground occurs on the generator field operating on an ungrounded system, no change in excitation should occur, but the machine should be removed from service because of the risk of system interruption and damage to the generator field.

Concerns

Page 94: Basic generator operations

Grounded Field Winding

• After a ground is indicated, the generator should be removed from service and the cause of the ground located and repaired.

• In no case should the generator be allowed to remain on the system for any appreciable time after a ground has occurred.

Actions

Page 95: Basic generator operations

Generator Load Capability

• The generator should not be allowed to operate at any loads above the nameplate rating even though operating temperatures are well below rated temperatures.

• Intermittent operations of loading beyond the nameplate values encroaches on the design margins built into the machine.