ballynacor wastewater treatment works environmental...

25
Ballynacor Wastewater Treatment Works Environmental Improvement Project Improving our environment for future generations November 2012

Upload: others

Post on 18-Apr-2020

21 views

Category:

Documents


0 download

TRANSCRIPT

Ballynacor Wastewater Treatment Works

Environmental Improvement Project

Improving our environment for future

generations

November 2012

Welcome

Jeff Bishop

Glen Water

Housekeeping

• Emergency exits

• No planned fire alarms

• WC’s

• Tea and biscuits at rear of room

Welcome

Dr Ray Flynn

[email protected]

Tel: 02890 974044

Meeting Agenda

Introduction & Welcome: Jeff Bishop (Jeff Bishop)

Setting the Scene: Ciaran Crozier (Northern Ireland Water)

What are we doing? Paul Foster (Glen Water) &

Dr Chris Piddington (Vertase)

Questions for the Panel: Dr Ray Flynn (Independent Chair &

Queens University Belfast)

Setting the Scene

Ciaran Crozier

Northern Ireland Water

Ballynacor WwTW lagoons

• Wastewater treatment produces two products – liquid

effluent and sludge mass - both require safe disposal

• UK sewage sludges were historically disposed of at sea or

spread to land as fertiliser

• EU/UK Legislation and Policy has evolved to limit such

disposal routes

• In 2000, Water Service committed to a policy of incineration

for sewage sludges

In 2007 two significant events occurred:

1. Formation of NI Water Ltd (GoCo)

• DRD transferred all assets and liability of the Lagoons

• The Pollution Prevention Control (NI) Regulations demanded

the lagoons needed remediated

• DRD agreed to fund the liability

2. Project Omega Contract Award

• 25 year project to develop and operate WWTW

• Ballynacor WWTW included

• PPC Permit would be held by Contractor

• Negotiated a Value For Money solution

Partner Relationships

What is being done?

Paul Foster (Glen Water)

Introduction to Ballynacor WwTW & the

remediation options

Ballynacor’s on site

lagoons are being

restored back to

grassland.

This will prevent the

contents of the

lagoons potentially

polluting the

environment in the

future.

Work starts in

January 2013 and is

expected to take 18

months.

Why restore the lagoons back to land?

• Environmental assessment shows no evidence of environmental

damage.

• The lagoons do contain a number of contaminants

• Environmental experts and engineers have been working on a

plan to restore the area.

• Our approach is acknowledged as the best environmental

solution.

Remediation Process Regulatory Approval

• Eighteen months of Groundwater monitoring

1. To establish if any environmental damage is occurring

2. To establish a base-line for future monitoring

• Propose a solution that is deliverable and meets all the regulatory

requirements

• Prove that the process will achieve the aims

• Conduct trials that satisfies the NIEA

• Conduct leachability trials of final product

• Exact remediation process to be approved in detail

“Stabilisation”

• Seals the contaminated soils and wastes in a solid structure

• Achieved by adding specific ‘binding’ materials to the sludge

• A chemical bond ensures contaminants become more insoluble

and more stable compounds

• The resulting mixture forms an impermeable stable block

• Prevents the release of contaminants into the environment

The Selected Process

• Safe

• Cost effective

• Sustainable & environmentally sound

• Approved by NIEA and NIW as the best available option

• Minimises local disruption

What is being done – the detail

Dr Chris Piddington (Vertase)

The Stabilisation Process

How the lagoon is being restored – Step One

• Sludge from the lagoons is pumped to an on-site treatment plant where it

is cleaned

• Clean water is discharged from the site and eventually ends up in Lough

Neagh

• This follows that standard process that exists on-site today

How is the lagoon being restored – Step Two

• The sediment from the lagoons is dried and mixed with safe stabilising

materials

• These materials are no more than ash & cement which bind to the

sediment making it safe to leave in the ground

• This is done on-site to remove the need for transporting large

quantities of materials by lorry which would cause disruption

Environmental Controls & Monitoring

• Strict environmental controls and monitoring will be undertaken

throughout the duration of the works and beyond, as required by the

regulators, including:

• Noise Control

• Dust

• Groundwater quality

• Surface water quality

• Odour

How is the lagoon being restored – Step Three

• Odour emissions are controlled by keeping the treatment process

covered

• A layer of water is maintained on the lagoon to keep the sediment

away from the air

• Equipment will be installed around the site that sprays a neutralising mist to remove odours from the air.

Odour Suppression

• Odour suppression equipment will be installed on site to ensure any odours that are created by the cleaning process are mitigated

How the is lagoon being restored – Step Four

Once the material from the lagoons has been treated, the stabilised

material is returned to the empty lagoon, covered with a layer of soil and restored to native grassland.

Leaving behind a restored native grassland.

Questions for the Panel

Chaired by Dr Ray Flynn

Want to learn more?

Visit our website at http://www.niwater.com/ballynacor.asp

Want to be added to our e-mail updates?

Email us at [email protected]

Do you have any more questions?

Email us at [email protected]

Thank you