POWER SERVICE Dr. D. Tscharntke 30/04/2008 A utomatic P hased A rray R otor I nspection APARI Alstom Power Service Berlin: Dr. V. Munikoti, A. Roesch, Dr. D. Tscharntke Alstom Power Service Nürnberg: A. Nowi, P. Schott Alstom Inspection Robotics Zürich: W. Zesch Alstom Schweiz Baden: R. Moser St. Gallen Dachtagung 2008 - 30/04/2008 - P 2 ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden. Konventionelle Prüfung von ex- MAN Turbinenläufern Alstom Prüfanweisung basierend auf VGB- Richtlinie VGB-R 504M (Prüfung von großen Schmiede- und Gussstücken für Dampf- und Gasturbosätze) VGB Empfehlung: In Umfangsrichtung: Longitudinalwelle: 0°, 7°, 14°, 21°, 28° Transversalwelle: 35°, 45°, 60°, 70° mindestens eine Einschallrichtung In axialer Richtung: Transversalwelle: 45° zwei Einschallrichtungen DACH-Jahrestagung 2008 in St.Gallen - Mi.1.B.2 1

Upload: others

Post on 01-Mar-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

POWER SERVICE

Dr. D. Tscharntke30/04/2008

Automatic Phased Array Rotor InspectionAPARI

Alstom Power Service Berlin:Dr. V. Munikoti, A. Roesch, Dr. D. Tscharntke Alstom Power Service Nürnberg:A. Nowi, P. SchottAlstom Inspection Robotics Zürich:W. ZeschAlstom Schweiz Baden:R. Moser

St. Gallen Dachtagung 2008 - 30/04/2008 - P 2ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Konventionelle Prüfung von ex- MAN Turbinenläufern

• Alstom Prüfanweisung basierend auf VGB- Richtlinie VGB-R 504M (Prüfung von großen Schmiede- und Gussstücken für Dampf- und Gasturbosätze)

VGB Empfehlung:

• In Umfangsrichtung: Longitudinalwelle: 0°, 7°, 14°, 21°, 28°Transversalwelle: 35°, 45°, 60°, 70°mindestens eine Einschallrichtung

• In axialer Richtung: Transversalwelle: 45°zwei Einschallrichtungen

DACH-Jahrestagung 2008 in St.Gallen - Mi.1.B.2

1

Page 2: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 3ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Konventionelle Prüfung von ex- MAN Turbinenläufern

• manuelle Ultraschallprüfung

• konventionelle PrüfköpfeLW: Typ B2S mit Vorsatzkeil für 0°, 7°, 14°, 21° und 28°TW: Typ WB2-35°/45°/60°/70°

• Bewertung AVG-Methode, Registrierschwelle: 2 mm KSR

• Anpassung des Prüfkopfkeils an Läuferkrümmung von Hand

• Anpassung an Kammnutenkontur in Dichtbereichen von Hand

St. Gallen Dachtagung 2008 - 30/04/2008 - P 4ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Kammnutenkontur in Dichtbereichen vonHD- und MD- Läufern

Kammnutenkontur

Vorsatzkeilangepasster Vorsatzkeil

2

Page 3: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 5ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Phased- Array- Prüfkonzept für ex- MAN Turbinenläufer

• mechanisierte Ultraschallprüfung

• Phased- Array- Prüfkopfmit zwei verschiedenen Vorsatzkeilen für LW und TW

• Realisierung der Einschallwinkel durch zwei SektorscansLW: 0° - 28°TW: 35° - 70°

• Empfindlichkeitseinstellung und Bewertung über Vergleichskörper und -reflektoren

• Verringerung der Prüfzeit um Faktor 2 - 3

• Verbesserung der Dokumentation durch Datenspeicherung

St. Gallen Dachtagung 2008 - 30/04/2008 - P 6ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Anfertigung von angepassten Prüfkopfsohlenmit mobiler 3D- CNC- Fräse

• Proxxon MF70 Fräse

• 3D- CNC- Controller-Karte

• 3 Motore für x-/y-/z- Achse

• Anpassung des Krümmungsradius

• Anpassung an Dichtkammprofil

3

Page 4: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 7ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

CIVA Modellrechungen zur Bestimmung der Prüfkopfparameter

• Optimierung der Keilwinkel

• Überprüfung der erfassten Volumenbereiche

LW TW

St. Gallen Dachtagung 2008 - 30/04/2008 - P 8ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Prüfbereiche - Beispiel ND- Läufer

~7800 mmWellendurchmesser~400-1500 mm

4

Page 5: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 9ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Konstruktionsentwurf kleiner Rotorscanner

Alstom Inspection Robotics AG (AIR)Zürich

St. Gallen Dachtagung 2008 - 30/04/2008 - P 10ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Konstruktionsentwurf großer Rotorscanner

Alstom Inspection Robotics AG (AIR)Zürich

Scanachseca. 500 mm

5

Page 6: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 11ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Komponenten des Prüfsystems

LaptopPA Gerät Motor-

Controller

großer RotorscannerVariante 1

AlstomPrüfbuggy

St. Gallen Dachtagung 2008 - 30/04/2008 - P 12ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Prüfung freier Wellenbereiche mit großem Rotorscanner

6

Page 7: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 13ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Großer Rotorscanner - Variante 2

• verkürzte Scanachse (300 mm)

• stabilere Konstruktion

• Gelenkarm für Prüfkopfhalterung

Scanachseca. 300 mm

St. Gallen Dachtagung 2008 - 30/04/2008 - P 14ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Modellrechnungen an 2 mm Flachbodenbohrungenzur Simulation der Echohöhenverhältnisse

• Bohrungsorientierungen: 0°, 7°, 14°, 21°, 28°

0°7°

14°21°

28°

7

Page 8: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 15ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Validierung an Flachbodenbohrungen (FBB)

8 mm FBB320 mm Schallweg

8 mm FBB320 mm Schallweg

RW

Um

fang

sric

htun

g

St. Gallen Dachtagung 2008 - 30/04/2008 - P 16ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Validierung an Flachbodenbohrungen (FBB)

B- Bild:

ø 4 mmø 6 mmø 8 mm

ø 10 mm

RW

Testkörper mit4, 6, 8 und 10 mm FBBund Rückwandecho

8

Page 9: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 17ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Konzept zur Empfindlichkeitseinstellung

• Bestimmung des einschallwinkel-abhängigen Verstärkungsausgleichs

• Halbzylinder mit 2 mm FBB in betrachteten Winkeln

• verschiedene Halbzylinderdurchmesser

• Tiefenabhängiger Verstärkungszuschlag

• Bestimmung der Grundverstärkung an Rückwand des zu prüfenden Läufers

0°14°28°

45°

70°2 mmFBB

St. Gallen Dachtagung 2008 - 30/04/2008 - P 18ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

• manuelle Läuferprüfung dauert ca. 50 Stunden(5 Tage à 10 Stunden)

• diverse Prüfkopfkeile benötigt, häufiger Vorlaufkeilwechsel

• häufiger Wechsel beinhaltet Zeitverlust und birgt Gefahr von Justierfehlern

• Läufer muss während der Prüfung gedreht werden können

• dauerhafte Bildschirmbeobachtung führt zur Ermüdung des Prüfers

Zusammenfassung - manuelle Prüfung

9

Page 10: Automatic Phased Array Rotor Inspection - APARIPOWER SERVICE Dr. D. Tscharntke 30/04/2008 Automatic Phased Array Rotor Inspection APARI Alstom Power Service Berlin: Dr. V. Munikoti,

St. Gallen Dachtagung 2008 - 30/04/2008 - P 19ALSTOM © 2007. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden.

Zusammenfassung - mechanisierte Prüfung

• erwartete Zeitersparnis um ca. Faktor 2 - 3

• verbesserte Dokumentation durch Datenspeicherung und bildhafte Auswertung

• bessere Möglichkeiten zur Beobachtung von Befunden über die Zeit

• weniger Vorlaufkeilwechsel, geringere Fehlergefahr

• Verringerung des menschlichen Einflussfaktors

• Läufer muss nicht drehbar sein

• Datenauswertung kann off-line erfolgen

www.alstom.com

Vielen Dank für Ihre Aufmerksamkeit !