bar chart 1

10
BAR CHART FOR CONSTRUCTION Name of Work :- Renovation work of UPPWD Building at Lucknow Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015 Contractor :- M/s R.K. Construction (India) Pvt.Ltd. Date of Start :-23.02.2015 Date of Complection :- 22.08.2015 Sl.No. Description of Item Fab-15 Mar-15 Apr-15 May-15 Jun-15 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 1 Excavation in Foundation 2 Piling Work for Front column 3 RCC/PCC work in foundatin 4 RCC Column and Beam work 5 Plaster repairing work 6 Brick work 7 Repair of wooden windows 8 Moulding/Cornice work 9 Putty and Painting work 10 Granite and stone Jali work 11 Fixinng of Railing post 12 Construction of RCC Dome 13 Foundation work mazine Floor 14 RCC work in Foundation 15 RCC work in Column for Mazine Floor 16 Brick work for Mazine Floor 17 RCC Slab for Mazine Floor 18 Sanitary work for Mazine Floor 19 Strengthing Of Old Damaged Arch 20 Plastering work for Mazine Floor 21 Flooring Work For Mazine Floor 22 Putty and Painting work 23 Door and Windows work

Upload: lkovijay

Post on 14-Apr-2016

8 views

Category:

Documents


3 download

DESCRIPTION

bar chart excel

TRANSCRIPT

Page 1: bar chart 1

BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow

Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015

Contractor :- M/s R.K. Construction (India) Pvt.Ltd.

Date of Start :-23.02.2015

Date of Complection :- 22.08.2015

Sl.No. Description of ItemFab-15 Mar-15 Apr-15 May-15 Jun-15

4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd

1 Excavation in Foundation

2 Piling Work for Front column

3 RCC/PCC work in foundatin

4 RCC Column and Beam work

5 Plaster repairing work

6 Brick work

7 Repair of wooden windows

8 Moulding/Cornice work

9 Putty and Painting work

10 Granite and stone Jali work

11 Fixinng of Railing post

12 Construction of RCC Dome

13 Foundation work mazine Floor

14 RCC work in Foundation

15 RCC work in Column for Mazine Floor

16 Brick work for Mazine Floor

17 RCC Slab for Mazine Floor

18 Sanitary work for Mazine Floor

19 Strengthing Of Old Damaged Arch

20 Plastering work for Mazine Floor

21 Flooring Work For Mazine Floor

22 Putty and Painting work

23 Door and Windows work

Page 2: bar chart 1

BAR CHART FOR CONSTRUCTION

Jun-15 Jul-15 Aug-154th 1st 2nd 3rd 4th 1st 2nd 3rd

Page 3: bar chart 1

BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow

Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015

Contractor :- M/s R.K. Construction (India) Pvt.Ltd.

Date of Start :-23.02.2015

Date of Complection :- 22.08.2015

Sl.No. Description of ItemUnit Total Qty

1 Excavation in Foundation fof front elevatin work Cum 220.12

2 Piling Work for Front column Metre 372.00

3 PCC work in foundatin Cum 101.38

4 RCC work in foundatin Cum 224.84

5 RCC work for elevation Column and Beam work Cum 336.07

6 Reinforcement Steel work in RCC Kg 133187.14

7 Brick work in foundation Cum 30.83

8 Brick work in Superstructure Cum 207.62

9 Brick work in arch work repair Cum 55.00

10 Plaster repairing work Sqm 12428.96

11 Putty and Painting work Sqm 18164.33

12 Waterproofing on roof top Sqm 1926.55

13 Repair of window frame with sal wood Cum 2.00

14 Structura Sttel work in window Grill Kg 3907.00

15 Repair of wooden windows Sqm 364.20

16 Removing old paint and polishing on windows shutter Sqm 1821.01

17 Granite work Sqm 177.60

18 Stone Jali work Sqm 111.20

19 Construction of Boundry wall railling piller Nos 4000.00

20 Construction of RCC Dome Cum 117.33

Page 4: bar chart 1

21 Excavation in Foundation work mazine Floor Cum 413.47

22 RCC work in Foundation Cum 83.77

23 RCC work in superstructure for Mazine Floor Cum 796.41

24 Repair of Sanitary work / water supply system LS 1.00

25 Strengthing Of Old Damaged Arch Sqm 500.00

Page 5: bar chart 1

BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow

Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015

Contractor :- M/s R.K. Construction (India) Pvt.Ltd.

Date of Start :-23.02.2015

Date of Complection :- 22.08.2015

Fab-15 Mar-15 Apr-15 May-15

4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st

Page 6: bar chart 1
Page 7: bar chart 1

BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow

Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015

Contractor :- M/s R.K. Construction (India) Pvt.Ltd.

Date of Start :-23.02.2015

Date of Complection :- 22.08.2015

May-15 Jun-15 Jul-15

2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd

Page 8: bar chart 1
Page 9: bar chart 1

BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow

Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015

Contractor :- M/s R.K. Construction (India) Pvt.Ltd.

Date of Start :-23.02.2015

Date of Complection :- 22.08.2015

Jul-15 Aug-15

4th 1st 2nd

Page 10: bar chart 1