Page 1: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Solutions to Common Demantra& ASCP Implementation Challenges

April 14, 2016

Page 2: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Welcome

• Deb Bryant, Marketing Coordinator

• Jim Heatherington, VP Sales

• Presenting:• Trudy Grieve, Sr. Principal Consultant

• Duane Hardacre, Managing Partner

Page 3: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Housekeeping Announcements• During the Webinar - Please remain muted throughout presentation

• After the Webinar› No Q&A at the end but we will send out an email to all of you with a copy of the

entire presentation and our contact information› The webinar will also be available on our SlideShare account as well as our

website

• Announcements› May 10 Webinar: S&OP in the Cloud for JD Edwards

[email protected]

Page 4: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

The AVATA DifferenceS u p p l y C h a i n P r a c ti ti o n e r s

Coupled with Deep VCP Expertise

Gartner Recognized as Industry Experts

Oracle SCP Specialized

Fusion Co-Development Partner

#1 Oracle SCP Cloud/BPS Partner

Partner Award for Excellence in SCP

Specialized by Oracle Preferred by CustomersRecognized by Industry

Page 5: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Specialized by Oracle Preferred by CustomersRecognized by Industry

Demantra Challenges

Page 6: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Demantra Key Challenges

• Change Management• Implementation• Data• Process • Configuration• Demantra Tips & Tricks

Page 7: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Change Management

Change requires commitment• Best practice vs. replication

• Change is resisted, understand and mitigate

• Assign ownership (Project and Process)

• Encourage collaboration/conversations of market information

• Metrics and Measures are learning devices, not smoking guns

• Demand Planning should be ‘unconstrained Demand’

• Policy and Procedures for ERP must be implemented

Page 8: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Implementation

Understand Demantra/Demand Planning

Demantra is not a source system. ERP system is the system of record.

Demantra is only a source of the Demand Plan.Demantra is not a reporting tool.

Support the ImplementationAssign sufficient resources to support system

implementationConfigurable systems require iteration

Data Validation is a critical

Page 9: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Implementation

DecisionsHave a steering committee to

support issues & opportunities.

Ensure a Stage Gate process is

followed.

Don’t revisit finalize proven

decisions.Interations - leads to good decisions.

Hierarchy Demantra requires a solid hierarchy to enhance the

engine results.

Determining the correct level for planning is critical

but performance should always be considered.

Page 10: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Implementation

Set reasonable timelines• Work within the business requirements (holidays, budget timing, etc)

Training• Navigation training provides an opportunity to improve design• Train the trainer

Page 11: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Data and DemantraData validation

Data ownership is critical

Priority should be on getting data in the early phase of the implementation• Data issues need to be addressed quickly and effectively• Expect data interations

Data needs to be relative to Demand Planning • Demand versus Shipments • Default Warehouse vs Ship From

Ownership of master data needs to be clear

Page 12: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Process

Design workshops • Time and effort to create a design

• Don’t over complicate - crawl, walk, run

• Best practice versus replication

• Look for opportunities to simplify and improve

• Entire team must be available for Design sessions

• Roles and responsibilities need to be clearly defined

Page 13: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Process

Understand Value• Understand opportunities for a solid ROI • Set reasonable timelines – improvement takes time

Demand Planning

• Demand Planning combines statistical information and judgment• Judgment cannot be automated• Unconstraint planning

Page 14: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Configuration

Out of the Box• Assign internal ownership to test configuration• Documentation and sign off is key• Configuration and iterations – can’t have one without the other• Be prepared to speak up, address issues, work for resolutions• Understand the need to tune the engine after implementation

(internally or externally)• Ensure an internal member is well versed on Business Modeler

Page 15: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

User Tips & TricksMember Management

• Operational but requires solid knowledge of how to use it

Chaining• Out of box system is too complex• Copy/paste chaining is more efficient

Similar Item• Risk of entering a bad record that hasn’t come from Core ERP systems• Can be an effective replacement for Chaining• Facility to remove combinations

Offline Functionality• Access without being on VPN

Export & Import of Excel• Need to ensure layout is not changed

New Item, View Item, Edit Item, Delete Item• Danger!!! Should limit usage or remove options

Page 16: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Specialized by Oracle Preferred by CustomersRecognized by Industry

ASCP Challenges

Page 17: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

ASCP – Common Challenges

• Change Management • Process • Data• Configuration

Page 18: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Change Management• Overly complex starting off

› Adoption and validation is more difficult

› Loss of trust in the solution (data, capabilities, output)

• Design through the end state initially but implement in phases• Must have a front line “Process Champion” in the business

› Empowered to drives change and solution adoption at lowest levels

› Deep enough content/experience in legacy processes/system (or excel) to bridge the gap between the old and the new

• Remove excuses

• Can be a super user but is often a supervisor / manager level

Page 19: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Change Management• Executive Support

› Educate executives on the “journey” • Ensure objectives, phases, timelines, and metrics are aligned through the

organization (from executive to planner)• Don’t go cheap on the training

› Train-the-trainer is the most effective training when executed correctly• Skillset assessment

Page 20: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

• Understand how you are aligning the roles & responsibilities across the process

› Demand Planning› Master Scheduling / Operations planning › Production Planning & Scheduling › Materials Planning / Buy Plan › Inventory Planning, Contract Mfg Planning

• Aligned by strategic accounts, products and/or Contract Manufacturers, business units, onshore/offshore

• Segment your supply chain: Customer, Product Family, Items, etc.,

• Align key functions: Drop-in Orders, Order change requests, supporting S&OP, strategic planning, materials planning, GOP (expediting) etc.

Process

Process down to the System level• Interact with the system• Expected/required data

• Expected output

“Software based process design”

Page 21: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Process

• Software Based Process Design / Re-engineering › Educate / train users and managers up front at the onset of process design /

process mapping

› Keep in mind the practical aspects, strengths and limitations of the software

› Understand the different roles within the system and their activities, and required data

Page 22: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

From Chaos to Cadence • Establish a Monthly, Weekly, Daily Cadence

› Especially for global operations, S&OP, Retail Industry (Min ord quantities)› Understand the underlying assumptions

Process Step Monthly Calendar Responsibility Matrix

Regions

Brand Inventory

TeamCorporate Planning

Corporate IT/BSA

Corporate Purchasing

Contract Mfg

Executive Team

1Monthly Meeting with Brands/Regions to review any changes needed to item attributes/new product familes. R, A R, A C I I

2 Brands & Regions to make necessary changes to data template(s) R, A R, A C I I3 Upload revised data templates to Planning Sharepoint Site R, A R, A4 Upload templates to EBS R5 Consensus forecast consoldiated and uploaded to CDR R R C R6 Demand plan updates R, A R, A

7EMEA inventory transfers for demand, review preliminary 'buy' approval and adust as needed R, A R, A C C

8 MOQ subsidiary updates R, A C

9 Capacity review and pre-load updates, send 'Buy' summary report to factories C R, A R, A10 MOQ global updates (current and future months) C R, A C11 Generate buy plan approval report C R, A C12 Buy plan approval, financial approval from executive management C R, A C

13Approved buy plan execution, forecast published to factories, PO's created and issued to factories I I R,A R,A I

14 Demand plan archived I I I R,A I

R=Responsible, A=Accountable, C=Consulted, I=Informed

Align Responsibilities

Orchestrate Execution

Monthly Planning Calendar

Page 23: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Process Cadence Document Weekly Planning Processes: Role Based, Event & Exception Driven

Page 24: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Process Cadence Publish Clear Calendar of Weekly / Daily Activities by Role

Week Group Mon. Tues. Wed. Thurs. Fri. Sat.

Customer Service/Order Management Evaluate Distributor Orders Evaluate Distributor Orders

Distributor Order Sourcing ReviewedProcess Cancellation

Demand Planning Evaluate Distributor OrdersFinal Demand Review

S&OP Pre-MeetingUpdated Forecast for Consensus

(including distributor) Push Approved Buy Consensus

Demand

Regional Planning Review Cancellations Evaluate Distributor Orders

Pull In OpportunitiesFinal Suppply Review S&OP Pre-Meeting

Distributor Order Sourcing Reviewed Push Out Opportunities Push Out Opportunities

Global Planning Full Collection for Buy Plan

Customer Service/Order Management

Demand Planning Push Consensus Forecast

Regional PlanningShip-To MOQ Analysis

Adjust Regional Buy PlanShip-To MOQ Analysis

Adjust Regional Buy PlanAdjust Regional Buy Plan

Pre- Exec S&OPSuppply Review Executive S&OP

Push Out OpportunitiesUpdate Buy Plans & Release POs

Global Planning Global MOQ &Capacity Analysis Global MOQ &Capacity Analysis Executive S&OP Run Collection

Week 4

Week 3

Activity / Who Mon. Tues. Wed. Thurs. Fri. Sat. Sun.

Review Recommended Releases & Cancellations

Pull In Opportunities

(Tactical S&OP)

Pull In Opportunities

Push Out Opportunities

Push Out Opportunities

Global/ Centralized

Supply Planners

ASCP PlanNet Collection

ATPNet Collection

ATPNet Collection

ATPNet Collection

ATP ATPFull Collection

ConsensusATP

Respond to Supply and Demand QuestionsAttribute Maintenance (before Friday plan run)

Sourcing Updates (before Friday plan run)Manage Lead Time

Regional Supply Planners

Respond to Supply and Demand Questions

Normalize the Process

AVATA Confidential

AVATA Confidential

Page 25: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Process Cadence

Translate the processes and activities to system execution• Queries & Folders & Pegging

• The process flow / activities should map to standard set of folders views and queries

• Folder views should be configured (customized) to tie back to roles and responsibilities ensuring the required fields /data are displayed

› Master Scheduler, Production Planner, Buyer, etc.,

• While not done the exact same way, the concept of mapping planner views / data to the process also applies to Rapid Planning

Strategy

Execution

Page 26: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Folders

• Almost every form in ASCP should be based on a customized folder / query

Caution when selecting Always and Open as Default options together. This will cause the forms to become very inflexible and cause you problems.

Page 27: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Queries & Exceptions• Appropriate Action & Exceptions Queries should be built based on the process,

and roles/responsibilities › Planner / buyer queries to release / reschedule planned orders based on their products,

specified timeframe, etc.,› Exception queries

Page 28: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Queries & Exception• Layout the appropriate exceptions and queries for your solution Exceptions Message

Owner Description Action Summary

Late Supply Pegged to a Sales Order

Planner When firm / non-firm supply due date is later than the demand due date for independent or dependent demand with top level affected demand being a sales order

Narrow exception by Org, Category or Planner Code

View Exception Detail Form Drill into necessary Supply /

Demand details to resolve Past Due Sales Orders

Order Mgt

Sales order with schedule ship dates past due.

Update Sales order date

Late Supply Pegged to a Forecast

Planner When firm / non-firm supply due date is later than the demand due date for independent or dependent demand which is a forecast when pegged to top level demand

Execute the same as “Late Supply Pegged to Sales Order”

Orders to be rescheduled- in

Planner / Buyer

Purchase Orders, Planned Orders and Discrete Jobs that need to be expedited. In order to meet demand dates, the order needs to be pulled in. Note: Firm Orders will not generate reschedule messages.

Narrow exception by Org, Category or Planner Code

View Exception Detail Form o View Old Date & New

Date Contact necessary people to

confirm reschedule and update the system.

Orders with compression days

Purchase Orders, Planned Orders and Discrete Jobs that need to be expedited. Compression days is the number of days the orders lead-time needs to be compressed to hit the demand due date.

Sort Compression Days in Descending

Orders to be cancelled

Planner / Buyer

Cancellations to avoid excess supply for Purchase Order, Reqs, Intransit, Discrete Jobs that the system does not peg to demand.

Confirm and Cancel Order

Orders to be rescheduled out

To avoid excess supply, these are purchase orders, discrete jobs, intransit, etc.. that need to be rescheduled to a later, recommended date.

Confirm and Reschedule Order

Past due orders

Planner / Buyer

Discrete Job, Intransit Shipments and Purchase orders that are past due

View Exception Detail o Note Old Date and

New Date Resolve exception

Note in release 12.2 you can enable just thoseappropriate exception messages for your solution, and disable the rest so the plan doesn’t generate them.• Improves plan performance• Increasing planner usability by not having to

“weed through” hundreds of exception messages

Page 29: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Workbench Preferences • Personalize the Planner Workbench

Process

Usability

Execution

Perfection is the enemy

Page 30: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Pegging• Caution: Has significant impacts› High Projected Available Balance (PAB) caused by

Safety Stock Pegging, and Planned orders recommended early

› PAB is below Safety Stock › Existing Supplies Pegged to Safety Stock Demands

and Real Demands ( Sales Orders and Forecasts) are met Late

› Leverage priority pegging along with proper profile option settings

• MSO: Supply Window Size and MSO:Demand Window Size

Note: In release 12.1.3.X you can leverageNew excel export capability A simplified excel pegging spreadsheetgenerated as part of the plan run

Page 31: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

And So Much More• Constraints

› Caution when using “Purchase constraints”

› Start with fewer constraints and add complexity (example: bottleneck resources)

› Caution with sequence dependent setups with getting overly complex constraint based plans

• Order modifiers› Critical to producing a reasonable, effective plan output that can be executed

› Critical to reducing plan nervousness

• Plan Run Time – Performance can be optimized with the right DBA tricks and later upgraded versions

• Collection optimization – break up collections to parallelize activities

• Profile Options – There can be a webinar just on those, use caution to understand their impacts especially some of the obscure, not so obvious ones.

› Share Plan partitions = No (this one gets everyone starting out)

• Forecast consumption / global forecasting – iterative testing and thoroughly

• Leverage multiple plans for various purposes

› Sales order only plan , What-if scenario plan, S&OP Plan, a Buy plan, ATP Plan, Various constraint modes, etc.,

Page 32: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges
Page 33: AVATA Webinar: Solutions to Common Demantra & ASCP Challenges

Thank You!