basf bm018 slow firing alkali
DESCRIPTION
Boiler Slow Firing ProcedureTRANSCRIPT
TRICHY
PROCEDURE FOR SLOW FIRING (OIL/GAS FIRED BOILERS)Project : M/s.BASF INDIA LIMITEDBoiler No.: BM018
Page 1 of 2
01. REFRACTORY DRY OUT:
After the refractory works are completed, the refractory work must be subjected to proper
curing and initial heating. These two procedures must be strictly carried out. Otherwise,
cracks may occur on the refractory surface. The procedure is given below.
02. CURING FOR CASTABLE REFRACTORY:
All the castable are hydraulic setting type and need the presence of moisture for setting
process, so it is necessary to ensure that the castable does not dry out to exposure or due
to heat produced within the mass. It should not be allowed to dry during first 24 hours
after it has been placed.
Moist condition has to be maintained by covering the castable with wet gunny sacks
or by frequent sprinkling of fine mist of cold water on all exposed surfaces. Sprinkling
should be started after the castable has set partially. It is generally advisable to spray
water on dense castables every 45 minutes for 24 hours.
03. INITIAL HEATING FOR REFRACTORY:
Proper attention should be given during initial heat up of castables, as they have
considerable lower permeability when compared to brick. It is more difficult for the water
to pass through the castable and escape as the refractory is heated more rapidly.
Rapid heating also causes the hot face to dry up and heat up while the rest of castables is
still comparatively cool.
This will lead to expansion of hot face and hence develops a crack on cold face.
TRICHY
PROCEDURE FOR SLOW FIRING (OIL/GAS FIRED BOILERS)Project : M/s.BASF INDIA LIMITEDBoiler No.: BM018
Page 2 of 2
04. SLOW FIRING PROCEDURE :
Following are to be done before slow firing is started:
a) No fans should be operated for the heating purpose. Firing should be done only by natural
draught. For this all dampers should be kept open.
b) Sufficient sized fire wood required has to be stocked for the dry out.
c) Slow firing can be done by burning sized wood in the furnace. The sized wood can be fed in
the furnace through the manhole. The fuel required shall be computed as if the boiler would
be operated to generate 20% MCR load.
The following heat and curing schedule is recommended:
1. Heat gradually upto 110°C and hold at this temperature for 18 hours.
2. Then raise the temperature at rate of 10°C to 15°C per hour upto 260°C and hold at this
temperature for 8 hours.
3. Then raise the temperature at rate of 10°C to 15°C per hour upto (550°C (or) to the
maximum possible temperature between 350°C to 550°C) and hold at this temperature
for 10 hours.
4. After this the furnace can be cooled naturally.
TEMPERATURE
TRICHY
PROCEDURE FOR ALKALI BOILOUT(OIL/GAS FIRED BOILERS)
Project : M/s.BASF INDIA LIMITEDBoiler No.: BM018
Page 1 of 2
1. The boiler shall be ready in all aspects for steaming to the design capacity and steam
parameters. Ensure drum internals including screen boxes are fixed and welding is
completed before alkali boilout. Close all sampling points and instrument tappings at
sources. Temporary sampling line for alkali boilout is recommended to avoid choking due
to loose mill scale, debris, etc.
2. Keep ready the following chemicals :-
2.1 Trisodium phosphate (Na3PO4) 4000 ppm
The quantity for each boilout shall be estimated 4 x water volume of boiler
(QM^3 x 4 Kgs)
2.2 sodium Carbonate (Na2CO3) 4000ppm.
The quantity for each boilout shall be estimated 4 x water volume of boiler
(QM^3 x 4 Kgs)
3. The boilout is to be carried out in three stages and fresh chemicals are to be charged
before each stage.
4. Fill the boiler with DM water (100 mm below manhole door level). Dissolve chemicals in
DM water (use plastic containers) and pour into the drum through manhole door. (Do not
put solids in drum).
5. Light-up the boiler and raise the steam pressure gradually to 5 kg/cm² as per standard
operating procedure and maintain the pressure for minimum 12 hours.
6. Blow down once in two hours for 2 minutes to be given.
7. Samples are to be taken for every two hours and analysis is to be carried out to
determine the following.
1. pH
2. Total alkalinity
3. Oil
TRICHY
PROCEDURE FOR ALKALI BOILOUT(OIL/GAS FIRED BOILERS)
Project : M/s.BASF INDIA LIMITEDBoiler No.: BM018
Page 2 of 2
8. Ensure the pressure is maintained in the boiler for each stage of alkali boilout as
follows :-
For 20 kg/cm² pressure boiler:
DURATION
I Stage - 5 Kg/cm² - 12 Hours.
II Stage - 7 Kg/cm² - 12 Hours
III Stage - 10 Kg/cm² - 12 Hours
For 44 kg/cm² to 68 kg/cm² line pressure boilers
DURATION
I Stage - 7 Kg/cm² - 12 Hours.
II Stage - 10 Kg/cm² - 12 Hours
III Stage - 20 Kg/cm² - 12 Hours
9. Each stage of boiling can be terminated when the content of oil in the boiler water
maintains a steady value. However final reading of oil should be
5-10 ppm. Decision for termination will be based on requirement for specific boiler.
10. For each stage, after termination of boilout procedure, shut down the boiler and allow
the unit to cool down gradually.
11. Drain the boiler after the drum pressure reaches atmospheric pressure. Water jet shall
be used to clean the headers for each stage.
12. After complete draining of boiler, clean the complete unit by filling the water and drain it
for atleast one time for each stage.
Repeat the fill and drain until free from Alkalies.
The handhole pipes of all headers preferably at bottom most point to be cut and
inspected for any foreign material and cleaned using water jet.
13. After inspection and cleaning re-weld the end caps and hydro test the boiler to working
pressure.