BANGLADESH
Digitizing Implementation Monitoring and Public Procurement Project (Cr. 6077-BD)
Third Implementation Support Review
(November 27 to December 4, 2018)
Aide Memoire
1. During November 27 to December 4, 2018, a World Bank team1 carried out the third implementation
support review of the Digitizing Implementation Monitoring and Public Procurement Project (DIMAPPP). The
Aid Memoire (AM) summarizes the findings on the status of the project implementation, recommendations, and
agreements reached with the relevant agencies to take measures to expedite implementation. The AM was
discussed at the wrap-up meeting on December 4, 2018, with Mr. Abul Mansur Md Faizullah, Secretary-In-
Charge, IMED in the Chair. During the wrap up meeting, it was agreed to classify the aide memoire document as
“public”.
OVERALL STATUS AND KEY PROJECT DATA
2. Overall progress: The achievement of project development objective is considered as satisfactory in view
of the progress of implementation of the project. There is good progress in implementing the project activities
with three major contracts signed. The results framework is in Annex 3.
3. Key project data: The key project data is provided below.
Table 1: Key Project Data
Board Approval 07/28/2017
Effectiveness Date 10/08/2017
Closing Date of IDA Credit 06/30/2022
IDA Credit Amount SDR 40.2 M
Amount Disbursed 17%
KEY POINTS DISCUSSED AND AGREED ACTIONS
4. The Central Procurement Technical Unit (CPTU) under the Implementation Monitoring and Evaluation
Division (IMED) of the Ministry of Planning is responsible for implementing the project. The Local Government
Engineering Department (LGED) is assisting CPTU with the specific implementation of electronic government
procurement (e-GP) in all local government institutions (LGIs) and their capacity development. The key points of
discussions and component-wise agreed actions are provided below, with timebound action plan in Table 1 and
details in three Annexes.
5. Component 1: Restructuring CPTU and Institutionalizing e-GP: It has two components: restructuring
CPTU into an Authority with more regulatory power and institutionalizing electronic government procurement
(e-GP) to function as a service provider with adequately staffed professional resources. Few months back, the
Prime Minister in principle already provided concurrence to the formation of such an Authority. Now, the draft
new law for the proposed Authority (Bangladesh Public Procurement Authority- BPPA) along with the
amendment of the existing Public Procurement Act (PPA) is at the final stage of submission to the Cabinet for its
in-principle approval that earlier went through several rounds of iterations and extensive consultations. After the
1 Messrs./Mmes. Zafrul Islam (Lead Procurement Specialist & Team Leader), Ishtiak Siddique (Sr. Procurement Specialist), Masud Mozammel (Sr.
Communications Officer), Mehrin A. Mahbub (Sr. Communications Officer), ANM Mustafizur Rahman (Sr. Procurement Specialist), Maxwell B. Dapaah
(Sr. Financial Management Specialist), Arafat Ishtiak (Procurement Specialist), Md Kamruzzaman (Procurement Specialist), Omar. F. Khandaker (Sr. IT Security Specialist), Shazia Amina Ahmed (Public Policy and Stakeholders Consultant), SM Hafiz Al Mamun (Project Support Consultant), and
Mahmuda Nusrat Hussain (Team Associate). Besides, Joseph Fagan (Sr. e-GP Consultant) provided input on-line.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
Cabinet approval, it will be placed to the Parliament. CPTU informs that enactment of the Law may take up to
April 2019 in view of the imminent general election in late December 2018. Nevertheless, the Bank review team
emphasized the need of concurrently finalizing the organogram of the Authority and associated regulations (if
applicable), to avoid delay in the implementation of the Law, once the Parliament passes it. Concerning e-GP,
although CPTU has further strengthened its own IT staffing resources as per the transition plan, couple of positions
are still to be filled up (web developer: international -1; local- 2).
6. Component 2: Enhancing Digitization of Public Procurement: This component aims to enhance the
scope of e-GP for all public-sector organizations across the country, with specific focus on the 28 newly selected
public-sector organizations (NSPSOs), covering about 3,000 procuring entities, followed by 4 previously selected
PSOs (PSPSOs). Of those NSPSOs, Local Government Institutions (LGIs) under the local government division
alone comprises 888 procuring entities. Other key activities include overall enhancement of the e-GP system with
more advanced features, like, robust contract management process including payments, geo-tagging, international
bidding, business modeling, national tenderers’ database.
7. Expansion of the use of e-GP is progressing fast in high momentum. Out of about 1359 procuring
organizations in Bangladesh, 1273 organizations are already registered in the e-GP system up to November 30,
2018. As of November 2018, over 52,000 tenderers have been registered in the system, with about 230,000
invitations of tender, valued $24 billion. The progress of major procurement under this component is moderate.
While few major procurement contracts are in good progress (signed or completed), yet a few other critical
activities are lagging: (i) CPTU- the development of contract management module; selection of firm for e-GP
training, and consulting firm for e-GP system enhancement; (ii) LGED- selection of consulting firm for capacity
development of the LGIs and LGED. Other agreements with CPTU involves: making available computers and
accessories in all 28 NSPSOs covering about 3000 procuring entities.
8. Component 3: Professionalizing Procurement and Citizen Engagement: This component aims to
improve public service delivery by operationalizing procurement cell/unit in the 32 SPSOs with 3-10 procurement
professionals, improving procurement management capacity of the 32 selected PSOs (SPSOs) and capacity of the
bidding community, enhancing citizens monitoring of public procurement at decentralized level (48 upazillas),
institutionalizing government-contractors forum (GTF), initiating open contracting data standard (OCDS) vis-a-
vis public disclosure of procurement information through citizen portal (supply and demand side governance).
9. As of November 2018, out of the 28, 27 NSPSOs have formed procurement cell/unit. To ensure
appropriateness of their skills to be able to serve as the knowledge bank of those NSPSOs, ITC-ILO/Turin will
review their qualifications and experience within the next couple of months and share reports. ITC-ILO, as the
key service provider for capacity development with the largest contract in the project, is onboard since mid-
October 2018. The Team Leader of ITC-ILO is available; however, other initial start-up activities appear slow.
The review team emphasized the need to make all relevant key staff available as per the provisions of the contract.
Also, the citizen engagement tasks by BRAC Institute of Governance and Development (BIGD), an affiliate of
the BRAC university, are behind schedule specifically starting the physical implementation of citizen monitoring
of procurement at upazilla level. Institutionalizing GTF as part of the behavioral change communication, a task of
Bangladesh Center for Communication Program (BCCP) needs to be expedited. The hiring of consultant for
developing the citizen portal is at the request for proposal stage. CPTU needs to expedite the selection of M&E
consultant and share the ToR with the Bank. CPTU is behind schedule on the actual implementation of OCDS
activities as the e-GP contract management module is yet to be completed.
10. Component 4: Digitizing Project Implementation Monitoring: The component aims to strengthen
implementation monitoring of development programs/projects at national level using digital technology. Although
some progress has been made in the selection of firm for need assessment, the overall progress of this component
is delayed substantially. The need assessment task is delayed over six months (September 2018 to March 2019)
which will have large impact on the making of parallel arrangements for the selection of firm for PMIS updating
including the existing PMIS framework, evaluation strategy, and research unit. Also, the IMED office refurbishing
contract is delayed which IMED now expects to sign within December 15, 2018.
3
FIDUCIARY COMPLIANCE AND SAFEGUARD MANAGEMENT
11. Fiduciary Performance: The overall fiduciary performance is moderately satisfactory (combined
procurement and financial management). Details are provided below.
12. Procurement Performance: The procurement performance is moderately satisfactory (MS). Procurement
consultant has been on boarded in CPTU. Both CPTU and LGED have completed the procurement process of few
major contracts of the Project. However, CPTU is yet to issue the REOI and Terms of Reference of Consulting
Services for eGP enhancement and operation and maintenance (CPTU/S-02). Also, CPTU needs to finalize
quantities for supply of computers and accessories for PEs of 28 NSPSOs. These two packages are now critical
for CPTU to start the bidding process to ensure the timely transition to the new contract for overall e-GP
enhancement and increase the use of eGP. IMED/ CPTU also needs to expedite the preparation of ToR of
consulting services for design /update on-line PMIS for IMED (CPTU/S-07) for which another consulting firm
has been engaged to assess the need. LGED is at the evaluation process of goods package for the supply of IT
Equipment to 491 LGIs (Upazila Parishad) under Package LGED/G – 06. Regarding the use of STEP (Systematic
Tracking of Exchange in Procurement), LGED duly uploads document and information of post review packages
as and when the procurement activities take place, however, CPTU has some post review packages (5) already
awarded but procurement document and information yet to be uploaded in STEP.
13. Financial Management (FM) Performance: FM performance is moderately satisfactory. IUFRs are
submitted on time and deemed satisfactory. The project is also adequately staffed with one qualified accountant
and one financial management officer at CPTU. At LGED one Junior Financial Management Specialist is working
for record keeping and reporting. Both in CPTU and LGED, a single person has authority for signing the checks
for all payments under the project. Both CPTU and LGED informs, however, that they follow the Government’s
standard practice as approved by the ministry of Finance. Considering better risk management, the Bank team
nevertheless requested to look into the matter further. For asset management, the team recommends that CPTU
explores introduction of on-line system for asset tracking like LGED (ProInfo) and LGED also incorporates
features like the value, funding source, asset number, etc. For conducting internal audit, CPTU will hire an external
professional auditing firm. With TOR acceptable to the Bank. CPTU is required to make its accounting software
(TALLY) more user friendly and functional so that it can capture category wise report.
14. Disbursement Status: As of November 30, 2018, disbursement is about 17% (USD 9.62 million). Based
on information provided by the project, an amount of BDT 567.11 million has been incurred as expenditure as of
November 30, 2018.
15. Environmental Safeguards: The project is Category “C”, with no major civil construction works. For IT
equipment procurement and disposal, LGED has incorporated ECoP (Environmental Code of Practice)
requirements in the tender documents for computers/ equipment etc. CPTU will need to incorporate similar
provisions in its tender documents for planned procurement of computers.
NEXT REVIEW
16. The next implementation support review is tentatively planned for late April/ early May 2019, in addition
to the continuous supervision of the project.
Table 1: Summary of Agreed Actions
Activities Responsibility Agreed timeline
Component 1: Restructuring CPTU and Institutionalizing e-GP
1 Approval from the Cabinet in principle on draft law of the proposed
BPPA and amendment of PPA, after completion of all requirements
including the Bank’s review.
CPTU January 31, 2019
Final Approval from Cabinet after vetting of Ministry of Law March 31, 2019
Placement of the Law to Parliament April 15, 2019
4
Activities Responsibility Agreed timeline
Share with the Bank the draft organogram and staffing of the
proposed Authority (job description with proposed scale)
February 15, 2019
2 Share with the Bank draft (i) 7 national tender documents in Bangla,
and (ii) remaining 5 documents
CPTU/
MIDAS
December 15, 2018
April 30, 2019
3 Hire three remaining web developers/specialists as CPTU’s in-house
resources (national: 2, international: 1)
CPTU January 31, 2019
Component 2: Enhancing Digitization of Public Procurement
4 Share with Bank the shortlist of consulting firm and RFP for
providing e-GP training (NSPSOs and bidders)
CPTU January 31, 2019
Share with the Bank Technical Evaluation report March 31, 2019
Share with the Bank draft negotiated contract April 30, 2019
Sign Contract May 15, 2019
5 Issue REOI for overall e-GP system enhancement CPTU December 15, 2018
Share with the Bank short list and draft RFP February 15, 2019
Share with the Bank Technical Evaluation report April 15, 2019
Share with the Bank draft negotiated contract May 15, 2019
Sign contract May 30, 2019
6 Share with the Bank draft bidding documents for procurement of
computers for 28 NSPSOs covering 2000 PEs
CPTU December 31, 2108
Share with the Bank bid evaluation report March 7, 2019
Sign contract March 31, 2019
Make available required computers and accessories in NSPSOs June 15, 2019
7 Make onboard the system architecture consultant for need
assessment of e-GP upgradation (Jboss – EAP 7.1 with Java 10)
CPTU/ GSS
Infotech/
Dohatec
December 15, 2018
Need assessment report from system architecture consultant January 25, 2019
Procurement of the system based on need assessment, potentially
Jboss – EAP 7.1 with Java 10
February 28, 2019
Build environment on the new system to implement eGP modules March 31, 2019
8 Share with the Bank final e-GP modules with detailed features:
Contract Management
CPTU/ GSS
Infotech/
Dohatec
January 31, 2019
Complete development of all modules for contract management February 28, 2019
Start piloting and testing the contract management module in e-GP
in four PSPSOs (RHD, LGED, BWDB, BREB)
March 31, 2019
Prepare a roll-out plan for implementation of e-contract management
across public sector agencies
April 30, 2019
9 Share with the Bank International bidding document- goods (e-PG4) CPTU/ GSS
Infotech/
Dohatec
December 15, 2018
Share with the Bank e-GP modules with detailed features:
International bidding document
January 31, 2019
Start piloting of international bidding in e-GP March 31, 2019
10 Final approval on e-GP modules with detailed features: national
tenderers’ database and data entry from Tenderer
CPTU/ GSS
Infotech/
Dohatec
March 31, 2019
11 Share with the Bank time extension request for the 6 helpdesk
executives
CPTU December 20, 2018
12 Make onboard the consultants for e-GP training and capacity
development of the Local Government Institutions (888)
LGED February 15, 2019
Component 3: Professionalizing Procurement and Citizen Engagement
13 Complete creation of specific procurement unit/cell in each SPSO
with identified skilled officials to serve as procurement knowledge
bank for the organization
32 SPSOs December 31, 2018
14 Make available the core key staffs for the capacity development
contract (6 P)
ITC-ILO January 15, 2018
Start 3 weeks training by consultant for capacity development and
professionalization (ITC-ILO)
CPTU/ ITC-
ILO
January 15, 2018
5
Activities Responsibility Agreed timeline
Uploading training calendar in the website January 15, 2019
Developing new training modules by ITC-ILO March 15, 2019
Share a draft Disposal Policy with CPTU and the Bank ITC-ILO April 30, 2019
15 Share with the Bank TOR of M&E consultant (CQS) CPTU December 20, 2018
Sign contract with the selected M&E consultant after completing all
procurement steps and procedural requirements
March 31, 2019
16 Finalize the array of data/ fields that will be disclosed in public
under the open contracting data standard (OCDS)
CPTU March 31, 2019
17 Receive proposal from the top ranked firm for developing citizen
portal
CPTU December 20, 2018
Sign contract with the selected firm January 20, 2019
18 Share with the Bank revised TOR of PPSC by BIGD CPTU/BIGD December 10, 2018
19 Start implementation of citizen monitoring of procurement at the
pre-identified upazilla
BIGD January 31, 2019
20 Arrange PPSC meeting CPTU/BIGD February 7, 2019
21 Share with the Bank strategic methodology for institutionalization
and sustainability of Central BGTF by consultant (BCCP)
CPTU/ BCCP December 31, 2018
Create Central BGTF with its branches at least at division level (8) April 30, 2019
Component 4: Digitizing Project Implementation Monitoring
22 Share with the Bank the need assessment report from Consultant in
strengthening IMED (PMIS framework, evaluation strategy, research
unit, possible disclosure of data in citizen portal)
IMED February 28, 2019
23 Share with the Bank TOR for design/updating of IMED’s on-line
PMIS for digital monitoring of project implementation
IMED March 31, 2019
Issue the REOI for designing/updating the on-line PMIS (based on
consultant’s report under item 22 above) after Bank’s review
April 7, 2019
Make the PMIS design/updating consultant onboard (PMIS) after
completing all requirements of review by the Bank
June 30, 2019
24 Sign contract with the selected firm for IMED refurbishing work IMED December 15, 2018
Complete refurbishing of IMED’s office March 15, 2019
25 Develop a comprehensive system (monitoring tools and techniques,
guidelines, data analytics and research, and on-line reporting)
IMED September 30,
2019
Procurement and Financial Management (FM) Performance
26 Hire external professional audit firm to carry out internal audit with
TOR acceptable to the Bank
CPTU February 28, 2019
27 Provide all project assets and share report with the Bank CPTU/ LGED January 31, 2019
28 Submit the first audited financial statements (FY 2017-18). CPTU December 31, 2018
Attachments:
Annex 1: List of Key Persons Met
Annex 2: Component Details (as applicable) & Fiduciary Aspects
Annex 3: Project Results Framework
6
Annex 1
List of Key Persons Met
Implementation Monitoring and Evaluation Division/ CPTU:
Mr. Md. Mofizul Islam, Secretary, IMED
Mr. Abul Mansur Md. Faizullah, Secretary-In-Charge, IMED
Mr. Faruque Hossain, Director General (Additional Secretary), CPTU
Mr. Md. Mahmudul Haque, Joint Secretary, IMED
Mr. Zehsan Islam, Director/CPTU & DIMAPPP Component 1 Director
Mr. Md. Aziz Taher Khan, Director/CPTU & DIMAPPP Component 2 Director
Mr. Shish Haider Chowdhury, Director/CPTU & DIMAPPP Component 3 Director
Mr. Mohammad Habibul Islam, Director/IMED & DIMAPPP Component 4 Director
Mr. Mujibul Ferdous, Director/IMED & DIMAPPP Component 4 Director
Mr. Md Shamimul Haque, Director, CPTU
Mr. Masud Akhter Khan, Director, CPTU
Mr. Md. Mosharraf Hussain, Sr. System Analyst, CPTU
Ms. Moushumi Habib, Deputy Director, CPTU
Mr. Md. Salah Uddin, Deputy Director, CPTU
Ms. Fatima Tuz Johora Thakur, Assistant Director, IMED
Mr. AKM Fazlul Karim, Procurement Reform Implementation Advisor, CPTU
Mr. Md. Mosta Gausul Hoque, Principal Project Management Consultant, CPTU
Mr. Syed Sarwar Hussain, Senior Procurement Consultant, CPTU
Mr. Shafiul Alam, Sr. Communications Consultant, CPTU
Mr. Ashfakul Islam, Sr. e-GP Management Consultant, CPTU
Mr. Mohammad Hafizur Rahman, Sr. Programmer, CPTU
Mr. Asad Ibne Moin, Security Assurance Consultant, CPTU
Mr. Md. Abu Saker Chowdhury, Call Center Manager, CPTU
Mr. Md. Mr. Mohammad Asadul Hoque, System Analyst, CPTU
Mr. Engr. Mohammad Ariful Islam, System Analyst, CPTU
Mr. Md. Zumshedul Abedin Chowdhury, System Administrator, CPTU
Mr. Abid Hossain, Application Administrator, CPTU
Ms. Naznin Nahar, Programmer, CPTU
Mr. Sk. Shariful Islam, Assist. Maintenance Engr., CPTU
Mr. Mohammad Salim, Sr. Financial Management Consultant, CPTU
Mr. Mohammad. Taherul Islam, FMC, CPTU
Mr. Lutful Muyeed, Database Administrator, CPTU
LGED:
Mr. Md. Abul Kalam Azad, Chief Engineer, LGED
Mr. Khondokar Ali Noor, Additional Chief Engineer, LGED
Mr. Abdus Sattar, Executive Engr & Focal Person & DIMAPPP PIT Member
Mr. Md. Abdus Salam Mondol, Superintent Engineer, Faridpur Region, LGED
Mr. Md. Noor Hossain, Executive Engr, Faridpur, LGED
Mr. Bimol Kumar Das, Executive Engr, Faridpur Region, LGED
Mr. Muhammad Shariful Islam, Senior Assistant Engineer, LGED
Agencies (SPSOs and NSPSOs):
Ms. Regia Begum, CAO, Office of Chief Accounts Officer, Hisab Bhaban, Segunbagicha
Mr. Saiful Islam, DD (Procurement), Directorate of Primary Education
Mr. Kazi mohammad Mahbubul Haque, Sr. System Analyst, RAJUK
Mr. S.M.Anwar Satter, Dhaka WASA
Md. Rezaul Karim Sheikh, Deputy Project Director, DG Food
7
Mr. Kaium Miah, Upazila Agriculture Officer, DAE
Mr. Md. Sultanul Arefin, Asst. Sytem Analyst, BIWTA
Ms. Humaira Binte Reza, Executive Engineer, PWD
Mr. Engr. A. F.M. Mizanur Rahman, Attached Officer, ICT cell, DTE
Mr. Md. Jahangir Alam, Director (P&D), DTE
Ms. Mazeda Begum, Desk Officer-Procurement, CMSD
Mr. Zafar Sadeque, Chief Engineer (P&O), BREB
Mr. Md. Yousuf Khan, Deputy Chief, DoF
Ms. Kazi Sayeda Momtaz, Sr. System Analyst, RHD
Mr. Md. Hamidul Islam Prodhan, System Analyst, Bangladesh Police, Police HQ, Dhaka
Mr. Engr. Md. Nazrul Islam, PD, DPHE
Mr. Md. Rafiqul Islam, Procurement Officer & DPM, DGFP
Mr. Sumon Kumar Shorma, Deputy Controller, Controller General of Accounts/Accounts
Mr. Manzoor Alam, System Analyst, Directorate of Food
Mr. Mamunur Hossen, Programmer, National Curriculum and Textbook Board
Mr. Md. Abdus Sattar, Executive Engineer (Proc.), LGED
Mr. Shafiqul Basher, System Analyst, Chittagong WASA
Mr. Md. Monirul Islam, Director, Contract & Procurement, BWDB
Mr. Engr. Mir Muazzem Hussain, Executive Engineer, EED
Mr. Mohammad Anisur Rahman, Deputy Director, DSHE
Mr. Md. Abdul Hamid, Executive Engineer, HED
Mr. Md. Zakir Hussain, Sr. Faculty, ESCB
Md. Sarower Murshed, Sub-Divisional Engineer, BPDB
GTF:
20 members of Government Tenderers Forum, Faridpur
BCCP:
Ms. Khadija Bilkis, Team Leader, BCCP
Ms. Meher Afroz, Deputy Director, BCCP
BIGD:
Dr. Imran Matin, Executive Director, BIGD
Dr. Mirza M. Hassan, Team Leader, Citizen Engagement, BIGD
Mr. Ahmed Asif Enam, Research Associate, BIGD
Dohatec/GSS Infotech/PWC/CNS Limited/Midas/ Thakral:
Mr. A.K.M Shamsuddoha, President, Dohatec
Mr. Nazmul Islam Bhuiyan, Deputy Team Leader, Dohatec
Mr. Raj Peesa, SVI-Sales & Operation, GSS Infotech
Mr. Joseph George, Team Leader, GSS Infotech
Dr. A.S.M. Mashi-Ur-Rahman, Managing Director, MIDAS
Mr. Kamrul Islam, Deputy General Manager, CNS Limited
Mr. Mohammad Masud, Manager, Sales, Thakral Information Systems Pvt. Ltd.
ITC-ILO/Turin:
Mr. Ralf Krueger, Manager, Sustainable Development Program
Mr. Richard Lorenz, Team Leader.
8
Annex2
Component Details (as applicable) & Fiduciary Aspects
Component 1: Restructuring CPTU and Institutionalizing e-GP
This component aims to restructure the CPTU in order to enhance its regulatory power and institutionalize e-GP
to function as a service provider with professional resources. Two major sub-components with progress is as
follows.
Component 1.1: Restructuring CPTU and Furthering Policy Reform
Major activities include: (i) framing of necessary law for restructuring CPTU into an Authority (Bangladesh
Public Procurement Authority- BPPA); (ii) revising/amending the Public procurement Act 2006 (PPA) to
incorporate necessary changes arising out of the proposed BPPA along with advanced procurement features like
framework agreement, sustainable procurement; gender equity, quality-based selection, etc.; (iii) drafting
remaining key tender documents including Bangla version for the identified national tender documents.
It is lagging by few months. The law for BPPA has been consulted widely in a few workshops involving all
stakeholders covering major ministries and procurement organizations, bidding community and business apex
bodies; civil society organizations; academia; and key development partners. Subsequently it was placed at the
CPTU website for public comments. All comment at various stages were then reviewed in detail in a series of
meeting at CPTU including at the final stage involving Secretary, IMED. Earlier about couple of months back,
the Prime Minister has given her consent in principle on the formation of BPPA. The law is now at its final stage
of submission to the Cabinet for approval following GOB internal process. Concurrently, the amendment of the
PPA is also drafted and finalized. Given that the process has been delayed already by few months, the review
team requested CPTU to expedite the subsequent steps. CPTU is expecting to place to the Parliament both the
drafts, that is, BPPA Act and amendment of PPA, at the same time around mid-April 2019 after fulfilling all
internal requirements (Ministry of Planning, Cabinet, Ministry of Law).
There are few remaining bidding documents to be drafted including drafting Bangla version of a few national
tender documents.
Component 1.2: Institutionalizing e-GP
Major activities include: (i) strengthening e-GP staffing of CPTU; (ii) putting in place IT Security Protocol with
system control functions; (iii) issuing the revised e-GP guidelines; and (iv) developing skills in CPTU in the
overall management of the e-GP system. All planned IT key staff are in place except a three positions of web
developers/specialists (international- 1, and national- 2). CPTU is expected to issue shortly the IT Security
Protocol after incorporating Bank’s comments. Also, CPTU will need to issue the revised e-GP guidelines that
has been recently updated in light of the experience of e-GP implementation in the last few years and
changes/adjustments in the PPA.
Component 2: Enhancing Digitization of Public Procurement
This component aims to enhance the existing e-GP system both in terms of its technology and widening
scope across the entire public-sector organizations, and e-contract management including payments. It has two
sub-components and progress is summarized below.
Component 2.1: Expansion of e-GP system
9
There have been extensive efforts in enhancing the scope of e-GP with greater awareness and ownership of
the key stakeholders that is procuring entities and the bidding community. This has resulted in exponential growth
of the use of e-GP as demonstrated in the below graph. Also, most organizations are appreciating and commending
the role of CPTU in operating its 24X7 helpdesk to provide as much as possible instant support and/or solutions
(e.g., Land Port Authority, SNSP Project Office).
The review team had an update on the progress of current activities for enhancing digitization of public
procurement. The CPTU will need to move quickly to issue the REOI for the selection of firm for e-GP system
enhancement (Package S-02) after incorporating Bank’s comments in the TOR. The selected firm is expected to
take over the e-GP system operation and management including transition/lap-over at the end of the current
contract extension of the existing firm (June 2019). The earlier the firm can be recruited the better to ensure there
is sufficient time to support the knowledge transfer and allow the best approach for enhancing the e-GP system
over the next 5 -10 years. Any delays with the recruitment of the new firm may have an impact on ensuring a
stable system environment during the transition period.
Cybersecurity threat mitigation is a continuous challenge and new threats are evolving every day. To
protect e-GP system from evolving cyber threats - continuous monitoring, regular security patches update,
vulnerability assessment and execution of Information Security Policies controls are needed. The Bank already
reviewed the Information Security Policy of e-GP system and provided feedback to CPTU. CPTU needs to finalize
the Information Security Policy and publish it for all the stakeholders of e-GP. Bank also reviewed the e-GP
Guidelines document and provided feedback to CPTU. The review team suggested to review the Information
Security and other policies execution status of e-GP monthly. CPTU shared the BCC Scan Report on e-GP system,
Internal Audit Report of Q1 with vulnerability scan and Internal Audit Report of Q2 with vulnerability scan with
the World Bank. Also, CPTU will need to share the comprehensive Quarterly Vulnerability Assessment Report
on e-GP System with the World Bank in each Quarter as soon as quarterly vulnerability scan is completed.
Component 2.2: Implementation of Contract Management
The development of the electronic Contract Management (e-CM) module is now at the advanced stage
after a substantial delay. A number of e-GP modules/forms’ data structure and features (e.g., particular conditions
of contract, form for work plan etc.) are undergoing changes to facilitate smooth operation of the e-CM. Besides,
with the new features, the procuring entities will now be able to prepare the complete contract documents through
the system and communicate electronically to the winning bidder as part of the electronic notification of award.
The preparation of the contract document will mostly take the advantages of auto filled/calculated information
from the tender document, tender submitted by the winning tenderer, and recommendation of the tender evaluation
committee. The winning tenderer will now be able to complete their part of the information in the contract
document (e.g., bank account information, contact person etc.) and accept the contract electronically. Contract
management module at the initial phase has the following features – update the work plan (milestones), register
actual progress as per the work plan, preparation and approval of the measurements of works as per the bill of
10
quantities, preparation and approval of invoices, view physical and financial progress of the contract at any point
of time, amend the contract including time extension and variation order, additional delivery/extra work, issue
work completion and part completion certificates etc. Work completion certificates/information in-turn will be
stored in the contractors’ database that is also under development.
Going forward, the contractors’ database will be linked with tender submission forms and tender
evaluation report which will ease the tender submission and evaluation efforts as the tenderers will only mention
the unique work completion certificate number in their tender and the system will auto-fill and verify all relevant
information. It will also greatly increase the efficiency of the system, reduce tender evaluation time and possibility
of submitting fake work experiences by the tenderers. The facilities for uploading geo tagged images will be
included in the next phase of development. It was agreed that the features of the complete e-CM module (Phase-
1) will be finalized by December 15, 2018. The developer will complete the development of the module (Phase-
1) including the related features listed above by February 28, 2018 and will start internal piloting of the module
by March 31, 2019.
Component 3: Professionalizing Procurement and Citizen Engagement
This component aims to improve procurement management capacity of the SPSOs and capacity of the
bidding community. The sub-component will encourage creation of knowledge base, analytical tasks, and research
and development. Concurrently, it will attempt to create a citizen monitoring mechanism of local level contracts
with specific reference to rural roads, education, and health service deliveries. Five subcomponents progress are
summarized below:
Component 3.1: Improving Procurement Management of SPSOs, IMED and CPTU
The key activity is to create and operationalize a procurement cell in each of the 28 NSPSOs, comprising
3-10 members depending on the organization. This cell will function as knowledge bank for the respective
organization. As of November 30, a total of 27 NSPSOs have formed procurement cell and staffed them. The
review team informed CPTU and NSPSOs that ITC-ILO will review the appropriateness of qualifications and
experience of the cell members and shar report based on which strengthening measures by March 31, 2019, if
requires any, will be undertaken. All remaining NSPSOs will complete formation of cell by December 31, 2018.
Component 3.2: Capacity Building and Professionalization of Procurement
The key consultant ITC-ILO is behind schedule and has just started their initial start-up activities. They
need to mobilize all their key staff, beyond the Team Leader, within mid-December 2018 so that the main three
week course can start as planned within December 15, 2018. Also, ITC-ILO will need to provide a detailed initial
plan at least for the initial six months for training of main courses and short courses covering 17 types of audience.
Component 3.3: Disclosure of Public Procurement Information in Open Data Format
This sub-component refers to establishment of transparency in public procurement with disclosure of supply-
driven data from the CPTU side, especially the e-GP data. The CPTU will decide on the category of data to be
disclosed on the Citizen Portal at this stage. CPTU will need to prepare a strategy on Open Contracting Data
Standard as soon as possible.
Component 3.4: Citizen Engagement
The two key activities of citizen engagement (CE) sub-component include: local level citizens’
monitoring and national level dialogue under the platform of Public-Private Stakeholders Committee (PPSC). The
implementing consultant for this sub-component, BRAC Institute of Governance & Development (BIGD), has
finalized the selection of the 48 upazilas (sub-districts) where the local level monitoring will be taking place.
11
BIGD is still in the process of finalizing the formalities including the TOR in engaging the partnering NGO,
BRAC’s Community Empowerment Program (CEP). The CEP will primarily manage the implementation of
different activities of local level citizens’ monitoring of procurement. With regards to the implementation of PPSC
activities, BIGD is revising the TOR of the PPSC following comments from the CPTU and the World Bank.
Following key actions were agreed:
- First PPSC meeting will be organized in late January or early February 2019;
- Start implementation of citizen monitoring of procurement contract at upazilla level by January 31, 2019.
Citizen Portal:
The expected outcome of this portal in Bangla at CPTU is to establish a culture of openness and promote
dialogue on public procurement for better service delivery which will eventually lead to greater transparency. The
portal will share/publish information related to public procurement process across the country. The Portal will
have two key features: Supply side of good governance from data available in the government procurement
system, and demand side of governance with data from the beneficiaries and citizens. The Portal would include
information stemming from e-GP system, local level citizen engagement activities, Government-Tenderers Forum
(GTF), PPSC discussions, etc. The Citizen Portal will be an information repository comprising both supply and
demand-driven data. The selection of the main consultant for the Citizen Portal is at the final stage and is expected
to be onboard in next couple of months.
Component 3.5: Behavioral Change and Strategic Communication
The main consultant for the strategic and behavior change communication, Bangladesh Center for
Communication Program (BCCP) has updated the communication strategy for DIMAPPP and organizing to
implement the various activities of GTF. Given the recommendations of a recent workshop on this it is anticipated
that creation of an apex GTF body and inclusion of provision for dialogues and citizen engagement in the Public
Procurement Rules-2008 may be necessary. Following key actions were agreed:
- Finalizing selection of Consultant for Citizens’ Portal;
- Finalizing TOR for PPSC.
Component 4: Digitizing Project Implementation Monitoring
At the national level, program/ project implementation monitoring and evaluation is the responsibility of
the Implementation Monitoring and Evaluation Division (IMED) of the Ministry of Planning. IMED expressed
its commitment to streamline the monitoring process and making it on-line through a single platform connecting
all public-sector organization.
This component is substantially delayed. The need assessment consultant (Computer Network System) has
submitted the inception report. The consultant will formulate the requirements for the modernized system to
support IMED current and future needs and to integrate with the e-GP and contract management system. The
consultant will review the existing PMIS system, monitoring tools and techniques and Data Analytics including
reporting parts and firm will prepare the TOR for main consultant for developing PMIS. They are expected to
submit their final report by March 2019. Based on this assessment and associated TOR, the main firm for updating
the PMIS system will be appointed. Also, other contract for the office refurbishing of IMED is expected to be
signed within mid- December 2018.
Procurement:
The procurement performance is moderately satisfactory. Although CPTU signed three major contracts
(capacity development, citizen engagement, and behavioral change communication), it is lagging in other
procurement. CPTU will need to process the e-GP system enhancement contract as soon as possible. Earlier the
12
Bank provided comments on the TOR. Also, it needs to expedite the selection of firm for e-GP training which is
delayed. The key individual consultants are already on boarded except three web developers (international- 1, and
national- 2). The procurement packages of LGED part are generally on track with some marginal delay. There is
no significant procurement progress in component 4 (IMED). Both CPTU and LGED are using STEP for
procurement plan update. CPTU needs to store all information and documentation in STEP for procurement post
review packages.
Financial Management:
Overall assessment
The FM rating for the project is rated as moderately satisfactory. IUFRs are submitted on time and deemed
satisfactory. The project is also adequately staffed with one qualified accountant and one financial management
officer at IPTU.
At LGED one Junior Financial Management Specialist is responsible for record keeping and reporting. The
Executive Engineer (Project Manager) is the single authority for signing the checks for all payments under the
project. This is also the case at CPTU. Although this seems to be a common practice for projects in Bangladesh,
The Bank team would like to highlight that there are risks with such an arrangement. Both CPTU and LGED
informs however that they follow the Government’s standard practice as approved by the Ministry of Finance.
Considering better risk management, the Bank team, however, requests to look into the matter further. This is best
practice in many jurisdictions and consistent with proper internal controls around check issuance.
Also, in review of sampled transactions at CPTU, we noted that Advances made to vendors are treated as
expenditure. Without any supporting documents indicating delivery of good or services it is inaccurate to treat
such an Advance as expense. The FM team was advised to keep track of Advances in the IUFRs and as well as in
the Bank reconciliations and only treat the portion for which goods or services have been delivered as an expense
within the relevant period.
Moreover, no record of fixed assets is kept at CPTU although, at LGED a bespoke system called ProInfo is being
developed to keep a records of assets distributed to implementing entities in local districts. Some key aspect of
asset records such as the value, funding source, and asset number are however missing from the system. The
Mission recommended this additional information be included in the system. The mission also advised CPTU to
visit LGED to study the system and to determine if CPTU can have access, and also make inputs without having
to acquire or developing a new fixed asset record system.
Per the PAD, at least two internal audits will be carried out by an external professional auditing firm in the lifetime
of the project. The project team was reminder of this and asked to initiate the hiring process. To initiate the first
round of internal audit by an external professional auditing firm, the project will share a draft Terms of Reference
(ToR) with the Bank for its review and concurrence.
Finally, the project team was reminded that Annual Audit report for the project is due on December 30, 2018.
Staffing: The project is adequately staffed including a Senior Financial Management Consultant and a Financial
Management Consultant to deal with day to day financial management affairs.
Internal Control (including internal audit): The project retains copy of supporting documents for all project’s
related transactions except for copy of deliverables and contract. The mission recommends that all supporting
documents which includes copy of contracts, deliverables etc. (at least copy of some sample pages) must be filed
with payment voucher ensuring audit trail to facilitate internal and external audits, as well as reviews by the Bank.
The project does not maintain any fixed assets register and the mission found lack of control over assets
management of the project. The mission noted that the Project’s consultants have been paid for procuring of
computer/laptop out of reimbursable expenses of consultant’s contract amount but the asset was not recorded
13
under the list of project assets. The mission didn’t find any record or document on disclaimer of restoring these
assets from the consultant at end of service period. The project team is requested to include an addendum to the
claim document of the consultant that the laptop is an asset of the GoB and that it should be returned after the
short-term assignment is over. The mission also recommends that an annual verification of all project assets shall
be carried out and a summarized report shall be shared with the Bank by December 31, 2018. As agreed, the
internal audits will be carried out by an external professional auditing firm at least two times over the lifetime of
the project. To initiate the first round of internal audit by an external professional auditing firm, the project will
share a draft Terms of Reference (ToR) with the Bank for its review and concurrence.
Accounting and Reporting: The project procured and installed an off-the-shelf accounting software TALLY,
which is essential in order to produce a timely and accurate financial statement. However, the system couldn’t
produce the required statements of the IUFR automatically i.e. category wise report; DA Activity statement and
the statement of contracts subject to prior review and not subject to prior review but it produces the component
wise report. Currently the project prepares the Interim Unaudited Financial Reports (IUFRs) manually through
data capturing from the system. Since the last mission the project submitted the IUFRs to the Bank on a regular
basis and these were found acceptable by the Bank based on its desk reviews.
Transaction Review: The Mission has reviewed the transactions reported in the Interim Unaudited Financial
Reports (IUFR) for the quarter ended June 30, 2018 and September 30, 2018. While reviewing the transactions
the mission was noted that some advance payments were reported as expenditures and lack of adequate supporting
documents with payment voucher. The mission advised the project team not to treat Advance as an expense any
longer since this is not proper accounting. Rather, a separate record of Advances should be kept and also included
in the quarterly IUFRs. The portion of the Advance that is retired with requisite supporting documents is what
should be treated an expense. Details of the transaction review have been shown in the Annex.
External Audit: External audit for FY 2017-2018 is underway by Foreign Aided Project Audit Directorate under
C&AG, with the final report expected to be submitted to the Bank by December 31, 2018.
Disbursement: An amount of USD 9.62 million was disbursed to DA as of November 30, 2018 which is 17% of
total commitment.
Annex 3 PROJECT RESULTS FRAMEWORK
Project Development Objective (PDO): To improve public procurement performance and enhance capacity for implementation monitoring
of development programs/projects
PDO Level Results Indicators2
Co
re UOM3
Baseline
(2017)
Cumulative Target Values4
Comments 2018
2019 2020 2021 2022
1. NSPSOs procurement lead time reduced in NCB
using e-GP system (invitation to contract award) Days 100 95 90 85 80
70
Achievement (as of November 2018) 75
2. NSPSOs invite bids in National Competitive
Bidding (NCB) through e-GP system % 2 2 15 30 50
75
Achievement (as of November 2018) 35
3. Selected sub-districts engage citizen monitoring in
contract implementatiion Number 4
4
5
15 30
45
Achievement (as of November 2018) 4
4. SPSOs’ projects implementation monitored on-line
by IMED % 0 0 0 5 10 25
45
Achievement (as of November 2018) 0
2 Please indicate whether the indicator is a Core Sector Indicator (for additional guidance – please see http://coreindicators). 3 UOM = Unit of Measurement. 4 Target values should be entered for the years data will be available, not necessarily annually. Target values should normally be cumulative. If targets refer to
annual values, please indicate this in the indicator name and in the “Comments” column.
15
Intermediate Results and Indicators
Intermediate Results Indicators
Co
re
Unit of
Measur
ement
Baseline
(2017)
Cumulative Target Values
Comments 2018 2019 2020 2021 2022
1. Draft bill establishing the proposed Authority and
amending the PPA 2006 placed in Parliament Yes/No N N Y
Achievement (as of November 2018) N
2. Government approved organogram with staffing of
the proposed Authority Yes/No N N Y
Achievement (as of November 2018) N
3. Procuring entities of NSPSOs have at least one
trained/certified procurement professional % 5 5 10 30 60
80
Achievement (as of November 2018) 5
4. PSPSOs' (RHD, LGED, BWDB, and BREB)
contract completion rate within the original time
schedule
% 0 0 0 10 30 50
Achievement (as of November 2018) 0
5. Core procurement unit operationalized in each of the
selected public sector organizations (SPSOs) % 0 0 5 20 50
80
Achievement (as of November 2018) 10
6. Procurement professionalization/accreditation
certificates issued % 0 0 5 20 40
70
Achievement (as of November 2018) 0
7. e-contract magement module in e-GP system
updated Yes/No N N Y
16
Intermediate Results and Indicators
Intermediate Results Indicators
Co
re
Unit of
Measur
ement
Baseline
(2017)
Cumulative Target Values
Comments 2018 2019 2020 2021 2022
Achievement (as of November 2018) N
8. Open contracting module developed and made
functional Yes/No N N N Y
Achievement (as of November 2018) N
9. Citizen portal developed and made functional Yes/No N N N Y
Achievement (as of November 2018) N
10. IMED’s on-line project implementation monitoring
module developed Yes/No N N Y
Achievement (as of November 2018) N
11. Disposal policy drafted and issued Yes/No N N N Y
Achievement (as of November 2018) N
12. Authority's officials in place compared with the
staffing plan % 0 0 5 20 40
70
Achievement (as of November 2018) 0
13. Officials trained in reference to the training plan % 0 0 10 30 50
75
Achievement (as of November 2018) 0
17
Intermediate Results and Indicators
Intermediate Results Indicators
Co
re
Unit of
Measur
ement
Baseline
(2017)
Cumulative Target Values
Comments 2018 2019 2020 2021 2022
14. Female officials level of participation in training % 0 0 5 10 15
20
Achievement (as of November 2018) 0
15. e-GP system generated procurement performance
reports of SPSOs published in CPTU/ Authority's
website
% 0 0 10 25 45
75
Achievement (as of November 2018) 10