BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION 1 | Page UPDATED FORM – 1 SUBMISSION TO MINISTRY OF ENVIRONMENT & FORESTS & CLIMATE CHANGE, NEW DELHI BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION [AMENDMENT TO ENVIRONMENTAL CLEARANCE] VILLAGE : BISHUNAPUR TEHSIL : BALRAMPUR DISTRICT : BALRAMPUR STATE : UTTAR PRADESH

Upload: others

Post on 25-Apr-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

1 | P a g e

UPDATED FORM – 1

SUBMISSION

TO

MINISTRY OF ENVIRONMENT & FORESTS & CLIMATE CHANGE,

NEW DELHI

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

[AMENDMENT TO ENVIRONMENTAL CLEARANCE]

VILLAGE : BISHUNAPUR

TEHSIL : BALRAMPUR

DISTRICT : BALRAMPUR

STATE : UTTAR PRADESH

Page 2: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

2 | P a g e

FORM – 1

Sl.

No.

Information/ Checklist

Confirmation

Details thereof (with approximate

quantities/rates, wherever possible) with

source of information data

1 Name of the Project Balrampur Chini Mills Ltd; Chemical Division,

Distt. Balrampur (UP)- 271201

2 Project Sector Industrial Project (Industry - II)

3 Sr. No in the Schedule Schedule 5(g) under category–A of EIA

Notification dated 14th September 2006.

4 Proposed capacity/Area/length

/tonnage to be

handled/command area/lease

area/number of wells to be

drilled.

The present proposal is Amendment in EC of

160 KLPD Distillery Plant at Specific

Condition No: 01 in amended EC dated 21st

December 2015:

Increase in no. of operational days of

Distillery from 330 Days to 365 Days / Year

5 New/Expansion/Modernization The present proposal is request amendment in

Specific Condition No: 01 in amended EC dated

21st December 2015: Increase in no. of operational days of Distillery

from 330 Days to 365 Days / Year

6 Existing capacity / Area Etc EC has been accorded by MOEF to the 160 KLPD

Distillery plant vide order no. J–11011/151/2006 –

IA II (I) dated December 21st, 2015 and 20th June

2006

7 Category of project i.e. ‘A’ or

‘B’.

A

8 Does it attract the General

condition? If yes, please specify.

NO

9 Does it attract the specific

condition? If yes, please specify

NO

10 Location

Village

Tehsil

Block

District

State

Bishunapur

Balrampur

Balrampur

Balrampur

Uttar Pradesh

11 Nearest railway station/airport

along with distance in Kms.

Railway Station: Balrampur Railway station : 2.9

km in north direction.

Airport : Gorakhpur Airport : 168.7 km in NEE

Page 3: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

3 | P a g e

12 Nearest town, City, District

Headquarters along with distance

in Kms.

Balrampur : 4.1 km in North .

13 Village Panchayats,

ZillaParishad, Municipal

Corporation, Local body

(Complete postal addresses with

telephone nos to be given)

Municipal Board Balrampur

14 Name of the applicant Balrampur Chini Mills ; Chemical Division ,

Balrampur

15 Registered address Village : Bishunapur, P.O. Balrampur, Distt. :

Balrampur UP

FAX : 05263-235051

Phone No : 05263 - 235052

16

Address for correspondence Village : Bishunapur, P.O. Balrampur, Distt. :

Balrampur UP

Name Mr N.K. Khetan

Designation Executive President

Address Village : Bishunapur, P.O. Balrampur, Distt. :

Balrampur UP

Pin Code 271201

E-mail [email protected]

Telephone No. +919793124466

17 Details of Alternatives sites

examined, if any. Location of

these sites should be shown on a

topo sheet.

No alternate sites are considered as the present

proposal is only request for amendment to EC

accorded vides reference cited above.

18 Interlinked Project No

19 Whether separate application of

interlinked project has been

submitted?

No

20 If yes, date of submission Not applicable

21 If no, reason Present proposal only for amendment to EC

22 Whether the proposal involves

approval/clearance under: If

yes, details of the same and

their status to be given.

The forest (Conservation)

Act, 1980.

No any

Page 4: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

4 | P a g e

The wildlife (Protection)

Act, 1972

The C.R.Z. Notification,

1992

23 Whether there is any

Government Order/Policy

relevant/relation to the site

No any

24 Forest land involved (Hectares) No any

25 Whether there is any litigation

pending against the project

and/or land in which the project

is propose to be set up?

Name of the Court

Case No

Orders/directions of the

court, if any and its

relevance with the proposed

project.

No any

26 Project Cost No Change in cost which we have presented

previously.

(II) ACTIVITY

1. Construction, operation or decommissioning of the Project involving actions, which will

cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Sl.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

1.1 Permanent or temporary change in land

use, land cover or topography including

increase in intensity of land use (with

respect to local land use plan)

No No extra land is required for this amendment

proposal.

The above proposal involves increase in number

of days.

For the above unit, Environmental Clearance was

accorded by Honorable Ministry vide order no. J-

11011/151/2006-IA II (I) dated 21-12-2015.

1.2 Clearance of existing land, vegetation

and buildings?

No The proposed increase in no. of operational days

of existing Distillery and does not involve any

clearance of existing land, vegetation and

buildings.

Page 5: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

5 | P a g e

1.3 Creation of new land uses? No No other land use other than industrial will be

created in the existing plant premises

1.4 Pre-construction investigations e.g.

bore houses, soil testing?

No As plant has already been constructed and in

operation, no such investigations or tests are

envisaged.

1.5 Construction works? No Nil

1.6 Demolition works? No No demolition works are envisaged as the present

proposal is only request for amendments to

increase of no. of operational days of existing

Distillery.

1.7 Temporary sites used for construction

works or Housing of construction

workers?

No Amendments to increase of no. of operational days of

existing Distillery. Hence no temporary sites for

construction workers will be constructed.

1.8 Above ground buildings, structures or

earthworks including linear structures,

cut and fill or excavations

Nil Nil

1.9 Underground works including mining

or tunneling?

No NA

1.10 Reclamation works? No No such work will be involved in present a

proposal.

1.11 Dredging? No No such work will be involved in present

proposal.

1.12 Offshore structures? No No such work will be involved in present

proposal.

1.13 Production and manufacturing

processes?

No The process of Fermentation & Distillation

already exists and there is no change.

1.14 Facilities for storage of goods or

materials?

No No additional storage of goods or materials is

envisaged.

1.15 Facilities for treatment or disposal of

solid waste or liquid effluents?

No Spent wash will be concentrated in multiple

effect evaporator (MEE) and then Slop is being

burn in incineration boiler (Slop fired travelling

grate).

Due to the above treatment system we can

operate distillery during rainy season also.

In view of the above, we request Honorable

Ministry to permit us to operate Distillery for

365.0 days / Annum.

1.16 Facilities for long term housing of

operational workers?

Yes Housing colonies available within the premises

and is being utilized.

1.17 New road, rail or sea traffic during No Already existing roads to the factory are being

Page 6: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

6 | P a g e

construction or operation? utilized. No new roads envisaged as a part of this

proposed amendments.

1.18 New road, rail, air waterborne or other

transport infrastructure including new

or altered routes and stations, ports,

airports etc?

No Already existing roads to the factory are being

utilized. No new roads envisaged as a part of this

proposed amendments.

1.19 Closure or diversion of existing

transport routes or infrastructure

leading to changes in traffic

movements?

No Already existing roads to the factory are being

utilized. No closure of roads or diversion is

envisaged as a part of this proposed amendment.

1.20 New or diverted transmission lines or

pipelines?

No No new or diversion of transmission lines or

pipelines is proposed as a part of this proposed

amendments.

1.21 Impoundment, damming, culverting,

realignment or other changes to the

hydrology of watercourses or aquifers?

No No impoundment, damming, culverting,

realignment or other changes to the hydrology of

watercourses or aquifers is envisaged.

1.22 Stream crossings? No Not Applicable as no stream crossings exists in

the Plant site.

1.23 Abstraction or transfers of water form

ground or surface waters?

Yes The total water requirement for the Distillery unit

is 1540.0 m3/day @ 9.63 KL/KL of alcohol.

Industrial Purposes : 1540.0 m3/day

There is not be any increase in water requirement.

In fact the water requirement is being reduced

due to extraction and recycle of water (MEE

condensate) from Evaporator.

1.24 Changes in water bodies or the land

surface affecting drainage or run-off?

No There will not be any change in water bodies or

the land surface affecting drainage or run-off due

to the proposed amendments.

1.25 Transport of personnel or materials for

construction, operation or

decommissioning?

No There will not be increase in traffic during

operation as no capacity enhancement is

proposed.

1.26 Long-term dismantling or

decommissioning or restoration works?

No No dismantling or decommissioning or

restoration works are envisaged.

1.27 Ongoing activity during

decommissioning which could have an

impact on the environment?

No No decommissioning activities are involved as a

part of these proposed amendments.

1.28 Influx of people to an area in either

temporarily or permanently?

No No Influx of people to an area in either

temporarily or permanently is anticipated.

1.29 Introduction of alien species? No There will not be any introduction of alien

species.

Page 7: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

7 | P a g e

1.30 Loss of native species or genetic

diversity?

No There will not be loss of native species or

Genetic diversity.

1.31 Any other actions? No Nil

2. Use of natural resources for construction or operation of the Project (such as land, water,

materials or energy, especially any resources which are non-renewable or in short

supply)

Sl.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

2.1 Land especially undeveloped or

agricultural land (ha)

No No additional land is envisaged for the proposed

amendment of increase in no. of operational days.

2.2 Water (expected source & competing

users) unit: KLD

Yes The total water requirement for the existing

Distillery unit is 1540.0 m3/day @ 9.63 KL/KL

of alcohol.

Industrial Purposes : 1540.0 m3/day

The water required which is being met from

ground water for the plant.

Recycling of waste water is being increased so

that water requirement for the plant will further

reduce.

2.3 Minerals (MT) No No usage of minerals is envisaged

2.4 Construction material – stone,

aggregates, sand / soil (expected source

– MT)

No NA

2.5 Forests and timber (source – MT) No -

2.6 Energy including electricity and fuels

(source, competing users) Unit: fuel

(MT), energy (MW) \

Yes Power generation : 6 MW

Power requirement: 2.5 – 3.0 MW use in self

consumption and surplus power will be export to

state power grid.

Fuel : Bagasse : 204 TPD

SLOP: 312 TPD

2.7 Any other natural resources (use

appropriate standard units)

No Nil

Page 8: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

8 | P a g e

3. Use, storage, transport, handling or production of substances or materials, which could

be harmful to human health or the environment or raise concerns about actual or

perceived risks to human health

Sl.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

3.1 Use of substances or materials,

which are hazardous (as per MSIHC

rules) to human health or the

environment (flora, fauna, and water

supplies) .

Yes Used oil generated is being given to SPCB

authorized recyclers.

3.2 Changes in occurrence of disease or

affect disease vectors (e.g. insect or

water borne diseases)

No No effect envisaged

3.3 Affect the welfare of people e.g. by

changing living conditions?

Yes The existing unit enabled local villagers to get

employment and improved the business

opportunities to the locals.

3.4 Vulnerable groups of people who could

be affected by the project e.g. hospital

patients, children, the elderly etc.,

No No any

3.5 Any other causes No --

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Sl.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

4.1 Spoil, overburden or mine wastes. No Not applicable as it is a Distillery unit

4.2 Municipal waste (domestic and or

commercial wastes)

No Municipal waste generated is being disposed to

authorized Municipal authorities.

4.3 Hazardous wastes (as per Hazardous

Waste Management Rules)

Yes

Used oil is being disposed to SPCB authorized

recyclers.

Other Industrial Wastes

4.4 Surplus product No No any

4.5 Sewage sludge or other sludge from

effluent treatment.

Yes Sewage sludge is being treated in septic tank and

soak pit.

Secondary ETP sludge: 0.5 KLPD, used as

manure for horticulture purposes.

Page 9: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

9 | P a g e

4.6 Construction and demolition wastes No NA

4.7 Redundant machinery or equipment No NA

4.8 Contaminated soil and other materials No NA

4.9 Contaminated soils and other materials No NA

4.10 Agriculture Waste No NA

4.11 Other solid waste Yes Fermenter Sludge : 15.4 Ton/Day

Total Fly ash generation : 59 Ton/Day

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Sl.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

5.1 Emissions from combustion of fossil

fuels from stationary or mobile

sources

Yes A 40 TPH slop fired Travelling grate Boiler is

install. Boiler operations result in emissions. A 70

m stack along with 40 TPH boiler, with ESP as

APCS. The stack is made up of RCC with internal

fire-brick lining.

The exhaust gases from the ESP is discharged

into the atmosphere through a stack of adequate

height for effective dispersion of gases into the

atmosphere as per CPCB norms for effective

dispersion of PM, emissions into the atmosphere.

5.2 Emissions from production

processes

Yes PM ,NOX,SO2,CO

5.3 Emissions from materials handling

including storage or transport

Yes Dust emissions and fugitive emissions shall arise

from material handling and transport. The control

measures shall include concrete/asphalt road

construction, water sprinkling, tarpaulin cover on

trucks carrying materials and covered storage yard

for fuel.

5.4 Emissions from construction

activities including plant and

equipment

No The present proposal involves installation of ESP

which requires minor construction activities.

5.5 Dust or odours from handling of

materials including construction

No These activities shall be for a short duration and

their impact shall be minimized by taking the

Page 10: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

10 | P a g e

materials, sewage and waste following measures:

Water sprinkling

Use of dust arresting panels/ sheets

Regular removal of construction waste

material

Proper storage of construction material

Use of cover on trucks

Speed limit for vehicles

There is no dust generation as ESP are installed to

the new boiler.

5.6 Emissions from incineration of waste No ESP is installed along with 70 Meter proposed

Stack. Hence no emissions will occur.

5.7 Emissions from burning of waste in

open air (e.g. slash materials,

construction debris)

No Not applicable

5.8 Emissions from any other sources No Not Applicable

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Sl.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

6.1 From operation of equipment e.g.

engines, ventilation plant, crushers

No All equipment’s installed in the unit are of

standard make manufactured as per noise

regulations stipulated by MoEF.

During operation phase, noise shall be generated

by the operation of pumps, air compressors,

boilers, TG set etc. as open structure is there, no

abnormal sound level is expected. Persons

working in the high noise area are being provided

the required earplugs & earmuffs.

6.2 From industrial or similar processes No All equipment’s installed in the unit are of

standard make manufactured as per noise

regulations stipulated by MoEF. The ambient

Page 11: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

11 | P a g e

7. Risks of contamination of land or water from releases of pollutants into the ground or into

sewers, surface waters, groundwater, coastal waters or the sea

Sl.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

7.1 From handling, storage, use or

spillage of hazardous materials

No Used oil is being disposed to SPCB authorized

recyclers

7.2 From discharge of sewage or other

effluents to water or the land

(expected mode and place of

discharge)

No It is ZERO discharge unit.

No waste water is disposed to outside plant premise.

Sanitary waste water generated is being treated in

septic tank followed by soak pit and STP.

Spent wash is being concentrated in MEE and

concentrated MEE is being incinerated in Slop fired

boiler.

7.3 By deposition of pollutants emitted to

air into the land or into water

No Existing 70m stack with ESP provided for the

boiler.

7.4 From any other sources No

7.5 Is there a risk of long term build up

of pollutants in the environment

from these sources?

No

noise levels in the plant are well within the

standards stipulated by MoEF.

6.3 From construction or demolition. No NA

6.4 From blasting or piling No Not Applicable.

6.5 From construction or operational

traffic

No NA

6.6 From lighting or cooling systems No Not applicable

6.7 From any other sources No Not applicable

Page 12: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

12 | P a g e

8. Risk of accidents during construction or operation of the Project, which could affect human

health or the environment

Sl.

No.

Information/Checklist confirmation Yes/

No

Details thereof (with approximate quantities

/rates, wherever possible) with source of

information data

8.1 From explosions, spillages, fires etc

from storage handling, use or

production of hazardous substances

No No such hazardous substances which lead to

explosions, spillages, fires etc from storage, handling

are being utilized or produced in the existing unit

8.2 From any other causes No Not applicable

8.3 Could the project be affected by

natural disasters causing

environmental damage (e.g. floods,

earthquakes, landslides, cloud burst

etc)?

Yes There are very less chances of natural disaster

causing environmental changes but as per our proper

Disaster management Plan & Environment

Management Plan if it will occur then we will try to

minimize the impacts of Natural Disaster on project.

9. Factors which should be considered (such as consequential development) which could lead to

environmental effects or the potential for cumulative impacts with other existing or planned

activities in the locality

Sl.No. Information/Checklist

confirmation

Yes/

No

Details thereof (with approximate quantities /rates,

wherever possible) with source of information data

9.1 Lead to development of

supporting facilities, ancillary

development or development

stimulated by the project which

could have impact on the

environment e.g.:

-Supporting infrastructure

(roads, power supply, waste or

waste water treatment, etc.)

No The existing unit has enabled the local to get

employment and also increased the business

opportunities to the locals

Page 13: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

13 | P a g e

- housing development

- extractive industries

- supply industries.

- other

9.2 Lead to after-use of the site,

which could have an impact on

the environment

No All precautionary measures are being taken in the unit

to avoid any impact on plant site.

9.3 Set a precedent for later

developments

Yes It will increase Ethanol production of the country,

which in turn in the long run could lead to further

industrial development and considerable savings of

Petrol.

9.4 Have cumulative effects due to

proximity to other existing or

planned projects with similar

effects.

No The existing unit is an isolated industry and not in

cluster. A better planned and executed project has to

yield a better result individually.

(III) ENVIRONMENTAL SENSITIVITY

Sl. No. Areas Name/

Identity

Aerial distance (within 15 km.) of proposed

project location boundary

1 Areas protected under

international conventions

national or local legislation for

their ecological, landscape

cultural or other related value

No No any

2 Areas which are important or

sensitive for ecological reasons

(Wetlands, watercourses or

other water bodies, coastal

zone, biospheres, mountains,

forests)

No River Rapti : 7.57Km in North direction.

3 Areas used by protected,

important or sensitive species of

No No any

Page 14: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

14 | P a g e

flora or fauna for breeding,

nesting, foraging, resting, over

wintering, migration

4 Inland, coastal, marine or

underground waters

No

5 State, National boundaries No

6 Routes or facilities used by the

public for access to recreation

or other tourist, pilgrim areas

No

7 Defense installations No

8 Densely populated or built-up

area

No The proposed project site lies in the vicinity

of city : Balrampur – 4.1 km

9 Areas occupied by sensitive

man-made land uses (hospitals,

schools, places of worship,

community facilities)

No Some such areas exist in city : Balrampur –

4.1 km

10 Areas containing important,

high quality or scarce resources

(ground water resources,

surface resources, forestry,

agriculture, fisheries, tourism,

minerals.)

No No such area exists.

11 Areas already subjected to

pollution or environmental

damage (those where existing

legal environmental standards

are exceeded)

No No such area exists.

12 Areas susceptible to natural

hazard which could cause the

project to present

environmental problems

(earthquakes, subsidence,

landslides, erosion, flooding or

No The proposed project area lies in Zone IV

Seismic area. All necessary design

considerations for earthquake resistant

structures shall be incorporated in the design

of the project.

Page 15: BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION …environmentclearance.nic.in/writereaddata/...E-mail nk.khetan@bcml.in Telephone No. +919793124466 17 Details of Alternatives sites examined,

BALRAMPUR CHINI MILLS LTD, CHEMICAL DIVISION

15 | P a g e

extreme or adverse climatic

conditions)

I hereby give an undertaking that the data and information given in the application and enclosures are

true to the best of my knowledge and belief and I am aware that if any part of the data and information

submitted is found to be false or misleading at any stage, the project will be rejected and clearance

given, if any to the project will be revoked at our risk and cost.

Date : 10.10.2018

Place : Balrampur

Balrampur Chini Mills ltd

(Chemical Division) Distt. Gonda.