BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow
Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015
Contractor :- M/s R.K. Construction (India) Pvt.Ltd.
Date of Start :-23.02.2015
Date of Complection :- 22.08.2015
Sl.No. Description of ItemFab-15 Mar-15 Apr-15 May-15 Jun-15
4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd
1 Excavation in Foundation
2 Piling Work for Front column
3 RCC/PCC work in foundatin
4 RCC Column and Beam work
5 Plaster repairing work
6 Brick work
7 Repair of wooden windows
8 Moulding/Cornice work
9 Putty and Painting work
10 Granite and stone Jali work
11 Fixinng of Railing post
12 Construction of RCC Dome
13 Foundation work mazine Floor
14 RCC work in Foundation
15 RCC work in Column for Mazine Floor
16 Brick work for Mazine Floor
17 RCC Slab for Mazine Floor
18 Sanitary work for Mazine Floor
19 Strengthing Of Old Damaged Arch
20 Plastering work for Mazine Floor
21 Flooring Work For Mazine Floor
22 Putty and Painting work
23 Door and Windows work
![Page 2: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/2.jpg)
BAR CHART FOR CONSTRUCTION
Jun-15 Jul-15 Aug-154th 1st 2nd 3rd 4th 1st 2nd 3rd
![Page 3: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/3.jpg)
BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow
Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015
Contractor :- M/s R.K. Construction (India) Pvt.Ltd.
Date of Start :-23.02.2015
Date of Complection :- 22.08.2015
Sl.No. Description of ItemUnit Total Qty
1 Excavation in Foundation fof front elevatin work Cum 220.12
2 Piling Work for Front column Metre 372.00
3 PCC work in foundatin Cum 101.38
4 RCC work in foundatin Cum 224.84
5 RCC work for elevation Column and Beam work Cum 336.07
6 Reinforcement Steel work in RCC Kg 133187.14
7 Brick work in foundation Cum 30.83
8 Brick work in Superstructure Cum 207.62
9 Brick work in arch work repair Cum 55.00
10 Plaster repairing work Sqm 12428.96
11 Putty and Painting work Sqm 18164.33
12 Waterproofing on roof top Sqm 1926.55
13 Repair of window frame with sal wood Cum 2.00
14 Structura Sttel work in window Grill Kg 3907.00
15 Repair of wooden windows Sqm 364.20
16 Removing old paint and polishing on windows shutter Sqm 1821.01
17 Granite work Sqm 177.60
18 Stone Jali work Sqm 111.20
19 Construction of Boundry wall railling piller Nos 4000.00
20 Construction of RCC Dome Cum 117.33
![Page 4: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/4.jpg)
21 Excavation in Foundation work mazine Floor Cum 413.47
22 RCC work in Foundation Cum 83.77
23 RCC work in superstructure for Mazine Floor Cum 796.41
24 Repair of Sanitary work / water supply system LS 1.00
25 Strengthing Of Old Damaged Arch Sqm 500.00
![Page 5: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/5.jpg)
BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow
Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015
Contractor :- M/s R.K. Construction (India) Pvt.Ltd.
Date of Start :-23.02.2015
Date of Complection :- 22.08.2015
Fab-15 Mar-15 Apr-15 May-15
4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st
![Page 6: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/6.jpg)
![Page 7: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/7.jpg)
BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow
Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015
Contractor :- M/s R.K. Construction (India) Pvt.Ltd.
Date of Start :-23.02.2015
Date of Complection :- 22.08.2015
May-15 Jun-15 Jul-15
2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd
![Page 8: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/8.jpg)
![Page 9: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/9.jpg)
BAR CHART FOR CONSTRUCTIONName of Work :- Renovation work of UPPWD Building at Lucknow
Agreement No. and Date :- 05/SE-39/2014-15 dated: 23.02.2015
Contractor :- M/s R.K. Construction (India) Pvt.Ltd.
Date of Start :-23.02.2015
Date of Complection :- 22.08.2015
Jul-15 Aug-15
4th 1st 2nd
![Page 10: bar chart 1](https://reader035.vdocuments.us/reader035/viewer/2022080304/56d6be3f1a28ab3016914ad3/html5/thumbnails/10.jpg)